Professional Documents
Culture Documents
Date: 24.07.2014
Prepared by:
Gensol Consultants Pvt Ltd,
108, Pinnacle Business Park,
Corporate Road, Prahaladnagar,
Ahmedabad, Gujarat-380015
Page 1 of 111
Disclaimer Notice
This document has been prepared for M/S Today Green Energy Pvt. Ltd. (the Client) only and
solely for the purpose stated in the contract (the Contract) between Gensol Consultants Pvt Ltd
(the Consultant) and the Client.
Page 2 of 111
Contents
GLOSSARY ...............................................................................................................................................................8
ABBREVIATIONS ..................................................................................................................................................10
EXECUTIVE SUMMARY......................................................................................................................................12
PROJECT AT A GLANCE ....................................................................................................................................16
1.
INTRODUCTION ..................................................................................................................................18
1.1 ABOUT TODAY GREEN ENERGY PRIVATE LIMITED ORGANIZATION ................................................................18
1.2 ABOUT PROJECT CONSULTANT........................................................................................................................19
1.3 SCOPE OF SERVICES FOR DPR .........................................................................................................................20
2.
3.
4.
5.
6.
Page 3 of 111
8.
9.
10.
Page 6 of 111
List of Figures
Figure 1: Seismic zone of India .............................................................................................................................33
Figure 2 Location of site .........................................................................................................................................34
Figure 3 Solar Resource Map of India .................................................................................................................39
Figure 4 Typical solar PV system components ...................................................................................................41
Figure 5 Mono-Crystalline Silicon Module ...........................................................................................................43
Figure 6 Multi-Crystalline Silicon Module ............................................................................................................43
Figure 7 Thin film PV module ................................................................................................................................44
Figure 8 Block diagram showing interconnection of various systems .............................................................58
Figure 9 Typical photovoltaic solar module .........................................................................................................59
Figure 10 Typical Solar Inverter ............................................................................................................................60
Figure 11 Typical Fixed tilt module mounting structure .....................................................................................61
Figure 12 Typical Control Room Section .............................................................................................................65
Figure 13 Tilt angle optimization snapshot from PVsyst ...................................................................................73
Figure 14 Sun path for the proposed location .....................................................................................................74
Figure 15: Organizational Chart ............................................................................................................................82
Page 7 of 111
GLOSSARY
Photovoltaic
PV Cell
PV Module
Array
Inverter
Insolation
Mounting Structure
Power Evacuation
Sub-station
Control Room
Cable
Junction Box
Current
Page 8 of 111
Voltage
Lightning
Arrestor
Transformer
Grid
SCADA
Page 9 of 111
ABBREVIATIONS
General
ACB
AC
Alternate current
ACSR
BOS
CO2
Carbon Dioxide
CT
Current Transformer
DC
Direct Current
DP
Double Pole
DPR
HT
High Tension
LT
Low Tension
LV
Low Voltage
MNRE
SECI
KWh
MCB
PLF/ CUF
PPA
PV
Photo Voltaic
PT
Power Transformer
VCB
XLPE
Page 10 of 111
Units
%
Percentage
Degree Centigrade
Kg
Kilogram
kV
Kilo-Volt
kW
kilo Watt
kWp
Lt
Liter
Meter
m2
Square meter
m3
Cubic meter
Tons
Tons
Page 11 of 111
EXECUTIVE SUMMARY
Today Green Energy Private Limited (TGEPL) is a SPV company promoted by Today
Homes & Infrastructure Private Limited (THIPL), a Group Today Company planning to
put up large scale Solar power projects at strategic locations suitable for Solar power
generation across India.
THIPL, is a well-established enterprise in the field of Real Estate Development with a
number of Residential, Retail and Commercial projects Delivered and Under
Development. Apart from real estate the THIPL is also in the business of Hospitality.
Over a period of next 5 years, the Company is committed to set up facilities to generate
more than 5000 MW of power, coal-based and renewable sources. The expansion will
be fuelled by setting up Greenfield projects as well as expansion in existing power plants.
THIPL has been declared as a successful bidder in the bid process against the Rfs No
SECI/JNNSM/SPV/P-2/B-1/Rfs/102013 issued by Solar Energy Corporation of India
(SECI) and had been issued Letter of Intents.
THIPL has formed a Project Company TGEPL for the development of Solar Power
Projects. In this regards, TGEPL is going to install a 20 MW (2x10MW) solar PV plant,
under the Open Category, at village That, situated in Jaisalmer district of Rajasthan state.
The geographical location of the project site is 26.840544 N and 71.818534 E. For the
proposed project approx. 115 acres of the land will be required.
Radiation profile of the location has been assessed using the industry standard
Meteonorm software and the electricity generation has been estimated. 255 Wp (or
higher) capacity poly-crystalline technology based PV modules are suggested for the
proposed solar plant. The basis of selection of poly-crystalline technology is its financial
competitiveness, long term stability and easy availability. Further, on the basis of basic
design engineering, 1000 kW solar inverter units are proposed and 20 nos. of inverters
shall be required for the plant. This project shall be using fixed tilt module mounting
structures for the installation of PV modules. With such arrangement, it is projected that
the proposed 20 MW project will operate at a CUF around 22.29% and will be generating
around 39, 048,487 kWh units per year. Probability analysis has also been presented in
the DPR at the P50, P75 and P90 probability level.
Page 12 of 111
The generated electricity from the solar PV plant will be evacuated in the dedicated 132
kV grid substation situated 12 kms from the project site. TGEPL has signed a PPA at flat
rate of Rs. 5.45/ kWh for life time of the project, which is considered as 25 years, with
Solar Energy Corporation of India (SECI).
The project cost of the envisaged 20 MW (AC) PV Plant is estimated to be Rs. 15070
Lakhs. Debt equity ratio of the investment is 70:30 and debt equity amount for this ratio
is Rs. 10549 lakhs and Rs. 4521 lakhs respectively. The project will receive VGF funding
to the tune of Rs. 2190 lakhs. Furthermore, considering the financial analysis, it is
projected that investment in the proposed project will give a project IRR of 11.81%.
Average Debt Service Coverage Ratio (ADSCR) of the proposed investment is worked
out to be 1.45.
Apart from the financial benefits the solar power plant also helps to reduce the release
of carbondioxide produced by fossil fuel generation. The project converts solar radiation
into useful electricity, adding to sustainability of the project and the local environment.
Besides all these concerns, this report highlights the details of the proposed power
generation scheme, site facilities, solar radiation in the proposed site location and water,
evacuation of generated power, features of main plant and equipment including the
inverter system, electrical systems, environmental aspects, estimate of capital cost and
the financial analysis and the schedule for project implementation.
Group Company Today Homes & Infrastructure Pvt. Ltd. (THIPL) located at Delhi is
a well established enterprise in the field of Real Estate Development and Hospitality with
numbers of Residential, Retail and Commercial projects already developed and the rest
are under development.
