1 Tower / Mast

The workpackage includes all work and material (e.g. antenna mast, associated steel parts) that is needed to prepare,
construct, manufacture/fabricate, transport, erect and align a new tower/mast for mounting GSM and Microwave
antennas to suit the necessities of the GSM project for RadioMobil in the Czech Republic.
In more detail the work/installation to be carried out has to be according to the following specifications, the relevant
Czech Norms (CSN), laws and regulations including amendments and includes and is limited to:
2

Building services
- Clear away and store adjacently topsoil from locations designated for cranes, lorries and storage areas
- Supply and deliver good bearing material for soil replacement and terrain adjustment for crane, lorry
and storage locations
- Cover topsoil with adjacently stored surface soil
Foundation for the tower
- Build a reinforced concrete foundation for a good bearing base, using the permissible loading pressures
and in accordance with fixed requirements including excavated materials, soil removal and refilling of
excavations.
- The reinforcing steel of the foundation and all other metal parts shall be connected to the lightning
protection and grounding system (see Clause 10, 11 or 12 Lightning protection and grounding
system)
- The foundation has to be built in accordance to a proofed static analysis
- The following difficulties are not covered in the workpackage price:
- Soil Classes 1, 6 and 7
- Lowering of ground water levels
- Contaminated soil, ordnance
- Clearing of terrain affected by fouling or crops
- Breaking up fortified areas
- Location and movement of supply lines
- Special foundations
- Any other additional work which have to be done due to the reason of special conditions on
site
Antenna mast
- The following materials are permitted:
- hot galvanized steel pipe, corrosion resistant for maritime climate and very aggressive air
- or grid mast, corrosion resistant for maritime climate and very aggressive air
- or centrifugal molded concrete.
- The construction has to be as follows:
- Fixing points for attachment of ladder and vertical cable ducting.
- Designed for 6 GSM antennae on top with a diversity distance as specified (see Annex 1),
2 x 120 cm diameter MW antennas 4 m below the top of mast and 2 x 120 cm diameter
MW antennas 10 m below the top of mast. The static calculation for the mast has to be done
according to Czech law/regulations this means 0,55 kN/m 2 wind load for sea levels < 700 m
and 0,7 kN/m 2 wind load for sea levels > 700 m. The maximum elongation of the mast should
not be more then 0,5 degree under the above mentioned conditions.
- The mast and the GSM and MW antenna poles has to be designed for a wind velocity up to
200 km/h
A ladder (e.g. anodized Y-tree ladder, with a rung span of 280 mm and a tread width of 150 mm per side)
starting approximately 20 cm above the foundation neck shall be installed. The ladder shall be equipped
with a upper and a lower end stops and an ladder cover sheet to prevent unauthorized ascent of the ladder,
even from the rear.
Accessories for GSM and MW antennas (see also Clause 9 Antenna poles)
- The necessary hot galvanized antenna mounting systems for OMNI or sector antennas. The design
of these antenna mounting systems have to make sure, that the antennas will be reachable from the
mast (e.g. designed with pivot and fastening options for antenna cables and antenna frame bars
plus a small hot galvanized steel changeover (e.g. platform) located below the GSM antenna
mounting system and a safety ring located approx. 1.0 m above it for the attachment of safety
cables). For the design of the GSM antenna mounting system the minimum diversity distance of the
used antenna type has to be followed (see Annex 1).
- A maximum of 4 MW antenna mounting systems for mirrors up to 120 cm diameter, with variable
fastening options for frame bars of 108 mm diameter projecting approx. 50 cm.
A small hot galvanized steel changeover (e.g. platform) located below the MW antenna mounting
system and with a safety ring located approx. 1.0 m above it for the attachment of safety cables.

N S KPK, Stefan Kutz


Version 3.0
30.10.97

Page 1 / 20

7
8
9
10
11
12

A lightning protection and grounding system as specified (see Clause 10, 11 or 12 Lightning protection
and grounding system)
The needed cable support system as specified (see Clause 13 Cable support system)
A safety system for the personal climbing and working on the tower/mast (Soell security system), according
to safety regulations and their amendments valid in the Czech Republic.
If a Soell safety system is installed the needed interchange and get off services has also to be installed.
Installation of a key deposit
Site specific documentation as specified (see Clause 8 Documentation)
After the site has been finished it has to be left in such a condition that all changes necessary for the
installation process are removed.

