Professional Documents
Culture Documents
Associate Professor, Department of Civil Engineering, College of Engineering and Technology, Bhubaneswar,
Odisha, India
Abstract
In this work the real time reservoir operation is tackled by LP formulation, which is minimization problem. The objective function
is the penalty value, contributed by deviation of reservoir level from the recommended rule curve, flow at d/s flood control point
above the non-damaging flow, absolute flow at the d/s flood control point and the rate of increase or decrease of release from
reservoir. The constraints of the LP formulation are mass balance of the reservoir, calculation of deviation of reservoir level from
the recommended rule curve, flow at d/s flood control point, flow above the non-damaging flow, rate of increase and decrease of
release from the reservoir and all other physical constraints of the reservoir. The real time operation is done in two phases,
calibration and validation phases. The calibration phase is dealt in this paper, where as validation phase is dealt in the next
paper. The parameters of LP formulation are obtained in calibration phase. Three extreme floods from the history of the reservoir
are considered during the calibration phase. The LP formulation with different sets of penalties in the objective function is run for
these three floods. The performance is evaluated by maximum level achieved by the reservoir, peak flow at Naraj, and duration of
operation of flood. The best set of penalties is selected based on this performance.
Keywords: Real time reservoir operation, variable rule curve, calibration phase, adaptive
-------------------------------------------------------------------***------------------------------------------------------------------1. INTRODUCTION
In developing countries, major river basins are not fully
developed to their potential due to scarcity of funds, even if
planning for most of them is completed. The objectives of
the reservoir system of a basin, considered during planning
stage, are tried to be achieved up to maximum possible
extent by the constructed reservoirs. But these satisfied
objectives are less than the required in the reservoir system.
This situation will continue until full development of the
river basin is achieved. The operation of this type of
reservoirs is quite challenging.
Reservoir operation is one of the major research areas in
water resources for last four decades. Many approaches with
complex mathematical programs are developed to achieve
various objectives of the reservoir. But very few are adopted
in actual practice. Three important reasons for this are
pointed out by Simonovic (1992). These are
1) Reservoir operators are not directly involved during
development of the reservoir operation models. The
mathematical model developed for the system by
academician is not acceptable to the reservoir
operators due to the mathematical complexity
involved in it.
2) The complex mathematical models are applied to a
simplified version of the real system.
3) The operator-academician interaction is negligible
due to institutional constraints.
for full development of the basin (Patri, 1993). But only one
was constructed in the year 1956 at Hirakud. Till now, there
is no proposal for construction of any more reservoirs due to
shortage of funds, public protest and above all, for lack of
political will-power. Hirakud reservoir was constructed
mainly to mitigate floods. As no more reservoirs are
constructed till date, the existing reservoir is used now both
for flood control and conservative purposes. The average
total monsoon inflow into the reservoir, observed in the
history, is about six times the live storage of the reservoir.
So flood control during high flood is extremely difficult and
sometimes is quite impossible. Efforts continue for last four
decades to extract maximum benefits from this single
reservoir of the basin. It is observed that the operating policy
in the form of rule curves for the reservoir was changed for
six times from 1958 till to date. These changes are due to the
climatic and hydrologic changes in the basin and changes in
objectives of the reservoir.
A two-phased model for its operation is developed in the
present study to tackle these critical situations. In the first
phase operating policy for the reservoir on long-term basis is
developed (Baliarsingh, 2000; Nagesh Kumar, 2010). Then
the procedure of operating the reservoir on short-term basis
for flood control is developed in the second phase. This
short-term reservoir operation is reported in two papers of
this journal. In this first paper calibration of the short-term
reservoir operation model is dealt where as in second paper
validation of the model is dealt.
_______________________________________________________________________________________
Volume: 03 Issue: 09 | Sep-2014, Available @ http://www.ijret.org
239
2. LITERATURE REVIEW
Reservoir operation is an important area of research in water
resources for more than four decades. Many mathematical
models for this purpose are developed in this period. But
still researchers are not fully satisfied with it as new
problems are coming up continuously with time. The
various components, those involved in the operation of a
reservoir, are different for different systems.
A review and evaluation of multiobjective programming
techniques is presented by Cohon and Marks (1975).
Dynamic programming applications to water resources are
reviewed by Yakowitz (1982). An excellent state-of-the-art
review of the mathematical models developed for reservoir
operation was made by Yeh (1985). Lund and Guzman
(1999) discussed about operating rules for the reservoirs
connected in series and parallel.
