Professional Documents
Culture Documents
February 2006
Prepared by
Prepared for
Table of Contents
Page
Section I
Section II
2.1
2.2
2.3
2.4
2.5
PROJECT BACKGROUND
OBJECTIVE OF THE REVIEW
REVIEW TEAM
REVIEW CLARIFICATIONS / QUALIFICATIONS
METHODOLOGY
3.3
3.4
13
20
4.1
4.2
22
Page
4.3
39
4.4
46
4.5
54
Appendices:
Page
Appendix A
62
Appendix B
64
Appendix C
86
Appendix D
88
Appendix E
92
REVIEW FINDINGS:
The findings of the Review are summarized as follows:
It was confirmed that the project estimate is consistent with the current stage of project
development
The river bridge extradosed type, aesthetics, configuration and constructability are major
contributors to the risk associated with the project costs.
Some specific scope was not accounted for the in the base estimate
Estimate did not account for inflation to the projects estimated mid-point of expenditure
Estimate did not account for Construction Contingencies that may be required due to unforeseen
conditions, changes in cost or time, etc.
Estimate did not account for other potential risk
Some enhanced components to the MnDOT Length, Width and Depth (LWD) conceptual cost
estimating system were recommended as follows:
o The selection of multipliers should be documented
o The LWD Process has limitations where major bridges are a part of the project and as such
should account for these conditions
The above table demonstrates that the Team considered an additional $68 Million should be
added to the 2004 cost estimate for the project. This additional amount is made up of $22
million of base costs for scope not included and $46 million of additional risk the Team
considered should be included in the estimate at this time. The 2010 Programming estimate
includes escalation to 2010, plus Construction Contingency and Management Reserve that the
Team recommended to be added to the Programming estimate.
5
REVIEW RECOMMENDATIONS:
The Team presented the following recommendations at the completion of the Review:
The proposed extradosed bridge for the river spans has a relatively high cost risk. This risk
should be managed through:
o Cost effective design decisions on the river bridge (aesthetics, configuration)
o Focus on the constructability of the river bridge
o Contractor involvement / options
The Cost Estimate should be increased to account for the additional known scope not accounted
for, the risks identified, inflation to mid-point of expenditure, and the construction contingencies.
The Team recommended that a cost estimate range be utilized when publishing estimated costs
for the project in lieu of a fixed cost estimate.
The Team provided the following cost estimate conclusions:
Description
Current Project
Estimate
2004 Base
2010 Programming
Team Recommended
Total Project
Estimate (with risk)
$373 M
$484 M
$305 M
Delta (Team
Recommendation
Current Estimate)
$68 M
Total
Project
Estimate
Review 2004
with Risk ~
$373 M
10% Probability
90% Probability
60%
Probability
from $400 to
$430 M
10% Probability
Current
Estimate
= $484M
90% Probability
Project Description:
Schedule:
Current
Estimate
= $484M
Project Benefits:
Level of
Project Design:
90% Probability
Project Risks:
10% Probability
Low
Financial Assumptions:
Inflation estimate of 3% per year
Contingencies based on conceptual nature of
plans
Medium
High
FHWA
MnDOT
WisDOT, and
Consultant (PBS&J) staff
Appendix E includes a complete list of all the attendees as well as the Work Shop Sign-In sheets.
2.5 METHODOLOGY:
The Cost Estimate Review methodology was developed to ensure team members understood the
project scope and the associated current cost estimate (dated August 2005) of the Preferred
Alternative Package (roadway approaches; bridges - river crossing, inland, and lift bridge; and,
mitigation). A detailed Cost Estimate Review Agenda and Work Plan are included in Appendices C
and D.
The Team initially reviewed the project cost estimate at a summary level, and developed a list of
items that required further clarifications during the review of the more detailed breakdown of the
current cost estimate. A site visit of the project was performed on the evening of the second day of
the review. This enabled the consultant Team members to get a better understanding of the site
conditions on both sides of the river and the constructability issues.
10
An understanding of the Minnesota DOT Metro Length, Width, and Depth (LWD) estimating
process of standardized cost estimates for Roadway elements (refer to section below)
Basis, Assumptions and Process in the development of the cost estimate
Scope included in the Preferred Alternative Package cost estimate
Understanding of the scope NOT accounted for in the current cost estimate
Technical Disciplines input (Roadway, Structures, ROW, Mitigation, etc.)
Basis of quantities and unit costs
Allowances, Mark-ups (contractor, design, etc.), and Contingencies
Validity of present day costs for Preferred Alternative Package
Review other similar bridge types Example of Connecticut Bridge
Market Conditions, Price Fluctuations
Identification and accounting for Risks and Opportunities
Overview of Project Schedules and Inflation analysis
Establishment of Estimated Total Future costs
11
LWD multiplier is based on previously awarded bid costs history (low accepted bids only)
LWD multiplier is arrived at based on analyzing recent similar projects, specific conditions
of the project being estimated, and estimators judgment.
