You are on page 1of 62

A brighter

outlook
International construction
cost survey 2013

Foreword
Overview

Australia
Brazil
Canada
China
Germany
Hong Kong
India
Ireland
Japan
Malaysia
Netherlands
Oman
Poland
Qatar
Russia
Singapore
South Africa
South Korea
UAE
Uganda
UK
US
Vietnam

12
14
16
18
20
22
24
26
28
30
32
34
36
38
40
42
44
46
48
50
52
54
56

Purchasing power parity

58

After an unprecedented period of global economic


instability, things are beginning to slowly improve.
Many markets remain fragile but its clear that sentiment
is improving. With recovery comes opportunity, and some
key markets around the world are showing sustainable
signs of growth.
Given this context, our international construction cost
survey 2013 makes for interesting reading. Data gathered
by our people around the world reflects major projects
and programmes in every sector. Our team of construction
economists provides expert analysis and ensure the data
is as robust as possible, given the ever-shifting nature
of such information.
This report contains data from 23 countries, with Brazil,
Poland and Uganda appearing for the first time. Clients
planning major programmes of work will find this a useful
decision-making tool that helps them compare future
construction costs between countries and regions.
To allow true country-to-country comparisons to be made,
we have introduced purchasing power parity methodology
this year to calculate construction costs. Developed by
Turner & Townsend with Bond University in Australia,
our construction purchasing power parity index takes
out the impact of exchange rate volatility. This is a new
approach for construction, and one we believe will become
significant (more about this on page 58).
Contact us if you require any more information about this
survey or if you need data and advice that can help inform
decision-making for your project or programme.
Vincent Clancy
Chief Executive Officer

With recovery
comes opportunity
The economic tide has turned and there is reason to be
optimistic. Construction markets around the world are
showing the first signs of recovery and shelved projects
are being dusted off. The results of our 2013 survey
of international construction costs reveal where the
potential opportunities might be for early movers.

The global outlook for construction


is the most positive we have seen
since the financial crisis began in
2008. Of the 23 markets included
in this survey, 13 expect to see more
projects starting in the year ahead
than they did in the previous
12 months.

Figure 1. More projects in the next 12 months


for over half the markets surveyed

Asia, parts of Europe, the Middle East


and the US are all warming up (see
Figure 1). Investment in housing and
infrastructure is building momentum
for stagnant economies and projects
which had been on hold since the
financial crisis began. These are
now going out for tender.
The start of a global recovery
is a great time to build. First-mover
advantages include stabilised
construction costs, reduced schedule
risk and the delivery of projects as
demand is increasing. In many regions
tender prices are becoming more
competitive and there are plenty
of firms keen to bid.
Of course, some developers will prefer
to watch and wait before making
their move. In the first fragile stages
of recovery, world events can erode
market confidence overnight, and
there are likely to be headwinds
still to come.
Stable costs are the trend, but
there are exceptions. In emerging
economies including China, India,
Malaysia, Russia and South Africa,
construction costs are expected to
rise steadily. And in certain hotspots
Brazil and Qatar, both future World
Cup hosts costs are also forecast
to increase strongly.

Cooler
Fewer projects
than last 12 months
China
India
Netherlands
Poland
South Africa
South Korea

Staying the same


Similar number of
projects to the last
12 months
Australia
Hong Kong
Ireland
Vietnam

Warmer
More projects starting
than last 12 months
Brazil
Canada
Germany
Japan
Malaysia
Oman
Qatar

Russia
Singapore
UAE
Uganda
UK
US

We asked our people around the world whether they expected more, fewer or the
same number of projects to start in the next 12 months compared to the previous
12 months. Of the 23 markets surveyed, 13 expect more projects to start, with four
predicting no change and six expecting fewer projects.

International construction cost survey 2013

A business park in Japan


would cost 24 percent
more to build than one
in the UK.

We can see some of these trends


emerging through our cost index
benchmarking of high-rise apartments
and offices in central business districts
(see Figures 2 and 3). So, for example,
while costs for offices in the UK have
risen just four percent between 2010
and 2013, comparable costs in India
have risen 25 percent.
Over the following pages, we present
the findings of our 2013 international
construction cost survey. The data
comes from current construction
programmes, and reflects prices at
the middle of 2013. All costs exclude
VAT and applicable sales taxes.
Purchasing power parity:
a new way to compare markets
For those who want to drill down
further into our data, we have
included output costs (cost per
square metre) and input costs (labour,
materials and plant) for each type
of building and geographical market
on pages 12 to 57. The costs are
shown in the local currency, in US
dollars and as a purchasing power
parity value.
The methodology allows a true
comparison between countries,
removing the impact of varying
currency exchange rates. The higher
the purchasing power parity adjusted
cost, the higher the relative costs
of building in one country over
another. Though purchasing power
parity indexes are used in some
branches of economics, this method
has rarely been used to compare
construction costs.

Turner & Townsend

For example, we can see that an office


building in a business park in Japan
would cost 24 percent more to build
than one in the UK; 3,339 purchasing
power parity units per m2 for Japan
compared to 2,690 units for the UK.
Purchasing power parity indicates
the cost relative to the cost of living,
so we can see that concrete in China
at 129 is almost half that of India
at 283.
Turner & Townsend worked with Bond
Universitys Centre for Comparative
Construction Research in Queensland,
Australia, to create this constructionspecific index, which we will be
employing and developing over the
coming years. You can read more
about purchasing power parity on
page 58.

Purchasing
power parity
methodology allows
a true comparison
between countries

+25%

the cost increase


of building offices
in India

Figure 2. Changes to the cost of central business


district offices since 2010
Mid-year

Figure 3. Changes to the cost of high-rise


apartments since 2010

2010

2011

2012

2013

2010

2011

2012

Australia

100

102

103

105

Mid-year
Australia

100

102

101

2013
101

Brazil

100

104

109

114

Brazil

100

104

108

112

Canada

100

102

104

106

Canada

100

102

103

104

China

100

107

113

120

China

100

107

112

118

Germany

100

102

104

106

Germany

100

102

104

106

Hong Kong

100

104

109

115

Hong Kong

100

104

109

115

India

100

108

117

125

India

100

108

117

125

Ireland

100

102

102

104

Ireland

100

101

100

101

Japan

100

100

100

101

Japan

100

100

100

101

Malaysia

100

104

109

113

Malaysia

100

105

109

113

Netherlands

100

102

104

106

Netherlands

100

102

103

105

Oman

100

101

103

105

Oman

100

101

103

105

Poland

100

102

104

106

Poland

100

101

103

105

Qatar

100

102

106

111

Qatar

100

100

103

108

Russia

100

104

110

116

Russia

100

104

109

115

Singapore

100

104

108

112

Singapore

100

103

105

109

South Africa

100

106

114

124

South Africa

100

105

112

120

South Korea

100

102

104

106

South Korea

100

102

104

106

UAE

100

100

102

105

UAE

100

100

102

104

Uganda

100

105

110

116

Uganda

100

104

108

114

UK

100

102

102

104

UK

100

102

101

103

US

100

100

103

107

US

100

100

102

106

Vietnam

100

110

119

128

Vietnam

100

108

116

124

Looking at cost changes for prime property in the residential


and commercial sectors helps us to identify trends and make
predictions for the future. The two charts show construction
costs indexed to 2010 = 100 for high-rise apartments and
central business district offices, for each region of the
survey based on cost per square metre.

We can see that for most countries, there has been a gradual
rise in costs for both types of building. There are exceptions:
costs have remained more-or-less stable in Australia, Ireland,
Japan and the UK; whereas in China, India, South Africa and
Vietnam, costs have risen more steeply.

International construction cost survey 2013

+12%
US house price
growth over the
last 12 months
US recovery still fragile
In the past 12 months, the US
economy has begun to pick up,
with the impact felt around the
world. Quantitative easing and
low interest rates adopted by the
USs central bank, the Fed, have
contributed to this fledgling recovery.
However, there is uncertainty
surrounding the Feds ability to taper
this policy, which could lead to further
problems when it is reduced and,
ultimately, stopped.
Suggestions from the Fed in May
this year that it might cut back on
its bond-buying programme over
the coming months had an immediate
and negative effect on global stock
markets. Investors ditched risky
assets in favour of certainty.
Confidence returned after further
assurances from the Fed, but
continued pressures remain.
Standard & Poors (S&P) 500, which
tracks publicly traded US companies,
has recently reached all-time highs
and global funds are moving back
into US dollars as the currency
starts to stabilise. Other markets have
followed the US, only pausing in May
2013 as the northern economies took
summer holidays.
Unemployment in the US is edging
downwards, and housing construction
is increasing again. The Case-Shiller
20-City-Index, which measures the
value of residential real estate in
20 metropolitan areas of the US,
shows a house price growth of 12
percent over the past 12 months.

Turner & Townsend

The USs newest industry and source


of energy, shale gas, is also injecting
further growth into the economy.
Projects to construct the pipelines and
associated infrastructure are ramping
up, with the prospect of US energy
self-sufficiency promising a big boost
to the economy.
Falling unemployment and recovering
house prices will encourage US
consumers to spend more, providing
a much-needed boost to international
trade and construction. Still, the US
recovery remains fragile, operating
within the confines of a quantitative
easing headwind and continued
government impasses.
Policy changes in Europe?
In contrast to the tactics of the
USs central bank, European
countries have chosen the path
of austerity. However, recent policy
announcements indicate a change
of approach. Expect investment in
infrastructure, which should help
relieve the chronic underemployment
holding several major European
countries back.
Though some European countries,
such as Greece, Portugal and
Spain, continue to suffer from
underemployment, many parts
of Europe are showing signs
of recovery. Here, forecasts
of GDP growth over the next
year are improving prospects
for construction.

$1.3tn

of Middle East
construction projects
are in the planning
or tendering stages
The Middle East is also increasing
its construction activity, reawakening
many of the ambitious projects
that have been dormant or partially
completed since the global financial
crisis. Some USD1.3tn worth of
construction projects are in the
planning or tendering stages across
the region.
Projects such as high-speed rail,
manufacturing plants, heavy
industrial plants, football stadiums,
and housing and cultural precincts
are moving to construction or already
underway. Traditionally, strong
markets such as Dubai are gradually
coming back to full strength and
new construction leaders such
as Qatar are emerging, with big
project portfolios.
There are other engines of global
growth. Japan is making substantial
efforts to stimulate its economy after
decades of stagnation by pumping
in money, causing the yen to fall
dramatically. The worlds third biggest
economy is becoming competitive
again, construction is picking up and
trade skills shortages are becoming
a problem.

Unemployment
in the US is edging
downwards, and
housing construction
is increasing again

International construction cost survey 2013

All change in China


For the past five years, Chinas growth
has kept the global economy growing
at above three percent, through its
demand for commodities. Its appetite
for iron ore, copper, coal and oil during
that period drove up commodity
prices and spurred a wave of mining
investment. Chinas manufacture
and export of cheap goods has also
kept global inflation down to below
two percent.
This changed in late 2012, following
concerns about the sustainability
of Chinese growth as their new
political leadership established itself.

Turner & Townsend

Indications show that China has


now entered a new lower-growth
trajectory, although with growth
forecast at seven to eight percent,
it will continue to be an important
driver of global growth.
Changes in China are felt elsewhere
in the world. Lower commodity prices
have caused the sudden cancellation
of numerous natural resource projects
worldwide, leading to concern in the
economies of Australia and Latin
America, where mining plays
a major role.

China has now entered


a new lower-growth
trajectory, although with
growth forecast at seven
to eight percent, it will
continue to be an important
driver of global growth.

International construction cost survey 2013

Competitive tenders
Though construction markets
around the world are warming
up, tender prices will not be following
suit immediately. In two-thirds
of the markets surveyed, there
is strong competition on tenders,
with others reporting moderate
competition.
In general, construction costs are
only increasing slowly, often in line
with a countrys general inflation.
In many regions, costs have barely
moved for five years. Flat prices go
all along the value chain: engineers,
architects and construction
consultants costs are competitive,
and skilled labour is fairly easy
to obtain in most markets.
Margins
Contractors margins in developed
economies have been hard hit by
the global financial crisis. Fierce
tender competition has forced
many contractors to tender with
very low margins, hoping to pick
up additional margin during the
construction by completing ahead
of schedule, through better
efficiency, or negotiating
advantageous deals with
their suppliers.

It is interesting to note that


countries in parts of Africa,
Asia, the Middle East and Russia
have indicated higher contractors
margins. A more vibrant construction
market allows margins to increase
through reduced tender competition.
Barriers to entry in some markets
may also limit the number of tenders
and help keep margins higher
(see Figure 5).
Preliminaries
Ranging from eight percent
to 15 percent, the spread in the
range of preliminaries costs such
as supervision, project set-up,
scaffolding, and temporary facilities
indicates different requirements
between countries. Higher-cost
countries may have higher
inclusions, due to elements such
as specifications for scaffolding
(based on local safety standards)
and insurance costs (see Figure 6).
Countries or regions where space
restrictions are common, with
awkward building sites, would
typically have higher preliminaries.
For example, the preliminaries for
a building in New York City might
be expected to be higher than
for the rest of the US.

Figure 4. Strong competition is keeping tenders competitive in the majority of markets


Intense competition, not
much work, prices low:
Ireland
Netherlands
South Korea
Strong competition,
moderate tender prices:
Australia
Canada
China
Germany
Malaysia
Oman
Singapore
South Africa
UAE
Uganda
UK
US
Vietnam
Moderate competition,
moderate tender prices:
Brazil
Hong Kong
India
Japan
Poland
Russia
Qatar
We asked our experts how they would describe tender conditions in their local
markets. 16 of the 23 described competition on bids as strong
or intense, limiting the prices of bids.

Turner & Townsend

Figure 5. Wide range of contractors margins tells story of the markets


Canada
Ireland
South Korea
Australia
US
UK
Vietnam
Netherlands
Germany
Hong Kong
Poland
China
Japan
Singapore
UAE
Oman
Malaysia
Brazil
Russia
South Africa
Uganda
Qatar
India

10
Percentage

This chart shows what percentage of a buildings cost a


contractor would typically make as profit on an office building
with a gross floor area of 5,000m2. Generally, where work
volumes are lower, margins are squeezed as contractors
lower their tender prices in order to win work.

14

12

16

18

20

At the lower end of the range, contractors in Canada, Ireland,


South Korea, Australia, US and UK all currently make less than
five percent margin. Whereas in South Africa, Uganda, Qatar
and India, margins are relatively high: above ten percent.

Figure 6. Difference in preliminaries, depending on projects location


20
19
18
17
16
15
14
13
Percentage

12
11
10
9
8
7
6
5
4
3
2
1

This chart shows what proportion of a buildings cost goes on


preliminaries for an office with a gross floor area of 5,000m2.
Preliminaries include costs such as scaffolding, approvals,
insurances, power and water, cleaning and handover,
and work supervision.

an
y

er
m
G

pa
Ja

d
an

Ko
n

Po
l

on
H

nd
s

rla
he
N

et

Ko
re
a
Au
st
ra
lia

at
ar
Q

UA
E

ut
h
So

So

el

an

d
Br
az
il
ut
h
Af
ric
a

e
or

Ir

ia

ng
ap

Si

an

ay
s

m
O

al
M

na
m

S
U

et
Vi

di
a
In

ad
a

in

Ca
n

Ch

si

Ru
s

ga
n

da

Typically, higher-cost countries have higher preliminaries.


Regulatory compliance, such as safety and environmental
requirements, adds further preliminary costs.

International construction cost survey 2013

A stable outlook for costs


Materials prices are competitive,
and are expected to increase only
slowly for several years. In 201112,
high prices for commodities fed into
cost hikes for construction products
such as steel, copper cables and
copper pipes. In late 2012, however,
those commodity prices started
to fall. Rises in manufacturing wages
and energy will cause only a gradual
price rise over the next few years.
The cost of manufacturing plants
and equipment is also relatively
stable. European manufacturers
who were hit hard after the global
financial crisis are likely to have
spare plant and labour capacity
for several years.

Construction wages and salaries


in advanced economies have changed
little since the financial crisis and are
expected to remain relatively stable.
In contrast, those in China, India,
South Africa and Vietnam will continue
to increase strongly, but from a low
base (Figure 7 shows relative labour
costs between markets).
Looking ahead, we forecast modest
rises in construction costs over the
coming 12 months in many markets.
Australia, Ireland, the Netherlands,
Poland, Oman and the UAE should
all experience just two percent cost
escalation between mid-2013 and mid2014, removing that element of risk
from projects. At the other end of the
scale, Brazil, Hong Kong, India, Qatar
and South Africa could all experience
cost escalation of six percent or more,
with South Africa predicting the
highest escalation, at ten percent
(see Figure 8).

+2%

cost escalation
over the coming
12 months in
many markets

10

Turner & Townsend

Figure 7. The cost of labour

China

Brazil

Poland

Qatar
Australia
Germany

Japan

Singapore
Ireland

India

South
Africa

Oman
UAE
UK

US

Hong
Kong

Uganda

Netherlands

Malaysia

Vietnam

South
Korea

Canada

Russia

From this chart, we can see how hourly labour costs compare
in different markets around the world. As might be expected,
construction operatives in the US where parts of the country
are still heavily unionised, enjoy the highest hourly rates in the
world, with size relating to cost (small circles = lower cost).

Figure 8. How much will costs rise over the next 12 months?
South Africa
India
Brazil
Hong Kong
Japan
China
Vietnam
Russia
Uganda
Qatar
Germany
UK
Canada
Singapore
Malaysia
South Korea
Ireland
Netherlands
US
Australia
UAE
Oman
Poland
0

We asked our experts to predict how much construction costs


would rise between mid-2013 and mid-2014. As can be seen from
the chart, we expect a great variation in cost escalation, with
costs in some markets remaining almost flat, while others are
rising quickly.

