Professional Documents
Culture Documents
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
0
TRB 2011 Annual Meeting
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
ABSTRACT
The in-situ piezocone penetration test (PCPT) has been widely used by the geotechnical
engineering community for subsurface soil identification and classification, and for the
evaluation of many engineering soil properties, such as the consolidation parameters. The
PCPT-derived consolidation properties can be used to estimate the magnitude and time
rate of consolidation settlement of loaded soils. This paper presents a case study on
implementing the PCPT technology to evaluate the embankment settlement at the Juban
Road I12 Interchange Bridge in Louisiana. The soil underneath each embankment site
of the bridge was instrumented with a horizontal inclinometer and vertical magnet
extensometers. In each embankment site, PCPT tests were performed and the soundings
of cone tip resistance (qc) were used to estimate the constrained modulus (M) profiles
using Abu-Farsakh et al. interpretation methods. Dissipation tests were also conducted at
specified penetration depths and used to estimate the vertical coefficient of consolidation
(cv) using Teh and Houlsby interpretation method. Shelby tube soil samples were
collected and used to carry out a laboratory testing program to evaluate the consolidation
properties. The embankments consolidation settlements were monitored with time and
the field-measured values were compared with the magnitude and rate of settlements
estimated using parameters derived from PCPT data and laboratory consolidation tests.
The results of this study showed that the piezocone penetration and dissipation data
reasonably estimated the magnitude and rate of consolidation settlement of both
embankment sites. The back-calculated M and cv parameters from field measurements are
in good agreement with PCPT-derived values.
26
27
28
29
30
1
TRB 2011 Annual Meeting
INTRODUCTION
Saturated fine-grained soils, when loaded, can undergo large consolidation settlements
over a long period of time, which can pose potential damage to overlaying
infrastructures. The presence of this type of soil deposit is very common in southern
Louisiana. Therefore, the construction of embankments, bridge abutments, and other
structures on soft Louisiana soils requires a reasonable estimate of the magnitude and
time rate of consolidation settlement of the natural soil deposits in order to conduct a
rational and safe analysis and design of these structures. This requires better and more
accurate evaluation of the consolidation parameters of the subsurface soils.
The consolidation settlement of the soft soil underneath the embankment can cause
excessive differential settlement between the approach slab and bridge deck, creating
bump problems, faulting at the approach slab-pavement connection, and/or sudden
change in slope of the slab at the bridge deck. This can cause unsafe rideability, damage
to bridge decks, and costly frequent maintenance. In an attempt to solve this problem,
state Departments of Transportation (DOTs) usually preload the embankment site for a
certain period of time prior to the construction of approach slab and pavement. Additional
surcharge load and/or installation of vertical drains are sometimes used to accelerate the
settlement. The real challenge facing DOTs is to be able to reasonably estimate the
magnitude and time rate of consolidation settlement caused by embankment loading.
The consolidation properties of cohesive soils can be estimated from either
laboratory or in-situ tests. Laboratory tests, such as the one-dimensional Oedometer
consolidation tests, are conducted on small samples recovered from the site at different
depths. However, almost all recovered samples are subjected to certain degrees of
disturbance, which makes the laboratory-derived parameters not truly representative of
the actual in-situ conditions. Moreover, laboratory testing on small samples for
interbedded or fissured soils can be misleading. Profiling the consolidation characteristics
from laboratory tests on small samples taken from different depths can easily miss
significant thin drainage layers (1).
In-situ tests, such as the piezocone penetration tests (PCPT), can provide more
accurate and reliable results than laboratory tests in evaluating the actual strength and
consolidation properties of the soil under in-situ stress and drainage conditions. The
PCPT is a fast and economical in-situ test that can provide continuous soundings of
subsurface soil with depth. The piezocone penetrometer is capable of measuring the cone
tip resistance, qc, sleeve friction, fs, and pore pressures at different locations. These
measurements can be effectively used for soil identification and evaluation of different
soil properties such as the consolidation characteristics of soils.