LWD includes 11 Roadway elements and other project elements
Railroad relocation costs not included in current estimate. Possible $4-$5 M
Public relations costs not included in the current estimate.
Bridge current cost estimates include little to no risk for the bridge structures
Roadway includes 10% scope risk
Unknown contamination with existing fertilizer terra terminal building included
Erosion control costs need to be higher in estimate based on current requirements
Water Quality cost impacts could be higher
Aesthetics costs are limited to budgets based on cost participating percentages
Utility relocation costs include Sanitary Sewer relocation due to depression in road
Higher fill quantity on the Minnesota side and at grade construction largely in Wisconsin
No muck anticipated on the Project
Landscaping costs are included in Visual Quality costs
No noise walls requirement anticipated for the Project
$200,000 included for signalization per signalized intersection (possibility of round-abouts
was noted, but costs would be similar)
LWD Multipliers vary from project to project based on location, complexity, scope and other
factors. For example the multiplier is $80,000 for the Wisconsin scope, $90,000 for
Minnesota Seg. I and $112,000 for the Minnesota Approach Spans.
LWD Factor accounts for all paved areas including concrete and bituminous areas
The above review of the LWD factors and approach and the current estimate was very beneficial to
the Team in preparing a strategy to assess the risks associated with the project and to complete the
Review.
The following sections describe the findings, recommendations, and the detailed probability analysis
that was performed in this review.
12
$ 6.9
$ 5.4
$ 3.8
$ 3.0
$ 0.7
$ 0.3
$ 0.3
$ 0.1
$5.3
$-4.2
$22 M
In addition, the Team analyzed the risks associated with several elements of the cost estimate and
identified the following additional costs to account for those risks.
$ 30
$ 4
$ 1
$ 2
$ 9
$ 46 M
Thus the combined assessment of the Team added approximately $68 million dollars ($22 million
due to additional scope on the base costs and $46 million in risk contingencies) to the 2004 Project
Cost Estimate, increasing it from a $305 million dollar base to a $373 million dollar base, which
amounts to an increase of approximately 22%.
13
Add $22 million due to known scope not previously accounted for
Add $46 million in risk based on a risk assessment the Team performed on the current estimate
of the project
Recommended 2004 Total Project Costs of $373 million including the above two additions
(Refer to Appendix A for a detailed breakdown of the $373 Million cost estimate)
Apply a 3% yearly Inflation rate to escalate the 2004 estimate to the projected estimated
midpoint of expenditures of 2010
Add 7.5% Construction Contingency (allowance for changes during construction)
Add 1% Management Reserve (allowance for third party changes during construction)
Recommended 2010 Total Project Costs of $484 million based on the above changes
Based on the Review of the project cost estimate, the Team recommended the following changes to
the project estimate:
Following the results of the estimate review and based on the revised cost estimate, the Team then
analyzed the probabilities with the estimate values to help determine an estimate range. The
following pages describe the probability analysis for the overall 2004 and 2010 project cost
estimates as well as the 2004 estimate of the extradosed bridge structure. Section IV describes in
detail the procedures and findings of the probability analysis for all other line items in the cost
estimate.
14
Total
Project
Estimate
Review 2004
with Risk ~
$373 M
10% Probability
90% Probability
15
Total
Project
Estimate
Review 2010
with Risk ~
$484 M
10% Probability
90% Probability
16
Total ED
River Bridge
Span 2004
Estimate ~
$135 M
10% Probability
90% Probability
17
It was confirmed that the project estimate is consistent with the current stage of project
development
The river bridge extradosed type, aesthetics, configuration and constructability are major
contributors to the risk associated with the project costs.
Some specific scope was not accounted for the in the base estimate
Estimate did not account for inflation to the projects estimated mid-point of expenditure
Estimate did not account for Construction Contingencies that may be required due to
unforeseen conditions, changes in cost or time, etc.
Estimate did not account for other potential risk
Some enhanced components to the MnDOT Length, Width and Depth (LWD) conceptual
cost estimating system were recommended as follows:
o The selection of multipliers should be documented
o The LWD Process has limitations where major bridges are a part of the project and as
such should account for these conditions
The proposed extradosed bridge for the river spans has a relatively high cost risk. The risk
should be managed through:
o Cost effective design decisions on the river bridge (aesthetics, configuration)
o Focus on the constructability of the river bridge
o Contractor involvement / options
The Cost Estimate should be increased to account for the additional known scope not
accounted for, the risks identified, inflation to mid-point of expenditure, and the construction
contingencies.
The Team recommended that a cost estimate range be utilized when publishing estimated
costs for the project in lieu of a fixed cost estimate
The recommended Range of the current Cost Estimate Probability in the mid-80% certainty level is
noted as follows:
Estimate
2004 Base
2010 Programming
Based on these summary conclusions the Team recommends that the project team continue to
finalize the extradosed bridge design concept using cost effective design decisions in the process.