Further in 2007 Today Homes & Infrastructure Pvt. Ltd. (THIPL) has diversified in
the Power Sector and form a company Today Energy (MP) Pvt Ltd.(TEMPPL)
promoted by Today Homes & Infrastructure Pvt Ltd.(THIPL) to set up 1320 MW
(2x660 MW) coal based Thermal Power Plant (IPP) at village Silari, Tehsil Gotegaon,
Dist. Narsinghpur, Madhya Pradesh. The details of the project is given below:
Page 13 of 111
I)
Land: Total land acquired is appox. 750 acres at Distt Narsinghpur in the State
of Madhya Pradesh (M.P.), which is sufficient, as per CEA norms for 1320
(2x660) MW coal based thermal Power Project with Supercritical technology.
a) Private Land appox 685.54 Acres of land in continuous stretch for the project
has been purchased directly from the land owners through consent route and is
in our possession.
b) Government land of 64.15 Acres has been allocated vide GoMP Revenue
Deptt. Order No. F16-41/2008/7/2A Bhopal dated 31.03.2011.
No forest land is involved.
II)
Firm allocation of 40 cusec of water has been granted by Water Resource Dept.
(WRD), GoMP.
III)
Coal:
(A) Coal linkage for one unit of 660 MW has been tied up with the State of Madhya
Pradesh.
(B) In addition, Central Electricity Authority (CEA) Standing Committee has
recommended the name of project company i.e. Today Energy (M.P.) Pvt Ltd
(TEMPPL) with maximum marks i.e. 90 (ninety) to Ministry of Power (MoP)
which has further recommended to Ministry of Coal (MoC). It is expected that
long term coal linkage shall be allocated to TEMPPL by Long Term Linkage
Committee shortly.
IV)
Page 14 of 111
V)
VI)
VII)
Open Access The Bulk Power Transmission Agreement for 800 MW entered
into with Power Grid Corporation of India Ltd.
VIII)
Chimney Height Clearance from Airports Authority of India has been accorded.
IX)
Defence Clearance has been obtained from Defence Estate Office, Jabalpur
Circle.
X)
XI)
Power Evacuation: In the past few years there was no procurement inspite of big
demand supply gap from various State Utilities because of the financial
constraints. The Central Government has approved a big financial package to
carry out the financial restructuring of the State Utilities. This has resulted into the
starting of the power procurement by such Utilities to meet their deficiency in
power. Recent bids have been in the range of Rs. 4/-kWh to Rs. 5/-kWh. Since
the fuel has been tied up, we are contemplating to participate in the various power
purchase bids being invited by various state Utilities. Some of them are already in
pipeline.
Page 15 of 111
PROJECT AT A GLANCE
Project Developer
Selected Location
Site Co-ordinates
1974.7 kWh/m2
Tariff details
Annual degradation
1%
Poly Crystalline
255 Wp
No. of modules
MS Galvanised
1000 kW
No. of inverters
20 Nos.
Inverters make
ABB
22.29 %
39,048,487 kWh
15070
4521
10549
Page 16 of 111
2190
Project IRR
11.81%
Equity IRR
14.01%
Land
Power Evacuation
Mode of Implementation
Page 17 of 111
1. INTRODUCTION
This report is referred to as the Detailed Project Report for installation of 20 MW (AC)
Photovoltaic (PV) Plant at village That, Tehsil Pokharan, District Jaisalmer, Rajasthan
(Project Site or Site). The report is prepared by Gensol Consultants Private Limited
having been appointed as the Project Consultant for the client with the intention to
provide a detailed project pre-feasibility analysis and advisory. This report includes the
feasibility studies, system design and techno-commercial analysis for installation of the
PV plant.
1.1 About Today Green Energy Private Limited Organization
Today Green Energy Private Limited. (TGEPL) is a company promoted by Today Homes
& Infrastructure Private Limited, a Group Today Company planning to increase its energy
portfolio in the renewable energy sector in India.
Today Homes & Infrastructure Pvt Ltd. is a well established enterprise in the field of Real
Estate Development with a number of Residential, Retail and Commercial projects
Delivered and Under Development. Apart from real estate the Group Today is also in the
business of Hospitality.
Over a period of next 5 years, the Company is committed to set up facilities to generate
more than 5000 MW of power, largely coal-based. The expansion will be fuelled by
setting up Greenfield projects as well as extension in existing power plants. Discussions
at various levels with concerned authorities are already in progress.
The power projects are planned to be diverse in geographic location, fuel type, fuel
source & off take, and each project is planned to be strategically located near an
available fuel supply load center.
Power generated from these units will be sold under the combination of long term and
short term PPAs to state owned/private distribution companies and industrial consumers.
Discussions are already in progress.
Page 18 of 111
Gensol Solar Division, set up in early months of 2009 is dedicated to using technology,
engineering and innovation to give its clients the best returns on their capital. It is with
this view that we strive to provide support and engineering expertise to clients and
investors in Solar Power Sector through our offerings of complete concept to
commissioning advisory services for MW scale grid-connected and off grid standalone
solar power projects. Gensol Solar Team boasts of years of on-ground experience in
setting up of Solar Power Plants. Comprising of Electrical, Civil and Mechanical
Engineers on one hand and Financial and Regulatory Consultants on the other, Gensol
Solar team presents a unique blend of technological expertise with market intelligence,
thus, helping us provide a 360o perspective to clients.
Gensol Consultants is empanelled with various lending institutions and Ministry of New
and Renewable Energy. Gensol also hold the distinction of representing Ministry of
Environment and Forestry (MoEF) at International Forums.
Page 19 of 111
Page 20 of 111
2. INDUSTRY OUTLOOK
2.1 Background of the project
THIPL had participated in the JNNSM Phase II Batch I solar bid conducted by Solar
Energy Corporation of India (SECI). In the bid results THIPL has been allotted a total of
5 PV projects of 10 MW capacity each. Out of this, 2 PV projects of 10 MW each i.e.
20MW are under open category and 3 PV projects of 10 MW each i.e. 30MW are under
the DCR category. THIPL has formed a Project Company TGEPL for the development
of Solar Power Projects. This DPR is meant for Open category i.e. 20MW. TGEPL board
has decided to install 2 x10 MW project capacity, near village That, Pokharan. Electricity
sale arrangement has already been done by signing a long term PPA with SECI at Rs.
5.45/ kWh for the 25 years.
This project will be executed with an EPC (Engineering, Procurement and Construction)
partner. TGEPL will invest 30% of the total project cost as equity investment and rest of
the money which is 70% of the project cost shall be arranged from a financial institution
as debt.
2.2 Objective and benefits of the project
The objective of the proposed solar power plant is to generate clean energy from the
solar radiation using photovoltaic phenomenon. This energy will be evacuated to the
nearby grid and further distributed in the electricity network. Solar energy is a clean
source of electricity and produces no pollution. Hence, there are many social economic
benefits are associate with the development of this project.