The magnitude of consolidation settlement of cohesive soils can be estimated using
the deformation or constrained modulus (M), while the time rate of settlement is
estimated using the coefficients of consolidation (cv or ch). Different interpretation
methods have been proposed in the literature to estimate M from PCPT data (2, 3, 4, 5, 6,
and 7), derived based on direct correlation with the laboratory measured constrained
modulus. Many interpretation methods have also been developed to estimate the
horizontal coefficient of consolidation (ch) of cohesive soils from analyzing the
piezocone dissipation curves (e.g., 8 through 13). Some of these methods were based on
estimating the time for 50% dissipation (t50) (e.g., 8, 10, 12, and 13), some based on the
gradient of initial linear dissipation (e.g., 12), and others based on the rate of dissipation
2
at a given dissipation level (e.g., 10). The rigidity of the soil (Ir) was included in some
methods (12, 13). The vertical coefficient of consolidation (cv) can then be calculated
from ch using the relationship suggested by Levadoux and Baligh (11), which is based on
the ratio of vertical to horizontal coefficients of hydraulic conductivity (kv/kh) of the soils.
Several case studies were reported in the literature to estimate the consolidation
settlement of subsurface soils using parameters derived from the PCPT data (e.g., 6, 13,
14, and 15). Oakley (14) used the PCPT data to calculate the settlement of a chemically
stabilized landfill. He reported reasonable comparison between the calculated settlement
from PCPT data and the measured settlement, while the time rates of settlement were
within 50% of the actual field measurements. Crawford and Campanella (15) compared
the measured settlements of earth embankment with settlements calculated from the
laboratory consolidation test, PCPT test, and dilatometer test. Their findings showed
good agreement among the three methods, but the actual settlement was about 60%
greater than the average calculated value. The calculated rates of settlement were also
compared with the observed values. Kuo-Hsia et al. (16) compared the PCPT predicted
settlement with the measured settlement of an instrumented test embankment. They
reported that the PCPT was the most valuable basis for evaluating the constrained moduli
and hence calculating the total settlement of soft soils. Abu-Farsakh et al. (7) compared
the magnitude and time rate of consolidation settlements estimated using PCPT data and
laboratory consolidation parameters with the field measurements at three different sites.
They demonstrated that the PCPT can be used to reasonably predict the consolidation
settlement better than the laboratory calculated settlements.
This paper presents a case study on evaluating the embankment settlements at the
Juban RoadI12 Interchange Bridge in Louisiana. The soils underneath the embankments
on both sides of the bridge were instrumented with horizontal inclinometer and vertical
extensometers. The embankments settlements were monitored with time, and the field
measurements were compared with the magnitude and rate of settlements estimated using
parameters derived using the PCPT data and laboratory consolidation test parameters.
29
30
31
32
The total magnitude of consolidation settlement (Sc) of cohesive soils can be estimated
utilizing the PCPT data through evaluating the constrained modulus (M) using the
following equation (3):
i
Sc = Hi
(1)
M av i
33
34
35
36
37
38
39
40
where Hi is the thickness of soil layer i, i is the induced stress in mid of layer i, Mavi is
to voi
+ i estimated using
the average constrained modulus for stress range from voi
equation 2 as suggested by Senneset et al. (3):
M avi = M i
+ i / 2
voi
voi
(2)
2
3
4
5
6
7
8
9
The compressibility of the soils can be expressed by the constrained modulus (M) that
can be evaluated from PCPT. Several correlations have been proposed to estimate the
constrained modulus (M) from either the cone tip resistance (qc) or the corrected cone tip
resistance (qt). The corrected cone tip resistance (qt) is given by:
qt = qc + u2 (1- a)
(3)
where u2 is the pore water pressure measured behind the base, and a is the cone area ratio,
equal to 0.59 for both the 10 and 15 cm2 piezocones used in this study. The general
relationship between (qc or qt) and M can be expressed as follows:
10
11
12
13
14
15
16
M = . qc or M = . qt
(4)
Sanglerat (2) proposed a correlation between qc and M. He presented a
comprehensive array of values for different soil types with different qc values. Jones
and Rust (5) found that for South African alluvial clay, a value of = 2.75 0.55 can
provide good correlation between M and qc. Senneset et al. (3) conducted correlation
between M and qt. For clayey soils, they related the M modulus by a linear interpretation
of the net cone tip resistance (qn = qt - vo). They proposed the following relation:
17
M = . qn = . (qt - vo)
(5)
18
19
20
21
22
23
24
25
26
27
28
29
30
where = 105 for the pre-consolidation range and = 62 for the normally consolidated
range, and vo is the total overburden stress. Kulhawy and Mayne (4) also studied the
relationship between M and qn and found a good correlation with = 8.25.