Yeh and Becker (1982) analyzed California Central Valley
Project to guide real time decision making for optimal
operation. The purposes of the project are hydropower,
aquaculture, to overcome salt-water intrusion in delta area,
irrigation, and recreation. The constraint method was used
for trade-off among these purposes. They suggested that the
information of trade-off should be presented to the decision
makers by a series of two dimensional plots instead of
tabular presentation.
Dagli and Miles (1980) used the adaptive planning approach
for a set of four reservoirs connected serially. Each of the
reservoirs was of multipurpose type, having hydroelectric,
irrigation, and low flow augmentation on downstream of
reservoir as various purposes. As per the adaptive planning
approach, the release policy is found out for specified
number of periods, but only the release of current period is
implemented. Again the model is re-run at the end of current
period with new set of forecasted data.
Datta and Burges (1984) explored the sensitivity of various
performance criteria of reservoir operation to the conflicting
storage and release target and the accuracy of streamflow
forecast. The compromise solution depends on uncertain
future streamflow and the shape of loss function while tradeoff between storage and release deviation from respective
targets was found.
The optimization model can be used as simulation tool for
real time reservoir system operation. Ginn and Houck
(1989) discussed a method for calibration of the objective
function, used in this optimization model. They have
developed the method for quadratic class of model. But, the
method can also be used for general non-linear programs
with polynomial objective function. They demonstrated the
use of the method to simulate operation of the Green River
basin hydrosystem in Kentucky.
A model for optimal operating policy of a reservoir for
multicrop irrigation was developed by Vedula and
Mujumdar (1992). Three variables, viz., reservoir storage,
inflow to the reservoir, and the soil moisture in irrigated area
MULTIPURPOSE
PROJECT
SYSTEM
The project under the present study, Hirakud single reservoir
system is situated in Mahanadi basin. The Mahanadi basin
lies mostly in Madhya Pradesh and Orissa States. It is
bounded on the north by Central India Hills, on the south
_______________________________________________________________________________________
Volume: 03 Issue: 09 | Sep-2014, Available @ http://www.ijret.org
240
4.
PROCEDURE
FOR
OPERATION
OF
HIRAKUD RESERVOIR
In general the reservoir is operated by following the rule
curve meant for that reservoir. At present Hirakud reservoir
is also operated by its rule curve. Rule curve for the
reservoir is the water level in the reservoir, which should be
attained at various time instant. A variable rule curve, i.e.
rule curves for different situations, like flood, normal, and
drought years have been developed and proposed for
Hirakud reservoir by the same author (Baliarsingh, 2000;
Nagesh Kumar, 2010). These can be taken as guidelines
during actual reservoir operation. This does not mean that
the reservoir level will stick to the rule curve at each and
every time instant, but it will be as close to it as possible. If
inflow into the reservoir is either less or more than the
expected amount, the reservoir level deviates from rule
curve and again comes back, when favourable situation
returns. There should be some guidelines for the reservoir
level to deviate from the rule curve.
RESERVOIR OPERATION
5.
METHODOLOGY
OF
REAL
TIME
_______________________________________________________________________________________
Volume: 03 Issue: 09 | Sep-2014, Available @ http://www.ijret.org
241
5.1 LP Formulation
The LP formulation is used in both calibration and
validation phases for operation intervals of 24 hours, 12
hours and 6 hours. For illustration, the formulation is
discussed for the operation interval of 24 hours. The LP
formulation is as follows.
Minimize
t 1
(1)
(2)
t = 3,4,....,L
(3)
t = 2,3....,L
(4)
(5)
Q2 = QH2 + DC2
(6)
t = 3, 4, ....L
(7)
Qt = QHt + DCt
t = 3, 4, ....L
(8)
Qt - QIt - QDt = 0
t = 2, 3, ....,L
(9)
(10)
t = 3, 4....L
(11)
t = 2,3, ....,L
(12)
QDt NDF
t = 2,3, ....,L
(13)
t = 1,2, ,L-1
(14)
SDSL St SFRL
t = 2,3, ,L
(15)
(16)
_______________________________________________________________________________________
Volume: 03 Issue: 09 | Sep-2014, Available @ http://www.ijret.org
242
QIt is the difference between flow at Naraj and nondamaging flow at beginning of time period t, when the flow
is more than non-damaging flow,.
QDt is the flow at Naraj at beginning of time period t, when
the flow is less than or equal to non-damaging flow.
ROAIt is the increase of release from reservoir (summation
of release for power and spill) within acceptable safe limit
during time period t.
ROADt is the decrease of release from reservoir within
acceptable safe limit during time period t.