5
Percentage

10

Developers in Ireland, Netherlands, US, Australia, UAE, Oman


and Poland will be taking on little risk of cost escalation, with
only two percent predicted. Whereas in countries such as South
Africa, India, Brazil and Hong Kong, rising construction costs
must be an important consideration.

International construction cost survey 2013

11

Australia
Residential recovery and falling exchange rate to drive growth
The Australian economy continued to grow during
the period following the global financial crisis, through
a massive investment in mining and energy projects.
Now that this investment is tailing off, where will the
next growth driver come from?

Meanwhile, domestic non-resources construction


has been hit by low demand, weak confidence and
a shortage of projects. This has kept margins low
and tendering very competitive.

Housing recovery is set to be the next growth sector.


Low interest rates and improving values are starting
to have the desired effect. Fortunately, the high Australian
dollar, which plagued the export sector, is now devaluing,
offering better opportunities for tourism, attracting
overseas students and services exports.
International building costs
per m2 of internal area, in 2013

AUD

USD

Purchasing
power parity

(exchange rate:
1.10)

Airports
Domestic terminal full service
Low-cost carrier basic service

4,900
3,880

4,455
3,527

4,900
3,880

Carparks
Multistorey above ground
Multistorey below ground

820
1,220

745
1,109

820
1,220

Commercial
Offices business park
CBD offices up to 20 floors medium (A-grade)
CBD offices high-rise prestige

1,860
2,940
3,260

1,691
2,673
2,964

1,860
2,940
3,260

Education
Primary and secondary schools
University

1,940
3,140

1,764
2,855

1,940
3,140

Hospitals
Day centre (including basic surgeries)
Regional hospital
General hospital (eg city teaching hospital)

2,960
3,400
5,340

2,691
3,091
4,855

2,960
3,400
5,340

Hotels
3 star travellers
5 star luxury
Resort style

2,350
3,900
3,600

2,136
3,545
3,273

2,350
3,900
3,600

Warehouse/factory units basic


Large warehouse distribution centre
High-tech factory/laboratory

770
950
1,560

700
864
1,418

770
950
1,560

Residential
Individual detached house medium standard
Individual detached house prestige
Townhouses medium standard
Apartments private medium density
Apartments high rise
Aged care/affordable units

1,650
2,160
1,700
1,960
2,440
2,350

1,500
1,964
1,545
1,782
2,218
2,136

1,650
2,160
1,700
1,960
2,440
2,350

Retail
Large shopping centre including mall
Neighbourhood incl supermarket
Prestige car showroom

2,240
1,900
2,500

2,036
1,727
2,273

2,240
1,900
2,500

Industrial

12

Turner & Townsend

Australia international building costs


per m2 of internal area

AUD

USD

Purchasing
power parity

22
36
261
2,076
122
134
2,400
200
620
35
773
14
110
52
60
82
61
46
250

20
33
237
1,887
111
121
2,182
182
564
32
702
13
100
47
55
74
55
42
227

22
36
261
2,076
122
134
2,400
200
620
35
773
14
110
52
60
82
61
46
250

66
59
52
38
75

60
54
47
35
68

66
59
52
38
75

Material
Concrete 30 MPa (m3) (1,500m3 job)
Reinforcement bar 16mm (tonne) (120 tonne job)
Concrete block (400x200) per 1,000 (>10,000 block job)
Standard brick per 1,000
Structural steel beams (tonne) (100 tonne + job)
Glass pane 10mm tempered (m2)
Softwood timber for framing 100mm x 50mm (m)
13 mm plasterboard (m2)
Emulsion paint (litre)
Copper pipe 15 mm (m) (1,000m+ job)
Copper cable (m) (3C + E, 2.5mm PVC) (100,000m+ job)

225
1,125
3,394
568
1,550
240
4
8
12
12
4

205
1,023
3,085
516
1,409
218
3
7
11
11
4

225
1,125
3,394
568
1,550
240
4
8
12
12
4

Plant
Hire 50t mobile crane + operator (day)

2,100

1,909

2,100

Composite
Excavate basement (m3) (1,800m3 job)
Excavate footings (m)
Concrete in slab (m3) (1,500m3 job)
Reinforcement in beams (tonne)
Formwork to soffit of slab (m2)
Blockwork in wall (m2) (10,000 block job)
Structural steel beams (tonne)
Pre-cast concrete wall (m2)
Curtain wall glazing incl support system (m2) (1,000m2 job)
Plasterboard 13mm thick to stud wall (m2) (3,000m2 job)
Single solid core door incl frame and hardware (50 door job)
Painting to walls primer + 2 coats (m2)
Ceramic tiling (m2) (1,000m2 job)
Vinyl flooring to wet areas (m2) (500m2 job)
Carpet medium tufted (m2) (4,500m2 job)
Lighting installation (m2) (5,000m2+ job)
Copper pipe 15mm to wall (m) (1,000m+ job)
Fire sprinklers (per m2) (5,000m2 job)
Air conditioning incl main plant (m2) (5,000m2+ job)
Labour
Group 1 tradesman eg plumber/electrician
Group 2 tradesman eg carpenter/bricklayer
Group 3 tradesman eg carpet layer, tiler, plasterer
General labourer
Site foreman

Market:
Tendering:

(exchange rate:
1.10)

staying the same

Adelaide

95

lukewarm

Brisbane

98

Cost escalation:

2%

Melbourne

98

Contractors margin:

4%

Perth

96

Preliminaries:

12%

Sydney

100

International construction cost survey 2013

13

Brazil
Public spending will maintain growth well beyond the World Cup and Olympics
Brazils continued growth and ambitious construction
plans for the 2014 World Cup and 2016 Olympics will
add pressure to construction costs, especially in the
venue cities. Skills and equipment shortages are likely
in these areas. However, Brazil is a large country with
a large population, and the additional construction
demand should be within its capabilities.

While non-residential construction spending growth


is likely to slow down after the build-up to the World Cup
and Olympics, spending on residential construction and
countrywide infrastructure is expected to accelerate
beyond 2016 to 2022.

Over the next five years, construction spending in the


country is expected to increase at a seven percent
compound annual growth rate. This growth is due
to mammoth public housing and infrastructure projects
across the country, in addition to the major works being
undertaken in preparation for the World Cup and the
Rio Olympics.
International building costs
per m2 of internal area, in 2013

Real

USD

Purchasing
power parity

(exchange rate:
2.28)

Airports
Domestic terminal full service
Low-cost carrier basic service

5,500
4,500

2,412
1,974

3,125
2,557

Carparks
Multistorey above ground
Multistorey below ground

1,650
2,150

724
943

937
1,222

Commercial
Offices business park
CBD offices up to 20 floors medium (A-grade)
CBD offices high-rise prestige

3,300
2,570
4,060

1,447
1,127
1,781

1,875
1,460
2,307

Education
Primary and secondary schools
University

1,980
2,640

868
1,158

1,125
1,500

Hospitals
Day centre (including basic surgeries)
Regional hospital
General hospital (eg city teaching hospital)

2,640
3,300
3,960

1,158
1,447
1,737

1,500
1,875
2,250

Hotels
3 star travellers
5 star luxury
Resort style

2,610
3,470
3,140

1,145
1,522
1,377

1,483
1,972
1,784

Industrial
Warehouse/factory units basic
Large warehouse distribution centre
High-tech factory/laboratory

1,520
1,960
4,060

667
860
1,781

864
1,114
2,307

Residential
Individual detached house medium standard
Individual detached house prestige
Townhouses medium standard
Apartments private medium density
Apartments high rise
Aged care/affordable units

1,500
2,000
2,200
2,480
3,330
2,810

658
877
965
1,088
1,461
1,232

852
1,136
1,250
1,409
1,892
1,597

Retail
Large shopping centre including mall
Neighbourhood incl supermarket
Prestige car showroom

2,900
2,610
3,960

1,272
1,145
1,737

1,648
1,483
2,250

14

Turner & Townsend

Brazil international building costs


per m2 of internal area

Real

USD

Purchasing
power parity

25
30
320
4,800
55
40
6,000
800
2,500
50
4,200
60
80
60
60
150
15
40
200

11
13
140
2,105
24
18
2,632
351
1,096
22
1,842
26
35
26
26
66
7
18
88

14
17
182
2,727
31
23
3,409
455
1,420
28
2,386
34
45
34
34
85
9
23
114

60
50
45
30
80

26
22
20
13
35

34
28
26
17
45

Material
Concrete 30 MPa (m3) (1,500m3 job)
Reinforcement bar 16mm (tonne) (120 tonne job)
Concrete block (400x200) per 1,000 (>10,000 block job)
Standard brick per 1,000
Structural steel beams (tonne) (100 tonne + job)
Glass pane 10mm tempered (m2)
Softwood timber for framing 100mm x 50mm (m)
13 mm plasterboard (m2)
Emulsion paint (litre)
Copper pipe 15 mm (m) (1,000m+ job)
Copper cable (m) (3C + E, 2.5mm PVC) (100,000m+ job)

250
4,000
1,500
945
5,000
880
8
20
10
5
3

110
1,754
658
414
2,193
386
4
9
4
2
1

142
2,273
852
537
2,841
500
5
11
6
3
2

Plant
Hire 50t mobile crane + operator (day)

3,200

1,404

1,818

Composite
Excavate basement (m3) (1,800m3 job)
Excavate footings (m)
Concrete in slab (m3) (1,500m3 job)
Reinforcement in beams (tonne)
Formwork to soffit of slab (m2)
Blockwork in wall (m2) (10,000 block job)
Structural steel beams (tonne)
Pre-cast concrete wall (m2)
Curtain wall glazing incl support system (m2) (1,000m2 job)
Plasterboard 13mm thick to stud wall (m2) (3,000m2 job)
Single solid core door incl frame and hardware (50 door job)
Painting to walls primer + 2 coats (m2)
Ceramic tiling (m2) (1,000m2 job)
Vinyl flooring to wet areas (m2) (500m2 job)
Carpet medium tufted (m2) (4,500m2 job)
Lighting installation (m2) (5,000m2+ job)
Copper pipe 15mm to wall (m) (1,000m+ job)
Fire sprinklers (per m2) (5,000m2 job)
Air conditioning incl main plant (m2) (5,000m2+ job)
Labour
Group 1 tradesman eg plumber/electrician
Group 2 tradesman eg carpenter/bricklayer
Group 3 tradesman eg carpet layer, tiler, plasterer
General labourer
Site foreman

Market:
Tendering:

getting warmer
warm

(exchange rate:
2.28)

Belo Horizonte

87

Brasilia

94

Cost escalation:

7%

Prto Alegre

Contractors margin:

9%

Rio de Janeiro

101

So Paulo

100

Preliminaries:

11%

81

International construction cost survey 2013

15

Canada
All sectors picking up, with tenders still competitive
The Canadian economy has been one of the strongest
global performers among advanced economies in
recent years. Unemployment is down to 7.2 percent and
a strong resources sector is helping to boost exports and
engineering construction. However, growth of 1.7 percent
in the second quarter of 2013 disappointed policymakers,
who were hoping for 2.5 percent.
Construction in most sectors tailed off in late 2012. But by
mid-2013 all sectors, including housing, commercial and
industrial, were picking up again, along with construction
employment, which is now showing moderate growth.
International building costs
per m2 of internal area, in 2013

The overvalued Canadian dollar has eased down


five percent against the US dollar in 2013. This will
shore up Canadas competitive position and
export earnings.
Construction cost increases will be moderate,
with tendering competitive and only small wage
increases. The relatively weak domestic private
sector should improve over 2013 and 2014.

CAD

USD

Purchasing
power parity

(exchange rate:
1.03)

Airports
Domestic terminal full service
Low-cost carrier basic service

5,750
4,020

5,583
3,903

5,301
3,706

Carparks
Multistorey above ground
Multistorey below ground

810
1,110

786
1,078

747
1,023

Commercial
Offices business park
CBD offices up to 20 floors medium (A-grade)
CBD offices high-rise prestige

1,710
2,020
2,920

1,660
1,961
2,835

1,577
1,862
2,692

Education
Primary and secondary schools
University

1,820
3,530

1,767
3,427

1,678
3,254

Hospitals
Day centre (including basic surgeries)
Regional hospital
General hospital (eg city teaching hospital)

3,730
5,750
6,860

3,621
5,583
6,660

3,439
5,301
6,325

Hotels
3 star travellers
5 star luxury
Resort style

1,410
2,820
2,820

1,369
2,738
2,738

1,300
2,600
2,600

Industrial
Warehouse/factory units basic
Large warehouse distribution centre
High-tech factory/laboratory

910
1,010
1,410

883
981
1,369

839
931
1,300

Residential
Individual detached house medium standard
Individual detached house prestige
Townhouses medium standard
Apartments private medium density
Apartments high rise
Aged care/affordable units

2,870
3,890
1,430
1,920
1,720
2,020

2,786
3,777
1,388
1,864
1,670
1,961

2,646
3,586
1,318
1,770
1,586
1,862

Retail
Large shopping centre including mall
Neighbourhood incl supermarket
Prestige car showroom

2,400
2,200
2,600

2,330
2,136
2,524

2,213
2,028
2,397

16

Turner & Townsend

Canada international building costs


per m2 of internal area

CAD

USD

Purchasing
power parity

15
20
192
1,919
121
105
3,283
125
934
45
1,100
10
86
66
56
51
66
35
165

15
20
186
1,863
117
102
3,187
121
907
44
1,068
10
83
64
54
49
64
34
160

14
19
177
1,769
112
97
3,026
115
861
41
1,014
9
79
61
51
47
61
33
152

62
56
51
46
76

60
54
50
44
74

57
52
47
42
70

Material
Concrete 30 MPa (m3) (1,500m3 job)
Reinforcement bar 16mm (tonne) (120 tonne job)
Concrete block (400x200) per 1,000 (>10,000 block job)
Standard brick per 1,000
Structural steel beams (tonne) (100 tonne + job)
Glass pane 10mm tempered (m2)
Softwood timber for framing 100mm x 50mm (m)
13 mm plasterboard (m2)
Emulsion paint (litre)
Copper pipe 15 mm (m) (1,000m+ job)
Copper cable (m) (3C + E, 2.5mm PVC) (100,000m+ job)

167
1,400
1,400
909
2,200
280
5
10
10
10
7

162
1,359
1,359
883
2,136
272
5
10
10
10
7

154
1,291
1,291
838
2,028
258
5
9
9
9
7

Plant
Hire 50t mobile crane + operator (day)

1,800

1,748

1,660

Composite
Excavate basement (m3) (1,800m3 job)
Excavate footings (m)
Concrete in slab (m3) (1,500m3 job)
Reinforcement in beams (tonne)
Formwork to soffit of slab (m2)
Blockwork in wall (m2) (10,000 block job)
Structural steel beams (tonne)
Pre-cast concrete wall (m2)
Curtain wall glazing incl support system (m2) (1,000m2 job)
Plasterboard 13mm thick to stud wall (m2) (3,000m2 job)
Single solid core door incl frame and hardware (50 door job)
Painting to walls primer + 2 coats (m2)
Ceramic tiling (m2) (1,000m2 job)
Vinyl flooring to wet areas (m2) (500m2 job)
Carpet medium tufted (m2) (4,500m2 job)
Lighting installation (m2) (5,000m2+ job)
Copper pipe 15mm to wall (m) (1,000m+ job)
Fire sprinklers (per m2) (5,000m2 job)
Air conditioning incl main plant (m2) (5,000m2+ job)
Labour
Group 1 tradesman eg plumber/electrician
Group 2 tradesman eg carpenter/bricklayer
Group 3 tradesman eg carpet layer, tiler, plasterer
General labourer
Site foreman

Market:
Tendering:

getting warmer
lukewarm

(exchange rate:
1.03)

Calgary

113

Edmonton

111

Cost escalation:

3%

Halifax

95

Contractors margin:

2%

Montreal

95

Preliminaries:

8%

Ottawa

103

Toronto

100

Vancouver

95

International construction cost survey 2013

17

China
Construction market cools as growth rate slows
Chinese growth has now settled at a more moderate
level of seven to eight percent, following several years
of very strong growth. The Chinese economy is still
investment led, despite efforts to stimulate domestic
consumption and grow the Chinese middle class.
Once again, housing and apartment construction
is in danger of overheating, although various government
efforts to slow this sector may prove successful for
a while. Efforts are being made to encourage more
foreign investment, such as healthcare provision.