Even though these relations might correlate well in some cases, local experience is
still essential to develop a better correlation between qt and M that can reflect the local
soil types and variations. To examine the possibility for obtaining better correlations, a
comprehensive study (6) was conducted on data collected from seven sites to reasonably
estimate the M values needed to calculate the consolidation settlement of cohesive soils
in Louisiana. In this study, the correlations were developed based on comparison between
the PCPT data and the reference M values obtained from the laboratory consolidation
tests. The following linear correlation was obtained between M and qt:
M = 3.15 qt (R2 = 0.91)
(6)
and the following linear correlation was also obtained between M and (qn):
31
32
33
34
35
36
37
38
39
40
41
The coefficients of consolidation (cv or ch) that is used to evaluate the rate of
consolidation settlement for cohesive soils can be estimated from the piezocone
dissipation test curves. The PCPT dissipation test consists of stopping the cone
penetration at pre-specified depths and recording the dissipation of excess pore pressure
(u) with time.
Several interpretation methods were developed to evaluate the horizontal coefficient
of consolidation (ch) of cohesive soils from analyzing the piezocone dissipation test data
4
curves, based on cavity expansion theories (e.g., 8, 9, 10), strain path method (11), and
the combination of the strain path method with the finite element technique (13). These
interpretation methods can be found in the corresponding references.
The most well-known interpretation method for estimating ch utilizing the piezocone
dissipation test was developed by Teh and Houlsby (13). They proposed the following
equation to estimate ch(piezo):
(8)
where T50* is a modified time factor at 50% dissipation ( T50* = 0.118 for the u1 piezocone
and 0.245 for the u2 piezocone), Ir = G/su is the rigidity index, G is the shear modulus,
and su is the undrained shear strength.. The shear modulus at 50% of yield stress (G50) is
usually used, which represents an average value of stress levels.
Since the dissipation of pore pressure occurs during the recompression range rather
than in the normal consolidation range, Levadoux and Baligh (11) suggested that the
predicted ch(piezo) = ch(overconsolidated) and they proposed the following relation to
transfer ch(piezo) to the normally consolidated condition ch(NC):
c h(NC) = ( RR / CR ) c h (piezo)
(9)
where RR and CR are the recompression and compression ratios, respectively. The
vertical coefficient of consolidation (cv) can then be calculated using the ratio of vertical
to horizontal coefficients of hydraulic conductivity (kv/kh) using the following expression
suggested by Levadoux and Baligh (11):
c v(NC) = (k v / k h )c h(NC)
(10)
22
23
24
25
26
27
28
29
In this study, Teh and Houlsby (11) method was used to evaluate the ch values of the
soil layers. In this method, the proper estimation of ch depends on the selection of an
appropriate value of the Ir= G/su index, and hence the G and su values. In this study, the su
values were estimated from the PCPT- qt data. The ko-anisotropic consolidated undrained
(CkoU) triaxial tests were conducted on selected Shelby tube samples obtained from soil
borings to estimate the G values for the soil layers. The average su value corresponding to
the same depth the sample was taken for triaxial test was used to calculate the Ir value
that represents each soil layer.
30
31
32
33
34
35
36
37
38
39
Boreholes were drilled in each embankment site and high quality 7.6 cm (3 in) standard
Shelby tube samples were recovered at different depths for comprehensive laboratory
testing. The laboratory testing program included basic soil characterization tests such as
water content, unit weight, Atterberg limits, grain size distribution, and specific gravity.
Computerized automatic one-dimensional consolidation tests were also conducted to
evaluate the constrained modulus (M), the coefficients of consolidation (cv and ch), the
OCR ratio, and the compression indices (cc and cr). Unconfined compression tests and koconsolidated undrained triaxial tests (CkoU) were also performed to estimate the
undrained shear strength (su) and the shear modulus (G) of the soils.
40
5
TRB 2011 Annual Meeting
2
3
4
5
6
7
8
9
10
11
12
13
14
The in-situ testing program included performing both piezocone penetration tests (PCPT)
and piezocone dissipation tests. The PCPT tests were performed in each embankment
using the 10 and 15 cm2, 60o piezocone penetrometers. All PCPT tests were conducted at
a penetration rate of 2 cm/sec. The 10 cm2 piezocone provided measurements of the cone
tip resistance (qc), sleeve friction (fs), and porewater pressure behind the base (u2). While
the 15 cm2 piezocone provided measurements of qc, fs, and porewater pressure at the cone
tip (u1). The profile of the PCPT tests was used to classify the soil using the probabilistic
region estimation method (17), evaluate the undrained shear strength (su), and evaluate
the constrained modulus (M) using Abu-Farsakh et al. (6, 7) interpretation methods.