ROEIt is the increase of release from reservoir beyond
acceptable safe limit during time period t.
ROEDt is the decrease of release from reservoir beyond
acceptable safe limit during time period t.
PLS, PUS, PQI, PQD are the relative penalties for unit change of
LS, US, QI, QD respectively.
PROEI, PROED, PROAI, PROAD are the relative penalties for unit
change of ROEI, ROED, ROAI, ROAD respectively.
St is the reservoir storage volume at beginning of time
period t.
CF is the conversion factor to convert from rate to volume
of any variable.
RPSt is the summation of release from reservoir for power
and spill at beginning of time period t.
It is inflow into the reservoir at beginning of time period t.
IRt is the release from reservoir for irrigation at beginning of
time period t.
RCSt is the recommended rule curve storage at beginning of
time period t.
Qt is the flow at Naraj at beginning of time period t.
DCt is d/s catchment contribution at beginning of time
period t.
QHt is the routed quantity of release from Hirakud reservoir
at Naraj at beginning of time period t.
RPSt is the release from Hirakud reservoir for power and
spill at beginning of time period t.
Qt is the flow at Naraj at beginning of time period t.
DCt is the d/s catchment contribution at beginning of time
period t.
C0, C1, C2 are coefficients of conventional Muskingum
equation.
RPSMIN is the minimum required release from reservoir for
power and spill.
RPSMAX is the maximum release capacity from reservoir
for power and spill.
ROAIMAX is the safe limit of increase of release from
reservoir during a specific time period.
ROADMAX is the safe limit of decrease of release from
reservoir during a specific time period.
SDSL is the reservoir storage at dead storage level.
SFRL is the reservoir storage at full reservoir level.
t is the time period.
L is the operating horizon for each iteration of the LP model.
Equations-1 to equation-16 are the multi-objective LP
formulation, proposed for operation of Hirakud reservoir on
real time basis. Q is the flow at Naraj, which is divided into
two components QI and QD. If the flow at Naraj (Q) is less
than the non-damaging flow, QD will be equal to Q and QI
will be zero. If the flow at Naraj (Q) is more than non-
_______________________________________________________________________________________
Volume: 03 Issue: 09 | Sep-2014, Available @ http://www.ijret.org
243
6.
RESULTS
AND
DISCUSSION
OF
CALIBRATION PHASE
The relative penalties for various components of objective
function in LP formulation are determined in the calibration
phase. The LP formulation for calibration phase is given by
equations-1 to equation-16. Three floods, viz., calibration
flood numbers 1, 2, and 3 are used here for calibration.
_______________________________________________________________________________________
Volume: 03 Issue: 09 | Sep-2014, Available @ http://www.ijret.org
244
7. CONCLUSIONS
The flow rate at Naraj is less than 25.5 thousand cumecs
except for third flood, where PUS is considered as 5. In the
third flood, the flow at Naraj is more than 25.5 thousand
cumecs at the cost of reservoir level not achieving full
reservoir level, which is not acceptable in flood operation.
Considering these factors, the trial penalty sets with PUS as 5
are avoided. So finally from above discussion and analysis,
the relative penalty ratio of PQD : PUS : PROAI : PROAD : PQI,
PLS, PROEI, PROED :: 1 : 3 : 1 : 1 : 8 is selected for further use.
The performance of this set of relative penalty is tested in
the validation phase, which is described in the next paper.
_______________________________________________________________________________________
Volume: 03 Issue: 09 | Sep-2014, Available @ http://www.ijret.org
245
[9]
REFERENCES
[1]
[2]
[3]
[4]
[5]
[6]
[7]
[8]
[10]
[11]
[12]
[13]
[14]
[15]
[16]
[17]
_______________________________________________________________________________________
Volume: 03 Issue: 09 | Sep-2014, Available @ http://www.ijret.org
246
7
6
5
4
3
2
1
0
0
10
20
Flood Condition
30
40
50
60
Time period (Days)
Drought Condition
70
80
90
100
Normal Condition
Fig. 3: Variable Rule Curve proposed for Hirakud Reservoir by Baliarsingh (Baliarsingh,2000; Nagesh Kumar, 2010)
_______________________________________________________________________________________
Volume: 03 Issue: 09 | Sep-2014, Available @ http://www.ijret.org
247
Sl.
No.
