Professional Documents
Culture Documents
Aim: To familiarize with Sure Trak Project Management Software (Version: Primavera
3.0
Oracle's Primavera SureTrak Project Manger 3.0 is a project management software that is ideal
for resource planning and control on small- to medium-sized projects. A Project is a set of
operations or activities to be completed in a logical order. A schedule is an attempt to model
these activities and their relationships. These operations take time to complete and may use
resources that have limited availability. Primavera Sure Trak project planner allows user to:
1. Enter the breakdown structure of the project(WBS or PBS) into the software
2. Assign durations, constraints, predecessors, successors of the activities and then calculate the
start and finish dates of all activities
3. Assign resources, which represent people, equipment or materials, to the activities and
calculate the project resource requirements.
4. Set target dates and budgets to compare progress against.
5. Record the actual progress of activities of the original plan and amend the plan when required
6. Record the consumption of resources and re-estimate the resources required to complete the
project
7. Prepare project management reports.
There are four modes or levels in which Sure Trak planning and the scheduling software may be
used.
Level 1. Planing without resources
Level 2. Traking Progress without resources
Level 3. Planing with resources
Level 4. Traking progress with resources
There are three methods of creating a new project in Sure Trak
1. Use a template that contains default data and formats.
2. Copy an old project and modify it.
3. Use the Sure Trak Project KickStart Wizard.
Sure Trak will work with four file types
1. Sure Trak is the standard format for the Sure Trak files in a single project environment
(without sub-projects) and allows Long File Names.
2. Project Groups is used when there are a number of projects sharing the same resources or
projects that need to be managed or reported as a group, and this file type should have exactly
four characters in the file name.
3. Concentric (P3) is used when it is required to share a project or project group with P3 users
and this file type must have exactly four characters in the file name.
4. MPX is a Microsoft Project text data format.
Display style is the format used to display durations in bar chart columns. Select days unless
more detailed planning are required.
2. Resource options
Resource options affect how the software calculates the percentages, remaining durations and
costs.
When the Link remaining duration and schedule percent complete is checked then the
remaining duration and percent complete will change proportionally. It is the only option that
affect the calculation of schedules without resources. It is suggested that it is left unchecked.
3. System Default Options
Starting SureTrak
The program is started by double clicking the Sure Trak icon
Use a long file name for Sure Trak file type. Must be exactly four characters when the Project
Groups or Concentric type is selected.
Select a project template. Template holds default calendars, resources, activity codes, activities,
relationships and resource assignments.
Planning units of days or hours is selected for concentric and project groups type files. A Sure
Trak Project calculates in hours and the duration may be displayed in days or hours.
Add this new project to a project group allows the creation of a project as a member of a project
gruop. Select the project group as the type and assign a two character ID that must start with a
letter.
Start Date: The Sure Trak will not schedule before this date
Must finish by is an optional field.
Primavera SureTrak Exercise1
Aim: To study the project planning and scheduling without resources using Primavera Sure Trak
3.0
1. Create a new project in SureTrak using the following data:
3. Define Calendars
Calendars are used to model holidays and other non-work period times. There are two types of
calendars; the Global Calendar and specific user defined Base calendars. The Global Calendar
affects all other calendars and all standard holidays. Typical calendars might be five day and six
day work weeks. This is also where we define how many hours are available per day. Base
calendars are assigned to Activities.
5. Creating Logic
SureTrak Relationships
Finish-To-Start (FS) -The succeeding activity can start immediately after the
predecessor finishes
Start-To-Start (SS) -The successor activity can start immediately when the
predecessor starts
Finish-To-Finish (FF) - The successor activity can finish immediately when the
predecessor finishes
7. Assigning Constraints
With Detail Form:
o Right Click on the activity, select Activity Detail, Constraints.
With Drag and Drop:
o Put curser over Activity until you see the + sign. click and drag activity to the
desired date.
Choose to Apply the Constraint
Driving Resource: When a driving resource is assigned to an activity it will determine the
duration of the activity and will over ride the duration entered in the task form. When there is
more than one driving resource then duration of the longest
resource will determine the length of the activity.
Non-driving Resource: Non-driving resource has no effect on the duration enterd in the task
form
It is recommended that all resources are entered as non-driving type unless scheduling
requirements dictate that driving resources are required.
Creating Resources
Add the following resources to the new project by adding them to the resource dictionary
9.
9
Results: The project planning and scheduling without resources using Primavera Sure
Trak 3.0 software are studied.
NO: 2
Exercise-I-Project Planning & Scheduling without Resources
Project definition: Installation of air pollution control equipment requires the following activities.