The penetration of the piezocone was stopped at specified penetration depths to
perform dissipation tests with respect to time. The dissipation test curves were then used
to estimate the horizontal and vertical coefficients of consolidation (ch and cv) based on
the Teh and Houlsby (11) interpretation method.
15
16
17
18
19
20
21
22
23
The site includes both ramp embankments constructed for the Juban Road Interchange
Bridge at Interstate I-12, located east of Baton Rouge in Livingston Parish. This includes
the construction of two embankment approaches to the bridge, the north embankment,
and the south embankment. Figure 1 presents a typical roadway cross section of the
Juban Road embankments, which has a top width of 30.5 m (100 ft) and a varied bottom
width depending on the location from bridge end. The embankments on both sides of
bridge were instrumented with horizontal inclinometers and vertical extensometers to
monitor the consolidation settlement with time.
30.5 m (100 ft)
1:
1
Horizontal Inclinometer
:1
Geotextile Fabric
(Class C)
Soil Surcharge
1 of
its
m
Li icks
w
L
wi imit
ck s o
s
f
Finish Grade
61 cm (2') Nonpastic
Drainage Layer
10 cm (4") PVC
Drain Pipe
Wicks
Vertical
Extensometer
24
25
26
27
28
29
30
31
32
33
The north embankment has a top width of 30.5 m (100 ft), an average bottom width
of 96.3 m (316 ft), and an average height of 8.96 m (29.4 ft). The south embankment has
a top width of 30.5 m (100 ft), an average bottom width of 83.52 m (274 ft) and an
average height of 8.08 m (26.5 ft). A surcharge height of 0.91 m (3 ft) and wick drains
with a 1.83-m (6-ft) triangular spacing and 12.5 m (41 ft) depth were used to accelerate
the consolidation settlement. The construction of embankments fill including surcharge
was completed after 180 and 140 days for the north and south embankments,
respectively. The surcharge on both embankments was maintained for six months. It
6
should be noted here that the instrumentations used for measuring the embankments
settlement were installed at around the average dimensions of the embankments.
Two boreholes were drilled on each embankment site and high Shelby tube samples
were recovered for laboratory testing. The subsurface soil stratigraphy, as revealed from
the soil borings, showed that the site consists of a top soil layer of grey to brown lean
clay down to about 11 to 12 m with occasional traces of organics and/or sand. The Soil
below that consists mainly of silty and clayey sand interbedded with silty-clay layers
down to about 17 m at the south embankment site and 20 m at the north embankment site.
A layer of brown to grey stiff clay and silty clay down to 20 m exists at the south
embankment site. The groundwater level was about 2 m below the ground surface.
The results of laboratory tests on samples taken from the soil borings showed that the
natural water content was close to the plastic limit with a mean value of 25%. The
undrained shear strength, su, varied from 17 kPa to 177.5 kPa for the north embankment
site and from 40 kPa to 137 kPa for the south embankment site. The vertical coefficient
of consolidation (cv) was in the range of 1.36 x 10-4 cm2/sec to 9.6 x 10-3 cm2/sec. High
OCR (20 to 22) was observed in the top layer down to the depth of 2 m. The description
of the soil profile for the north embankment showing soil log, Atterberg limits, undrained
shear strengths, constrained modulus, coefficient of consolidation, and OCR are
presented in Figure 2. The soil profile and properties at the south embankment are close.
Four PCPT tests were conducted on the north embankment site and three PCPT tests
were conducted on the south embankment site, prior to the construction, down to 20 m
using either u1 or u2 measurements. The profiles of PCPT test results and the
corresponding CPT soil classification (17) for the north embankments are presented in
Figure 3. The PCPT data at the south embankment site are close. The CPT soil
classification indicates that the soil profile consists of silty clay soils down to about 10.5
m interbeded with thin sand layers. Two PCPT tests (with u1 measurement) were selected
to conduct dissipation tests on each embankment site. The depths of dissipation tests
were: 2.13, 4.02, 6.04, 7.80, 7.91, 9.83, 10.81, and 11.01 m below the ground surface for
the north embankment; and 2.13, 4.05, 6.03, 8.09, and 10.01 m for the south
embankment. Figure 4 depicts the results of dissipation tests.