Hydro 17%
Nuclear
2%
Thermal
68%
Page 22 of 111
RES 25%
Hydro
11%
Thermal
60%
Nuclear
4%
1http://www.cea.nic.in/reports/monthly/inst_capacity/dec13.pdf
2http://www.cea.nic.in/reports/yearly/lgbr_report.pdf
Page 23 of 111
Energy in MU
Requirement (MU)
Availability (MU)
Page 25 of 111
Page 26 of 111
State Policies
Individual states like Gujarat, Rajasthan, Karnataka and
Madhya Pradesh have released their own policies to set
up Solar PV Power Plants in the respective states
The Jawaharlal Nehru National Solar Mission is a major initiative of the Government of
India with active participation from States to promote ecologically sustainable growth
while addressing Indias energy security challenge. It will also constitute a major
contribution by India to the global effort to meet the challenges of climate change. The
objective of the Mission is to establish India as a global leader in solar energy, by creating
the policy conditions for its large scale diffusion across the country as quickly as possible.
The Mission has set a target, amongst others, for deployment of grid connected solar
power capacity of 20,000 MW by 2022 and is planned to be implemented in three phases
with phase-1 by 2013, phase-2 by 2017 and phase 3 by 2022. Against the targets for
phase 1, major achievements include the following:
Page 27 of 111
The entire capacity of 1,100 MW of grid connected solar power has been allocated.
The sanctioned capacity for off grid applications is over 118 MW.
No direct financial assistance is provided by the government for setting up solar power
projects connected to the grid. One scheme of 1000 MW has been implemented through
a mechanism of bundling of solar power with thermal power from unallocated quota of
the Government. For projects connected to less than 33 kV grid, a scheme of generation
based incentive has been implemented under which a total of 98 MW capacity projects
were allotted.
To support deployment of off-grid solar applications, the Government provides capital
subsidy upto 30% of the benchmark cost and / or soft loan at a rate of 5% interest.
Since launch of the JNNSM, the capacity of grid-connected solar power projects has
grown from 8 MW in January 2010 to over 2208 MW 4 by January 2014 in the country.
Recently, MNRE has established the Solar Energy Corporation of India (SECI) for
handling the power procurement from the second batch of the JNNSM. SECI (MNRE)s
role would be limited to providing a subsidy known as Viability Gap Funding (VGF), which
is basically a part payment, made by SECI to the project developer in order to make the
project viable. MNRE has recently unveiled guidelines for allocation of solar power
project worth 750 MW under the VGF route, out of which, half if earmarked for projects
opting for cells and modules of domestic origin.
State Policies
Subsequent to the launch of the JNNSM, many states have acknowledged the
importance of solar energy and hence formulated their own respective policies regarding
the same. Solar potential with their installed capacities for the states which have released
the solar policies have been summarized in the following table:
Summary of solar potential, state policy targets and installed capacities in the states of India5
S.No.
State
Average
Solar
Annual
Govt. Policy/Target
Resource
Installed
PV
Capacity (MW)
(kWh/m2/day)
1)
Rajasthan
5.0-6.3
666.75
12000 MW capacity by
2022.
2)
Gujarat
5.2-6.0
500 MW by 2014
860.4
3)
Karnataka
4.6-5.8
200 MW by 2016
31
4)
Tamil Nadu
4.8-5.8
3000 MW of power by
31.82
2015
5)
Andhra Pradesh
4.8-5.8
97.2 MW sanctioned
92.9
6)
Madhya Pradesh
5.0-5.6
500 MW by 2013
195.32
7)
Chhattisgarh
5.0-5.6
500-1000 MW by March
5.1
2017
8)
Maharashtra
4.6-5.6
No
declared
specific
target
state-
237.25
other
9)
Uttar Pradesh
4.6-5.2
1000 MW by 2017
17.38
10)
Punjab
4.6-5.1
300 MW in Phase-I
9.33
11)
Haryana
4.7-5.3
No
declared
solar
7.8
solar
5.05
solar
16
solar
7.05
solar
15.5
solar
3.01
solar
5.1
solar
1.62
specific policy
12)
Uttarakhand
3.8-5.7
No
declared
specific policy
13)
Jharkhand
4.7-5.5
No
declared
specific policy
14)
West Bengal
4.2-5.1
No
declared
specific policy
15)
Odisha
5.1-5.5
No
declared
specific policy
16)
Delhi
4.7-5.1
No
declared
specific policy
17)
18)
Andaman
and
4.7-5.1
No
declared
Nicobar
specific policy
Others
No
declared
specific policy
Total
2208 MW
Page 30 of 111
The policy aims at developing Rajasthan as a global hub of solar power of 10,00012,000 MW capacity in next 10-12 years to meet energy requirements of Rajasthan
and India. To achieve grid parity in next 7-8 years, the State will encourage the Solar
Power Developers to establish manufacturing plant of their technology in Rajasthan.
The Rajasthan State will promote setting up of solar power projects for direct sale to
Discoms of Rajasthan. The total capacity under this category will be distributed equally
between SPV and CSP based power plants. The total maximum capacity under this
category for phase-1 (up to 2013) and phase-2 (2013-2017) would be as follows:-
200 MW
400 MW (Additional)
Selection of these Solar Power Projects shall be through tariff based competitive
bidding process. The State Government may undertake the review of targets mentioned
above as and when the need arises in view of any technological breakthrough resulting
in substantial decrease in cost of Solar Power generation. The Rajasthan State will also
promote Solar Power Producers to set up Solar Power Plants of unlimited capacity for
captive use or sale of power to 3rd party/States other than Rajasthan. The State will
also promote deployment of Roof Top and Other Small Solar Power Plants connected
to LT/11kV Grid as per guidelines of MNRE under Rooftop PV & Small Solar Generation
Programme (RPSSGP) of NSM and orders of appropriate Regulatory Commission.
Page 31 of 111
Page 32 of 111
Page 33 of 111
1.1.1.1.1.1
Page 34 of 111
The site selection for a solar power plant is pre-dominantly determined by solar insolation
availability & grid connectivity for exporting power. Equally important are other essential
factors/considerations such as:
Availability of adequate land for power plant and green belt development
Page 35 of 111
The site receives scanty rainfall annually around 308.5 mm. Rainfall occurs mainly in the
months of June, July, August and September.
115.63
86.8
32.7
4.65
6.16
4.65
5.7
8.68
Jan
Feb
Mar
Apr
May
32.1
8.68
Jun
Jul
Aug
Sep
Oct
0.9
1.86
Nov
Dec
Page 36 of 111
The interconnection cables are routed within the structure and the output cables from
the modules are taken through proper size conduit to the String Combiner Box (SCB).
The output cables from the SCBs are routed under the ground through conduits or cable
trenches. Earthing for the entire module mounting structures will be done using copper
or GI conductors. The earth pits for module area will be provided as the electrical
standards. In order to protect the modules from lightning, lightning protection will be
provided in the module mounting area. Sufficient number of lightning arrestors will be
provided in this area alone for protection of modules.
The layout of the array structures shall be so designed that it shall occupy minimum
space without sacrificing the output of Solar PV modules.
Page 37 of 111
Irradiance. The diffused sunlight can vary from about 20% on a clear day to 100% in
heavily overcast conditions. The peak irradiance of 1,000 W/m 2 is taken as the standard
value in the industry by which PV modules are rated. However, the total solar energy
received in a day over a specific area, called daily solar irradiance or insolation, is more
important
than the instantaneous solar irradiance. The solar resource is not equally
available in all regions of the world hence a site specific solar resource assessment is
required for every project.
