Professional Documents
Culture Documents
Risk
Ref.#
(Cause and
ProbabilityImpact
Matrix
Certain Not To
Happen
Somewhat
Unlikely
Slightly Unlikely
Unknown
Slightly
Likely
Somewhat
Likely
Prob
<5%
5-25%
25-40%
40-60%
60-75%
75-95%
>95%
Cost ($)
<250K
250 - 500K
500K - 2M
2-5M
>5 -7 M
7 - 10 M
Time (Days)
1 Week
1-2 weeks
2 weeks-1 months
1-2
months
Schedule
Impact
Rank
On-Time
Completion
Within
Budget
2 - 3 months 3 - 6 months
>10 M
>6 months
20 Minnesota Approach
Difficulty in constructing foundations due to
contaminated materials and remnant from the
energy plant, land fills site or other unknown
20.3 difficulties related to the Super Fund site that
may create environmental issues and cause
delays to project schedule and increase costs or
impact the environment.
Certain To Happen
30
30
Public/
Worker
Safety
Agency
Reputation
Protecting
Environment
10 Wisconsin Approach
Complications during construction of the drop
shaft on the Wisconsin bluff results in excessive
10.4 bluff disturbance, probable construction
modifications, delays, Agency friction and
compromisesWisDOT reputation.
20
25
18
31.2
28
18
16
1 of 2
Risk
Ref.#
(Cause and
ProbabilityImpact
Matrix
Certain Not To
Happen
Somewhat
Unlikely
Slightly Unlikely
Unknown
Slightly
Likely
Somewhat
Likely
Prob
<5%
5-25%
25-40%
40-60%
60-75%
75-95%
>95%
Cost ($)
<250K
250 - 500K
500K - 2M
2-5M
>5 -7 M
7 - 10 M
Time (Days)
1 Week
1-2 weeks
2 weeks-1 months
1-2
months
Schedule
Impact
Rank
On-Time
Completion
Within
Budget
2 - 3 months 3 - 6 months
>10 M
>6 months
20 Minnesota
Approach
130
Environmental
/ Permits
Presence of endangered species may impact the
construction of the bridge (during construction)
Certain To Happen
Public/
Worker
Safety
21
33
20
24
20
18
130.5
110.1
Agency
Reputation
Protecting
Environment
21
2 of 2