You are on page 1of 166

Facilities Project Managers

Guide
May 2008

TA B L E O F C O N T E N T S
Introduction to the Facilities Project Managers Guide ........................................................ 8
Part I: Stakeholders and Roles ............................................................................................ 11
Part II: Project Requests and Approval Process ................................................................. 27
Part III: Project Controls ........................................................................................................ 34
Part IV: Project Process Phases ........................................................................................... 56
Part V: Appendix ................................................................................................................... 75

FOR ASSISTANCE IN USING THIS GUIDE OR TO PROVIDE COMMENTS AND EDITS,


PLEASE CONTACT DONNA GOSS

Facilites Project Managers Guide

Page 1

D E TA I L E D T A B L E O F C O N T E N T S
Introduction to the Facilities Project Managers Guide ........................................................ 8
Executive Summary ............................................................................................................................................... 8
How to Locate the Guide ....................................................................................................................................... 8
Summary Overview of this Guide .......................................................................................................................... 9
This Guide and Other Documents ......................................................................................................................... 9
The Cornell Project Management Methodology (CPMM) Guide ....................................................................... 9
The Project Managers Toolbox......................................................................................................................... 9
Facilities Services Website and Other Websites ............................................................................................. 10

Part I: Stakeholders and Roles ............................................................................................ 11


Facilities Services: Key Departments ................................................................................................................. 13
Project Team ....................................................................................................................................................... 15
Core Team ....................................................................................................................................................... 15
Executive Group .............................................................................................................................................. 15
Primary Customer ............................................................................................................................................ 15
Project Executive / Director ............................................................................................................................. 16
Project Manager .............................................................................................................................................. 16
Construction Manager ..................................................................................................................................... 16
Project Coordinator .......................................................................................................................................... 16
Project Coordinator Responsibilities ........................................................................................................... 16
Role Agreement .......................................................................................................................................... 17
Cornell Approval Groups ..................................................................................................................................... 18
Consultants and Contractors ............................................................................................................................... 19
Cornell Stakeholders ........................................................................................................................................... 20
Alumni Affairs and Development ..................................................................................................................... 20
Construction Management Office .................................................................................................................... 20
Contracts & Capital Projects Office ................................................................................................................. 21
Cornell Information Technologies .................................................................................................................... 21
Cornell Police................................................................................................................................................... 21
Alumni Affairs and Development ..................................................................................................................... 21
Environmental Compliance and Sustainability Office ...................................................................................... 21
ECOS Checklist .......................................................................................................................................... 22
Environmental Health and Safety .................................................................................................................... 22
Facilities Management ..................................................................................................................................... 22
Maintenance Management .............................................................................................................................. 22
Office of Government and Community Relations Office.................................................................................. 22
Office of the University Counsel ...................................................................................................................... 23
Project Planning and Estimating ..................................................................................................................... 23
Risk Management and Insurance .................................................................................................................... 23
Transportation and Mail Services .................................................................................................................... 23
Treasurers Office ............................................................................................................................................ 23
Facilities Project Managers Guide

Page 2

University Architect .......................................................................................................................................... 23


University Budget Office .................................................................................................................................. 23
University Engineer ......................................................................................................................................... 24
University Planner ........................................................................................................................................... 24
The Roles of the University Planner and University Architect .................................................................... 24
Utilities and Energy Management ................................................................................................................... 24
External Stakeholder Groups............................................................................................................................... 25
Building Inspector and Fire Marshall ............................................................................................................... 25
Community/Neighborhood Associations ......................................................................................................... 25
Planning and Development Boards ................................................................................................................. 25
Other Boards ................................................................................................................................................... 26

Part II: Project Requests and Approval Process ................................................................. 27


Cornell University Approval Process ................................................................................................................... 27
Transaction Authority Policy ................................................................................................................................ 28
The Project Approval Request (PAR) .................................................................................................................. 29
Project Plans.................................................................................................................................................... 29
How to Write a PAR ............................................................................................................................................. 30
Types of PARS ................................................................................................................................................ 30
Concept PAR .............................................................................................................................................. 30
Design PAR ................................................................................................................................................. 30
Construction PAR ........................................................................................................................................ 31
Revised PARS ............................................................................................................................................ 31
Municipal Approval Process ................................................................................................................................ 31
Project Authorization Letter ................................................................................................................................. 33
Letter of Authorization ..................................................................................................................................... 33

Part III: Project Controls ........................................................................................................ 34


Introduction .......................................................................................................................................................... 34
Budget Development ........................................................................................................................................... 34
Budget Planning Phases: Overview ................................................................................................................ 34
Planning Phase ........................................................................................................................................... 34
Design Phase .............................................................................................................................................. 34
Bid Phase .................................................................................................................................................... 34
Construction Phase Cost Tracking ............................................................................................................. 34
Budget Template ............................................................................................................................................. 35
Planning Phase Budget Development ............................................................................................................. 35
Design Phase Budget Development ............................................................................................................... 37
Feasibility Study Phase Budget Development ............................................................................................ 37
Schematic Design (SD) Phase Budget Development ................................................................................. 37
Step 1: Parallel estimate ......................................................................................................................... 37
Step 2: Reconciliation of estimates ........................................................................................................ 37
Facilities Project Managers Guide

Page 3

Step 3: Allowance Items ......................................................................................................................... 37


Step 4: Value Analysis /Value Engineering (VA/VE) .............................................................................. 37
Design Development (DD) Phase Budget Development ............................................................................ 39
Step 1: Perform a cost/value analysis .................................................................................................... 39
Step 2: VA/VE Items ............................................................................................................................... 39
Step 3: Life Cycle Costs ......................................................................................................................... 39
Step 4: DD Estimate ............................................................................................................................... 39
Step 5: Project Budget Validation ........................................................................................................... 39
Construction Documents Phase Budget Development ............................................................................... 39
Bid Project Phase Budget Development ......................................................................................................... 40
Lump Sum Projects ..................................................................................................................................... 40
Public or Private Bid Openings ................................................................................................................... 40
GMC Projects Negotiations ......................................................................................................................... 40
Bids Exceed Construction Budget .............................................................................................................. 41
Awarding the Project to a Bidder ................................................................................................................ 41
Construction Phase PAR ............................................................................................................................ 41
Construction Phase Cost Tracking .................................................................................................................. 42
Pre-construction .......................................................................................................................................... 42
Construction ................................................................................................................................................ 43
Keep Schedule ....................................................................................................................................... 43
Validate, Track and Monitor Change Orders .......................................................................................... 43
Review for ADA Access Compliance ...................................................................................................... 43
Timely Responses to Contractor ............................................................................................................ 43
Timely Payments .................................................................................................................................... 43
Quality Assurance/Quality Control .......................................................................................................... 43
Monitor Contractors Compliance ........................................................................................................... 43
Close-out/Move-in ....................................................................................................................................... 44
Resolve any claims ..................................................................................................................................... 44
Project Contingencies ...................................................................................................................................... 44
Escalation Contingency............................................................................................................................... 44
Projects with fixed, non-escalating budgets ........................................................................................... 45
Projects with budgets that are allowed to increase with escalation ....................................................... 45
Design Contingency .................................................................................................................................... 46
Design Contingency for Design Phase of Budget .................................................................................. 46
Construction Contingency ........................................................................................................................... 46
Errors and Omissions ............................................................................................................................. 47
Unforeseen Conditions ........................................................................................................................... 47
Scope/Program Change ......................................................................................................................... 47
Capital Project Funding Plan ............................................................................................................................... 50
Schedule Development ........................................................................................................................................ 50
Contractual Agreements ...................................................................................................................................... 50

Facilities Project Managers Guide

Page 4

Design Agreements ......................................................................................................................................... 51


Project Manager Issues Request for Proposal (RFP) ................................................................................. 51
Project Manager Presents Proposals to C&CP .......................................................................................... 51
C&CP Reviews Proposal ............................................................................................................................ 51
Types of Design Agreements ...................................................................................................................... 52
Construction Agreements ................................................................................................................................ 53
Types of Construction Contracts ............................................................................................................ 53
Invoices and Payment Applications ..................................................................................................................... 54
Setting up an Account ..................................................................................................................................... 54
Receipt of Invoice in C&CP ............................................................................................................................. 54
C&CP Review of Invoice ................................................................................................................................. 54
Construction Manager Reviews....................................................................................................................... 54
Project Coordinator Review ............................................................................................................................. 54
Approval by PM and Return to C&CP ............................................................................................................. 54
CC&P Requests Payment by DFA .................................................................................................................. 55
Project Over Budget ........................................................................................................................................ 55
Project Managers Report ................................................................................................................................ 55
Financial Reviews and Reporting ........................................................................................................................ 55
Projects over $5 Million ................................................................................................................................... 55
Projects under $5 Million ................................................................................................................................. 55

Part IV: Project Process Phases ........................................................................................... 56


Project Delivery Flow Chart ................................................................................................................................. 56
Planning Phase .................................................................................................................................................... 57
Goal ................................................................................................................................................................. 57
Deliverables ..................................................................................................................................................... 57
Client Responsibilities ..................................................................................................................................... 57
PM Responsibilities ......................................................................................................................................... 57
Steps ................................................................................................................................................................ 58
Initiate Project ............................................................................................................................................. 58
Review Project Plan .................................................................................................................................... 58
Create Project Team ................................................................................................................................... 58
Create Project Space Program ................................................................................................................... 58
Site Selection (new construction only) ........................................................................................................ 59
Consultant Selection ................................................................................................................................... 59
Decide need for either Concept Study and/or Feasibility Study ................................................................. 59
Project Formulation ..................................................................................................................................... 60
Primary Customer Approval ........................................................................................................................ 60
Planning Phase Approval ................................................................................................................................ 61

Facilities Project Managers Guide

Page 5

Design Phases ..................................................................................................................................................... 62


Schematic Design (SD) ................................................................................................................................... 62
Deliverables ................................................................................................................................................ 62
Process ....................................................................................................................................................... 63
Schematic Design Approvals ...................................................................................................................... 64
Design Development (DD) ............................................................................................................................... 64
Deliverables ................................................................................................................................................ 64
Process ....................................................................................................................................................... 64
Design Development Approvals .................................................................................................................. 65
Construction Contract Documents (CD) .......................................................................................................... 65
Deliverables: ............................................................................................................................................... 65
Process ....................................................................................................................................................... 65
Construction Documents Approvals ............................................................................................................ 66
Bid Phase............................................................................................................................................................. 66
Deliverables ..................................................................................................................................................... 66
Process ............................................................................................................................................................ 66
Bid Phase Approvals ....................................................................................................................................... 67
Construction Phase ............................................................................................................................................. 67
Site Preparation / Mobilization ......................................................................................................................... 67
Construction..................................................................................................................................................... 67
Deliverables ................................................................................................................................................ 67
Close-out/Move-in ........................................................................................................................................... 68
Deliverables ................................................................................................................................................ 68
Process ....................................................................................................................................................... 68
Obstacles to Closing a Project Account .......................................................................................................... 69
Resources........................................................................................................................................................ 69
Risk Management in Project Management .......................................................................................................... 71
Assess Financial Risk ...................................................................................................................................... 71
Outline Legal Relationships: Design Phase/Have Clear Contracts ............................................................... 71
Oversee Aspects of the Claims Process ......................................................................................................... 72
Three Types of Claims ................................................................................................................................ 73
Workers Compensation .......................................................................................................................... 73
Liability .................................................................................................................................................... 73
Property Damage Liability Claims .......................................................................................................... 74
Property .................................................................................................................................................. 74

Facilities Project Managers Guide

Page 6

Part V: Appendix ................................................................................................................... 75


Sample Matrix for Project Coordinator (PC) Responsibilities .............................................................................. 76
Sample Project Manager and Construction Manager and Project Coordinator Duties and Responsibilities ..... 79
Sample Role Agreement...................................................................................................................................... 82
Sample Revised Par ............................................................................................................................................ 84
Construction Contingencies Exposures ............................................................................................................... 89
GMC Systems ...................................................................................................................................................... 90
GMC Cost of Work (Current Bidding Climate) ..................................................................................................... 91
GMC GCs............................................................................................................................................................ 93
Sample Budget Sheet .......................................................................................................................................... 96
Sample Budget: Building Cost ............................................................................................................................. 98
Sample Budget : $110 Million .............................................................................................................................. 99
Sample Budget: $154 vs. $140 Million .............................................................................................................. 104
Sample Project Plan .......................................................................................................................................... 109
Sample Feasibility Study ................................................................................................................................... 114
Sample SD VE ................................................................................................................................................... 127
Sample SD Cost Strategy .................................................................................................................................. 133
Sample Design Development Value Engineering ............................................................................................ 135
Sample Construction Development 50 Value Engineering ............................................................................... 150
Sample Change Order Letter............................................................................................................................. 162

Facilities Project Managers Guide

Page 7

Introduction to the Facilities Project Managers Guide


Executive Summary
The Facilities Project Managers Guide is designed to support the Capital Project Delivery Process
Guide by providing the how to of Project Management for capital projects at Cornell
University. It is written for Project Managers.
The Capital Project Delivery Process Guide describes the what of Project Management, and was
written to provide better clarity of the process for project development for clients and users
outside Facilities Services.
The Facilities Project Managers Guide describes the process for managing large capital
projects overseen by Facilities Services; it also provides guidelines common to all capital
projects. Small projects may have a very different structure than large projects. Project size and
difficulty depend on the desired program, scope of work, and the complexity of the space in
which it is to be constructed. Renovation projects are also addressed, to some degree, in this
guide.

How to Locate the Guide


Go to www.fs.cornell.edu

From the drop down box under Policies and Procedures, select Facilities Manager Project
Managers Guide.

Facilities Project Managers Guide

Page 8

Summary Overview of this Guide


The Facilities Project Managers Guide is organized into four parts.

Part I describes the role of Facilities Services in capital project execution and the list of
stakeholders that participate in the process along with their principle roles.

Part II describes the project requests and approval process at Cornell.

Part III describes project controls. Presented separately to emphasize its importance, the
controls section describes the systems the University has designed to control the project
budget and schedule, and presents an overview of the contract tools used to define the
relationship between Cornell and the consultants and contractors that work for us.

Part IV outlines how projects are managed and presents the phases of a typical project and
describes what happens in each phase.

This Guide and Other Documents


In addition to this document and the Cornell Project Delivery Guide mentioned above, there
are two additional reference tools available to assist project managers when leading projects:

The Cornell Project Management Methodology Guide (CPMM)

The Project Managers Toolbox.

The Cornell Project Management Methodology (CPMM) Guide


The CPMM website is located at http://projectmanagement.cornell.edu/
The guide can be found at this web address:
http://www.cit.cornell.edu/computer/robohelp/cpmm/cpmm_guidebook.htm
The website contains useful tools such as templates, training announcements, and document
examples. Although Facilities Project Managers typically have the training and knowledge
covered in this guide, these resources are still valuable for Project Managers who want to
refresh and refine their knowledge.
The Project Managers Toolbox
The Project Managers Toolbox is the archive for past PM trainings delivered by Facilities
Services PM Toolbox team. These materials can be found at

Facilities Project Managers Guide

Page 9

http://www.fs.cornell.edu/fs/PMT/default.cfm
Throughout this guide we
will reference the various
trainings that have been
offered and archived as they
relate to a particular topic.
Facilities Services Website
and Other Websites
Throughout this guide, there
will be references to the
Facilities Services web site
http://www.fs.cornell.edu.
Many topics are explained in
detail under the Resources
and the Procedures dropdown boxes. For instance, the
Project Managers Toolbox
page found in the Resources
list provides a library of
resources for capital project
planning and processes that
was created specifically for
project managers across the
University.
This guide will point the
reader to other various web
sites, such as Environmental
Health and Safety, or the City
of Ithaca, that have relevant
information on how to
perform the tasks outlined in
this guide.

Facilities Project Managers Guide

Page 10

Part I: Stakeholders and Roles


One of the most important responsibilities of the Project Manager is to identify the key
stakeholders for a capital project. The stakeholders listed in this guide include

Facilities Services

Project Team

Cornell Approval Groups

Consultants and Contractors

Cornell Stakeholders

External Stakeholders

The organizational diagram below shows most of the participants in the execution of Cornells
capital projects. The Core Project Team carries the project from its inception through
completion and works with internal and external stakeholders to ensure that their needs are
met across the University and in the community.

Facilities Project Managers Guide

Page 11

Core Team
Executive Group
Primary Customer
Project Executive/Director
Project Manager
Construction Manager
Project Coordinator

Cornell Approval Groups

Consultants and
Contractors
Cornell Stakeholders
PDCs Construction Management Contracts & Capital Projects
Cornell Information Technology Cornell Police
Environmental Compliance Office
Facilities Management
Government and Community Affairs Office of the University Counsel
PDCs Project Planning and Estimating
Risk Management
Transportation and Mail Services
Treasurers Office
University Architect
University Engineer
University Planner
Utilities & Energy Management

External Stakeholder Groups


City, State and Federal Agencies
Building Inspector
Planning and Development Boards
Other Boards

Facilities Project Managers Guide

Page 12

Facilities Services: Key Departments


Facilities Services is an administrative support division that includes many of the departments
typically involved in capital projects. In this section, we will briefly outline some of these key
departments and their roles in capital projects:

Contracts & Capital Projects

Contract Colleges Facilities

Facilities Management

Planning, Design and Construction

Office of the University Architect

Utilities and Energy Management

The Office of the Vice President, Facilities Services serves Cornell through the planning,
design, construction, operation and ongoing maintenance of University facilities. All of the
departments in Facilities Services may participate as stakeholders in the Project Delivery
Process. Two of the departments, Contract Colleges Facilities and Planning, Design and
Construction, play a central role in the management of projects for customers outside the
Facilities Services Division. Contracts & Capital Projects also plays a central role in executing
the contracts and administering the payments associated with the contracts. The role of these
three departments, along with others, in the execution of Cornells capital projects is
summarized below.
The Contracts & Capital Projects Office (C&CP) has two primary functions:
The formation and management of facilities-related contracts;
The financial tracking support for Project Managers who manage capital projects.
Contract formation and management services typically include contracts for
architectural/engineering design, consulting services, testing services, renovations and
construction services for both capital and non-capital projects.
Financial support includes invoice processing and project tracking to monitor the financial
status of projects in support of Project Managers who are responsible for capital projects.
Further, this office provides regular project status report summaries to the Buildings &
Properties Committee of the Board of Trustees.
The Contracts & Capital Projects Office is funded as an enterprise and charges both on an
hourly rate and on a lump sum basis for its services.
The Contract Colleges Facilities Office (CCF) manages the Contract Colleges Capital Plan
including project development, initiation, and execution. They facilitate the management of
State University Construction Fund (SUCF) projects and provide project management for
College and University funded capital projects for the Contract Colleges (State campus). The
Contract Colleges Facilities Office is funded by an appropriation.

Facilities Project Managers Guide

Page 13

Project Design and Construction (PDC) provides project management services for general
building and renovation projects in its Science and Technology and Architectural sections.
Projects that are somewhat trade specific, such as a mechanical upgrade or structural repair,
are generally managed in one of the PDC Engineering sections. PDC is funded as an enterprise
and bills on an hourly rate for project management services.
Project Planning and Estimating (PP&E) is often the first point of contact when considering a
renovation or small project. This group provides estimates for work and architectural design
services that in most cases are constructed by the PDC Shops. Projects that are constructed by
the PDC Shops may be managed within one of the Shops or by one of the aforementioned
sections.
PDC also includes a Construction Management section that specializes in the management of
the construction phase of our medium and large building projects.
The Campus Planning Office and the University Architect become involved in any new
building project and any other project that impact the physical campus of the University. See
the PM Toolbox training: The Campus Planning office in Capital Projects.
Maintenance Management provides an ADA Coordination function that serves to assist
Project Managers in the ADA accessibility implications of their projects. For every project,
Project Managers should conduct a preliminary review to determine what, if any, elements
will impact accessibility in the interim (construction) or long term for their project. If their
projects have implications for accessibility in either the short or long terms, the ADA
Coordinator should be involved. If it is unclear if there are any elements for accessibility,
consultation with the ADA Coordinator for determination is recommended.

Facilities Project Managers Guide

Page 14

Project Team
Core Team
Executive Group

Primary Customer

Project Executive / Director

Project Manager

Construction Manager

Project Coordinator

The Core Team for a project includes, at a minimum, the Primary Customer and the Project
Manager. The Core Team may also include a Construction Manager, a Project Coordinator, a
Project Director and others who are directly involved with the project. The Core Team may
report to an Executive Group.
Executive Group
Larger, more complex projects (e.g., new buildings, laboratory renovations) often have an
Executive Group. The Executive Group makes strategic project decisions that dont require
approval by the senior University administrators who represent the Capital Funding and
Priorities Committee (CF&PC) or the Buildings and Properties Committee (B&P) of the Board
of Trustees, and makes recommendations for decisions that do require such approvals. The
group stays informed of project progress and challenges, and provide guidance to the Core
Team. The Executive Group is selected by and may be chaired by the Executive Vice President
for Finance and Administration. Alternatively the Group may be chaired by the Dean or Vice
President of the College or Division sponsoring the project.
Other members typically include the following:

The Department Directors who will use or administer the new space;

Someone from the Office of Planning and Budget , if central University funds are
involved;

The Vice President for Facilities Services or the Director of Project Design and
Construction;

Others associated with the project.

The Core Project Team acts as staff to support the Executive Group, and may provide the
agenda for the meetings. When properly configured and chaired, the Executive Group
provides a valuable forum for debating and resolving project issues and establishing strategic
project goals and direction.
Primary Customer
The Primary Customer establishes the desired program (scope) and works with the Project
Manager to define schedule and budget for the project. The Primary Customer may be the
Facilities Project Managers Guide

Page 15

eventual user of the finished project, or may be acting on behalf of the user. The Primary
Customer may be an individual or a group of people. If the latter, the Primary Customer
group is encouraged to identify a single individual to work with the Project Manager and
serve as program manager.
Project Executive / Director
Construction programs consisting of a series of capital projects or a very complex single
project (e.g. residential initiatives, new science buildings), may have a Project
Executive/Director (PE/PD). The purpose of this position is to ensure that the sequence of
capital projects are coordinated and meet the overall scope, schedule and budget goals of the
University. The PE/PD is generally a senior staff member in the Facilities Services Division
and serves to guide the project team.
Project Manager
The principle responsibility of the Project Manager is to deliver the project within the scope,
schedule, and budget agreed to by all of the stakeholders of the project. The Project Manager
may delegate tasks to other project team members, but still retains the responsibility for project
success. One of the key responsibilities of the Project Manager is to communicate and consult
with all of the various stakeholders. In one of the sections below in this guide, you will find the
numerous project stakeholders who may have a stake in capital projects. The Project Manager
is responsible for including those stakeholders relevant to the project, and establishing a
balance between the sometimes conflicting goals of project stakeholders and between the
various elements of the project (scope, schedule, budget, etc.).
Construction Manager
Larger projects (>$2M) typically use the services of a Construction Manager (CM) who
manages the construction phase of the project and who is the single point of contact for the
Contractor. The split of project tasks between the Project Manager and Construction Manager
is not fixed; however, the Project Manager retains responsibility for the overall success of the
project, budget and design.
Project Coordinator
Larger projects typically have a Project Coordinator (PC) who assists the Project Manager.
PCs also manage projects that range in value from $50,000 to $500,000 having the same
responsibilities as a Project Manager. The PC provides both administrative support to the
project team, and technical support to the project. PCs play a major role in large and small
projects, from inception of the project through to close-out.
Project Coordinator Responsibilities
The PC Matrix is a sample guide for the roles and responsibilities of each of the three
levels of Project Coordinator (PC1, PC2, and PC 3). The roles may be assigned
differently for each project and depending on the expereineces of thos involved. They
may also change as the project progresses.
See: Sample Matrix for Project Coordinator (PC) Responsibilities

Facilities Project Managers Guide

Page 16

Role Agreement
The Project Manager, Construction Manager and Project Coordinator project team
should start with "PM-CM-PC Responsibility agreement in which they agree on roles.
Below are samples of how the Project Manager (PM) , Project Coordinator (PC), and in
the first sample, the Construction Manager (CM) can create a clear understanding of
what role each plays in a project. Each project will be unique, so please use this as a
guide.
See Sample Role Agreement
See Sample Project Manager and Construction Manager and Project Coordinator Duties
and Responsibilities

Facilities Project Managers Guide

Page 17

Cornell Approval Groups


The PM is responsible for coordinating timely authorizations and approvals of the various
phases of the project with the following Approval Groups:

Executive Vice President for Finance and Administration (EVP) or Provost ;

Capital Funding and Priorities Committee (CF&PC - members include Senior


Administration of the University);

Buildings and Properties Committee (B&P - a committee of the Board of Trustees).

The Project Approval Request (PAR) is the principle document for seeking authorizations and
approvals. (See Part II of this guide.) A PAR is required for any capital project with a total
project budget greater than $50,000. The approvals required for a project are dependent on the
total budget.

PROJECT IS AUTHORIZED/APPROVED WHEN.


TOTAL COST PAR signature list
complete
OF PROJECT

$50K- $500K

Capital Funding and


Priorities Committee
approves (CF&PC)

Buildings and
Properties Committee
(B&P) and Executive
Committee
(funding/financing)
approves

(Referred to as a Signature
PAR.)

$500K - $5M

> $5M

See Part II: Project Requests and Approval Process to learn more about the different types of
PARS and how to fill them out.
See Part II: Project Requests and Approval Process for more on the approval process.

Facilities Project Managers Guide

Page 18

Consultants and Contractors


Cornells facility capital projects are

generally designed by architectural and engineering consultants (A/E);

built by contractors, with the construction managed by construction managers.

The Project Manager is responsible for insuring that

the A/E and contractors are selected using approved processes .

appropriate contract documents are executed

the work of the A/E and contractor is properly managed.

The Project Manager is generally the Universitys point person with the A/E.
As mentioned above, the CM serves as point person for the contractor.
Note:

PDC has an in-house design group that provides A/E services for renovation projects up to
about $1M.

The PDC Shops occasionally compete for construction of projects up to about $1M.

See the FS website for more on architect/engineer procurement process. Also see the PM
Toolbox training, Architect-Engineer Procurement.
See the Quality control section below for proper management of contractors. Also see the
Contractor Qualifications information.

Facilities Project Managers Guide

Page 19

Cornell Stakeholders
Cornell has numerous departments and individuals who play a role in our capital projects.
The PM is responsible for including them as appropriate to the project. Possible stakeholders
are:

Alumni Affairs

Construction Management Office

Contracts & Capital Projects Office

Cornell Information Technologies

Cornell Police

Environmental Compliance and Sustainability Office

Environmental Health and Safety

Facilities Management

Government and Community Relations Office

Maintenance Management

Office of the University Counsel

Project Planning and Estimating

Risk Management

Transportation and Mail Services

Treasurers Office

University Architect

University Budget Office

University Engineer

University Planner

Utilities and Energy Management

Alumni Affairs and Development


Construction Management Office
PDCs Construction Management Office includes construction managers and project
coordinators who manage contractors and construction phase activities. Individuals in the
Construction Management Office are frequently members of the project Core Team. The
Director of Construction Management is also responsible for leading the contractor selection
process for PDC-managed projects. Core Teams work with the Director to select preconstruction contractors, construction managers, general contractor bidders lists, and to
develop a construction delivery strategy.
Facilities Project Managers Guide

Page 20

Contracts & Capital Projects Office


Most projects that involve hiring companies to provide labor for design, construction and
renovation work require execution of a contract, as opposed to a purchase order which is used
for procurement of supplies and/or materials. The C&CP Office writes the Universitys
contracts. The C&CP Office also administers the Capital Project System, an accounting system
that tracks PAR authorizations, budget allocations, and commitments/expenditures associated
with capital projects.
Cornell Information Technologies
Cornell Invormation Technologies (CIT) can play one of three roles in a facilities project:

Construction Standards: CIT authors construction standards and works with designers on
the design of IT systems, including telecommunication rooms and raceway systems.

Installation and Maintenance: CIT installs and maintains telecommunication equipment


and software across campus and/or manages installation of these systems by contractors.

AV Consulting: CIT provides an audio/visual consulting group that helps project teams
and consultants specify, install and commission high tech A/V systems.

See PMT Trainings Communications Wiring, Phone Services and Data Services and Total
Technology Integration.
Cornell Police
Cornell Police participate in projects when the following are being addressed:

building security system design

electronic access

video surveillance

intrusion alarm

locations for Blue Light telephones

movement of large construction-related vehicles across campus roadways.