Construction in the commercial and retail sectors


is buoyant, but industrial spending appears to be
slowing, especially in the more developed southern
and eastern cities.
Though the Chinese market is cooler, tender prices
are still expected to increase, albeit at a lower rate than
in previous years. Labour costs, while still a relatively
low portion of total construction costs, are still growing
and are likely to have more of an impact on tender prices
in the future.
USD

Purchasing
power parity

10,900
8,010

1,778
1,307

3,282
2,412

Carparks
Multistorey above ground
Multistorey below ground

2,140
4,780

349
780

644
1,439

Commercial
Offices business park
CBD offices up to 20 floors medium (A-grade)
CBD offices high-rise prestige

4,690
7,450
9,300

765
1,215
1,517

1,412
2,243
2,800

Education
Primary and secondary schools
University

3,640
5,390

594
879

1,096
1,623

Hospitals
Day centre (including basic surgeries)
Regional hospital
General hospital (eg city teaching hospital)

4,410
5,350
5,980

719
873
976

1,328
1,611
1,800

5,780
15,000
8,750

943
2,447
1,427

1,740
4,516
2,634

Industrial
Warehouse/factory units basic
Large warehouse distribution centre
High-tech factory/laboratory

2,580
3,050
5,870

421
498
958

777
918
1,767

Residential
Individual detached house medium standard
Individual detached house prestige
Townhouses medium standard
Apartments private medium density
Apartments high rise
Aged care/affordable units

4,540
5,240
4,110
3,330
4,600
2,710

741
855
670
543
750
442

1,367
1,578
1,237
1,003
1,385
816

Retail
Large shopping centre including mall
Neighbourhood incl supermarket
Prestige car showroom

6,180
4,220
3,650

1,008
688
595

1,861
1,271
1,099

International building costs


per m2 of internal area, in 2013
Airports
Domestic terminal full service
Low-cost carrier basic service

Hotels
3 star travellers
5 star luxury
Resort style

18

Turner & Townsend

CNY

(exchange rate:
6.13)

China international building costs


per m2 of internal area

CNY

USD

Purchasing
power parity

34
54
560
5,200
90
155
9,800
210
1,600
180
2,670
48
210
385
390
320
85
280
490

6
9
91
848
15
25
1,599
34
261
29
436
8
34
63
64
52
14
46
80

10
16
169
1,566
27
47
2,950
63
482
54
804
14
63
116
117
96
26
84
148

22
21
19
13
31

4
3
3
2
5

7
6
6
4
9

Material
Concrete 30 MPa (m3) (1,500m3 job)
Reinforcement bar 16mm (tonne) (120 tonne job)
Concrete block (400x200) per 1,000 (>10,000 block job)
Standard brick per 1,000
Structural steel beams (tonne) (100 tonne + job)
Glass pane 10mm tempered (m2)
Softwood timber for framing 100mm x 50mm (m)
13 mm plasterboard (m2)
Emulsion paint (litre)
Copper pipe 15 mm (m) (1,000m+ job)
Copper cable (m) (3C + E, 2.5mm PVC) (100,000m+ job)

430
4,500
3,200
450
8,600
530
62
38
65
53
18

70
734
522
73
1,403
86
10
6
11
9
3

129
1,355
964
135
2,589
160
19
11
20
16
5

Plant
Hire 50t mobile crane + operator (day)

2,100

343

632

Composite
Excavate basement (m3) (1,800m3 job)
Excavate footings (m)
Concrete in slab (m3) (1,500m3 job)
Reinforcement in beams (tonne)
Formwork to soffit of slab (m2)
Blockwork in wall (m2) (10,000 block job)
Structural steel beams (tonne)
Pre-cast concrete wall (m2)
Curtain wall glazing incl support system (m2) (1,000m2 job)
Plasterboard 13mm thick to stud wall (m2) (3,000m2 job)
Single solid core door incl frame and hardware (50 door job)
Painting to walls primer + 2 coats (m2)
Ceramic tiling (m2) (1,000m2 job)
Vinyl flooring to wet areas (m2) (500m2 job)
Carpet medium tufted (m2) (4,500m2 job)
Lighting installation (m2) (5,000m2+ job)
Copper pipe 15mm to wall (m) (1,000m+ job)
Fire sprinklers (per m2) (5,000m2 job)
Air conditioning incl main plant (m2) (5,000m2+ job)
Labour
Group 1 tradesman eg plumber/electrician
Group 2 tradesman eg carpenter/bricklayer
Group 3 tradesman eg carpet layer, tiler, plasterer
General labourer
Site foreman

Market:
Tendering:

getting cooler
lukewarm

(exchange rate:
6.13)

Beijing

97

Chongqing

100

Cost escalation:

5%

Guangzhou

Contractors margin:

6%

Shanghai

100

Preliminaries:

8%

Shenzhen

105

92

International construction cost survey 2013

19

Germany
Solid growth which looks set to continue
Germany achieved a region-leading growth rate of
0.9 percent in the second quarter of 2013 compared
to the same period in 2012. Business confidence is now
at its highest level in 16 months, indicating the improving
prospects of the region.

Some of the major infrastructure projects which added


to this growth rate, such as the Berlin airport and the
Frankfurt airport expansion, are, however, coming to
an end. The outlook for commercial and infrastructure
construction for the immediate future is slightly weaker.

Housebuilding is benefiting from low interest rates,


improving demand and a growing preference to hold
physical assets rather than shares. German industry
is doing well, with orders continuing to increase. This also
holds for the building, civil engineering and underground
construction sectors which have grown by nearly ten
percent over the last year.

As a consequence, construction cost escalation is mild.


But as the economies of Germanys European neighbours
improve over 201416, German construction activity
is set to increase further.

International building costs


per m2 of internal area, in 2013

USD

Purchasing
power parity

2,800
1,650

3,684
2,171

4,188
2,468

600
760

789
1,000

897
1,137

Commercial
Offices business park
CBD offices up to 20 floors medium (A-grade)
CBD offices high-rise prestige

1,250
1,940
2,300

1,645
2,553
3,026

1,870
2,902
3,440

Education
Primary and secondary schools
University

1,540
1,930

2,026
2,539

2,303
2,887

Hospitals
Day centre (including basic surgeries)
Regional hospital
General hospital (eg city teaching hospital)

1,970
2,750
3,030

2,592
3,618
3,987

2,946
4,113
4,532

Hotels
3 star travellers
5 star luxury
Resort style

1,490
3,250
2,110

1,961
4,276
2,776

2,229
4,861
3,156

Industrial
Warehouse/factory units basic
Large warehouse distribution centre
High-tech factory/laboratory

620
750
1,750

816
987
2,303

927
1,122
2,617

Residential
Individual detached house medium standard
Individual detached house prestige
Townhouses medium standard
Apartments private medium density
Apartments high rise
Aged care/affordable units

1,000
1,390
1,050
950
1,370
1,100

1,316
1,829
1,382
1,250
1,803
1,447

1,496
2,079
1,570
1,421
2,049
1,645

Retail
Large shopping centre including mall
Neighbourhood incl supermarket
Prestige car showroom

2,050
1,750
2,240

2,697
2,303
2,947

3,066
2,617
3,350

Airports
Domestic terminal full service
Low-cost carrier basic service
Carparks
Multistorey above ground
Multistorey below ground

20

Turner & Townsend

EUR

(exchange rate:
0.76)

Germany international building costs


per m2 of internal area

EUR

USD

Purchasing
power parity

14
26
132
1,342
41
68
3,617
101
614
49
865
7
53
29
24
56
30
79
90

18
34
174
1,766
55
89
4,759
133
808
64
1,138
9
69
38
32
74
39
104
118

21
39
197
2,007
62
102
5,410
151
918
73
1,294
10
79
43
37
84
45
118
135

45
38
38
28
41

59
50
50
37
54

67
57
57
42
61

Material
Concrete 30 MPa (m3) (1,500m3 job)
Reinforcement bar 16mm (tonne) (120 tonne job)
Concrete block (400x200) per 1,000 (>10,000 block job)
Standard brick per 1,000
Structural steel beams (tonne) (100 tonne + job)
Glass pane 10mm tempered (m2)
Softwood timber for framing 100mm x 50mm (m)
13 mm plasterboard (m2)
Emulsion paint (litre)
Copper pipe 15 mm (m) (1,000m+ job)
Copper cable (m) (3C + E, 2.5mm PVC) (100,000m+ job)

108
823
4,667
673
1,800
100
3
4
5
8
4

142
1,083
6,141
885
2,368
132
4
5
7
11
5

162
1,231
6,980
1,006
2,692
150
4
5
7
12
6

Plant
Hire 50t mobile crane + operator (day)

1,250

1,645

1,870

Composite
Excavate basement (m3) (1,800m3 job)
Excavate footings (m)
Concrete in slab (m3) (1,500m3 job)
Reinforcement in beams (tonne)
Formwork to soffit of slab (m2)
Blockwork in wall (m2) (10,000 block job)
Structural steel beams (tonne)
Pre-cast concrete wall (m2)
Curtain wall glazing incl support system (m2) (1,000m2 job)
Plasterboard 13mm thick to stud wall (m2) (3,000m2 job)
Single solid core door incl frame and hardware (50 door job)
Painting to walls primer + 2 coats (m2)
Ceramic tiling (m2) (1,000m2 job)
Vinyl flooring to wet areas (m2) (500m2 job)
Carpet medium tufted (m2) (4,500m2 job)
Lighting installation (m2) (5,000m2+ job)
Copper pipe 15mm to wall (m) (1,000m+ job)
Fire sprinklers (per m2) (5,000m2 job)
Air conditioning incl main plant (m2) (5,000m2+ job)
Labour
Group 1 tradesman eg plumber/electrician
Group 2 tradesman eg carpenter/bricklayer
Group 3 tradesman eg carpet layer, tiler, plasterer
General labourer
Site foreman

Market:
Tendering:

getting warmer
lukewarm

Berlin

90

Frankfurt

95

Cost escalation:

3%

Munich

Contractors margin:

5%

Stuttgart

Preliminaries:

(exchange rate:
0.76)

100
96

15%

There was an average German escalation of two percent during 210213. Some costs/rates are significantly higher than previous
editions following an exercise to align specifications and inclusions with regional peers.

International construction cost survey 2013

21

Hong Kong
Booming civil sector will push prices up in 2014
Hong Kongs construction industry is experiencing
strong growth, with several sectors booming again.
The civil construction sector is by far the largest growth
driver, with five large rail projects underway or scheduled
to commence soon. Besides these high-profile rail projects,
an Environmental Impact Statement for an USD11.1bn
third runway at the citys airport is now underway.
Due to these projects and incessant demand for
commercial and residential real estate in the densely
populated city, construction volumes are at a high level.
International building costs
per m2 of internal area, in 2013

Construction materials costs are rising relatively slowly,


with the exception of key civil materials, such as concrete
and rebar. Labour costs, however, suffer from high cost
escalation due to increasing labour shortages and
an ageing workforce.
In the short term, construction cost escalation will
remain comparatively moderate. However, from the
second quarter of 2014 costs are forecast to increase
strongly again.

HKD

USD

Purchasing
power parity

(exchange rate:
7.75)

Airports
Domestic terminal full service
Low-cost carrier basic service

40,000
25,000

5,161
3,226

7,018
4,386

Carparks
Multistorey above ground
Multistorey below ground

10,000
18,000

1,290
2,323

1,754
3,158

Commercial
Offices business park
CBD offices up to 20 floors medium (A-grade)
CBD offices high-rise prestige

18,000
21,000
24,000

2,323
2,710
3,097

3,158
3,684
4,211

Education
Primary and secondary schools
University

18,000
24,000

2,323
3,097

3,158
4,211

Hospitals
Day centre (including basic surgeries)
Regional hospital
General hospital (eg city teaching hospital)

18,000
28,000
32,000

2,323
3,613
4,129

3,158
4,912
5,614

Hotels
3 star travellers
5 star luxury
Resort style

26,000
32,000
35,000

3,355
4,129
4,516

4,561
5,614
6,140

Industrial
Warehouse/factory units basic
Large warehouse distribution centre
High-tech factory/laboratory

13,500
15,000
25,000

1,742
1,935
3,226

2,368
2,632
4,386

Residential
Individual detached house medium standard
Individual detached house prestige
Townhouses medium standard
Apartments private medium density
Apartments high rise
Aged care/affordable units

28,000
35,000
22,000
20,000
22,000
14,000

3,613
4,516
2,839
2,581
2,839
1,806

4,912
6,140
3,860
3,509
3,860
2,456

Retail
Large shopping centre including mall
Neighbourhood incl supermarket
Prestige car showroom

28,000
22,000
28,000

3,613
2,839
3,613

4,912
3,860
4,912

22

Turner & Townsend

Hong Kong international building costs


per m2 of internal area

HKD

Composite
Excavate basement (m3) (1,800m3 job)
Excavate footings (m)
Concrete in slab (m3) (1,500m3 job)
Reinforcement in beams (tonne)
Formwork to soffit of slab (m2)
Blockwork in wall (m2) (10,000 block job)
Structural steel beams (tonne)
Pre-cast concrete wall (m2)
Curtain wall glazing incl support system (m2) (1,000m2 job)
Plasterboard 13mm thick to stud wall (m2) (3,000m2 job)
Single solid core door incl frame and hardware (50 door job)
Painting to walls primer + 2 coats (m2)
Ceramic tiling (m2) (1,000m2 job)
Vinyl flooring to wet areas (m2) (500m2 job)
Carpet medium tufted (m2) (4,500m2 job)
Lighting installation (m2) (5,000m2+ job)
Copper pipe 15mm to wall (m) (1,000m+ job)
Fire sprinklers (per m2) (5,000m2 job)
Air conditioning incl main plant (m2) (5,000m2+ job)
Labour
Group 1 tradesman eg plumber/electrician
Group 2 tradesman eg carpenter/bricklayer
Group 3 tradesman eg carpet layer, tiler, plasterer
General labourer
Site foreman
Material
Concrete 30 MPa (m3) (1,500m3 job)
Reinforcement bar 16mm (tonne) (120 tonne job)
Concrete block (400x200) per 1,000 (>10,000 block job)
Standard brick per 1,000
Structural steel beams (tonne) (100 tonne + job)
Glass pane 10mm tempered (m2)
Softwood timber for framing 100mm x 50mm (m)
13 mm plasterboard (m2)
Emulsion paint (litre)
Copper pipe 15 mm (m) (1,000m+ job)
Copper cable (m) (3C + E, 2.5mm PVC) (100,000m+ job)
Plant
Hire 50t mobile crane + operator (day)

Market:
Tendering:

Purchasing
power parity

120
130
1,260
10,900
300
350
37,500
1,200
5,040
450
6,000
120
650
300
480
850
210
520
2,600

15
17
163
1,406
39
45
4,839
155
650
58
774
15
84
39
62
110
27
67
335

21
23
221
1,912
53
61
6,579
211
884
79
1,053
21
114
53
84
149
37
91
456

110
140
120
78
160

14
18
15
10
21

19
25
21
14
28

650
6,015
3,500
1,950
12,000
1,880
65
80
55
28
14

84
776
452
252
1,548
243
8
10
7
4
2

114
1,055
614
342
2,105
330
11
14
10
5
2

6,000

774

1,053

staying the same


warm

Cost escalation:

6%

Contractors margin:

6%

Preliminaries:

USD

(exchange rate:
7.75)

15%

International construction cost survey 2013

23

India
Slow now, but long-term prospects look good
At five percent year-on-year, growth in the Indian
economy in 201213 has been the slowest the country
has seen in the past decade.
Rising interest costs and fewer government and private
projects have affected the construction sector. Contractors
also complain about excessive bureaucracy causing slower
project approvals and increased financial risks.

Recently announced government programmes include


easing of foreign direct investment rules in the multi-brand
retail and aviation sectors and increased investment plans
for metro rail projects in 19 cities, motorways and roads.
Inflation and construction cost escalation remain quite
high. The weakened exchange rate will add to costs
of imported equipment, machinery, fuel and materials.

Despite the short-term weakness, the outlook for the


sector remains positive in the longer term. The upside
of the weakening exchange rate will be improved export
earnings, providing much-needed capital for investment.
International building costs
per m2 of internal area, in 2013

INR

USD

Purchasing
power parity

(exchange rate:
58.00)

Airports
Domestic terminal full service
Low-cost carrier basic service

70,850
49,600

1,222
855

3,633
2,543

Carparks
Multistorey above ground
Multistorey below ground

27,360
43,320

472
747

1,403
2,221

Commercial
Offices business park
CBD offices up to 20 floors medium (A-grade)
CBD offices high-rise prestige

34,200
39,900
43,320

590
688
747

1,754
2,046
2,221

Education
Primary and secondary schools
University

20,520
43,320

354
747

1,052
2,221

Hospitals
Day centre (including basic surgeries)
Regional hospital
General hospital (eg city teaching hospital)

23,940
42,180
33,060

413
727
570

1,227
2,163
1,695

Hotels
3 star travellers
5 star luxury
Resort style

43,320
85,500
54,720

747
1,474
943

2,221
4,384
2,806

Industrial
Warehouse/factory units basic
Large warehouse distribution centre
High-tech factory/laboratory

29,420
37,190
44,400

507
641
766

1,508
1,907
2,277

Residential
Individual detached house medium standard
Individual detached house prestige
Townhouses medium standard
Apartments private medium density
Apartments high rise
Aged care/affordable units

34,200
42,750
28,500
22,800
51,300
20,520

590
737
491
393
884
354

1,754
2,192
1,461
1,169
2,630
1,052

Retail
Large shopping centre including mall
Neighbourhood incl supermarket
Prestige car showroom

43,320
29,640
19,950

747
511
344

2,221
1,520
1,023

24

Turner & Townsend

India international building costs


per m2 of internal area

INR

USD

Purchasing
power parity

350
542
7,500
66,000
541
1,300
96,000
8,910
12,000
4,000
34,000
220
3,146
2,360
2,462
2,300
660
891
4,500

6
9
129
1,138
9
22
1,655
154
207
69
586
4
54
41
42
40
11
15
78

18
28
385
3,384
28
67
4,922
457
615
205
1,743
11
161
121
126
118
34
46
231

63
56
43
23
90

1
1
1
0
2

3
3
2
1
5

Material
Concrete 30 MPa (m3) (1,500m3 job)
Reinforcement bar 16mm (tonne) (120 tonne job)
Concrete block (400x200) per 1,000 (>10,000 block job)
Standard brick per 1,000
Structural steel beams (tonne) (100 tonne + job)
Glass pane 10mm tempered (m2)
Softwood timber for framing 100mm x 50mm (m)
13 mm plasterboard (m2)
Emulsion paint (litre)
Copper pipe 15 mm (m) (1,000m+ job)
Copper cable (m) (3C + E, 2.5mm PVC) (100,000m+ job)

5,525
44,800
36,750
6,647
56,000
1,250
283
350
275
550
130

95
772
634
115
966
22
5
6
5
9
2

283
2,297
1,884
341
2,871
64
15
18
14
28
7

Plant
Hire 50t mobile crane + operator (day)

16,020

276

821

Composite
Excavate basement (m3) (1,800m3 job)
Excavate footings (m)
Concrete in slab (m3) (1,500m3 job)
Reinforcement in beams (tonne)
Formwork to soffit of slab (m2)
Blockwork in wall (m2) (10,000 block job)
Structural steel beams (tonne)
Pre-cast concrete wall (m2)
Curtain wall glazing incl support system (m2) (1,000m2 job)
Plasterboard 13mm thick to stud wall (m2) (3,000m2 job)
Single solid core door incl frame and hardware (50 door job)
Painting to walls primer + 2 coats (m2)
Ceramic tiling (m2) (1,000m2 job)
Vinyl flooring to wet areas (m2) (500m2 job)
Carpet medium tufted (m2) (4,500m2 job)
Lighting installation (m2) (5,000m2+ job)
Copper pipe 15mm to wall (m) (1,000m+ job)
Fire sprinklers (per m2) (5,000m2 job)
Air conditioning incl main plant (m2) (5,000m2+ job)
Labour
Group 1 tradesman eg plumber/electrician
Group 2 tradesman eg carpenter/bricklayer
Group 3 tradesman eg carpet layer, tiler, plasterer
General labourer
Site foreman

Market:
Tendering:
Cost escalation:
Contractors margin:
Preliminaries:

getting cooler
warm

(exchange rate:
58.00)

Bangalore

104

Chennai

96

7%

Kolkata

96

16%

Mumbai

100

9%

New Delhi

97

International construction cost survey 2013

25

Ireland
Low demand and high competition are keeping prices down
The Irish construction sector has shrunk considerably
since 2006, with 34 percent fewer firms in 2013
compared to then. Skills and expertise have been lost,
with professionals and tradespeople moving to work
overseas. At the height of Irelands construction boom,
273,000 people were directly employed in the sector,
a figure that had shrunk to 99,600 in 2012.
GDP growth remains below one percent in 2013 as Ireland
faces weaker demand from Europe and the UK. Domestic
demand is hampered by continued austerity measures
aimed at correcting fiscal imbalance; its effects include
a lack of development finance, weak confidence and
low demand.