6.2 Indias Solar Radiation Profile
India being a tropical country is blessed with good sunshine over most parts, and the
number of clear sunny days in a year also being quite high. The country receives solar
energy equivalent to more than 5,000 trillion kWh per year. Indias equivalent solar
energy potential is about 6,000 million GWh of energy per year. Being a tropical country,
India is blessed with good sunshine over most parts, and the number of clear sunny days
in a year also being quite high.
The daily average global radiation is around 5.0 kWh/m2 in north-eastern and hilly areas
to about 7.0 kWh/m2 in western regions and cold desert areas with the sunshine hours
ranging between 2300 and 3200 per year. In most parts of India, clear sunny weather is
experienced for 250 to 300 days a year. The annual global radiation varies from 1600 to
2200 kWh/m2. Following figure presents the global solar radiation map of India jointly
developed by MNRE and NREL.
Page 38 of 111
Page 39 of 111
Average horizontal solar radiation at the site comes out to be 5.41 kWh/m2/day as per
meteonorm data. Monthly averages of the same data are given as follows:
Table 1: Solar Insolation, temperature and wind speed data for the site
Page 40 of 111
7. SELECTION OF TECHNOLOGY
Photovoltaic comprises the technology to convert sunlight directly into electricity. The
term photo means light and voltaic, electricity. A photovoltaic (PV) cell, also known as
solar cell, is a semiconductor device that generates electricity when light falls on it.
Since its first commercial use in powering orbital satellites of the US space programs in
the 1950s, PV has made significant progress with total photovoltaic module industry
growing at more than 40% in the past decade.
The PV modules combined with a set of additional application-dependent system
components (e.g. inverters, batteries, electrical components, and mounting systems),
form a PV system. These PV systems are highly modular, i.e. modules can be linked
together to provide power ranging from a few watts to tens of megawatts (MW).
The solar PV panels typically produce DC electricity that is fed to a grid interactive
inverter, which in turn converts the DC electricity into AC electricity at a required voltage
level. In order to achieve a higher system voltage, the output of inverters is fed to step
up transformers to increase the voltage levels at the desired level. From the transformer,
the power is routed through the high voltage panel and eventually to other required
measuring & protection devices before connecting to the grid. The major equipment and
components of a typical solar plant are shown in the following figure.
Page 41 of 111
Page 42 of 111
Multi-Crystalline Silicon
Multi-crystalline (or poly-crystal) silicon panels are made by using polycrystalline wafers.
Multi crystalline wafers consists of number of crystallites with different grain sizes will be
having grain boundaries and several defects. Multi-crystalline Si growth is relatively
cheaper than the mono crystalline Si and the cells made up of these wafers are relatively
cheaper. Due to the less pure crystals, the efficiency of these cells reduces and the
module efficiencies typically range in between 14-16%. The lifetime of these modules is
also around 25 years or more and these panels are cheaper option where the space is
not a limitation. These panels are commonly preferred ones for grid connected
applications.
7.1.2 Thin Film Technology
Thin film modules are potentially cheaper to manufacture than crystalline cells have a
wider customer appeal as design elements due to their homogeneous appearance
present. Disadvantages include low-conversion efficiencies and requiring larger areas of
PV arrays and more material (cables, support structures) to produce the same amount
of electricity.
Page 43 of 111
Parameter
Crystalline
1)
Types of Materials
Poly-crystalline,
Thin Film
mono-
crystalline silicon
2)
Handling
Better
protection
against
breakage
3)
Power Efficiency
13-21.5%
7-13%
4)
Technology
Well Developed
Well Developed
5)
Module Weight
6)
Area utilization
7)
Temperature Effects
variations
variations
radiations
radiations
8)
Irradiance
Page 44 of 111
9)
Module quantity
10)
Output
per
MW
High
Higher
installed
11)
Land Requirement
12)
Cost
13)
Environment Effects
Less Sensitive
Sensitive
14)
Stabilization
stages
months
15)
Availability
Easily available
Easily available
16)
Power Degradation
Less degradation
17)
Plant Maintenance
18)
Repair
Relatively easy
Easy
19)
Cooling Requirement
Required
Not required
20)
Cabling
Easy installation
Easy installation
21)
Good
Good
Tech.
a-Si
CdTe
CIS/CIGS
1)
Lesser degradation
Lesser degradation
Page 45 of 111
2)
3)
4)
Spectral Sensitivity
towards short wavelength
Page 46 of 111
Inverter is the heart of a solar power project. It is also known as Power Conditioning Unit
(PCU). A PCU consists of an electronic Inverter along with associated control, protection
and data logging devices. Typically the utility scale inverters are unidirectional and supply
the power to the grid in the form of AC power conforming to IEC 61727 or equivalent
standard. The inverter has a feature that it automatically adjusts with the grid conditions
such as the voltage & frequency levels to suit the Grid. It is advised that following key
points can be considered while specifying your inverter requirements to various vendors.
a) Proven Technology: The inverter should be selected based on the proven
technology and it is advisable that the inverter has completed at least one year
successful operation in the high temperature weather conditions and fluctuating grid
conditions.
b) Grid Compliance: At times you may require changing some of the key parameters
of the inverters to match with your local grid conditions, hence the inverter should
have features of changing some of the threshold parameters, and it can be
programmed accordingly. It should also have features of grid islanding through Air
Circuit Breakers. Some of the new generation inverters have provision of self
protective and self diagnostic features so that it can protect itself from the PV array
faults and adjust with the changing parameters of the solar PV array. The Inverter
should have provisions of automatically wake up in the morning and begin to export
power provided there is sufficient solar energy and the grid voltage and frequency is
in range.
Page 47 of 111
The inverter should have MPPT control algorithm in such a way that it adjust itself
with the voltage of the SPV array to optimize solar energy fed into the grid. The MPPT
must have provision for constant voltage operation. The inverter MPPT feature
should comply with EN50530 or Equivalent standard.
The inverter output always follows the grid in terms of voltage and frequency. This
should be achieved by sensing the grid voltage and phase and feeding this
information to the feedback loop of the inverter. Thus control variable then controls
the output voltage and frequency of the inverter, so that inverter is always
synchronized with the grid.
c) Inverter Efficiency: The efficiency of the inverter is another key factor, and most of
the inverters are available in the efficiency range of about 97-98% efficiency levels.
However it is important to make a note of the inverter efficiency at the part load
conditions. Typically the part load efficiency levels are more than 97 % at 75% load
as per IEC 61683 or equivalent standard. It is important to assess the inverter
efficiency levels at different load say 25%, 50%, 75% and 100% and it should meet
the IEC 61683 standard.
d) Control and Protection: The inverter should have internal protection arrangement
against any sustained fault in the feeder line and against lightning in the feeder line.
It should also have the required protection arrangements against earth leakage faults.
The inverter should also have suitable rated DC disconnecting arrangement to allow
safe start up and shut down of the system. Inverter should also have required
protection arrangements against reverse polarity of DC Connection. There should be
suitable surge protection arrangement to pass the fault current to earthing
system. During the earth fault condition, the inverter should be having provision of
disconnection.