Alumni Affairs and Development


Please see the Alumni Affairs and Development web site for information on this stakeholder.
Environmental Compliance and Sustainability Office
The Environmental Compliance and Sustainability Office
services to project teams:

(ECOS) provides three distinct

They are available to lead or support the Municipal Site Plan Approval process, including
preparation of environmental assessment forms and presentations to municipal approval
groups.

They assist in making sure completed projects comply with various State and Federal
regulations concerning the protection of air and water resources.

They oversee construction phase preparation and compliance with storm water pollution
protection regulations and assist with the LEED certification process.
Facilities Project Managers Guide

Page 21

For information on the Green Buildings Oversight Committee, contact the Services Team at
ECOS.
See Cornells Environmental Compliance and Voluntary Environmental Initiatives
See Cornells Green Building Guidelines
ECOS Checklist
To better understand how ECOS interacts with capital projects, see the checklist on its
website.
PMs are encouraged to fill out this checklist to help them determine what needs to be
considered with respect to environmental compliance issues for their projects.
Environmental Health and Safety
Environmental Health and Safety (EH&S) provides four distinct services to project teams.

The Lab Safety group provides advice and review of construction documents for lab
projects.

The Fire Protection group provides advice for sprinkler and fire alarm systems.

Document Review for overall code compliance, and assistance with abatement of asbestos
and hazardous materials.

EH&S can help with the oversight of construction site safety and review contractor safety
plans.

See Your Project and EH&S and EH&S and Construction Services in the PMT Training.
Facilities Management
Facilities Management (FM) provides maintenance and custodial care for academic buildings
and grounds care for the overall campus. They provide advice and review of construction
documents regarding maintainability of building and site elements of the project. They also
provide advice to project managers regarding the forecasted operating and maintenance costs
that must be identified and included in Section 8 of PARs.
Maintenance Management
Project managers are encouraged to take advantage of collaboration with the ADA
Coordinator within Maintenance Management for all projects planned. This is available to
Project Managers to ensure ADA compliance for every project on Campus.
Office of Government and Community Relations Office
The Office of Government and Community Relations must be involved in the project for all
municipal approvals or when the project is of interest to Cornells neighbors. Examples
include projects that involve construction on the perimeter of campus, that make a noticeable
change in vehicular traffic flow on surrounding streets, or that have other noticeable
environmental impact.

Facilities Project Managers Guide

Page 22

Office of the University Counsel


Office of the University Counsel represents Cornells interests with regard to municipal law
and the impact on the community and the University. Projects requiring zoning variances or
having complex site plan approval processes should involve the University Counsel.
Project Planning and Estimating
PDCs PP&E Office provides project plans, cost estimates, design services and project
management for projects intended for execution by the PDC Shops. When not occupied in
design work intended for the Shops, PP&E is available to prepare architectural designs for bid.
The Manager of PP&E also chairs regular meetings with the City and Town Building
Departments.
Core Teams are encouraged to use the PP&E venue to initiate discussions with the City and
Town Building Departments.
See the PM Toolbox training on Permits.
Risk Management and Insurance
The Risk Management and Insurance Department makes decisions regarding required levels
and types of insurance for consultants and contractors, and also analyzes the fiscal health of
those companies. See more information on Risk Management in Project Management below.
Transportation and Mail Services
Transportation and Mail Services works with project teams to identify parking resources both
for contractors and to support the finished project. See the Transportation Infrastructure
Charge Policy in the Cornell Project Delivery Process, Appendix M.
Treasurers Office
The University Treasurer (Treasury Management Services):

Arranges debt financing for projects as necessary.

Should be consulted on the source of funding for projects that may have an effect on
historic/cultural resources. Projects using State of New York funds or State-issued bonds
will trigger review by the NYS Historic Preservation Office.

University Architect
The University Architecht (UA):

Leads the architect selection process. (See also PM Toolbox for more on architect selection.)

Serves as steward for all architectural matters, including working with the University
Planner in the site selection process.

Makes presentations at CF&PC and B&P for approval of project concept and design.

University Budget Office


Please see this University Budget Office web site for information about this stakeholder.

Facilities Project Managers Guide

Page 23

University Engineer
The University Engineer ( UE ):

Works with designers to develop concepts for engineered systems.

Maintains the Cornell Design and Construction Standards

Ensures that construction documents comply with the Design and Construction Standards
and other standards of quality. In this role, the UE
o meets with the A/E early in the development of the design,
o reviews design documents.

University Planner
The University Planner ( UP):

Brings the campus-wide planning context to bear upon the individual project and plays a
major role in site selection.

Advises on the long-term planning impacts of siting decisions, both from the Universitys
perspective as well as from the communitys and ensures that decisions are consistent with
existing plans.

Writes the Site Development Guidelines (formely called Site Criteria) for new
construction projects. (See CPDP, Appendix C).

Presents selected sites for approval to the CF&PC .


The Roles of the University Planner and University Architect
Here is what the Project Manager needs to know regarding the responsibilities of the
University Architect and the University Planner
UNIVERSITY ARCHITECT

UNIVERSITY PLANNER

New buildings

Site selection for new building

Building expansions

Landscaping, mapping, signage

Exterior building changes

Other site design

Major interior building changes

Land use questions

Building aesthetics

Open space use questions

Exterior building finish or other changes

Site Development Guidelines

University Architect Selection leadership

Planning consultant selection leadership

Utilities and Energy Management


Utilities and Energy Management has two principle functions:

They work with project teams to identify utility construction methods, including metering
systems and connections to the various campus distribution networks.
Facilities Project Managers Guide

Page 24

They provide advice and review of construction documents for energy saving initiatives.
See Energy Management and Utilities Customer Relations - Construction Projects

External Stakeholder Groups


The project team is responsible for acquiring approvals of the following groups external to the
University.
Note that the Cornell central campus occupies one county and three municipalities.

Tompkins County

City of Ithaca

Town of Ithaca

Village of Cayuga Heights

In some instances the Village of Lansing and the Town of Dryden may be involved.
Each has unique procedures for permitting and site plan review. The following is intended to
be a very general overview of these processes.
Building Inspector and Fire Marshall
The Building Inspector generally works with the project team and the Architect/Engineer
during design of the project to prepare a strategy for code compliance. The Building Inspector
may include the Fire Marshall to gain consensus on things such issues as fire truck access to
the project site, design of fire protection systems, and proposals for handling flammable
materials.
Although Cornells contractors generally apply for building permits and arrange for
inspections themselves, most jobs require the Project Manager to facilitate discussions and
resolution of code issues during construction and project close-out phases.
Community/Neighborhood Associations
Cornells campus is surrounded by many neighborhoods, each of which has an association of
homeowners. Cornells Office of Government and Community Relations normally arranges for
meetings with these groups as appropriate to keep them informed of projects near their
neighborhoods.
Planning and Development Boards
As mentioned above, Cornells central campus in Ithaca occupies Tompkins County and three
municipalities (City and Town of Ithaca, Village of Cayuga Heights).
Each has a unique Environmental Quality Review and Site Plan Review and approval process,
and the PM is responsible for ensuring the timely engagement of the various staff and
planning board groups. See ECOSs Environmental and Local Approvals Resource (ELAR)
site for information. Also see the PM Toolbox training called ELAR Website Review.

Facilities Project Managers Guide

Page 25

Other Boards
These include zoning boards for projects requiring some form of variance. The City of Ithaca
has an Ithaca Landmarks Preservation Commission that must approve projects in the City that
affect historic resources that are Designated Landmarks and Designated Historical Districts.

Facilities Project Managers Guide

Page 26

Part II: Project Requests and Approval Process


Cornell University Approval Process
Building maintenance, renovation and new construction projects with total costs exceeding
$50K are designated as capital projects.
The Transaction Authority Policy - Procedure for Processing Facilities Projects establishes cost
thresholds and associated approvals.
Schedules for Capital Funding and Priorities Committee (CF&PC) and Building and Properties
Committee (B&P) meetings are published by the Vice President for Facilities Services office
each summer for the upcoming academic year, and include dates for submission of enabling
documents.
PMs should note that all requests and presentations to the Buildings and Properties
Committee (B&P) must first be authorized by the Capital Funding and Priorities Committee
(CF&PC)

Facilities Project Managers Guide

Page 27

Transaction Authority Policy


Procedure for Processing Facilities Projects
As adopted by the Executive Committee of the Board of Trustees, March 2, 2005. This can also be
found at http://www.fs.cornell.edu/fs/IR/fs_ta_facility.cfm (Transaction Authority Policy & Procedure
For Processing Facilities Projects)
Project Approval

Transaction Authority

$50,000 to $500,000

Executive Vice President


Administration or Provost

$500,000 - $5,000,000

CF&PC

for

Finance

and

$5,000,000 and beyond: New Construction


Architect Selection

CF&PC

Project Concept *

Buildings and Properties Committee

Project Design **

Buildings and Properties Committee

Project Construction ^

Buildings and Properties Committee

Financing

Executive Committee

$5,000,000 and beyond: Major Renovation


Architect Selection

CF&PC

Budget

Buildings and Properties Committee

Financing

Executive
Committee
(Investment
Development Committees as appropriate)

and

Annual Campus Plan

Buildings and Properties Committee and Board

Annual Operating & Capital Plan

Board

The B&P Committee may also review any project that significantly changes the outward appearance of a building or
area within the core campus.
* Includes a description of the functional program to be satisfied, a general description of the scope of construction,
citation of the key project schedule milestones, and the major components of a preliminary budget. For new structures,
Project Concept approval may also include review of criteria for the placement of the structure upon a site.
** Design approval includes a review of the schematic or design development documents that illustrate the layout,
massing and exterior appearance of the facility within the context of its site. Also included is an updated planning
budget based upon a refined definition of the project scope and delivery schedule.

Facilities Project Managers Guide

Page 28

^ Construction approval authorizes construction of the final project scope defined by the construction documents and
specifications. The final project budget is reviewed for the recommendation to the Executive Committee for approval.

The Project Approval Request (PAR)


The PAR is the principle enabling document for capital projects. The purpose of the PAR is to
provide information about the project to the project approvers, including the primary
customers, and to confirm their agreement with the information provided.
The electronic PAR Approval Process is available online.
In general, Project Managers prepare PARs. The Project Manager places his or her name on
the front page of the PAR, and is the person responsible for the overall execution of the project.

PARs are submitted through CCF, FM or PDC, or directly to the VP Facilities Services
office, to be entered into the ePAR system to circulate for signature. This also ensures the
project is included on the CF&PC/B&P agendas as appropriate.

The approval of a capital project is accomplished by getting full sign-off of the PAR
signature page, and approval by CF&PC and B&P, as applicable.

The PAR template lists specific directions for the creation of the PAR, as well as details on
who should be included in the signature page.

Project managers are encouraged to become familiar with the schedules for CF&PC and B&P.
(For the most recent project approval calendar and the schedules for CF&PC and B&P
approvals, see Project Approval Calendars in Information and Resources)

CF&PC meets monthly

B & P meets seven times a year, in September, October, December, January, March, May
and June.

See How to Write a PAR below, and the various types of PARs.
Project Managers for State-funded and Contract Colleges projects should consult with the CCF
office to obtain the slightly different PAR template and coordinate with their schedule due
dates for submittal. Its PAR template is located under Get Things Done on CCFs home page.
Please note the CCF approval calendar that this section provides.
Project Plans
Project Managers are encouraged to write a Project Plan for projects requiring approval by
CF&PC. The Project Plan uses the PAR template and describes the overall project purpose and
scope, and an estimated schedule, and budget. Project Plans may be combined with PARs
requesting approval to begin design work, or for large projects for approval to begin planning.
See a Sample Project Plan.

Facilities Project Managers Guide

Page 29

How to Write a PAR


The PAR is the first approval needed in order for a project to take the next step in the planning
phase. See Initiate Project in Part IV.
In the Cornell Project Management Methodology Guide (CPMM), which is a general
introduction to project management, the PAR is referred to as a PIP. (Project Initiation Plan).
Types of PARS
In the Plan/Design/Bid/Construct Model used at Cornell, the PM might generate PARs
throughout the various phases of the project. There are three general phases of a project:
Planning, Design, and Construction. The most often used PARs for each phase include:
Concept PAR
A Concept PAR is used during the Planning Phase and may include the following:
Fleshing out alternatives
Outlining the major Alternatives Considered and Why Rejected
See below Part IV: for more on the Concept Study.
Design PAR
The description of the scope in a Design PAR may include this type of language:
Create design
Design layout
o See Section 3.3 of CPDP Guide, page 36ff.
When the PM outlines the scope of work during the Design Phase with the client,
she/he should refer to the Owner/Architect Agreement Schedule G.
This contract
includes what architects and engineers are required to provide during the design phase.
The PM may want to split the design phase into three PARs:
Schematic Design PAR
Design Development PAR
Construction Documents and Bid PAR
Each of these PARs is a milestone in the design process.

Facilities Project Managers Guide

Page 30

Construction PAR
The scope of a Construction PAR may include these terms:
Demolish
Construct
Provide (furnish and install)
See Section 3.5 of CPDP Guide page 39ff.
Revised PARS
On an infrequent basis it is necessary to revise a PAR. This may be due to a change in
the project scope, schedule, or budget. Revised PARs follow the same procedures and
pathways as the original PAR. An effective way to write a revised PAR is to use the text
of the original and insert changes in bold type. This allows the reviewers to readily see
the changes from what they had originally approved. See Sample Revised PAR.
Revised PARs are submitted for the following cases:
1) To request an increase in the approved project budget;
2) For revisions to the projects scope of work;
3) For project schedule changes due to unforeseen issues/conditions that occurred
during the current phase (design or construction) of the project.

Municipal Approval Process


Local Municipalities
The requirements for municipal approval and permitting vary by municipality. Portions of
Cornells main campus fall into the jurisdiction of the:
o City of Ithaca
o Town of Ithaca
o Village of Cayuga Heights.
Projects off of the main campus may also be in the:
o Town of Dryden
o Town of Lansing
o other municipalities

Facilities Project Managers Guide

Page 31

State-funded and/or State-owned Buildings


Projects funded by the State University Construction Fund (SUCF) or performed in a stateowned building are not subject to approval by the local municipality, but instead are reviewed
and approved by the Code Enforcement Officer in the Contract Colleges Facilities Office.
New York State Building Code and Local Code Ordinances
All but very small projects require a building permit issued by the municipality in which the
project is located. A prerequisite to obtaining a permit is the demonstration to the building
inspector that the project meets applicable requirements of the New York State Building Code
and local codes and ordinances.
Building Inspector / Fire Department
The Project Manager is responsible for arranging communication between the designers of the
project and the building inspector. These meetings may also include a representative from the
fire department and from Cornells Environmental Health and Safety group. PDCs Project
Planning and Estimating group meets regularly with both the City and Town of Ithaca
Building Departments. Project managers are encouraged to use these meetings to initiate
discussions on new projects.
Municipal Site Plan Approval
Projects that change the exterior appearance of the campus generally require site plan
approval from the municipality in which the project is located. Municipal Site Plan Approval
is a multi-step process that includes

an environmental quality review and

Preliminary and final site plan review and approval.

The project manager is responsible for moving the project through these processes and
including stakeholders as appropriate to the project.
Municipal Approvals
As with Cornells internal approvals, the Project Manager must include time for municipal
approvals in the overall project schedule. Projects under SUCF or CCF Code Authority are
exempt from Municipal site plan review, but courtesy presentations are sometimes given.

Facilities Project Managers Guide

Page 32

Project Authorization Letter


Once a project has been authorized/approved by the appropriate group and all signatures are
complete in the ePAR system, the Office of the Vice President for Facilities Services issues a
Project Authorization Letter (See the sample in the CPDP, Appendix, Item O).
This letter serves as the vehicle for Contracts and Capital Projects to request an account from
the Division of Financial Affairs and proceed with the issuance of contracts for the project.
Without this documentation, the C&CP office does not have authorization to proceed or incur
expenses for the project. No project may start without a written contract.
Letter of Authorization
Under certain circumstances, a project contract may commence with a Letter of Authorization
(LOA) signed by the Vice President for Facilities Services or Executive Vice President for
Finance and Administration, depending on the dollar amount requested. A LOA is a
contractual document that authorizes a consultant or contractor to proceed with a fixed scope
of work and to expend a fixed dollar amount which sum shall then be included in their
contract.

Facilities Project Managers Guide

Page 33

Part III: Project Controls


Introduction
This section describes Project Controls. Project Controls exist to help insure projects are
efficiently organized and executed in a manner consistent with sound business practices.
Controls exist for the following areas of project management:

Budget Development

Funding Plan

Schedule Development

Contracts

Invoices and Payment Applications

Financial Reviews and Reporting

Budget Development
Budget Planning Phases: Overview
Planning Phase
The Project Manager, working with the Core Team, develops an initial model for the
overall project budget during the Planning Phase, using benchmark data and the Project
Budget Template. See CPDP Guide Item L. (Disclaimer: Please note that at this time, the
budget model provided here does not match up with the Project Managers report
produced for the project.).
Design Phase
The Project Manager develops and refines the budget model as the project proceeds
through the Design Phase.
Bid Phase
Construction Phase Cost Tracking
During the Construction Phase, or project execution phase, the Project Manager updates
the budget model at least monthly, including approved amounts, paid amounts to date,
and forecast amounts, for each line of the budget model.

Facilities Project Managers Guide

Page 34

Budget Template
Budget development, tracking and control are primary responsibilities of the Project Manager.
The main subcategories of project costs from the Project Budget Template are:
1.
2.
3.
4.
5.
6.
7.

Construction
Planning & Design
Furniture, Fixtures & Equipment (FFE)
Project Support
Transportation Assessment (if applicable. See Appendix, Item M, in CPDP Guide)
Project Management
Project Contingency

The definitions of the above budget lines are provided in the Appendix of the CPDP Guide,
Item L. (Disclaimer: Please note that at this time, the budget model provided here does not
match up with the Project Managers report produced for the project.)
Planning Phase Budget Development
The development of a Planning Budget can start with either:

the selection of a desired budget number, from which a corresponding range for
project/program scope can be derived, or

a program scope, from which a budget range can be derived.


In either case a key deliverable for the Project Team is to establish a range of typical unit
($/sf) construction costs and a ratio of construction costs to total project cost.

Estimations of unit construction cost are based on a preliminary understanding of the program
and site, and selection of appropriate benchmark projects for comparative purposes. The
Project Team will select representative projects at Cornell and, if possible, at other institutions,
to establish a range of unit $/SF construction costs.
The Project Manager will also work with the core team to identify any unusual project soft
costs. For purposes of the initial Planning Budget, the ratio of construction cost to total project
cost at the beginning of a project is generally in the range of 2/3 to 3/4, and depends on the
anticipated level of the soft costs.
Soft costs are all costs not incorporated in the finished building; they are the expenses other
than bricks and mortar incurred in developing a building project. Lines 2.0 (Planning and
Design), 4.0 (Project Support), 5.0 (Transportation Assessment) are budget line items for soft
costs. 1.0 (Construction) and 3.0 (FF&E) may also show soft costs for suchs things as quality
assurance services.
The following table lists the soft cost budget lines and a range of typical percentages of project
cost.

Facilities Project Managers Guide

Page 35

LOW

HIGH

Planning and Design

10%

16%

Fixtures, Furnishing and Equipment

2%

6%

Project Support

2%

8%

Transportation Assessment

2%

2%
See CPDP
Guide Appendix, M

Project Management

2%

6%

Contingency

8%

10%

Building efficiency is another important factor in establishing the relationship between


program size and construction cost. The ratio of net program area to building gross area is
normally in the range of 55% to 65%.
Remember that the cost per square foot is proportional to efficiency; the higher the efficiency,
the greater the cost per gross square foot.
Relationship Between Area Efficiency (NASF/GSF) and Cost Per GSF
NASF

GSF

Efficiency

Cost/GSF

Total Cost

80,000

160,000

50%

200

$ 32,000,000

80,000

153,846

52%

205

$ 31,538,462

80,000

145,455

55%

211

$ 30,690,909

80,000

140,351

57%

218

$ 30,596,491

80,000

133,333

60%

225

$ 30,000,000

80,000

129,032

62%

230

$ 29,677,419

Note: It's not easy to increase efficiency. The program and mechanical space are the costlliest spaces.
As efficiency increases, it's the less costly space that's being reduced.
Please note that un-programmed space includes

entrance areas

attics

mechanical rooms

lavatories

corridors

stairways

space within walls

left-over spaces that occur in a building design.

To estimate archiving fees, see Worksheet for Computation of Capital Project Fees (projects $50K or
greater)
Facilities Project Managers Guide

Page 36

Design Phase Budget Development


Feasibility Study Phase Budget Development
A feasibility study can be quickly done for some projects, but significant projects
usually require a feasibility / concept study. Using the preliminary program
requirements for the project, an order of magnitude planning budget will be
developed by the Core Team. See sample feasibility study.
During this phase of the project a range of project costs, e.g., design fees, management
fees, construction estimate, should be used. This range of costs will be further refined as
the design progresses.
Realistic contingencies to account for unforeseen circumstances during the development
of the project should be established. These tend to be substantial at this stage of project
development.
The product of a feasibility phase is the Schematic Design PAR and the budget for this
phase, discussed next.
Schematic Design (SD) Phase Budget Development
An important objective at the end of the feasibility study is to develop a Schematic
Design phase project budget for the project scope that fully meets the program
requirements. The project budget should only require slight adjustments after the end
of this phase if the scope of the project does not change.
The Core Team should follow these steps to develop the SD budget:
Step 1: Parallel estimate
In addition to the SD cost estimate provided by the design consultant as part of their
contract, an independent cost estimating professional should be used to furnish a
second, parallel cost estimate of the proposed work. The estimates should utilize similar
formats so that they can be easily compared.
Step 2: Reconciliation of estimates
To the extent possible, both estimators must reconcile the two cost estimates to ensure
that they both include the same scope of work. The result of this reconciliation is the
determination of a budget for the project.
Step 3: Allowance Items
Identify, and budget for, those items that will be carried in the budget as allowance
items. Such things as furniture, special user equipment, audio-video equipment, special
furnishings, etc., may fall into this category. This allowance will represent the not-toexceed amount for these items.
Step 4: Value Analysis /Value Engineering (VA/VE)
Earned Value Management (EVM) is a project management technique that measures
project progress objectively. EVM has the unique ability to combine measurements of
technical performance (i.e., accomplishment of planned work), schedule performance
Facilities Project Managers Guide

Page 37

(i.e., behind/ahead of schedule), and cost performance (i.e., under/over budget) within
a single integrated methodology. EVM provides an early warning of performance
problems while there is time for corrective action. In addition, EVM improves the
definition of project scope, prevents scope creep, communicates objective progress to
stakeholders, and keeps the project team focused on achieving progress.
This process is a rigorous one, in which the project manager attempts to deliver project
scope at a lower cost. The Project Managers responsibility is to consider life cycle costs.
In this process, called value analysis / value engineering (VA/VE), the core team,
impacted stakeholders, and appropriate experts need be invited to review and accept
decisions.
VA/VE is one of the first steps in the Earned Value Management process, which is
designed to test and validate cost estimates. The team will identify a long list of items
to consider, if estimates exceed the target budget established during the Feasibility
Planning Phase. It is strongly recommended that the Project Manager manage the
project at or below the maximum range of costs for the design at this phase, before
moving on to Design Development. It will become increasingly more difficult (and
costly) to identify significant cost savings as the design moves toward completion.
See PM Toolbox training Life Cycle Costing in Value Engineering
See Sample SD VE
Sample SD Cost Strategy.
At the end of Schematic Design, the project budget and program should be aligned and
the final budget should be approved.
If the budget and the scope do not yet align, the team will return to the SD
process to make the adjustments necessary to get the project scope and
budget in alignment before proceeding to the Design Development phase of
work.

Facilities Project Managers Guide

Page 38

Design Development (DD) Phase Budget Development


Step 1: Perform a cost/value analysis
The selected service provider of pre-construction services may perform this analysis
which allows the contractors to review the design and propose alternatives that could
result in additional cost savings. Design options must be decided on so that the design
may progress including the lowest cost systems/assemblies that meet the stated design
criteria. This step is a follow up to the cost/value analysis that was conducted at the
end of Schematic Design.
Step 2: VA/VE Items
Determine a comprehensive list of VA/VE items to be considered through the
subsequent design and bid phase. Even if the budget estimate shows the project aligns,
this will not be certain until after bids have been secured and analyzed. See sample DD
VE.
Step 3: Life Cycle Costs
Cornells project teams are required to design for minimum life cycle costs. Core Teams
will consult with Cornell stakeholders (for instance, Maintenance Management,
Utilities, and other Facilities Services groups) to solicit their participation in design
decisions regarding life-cycle costs, durability and maintainability.
See the PM Toolbox training Life Cycle Costing in Value Engineering.
Step 4: DD Estimate
Perform a DD estimate at the end of the Design Development Phase along with an
optional parallel estimate from an independent, professional cost-estimating firm as
deemed necessary by the Project Manager. This estimate should have a consistent
format with schedule of values in the budget template so that useful forecasting
statistics can be maintained.
Step 5: Project Budget Validation
Validate the Project Budget with the DD estimate. At this phase of design, the range of
costs must be narrowed to a fairly certain Project Budget target that will carry through
the Construction Document/Bid Phase.
Construction Documents Phase Budget Development
The design must not change during this phase.
Alternates to the base bid design must be finalized and agreed to by the Core Team.
Alternates are often developed during the Construction Documents (CD) phase to
estimate the costs of specific scope elements or to identify scope that can be deleted
from the project in the event that the bids exceed the budget.
Separating items provides a clear means for cost benefit analysis of options that would
enlarge or shrink the building program, according to the available project budget.
Facilities Project Managers Guide

Page 39

A final CD cost estimate is prepared at the end of this design phase.


A contractor selected to perform pre-construction services will review the construction
documents to validate the final cost estimate and to help avoid potential bid cost over
runs.
Perform final budget reconciliation just prior to bid. Ensure that the selected alternates
will allow a construction contract to be issued.
Bid Project Phase Budget Development
The Contracts & Capital Projects Office (C&CP) is responsible to uphold the integrity of the
bid process for all construction projects at the University.

For all projects, the Architect /Engineer provide the Technical Requirements
(specifications and drawings).

The Core Project Team edits Cornells General Requirements to represent the specific
circumstances of the project, and provides both the Technical and General Requirements to
the Contracts & Capital Projects Office.

C&CP prepares Instructions to Bidders, Bid Forms and Cornells General Conditions with
assistance from the PM as requested.

C&CP issues the resulting bid documents and administers all flow of paper and
information associated with the bid, including conducting the bid opening.
o See in the CPDP, Appendix G, Bid Document Package, and Appendix H, General
Conditions and General Requirements.
o See C&CP web page Pricing your Construction Project .
Lump Sum Projects
On lump sum projects, the bids from the invited general contractors are received by
C&CP and analyzed with the Core Team.
Public or Private Bid Openings
Bid openings are typically public. However, private openings may be held at the
discretion of the Contracts & Capital Projects Office. (State-funded Project must conduct
a public bid opening).
If a qualified bid is within the Project Budget, a contractor may be selected for the work.
GMC Projects Negotiations
When the form of contract is Guaranteed Maximum Cost (GMC) the Core Team and the
Contracts & Capital Projects Office will negotiate General Conditions, General
Requirements (which can be found in the CPDP, Appendix H), contractor fee, and other
contractual terms with the selected general contractor. See PM Toolbox Training
Negotiations for Project Managers and Fixed Price Audit Program.
All work will be competitively bid by the selected general contractor, and the result will
be a negotiated guaranteed maximum cost for the work, that is within the project
budget.
Facilities Project Managers Guide

Page 40

GMC may be used when there is a challenging project schedule or a highly technical or
complex project.
The GMC delivery method allows the owner, contractor and design team to work
together to save time during construction.
o See the GMC Cost of Work spreadsheet for estimating.
o See Appendix for examples of GMC documents and spreadsheets:
GMC Systems
GMC Cost of Work (Current Bidding Climate)

GMC GCs
Bids Exceed Construction Budget
If all bids exceed the construction budget, conduct a scope review and/or value
engineering (cost saving) session to determine if the project can be completed within the
approved construction budget. This is sometimes referred to as de-scoping the
bidder.
De-scoping the bidder is the process the Project Manager uses to reassure herself that
the contractor has provided a responsible bid and has priced the project for the scope of
work the contractor was asked to bid on. The Project Manager might sit down with the
contractor and review the responsibilities of the contractor in order to confirm explicitly
what the contractor is responsible for in the bid scope.
Awarding the Project to a Bidder
On a Lump Sum project, award is made on the basis of low base bid or project specific
criteria. Once this selection has been made, alternate pricing is then taken into
consideration.
State-funded projects are awarded on the basis of base bid plus alternates in sequential
order.
A contract is then awarded by the Contracts & Capital Projects Office.
Prior to award, the Core Team considers and makes decisions as to incorporation of all
acceptable VA/VE suggestions made by the selected contractor.
See the PM Toolbox Training Bidding a Project.
See sample budgets.
Construction Phase PAR
The Construction Phase PAR is finalized with the construction budget fixed, including
contingency. Funds are authorized.

