Professional Documents
Culture Documents
Norazliani Md Sapari
University of Malaya Power Energy
Dedicated Advanced Centre (UMPEDAC),
Level 4, Wisma R&D, 59990,
Kuala Lumpur, Malaysia.
rapidly and the situation can lead to the system collapse. The
frequency however can be restored by shedding certain
amount of load so that the system is back into equilibrium.
This method is called Under-Frequency Load Shedding
(UFLS).
I.
INTRODUCTION
488
2014 IEEE 8th International Power Engineering and Optimization Conference (PEOCO2014), Langkawi, The Jewel of Kedah,
Malaysia. 24-25 March 2014
489
2014 IEEE 8th International Power Engineering and Optimization Conference (PEOCO2014), Langkawi, The Jewel of Kedah,
Malaysia. 24-25 March 2014
START
TABLE 1
LOAD RANKING TABLE
Is distribution
network islanded?
Load
Name
Base Load
Peak Load
Load
Category
P
(MW)
Q
(MVAR)
P
(MW)
Q
(MVAR)
L1
0.0585
0.0372
0.0762
0.0471
L2
0.0798
0.0495
0.1038
0.0642
L3
0.1680
0.1042
0.2184
0.1353
L4
0.1878
0.1098
0.2204
0.1458
L5
0.3918
0.2427
0.4524
0.2756
L6
0.5178
0.3210
0.6058
0.3673
Vital
L7
0.5598
0.3468
0.6427
0.4009
Vital
1.9635
1.2112
2.3197
1.4362
NO
YES
Load
Ranked
TOTAL
Non
Vital
Non
Vital
Non
Vital
Semi
Vital
Semi
Vital
NO
III.
YES
A. Case Studies
The cases are tested on the test system as in Figure 4.
During grid connected, a total power of 1.78 MW is
dispatched by the generator with the remaining power is
dispatched by the grid. During islanding, the load in the
island is only supplied by a mini hydro generator (DG). In
an attempt to test UFLS technique, an intentional islanding
is simulated with the opening of incoming grid substation
breaker at time t=10.5 seconds (s). Load L4 is temporarily
disconnected from the system and only reconnected at
simulation time t=25.5s. Three cases are evaluated: base
load, peak load and overload case.
END
B. Test Network
a) Test system
The test system as shown in Figure 4 was modeled
using PSCAD software. The system consists 7 buses, 8
lumped load with 2 MVA mini hydro generation operated
at 3.3kV. The DG is connected via generator transformer
which step up the voltage level to 11.0kV. The distribution
network is connected to the main grid via two parallel step
up transformer (33kV/11kV) which is rated at 20MVA. This
test system has 17 remotes circuit breaker (RCB). That RCB
consists of a DG breaker, an islanded breaker, 2 breakers for
incoming grid substation, 8 breakers for load feeder and 5
breakers for additional breaker. The network was designed
using standard model of synchronous generator, exciter and
governor provided in PSCAD library.
b) Load
Based on test network, there are 7 loads (L1-L7)
and 1 addload (more explanation in section III) connected to
the network. The load is categorized into non-vital, semivital and vital as shown in Table 1. Non-vital load category
is less important load compared to semi-vital load and vital
load is the most important load in the system. The load will
be shed according to priority of load where less important
load will be shed first.
3
490
2014 IEEE 8th International Power Engineering and Optimization Conference (PEOCO2014), Langkawi, The Jewel of Kedah,
Malaysia. 24-25 March 2014
s
for base load
Figure 5 : System frequency response without load shedding
Figure 6 : System frequency response with load shhedding for base load
491
2014 IEEE 8th International Power Engineering and Optimization Conference (PEOCO2014), Langkawi, The Jewel of Kedah,
Malaysia. 24-25 March 2014
Figure 9 : System frequency response with load shhedding for peak load
IV.
TABLE 2
OPTIMAL LOAD SHEDDING BY LSCM
L
Load Case
Base Load
Peak Load
Overload
0.0871
0.4275
0.2613
0.0585
0.3984
0.2478
CON
NCLUSION
c) Overload scenario
In this case, an overload scenario is simulated
s
for base
case study. In contrast to base case, an
a additional load
referred as Addload (P=0.300MW and Q=
=0.1857MVAR) is
connected to the network at time t=45.55s. Obviously, the
excess of load would lead to frequency instability, unless
load shedding is performed. LSCM perform
m load shedding if
the estimated value of power imbalance exxceeds the unused
capacity of generator. In this case, two looad i.e L2 and L3
are shed. As a result, the frequency respponse manages to
restore. It is observed from the results thatt, the estimation of
ACKNOWLEEDGEMENT
This work was supportted by the University of
Technology MARA, Malaysiia under RIF grant project
(Grant Code: 600-RMI/DANA 5/3/RIF(366/2012)).
492
2014 IEEE 8th International Power Engineering and Optimization Conference (PEOCO2014), Langkawi, The Jewel of Kedah,
Malaysia. 24-25 March 2014
REFERENCES
[1]
[2]
[3]
[4]
[5]
[6]
[7]
[8]
[9]
[10]
493