Professional Documents
Culture Documents
TWO-RIVERS PROJECT
Date: 22
nd
August 2014
INTRODUCTION
Where slabs are continuous over beam edges, top rebar which stretches
into
onthe
thatnegative moments normally over the
beamboth
waspanels
noted meeting
to counter
whole length of that support.
At mid spans on both directions, main rebar is placed at bottom where
high bending moments dominate.
Particular note was made on the reinforcement at discontinuous edges
of
slabsachieved
where a by
double
layer was
noted,
u-bending
of bottom rebar for a distance into the
span
(ascracking
top rebar).
is done
to
prevent
dueThis
to some
torsional
action (as
on the
stipulated
edges on the BS8110-pt1 clause 3.5.3.5)
Flat Slabs
These are slabs bearing on columns or column heads with drops, unlike
in
thebear
conventional
slabs
on beamspractice where
These slabs are reinforced in strips- in theory idealized as column strips
and middle
strips
running
in theoflong
span
and short
span
(two way)
the panels.
Each strip is reinforced like a beam.
The middle and column strips were distinct, their reinforcement being
done individually.
The main rebar for each strip (middle and column strips both directions)
was
at the on
support
zonesplaced
and atonthetop
bottom
the mid spans. This is due to the fact that
negative
dominate
the dominate over mid-spans.
supports moments
and positive
saggingover
moments
At points where these rebar groups meet, tension and compression laps
are provided.
Main reinforcement bars are carried through the column drop and
nominal
the drop.rebar provided at the bottom of
At the column-slab interfaces, shear links in single legs were also noted,
bent around
bottom
rebar in the
drop
and topthe
main
reinforcement
of the slab. These links are put around
the
critical
perimeters
to these supports.
counter
theshear
high shear
around
Beams
Beams are members designed primarily for flexure.
In the field reinforcement is checked in mid spans and at supports.
Whereare
internal
high
supports.
tiedshear
across
Tension
is expected,
the whole
laps as
are
span
inprovided
the
of beam
regions
atbeing
regions
nearclosely
thewhere
supports
spaced
the rebar
innearis
For
a
beam,
main
reinforcement
is
placed
at
the
bottom
around
the
mid
no
predominates.
highly
bars
Links
longer
from
supports
loaded
needed.
the beam
beams
where
sloping
there
high shear
are
into the columns around the support. span and at top of beam
bentover
up
5.
6.
7.
8.
9.
bonding. Also, at some instances, the bent up bars near columns are so
dense
no concrete can pass
through
The slabs reinforcement bars are meandering losing the linearity
between
sections
Too manystraight
openings
in beams most of which are in critical regions near
supports
and at
Some beams
hadmid-spans.
as many as 18 pipe openings each approx. 200mm dia(
6mid
at each
support and six at
support).
What could be the impact of these openings on the capacity of
concrete
in such
regions?
The flat slabs
on the
mall, first floor, had the steel bars terminated at
critical
regions
(at for
midstrips).
spans and
on top of
supports
Rebar has been continuously lapped on
top
of supports
without
staggering
which
could lead to weak moment links.
The formwork of the 1200mm deep column pads was not well tie d
leading
wedge-like
facesofdue
bulging to
unde
r the loading
thetolarge pour of concrete.
Some beams had been reinforced (beam 1) before full issuance of
drawings
RECOMMENDATION
Supervision should be provided on site to ensure quality of work is as
per
the design.
Such will
such
unexpected
omissions
andprevent
their repetition.
It should be ensured that all works on going are as per drawings issued
and
no work progresses without
drawings
Foremen should accompany their gangs for direction and guidance
Frequent site visits will be good to follow the progress.
CONCLUSION
I was able to appreciate design and the need for supervision in any
engineering
It done,
was clear
that while
designs maywork.
be well
without
supervision there is a risk of not
achieving what the designs stipulate.
I was also happy to see workmanship in the field where practical
knowledge coupled with theory is needed.
Am so thankful for that opportunity.