This will result in further defining the project costs and possibly reducing the amount of cost risk to
be included in future cost estimates.
18
Due to the recent national disasters related to Hurricanes Katrina, Rita and Wilma, there is wide
spread speculation that the construction industry will be impacted with increasing prices, shortage of
material, labor and equipment and also increasing bonding and insurance costs. It is recommended
that for this project, the construction market be closely monitored to capture any such impacts as
they relate to the project budget. In addition, due to the unique nature of the proposed extradosed
bridge, since the New Haven Harbor Crossing Pearl Harbor Memorial Bridge (Q-Bridge) is very
similar in nature to the proposed bridge; the eventual bid costs of the Q-Bridge (after letting/award)
should be utilized to update the proposed budgets for the St. Croix River Crossing project.
19
The preceding sample probability chart demonstrates that the selector of this curve considered
that the highest probability for a bid amount for this item is in the range of $16,000,000 to
$17,000,000 (this highest range is typically the current cost estimate for the item). The selector
also considers that there is a chance the low bid could come in quite low (see minimal range of
probability between $6,000,000 and $12,000,000), but a lower possibility that a high bid would
be significantly high (see highest range is close to $20,000,000). Probability curves like this one
are typically selected based on the risks and opportunities identified with each item. In this case,
the Team selecting the probability curve had confidence that a bid would be submitted for the
item in the current estimate range of $16 million to $17 million, and that it was more likely that a
lower bid would be received, demonstrating the Teams confidence that there were good
opportunities for a lower bid, and there were no risks identified that would result in a
significantly higher bid than the current cost estimate.
Once the probability curves are selected, the software program generates random numbers based
on the curve (if run thousands of times the results would closely approximate the curve). These
random numbers are then added at bottom line forecast totals, and a forecast curve is then
generated creating a combined probability curve for the sub-total and totals of a group of
numbers.
20
21
Note: Aesthetics calculation in the above table excludes the Loop Trail costs
2004 Estimate
10% Probability
90% Probability
22
A review of the roadway elements for this section of the project showed that the LWD multiplier
utilized appeared to be reasonable for the scope, noting that this portion would have a higher fill
quantity than the Wisconsin approach. An additional 5% was added to this item for the
contractors costs to meet environmental regulations such as erosion control requirements. An
additional 1.25% was also added to the multiplier to cover the costs of high performance
pavement. Based on the MnDOT history on the price per square foot, the $94,500 utilized is
considered conservative for this work.
Curve: Minimum Extreme Distribution - Lower risk of bid greatly exceeding estimate. Bid
could fall somewhat below the estimate as a result of the conservatively high unit price utilized
as a multiplier in the LWD system.
23
4.1.2
Loop Trail
A review of the trail elements showed that the Team felt the $80,000 per mile unit price was
reasonable for this work effort. The Team did not see any significant risk in this item.
Curve: Students t distribution - Low probability of bid being significantly higher or lower
than estimate for the trail.
4.1.3
The modular brick retaining walls unit price was based on similar walls. The $20 per square foot
was considered reasonable by the team.
Curve: Normal distribution - Medium risk bid could fall higher or lower than estimate
24
4.1.4
Signals
Signal costs were estimated at $200,000 per intersection based on similar recent projects. The
Team considered this as a reasonable estimate that had relatively low cost risk.
Curve: Students t distribution - Low risk on bid being significantly higher or lower than
estimate.
4.1.5
Risk (10%)
The MnDOT LWD system estimate had included a risk factor of 10% for this Part I of the
Project. Based on the Teams assessment of risk, the 10% factor was considered a reasonable
amount for this scope of work.
25
4.1.6
Aesthetics (7.5%)
The cost for aesthetic enhancements has been included in the estimate and capped at a mitigation
package negotiation maximum level of 7.5% of the construction costs. As the aesthetics become
further defined, it will be required to ensure that the costs will be within the 7.5% limit.
Curve: Minimum Extreme Distribution - Lower risk of bid greatly exceeding estimate. Bid
could fall somewhat below the estimate as a result of the conservatively high unit price
26
4.1.7
Right of Way
The review of right-of-way cost estimates demonstrated that the parcels have been identified and
the MnDOT right-of-way staff had estimated all of the costs considered to be associated with
securing the right-of-way for the project. The Review Team agreed to add an additional 10%
contingency on the estimates for this section of the Project.
Curve: Gamma Distribution - Probability is high that costs will exceed the estimate, while
considered low that prices will fall below the estimate. Increasing land and housing prices have
been considered in this probability.
