Professional Documents
Culture Documents
Document ref
BC-PBA-GLTSP102SPC-0001-1-03
26 May 2010
DCN: 00047
IFA / AFC
May 2010
Job number
A125840
PB2108209A
Document Verification
Page 1 of 1
Job title
Job number
PB2108209A A125840
Document title
Document ref
BC-PBA-GLTSP102-SPC-0001-1-03
Revision
Date
26 May 2010
Filename
BC-PBA-AGTSP100-SPC-0002-0-01.doc
Description
AFC Issue
Name
File reference
Prepared by
Checked by
Approved by
Andreas Amon
Robert Bertuzzi
Eddie Woods
Signature
Review
16/02/10
Filename
BC-PBA-GLTSP102-SPC-0001-1-01.doc
Description
Name
Prepared by
Checked by
Approved by
Eddie Woods
Richard Page
Eddie Woods
Signature
Review
29/03/10
Filename
BC-PBA-GLTSP102-SPC-0001-1-02.doc
Description
Name
Prepared by
Checked by
Approved by
Eddie Woods
Richard Page
Eddie Woods
Signature
IFA / AFC
26/05/10
Filename
BC-PBA-GLTSP102-SPC-0001-1-03.doc
Description
Name
Prepared by
Checked by
Approved by
Eddie Woods
Richard Page
Eddie Woods
Signature
C:\APL-PBAJV\KIERAN.COOK\DMS47695\BC-PBA-GLTSP102-SPC-0001-1-03.DOC
BC-PBA-GLTSP102-SPC-0001-1-03
26 May 2010
Contents
1
Page
1
General
1.1
Scope
1.2
Definition of Terms
1.3
1.4
1.5
1.6
2.1
General
2.2
2.3
10
2.4
Testing Frequency
10
2.5
10
Shotcrete Materials
11
3.1
General
11
3.2
Shotcrete Types
11
3.3
Water
11
3.4
Cement
11
3.5
12
3.6
Aggregates
12
3.7
14
3.8
Admixtures
14
3.9
Fibres
16
3.10
17
Shotcrete Requirements
17
4.1
17
4.2
Mix
18
4.3
18
4.4
19
4.5
Submission Details
21
4.6
Performance
21
22
5.1
22
5.2
23
5.3
23
C:\APL-PBAJV\KIERAN.COOK\DMS47695\BC-PBA-GLTSP102-SPC-0001-1-03.DOC
BC-PBA-GLTSP102-SPC-0001-1-03
26 May 2010
24
Parsons Brinckerhoff Arup Joint Venture
IFA / AFC 26 May 2010
6.1
Equipment
24
6.2
Proficiency of Nozzlemen
25
6.3
25
6.4
Application
26
6.5
27
6.6
Curing
28
Shotcrete Testing
28
7.1
Production Tests
28
7.2
30
7.3
31
7.4
31
7.5
Fibre Content
31
7.6
Slump
32
7.7
32
Repair of Shotcrete
32
8.1
General
32
8.2
32
32
9.1
General
32
9.2
33
Tables
Table 1 Definition of Terms
Table 2 Changes made to previously issued revisions
Table 3 Hold Points
Table 4 Witness Points
Table 5 Milestones
Table 6 Work Method Statements
Table 7 Items Requiring Use of QDMR Registered Suppliers and Products
Table 8 Aggregate Grading for Shotcrete
Table 9 Maximum Dosages of Accelerator
Table 10 Maximum Values of Acid-Soluble Chloride-Ion Content in Shotcrete
Table 11 Particular Mix Requirements
Table 12 Testing Methods Field Trials
Table 13 Minimum Performance Requirements for Shotcrete
Table 14 Test Methods Production Testing for Temporary Shotcrete Lining
Table 15 Test Methods Production Testing for Permanent Shotcrete Lining
Appendices
Appendix A
Verification Records
Appendix B
Response to Comments
C:\APL-PBAJV\KIERAN.COOK\DMS47695\BC-PBA-GLTSP102-SPC-0001-1-03.DOC
BC-PBA-GLTSP102-SPC-0001-1-03
26 May 2010
General
This technical specification has been provided by Parsons Brinckerhoff Arup Joint Venture
on behalf of Thiess John Holland Joint Venture for use in execution of the Design and
Construct Contract with the Airport Link, Northern Busway and ARU project (the Project).
1.1
Scope
The specification covers both temporary works shotcrete and permanent shotcrete. The
specification complies with the Mined Tunnels Design Manual and will be reviewed and
updated as necessary during execution of the Works.
The types of shotcrete for underground works are as follows:
SFRS applied as temporary (initial) and permanent (pump sumps and substations)
ground support
This Specification shall be read in conjunction with the Temporary and Permanent Works
Design Drawings and other relevant Specifications. The thickness dimensions shown on the
Drawings are minimum thicknesses. Shotcrete thicknesses shall be such as to provide a
minimum cover, as shown on the Drawings, over all steel components and fixtures including
rockbolt heads, steel sets, lattice girders and reinforcing mesh.
The General Specification (reference BC-PBA-GLRSP000-SPC-0001) provides general
information relating to all other specifications. The General Specification must be used with
this Specification.
Users of this Specification and related specifications and documents are required to ensure,
that they are referring the current version.
The durability of shotcrete manufactured in accordance with this specification has been
assessed in the Durability Report (reference PBA-BC-AGDTR100-RPT-0001).
This specification is to be read in conjunction with the related specifications outlined in
Clause 1.3.
C:\APL-PBAJV\KIERAN.COOK\DMS47695\BC-PBA-GLTSP102-SPC-0001-103.DOC
BC-PBA-GLTSP102-SPC-0001-1-03
26 May 2010
Page 1
1.2
Definition of Terms
Definitions applicable to many specifications, including this Specification, shall include those
found in the General Specification (reference BC-PBA-GLRSP000-SPC-0001).
While the definitions found in the General Specification take precedence, the following
definitions, when not found in the General Specification, apply particularly to this
Specification:
Table 1 Definition of Terms
Term
Definition
The relative strength for silica fume is the ratio (in percent) of the
compressive strength of standard mortar bars, prepared with 90% cement
plus 10% silica fume by mass, to the compressive strength of standard
mortar bars made from cement only.
Admixtures
Cement
Characteristic
Cylinder strength at
28 days
Curing
The control of temperature and moisture in the concrete until the concrete
has developed required properties.
Flash Coat
In Situ Cylinder
Strength
Lattice Girder
Layer
Nozzle
Overspray
Rebound
Shotcrete which having passed through a spraying nozzle does not adhere
to the surface to which shotcrete is being applied.
SFRS
Sloughing
Shotcrete
C:\APL-PBAJV\KIERAN.COOK\DMS47695\BC-PBA-GLTSP102-SPC-0001-103.DOC
BC-PBA-GLTSP102-SPC-0001-1-03
26 May 2010
Page 2
Term
Definition
nozzle into place to produce a dense, homogeneous mass, applied directly
to the ground surface in one or more layers to form the lining of a sprayed
concrete support structure.
Shotcrete Type S1
Shotcrete Type S2
Shotcrete Type S3
Shotcrete Type S4
Shotcrete Type P1
Shotcrete Type P2
Shotcrete Type P3
Base Mix: Concrete designed, tested and supplied independent from the
shotcreting process, equipment and personnel.
Shotcrete Mix: The base mix after it is applied to the Works, or to test
panels.
Sprayed Concrete
Support Systems
Structure
Standard Cylinder
strength
URS
Unreinforced Shotcrete
Waterproofing
Supervisor
Wet-mix Process
1.3
1.3.1
General Specification
The General Specification (reference BC-PBA-GLRSP000-SPC-0001) contains information
required for an understanding of any and all of the specifications applicable to the Project.
The General Specification shall be read prior to use of any of the other specifications,
including this Specification.