Facilities Project Managers Guide

Page 41

Construction Phase Cost Tracking


Construction phase Project Contingency is generally set at 10% of the value of the
construction contract. During the Construction Phase, the Project Manager and Construction
Manager are responsible for

administering the intent of the construction agreement

monitoring progress

ensuring conformance to plans and specifications

quality control

payment application approvals

pending items

controlling the budget


Pre-construction
The Project Manager should implement effective processes of communication between
the Core Team, design consultant and contractor.
See PM Toolbox Training:
o Projects Communications Plan
o Managing Expectations
o Project Communications
o Project Communications Checklist (use this as a model)
o The Project Manager is responsible for conducting a pre-construction meeting per
the terms of the Agreement.
Prior to a contractor mobilizing on site, a contract must be fully executed and all
contractual requirements for insurance, bonding, etc., as specified in the Contract must
be in place. Project-specific methods for addressing such things as Change Orders,
answering questions related to the work and control of payments are discussed. See
Risk Management below.
Minimize or eliminate the occurrence of scope creep. Contingency funds are not to be
used for discretionary design changes or scope items not specifically defined in the
PAR.
The Project Manager and Construction Manager develop an expedited means to
review/approve submittals, and monitor it carefully. Coordination of trades and site
logistics must be expedited, as well, by the Construction Manager.

Facilities Project Managers Guide

Page 42

Construction
Keep Schedule
The Construction Manager keeps to current published schedule.
The Project Manager and Construction Manager avoid discretionary changes to the
design at this phase. Changes made now carry a severe cost penalty.
Validate, Track and Monitor Change Orders
o The Project manager and Construction Manager validate all Change Orders in a
timely manner including the processing of contractual change orders. Document the
cause of all Change Orders ( e.g., field conditions, design errors and omissions,
owner initiated program change).
o Keep an accurate, current Change Order log and insure Change Order costs are
added to/deducted from the Master Project Budget Model.
o See C&CP website for information on change orders.
o See Sample Change Order letter.
Review for ADA Access Compliance
Project Managers should -keep an accurate review of partners consulted on access
review, as well as have conversations with architects and Cornell University staff on
access elements.
Timely Responses to Contractor
Make sure there is always a timely response to all requests by the Contractor.
Adopt an effective system to manage and document this flow of information.
Timely Payments
Make timely payments. See invoice payment.
Quality Assurance/Quality Control
Implement a Quality Assurance/Quality Control system during the Construction
Phase. See PM Toolbox training Quality Control, Inspections and Commissioning.
Also, see next section.
Monitor Contractors Compliance
Continue to monitor Contractors compliance with contractual submissions. Many
different Cornell stakeholders can play a role in monitoring compliance. The Cornell
shops, structural engineers, designers, project team, EH&S, clients, the commissioning
agent, Maintenance Management, are examples of groups who can provide input into
compliance of the contractor.
See PM Toolbox training for contractor compliance and quality assurance topics
Energy Management Tools
Facilities Project Managers Guide

Page 43

LEED Rating System at Cornell


Quality Control, Inspections & Commissioning
Testing & Inspection Services
Your Project and Environment Health and Safety
Close-out/Move-in
During this phase of the project, the Project Manager should promptly initiate the
financial close-out of all Project commitments. This will avoid accumulation of
unnecessary administrative costs to the Project.
Resolve any claims
The Project Manager should resolve any claims. See Risk Management. Morever, this
is a good time to advise other Project Teams of any lessons learned and/or innovations
that could be used in the future.
Project Contingencies
Capital building project budgets carry three types of contingencies:

Escalation

Design

Construction
Escalation Contingency
Escalation Contingency adjusts the project budget model for changes in the cost of
construction, caused by increases in labor costs and volatility/increases in material
costs, and inflation of the other budget lines over time.
Escalation Contingency must be considered for projects lasting over a year.
The following guidelines apply to the use of cost escalation in project budgets.
o Project budget models should list a separate line for escalation for each of the six
major budget categories. Construction cost estimates from our pre-construction
estimators should break escalation out separately and the same factor used to
escalate the construction estimate to the bid date should be used in the Construction
section of the project budget.
o Escalation factors will probably be different for each of the project budget sections.
For example:
The Planning and Design section might not escalate once the A/E fee has
been negotiated.
Project Management costs will escalate with increases in the enterprise billing
rates.
Construction costs will escalate per the anticipated conditions in the local
construction market.
Facilities Project Managers Guide

Page 44

Projects with fixed, non-escalating budgets


o Projects with fixed, non-escalating budgets are more sensitive to volatile
construction escalation than projects that are allowed to escalate.
o Fixed budget projects require the project team to estimate future escalation figures at
the start of the project, and then adjust the scope if the escalation estimates are
wrong.
o Scope adjustment can be very difficult, especially late in the design phase of the
project. Consequently fixed budget projects require a more conservative approach to
picking escalation figures, i.e., they have a larger escalation contingency.
o The intent of fixed project budgets is to emphasize preservation of project budget
over scope.
o The preferred method for building the project budget is to structure the budget
model at each project milestone cost estimate (i.e., Concept, SD, DD 50%DD),
assuming immediate construction start. Then an escalation contingency factor is
applied to each of the main budget subcategories to arrive at the total project cost.
Finally the scope is adjusted as required to match the estimated total project cost to
the budget. Escalation contingency applied to the construction line should come
from the construction cost estimators working on the project, in concert with the
Project Team.
o Finally the scope must be adjusted as required to match the estimated total project
cost to the budget. Escalation contingency applied to the construction line should
come from the construction cost estimators working on the project, in concert with
the Project Team.
o Projects with fixed, nonescalating bugets should include bid alternates that may be
taken in the event that escalation assumptions are inadequate. Development of a
strategy for use of alternates is particularly important if the project budget is nonescalating.
Projects with budgets that are allowed to increase with escalation
o Projects with budgets that are allowed to increase with escalation are easier to match
scope with cost than projects with fixed budgets, because there is less risk from
faulty escalation assumptions.
o The concept is that, if you can afford the project now, you will be able to afford it in
the future because you are protected from escalation, except in circumstances where
the escalation is so extreme, the project becomes unaffordable.
o For projects with budgets that are allowed to escalate, the starting budget is allowed
to escalate from the project approval date (the date the project base budget is set) to
the start of construction.
o The intent of escalating project budgets is to emphasize preservation of project scope
over budget.

Facilities Project Managers Guide

Page 45

o Escalating project budget models can be structured in the same manner as nonescalating projects except the escalation contingencies are treated as additions to the
project budget.
o The purpose of the escalation contingency is to provide an estimate of the eventual
total project cost.
Design Contingency
Design Contingency is used in the design phase of a project in acknowledgement that,
until the design is completed, the construction cost estimate is based on incomplete
information.
The following guidelines apply to use of Design Contingency in project budgets.
Design Contingency for Design Phase of Budget
Design phase Project Contingency is used during the design phase of the project to pay
for things such as
o increases in A/E fees due to program changes,
o complications in the site plan review process, or
o delays in the project during which the project team continues to work and bill its
time.
The Design Contingency belongs in the construction section of the budget. Funds are
moved from the Design Contingency line into the construction line to pay for scope that
is identified as the design progresses.
There is no need for a Design Contingency when using unit square foot costs to
benchmark the cost of a proposed project during the Planning phase. The proposed
project is being compared to an existing facility that is complete.
The Design Contingency should be set at 10% to 15% of the construction cost-of-work
amount in cost estimates during the planning or feasibility stage of a project. Projects
typically carry
o 10% at the end of Schematic Design,
o 5% at the end of Design Development, and
o 2.5% at the 50% construction document estimate.
o Design Contingency is 0% when the design is complete and ready for bid.
Construction Contingency
Construction phase Project Contingency is generally set at 10% of the value of the
construction contract. Project contingency is used during the construction phase for
some of the above reasons, as well as for the following possibilities:
o unforeseen expenses in areas such as underperforming value engineering initiatives,
o quality assurance inspections
o

added commissioning costs. See sample budgets.

Facilities Project Managers Guide

Page 46

o allowances or alternates to the construction contract


o Factory Mutual (insurance) or Building Inspector requirements identified during
construction.
Use of the contingency for these items is generally determined by the Project Manager
with input from the Construction Manager.
Project Contingency is also used during the construction phase to pay for three general
categories of cost increases related to the construction contract:
o Errors and Omissions
o Unforeseen Conditions
o Scope / Project Changed
Errors and Omissions
Errors and Omissions (E&O) in the design documents are defined this way:
o Errors occur when the designer makes mistakes in the contract documents; e.g.
specifying a 32 wide door when a 36 door is required.
o Omissions occur when the designer neglects to put something in the contract
documents that should have been there; e.g. forgetting to put a door where one is
needed.
Unforeseen Conditions
Unforeseen conditions occur when the architect or contractor had no way of
anticipating a job site condition that affects the project. For example, in a renovation
project the contractor may discover a structural problem in the building when a wall is
opened up. Another example is the contractor doing an excavation and encountering a
utility line that was not on the construction documents and not on the Owners utility
maps. In each case, no one is responsible for not having addressed the condition in the
construction documents and Cornell must pay to fix the problem.
Responsibility: E & O and Unforeseen Conditions
The Project Manager is responsible for determining use of contingency in the
E&O and Unforeseen Conditions categories.
Project teams frequently encounter circumstances at the conclusion of a
project, when the building is newly occupied and problems arise as a result of
the dissatisfaction of certain occupants or stakeholders. For example, the
occupant of an office might want an extra data outlet, or a piece of mechanical
equipment may prove to be unreliable, even though it was purchased and
installed according to the contract documents. The Project Manager is
responsible for post-construction contingency use when it falls into the E&O
and Unforeseen Conditions categories.
Scope/Program Change

Facilities Project Managers Guide

Page 47

Scope or program changes occur when Cornell makes a change to the scope of the
project after the work has been bid and awarded. It is important to note that
discretionary changes to the project after construction has begun are strongly
discouraged.
Although Project Contingency is not intended for scope/program changes during the
construction phase, these changes are sometimes unavoidable.
Typically there is an executive committee comprised of the Project Manager and the
PDC Director; there may also be a a central admininistrative representative and the
program representatives. This group discusses options and makes a recommendation
on the use of contingency. At the next level--VP Facilities s/he will probably insist
on bringing forward a PAR to approve the use. For example, on the Life Sciences
Technology Building project, the PAR's have noted the use of contingency and asked
for backup in that amount if the project goes over budget.
Responsibility: Scope / Program Change
Requests to spend construction contingency on Scope/Program change
require the authorization of the
VP for Facilities Services,
the person representing the source of the funding, and, depending on
the size of the change,
CF&PC.
When large projects are involved, the Executive Committee should make
timely decisions on the use of contingency for scope changes.
A Construction Contingency Worksheet
managers.

Facilities Project Managers Guide

for exposures is available for project

Page 48

BUDGET
TYPE OF

PLANNING

DESIGN

CONSTRUCTION

CONTINGENCY
ESCALATION

DESIGN

The Planning and Design section might not


escalate once the A/E fee has been negotiated.
Project Management costs will escalate with
increases in the enterprise billing rates.

Construction costs will


escalate per the
anticipated conditions in
the local construction
market.

10% to 15% of the


construction cost-ofwork amount in cost
estimates during the
planning or feasibility
stage of a project.

The Design Contingency


belongs in the
construction section

CONSTRUCTION

10% of the cost of the


design fee for each
phase
--10% at the end of
Schematic Design,
--5% at the end of
Design Development,
and
--2.5% at the 50%
construction
document estimate.
Design Contingency
is 0% when the
design is complete
and ready for bid.

10% of the value of the


construction contract.

Errors and
Omissions
Unforeseen
Conditions
Scope / Project
Changed

Facilities Project Managers Guide

Page 49

Capital Project Funding Plan


Each capital project is required to have a funding plan, identifying

the source(s) of funding for project costs,

the need for debt financing and

the source of repayment of debt service (principal and interest).

This funding/financing plan is the responsibility of the business manager or similar position
within the unit that is providing the project funding.
Funding sources, including identification of account numbers, must have sufficient funds
available to cover the project cost or an explanation of where funding will ultimately come
from. If debt financing is needed to cover project cost, either on a short-term, bridge basis or
long-term, permanent basis, the unit business manager is to work with the Universitys
Director of Debt on the loan terms and loan application process.
Project funding to come from gifts must have backup listing the gifts raised for the project,
payments received, and a schedule of anticipated payments on outstanding gift pledges.

Schedule Development
Schedule development and update is another principal responsibility of the Project Manager.
The contractor provides the schedule to the Project Manager.
A properly designed schedule includes

each phase of design work with time for design review

cost estimating milestones

associated redesign periods if needed,

bid or buy-out period,

construction period, and

internal and municipal approvals.

The duration of a typical project that experiences no unusual delays, from start of initial
programming through move-in of users, ranges from 6-8 months for a smaller project
designed and built by PDC, to five or six years for a large laboratory building.
See PM Toolbox training Construction Scheduling

Contractual Agreements
After a consultant or contractor has been selected for a project, and prior to start of design or
construction work, the terms and conditions surrounding the execution of the work must be
documented in a Contractual Agreement.
Cornells Office of Contracts & Capital Projects (C&CP) maintains Cornells contractual
instruments and develops all Contractual Agreements between the University and its
consultants and contractors. The Project Manager is responsible for working with Contracts &
Facilities Project Managers Guide

Page 50

Capital Projects on modification of the contract instrument to meet the specific requirements of
the project.
Design Agreements
Project Manager Issues Request for Proposal (RFP)
The Project Manger issues the RFP. In order for a contract to be executed with a
consultant, the consultant needs to have responded to a Request for Proposal which
includes
o a description of the services requested,
o the deliverables and schedule requirements, and
o a copy of Cornells A/E agreement (see page 8) which allows the consultant to
respond to the RFP with an understanding of the terms of the proposed contract.
o The University Architect is also involved in the selection of an architect for the
project.
Project Manager Presents Proposals to C&CP
The Project Manager should review thoroughly (but not sign) proposals from
consultants to ensure that all required work has been addressed and that no fees are
included for services that are not requested (alternate pricing options may be identified)
and present the resulting proposal to Contracts & Capital Projects for consideration in
the preparation of a contract.
C&CP Reviews Proposal
Contracts & Capital Projects will review the proposal to make sure that it is consistent
with the stipulations within the proposed contract.

Facilities Project Managers Guide

Page 51

Types of Design Agreements


DOCUMENT
NAME
Owner/Architect
Agreement
(Short Form)

USE

BACK-

LIMIT

UP

Professional
Design Fees
and Services

None

Less than
$100,000 in
Professional
Fees

None

See Long form

Professional
Design Fees
and Services

Greater
than
$100,000 in
Professional
Fees

Preconstruction
Services
Agreement

Preconstruction
Fees and
Services

None

No Limit

Short Form
(limited)
Short form (full
service)
Owner/Architect
Agreement

See Design Agreements.


See Blanket A/E Agreements.
See relevant sections in PMToolbox Architectect Procurement
For Contract College Facilities, see
o Pofessional Service Selection Information Sheet
o Standard 254 Form
o Standard 254 Form Guidelines

Facilities Project Managers Guide

Page 52

Construction Agreements
The Core Team, working with Contracts & Capital Projects, selects the bid and/or negotiates
the proposal that is most advantageous to the University.
Contracts & Capital Projects handles the development and execution of the construction
contract.
Types of Construction Contracts
DOCUMENT
NAME

USE

BACK-UP

LIMIT

Short form agreement

The procurement of
small renovation and/or
construction services

Written scope of
work, contract value
cost, schedule,
funding source, PAR
(over $50,000)

Typically
$100,000

Construction
Agreement

Construction costs and


services contracted
with a Lump Sum cost.

Bid Form Plans,


Specifications,
Addendums
incorporated by
reference.

Typically
greater than
$100,000

*Guaranteed Maximum
Cost (GMC) Agreement

Construction costs and


services contracted
with a Guaranteed
Maximum Cost

Contractor Proposal,
General Conditions
Costs, Assumptions
and Clarifications
Plans, Specifications,
Addendums
incorporated by
reference.

Typically
greater than
$1,000,000

*These are customized agreements in which the Project Team works closely with the
Office of Contracts and Capital Projects on the wording of the General Conditions (see
GMC GCs).
Key items for negotiation with the Construction Manager include fee, general
conditions costs (see GMC GCs), contractors contingency and sometimes
incentive/disincentive clauses.
Under this contracting method, assembly, distribution of the bid documents and receipt
of bids for subcontractor work is generally done by the Construction Manager.
See PM Toolbox Training Managing Contracts.

Facilities Project Managers Guide

Page 53

Invoices and Payment Applications


The Project Manager is responsible for insuring the accuracy and appropriateness of payments
made by the University to consultants and contractors in payment for execution of the various
work tasks of the project. C&CP oversees the payment of invoices for projects.
Setting up an Account
Before invoices can be paid, the PM must generate a PAR and have an Approval Letter, which
C&CP uses to set up the project account with the Division of Financial Affairs (DFA).
Each month C&CP receives an accounting statement from DFA.
Receipt of Invoice in C&CP
Invoices are received by the Contracts & Capital Projects Office. Invoices received by the
Project Manager or Construction Manager should be routed to C&CP.
C&CP Review of Invoice
Upon receipt of an application for payment C&CP performs the following steps before
forwarding it to the Project Manager for approval:

Identify the payment source

Review the payment history

Check invoice against contract terms and conditions

Resolve any discrepancies with the applicants accountant

Construction Manager Reviews


The Construction Manager reviews the construction invoices. The Construction Manager
negotiates changes, and can determine if the contractor is offering a responsible proposal. The
Construction Manager also ensures that the services for which Cornell is being billed have
been delivered. If the project has a Project Coordinator, and if general conditions are included
in the contract, the Construction Manager may create a pencil copy.
Project Coordinator Review
Project Managers typically route payment applications to a Project Coordinator who reviews
them for completeness of supporting documentation and accuracy.

For contracts that allow billing of reimbursable expenses, the supporting documentation
must include receipts for all expenses.

For contracts that allow billing of actual general conditions costs (Cornells GMC
contract), the PM must check to be sure only allowable expenses are billed.

Approval by PM and Return to C&CP


The Construction Manager or Project Coordinator returns the invoice to the Project Manager,
who approves payment. The PM sends the invoice to others for approval, including the PMs
Facilities Project Managers Guide

Page 54

supervisor and, in the case of PDC PMs, to the PDC Director, the appropriate finance person,
and the VP for Facilities Services.
The PM then sends the payment applications to the Contracts & Capital Projects Office where
all contractual payments are processed.
CC&P Requests Payment by DFA
Pay requests are sent to the DFA, where checks are issued.
Project Over Budget
CC&P will not sign off on a commitment if it causes the project to go over budget. The Project
Manager must submit a new PAR or re-allocate funds (for example, use contingency.)
Project Managers Report
The Project Managers Report contains

Approved Budget

Current Commitments in the contract

Amount of the budget expended to date.

See an example of a Project Managers Report in the CPDP Guide, Appendix , Item N.
CC&P sends this report to Project Managers monthly.
The Project Manager can access job cost invoices by going to the Facilities Services website,
and click on Facilities Information and then on FS Administrative Services /Job Cost.
See also Project Controls and Payments.

Financial Reviews and Reporting


Projects over $5 Million
For projects with a budget greater than $5 million, the Project Manager submits a Project
Status Report (PSR) to the VP Facilities Services and Primary Customer on a monthly basis.
The PSR includes:

a financial status report using the seven budget categories,

a brief summary of project activity, with focus on elements of the project that are significant
milestones or challenges.

Projects under $5 Million


For projects with a budget less than $5 million, the PM prepares a monthly PSR if requested by
the Primary Customer. See Appendix, Item P in the CPDP Guide for an example of a PSR.

Facilities Project Managers Guide

Page 55

Part IV: Project Process Phases


Project Delivery Flow Chart
The Project Delivery Flowchart summarizes the approval process for endowed Cornell capital
construction projects on the Ithaca campus. This chart represents the most common method of
project delivery used by Cornell University Design/Bid/Build. Contract College Facilities
has a similar flow chart which can be obtained from their office.
The chart has two basic purposes. (1) to consolidate a very complex process into a simple, one
page format that can be easily understood by any Project Team member or other interested
person that may want to gain a basic understanding of the overall Project Delivery Process. (2)
to provide a concise visual tool for the Project Management Team to manage milestone
activities as well as to provide a list of common tasks that must be accomplished each step of
the way.
The chart shows the general phases of each project Planning, Design and Construction.
Individual steps within each general phase further define the order normally followed by
projects.
The Steps section of the chart indicates the various stages in the sequence of project delivery.
The section of the chart above the steps, describes the various approvals for either funding or
design required for the project by senior university administration, Board of Trustee
committees or the Board of Trustees. Level of approval required is based on the total project
budget.
The section of the charts below the steps describes project milestones for the Project Team,
including the client group.
See the Project Deliver Flow Chart in the CPDP, page 34.

Facilities Project Managers Guide

Page 56

Planning Phase
Goal
The Project Managers goals during the planning phase are to initiate the project properly,
review and understand the clients needs, address options thoroughly, and select the option
that is most feasible.
Deliverables
Project Space Program
Site Selection (new construction only)
Consultant Selection
Project Formulation
Approvals
Client Responsibilities
Define need and project goals
Develop Project Plan (sometimes with the PM)
Identify funding sources
Initiate project
PM Responsibilities
Initiate Project with client
Review and/or help develop Project Plan.
Create project team.
Initiate Project Space Program.
Ensure Site Selection is completed(new construction only) or define existing boundaries
(renovation)
Select Consultant
Decide need for either Concept Study and/or Feasibility Study
Project Formulation
Ensure Primary Customer Approval
Develop Schematic Design PAR and/or Design Development PAR to begin next phase
of the Project Management Process

Facilities Project Managers Guide

Page 57

Steps
Initiate Project
The client may initiate a project with either of the following:
o Ticket through Facilities Services Customer Services
o Request for Services
o Request for Capital Project
o Request for Renovation work
All of the above methods for entering into a project are a device to engage resources for
information and advice about infrastructure and existing space
Review Project Plan
Client and Project Manager review Project Plan. See a Sample Project Plan.
Create Project Team
o Identify all stakeholders that will contribute to program development.
o Identify the Project Team.
o Run team meetings. See PM Toolbox for tips on how to run effective meetings:
Job Meeting Problems
PM Meeting Techniques
Running Job Meetings
Create Project Space Program
o Define programming needs with the Core Team.
o Create Space Program. New building and building addition projects always start
with a Space Program. Initially, it begins as a simple list of space types (e.g. faculty
office, class room) and floor area. The Program is developed over time to include a
complete description of each space. The description includes area, finishes,
adjacencies to other spaces, environmental and infrastructure requirements, and
furnishings to be provided by the contractor.
o Resources for developing a space program may include:
Search Facilities Services Web Sites
Find Information About Your Facility
Document Archive
Project Managers Environmental Checklist
o For a restoration project, define the project boundaries.

Facilities Project Managers Guide

Page 58

Site Selection (new construction only)


o The Project Manager should contact the University Planning Office and the
University Architect as soon as he or she is aware of a project of significant size.
o Project Team, University Planner and University Architect develop context study in
which the question how does this project fit with the rest of the neighborhood and
surrounding area? is addressed.
o Site selection options are explored and narrowed to the preferred site. Criteria for
selecting the site must be developed with the University Planning Office and
University Architect.
o It takes a few months to complete the Site Development Guidelines (formely called
Site Criteria). The University Planning Office will review the Site Development
Guidelines (formely called Site Criteria) with the project team, stakeholders, and
the Campus Planning Committee.
o Once a preferred site has been identified, the University Planning Office and the
Project Team will develop the Site Development Guidelines (formely called Site
Criteria). (See CPDP, Appendix C).
o For both site selection and criteria the UP presents to CF&PC and B&P for approval.
Consultant Selection
o The established University Consultant Selection process will be followed. This effort
is led by the chair of the selection team.
Decide need for either Concept Study and/or Feasibility Study
The Project Plan usually leads to a Feasibility Study (see sample Feasibility Study) or a
Concept Study.
o Both studies are conducted by a consultant to determine if the project is possible
within a pre-defined budget or other program expectation.
o A Concept Study looks in more detail at options for the deliverables listed below
and produces a plan that can be reviewed by the customer and University. A
Feasibility Study generates a possible solution to that space need with associated
dollar amount. It generally has a program study. The feasibility study asks: I
know I need the space, how do I get the space?
o Upon the completion of this phase and after the required approvals are obtained, the
preferred option will then proceed into design.

Facilities Project Managers Guide

Page 59

Both the Concept Study and the Feasibility Study take into account the following:
PROGRAM

SCOPE

STAKEHOLDER

Codes and regulations

Federal, state,
municipal,

ECOS, EH&S,
Maintenance
Management (ADA
compliance) local code
officials

Site or location

Site Selection

University Planner

Building context and existing


campus fabric

Context Study

University Architect

Building technology

Lab? Office?

CIT

Cost

See budget section

Utilities, O&M, Client

Project Formulation
o Develop conceptual budgets and timelines.
o Consider the various project delivery methods for design and construction.
o Funding sources should be identified by the primary customer.
o Known risks should be identified for budget and schedule impacts.
o Narrow possible options that meet stated program requirements.
o Project Manager prepares PAR for Schematic Design Phase which includes an
overall context, concept and scope of the project.
Primary Customer Approval
o Select one concept for development
o Approve and align program and conceptual budget
o Finalize site selection.
o Develop Site Development Guidelines (formely called Site Criteria).
o Agree on the project delivery method for design and construction.
o Identify known risks to primary customer.

Facilities Project Managers Guide

Page 60

Planning Phase Approval


With these approvals, the schematic design phase can begin.

Approve site selection


Authorize funding if >$5M

EXECUTIVE
COMMITTEE OR
FULL BOARD

Review A/E Selection


Approve Project Plan
Approve site selection
Approve Site Development
Guidelines (formely called
Site Criteria)

B&P

CF&PC

Facilities Project Managers Guide

Approve Concept Par


Authorize PAR

Authorize site selection


Approve Site Development
Guidelines (formely called
Site Criteria)
Authorize SD
Authorize project plan:
budget, scope, schedule and
funding

Page 61

Design Phases
Schematic Design (SD)
The Schematic Design:

leads to clarification of the project program

explores of the most promising alternative design solutions

provides a reliable basis for analyzing the project cost.

The result of the Schematic Design is a clearly defined, feasible concept that can be presented
in a form that achieves the Primary Customers understanding and acceptance.
Deliverables
o 100% Schematic Design documents (See CPDP, Appendix, Item F, Schedule G,
Documents Submittal Requirements ) from the Design Consultant that include, but
are not limited to:
Site Plan , Including connection to central Utilities, if required.
Typical floor pllans for each level
All typical elevations
Two or more sections
An outline specification
Other characteristics in comparison to the program
A preliminary cost estimate (may require an independent additional
estimate)
Renderings, models or other drawings needed adequately present the
concept, including sustainable design charrette and narrative which is
required during this phase for all capital projects.
o Confirmed budget
o Confirmed schedule
o Commissioning Strategy (SeePM Toolbox training Quality Control, Inspections and
Commissioning.)
o Identification of local, state and federal approvals needed and strategies to obtain
them.
o Plan for occupant relocation, swing space, and move timing
o Schematic Design Package review and approval. Refer to Schedule G, Document
Submittal Requirements.
o Engagement of Facilities Inventory Group.
o PAR for Design Development Phase
Facilities Project Managers Guide

Page 62

Process
o Develop schematic design budget and ensure project budget confirmation
(including adjustments to either the program or budget to achieve alignment).
o Project schedule confirmation.
o Project Team must coordinate with stakeholders (such as PDC Engineering, Utilities,
Contracts, Cornell Police, CIT, Maintenance Management, EH&S, ECOS, etc.)
o Review for ADA Access Compliance
o Keep an accurate review of partners consulted on access review.
o Conversations with architects and Cornell University staff on
access elements.
o Optional pre-construction services of a qualified contractor or construction manager.
o Commissioning strategy development, depending on project scope a 3rd party
commissioning agent should be brought in at this time if not sooner. SeePM Toolbox
training Quality Control, Inspections and Commissioning.
o Form Municipal Approvals Team which will identify local, state and federal
approvals needed and strategies to obtain them. Be aware of municipal calendar.
o Begin planning for occupant relocation, swing space and move timing.
o Review and approve the Schematic Design package. (See Schedule G.) Obtain
Primary Customer and Stakeholder approvals (including design review by PDC
Engineering or Facilities Management).
o Project team must engage Facilities Inventory Group for assignment of facility code
(new buildings) and for room numbering (all new buildings and renovations that
move partition walls). See For Project Managers: When does a new building or
renovation get added to the Facilities Inventory?
See PMT Training Project Archiving and Project Documentation.
For document archives, go to the FIG archiving page.
o Prepare PAR for Design Development Phase.

