Professional Documents
Culture Documents
Conception
Feasibility &
Selection
Design &
Planning
Development
Decommissioning
Operations
Closeout
Fundamentals: Risk
Payment Methods
Lump Sum / fixed price
Time & materials - Unit Prices
Cost Plus Percentage
Cost Plus Fixed Fee
Guaranteed Maximum Price
Incentive
3
Schwalbe, 2006
Table 3-1: Potential negative risk conditions associated with each knowledge area
Knowledge Area
Integration
Scope
Risk Conditions
Inadequate planning; poor resource allocation; poor integration management;
lack of post-project review
Poor definition of scope or work packages; incomplete definition
Cost
Quality
Time
Risk
Procurement
Human Resources
Communications
Source: Wideman, R. Max, Project and Program Risk Management: A Guide to Managing Project Risks & Opportunities, Upper Darby,
PA: Project Management Institute, 1992, II 4.
Medium
Big risk
Figure 3-1: Risk classification
based on likelihood of occurrence
and impact on project
Likelihood/
probability
Small risk
Medium
Severity of impact
10
Cost(OMR)
11
Delay
Quality
Reputation
Major
Impact
Extra
100,000s
Medium
impact
Some impairment
of a major
function
Some impact on
Goodwill
Low
Impact
Extra 1,000s
Some impairment
of a minor
function
Minor impact on
Goodwill
Several
months
A few
days
Severe
Negative publicity in
impairment or loss major news channels
of a function
Loss of public trust
Significant impact on
Goodwill
Response/ treatment
Summary
Accept
12
Risk sharing
Reducing the
likelihood
Likelihood
(L)
1
2
3
4
5
14
Severity
(S)
Very unlikely
Unlikely
Likely
Very Likely
Probable
1
2
3
4
5
No impact or harm
Low Impact minor injury no lost time
Medium impact injury or ill health OVER 3 days lost time
High impact major injury or possible loss, including death
Very high impact multiple casualties or loss of more than one
life
10
15
20
25
12
16
20
12
15
10
HIGH
MEDIUM
LOW
Fundamentals
Payment Methods
Fixed price or Lump Sum
Time and Materials (T&M) -Unit Prices
Cost reimbursable
Cost Plus Percentage
Cost Plus Fixed Fee
Guaranteed Maximum Price
Incentive
15
Example:
Owner and contractor enter into a Lump Sum
agreement, OMR 20,000. The actual costs
incurred by the contractor are OMR 18,500.
Price charged to owner:
Contractor profit:
17
Fundamentals
Payment Method
Lump Sum
Unit Prices
Cost Plus Percentage
Cost Plus Fixed Fee
Guaranteed Maximum Price
Incentive
18
Fundamentals
Payment Method
Lump Sum
Unit Prices
Cost Plus Percentage
Cost Plus Fixed Fee
Guaranteed Maximum Price
Incentive
20
21
Example:
Your company has entered into a Cost plus
Percentage contract with contractor X. At the end
of the project the contractors actual costs are
OMR10,000. The contract percentage is 2%. What
is the price charged to the owner? What is the
contractors profit?
Price charged:
Contractor profit:
22
Fundamentals
Payment Method
Lump Sum
Unit Prices
Cost Plus Percentage
Cost Plus Fixed Fee
Guaranteed Maximum Price
Incentive
23
Example:
Owner and contractor enter into Cost plus fixed
fee agreement with the owner agreeing to pay
the contractor his costs plus an additional
OMR500. The actual costs were OMR3000.
What is..
The price charged to the owner:
Contractor profit:
25
100%
Lump Sum
0%
Owners risk
Contractors risk
CPFF
CP%
0%
100%
Figure 3-2: Risk sharing meter; comparing between lump sum, CPFF &
CPPC
26
Fundamentals
Payment Method
Lump Sum
Unit Prices
Cost Plus Percentage
Cost Plus Fixed Fee
Guaranteed Maximum Price
Incentive
27
28
Fundamentals
Payment Method
Lump Sum
Unit Prices
Cost Plus Percentage
Cost Plus Fixed Fee
Guaranteed Maximum Price
Incentive
29
Estimate
Mark-up
Contractor share
Owner Share
Actual cost
8000000
8500000
9000000
9500000
10000000
10500000
11000000
11500000
12000000
32
10000000
2%
30%
70%
Owner's Payment
Contractor's Gross
Profit
Owner's
Savings/Losses
Estimate
Mark-up
Contractor share
Owner Share
Actual cost
8000000
8500000
9000000
9500000
10000000
10500000
11000000
11500000
12000000
33
10000000
2%
30%
70%
Owner's Payment
8800000
9150000
9500000
9850000
10200000
10550000
10900000
11250000
11600000
Contractor's Gross
Profit
800000
650000
500000
350000
200000
50000
-100000
-250000
-400000
Owner's
Savings/Losses
1400000
1050000
700000
350000
0
-350000
-700000
-1050000
-1400000
References
Dr. Lee, S. (2007). Presentation to Project Management course in
MIT.
Project Management for Construction by Chris Hendrickson
available at http://pmbook.ce.cmu.edu/
Schwalbe, K., Information Technology Project management, 4th
Edition, 2006, Thomson Course Technology
Harold Kerzner, Ph.D., Project Management A systems approach
to planning, scheduling & controlling, 9th ed., 2006, John Wiley
& Sons, Inc.
Heldman, Kim, PMP: Project Management Professional, Study
Guide, 3rd edition, 2005, Wiley Publishing
Dr. Ammar Al Ojaili
34