27
Note: Aesthetics calculation in the above table excludes the bridges and trail costs
2004 Estimate
10% Probability
90% Probability
A review of the roadway elements for this section of the project showed that the LWD multiplier
utilized appeared to be reasonable for the scope, noting that this portion would also have a higher
fill quantity than the Wisconsin approach. This section included an interchange and ramps that
made the estimate higher on a cost per square foot basis. An additional 5% was added to this
item for the contractors costs to meet environmental regulations such as erosion control
requirements. An additional 1.25% was also added to the multiplier to cover the costs of high
performance pavement. Based on the MnDOT history on the price per square foot, the $117,600
utilized is considered conservatively high for this work.
29
4.2.2
The estimated bridge cost, for an assumed curved steel structure of $125 per square foot for
Beach Road over Trunk Highway (TH) 36 was discussed by the bridge structure focus group and
found to be reasonable. The bid results from previous projects and current industry knowledge
were utilized to arrive at this value.
Curve: Maximum Extreme Distribution - The Team considered a high probability of the bid
exceeding the estimate for this bridge. Low probability of the bid coming in significantly below
the estimate.
30
4.2.3
The estimated cost of $130 per square foot for the bridge at the Treatment Plant Access Road
was discussed by the bridge structure focus group and found to be reasonable. The concept of a
steel beam structure was the basis for the unit price. The bid results from previous projects and
current industry knowledge were utilized to arrive at this value.
Curve: Maximum Extreme Distribution - The Team considered a high probability of bid
exceeding estimate for this bridge, and a low probability of the bid coming in significantly below
the estimate.
31
4.2.4
TH 36 Bridges
The estimated cost of $180 per square foot for the Trunk Highway (TH) 36 Bridges was
discussed by the bridge structure focus group and found to be reasonable. Although the final
concept for these bridges has not been finalized, they will be the approach spans to the
extradosed main spans of the River Bridge. These approach spans will be designed to fit
functionally and aesthetically with the main spans. They will also be constructed in a sensitive
environmental area, thus increasing the cost of construction. The Teams knowledge of the area
and of recent projects was utilized in arriving at this price. The Team did see significant cost
risk with this project element due to environmental considerations and design complexity.
Curve: Maximum Extreme Distribution - High probability of bid exceeding estimate. Low
probability of the bid coming in significantly below the estimate.
4.2.5
The removal of two existing bridges will be required during the construction of this part of the
Project. The MnDOT Team member provided an estimate of $100,000 per bridge, and the Team
considered that this is a reasonable estimate for this scope of work.
Curve: Logistic Distribution- Reasonable probability that the bid will fall within the range of
the estimate for the existing bridge removals.
32
4.2.6
Loop Trail
A review of the Loop Trail elements showed that the Team felt the $80,000 per mile unit price
was reasonable for this work effort. The Team did not see any significant risk in this item.
Curve: Normal Distribution- Average probability that the bid will fall within the range of the
estimate with equal chance of being above or below the estimate.
4.2.7
Approach Panels
Bridge approach panels were estimated based on recent MnDOT pricing. The bid results from
previous projects were utilized to arrive at this value. The Team considered the price of $20,000
per panel as a reasonable current estimate for this work.
Curve: Normal Distribution - Average probability that the bid will fall within the range of the
estimate with equal chance of being above or below the estimate.
33
4.2.8
A relative low quantity of cast-in-place (CIP) retaining walls has been estimated for this part of
the Project. The Team agreed with the MnDOT estimate of $75 per square foot of wall area as a
reasonable price for this element.
Curve: Normal Distribution - Average probability that the bid will fall within the range of the
estimate with equal chance of being above or below the estimate.
4.2.9
An allowance of $200,000 was utilized for contaminated soils cleanup. This is based on those
areas that have been identified where it is likely that this could occur. The environmental team
members knowledge of the corridor provided the impression to the Team that this was a
reasonable allowance without a huge risk.
Curve: Maximum Extreme Distribution - High probability of bid exceeding estimate. Low
probability of the bid coming in significantly below the estimate.
34
4.2.10
Signals
Signal costs were estimated at $200,000 per intersection based on similar recent projects. The
Team considered this as a reasonable estimate that had relatively low cost risk.
Curve: Students t distribution - Low probability on bid being significantly higher or lower
than estimate.
4.2.11
The MnDOT LWD system estimate had included a risk factor of 10% for this Part 2 of the
Project. Based on the Teams assessment of risk, the 10% was considered a reasonable amount
for this scope of work, excluding the bridge approach spans to the main span of the River Bridge.
The Team considered that the LWD multiplier for this item was conservatively high.