Standards and Related Specifications
1.3.2
This specification is to be read in conjunction with the following:
PBAJV SS
C:\APL-PBAJV\KIERAN.COOK\DMS47695\BC-PBA-GLTSP102-SPC-0001-103.DOC
BC-PBA-GLTSP102-SPC-0001-1-03
26 May 2010
Page 3
PSTS03
PSTS50
PSTS70
Concrete
PSTS71
Reinforcing Steel
Australian Standards
AS 1012
AS 1141
AS 1379
AS 1478.1
AS 2350
AS 2758.1
AS 3582.1
AS 3582.2
AS 3582.3
AS 3583.6
AS 3972
AS/NZS 4671
ASTM C1260
ASTM C1550
C:\APL-PBAJV\KIERAN.COOK\DMS47695\BC-PBA-GLTSP102-SPC-0001-103.DOC
BC-PBA-GLTSP102-SPC-0001-1-03
26 May 2010
Page 4
ASTM C311
Standard Test Methods for Sampling and Testing Fly Ash or Natural
Pozzolans for Use in Portland-Cement Concrete
ASTM C94
British Standards
BS EN 1367-2
BS EN 14488-4
BS EN 14488-7
BS EN 14889-1
BS EN 14889-2
Other Standards
ACI 506R-05
Guide to Shotcrete
Specification for Tunnelling, British Tunnelling Society and the Institution of Civil Engineers
ITA-shotcrete guidelines, Sprayed concrete for final linings: ITA working group report,
AITES / ITA, 2001
Concrete Institute of Australia, Recommended Practice Shotcreting in Australia
1.4
Where a discrepancy exists between the Design Drawings and this Specification the
Contractor shall seek clarification from the Construction Certifier. Drawing notes will take
precedence over the Specification.
1.5
The following table details all the changes made to this specification since previously issued
revisions.
Table 2 Changes made to previously issued revisions
Revision
Clause
Change
Description
Description
1-01
General
Modification
DCN:
00047
Modification
1.1
Modification
1.2
Modification
1.3
Addition
1.5
Addition
C:\APL-PBAJV\KIERAN.COOK\DMS47695\BC-PBA-GLTSP102-SPC-0001-103.DOC
BC-PBA-GLTSP102-SPC-0001-1-03
26 May 2010
Page 5
the report.
3.2
Modification
3.5.2 a)
I.
Deletion
3.5.2
Modification
3.6 v.
Addition
3.6
Modification
3.8.2 e)
Addition
3.10
Addition
4.1
Addition
4.2
Modification
4.3 vi.
Addition
4.4. ( b)
Modification
Addition
4.4.( i)
Addition
4.4 (n)
Addition
4.6
Modification
Table 13 updated
Field trials and Production Tests (Cylinder) updated
Dry density 2150 to 2400Kg/m
- for permanent shotcrete only added to Boiled
Absorption and Apparent Volume
C:\APL-PBAJV\KIERAN.COOK\DMS47695\BC-PBA-GLTSP102-SPC-0001-103.DOC
BC-PBA-GLTSP102-SPC-0001-1-03
26 May 2010
Page 6
Addition
6.3 f)
Addition
7.1
(Table
14)
Modification
7.1
(Table
15)
Modification
1-02
1.1
Addition
1.2
Modification
1.2
Addition
1.3
Addition
3.6
Modification
3.8.2
Modification
3.8.4
Modification
3.9
Addition/Modification
DCN:
00047
C:\APL-PBAJV\KIERAN.COOK\DMS47695\BC-PBA-GLTSP102-SPC-0001-103.DOC
BC-PBA-GLTSP102-SPC-0001-1-03
26 May 2010
Page 7
1.6
4.2
Modification
Table 11
Modification
4.4 b
Modification
5.3
Addition
5.3.1
Deletion
5.3.1
Modification
6.1
Addition
General
Modification
General
Modification
a) General guidelines for records are provided in the General Specification (reference BCPBA-GLRSP000-SPC-0001).
b) Records of work methods, listed in Table 6 related to this specification are required to
be submitted by the Contractor to the Construction Certifier in accordance with the
quality system requirements of the Contract.
c) This Specification requires the Contractor to prepare and maintain, as a minimum, the
following documents in accordance with the Contractors Project Quality Plan and make
them available for audit purposes:
i.
ii.
iii. Details of cement for shotcrete, including suppliers details and information to
demonstrate compliance with AS 3972
iv. Details of fly ash, slag and silica fume for shotcrete
v.
Details of aggregates and aggregate sources for shotcrete, including testing and
properties of the aggregates
vi. Manufacturers test certificates and product analysis certificates for the fibres to be
used for the fibre reinforced shotcrete
vii. Test results for the water used in the mixing and curing of the shotcrete
viii. Concrete Suppliers batch card showing details of the mix design for each type of
shotcrete
ix. Details of all admixtures for shotcrete, including manufacturers product data, and
the equipment and method of controlling the addition of admixtures to the shotcrete
x.
Records of the type of equipment used for batching, mixing, transport and
application of shotcrete, including location of the batching plant and method of
delivery to site
C:\APL-PBAJV\KIERAN.COOK\DMS47695\BC-PBA-GLTSP102-SPC-0001-103.DOC
BC-PBA-GLTSP102-SPC-0001-1-03
26 May 2010
Page 8
xi. Results of all acceptance testing and field trials, and results of production testing of
the shotcrete
xii. The mix design for each type of shotcrete shall be approved by the Construction
Certifier.
xiii. Records of inspection and written approval of the Temporary and Permanent Works
shall be provided in accordance with this Specification.
General
a) The Hold and Witness Points particular to this Specification are listed in Table 3, Table
4 and Table 5 below. Refer General Specification (reference BC-PBA-GLRSP000-SPC0001) for Hold Point, Witness Point and Milestone definitions and requirements.
b) The Contractor shall not proceed beyond a Hold Point until the Hold Point has been
released by the person nominated in Table 3. The Contractor shall notify the relevant
person when a Hold Point will be reached so that they can review and/or witness any
work process, record or test being undertaken by the Contractor and thus expedite the
release of that Hold Point.
Table 3 Hold Points
Specification Clause
For Release By
IV
Contractor
4.3
Construction Certifier
6.2
Certification of nozzlemen
Contractor
Repair of shotcrete
Construction Certifier
Construction Certifier
c) The Contractor shall provide the person nominated in Table 4 reasonable notice
(minimum 24 hours or as otherwise specified) of all Witness Points so that inspection
may be made of the following:
Table 4 Witness Points
Specification
Clause
For Release By
IV
Contractor
C:\APL-PBAJV\KIERAN.COOK\DMS47695\BC-PBA-GLTSP102-SPC-0001-103.DOC
BC-PBA-GLTSP102-SPC-0001-1-03
26 May 2010
Page 9
Specification
Clause
For Release By
6.5
Construction Certifier
Construction Certifier
Construction Certifier
d) The Contractor shall submit at the time nominated in Table 5, documentary evidence of
Milestones to the Construction Certifier for approval of materials and workmanship as
specified throughout the Specification.
Table 5 Milestones
Specification Clause
2.3
Milestone Details
Timing
4.1
30 days prior to
commencement of work
4.3
30 days prior to
commencement of work
4.3
30 days prior to
commencement of work
Work Method Statements which are required to be submitted by the Contractor to the
Construction Certifier in accordance with the quality system requirements of the Contract
are listed below in Table 6.
Table 6 Work Method Statements
Specification Clause
4.1
2.4
Testing Frequency
The minimum testing frequency for work covered by this Specification is specified in
Clause 7.
2.5
The use of QDMR registered suppliers and products for the construction of the project
works are required for the items listed in Table 7.
