You are on page 1of 8

BOW TIE ANALYSIS

Pit Wall Collapse

Abstract
Bow tie diagrams have become popular
methods in risk analysis and safety
management.
This
tool
describes
graphically, in the same scheme, the whole
scenario of an identified risk and its
respective preventive and protective
barriers.

Jessica Morgana Ribeiro Santana


Mining Engineering

Introduction
Walls on a mine are a very sensitive case. It should be taken seriously and risk
assessment to it is indispensable considering the fact that without stable walls a mine
cannot work properly and a wall collapse it a very serious accident that should be
avoided at all costs.
A wall collapse on a mine can have many ramifications including:
1. Loss of life or injury to persons working or visiting the mine (Safety factors);
2. Loss of worker income, loss of worker confidence, loss of corporate credibility,
increased legal liability (Social factors);
3. Disruption of operations, loss of ore, loss of equipment, increased stripping,
cost of clean-up, loss of markets (Economic factors), and
4. Collapse of nearby infrastructure/facilities into the open pit, for example, mine
waste dumps, tailings storage facilities etc, and interference with natural
drainage (Environmental factors).
It is recognised that mining experience and professional judgement are important
aspects of risk assessment that are not easily quantified, but can contribute
significantly to the formulation of various acceptable and equally viable solutions to a
particular mining problem. Management at each mining operation should recognise,
identify and address the issues that are unique to each particular mine, using current
geotechnical knowledge, methodology, software and hardware appropriate to the
situation.
Using the bowtie to analyse the hazards regarding the dependence of a stable walls
system allows the visualization of the relationship between undesirable event, its
causes, accidental scenarios, the preventive and mitigation measures to limit their
consequences, demonstrates the effectiveness of existing controls and it is affective on
structured risk analysis where quantification is not possible or desired.

Threats & Preventions


It is obvious that the level of exposure of the workforce to potentially hazardous
conditions will govern the occurrence of injuries and fatalities at a mine site. It is also
obvious that in order to reduce the level of exposure to hazards, a system must exist
whereby hazards can be systematically recognised/identified and managed. This
system of hazard recognition and management (in this case wall control hazards)
should be incorporated within the overall mine plan. The implementation of an allencompassing mine plan presents a major challenge for mine management. A sound
understanding of the mining site conditions is vital for the selection of the most
appropriate mine design, mining method(s) and risk management for a new or existing
mining operation. The level of risk, both in human and economic terms, will be
substantially increased if the conditions of the mining site are not sufficiently well
understood.

The top event in this assessment in the collapse of the wall in mining, which can be
trigged by many causes, some of them are listed below:
1. Rock fall of accumulated weathered rocks: can be prevented by removing all
the unstable rocks that can cause a toppling.
2. Water flows: monitoring the weather forecasts, analysing the subterranean
waterflows to avoid any surprises and install drainage bores at some strategic
places should avoid that.
3. Blasting: in order to avoid accidents due to the blast activities, reinforce the
walls in order to be more resistant to the seismicity that the blasting causes,
calculating properly the blasting to avoid mistakes are storing the explosives in
a blastproof area should be enough
4. Defective construction of walls: A inspection should be done do make sure that
proper materials are be used to construct the walls taking into account the
strength of materials and also a preventive slope flattening.
5. Seismic events: Monitoring the seismic events in the area of the mine to know
what to expect and having a good plan to take action when a seismic event
occurs are good preventive measures.
6. Improperly used or malfunctioning mining equipment: having trained people
to work with the equipment and having at least monthly inspections on all the
equipment should be enough to avoid the consequences.

Recovery Measures & Consequences


If the controlling measures were not enough to avoid the top event (collapse of the
walls), then recovery measures should be done. And it is important to have them
planned before it happens, that is the importance of a risk assessment, knowing what
can happen and using the bow tie it is even more important because it makes clear
what should be done after the accident happened. A few of them are listed below:
1. Use of rock mesh and catchment fence: because of injuries to the
stakeholders;
2. Ditching/benching: because it is necessary to remove fallen debris;
3. Sotckpilling, an emergency clean-up plan and backup equipment: in order to
avoid loss of production;
4. Construct rock fall barriers and having a protocol for equipment storage:
because debris can crush the equipment;
5. Having a fast emergency team response and personal protective equipment: in
case of debris crushing workers.
In order to detect instability at an early stage, a sufficient monitoring system should be
created to allow the formulation of safety measures. Monitoring after the accident
happens it is not very effective since it does not undo the damage cause by an

unexpected failures. The purpose of a monitoring plan (adapted from Call & Savely,
1990) is to:
1. Maintain safe operational practices for the protection of personnel, equipment,
and facilities;
2. Provide warning of instability so action can be taken to minimize the impact;
3. Provide crucial geotechnical information to analyse the walls collapse
mechanism and design the appropriate corrective measures.
The following steps should be taken when planning the instrumentation portion of the
monitoring program:
1. Understand the mechanisms that cause instability;
2. Define and prioritize the geotechnical information required;
3. Establish monitoring locations;
4. Predict the magnitudes of movement and other parameters at these locations.