Options if necessary (included in the package):


- If requested by a local authorithy etc. (e.g. army) an aircraft warning light including cabling, electrical
installation, sensor and connection to the back-up power supply from independent power supply
system.
Excluded but not limited to:
The following services are not included in the workpackage price:
- Provide a geological expertise or alternative a specialist subsoil assessment
- Flight warning markings (painting red/white)
- Additional painting of the whole tower.
- Protection of the site with a fence, including a door and a lock.
- Delivery of a key deposit
- Fell/remove and reprocess bushes, trees, overhanging branches etc. from the building site and the
closed area, including clearance of rootstocks
- Protect trees from damages where necessary
- Remove existing fencing and replace where necessary
- Protect existing power supplies or remove if necessary
- Rebuild fortified areas with asphalt following completion of the works if necessary
- Establish excavated earth dump for site, for the purposes of soil replacement
- Remove excess materials, including dumping charges
- Drain ditches
- Level and compress subsoil
- Construction of an access road
- Ensure that existing bridges and canals can be traversed by crane and lorries, and clear as necessary
- Remove of respectively divert existing services, both underground and above ground (e.g. water pipes,
power cables, sewage ducts).
- Delivery and installation of antennae and antenna cables
- All special or additional work due to the reason of the request by local authorities, environmental
department, army etc.
- Any other additional work which have to be done due to the reason of special conditions on site

N S KPK, Stefan Kutz


Version 3.0
30.10.97

Page 2 / 20

13 Roof top structure up to 8 m


The workpackage includes all work and material that is needed to prepare, construct, manufacture/fabricate,
transport, erect and align a roof-top structure for mounting GSM and Microwave antennas to suit the necessities of
the GSM project for RadioMobil in the Czech Republic.
In more detail the work/installation to be carried out has to be according to the following specifications, the relevant
Czech Norms (CSN), laws and regulations including amendments and includes and is limited to:
14
15
16
17
18
19

The needed antenna poles (MW and GSM) as specified (see Clause 9 Antenna poles)
A lightning protection and grounding system as specified (see Clause 10, 11 or 12 Lightning protection
and grounding system)
The needed cable support system as specified (see Clause 13 Cable support system)
Installation of a key deposit
Site specific documentation as specified (see Clause 8 Documentation)
After the site has been finished it has to be left in such a condition that all changes necessary for the
installation process are removed.

Options if necessary (included in the package):


- Installation of foot steps or ladder as specified (see Clause 9 Antenna poles).
Excluded but not limited to:
The following services are not included in the workpackage price:
- A improvement, reinforcement, restoration etc. of the roof top structure (e.g. existing walls, plaster, new
painting, roof structure, roofing felt/isolation, ladder), of the already existing building ground and
lightning protection system or other comparable repairs.
- Installation of a new lightning protection and grounding system etc. for the existing building.
- Building of new walls etc.
- Delivery of a key deposit
- A new structural analysis for the existing building
- All special or additional work due to the reason of the request by local authorities, environmental
department, army etc.
- Any other additional work which have to be done due to the reason of special conditions on site

N S KPK, Stefan Kutz


Version 3.0
30.10.97

Page 3 / 20

20 Existing Tow er
The workpackage includes all work and material that is needed to prepare, construct, transport, erect and align a
structure on an existing tower for mounting GSM and Microwave antennas to suit the necessities of the GSM project
for RadioMobil in the Czech Republic.
In more detail the work/installation to be carried out has to be according to the following specifications, the relevant
Czech Norms (CSN), laws and regulations including amendments and includes and is limited to:
21
22
23
24
25
26

The needed antenna poles (MW and GSM) as specified (see Clause 9 Antenna poles)
A lightning protection and grounding system as specified (see Clause 10, 11 or 12 Lightning protection
and grounding system)
The needed cable support system as specified (see Clause 13 Cable support system)
Installation of a key deposit
Site specific documentation as specified (see Clause 8 Documentation)
After the site has been finished it has to be left in such a condition that all changes necessary for the
installation process are removed.

Options if necessary (included in the package):


- A safety system for the personal climbing and working on the tower, according to safety regulations and
their amendments valid in the Czech Republic, if there is not already an existing one.
If there is no safety system installed, a Soell security system has to be installed.
If a Soell safety system will be installed the needed interchange and get off services has also to be
installed.
Excluded but not limited to:
The following services are not included in the workpackage price:
- A improvement, reinforcement, restoration etc. of the existing tower (e.g. new painting, foundation,
tower structure, ladder, platform), of the already existing tower grounding and lightning protection
system or other comparable repairs.
- Installation of a new ladder, platform, lightning protection and grounding system etc. for the existing
tower.
- Protection of the site with a fence, including a door and a lock.
- Delivery of a key deposit
- A new structural analysis for the existing tower
- All special or additional work due to the reason of the request by local authorities, environmental
department, army etc.
- Any other additional work which have to be done due to the reason of special conditions on site

N S KPK, Stefan Kutz


Version 3.0
30.10.97

Page 4 / 20

27

S p e c i a l s t r u c tu re ( C h i mn ey, Wat e r Tow e r, S i l o e t c . )

The workpackage includes all work and material that is needed to prepare, construct, transport, erect and align a
special structure for mounting GSM and Microwave antennas to suit the necessities of the GSM project for
RadioMobil in the Czech Republic.
In more detail the work/installation to be carried out has to be according to the following specifications, the relevant
Czech Norms (CSN), laws and regulations including amendments and includes and is limited to:
28
29
30
31
32
33

The needed antenna poles (MW and GSM) as specified (see Clause 9 Antenna poles)
A lightning protection and grounding system as specified (see Clause 10, 11 or 12 Lightning protection
and grounding system)
The needed cable support system as specified (see Clause 13 Cable support system)
Installation of a key deposit
Site specific documentation as specified (see Clause 8 Documentation)
After the site has been finished it has to be left in such a condition that all changes necessary for the
installation process are removed.