Some projects are coming through in the public sector,


thanks to the governments school-building programme,
its purchasing power parity stimulus package, and
spending on maintenance and energy-efficiency measures
for schools, roads and local authority housing. Despite this,
construction opportunities overall are down.
Tender prices are competitive and high levels of
unemployment in construction will keep construction
cost increases to a minimum for several years. Gradually,
as the European and US economies improve over 201415,
Ireland will benefit through improved demand and the
relaxation of austerity measures.
Data for Northern Ireland is included in UK figures
on pages 5253.
USD

Purchasing
power parity

3,540
2,470

4,658
3,250

6,850
4,779

510
880

671
1,158

987
1,703

Commercial
Offices business park
CBD offices up to 20 floors medium (A-grade)
CBD offices high-rise prestige

1,200
1,810
2,730

1,579
2,382
3,592

2,322
3,502
5,282

Education
Primary and secondary schools
University

1,100
2,030

1,447
2,671

2,128
3,928

Hospitals
Day centre (including basic surgeries)
Regional hospital
General hospital (eg city teaching hospital)

2,210
3,270
3,270

2,908
4,303
4,303

4,276
6,327
6,327

Hotels
3 Star travellers
5 Star luxury
Resort style

1,570
2,780
2,020

2,066
3,658
2,658

3,038
5,379
3,909

Industrial
Warehouse/factory units basic
Large warehouse distribution centre
High tech factory/laboratory

510
890
1,600

671
1,171
2,105

987
1,722
3,096

Residential
Individual detached house medium standard
Individual detached house prestige
Townhouses medium standard
Apartments private medium density
Apartments high rise
Aged care/affordable units

1,010
1,620
1,010
1,360
1,520
1,840

1,329
2,132
1,329
1,789
2,000
2,421

1,954
3,135
1,954
2,632
2,941
3,560

Retail
Large shopping centre including mall
Neighbourhood incl supermarket
Prestige car showroom

2,250
2,040
2,700

2,961
2,684
3,553

4,354
3,947
5,224

International building costs


per m2 of internal area, in 2013
Airports
Domestic terminal full service
Low-cost carrier basic service
Carparks
Multistorey above ground
Multistorey below ground

26

Turner & Townsend

EUR

(exchange rate:
0.76)

Ireland international building costs


per m2 of internal area

EUR

USD

Purchasing
power parity

9
19
140
950
29
23
1,850
85
433
52
742
6
57
33
26
45
29
75
120

12
24
184
1,249
38
30
2,434
112
569
68
976
8
75
43
34
59
39
99
158

18
36
271
1,837
56
44
3,579
164
837
100
1,435
12
110
64
50
87
57
145
232

29
29
29
22
29

38
38
38
29
38

56
56
56
43
56

Material
Concrete 30 MPa (m3) (1,500m3 job)
Reinforcement bar 16mm (tonne) (120 tonne job)
Concrete block (400x200) per 1,000 (>10,000 block job)
Standard brick per 1,000
Structural steel beams (tonne) (100 tonne + job)
Glass pane 10mm tempered (m2)
Softwood timber for framing 100mm x 50mm (m)
13 mm plasterboard (m2)
Emulsion paint (litre)
Copper pipe 15 mm (m) (1,000m+ job)
Copper cable (m) (3C + E, 2.5mm PVC) (100,000m+ job)

75
750
2,400
450
1,250
178
1
3
4
3
1

99
986
3,158
592
1,644
234
1
4
5
4
1

145
1,451
4,644
871
2,418
345
2
6
8
6
2

Plant
Hire 50t mobile crane + operator (day)

1,150

1,513

2,225

Composite
Excavate basement (m3) (1,800m3 job)
Excavate footings (m)
Concrete in slab (m3) (1,500m3 job)
Reinforcement in beams (tonne)
Formwork to soffit of slab (m2)
Blockwork in wall (m2) (10,000 block job)
Structural steel beams (tonne)
Pre-cast concrete wall (m2)
Curtain wall glazing incl support system (m2) (1,000m2 job)
Plasterboard 13mm thick to stud wall (m2) (3,000m2 job)
Single solid core door incl frame and hardware (50 door job)
Painting to walls primer + 2 coats (m2)
Ceramic tiling (m2) (1,000m2 job)
Vinyl flooring to wet areas (m2) (500m2 job)
Carpet medium tufted (m2) (4,500m2 job)
Lighting installation (m2) (5,000m2+ job)
Copper pipe 15mm to wall (m) (1,000m+ job)
Fire sprinklers (per m2) (5,000m2 job)
Air conditioning incl main plant (m2) (5,000m2+ job)
Labour
Group 1 tradesman eg plumber/electrician
Group 2 tradesman eg carpenter/bricklayer
Group 3 tradesman eg carpet layer, tiler, plasterer
General labourer
Site foreman

Market:
Tendering:

staying the same


cold

Cost escalation:

2%

Contractors margin:

2%

Preliminaries:

(exchange rate:
0.76)

10%

International construction cost survey 2013

27

Japan
Abenomics helps Japan to rise again
Are the years of stagnation for the Japanese economy
coming to an end? The signs look positive.
Business conditions are recovering, with the share
market rising 42 percent between January and the
end of September 2013. GDP growth is positive again
as Abenomics, the policies of Prime Minister Shinz Abe,
take effect. These include further monetary easing,
tax breaks and a weaker currency, which will stimulate
Japanese export growth.

The news in September 2013 that Tokyo will host the 2020
Olympics is also positive for the construction sector, with
investment in stadiums, housing and transport expected.
Reports of sporadic skills shortages in key construction
trades means that cost escalation is presently a little
higher than in other developed economies.

Property prices look set to rise. New housing starts


have increased by nearly 15 percent in the last year.
Rebuilding after the 2011 tsunami has also added
to construction activity.
International building costs
per m2 of internal area, in 2013

JPY

USD

Purchasing
power parity

(exchange rate:
97.90)

Airports
Domestic terminal full service
Low-cost carrier basic service

370,000
302,100

3,779
3,086

5,359
4,376

Carparks
Multistorey above ground
Multistorey below ground

205,300
444,800

2,097
4,543

2,974
6,443

Commercial
Offices business park
CBD offices up to 20 floors medium (A-grade)
CBD offices high-rise prestige

230,500
266,500
303,800

2,354
2,722
3,103

3,339
3,860
4,401

Education
Primary and secondary schools
University

202,400
186,300

2,067
1,903

2,932
2,699

Hospitals
Day centre (including basic surgeries)
Regional hospital
General hospital (eg city teaching hospital)

164,000
164,000
247,800

1,675
1,675
2,531

2,376
2,376
3,589

Hotels
3 star travellers
5 star luxury
Resort style

349,000
523,400
289,500

3,565
5,346
2,957

5,055
7,581
4,193

Industrial
Warehouse/factory units basic
Large warehouse distribution centre
High-tech factory/laboratory

154,500
207,900
455,000

1,578
2,124
4,648

2,238
3,011
6,591

Residential
Individual detached house medium standard
Individual detached house prestige
Townhouses medium standard
Apartments private medium density
Apartments high rise
Aged care/affordable units

201,500
235,800
186,700
189,300
284,000
164,800

2,058
2,409
1,907
1,934
2,901
1,683

2,919
3,416
2,704
2,742
4,114
2,387

Retail
Large shopping centre including mall
Neighbourhood incl supermarket
Prestige car showroom

304,000
368,400
485,000

3,105
3,763
4,954

4,403
5,336
7,025

28

Turner & Townsend

Japan international building costs


per m2 of internal area

JPY

USD

Purchasing
power parity

450
500
13,710
97,000
2,680
4,410
114,960
15,140
100,000
3,050
73,600
860
5,820
3,380
4,300
4,500
2,290
4,000
28,900

5
5
140
991
27
45
1,174
155
1,021
31
752
9
59
35
44
46
23
41
295

7
7
199
1,405
39
64
1,665
219
1,448
44
1,066
12
84
49
62
65
33
58
419

2,400
2,210
2,140
1,700
2,440

25
23
22
17
25

35
32
31
25
35

Material
Concrete 30 MPa (m3) (1,500m3 job)
Reinforcement bar 16mm (tonne) (120 tonne job)
Concrete block (400x200) per 1,000 (>10,000 block job)
Standard brick per 1,000
Structural steel beams (tonne) (100 tonne + job)
Glass pane 10mm tempered (m2)
Softwood timber for framing 100mm x 50mm (m)
13 mm plasterboard (m2)
Emulsion paint (litre)
Copper pipe 15 mm (m) (1,000m+ job)
Copper cable (m) (3C + E, 2.5mm PVC) (100,000m+ job)

11,900
66,000
110,000
97,500
80,000
1,730
1,210
230
270
661
181

122
674
1,124
996
817
18
12
2
3
7
2

172
956
1,593
1,412
1,159
25
18
3
4
10
3

Plant
Hire 50t mobile crane + operator (day)

150,000

1,532

2,173

Composite
Excavate basement (m3) (1,800m3 job)
Excavate footings (m)
Concrete in slab (m3) (1,500m3 job)
Reinforcement in beams (tonne)
Formwork to soffit of slab (m2)
Blockwork in wall (m2) (10,000 block job)
Structural steel beams (tonne)
Pre-cast concrete wall (m2)
Curtain wall glazing incl support system (m2) (1,000m2 job)
Plasterboard 13mm thick to stud wall (m2) (3,000m2 job)
Single solid core door incl frame and hardware (50 door job)
Painting to walls primer + 2 coats (m2)
Ceramic tiling (m2) (1,000m2 job)
Vinyl flooring to wet areas (m2) (500m2 job)
Carpet medium tufted (m2) (4,500m2 job)
Lighting installation (m2) (5,000m2+ job)
Copper pipe 15mm to wall (m) (1,000m+ job)
Fire sprinklers (per m2) (5,000m2 job)
Air conditioning incl main plant (m2) (5,000m2+ job)
Labour
Group 1 tradesman eg plumber/electrician
Group 2 tradesman eg carpenter/bricklayer
Group 3 tradesman eg carpet layer, tiler, plasterer
General labourer
Site foreman

Market:
Tendering:

getting warmer
warm

Cost escalation:

5%

Contractors margin:

6%

Preliminaries:

(exchange rate:
97.90)

15%

International construction cost survey 2013

29

Malaysia
Road, rail and major housing projects will drive costs up from low base
Malaysia is making fresh progress towards its goal of
achieving developed nation status by 2020. And a major
part of its strategy is an ambitious construction plan.
The Economic Transformation Programme (ETP) includes
USD52bn of new rail and road projects. Among these
projects are new light rail transit extensions, mass rapid
transit systems and a high-speed railway between Kuala
Lumpur and Singapore.
International building costs
per m2 of internal area, in 2013

The government is also planning large public housing


schemes. Rolled out progressively between now and
2020, these developments will provide a boost to the
construction sector.
For now, Malaysia remains a low-cost country
for construction. Shortages of skilled labour are,
however, likely to increase costs in the future.

MYR

USD

Purchasing
power parity

(exchange rate:
3.23)

Airports
Domestic terminal full service
Low-cost carrier basic service

6,240
4,370

1,932
1,353

4,136
2,896

Carparks
Multistorey above ground
Multistorey below ground

1,500
2,120

464
656

994
1,405

Commercial
Offices business park
CBD offices up to 20 floors medium (A-grade)
CBD offices high-rise prestige

3,110
4,060
5,680

963
1,257
1,759

2,061
2,691
3,764

Education
Primary and secondary schools
University

1,870
4,600

579
1,424

1,239
3,049

Hospitals
Day centre (including basic surgeries)
Regional hospital
General hospital (eg city teaching hospital)

2,810
3,740
4,210

870
1,158
1,303

1,862
2,479
2,790

Hotels
3 star travellers
5 star luxury
Resort style

5,140
8,920
9,330

1,591
2,762
2,889

3,407
5,912
6,183

Industrial
Warehouse/factory units basic
Large warehouse distribution centre
High-tech factory/laboratory

1,890
2,430
4,060

585
752
1,257

1,253
1,610
2,691

Residential
Individual detached house medium standard
Individual detached house prestige
Townhouses medium standard
Apartments private medium density
Apartments high rise
Aged care/affordable units

2,340
2,990
1,560
1,820
2,600
1,950

724
926
483
563
805
604

1,551
1,982
1,034
1,206
1,723
1,292

Retail
Large shopping centre including mall
Neighbourhood incl supermarket
Prestige car showroom

4,600
3,920
5,000

1,424
1,214
1,548

3,049
2,598
3,314

30

Turner & Townsend

Malaysia international building costs


per m2 of internal area

MYR

USD

Purchasing
power parity

35
50
347
3,950
52
70
6,798
226
418
94
836
8
115
103
94
157
82
105
314

11
15
108
1,223
16
22
2,105
70
129
29
259
3
36
32
29
49
25
32
97

23
33
230
2,618
35
46
4,505
149
277
62
554
5
76
68
62
104
54
69
208

21
15
21
10
56

6
5
6
3
17

14
10
14
7
37

Material
Concrete 30 MPa (m3) (1,500m3 job)
Reinforcement bar 16mm (tonne) (120 tonne job)
Concrete block (400x200) per 1,000 (>10,000 block job)
Standard brick per 1,000
Structural steel beams (tonne) (100 tonne + job)
Glass pane 10mm tempered (m2)
Softwood timber for framing 100mm x 50mm (m)
13 mm plasterboard (m2)
Emulsion paint (litre)
Copper pipe 15 mm (m) (1,000m+ job)
Copper cable (m) (3C + E, 2.5mm PVC) (100,000m+ job)

236
3,301
4,080
410
2,992
775
13
27
28
28
16

73
1,022
1,263
127
926
240
4
8
9
9
5

156
2,187
2,704
272
1,983
514
9
18
19
19
11

Plant
Hire 50t mobile crane + operator (day)

1,800

557

1,193

Composite
Excavate basement (m3) (1,800m3 job)
Excavate footings (m)
Concrete in slab (m3) (1,500m3 job)
Reinforcement in beams (tonne)
Formwork to soffit of slab (m2)
Blockwork in wall (m2) (10,000 block job)
Structural steel beams (tonne)
Pre-cast concrete wall (m2)
Curtain wall glazing incl support system (m2) (1,000m2 job)
Plasterboard 13mm thick to stud wall (m2) (3,000m2 job)
Single solid core door incl frame and hardware (50 door job)
Painting to walls primer + 2 coats (m2)
Ceramic tiling (m2) (1,000m2 job)
Vinyl flooring to wet areas (m2) (500m2 job)
Carpet medium tufted (m2) (4,500m2 job)
Lighting installation (m2) (5,000m2+ job)
Copper pipe 15mm to wall (m) (1,000m+ job)
Fire sprinklers (per m2) (5,000m2 job)
Air conditioning incl main plant (m2) (5,000m2+ job)
Labour
Group 1 tradesman eg plumber/electrician
Group 2 tradesman eg carpenter/bricklayer
Group 3 tradesman eg carpet layer, tiler, plasterer
General labourer
Site foreman

Market:
Tendering:

getting warmer
lukewarm

(exchange rate:
3.23)

Georgetown

97

Ipoh

97

Cost escalation:

3%

Johor Bahru

Contractors margin:

8%

Kuala Lumpur

100

Kuching

112

Preliminaries:

10%

88

International construction cost survey 2013

31

Netherlands
Projects thin on the ground beware of low bids
Despite being the fifth biggest economy in the
eurozone and its third largest exporter, GDP growth
in the Netherlands fell during 2013. New housing projects
are decreasing and business confidence remains firmly
in negative territory.
The forecast for 2014 economic growth was cut by another
quarter of a percentage point to 0.5 percent recently.
This reflects the 6bn in austerity measures needed
to bring Dutch public finances close to eurozone targets.
These measures, combined with weaker export demand,
mean unemployment has risen by nearly two percent since
July 2012, to 8.7 percent.
International building costs
per m2 of internal area, in 2013

Purchasing power parity projects are currently


one of the more buoyant construction sectors.
But overall, infrastructure growth is down and
private sector construction is subdued.
Tenders are very competitive. Cost escalation
is low, but low-value submissions are adding
to commercial risk.

