Professional Documents
Culture Documents
By
Andrius Maneikis
HannanAfifi
MdShahinur Islam
Pratik Sonthalia
Contents
EH2741- Communication & Control in Electric Power Systems Project Assignment. . .1
Part 1 Substation Automation Systems.................................................................1
1.1 Theory Part: Design a substation automation systems.....................................3
1.1.1 Detailed Substation Design.........................................................................3
1.1.2 Circuit Breaker Maintenance.......................................................................6
1.1.3 Substation protection zones......................................................................12
1.1.4 Protection in Substation............................................................................ 14
1.1.5 Example of Logical Nodes interaction for over-current protection.............17
References................................................................................................................ 20
Appendix.................................................................................................................. 21
List of Figures........................................................................................................ 21
List of Tables.......................................................................................................... 21
Page 2 of 22
Single Bus
Double bus, double breaker
Main and transfer bus
Double Bus, single breaker
Ring Bus
Breaker and a half
Reliability
Flexibi
Page 3 of 22
Cost
Single Bus
Double Bus,
double breaker
No
Yes
lity
No
Yes
Main and
Transfer Bus
Double Bus,
single breaker
Ring Bus
No
No
No
No
Yes
Breaker and a
Half
Yes
Least
High Cost- duplicated
components
Page 4 of 22
Circuit Breakers
Protecti
on
Disconnectors
Component Label
CB1
CB2
CB3
CB4
CB5
CB6
CB7
CB8
CB9
CB10
CB11
CB12
CB13
DS1, DS2
DS3, DS4
DS5, DS6
DS7, DS8
DS9, DS10
DS11, DS12
DS13, DS14
DS15, DS16
Bay Number
Bay1
Bay2
Bay3
Bay4
Bay4
Bay4
Bay6
Bay5
Bay6
Bay6
Bay1
Bay2
Bay3
Bay1
Bay2
Bay3
Bay4
Bay4
Bay4
Bay5
Bay6
Bus Bars
System
Line
Transformer
Bus Bar1
Bus Bar 2
Line 2
Line 1
Line 3
T1
T2
Bay1
Bay2
Bay6
Bay3
Bay5
Measurem
ent
Current Transformer
CT6
CT5
CT2
CT1
Page 5 of 22
Bay1
Bay2
Bay3
Bay3
Voltage Transformer
CT3
CT4
CT7
VT1
VT2
Bay5
Bay5
Bay6
The diagram for the division of the bay has been shown below:
lifetime and can be still operated. Generally, in a breaker and a half configuration,
all the circuit breakers are kept closed normally to increase the redundancy.The
maintenance process will have to be done ensuring that the supply to none of the
feeders is disrupted. The detailed steps have been described below:
1. Initial condition is shown in the figure below. The current flows into Line2
through both CB1 and CB4.
2. Open CB1. Upon tripping the circuit breaker CB1, the current stops flowing
into Line2 through the circuit breaker CB1. However, it is still being fed
through the circuit breaker CB4 ensuring supply and reliability.
Page 7 of 22
3. Once the circuit breaker is open, the disconnectersDS1 and DS2 can be safely
opened.
Page 8 of 22
Page 9 of 22
Page 10 of 22
6. Close the disconnecters DS1, DS2 and then circuit breaker CB1 new. Now the
current flows into the feeder from both the circuit breakers CB1 new and CB4.
Page 11 of 22
Thus circuit breaker that has reached its lifetime can be replaced without
disrupting the supply.
1.1.3 Substation protection zones
To denote the protection type, the entire design has been divided into a
number of zones. The diagram depicting the zones is shown in the figure.
Page 12 of 22
Each of the above zones deploys its own protection mechanism which has been
summarized in the table below and described the following section.