Options if necessary (included in the package):


- Installation of a ladder and a platform if necessary for the MW-antenna maintenance.
- A safety system for the personal climbing and working on the tower, according to safety regulations and
their amendments valid in the Czech Republic, if there is not already an existing one.
If there is no safety system installed, a Soell security system has to be installed.
If a Soell safety system will be installed the needed interchange and get off services has also to be
installed.
Excluded but not limited to:
The following services are not included in the workpackage price:
- A improvement, redevelopment, reinforcement, restoration etc. of the special structure (e.g. new
painting, foundation, ladder, platform), of the already existing grounding and lightning protection system
or other comparable repairs.
- Installation of a new lightning protection and grounding system etc. for the special structure.
- Protection of the site with a fence, including a door and a lock.
- A new structural analysis for the existing special structure
- All special or additional work due to the reason of the request by local authorities, environmental
department, army etc.
- Any other additional work which have to be done due to the reason of special conditions on site

N S KPK, Stefan Kutz


Version 3.0
30.10.97

Page 5 / 20

34Infrastructure for outdoor unit installation


The workpackage includes all work and material that is needed to prepare, construct, transport, erect and align the
infrastructure for an outdoor unit installation for the operation of a Mobile Network System to suit the necessities of
the GSM project for RadioMobil in the Czech Republic.
In more detail the work/installation to be carried out has to be according to the following specifications, the relevant
Czech Norms (CSN), laws and regulations including amendments and includes and is limited to:
35
36
37
38
39
40
41
42
43
44

The electrical installation as specified (see Clause 20 Electrical installation outdoor)


A metal frame for BTS outdoor unit as specified (see Clause 23 Metal frame for BTS outdoor unit)
A lightning protection and grounding system as specified (see Clause 12 Lightning protection and
grounding system)
The needed cable support system as specified (see Clause 13 Cable support system)
The AC Distributor as specified (see Clause 18 AC distributor)
Installation of a fire extinguisher support
An emergency escape plan and fire hose location plan has to be placed near the BTS outdoor-unit
The main power supply as specified (see Clause 14 Main power supply)
Site specific documentation as specified (see Clause 8 Documentation)
After the site has been finished it has to be left in such a condition that all changes necessary for the
installation process are removed.

Excluded but not limited to:


The following services are not included in the workpackage price:
- A fire extinguisher including the needed support (approved by the fire department for the next 12
month).
- All special or additional work due to the reason of the request by local authorities, environmental
department, army etc.
- All additional work which have to be done due to the reason of special conditions on site

N S KPK, Stefan Kutz


Version 3.0
30.10.97

Page 6 / 20

45In-house Equipment Room


The workpackage includes all work and material that is needed to prepare, construct, erect and align an in-house
equipment room for the operation of a Mobile Network System to suit the necessities of the GSM project for
RadioMobil in the Czech Republic.
In more detail the work/installation to be carried out has to be according to the following specifications, the relevant
Czech Norms (CSN), laws and regulations including amendments and includes and is limited to:
46
47
48

49
50
51
52
53
54
55
56
57
58
59
60

Preparation of the construction site.


Removal works
- Floor cleaning and preparation to lay a new anti static PVC floor cover
- All necessary removal works to gain free space up to 12m 2.
Cleaning, mason and armed concrete work
- Masonry up to 25m2 d = 24 cm, bricks or concrete prefabricates (delivery and installation), or a
partition wall made of drywall d=14.5 cm
- Ceiling of up to 12 m 2 of drywall or cement plaster, up to 46 m 2 of wall plaster
- Up to 12 m 2 of floor-space for
- cement coating
- preparation of floating base including insulation
- Preparation of equal and uniform floor level up to 12m 2.
- Preparation of all necessary wall break-throughs.
Up to 48 m 2 of wall and ceiling space, 2 coating painted with dispersion paint
Laying up to 12 m 2 of anti static PVC floor-cover.
A door as specified (see Clause 19 Door)
The electrical installation as specified (see Clause 21 Electrical installation indoor)
Reinforcement of ceilings and walls.
A cable support system as specified (see Clause 13 Cable support system)
A grounding system as specified (see Clause 11 Lightning protection and grounding system)
The AC Distributor as specified (see Clause 18 AC distributor)
Installation of a fire extinguisher and the needed support
An emergency escape plan and fire hose location plan has to be placed in the room
The main power supply as specified (see Clause 14 Main power supply)
Site specific documentation as specified (see Clause 8 Documentation)