EUR

USD

Purchasing
power parity

(exchange rate:
0.76)

Airports
Domestic terminal full service
Low-cost carrier basic service

3,180
2,230

4,184
2,934

5,301
3,717

Carparks
Multistorey above ground
Multistorey below ground

550
1,070

724
1,408

917
1,784

Commercial
Offices business park
CBD offices up to 20 floors medium (A-grade)
CBD offices high-rise prestige

1,550
2,110
2,550

2,039
2,776
3,355

2,584
3,517
4,251

Education
Primary and secondary schools
University

1,600
1,870

2,105
2,461

2,667
3,117

Hospitals
Day centre (including basic surgeries)
Regional Hospital
General Hospital (eg city teaching hospital)

2,200
2,500
3,000

2,895
3,289
3,947

3,667
4,167
5,001

Hotels
3 star travellers
5 star luxury
Resort style

1,770
2,770
2,330

2,329
3,645
3,066

2,951
4,617
3,884

Industrial
Warehouse/factory units basic
Large warehouse distribution centre
High-tech factory/laboratory

890
860
1,150

1,171
1,132
1,513

1,484
1,434
1,917

Residential
Individual detached house medium standard
Individual detached house prestige
Townhouses medium standard
Apartments private medium density
Apartments high rise
Aged care/affordable units

1,150
1,450
1,150
1,330
1,890
1,600

1,513
1,908
1,513
1,750
2,487
2,105

1,917
2,417
1,917
2,217
3,151
2,667

Retail
Large shopping centre including mall
Neighbourhood incl supermarket
Prestige car showroom

2,310
1,870
2,590

3,039
2,461
3,408

3,851
3,117
4,317

32

Turner & Townsend

Netherlands international building costs


per m2 of internal area

EUR

USD

Purchasing
power parity

13
25
195
1,158
35
47
2,527
105
632
79
1,120
17
75
46
35
68
26
37
86

17
33
257
1,524
46
62
3,324
138
831
104
1,474
22
99
61
46
89
34
48
114

22
42
325
1,930
58
79
4,212
175
1,053
132
1,867
28
125
77
58
113
43
61
144

42
34
30
23
39

56
45
40
30
52

71
57
50
38
65

Material
Concrete 30 MPa (m3) (1,500m3 job)
Reinforcement bar 16mm (tonne) (120 tonne job)
Concrete block (400x200) per 1,000 (>10,000 block job)
Standard brick per 1,000
Structural steel beams (tonne) (100 tonne + job)
Glass pane 10mm tempered (m2)
Softwood timber for framing 100mm x 50mm (m)
13 mm plasterboard (m2)
Emulsion paint (litre)
Copper pipe 15 mm (m) (1,000m+ job)
Copper cable (m) (3C + E, 2.5mm PVC) (100,000m+ job)

95
968
2,632
406
1,337
132
2
5
9
5
2

125
1,274
3,463
535
1,759
174
2
7
12
6
3

158
1,614
4,387
677
2,229
220
3
9
15
8
4

Plant
Hire 50t mobile crane + operator (day)

1,300

1,711

2,167

Composite
Excavate basement (m3) (1,800m3 job)
Excavate footings (m)
Concrete in slab (m3) (1,500m3 job)
Reinforcement in beams (tonne)
Formwork to soffit of slab (m2)
Blockwork in wall (m2) (10,000 block job)
Structural steel beams (tonne)
Pre-cast concrete wall (m2)
Curtain wall glazing incl support system (m2) (1,000m2 job)
Plasterboard 13mm thick to stud wall (m2) (3,000m2 job)
Single solid core door incl frame and hardware (50 door job)
Painting to walls primer + 2 coats (m2)
Ceramic tiling (m2) (1,000m2 job)
Vinyl flooring to wet areas (m2) (500m2 job)
Carpet medium tufted (m2) (4,500m2 job)
Lighting installation (m2) (5,000m2+ job)
Copper pipe 15mm to wall (m) (1,000m+ job)
Fire sprinklers (per m2) (5,000m2 job)
Air conditioning incl main plant (m2) (5,000m2+ job)
Labour
Group 1 tradesman eg plumber/electrician
Group 2 tradesman eg carpenter/bricklayer
Group 3 tradesman eg carpet layer, tiler, plasterer
General labourer
Site foreman

Market:
Tendering:

getting cooler

(exchange rate:
0.76)

Amsterdam

103

cold

Rotterdam

98

Cost escalation:

2%

The Hague

100

Contractors margin:

5%

Preliminaries:

13%

International construction cost survey 2013

33

Oman
Construction activity increasing, with major projects planned
The Sultanate of Oman was insulated for the most
part from the negative effects of the global financial
crisis, thanks to increased oil revenue. The government,
in its eighth five-year Development Plan (201115),
announced over OMR5.6bn of state spending on education,
healthcare, defence, transport infrastructure, and oil and
gas field development.
While private investment lags behind, groundwork is being
established for secure future investment, as Oman remains
one of the most politically and economically stable of the
GCC countries. Major projects include the Muscat
International building costs
per m2 of internal area, in 2013

International Airport and Salalah Airport, projected to


complete in 2015, and the development of international
ports at Duqm, Muscat, Salalah and Sohar.
As the country continues to develop its infrastructure and
industry to move away from its historic reliance on oil and
gas production, a broad increase in construction activity
is expected over the immediate future.

USD

Purchasing
power parity

1,400
950

3,684
2,500

7,458
5,061

Carparks
Multistorey above ground
Multistorey below ground

360
440

947
1,158

1,918
2,344

Commercial
Offices business park
CBD offices up to 20 floors medium (A-grade)
CBD offices high-rise prestige

410
510
690

1,079
1,342
1,816

2,184
2,717
3,676

Education
Primary and secondary schools
University

590
670

1,553
1,763

3,143
3,569

Hospitals
Day centre (including basic surgeries)
Regional hospital
General hospital (eg city teaching hospital)

590
740
900

1,553
1,947
2,368

3,143
3,942
4,794

920
1,230
1,490

2,421
3,237
3,921

4,901
6,552
7,937

440
410
620

1,158
1,079
1,632

2,344
2,184
3,303

620
1,000
540
560
670
490

1,632
2,632
1,421
1,474
1,763
1,289

3,303
5,327
2,877
2,983
3,569
2,610

670
720
970

1,763
1,895
2,553

3,569
3,835
5,167

Airports
Domestic terminal full service
Low-cost carrier basic service

Hotels
3 star travellers
5 star luxury
Resort style
Industrial
Warehouse/factory units basic
Large warehouse distribution centre
High-tech factory/laboratory
Residential
Individual detached house medium standard
Individual detached house prestige
Townhouses medium standard
Apartments private medium density
Apartments high rise
Aged care/affordable units
Retail
Large shopping centre including mall
Neighbourhood incl supermarket
Prestige car showroom

34

Turner & Townsend

OMR

(exchange rate:
0.38)

Oman international building costs


per m2 of internal area

OMR

USD

Purchasing
power parity

3
3
50
432
11
11
1,079
70
151
13
394
1
11
11
32
16
6
10
74

9
9
131
1,136
28
28
2,839
185
398
34
1,036
3
28
30
85
43
16
27
196

17
17
264
2,299
57
57
5,748
374
805
69
2,098
6
57
60
172
86
32
55
397

3
3
3
2
8

9
9
8
4
21

17
17
16
9
43

Material
Concrete 30 MPa (m3) (1,500m3 job)
Reinforcement bar 16mm (tonne) (120 tonne job)
Concrete block (400x200) per 1,000 (>10,000 block job)
Standard brick per 1,000
Structural steel beams (tonne) (100 tonne + job)
Glass pane 10mm tempered (m2)
Softwood timber for framing 100mm x 50mm (m)
13 mm plasterboard (m2)
Emulsion paint (litre)
Copper pipe 15 mm (m) (1,000m+ job)
Copper cable (m) (3C + E, 2.5mm PVC) (100,000m+ job)

27
311
375
268
589
69
2
2
6
1
0

70
817
986
704
1,550
180
4
4
16
3
1

143
1,654
1,996
1,426
3,137
365
8
8
32
7
2

Plant
Hire 50t mobile crane + operator (day)

627

1,650

3,340

Composite
Excavate basement (m3) (1,800m3 job)
Excavate footings (m)
Concrete in slab (m3) (1,500m3 job)
Reinforcement in beams (tonne)
Formwork to soffit of slab (m2)
Blockwork in wall (m2) (10,000 block job)
Structural steel beams (tonne)
Pre-cast concrete wall (m2)
Curtain wall glazing incl support system (m2) (1,000m2 job)
Plasterboard 13mm thick to stud wall (m2) (3,000m2 job)
Single solid core door incl frame and hardware (50 door job)
Painting to walls primer + 2 coats (m2)
Ceramic tiling (m2) (1,000m2 job)
Vinyl flooring to wet areas (m2) (500m2 job)
Carpet medium tufted (m2) (4,500m2 job)
Lighting installation (m2) (5,000m2+ job)
Copper pipe 15mm to wall (m) (1,000m+ job)
Fire sprinklers (per m2) (5,000m2 job)
Air conditioning incl main plant (m2) (5,000m2+ job)
Labour
Group 1 tradesman eg plumber/electrician
Group 2 tradesman eg carpenter/bricklayer
Group 3 tradesman eg carpet layer, tiler, plasterer
General labourer
Site foreman

Market:
Tendering:

getting warmer
lukewarm

Cost escalation:

2%

Contractors margin:

8%

Preliminaries:

(exchange rate:
0.38)

10%

International construction cost survey 2013

35

Poland
Costs stable in the short-term, but construction activity likely to increase from 2014
During 2013, the Polish construction market has slowed.
This follows several years of strong growth, in line with the
countrys GDP growth rates, which have been among the
highest in the EEC countries.
The market for apartments appears to be temporarily
oversupplied, and activity in the civil engineering sectors
of roads, water and energy is also slowing. Bankruptcies
among construction firms increased during 201213
as the market flattened out.

International building costs


per m2 of internal area, in 2013

Unemployment in Poland has been rising since late


2008, and grew from 9.9 percent in January 2012 to
10.7 percent in March 2013. Inflation is well under control,
and construction costs are expected to grow very little
over the next 12 months, with a predicted cost escalation
of just two percent.
By 2014, the sector is likely to start picking up in line
with improving European growth. EU funding of 72.9bn
between 2014 and 2020 a third of which is aimed
at infrastructure and the environment is likely to give
the Polish construction market a further boost.
PLN

USD

Purchasing
power parity

(exchange rate:
3.17)

Airports
Domestic terminal full service
Low-cost carrier basic service

8,000
4,000

2,524
1,262

6,885
3,442

Carparks
Multistorey above ground
Multistorey below ground

1,700
2,200

536
694

1,463
1,893

Commercial
Offices business park
CBD offices up to 20 floors medium (A-grade)
CBD offices high-rise prestige

3,200
4,000
4,400

1,009
1,262
1,388

2,754
3,442
3,787

Education
Primary and secondary schools
University

2,300
3,500

726
1,104

1,979
3,012

Hospitals
Day centre (including basic surgeries)
Regional hospital
General hospital (eg city teaching hospital)

2,600
3,300
3,300

820
1,041
1,041

2,238
2,840
2,840

Hotels
3 star travellers
5 star luxury
Resort style

4,000
6,500
4,500

1,262
2,050
1,420

3,442
5,594
3,873

Industrial
Warehouse/factory units basic
Large warehouse distribution centre
High-tech factory/laboratory

1,500
1,800
2,500

473
568
789

1,291
1,549
2,151

Residential
Individual detached house medium standard
Individual detached house prestige
Townhouses medium standard
Apartments private medium density
Apartments high rise
Aged care/affordable units

2,100
2,900
2,400
2,500
2,800
2,700

662
915
757
789
883
852

1,807
2,496
2,065
2,151
2,410
2,324

Retail
Large shopping centre including mall
Neighbourhood incl supermarket
Prestige car showroom

2,100
2,400
3,400

662
757
1,073

1,807
2,065
2,926

36

Turner & Townsend

Poland international building costs


per m2 of internal area

PLN

USD

Purchasing
power parity

24
90
540
3,500
90
107
8,500
460
1,075
54
2,500
15
115
90
90
210
65
65
520

8
28
170
1,104
28
34
2,681
145
339
17
789
5
36
28
28
66
21
21
164

21
77
465
3,012
77
92
7,315
396
925
46
2,151
13
99
77
77
181
56
56
448

33
31
31
22
45

10
10
10
7
14

29
27
27
19
39

Material
Concrete 30 MPa (m3) (1,500m3 job)
Reinforcement bar 16mm (tonne) (120 tonne job)
Concrete block (400x200) per 1,000 (>10,000 block job)
Standard brick per 1,000
Structural steel beams (tonne) (100 tonne + job)
Glass pane 10mm tempered (m2)
Softwood timber for framing 100mm x 50mm (m)
13 mm plasterboard (m2)
Emulsion paint (litre)
Copper pipe 15 mm (m) (1,000m+ job)
Copper cable (m) (3C + E, 2.5mm PVC) (100,000m+ job)

271
2,410
4,000
900
4,000
160
6
11
11
18
4

85
760
1,262
284
1,262
50
2
3
3
6
1

233
2,074
3,442
775
3,442
138
5
9
9
15
3

Plant
Hire 50t mobile crane + operator (day)

4,150

1,309

3,571

Composite
Excavate basement (m3) (1,800m3 job)
Excavate footings (m)
Concrete in slab (m3) (1,500m3 job)
Reinforcement in beams (tonne)
Formwork to soffit of slab (m2)
Blockwork in wall (m2) (10,000 block job)
Structural steel beams (tonne)
Pre-cast concrete wall (m2)
Curtain wall glazing incl support system (m2) (1,000m2 job)
Plasterboard 13mm thick to stud wall (m2) (3,000m2 job)
Single solid core door incl frame and hardware (50 door job)
Painting to walls primer + 2 coats (m2)
Ceramic tiling (m2) (1,000m2 job)
Vinyl flooring to wet areas (m2) (500m2 job)
Carpet medium tufted (m2) (4,500m2 job)
Lighting installation (m2) (5,000m2+ job)
Copper pipe 15mm to wall (m) (1,000m+ job)
Fire sprinklers (per m2) (5,000m2 job)
Air conditioning incl main plant (m2) (5,000m2+ job)
Labour
Group 1 tradesman eg plumber/electrician
Group 2 tradesman eg carpenter/bricklayer
Group 3 tradesman eg carpet layer, tiler, plasterer
General labourer
Site foreman

Market:
Tendering:

getting cooler
warm

Cost escalation:

2%

Contractors margin:

6%

Preliminaries:

(exchange rate:
3.17)

14%

International construction cost survey 2013

37

Qatar
Major projects on the horizon will lead price rises from late 2014
With a booming gas export industry and extensive
local development plans to meet the FIFA World Cup
commitment and the 2030 National Vision, Qatars
construction industry is poised to expand by an average
of 12 percent a year over the next ten years. By 2021,
the value of the construction industry should double
to USD15bn per annum in real terms.
The robust programme of development activities
comprises signature FIFA World Cup projects including
a new metro system, expressways, a road tunnel under
Doha Bay, 12 stadiums and over 200 hotels.