Page 13 of 22
Protection
Zones
Zone 1
Zone 2
Zone 3
Zone
Zone
Zone
Zone
Zone
4
5
6
7
8
Zone 9
Protection Types
Over-current
Over-current Protection
Under voltage &Differential
Protection
Differential Protection
Over-current
Over-current Protection
Over-current Protection
Under voltage & Differential
Protection
Differential Protection
input of transformer is used for both differential protection for transformer and also
over-current protection for the line. For outcoming load, each has CT to measure
current flowing. In this case, we assume that all outcoming feeders are identical.
Therefore the settings of the over-current protection are similar for those lines.
In figure x, we take zone protection 7 as an example of over-current
protection. Since we are using half and breaker configuration, we assume each of
the outcoming feeder receive power from both bus bar (bus 1 & bus 2). Therefore,
line 2 is supplied directly from incoming feeder of zone protection 1 and bus bar 1. If
fault is occurred in line2, relay will send signal to CB 1 and CB 4 to trip to isolate
only line 2 (faulted feeder).
2. Differential protection
Differential protection is principally based on comparison between current
flowing into and out from the equipment, either in magnitude or phase. During
normal condition, ideally the current entering and leaving equipment should be the
same. However, fault condition in apparatus will cause significant difference
between entering and leaving current.
Differential protection is implemented for protecting power transformer and
busbars in our substation design. Power transformer, as one of main and expensive
instrument in substation, has to be protected properly to prevent any further
damage when fault occurred in it. The use differential protection provide
advantages in potential transformer such as helping Buccholz relay to detect any
internal fault in transformer outside insulating oil quickly and also protecting faults
outside transformer but inside the differential protection zone of transformer [3]
Page 15 of 22
I PI S I T
IT
Where
difference between input and output current of transformer equal or bigger than
threshold current, relay will active and send trip signal to trip the transformer.
In
bus
bar
protection, differential relay is implemented by assembling three CTs connected in
parallel in the line which is connected to the bus bar as input of the relay.
Principally, bus bar should be protected as bus bar availability will determine
performance of substation. If we take example bus bar 1 in zone protection 8, we
can see that there are three CTs (CT 11, CT 12 and CT 13) connected to bus bar 1.
According to KCL (Kirchoff Current Law), during normal condition the current flowing
to relay should be
I 1 +I 2+ I 3=0
Which means no current will flow to relay protection. However, if fault happens
inside protection of zone 8, current flowing to relay will no longer zero and relay will
send trip signal to CB which is connected faulted line.
Page 16 of 22
3. Undervoltage protection
Undervoltage relay is type of relay that operates when input voltage drops
below limit value.
Undervoltage relays are typically device which measure
instantaneous value. Therefore, every time the input voltage drops below set point,
instantaneous undervoltage relay should react immediately. Setting of
Instantaneous undervoltage relay depends on the drop voltage and also VT ratio. [4]
In our design, undervoltage relay is implemented to protect bus bar. As
mentioned earlier, availability of bus bar will effect on operation of entire
substation. Hence we use undervoltage protection as backup of differential
protection for protecting bus bar. However, as undervoltage is defined as backup,
time delay and block settings should be set to allow differential relay to operate
first. In implementation of undervoltage protection, each bus baris installed with VT
as input of undervoltage relay (VT 1 for bus bar 1 and VT 2 for bus bar 2). If fault
happens in bus bar, and differential protection fails to operate, undervoltage will
send signal to trip all the feeders connected to the relevant bus bar.