4.2.12
The risk on the approach spans to the extradosed main span was analyzed separately by the
structural focus group assembled during the Review. The Team concluded that once the design
is further formalized, the risk could possibly be reduced. The risk was arrived at by analyzing
the elements of the bridge structure and coming up with a composite risk as shown in the
following table:
CATEGORY
Deck
Cables
Pylons / Piers
Foundations
Other / Miscellaneous
Total
a). Percentage of
Construction Cost
65%
N/A
10%
20%
5%
b). Risk /
c). = a x b; Composite
Contingency
Risk Factor
25%
16.3%
0.0%
50%
5.0%
10%
2.0%
20%
1.0%
100%
24.3%
35
4.2.13
Aesthetic elements were included in the estimate at 7.5% of the non-bridge elements (assuming
that bridge aesthetics are adequately accounted for in the bridge unit price). However, a portion
of this aesthetics amount is included for aesthetic modifications to the existing lift bridge, which
in the preferred alternative package is to become a part of the Loop Trail system.
Curve: Minimum Extreme Distribution - Lower risk of bid greatly exceeding estimate. Bid
could fall somewhat below the estimate as a result of the conservatively high unit price
36
4.2.14
Right of Way
The majority of the right-of-way for this portion of the project was purchased in the past. The
review of right-of-way cost estimates demonstrated that the parcels have been identified and the
MnDOT right-of-way staff had estimated all of the costs considered to be associated with
securing the right-of-way for the project. The Review Team agreed to add an additional 10%
contingency on the estimates for this section of the Project.
Curve: Gamma Distribution - Probability is high that costs will exceed the estimate, while
considered low that prices will fall below the estimate. Increasing land and housing prices have
been considered in this probability.
37
4.2.15
A railroad agreement will be required for railroad relocation and coordination during the
construction of this section of the project. An estimate of $5 million dollars was provided by the
MnDOT Team members based on current scope and estimates.
Curve: Normal Distribution - Average probability that the agreement costs will fall within the
range of the estimate with equal chance of being above or below the estimate.
4.2.16
MnDOT provided detailed costs on the major utility relocation anticipated for this portion of the
project. Unit prices were reviewed and considered adequate based on present day pricing.
Curve: Maximum Extreme Distribution - High probability of bid exceeding estimate. Low
probability of the bid coming in significantly below the estimate. The Team considered that the
utility unit prices did not include a lot of risk factors.
38
Note: Aesthetics calculation in the above table excludes the trail costs
2004 Estimate
90% Probability
10% Probability
A review of the roadway elements for this Wisconsin approach section of the project showed that
the LWD multiplier utilized appeared to be reasonable for the scope, noting that this portion had
minor fill quantities. The Wisconsin DOT also reviewed the multiplier and found it reasonable
for the scope of the Wisconsin approach. An additional 5% was added to this item for the
contractors costs to meet environmental regulations such as erosion control requirements. An
additional 1.25% was also added to the multiplier to cover the costs of high performance
pavement.
40
4.3.2
A unit price of $125 per SF of bridge deck was considered reasonable, considering that the Team
felt it would be a steel bridge in lieu of a standard concrete beam bridge.
Curve: Maximum Extreme Distribution - High probability of bid exceeding estimate. Low
probability of the bid coming in significantly below the estimate.
4.3.3
The Team considered a unit price of $75 per square foot of bridge deck was reasonable for this
bridge, with a concept of a standard concrete beam bridge considered.
4.3.4
Loop Trail
A review of the trail costs showed that the $80,000 per mile unit price was reasonable. The
Team did not see any significant risk in this item. (Note: The Trail only covers that portion to be
built on existing STH 64 from the east end of the existing lift bridge up the hill to existing STH
35. The other portions will be along a new STH 64 from the river to 35/E interchange).
Curve: Normal Distribution - Average probability that the bid will fall within the range of the
estimate with equal chance of being above or below the estimate.
4.3.5
Approach Panels
Bridge approach panels were estimated based on recent MnDOT pricing. The bid results from
previous projects were utilized to arrive at this value. The Team considered the price of $20,000
per panel as a reasonable current estimate for this work.
Curve: Logistic Distribution - Reasonable probability that the bid will fall within the range of
the estimate.
42
4.3.6
A price of $85 per square foot of retaining wall was agreed to by the Team, confirming the
current estimate.
Curve: Logistic Distribution - Reasonable probability that the bid will fall within the range of
the estimate
4.3.7
Signals/Roundabouts
Signal costs were estimated at $200,000 per intersection based on similar recent projects. The
Team considered this as a reasonable estimate that had relatively low cost risk. Roundabouts
may be considered in lieu of signals at the intersections in Wisconsin, and the Team considered
that the costs of each would be reasonably close.
Curve: Students t distribution - Low risk on bid being significantly higher or lower than
estimate, considering that signal costs are relatively consistent for an intersection
43
4.3.8
Risk (10%)
The MnDOT LWD system estimate had included a risk factor of 10% for this Part of the Project.
Based on the Teams assessment of risk, the 10% was considered a reasonable amount for this
scope of work.
4.3.9
Aesthetics (7.5%)
The cost of aesthetics has been included in the estimate at a mitigation package negotiation
maximum level of 7.5% of the construction costs. As the aesthetics become further defined, the
project team will be required to ensure that the associated estimated costs would be within the
7.5% limit.