The inverter should have suitable display panels so that all important parameters
such as DC input voltage, DC input current, all phase to phase AC voltages , all phase
AC current, AC output power, frequency , apparent power , reactive power etc are
visible to the plant operators. Some of the inverters come with a suitable PCU with
display, and can be connected to the SCADA system.
During the sleep mode the inverter should be having the automatic control provisions
so that the threshold dc voltage of the inverter can decide the inverter to enter in
sleep mode and back to standby mode. The inverter must also automatically re-enter
standby mode when threshold of standby mode.
The standard warranty of these inverters is 5 to 10 years. However many inverter
manufacturer offer extended warranty also considering string inverter is a costlier
proposition as compared to a central inverter, however an apple to apple comparison
can only be made consideration of not only cost per watt of string versus central, but
also cost reduction of DC cables and other associated benefits such as reduced down
time in case of string inverter.
The central inverter takes input from number of arrays and operates at single MPP.
Hence the inverter MPP (maximum power point) is governed by the arrays which are
having partial shading ,mismatch losses , modules with tolerances which may lead to
reduce output in case of central inverter. However this can be reduced by selection
of string inverter as different strings have different MPP so that the output is
maximized.
7.5 Cabling
a) DC Cables and Connectors: Working with solar PV arrays can be hazardous since
Solar panels connected together in an array are often configured to produce high DC
voltage. Furthermore, DC voltages are constant in nature so, effect of electric shock
due to DC voltage will surely be severe. Hence, DC Cables should be double
insulated and polarized and DC connectors should always be used. The minimum
technical requirements for Cables laid down by MNRE states that they should
conform to General Test and Measuring Method PVC insulated cables for working
voltage up to and including 1100 V and UV resistant for outdoor installation
Page 49 of 111
(Standard: IEC 60227 / IS 694 IEC 60502 / IS 1554 (Pt. I & II)). However, operating
temperatures at the proposed Solar PV plant are expected to be high. Additionally,
the corrosive conditions at the site would put the cable strength to test. Therefore,
Electron beam cross-linked DC cables, though marginally costlier, may be used.
Adequate size of cable is selected for minimal voltage drop i.e. maximum voltage
drops in the string designed to be around 1%.
b) AC Cables: In order to make the system more reliable and facilitate maintenance
and management, output of three phase AC cables from the inverter are connected
to AC disconnector unit. The voltage output of the inverter is connected to the
transformer using required rating LT cables to step up the voltage. From the
transformer, the lines are connected to grid. AC cables sizing are designed to achieve
less than 1% of AC voltage drop from inverter to transformer. However, size of cable
varies by relative position of inverter, transformer and grid supply lines.
7.6 Module Mounting System
Solar PV modules are mounted on the structure, generally casted of galvanized steel.
Designing of mounting structure is majorly depended on two factors namely orientation
scheme and wind load. In case orientation scheme is sun tracking scheme (Single
tracking or duel tracking) then scope of movement in the tiled part of the structure is
provided. Generally, this movement is achieved through a motor.
Second important consideration in the design of mounting structures is the nature of wind
loads in the proposed location, taking into cognizance any seasonal /local winds that
may exert additional load. Accordingly, the concrete blocks are to be designed to counter
balance the load. This is done through STAAD Pro analysis or Field flow analysis. In
addition, the material of the structure is to be selected in such a way that it serves at
least for 25 years. In general galvanized steel is used to make the structures. The
mounting structures shall be designed as per the soil and wind conditions at the site.
However the typical practice is to design mounting structure to withstand a wind load of
160-170 km/hr. The support structure design & foundation shall also be designed to
withstand wind speed applicable for the site conditions. Nut & bolts, supporting structures
Page 50 of 111
Page 51 of 111
Page 52 of 111
c) Other Clearances
Sanction of construction power from the office of Chief Engineer of the respective state
Electricity Utility and permission to use ground water if applicable.
Table 3: List of Clearances required for PV Projects in Rajasthan
S.No.
Responsible
Agency
Items
Tentative
Date
RRECL
Zero + 10
RRECL
Between Seller
& Buyer
RRECL
Zero + 25
Panchayat
Zero + 30
RVPNL
Zero + 45
RVPNL
RVPNL
Zero + 60
Zero + 75
Energy Minister
Zero + 75
10
Allotment of Bay
RVPNL
Zero + 75
11
Local Discom
Zero + 75
12
Metering Approval
Local Discom
Zero + 75
13
REC Accreditation
Zero + 90
14
RRECL
District Collector
Office
15
RDPPC
Zero + 100
16
PCB
Zero + 100
17
CEI
Zero + 110
18
RVPNL
Zero + 110
19
RDPPC
Zero + 110
20
RRECL
Zero + 110
21
NLDC
Zero + 110
22
REC Registration
Certificate of Commissioning - Nodal Agency/ Local
Agency
RRECL
Zero + 120
23
MNRE
RRECL
24
PCB
5
6
7
8
Zero
Zero + 20
Zero + 90
&
Ongoing
Basis
Zero + 150
Page 53 of 111
Power evacuation facility in the vicinity of the proposed site along with grid
availability on 24 Hours a day basis.
Details of the design process and are presented in the below sections.
9.1 Design and Simulation projections by PVSYST
PVSYST tool is one of the most accepted design tool for the study, sizing, simulation
and data analysis of complete PV systems. We have used this tool to generate the most
realistic energy yield simulation results, which are detailed in this report. Main features
of PVSYST:
1.
2.
3.
4.
Most accepted and used tool to generate simulation results for PV power plants,
as the results are based on systematic and refined approach.
5.
Program with the most accurate results and functions available in the market.
Page 54 of 111
1.
2.
The mounting and orientation of the system (i.e., flat, fixed-tilt, tracking, etc.)
3.
4.
5.
6.
2.
3.
Page 55 of 111
4.
5.
6.
Logs system data and error messages for further processing or storing.
7.
Stores and visualizes energy yield data (for life of the plant) in the portal from
where the data can be accessed remotely.
Page 56 of 111
Solar PV Modules
Page 57 of 111
Central inverters
Monitoring system
SCADA
A simple block diagram, related to the interconnection of various systems for grid
connectivity, is shown below for reference. The power from modules is directed to the
central inverters through the DC combiner boxes and from the inverters it is routed
though the Low voltage panel to the transformer. From the transformer, the high voltage
power is routed to the metering panel and eventually to grid through the High Voltage
Panel.
Parameter
Value
9.00 A
8.43 A
-0.43%/0C
37.4 V
30.2 V
Page 59 of 111
In the proposed project the inverters will connect string of modules (each module of 255
Wp (0,+5). The output of the strings will be connected to an ABB_Multi_MPPT 1000 kW
inverter (Specification sheet enclosed in Annexure-III). 20 inverters are required (10 nos
each for the two10 MW blocks). The inverter converts the DC Power into AC power and
feeds it to the grid. The inverters are designed with a high efficiency >98% with IGBT
technology. It has a provision to deliver the maximum power generated through solar
modules in to grid due to its in-built feature of MPPT operations. The inverter is having
internal self-protection in case of any fault in the grid in addition to the inbuilt
contactors/breakers with fuses for self-protections.