Facilities Project Managers Guide

Page 63

Schematic Design Approvals


With these approvals, the project can move to the Design Development Phase.
EXECUTIVE

Authorize funding if > $5M

COMMITTEE OR
FULL BOARD
B&P
CF&PC

Approve Schematic Design


Authorize DD if >$5M
Validate budget, scope, schedule, funding
Approve SD
Authorize DD

Design Development (DD)


This phase develops the scope of work previously approved in the Schematic Design Phase.
The primary purpose is to define and describe all important aspects of the project so all that
remains after the completion of this phase is the creation of construction contract documents.
Deliverables
100% Design Development documents from the Design Consultant that include all
documents from SD, documentation defined in the contracts Schedule G (Appendix
Item F in CPDP) modified as required to meet the project requirements, as well as:
o Fully developed floor plans, interior and exterior elevations, reflected ceiling plans,
wall and building sections, and key details
o Basic mechanical, electrical, plumbing and fire protection systems are accurately
defined, if not fully drawn.
Process
o Project Team must continue to coordinate with stakeholders such as PDC
Engineering, Utilities, Contracts, Cornell Police, CIT, Maintenance Management,
EH&S, ECOS, etc.
o Validate project schedule, including definition of long-lead items.
o Validate and reconcile project budget with DD estimate. This may require an
additional independent estimate.
o Review and get approvals for DD package from Core Team and Stakeholders
(including design review by PDC Engineering or Facilities Management and
customer agent). Obtain sign-off on plans.
o Begin dialogue and agreements regarding front ends General Conditions and
General Requirements for the bid package by our contracts office and the consultant.

Facilities Project Managers Guide

Page 64

o Prepare PAR for Construction Contract Document and Bid Phase. (See CPDP,
Appendix Item B)

Design Development Approvals


With these approvals, the project can move to the Construction Phase.
EXECUTIVE
COMMITTEE OR
FULL BOARD
CF&PC

Authorize funding if > $5M

Validate budget, scope, schedule, funding


Approve DD
Authorize CD

Construction Contract Documents (CD)


This is the final stage of the design process, which finalizes the drawings and specifications for
all components and systems of the project, resulting in construction contract documents used
to solicit bids for the work and construct the project.
Deliverables:
100% Construction Contract Documents. This set of documents fully describes the
project and will be the basis for soliciting bids from the selected contractors. This
documentation is defined in the contracts Schedule G (Appendix Item F in CPDP)
modified as required to meet the project requirements.
Internal review of the documents by University stakeholders is normally done at 50%
and 95% completion for content and final comments.
Process
o Construction Documents Estimate
A Construction Document Estimate that finalizes the project budget is required. All
final adjustments to the program and budget should be completed in anticipation of
bidding the project.
o Validate schedule and budget.
o Construction management plan finalized.
o Review and approve CD package.
o Prepare bid document package, noting any special project requirements such as
accelerated schedule or working on off shifts .
o Prepare DRAFT PAR for Construction Phase awaiting bids.

Facilities Project Managers Guide

Page 65

Note that the PAR requires changes to Operating and Maintenance (O&M)
Costs; these costs should be researched and described within the document.
See PM Toolbox Maintenance Costs.
The key issue is to identify the range of the costs, and which department(s)
will be responsible for assuming them. The analysis should include a
discussion on energy use and life cycle costs.
For energy use range of costs, see PM Toolbox Utilities and Your Project.
Please contact Facilities Management for assistance.
Construction Documents Approvals
With these approvals, the project can move to the Bid Phase.
CF&PC

Authorize Bid Phase

Bid Phase
The bid phase tasks include working closely with the Contracts & Capital Projects Office as
well as Director of Construction Management in selecting preferred, qualified contractors, and
securing bids for the specified work. A construction contract will eventually be negotiated and
awarded to the selected bidder.
Deliverables
Select qualified contractors, including interviews, if deemed necessary.
Process
o Determine whether bid opening will be public or private. (Note: State-funded
projects require that certain procedures be followed regarding bidders, public bid
opening, payment of prevailing wages, etc.)
o Determine bidding period and schedule pre-bid meeting with all invited bidders to
answer any remaining questions about the work. Issue addendum to the bid
documents, if necessary. (See CPDP, Appendix, Item G)
o Select lowest responsive responsible bid, after consideration of all other factors.
o Finalize PAR for Construction Phase. Note the O&M section and expected utility
costs need to be complete at this stage.
o Contract preparation and execution.
o See PM Toolbox training
Bidding a Project.
Managing Contracts
General Conditions and Requirements
Negotiations for Project Managers
Facilities Project Managers Guide

Page 66

Bid Phase Approvals


With these approvals, the project can move to the Construction Phase.
EXECUTIVE

Authorize construction if > $5M

COMMITTEE OR
FULL BOARD
B&P
CF&PC

Authorize construction if > $5M


Authorize construction if > $500K

Construction Phase
The primary objective is to build the specified project within the agreed-upon schedule and
budget and with a high level of quality.
Site Preparation / Mobilization
During the early phase of construction, a the Construction Manager will establish will
establish with the contractor:
o administrative procedures
o progress meeting schedules
o progress update requirements
o schedule controls
o methods to expedite the required approvals of certain documents provided by the
design consultants.
Permits must be obtained by the contractor, and coordination of building trades and site
logistics must be determined and agreed to by the Construction Manager.
Construction
Deliverables
Required submissions are listed in the General Conditions and General Requirements
sections of the contract which can be found in the CPDP, Appendix H.
o The Construction management point of contact information plan as described in the
General Requirements, includes a site-specific Safety Plan, Affirmative Action
requirements for the general contractor (GC), etc.
Cornell Construction Contract Environmental General Requirements
o Manage and limit scope creep.

Facilities Project Managers Guide

Page 67

o Keep schedule and budget current and communicated to the Project Manager and
Construction Manager.
o Process any Change Orders in a timely manner.
Reminder: If there are changes in the design that impact the floor plan,
Facilities Inventory needs to be notified to re-assign official room
numbers. It could be costly to correct errors after design documents
have been published.
o Pay contractors promptly.
o Assure quality of work.
o Review for ADA Access Compliance
Keep an accurate review of partners consulted on access review.
Conversations with architects and Cornell University staff on access elements.
o Contractor must communicate clearly with the Construction Manager, especially on
items that pose a risk to either the budget or schedule.
o Core Team and contractor must finalize move-in plan, and date of occupancy.
o Punch list
Close-out/Move-in
This phase facilitates the occupancy and turnover of the completed and commissioned project
to the Primary Customer.
Deliverables
Delivery of the completed project to the occupants.
Process
o See CPDP Guide, Appendix, Item K for the suggested close-out procedures.
o Coordinate with Primary Customer on CIT, furnishings and move-in .
o Punch list items completed promptly.
o Before occupancy, initiate the process of obtaining measured drawings through
Facilities Inventory see When does a new bulding or renovation get added to the
Facilities Inventory? (budget line 02.06.03), and site conditions CAD mapping
through PDC Civil Section (budget line 02.06.01).
o Obtain Certificate of Occupancy.
o Archiving: Sort project materials for dispensation to one of these:
the University Archives (See FIG website)
Facilities Document Records Center
Primary Customer.

Facilities Project Managers Guide

Page 68

o See CPDP, Appendix Item I. The master list defines those records needed for the
archives. All other records belong in the Records Center with copies sent to the
Primary Customer as needed.
o Meet with the PDC archivist to turn over project records to turn over project records,
including record drawings and develop a plan for any outstanding documents. See
Archiving Questionnaire for this meeting. Other useful links include filing
protocol worksheet and document archiving instructions.
o Complete commissioning activities, including generation of final building
commissioning report and owner training in building operations by the Design
consultant and Contractor.
o EH&S Hood / Safety Inspections
o Fire alarm testing - EH&S
o Post-occupancy survey/analysis if desired
o Resolution of any claims
o Obtain contractual close-out documentation and make final payment to the
Contractor.
o Financial close-out of project promptly after completion of all work and payment of
all project related expenses.
Obstacles to Closing a Project Account
1. Open RFS or Purchase Order against a project
2. Legal action or claim (see Risk Management)
3. Lack of final paperwork from the contractor. (for example, .e., record
drawings/asbuilts, required O&M manuals & warranties.)
4. Open contract or commitment.
Close-out phase lasts through the end of contract warranty periods.
Resources
PM Toolbox training Closing out a Project which provides checklists for close-out for
the following areas:
o Project Close- out: Construction Site
o Contract Close-out and Final Payment
o Capital Project Account Closure
o Archiving
Suggested Close-out Procedures in the CPDP Guide, Appendix, Item M.
Final Release in General Conditions Article 12.04, located in the PM Toolbox training
Closing out a Project and the CPDP, Appendix Item H.
Guarantee in General Conditions, Article 14
Facilities Project Managers Guide

Page 69

Consent of Surety of Final Payment in General Conditions, Article 12.04


Record drawings as cited in Owner/Engineer Agreement, p. 13, section 9 and in
Retention of University Records Policy
Complete specifications as cited in Owner/Engineer Agreement, Schedule G,
Document submittal requirements, first item.
Master List of Records for archival storage from all PAR level facilities projects

Facilities Project Managers Guide

Page 70

Risk Management in Project Management


There are three responsibilities the PM assumes in Risk Management of a project:

Assess Financial Risk

Outline Legal Relationships

Oversee Aspects of the Claim Process

Assess Financial Risk


During Design Phase/Bid Process/Bid Analysis: Risk Management and Insurance reviews
financial risk of contractors with a model developed to determine a contractors risk of
bankruptcy. The model is only one indicator among others that are used by Contracts
Management to evaluate risk of contractors.

If the risk is high, Cornell can require a bond from the contractor, which will add to the
cost of the project.

Outline Legal Relationships: Design Phase/Have Clear Contracts


The legal relationship concerning risk is defined in the answers to these two questions:

1) Who is responsible for insuring safety on the site?


2) How are safety roles and issues addressed? (see Claims below)
Risk Management defines these types of relationships with respect to who is responsible
for safety
TYPE OF

WHO HAS

RISK LEVEL

INSURANCE

RELATIONSHIP

RESPONSIBILITY

FOR

COVERAGE

FOR RISK

OPERATIONS-

RISK

SIR
EXPOSURE

Normal construction
process

Contractors

Low

High

Owner-Controlled
Insurance Program or
OCIP

Contractors but Cornell


has financial risk.

High

Low

Cornell as General
Contractor

Cornell

High

Low

State

The PM should understand these relationships. They are defined in the contracts. If the
PM knows the contracts and legal relationships which define the Universitys exposure to
risk, they can better manage the project by determining if the contractor is adhering to
responsibilities defined in the contract.

Facilities Project Managers Guide

Page 71

See the PM Toolbox presentation Risk Management at Cornell University. Slides 15 18


define the insurance requirements relative to the contract, and how to make claims
1)
2)
3)
4)

Major Construction Project General Liability


Contractor Insurance Requirements
A/E Insurance Requirements
Builders Risk

What if contractor is not adhering to safety requirements as stated in the contract?


Set up meeting with contractor. If contractor still not meeting requirements:
o Set up meeting with contractor and Director of Risk Management and Insurance. If
contractor still not meeting requirements:
Set up meeting with contractor and Director of Risk Management and
Insurance where Risk Management will state consequences. If contractor still
not meeting requirements:
Cornell may create a work stoppage, dismiss contractor from site, or
terminate contract (depending on seriousness of noncompliance.) It
is important that the PM brings many people to the table before this
last point is reached, such as EH&S, Director of Construction, etc.
Oversee Aspects of the Claims Process
The claims process is determined by the relationships defined in the contracts. Claims
occur during the Construction Phase.

PM needs to know who to call to start the process.

PM may be asked to provide information about an incident. For this reason, it is important
that the PM keep good notes and meeting minutes. PM may also be called to testify in
court.
Caution: The PM must be concerned with the facts of the case and not
attempt to place blame. Responsibility can only be determined after a full
investigation and after all experts have weighed in regarding an incident.
Contact Legal Counsel and/or Risk Management before giving any
statements.

Facilities Project Managers Guide

Page 72

Three Types of Claims


The PM should be aware of the following claims, and should be prepared to address
them should they arise:
o Workers Compensation
o Liability
o Property
Workers Compensation
PERSON

RELATIONSHIP

CLAIMS PROCESS

INJURED

Cornell Endowed
employee

All Contracts

Cornell Medical Leave


Administration-EH&S link

Cornell State
employee

All Contracts

Covered by state insurance fund

Contractors employee

Normal contract

Contractors insurance

OCIP

OCIP claims process-OCIP


Administrator

See http://prp.ehs.cornell.edu/Acc-Inj/ for endowed employee claims forms.


Liability
RELATIONSHIP

PERSON
RESPONSIBLE FOR

CLAIMS
PROCESS

INJURY

Normal contract

OCIP

Facilities Project Managers Guide

Cornell Employee

Cornell Insurancereport
to Risk Management

Contractor

Contractor reports to his


carrier

Contractor employee is injured


and sues Cornell

May tender back to


ContractorOver-action
Claim

All

Report to OCIP
administrator

Page 73

Property Damage Liability Claims


PROPERTY
OWNER

PERSON

CLAIM PROCESS

RESPONSIBLE

Cornell

Contractor

Cornell files claim or sues


contractor

Contractor

Cornell

Contractor files claim or sues


Cornell

Property
PROPERTY OWNER

COVERAGE

CLAIMS

Cornell

Builders risk

Requires an
understanding of who is
carrying builders risk,
Cornell or contractor

Contract College

Builders risk

SUCF process

Contractor

Contractors property
insurance

Contractors claim
process

Facilities Project Managers Guide

Page 74

Part V: Appendix

Facilities Project Managers Guide

Page 75

Sample Matrix for Project Coordinator (PC) Responsibilities

PC1

PC2

PC3

COMMUNICATION
Work directly with User Groups on logistical issues such as moving,
signage and data jacks.

Communicates with and coordinates day-to-day issues with the


customer contact person, e.g. moves, information exchange, parking,
traffic, EHS, police, fire department/alarm testing, crane schedules,
inspections, COs and TCOs, etc.

Coordinate with Transportation on issues such as parking, coordinating


contractor permits, laydown areas, etc.

Answer public questions on the project with standard responses.


Provide site tours.

Manage non-capital projects and segments of projects with budgets of <


$50k.

PM for projects that are in the range of $50k-250k

PM for projects in the range of 50k-2M

FINANCIAL
Financial Management - Generate reports from database using BRIO,
monitor expenses against budget lines, and maintain spreadsheet of
project expenses. Supervise administrative activities related to the
project (i.e. accounts payable, job cost, status reports).

Issue tickets to the shops and monitor progress. Track ticket costs and
keep PM informed. Highlight deviations from budget estimates.

RESPONSIBILITIES
Coordinate job site safety efforts of EH&S including review of the Safety
Plan and scheduling mock OSHA inspections.

x
x

Manage and enforce site safety plan


Coordinates with CIT - schedule and coordinate activities

x
x

Coordinates with CIT - Secure estimates and manage installation


Coordinate field inspections by PDC Shops and other parties. Monitor
quality of workmanship and materials with the assistance and support of
the Design Consultant and associated PDC Shops to maintain high
standards
Conduct field inspects and punch list conformance inspections.
Facilities Project Managers Guide

x
x
Page 76

PC1

PC2

Supervise and conduct field inspections to assure conformance with


plans and specifications.
Schedule and attend regular job meetings, prepare and distribute
minutes. Work with the PM to prepare meeting agenda.

PC3
x

x
x

Run regular job meetings in absence of PM.


Provide direction at regular job meetings, make immediate decisions
within the authority given by the project manager.
Manage submittal process including tracking submittals & RFI's on
projects

x
x

Manage change orders to agree upon the scope, cost, and schedule
impact of changed conditions. Prepares independent CU cost
estimates. Present rational/justification for approval to the PM.

Approve Change Orders presented by the CM

Coordinates and directs, as authorized by the contract, Contractors


during construction, acts as a single voice for CU to the contractor. PM
is the backup voice. Day-to-day communication is between contractor
and CM.

x
x

Prepare RFPs with direction from the PM.


Independently prepare RFPs within established procedures. Review
terms of contracts with respect to examples.

Manage consultant selection process, negotiate terms of contract.

Manage and direct the activities of A/E consultants. Review contract


compliance and authorize payments.

TECHNICAL SKILLS
Project Scheduling - Builds and maintains project schedule using MS
Project or Primavera from data given by others.

Project Scheduling - Monitors project schedule milestones against


progress.

Project Scheduling - Implements corrective action to keep project on


schedule
Lab furniture and equipment - coordinate purchase, arrange for storage
and transport as requested by the PM.

x
x

Lab furniture and equipment - manage purchasing process, responsible


for inspection prior to turnover to contractor, Responsible for installation
contract.

x
x

Lab furniture and equipment purchasing - review technical standards


Formal Training in construction and contracting practices (TC3 class or
CEE 595)

Build and maintain databases in Access

Independently prepare Power point presentations for project approval


from Sr Administration

Facilities Project Managers Guide

Page 77

PC1
Develop and maintain comprehensive section schedule

Author PARS (Draft)

Maintain section web site and Project web site

Maintain List Serve

Maintain Standards on web

x
x

Manage commissioning process

Facilities Project Managers Guide

PC3

Manage section work schedule by recommending adjustments to staffing


assignments

Perform Web Research for products and services

PC2

Page 78

Sample Project Manager and Construction Manager and Project


Coordinator Duties and Responsibilities
Action

PM

Manage change orders to agree upon the scope, cost, and


schedule impact of changed conditions. Prepares
independent CU cost estimates. Present
rational/justification for approval to the PM.
Approve Change Orders presented by the CM

PC

Coordinates and directs, as authorized by the contract,


Contractors during construction, acts as a single voice for
CU to the contractor. PM is the backup voice. Day-to-day
communication is between contractor and CM.
Work directly with User Groups on scope items and project
development issues. CM and PM negotiate the magnitude
of scope items the CM can and can't commit to during
construction (scope creep). PM and CM to negotiate the
level of cost change issues, either additive or deductive, that
need PM approval before the fact.

CM

Communicates with and coordinates day-to-day issues with


the customer contact person, e.g. moves, information
exchange, parking, traffic, EHS, police, fire
department/alarm testing, crane schedules, inspections,
COs and TCOs, etc.

Reviews schedule for constructability. Monitors progress


against the schedule and keeps PM informed of deviations.
Recommends actions to get back on schedule if needed.
Maintains schedule.

Reviews schedule evaluation and recommendationss from


CM. Advises CM as to correctness of schedule and
evaluation and to jointly develop actions for schedule
compliance corrections.

Monitor output of Contractors; feedback, site productivity, etc

Coordinate efforts of EH&S (Job Site Safety). Work with


EHS to review the Safety Plan, enforces Safety Plan.
Schedules mock OSHA inspection with EHS.

Coordinates the construction efforts of CIT

Coordinates the construction efforts of Cornell Line Crew


(cableing and hookups)

Oversee purchasing (ex: buying furniture) for owner


supplied equipment identified in the PAR as an F&CS
responsibility.
Coordinate arrival of CU purchased equipment. Arrange for
storage and transport to the site as required and requested
by the PM. Responsible for inspection prior to turnover to
contractor. Responsible for installation contract if needed.

Facilities Project Managers Guide

Assist
PM & CM

Page 79

Action

Responsible for installation contract if needed.

PM

PC

Tracking construction costs, telecommunications costs, site


work and other costs that need to be tracked on an as
needed basis against budget costs
Responsible for controlling the use of contingency funds

CM

Issue tickets to the shops and monitor progress. Track ticket


costs and keep PM informed. Highlight deviations from
budget estimates.

Supervise the coordination of administrative activities related


to the project (i.e. accounts payable, job cost, status
reports). CM to track reports as requested by PM.

Develop contracts and subcontracts as needed

Supervise payments for project services, ensure that


expenses are monitored against project budgets.

Supervise and inspect field conditions and progress of work


against project schedule; coordinate and/or act as liaison
among participants to resolve problems or conflicts. Work
with PDC Shops in providing quality inspections

Who can say "NO" from a contractual perspective to the


Contractors? The Contracting Officer

Run the "owners" weekly job meetings. Write the minutes.


PM and CM work together to develop the format of the
meetings.

Prepare space programs, building standards and other


project criteria to guide the work of outside A/E consultants.

Assist PM

Assist
PM

Interview and advise on the selection of A/E consultants for


major design projects.

Assist PM

Assist
PM

Negotiate service agreements with outside A/E consultants.


Prepare contracts.

Assist PM

Assist
PM

Manage and direct the activities of A/E consultants. Review


contract compliance and authorize payments.

Assist PM

Assist
PM

Monitor quality of workmanship and materials with the


assistance and support of the Design Consultant and
associated PDC Shops to maintain high standards.
Coordinate and schedule Shops inspections.

Assist
CM

Assist
CM

Create the CM and PC budget line dollar amount.

Responsible for the project construction documents


review/written response process.

Empowered to give field direction changes to the contractor

Assist
CM

Assist
CM

Facilities Project Managers Guide

Page 80

Ensures frequent contact between the CM and the Contract


Officer. Computer status reports by CM and
Superintendent.

Establish criteria and measure Team performance

Responsible for the monthly/trustee report

Assist PM

Assist
PM

Review and approve progress payments

Approves

Approves

Assist
PM & CM

Authorized to release retainage

Approves

Approves

Provides feedback on contractors/AE performance

X (AE)

X
(Contractor)

Speaks to the news media

Assist
PM & CM

Coordinate parking issues, such as coordinating contractor


permits and how does PDC arrange for laydown areas, etc.

Assist
PM & CM

Recommend a scope or time increase during construction

Authority to make no cost/no time field related changes?


PM & CM to discuss & negotiate

At least once a month review of the project with the PM, CM,
University Architect, University Engineer, Director of
Construction Management, Director of Facilities and Director
for Contracts Administration

Bid Attendance. Who determines how money shortages will


be met, whether from contingency or elsewhere? Who
determines which alternates will be accepted? The PM has
authority up to 25%; The Director of PDC has authority
greater than 25%. If continugencybring to attention of
Director of PDC and VP for Facilities

Who settles insurance issues? Risk Management and


Contract Officer
Who is empowered to settle claims?
Administration

Director for Contracts

Authority to take risks with University resources? University


Architect, University Engineer, and Director of PDC
NOTE: The PM may delegrate authority for any of the above to the CM, and may ask that the CM
perform any of the above. In such cases, the PM remains responsible for those portions of the
project listed above.

Facilities Project Managers Guide

Page 81

Sample Role Agreement


RESPONSIBILITY GUIDELINES FOR CONSTRUCTION
ACTION

PM

Manage change orders to agree upon the scope, cost, and


schedule impact of changed conditions. Prepares
independent CU cost estimates. Presents
rational/justification for approval to the PM

CM

Work directly with the User Groups on scope items and


project development issues. CM and PM negotiate the
magnitude of scope items the CM can and cannot commit
to during construction. PM and CM negotiate the level of
cost change issues, either additive or deductive that need
PM approval before the fact.

Reviews schedule for constructability. Monitors progress


against the schedule and keeps PM informed of deviations.
Recommends actions to get back on schedule and
maintains schedule

Coordinates efforts of EH&S for job site safety. Work with


EHS to review Safety Plan, enforces Safety Plan.
Schedules mock OSHA inspection with EHS.

Coordinates the construction effort of CIT

X
X

Coordinate arrival of CU purchased equipment. Arrange for


storage and transport to site as required and requested by
the PM. Responsible for inspection prior to turnover to
contractor. Responsible for installation contract if needed.

Tracking construction costs, telecommunication costs and


other costs that need to be tracked against budget costs

Responsible for controlling the use of contingency funds

Issue tickets to the shops and monitor progress. Track


ticket costs and keep PM informed. Highlight deviations
from budget estimates.

Supervise the coordination of administrative activities


related to the project (i.e. accounts payable, job cost, status
reports). CM to track reports as requested by PM.

Supervise and inspect field conditions and progress of work


against project schedule: coordinate and or act as liaison
among participants to resolve problems or conflicts

Facilities Project Managers Guide

PC

Communicates with and coordinates day-to-day issues with


the customer contact person, e.g. moves, information
exchange, parking, traffic, EHS, police, fire department
alarm testing, crane schedules, inspections, COs and
TCOs

Run the owners weekly job meetings and write minutes.

CM

PC
X

Approve Change Orders presented by the CM

Oversee purchasing for owner supplied equipment such as


Cage Wash and racks.

PM

X
Page 82

ACTION

Manage and direct the activities of the A/E consultants.


Review contract compliance and authorize payment

PM

CM

Coordinate and schedule Shops inspections

X
X
X

Coordinate parking issues, site layout, staging areas


Recommend scope or time increases during construction

X
X

Authority to make no cost/no time field related changes

X
X

Coordinate for A/E meetings or attendance


Responsible for Budget and cost compliance
Responsible for the coordination and recommendations for
independent lab testing

Facilities Project Managers Guide

Review progress payments for approval and payment


Approve progress payments

PC

Empowered to give field direction changes to contractor


Responsible for monthly trustee report

CM

PC
X

Monitor quality of workmanship and materials with the


assistance of the Design Consultant and associated PDC
Shops to maintain high standards

Responsible for project construction documents


review/written response process

PM

X
X
X

Page 83

Sample Revised Par


This example of a Revised PAR is a request for additional money to cover an increase in the project's
scope of work.

PROJECT APPROVAL
REQUEST (PAR)
#
BUILDING Q
ELECTRIC SERVICE
CONSTRUCTION
PAR ID #
Project Team

Project Manager: (name)

PDC Shops Representative: (name)

Engineer-in-Charge: (name)

Utilities Representative: (name)

Questions or comments should be directed to the


Facilities Services Project Manager:
(name)
Revised (date)

Facilities Project Managers Guide

Page 84

PROJECT APPROVAL REQUEST


==================================================================
This PAR requests an increase in the original authorized amount of $68K (date) to $95k for the
connection of the Office Q electric service to the Utility Departments 13.2kV electric distribution
system. This revised PAR will allow for an increase in electric distribution capacity and reliability to
accommodate a planned facility to be located near the new office building.
==================================================================
1.

Sponsoring Department: Utilities Department

2.

Purpose and Need: The purpose of this project is to add distribution equipment to an existing medium
voltage circuit to allow for the connection of cables to feed the new office building. The need to provide
service to the office building comes from the customers desire for low electric rates and a high level of
reliability.

3.

Scope of Work: The scope of work for this PAR includes the following:

4.

Install a three-way separable tap in manhole 112.

Increase cable capacity from 200 amps to 400 amps.

Increase duct capacity from two-way to three-way. This will allow for a loop circuit plus one spare
duct.

The 13.2kV loop circuit will be completed only when plans for future construction are finalized.

Major Alternatives Considered and Why Rejected:

5.

Have NYSEG provide the electric service to the new office building. This was rejected due to the
customer desire for lower electric rates and higher reliability.

Proposed Schedule: The proposed schedule for this phase is as follows:

Construction

Facilities Project Managers Guide

Approval
Jun (year)

Begin
Jul (year)

Complete
Jan (year)

Page 85

6.

Project Budget: This PAR requests an increase in the original authorized amount of $68K (date) to $95k
for the connection of the Office Q electric service to the Utility Departments 13.2kV electric distribution
system. This revised PAR will allow for an increase in electric distribution capacity and reliability to
accommodate a planned facility to be located near the new office building. The proposed budget for this
PAR is as indicated below:

1.
2.
3.
4.
5.
6.
7.

