RISK ASSESSMENT FOR ERECTION AND HOT WORK ACTIVITES OF CANOPY ON DOME, LOUVRE PROJECT.

SN

ACTIVITY

Hot Work
Welding
activities

HAZARD

Fire & Explosion

RISK
EVALUATION

Associated Risks

RISK
LEVEL

RESIDUAL RISK
IMPLEMENTED CONTROL MEASURES

H/M/L

H/M/L

supervisor

Fire of Building and workers

Metal particles

Fatal incident, injuries,

Electric burn

Abrasion, eye problem.

Responsible
Person

Ensure the proper housekeeping before start


od welding.

Ensure the safe platform for the erection of


canopy and hot work.

Fall of welder from


height

Ensure proper cable management.


Ensure welding machines, cords and cables
are in good conditions.
Ensure that the permit is issue as per client/
main contractor procedures.
Ensure the fire extinguisher media are in
place.
Ensure certified and competent welders.
Ensure fire watcher for each welder.
Ensure safe platform and safe access / egress
of scaffold while work at height.
Ensure regular supervision of hot work
activities.
Ensure monthly colour coding of all plant /
equipment.

Grinding
Activities

Sparks

Abrasion, injury and fractures

Fire & Explosion

Fatality, first aid case and near misses.

Sharp pieces,

Cut of finder / hand.

particles

Skin dermatitis.

Fall of material and


workers

Slip, trip and fall.

Noise and electricity


Workplace station

Ear deafness.
Electric shock and burn,
Dislocation of postures.

Ensure safe MEWP or Scaffold and inspected


by competent scaffold.

Maintain a gap of not more 6 mm (1/4)


between the grindstone and the guard shield.
Maintain a gap of not more than 3 mm (1/8)
between the grindstone and tool rest.
Install a transparent guard.
Ensure a safe system of work in place.
Ensure the ear muff and ear plug for workers.
Ensure the monthly inspection of power tools
(Grinders).
Ensure 110 v cable and power tool but in case
of high voltage than ensure the RCD of 30 mA.
Ensure the JSA and tool box talk for all
workers and staff.
Ensure complete PPEs for grinding work.

Page

1 of 5

RISK ASSESSMENT FOR ERECTION AND HOT WORK ACTIVITES OF CANOPY ON DOME, LOUVRE PROJECT.
3

2
Painting Works

Paints
HEMPELS GAL VOSIL15700, HEMPADUR
MASTIC-45881,
HEMPATHENE TOP
COAT-552H

Storage of
paints

Working at
heights

6
Wear the right personal Protective
Equipment

Ensure the job start card and TBT


before commencement of paints work.

Proper warning signs/ Close


Supervision

Ensure the availability of first aid


medicines & eye wash stations at
storage area

Understand on MSDS & this will discuss


in toolbox meetings

Follow Smoking policy at site

Ensure no hot work near the painting


activity

Provide proper storage facility as per


AD EHSMS VERION-2, FEBRUARY 2012

Provide enough ventilation/ Fire


Extinguisher

Ensure & keep the spill tray in


designated work area.

Keep inflammable materials away


from each other and direct heat

Identification tags to be displayed

Keep a copy of MSDS in store room

Provide proper platform with hand rails

Injury , Fatal accident

Scaffold & platform must be inspected


by competent person.

Property damage

Ensure the life line for anchorage

Provide full body harness of double


hooks for personnel

Provide proper signage & safe access/


egress.

Follow good house keeping

Barricade the area

Provide proper training & affective


supervision.

Injury to eyes
Skin Allergy & Burns
Headache & Un consciousness.

Fire

Fire or explosion

Falling from height


(cherry picker)
Falling of material and
people.

Engineer
Supervisor

Engineer
Supervisor

Page

2 of 5

RISK ASSESSMENT FOR ERECTION AND HOT WORK ACTIVITES OF CANOPY ON DOME, LOUVRE PROJECT.

SN

ACTIVITY

Painting works

LOADING,
OFFLOADIN
G AND
ERECTION
OF Canopy
or Edge
cladding to
Dome

HAZARD

Environmental
Hazard

Danger of
personnel
falling from
load

RISK
EVALUATION

Associated Risks
Contamination

P
3

RISK
LEVEL

S
2

H/M/L
6

Injury

Property damage, Personal serious


injuries, toppling of equipment,
accident

RESIDUAL RISK
IMPLEMENTED CONTROL MEASURES

Precautions in MSDS to follow

Ensure that all the chemical in concrete


bund and also inside the trip trays.

Ensure mock drill of chemical spillage


by environment engineer.

Proper disposal of paints and solvents

Proper storage of materials

Ensure the inventory log is display and


updated.

Swinging
of load
Improper
weather
conditions
Crane
failure
Incompete
nt people
like riggers
etc.
Uneven
ground
conditions
on site
Improper
use of
lifting

S
2

H/M/L
2

Responsible
Person

Safety
Officer

Ensure that only competent


and inducted people are
working at the site.
All the equipment like
crane should be inspected
by third party and
according to expected
lifting capacity.
All the lifting tackles must
be properly selected and
should valid third party
inspection.
Ensure proper PPEs.
Ensure safe access to load
Ensure crane operators
competency certificates.
Ensure area is barricaded
and unauthorized entry to
the area is prohibited.
The riggers should use tag
line while loading offloading the loads.
Ensure that weather
conditions are OK like high
wind and rain is not there.
Ensure TBT before lift.
Ensure proper supervision
for lifti

Page

3 of 5

RISK ASSESSMENT FOR ERECTION AND HOT WORK ACTIVITES OF CANOPY ON DOME, LOUVRE PROJECT.
gears

Persons in danger

All operatives and workers working around the area.

Visitors and neighbors of the working area.

Personal protective equipment

Safety Helmet, Safety Shoes, Coveralls, goggles. Chemical hand gloves , respiratory mask, painting dress, ear plug

Information, instruction and training

All personnel in the team are to be made aware of the safe systems of work.

Emergency procedures

Site emergency procedures should make provision for the rescue of individuals.

First-aid facilities should be available to cope with any significant injuries that may arise from the hazard.

Monitoring and review

Work should be monitored by Foreman and charge hands that are trained to ensure that any additional precautions or equipment required are
provided.

RISK ASSESSMENT COMMITTEE:

Project Manager/ Safety Engineer

Page

4 of 5

RISK ASSESSMENT FOR ERECTION AND HOT WORK ACTIVITES OF CANOPY ON DOME, LOUVRE PROJECT.

Page

5 of 5