44
Curve: Gamma Distribution - Probability is high that costs will exceed the estimate, while
considered low that prices will fall below the estimate. Increasing land and housing prices have
been considered in this probability.
45
4.4
Scope of Part 4: The new four lane bridge will cross the river at the present location of the
Highway 36/Highway 95 Interchange, approximately 7,550 feet south of the Lift Bridge along
the Minnesota shoreline, crossing the St. Croix River perpendicular to its centerline and landing
approximately 6,450 feet south of the Lift Bridge along the Wisconsin shoreline.
Note: Aesthetics in the above table is a set allowance for the river bridge.
2004 Estimate
Total ED
River Bridge
Span 2004
Estimate ~
$135 M
10% Probability
90% Probability
Estimate Review Base without Risk = $105 M
46
The Team determined that there was significant risk in the extradosed main span portion of this
project. Some of the major risks noted include the following:
Most of the work associated with pre-cast construction is done in the pre-casting
operation, which minimizes the time that the construction impacts the site
Pre-cast construction elements are highly durable (high performance concrete),
with lower life-cycle cost
Can improve construction zone safety with less work on-site
Based on the total width of the structure, if two Segmental concrete box girders
are be proposed at this location, the Precast concept will result in an increased
speed of construction as a result of ease of handling and erection.
48
Because of the short construction season the contractor may elect to perform as
much of the construction activity as possible using conventional precast
segmental technology
The Precast segments can reduce the erection time, the casting and erection can
occur simultaneously but independently. This parallel (production-line) method
provides maximum scheduling flexibility and construction time
This project is considered a large project; a standard shape of the superstructure
box girder will result in a significant cost saving as a result of increase speed of
erection.
The nature of segmental bridge requires that the protection of the deck be
paramount since the decks are not readily replaceable. To this end, overlays
should be considered for Extradosed bridge and also the approach bridge. Based
on the AASHTO LRFD Bridge Design Specifications, overlay is encouraged.
Additional cost should be added to the cost of the superstructure.
Impact loads
The design of the bridge foundations / piers to withstand the impact of ships or floating objects
was considered a cost risk to the project.
Other considerations the Team determined to minimize the potential time delay during design
and construction included the following:
The type of project delivery and procurement method was also discussed. Some of the major
items discussed included the following:
Design-build delivery system could result in a shorter construction time and shifts
the responsibility and risk to the design-build team. Stipends were also discussed
as a possibility. Concern with design-build is the amount of risk the contractor
will include for the extradosed bridge type.
Partial design/build (Best Value selection) was discussed as an alternative.
Design/bid/build; Traditional alternative could provide more price competition.
Risk is not having contracting community involved through the design phase and
bidding a less than optimal construction price.
Construction manager at risk (guaranteed maximum price); This system has good
contractor input through design, but no price competition.
Cost + time bidding; include incentives for schedule
Contracting techniques-incentive/disincentive
Partnering agreements
These major risks and factors provide an opportunity for the design selection team to manage the
concepts to result in alternatives that will allow a competitive market for efficient construction
solutions, thus minimizing the cost risks. Based on these risks the structural team evaluated each
category on the bridge and arrived at a composite risk factor for this portion of the project as
shown in the following table:
CATEGORY
Deck
Cables
Pylons / Piers
Foundations
Other / Miscellaneous
Total
a). Percentage of
Construction Cost
35%
10%
15%
35%
5%
b). Risk /
c). = a x b; Composite
Contingency
Risk Factor
20%
7.0%
15%
1.5%
100%
15.0%
25%
8.8%
20%
1.0%
100%
33.3%
After discussing the risk with the Team, the decision was made to utilize a 30% risk factor at this
time. This 30% factor was then included in the estimate and considered to cover much of the
risk associated with the risk items noted for this bridge.
50
51
4.4.2
Aesthetics (Allowance)
MnDOT discussed that, according to cost participation policy, an allowance of $3 million dollars
would be utilized for aesthetics on the St. Croix River Crossing. This includes the extradosed
river spans plus the main approach spans. The Team did not review this allowance.
Curve: Uniform Distribution - Fixed allowance for this aesthetics item resulted in the Team
recommending a uniform probability distribution.
52
4.4.3
Based on other comparable projects, an allowance of $3 million dollars was included in the
estimate for anti-icing equipment to be installed on the bridge. The Team considered this
allowance reasonable for this stage of the project.
Curve: Logistic Distribution - Reasonable probability that the bid will fall within the range of
the estimate for this bridge equipment. Team felt comfortable with information from recent
projects.
4.4.4
Right of Way
No right-of-way is required for this portion of the project crossing the river.
53
Mitigation
Fixed:
Variable:
Inflation
Estimate of the inflation (escalation) of the cost of design and construction costs as the
project progresses.