Table 7 Items Requiring Use of QDMR Registered Suppliers and Products
Specification Clause
3.4
Category of Work
Cement Supply
3.5.1
Fly Ash
3.5.2
Silica Fume
3.8
Admixtures
C:\APL-PBAJV\KIERAN.COOK\DMS47695\BC-PBA-GLTSP102-SPC-0001-103.DOC
BC-PBA-GLTSP102-SPC-0001-1-03
26 May 2010
Page 10
Shotcrete Materials
3.1
General
Materials for shotcrete as a minimum must conform to the requirements of this Clause of the
Specification.
3.2
Shotcrete Types
Shotcrete Type P2: Steel mesh reinforced shotcrete for permanent support of
excavations. The characteristic cylinder strength of Shotcrete Type P2 at 28 days is
40 MPa.
g) Shotcrete Type P3: Plain Shotcrete shall have monofilament polypropylene fibres in
accordance with Section 3.9. The characteristic cylinder strength of Shotcrete Type P3
at 28 days is 40 MPa.
3.3
Water
a) Water incorporated into shotcrete shall be potable, free from contaminants harmful to
concrete or reinforcement and have electrical conductivity not exceeding 1000 microsiemens/metre.
b) Water to be used in the manufacture of shotcrete for the Temporary and Permanent
Works shall be of an acceptable quality as defined in Clause 2.4 of AS 1379.
c) Water used for curing, testing water tightness or for other purposes where it may come
in contact with shotcrete, shall be potable, clean and free from oil and suspended
matter, and shall otherwise comply with the requirements of Clause 2.4 of AS 1379.
3.4
Cement
Page 11
certificates shall cover the period from at least 12 months prior to commencement of the
project. Testing of cement properties in accordance with AS 3972 shall be carried out at
least monthly.
f)
3.5
3.5.1
Fly Ash
a) Supplementary cementitious materials Fly Ash and Slag shall comply with AS 3582
Parts 1 and 2 respectively and shall be a QDMR registered fly ash or slag, with the
following modifications:
i.
The amount of fly ash retained when wet sieved on a 45 micron sieve shall not
exceed 15% by weight.
ii.
iii. Specific gravity shall not vary by more than 5%. The uniformity of specific gravity
shall be determined in accordance with Section 17 of ASTM C311.
3.5.2
Microsilica (Silica Fume)
a) Supplementary cementitious material Silica Fume shall comply with AS 3582 Part 3.
Silica fume is a latent hydraulic binder which shall comply with the following
requirements:
I.
ii.
ii.
ii.
e) The Contractor shall maintain details of silica fume used in shotcrete for audit purposes.
3.6
a)
Aggregates
C:\APL-PBAJV\KIERAN.COOK\DMS47695\BC-PBA-GLTSP102-SPC-0001-103.DOC
BC-PBA-GLTSP102-SPC-0001-1-03
26 May 2010
Page 12
i. The nominal maximum particle size shall be 10mm unless approved otherwise by the
Construction Certifier.
ii.
The Los Angeles coefficient shall be determined in accordance with sub clause 10.2
of AS 2758.1
vi. The fines content less than 75 micron determined in accordance with AS 1141.12
shall not exceed 2%.
vii. The aggregate shall be tested for reactivity with the cementitious materials and
admixtures (including accelerators) using the ASTM C1260-01 accelerated mortar
bar method.
viii. Single size aggregates shall be combined in the proportions determined during the
field trials. The individual fractions shall be stored separately.
b)
Coarse and fine aggregates shall be free from earth, clay loam and soft clayey, shaley
or decomposed stone, organic matter, friable particles and other impurities and shall be
hard and dense. The grading shall be within the acceptable range according to the
grading given in Table 8 below for wet mix shotcrete.
c) The grading and moisture content of the individual fractions of the aggregate shall be
checked and recorded at least weekly.
d) The Contractor shall maintain for audit purposes details of aggregates and aggregate
sources for shotcrete, including testing and properties of the aggregates.
e) The following aggregates have been tested and confirmed as suitable for use with
polypropylene fibres for permanent shotcrete requiring resistance to fire:
Beenleigh Meta-Greywacke,
Petrie Greenstone
f) Should the contractor wish to use other aggregates these will require further testing.
C:\APL-PBAJV\KIERAN.COOK\DMS47695\BC-PBA-GLTSP102-SPC-0001-103.DOC
BC-PBA-GLTSP102-SPC-0001-1-03
26 May 2010
Page 13
3.7
S4
9.5 mm
90 100
6.70 mm
80 90
90 100
4.75 mm
70 85
75 90
2.36 mm
50 70
50 75
1.18 mm
35 55
35 55
600 m
20 40
20 40
300 m
8 20
8 20
150 m
2 10
2 10
75 m
02
02
a) Aggregates intended for use in shotcrete shall not react with alkalis in the concrete that
may result in excessive expansion. The aggregate supplier must provide documentation
of the potential reactivity of the aggregate in accordance with PSTS70 clause 11.1. The
proposed concrete mixes shall meet the innocuous classification of QDMR Test Method
Q458.
3.8
Admixtures
3.8.1
General
b) Admixtures for the purposes of this Specification shall not be used without the approval
of the Construction Certifier.
c)
d) Admixtures to the sprayed concrete mix shall be stated in the Method Statement. The
performance of the modified mix shall be demonstrated by site trials prior to that mix
being used in the Works.
e) All admixtures for shotcrete shall be sourced from a single manufacturer or supplier
where possible to ensure compatibility of admixtures for use in the shotcrete. Where
admixtures are sourced from different suppliers, evidence shall be obtained to
demonstrate the compatibility of the admixtures. Compatibility of all admixtures with
each other and with all other sprayed concrete constituents shall be verified during site
trials.
f)
The Contractor shall obtain sufficient documentation to support the use of all admixtures
prior to commencement of field trials. The documentation shall include the
manufacturers product data and details of the equipment and method for controlling the
addition of admixtures to the shotcrete.
g) Confirmation of the following requirements for all admixtures shall be obtained by the
Contractor from the manufacturer prior to use in the tunnels and shafts:
i.
ii.
C:\APL-PBAJV\KIERAN.COOK\DMS47695\BC-PBA-GLTSP102-SPC-0001-103.DOC
BC-PBA-GLTSP102-SPC-0001-1-03
26 May 2010
Page 14
vi. Results of testing as required by this Specification for each type of admixture
vii. Confirmation that the additives are safe to use in a tunnel environment and any
safety precautions that are to be taken
3.8.2
Accelerators
a) Accelerators are admixtures. Only liquid accelerators shall be used.
b) Sodium Silicate (Waterglass) shall not be used.
c) Only the minimum quantity of accelerator necessary shall be permitted in normal
shotcreting operations. The quantity shall be determined by field trials, subject to the
maximum dosages specified in Table 9:
Table 9 Maximum Dosages of Accelerator
Shotcrete Type
S1
8%
S2
8%
S3
8%
S4
8%
P1
5%
P2
5%
P3
5%
Accelerators shall be selected such that, at the dosage chosen for use, the decrease in
strength of any Shotcrete Type at an age of 28 days, compared with the base concrete
without any accelerators, shall not exceed 25%. Also, there shall be no further
reduction in strength of the shotcrete mix between 28 and 90 days. Compliance with this
clause shall be demonstrated by testing at a frequency as deemed necessary.
3.8.3
Plasticisers and Retarders
a) Plasticisers and retarders are admixtures and shall comply with AS 1478 and may be
used in Shotcrete Types S1, S2, S3, S4, P1, P2 and P3 subject to the approval of the
Construction Certifier.
b) Plasticisers and retarders may be used to reduce the quantity of the mixing water and to
improve the pumpability of the shotcrete. The effects and optimum dosages of
C:\APL-PBAJV\KIERAN.COOK\DMS47695\BC-PBA-GLTSP102-SPC-0001-103.DOC
BC-PBA-GLTSP102-SPC-0001-1-03
26 May 2010
Page 15
plasticisers and retarders shall be determined during development of the mix design
and/or by field trials in accordance with this Specification.
c) Plasticisers and retarders shall not contain calcium chloride.
d) Compatibility of plasticisers and retarders with cements, latent hydraulic binders and
accelerators shall be verified by observation during development of the mix design
and/or in the field trials.
e) Plasticisers and retarders shall be used in accordance with the manufacturers
instructions.
