You are on page 1of 4

white paper

Reining in your project controls


Introducing the project controller
New position separates project management duties, freeing project managers to focus on project
leadership and meeting strategic business objectives.

W
hen project Art vs science: the two facets of ‘planner’. Other organizations had this
management project management role perform on-going schedule
first entered Most professionals agree that project tracking and analysis, often using the
the business management skills can be divided into term ‘scheduler’. Responsibilities of
vernacular in two basic components, commonly tracking issue and risk logs, analyzing
the 1950s and referred to as the ‘art’ and ‘science’ of schedules, and facilitating all planning
early 1960s, early adopters of project project management. and status sessions were usually
management initiatives included the The primary segment of the project included in the role.
construction and utilities industries as manager’s work deals with the art, or More recently, responsibilities
well as major defence programmes. leadership, side of project manage- increased to include handling resource
These large, bureaucratic, command- ment. It demands vision, communi- allocations and constraints, schedule
and-control organizations focused on cation, negotiation, motivation, and and critical-path analysis, financial
project planning and controls and interpersonal skills. In this capacity, reporting of earned value, and providing
utilized tools such as Gantt charts, business acumen and knowledge of the other documentation sufficient to
network diagrams, and PERT. industry serve as a critical foundation. comply with regulatory requirements
Since then, countless new industry On the other hand, the science side such as the Sarbanes-Oxley Act.
trends have emerged. Organizations requires detailed knowledge of project Today, the role of project
have flattened out, matrixed management methodology and tools, coordinator, planner, and scheduler has
organizations have taken root, and new plus strong analytical and problem- evolved into that of ‘project
information technology has allowed solving skills. Here, the ability to controller’. The project controller
people to communicate more quickly gather data and communicate supports the project manager by
effectively and reduce cycle times status under pressure is critical. handling most of the critical, detail-
across all business processes. Because these two distinct skill sets oriented, analytical-focused, time-
As a result, management began are best provided by two very different intensive project tasks. As a result, the
pushing more projects onto an types of people, some organizations project manager is free to focus on
increasingly complex organization and have begun dividing the current set of more strategic project goals and
the project manager suddenly became responsibilities into two separate objectives, and often is even able to
the ‘Jack of all trades’ – forced to be positions: a project manager (which take on additional projects.
everything to everyone. The role of may include product managers and Best practice organizations look at
project manager is now very programme managers), and a project the project manager as the CEO of the
demanding, and requires an ever controller. project, and the project controller as the
expanding arsenal of skills, especially CFO – two roles that operate
‘soft’ or interpersonal skills. The emergence of the project independently of each other, yet are
Most recently, industry professionals controller role critical to the other’s success. The CEO
have noticed a powerful new trend The development of the project develops the overall vision and
sweeping the world of project controller position has been an provides leadership for the entire
management: the separation of duties evolutionary process. Initially, many organization. The CFO, on the other
within the project manager role. organizations created a position called hand, ensures the financial viability of
Specifically, many organizations are ‘coordinator’. The coordinator was the firm by following strict industry
taking the intensive planning and responsible for handling policies and procedures. Both the CEO
controls work from the project administrative tasks, entering data into and CFO lean on and trust the other to
manager and building these a timekeeping and scheduling system, achieve organizational goals. Like the
responsibilities into a formal project gathering status information, and CEO and CFO, both the project
controller position. helping to produce status charts. manager and project controller carry
Before delving into a detailed Over time, additional responsibilities out crucial duties, and both possess
explanation of this trend, it’s necessary – such as developing the initial significant albeit different skill sets and
to briefly review the existing position schedule and estimates – caused many responsibilities in order to bring the
of project manager. organizations to develop the role of projects in on time and under budget.
Reprinted by permission of PM Solutions. ‘Reining in your project controls’ White Paper. Copyright © 2004 by PM Solutions. All rights reserved.

10 PROJECT CONTROL PROFESSIONAL May 2007


Job responsibilities of the the project manager to help define the work schedules, and recommend and
project controller project’s goals and objectives, create and take action to improve progress. For a
The project controller is a key member of maintain a project’s budget and schedule, visual representation of how the two
the project team and works directly with analyze progress reported against the work in tandem, see Figure 1.

Figure 1: duties of the project manager versus the project controller


*PMBOK® Guide (A Guide to the Project Management Body of Knowledge) is a registered trademark of the Project Management Institute (PMI®), Inc.

PROJECT CONTROL PROFESSIONAL May 2007 11


needs; and meet with the project
manager to discuss project status.

5) Track and analyze costs


The project controller must work
with available accounting and project
management software tools to track
actual (or blended) costs, including
labour hours, equipment usage,
procured resources, etc. He or she
must also analyze cost run rates and
variations to extrapolate/forecast
total costs, as well as report findings
to the project manager, project office,
and any financial oversight
committee.