Excluded but not limited to:


The following services are not included in the workpackage price:
- An alarm system
- A fire extinguisher including the needed support (approved by the fire department for the next
12 month)
- A compact cooling/ heating air conditioning unit, inside temperature range ensured under normal
climatic conditions: +15 to + 27
- All special or additional work due to the reason of the request by local authorities, environmental
department, army etc.
- Any other additional work which have to be done due to the reason of special conditions on site

N S KPK, Stefan Kutz


Version 3.0
30.10.97

Page 7 / 20

61Container
The workpackage includes all work and material that is needed to prepare, construct, manufacture/fabricate,
transport, erect and align a container for the operation of a Mobile Network System to suit the necessities of the GSM
project for RadioMobil in the Czech Republic.
In more detail the work/installation to be carried out has to be according to the following specifications, the relevant
Czech Norms (CSN), laws and regulations including amendments and includes and is limited to:
62

63
64
65
66
67
68
69
70
71

Description of container:
- Minimum inside dimensions - 2200 x 2700 x 2500 mm ( w x l x h )
- Minimal roof live load 150 kg/m 2
- Roof resistance against falling ice from the tower/mast, chimney, silo, water tower etc.
- A anti static PVC floor covering
- The interior walls has to be laminated plastic and/or 15 mm gypsum board painted with washable
paint
- The exterior walls has to be a puncture and water resistant material finished with weather and water
repealing finish
- The life expectancy has to be > 30 years
- The heat permeability coefficient has to be k < 0,5 WK/ m 2 but target k < 0,3 WK/ m 2
- The container must be weather and vandalism proof, anchored to the foundation if necessary
Door installation as specified (see Clause 19 Door)
Electrical installation as specified (see Clause 22 Electrical installation container)
A cable support system as specified (see Clause 13 Cable support system)
A reinforced concrete strip foundation placed under the long sides of the container or comparable.
A lightning protection and grounding system as specified (see Clause 10 Lightning protection and
grounding system)
The AC Distributor as specified (see Clause 18 AC distributor)
The main power supply as specified (see Clause 14 Main power supply)
Installation of a fire extinguisher and the needed support
Site specific documentation as specified (see Clause 8 Documentation)

Excluded but not limited to:


The following services are not included in the workpackage price:
- A compact cooling/ heating air conditioning unit, inside temperature range ensured under normal
climatic conditions: +15 to + 27
- An alarm system
- A fire extinguisher including the needed support (approved by the fire department for the next 12
month)
- An external power supply (diesel generator, solar panel).
- A galvanized metal grid with a grid size of 10/30 mm, at least 60 cm deep on pedestrals in front of the
door.
- All special or additional work due to the reason of the request by local authorities, environmental
department, army etc. like a wooden coverage, a double pitch, special painting etc.
- Any other additional work which have to be done due to the reason of special conditions on site

N S KPK, Stefan Kutz


Version 3.0
30.10.97

Page 8 / 20

72Documentation:
73
74

75
76
77

A complete documentation in 2 copies shall be provided on paper with the maximum format DIN A1 and
also where possible on electronic data media in a format, which the principal can read has to be handed
over according to the following time schedule.
The documentation shall contain all site specific information. All elements shall be shown in horizontal and
vertical projections and in the necessary number of sectional views. The dimension of the method of
construction (height, width, depth, weight) of all necessary facilities shall be specified. In case of
modifications the supplier shall update all drawings.
The dimensions (e.g. height, width, depth), weight, volume etc. has to be given in accordance to ISO
standard.
The documentation has to be written in English or in Czech.
The following documentation has to be handed over on RFA:
- structural analysis (Czech)
- application for hygiene permission (Czech)
- hygiene permission (Czech)
- application for fire protection permission (Czech)
- fire protection permission (Czech)
- application for building permission c/w contract documentation (Czech)
- building permission/announcement (Czech)
- electrical plan c/w wiring plan (English)
- plot plan 1:50 000 (Czech)
- access regulation (English)
- cable layout and cable tray information (English)
- Antenna placement plan (side and top view, antenna type, length of) (English)
- lightening system acceptance protocol c/w measurements (Czech)
- grounding system acceptance protocol c/w measurements (Czech)
- project documentation for realization (English)
- project description (Czech)
- emergency escape plan (Czech)
- fire extinguisher and fire hose location plan (Czech)
The following documentation has to be handed over latest 50 days after the GSM station has gone on air:
- hygienic measurement protocol (Czech)
- application for building acceptance (Czech)
- authorities building acceptance (Czech)