Hydration Control Admixtures
3.8.4
a) Hydration control admixtures may be used with Shotcrete Types S1, S2, S3, P1, P2 and
P3 in accordance with this Specification and subject to the approval of the Construction
Certifier. Hydration control admixtures used with accelerator in Shotcrete Type S1, S2,
S3, S4, P1, P2 and P3 shall not cause a decrease in strength with age.
b) Hydration control admixtures may be used to control the hydration of the mix as
appropriate to expedite construction of the Temporary and Permanent Works. The
effects and optimum dosages of hydration control admixtures shall be determined by
field trials in accordance with this Specification.
c) Hydration control admixtures that delay the setting process by greater than 10 hours for
Shotcrete Type S1, S2, S3, S4, P1, P2 and P3 shall not be used. Proposals to use
hydration control admixtures for longer periods may require additional field trials and/or
testing as specified by the Construction Certifier.
d) Compatibility of hydration control admixtures with cements, latent hydraulic binders and
accelerators shall be verified by observation in the field trials.
e) Hydration control admixtures shall be used in accordance with the manufacturer's
instructions.
3.9
Fibres
3.9.1
General
a) Fibres may be collated with fast-acting water-soluble glue, or may be uncollated
individual fibres. Water-soluble glue or other additives used to collate fibres shall be
compatible with other shotcrete components.
b) Fibres shall be stored in dry sealed containers until ready for use and shall be free from
corrosion, oil, grease, chlorides and deleterious materials which may reduce the
efficiency of mixing or spraying processes, or which may reduce the bond between the
fibres and the shotcrete. Containers of fibres shall be stored in areas protected from the
weather and extremes of heat as per the manufacturers instructions.
c) Fibre type shall be selected on the basis of compliance with this Specification and on
suitability and ease of use in the batching, mixing and shotcreting processes proposed,
as demonstrated by field trials. Fibres which tend to form fibre balls during batching and
mixing shall not be used.
3.9.2
Steel Fibres
a) Steel fibre shall be deformed steel fibre Type 1, 2 or 3 in accordance with ASTM A820
except that Type 1 fibre may be either circular or rectangular in section. Fibres shall be
produced from milled steel or cold drawn wire and shall be ungalvanised.
b) Steel fibres shall have an aspect ratio in the range of 30 to 150. Tolerances shall be in
accordance with ASTM A820.
C:\APL-PBAJV\KIERAN.COOK\DMS47695\BC-PBA-GLTSP102-SPC-0001-103.DOC
BC-PBA-GLTSP102-SPC-0001-1-03
26 May 2010
Page 16
3.9.3
Synthetic Fibres (Structural)
a) Synthetic fibres shall be of the structural macro-synthetic type of fibre in accordance
with BS EN 14889-2 and of greater than 0.3mm diameter. The fibre shall have a
textured surface and be produced from polyolefin or a similar base resin material. .
Synthetic Fibres (Fire)
3.9.4
a) Synthetic Fibre may be used in Shotcrete Type P1, P2 or P3 to achieve the specified
design requirements for the fire load case.
a) The chloride ion content of the hardened shotcrete must be tested in accordance with
AS1012.20. A representative sample of at least 20 grams of crushed and ground
shotcrete shall be used, with the titrating solution being 0.01 to 0.02N. For the test, use
the Volhard method calibrated using a concrete with known chloride content.
b) The mass of acid-soluble chloride ion per unit volume of permanent shotcrete as placed
must not exceed the values given in Table 10.
c) The sulphate content of shotcrete, determined by calculation and expressed as the
percentage by mass of acid-soluble SO3 to cement, must not be greater than 4.0%.
Table 10 Maximum Values of Acid-Soluble Chloride-Ion Content in Shotcrete
Maximum acid-soluble chloride ion content (kg/m)
Exposure *
Classification
0.8
B1
0.8
B2
0.8
Note: Chloride ion content may be expressed in percentage weight of oven dried concrete.
(0.1 kg/m3 ion content is approximately equivalent to 0.004% by weight of oven dried
concrete). *For information on exposure classifications see AS 5100.5.
Shotcrete Requirements
4.1
a) A Construction Method Statement for the tunnel shotcrete lining works shall be
prepared prior to commencing any work. The method statement is to be submitted for
review to the Construction Certifier at least 30 days prior to the commencement of
temporary or permanent shotcreting works Milestone. The Construction Method
Statement shall contain, as a minimum, full details of the following where appropriate:
i.
Methods of working
ii.
Page 17
Proposed methods for use of steel reinforcement and other embedments where
applicable
vi. Proposed methods and equipment for mixing, conveying and applying shotcrete
vii. Details of procedures for monitoring of shotcrete thickness, including spacing of
depth indicators (if applicable) and details of how the profile is to be maintained.
viii. Repair procedures, including proposed mix designs for core hole repair
4.2
Mix
a) Mix designs shall comply with the requirements shown in Table 11. Witness Point.
Table 11 Particular Mix Requirements
Shotcrete Type
Parameter
S1
S2
S3
S4
P1
P2
P3
Steel Fibre
- minimum tensile strength (MPa)
900
N/A
900
N/A
25
N/A
25
N/A
50
N/A
50
N/A
30
N/A
30
N/A
400
0.45
Accelerator Type
5-10%
(4-8% when used with Type GP or GB)
b) Shotcrete shall be applied by the wet mix process and be capable of being applied in
layers up to 150 mm in thickness with good adhesion to the ground or previous layers of
shotcrete without sagging or slumping.
c) Shotcrete shall be dense and homogeneous without segregation of aggregate and/or
fibre or other visible imperfections.
4.3
a) The purpose of the field trials is to check the suitability of the proposed mix design,
materials, plant, the work methods and the competence of the shotcrete operators.
Sprayed panels shall be used to verify the following design properties:
i.
Compressive strength;
ii.
Density;
C:\APL-PBAJV\KIERAN.COOK\DMS47695\BC-PBA-GLTSP102-SPC-0001-103.DOC
BC-PBA-GLTSP102-SPC-0001-1-03
26 May 2010
Page 18
If field trials are required, testing for field trials shall be in accordance with Table 12.
Method
ASTM C1550-03a
This Specification
4.4
a) From the field trial mix an experienced nozzleman shall prepare sufficient test panels.
Panels for coring shall be at least 1000 x 1000mm in size and shall be 200mm thick.
The panels shall be prepared by shotcreting into rigidly supported vertical moulds.
Moulds shall be constructed of steel or other non-water absorbing rigid materials. The
upper and lower edges of the mould shall have parallel sides splayed outwards at 45
degrees to the back face to prevent the entrapment of rebound. The vertical edges of
the mould shall have parallel sides at 90 degrees to the back face to facilitate coring
perpendicular to the spray direction. Round panels for flexural toughness testing shall
be 800 10mm diameter and 75 15mm thick, and prepared by shotcreting into rigidly
supported vertical moulds in accordance with ASTM C1550-03a. In all cases, the
shotcrete in panels shall adhere well to the backform, be properly compacted and
exhibit no sagging.
b) The target slump(s) shall be confirmed by trial mixes with and without superplasticisers.
The pre production and production tests on sprayed shotcrete shall comply with the
short and long term strengths specified in Table 13 for field tests and production tests
(cores). For sprayed concrete the target slump shall be;
c) All panels shall be protected immediately against moisture loss using the same method
to be used in construction, shall not be moved for 18 hours after spraying, and shall be
stored without disturbance until the time of coring, sawing, or testing. Cores for 1, 7, 28
and 90 day compressive strength tests shall be obtained from the panels at 22hours.