Construction Contingency
Contingency set aside for changes and unforeseen conditions during construction based
on the typical changes on other major structure projects throughout the country.
Management Reserve
Reserve set aside for the cost of approved requests for changes from outside parties such
as local municipalities and other public agencies/entities during construction.
54
4.5.1
Mitigation (Fixed)
Curve: Uniform Distribution - Fixed items for a portion of the mitigation have been identified
separately for this uniform probability distribution.
55
4.5.2
Mitigation (Variable)
Curve: Logistic Distribution - Reasonable probability that the bid will fall within the range of
the estimate for these variable mitigation items.
56
Limited pool of qualified consultants, designers, contractors could result in higher costs
Risk of increased costs due to delays
Risk of depth of knowledge/experience on this type of project
Risk of increased costs due to multiple contracts and multiple delivery methods
Funding availability could result in extended project duration increasing inflation costs
Curve: Maximum Extreme Distribution - High probability of bid exceeding estimate. Low
probability of the bid coming in significantly below the estimate. Although the Team considered
that the 25% factor covered all of these items, there was some concern that additional labor may
be required for the completion of the design stage, the construction stage, and the other project
development costs such as public involvement.
57
4.5.4
Inflation
Both MnDOT and WisDOT contacted their financial management team for information on
recent inflation. Both States considered that a 3% factor for inflation would be sufficient. The
Team did see significant risk in utilizing this amount, however, agreed to utilize this amount in
calculating inflation to the estimated midpoint of project expenditures in approximately 2010.
Curve: Normal Distribution - Average probability that the bid will fall within the range of the
estimate with equal chance of being above or below the estimate. This is based on the Minnesota
and Wisconsin DOTs agreeing that a 3% inflation factor is considered appropriate at this time.
Although a normal distribution was utilized, this is a major unknown that could play a significant
part in the bid costs when the project is bid.
58
4.5.5
Construction Contingency
Based on FHWA major projects having changes during construction in the range of 5% to 10%,
and WisDOT experiencing similar change values on their major projects, the Team agreed to
utilize a 7.5% construction contingency for unknowns during this project. This contingency is
intended to cover unforeseen conditions, scope changes and other impacts where contractually
the contractor is owed additional funds beyond the contract amount.
Curve: Normal Distribution - Average probability that the bid will fall within the range of the
estimate with equal chance of being above or below the estimate. Unknowns due to weather,
resource availability, site conditions and other events could impact this cost item.
59
4.5.6
Management Reserve
The Team discussed a management reserve to account for third party changes during
construction that have not been anticipated in the design. Although the Team did not consider
this a significant risk at this time, a 1% allowance was included in the estimate for the
management reserve.
This item is only an allowance and was not calculated in the bottom line probability distribution.
However, the 1% for management reserve is included in the final estimate based on the Teams
review.
4.5.7
Although not a specific line item in the estimate, the risks associated with different types of
project delivery methods were discussed by the Team. Some of the risks and opportunities
associated with utilizing Design-Build in lieu of the Design-Bid-Build method were identified as
the following:
Risks by utilizing Design-Build:
60
APPENDICES
61
APPENDIX A
Estimate Summary Spreadsheet
and
Summary of Mitigation Items
62
63
APPENDIX B
Estimate Review Summary Presentation
64
65
66
FHWA Staff
MnDOT Staff
WisDOT Staff
PBS&J (Consultant)
67
68
Monday, Aug. 8
Tuesday, Aug. 9
Thursday, Aug. 11
Wednesday, Aug. 10
Friday, Aug. 12
70
71
72
Project
Estimate
Review
Results
$295
$311
$10
$55
$305
$366
$71
$437
$37
$474
73
Project
Estimate
Review
Results
Delta
$295
$311
$16
$10
$55
$45
$305
$366
$61
$71
$437
$37
$474
74
Railroad Agreement
Erosion Control and High Perf. Pavement
Anti-Ice Bridge Deck Equipment
Major Utility Relocation Cost
Adjusted Wisc. STH 35 Bridge Cost per SF
Bridge Removals
Contaminated Soil Removal
Retaining Walls revised estimate
Reduction in Aesthetics revised estimate
75
$ 6.9
$ 5.4
$ 3.8
$ 3.0
$ 0.7
$ 0.3
$ 0.3
$ 0.1
$-4.2
~ $16 M
$ 30
$ 4
$ 1
$ 2
$ 8
$ 45 M
77
Frequency
Frequency
Estimated Cost
Estimated Cost
60% Certainty
River Bridge Maximum Extreme Distribution
Signals Students t Distribution
60% Certainty
Frequency
60%from
Probability
$306 to
from
$400
from$332
$100Mto to
$430
$120
M M
Estimated Cost
60% Probability
from $306 to
$332 M
Total Project
Estimate
Review 2004
with Risk ~
$366 M
60% Probability
from $400 to
$430 M
Total Project
Costs with risk
and inflation
2010 ~ $475 M
60% Probability
from
$100
to
60%
Probability
$120 from
M
$400 to
60% Probability
$430 M
from $100 to
$120 M
Total ED River
Bridge Spans
Estimate with risk
~ $135 M
82
Constructability
Competition precast vs. cast-in-place option
Materials availability
2004 Base
2010 Programming
20%
80%
$306 M
$400 M
$332 M
$430 M
84
Questions?