The inverters are self-synchronizing with the utility (grid) power with respect to the
Voltage and frequency of grid and it gets corrected itself according to the grid parameters
within its settable limits. The inverter is designed in such a way that it will sense the array
power and grid power; if both are available it starts and stops automatically in the
morning and evening respectively. Each inverter is having a remote and local data
monitoring system with which we can monitor all the parameters and current energy
generation & past generation for the given period. The output voltage of the inverter shall
be connected to a step-up transformer of 0.400/33 KV.
Page 60 of 111
Parameter
Value
600V
850 V
1000 V
Output voltage
400 V
Maximum Efficiency
98.6%
Page 61 of 111
Foundations and structures shall be designed in view of the following standards with a
minimal safety factor of 1.5:
IS-875-1987 (PART-2)
SP-16
SP-34
Reinforced detailing
Page 62 of 111
Logs system data and error messages for further processing or storing
Stores and visualizes energy yield data (for life of the plant) in the Portal from
where the data can be accessed remotely.
SCADA
The instrumentation & control system for the solar power plant will be based on the
prevailing standard engineering practices
Design will ensure full compliances of codes and standards as applicable the field of
instrumentation & control for power plant
The whole plant will be operated through SCADA system
a. The SCADA system shall have the following features:
Monitoring: Ability to control, using specially designed devices, the state &
evolution of one or various physiologic (or others) parameters to detect
possible malfunctions
Remote control: Group of devices which allow modifying the state of the
equipment and devices of the plant, from a remote location
b. The SCADA system shall be used for the following minimum tasks:
c. The SCADA System will be reliable and robust and some components need
redundancy for trouble free operation
10.6 Cables and Connectors
The size of the cables between array interconnections, array to junction boxes, junction
boxes to PCU etc shall be so selected to keep the voltage drop and losses to the
Page 63 of 111
minimum. The bright annealed 99.97% pure bare copper conductors that offer low
conductor resistance, they result in lower heating thereby increase in life and savings in
power consumption. These wires are insulated with a special grade PVC compound
formulated. The skin coloration offers high insulation resistance and long life. Cables are
flexible & of annealed electrolytic grade copper conductor and shall confirm to IS
1554/694-1990 and are extremely robust and resist high mechanical load and abrasion.
Cable is of high temperature resistance and excellent weather proofing characteristics
which provides a long service life to the cables used in large scale projects. The
connectors/lugs of copper material with high current capacity and easy mode of
assembly are proposed.
10.7 Buildings for Plant Equipment (Inverter Rooms and Control Room)
Concrete or pre-fabricated buildings will be utilized for housing the inverters, Low Voltage
panels, High Tension panels, Plant Monitoring system, Safety equipment, Office room
etc.
The buildings will be equipped with all necessary safety equipment as per the safety
rules and shall be appropriately ventilated. The equipment will be erected as per the
Indian Electrical Standards. The cables will be routed through cables trenches or cable
trays as required. Alarm system will be provided to alert the operator in case of
emergency or plant break-down.
The proposed power transformer will be installed outside next to the main control room.
The civil engineering and building works shall include the design, detailing, and
construction of all foundations, structures, buildings, installation and service of facilities
required for the installation, commissioning, operation and maintenance of all equipment
associated with the power plant.
The civil works includes preliminaries, additional survey, soil exploration, piling
if
Page 65 of 111
33kV Transformer Oil immersed type with Off circuit tap changer with all
accessories
132kV Power Transformer Oil immersed type with Off circuit tap changer with
all accessories
LT & HT cables
11.2 Transformers
The proposed transformer shall be installed outdoor suitable for hot, humid and tropical
climate. The transformer will be free from annoying hum and vibration when it is in
operation, even at 10% higher voltage over the rated voltage. The noise level will be in
accordance with respective standards.
Page 66 of 111
The transformer will be designed and constructed so as not to cause any undesirable
interference in radio or communication circuits. The oil filled transformer will be capable
of operating continuously at its rated output without exceeding the temperature rise limits
as given below over design ambient temperature of 50 deg C.
The transformer will be designed to withstand without injury, the thermal and mechanical
effect of short circuit at its terminal with full voltage maintained behind it for a period of 1
second. The transformer will be capable of continuous operation at the rated output
under voltage and frequency variation without injurious heating at that particular tap for
all tap positions.
Phase connections will be delta on LV side and star on HV side. HV side shall be
resistance earthed. HV side shall be suitable for connection to HT panels for the
respective transformers. LV side shall be suitable for connection to LV panel.
Transformer will be designed for over fluxing withstand capability of 110% continuous
and 125% for at least 1 minute. Further it shall be capable of withstanding 140% of rated
voltage at the transformer LV terminal for a period of 5 seconds to take into account
sudden load throw off conditions.
Overloads will be allowed within conditions defined in the loading guide of applicable
standard. Under these conditions, no limitations by terminal bushings, off circuit tap
changers or other auxiliary equipment shall apply.
11.3 132 kV Switchyard
A 132kV Switchyard has been envisaged for evacuation of power through Step up
Transformers for the proposed plant. The switchyard shall be located in adjacent to
Central Control Building. The switchyard shall be interconnected with the 132 kV grid
Substation by means of overhead conductor.
Switchyard equipment:
Page 67 of 111
a) Circuit beakers
The circuit breakers and accessories will be in general conforming to IEC: 600 56, IS
60947 Part I,II,III, EN 50521 and IS:13118 as applicable. The circuit breaker will be totally
re-strike free under all the duty conditions and will be capable of breaking magnetizing
current of transformer and capacitive current of unloaded overhead lines without causing
over voltages of abnormal magnitudes.
b) Disconnecting Switches
Electric motor operated center rotating post horizontal double break triple pole
disconnecting switch with or without earth switch will be provided. Operation of the
disconnecting switch will be interlocked with associated breaker and earth switch.
c) Current Transformers
Live or dead tank type single phase multi-core multi ratio current transformers will be
provided for indication, metering and protection requirements. Accuracy of tariff metering
cores shall not be less than Class 0.2. Separate CT cores will be provided for Main and
Check Tariff Metering
Page 68 of 111
g) Plant DC System
To supply power to various unit / loads, the following DC Systems (one main and one
standby) have been envisaged for the proposed plant:
The Battery and Battery Charger System shall be installed with float & float cum boost
charger for HT& the LT Control Building at different locations inside the plant area. The
battery & charger shall cater to all the DC loads of the respective building which mainly
comprises of DC lighting load, Control supply for the switchgears etc.
h) Battery
The battery shall be of storage type Valve Regulated Lead Acid Type (VRLA) battery
(Conforming to IS: 1652) or Nickel Cadmium (Ni-Cd) type. The Battery shall be high
discharge performance type. The plates shall be designed for maximum durability during
all service conditions including high rate of discharge & rapid fluctuation of load. For the
purpose of design, an ambient temperature of 50C and relative humidity of 85% shall
be considered.
i) Battery Chargers
Battery charger for each battery will be one number float & float cum boost charger of
suitable capacity for quick boost and trickle charging as well as supplying the DC loads.
The battery chargers will be of silicon controlled rectifier type completely automatic and
self-regulating type. The float charger will be capable of floating the battery and at the
same time supply the continuous DC load. The boost charger will be capable of charging
the fully discharged battery to full charge.