7.

Category
Construction
Planning & Design Fees
Long-Lead Equipment
Project Support (Shops)
Project Management
CP Admin Fee
Project Contingency
TOTAL

$
$
$

Previously
Authorized
This Request
52,000 $
25,000
- $
- $
- $
5,000 $
2,000
3,000
8,000

68,000 $

27,000

To Date Budget
$
77,000
$
$
$
$
7,000
$
3,000
$
8,000
$

95,000

The project will be funded as follows:


Amount

Primary Account
Number funds will be
provided by

Funds provided by Unit / College

$95,000

Total project expenses ***see below

$95,000
Name

Contact person in unit for funding


issues/questions

(name)

Contact person to authorize transfer of


funds.

(name)

(account #)
Phone

NetID

***Total project expenses must equal the total project budget amount to date as listed on
this PAR.

8.

Change in Maintenance and Operating Costs: Maintenance and Operating costs will slightly increase
when the projects electric distribution equipment is turned over to Utilities.

9.

Mode of Accomplishment: (name) will serve as Project Manager of this project. Construction will be
performed by the PDC Electric Shop on a Time & Material (T&M) basis.

Facilities Project Managers Guide

Page 86

10.

Municipal, State and Federal Discretionary Approvals: This project falls within the municipal jurisdiction
of the Town of Ithaca. There are no related discretionary issues and it is not subject to the State
Environmental Quality Review (SEQR) process.

11.

Potential Issues:

An outage to the (building name) will be required. A generator can be provided during the outage
time frame, if needed, to alleviate disruption to building occupants.

Facilities Project Managers Guide

Page 87

12.

Submitted by:
Project Manager
Planning, Design and Construction

Date

Manager
Electric Purchasing & Energy Distribution

Date

University Engineer
Planning, Design and Construction

Date

Director
Planning, Design and Construction

Date

Director
Utilities and Energy Management

Date

Endorsed by:

Vice President
Facilities Services

Date

Vice President
Planning and Budget

Date

Executive Vice President


Finance and Administration

Date

(date)
Date Prepared
dm

Facilities Project Managers Guide

Page 88

Construction Contingencies Exposures


Budgeted
Amount or
Exposure Category

Low

High

Subcontract(s)

Estimate

Estimate

Value

Regulatory/Variance Code We have


negotiated mitigations to gain the City
Building/Fire department support for the use of
flammable gases, flammable liquids in the
basement and high toxics in BUILDING H

$
600,000

$
750,000

$
-

Contractor Parking We will probably lose


the Hoy South lot.

50,000

Building Skin We expect to encounter


additional costs for integration with building
systems and field implementation issues.

750,000

1,250,000

12,403,845

PDC Shops Q/A Inspections Missing or


incorrect items are typically found during
inspection, especially in the mechanical,
electrical, and plumbing systems.

500,000

600,000

MEP Coordination & Commissioning The


coordination and commissioning process
uncover issues that need to be addressed
similar to the inspection process.

750,000

1,250,000

32,706,609

Furniture Purchase The budget is very tight


for this item.

500,000

1,000,000

2,000,000

Utility Costs During Construction


Contingency may be required to cover rising
costs.

500,000

750,000

1,050,000

NYSERDA The project financial plan includes


$440K of rebates that may not be fully realized
or the program could be eliminated.

220,000

440,000

440,000

Plant Science Tunnel - Addl underpinning,


interior stair change, custom elevator.

300,000

500,000

2,245,866

Space Customization Construction inflation


is eroding our ability to accommodate specific
faculty.

250,000

750,000

Fit-out Construction inflation is eroding our


ability to accommodate a longer schedule
and/or customization of labs.

800,000

1,000,000

4,231,110

$5,170,000

$ 8,340,000

$ 55,077,430

Current GMC Value

$104,235,108

Value of Work in Place

(25,000,000)

Balance To Be Accomplished

$79,235,108

Contingency on balance
Facilities Project Managers Guide

Notes

$7,923,511
Page 89

GMC Systems
Description

Source/Phase

GMC Cost of Work (Current Bidding Climate)


Foundations

Structure
Exterior Enclosure
Roofing
Interior Architectural Development
Specialties & Millwork
Furnishings, Fixtures and Equipment
Vertical Circulation
Plumbing
Fire Protection
HVAC
Electrical
Controls
Sitework and Utilities
FitOut
SubTotal GMC Cost of Work
Design/Estimating Contingency to 100% CDs

Escalation to Bid Date

$
-

C=A*B

E=(A+C)*D

$
-

Total GMC Cost of Work

GMC General Conditions


-

G (from GC
detail)

J=F*I

GL Insurance

L=F*K

Performance Bond

N=F*M

General Conditions Worksheet

H=G/F

Builders Risk

Total GMC General Conditions

P=O/F

GMC Internal Contingency

GMC Fee

Total GMC
Facilities Project Managers Guide

$
$
$
$

O
R=(F+O)*Q
T=(F+O+R)*S
U=F+O+R+T
Page 90

GMC Cost of Work (Current Bidding Climate)


Section

Description

Division 1

General Requirements

Division 2

Existing Conditions

Division 3

Concrete

Division 4

Masonry

Division 5

Metals

Division 6

Wood & Plastics

Division 7

Thermal & Moisture

Division 8

Openings

Division 9

Finishes

Division 10

Specialties

Division 11

Equipment

Division 12

Furnishings

Division 13

Special Construction

Division 14

Conveying Equipment

Division 21

Fire Suppression

Division 22

Plumbing

Division 23

HVAC

Division 25

Integrated Automation

Division 26

Electrical

Division 27

Communications

Division 28

Electronic Safety and Security

Division 31

Earthwork

Division 32

Exterior Improvements

Division 33

Utilities

Division 34

Transportation

Division 35

Waterway and Marine Construction

Division 40

Process Integration

Division 41
Division 42

Material Processing and Handling Equip.


Process Heating, Cooling & Drying
Equip.

Division 43

Process gas and Liquid handling Equip.

Division 44

Pollution Control Equipment

Division 45

Industry-Specific Mfgr. Equipment

Division 48

Electrical Power Generation


SubTotal GMC Cost of Work

Facilities Project Managers Guide

Source/Phase
$
-

$
-

A
Page 91

Design/Estimating Contingency to
100% CDs

Escalation to Bid Date

Total GMC Cost of Work

$
-

C=A*B

$
-

E=(A+C)*D
F

GMC General Conditions


General Conditions Worksheet

$
-

G (from GC
detail)

Builders Risk

J=F*I

GL Insurance

L=F*K

Performance Bond

N=F*M

Total GMC General Conditions

P
=
O
/
F

$
-

GMC Internal Contingency

$
-

R=(F+O)*Q

GMC Fee

$
-

T=(F+O+R)*S

$
-

U=F+O+R+T

Total GMC

Facilities Project Managers Guide

Page 92

GMC GCs
Description

Quantity

Unit

Unit Price

Total

On Site Staff
Project Executive

$
-

weeks
Reimbursables

Senior Project Manager

weeks
weeks

Reimbursables
Project Manager

weeks
weeks

Reimbursables
Superintendent

weeks
weeks

Reimbursables
Project Engineer

weeks
weeks

Reimbursables
Accountant/Cost Eng

weeks
weeks

Reimbursables
Project Safety Manager

weeks
weeks

Reimbursables
Administrative Assistant

weeks
weeks

Reimbursables

weeks
On Site Staff
SubTotal

$
-

Off Site Staff


Project Executive

$
-

weeks
Reimbursables

Project Scheduler Mngr

weeks
weeks

Reimbursables
Project Accountant

weeks
weeks

Reimbursables
Computer Support

weeks
weeks

Reimbursables

weeks
Off Site Staff
SubTotal

Facilities Project Managers Guide

$
-

Page 93

Field Office Expenses


Extra Plan Copies

sets

Office Supplies

lump sum

Telephone, Data

month

Office Trailers

month

Trailer Utilities

month

Trailer Furniture & Equipment

lump sum

$
-

Field Office
Expenses SubTotal

$
-

Professional Expenses
Stormwater Plan

lump sum

Licensed Surveyor

lump sum

$
-

Temporary Utilities
Temporary Electric

lump sum

Temporary Water and


Sewer

lump sum

Temporary Heating
Equipment

lump sum

Fuel for Temporary


Heating

lump sum
Professional
Expenses SubTotal

$
-

Construction Site
Fire / Safety

lump sum

Winter Protection

lump sum

General Hoisting

lump sum

Portable Restrooms

month

Trash Removal

lump sum

Protect Trees to
Remain

lump sum

Pump Water

lump sum

Snow Removal

lump sum

Storage Trailer

month

Temporary Fencing

linear foot

Wash Glass

square foot

Facilities Project Managers Guide

$
-

Page 94

Protect Floors

square foot

Final Cleaning

lump sum

Maintain Traffic / Street


Clean

lump sum

Trucking

lump sum
Construction Site
SubTotal

$
-

Total GMC General


Conditions

$
-

NOTES: Reimbursable expenses include transportation, lodging, meals for the individual listed.
List all other general conditions expenses as applicable.

Facilities Project Managers Guide

Page 95

Sample Budget Sheet


$90 Million Dollar Project
GSF:

193,400

NSF/GSF

NSF:

113,410

58.64%

DESCRIPTION

$
90,000,000
$
-

Project
Budget

CONSTRUCTI0N

Building Construction

62,000,000

Site Work (Utl, Parking, etc)

2,900,000

Furnishings, Tele/Data & Equipment

2,400,000

Munincipal Approvals (Bldg permit, Site Plan,


SEQR)

485,000

Construction Contingency

6,730,000

Total Construction Budget

$74,515,000

PROFESSIONAL FEES

Design Fees

Environmental & Safety Consultants (EIS)

8,300,000

0.133871

1,560,000

Pre-construction Services

750,000

Professional Fees Contingency

475,000

Total Professional Fees

530,500.00

$11,085,000

0.148762

OTHER COSTS

Design Review & Project Supervision

Project, Enviro, Contract & Construction Mgmt

500,000
2,500,000

Commissioning & Q/A

500,000

General Expenses

500,000

Other Costs Contingency

400,000

4,000,000

$ 4,400,000

Total Other Costs

0.059049

CONTINGENCY

Construction

6,730,000

Professional Fees

475,000

Other Costs

400,000

Total Contingency

Facilities Project Managers Guide

$ 7,605,000

0.0845

Page 96

PROJECT BUDGET SUMMARY

CONSTRUCTION

PROFESSIONAL FEES

74,515,000
11,085,000

OTHER COSTS

4,400,000

PROJECT TOTAL

$90,000,000

$'s/GSF

Bldg Cost

290

$ 56,086,073

300

$ 58,020,075

310

$ 59,954,078

320

$ 61,888,080

330

$ 63,822,083

340

$ 65,756,085

350

$ 67,690,088

360

$ 69,624,090

370

$ 71,558,093

380

$ 73,492,095

390

$ 75,426,098

Facilities Project Managers Guide

Page 97

Sample Budget: Building Cost


Bldg GSF:

230,000

Bldg/Proj=70.9%

$'s/GSF

Bldg Cost

Proj Cost

290

$ 66,700,000

300

70.91%

94,058,354

53000000

69,000,000

97,301,745

290000

310

71,300,000

100,545,137

320

73,600,000

103,788,528

330

75,900,000

107,031,920

340

78,200,000

110,275,311

350

80,500,000

113,518,703

360

82,800,000

116,762,094

370

85,100,000

120,005,486

380

87,400,000

123,248,877

390

$ 89,700,000

O&M Item

Cost/GSF

Annualized Cost

Bldg Care

182.7586

Realistic
Target

126,492,269

BUILDING H O&M Model

1.50

345,000

Routine & Preventive Maint

1.50

345,000

Planned Maint @1.5% of


construction

4.95

1,138,500

7.50
$
15.45

1,725,000
$
3,553,500

Utilities

Facilities Project Managers Guide

Page 98

Sample Budget : $110 Million

ITEM

#REF!
#REF!
DESCRIPTION

01.

CONSTRUCTI0N

Area GSF:
Area NSF:
Current
Budget

250,037
131,767
REMARKS

GMP

$
74,816,000

BUILDING H,
tunnel to
PlantSci and
landscape

Cost of Work (Trades-All)

64,000,000

54,400,000.00

GMP-GCs

$6,400,000

GC/CoW =
10.00%, incl
Bldr's Risk Ins

Contractor Contingency

1,600,000

Cntgcy='s 2.5%
CoW

GMP-Fee

2,816,000

Fee ='s 4% of
CoW+GC

01.0102

Athletics Compensation
Projects

2,000,000

01.0103

Asbestos
Removal/Monitoring

250,000

Asbestos Removal

175,000

Asbestos Monitoring

75,000

Municipal Approvals/Fees

474,400

01.0101

01.0900

01.1000

Building Permit

360,000

Initial fee +10%


for extend
beyond 3yrs

Municipal Services-Site
Plan Review

54,400

$1/K of CoW

EIS Review Consultant to


City

60,000

CEQR approval
facilitation

PDC/CIT Construction
Support

590,000

PDC Shops Construction


Support

70,000

Facilities Project Managers Guide

74,816,000

299.22

Page 99

CIT Construction Support

20,000

Q/A, Commissioning, T&B


(PDC Shops)

500,000

Uncommited
Total Construction
02.

78,130,400

115.20

SITE WORK
ID Utilities & other civil
support

02.0100

UFPO/PDC Engr - Site Support

02.0200

Utility Operations

500,000

Utility costs until


occupancy

02.0300

CU Utilities Reloc & Ext

1,725,000

Stm, ChW & PotW - by CU


Utilities Dept

02.0400

NYSE&G Relocation

5,000

NYSEG, Bell Atlantic &


Time Warner

02.0500

Tel/TV/Computer Conduits

02.0600

Project Control

30,000

Detailed site surveys

02.0700

Landscaping

50,000

Tree protection &


relocation of donor trees

02.0800

Parking Tax - 2%

2,200,000

2% of project budget
$110M

02.0801

Replacement Parking

345,000

69 spaces @$5Kea

02.0900

Construction Site Preparation

02.1100

Misc Site Unfpreseen

25,000

Uncommited
$
4,880,000

Total Site Work


03.

FURNISHINGS

03.0100

New Furniture Purchase

$
2,000,000

03.0600

Moving Costs

100,000

03.0700

Telephone & Data

350,000

03.0900

Janitorial Svcs & Supplies

50,000

03.1100

Plaques & Signs

75,000

03.1400

AV Equipment

300,000

Uncommited

04.
04.0100

04.0100

Total Furnishings

$
2,875,000

PROFESSIONAL FEES
A/E Fee (RMP)

#REF!

Feasibility Study
Facilities Project Managers Guide

#REF!
Page 100

04.0200

Schematic Design

#REF!

04.0300

Design Development

#REF!

04.0400

Construction Documents

#REF!

04.0500

Add'l Due To EIS

100,000

04.0600

Construction Administration

#REF!

04.0700

A/E Reimbursables

#REF!

04.0800

Utility Design

195,000

04.0900

Geotechnical Engineer

100,000

05.1500

CM Pre-Construction Fee/Direct
Payment

600,000

05.1600

CM Pre-Construction
Reimbursables

200,000

04.0800

Special Consultants

150,000

04.0800

EIS Consultant

120,000

04.1000

Environmental Engineer

600,000

04.1100

Existing Conditions-Survey

20,000

04.1200

Asbestos Design Services

25,000

04.1300

As-Built Drawings

37,506

Gryphon

Space Inventory dwgs


@ $0.15/gsf

Uncommited
Total Professional Fees
05.

#REF!

OTHER COSTS

05.0100

PDC - Design

$
150,000

UA, Dir PDC & design


reviews

05.0200

PDC - Engr

200,000

UE & PDC design


reviews

05.0300

Contract/Financial Mgmt

100,000

05.0400

Proj Mgmt

825,000

5 yrs full time @$110/hr

825000

05.0400

Asst Proj Mgmt

414,000

5 yrs full time @$60K/yr

414000

05.0401

Proj Coord

412,500

5 yrs full time @$50/hr

412500

05.0402

Constr Mgmt

427,500

3 yrs full time @ $90/hr

427500

05.0402

Environmental Proj Mgmt

150,000

05.0500

Travel & Subsistence

150,000

05.0600

Reproduction & Printing


Facilities Project Managers Guide

Page 101

25,000
05.0700

Photography

10,000

05.0800

Communications

10,000

05.0900

Publicity

30,000

05.1000

Testing Services

150,000

05.2000

Job Office Site

20,000

Uncommited
$
3,074,000

Total Other Costs


06.

CONCEPTUAL COSTS

06.0100

A/E Fees

$
38,000

06.0200

Other Costs

6,000

Preplanning Phase
$
44,000

Total Conceptual Costs


99.

Actual costs - ASTI


Space Assessment &

CONTINGENCY

Target %

99.01

Construction

$
7,813,040

10%

99.02

Site Work

488,000

10%

99.03

Furnishings

287,500

10%

99.04

Professional Fees

#REF!

2.50%

99.05

Other Costs

184,440

6%

99.06

Conceptual Costs

Completed

Total Contingency

#REF!

PROJECT BUDGET
SUMMARY

01.

CONSTRUCTION

$
78,130,400

02.

SITE WORK

4,880,000

03.

FURNISHINGS

2,875,000

04.

PROFESSIONAL FEES

#REF!

05.

OTHER COSTS

3,074,000

Facilities Project Managers Guide

Page 102

06.

CONCEPTUAL COSTS

44,000

99.

CONTINGENCY

#REF!

PROJECT TOTAL

#REF!

Facilities Project Managers Guide

#REF!

Page 103

Sample Budget: $154 vs. $140 Million


Area GSF:
Area NSF:

ITEM

DESCRIPTION

01.

01.0101

Cost of Work (Trades-All)

78,834,992

Asbestos Removal/Monitoring

02.

96,345,309

92,000,000

GMC @ $382
vs $371/GSF

REMARKS

3,500,000

2,000,000

250,000

250,000

175,000

175,000

Asbestos Monitoring

75,000

75,000

Municipal Approvals/Fees

BUILDING H, tunnel
to Building I and
landscape

75,440,000

Asbestos Removal

562,575

540,930

Building Permit

402,060

384,744

$6/K of adjusted CoW

Municipal Services-Site Plan Review

100,515

96,186

$1.50/K of adjusted
CoW

EIS Review Consultant to City

60,000

60,000

CEQR approval
facilitation

PDC/CIT Construction Support

590,000

1,090,000

Construction Support

70,000

70,000

Construction Support

20,000

20,000

Q/A, Commissioning, T&B

500,000

1,000,000

200,000

Construction Testing Services


Total Construction

ITEM

$140M Budget

01.0103

01.1100

$154M Budget

GMC

Athletics Compensation Projects

01.1000

247,978
130,189

CONSTRUCTI0N

01.0102

01.0900

251,057
132,135

DESCRIPTION

200,000

$ 101,447,884

$154M Budget

$140M Budget

Independent Testing
Agency

96,080,930
REMARKS

SITE WORK

02.0100

Engr - Site Support

$
25,000

$
25,000

ID Utilities & other civil


support

02.0200

Utility Operations

500,000

500,000

Utility costs until


occupancy

Facilities Project Managers Guide

Page 104

02030.0

CU Utilities Reloc & Ext

500,000

2,000,000

Stm, ChW & PotW by CU Utilities Dept

02.0400

Non-CU Utl Relocation

5,000

5,000

NYSEG, various
company names

02.0500

Connection to HiVolt

50,000

50,000

02.0600

Project Control

30,000

Detailed site surveys


Tree protection &
relocation of donor
trees

02.0700

Landscaping

50,000

02.0700

Job Office Site

20,000

02.0801

Replacement Parking

414,000

414,000

Total Site Work

ITEM
03.

20,000

DESCRIPTION

1,594,000

$154M Budget

69 spaces @$6Kea or
reduce and pave
something

3,014,000

$140M Budget

REMARKS

FURNISHINGS FF&E

New Furniture Purchase

$
2,000,000

$
2,000,000

~$4K/person, expl
recyclers

03.0300

Growth Chambers Equipment

$
6,000,000

$
3,210,000

Growth Chambers &


other unique unshared
equip.

03.0400

Vivarium Equipment

$
2,050,000

$
1,100,000

Mouse racks

03.0600

Moving Costs

100,000

100,000

03.0700

Telephone & Data

750,000

750,000

Based on discussions
w/ CIT Engr

03.0800

Security System Equipment

350,000

350,000

Allowance based on
previous

03.0900

Janitorial Svcs & Supplies

50,000

50,000

Allowance based on
previous

03.1100

Plaques & Signs

75,000

75,000

Allowance based on
previous

03.1400

AV Equipment

500,000

500,000

Allowance, need
program and design

03.0100

Uncommited
Total Furnishings
ITEM
04.

DESCRIPTION

11,875,000

$154M Budget

8,135,000

$140M Budget

REMARKS

PROFESSIONAL FEES

04.0100

A/E Fee

17,325,000

14,226,019

04.0100

Feasibility Study

$
750,000

$
750,000

04.0200

Schematic thru Construction Admin

15,675,000

11,960,000

Facilities Project Managers Guide

16.5% vs 13% of
GMC

Page 105

04.0300

Record Drawings

50,000

04.0400

Pre-guarantee Expiration Inspection

20,000

04.0500

Add'l Due To EIS

100,000

Excess Liability Insurance

446,019

3.73%

04.0700

A/E Reimbursables

900,000

900,000

04.0800

Utility Design

50,000

100,000

04.0900

Geotechnical Engineer

100,000

05.1500

CM Pre-Construction Fee/Direct
Payment

550,000

550,000

05.1600

CM Pre-Construction Reimbursables

250,000

04.0800

Special Consultants

150,000

150,000

04.0800

EIS Consultant to Faciltate Municipal


Approvals

120,000

04.1000

Environmental Engineer

600,000

400,000

EIS, wind tunnel,


chemical analysis

04.1100

Existing Conditions-Survey

20,000

20,000

Interface with existing


buildings

04.1200

Asbestos Design Services

25,000

25,000

05.0700

Photographer

10,000

10,000

Fly Overs, Visual


Simulations, etc.
Space Inventory &
Archiving dwgs @
$0.35/gsf

04.1300

In A/E Fee

37,659

86,792

Total Professional Fees

ITEM

DESCRIPTION

$154M Budget

Per Agreement

Safety, LEEDs, etc.


By Proj Team

Archiving and Inventory Services

19,237,659

Stm, ChW & PotW by CU Utilities Dept

15,567,811

$140M Budget

REMARKS

05.

OTHER COSTS

05.0100

Project Executives

$
150,000

$
150,000

Dir PDC, UA

05.0200

Engr

600,000

400,000

UE, Proj Dir & PDC


design reviews

05.0300

Contract/Financial Mgmt

100,000

100,000

05.0400

Proj Mgmt

825,000

670,000

$'s ToDate, 2 yrs full


time, 2 yrs half time
@$x/hr

05.0400

Prgm Mgmt

414,000

414,000

5 yrs full time @DPE

05.0400

Asst Proj Mgmt

594,000

475,200

4 yrs full time @$x/yr

05.0401

Construction Admin Asst

412,500

68,112

2.5 yrs full time


@$x/hr

05.0402

Constr Mgmt
Facilities Project Managers Guide

2.5 yrs full time


Page 106

855,000

427,500

@$x/hr
Technical Review and
Site Inspections

05.0402

Environmental Proj Mgmt

150,000

50,000

05.0500

Travel & Subsistence

200,000

150,000

05.0600

Reproduction & Printing

25,000

25,000

05.0700

Photography

10,000

10,000

05.0800

Communications

10,000

10,000

05.0900

Publicity

30,000

30,000

Total Other Costs

ITEM
06.

DESCRIPTION

4,375,500

$154M Budget

2,979,812

$140M Budget

CONCEPTUAL COSTS

REMARKS

Report

06.0100

A/E Fees

$
34,584

$
34,584

Actual costs - Space


Assessment &

06.0200

Other Costs

12,047

12,047

(company name)

$
46,631

Total Conceptual Costs

ITEM
99.

DESCRIPTION

$
46,631

$154M Budget

$140M Budget

REMARKS

CONTINGENCY

Target %

99.01

Construction

$
10,144,788

99.02

Site Work

159,400

301,400

10%

99.03

Furnishings

1,187,500

813,500

10%

99.04

Professional Fees

961,883

778,391

5.00%

99.05

Other Costs

262,530

178,789

6%

99.06

Conceptual Costs

Completed

Total Contingency

ITEM

DESCRIPTION

12,716,101

$154M Budget

$
9,608,093

10%

11,680,172

$140M Budget

REMARKS

PROJECT BUDGET SUMMARY


01.

CONSTRUCTION

$
101,447,884

$
96,080,930

02.

SITE WORK

1,594,000

3,014,000

03.

FURNISHINGS
Facilities Project Managers Guide

Page 107

11,875,000

8,135,000

04.

PROFESSIONAL FEES

19,237,659

15,567,811

05.

OTHER COSTS

4,375,500

2,979,812

06.

CONCEPTUAL COSTS

46,631

46,631

99.

CONTINGENCY

12,716,101

11,680,172

PROJECT SubTOTAL

$ 151,292,775

$ 137,504,357

2% Parking Tax

3,025,855

2,750,087

PROJECT TOTAL

154,318,630

140,254,444

Facilities Project Managers Guide

9.19% vs 9.29%

Page 108

Sample Project Plan


PROJECT PLAN
ROUTINE MAINTENANCE
COST STUDY
Project Team
Project Manager:
PDC Shops Representative:
Customer Representative:
IT Representative:
Facilities Customer Service Representative:

Questions or comments should be directed to the


Facilities Services Project Manager:
(name and phone)
(date)

Facilities Project Managers Guide

Page 109

PROJECT PLAN
==================================================================
This Project Plan requests authorization for $75K to fund a Routine Maintenance Cost Study. Associated
PARs may be forthcoming, as the study is expected to provide recommendations requiring additional actions.
==================================================================
1. Sponsoring Department: Facilities Management
2. Purpose and Need:
The purpose of this project is to analyze and investigate routine maintenance cost data. This is needed to
guide planning efforts and assure cost effective maintenance is provided consistent with the University
mission and maintenance goals.
The Cornell University core endowed campus consists of approximately five million square feet of
classrooms, laboratories, offices, athletic facilities, recreation, and other specialty areas. In its mission to lead
excellence in education and research, the University facilities continuously evolve and age, with associated
changes in maintenance requirements. As a result, it has become increasingly difficult to forecast costs for
the routine maintenance portion of the maintenance budget. The maintenance allocation is budgeted in three
major categories: planned, routine (unplanned /breakdown), and preventive maintenance. Gross analysis of
these major budgetary components indicates the requirements for routine maintenance are growing at a
greater rate than the others. Routine Maintenance Costs have more than doubled over the last ten years,
going from approximately $1.5M to $3.5M annually. While it could be predicted that routine maintenance
spending would be up as a result of the aging physical plant and the growth in the planned maintenance
inventory, the exact correlation among these factors is unclear. Analysis of the maintenance costs data is
expected to provide useful guidance to correct the trend or verify appropriateness of the current maintenance
spending.
3. Scope of Work:
The scope of work for this Project Plan includes the following:
o Preliminary investigation of routine maintenance cost information and
development of data plots to establish and verify routine maintenance cost trends in
terms of maintenance categories, and building usage types. Both macro level
(campus) and micro level (building) investigations will be completed.

o Secondary investigation and analysis to suggest correlations between maintenance


costs and applicable building maintenance cost factors: building infrastructure,
building use/function, building system technology, building code, legal factors, as
well as, University policies and business practices.
o Responsive managerial initiative(s) to guide routine maintenance activities for
continued improvement.
o Review the efficacy of the routine maintenance work management process,
including work identified, work planning, work scheduling, work accomplishment,
documentation, analysis and performance.
4. Major Alternatives Considered and Why Rejected:

Facilities Project Managers Guide

Page 110

Do nothing. This was rejected because unscheduled maintenance costs have increased
significantly in recent years and the investigation will provide necessary facilities
managerial information for continuous improvement.

Maintenance Management has considered funding a term position to achieve the goals of
this project but rejected the alternative; because, developing the expertise requires
extended time and a change of career path is likely to occur before significant results are
gleaned.