N S KPK, Stefan Kutz


Version 3.0
30.10.97

Page 9 / 20

78Antenna poles
79
80
81

82
83
84
85
86
87

88
89
90
91
92

93
94
95
96

MW antenna poles
The MW antenna poles have to be built in accordance to the MW description and line of site survey.
The following materials are permitted for the poles:
- hot galvanized steel pipe to provide corrosion resistance in a maritime climate and extremely
aggressive air and has to be free of damages (e.g. scratches, dents, rust).
- grid mast, corrosions protection as above
- centrifugally molded concrete
The whole metal work has to be hot galvanized to provide corrosion resistance in a maritime climate and
extremely aggressive air and has to be free of damages (e.g. scratches, dents, rust).
The surface of the metal parts shall not be rough.
The diameter of the MW antenna support (fixing point) has to be 108 mm for MW antennas with diameter
0,3 m, 0,6 m and 1,2 m.
Behind the MW antenna support there has to be a free space of > = 500 mm.
There has to be enough space on both side of the MW antenna to change the direction maximum 15
degree.
The static calculation for the MW antenna poles have to be done according to Czech law/regulations this
means 0,55 kN/m 2 wind load for sea levels < 700 m and 0,7 kN/m 2 wind load for sea levels > 700 m. The
maximum elongation of the MW antenna pole should not be more then 0,5 degree under the above
mentioned conditions. The MW antenna poles have to be designed for a wind velocity up to 200 km/h
The installation of the MW antenna poles have to be done on base of a proved structural analysis for the
pole and the load transfer to the building.
The joints has to be secured according to CSN-Norm and the statical planning. The used screws has to be
hot galvanized.
The structural analysis on base of the MW antennas mentioned in the MW description have to be done one
level higher (0.3 m = 0.6 m, 0.6 m = 1.2 m and 1.2 m = 1.2 m).
All mounting components are to be made of hot galvanized steel and of suitable strength and appropriate
dimension.
Safety installations (Soell security system) for the personal climbing and working on the MW antenna pole
has to be installed, according to the safety regulations and their amendments valid in the Czech Republic.
If a Soell safety system is installed the needed interchange and get off services has also to be installed. The
Soell security system has to be installed at free standing MW antenna poles with a height of more than 5 m
above floor level.
Foot steps (for poles with a height of less than 5 m above floor level) or a Soell ladder (for poles with a
height of more than 5 m above floor level) has to be installed until approximately 1,5 m below the fixing
point of the MW antenna.
A grip for the rope for antenna transport has to be arranged on top of the antenna pole with a minimum
diameter of 30 mm.
If it is possible to walk in front of the MW antenna, there has to be a minimum vertical safety distance above
the possible walking level of 2,5 m.
A connection point for the grounding of the MW antenna system has to be provided at the antenna pole.

N S KPK, Stefan Kutz


Version 3.0
30.10.97

Page 10 / 20

97
98
99

100
101
102
103
104

105
106
107
108

109
110
111

GSM antenna poles


The GSM antenna poles have to be built in accordance to the site cell description and the used antenna
type. The horizontal and vertical diversity distance, in accordance of the radiation diagram (the free angle)
and the needed free space of the used antenna type has to be followed (see Annex 1).
The following materials are permitted for the poles:
- hot galvanized steel pipe to provide corrosion resistance in a maritime climate and extremely
aggressive air and has to be free of damages (e.g. scratches, dents, rust).
- grid mast, corrosions protection as above
- centrifugally molded concrete
The whole metal work has to be hot galvanized to provide corrosion resistance in a maritime climate and
extremely aggressive air and has to be free of damages (e.g. scratches, dents, rust).
The surface of the metal parts shall not be rough.
The diameter of the GSM OMNI antenna supports (fixing point) have to be between 70 and 90 mm.
The diameter of the GSM sector antenna supports (fixing point) have to be between 70 and 115 mm.
The static calculation for the GSM antenna poles have to be done according to Czech law/regulations this
means 0,55 kN/m 2 wind load for sea levels < 700 m and 0,7 kN/m 2 wind load for sea levels > 700 m. The
maximum elongation of the GSM antenna poles should not be more then 3,0 degree under the above
mentioned conditions. The GSM antenna poles has to be designed for a wind velocity up to 200 km/h
The installation of the antenna poles have to be done on base of a proved structural analysis for the pole
and the load transfer to the building.
The joints have to be secured according to CSN-Norm and the statical planning. The used screws have to
be hot galvanized.
A grip for the rope which can be used for antenna transport or safety fixing point for personal working on the
antenna pole has to be arranged on top of the antenna pole with a minimum diameter of 30 mm.
Safety installations (Soell security system) for the personal climbing and working on the GSM antenna poles
has to be installed, according to the safety regulations and their amendments valid in the Czech Republic.
If a Soell safety system is installed the needed interchange and get off services has also to be installed. The
Soell security system has to be installed at free standing GSM antenna poles with a height of more than 5 m
above floor level.
All mounting components are to be made of hot galvanized steel and of suitable strength and appropriate
dimension.
If it is possible to walk in front of the GSM antenna, there has to be a minimum vertically safety distance
above the possible walking level of 2,5 m.
A connection point for the grounding of the GSM antenna system has to be provided at the antenna pole.