11.4 HT, LV, 33KV and 132kV Metering Equipment
Under the normal climatic and earthquake conditions, the HT and LV panels will meet
the following requirements:
1.
The physical alignment of switchgear panel along with incoming and outgoing feeder
connections, supporting insulators & structures of bus bars will not get disturbed and
there will not be any internal flashover and/or electrical fault.
2.
All relays, transducers, indicating instruments, devices in switchgear panels will not
mal-operate.
Page 69 of 111
3.
Current carrying parts, supporting structure, earth connection etc. will not get
dislocated and /or will not break or distort.
4.
All equipment will have necessary protections. Every switchgear will be provided with
necessary arrangement for receiving, isolating, distributing and fusing of 230V AC and
DC supplies for various control, lighting, space heating and spring charging circuits. DC
supply for control shall be duplicated for each board which shall run through auxiliary
bus wires.
Lightning Arrestor will be of non-linear resistor type. Unless otherwise modified in this
specification the lightning arrestor shall comply with IS 3070(Pt.1)1974 or the latest
version thereof.
11.5 Cables
Cables will be unearthed grade suitable for use in medium resistance earthed system,
with stranded & compacted aluminum conductors, extruded semi-conducting compound
screen, extruded XLPE insulated, extruded semi-conducting compound with a layer of
non- magnetic metallic tape for insulation screen, extruded PVC (Type ST-2) FRLS outer
sheathed, multi-cored conforming to IS 7098 (Part II) IEC-60502 for constructional
details and tests.
LT Power Cables
LT Power Cable will be unearthed grade, multi-core, stranded aluminum conductor,
XLPE insulated with PVC outer sheath made on FRLS PVC compound. All other details
will be as applicable. Minimum conductor cross section of power cables will be 6 Sq.mm.
Control Cables
Control cables will be 1100V Grade, multi-core, minimum 2.5 mm2 cross section,
stranded copper conductor having 7 strands, PVC insulated, and outer sheath made of
FRLS PVC compound. In situations where accuracy of measurement is or voltage drop
in control circuit is not warrant, higher cross sections as required will be used. 4 sq.mm
copper conductor cables will be used for CT circuits all other specifications remaining
same.
Page 70 of 111
Page 71 of 111
Modules and Inverters database: Direct link for importing PV modules and
inverters from PHOTON database.
Meteo data: Hourly/daily values of global solar radiation, diffuse solar radiation,
and other meteorological parameters including wind
Page 72 of 111
Page 73 of 111
The energy yield is calculated based on the optimized annual tilted (i.e. 250 estimated
from the PVsyst) SPV array surface considering south facing (i.e. zero azimuth angles).
The expected plant production for different probability scenarios (probability of meeting
a generation value) is presented in the below:
Table 6: Energy Generation and technical losses expected for 10MW Block
S. No.
Technical Losses
Value (%)
2.70%
0.10%
Near Shadings
1.60%
Module temperature
9.00%
Array Soiling
2.00%
1.50%
2.00%
1.00%
1.30%
10
AC Ohmic Losses
0.30%
11
1.80%
19,880,000
0.50%
Page 74 of 111
13
Auxiliary Consumption
0.80%
14
Transmission Loss
0.50%
19,524,243
22.29%
18,356,468
20.95%
17,304,777
19.75%
In order to calculate the total amount of electricity annually we have considered the
following formula:
Total generation of units (kWh) = Sunshine Hours x Yield Factor x Total installed capacity
---- (1)
The plants Capacity Utilization Factor (CUF)/Plant Load Factor(PLF) has been
calculated using the following formula:
Yield factor
Yield factor is defined to be a factor consolidating all the system losses that are occurring
across this power plant. The major losses that occur during the operation of the solar PV
power plant are module quality loss, dirt and dust loss, temperature loss, array soiling
loss, DC to AC conversion losses, transformer losses and cable losses. Yield factor is
the multiplication of the typical coefficients for all these losses occurring across the
module up to the transformer output in this photovoltaic power plant. It is a figure that
Page 75 of 111
helps in understanding the totally generated units that can be evacuated into the grid.
These losses are explained in brief as follows:
Dirt and dust can accumulate on the solar module surface, blocking some of the sunlight
and reducing output. Much of the area has a dry season. A typical annual dust reduction
factor to use is 98.0% or 0.98 accounting for marginal 2% loss due to dirt and dust.
The maximum power output of the total PV array is always less than the sum of the
maximum output of the individual modules. This difference is a result of slight
inconsistencies in performance from one module to the next and is called module
mismatch. Maximum 3-4% losses will be there for module mismatch, but the modules
will be connected in series and parallel after testing to match the properties. This will be
reducing the mismatch losses to 2%.
Cable Losses
Power is also lost to resistance in the system wiring. These losses should be kept to a
minimum but it is difficult to keep these losses below 1% for the system. For this project
the total energy loss in the cables has been considered to be 1.3%.
DC to AC Conversion Losses
The DC power generated by the solar module must be converted AC power using an
inverter. Some power is lost in the conversion process. In this case as discussed before
that selected inverter has maximum DC power into AC power conversion efficiency of
98.6%.
Transformer Losses
Page 76 of 111
To account for different losses in the transformers like core and ohmic losses a typical
coefficient of 0.982 has been considered i.e. 1.8 %.
Temperature Losses
Shading Losses
Shading on the solar PV panel can bring gigantic malicious effect on the energy yield.
Generally, the potential solar PV shading objects are tree, nearby building buildings.
Rooftop solar PV installations are more prone to the shading losses. As far as the large
scale solar PV installation is concerned, shading of inverter room, control room and interrow are the potential reason of shading losses. Moreover, these objects provide shading
in the early morning hours or late evening hours. However, while designing the solar PV
plant, all these factors are always taken under serious consideration and shading losses
are optimized. As the project design can be fixed at this stage, only inter-row shading
analysis has been exercised. A total loss due to the inter-row shading is of the order of
1.6%.
Annual degradation
The estimated life of PV modules is considered as 25 years. Performance of solar PV
modules degrades over its specified lifetime. Normally, PV module manufacturers
provide a performance guarantee and indicate the rate of degradation over the module
lifetime. Essentially the solar PV modules used in grid solar power plants are warranted
for output wattage which should not be less than 90% at the end of 10 years and 80% at
the end of 25 years. In the present analysis, the annual degradation in production has
been taken conservatively taken as 1 %, linear for entire project life of 25 years.
Page 77 of 111
Page 78 of 111
Mode of Operation
The PV system basically consists of the following components:
1 PV arrays convert Sun light into DC Power.
2 This generated DC power is passed through the Inverter to convert DC power into
AC power.
3 This convert AC power at 400 V AC and is stepped up to 33 kV and then to 132kV
using step-up transformers.
4 AC power at 132kV is connected to the grid
5 Both on DC side of generation as well as AC side of conversion, protection and
safety devices are provided to ensure safe and reliable operation of the complete
Solar Power Generating system.
6 Monitoring and Analysis system provided with the power plant will record, store
and transfer data that are essential for the same purpose.
2.