Qatars National Vision target of becoming an advanced


economy by 2030 includes ambitious construction
projects in transportation, such as a long-distance
freight and passenger railway, social infrastructure
and housing. Several new ports are also planned
to improve import capacity.
Expect cost escalation on local commodities such
as concrete, sand and aggregate in the shorter term,
with the cost of imported equipment from Japan and
Europe remaining competitive. Once major tenders have
been awarded, expect all costs to rise more significantly
from late 2014 onwards.
USD

Purchasing
power parity

14,500
11,000

3,984
3,022

7,261
5,509

Carparks
Multistorey above ground
Multistorey below ground

3,420
3,620

940
995

1,713
1,813

Commercial
Offices business park
CBD offices up to 20 floors medium (A-grade)
CBD offices high-rise prestige

4,050
6,450
7,050

1,113
1,772
1,937

2,028
3,230
3,531

Education
Primary and secondary schools
University

6,000
7,000

1,648
1,923

3,005
3,506

Hospitals
Day centre (including basic surgeries)
Regional hospital
General hospital (eg city teaching hospital)

9,500
11,500
13,110

2,610
3,159
3,602

4,757
5,759
6,565

Hotels
3 star travellers
5 star luxury
Resort style

7,830
12,450
13,200

2,151
3,420
3,626

3,921
6,235
6,610

3,460
4,010
4,480

951
1,102
1,231

1,733
2,008
2,244

4,200
11,540
6,200
5,220
5,930
5,500

1,154
3,170
1,703
1,434
1,629
1,511

2,103
5,779
3,105
2,614
2,970
2,754

7,000
8,000
9,500

1,923
2,198
2,610

3,506
4,006
4,757

International building costs


per m2 of internal area, in 2013
Airports
Domestic terminal full service
Low-cost carrier basic service

Industrial
Warehouse/factory units basic
Large warehouse distribution centre
High-tech factory/laboratory
Residential
Individual detached house medium standard
Individual detached house prestige
Townhouses medium standard
Apartments private medium density
Apartments high rise
Aged care/affordable units
Retail
Large shopping centre including mall
Neighbourhood incl supermarket
Prestige car showroom

38

Turner & Townsend

QAR

(exchange rate:
3.64)

Qatar international building costs


per m2 of internal area

QAR

USD

Purchasing
power parity

40
44
591
4,745
110
113
13,949
650
1,610
180
4,185
26
188
152
170
315
63
109
794

11
12
162
1,304
30
31
3,832
179
442
49
1,150
7
52
42
47
87
17
30
218

20
22
296
2,376
55
57
6,986
326
806
90
2,096
13
94
76
85
158
32
55
397

47
42
26
14
50

13
12
7
4
14

24
21
13
7
25

Material
Concrete 30 MPa (m3) (1,500m3 job)
Reinforcement bar 16mm (tonne) (120 tonne job)
Concrete block (400x200) per 1,000 (>10,000 block job)
Standard brick per 1,000
Structural steel beams (tonne) (100 tonne + job)
Glass pane 10mm tempered (m2)
Softwood timber for framing 100mm x 50mm (m)
13 mm plasterboard (m2)
Emulsion paint (litre)
Copper pipe 15 mm (m) (1,000m+ job)
Copper cable (m) (3C + E, 2.5mm PVC) (100,000m+ job)

288
3,335
4,025
2,875
6,325
736
18
12
75
14
3

79
916
1,106
790
1,738
202
5
3
21
4
1

144
1,670
2,016
1,440
3,167
369
9
6
38
7
2

Plant
Hire 50t mobile crane + operator (day)

6,300

1,731

3,155

Composite
Excavate basement (m3) (1,800m3 job)
Excavate footings (m)
Concrete in slab (m3) (1,500m3 job)
Reinforcement in beams (tonne)
Formwork to soffit of slab (m2)
Blockwork in wall (m2) (10,000 block job)
Structural steel beams (tonne)
Pre-cast concrete wall (m2)
Curtain wall glazing incl support system (m2) (1,000m2 job)
Plasterboard 13mm thick to stud wall (m2) (3,000m2 job)
Single solid core door incl frame and hardware (50 door job)
Painting to walls primer + 2 coats (m2)
Ceramic tiling (m2) (1,000m2 job)
Vinyl flooring to wet areas (m2) (500m2 job)
Carpet medium tufted (m2) (4,500m2 job)
Lighting installation (m2) (5,000m2+ job)
Copper pipe 15mm to wall (m) (1,000m+ job)
Fire sprinklers (per m2) (5,000m2 job)
Air conditioning incl main plant (m2) (5,000m2+ job)
Labour
Group 1 tradesman eg plumber/electrician
Group 2 tradesman eg carpenter/bricklayer
Group 3 tradesman eg carpet layer, tiler, plasterer
General labourer
Site foreman

Market:

(exchange rate:
3.64)

getting warmer

Tendering:

warm

Cost escalation:

3.6%

Contractors margin:

15%

Preliminaries:

11%

International construction cost survey 2013

39

Russia
Housing, commercial and infrastructure all on the up
The Russian construction market is experiencing strong
growth, in contrast to the weak overall economy. This is
due to an increase in residential construction, combined
with non-residential and infrastructure projects connected
to the 2014 Winter Olympics and the 2018 FIFA World Cup.
A record 66 million m2 of residential space was constructed
in 2012, a large percentage of which was affordable
housing encouraged by the governments 2030 housing
strategy. Rising house prices are expected to sustain this
high output trend.
International building costs
per m2 of internal area, in 2013

More than 50 percent of construction activities,


however, are accounted for by the infrastructure sector.
This includes construction in the oil and gas sector and
development of transport infrastructure, including roads,
railways and airport expansions, in preparation for the
2018 FIFA World Cup. Construction of eight of the
12 stadiums planned is expected to start in 2014.

USD

Purchasing
power parity

138,600
95,700

4,200
2,900

6,860
4,736

Carparks
Multistorey above ground
Multistorey below ground

27,720
34,650

840
1,050

1,372
1,715

Commercial
Offices business park
CBD offices up to 20 floors medium (A-grade)
CBD offices high-rise prestige

49,500
52,800
66,000

1,500
1,600
2,000

2,450
2,613
3,267

Education
Primary and secondary schools
University

66,000
77,550

2,000
2,350

3,267
3,838

Hospitals
Day centre (including basic surgeries)
Regional hospital
General hospital (eg city teaching hospital)

57,750
77,480
85,800

1,750
2,348
2,600

2,858
3,835
4,246

Hotels
3 star travellers
5 star luxury
Resort style

58,740
90,420
77,550

1,780
2,740
2,350

2,907
4,475
3,838

Industrial
Warehouse/factory units basic
Large warehouse distribution centre
High-tech factory/laboratory

26,730
27,720
66,000

810
840
2,000

1,323
1,372
3,267

Residential
Individual detached house medium standard
Individual detached house prestige
Townhouses medium standard
Apartments private medium density
Apartments high rise
Aged care/affordable units

34,650
61,050
37,950
46,200
57,750
44,550

1,050
1,850
1,150
1,400
1,750
1,350

1,715
3,022
1,878
2,287
2,858
2,205

Retail
Large shopping centre including mall
Neighbourhood incl supermarket
Prestige car showroom

51,150
37,950
77,550

1,550
1,150
2,350

2,532
1,878
3,838

Airports
Domestic terminal full service
Low-cost carrier basic service

40

Turner & Townsend

RUB

(exchange rate:
33.00)

Russia international building costs


per m2 of internal area

RUB

USD

Purchasing
power parity

510
660
7,194
56,100
1,006
1,495
92,400
6,996
28,050
2,475
28,050
330
1,980
1,645
1,650
1,980
528
957
4,950

15
20
218
1,700
30
45
2,800
212
850
75
850
10
60
50
50
60
16
29
150

25
33
356
2,777
50
74
4,573
346
1,388
122
1,388
16
98
81
82
98
26
47
245

564
564
564
511
830

17
17
17
15
25

28
28
28
25
41

Material
Concrete 30 MPa (m3) (1,500m3 job)
Reinforcement bar 16mm (tonne) (120 tonne job)
Concrete block (400x200) per 1,000 (>10,000 block job)
Standard brick per 1,000
Structural steel beams (tonne) (100 tonne + job)
Glass pane 10mm tempered (m2)
Softwood timber for framing 100mm x 50mm (m)
13 mm plasterboard (m2)
Emulsion paint (litre)
Copper pipe 15 mm (m) (1,000m+ job)
Copper cable (m) (3C + E, 2.5mm PVC) (100,000m+ job)

4,785
26,400
59,400
15,840
41,250
5,940
165
158
50
361
70

145
800
1,800
480
1,250
180
5
5
2
11
2

237
1,307
2,940
784
2,042
294
8
8
2
18
3

Plant
Hire 50t mobile crane + operator (day)

49,500

1,500

2,450

Composite
Excavate basement (m3) (1,800m3 job)
Excavate footings (m)
Concrete in slab (m3) (1,500m3 job)
Reinforcement in beams (tonne)
Formwork to soffit of slab (m2)
Blockwork in wall (m2) (10,000 block job)
Structural steel beams (tonne)
Pre-cast concrete wall (m2)
Curtain wall glazing incl support system (m2) (1,000m2 job)
Plasterboard 13mm thick to stud wall (m2) (3,000m2 job)
Single solid core door incl frame and hardware (50 door job)
Painting to walls primer + 2 coats (m2)
Ceramic tiling (m2) (1,000m2 job)
Vinyl flooring to wet areas (m2) (500m2 job)
Carpet medium tufted (m2) (4,500m2 job)
Lighting installation (m2) (5,000m2+ job)
Copper pipe 15mm to wall (m) (1,000m+ job)
Fire sprinklers (per m2) (5,000m2 job)
Air conditioning incl main plant (m2) (5,000m2+ job)
Labour
Group 1 tradesman eg plumber/electrician
Group 2 tradesman eg carpenter/bricklayer
Group 3 tradesman eg carpet layer, tiler, plasterer
General labourer
Site foreman

Market:
Tendering:
Cost escalation:
Contractors margin:
Preliminaries:

getting warmer

(exchange rate:
33.00)

Moscow

100

warm

St Petersburg

92

5%

Yekaterinburg

87

10%
8%

International construction cost survey 2013

41

Singapore
Growth continues, contractors face skills shortages
Singapores construction sector continued to grow
in the first half of 2013, although the rate of GDP growth
slowed as the year progressed to 5.1 percent by the end
of the second quarter, compared to 7.3 percent at the end
of the first quarter.
The value of contracts awarded in both the public and
private sectors slowed down, resulting in a 27 percent
year-on-year decline at the end of the second quarter.
Total construction output in 2013 is projected to be
between SGD1bn and SGD33bn in 2013, moderating
between SGD26bn and SGD33bn in 2014 and 2015.

International building costs


per m2 of internal area, in 2013

Public sector demand is expected to strengthen


significantly, however, contributing between SGD14bn
and SGD17bn or around half of industry demand
in 2013. This is due to the rescheduling of some major
public housing and civil engineering projects, now to be
tendered in 2013, and the ramping up of public housing
and rail construction. The public mass rapid transit
infrastructure expansion programme remains strong,
with preparations taking place for the next major roll-out
of rail and road construction contracts in 2013 and 2014.
Contractors have been complaining about professional and
labour skills shortage, in part due to tighter restrictions on
overseas workers, which have been leading to higher wage
bills. Low-margin bids and the widespread use of lump sum
contracts make it difficult to recover costs.
SGD

USD

Purchasing
power parity

(exchange rate:
1.27)

Airports
Domestic terminal full service
Low-cost carrier basic service

5,200
4,000

4,094
3,150

5,712
4,394

Carparks
Multistorey above ground
Multistorey below ground

1,230
1,740

969
1,370

1,351
1,911

Commercial
Offices business park
CBD offices up to 20 floors medium (A-grade)
CBD offices high-rise prestige

2,050
2,560
2,970

1,614
2,016
2,339

2,252
2,812
3,262

Education
Primary and secondary schools
University

1,500
2,770

1,181
2,181

1,648
3,043

Hospitals
Day centre (including basic surgeries)
Regional hospital
General hospital (eg city teaching hospital)

1,850
3,000
3,900

1,457
2,362
3,071

2,032
3,295
4,284

Hotels
3 star travellers
5 star luxury
Resort style

3,280
4,310
5,150

2,583
3,394
4,055

3,603
4,734
5,657

Industrial
Warehouse/factory units basic
Large warehouse distribution centre
High-tech factory/laboratory

2,200
2,500
3,080

1,732
1,969
2,425

2,416
2,746
3,383

Residential
Individual detached house medium standard
Individual detached house prestige
Townhouses medium standard
Apartments private medium density
Apartments high rise
Aged care/affordable units

4,100
4,720
2,870
2,150
2,770
1,540

3,228
3,717
2,260
1,693
2,181
1,213

4,503
5,184
3,152
2,362
3,043
1,692

Retail
Large shopping centre including mall
Neighbourhood incl supermarket
Prestige car showroom

3,280
2,150
3,380

2,583
1,693
2,661

3,603
2,362
3,713

42

Turner & Townsend

Singapore international building costs


per m2 of internal area

SGD

USD

Purchasing
power parity

75
25
158
1,550
37
65
4,100
135
1,365
25
845
10
87
80
63
205
28
82
267

59
20
124
1,220
29
51
3,228
106
1,075
20
665
7
68
63
50
161
22
65
210

82
27
174
1,703
41
71
4,503
148
1,499
27
928
10
95
88
69
225
30
90
293

26
18
25
15
25

20
14
20
12
20

28
20
27
17
27

Material
Concrete 30 MPa (m3) (1,500m3 job)
Reinforcement bar 16mm (tonne) (120 tonne job)
Concrete block (400x200) per 1,000 (>10,000 block job)
Standard brick per 1,000
Structural steel beams (tonne) (100 tonne + job)
Glass pane 10mm tempered (m2)
Softwood timber for framing 100mm x 50mm (m)
13 mm plasterboard (m2)
Emulsion paint (litre)
Copper pipe 15 mm (m) (1,000m+ job)
Copper cable (m) (3C + E, 2.5mm PVC) (100,000m+ job)

108
1,200
700
350
2,200
120
12
8
18
13
2

85
945
551
276
1,732
94
9
6
14
10
2

119
1,318
769
384
2,416
132
13
9
20
15
2

Plant
Hire 50t mobile crane + operator (day)

2,000

1,575

2,197

Composite
Excavate basement (m3) (1,800m3 job)
Excavate footings (m)
Concrete in slab (m3) (1,500m3 job)
Reinforcement in beams (tonne)
Formwork to soffit of slab (m2)
Blockwork in wall (m2) (10,000 block job)
Structural steel beams (tonne)
Pre-cast concrete wall (m2)
Curtain wall glazing incl support system (m2) (1,000m2 job)
Plasterboard 13mm thick to stud wall (m2) (3,000m2 job)
Single solid core door incl frame and hardware (50 door job)
Painting to walls primer + 2 coats (m2)
Ceramic tiling (m2) (1,000m2 job)
Vinyl flooring to wet areas (m2) (500m2 job)
Carpet medium tufted (m2) (4,500m2 job)
Lighting installation (m2) (5,000m2+ job)
Copper pipe 15mm to wall (m) (1,000m+ job)
Fire sprinklers (per m2) (5,000m2 job)
Air conditioning incl main plant (m2) (5,000m2+ job)
Labour
Group 1 tradesman eg plumber/electrician
Group 2 tradesman eg carpenter/bricklayer
Group 3 tradesman eg carpet layer, tiler, plasterer
General labourer
Site foreman

Market:
Tendering:

getting warmer
lukewarm

Cost escalation:

3%

Contractors margin:

8%

Preliminaries:

(exchange rate:
1.27)

10%

International construction cost survey 2013

43

South Africa
Residential and commercial sectors sluggish, but retail on the rise
South Africas economy weakened in 201213 due
to two factors: lower global demand for resources and
labour strikes, with workers demanding wage increases
above the high rate of inflation. The falling exchange rate
is adding to the cost of imports, though this makes exports
more competitive.

Confidence in the industry is expected to increase


under forecasts of lower interest rates and slightly
firmer exchange rates in the immediate future. However,
recovery is likely to be modest, due to poor economic
growth, slower growth in consumer spending and
labour unrest.

Residential construction remained sluggish, trapped in a


cyclical low. After a few years of operating below capacity,
the commercial sector, on the other hand, is now healthy
and recovering. However, there has been demand in the
retail sector which looks set to continue. The public sector
has added to the overall level of construction work,
with projects in several sectors, such as transportation
and power generation.

Construction cost increases of more than ten percent


are being driven by large annual trade wage increases,
increased demand for local materials from the retail
sector and higher imported material costs.

International building costs


per m2 of internal area, in 2013

USD

Purchasing
power parity

24,450
17,120

2,495
1,747

4,336
3,036

4,450
5,270

454
538

789
935

Commercial
Offices business park
CBD offices up to 20 floors medium (A-grade)
CBD offices high-rise prestige

7,610
9,950
13,460

777
1,015
1,373

1,349
1,764
2,387

Education
Primary and secondary schools
University

8,190
10,530

836
1,074

1,452
1,867

Hospitals
Day centre (including basic surgeries)
Regional hospital
General hospital (eg city teaching hospital)

7,020
8,780
10,530

716
896
1,074

1,245
1,557
1,867

Hotels
3 star travellers
5 star luxury
Resort style

10,060
12,290
11,700

1,027
1,254
1,194

1,784
2,179
2,075

4,000
4,500
7,020

408
459
716

709
798
1,245

6,200
11,120
6,790
7,250
8,780
6,440

633
1,135
693
740
896
657

1,099
1,972
1,204
1,286
1,557
1,142

9,360
8,190
8,780

955
836
896

1,660
1,452
1,557

Airports
Domestic terminal full service
Low-cost carrier basic service
Carparks
Multistorey above ground
Multistorey below ground

Industrial
Warehouse/factory units basic
Large warehouse distribution centre
High-tech factory/laboratory
Residential
Individual detached house medium standard
Individual detached house prestige
Townhouses medium standard
Apartments private medium density
Apartments high rise
Aged care/affordable units
Retail
Large shopping centre including mall
Neighbourhood incl supermarket
Prestige car showroom

44

Turner & Townsend

ZAR

(exchange rate:
9.80)

South Africa international building costs


per m2 of internal area

ZAR

Composite
Excavate basement (m3) (1,800m3 job)
Excavate footings (m)
Concrete in slab (m3) (1,500m3 job)
Reinforcement in beams (tonne)
Formwork to soffit of slab (m2)
Blockwork in wall (m2) (10,000 block job)
Structural steel beams (tonne)
Pre-cast concrete wall (m2)
Curtain wall glazing incl support system (m2) (1,000m2 job)
Plasterboard 13mm thick to stud wall (m2) (3,000m2 job)
Single solid core door incl frame and hardware (50 door job)
Painting to walls primer + 2 coats (m2)
Ceramic tiling (m2) (1,000m2 job)
Vinyl flooring to wet areas (m2) (500m2 job)
Carpet medium tufted (m2) (4,500m2 job)
Lighting installation (m2) (5,000m2+ job)
Copper pipe 15mm to wall (m) (1,000m+ job)
Fire sprinklers (per m2) (5,000m2 job)
Air conditioning incl main plant (m2) (5,000m2+ job)
Labour
Group 1 tradesman eg plumber/electrician
Group 2 tradesman eg carpenter/bricklayer
Group 3 tradesman eg carpet layer, tiler, plasterer
General labourer
Site foreman
Material
Concrete 30 MPa (m3) (1,500m3 job)
Reinforcement bar 16mm (tonne) (120 tonne job)
Concrete block (400x200) per 1,000 (>10,000 block job)
Standard brick per 1,000
Structural steel beams (tonne) (100 tonne + job)
Glass pane 10mm tempered (m2)
Softwood timber for framing 100mm x 50mm (m)
13 mm plasterboard (m2)
Emulsion paint (litre)
Copper pipe 15 mm (m) (1,000m+ job)
Copper cable (m) (3C + E, 2.5mm PVC) (100,000m+ job)
Plant
Hire 50t mobile crane + operator (day)

Market:
Tendering:
Cost escalation:

getting cooler
lukewarm
9%

Contractors margin:

12%

Preliminaries:

11%

USD

Purchasing
power parity

39
140
1,467
12,500
221
227
24,000
486
2,500
270
1,840
30
250
182
246
90
56
276
1,412

4
14
150
1,276
23
23
2,449
50
255
28
188
3
26
19
25
9
6
28
144

7
25
260
2,217
39
40
4,256
86
443
48
326
5
44
32
44
16
10
49
250

60
48
45
28
100

6
5
5
3
10

11
9
8
5
18

1,334
9,963
3,500
1,720
21,160
1,696
60
50
39
36
15

136
1,017
357
176
2,159
173
6
5
4
4
2

237
1,767
621
305
3,752
301
11
9
7
6
3

9,000

918

1,596

(exchange rate:
9.80)

Gauteng

100

KwaZulu-Natal

101

Western Cape

103

International construction cost survey 2013

45

South Korea
Housing slowdown hits construction
South Korea is now facing its worst property market
slowdown since 2004. Residential building permits
fell 24.4 percent in the first half of 2013 from a year
earlier, while housing starts dropped 19.2 percent
in the same period.
With tightening credit conditions, falling property
values and the expiry of temporary tax breaks
on property acquisition, domestic construction
is weakening. Infrastructure construction, on the
other hand, is experiencing moderate growth.