1
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
Year
2
1958
1959
1960
1961
1962
1963
1964
1965
1966
1967
1968
1969
1970
1
23
24
25
26
27
28
29
30
2
1971
31
32
33
34
35
36
37
38
39
40
41
42
1974
1975
1976
1972
1973
1977
1978
1979
1980
1981
3
27/7 - 30/7
03/8 - 05/8
30/8 - 02/9
12/9 - 18/9
09/7 - 17/7
19/8 - 22/8
02/9 - 06/9
28/10
31/10
17/8 - 21/8
20/8 - 30/8
04/8 - 08/8
11/8 - 18/8
27/7 -02/8
07/8 - 11/8
17/8 - 21/8
26/8 - 03/9
09/8 - 13/8
12/9 - 16/9
19/9 - 30/9
16/8 - 26/8
Peak d/s
contribution
Thousand
Cumec
10 = 9-7
20.23
05.38
24.95
02.99
13.54
20.15
13.38
24.56
23.94
16.84
12.26
14.02
16.79
13.62
07.15
19.66
24.75
13.45
10.59
28.22
25.53
14.02
4
28-7
03-8
31-8
13-9
10-7
20-8
03-9
29-10
Table 1:
5
23.38
16.18
17.82
11.76
18.36
18.05
18.82
14.45
Continued
6
14.37
10.29
12.84
14.40
09.35
11.34
15.27
14.48
7
10.63
07.61
09.50
10.65
06.92
08.39
11.30
10.72
8
31-7
05-8
01-9
15-9
15-7
22-8
06-9
31-10
9
21.71
23.92
21.23
20.83
23.58
21.11
23.44
20.40
10
11.08
16.31
11.73
10.18
16.66
12.72
12.13
09.69
17-8
21-8
06-8
15-8
30-7
08-8
18-8
30-8
10-8
15-9
20-9
23-8
17.34
22.61
12.64
21.37
12.47
17.99
16.63
18.50
15.30
13.15
37.75
13.43
12.75
17.09
02.55
07.23
06.80
10.40
10.49
11.17
03.77
13.46
33.41
08.78
09.44
12.64
01.89
05.35
05.03
07.70
07.76
08.26
02.79
09.96
24.72
06.50
19-8
23-8
04-8
15-8
01-8
11-8
21-8
29-8
10-8
14-9
22-9
24-8
22.50
23.44
19.21
25.90
13.15
17.80
19.67
28.14
18.90
24.20
35.99
18.90
13.06
10.79
17.33
20.55
08.12
10.10
11.91
19.88
16.11
14.24
11.27
12.40
_______________________________________________________________________________________
Volume: 03 Issue: 09 | Sep-2014, Available @ http://www.ijret.org
248
43
44
45
46
47
48
1982
1983
1984
1985
07/8 - 28/8
30/8 - 04/9
01/9 - 13/9
09/8 - 11/8
16/8 - 25/8
30/7 - 14/8
19-8
31-8
07-9
10-8
18-8
09-8
17.00
26.92
15.87
15.73
15.98
14.74
Table 1: Continued
6
49
1986
25/6 - 30/6
29-6
24.37
21/8 - 22/8
22-8
50
06.66
00.00
11.93
07.03
11.14
06.91
04.93
00.00
08.83
05.20
08.24
05.12
20-8
31-8
09-9
10-8
17-8
07-8
20.55
44.89
25.56
19.04
25.05
26.35
15.62
44.89
16.73
13.84
16.81
21.24
10
08.73
06.46
29-6
24.65
18.20
13.04
01.98
01.47
22-8
26.92
25.45
51
1987
28/8 - 31/8
28-8
14.74
00.00
00.00
31-8
05.55
05.55
52
1988
03/8 - 10/8
04-8
13.29
00.00
00.00
09-8
12.47
12.47
53
1989
27/7 - 01/8
29-7
08.08
00.00
00.00
30-7
07.08
07.08
54
1990
29/8 - 10/9
06-9
12.64
09.12
06.75
06-9
24.65
17.90
10/9 - 21/9
16-9
15.30
15.22
11.26
17-9
23.10
11.83
20/7 - 04/8
24-7
15.22
01.67
01.24
01-8
20.55
19.31
57
12/8 - 21/8
14-8
19.16
02.55
01.89
14-8
36.02
34.13
58
22/8 - 01/9
25-8
14.00
06.43
04.76
24-8
18.14
13.38
28/7 - 02/8
30-7
13.49
00.00
00.00
30-7
32.14
32.14
16/8 - 30/8
22-8
16.58
02.27
01.68
21-8
31.91
30.23
55
56
59
1991
1992
60
61
1993
14/8 - 26/8
21-8
11.82
08.56
06.33
21-8
22.10
15.77
62
1994
19/6 - 25/6
21-6
20.63
08.53
06.31
22-6
17.63
11.31
63
08/7 - 19/7
11-7
25.84
17.71
13.11
13-7
29.02
15.91
64
20/7 - 25/7
21-7
19.84
17.97
13.30
23-7
22.93
09.63
65
03/8 - 09/8
04-8
17.77
07.88
05.83
05-8
14.51
08.68
66
18/8 - 26/8
20-8
13.21
02.92
02.16
20-8
22.05
19.89
67
27/8 - 10/9
01-9
17.23
11.00
08.14
06-9
30.63
22.50
18/7 - 29/7
26-7
15.61
00.99
00.73
25-7
25.93
25.20
68
1995
Table 2: Peaks of Inflow Hydrograph into the Reservoir (Thousand Cumecs) of Historical Sixty-eight Floods (1958 - 1995) for
Various Block Period
B
L
O
C
K
P
E
R
I
O
D
Sl.