Careful control and supervision of operating conditions. Wide and rapid variations
in voltage and frequency conditions do contribute to increased maintenance.
3.
4.
Page 79 of 111
5.
6.
7.
Typically the O&M costs for PV plant normally range from Rs. 5 lakhs/MW to 8
lakhs/MW. The difference in prices can be due to many factors like use of thinfilm modules (requiring more area and hence more maintenance), plant design,
margins of different contractors etc.
8.
The O&M cost for a 50 MW Solar power project will be reduced significantly in
comparison to a 5-10 MW Solar power project. Accordingly we have assumed
O&M cost of INR 5 Lakhs/MW for the project.
2.
3.
4.
Judicious fixation of inventory levels and ordering levels for spare parts based on
past experience.
2.
The detailed operating instructions on each section and equipment of the plant.
3.
4.
The emergency procedures and all related HSE issues according to the
standards.
5.
The basis for the training shall be the plant's Operation and Maintenance Manual,
Contract document and drawings provided by the manufacturer.
Shift supervisors should be provided housing nearby the power plant premises. It is
considered that these personnel will be available for 24 hours for meeting any emergency
requirements of the operation of the plant.
The plant manager will be in charge for both technical and administrative functions. The
organization under plant manager shall be divided into operation and maintenance
group.
The plant operation team will work in three shifts per day. Each shift will be controlled by
a shift supervisor. There will be an additional shift supervisor who will function as reliever.
Page 81 of 111
PLANT MANAGER
PLANT SUPERVISOR
PLANT SUPERVISOR
PLANT SUPERVISOR
PLANT HELPER
PLANT HELPER
PLANT HELPER
PLANT SUPERVISOR
PLANT OPERATOR
PLANT HELPER
ACCOUNTANT
SECURITY
SECURITY
SECURITY
SECURITY
Page 82 of 111
2.
3.
4.
5.
6.
2.
3.
4.
Financial closure
Page 83 of 111
Since, the project execution calls for closer coordination among the contractors,
consultants and the company, proper contract co-ordination and monitoring procedures
shall be made to plan and monitor the project progress.
14.4 Procurement and Construction
The procurement is an important function of the implementation of the project. Once the
purchase order is placed, the project team follows up regularly to ensure smooth and
timely execution of the contract and for obtaining technical information for the interpackage engineering.
When the contract for the equipment are awarded, detailed program in the form of
network are tied up with the supplier to clearly indicate the owner's obligations and the
suppliers responsibilities. And upon placement of the purchase order, the project team
follows up regularly to ensure smooth and timely execution of the contract and or
obtaining technical information for the inter-package engineering. The procurement
activity includes review of drawings, expediting, stage and final pre-delivery inspection,
supervision of installation and commissioning.
To expedite supplies from the manufacturers, regular visits to the supplier's works will
have to be undertaken by the project engineers/consultants. The manufacturing program
and quality plans finalized at the time of award of contract. Regular reports shall be
prepared indicating the schedule variations, if any, their likely impact on the delivery
schedule, and the recommendations to meet with the schedules.
During construction, the erection and commissioning phase of all the contracts proceed
simultaneously. Adequate power and water shall be made available for the construction.
14.5 Erection and Commissioning Phase
The commissioning phase in a project is one where design, manufacturing, erection and
quality assurance expertise are put to test. The commissioning team will be from
manufacturer of the equipment, consultant and the company. As discussed in the earlier
section, staff identified to operate the plant will be involved in the commissioning phase
of the project itself.
Page 84 of 111
When construction phase is complete, the check list designed to ensure that the plant
has been properly installed with appropriate safety measures. The commissioning team
will follow the operating instructions laid down by the plant and equipment manufacturer.
The plant shall be subjected to a performance test, after the successful completion of
the performance test of the plant; the plant will be taken over by the company.
It is responsibility of the company to ensure that major civil work shall have to be planned
in the non-monsoon period. All the statutory clearances like pollution control board
clearance will be obtained much before of the start of the project commissioning.
Page 85 of 111
Observation / Mitigation:
The plant PPA has already been signed which favours the project progress. The
technical consultant is already engaged with the project to assist the developer and has
experience with MW scale having long term relationship with vendors, which will ease
out the supply of plant equipment and project implementation.
15.2 Technology Risk Low
Choice of unsuitable PV technology or system can affect the project significantly. E.g. if
a new or emerging technology is chosen there may be a possibility of underperformance
as it may not have been tested sufficiently and for all environmental conditions and
locations. It may also suffer from technical issues.
Observation / Mitigation:
The
Consultant
recommends
crystalline-silicon
photovoltaic
technology
after
A study6 conducted by NREL verifies that crystalline PV module degradation rate is less
than 1% as indicated in the table below:
6 Source: C.R. Osterwald, J. Adelstein, J.A. del Cueto, B. Kroposki, D. Trudell, and T. Moriarty, National Renewable Energy
Laboratory (NREL), Comparison of degradation rates of individual modules held at maximum power 2006.
Page 87 of 111
Page 88 of 111
Page 89 of 111
The cost of the solar power plant, presented in this section of the report covers all the
costs associated with the construction of the plant and included civil construction cost,
cost of equipment for power generation, cost of auxiliaries and utilities. We have also
taken the reference of CERC considered capital cost for approving the purchase tariff for
solar photovoltaic based power plants in the country.
The estimated project cost for 23 MWp capacity (11.5x2 MWp) is Rs. 150.7 Cr. This is
estimated based on the land price, financing cost EPC cost, pre-operative costs, and
interest during construction. The main financial assumptions and indicators for the
project are given in the following table:
Page 90 of 111
7.535
6.552
150.70
VGF
21.90
5.45
CUF
22.29%
Rate of Interest
10.50%
Min DSCR
1.18
Average DSCR
1.45
EIRR
14.01%
PIRR
11.81%
Payback Period
Generation (in Million Units)
8.75 Years
39.05
Page 91 of 111
S.No.
Supplier
Website
Canadian Solar
http://www.canadiansolar.com/in/
Trina Solar
http://www.trinasolar.com/
Yingli Solar
http://www.yinglisolar.com/en/
Renesola
http://www.renesola.com/
Jinko Solar
http://www.jinkosolar.com/
REC
http://www.recgroup.com/
Page 92 of 111
The following table contains a list of major PV inverter suppliers having presence in India :
S.No.
Manufacturer
Website
ABB Ltd.
(http://www.aegps.com/en/)
(http://www.solar-inverter.com/in/index.htm)
Refusol GmBH
(http://asiapacific.refusol.com/en/)
(http://www.sma-india.com/)
Schnider Electric
(http://www.schneider-electric.com/)
Hitachi
(http://www.hitachi-hirel.com/res.htm)
Toshiba
(http://www.toshiba-
(http://new.abb.com/indian-subcontinent/about)
tds.com/tandd/technologies/smartgrid/en/solar.htm)
S.No.
Manufacturer
Website
(http://www.polycab.com/)
(http://www.sterlitetechnologies.com/)
(http://www.kei-ind.com/)
(http://www.havells.com)
Page 93 of 111
Page 94 of 111
Page 95 of 111
Page 96 of 111
Page 97 of 111
Page 98 of 111
Page 99 of 111