Activity ID

2013
2014
Original Early Start Early Finish
September
October
November
December
January
February
March
April
Duration
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 3006
194 25-Sep-13 06-Apr-14

Activity Name

ADCB @ KBW Fit out & MEP works programme - R2

194 25-Sep-13 06-Apr-14

Interior fit-out works

3 25-Sep-13 28-Sep-13

General
Engineering / Pre-construction
Construction
Priliminary works
A1000
Access to site
Demolition
A1020

Removal of existing fittings & fixtures and H/O to client

77 19-Jan-14

06-Apr-14

0 19-Jan-14
0 19-Jan-14

19-Jan-14

15 19-Jan-14
2 19-Jan-14

03-Feb-14
21-Jan-14

A1330

Demolition works

9 21-Jan-14

30-Jan-14

A1340

Reparing disturbed surfaces due to demolition

4 30-Jan-14

03-Feb-14

Cement sand screed on floor

3 20-Feb-14 23-Feb-14
3 20-Feb-14 23-Feb-14

Civil works
A1370

Work
Kick
Receipt
off
order
meeting
of confirmation
drawings and docuemnts from the client / consultant

108 29-Sep-13 14-Jan-14

MEP 1st & 2nd fix


A1590
Conduiting & wiring

Preparation
Preparation
Submission
Preparation
Submission
Approval
Approval
Preparation
Submission
Approval
Preparation
of
of
Submission
for
of
of
layouts
Approval
Docs
MEP
sample
demolition
Civil
samples
documents
ofof
priliminary
for
of
Architectural
&and
Architectural
architectural
MEP
Demolition
of
boards
ofProduction
Joinery
joinery
plans
joinery
Glass
toitems
Carpet
CD
Production
drawings
for
drawings
Procurement
drawings
drawings
procurement
drawings
Authority
drawings
of
procurement
door
of frames
Submission
cupboards
loose
furniture
& doors
Delivery
CD
Submission
DM
approval
approval
of AHU
to
(Due
DMto Eid Holiday, varies)

Removal of existing fittings & fixtures and H/O to client


Demolition works
Reparing disturbed surfaces due to demolition
Cement sand screed on floor