N S KPK, Stefan Kutz


Version 3.0
30.10.97

Page 11 / 20

112Lightning protection and grounding system


(Container)
113
114
115
116
117
118

119
120
121

For protection against lightning damages, all metallic parts have to be connected to the lightning protection
system as specified (see Annex 2).
A main ground with maximum 5 Ohm has to be provided.
A isolated copper ground bar with minimum 10 connection points (see F Annex 2) has to be installed inside
of the container.
A isolated hot galvanized steel ground bar with minimum 10 connection points (see G Annex 2) has to be
installed outside of the container.
The two ground bars (see G and F Annex 2) and all other grounding points have to be labeled.
The ground bar inside of container (see F Annex 2) has to be connected directly by a separate copper-cable
with a minimum cross section of 50 mm 2 (see H Annex 2) to the buried external ring bus. The second
ground bar outside of the container (see G Annex 2) below the cable entry point to the container has to be
connected directly by a separate FeZn-conductor with a minimum cross section of 16 mm 2 (see E Annex 2)
to the buried external ring bus
All metall parts (mast, poles, cable trays etc.) outside of the container has to be connected directly by a
FeZn-conductor with a minimum cross section of 16 mm 2 (see Annex 2) to the buried external ring bus.
Connection point for lightning protection has to be placed on the bottom of the mast/poles.
Delivery and erection of all necessary materials such as conductors, ground bars, cross connectors, cable
ducts etc. for complete lightning protection and complete grounding of all elements.

N S KPK, Stefan Kutz


Version 3.0
30.10.97

Page 12 / 20

122Lightning protection and grounding system


(In-house equipment room)
123
124
125
126
127
128

129
130
131
132

For protection against lightning damages, all metallic parts have to be connected to the lightning protection
system as specified (see Annex 3 and 4).
A main ground with maximum 5 Ohm has to be provided.
A isolated copper ground bar with minimum 10 connection points (see F Annex 3) has to be installed inside
of the building.
A isolated hot galvanized steel ground bar with minimum 10 connection points (see G Annex 3 and 4) has
to be installed outside of the building.
The two ground bars (see G and F Annex 3 and 4) and all other grounding points have to be labeled.
The ground bar inside of the building (see F Annex 3) has to be connected by a separate copper-cable with
a minimum cross section of 50 mm 2 to the main ground of the building. The second ground bar outside of
the building (see G Annex 3 and 4) should be installed at the cable entry point to the building. This ground
bar should be connected directly by a separate FeZn-conductor with a minimum cross section of 16 mm 2 to
the existing lightning protection system of the building.
All metall parts (poles, cable trays etc.) outside of the building has to be connected directly by a FeZnconductor with a minimum cross section of 16 mm 2 (see Annex 3 and 4) to the existing lightning protection
system of the building.
Connection point for lightning protection has to be placed on the bottom of the mast/poles.
Delivery and erection of all necessary materials such as conductors, ground bars, cross connectors, cable
ducts etc. for complete lightning protection and complete grounding of all elements.
The lightning protection must not be connected to the building ground.

N S KPK, Stefan Kutz


Version 3.0
30.10.97

Page 13 / 20

133Lightning protection and grounding system


(Outdoor unit)
134
135
136
137
138

139
140
141
142

For protection against lightning damages, all metallic parts has to be connected to the lightning protection
system as specified (see Annex 5 and 6).
A main ground with maximum 5 Ohm has to be provided.
A isolated hot galvanized steel ground bar with minimum 10 connection points (see Annex 5 and 6) has to
be installed outside of the building.
This ground bar (see G Annex 5 and 6) and all other grounding points have to be labeled.
The ground bar outside of the building (see G Annex 5 and 6) has to be connected directly by a separate
FeZn-conductor with a minimum cross section of 16 mm 2 (see Annex 5 and 6) to the existing lightning
protection system of the building. This ground bar should be placed below the cable tray and the metal
frame of the outdoor unit (see G Annex 5 and 6).
All metall parts (poles, cable trays etc.) outside of the building has to be connected directly by a FeZnconductor with a minimum cross section of 16 mm 2 (see Annex 5 and 6) to the existing lightning protection
system of the building.
Connection point for lightning protection has to be placed on the bottom of the mast/poles.
Delivery and erection of all necessary materials such as conductors, ground bars, cross connectors, cable
ducts etc. for complete lightning protection and complete grounding of all elements.
The lightning protection must not be connected to the building ground.