6) Manage issue, risk, and change


In order to ensure accurate planning sessions also fall within the control
documentation and reporting on a realm of the project controller’s role. The project controller ensures that
consistent basis, many organizations are These sessions may deal with a variety issues, risks, and change requests are
positioning the project manager and of topics such as planning, developing identified, analyzed and estimated, so
project controller as part of a centralized the work breakdown structure (WBS), they can be escalated to the
Project Support organization, usually developing the network diagram, appropriate levels of management for
referred to as the Project Management integrating the WBS and network disposition, and documented/tracked
Office (PMO) or the Project Office. diagram into the project schedule, in the project’s collaboration database.
Typically, the PMO reports to a high- estimating resource hours and task The project controller monitors issue,
level business executive who is durations, controlling issue/risk risk, and change request resolution
responsible for driving the business in management, capturing lessons dates; contacts team members listed as
his or her domain, whether they are the learned, and project reporting. responsible parties, for status and
CIO, VP of Operations, or head of New documentation; offers assistance to
Product Development. In today’s more 3) Develop the project schedule responsible parties to facilitate
regulated business world, these Using organizational project office progress and/or resolution meetings;
executives demand consistent and standards, the project controller works and provides the project manager with
reliable status reporting across all their with other key members of the team to the status of open issues, risks, and
projects. develop the project schedule, changes.
As a key contributor within the including resource levelling and
PMO, the project controller is critical path analysis. Once baselined, 7) Document and deliver status
responsible for carrying out the the schedule is used to measure work information
following functions, which provide progress, manage resource With new corporate governance
critical input into the project reporting assignments, track milestones, and standards for many organizations, the
process: monitor and report on project project controller is recognized as the
performance metrics. individual responsible for developing
1) Educate the team on proper earned value reports and presentation
processes 4) Control progress to ensure material for executive management.
The project controller educates and success Although the project manager is tasked
advises the team on project The project controller proactively with corporate communications, it’s
management policies and standards, ‘manages’ the schedule to ensure that the project controller who performs the
methodologies, and processes across the project is delivered on time. As part analysis and forecast and makes
all phases of the project: initiating, of this responsibility, the project recommendations.
planning, controlling, executing, and controller must: regularly collect task
closing. This includes describing the statuses and update the schedule; What makes a good project
processes’ purpose, utilizing analyze any variation or forecasted controller?
scheduling and costing tools, variation to the plan, emphasizing In order to efficiently handle the
determining who is responsible for items such as critical path, slipped responsibilities outlined above, the
deliverables, and detailing approval tasks, and upcoming tasks; calculate, successful project controller must
procedures. analyze, and present metrics such as possess technical expertise in project
earned value; manage resource management software, and related
2) Facilitate/oversee project assignments including submitting spreadsheet and/or database (financial,
planning/control sessions resource requests, monitoring current resource) tools; as well as business
Organizing and facilitating team allocations, and forecasting future process expertise in cost budgeting and

12 PROJECT CONTROL PROFESSIONAL May 2007


estimating, risk analysis, critical path
diagramming and analysis, resource
forecasting, and change control.
It’s important to note that the project
controller may be supporting several
projects simultaneously (based on
project size and work experience).
Therefore, he or she must also be
flexible in dealing with multiple
project managers, while maintaining
the required level of standards
demanded by the organization.

Getting executive buy-in: how


to build a successful business
case for project controllers
Corporate decision makers – not to
mention stockholders – keep a close
eye on all of their investments. The
first and foremost thing that executives
need to know about project
management is its ultimate impact and
value on their businesses. They may be
suspicious of any new expenses –
especially if the expenses include
expanding their project management
staff to include a new role. The key to
building a successful business case for
the project controller role is to educate
corporate decision makers about the
responsibilities of the new position,
and emphasize the positive impact that
it will have on the company.
Here are a few key points to include: project manager should be able to G Improve project performance
spend more quality time with and project success rates
G Strengthen communication with executives in explaining status, By delegating critical, yet time-
high-level executives gaining insight into political and consuming, tasks to a project
With the support of the project budgetary issues, and basically controller, project managers can focus
controller, project managers can share ‘selling’ the project. on higher-level project issues, while
vital information more regularly – project controllers can ensure that no
including financial reporting of earned G Boost staff motivation part of the project is missed or delayed
value and other documentation Many project managers are frustrated due to scheduling issues or
sufficient to comply with regulatory with the detailed tasks of project communications failures. This means
requirements such as the Sarbanes- planning and controls. They would that more projects will be completed
Oxley Act – without taking time away much prefer to deal with executives on on time and within budget – saving the
from other critical project areas. scope management issues, handle company the debilitating cost of
Executives will have a better high-risk issues, communicate status to project failures and project delays.
understanding and more control of the the organization, and work on other
projects and their financial high-visibility activities. Having a
implications, and decisions will be professional project controller reduces About PM Solutions
made in a more timely fashion. stress on the project manager and PM Solutions is a management consulting,
makes the job more enjoyable. training, and research firm dedicated to
G Leverage the project manager Similarly, most project controllers helping organizations improve project
and take on additional projects do not enjoy the ‘politics’ of project performance and profitability. For more
By utilizing the project controller management, and would prefer to deal information, call 610-853-3679 (USA) or
role, companies can leverage and with the tactical staffing and visit www.pmsolutions.com.
expand the capacity of project scheduling issues. This, to them, is less
managers to handle more projects stressful and more rewarding. Utilizing © 2004 Project Management Solutions Inc.
concurrently. This will enable the two people in these two roles of project All rights reserved.
organization to derive benefits more management motivates both parties to Reprinted in Project Control Professional
quickly than before. In addition, the perform their jobs well. by kind permission.

PROJECT CONTROL PROFESSIONAL May 2007 13