5. Proposed Schedule: The proposed schedule for the study phase is as follows:
Investigation Phase I
Approval

Begin

Complete

Feb 04

Feb
04

Jun 04

6. Project Budget: This Project Plan requests authorization for $75K to fund a Routine Maintenance Cost
Study. Associated PARs may be forthcoming, as the study is expected to provide recommendations requiring
additional actions. The proposed budget for this Project Plan is as indicated below:
Study Phase
Consultant Fees
$
Project Management
Contract Admin
Miscellaneous
Contingency
Total
$
7. The project will be funded as follows:
Primary Account
Number funds
will be provided
by

Funds provided by
Unit / College
Contact person in
department to
authorize transfer of
funds

Amount
$

8. Change in Maintenance and Operating Costs:


The study is intended to provide insight into causes for trends in increased routine maintenance costs. The
results will be used to identify initiatives that assure effective use of maintenance resources.
9. Mode of Accomplishment:
Facilities Project Managers Guide

Page 111

X Inc. will investigate trends of increasing routine maintenance costs to provide data plots and analytic tools
for the project team. The project team will assist X Inc with gaining access to necessary information,
interpret investigation results, and identify productive initiatives.
10. Potential Issues:
The investigation will rely on data available through the job cost system. Skanska will be given access to
the maintenance cost data.
Outreach to other university databases and facilities information may be required.

Facilities Project Managers Guide

Page 112

12. Submitted by:

Project Manager
Planning, Design, and Construction

Date

, Director
Maintenance Management

Date

Director
Facilities Management

Date

Director
Planning, Design, and Construction

Date

Associate Vice President


Division of Facilities Services

Date

Vice President
Planning and Budget

Date

Vice President
Administration and CFO

Date

Endorsed by:

Date Prepared

Facilities Project Managers Guide

Page 113

Sample Feasibility Study


Executive Summary
The department of x intends to augment its research capabilities at (name of building) by installing two
growth chambers in Room B74. Two used XYZ Company growth chambers have been purchased and
reassembled in the East wing of (name of building). The chambers are approximately 15 years old and
when completed, they will be made operational as part of the departments purchase agreement. To
complete the growth chamber installation, they must be connected to an electric power source, a heat
rejection system, and additional requirements may become evident during design development.
To develop this report Persopn A met with Person B (name of company.), Person C (PDC HVAC/R
Shop), and Person D (PDC Mechanical Design) to review the conditions at the site. We reviewed the
building conditions to establish options for heat rejection Appling a diversity factor to full time
operations, we estimated life cycle energy costs for each of the heat rejection options. Identifying
categorical scope elements, we applied gross cost estimating methods and contacted XYZ Company for
budget cost information to develop a potential range of construction costs.
Infrastructure costs will be sensitive to the design details, selected scope of construction work, and the
existing conditions. In this case, electric power is readily available for connection to the growth
chambers; however, water based heat rejection sources are not readily available. A source for chilled
water requires approximately 500 ft of piping; there is no cooling tower based condenser water loop in
the building. A domestic water source is readily available; however, it is not a feasible long term means
for heat rejection. Based on these observations and associated economic analysis, air cooled condensing
is the most economically feasible means of rejecting heat from the growth chambers. (See Table 1)
Reviewing the decision to purchase new or used equipment, we note economic considerations. Two used
chambers cost $73K; two new units of equivalent capacity cost approximately $260K. Accommodative
infrastructure is necessary for both new and used equipment, as (name of building) is not fully equipped
to support growth chamber operations, the cost to provide the infrastructure is expected to be in a range
of $100K to $160K. Therefore, capital costs for the new vs. used option are in the ranges of $360K to
$420K and $170K to $230K, respectively. Energy requirements are not appreciably different for new
and used equipment. The manufacturer representative indicates the technological advances employed in
the new chambers primarily reduce manufacturing costs. Long term maintenance costs will also be
similar for the used and new equipment; driven by reliability requirements, a comprehensive
maintenance program is recommended for both new and used equipment. Nonetheless, there is a risk
that maintenance costs will be initially higher for the used equipment, but the decision to purchase new
or used equipment is not sensitive to this difference. Therefore, we conclude the used equipment will
have minimum life cycle costs.
In conclusion, modifying the existing equipment to achieve heat rejection via air cooled condensers
results in minimum life cycle costs. To implement this option, new air cooled condensers will be located
on the roof immediately above the growth chambers. XYZ Company will adapt new heat rejection
systems to the existing growth chambers, and install the new equipment in coordination with local
trades. A structural design will also be necessary to place the condensers on the roof, assure structural
integrity, and coordinate the required utility connections. Project cost to provide the necessary
modifications and infrastructure is estimated to be in the range of $100K to $160K.

Facilities Project Managers Guide

Page 114

(NAME OF BUILDING)
B74 ENVIRONMENTAL GROWTH CHAMBER
FEASIBILITY STUDY
TABLE OF CONTENTS
Page

Executive Summary
Background
Condition Evaluation of the Growth Chambers
Heat Rejection Options
Economic Analysis
Alternatives for Condenser Heat Rejection
New vs. Used Growth Chamber Purchase
Schedule and Mode of Accomplishment
Conclusion
Appendix A Life Cycle Cost of Differential Options
Option 1-Air cooled Condenser
Option 2 Cooling Tower Water Cooled Condenser
Option 3 Chilled Water Condenser Cooling
Option 4 Domestic Water Cooling
Option 5 Chilled Water Direct Cooling

Facilities Project Managers Guide

Page 115

Background
The Department of X intends to augment its research capabilities at (name of building) by installing two
growth chambers and has purchased two used XYZ Company growth chambers. The growth
chambers have been reassembled at (name of building), but they must be connected to electric power
and a means for heat rejection. Electric power is readily available for
connection to the growth chambers; however, there are several heat rejection options having
significantly different first cost and life cycle costs.
The growth chambers have been situated in their present location since 2002 and the department is
anxious to put them into operation. The equipment had been purchased through a used equipment
broker; disassembly, storage, reassembly, and start-up services had been purchased with costs to date of
$73K. If purchased new, a budget estimate of the cost is $130K per chamber. The service provider is
contracted to return to the site to complete the work after utility connections have been
completed. In an effort to expedite placing the chambers into operation, Person B (name of company.),
provided a proposal to design a temporary domestic water system anticipating availability of chilled
water in the near future. Person B provided valuable input to establish the alternative options for long
term operations.
The original water-cooled heat rejection systems on the growth chambers had been connected to a
cooling tower condenser water system. A cooling tower is not available at the (name of building)
facility, so an alternate means for heat rejection is required.
There are several options for providing the necessary heat rejection systems, which have varying levels
of cost. (See Heat Rejection Options for a comprehensive explanation of the different system
characteristics and cost factors.)
Economic analysis indicates that modifying the existing equipment to achieve heat rejection via air
cooled condensers results in minimum life cycle costs, and the used equipment will also result in
minimum life cycle costs as opposed to purchasing new equipment.
Analysis indicates that completing the installation is feasible, and that converting the condensing portion
of the refrigeration system water cooled to air cooled will have minimum life cycle costs. Total project
costs associated with completing the installation are estimated to be in a range between $100K and
$160K.
Condition Evaluation of the Growth Chambers
The growth chambers are approximately 15 years old and appear to be in good condition capable of
providing precision control of environmental conditions for growing plants. A combination of Metal
Halide and High Pressure Sodium Lights are used to illuminate the chambers to what the manufacturer
describes as an optimal spectral blend. The level of lighting can be automatically varied with several
levels of lighting. Control is provided electronically by a programmable panel
that maintains the lighting level, temperature, humidity, and auxiliary functions such as automatic
watering and can be ramped or stepped up to 192 times per day.
The design temperature range is 4?C to 40? C with the lights off and 10?C to 40? C with the lights on. The
humidity control system is design to maintain 85%RH at 30C, by adding water via spray nozzle
humidification, but is not capable of active dehumidification. Temperature is controlled to within 0.5?C
and humidity is controlled to within 3%. The design ranges are generally considered to be the industry
standard for growth chambers.
Facilities Project Managers Guide

Page 116

The X Departmentwill be using the chambers for plant growth experiments. The temperature range will
be from 10 C to 38 C as a min and max, with most experiments probably in the 24 to 28 range. The
humidity control will be in the 45 to 85 %RH range, with most experiments around 50-60%RH. These
conditions are all within the capabilities of the growth chambers being considered.
Reviewing the condition of the used equipment, the cabinet shells are solid and square, appearing to
have good insulation and panel seals. The doors open and close freely. There is some disarray, as most
of the ceiling panels have not been installed, and the interior of the units have not been cleaned. The
control cabinets remain in a standard condition and control wiring has been terminated at the I/O
devices. We understand the assembly contractor will be responsible for final testing of the control
components upon connecting the systems to the required utilities. Prior to disassembly, the units where
reported to be operational. Nonetheless, the equipment is used and increasing levels of maintenance will
be required to keep them operational. Spare parts from a third chamber may reduce the material costs;
however, labor associated with storing, handling, cataloging the spare parts will increase the operating
expenses.
The refrigeration systems will be critical elements in terms of system reliability. The system components
have been completely reassembled and the refrigerant piping is brazed together. As such, the
refrigeration systems have not been left open to the damaging affects of humidity and airborne dirt.
Upon placing the equipment into operation, the lighting and cooling systems will impart significant
loads on the electrical system, with associated cost. To provide close tolerance temperature control, the
refrigeration compressors will run continuously when the chambers are in operation contributing electric
load. The associated energy costs are expected to be in the range of $10K to $20K per year In terms of
sustained operability, XYZ Company remains in business providing standard replacement parts for the
systems and supporting versatile and reliable growth chamber operation. Additionally, the
campus contains many other XYZ Company chambers and there is a significant resource base for
maintenance, trouble shooting, and repair. As previously mentioned the refrigeration compressor run
continuously and periodic compressor replacement may be necessary. To assure reliable operations, a
preventive maintenance program is also outlined in the manufacturers operating instructions. It includes
daily system checks and periodic cleaning. Depending upon the reliability requirements and mode of
accomplishment, the maintenance costs could vary over a large ranger, but through an effective
maintenance strategy, they may be kept between $5K and $10K per year.
Heat Rejection Options
As previously noted, the purchased growth chambers require a heat rejection system. The existing
chambers were previously connected to a cooling tower rejection system. Cooling towers normally
complete the heat rejection system and recirculate bulk system water while a portion evaporates to reject
waste heat to the atmosphere. The associated cooling towers require ongoing maintenance to prevent
fouling from dissolved build-up from the make-up water. However, when combined to serve
a large quantity of individual units, they provide the most efficient refrigeration effect with the best
economy. In this case, the scale is not sufficiently large to support cooling tower operations.
Dry coolers are more commonly used where individual water cooled condensers units must reject heat
remotely and at a distance. They recirculate water mixed with antifreeze within a closed circuit having a
water-to-air finned heat exchanger and operate at relatively high temperatures, relying on sensible
Facilities Project Managers Guide

Page 117

cooling. Spray systems can be incorporated to improve heat transfer with increased maintenance
requirements. They provide the advantage of rejecting heat remotely, trading off
lowered efficiency caused by higher operating temperature. In this case, we will not consider a dry
cooler because, heat rejection can be accomplished within a relatively short distance from the growth
chamber.
Air cooled condensing provides the most direct means of rejecting system heat. Refrigerant is
circulated directly through a remote air cooled heat exchanger. Sensible cooling requires relatively high
condensing temperatures, with lower operating efficiency and higher electrical energy costs for the
refrigeration compressor energy. Spray water systems can be added to improve efficiency, additional
maintenance and first cost requirements must be compared with base characteristics to
establish benefit. Relative to the base cooling tower case, the heat rejection costs are minimal and
include condenser fan energy and increased refrigeration compressor energy from reduced efficiency of
higher condensing temperatures. This is the most economically attractive option.
Chilled water condenser cooling is a form of cascaded cooling; the cooling medium is pumped to the
site at significant expense to except the heat of rejection from the local refrigeration system. The local
system contains a refrigeration compressor which operates at significant expense to refrigerate the
system. The cumulative costs of the two refrigeration systems are prohibitively expensive. Therefore the
option is not recommended for this application.
Domestic water condensing is cost prohibitive and wasteful of potable water resources. Termed once
through cooling, this method of condenser cooling results in utility cost to cover the potable water
treatment and transportation, as well as, the sanitary waste treatment costs. This method typically
provides emergency backup of cooling tower operations or for interim operations while a normal source
is being planned and implemented.
Direct Chilled Water Cooling is a feasible option that replaces the local refrigeration circuit entirely.
Implementing this option requires replacement of the refrigerated cooling coil in the growth chamber
with a new chilled water coil. Control system retrofit for the chamber temperature is also necessary.
These changes have significant expense and also have a significant impact on operational performance.
The cooling coil dewpoint temperature is limited by the chilled water supply
temperature, which also limits the ability to operate at lower temperatures and limits the ability to
control humidity. Frequently, these limits do not impact usefulness for research involving plant growth.
Economic Analysis
Alternatives for Condenser Heat Rejection
To provide an economic analysis of the alternatives for heat rejection at the condenser, we assume each
of the options has a similar level of cost for compressor energy consumption, maintenance, and
operation of the refrigeration systems, and develop differential analysis of the available heat rejection
media. The analysis indicates that conversion to air cooled condensers will result in minimum life cycle
costs. Net present values of five options including first cost and annual differential cost over a 20 year
analysis period are presented in the following table.

Facilities Project Managers Guide

Page 118

Local Refrigeration Compressor


Air cooled

Tower Water

Chilled

Domestic

Direct Chilled

condenser

Cooled

Water

Water Cooled

Water Growth

Condenser

Cooled

Condenser

Chamber

Condenser

Cooling

First Cost

90,000

$120,000

$90,000

$50,000

$93,500

Annual
Condenser
Heat Rejection
Cost

$657

$6,728

$35,040

$37,142

$28,032

NPV of Life
Cycle
Operating Cost

$ $64,000

$81,000

$290,000

$306,000

$216,000

NPV of Total
Life Cycle
Costs

154,000

$201,000

$380,000

$356,000

$310,000

Table 1

Please note the analysis does not include the energy costs associated with lighting, humidifying, and
heating the chamber. Those costs may be higher by a factor closely related to the Energy Efficiency
Ratio of the refrigeration system. This analysis is intended to inform a decision regarding the most
economical means of rejecting chamber heat associated with the application described in this report.
New vs. Used Growth Chamber Purchase
Comparing life cycle costs of purchasing new or used equipment, the energy requirements to operate
new or used chambers are similar. The manufacturer indicates that the technology advances employed in
the new chambers primarily reduce manufacturing costs and have little if any impact on energy
consumption. For example, new lighting ballasts tend to be lighter in terms of weight of the materials
used to make them, as higher starting voltage can be generated with electronic components, but the
energy required to operate the lights is lower.
Growth Chamber with Air cooled condenser
Used

New

First Cost

$148,000

$380,000

Annual Condenser Heat Rejection Cost

$657

$657

NPV of Life Cycle Heat Rejection Costs

$64,000

$64,000

Annual differential Maintenance Cost $

28,000

$0

NPV of Annual Differential


Maintenance Costs

$216,000

$0

Annual Differential Chamber Energy

$0

$0

Facilities Project Managers Guide

Page 119

Costs
NPV of Annual Differential Chamber
Energy Costs

$0

$0

NPV of Total Life Cycle Costs

$428,000

$444,000

Table 2

The refrigeration system components have changed slightly, however, the main characteristic in term of
energy consumption has not changed; the refrigeration compressor runs continuously during operation.
As the system is used and the refrigeration system had been disassembled there is some risk of an early
failure which would cost approximately $10K to replace; failure usually results in acid byproducts in the
refrigeration circuit that must be removed. However, both the new and used systems require periodic
maintenance to assure early detection of refrigeration leaks, failed components, and clean heat transfer
surfaces. Here we would note that the used equipment first costs are significantly lower than new
equipment and a decision for used equipment purchase is not sensitive to maintenance costs. In this case
annual differential maintenance cost would have to be in excess of $28K to trigger a decision to buy new
equipment. See Table 2.
Schedule and Mode of Accomplishment
As the anticipated costs exceed $50K, the project will require authorization as a capital project through
the PAR system for design and construction. The feasibility study report will form the basis of a Design
and Construction PAR. Gaining authorization for design and construction will enable pre-purchase of
the condensing units which have a 60 to 90 day lead time.
Upon receiving PAR approval, design services will begin in order to occur in parallel with equipment
pre-purchase. The design documents will define the construction work for a fixed price estimate by PDC
shops.
After receiving a fixed price estimate within the construction budget, a 2 month construction period is
anticipated. Based on this approach, the project can be completed in approximately 6 months after
receiving departmental approval to proceed. This approach will also allow for an abbreviated design
effort with associate reduction in time requirements and costs. To validate the fixed price cost estimate,
we also recommend a parallel estimate; this will add approximately $2K to the project costs.
Alternatively, construction documents can be developed for a competitive bid. These documents would
have to be developed to a higher level of detail with specifications and general requirements for a
contract. The additional design and associated bid periods will add approximately 3 months to the
completion schedule.
Conclusion
In conclusion, providing a mean to reject the heat generated in the growth chambers presents the most
challenging obstacle to placing the growth chambers into operation. Several options were considered for
meeting the most challenging component of the project. On the basis of minimum life cycle costs, air
cooled condensing is a clear choice. Although this choice does not have the lowest first costs, the lowest
first cost alternative, domestic water cooling, has high water and sewerage utility costs and is not a
viable long term option. The other options have significantly higher costs than the air cooled option.

Facilities Project Managers Guide

Page 120

To implement this option, new air cooled condensers will be located on the roof immediately above the
growth chambers. XYZ Company will provide proprietary engineered components for installation by
union tradesmen. A structural design will also be necessary to place the condensers on the roof, assure
structural integrity, and coordinate the required roof penetrations.
A new water supply and drainage system will also be provided for humidification and watering. The
refrigeration systems will contain sufficient refrigerant to require leak detection and alarm. At this early
stage, we also anticipate additional scope may be required to accommodate design details not considered
at this early stage, feasibility.
Total project costs associated with completing the installation, are estimated to be in a range between
$100K and $160K as indicated in the budget presented below. Additional breakdown of the anticipated
costs are presented in the appendices.
Budget
Construction
Planning and Design
FFE
Project Support
Transportation
Project Management
Contingency
Total

Range
$75,000
8,000
0
2,000
0
10,000
5,000
$100,000

$120,000
10,000
3,000
15,000
12,000
$160,000

Table 3

Facilities Project Managers Guide

Page 121

APPENDIX A LIFE CYCLE COST OF DIFFERENTIAL OPTIONS


Option 1-Air cooled Condenser
Construction Costs

low

NPV

high

General Conditions

$5,000

$6,000

GC Roof penetrations and


stuctural dunnage

5,000

10,000

Mechanical

2,000

5,000

Electrical

20,000

25,000

Plumbing

10,000

20,000

Refrigerant
Monitoring

3,000

5,000

Refrigeration

8,000

12,000

Condensing unit

22,000

22,000

15,000

Refrigeration

Design Development
Allowance

$75,000
Used Equipment Purchase

$75,000

$120,000

73,000
Net Present Value of Life Cycle
Compressor Energy Costs(eer=5)

Annual Air cooled condenser hear rejection cost


Energy Consumption (electrical)
Cooling Capacity (tons)
Diversity
delta Temp (air)
condenser fan horse power
annual hours of operation
electric use rate (kw)
annual useage (kwh)
electric billing rate ($.10/kwh)
annual air cooled condenser heat rejection cost
Refrigeration Compressor (Air Cooled)
Rated Amps
Voltage
Phase factor
KVA
EER @ Tc=115
full load heat rejection(tons)
full load refrigeration capacity (tons)
diversity
Annual hours of operation
Annual compressor energy consumption (kwh)
Electric power billing rate ($/kwh)
Annual compressor energy cost ($)
discount rate

Facilities Project Managers Guide

40
0.50
10
1
8,760
1
6,570
$0.10
$657.00
Net Present value

58,979

$5,073
$212,052

21
480
1.73
17
5
25
20
50%
8760
76,380
$0.10
7,638
0.05

Page 122

Net Present Value of Life Cycle Compressor Energy Costs(eer=5) 58,979

Option 2 Cooling Tower Water Cooled Condenser


NPV
General Conditions
Mechanical
Electrical
Plumbing
Domestic water & sanitary connection
Roof
Cooling Tower Package
Design Development Allowance

$5,000.00
16,000
23,000
26,000
15,000
20,000
15,000
$120,000.00

$120,000
$29,489

Net Present Value of Life Cycle Compressor Energy Costs(eer=10)


Energy Consumption (condenser water)
Cooling Capacity (tons)
Diversity
delta Temp
average flow rate (gpm)
annual hours of operation
annual evaporation rate (gal)
blowdown
domestic water billing rate ($/gal)
sanitary waste billing rate
fan energy
water treatment
annual domestic water cost
annual sanitary waste cost

40
0.50
8
72
8,760
33,692
67,385
$0.0032
$0.0040
1,000
5,000
323
404
$6,727.75
Net Present Value

Refrigeration Compressor (Chilled Water Cooled Condenser)


Rated Amps
Voltage
Phase factor
KVA
EER @ Tc=115
EER @ Tc=85
full load heat rejection(tons)
full load refrigeration capacity (tons)
diversity
Annual hours of operation
Annual compressor energy consumption (kwh)
Electric power billing rate ($/kwh)
Annual compressor energy cost ($)
discount rate
Net Present Value of Life Cycle Compressor Energy Costs(eer=10)

Facilities Project Managers Guide

$51,950
$201,439

21
480
1.73
17
5
10
25
20
50%
8760
38,190
$0.10
3,819
0.05
29,489

Page 123

Option 3 Chilled Water Condenser Cooling


NPV
General Conditions
Mechanical
Electrical
Plumbing
Domestic water & sanitary connection
Isolation heat exchanger package
2" Chilled water line 500 ft.
Design Development Allowance

$2,500
2,000
14,000
16,500
20,000
20,000
15,000
90,000

Net Present Value of Life Cycle Compressor Energy Costs(eer=15)


Energy Consumption (chilled water)
Cooling Capacity (tons)
Diversity
delta Temp
average flow rate (gpm)
annual hours of operation
annual flow rate 10,
annual useage (ton hours)
chilled water billing rate ($/ton hour)
annual chilled water heat rejection cost

40
50%
24
20
8,760
512,000
175200
$0.20
$35,040
Net Present Value

Refrigeration Compressor (Chilled Water Cooled Condenser)


Rated Amps
Voltage
Phase factor
KVA
EER @ Tc=115
EER @ Tc=70
full load heat rejection(tons)
full load refrigeration capacity (tons)
diversity
Annual hours of operation
Annual compressor energy consumption (kwh)
Electric power billing rate ($/kwh)
Annual compressor energy cost ($)
discount rate
Net Present Value of Life Cycle Compressor Energy Costs(eer=15)

Facilities Project Managers Guide

$90,000
19,660

270,570
$380,229

21
480
1.73
17
5
15
25
20
50%
8760
25,460
$0.10
2,546
0.05
19,660

Page 124

Option 4 Domestic Water Cooling


Option 4 - Domestic Water Cooling
General Conditions $
Mechanical
Electrical
Plumbing
Design Development Allowance

NPV

2,500
2,000
14,000
16,500
15,000
50,000
Net Present Value of Life Cycle Compressor Energy Costs(eer=15)
Energy Consumption (domestic water)
Cooling Capacity (tons)
Diversity
delta Temp
average flow rate (gpm)
annual hours of operation
annual flow rate
domestic water billing rate ($/gal)
Sewer water billing rate ($/gal)
annual domestic water cost
annual sanitary waste cost
annual domestic water heat rejection cost

Facilities Project Managers Guide

$50,000
19,660

40
0.50
48
10
8,760
5,256,000
$0.0031
0.004
$16,118
$21,024
$37,142.40
286,804
Net Present Value $356,463

Page 125

Option 5 Chilled Water Direct Cooling

Option 5 - Chilled Water Direct Cooling


General Conditions
Mechanical
Electrical
Plumbing
Control Modifications
Evap Coil
2" Chilled water line 500 ft.
Design Development Annalysis

NPV
$2,500
2,000
14,000
15,000
25,000
20,000
15,000
93,500

Net present value of compressor energy costs


Energy Consumption (chilled water)
Cooling Capacity (tons)
40
Diversity
0.50
delta Temp
12
average flow rate (gpm)
40
annual hours of operation
8,760
annual flow rate
21,024,000
annual useage (ton hours)
140160
chilled water billing rate ($/ton hour)
$0.20
annual chilled water heat rejection cost
$28,032
216,456
Net Present Value
$309,956

Facilities Project Managers Guide

$93,500
0

Page 126

Sample SD VE
Value Engineering Ideas by
Discipline

Cost Impact

Comments

Yes

Maybe

No

Mechanical
1

Heat Recovery Options

Eliminate 2 speeds
from Recirc clean room

50% fixed sash @31


fume hoods

Eliminate 3rd floor


specialty labs Scrubber

4a

Downsize scrubber

View current AHU #4 Eliminate Fan Coil

Reduce Floor Ht at 16'


floors and raise
penthouse

Acid Nuetralization
systems -Eliminate

(30,000)

(30,000)

Eliminate all
humidifyers for clean
room

(20,000)

(20,000)

Eliminate lab
humidifyers in
penthouse

(50,000)

(50,000)

10

Unify humidification /
dehudificate to 42%

(65,000)

(65,000)

11

Central HVAC in
Penthouse

(20,000)

12

Delete 18 meg ohm


system

13

PVC Pipe for DI water

14

Galvanized steel
ductwork for solvent
exhaust

14a

Consolidate all solvent


exhaust

(20,000)

add CNF to lab

15

Revise non-potable
water system

(21,000)

at lab sinks

(21,000)

16

Delete natural gas to

(21,000)

Utility corridor

(21,000)

Facilities Project Managers Guide

(60,000)

Analyze in DD

(60,000)

(150,000)

Analyze in DD

(150,000)

(31,000)

(31,000)

(245,000)

(245,000)
ENSR advise, $
TBD

(10,000)

(200,000)

(360,000)

(10,000)
Verify
archit/struct/ME
P impact

Reduce # of
AHU
Reduce
distribution, final
polish

(200,000)

(20,000)

(360,000)

(32,000)

(32,000)

(100,000)

(100,000)
(20,000)

Page 127

Value Engineering Ideas by


Discipline

Cost Impact

labs
17

Delete nitrogen to labs

18

Delete vacuum
sys/install exhaust
system

19

Reduce Utl
compressed air

20

Reuse Company E
AHU/Combine non lab
AHUs
SubTotal

Comments

Yes

Maybe

No

distribution only
(5,000)

Utility corridor
distribution only

(5,000)

(100,000)

explore
requirements

(100,000)

(20,000)

explore
requirements

(20,000)

$ (1,560,000)

SubTotal
SubTotal w/
20% Markup

(979,000)

$
(350,000)

$
(231,000)

(1,174,800)

(420,000)

(277,200)

$ (1,174,800)

$
(147,000)

20%

Markup

(1,872,000)

60%

Realized

$ (1,123,200)

VFD Change

Locate generator in
basement

Downsize generator look at optional


standby

Relax CU spare
capacity standard generator

(5,000)

Lighting package
reduction to $6/sqft

(131,000)

Review quantity of
power outlets

(12,500)

(12,500)

6a

Reduce raceway
standards

(13,000)

(13,000)

Rough in changes

(25,000)

(25,000)

delete Central Clock


sys

(31,000)

(31,000)

TeleData

10

Delete Video/Confr

(18,000)

Not construction
budget

(18,000)

11

Delete Paging Sys

(16,000)

Not construction

(16,000)

Realize 100%
Yes, 35% Maybe

Electrical

Facilities Project Managers Guide

(24,000)
(40,000)

(24,000)
verify storage of
fuel

(140,000)

(40,000)

(140,000)

(5,000)
consider fewest
# of fixtures

Adjust to 500
drops

(131,000)

Page 128

Value Engineering Ideas by


Discipline

Cost Impact

Comments

Yes

Maybe

No

budget
12

Lightning Protection
system
SubTotal

(65,000)
$

(65,000)

(520,500)

SubTotal

(624,600)

SubTotal w/
20% Markup
Realize 100%
Yes, 35% Maybe

20%

Markup

60%

Realized

(374,760)

Reduce vibration at 3rd


floor

(50,000)

Relocated tunnel, infill


basement, move
elevator

(386,500)

$
(129,000)

$
(5,000)

(463,800)

(154,800)

(6,000)

(463,800)

$
(54,180)

$
(100,000)

(120,000)

$
(42,000)