85
APPENDIX C
Review Agenda
86
WORKSHOP AGENDA
DATE
TIME
ACTIVITY
8/8 - 8/12
7:30 am
Continental Breakfast
8/9 - 8/11
12:0012:30 Lunch
8/8 Mon
8-11
8/8
11-12
8/8
12-1
8/8
1 4:30
8/9 Tue
89
9-9:45
9:45-10:30
10:30-12:00
8/9
10:30-12:00
8/9
12:302:30
8/9
2:30-4:30
8/10 Wed
8-10:30
8/10
10:3012
8/10
12:304:30
8/11 Thu
812
8/11
12:304:30
8/12 Fri
8 11:30
8/12
12 2
87
APPENDIX D
Review Work Plan
88
WORK PLAN
Objective: Verify the accuracy and reasonableness of the current total cost estimate to complete the
St. Croix River Bridge project and to develop a probability range for the cost estimate that represents
the projects stage of design.
Project Background: This project consists of a new National Highway System crossing of the St.
Croix River, a federally designated wild and scenic river and the State Line between Minnesota and
Wisconsin. The purpose of the project is to provide the capacity for existing and future traffic needs
and to remove through traffic from local traffic within historic downtown Stillwater, Minnesota.
The construction portion of the project consists of 4 elements: 1) Trunk Highway (TH) 36 Trunk
Highway (TH) 5 to Osgood Ave., 2) the Minnesota Approach, 3) The River Bridge Crossing, and 4)
the Wisconsin Approach. This project is currently in the National Environmental Policy Act of 1969
(NEPA) stage. The cost estimate for the extradosed bridge in alternative B-1 will be reviewed along
with the Minnesota and Wisconsin Approaches and TH36-TH 5 to Osgood Ave.
Approach/Methodology:
Use a systematic process review to evaluate the available information and then identify and
describe cost risks associated with the unknown elements of the project. Prioritize all
identified risks and assign costs to each risk.
Use appropriate computer simulation software to model the cost estimate structure.
Develop the cost estimate and schedule for the project as a probability range.
A team has been assembled to meet the above objective utilizing information, which will be
provided by MnDOT. The Team will be reviewing with the Supplemental Draft Environmental
Impact Statements (SDEIS) total project cost estimate report for Alternative B-1 extradosed bridge
option.
89
Task / Time
Mon 8/8
am
pm
Tue 8/9
am
pm
Wed 8/10
am
pm
Thu 8/11
am
pm
Fri 8/12
am
pm
The above schedule will be utilized to keep the Review on track, however, there will be flexibility
should further review of certain disciplines be required.
The team will review all components of the Total Project Current Cost Estimate. Validity of present
day costs, inflation factors, and the application of contingencies will be analyzed.
90
Results: The results will be summarized for a preliminary briefing on Friday afternoon, August 12th,
and will be submitted in a final report to be issued within 30 days of the completion of the Review.
Team Members: The following will participate as team members for the cost review:
91
APPENDIX E
Cost Estimate Review
List of Attendees
and
Daily Sign-in Sheets
92
Represents
MnDOT ICI
MnDOT BR DB
MnDOT Metro
WisDOT PM
MnDOT Envir.
PBS&J
PBS&J
PBS&J
FHWA
FHWA
FHWA
FHWA
FHWA Washington
MnDOT Bridge
MnDOT Metro
MnDOT Metro
MnDOT ICI
MnDOT Metro
MnDOT Metro
MnDOT LA
MNDOT Bridge
MnDOT Metro
MnDOT Metro
MnDOT Dep Comm
MnDOT Operations
MnDOT Eng Services
MnDOT Metro
MnDOT Bridge
MnDOT Bridge
MnDOT Bridge
MnDOT Bridge
MnDOT Bridge
WisDOT Bridge
MnDOT Grad. Eng.
MnDOT Construction
MnDOT Geotech
FHWA
WisDOT Environmental
WisDOT
MnDOT Metro
WisDOT Planning
On the second day (Tuesday) of the Review, a member of the design team for an extradosed
bridge structure currently being designed for the I-95 New Harbor Crossing (Pearl Harbor
Memorial Bridge) in New Haven, Connecticut, also joined the Team to provide an overview of
extradosed bridges and to participate in a bridge structures focus group that day.
93
94
95
96
97
98