C:\APL-PBAJV\KIERAN.COOK\DMS47695\BC-PBA-GLTSP102-SPC-0001-103.DOC
BC-PBA-GLTSP102-SPC-0001-1-03
26 May 2010
Page 19
The cores for 7, 28 and 90 day strength tests shall be stored in water in accordance
with AS 1012. Round panels for flexural toughness testing shall be stored in water in
accordance with AS 1012.
d) Cylindrical test specimens shall be cored from each test panel and tested as listed
below. Drilling of test specimens shall be in accordance with AS 1012.14. Drilling of
cores shall be located to avoid areas of possible rebound. No two cores to be tested at
any given age shall come from the same panel. Cores to be tested at different ages (i.e.
1, 7 and/or 28 days) may come from the same panel. For each test at least one spare
specimen shall be provided. The testing requirements and core dimensions shall be:
i.
ii.
e) Each cored cylinder or round determinate panel shall be marked with an appropriate
reference mark and the date and time of shotcreting.
f)
Steel fibres used shall have a minimum tensile strength of at least 900 MPa
g) Setting times shall be observed during the field trials in accordance with BS EN 196-3.
h) Optimum fibre content shall be determined dependent on ease of use in the batching,
mixing, and shotcreting processes proposed, and from the results of the tests to
determine flexural toughness by the testing of round determinate panels.
i)
The compressive strength of shotcrete cores from test panels shall be acceptable if the
compressive strength results both for samples with their axes parallel to the direction of
spraying and for samples with their axes perpendicular to the direction of spraying,
comply with the minimum performance requirements set out in this Specification. One
test result shall consist of the mean of three core strengths (a spare specimen shall be
taken but not tested). Seven day results shall be used for indicative purposes only. The
compressive strength of cores in steel fibre reinforced or plain shotcrete shall be
deemed to be the in situ cylinder strength provided that the specified requirements are
met in terms of core diameter and height: diameter ratio.
j)
A minimum of three successful Round Panels tests that meet the specification in Table
13 are required for each shotcrete mix.
k) The Contractor shall carry out such other tests and trials during the period of the field
trials as may be necessary, to confirm that proposed mixes and methods meet the
minimum performance requirements and particular mix requirements of this
Specification.
l)
The field trials shall be repeated if the source or qualities of any of the materials or the
mix proportions are required to be changed during the course of the Temporary and
Permanent Works.
m) For permanent quality shotcrete applications the durability of the sprayed concrete mix
shall be established by water permeability tests carried out on additional cores taken
from the panels
n) The Contractor shall provide 1,7,28 & 90 day strength verses time curves for cores
taken directly from the tunnel lining together with early strength results (less than 1 day)
for beam end test verses needle penetrometer tests
C:\APL-PBAJV\KIERAN.COOK\DMS47695\BC-PBA-GLTSP102-SPC-0001-103.DOC
BC-PBA-GLTSP102-SPC-0001-1-03
26 May 2010
Page 20
4.5
Submission Details
a) The Contractor shall submit details of each shotcrete mix design for approval to the
Construction Certifier at least 30 days prior to the commencement of shotcreting works.
The submission shall include, as a minimum, the following information:
I.
Mix Design
i.
The name of the concrete supplier and the proposed methods and degree of
quality control
ii.
iii. A copy of the Quarry Assessment Certificate for each material source
iv. Target strength
v.
Trial Mix
i.
ii.
vi. The degree of control required to achieve uniform shotcrete without excessive
rebound, sloughing, partial or total collapsing during shotcreting.
b) This constitutes a hold point for each different shotcrete mix used in the works covered
by this Specification.
4.6
Performance
Test Method or
Clause No
Shotcrete Type
S1
S2
S3
S4
P1
P2
P3
at 1 day +
AS 1012.14
8MPa
at 7 days*
(cored
samples)
Field trials
and
Production
Tests
(Cylinder)
at 1 day +
AS 1012.8.1
8MPa
N/A
8MPa
at 7 days*
AS1012.9
25MPa
N/A
25MPa
at 28 days
(cylinder
samples)
40MPa
25MPa
40MPa
at 28 days
at 90 days ++
at 90 days ++
N/A
8MPa
20MPa
N/A
20MPa
32MPa
25MPa
32MPa
32MPa
As above
32MPa
40MPa
40MPa
70MPa(1)
Page 21
Determinate Panels)
at 1.0mm deflection
ASTM
12 J
at 5.0mm deflection
C1550-03a
62 J
62 J
at 20mm deflection
211J
211J
at 40mm deflection
282J
282 J
Dry Density
[All tests at 28 days]
N/A
12 J
AS 1012.8
2150 to 2400kg/m
AS 1012.21
8% max
AS 1012.21
17% max
N/A
AS1012.13
N/A
850 microstrain
after 8 weeks
drying
DIN1048
Part 5
N/A
25mm
maximum
penetration
Fire Performance of P3
shotcrete
Maximum Strength is specified to avoid brittle failure of shotcrete. Exceptions may be approved on
a case by case basis through the RFI process.
Before the application of sprayed concrete, the excavated surfaces shall be scaled by
mechanical hydraulic hammers or high-pressure hydro scaling to remove loose rock or
scats or shall be cleaned with compressed air and, as far as the local conditions permit, with
an air-water mixture as necessary to remove all material which may prevent proper
C:\APL-PBAJV\KIERAN.COOK\DMS47695\BC-PBA-GLTSP102-SPC-0001-103.DOC
BC-PBA-GLTSP102-SPC-0001-1-03
26 May 2010
Page 22
adhesion of the sprayed concrete to the excavated surface. The surface to receive shotcrete
shall be damp and without free water prior to application of sprayed concrete.
Action shall be taken as necessary to control ground water and prevent it adversely
affecting the sprayed concrete lining. Water inflows which might cause deterioration of the
concrete, or prevent adherence, shall be diverted by channels, chases, pipes or other
appropriate means to the invert or to the ground water drainage system.
Where necessary, pressure relief holes shall be provided through the primary lining to
ensure that no hydrostatic pressure develops behind the lining.
5.2
a) Smoothing shotcrete shall conform to the general requirements of PSTS04 with respect
to material and workmanship.
b) The tunnel shotcrete smoothing layer shall be in accordance with Design Drawings and
generally as follows:
i.
ii.
Surfaces on which waterproofing systems will be installed shall be clean, free from
loose aggregate, sharp protrusions, projecting tying wire, release agents and other
substances which are likely to damage or affect the waterproofing system.
C:\APL-PBAJV\KIERAN.COOK\DMS47695\BC-PBA-GLTSP102-SPC-0001-103.DOC
BC-PBA-GLTSP102-SPC-0001-1-03
26 May 2010
Page 23
iv. Large circumferential irregularities shall not exceed 200 mm when measure from a
1.0 m curved edge held against the tunnel circumference.
v.
Any curvature or irregularity shall have a radius greater than 200 mm.
vi. The shotcrete shall be cured for at least 24 hours prior to membrane application.
vii. Steel elements, such as reinforcement bars, steel fibres, steel girders and the
heads of rock bolts (as far as not used to hold inner lining structures) shall be
covered with at least 20mm of shotcrete.
viii. Running water ingress shall be plugged prior to the final lining. Heavy water ingress
can be collected into half-pipes (or flexi-drain or strip-drains or similar), mounted by
nailing and led into the permanent drainage system. The mounted half-pipe should
be covered with at least 20mm of shotcrete prior to the initial temporary works
shotcrete lining installation.
ix. Where water is found to be penetrating through the shotcrete lining at a rate that
may adversely affect the installation of membrane, the water shall be collected by
means of hoses and drained to the tunnel invert. The drainage shall be maintained
during the membrane installation process so that no water pressure can develop
behind the membrane.
x.
xi. The shotcrete smoothing layer shall be completed using a maximum aggregate size
of 4mm unless it can be demonstrated that a coarser aggregate can achieve a
surface compatible with the membrane manufacturers recommendations.