Structural

SubTotal
20%

Markup

50%

Realized

(50,000)
$

(50,000)

Verify sheilding

(100,000)

SubTotal

(120,000)

SubTotal w/
20% Markup

(60,000)

(120,000)

Realize 100%
Yes, 35% Maybe

(50,000)
$

Architectural
1

Adjust slate flooring


pricing to thin set

Reduce stone walls in


atrium

(200,000)

2a

Add 40 fire shutters @


Atrium

80,000

80,000

Reduce railings in
atrium

(30,000)

(30,000)

Reduce stone on
exterior

(50,000)

Another freight
elevator scheme

(50,000)

(50,000)

Review casework
allowance

(100,000)

(100,000)

Delete Natural gas

Barrell vault roof


Facilities Project Managers Guide

(120,000)
Revise materials

(200,000)

(50,000)

in Mechanical
(50,000)

(50,000)
Page 129

Value Engineering Ideas by


Discipline

Cost Impact

Comments

Yes

Cleanroom Wall
system

(50,000)

9a

Revise perimeter walls


of cleanroom

(50,000)

(50,000)

9b

Reduce ClnRm ceiling


system

(70,000)

(70,000)

10

Reduce sound
treatment at atrium

(50,000)

(50,000)

11

Reduce carpet
allowance to $25/sqyd

(20,000)

(20,000)

12

Eliminate cleanroom
casework

13

Eliminate Elevator or
Stair

(45,000)

(45,000)

14

Reduce Curtainwall

(50,000)

(50,000)

15

Eliminate fritted glass

(20,000)

16

Terrace deck material


change 80/20
crete/stone

(150,000)

17

Delete Window
washing equipment

(25,000)

(25,000)

18

Cleanroom floor
system

(45,000)

(45,000)

19

Interior Signage

(40,000)

(40,000)

20

Gas cabinets to fit out

(220,000)

(220,000)

SubTotal
20%

Markup

50%

Realized

$ (1,355,000)
(1,626,000)

(813,000)

Verify rated
assembly needs

Maybe

No

(50,000)

TBD

Increases HVAC

(20,000)

(150,000)

SubTotal

(895,000)

$
(340,000)

$
(120,000)

(1,074,000)

(408,000)

(144,000)

$ (1,074,000)

$
(142,800)

SubTotal w/
20% Markup
Realize 100%
Yes, 35% Maybe

Contract/Purchasing Strategy
Adjust
Escalation/Acceleratio
n Assumptions

Early Procurement

Open Spec

SubTotal

Facilities Project Managers Guide

(300,000)
(300,000)

TBD
Big $ items

(300,000)

TBD
SubTotal

Page 130

Value Engineering Ideas by


Discipline

Cost Impact

Comments

Yes

Maybe

No

(300,000)
(360,000)

SubTotal w/
20% Markup

(360,000)

Realize 100%
Yes, 35% Maybe

20%

Markup

100%

Realized

Total Projected value


of VE Ideas

$ (2,730,960)

$ (2,712,600)

(350,000)

(350,000)

(360,000)

$
(126,000)

$
(511,980)

$
-

Function/Program Options
1

Office Support
adjustment by Users

Adjust Program - swap


space types

Reduce Dry Lab


covertiblity

Reduce Cleanroom;
Accommodate all
characterization,
Teaching Lab & CNF
Admin

TBD

Reduce Cleanroom
Class to 10,000

TBD

No High Toxic Lab


capability

Change module size


from 11' to 10'-6"

Variable, but
insufficient

(250,000)

(250,000)

(665,100)

Shorten bldg by
8'

(665,100)

Trim 1 module slice

(1,490,320)

Shorten bldg by
10'6"'

(1,490,320
)

Trim 2 module slice

(2,981,200)

Shorten bldg by
21'

(2,981,200
)

10

Move Colloquium to
Bldg footprint

(250,000)

Reduces other
program

(250,000)

SubTotal

20%

SubTotal w/
20% Markup

Markup
Total Projected
value of
Function/Progra
Facilities Project Managers Guide

Realize 100%
Yes & Maybe

(350,000)

$
(2,405,420
)

$
(3,231,200
)

(420,000)

(2,886,504
)

(3,877,440
)

(420,000)

$
(2,886,504

$
Page 131

Value Engineering Ideas by


Discipline

Cost Impact

Comments

Yes

m Ideas

Maybe

No

)
Building
Atrium

Name W

64

70

72

90

4608

6300
73.14%

12

30

22

30

264

900

5.73%

14.29%

4344

5400
80.44%
Building

Building Name

Name W

80

70

72

90

5760

6300
91.43%
Building

Building Y

Name W

30

70

194

90

5820

6300
92.38%
Building

Total Atrium
16188

Name W
6300
256.95%

Facilities Project Managers Guide

Page 132

Sample SD Cost Strategy


Building

Company A

Company B

Project Elements

Estimate

Estimate

New Bldg.

31,390,718

32,623,000

Delta
$ (1,232,282)

Atrium Addition and


Modifications

5,995,745

6,530,000

(534,255)

B Hall

2,044,009

1,077,000

967,009

Sitework

2,639,180

2,607,000

32,180

Total

42,069,652

42,837,000

Buidling

Company A

Company C

Project Elements

Estimate

Estimate

Landscape (Carried
Above)

953,000

$
(767,348
)

Delta
$
(347,000
)

1,300,000

Gross Area
Type of Space

Budget

Estimate

Delta

Mechanical Rooms

22,500

46,934

24,434

Service, Misc.

13,120

12516

(604)

1st Floor Clean Room **

36,600

27301

(9,299)

2nd Floor Lab Space

30,000

26954

(3,046)

3rd Floor Lab Space

28,640

27589

(1,051)

Atrium

18,940

22142

3,202

Total Project GSF

149,800

163,436

Project Budget/SD Estimate

37,000,000

42,069,652

Cost/GSF

247.00

257.41

Cost/GSF x GSF Delta

Facilities Project Managers Guide

(3,368,037)

13,636
$

5,069,652

(3,510,009)

Page 133

How to get to 37 million?

Goals

I.

Reconcile A/BDifferences

II.

Reconcile A/C Differences

III.

Value Engineering

Yes

Mechanical

Electrical
Architectural

Maybe

1,174,800

147,000

463,800

54,180

1,074,000

142,800

Structural

42,000

Contract/Purchasing

126,000

$
2,712,600

SubTotal VE

$
511,980
Continued

IV.

Yes

Functional/Program Changes
Reconfirm program

Maybe

420,000

Quantity/function of lab

300,000

SqFt reduction

2,586,504

Redesign

Reduce Quality

Not Explored Beyond VE


$

420,000

Yes
Net Total Cost Reductions

V.

3,132,600

2,886,504
Maybe

3,398,484

Risk Items

Rock
Vibration
Shoring/Underpinning
Code Issues
Company E In Operation
Off peak work
vibration, sound
Const. Freight
elevator, travel
Temp Eclosure on west
elevation
I.E.S. study
Wind Tunnel results
Environmental
Casework in cleanroom
Facilities Project Managers Guide

Verify storage for


events
Study Redundancy
EIS Study
Gas Detection

Page 134

Sample Design Development Value Engineering

Compnay A

Building X

VALUE ENGINEERING/COST ADJUSTMENTS

Cornell University June 21, 2000

NO

DATE

DESCRIPTION

AMOUNT

ACTION

COMMENTS

Foundations
1.01

6/12/2000

Delete stainless steel


rebar at characterization.

(10,000)

Pending

1.02

6/12/2000

Revise rock unit pricing.

226,000

Approved

1.03

6/12/2000

Revise bank shoring unit


pricing/quantity, look at
alternate wall forming
methods (in at $36/sf).

(21,000)

Approved

1.04

6/12/2000

included with 1.06

1.05

6/12/2000

Raise basement floor


elevation 1' in mechanical
room and 2' in electrical
room

(72,000)

Approved

1.06

6/12/2000

Revise Caisson per new


sizing.

(25,000)

Approved

Need EMI
consultant

N/A

Floor and Roof Structures


3.01

6/12/2000

Change concrete frame


unit prices.

Pending

3.02

6/12/2000

Delete fireproofing at
penthouse roof framing.

3.03

6/12/2000

Change roof framing from


15# to 10# per sf.

(85,000)

Approved

3.04

6/12/2000

Reduce concrete frame


heating.

(33,000)

Approved

N/A

included in
revised design
and estimate

Per John H.

Enclosure
4.01

6/12/2000

Revise composite metal


panels from gasketed
system to wet seal.

(80,000)

Rejected

4.02

6/12/2000

Lower atrium curtain wall


elevation heights 5'-0" +/-.
Eliminate/minimize
clerestory windows at
Building Y terrace (reduce
by 5'-0" +/-)

(75,000)

Pending

ABC to review
design
implications

4.04

6/12/2000

Delete storefront on north


side of Building Y; existing
to remain

(18,000)

Rejected

Bob thinks we
are light in the
estimate

Facilities Project Managers Guide

Page 135

NO

Compnay A

Building X

VALUE ENGINEERING/COST ADJUSTMENTS

Cornell University June 21, 2000

DATE

DESCRIPTION

AMOUNT

ACTION

COMMENTS

Roofing and Waterproofing


5.01

6/12/2000

Eliminate rectangular
skylights at Atrium.

(16,000)

Rejected

5.02

6/12/2000

Eliminate skylight at
Atrium stair

(7,500)

Rejected

5.03

6/12/2000

Weathered Terne Coated


Steel to painted metal on
barrel vault roof.

(88,000)

Rejected

Cannot be
taken with
5.03a

5.03a

6/12/2000

Terne Coated Steel to


Sarnafil profile

(105,000)

Rejected

Cannot be
taken with 5.03

Cannot be
taken with
17.17

Interior Partitions
6.01

6/12/2000

Reduce cleanroom ceiling


height to 9'. (from 10')

(18,000)

Approved

6.02

6/12/2000

Use hollow metal frames


in lieu of aluminum.

(40,000)

Approved

6.03

6/12/2000

Change all interior doors


from 9'-0" to 8'-0".

(4,500)

Rejected

6.03a

6/12/2000

Change all interior doors


from 8' to 7'

(4,500)

Rejected

6.04

6/12/2000

Review extent of
sidelights/transoms at
interior doors.

6.05

6/12/2000

Change interior doors


from solid core maple
finish to more economical
species - based on 3x9'
doors

(10,000)

Rejected

Possible Bid
Alternate

6.05a

6/12/2000

Change interior woodwork


from maple to more
economical species

(20,000)

Rejected

Possible Bid
Alternate

Facilities Project Managers Guide

N/A

Page 136

NO

Compnay A

Building X

VALUE ENGINEERING/COST ADJUSTMENTS

Cornell University June 21, 2000

DATE

DESCRIPTION

AMOUNT

ACTION

6.06

6/12/2000

Eliminate roll down fire


shutters and glass
guardrails at all openings
(1st, 2nd, 3rd floors).
Replace with
tempered/laminated glass
windows in gasketed
frames with minimum two
deluge sprinklers per
opening (to maintain 2
hour separation required
by New York State
Building Code.) include
bridge connections in this
change

(6,000)

6.07

6/12/2000

Included in 6.06

6.08

6/12/2000

Reduce number of doors


in clean room or change
size or type.

(8,000)

Approved

6.09

6/12/2000

Replace automatic sliding


doors in clean room with
single swinging doors.

(19,000)

Approved

6.10

6/12/2000

Reduce size of doors


upstairs to serv. Corridorwidth double doors to
single doors.

(11,000)

Approved

6.11

6/12/2000

Replace ZB walls with Z

(39,000)

Approved

6.11a

6/13/2000

Replace some clean room


walls with standard stud
walls for "fixed" rooms

(11,000)

Rejected

6.12

6/12/2000

Revise F13 Partition @


clean room to Epoxy finish

(30,000)

Approved

Pending

COMMENTS
1450 sqft of
acoustical
treatment
needed.

N/A

research finish
hardware count
on these leaves

Floor, Wall and Ceiling Finishes


7.01

6/12/2000

Change slate paving to


slate tile, thin set
application. (Investigate
fixed tile sizes, pattern
options, and domestic
stone supplier.)

Facilities Project Managers Guide

N/A

included in
revised design
& estimate

Page 137

NO

Compnay A

Building X

VALUE ENGINEERING/COST ADJUSTMENTS

Cornell University June 21, 2000

DATE

DESCRIPTION

AMOUNT

ACTION

COMMENTS

7.02

6/12/2000

Change stone tile to


patterned stained
concrete for Atrium floor.

(75,000)

Rejected

7.03

6/12/2000

Change stone tile walls to


painted gyp. Board.

(29,000)

Rejected

7.04

6/12/2000

At Atrium ceiling, revise


ceiling design to utilize
suspended T-bar/perf.
Metal lay-in panel
construction with
acoustical material
behind.

(27,000)

Rejected

7.05

6/12/2000

Revise Atrium ceiling to


use Tectum type
acoustical panel instead
of perf. Metal.

(41,000)

Rejected

7.06

6/12/2000

Eliminate acoustical fabric


wrapped paneling
Compare
performance/cost to glue
down fabric installation

(37,000)

Rejected

7.07

6/12/2000

Revise carpet cost from


$35/yd to $28/yd. Verify
carpet as direct glue
installation, no pad.
(Cannot be taken with
7.08)

(13,000)

Approved

7.08

6/12/2000

Investigate using polyolefin type carpet and


reducing carpet cost to
$15-$20/yd.) (Cannot be
taken with 7.07)

N/A

see 7.07

7.09

6/12/2000

Revise cleanroom
materials

N/A

see 6.11 and


6.12

7.10

6/12/2000

Revise cleanroom layout

7.11

6/12/2000

Remove ceiling grid over


service area in clean room

N/A

included with
7.13

7.12

6/12/2000

Change floor in mos


service area (end of clean
room) to vct controls?

N/A

included with
7.13

7.13

6/12/2000

Reduce ceiling grid at


clean room - eliminate
furnace back area - use

Facilities Project Managers Guide

(240,000)

(18,000)

Potential to reprice slate tile in


lieu of stamped
concrete

Rejected

Approved

Page 138

NO

Compnay A

Building X

VALUE ENGINEERING/COST ADJUSTMENTS

Cornell University June 21, 2000

DATE

DESCRIPTION

AMOUNT

ACTION

COMMENTS

VCT in lieu of static


flooring

Function Equipment and Specialties


8.01

6/12/2000

Eliminate all racks, etc. in


chem storage area.
Owner will fit out as
needed.

(52,850)

Approved

8.02

6/12/2000

Replace walk-in hoods in


chem waste area with
snorkels.

(37,000)

Approved

8.03

6/12/2000

Reduce/eliminate
overhead service carriers.

N/A

with 8.05

8.04

6/12/2000

Reduce out fitting of toxic


gas labs until occupants
better known.

N/A

with 8.05

8.05

6/12/2000

Eliminate some lab


specialties items.

Approved

Target
$1,000,000 for
lab equipment Lynn to review
Kewaunee
estimate

8.06

6/12/2000

Reduce Lab Furniture

N/A

with 8.05

8.07

6/12/2000

Delete Clean Room


Equipment added at DD

N/A

with 8.05

8.08

6/12/2000

Reduce Signage
allowance to $30,000

(30,000)

Approved

(24,000)

Approved

go to the
standard
stainless cab
interior

N/A

estimate not
based on
custom design

Approved

Go to standard
riser

N/A

included with
9.11

(415,851)

Vertical Transportation and Stairs


9.01

6/12/2000

Provide standard cab


finishes in elevators.

9.02

6/12/2000

Stair railings to be
standard SS mesh
product in painted metal
frame with SS grab rails

9.03

6/12/2000

Delete translucent glass


risers

9.04

6/12/2000

Relocate elevator at
Building Y south.

Facilities Project Managers Guide

(30,000)
-

Page 139

NO

Compnay A

Building X

VALUE ENGINEERING/COST ADJUSTMENTS

Cornell University June 21, 2000

DATE

DESCRIPTION

AMOUNT

9.05

6/12/2000

Change Stair #1 and #2 to


rectangular switchback
stairs (not squares).

N/A

9.06

6/12/2000

Eliminate star #3 at South


Building Y. Retain
exterior fire escape for
egress from 2nd floor.

N/A

9.07

6/12/2000

Remove dumbwaiters
completely, transport
chemicals in service
elevators.

9.08

6/12/2000

Change guardrails from


stainless steel/mesh to all
painted metal.

N/A

included with
9.02

9.09

6/12/2000

Review changing
handrails from stainless
steel to wood.

N/A

included with
9.02

9.10

6/12/2000

Alternative to the
handicap elevator - wheel
chair lift

N/A

not allowed by
code

9.11

6/12/2000

Redesign HRM delivery


systems. Delete Stair 12,
delete elevator 1, Elevator
2 becomes (elev 1) freight
& passenger and adds
basement HRM corridor
stop. Elevator 3 becomes
hydraulic three stop (
basement MER, HRM and
cleanroom/service). Add
6x6 hatch in penthouse
deck with chain fall to 3rd
floor (service corridor @
south?). South Building Y
stair (#3) extended to
785'6". Move dumbwaiter
to that area, use
Company E basement for
HRM route & storage.
Ventilate storage w/HRM,
new lights in storage.

9.12

6/12/2000

Change Traction Freight


elevator to hydraulic

(430,000)

$
(1,225,701)

Subtotal Architectural
$
Facilities Project Managers Guide

(24,000)

(91,000)

ACTION

COMMENTS

impacted by
9.11

Rejected

Approved

N/A

included with
9.11
Approved

Pending
Page 140

NO

Compnay A

Building X

VALUE ENGINEERING/COST ADJUSTMENTS

Cornell University June 21, 2000

DATE

DESCRIPTION

AMOUNT
$

(837,500)

(2,154,201)

ACTION

COMMENTS

Rejected
Total

10.01

6/12/2000

Delete non-potable water


system.

(14,000)

Approved

Cannot be
taken with
10.05

10.02

6/12/2000

Delete laboratory suction


vacuum system.

(94,000)

Rejected

Reconsider
distribution to
2nd & 3rd floors
Watch
acceptance of
10.06

10.03

6/12/2000

Eliminate roof
drains/overflows. Provide
scuppers/gutters at
exterior.

10.04

6/12/2000

Add insulation for non


potable domestic water

39,000

Approved

10.05

6/12/2000

Delete non potable hot


water system and
associated 10.04
insulation

(114,000)

Rejected

Cannot be
taken with
10.01

10.06

6/13/2000

Delete gases distribution


in corridors, risers only

(55,000)

Rejected

Reduce credit
by 8,000 if
10.02 is
accepted

10.07

6/13/2000

Bring gases into building


only

10.08

6/13/2000

Use copper materials in


lieu of stainless for
nitrogen

Subtotal Plumbing

Rejected

Rejected
$

(5,000)

Rejected

25,000

Approved

Pending

(268,000)

Rejected

(243,000)

Total

HVAC
11.01

6/12/2000

Reduce HEPA's (increase


air flow from 62 fpm to 80
fpm), changes coverage
from 30% to 25%

(39,500)

Rejected

11.02

6/12/2000

Reduce process cooling


from 400 to 200 gpm.

(17,000)

Approved

Facilities Project Managers Guide

Page 141

Compnay A

Building X

VALUE ENGINEERING/COST ADJUSTMENTS

Cornell University June 21, 2000

NO

DATE

DESCRIPTION

11.03

6/12/2000

Reduce chilled water


system gpm.

Rejected

11.04

6/12/2000

Reduce heating water


system gpm.

Rejected

11.05

6/12/2000

Delete temporary exhaust


system for canopies.

(121,000)

Rejected

11.06

6/12/2000

Fan filter units at clean


room.

(416,000)

Rejected

Mario would
prefer 11.26

11.06a

6/20/2000

Fan Filters at Corridors

Pending

Explore at CD's

11.06b

6/20/2000

In duct HEPAs at class


10,000 space

Pending

Explore at CD's

11.07

6/12/2000

Delete heat recovery unit


along with all heat
recovery piping, pumps,
controls, etc.

Approved

need this with


constant
volume

11.08

6/12/2000

Change all fume hoods to


constant volume half
sash. Use a non ddc
phoenix valve heresite
coated with sound
attenuator for each fume
hood or grouped snorkels.
The labs will remain vav
with ddc tracking supply
and exhaust terminal units
with Building Z Control
controllers mounted on
teh terminal units.
Therefore, you eliminate
the Anemostat lab control
system. To save further
energy consider using the
Air Sentry fume hood by
Flow Safe Inc which
requires 330 to 500 cfm
for a 18"-21" sash
opening at 40' per minute
velocity compared to 900
cfm at 100 fpm for the
standard hood.

Pending

11.08a

6/20/2000

Low Flow Fume Hood

Pending

Cornell To Give
Guidence

11.09

6/12/2000

Delete the return air


terminal units in the office
areas. Use flow
measuring station in the

Rejected

Already
included in
estimate

Facilities Project Managers Guide

AMOUNT

(331,000)

ACTION

COMMENTS

Page 142

NO

Compnay A

Building X

VALUE ENGINEERING/COST ADJUSTMENTS

Cornell University June 21, 2000

DATE

DESCRIPTION

AMOUNT

ACTION

COMMENTS

main return duct to track


the supply fan.

11.10

6/12/2000

Verify that there are no


control valves at the
radiant panels.. The
radiant panel system is a
constant flow variable
temperature system. A
main control valve
controls the loop
temperature based on
outdoor air temperature.

11.11

6/12/2000

Delete scrubber. Leave


space.

11.12

6/12/2000

Delete clean steam


generator for clean room.

11.13

6/12/2000

Eliminate some back up


systems/pumps.

11.13a

6/19/2000

Eliminate Chilled Water


stand-by pump chp-2

(28,000)

Rejected

11.13b

6/19/2000

Eliminate process chilled


water stand-by pump
PCHP-2

(9,000)

Rejected

11.13c

6/19/2000

Eliminate glycol hot water


stand-by pump gwp-2

(10,000)

Rejected

11.13d

6/19/2000

Eliminate hot water stand


by pump HWP-2

(10,000)

Rejected

11.13e

6/19/2000

Eliminate perimeter heat


stand-by pump HWP-4

(6,000)

Rejected

11.14

6/12/2000

Fan filters instead of fans


and filters.

11.15

6/12/2000

Reduce di capacity.

N/A

11.16

6/12/2000

Reduce air changes in


upstairs labs.

N/A

11.17

6/12/2000

Reuse some Company E


lab Exh. Lam. Flow
benches.

Pending

11.18

6/12/2000

Eliminate natural gas on


3rd floor. (Still costing
Cornell at least $16,000.)

Facilities Project Managers Guide

N/A

(36,000)

Rejected

Already
included in
estimate

Rejected
Rejected

(4,000)

N/A

Approved

void

(name) to reprice

Page 143

Compnay A

Building X

VALUE ENGINEERING/COST ADJUSTMENTS

Cornell University June 21, 2000

NO

DATE

DESCRIPTION

11.21

6/12/2000

Utilize steam preheat in


lieu of hot water with
glycol

(100,000)

Rejected

11.23

6/12/2000

Replace desiccant drier


with low temp chiller and
coil

100,000

Rejected

11.24

6/12/2000

Delete clean room


instrument air loop

(37,000)

Approved

11.25

6/13/2000

Delete stack sound


attenuators

(55,000)

Approved

11.26

6/13/2000

Adjustment of recirculating supply duct to


units

(391,500)

Approved

11.27

6/13/2000

Provide premanufactured
clean room system
(modular tunnel)

Pending

11.28

6/13/2000

Reduce recirculation air


by 10%

Rejected

Subtotal HVAC

AMOUNT

$
$

(835,500)
-

(675,500)

(1,511,000)

ACTION

COMMENTS

Approved
Pending
Rejected
Total

Electrical
12.01

6/12/2000

Remove cable
tray/isoduct language
from office spaces and
distribute majority of
voice/data at the
perimeter walls.
Distribute to centers of
rooms via fixed drop
(poles or fixed
architectural walls).

12.02

6/12/2000

Rotate lights parallel to


lab benches and maintain
75 fc at bench height.

(16,000)

Approved

12.03

6/12/2000

Select cheaper fixture for


Labs and provide
alternate
selections/manufacturers.stay with parallel scheme

(87,000)

Approved

Facilities Project Managers Guide

N/A

refer to 12.07

Page 144

Compnay A

Building X

VALUE ENGINEERING/COST ADJUSTMENTS

Cornell University June 21, 2000

NO

DATE

DESCRIPTION

12.04

6/12/2000

Provide fixture alternates


for Offices at $6/sf.

(90,000)

Approved

12.05

6/12/2000

Reduce cost of Atrium


lighting by 10% without
affecting the design (does
not include light tube).

(30,000)

Approved

12.06

6/12/2000

Eliminate draw-out
construction for feeder
circuit breakers on the
main switchboard. Main
draw-outs for the main
and tie circuit breakers.
This will require that one
side of the main
switchboard be shut down
to pull periodic
maintenance of feeder
circuit breakers.

(36,000)

Approved

Bob review by
maintenance

12.07

6/12/2000

Provide a system of fixed


power poles in lieu of
linear flexibility Quantities
and layout to be
determined.

(55,000)

Pending

Pending
redesign

12.08

6/12/2000

Fully develop the design


of the cleanroom to
determine the actual
power requirements. At
this time the requirements
are for an allowance of 30
watts/sf. This needs to be
confirmed. Detailed
equipment lists will be
required.

N/A

Pending overall
design

12.09

6/12/2000

Delete door access and


card reader system $
remaining in construction
cost. Limit security and
CCTV work to power and
raceways only. System
equipment and wiring to
be provided by the Owner.

(30,000)

Rejected

12.10

6/12/2000

Relocate the generator to


the roof of Building X to
reduce the length of the
emergency feeder.

(37,000)

Rejected

Facilities Project Managers Guide

AMOUNT

ACTION

COMMENTS

Page 145

Compnay A

Building X

VALUE ENGINEERING/COST ADJUSTMENTS

Cornell University June 21, 2000

NO

DATE

DESCRIPTION

12.11

6/12/2000

Reduce emergency
generator capacity - life
safety only- 1250 kw to
900 kw

(135,000)

Approved

12.12

6/12/2000

Reduce 110v outlets by


25%

(29,000)

Rejected

12.13

6/12/2000

Reduce isoduct by 25%shorter sections along


each wall.

(11,000)

Rejected

12.14

6/12/2000

Lighting in labs - drop in


fixtures vs alternate
pendant fixtures parallel to
benches

(58,000)

Pending

additive with
12.03

12.14a

6/12/2000

Lighting in offices - drop in


fixtures not pendant.

(187,000)

Pending

Additive with
12.04

12.15

6/12/2000

Wireless as a solution to
the open office tele/data
problem.

N/A

12.16

6/12/2000

Alternative wire
distribution in flex-office
space.

N/A

12.17

6/13/2000

Review & Adjust Clean


Room Fixture Counts &
Pricing

(30,000)

Approved

12.18

6/13/2000

Delete Lightning
Protection

(30,000)

Pending

Bob get
comments from
FMI

12.19

6/20/2000

Additional Smoke
Detectors at all rooms that
are enclosed

100,000

Approved

Mike to confirm
qtys and budget

(324,000)

Approved

(330,000)

Pending

(107,000)

Rejected

(761,000)

Total

(55,000)

Pending

Subtotal Electrical

AMOUNT

ACTION

COMMENTS

see 12.07

Sitework
15.01

6/12/2000

Direct burial of utilities in


lieu of cast in place

15.02

6/12/2000

Remove terrace walkway


(no wall, simple path.

Facilities Project Managers Guide

Additional
saving to 16.01
- precast utility
tunnel.

Rejected
Page 146

Compnay A

Building X

VALUE ENGINEERING/COST ADJUSTMENTS

Cornell University June 21, 2000

NO

DATE

DESCRIPTION

15.03

6/12/2000

Make terrace walk


narrower (12 feet instead
of 16 feet).

(4,000)

Rejected

15.04

6/12/2000

Revise pricing cover at


Loading Dock area.

(35,000)

Approved

15.04a

6/12/2000

Remove cover on Loading


Dock area.

(60,000)

Rejected

15.05

6/12/2000

Remove enclosure walls


@ service area

(14,000)

Rejected

15.06

6/12/2000

Move X north entrance to


Quad budget

(66,000)

Pending

15.07

6/12/2000

Delete limestone and


llenroc handrail at west
side terrace from
mechanical shaft south to
ahndicap access (137 lf)
and associated concrete
footing/retaining wall

(45,000)

Rejected

16.01

6/12/2000

Precast south utility tunnel


in lieu of cast in place

(170,000)

Approved

Cannot accept
with 15.01

16.02

6/12/2000

Sleeves versus concrete


for utility tunnel.