1/7 11/7
- 21/7
- 1/8
- 11/8
- 21/8
- 1/9
- 11/9
- 21/9
- NonNo.
10/7
20/7
31/7
10/8
20/8
31/8
10/9
20/9
30/9
monsoon
of
season
1
2
3
4
5
6
7
8
9
flood
1
43.22
23.83
14.42
27.49
23.46
15.73
25.79
24.43
16.86
14.4(29.10.7
3)
2
21.54
23.12
23.83
7.88
18.42
29.81
18.82
19.69
24.37(29.6.8
6)
3
18.87
25.84
12.47
23.52
24.4
18.08
15.87
11.76
20.63(21.6.9
4)
4
18.36
8.08
7.91
20.66
13.94
12.64
13.15
5
15.22
16.18
18.05
17.82
17.23
37.75
_______________________________________________________________________________________
Volume: 03 Issue: 09 | Sep-2014, Available @ http://www.ijret.org
249
13.49
12.64
17.34
22.61
19.84
17.99
21.37
18.5
15.61
15.3
16.63
13.43
15.73
17
26.92
10
14.74
15.98
13.04
11
13.29
19.16
14.74
12
17.77
13.21
14
13
16.58
14
11.82
15.3
MAX
43.22
25.84
23.83
27.49
23.46
29.81
25.79
37.75
16.86
MIN
18.36
23.12
8.08
7.88
13.21
13.04
12.64
11.76
16.86
No.
of
flood
12
12
14
Duration of
block period
Block period No.
Peak inflow
into
the
reservoir
(T. Cumecs)
Peak
calculated d/s
catchment
contribution
(T. Cumecs)
11th July
20th
July
2
21st July
31th
July
3
1st Aug
- 10th
Aug
4
11th Aug
20th
Aug
5
21st Aug
31st
Aug
6
1st Sep
- 10th
Sep
7
11th Sep
20th
Sep
8
21st Sep
30th
Sep
9
04/07/6
1
to
13/07/6
1
43.2
08/07/94
to
19/07/94
27/07/71
to
30/07/71
16/08/64
to
19/08/64
22/08/65
to
26/08/65
23/09/65
to
29/09/65
23.4
24.4
29.8
01/09/6
1
to
11/09/6
1
25.8
19/09/80
to
30/09/80
25.8
29/07/5
9
to
07/08/5
9
27.5
37.7
16.9
13.7
15.9
11.1
05.4
16.8
13.6
24.4
11.3
07.1
30/06/64
to
08/07/64
Second most severe flood
Peak inflow
into
the
reservoir
(T. Cumecs)
Peak
calculated d/s
catchment
contribution
(T. Cumecs)
Duration of
occurrence
Duration of
occurrence
1st July
- 10th
July
1
Table 3: Data of Severe Floods Among Sixty-eight Floods from 1958 to 1995 in Ten Days Block Period-Wise.
21.5
10/07/5
8
to
22/07/5
8
23.8
18/07/9
5
to
29/07/9
5
15.6
02/08/6
7
to
05/08/6
7
23.5
15/08/6
0
to
19/08/6
0
23.5
30/08/8
2
to
04/09/8
2
26.9
02/09/7
3
to
06/09/7
3
18.8
10/09/5
9
to
18/09/5
9
24.4
14.2
20.2
25.2
24.7
03.0
44.9
12.2
24.9
_______________________________________________________________________________________
Volume: 03 Issue: 09 | Sep-2014, Available @ http://www.ijret.org
250
Calibration
flood No.
_______________________________________________________________________________________
Volume: 03 Issue: 09 | Sep-2014, Available @ http://www.ijret.org
251