Professional Documents
Culture Documents
POINT A
O-RING LOCATION
WARNING
W6510*A/IL
Installation
Refer to the System 9000 instruction manual, Form
5408, for additional or supporting information.
The following steps describe how to install the System
9000 actuator onto a Valtek Mark One valve.
1. Refer to steps 1 to 3 in the System 9000 instruction
manual, Form 5408 in the section entitled Changing
Actuator Action to remove the cover and FIELDVUE
positioner.
2. Place the standard Mark One split rings onto the
bonnet.
3. Place the System 9000 yoke over the split rings.
4. Position the yoke clamps and bolts onto the bonnet, so that the bolts can be accessed through the
yoke windows.
7. Spin the jam nut all the way down on the stem.
6. Install the gland flange and proper bolting, tightened per Mark One requirements.
FIELDVUE, FloVue, Fisher, Fisher-Rosemount, and Managing The Process Better are marks owned
by Fisher Controls International, Inc. or Fisher-Rosemount Systems, Inc.
All other marks are the property of their respective owners.
Fisher Controls International, Inc. 1997; All Rights Reserved
D300918X012 09/97
Installation Instructions
System 9000 Actuator Retrofit for Valtek Mark One Valves
Note
DESIRED TRAVEL
MEASUREMENT
YOKE
STEM
CONNECTOR
DESIRED TRAVEL
MEASUREMENT
JAM NUT
GLAND FLANGE
YOKE CLAMP
SPLIT RINGS
A7033/IL
Parts List
9. Mount the power module assembly to the yoke in
the proper orientation and torque the bolts to 15 lbfSft.
Description
Stem Connector
Yoke
Jam Nut
Installation Instructions
Part Number
17B7321X012
37B7323X012
1A353735252
D300918X012