Koreas exceptional manufacturing growth is now


threatened by its strong currency which, against the
weakened yen, is gradually eroding Koreas competitive
advantage. Static inflation and the slowdown in the
property sector should keep construction costs down
during 201314.

(exchange rate: 1,114.00)

USD

Purchasing
power
parity

2,626,500
1,838,550

2,358
1,650

6,481
4,537

566,500
824,000

509
740

1,398
2,033

Commercial
Offices business park
CBD offices up to 20 floors medium (A-grade)
CBD offices high-rise prestige

1,133,000
1,390,500
1,751,000

1,017
1,248
1,572

2,796
3,431
4,321

Education
Primary and secondary schools
University

1,030,000
1,400,800

925
1,257

2,542
3,457

Hospitals
Day centre (including basic surgeries)
Regional hospital
General hospital (eg city teaching hospital)

1,133,000
1,648,000
1,751,000

1,017
1,479
1,572

2,796
4,067
4,321

Hotels
3 star travellers
5 star luxury
Resort style

1,545,000
3,296,000
2,111,500

1,387
2,959
1,895

3,812
8,133
5,210

Industrial
Warehouse/factory units basic
Large warehouse distribution centre
High-tech factory/laboratory

927,000
721,000
2,678,000

832
647
2,404

2,287
1,779
6,608

Residential
Individual detached house medium standard
Individual detached house prestige
Townhouses medium standard
Apartments private medium density
Apartments high rise
Aged care/affordable units

1,184,500
1,751,000
1,400,800
1,133,000
1,442,000
1,236,000

1,063
1,572
1,257
1,017
1,294
1,110

2,923
4,321
3,457
2,796
3,558
3,050

Retail
Large shopping centre including mall
Neighbourhood incl supermarket
Prestige car showroom

1,750,000
978,500
1,926,100

1,571
878
1,729

4,318
2,415
4,753

International building costs


per m2 of internal area, in 2013
Airports
Domestic terminal full service
Low-cost carrier basic service
Carparks
Multistorey above ground
Multistorey below ground

46

Turner & Townsend

KRW

South Korea international building costs


per m2 of internal area

KRW

Composite
Excavate basement (m3) (1,800m3 job)
Excavate footings (m)
Concrete in slab (m3) (1,500m3 job)
Reinforcement in beams (tonne)
Formwork to soffit of slab (m2)
Blockwork in wall (m2) (10,000 block job)
Structural steel beams (tonne)
Pre-cast concrete wall (m2)
Curtain wall glazing incl support system (m2) (1,000m2 job)
Plasterboard 13mm thick to stud wall (m2) (3,000m2 job)
Single solid core door incl frame and hardware (50 door job)
Painting to walls primer + 2 coats (m2)
Ceramic tiling (m2) (1,000m2 job)
Vinyl flooring to wet areas (m2) (500m2 job)
Carpet medium tufted (m2) (4,500m2 job)
Lighting installation (m2) (5,000m2+ job)
Copper pipe 15mm to wall (m) (1,000m+ job)
Fire sprinklers (per m2) (5,000m2 job)
Air conditioning incl main plant (m2) (5,000m2+ job)
Labour
Group 1 tradesman eg plumber/electrician
Group 2 tradesman eg carpenter/bricklayer
Group 3 tradesman eg carpet layer, tiler, plasterer
General labourer
Site foreman
Material
Concrete 30 MPa (m3) (1,500m3 job)
Reinforcement bar 16mm (tonne) (120 tonne job)
Concrete block (400x200) per 1,000 (>10,000 block job)
Standard brick per 1,000
Structural steel beams (tonne) (100 tonne + job)
Glass pane 10mm tempered (m2)
Softwood timber for framing 100mm x 50mm (m)
13 mm plasterboard (m2)
Emulsion paint (litre)
Copper pipe 15 mm (m) (1,000m+ job)
Copper cable (m) (3C + E, 2.5mm PVC) (100,000m+ job)
Plant
Hire 50t mobile crane + operator (day)

Market:
Tendering:

USD

Purchasing
power
parity

6,489
6,489
130,000
1,251,450
27,000
36,633
2,008,500
257,500
309,000
46,350
257,500
4,635
46,350
36,050
51,500
43,260
11,330
23,175
208,060

6
6
117
1,123
24
33
1,803
231
277
42
231
4
42
32
46
39
10
21
187

16
16
321
3,088
67
90
4,956
635
762
114
635
11
114
89
127
107
28
57
513

18,000
17,436
17,436
12,216
15,924

16
16
16
11
14

44
43
43
30
39

81,502
1,032,060
988,800
679,800
1,176,000
133,680
1,112
3,205
3,063
6,526
370

73
926
888
610
1,056
120
1
3
3
6
0

201
2,547
2,440
1,677
2,902
330
3
8
8
16
1

940,000

844

2,320

getting cooler
cold

Cost escalation:

3%

Contractors margin:

3%

Preliminaries:

(exchange rate: 1,114.00)

12%

International construction cost survey 2013

47

UAE
Rapid recovery will stretch construction sector
Though the UAE economy was affected by the global
recession, it has rapidly regained much of its past
momentum. The economy grew by 4.4 percent
in 2012, partly due to recovery in construction activity.
Prospects are strongest in Abu Dhabi, where demand
tends to exceed supply in the commercial and retail
sectors and the government continues to invest in
key infrastructure projects to support the 2030 vision
of a diversified economy. Dubai is a little further behind
in the upswing, although property values are now
increasing, bank lending is growing and tourism
is thriving again.
International building costs
per m2 of internal area, in 2013

Construction cost escalation is still moderate but set


to increase as USD350bn of announced projects get
underway, stretching the capacity of the construction
sector. While some mega developments are in this mix,
there has been a general shift in the region away from
residential and commercial projects to large social
and transport infrastructure projects.

USD

Purchasing
power parity

14,350
10,050

3,910
2,738

8,260
5,785

Carparks
Multistorey above ground
Multistorey below ground

3,590
4,360

978
1,188

2,066
2,510

Commercial
Offices business park
CBD offices up to 20 floors medium (A-grade)
CBD offices high-rise prestige

4,100
5,130
6,920

1,117
1,398
1,886

2,360
2,953
3,983

Education
Primary and secondary schools
University

5,890
6,660

1,605
1,815

3,390
3,833

Hospitals
Day centre (including basic surgeries)
Regional hospital
General hospital (eg city teaching hospital)

5,890
7,430
8,970

1,605
2,025
2,444

3,390
4,277
5,163

9,230
12,300
14,860

2,515
3,351
4,049

5,313
7,080
8,553

Industrial
Warehouse/factory units basic
Large warehouse distribution centre
High-tech factory/laboratory

4,360
4,100
6,150

1,188
1,117
1,676

2,510
2,360
3,540

Residential
Individual detached house medium standard
Individual detached house prestige
Townhouses medium standard
Apartments private medium density
Apartments high rise
Aged care/affordable units

6,150
9,990
5,380
5,640
6,660
4,870

1,676
2,722
1,466
1,537
1,815
1,327

3,540
5,750
3,097
3,246
3,833
2,803

Retail
Large shopping centre including mall
Neighbourhood incl supermarket
Prestige car showroom

6,660
7,180
9,740

1,815
1,956
2,654

3,833
4,133
5,606

Airports
Domestic terminal full service
Low-cost carrier basic service

Hotels
3 star travellers
5 star luxury
Resort style

48

Turner & Townsend

AED

(exchange rate:
3.67)

UAE international building costs


per m2 of internal area

AED

USD

Purchasing
power parity

31
31
472
4,100
115
150
10,250
666
1,435
123
3,741
15
120
110
308
154
56
130
900

8
8
128
1,117
31
41
2,793
182
391
34
1,019
4
33
30
84
42
15
35
245

18
18
271
2,360
66
86
5,900
383
826
71
2,153
9
69
63
177
88
32
75
518

31
31
29
15
77

8
8
8
4
21

18
18
17
9
44

Material
Concrete 30 MPa (m3) (1,500m3 job)
Reinforcement bar 16mm (tonne) (120 tonne job)
Concrete block (400x200) per 1,000 (>10,000 block job)
Standard brick per 1,000
Structural steel beams (tonne) (100 tonne + job)
Glass pane 10mm tempered (m2)
Softwood timber for framing 100mm x 50mm (m)
13 mm plasterboard (m2)
Emulsion paint (litre)
Copper pipe 15 mm (m) (1,000m+ job)
Copper cable (m) (3C + E, 2.5mm PVC) (100,000m+ job)

256
2,973
3,588
2,563
5,638
656
13
10
60
12
3

70
810
978
698
1,536
179
4
3
16
3
1

147
1,711
2,065
1,475
3,245
378
7
6
35
7
2

Plant
Hire 50t mobile crane + operator (day)

6,606

1,800

3,802

Composite
Excavate basement (m3) (1,800m3 job)
Excavate footings (m)
Concrete in slab (m3) (1,500m3 job)
Reinforcement in beams (tonne)
Formwork to soffit of slab (m2)
Blockwork in wall (m2) (10,000 block job)
Structural steel beams (tonne)
Pre-cast concrete wall (m2)
Curtain wall glazing incl support system (m2) (1,000m2 job)
Plasterboard 13mm thick to stud wall (m2) (3,000m2 job)
Single solid core door incl frame and hardware (50 door job)
Painting to walls primer + 2 coats (m2)
Ceramic tiling (m2) (1,000m2 job)
Vinyl flooring to wet areas (m2) (500m2 job)
Carpet medium tufted (m2) (4,500m2 job)
Lighting installation (m2) (5,000m2+ job)
Copper pipe 15mm to wall (m) (1,000m+ job)
Fire sprinklers (per m2) (5,000m2 job)
Air conditioning incl main plant (m2) (5,000m2+ job)
Labour
Group 1 tradesman eg plumber/electrician
Group 2 tradesman eg carpenter/bricklayer
Group 3 tradesman eg carpet layer, tiler, plasterer
General labourer
Site foreman

Market:
Tendering:

getting warmer
lukewarm

Cost escalation:

2%

Contractors margin:

8%

Preliminaries:

(exchange rate:
3.67)

12%

International construction cost survey 2013

49

Uganda
Government investment signals sustainable construction growth
After a period of sluggish growth, Ugandas construction
market is showing signs of more rapid growth following
the recent announcement of several large projects.
Government investment in infrastructure and public
facilities including roads, energy, schools and hospitals
has been increasing steadily.
With the help of foreign investment, particularly from
China, several high-profile projects have recently been
announced by the government. These include the
USD1.4bn Karuma hydropower dam across the River Nile
and a new railway line between Kenya and Rwanda,
running through Uganda.
International building costs
per m2 of internal area, in 2013

Private sector investment is still subdued, hampered


by high borrowing costs introduced to control spiralling
inflation levels, which reached a high of 30.5 percent
in October 2011.
Ugandas economy is expected to be further boosted when
oil production begins, scheduled for 2018. This will require
construction of wells, pipelines, roads and a refinery.

UGX

USD

Purchasing
power parity

(exchange rate:
2,595.00)

Airports
Domestic terminal full service
Low-cost carrier basic service

5,070,000
3,802,500

1,954
1,465

2,996
2,247

Carparks
Multistorey above ground
Multistorey below ground

1,014,000
887,250

420
450

599
524

Commercial
Offices business park
CBD offices up to 20 floors medium (A-grade)
CBD offices high-rise prestige

2,154,750
2,281,500
3,491,680

830
879
1,346

1,273
1,348
2,064

Education
Primary and secondary schools
University

1,521,000
1,774,500

580
650

899
1,049

Hospitals
Day centre (including basic surgeries)
Regional hospital
General hospital (eg city teaching hospital)

2,166,830
2,408,250
3,295,500

835
928
1,270

1,281
1,423
1,948

Hotels
3 star travellers
5 star luxury
Resort style

3,171,430
3,794,560
3,687,130

1,222
1,462
1,421

1,874
2,243
2,179

Industrial
Warehouse/factory units basic
Large warehouse distribution centre
High-tech factory/laboratory

1,267,500
1,267,500
3,168,750

350
380
950

749
749
1,873

Residential
Individual detached house medium standard
Individual detached house prestige
Townhouses medium standard
Apartments private medium density
Apartments high rise
Aged care/affordable units

1,954,040
3,295,500
2,122,040
2,028,000
2,509,370
1,521,000

370
620
550
641
770
350

1,155
1,948
1,254
1,199
1,483
899

Retail
Large shopping centre including mall
Neighbourhood incl supermarket
Prestige car showroom

2,205,620
1,930,680
2,068,220

1,200
800
797

1,303
1,141
1,222

50

Turner & Townsend

Uganda international building costs


per m2 of internal area

UGX

USD

Purchasing
power parity

10,140
7,605
760,500
4,687,200
38,025
76,050
8,500,000
304,200
507,000
63,375
1,140,750
12,675
63,375
50,700
101,400
228,150
76,050
50,700
253,500

4
3
293
1,806
15
29
3,276
117
195
24
440
5
24
20
39
88
29
20
98

6
4
449
2,770
22
45
5,023
180
300
37
674
7
37
30
60
135
45
30
150

10,140
10,140
10,140
3,803
30,420

3
2
2
1
3

6
6
6
2
18

Material
Concrete 30 MPa (m3) (1,500m3 job)
Reinforcement bar 16mm (tonne) (120 tonne job)
Concrete block (400x200) per 1,000 (>10,000 block job)
Standard brick per 1,000
Structural steel beams (tonne) (100 tonne + job)
Glass pane 10mm tempered (m2)
Softwood timber for framing 100mm x 50mm (m)
13 mm plasterboard (m2)
Emulsion paint (litre)
Copper pipe 15 mm (m) (1,000m+ job)
Copper cable (m) (3C + E, 2.5mm PVC) (100,000m+ job)

633,750
4,056,000
3,549,000
354,900
7,605,000
263,640
7,605
31,000
3,803
65,910
50,700

244
1,563
1,368
137
2,931
102
3
12
1
25
20

375
2,397
2,097
210
4,494
156
4
18
2
39
30

Plant
Hire 50t mobile crane + operator (day)

3,373,500

1,300

1,994

Composite
Excavate basement (m3) (1,800m3 job)
Excavate footings (m)
Concrete in slab (m3) (1,500m3 job)
Reinforcement in beams (tonne)
Formwork to soffit of slab (m2)
Blockwork in wall (m2) (10,000 block job)
Structural steel beams (tonne)
Pre-cast concrete wall (m2)
Curtain wall glazing incl support system (m2) (1,000m2 job)
Plasterboard 13mm thick to stud wall (m2) (3,000m2 job)
Single solid core door incl frame and hardware (50 door job)
Painting to walls primer + 2 coats (m2)
Ceramic tiling (m2) (1,000m2 job)
Vinyl flooring to wet areas (m2) (500m2 job)
Carpet medium tufted (m2) (4,500m2 job)
Lighting installation (m2) (5,000m2+ job)
Copper pipe 15mm to wall (m) (1,000m+ job)
Fire sprinklers (per m2) (5,000m2 job)
Air conditioning incl main plant (m2) (5,000m2+ job)
Labour
Group 1 tradesman eg plumber/electrician
Group 2 tradesman eg carpenter/bricklayer
Group 3 tradesman eg carpet layer, tiler, plasterer
General labourer
Site foreman

Market:
Tendering:
Cost escalation:
Contractors margin:
Preliminaries:

(exchange rate:
2,595.00)

getting warmer
lukewarm
5%
15%
8%

International construction cost survey 2013

51

UK
Growth again, but concentrated in London and the South East
After several tough years, the UK economy is picking up
in certain sectors and locations. GDP growth had increased
to 1.5 percent year-on-year by the third quarter of 2013,
unemployment was stable at 7.7 percent, and business
confidence is now well into positive territory. Despite this,
construction is still 13.3 percent down from its 2008 peak.
The government has introduced various schemes to boost
housing, including shared equity where first-time buyers
can receive a government loan. This is helping the housing
market to grow again, prompting premature warnings of
a housing bubble.
Fuelled by low interest rates and undersupply,
the rejuvenated real estate sector will help boost
construction activity and lead growth in the rest of the
economy. However, it is still early days, with growth

primarily in high-end property in the South East,


but set to ripple out from there.
The government also announced an infrastructure
spending boost of 100bn after its June spending review.
However, many of these projects, which will include road,
rail and energy, will take some time to start feeding
through in capital expenditure terms.
Construction wages have not risen for several years and
some spare capacity still exists, so construction cost
increases will be minimal until mid-2014. The exception
to this will be the South East.