One horizontal inclinometer was installed in each embankment at a selected location
to monitor the profile of consolidation settlement with time of the soil deposit underneath
each embankment. In this study, a digital horizontal inclinometer system manufactured
by RST Instruments Ltd. was used, which consists of inclinometer casing, a horizontal
probe, control cable, pull cable, and a readout unit. A 0.61 m wide 0.61 m deep trench
was first excavated across each embankments width prior to the placement of any
embankment fill. The inclinometer casing of 85 mm (3.34 in) diameter and the return
pipe were then installed along the trench (Figure 5). The trench was then filled with sand
and compacted by the contractor. Each end of the inclinometer casing was attached to
two wooden posts to secure its position. The settlement survey was conducted by drawing
the probe from one end of the casing to the other, halted in its travel at 2 ft intervals for
inclination measurements. The elevations of posts relative to a reference fixed point were
measured every time using a survey level device. The first survey was conducted after
sand compaction to establish the initial profile of the casing (as baseline survey). The
subsequent surveys revealed the changes in the profile due to embankment settlement.
7
Soil Type
0 20 40 60 80 100 0
Su (kPa)
Cv (c
cm2/sec)
Modulus M (MPa)
50 100 15
50 200 0
2
4
6
81E-004 1E
E-003 1E-002 0
0
1
12
16
6
7
8
Depth (m)
9
10
11
24
Brown and Gray Clay
28
Brown Clay
Brown and Gray Clay
w/ TR ORG
32
36
12
13
20
PL
LL
mc
Depth (ft)
OCR
5 10 15 20 25
40
44
14
Gray Clay
48
15
16
17
18
19
3
4
4
5
10
11
12
13
14
52
Silty
56
60
w/ TR Conc
64
w/TR ORG
20
P
profilles and soil classificatioon for north
h embankmeent site
Figure 3. PCPT
O set of vertical magnnet extensom
One
meter was installed at eaach embankm
ment site neaar
the loocation of th
he horizontaal inclinometer to measuure the settlement in eaach soil layer.
s
consiists of one datum
d
magneet fixed at thhe bottom off the boreholle, seven rinng
The system
(spider) magnets that slide onn a 2.54 cm diameter veertical pvc pipe and one plate magneet
at thee ground surrface. The magnets
m
werre installed in
i a boreholle at pre-speecified depthhs
8
6.0
2.13 m
4.02 m
7.80 m
10.81 m
7.91 m
9.83 m
6.04 m
9
10
11
12
13
14
15
16
5.0
4.0
2.13 m
3.0
2.0
1.0
11.01 m
10.01 m
8.09 m
6.03m
6
4.05 m
0.0
10
11
12
13
14
15
10
100
1000
0
Time (sec)
10000
100000
10
1
100
1000
10000
10000
00
Time (sec)
(a)
( North siite
b) South site
(b
Figure 4. Dissipatiion tests at Juban
J
Road
d I-12 emb
bankment sites
16
9
TRB 2011 Annual Meeting
3
4
5
The profiles of PCPT soundings with depth and the results of piezocone dissipation tests
were used to calculate the consolidation parameters: constrained modulus (M) and
coefficients of consolidation (ch and cv) of subsurface soils for each embankment site.
6
7
8
9
10
11
12
13
14
15
Constrained Modulus
The profiles of constrained modulus (M) was calculated from PCPT using Abu-Farsakh
et al. (6, 7) methods based on corrected qt or net qn cone tip resistance (equations 6 and
7). The average values of total overburden pressure (vo) needed for each soil layer to
compute the qn were estimated from the soil borings. The comparison of predicted M
values from PCPT versus the laboratory measured M are presented in Figure 6 for both
north and south embankment sites. It is evident from the figure that the PCPT-M values
for both sites are greater than the laboratory estimated M values. Comparison with backcalculated values from field measurements for the south embankment site will be
presented later.