Holes in the Swiss cheese


Doing a risk management is doing a systematic use of available information to
determine how often adverse events may occur, the magnitude of their consequences
and how acceptable the resulting harm may be.
But still, sometimes there are some unexpected outcomes and the consequence of
that is likely to be serious, such as death or serious injuries. That is what the James
Reasons Swiss Cheese model is about, it is not accepting the risks. If the holes in the
cheese line up, the accident definitely is going to happen.

Figure 1: James Reasons Swiss cheese model. Redrawn from James Reasons 1991 revised for the 2006
MineSafe Magazine

A lot of shortcoming (holes in the Swiss cheese) can happen when it comes to pit wall
stability, for instance:
1. Incompetent personnel at an early stage of the mine design, it needs to be
made sure that the right professional with competence to do the mine design.
2. Incompetent personnel at monitoring and maintenance, making sure the a
competent staff is used on the mine is indispensable;
3. Also the use of proper material on the supports, if the wrong material with a
flaw strength is used, the accident is bound to happen. So it should not be
used poor material in order to save money, the safety needs to be put in first;
4. Failure of machinery can be crucial, so the equipment should be monitored
often and also maintenance should be taken place on at least monthly basis;
5. Poor study of natural conditions, such as seismicity and ground conditions.
Knowing the ground and site where the mine is constructed is crucial;
6. Not having a response team available when the accidents happens. A response
team with a proper number of member and trained in emergency first aid and
a rescue team should be available at all times;
7. Emergency procedure not being followed. The procedures in case of
emergency should be clear and known by all member of the mine staff and
followed completely.

Conclusion
It is recommended that a sensitivity assessment be carried out to determine the effect
of critical geotechnical parameters involved with wall stability. This will assist with
assessment of the quality of geotechnical data obtained and required and the
appropriate mine design options. Common methods used to increase the effective
stability of walls include reducing slope angles, controlled blasting practices, installing
reinforcement, and depressurisation of groundwater. Any deficiencies that are
highlighted in the analytical methods should encourage further work to remedy these
matters, extend the use of the method or develop a new method.
It is really import to have a good monitoring system to always know what it happening
within the mine. An important aspect of any monitoring program is the development
of a monitoring strategy, which is implemented rigorously within the mine's ground
control management plan. The strategy should define the monitoring schedule, the
time allowed and methods used for data recording, interpretation, and reporting, and
provide basic courses of action to be taken in the advent of signs of impending pit wall
failure. It is essential that the monitoring data collected is correctly assessed and the
results and recommendations passed on to the relevant operations personnel at
regular intervals for assessment of the performance of pit wall.
To be able to control the stability and to have the possibility of taking the necessary
stabilizing measures in time, continuous geological mapping, particularly of distinct
joints, is crucial. Even when this is done, it is often difficult to get safe access into the
areas that require support due to the high and steep walls. Thus, it is very important to
4

use skilled and experienced people for carrying out this type of work. In any case, good
quality perimeter blasting is important for the stability, and also for ensuring safer
working conditions at lower levels of the mine.

Bow Tie for Pit Wall Collapse


A Bow Tie Analysis (Annex 1) with the threats, controls, mitigation measures (and it
threats) and consequences was made using the BowTie Pro, a software which
graphically assists companies complete their risk assessments using the bow tie
methodology. A free trial was given, what allowed the creation of the BTA.

References
BowTiePro.com
Welcome.
Accessed
December
14,
2013.
http://www.bowtiepro.com/.
Microsoft Word - CapeTown_Titania06.doc - CapeTown_Titania06.pdf. Accessed
December 14, 2013. http://folk.ntnu.no/bnilsen/CapeTown_Titania06.pdf.
Mining.
Accessed
December
14,
2013.
http://www.cgerisk.com/customers/industries/mining.
Underground Mining Methods and Equipment - e6-37-06-02.pdf. Accessed
December 14, 2013. http://www.eolss.net/sample-chapters/c05/e6-37-06-02.pdf.
ZME048BF.PDF
MSH_G_GeotechnicalConsiderationsOpenPitMinespdf.pdf.
Accessed
December
14,
2013.
http://www.dmp.wa.gov.au/documents/Guidelines/MSH_G_GeotechnicalConsiderati
onsOpenPitMinespdf.pdf.
06488_NL_MineSafe0506.indd - 024_MineSafe.pdf. Accessed December 16, 2013.
http://www.dmp.wa.gov.au/documents/Magazine/024_MineSafe.pdf.
ASSESSING AND MONITORING OPEN PIT MINE HIGHWALLS - Aamop.pdf. Accessed
December
16,
2013.
http://www.cdc.gov/niosh/mining/UserFiles/works/pdfs/aamop.pdf.

Annex 1: BTA for pit wall collapse

You might also like