N S KPK, Stefan Kutz


Version 3.0
30.10.97

Page 14 / 20

143Cable support system


144Indoor Installation
145
146
147
148
149

Inside of the BTS equipment room the PUK wire-mesh cable tray G 50 40 S or comparable has to be used
for horizontal cable installation.
Inside of the container a wire-mesh cable tray or comparable has to be used for horizontal cable installation
(300 mm inside width).
Cable trays interior have to be provided according to the floor plan (if possible two long trays along long
walls and one cross tray at the center of the equipment room or the container)
The minimum heights of the cable support system above floor level has to be 2,25 m inside of the
equipment room or container.
All metal parts have to be joined and connected to grounding system.

150Outdoor Installation
151
152
153
154
155
156

157
158

159
160

Outside of the BTS equipment room but inside of the building (indoor) the PUK RGS 60 20 - S or
comparable (until 3 cables) and the RGS 60 40 S or comparable (more than 3 cables) has to be used for
horizontal cable installation
Outside of the building the PUK RGS 60 20 - F or comparable (until 3 cables) and the RGS 60 40 F or
comparable (more than 3 cables) has to be used for horizontal cable installation
If there is a risk, that someone could step on the cables or could damage it, the cable tray has to be covered
with the cover RDR-20 S or RDR-40 S or comparable outside of the BTS equipment room, but inside of the
building.
Outside of the building the cable tray has to be covered with the cover RDR-20 F or RDR-40 F or
comparable to protect the cables against e.g. falling ice, unauthorized touch.
For horizontal cable installation outside of the building the cable tray has to be fixed on concrete stones of
instructed dimensions. The cable tray will be screwed to the stones, the distance between the stones is max.
2 m. The stones have to stand on a fixed ground (e.g. not on gravel)
In inaccessible places outside of the building the cables could be fixed only on stones with C-bars (e.g.
INOX) and clamps and in the case of vertical cable installation inside and outside of the building the cables
will be fixed only with C-bars and clamps. The minimum wide of the C-bars and clamps should be 40 cm.
The distance between the C-bars have to be not more than 60 cm.
If it is inevitable to project the cables against unauthorized touch the PUK cable tray RG 110-20 F (until 3
cables) or RG 110-40 F (more than 3 cables) together with the cover RDR-20 F or RDR-40 F have to be
used for vertical cable installation outside and inside of the building.
If antenna cables are to be fed in underground, suitable empty pipes shall be bedded into sand. The
minimum bending radius (for repeated bending) of the supplier of the antenna cables (1/2 ins until 1 5/8 ins
cables) has to be followed. The used pipe has to protect the installed antenna cable against all possible
damages (e.g. it has to be resistance against pressure, UV-resistant, resistance against decay). The
minimum deep under ground has to be 80 cm.
The cable tray shall be connected to the lightning protection system.
If the galvanization of the cable tray or the cable tray coverage will be damaged by cutting it has to be
deburred and covered by zink-painting.

161General for in- and outdoor Installation


162
163
164
165
166
167
168
169

The minimum bend radius (for repeated bending) of the supplier of the antenna cables (1/2 ins until 1 5/8
ins cables) has to be followed.
The cable support system (cable tray, C-bars) has to be built according to the specification of the needed
grounding of the antenna cables.
If a power cable for 220 V will be installed in the cable support system (cable tray, C-bars), the distance to
the antenna cables has to be more than 10 cm.
The installed coverage-edges has to be covered
The cable support system (cable tray, C-bars) has to allow fixing of GSM/MW antenna cables with the help
of RSB, FIMO or PUK clips (1/2 ins until 1 5/8 ins cables).
Cable trays/ducts up to 40 m per antenna sector for leading MW + GSM cables from the antennas into
equipment room/outdoor unit/container.
The cable tray has to be well fixed with the appropriate PUK support element or comparable
A suitable installation frame for the introduction of the GSM and MW antenna cables (Brattberg, Roxtec
frame or comparable) shall be provided.

N S KPK, Stefan Kutz


Version 3.0
30.10.97

Page 15 / 20

170 Main power supply for BTS


171
172
173
174
175
176
177
178

The main fuse has to be 25 A per phase (3 x 25 A or if not possible 3 x 16 A)


Installation/Building of a electrical power meter housing incl. arrangement for electrical power meter
according to the instructions of EVU
The cable (CYKY) from the energy provider to the electrical power meter (but only up to 5 m are included in
the workpackage) according to Czech law
The cable (CYKY) from the electrical power meter to the AC Distribution box (but only up to 10 m are
included in the workpackage) according to Czech law
The electrical power meter and the power cable has to be labeled with RadioMobil
The installation of the cables has to be according to Czech law
The introduction of the electrical cables should be water proof.
All outdoor cable channels has to be weather proof.