Shotcrete surface shall be at least 28 days old prior to the application of spray
applied membranes.
Equipment
a) Only wet mix process equipment shall be used for Shotcrete Types, S1, S2, S3, S4, P1,
P2 and P3. Equipment for the wet mix process shall be set up according to the
recommendations of the manufacturer. Pumping equipment shall ensure the continuous
conveyance of shotcrete at a steady and quantifiable rate with minimal pulsation. The
equipment shall allow for air and water in any combination to be available for
preparation of surfaces and/or cleaning of finished work in accordance with this
Specification.
b) All equipment used for batching and mixing of materials, and the transport and
application of all types of shotcrete shall be of suitable design and shall be maintained
in proper working order for the duration of excavation and lining works. The shotcrete
gun and ancillary equipment shall be of an adequate capacity for the volumes to be
applied, and shall be manufactured from suitable materials compatible with the
proposed accelerators and additives. A stand-by shotcrete system of plant and ancillary
equipment shall be available for the duration of excavation operations to ensure
shotcrete is available at all times to stabilise all exposed excavation faces. Air for the
equipment is to be clean, dry and oil free and to be provided at the equipment at not
less than the operating pressure and volume rates specified by the manufacturer.
c) Shotcreting equipment shall be capable of feeding materials at a regular rate and
ejecting shotcrete from the nozzle at velocities that will allow adherence of the materials
to the surface being shotcreted with a minimum of rebound and maximum adhesion and
density.
d) Equipment shall be leak proof with respect to all materials.
C:\APL-PBAJV\KIERAN.COOK\DMS47695\BC-PBA-GLTSP102-SPC-0001-103.DOC
BC-PBA-GLTSP102-SPC-0001-1-03
26 May 2010
Page 24
e) Equipment shall be thoroughly cleaned at least once per shift, or more frequently at
appropriate intervals if hydration control admixtures are used, to prevent accumulations
of residual deposits and/or deterioration due to the accelerators used.
f)
Transport pipes consisting of hoses or pipes shall be laid straight or in gentle curves.
The transport pipes shall have a uniform diameter appropriate to the mix and fibre
characteristics determined by field trials, and be free of any dents or kinks between the
shotcrete machine and the nozzle.
g) Equipment shall allow application of shotcrete to all surfaces with the nozzle at the
distances from the surfaces to be sprayed in accordance with this Specification.
h) Working areas for shotcreting shall be well illuminated. Cap lamps attached to safety
helmets will not be accepted as sufficient illumination. Dust pollution shall be minimised
by choice of appropriate equipment and by means of additional ventilation, water
sprays, and by maintaining equipment in good order.
i)
j)
Dosing of admixtures by hand is not permitted. Each machine provided for the wet mix
process shall incorporate:
i.
ii.
As far as practicable all shotcrete shall be applied using remote controlled spraying
equipment appropriate to particular applications. Hand spraying of wet mix shotcrete is
permitted.
k) Remote controlled spraying equipment shall be provided with as long reach as possible.
This shall ensure that the operator can observe the nozzle at all times during spraying
from a position of safety under supported ground. The controls shall provide the
operator with full and effective control of the nozzle articulation and other functions. The
equipment shall be used, cleaned and maintained in accordance with the
manufacturer's instructions.
6.2
Proficiency of Nozzlemen
a) Nozzlemen shall have had previous experience and be proficient in the application of
shotcrete. Production shotcrete shall be applied only by nozzlemen who have
demonstrated their competence and their ability to produce either plain or steel fibre
reinforced shotcrete by the method to be used. Nozzlemen shall hold certificates of
competence issued by the Contractor Hold Point 2.
6.3
a) The individual components for the production of shotcrete shall be measured by weight
with an automatic batching device, except that admixtures may be measured by
volume. The batching accuracy shall be within 3% for all constituents except
admixtures (refer to Section 6.1.i.ii.). Silica fume shall be weighed separately. The
method of batching used shall ensure that the accuracy can be easily checked. All
measuring equipment shall be maintained in a clean and serviceable condition and shall
be zeroed daily and calibrated monthly.
b) Mixing shall be carried out in a mixer suitable for the efficient mixing and discharge of
wet batched materials.
C:\APL-PBAJV\KIERAN.COOK\DMS47695\BC-PBA-GLTSP102-SPC-0001-103.DOC
BC-PBA-GLTSP102-SPC-0001-1-03
26 May 2010
Page 25
c) Regular checks shall be made to ensure that complete mixing is routinely achieved.
Tests for mix consistency shall be in accordance with ASTM C94-04 or similar approved
international standard.
d) The addition of fibres shall be at a stage in the mixing suitable for the shotcreting
equipment. The procedure for the addition of fibres shall be determined during the field
trials. Fibres shall be added and mixed in a manner to avoid clumping and bending of
the fibres. Any fibre clumps in the mix shall be diverted and removed by means of a
screen placed over the shotcrete hopper. Fibres shall be uniformly distributed
throughout the mortar matrix without isolated concentrations. Fibres shall not be added
to the mix at a rate faster than that at which they can be blended with the other
ingredients without forming balls or clumps.
e) The mixed base concrete for the wet mix process shall be applied within one and a half
(1.5) hours of charging the mixer. This time may be extended by the use of retarders,
plasticisers or hydration control admixtures in accordance with this Specification.
f)
6.4
The base concrete for shotcrete produced by the wet mix process shall be transported
by truck mixers, concrete pumps or other suitable containers and shall prevent
segregation or possible loss or gain of water. Remixing of material shall not be
permitted, however, using a drop pipe to transfer the concrete from the surface
underground into an agitator truck is acceptable provided the material does not become
overly segregated and remixing produces a homogenous sprayable mix. The mixture
shall be effectively protected against any influence of the weather.
Application
The following requirements shall be achieved prior to and during the application of the
shotcrete:
a) Method statement and procedures have been submitted and approval has been given
by the Construction Certifier.
b) Checking and correction of the excavated cross section profile shall be carried out and
rock surfaces and/or existing shotcrete shall be cleaned with compressed air and, as far
as the local conditions permit, with an air-water mixture as necessary to remove all
material which may prevent proper adhesion of the shotcrete to the surface. The
surface to receive shotcrete shall be damp, but without free water prior to the
application of shotcrete. Treatment with an air-water mixture to ensure that the surface
is sufficiently clean and damp shall be done shortly before the application of shotcrete.
c) Action shall be taken to control groundwater and prevent it adversely affecting the
shotcrete lining. Adopted measures shall remain effective for at least 28 days. Water
inflows which might cause deterioration of the shotcrete, or prevent adherence, shall be
diverted as detailed on the Drawings, or otherwise proposed by the Contractor, by
channels, chases, pipes or other appropriate means, to the invert or to the temporary
groundwater drainage system.
d) Where necessary, pressure relief holes shall be provided through the primary lining to
ensure that no hydrostatic pressure develops behind the lining.
e) Ensure the thickness control devices are in place
f)
The distance between the nozzle and the surface to be shotcreted shall not exceed
1.8m for remote controlled spraying and 1.0m for hand spraying with the wet mix
process. The nozzle shall, as a general rule, be held perpendicular to the application
surface except as necessary to ensure proper embedment of steelwork such as lattice
girders where shown on the Drawings.
g) Depending on the required final thickness the application of steel fibre reinforced
shotcrete may be undertaken in two or more stages to minimise rebound, the first phase
being as stated on the Drawings.