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
Coefficient of Consolidation
The horizontal coefficients of consolidation (ch) for the subsurface soils were calculated
from the piezocone dissipation tests presented in Figure 4 using the Teh and Houlsby (13)
interpretation method (equations 8 and 9). This method requires the evaluation of t50 from
the dissipation test curves. The vertical coefficients of consolidation (cv) can then be
calculated from ch using the relationship proposed by Levadoux and Baligh (11) in
equation 10, which is based on the kv/kh ratio. However, in this study the cv /ch ratio was
estimated to be about 0.56 from the results of one-dimensional consolidation tests
conducted on samples oriented both vertically and horizontally. By investigating the
figures, the reader can distinguish two different types of dissipation curves: Monotonic
dissipation curves (A Type I) and dilatory dissipation curves (Type III) (18, 19). Type I
curve shows a gradual decrease of excess pore pressure with time, and is usually obtained
in normally and lightly over-consolidated soils (19). The Type III curve is usually
obtained for pore pressure measurements behind the tip (u2 and u3) in overconsolidated
soils. This is mainly due to the dilatory behavior of overconsolidated soils (18), and
partially due to the redistribution of excess pore pressure around the cone at early stages
of dissipation before it dissipates to the surrounding media. Sully et al. (19) evaluated the
Type III dissipation curve and suggested applying certain correction by evaluating the
time tp at peak as the new zero time and the corresponding pore pressure is taken as the
peak initial excess pore pressure for the dissipation curve. This approach was used in this
study. To calculate the rigidity index (Ir = G/su), the undrained shear strength was
estimated from the cone tip resistance data using the cone tip factor, Nk = 15, and the
shear modulus (G) was determined from CkoU triaxial tests.
The plots of piezocone estimated versus laboratory calculated cv values are presented
in Figure 7 for the Juban road embankments. Although the figure do not show good
correlation between the PCPT and laboratory cv values, it is obvious that the subsurface
cohesive soil at Juban road site has a cv value ranges from 210-2 to 410-3 cm2/sec, with
an average of 110-3 cm2/sec.
10
100
150
200
250
300
400
0
0
Constraints Modulus (M)
M = 3.58 (qt- vo)
50
100
150
300
350
400
20
250
10
200
0
2
Measured
Depth (m)
10
20
30
10
30
10
SANDY LAYER
12
40
SANDY LAYER
14
12
SANDY LAYER
14
SANDY LAYER
40
50
16
50
16
18
60
20
18
60
20
1
2
10
15
20
25
30
35
40
10
15
20
25
30
35
40
100
150
200
250
300
350
400
50
100
150
300
350
400
4
20
250
10
200
0
2
Measured
Depth (m)
0
0
10
20
8
30
10
30
10
SANDY LAYER
SANDY LAYER
12
40
14
40
SANDY LAYER
14
SANDY LAYER
50
SANDY LAYER
16
12
60
20
50
SANDY LAYER
16
18
Depth (ft)
18
60
20
0
3
4
Depth (ft)
10
15
20
25
30
35
40
10
15
20
25
30
35
40
11
TRB 2011 Annual Meeting
PCPT cv (cm2/sec)
10-2
Eq
ui
ty
North Embankment
South Embankment
Li
ne
10-1
10-3
10-4
10
-5
10-5
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
10-3
10-2
10-1
Laboratory cv (cm2/sec)
1
2
3
10-4
(11)
where, Uv, Ur are the average degree of consolidation due to vertical and radial (or
horizontal) drainage, respectively. In this study, the radial consolidation was estimated to
contribute to about 85%-88% of the total consolidation settlement of the embankments.
The settlement profiles along the width of the embankment calculated using the
PCPT interpretation method, laboratory-estimated parameters, and the settlement
measured using the horizontal inclinometer are presented in Figures 8a and 8b for north
and south embankments, respectively. The comparison in the figures was made at a time
corresponds to about 95% of the estimated consolidation. For the north embankment site,
the PCPT over-estimated the measured (actual) settlement by about 12% and the
laboratory parameters under-estimated the measured settlement by about 13%. However,
for the south embankment site, the PCPT and the laboratory parameters over-estimated
the field measurements by about 50% and 20%, respectively. This is in agreement with
12
findings from previous studies (7, 13, 14, and 15), which demonstrated the difficulty of
predicting the actual field settlements using either PCPT or laboratory derived
parameters. However, being able to estimate the magnitude of settlement using the PCPT
data within the same range as the laboratory estimate will have a potential benefit in
speeding up the construction and avoiding delays.