179 Main power supply for BSC


Has to be defined later (not requested by RadioMobil until now)

180 Main power supply for BSC plus BTS


Has to be defined later (not requested by RadioMobil until now)

181 Main power supply for MW repeater


Has to be defined later (not requested by RadioMobil until now)

N S KPK, Stefan Kutz


Version 3.0
30.10.97

Page 16 / 20

182 AC Distributor
183
184
185
186

Specification for the AC Distributor for indoor, container (Annex 7 and 8) and outdoor unit (Annex 9 and
10) has to be followed.
All fuses are to be labeled
The wiring plan of the AC distributor shall be placed inside of the distributor box
The outdoor AC distributor box which should be appropriate for outdoor usage (e.g. water resistant,
lockable, weather proof)

N S KPK, Stefan Kutz


Version 3.0
30.10.97

Page 17 / 20

187 Door
188
189
190
191
192
193

A swinging door opening outwards should be installed


The minimum door opening aperture has to be approximately 0.80 m x 1.97 m
Penetration of hard rain, splash water and surface water is to be prevented
The door, door filling, frame fittings and related components shall be burglar resistant and fire-proof in
accordance with Class ET 1
A cylindrical security lock shall be used to lock the door.
The door has to be painted with exterior paint

N S KPK, Stefan Kutz


Version 3.0
30.10.97

Page 18 / 20

194 Electrical installation outdoor


195
196
197
198
199

Installation and delivery of 1 pcs of a 220 V socket including the necessary wiring
Installation and delivery of 1 pcs of a 3 phase 380V, 3-phase AC distribution board, 3-phase circuit-breakers,
over-voltage arresters, copper grounding bar (with minimum 10 connection points). A water proof installation
in case of outdoor mounting.
All electrical installation has to be placed maximum 5 m from expected place of BTS outdoor unit.
A CYKY cable (5 wire cable 3 x L, N, PE) has to be used and should be installed in a cable channel between
the AC-Distributor box and the BTS outdoor unit.
All outdoor cable channels has to be weather proof.

200 Electrical installation indoor


201
202
203
204

Installation and delivery of 4 pcs of fluorescent tubes (up to 40 W) or equal including the necessary wiring
and a switch.
Installation and delivery of 4 pcs of a 220 V socket including the necessary wiring
Installation and delivery of 1 pcs of a 3 phase 380V, 3-phase AC distribution board, 3-phase circuit-breakers,
over-voltage arresters, copper grounding bar (with minimum 10 connection points).
A CYKY cable (5 wire cable 3 x L, N, PE) has to be used and should be installed in a cable channel between
the AC-Distributor box and the BTS indoor unit.

Excluded but not limited to:


Installation and delivery of 1 pcs of an emergency light with a manual switch incl. battery backup for at least
one hour 220V / ~ 12 W

205 Electrical installation container


206
207
208
209
210

Installation and delivery of 4 pcs of fluorescent tubes (up to 40 W) or equal including the necessary wiring
and a switch.
Installation and delivery of 4 pcs of a 220 V socket including the necessary wiring
Installation and delivery of 1 pcs of a 3 phase 380V, 3-phase AC distribution board, 3-phase circuit-breakers,
over-voltage arresters, copper grounding bar (with minimum 10 connection points).
Installation and delivery of 1 pcs power inlet exterior 3 phase 380 V / 50 Hz / 32 A for a diesel generator
A CYKY cable (5 wire cable 3 x L, N, PE) has to be used and should be installed in a cable channel between
the AC-Distributor box and the BTS indoor unit.

Excluded but not limited to:


Installation and delivery of 1 pcs of an emergency light with a manual switch incl. battery backup for at least
one hour 220V / ~ 12 W

N S KPK, Stefan Kutz


Version 3.0
30.10.97

Page 19 / 20

211 Metal frame for BTS outdoor unit


212
213
214
215
216
217
218
219
220
221

Distance between the wall and the approx. BTS = 100 mm.
Distance between the ground and the approx. BTS = 500 mm.
Free space above the BTS.
The metal frame has to be built like specified (Annex 11 and 12).
Fixing points for the BTS like specified (Annex 11 and 12)
The whole metal work has to be hot galvanized to provide corrosion resistance in a maritime climate and
extremely aggressive air and has to be free of damages (e.g. scratches, dents, rust).
The installation of the metal frame has to be done on bases of a proved structural analysis for the frame and
the load transfer to the building.
The joints has to be secured according to CSN-Norm and the statical planning.
If possible the frame has to be installed on the north side of the building
Two different connection points (left and right) for lightning protection have to be provided.

N S KPK, Stefan Kutz


Version 3.0
30.10.97

Page 20 / 20