C:\APL-PBAJV\KIERAN.COOK\DMS47695\BC-PBA-GLTSP102-SPC-0001-103.DOC
BC-PBA-GLTSP102-SPC-0001-1-03
26 May 2010
Page 26
h) Each layer of shotcrete shall be built up by making several passes of the nozzle over
the working area using good working practices and nozzle manipulation. The shotcrete
shall emerge from the nozzle in a steady uninterrupted flow. Should the flow become
intermittent for any cause the nozzleman shall direct it away from the work until it again
becomes constant.
i)
j)
No rebound material shall be covered with shotcrete. All rebound material shall be
removed from the working area and shall not be used in the Temporary and Permanent
Works. Disposal shall be undertaken with proper regard to the risks of environmental
pollution by both the cementitious materials and/or the admixtures.
k) For vertical and near vertical surfaces application shall commence at the bottom. Layer
thickness shall be governed mainly by the requirement that the material shall not sag.
Where thick layers are applied the top surface shall be maintained at a slope of
approximately 45 degrees. For overhead surfaces shotcrete shall preferably be applied
from the shoulder to the crown.
l)
Pockets, sags or other defects shall be cut out and resprayed. The area of respraying
shall not be less than 300mm x 300mm.
m) Unless specifically required and appropriate mixes designed, finishing actions, such as
trowelling or screeding, shall be avoided and may require remedial works to be
undertaken.
n) The temperature of the mix before spraying shall not be below 5C or above 35C
unless special provisions are made to the approval of the Construction Certifier.
Spraying shall not be undertaken when the ambient temperature is below 5C.
o) Sprayed concrete shall not be applied in the Temporary and Permanent Works until the
correct setting characteristics are observed during the start-up and a continuous
shotcrete stream is ejecting from the nozzle.
p) Where two layers of reinforcement are used, the far face reinforcement shall be covered
by sprayed concrete before the near layer is installed. The near layer shall be covered
by sprayed concrete up to the required thickness with the minimum delay.
6.5
a) Where specified on the Drawings the minimum layer thickness shall be controlled by
depth pins attached to the rock bolt plates or lattice girders. Depth pins shall be used at
a frequency of at least one marker per 5m2 sprayed area. Where not specified on the
Drawings suitable thickness control measures shall be implemented by the Contractor
Witness Point.
b) Steel sets and/or other embedded steelwork shall be embedded as specified on the
Drawings.
c) Control of the profile of the shotcrete lining as shown on the Drawings shall be by
manual or electronic means. Laser based equipment shall comply with all necessary
local health and safety legislation and shall be used in accordance with the
manufacturer's instructions.
d) The shotcrete thickness shall be determined by surveying the tunnel section before and
after shotcrete application at intervals along the tunnel of not more than 5 m separation.
e) Tolerances are to be in accordance with those specified on the Design Drawings.
C:\APL-PBAJV\KIERAN.COOK\DMS47695\BC-PBA-GLTSP102-SPC-0001-103.DOC
BC-PBA-GLTSP102-SPC-0001-1-03
26 May 2010
Page 27
6.6
Curing
a) All final surfaces of shotcrete Types S1, S2, S3, S4, P1, P2 and P3 need not be subject
to special measures unless the results of testing indicate that the performance
requirements of this Specification are not being consistently achieved and that such
underperformance is attributable to poor curing, in which case the Contractor shall
make a proposal for curing the shotcrete for acceptance by the Construction Certifier.
Shotcrete Testing
7.1
Production Tests
b) Tests shall be carried out on a routine basis on cores or other samples taken from
shotcrete placed in the tunnels and shafts, or from panels prepared for test purposes.
c) Specimens shall be tested in accordance with the following clauses. The tests shall be
carried out as specified in Table 14 for temporary and Table 15 for permanent shotcrete
lining.
d) The frequency of carrying out each production test on specimens taken from shotcrete
placed in the tunnels and shafts is given in the following Clauses of this Specification.
The dimensions of test specimens shall be as specified elsewhere in this Specification.
e) Where cores are to be taken from the tunnels and shafts, and where the nominal
required shotcrete thickness is less than 100mm the cores for compressive strength or
other testing requiring specimens longer than 100mm shall be taken from areas where
the actual thickness is greater than 100mm. Alternatively, additional shotcrete thickness
shall be applied in selected areas for subsequent coring of test specimens.
C:\APL-PBAJV\KIERAN.COOK\DMS47695\BC-PBA-GLTSP102-SPC-0001-103.DOC
BC-PBA-GLTSP102-SPC-0001-1-03
26 May 2010
Page 28
Test Method
Test Frequency
One (1) for every 100m3 sprayed shotcrete.
Compressive Strength
(cored sample)
Compressive Strength
(cylinder sample)
AS 1012.14
AS1012.8.1
AS1012.9
7day
28day
90day
For each 100m3 sprayed shotcrete three (3)
cylinder samples each for:
7day
28day
90day
Flexural
Toughness(Panels, SFRS
only)
ASTM C1550
AS 1012.12 and AS
1012.14
AS 1012.8
BS EN 14488.7
Slump
AS 1012.3 and AS
1379
C:\APL-PBAJV\KIERAN.COOK\DMS47695\BC-PBA-GLTSP102-SPC-0001-103.DOC
BC-PBA-GLTSP102-SPC-0001-1-03
26 May 2010
Page 29
Test Method
Test Frequency
One (1) for every 100m3 sprayed
shotcrete.
Compressive Strength
(cored sample)
Compressive Strength
(cylinder sample)
AS 1012.14
AS1012.8.1
AS1012.9
7day
28day
90day
For each 100m3 sprayed shotcrete three
(3) cores each for:
7day
28day
90day
Flexural Toughness(Panels,
SFRS only)
ASTM C1550
AS 1012.12 and AS
1012.14
AS 1012.8
AS 1012.21
BS EN 14488.7
Slump
Permeability
DIN1048
Shrinkage Strain
AS1012.13
3
Three (3) specimens for each 500m of
shotcrete
Flexural Strength
ASTM C 1609
Boiled Absorption
(permanent shotcrete only)
Fibre Content (SFRS only)
7.2
a) Compressive strength tests shall be carried out on prepared test cores of at least 75mm
diameter and with height: diameter ratio of 2:1 taken from shotcrete in the tunnels or
shafts, or from panels in accordance with AS 1012.14. For Permanent Works cores
shall only be taken from panels. The time of coring shall be not less than 20 hours after
placing. Cores required for 28 day strength tests and 90 day strength tests (when
required) shall be obtained at the same time as those for 1 and/or 7 day tests and
stored in the laboratory in accordance with AS 1012.14.
C:\APL-PBAJV\KIERAN.COOK\DMS47695\BC-PBA-GLTSP102-SPC-0001-103.DOC
BC-PBA-GLTSP102-SPC-0001-1-03
26 May 2010
Page 30
a) Tests to determine flexural toughness by the testing of round panels shall be carried out
in accordance with ASTM C1550.
b) Panels shall be clearly marked to identify the time, date and location of spraying. Panels
shall not be moved for 18 hours after spraying and shall be cured and protected.
c) Frequency of round panel testing shall be three (3) tests on panels (prepared from the
same shotcrete batch) for each 250 m3 of each Shotcrete Type S1 and P1 placed.
d) Shotcrete shall be acceptable if the results from round determinate panel toughness
testing are derived in accordance with ASTM C1550 and the results from at least 2 out
of 3 panels tested for each test exceed the minimum requirements of this Specification.
e) Samples for flexural toughness tests shall be taken from the same shotcrete as samples
for testing of steel fibre content (see Section 7.5). If four successive flexural toughness
tests demonstrate compliance with this Specification, and show a correlation with the
results of steel fibre content tests then, subject to approval of the Construction Certifier,
further testing for flexural toughness is not required.
7.4
a) Dry density, boiled absorption and voids volume shall be determined for shotcrete
sampled from the Temporary and Permanent Works. Material sampled for other
purposes may be used.
b) Shotcrete shall be acceptable if the average results for each test comply with the
specified requirements.
7.5
Fibre Content
Page 31
c) The shotcrete shall be acceptable if the average result of the three tests exceeds the
specified minimum requirements and no individual result is less than the specified
minimum by more than 20%.