25 30-Jan-14
21 30-Jan-14

24-Feb-14
20-Feb-14

Conduiting & wiring


AC ducting installation

A1670

AC ducting installation

21 30-Jan-14

20-Feb-14

A1700

FF pipes & drops installation

21 30-Jan-14

20-Feb-14

A1600

Cable tray installation

4 09-Feb-14 13-Feb-14

A1640

Low current wires instalaltion

4 13-Feb-14 17-Feb-14

Low current wires instalaltion

A1580

DB relocation & upgrading

4 17-Feb-14 21-Feb-14

DB relocation & upgrading

A1680

Connecting ducts to FCUs

4 20-Feb-14 24-Feb-14

Connecting ducts to FCUs

A1810

AHU installation and connection

4 20-Feb-14 24-Feb-14

AHU installation and connection

Ceiling finishes
A1520
Framework for ceiling

28 11-Feb-14
12 11-Feb-14

FF pipes & drops installation


Cable tray installation

11-Mar-14
23-Feb-14

Framework for ceiling

A1530

MEP clearence before ceiling closure

1 23-Feb-14 24-Feb-14

A1540

Board fixing, taping & jointing

8 24-Feb-14 04-Mar-14

MEP clearence before ceiling closure


Board fixing, taping & jointing

A1570

Lighting trough installation

4 04-Mar-14 08-Mar-14

Lighting trough installation

A1550

Suspended tile ceiling

4 07-Mar-14 11-Mar-14

Suspended tile ceiling

Wall Partitions
A1030
Stud framing for gypsum board partition

15 23-Feb-14 10-Mar-14
9 23-Feb-14 04-Mar-14

Stud framing for gypsum board partition

A1350

Gypsum lining to walls & columns

8 23-Feb-14 03-Mar-14

Gypsum lining to walls & columns

A1040

Gypsum boardng, taping & jointing including forming openings

7 24-Feb-14 03-Mar-14

Gypsum boardng, taping & jointing includi

A1060

Installation of glass panels

7 03-Mar-14 10-Mar-14

Wall finishes
A1450

Installation of glass panels

21 27-Feb-14 20-Mar-14
8 27-Feb-14 07-Mar-14

Primer / stucco on walls & ceiling

Primer / stucco on walls & ceiling

A1460

Wall tiles at toilet ar ea

5 03-Mar-14 08-Mar-14

A1440

Painting 1st coat on walls & ceiling

4 07-Mar-14 11-Mar-14

A1470

Backpainted glass installation

4 11-Mar-14

15-Mar-14

Backpainted glass installation

A1490

Repainting existing external walls

4 11-Mar-14

15-Mar-14

Repainting existing external walls

A1560

Painting 2nd & final coat on walls & ceiling

4 13-Mar-14 17-Mar-14

Painting 2nd & final coat on walls

A1480

Wall graphics and polycarbonate sheets

3 16-Mar-14 19-Mar-14

Wall graphics and polycarbonate

A1500

Skirting installation

3 17-Mar-14 20-Mar-14

Skirting installation

Project Start: 25-Sep-13

Actual Work
Remaining Work

Date: 16-Jan-14

Critical Remaining Work

ADCB @ KBW Fit out MEP works


programme - R2

Page 1 of 2

Wall tiles at toilet ar ea


Painting 1st coat on walls & ceiling

Date

Revision

Checked Approved

Activity ID

2013
2014
Original Early Start Early Finish
September
October
November
December
January
February
March
April
Duration
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 02 09 16 23 3006
14 07-Mar-14 21-Mar-14
4 07-Mar-14 11-Mar-14
Floor tiles combination

Activity Name

Floor finishes
A1380
Floor tiles combination
A1390

Jhonson wood grain tiles installation

3 11-Mar-14

14-Mar-14

Jhonson wood grain tiles installation

A1420

Raised access flooring installation

3 11-Mar-14

14-Mar-14

Raised access flooring installation

A1400

Viny flooring & unpolished tiles

3 14-Mar-14 17-Mar-14

A1410

Recessed carpet flooring including underlay

4 17-Mar-14 21-Mar-14

A1430

Grouting for tiles

2 17-Mar-14 19-Mar-14

Grouting for tiles

18 07-Mar-14 25-Mar-14
4 07-Mar-14 11-Mar-14

Instalaltion of door frames

Fixture units & joinery works


A1130
Instalaltion of door frames

Viny flooring & unpolished tiles

Recessed carpet flooring includ

A1110

Water closet ci stern enclosure installation

1 11-Mar-14

12-Mar-14

Water closet ci stern enclosure install

A1140

Instalaltion of door & ironmongery

4 11-Mar-14

15-Mar-14

Instalaltion of door & ironmongery

A1070

Floor mounted unit with work surface installation

4 20-Mar-14 24-Mar-14

Floor mounted unit with work

A1080

Overhead cupboards installation

4 20-Mar-14 24-Mar-14

Overhead cupboards installati

A1090

Installation of wall mounted vanity countertop

4 20-Mar-14 24-Mar-14

Installation of wall mounted va

A1100

Janitor's cupboard installation

4 20-Mar-14 24-Mar-14

Janitor's cupboard installation

A1120

Mirrors installation

1 24-Mar-14 25-Mar-14

Mirrors installation

Switches, socketes & light fittings ins

MEP final fix


A1650

Switches, socketes & light fittings installation

5 08-Mar-14 13-Mar-14
5 08-Mar-14 13-Mar-14

A1660

Grills & diffusers instalaltion

5 08-Mar-14 13-Mar-14

Grills & diffusers instalaltion

A1690

Sprinklers & fire alarm devices instalaltion

5 08-Mar-14 13-Mar-14

Sprinklers & fire alarm devices insta

23 10-Mar-14 06-Apr-14
6 10-Mar-14 17-Mar-14

Electrical & mechanical testing

MEP testing & comissioning


A1710
Electrical & mechanical testing
A1720

Authority inspection & approval

5 17-Mar-14 23-Mar-14

A1730

Snagging & desnagging

6 25-Mar-14 01-Apr-14

Snagging & desnagging

A1740

Client inspection

1 01-Apr-14

02-Apr-14

Client inspection

A1750

Final cleaning

2 02-Apr-14

05-Apr-14

Final cleaning

A1790

Handover

1 05-Apr-14

06-Apr-14

Handover

Project Start: 25-Sep-13

Actual Work
Remaining Work

Date: 16-Jan-14

Critical Remaining Work

ADCB @ KBW Fit out MEP works


programme - R2

Page 2 of 2