N/A

see 15.01

Subtotal Site

AMOUNT

ACTION

COMMENTS

(205,000)

Approved

(121,000)

Pending

(123,000)

Rejected

(449,000)

Total

(60,000)

Approved

adjust duration
to 14 months

N/A

No value in
current market

General Conditions and Scope


17.01

6/12/2000

Refine tower crane


duration/size/cost, move
to GC's.

17.02

6/12/2000

Adjust escalation.

17.03

6/12/2000

Take 6'-0" off south end of


Building X (approximately
1,000 gsf).

(30,000)

Rejected

17.04

6/12/2000

Eliminate
bridge/interaction space at
Building Y Atrium on 3rd
floor (+/- 500 sf).

(27,000)

Rejected

Facilities Project Managers Guide

Page 147

Compnay A

Building X

VALUE ENGINEERING/COST ADJUSTMENTS

Cornell University June 21, 2000

NO

DATE

DESCRIPTION

17.05

6/12/2000

Eliminate bridge
connection between
Building Y and at the 3rd
floor level.

(35,000)

Rejected

17.06

6/12/2000

Eliminate bridge
connection between
Building Y and at 2nd
level

(35,000)

Rejected

17.07

6/12/2000

Build Chem. Tunnel in


Phase 2, use Stair #3 to
acccess/egress from
basement level. Use
Elevator #4 as temporary
service elevator and serve
Building X through west
entry until completion of
tunnel in Phase 2
(demolition of Company
E) is complete.

N/A

included with
9.11

17.08

6/12/2000

Move service elevator and


dumbwaiters outside of
Building Y footprint (into
Atrium).

N/A

included in 9.11

17.09

6/12/2000

Delay renovation to
Building Y 1st floor. Use
chemical storage trailers
at exterior. Perform
renovation as part of
donor or grant proposal
build out (by future
occupants, companies,
etc.)

N/A

Sacred Program
compromise

17.10

6/12/2000

Delete owner/architect
trailer rental/setup/utilities.

Approved

Target some
savings from
$26,500;
perhaps utilize
larger
contractor
trailer

17.11

6/12/2000

Reduce Kitchen/vending

N/A

17.12

6/12/2000

Abandon the flex office


concept.

N/A

Facilities Project Managers Guide

AMOUNT

(13,000)

ACTION

COMMENTS

Page 148

Compnay A

Building X

VALUE ENGINEERING/COST ADJUSTMENTS

Cornell University June 21, 2000

NO

DATE

DESCRIPTION

17.13

6/12/2000

Reduce basement size by


using some of Company E
lab basement for
incidental mechanical
items.

N/A

included in
other items

17.14

6/12/2000

Basement smaller,
penthouse bigger to cut
down on rock excavation.

N/A

too late in
design

17.15

6/12/2000

Shorten time frame by


early occupation of clean
room.

General Conditions and Scope Summary

AMOUNT

ACTION

COMMENTS

Pending

(73,000)

Approved
Pending

(127,000)

Rejected

(200,000)

Total
W/ 15 %
markup

Total Summary

(2,638,201)

Approved
(3,033,931)

(542,000)

Pending
(623,300)

(2,138,000)

Rejected
(2,458,700)

(5,318,201)

Total
(6,115,931)

Summary

Facilities Project Managers Guide

DD Estimate

$43,341,000

Budget

$39,000,000

Delta

$4,341,000

Approved VE W/ markup

($3,033,931)

Current Delta

$1,307,069

Page 149

Sample Construction Development 50 Value Engineering


Company A
VALUE ENGINEERING/COST ADJUSTMENTS

Building X Hall
Cornell University
(date)

NO

ACTION

DATE

DESCRIPTION

AMOUNT

Don't forget to hide these


columns

COMMENTS

1 - Foundations

Approved

Pending

Rejected

1.01

11/30/2000

Review Rock
Excavation
Quantity

$
20,000

Approved

Provide trench for


laterals/pit

20000

1.02

11/30/2000

Review MEP
Trench excavtion in
rock

$
(124,794)

Approved

Provide all MEP


rock excavation by
sitework

-124794

1.03

11/30/2000

Review bank
shoring - unrealized VE of
$235K

$
(200,000)

Approved

Company
C/company B qtys
- 9,900 sf

-200000

1.04

11/30/2000

Verify underdrain
quantity at
basement slab

$
(20,000)

Approved

ABC to validate
700 lf quantity with
geotech

-20000

1.04a

11/30/2000

Review
requirement for
underdrains at
basement slab

$
(24,000)

Pending

ABC to validate
requirement with
geotech

-24000

20000

3 - Floor and Roof Structures


3.01

11/30/2000

Add penthouse
structure to
Building Y for
HVAC equipment

$
20,000

Approved

3.02

11/30/2000

Revise atrium
structural steel
pricing to
$3200/ton

$
(46,000)

Approved

-46000

3.03

11/30/2000

Review concrete
pan slab pricing target savings

$
(50,000)

Approved

-50000

3.03 A

12/7/2000

Eliminate all 4"


distribution ribs at
pans slab

$
(5,000)

Approved

-5000

3.03 B

12/7/2000

Revise pan slab


layout to eliminate
20" wide pans

$
(15,000)

Rejected

-15000

3.04

11/30/2000

Delete fireproofing
at penthouse steel

$
(41,800)

Rejected

-41800

3.05

11/30/2000

Delete fireproofing
at upper atrium
steel and/or
bridges

$
(16,000)

Approved

-16000

4 - Enclosure
Facilities Project Managers Guide

Page 150

Company A
VALUE ENGINEERING/COST ADJUSTMENTS

Building X Hall
Cornell University
(date)

NO

DATE

DESCRIPTION

ACTION

COMMENTS

4.01

11/30/2000

Adjust unit pricing


for curtain
walls/support steel
at atruim

Pending

ABC to refine
design for future
cost review

AMOUNT
$
-

Don't forget to hide these


columns

ABC to refine
design for future
cost review

4.02

11/30/2000

Adjust unit price for


curtain
walls/support steel
at Dufflied

$
-

Pending

4.03

11/30/2000

Revise north entry


to existing Building
Y - existing to
remain

$
(32,000)

Pending

-32000

4.04

11/30/2000

Revise exterior
caulking scope

$
(15,000)

Approved

-15000

5 - Roofing and Waterproofing


5.01

11/30/2000

Provide
membrane
roofing as 0.060
EPDM unreinforced fully
adhered with
design average
R-value

$
(20,000)

Approved

-20000

5.02

11/30/2000

Revise smoke
vents at
stairwell roofs

$
7,000

Approved

7000

5.03

11/30/2000

Fluid applied vs.


membrane
foundation
waterproofing

$
(16,000)

Approved

-16000

6 - Interior Partitions
6.01

11/30/2000

Pending

$
-

Pending

7 - Floor, Wall and Ceiling Finishes


7.01

11/30/2000

Revise slate wall


material/thickness
from mechanically
fastened to
adhered

$
(42,000)

Approved

Confirm unit
pricing

-42000

7.02

11/30/2000

Revise source of
slate materials

$
(72,000)

Approved

Vermont Slate

D/A

-72000

7.03

11/30/2000

Review clean room


ceiling
quantites/details at
partitions

$
-

Pending

16192 sf per ABC

7.04

11/30/2000

Review clean room


ceiling support
system under

$
-

Pending

Company A to
verify estimate

Facilities Project Managers Guide

Page 151

Company A
VALUE ENGINEERING/COST ADJUSTMENTS

Building X Hall
Cornell University
(date)

NO

ACTION

DATE

DESCRIPTION

AMOUNT

Don't forget to hide these


columns

COMMENTS

recirc units and


ductwork
7.05

11/30/2000

Revise Mech room


B0070 floor to clear
sealer

$
(17,000)

Approved

-17000

7.06

11/30/2000

Delete ceiling grid


at clean room
furnace area

$
(14,117)

Approved

-14117

-102545

8 - Function Equipment and Specialties


8.01

11/30/2000

Reduce quantity
of lab casework
and equipment
to 85% DD VE
scope

$
(102,545)

Approved

8.01 A

12/8/2000

Delete coldroom
- move to fitout
costs

$
(45,000)

Approved

8.02

11/30/2000

Review lab
casework unit
pricing

$
-

Pending

8.03

11/30/2000

Add gas
cylinder
restraints at labs

$
-

Rejected

8.04

11/30/2000

Revise window
treatment unit
pricing

$
(40,000)

Approved

-40000

8.05

11/30/2000

Reivew
projection
screen vs.
marker board
quantities

$
(8,000)

Approved

-8000

-45000

Still have 6000 sf


at $5/sf

9 - Vertical Transportation and Stairs


9.01

11/30/2000

Reduce freight
elevator
capacity from
7000# to 5000#
for #1 and #4

$
(135,000)

Pending

Changes openings
and door heights
and arrangements

D/A

-135000

9.02

11/30/2000

Provide direct
purchase of
dumbwaiters

$
(20,000)

Approved

Need vendor
quotes

D/P

-20000

$
(826,456)

Approved

$
(191,000)

Pending

$
(56,800)

Rejected

$
(1,074,256)

Total

Subtotal Architectural

Facilities Project Managers Guide

Page 152

Company A
VALUE ENGINEERING/COST ADJUSTMENTS

Building X Hall
Cornell University
(date)

NO

DATE

DESCRIPTION

ACTION

10.01

11/30/2000

Reduce misc.
plumbing R/I's
quantity from 100
to 50

10.02

11/30/2000

Revise Laboratory
air compressor

10.03

11/30/2000

Provide
mechanical joint
pipe at under 3"
vents for acid
waste piping

10.04

11/30/2000

10.05

AMOUNT
$
(10,649)

Don't forget to hide these


columns

COMMENTS

Approved

-10649

Pending

$
(10,562)

Approved

-10562

Provide
mechanical joint
pipe at under 3"
drains for acid
waste piping

w/10.03

Approved

w/10.03

11/30/2000

Provide welded
stainless steel
nitrogen piping for
clean roon

$
30,000

Pending

Bob to pursue as
vendor provided

30000

10.06

11/30/2000

Delete fire wrap on


plastic pipe in
plenums ((DI, acid
waste)

$
(15,900)

Approved

Need sprinklers on
ceiling plenum at
cleanroom

-15900

10.07

11/30/2000

Revise cost per


Company Dl
pricing

all

10.08

11/30/2000

Provide kitchen
equipment roughins

$
20,000

Approved

D/P

20000

10.09

11/30/2000

Delete tool hook-up


piping - provide as
fit-out (DI, vacuum,
air, nitrogen)

$
(92,914)

Rejected

-92914

10.10

11/30/2000

Bore permanent
Building Y water
feed from Building
X thru to Building Y
basement

Pending

10.11

11/30/2000

Future drain
locations above
clean-rooms

Approved

10000

10.12

11/30/2000

Simplify cleanroom fit-out

10.13

11/30/2000

Delete automatic
flush valves

$
(14,076)

Approved

-14076

10.14

11/30/2000

Delete domestic
water booster
pump

$
(9,700)

Approved

-9700

10.15

11/30/2000

Delete vacuum to
2nd and 3rd floor
labs

$
(40,000)

Approved

-40000

10.16

11/30/2000

Pending

$
10,000

Pending

Facilities Project Managers Guide

No exhaust

Cornell to confirm
scope

Page 153

Company A
VALUE ENGINEERING/COST ADJUSTMENTS

Building X Hall
Cornell University
(date)

NO

ACTION

DATE

DESCRIPTION

Subtotal Plumbing

AMOUNT

Don't forget to hide these


columns

COMMENTS
0

-200000

Rejected

Approved

-54000

Pending

D/A

-27089

-10000

$
(60,238)

Approved

$
30,000

Pending

$
(92,914)

Rejected

$
(123,152)

Total

Approved

11- HVAC
11.01

11/30/2000

Revise cost per


Company D
pricing

11.02

11/30/2000

Change FRP
duct to alternate
material

$
(200,000)

11.03

11/30/2000

Revise
loacations for
FRP duct

w/11.02

11.04

11/30/2000

Delete FRP duct


connections to
hood - provide
with fit-out

11.05

11/30/2000

Utilize standard
valves in lieu of
process quality
valves and
controls at recirc air units at
clean room quantity of 24
(all but RAHU
2/3)

11.06

11/30/2000

Provide
competitve
controls bidding

11.07

11/30/2000

Revise smoke
exhaust duct in
atrium

$
(40,000)

Approved

11.08

11/30/2000

Eliminate
cooling at
bridges

$
(27,089)

Approved

11.09

11/30/2000

Review costs for


temporary air
intake relocation
(only needed 2
months per
Cornell)

$
(10,000)

Approved

$
(54,000)

Facilities Project Managers Guide

(name) to confirm
pricing

(name) to review
BR+A drawings

Review schedule

Page 154

Company A
VALUE ENGINEERING/COST ADJUSTMENTS

Building X Hall
Cornell University
(date)

NO

ACTION

DATE

DESCRIPTION

AMOUNT

11.10

11/30/2000

Spark resistant
vs. explosion
proof motors at
exhast fans

$
(2,000)

Approved

11.11

11/30/2000

Add flying fintube heating of


curtain walls no cover

$
18,000

Approved

11.12

11/30/2000

Bore permanent
Building Y
steam feed and
condensate
return from
Building X thru
to Building Y
basement

11.13

11/30/2000

Delete clean
room process
cooling fit-out

$
(65,286)

Rejected

11.14

11/30/2000

Delete lap-top
computer with
full graphical
software
package

$
(5,000)

Approved

11.15

11/30/2000

Delete training
instructions per
specifications

$
(10,000)

Pending

11.16

11/30/2000

Provide
laboratory
quality in lieu of
process quality
temperature
transmitters
(except for
RAHU 2/3)

$
(12,000)

Approved

11.17

11/30/2000

Change silane
duct from SS
304 welded to
galvanized
spiral

$
(42,824)

Approved

11.18

11/30/2000

Delete
recirculating
pumps at 24
RAHU's

$
(33,000)

Pending

COMMENTS

Need drawings
from A/E

Pending

11.19

11/30/2000

Change class of
instructional lab
from 1000 to
10,000

$
(27,000)

Approved

11.20

11/30/2000

Adjust chilled
water and
condensate
meters

$
8,000

Approved

Facilities Project Managers Guide

Don't forget to hide these


columns

confirm pricing of
revised spec

review load calcs

-2000

18000

-65286

-5000

-10000

-12000

-42824

-33000

8000

Page 155

Company A
VALUE ENGINEERING/COST ADJUSTMENTS

Building X Hall
Cornell University
(date)

NO

DATE

ACTION

COMMENTS

11.21

11/30/2000

Change vacuum
pump exhaust
duct riser from
20 to 12 inch
diameter

$
-

Pending

(name) to confirm
pricing

11.22

11/30/2000

Change outside
air plenumbs
from SS to
galvanized G90
except for the
bottom panel

$
(4,700)

Approved

11.23

11/30/2000

AHU-2, 3 & PH1 to be double


wall in lieu of
single wall

$
50,250

Approved

11.24

11/30/2000

$
-

Pending

$
(281,363)

Approved

$
(43,000)

Pending

$
(65,286)

Rejected

$
(389,649)

Total

DESCRIPTION

Subtotal HVAC

AMOUNT

Don't forget to hide these


columns

(name) to confirm
with Trane

-4700

50250

12 - Electrical
12.01

11/30/2000

Delete lab
equipment
connections

$
(75,583)

Approved

-75583

12.02

11/30/2000

Provide solid
bottom/covered
cable tray vs.
ladder type

$
(17,000)

Approved

-17000

12.03

11/30/2000

Revise pricing
of light pipe at
Atrium

$
-

Rejected

Cornell to
prepurchase

12.04

11/30/2000

Revise power
pole pricing at
offices

$
-

Approved

No data - (name)
to price

12.05

11/30/2000

Review
Company E
demolition costs

$
(20,000)

Approved

-20000

12.06

11/30/2000

Owner to
provide
tele/data wiring

$
(34,000)

Approved

all

-34000

12.07

11/30/2000

Provide kitchen
equipment
rough-ins

$
10,000

Approved

D/A

10000

12.08

11/30/2000

Increase power
and data outlets
at Atrium

$
9,450

Approved

9450

Facilities Project Managers Guide

Page 156

Company A
VALUE ENGINEERING/COST ADJUSTMENTS

Building X Hall
Cornell University
(date)

NO

DATE

ACTION

COMMENTS

12.09

11/30/2000

Approved

(name) to review
pricing

DESCRIPTION
Delete remote
ballasts at ebeam rooms
and utilize
incandescent

AMOUNT
$
-

12.10

11/30/2000

Class A wiring
for initiating
devices not
required - use
class B

$
(10,000)

Approved

12.11

11/30/2000

Change 600
kcmil to 500
kcmil up to
800A, eliminate
special devices

$
(20,000)

Approved

12.12

11/30/2000

Delete witness
testing on
transformer and
generator

$
(15,000)

Approved

12.13

11/30/2000

Delete impulse
testing on
transformers,
provide data for
similar
equipment

12.13

11/30/2000

Utilize aluminum
in lieu of copper
at switchgear,
panels, etc.

12.14

11/30/2000

COMPANY A delete limit 6


buckets per
vertical stack

Subtotal Electrical

$
(1,000)

Revises to
standard breakers
at 80%

Approved

Pending

$
(2,000)

Don't forget to hide these


columns

(name) to price

Approved

$
(175,133)

Approved

$
-

Pending

$
-

Rejected

$
(175,133)

Total

$
(31,306)

Approved

-10000

-20000

-15000

-1000

-2000

-31306

-6700

13 - Fire Protection
13.01

13.02

11/30/2000

11/30/2000

Eliminate flex
heads at clean
rooms

Provide Sch. 10
vs. Sch. 40

$
(6,700)

Facilities Project Managers Guide

Approved

BR+A to review
details for ability to
change hepas

D/A

Page 157

Company A
VALUE ENGINEERING/COST ADJUSTMENTS

Building X Hall
Cornell University
(date)

NO

ACTION

DATE

DESCRIPTION

AMOUNT

Don't forget to hide these


columns

COMMENTS

piping

13.03

13.04

13.05

11/30/2000

11/30/2000

11/30/2000

Verify no
sidewall heads
at skylights

Add pre-action
system to Ebeam rooms

Delete Preaction system to


Characterization

Subtotal Fire Protection

$
-

$
40,000

$
(41,000)

Pending

Rejected

BR+A to review

Estimate include
preaction at
Characterization

Pending

$
(38,006)

Approved

$
(41,000)

Pending

$
40,000

Rejected

$
(39,006)

Total

40000

-41000

15 - Sitework
15.01

11/30/2000

Revise routing
for emergency
generator thru
Building Y Hall

$
(85,000)

Approved

BR+A and
Lemessuir to
review routing,
Company A to
price

-85000

15.02

11/30/2000

Revise routing
for tele/data
ductbank thru
Building Y Hall

$
(50,000)

Approved

Need design
information from
BR+A

-50000

15.03

11/30/2000

Provide on-site
stockpiling of
excavated
materials to be
re-used/filled

$
(5,000)

Rejected

Discuss with
Company M,
potential location
at equestrian
building

-5000

15.04

11/30/2000

Revise natural
gas
piping/NYSEG
allowance $40,000

Pending

Costich to
evaluate

15.05

11/30/2000

Review
concrete vault
removal costs

$
-

Pending

Company A to
evaluate

15.06

11/30/2000

Review site
painting cost of
$25K

$
(10,000)

Approved

-10000

Facilities Project Managers Guide

Page 158

Company A
VALUE ENGINEERING/COST ADJUSTMENTS

Building X Hall
Cornell University
(date)

NO

DATE

ACTION

COMMENTS

15.07

11/30/2000

Review
dumping costs
for Company E
and Building Y

$
(20,000)

Pending

Company A to
evaluate

-20000

15.08

11/30/2000

Add SDR-21
liner to 16" DIP
sanitary sewer
under Atrium

$
-

Pending

(name) to review
with (name)

15.09

11/30/2000

Provide clean
corridor and
elevation
adjustment for
access between
clean rooms in
Company E and
Building X

$
-

Pending

Review at future
CNF move
strategy meeting

15.10

11/30/2000

Delete or
change Gothic
lights

$
(21,000)

Approved

-21000

15.11

11/30/2000

Revise pricing
for bulk Nitrogen
tank piping

$
(4,000)

Pending

-4000

15.12

11/30/2000

Add temporary
stairs for south
Building Y
during
construction

$
5,000

Approved

5000

15.13

11/30/2000

Add temporary
dock for CNF
move

$
5,000

Pending

Review at future
CNF move
strategy meeting

5000

15.14

11/30/2000

Revise pricing
for bulk Nitrogen
tank systems

$
(25,000)

Pending

(comments)

-25000

15.15

11/30/2000

Temporary
HRM storage
facility

$
-

Pending

(comments)

15.16

11/30/2000

Revmove cost
of stairs and
bollards at
loading dock
and site signage

$
(19,000)

Approved

-19000

15.17

11/30/2000

Eliminate
benches

$
(10,600)

Approved

-10600

15.18

11/30/2000

Delete special
shoring

$
(10,000)

Approved

-10000

15.19

11/30/2000

Delete
duplication on
Gothic lights on
wall

$
(56,250)

Approved

-56250

DESCRIPTION

AMOUNT

$
(256,850)

Approved

Pending

Facilities Project Managers Guide

(comments)

Don't forget to hide these


columns

Page 159

Company A
VALUE ENGINEERING/COST ADJUSTMENTS

Building X Hall
Cornell University
(date)

NO

ACTION

DATE

DESCRIPTION

AMOUNT

Don't forget to hide these


columns

COMMENTS

(44,000)
$
(5,000)

Rejected

$
(305,850)

Total

17 - General Conditions and Scope


17.01

11/30/2000

Review moving
CNF to Building
X with 100%
shutdown of
Company E as
soon as Duffiled
cleanroom is on
line and
validated

$
-

Pending

17.02

11/30/2000

Provide unit
prices for lab fitout work a
reduce fit-out
work included in
construction

$
-

17.03

11/30/2000

Revise General
Conditions
estimate

17.04

11/30/2000

Reduce
contingency to
2.5%

General Conditions and Scope


Summary

Review at future
CNF move
strategy meeting

Pending

$
(50,000)

Approved

-50000

$
(358,149)

Pending

-358149

$
(50,000)

Approved

$
(358,149)

Pending

$
-

Rejected

$
(408,149)

Total
App/pend
(2,521,782)

Total Summary

$
(1,698,695)

Approved

$
(647,149)

Pending

$
(180,000)

Rejected

$
(2,525,844)

Total

(1,826,097)
(695,685)
(193,500)

50% CD Estimate

Facilities Project Managers Guide

(2,715,282)

$42,017,447

Page 160

Company A
VALUE ENGINEERING/COST ADJUSTMENTS

Building X Hall
Cornell University
(date)

NO

ACTION

Summary

DATE

DESCRIPTION

AMOUNT

COMMENTS

Budget

$39,100,000

Delta

$2,917,447

Approved VE W/ markup

($1,826,097)

Current Delta

$1,091,350

Facilities Project Managers Guide

Don't forget to hide these


columns

Page 161

Sample Change Order Letter


DATE:

June 8, 1998

TO:

(name)
(name at C&CP)

FROM:

Project manager

SUBJECT:

X Project
Change Order #6, Contract # C
X Construction Company

Please process Change Order #6 to the Guaranteed Maximum Cost (GMC) agreement between Cornell
and the Company G contract #C, dated , to cover the following detailed in the attached
documentation:
The following Potential Change Orders (PCOs) were due to Design Changes:
PCO

General Description

COW

149

Added type FAG light fixtures not indicated on


drawings

167

Fee

Amount

$7,965

$159

$8,124

RFI#404 -- Foot grill size increase

$807

$16

$823

174

ASI#110a - Relocation of floor boxes in


classrooms

$20,743

$415

$21,158

216

Change to ACT-4, ceiling tile in classrooms

$3,444

$69

$3,513

218

Upgrade brackets & standards in 20 faculty


offices

$3,905

$78

$3,983

236

Add 8 ceiling cruciforms in classrooms at


projectors

$5,317

$106

$5,423

243

Upgrade concrete and asphalt walks to CU


standards

$13,718

$274

$13,992

248

RFI#423-Provide (12) 2" circuit setters

$2,526

$51

$2,577

253

RFI#618-Relocate classroom equipment

$2,550

$51

$2,601

254

Finials atop vaulted roof

$1,369

$27

$1,396

269

Gold Leaf on signature stones

$1,505

$30

$1,535

Total PCOs due to Design Changes:

$63,849

$1,276

$65,125

Facilities Project Managers Guide

GC's

Page 162

The following PCO was due to a Scheduled Allowance Adjustment:


PCO
General Description
COW
GC's
Fee
114

Spire Allowance Adj.

$66,828

The following PCOs were Owner Directed:


PCO
General Description
COW

Amount

$8,483

$1,337

$76,648

GC's

Fee

Amount

217

Change shelving to bookcases in 40


faculty offices

$143,280

$2,866

$146,146

225

Wood ceiling in Exec Ed classroom


141

$8,435

$169

$8,604

244

ASI#123-Added concrete walks

$8,473

$169

$8,642

255

Delete mow strip

($4,500)

262

Added locks at storm windows per CU $2,065

$41

$2,106

266

Additional receptacles in telephone


closets per CU

$4,337

$87

$4,424

273

Telecom Tie-in to Dover Elevator

$1,413

$28

$1,441

Total PCOs due to Owner Directed:

$163,503

$3,360

$166,863

Fee

Amount

The following PCOs were due to Unforeseen Conditions:


PCO
General Description
COW
GC's

($4,500)

081

Existing Floor Joist Work per


RFI#316

$1,049

$21

$1,070

104

Remove existing plank at roof edge


for blocking

$693

$14

$707

116

Unforeseen at Projected Dormer

$2,073

$41

$2,114

185

Window jamb extensions

$28,456

$569

$29,025

222

Upgrade parking lot to CU standard

$34,402

$688

$35,090

$1,333

$68,006

PCOs due to Unforeseen Conditions: $66,673

Facilities Project Managers Guide

Page 163

The following table summarizes Change Order #5 costs and the impact to the GMC line items:
Item

Current

Change

Unforeseen Conditions

$68,006.00

Scheduled Allowance Adj.

76,648.00

CU Directed Changes

166,863.00

Design Changes

65,125.00

Revised

Cost Of Work

$23,680,821.00

$360,853.00

$24,041,674.00

General Conditions

$2,216,869.00

8,483.00

$2,225,352.00

Fee

$902,851.00

7,306.00

$910,157.00

Total GMC

$26,800,541.00

$376,642.00

$27,177,183.00

Additionally, retainage reduction to zero is requested for various . subcontractors:


Original
Final
Retainage
Retainage
Contract
Contract
Reduction
Company
Trade
Held
Amount
Amount
Request
(name)

Spire Steel Fab

$19,900

$19,900

$1,990

$1,990

(name)

Spire Erection,
etc.

$43,954

$43,954

$4,779

$4,779

(name)

Fireproofing

$228,375

$280,914

$28,247

$28,247

(name)

Scaffolding

$288,680

$314,621

$31,462

$31,462

(name)

Auto Closing
Doors

$82,616

$86,386

$4,319

$4,319

(name)

Accordion Doors

$52,173

$52,173

$5,217

$5,217

(name)

Telephone Spec. $4,800

$4,800

$480

$480

(name)

Signage

$4,091

$4,091

$409

$409

(name)

Libr. Security
Sys.

$13,145

$13,145

$1,314

$1,314

(name)

Access Flooring

$4,500

$4,500

$225

$225

(name)

Microfiche
Cabinets

$14,928

$14,928

$1,492

$1,492

(name)

Historic Moldings $5,940

$5,940

$594

$594

(name)

Refrigerators

$1,088

$1,088

$108

$108

(name)

Louvers

$5,041

$5,041

$504

$504

(name)

Library Book
Drop

$2,133

$2,133

$213

$213

Facilities Project Managers Guide

Page 164

Company
(name)

Trade
Foot Grilles

Original
Contract
Amount
$5,900

Final
Contract
Amount
$16,457

Retainage
Held
$1,645

Retainage
Reduction
Request
$1,645

If you have any questions or require additional documentation, please let me know.
Thank you.
Attachments

xc:

Facilities Project Managers Guide

Page 165

You might also like