0
10
20
30
40
Distance (m)
50
60
70
80
90
100
2
4
10
14
HI Measurements
6
7
Lab Estimate
16
PCPT Estimate
18
20
360
8
0
6
7
12
40
80
120
160
200
Distance (ft)
240
280
Settlement (cm)
Settlement (Inches)
H = 32.4 ft
320
10
20
30
Distance (m)
40
50
60
70
80
90
Settlement (Inches)
1
2
3
4
5
Settlements at 260 days
HI Measurement
Lab Estimate
PCPTEstimate
9
0
40
80
120
160
200
Distance (ft)
240
280
0
2
4
6
8
10
12
14
16
18
20
22
Settlement (cm)
H = 29.5 ft
320
8
9
10
11
12
13
14
15
0
Settlement with Time
Settlement (inches)
HI Measurements
Laboratory
PCPT
10
Settlement (cm)
1
2
3
4
5
6
12
14
6
0
30
60
7
8
Days
North Embankment
0
0
Settlement with Time
HI Measurement
Laboratory
PCPT
10
Settlement (cm)
Settlement (inches)
12
14
6
0
9
10
11
30
60
90
120
150
180
210
240
270
Days
12
13
14
15
16
17
Measurements from the vertical magnet extensometer were used to back-calculate the
consolidation parameters (M and cv) of the subsurface soil layers for the south
embankment site. As mentioned earlier, the vertical extensometer for the north site was
damaged during construction. By recording the relative movement of spider magnets, the
corresponding vertical settlement of each layer was calculated for each incremental stress
14
20
40
60
80
100
1.0E-004
0
1.0E-003
1.0E-002
1.0E-001
4
2
8
12
Depth (m)
2
8
12
16
6
20
16
20
Depth (ft)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
24
24
28
28
Constraints Modulus (M)
Back-calculated
Lab Measured
10
32
M = 3.58(qt-vo)
12
2
10
32
Back-Calculated
Lab Measured
Teh and Houlsby
36
M = 3.15 qt
Cv (cm2/sec)
10
12
1E-004
1E-003
1E-002
1E-001
Coefficient of consolidation Cv
36
1E+000
(cm2/sec)
15
16
17
18
19
CONCLUSIONS
20
21
22
23
24
25
26
This paper presents a case study on evaluating the embankment settlement at the Juban
Road I-12 Interchange Bridge in Louisiana. The soil underneath each embankment was
instrumented with a horizontal inclinometer and vertical magnet extensometers to
monitor the settlement with time. Piezocone penetration and dissipation tests were used
to calculate the consolidation parameters (M and cv), which were then used to evaluate
the magnitude and time rate of embankment settlements. Laboratory tests were also
conducted to estimate the consolidation properties of soils from borings. Settlement
15
TRB 2011 Annual Meeting
calculated using PCPT and laboratory derived consolidation parameters were compared
with actual field measurements. Based on this study, the following conclusions can be
drawn:
Actual field measurements from horizontal inclinometers were compared with the
consolidation settlements estimated using the PCPT and laboratory derived
parameters. The results, in general, showed that the piezocone penetration and
dissipation data can be used to estimate the magnitude and time rate of consolidation
settlement of embankments within the same range as of the laboratory calculations.
The settlement predictions based on PCPT derived constrained modulus (M) using the
Abu-farsakh et al. (6, 7) method reasonably estimated the magnitude of consolidation
settlement of Juban Road embankments within the same range as of the laboratory
calculations. Performing the PCPT tests is much faster compared to the timeconsuming of sampling and subsequent laboratory testing of soil samples, thus the
use of PCPT will help in speeding up the field construction.
The PCPT estimation of rate of consolidation with time from dissipation tests using
the Teh and Houlsby (13) interpretation method matched fairly well the field
monitoring of the north embankment site, while it under-estimated the rate of
consolidation of the south embankment site. However, the PCPT gave a little better
estimate of the rate of consolidation than the laboratory estimations.
Back-calculated constrained modulus from vertical magnet extensometers were
compared with PCPT and laboratory derived M. The results showed that the PCPT
estimated M values are in good agreement with back-calculated values. The
laboratory estimated M values are lower.
Comparison of the cv values estimated from dissipation tests using the Teh and
Houlsby (13) method with the back-calculated and laboratory measured cv values
showed reasonable agreement among all and that most cv values fall within a narrow
range of an order of magnitude of one log cycle.
28
ACKNOWLEDGMENT
This research project is funded by the Louisiana Department of Transportation and
Development (State Project No. 736-00-0781) and the Louisiana Transportation Research
Center (LTRC Project No. 00-3GT). The comments and suggestions of Mark Morvant,
Associate Director of Research at LTRC, are gratefully acknowledged.
29
REFERENCES
30
31
32
33
34
35
36
37
38
1.
2.
3.
4.
5.