7.6
Slump
a) The slump of Shotcrete Types S1, S2, S3, P1, P2 and P3 shall be measured in
accordance with AS 1012.3 and AS 1379 after the addition of fibre (where required) and
plasticiser to the required dosages.
b) Shotcrete shall be acceptable if the slump is within the range nominated for the
approved shotcrete mix design.
7.7
a) Tests on steel fibre shall be in accordance with ASTM A820-04 except that the cross
sectional area used to compute the tensile strength shall be calculated to four decimal
places, in units of square millimetres, and shall be:
i.
For drawn wire fibres, the area calculated from the actual diameter of the parent
source material or finished fibres
ii.
For cut sheet fibres, the area calculated from the actual thickness and width of the
parent source specimen, or if fibres are tested, the area of each individual fibre
calculated from the measured length and weight of the fibre, weighed to the nearest
0.0001 g, based on a density of 7,85 0kg/m3
iii. For melt-extraction fibres, the area calculated from the equivalent diameter of the
fibres, computed from measured average length and the weight of a known quantity
of fibres, based on a density 7,850 kg/m3
Repair of Shotcrete
8.1
General
a) Before repairing shotcrete, all test results as specified in Clause 7 shall be submitted for
approval unless where it is deemed by the Contractor the safety of the Works and
persons is endangered then shotcrete shall be repaired immediately Hold Point 3.
8.2
a) The core holes/reamed holes shall be cleaned thoroughly with all loose material or
material that otherwise has the potential to break away, scaled back and refilled with dry
pack mortar
General
C:\APL-PBAJV\KIERAN.COOK\DMS47695\BC-PBA-GLTSP102-SPC-0001-103.DOC
BC-PBA-GLTSP102-SPC-0001-1-03
26 May 2010
Page 32
Remove the defective shotcrete in strips or panels in such a way that the safety of
the Temporary and Permanent Works and persons is not endangered, and replace
with shotcrete that is acceptable, or;
ii.
a) If the strength requirements at 28 days are not met during the testing process, the
following actions are to be undertaken:
i.
ii.
The Contractor shall submit a remedial works proposal to the Construction Certifier
for review
vi. Repair the area by the method agreed with the Construction Certifier.
C:\APL-PBAJV\KIERAN.COOK\DMS47695\BC-PBA-GLTSP102-SPC-0001-103.DOC
BC-PBA-GLTSP102-SPC-0001-1-03
26 May 2010
Page 33
Appendix A
Verification Records
Appendix B
Response to Comments
EXTERNAL (IV,CNI,BC): WORK VERIFICATION RECORD - DESIGN REVIEW COMMENT, RESPONSE AND INCORPORATION RECORD
Date:
26/05/2010
Rating Impact
1 = high impact
2 = medium impact
WVR: GLTSP102VL16B
Shotcrete Lining
3 = Low impact
VL16B 1-01
No.
Name
Discipline
Area-Organisation
Document
Revision
Robert Burke
Geo/Tunnelling
IV
DCN 00047
BC-PBA-GLTSP102SPC
0001
Robert Burke
Geo/Tunnelling
IV
DCN 00047
BC-PBA-GLTSP102-
0001
No.
Name
Discipline
Area-Organisation
Document
Revision
Reference
BC-PBA-GLTSP102-SPC-0001
Section 5.3
Please detail who is to determine what remedial measures if any are required prior to
placement of shotcrete.
Section 5.3.1
It is unclear what is the maximum aggregate size for the smoothing layer as maximum
aggregate sizes detailed in ii and xi are different. Please clarify.
Reference
Rating
Impact
IV Status
TJH Comment
Designer response
The waterproofing supervisor has been added and reference
made to his responsibilities in accordance with specification
BC-PBA-GLTSP107-SPC-0001
Response
agreement
Incorporated
CLOSED
CLOSED
No.
Name
Andrew Axton
Discipline
Area-Organisation
Document
Revision
CNI
DCN 00047
BC-PBA-GLTSP102SPC
0001
Reference
Incorporated
Rating
Impact
IV Status
TJH Comment
Designer response
Response
agreement
Incorporation status
Rating
Impact
IV Status
TJH Comment
Designer response
Response
agreement
Incorporation status
No Comments
Incorporation status
N/A
With reference to the definition for silica fume concrete, is not known what
is meant by the statement 'care should be taken in the choice of
cementitious material to ensure that sufficient lime is available for reaction
with silica fume'. It is not evident why the requirements for lime quantities are
not defined within this specification. Please address this issue.
Incorporated
CLOSED
10
11
Andrew Axton
Andrew Axton
Andrew Axton
Andrew Axton
Andrew Axton
Andrew Axton
Andrew Axton
CNI
CNI
CNI
CNI
CNI
CNI
CNI
DCN 00047
BC-PBA-GLTSP102SPC
0001
DCN 00047
BC-PBA-GLTSP102SPC
0001
DCN 00047
BC-PBA-GLTSP102SPC
0001
DCN 00047
BC-PBA-GLTSP102SPC
0001
DCN 00047
BC-PBA-GLTSP102SPC
0001
DCN 00047
BC-PBA-GLTSP102SPC
0001
DCN 00047
BC-PBA-GLTSP102SPC
0001
It is noted that the text implies that dosages outside the manufactures
recommended dosage could be used. It is also noted that 10% dosage of
accelerator could have detrimental effects on the long term strength gain of
the shotcrete. Please address this issue.
Specification Section 3.10, Table It is noted that reference has been made to AS5100.5 with respect to
10
exposure classifications and maximum acid-soluble chloride ion contents.
Given that AS5100.5 only applies to concrete works, and noting that installed
shotcrete is different to cast-in-situ concrete, it is not evident if the durability
assessment, as required by Section 6.6.2 of Annexure 1 Part 1 of the
Performance Specification, has taken into account the performance criteria
of shotcrete to meet the durability requirements and the required Design Life
of the underground structure in the environment in which it is situated.
Please address this issue.
It is noted that the use of fly ash is not mandated in the shotcrete mix
requirements. It appears that specifications, whilst specifying performance
criteria, also need to take into consideration (and specify) durability criteria.
It is not evident that the fly ash content specified is consistent with the
durability report. Please address this issue.
It is noted a W/C ratio of 0.45 has been specified for permanent shotcrete. It
is not evident that the W/C ratio specified is consistent with the durability
report. Please address this issue.
CLOSED
It is noted that the text states that target slumps shall be determined by trial
mixes, but then goes on to specify the target slump. Please address this
discrepancy.
CLOSED
It is not evident with reference to the use of a drop pipe, what is meant by
'overly segregated', how this will be determined, and who will determine this.
Please address this issue.
Incorporated
CLOSED
Noted.
The issue of shotcrete durability is now addressed in Durability
Report which covers shotcrete. Shotcrete is concrete with the
method of placement being the only difference. A reference to
teh durabilty report has been added to the specififcation and
the following text added to section 1.1
Incorporated
CLOSED
N/A
CLOSED
N/A
Incorporated
N/A
CLOSED
N/A
OPEN
19-5-10 CLOSED
VL16B 1-02
No.
Name
Discipline
Area-Organisation
Document
Revision
Reference
Reviewer Comment
12
Andrew Axton
CNI
Report-General
It is not evident from the report whether the comments from the previous issue of this
DCN have been addressed. These comments were issued under TRIM ref: 10/18239
12 March 2010 (letter reference 10/20116). Please address this issue
13
Andrew Axton
CNI
It is noted that item (iii) and item (xi) contradict each other with respect to aggregate
size. Please address this discrepancy.
IV Status
*
Y
N
M
N/A
Means
Means
Means
Means
Means
Transmittal
Stage
Doc Number
Revision
Area
Element Title
Rating
Impact
IV Status
TJH Comment
Designer response
Response
Incorporation status
agreement
19-5-10 CLOSEDN/A
Conditional of
incorporation of
designer response
19-5-10 CLOSEDConditional of
incorporation of
N/A