Page 17 of 22
Page 18 of 22
Information Attribute
TCTR
TCTR.Amp.instMag
PTOC1
TCTR
TCTR. Amp.instMag
CSWI1.OpOpn.general
CSWI1.OpCls.general
PTOC2
CSWI1
CSWI1.Pos.origin
CSWI1.OpOpn.general
CSWI1.OpCls.general
XCBR1
CSWI1
CSWI1.Pos.origin
CSWI1.OpOpn.general
CSWI1.OpCls.general
XSWI1
CSWI1
CSWI1.Pos.origin
CILO1.EnaOpn.stVal
XSWI2
CILO1
COLO1.EnaCls.stVal
CILO1.EnaOpn.stVal
CSWI1
CILO1
COLO1.EnaCls.stVal
PTOC1.Str.general
CILO3
PTOC1
PTOC1.Op.general
PTOC1.Str.general
IHMI
PTOC1
PTOC1.Op.general
PTOC1.Str.general
CSWI1
PTOC1
PTOC1.Op.general
CSWI2
Page 19 of 22
CSWI2.OpOpn.general
CSWI2.OpCls.general
CSWI2
CSWI2.Pos.origin
CSWI2.OpOpn.general
CSWI2.OpCls.general
XCBR2
CSWI2
CSWI2.Pos.origin
CSWI2.OpOpn.general
CSWI2.OpCls.general
XSWI3
CSWI2
CSWI2.Pos.origin
CILO2.EnaOpn.stVal
XSWI4
CILO2
COLO2.EnaCls.stVal
CILO2.EnaOpn.stVal
CSWI2
CILO2
COLO2.EnaCls.stVal
XCBR1.Loc.stVal
XCBR1.Op.Cnt.stVal
XCBR1.Pos.origin
XCBR1.BlkOpn.origin
XCBR1.BlkCls.origin
CILO3
XCBR1
XCBR1.CBOpCap.origin
XCBR2.Loc.stVal
XCBR2.Op.Cnt.stVal
XCBR2.Pos.origin
XCBR2.BlkOpn.origin
XCBR2.BlkCls.origin
CILO1
XCBR2
CILO2
XCBR2.CBOpCap.origin
CILO3.EnaOpn.stVal
CILO3
COLO3.EnaCls.stVal
CILO3.EnaOpn.stVal
CSWI1
CILO3
COLO3.EnaCls.stVal
CSWI2
IHMI
IHMI
CSWI1
IHMI
CSWI2
IHMI
References
[1] McDonald, John D, Electric Power Substations Engineering, Third Edition, CRC
Press, 2012
[2] Chen, Wai-Kai (eds), The Electrical Engineering Hand Book, Academic Press,
2004
Page 20 of 22
[3]
http://www.electrical4u.com/differential-protection-of-transformer-differentialrelays/, accessed 22 Nov 2014
[4] Sleva, Anthony, Protective Relay Principle, CRC Press, 2009
[5]
http://electrical-engineering-portal.com/types-and-applications-of-over-current
-relay-1, accessed 22 Nov 2014
[6] IEC-62850-5, Communication Network System in Substation, IEC, 2003
[7] Aktaibi et al, Digital Differential Protection of Power Transformer Using Matlab,
Intech, 2012
Page 21 of 22
Appendix
List of Figures
Figure 1 Substation Topology Overview......................................................................3
Figure 2 Single Line Diagram of a double-bus single breaker system.........................4
Figure 3Single Line Diagram depicting the bays.........................................................6
Figure 4 Normal Operating Condition for the substation............................................7
Figure 5 Open CB1- First step for circuit breaker maintenance...................................8
Figure 6 Open the disconnecters- Step 2 for CB maintenance...................................9
Figure 7 Remove CB1 -Third step for CB maintenance.............................................10
Figure 8 Place new CB1 -Fourth step for CB maintenance........................................11
Figure 9 Close the disconnecters and CB1new Sixth step for CB maintenance...........12
Figure 10 Zones in the substation design.................................................................13
Figure 11 Instantaneous over-current, definite time over-current and IDMT relays. .14
Figure 12 Substation protection zone 7....................................................................15
Figure 14 Differential protection in Bus bar 1..........................................................16
Figure 13 Differential protection of Power Transformer (Source: Adel Aktaibi et al, 2 )
................................................................................................................................. 16
Figure 15 Implementation of undervoltage protection in bus bar 2 by placing VT 2 17
Figure 16 Over-current protection scheme...............................................................18
List of Tables
Table
Table
Table
Table
Table
Page 22 of 22