USD

Purchasing
power parity

3,190
2,240

4,908
3,446

5,918
4,156

550
890

846
1,369

1,020
1,651

Commercial
Offices business park
CBD offices up to 20 floors medium (A-grade)
CBD offices high-rise prestige

1,450
2,100
2,800

2,231
3,231
4,308

2,690
3,896
5,194

Education
Primary and secondary schools
University

1,410
2,280

2,169
3,508

2,616
4,230

Hospitals
Day centre (including basic surgeries)
Regional hospital
General hospital (eg city teaching hospital)

1,720
2,350
2,850

2,646
3,615
4,385

3,191
4,360
5,287

Hotels
3 star travellers
5 star luxury
Resort style

1,360
2,620
2,300

2,092
4,031
3,538

2,523
4,860
4,267

Industrial
Warehouse/factory units basic
Large warehouse distribution centre
High-tech factory/laboratory

840
940
1,570

1,292
1,446
2,415

1,558
1,744
2,913

Residential
Individual detached house medium standard
Individual detached house prestige
Townhouses medium standard
Apartments private medium density
Apartments high rise
Aged care/affordable units

1,070
1,530
1,260
1,890
2,410
1,910

1,646
2,354
1,938
2,908
3,708
2,938

1,985
2,838
2,337
3,506
4,471
3,543

Retail
Large shopping centre including mall
Neighbourhood incl supermarket
Prestige car showroom

2,550
2,050
2,400

3,923
3,154
3,692

4,731
3,803
4,452

International building costs


per m2 of internal area, in 2013
Airports
Domestic terminal full service
Low-cost carrier basic service
Carparks
Multistorey above ground
Multistorey below ground

52

Turner & Townsend

GBP

(exchange rate:
0.65)

United Kingdom international building costs


per m2 of internal area

GBP

USD

Purchasing
power parity

11
18
145
925
34
37
1,943
75
513
38
685
6
42
24
25
48
20
35
100

17
28
223
1,424
53
57
2,990
115
790
58
1,053
9
65
37
38
74
31
54
154

20
33
269
1,717
64
69
3,605
139
952
70
1,270
11
78
44
46
89
37
65
186

31
26
26
17
33

48
40
40
25
50

57
48
48
31
60

Material
Concrete 30 MPa (m3) (1,500m3 job)
Reinforcement bar 16mm (tonne) (120 tonne job)
Concrete block (400x200) per 1,000 (>10,000 block job)
Standard brick per 1,000
Structural steel beams (tonne) (100 tonne + job)
Glass pane 10mm tempered (m2)
Softwood timber for framing 100mm x 50mm (m)
13 mm plasterboard (m2)
Emulsion paint (litre)
Copper pipe 15 mm (m) (1,000m+ job)
Copper cable (m) (3C + E, 2.5mm PVC) (100,000m+ job)

85
749
2,100
414
1,564
148
2
5
4
6
2

131
1,152
3,231
637
2,406
228
3
7
6
9
3

158
1,389
3,896
768
2,902
275
3
9
7
11
4

Plant
Hire 50t mobile crane + operator (day)

1,000

1,538

1,855

Composite
Excavate basement (m3) (1,800m3 job)
Excavate footings (m)
Concrete in slab (m3) (1,500m3 job)
Reinforcement in beams (tonne)
Formwork to soffit of slab (m2)
Blockwork in wall (m2) (10,000 block job)
Structural steel beams (tonne)
Pre-cast concrete wall (m2)
Curtain wall glazing incl support system (m2) (1,000m2 job)
Plasterboard 13mm thick to stud wall (m2) (3,000m2 job)
Single solid core door incl frame and hardware (50 door job)
Painting to walls primer + 2 coats (m2)
Ceramic tiling (m2) (1,000m2 job)
Vinyl flooring to wet areas (m2) (500m2 job)
Carpet medium tufted (m2) (4,500m2 job)
Lighting installation (m2) (5,000m2+ job)
Copper pipe 15mm to wall (m) (1,000m+ job)
Fire sprinklers (per m2) (5,000m2 job)
Air conditioning incl main plant (m2) (5,000m2+ job)
Labour
Group 1 tradesman eg plumber/electrician
Group 2 tradesman eg carpenter/bricklayer
Group 3 tradesman eg carpet layer, tiler, plasterer
General labourer
Site foreman

Market:
Tendering:

getting warmer
lukewarm

(exchange rate:
0.65)

East Anglia Region


East Midlands Region

96
87

Cost escalation:

3%

Greater London

Contractors margin:

4%

Northern Ireland

80

12%

Northern Region

83

North West Region

83

Scotland

87

South East Region (excluding Greater London)

99

South West Region

93

Wales

86

West Midlands Region

89

Yorkshire and Humberside Region

89

Preliminaries:

Source BCIS, Turner & Townsend

100

International construction cost survey 2013

53

US
Signs of recovery, but its still early days
The US economy has improved considerably during 2013,
with the all-important housing sector starting to stage
a comeback. This follows a 3040 percent decrease in
house prices since 2006, as the market corrected itself.
The manufacturing sector is also growing again. This is
thanks to labour costs, which are now low by international
standards, and to cheaper energy prices due to the
availability of home-grown shale gas.
Equity valuations are high and confidence is improving now
that a relaxation of the Feds policy of quantitative easing is
expected over the next 12 months. This all bodes well for a
International building costs
per m2 of internal area, in 2013
Airports
Domestic terminal full service
Low-cost carrier basic service

gradual recovery in construction, with housing, industrial


and gas projects leading the way. However, it is still early
in the recovery cycle.
There is a large disparity in costs across the US, with the
Northeast far more expensive than the South and
Southwest. Closed shop conditions and strong labour
unions keep wages high in the Northeast, compared
to other regions where open shop labour laws apply.
Until construction volumes increase substantially,
cost increases are likely to remain moderate.

USD

Purchasing
power parity

3,620
2,530

3,516
2,457

Carparks
Multistorey above ground
Multistorey below ground

710
1,340

690
1,302

Commercial
Offices business park
CBD offices up to 20 floors medium (A-grade)
CBD offices high-rise prestige

1,920
2,180
2,570

1,865
2,117
2,496

Education
Primary and secondary schools
University

1,600
2,240

1,554
2,176

Hospitals
Day centre (including basic surgeries)
Regional hospital
General hospital (eg city teaching hospital)

2,100
3,410
3,370

2,040
3,312
3,273

Hotels
3 star travellers
5 star luxury
Resort style

1,610
2,650
2,350

1,564
2,574
2,283

Industrial
Warehouse/factory units basic
Large warehouse distribution centre
High-tech factory/laboratory

880
1,160
1,820

855
1,127
1,768

Residential
Individual detached house medium standard
Individual detached house prestige
Townhouses medium standard
Apartments private medium density
Apartments high rise
Aged care/affordable units

1,520
1,840
1,380
1,630
2,140
1,580

1,476
1,787
1,340
1,583
2,079
1,535

Retail
Large shopping centre including mall
Neighbourhood incl supermarket
Prestige car showroom

2,000
1,400
2,600

1,943
1,360
2,525

54

Turner & Townsend

US international building costs


per m2 of internal area
Composite
Excavate basement (m3) (1,800m3 job)
Excavate footings (m)
Concrete in slab (m3) (1,500m3 job)
Reinforcement in beams (tonne)
Formwork to soffit of slab (m2)
Blockwork in wall (m2) (10,000 block job)
Structural steel beams (tonne)
Pre-cast concrete wall (m2)
Curtain wall glazing incl support system (m2) (1,000m2 job)
Plasterboard 13mm thick to stud wall (m2) (3,000m2 job)
Single solid core door incl frame and hardware (50 door job)
Painting to walls primer + 2 coats (m2)
Ceramic tiling (m2) (1,000m2 job)
Vinyl flooring to wet areas (m2) (500m2 job)
Carpet medium tufted (m2) (4,500m2 job)
Lighting installation (m2) (5,000m2+ job)
Copper pipe 15mm to wall (m) (1,000m+ job)
Fire sprinklers (per m2) (5,000m2 job)
Air conditioning incl main plant (m2) (5,000m2+ job)

USD

Purchasing
power parity

10
18
174
1,600
72
77
2,912
122
791
35
1,100
10
75
65
45
85
33
60
155

10
17
169
1,554
70
74
2,829
119
768
34
1,068
10
73
63
44
82
32
58
151

76
66
58
54
78

74
64
56
52
76

Material
Concrete 30 MPa (m3) (1,500m3 job)
Reinforcement bar 16mm (tonne) (120 tonne job)
Concrete block (400x200) per 1,000 (>10,000 block job)
Standard brick per 1,000
Structural steel beams (tonne) (100 tonne + job)
Glass pane 10mm tempered (m2)
Softwood timber for framing 100mm x 50mm (m)
13 mm plasterboard (m2)
Emulsion paint (litre)
Copper pipe 15 mm (m) (1,000m+ job)
Copper cable (m) (3C + E, 2.5mm PVC) (100,000m+ job)

125
1,012
1,051
357
2,052
237
3
5
5
7
4

121
983
1,020
347
1,993
230
3
5
5
7
4

Plant
Hire 50t mobile crane + operator (day)

2,520

2,448

Labour
Group 1 tradesman eg plumber/electrician
Group 2 tradesman eg carpenter/bricklayer
Group 3 tradesman eg carpet layer, tiler, plasterer
General labourer
Site foreman

Market:
Tendering:

getting warmer

Chicago

105

lukewarm

Houston

82

Cost escalation:

2%

Los Angeles

100

Contractors margin:

4%

New York

125

Preliminaries:

9%

Philadelphia

113

International construction cost survey 2013

55

Vietnam
Construction volumes growing but start from a low base
Inflation in Vietnam is now a more manageable 7.2 percent
after reaching 22 percent in late 2012. Growth at five
percent is moderate; efforts to reform and stimulate
the economy have had mixed results.

The residential sector is the strongest construction sector,


with apartments dominating, although these are beginning
to become oversupplied at higher price points, for now.
This has caused problems with non-performing loans.

There is still massive opportunity in construction.


But there is insufficient financial strength to carry
out all the infrastructure and building works needed
to modernise the economy.

Construction volumes are growing strongly, off a low


base. Construction wages are low, but systemic inflation
will ensure construction costs keep rising, even if they
remain low by world standards.

International building costs


per m2 of internal area, in 2013

VND

USD

Purchasing
power parity

(exchange rate:
21,200.00)

Airports
Domestic terminal full service
Low-cost carrier basic service

49,007,460
34,305,220

2,312
1,618

6,909
4,837

Carparks
Multistorey above ground
Multistorey below ground

7,862,400
16,338,070

371
771

1,108
2,303

Commercial
Offices business park
CBD offices up to 20 floors medium (A-grade)
CBD offices high-rise prestige

14,004,060
17,505,070
19,586,810

661
826
924

1,974
2,468
2,761

Education
Primary and secondary schools
University

11,681,280
14,017,540

551
661

1,647
1,976

Hospitals
Day centre (including basic surgeries)
Regional hospital
General hospital (eg city teaching hospital)

14,902,620
28,680,690
28,680,690

703
1,353
1,353

2,101
4,044
4,044

Hotels
3 star travellers
5 star luxury
Resort style

28,062,030
37,019,320
31,674,240

1,324
1,746
1,494

3,956
5,219
4,466

Industrial
Warehouse/factory units basic
Large warehouse distribution centre
High-tech factory/laboratory

9,246,180
9,371,980
16,353,790

436
442
771

1,304
1,321
2,306

Residential
Individual detached house medium standard
Individual detached house prestige
Townhouses medium standard
Apartments private medium density
Apartments high rise
Aged care/affordable units

13,990,580
15,156,460
11,658,820
15,156,460
17,488,220
11,658,820

660
715
550
715
825
550

1,972
2,137
1,644
2,137
2,466
1,644

Retail
Large shopping centre including mall
Neighbourhood incl supermarket
Prestige car showroom

15,171,060
11,670,050
12,837,050

716
550
606

2,139
1,645
1,810

56

Turner & Townsend

Vietnam international building costs


per m2 of internal area

VND

USD

Purchasing
power parity

72,360
86,400
1,555,200
23,801,040
224,640
280,800
30,944,160
972,000
9,720,000
432,000
5,660,928
89,640
438,048
348,192
712,800
388,800
723,600
648,000
864,000

3
4
73
1,123
11
13
1,460
46
458
20
267
4
21
16
34
18
34
31
41

10
12
219
3,356
32
40
4,363
137
1,370
61
798
13
62
49
100
55
102
91
122

233,280
200,880
162,000
129,600
216,000

11
9
8
6
10

33
28
23
18
30

Material
Concrete 30 MPa (m3) (1,500m3 job)
Reinforcement bar 16mm (tonne) (120 tonne job)
Concrete block (400x200) per 1,000 (>10,000 block job)
Standard brick per 1,000
Structural steel beams (tonne) (100 tonne + job)
Glass pane 10mm tempered (m2)
Softwood timber for framing 100mm x 50mm (m)
13 mm plasterboard (m2)
Emulsion paint (litre)
Copper pipe 15 mm (m) (1,000m+ job)
Copper cable (m) (3C + E, 2.5mm PVC) (100,000m+ job)

1,215,778
18,695,880
6,183,000
1,566,000
21,792,240
1,144,800
54,000
54,000
51,613
409,471
37,800

57
882
292
74
1,028
54
3
3
2
19
2

171
2,636
872
221
3,072
161
8
8
7
58
5

Plant
Hire 50t mobile crane + operator (day)

25,440,000

1,200

3,587

Composite
Excavate basement (m3) (1,800m3 job)
Excavate footings (m)
Concrete in slab (m3) (1,500m3 job)
Reinforcement in beams (tonne)
Formwork to soffit of slab (m2)
Blockwork in wall (m2) (10,000 block job)
Structural steel beams (tonne)
Pre-cast concrete wall (m2)
Curtain wall glazing incl support system (m2) (1,000m2 job)
Plasterboard 13mm thick to stud wall (m2) (3,000m2 job)
Single solid core door incl frame and hardware (50 door job)
Painting to walls primer + 2 coats (m2)
Ceramic tiling (m2) (1,000m2 job)
Vinyl flooring to wet areas (m2) (500m2 job)
Carpet medium tufted (m2) (4,500m2 job)
Lighting installation (m2) (5,000m2+ job)
Copper pipe 15mm to wall (m) (1,000m+ job)
Fire sprinklers (per m2) (5,000m2 job)
Air conditioning incl main plant (m2) (5,000m2+ job)
Labour
Group 1 tradesman eg plumber/electrician
Group 2 tradesman eg carpenter/bricklayer
Group 3 tradesman eg carpet layer, tiler, plasterer
General labourer
Site foreman

Market:
Tendering:

staying the same


lukewarm

Cost escalation:

5%

Contractors margin:

5%

Preliminaries:

(exchange rate:
21,200.00)

Hanoi

92

Ho Chi Minh City

100

10%

International construction cost survey 2013

57

Purchasing power parity


Turner & Townsend has worked with Bond University,
Queensland, to develop a more reliable method for
comparing international construction costs.
There are two major reasons why construction costs
between countries cannot be compared reliably using
currency exchange rates. First, this method fails to take
account of local living standards. And second, exchange
rates are highly volatile.
Take Australia and the US as an example. In 2001,
1 AUD = 0.5 USD. In 2012, 1 AUD = 1.08 USD. Yet the
relative prices (or purchasing power) of construction items
remained virtually unchanged.
Purchasing power parity is a more reliable way of
comparing prices. Although used in other areas of
economics, its application in this survey and report is the
first attempt to properly compare international
construction costs.
We use a standard basket of equally weighted construction
items, comprising material, labour and plant, to calculate
purchasing power parity values in each country. The
average price of items in the standard basket for a
particular country is then divided by the average price
for a base country to calculate relative purchasing
power parity.

The values in the purchasing power parity columns in the


report express local costs in terms of purchasing power by
weighting them according to the basket priced in-country.
The higher the purchasing power parity-adjusted cost, the
higher are the relative costs of building in one country over
another. When making relative cost comparisons between
cities in different countries, purchasing power parity is the
correct methodology to apply.
In countries where cheap labour predominates, the value
of the basket is lower to reflect lower living standards.
The choice of items in the standard basket is based
on typical construction items available globally.
Use of purchasing power parity to compare cost
performance over time should be aware of current market
conditions in each location, therefore after converting
all costs to a common year, further adjustment (perhaps
ten percent) for abnormal levels of competition may
be required.
Turner & Townsend is grateful to Bond Universitys Centre
for Comparative Construction Research for assistance with
this methodology. Further background on comparing
international construction performance can be accessed
from http://epublications.bond.edu.au/sustainable_
development/150/

In this report, trade, labour and material prices and prices per m2 are
indicative, and should not be relied on without first obtaining advice
from a qualified professional person. Costs are dependent on building
design, inclusions, exclusions, and site conditions. Cost comparisons
between countries are subject to different interpretations, building
methods, and standards for costing, measurement and construction.
Costs may vary substantially between regions within countries. Turner
& Townsend plc and its subsidiaries, the authors and contributors,
expressly disclaim all and any liability and responsibility to any person
in respect of anything done or omitted to be done in reliance wholly
or in part upon the whole of the contents of this publication.

We value your feedback, please get in touch at


gary.emmett@turntown.com

58

Turner & Townsend

www.turnerandtownsend.com

You might also like