Unit 3&4
MES - TSW WIND SPEED MONITORING Ref : EB-STM-SF0004
JOINT OPERATION PROCEDURE Date : 18 Nov 2009
Rev. :0
Table of Content
I. General..................................................................................................... 2
II. Scope........................................................................................................ 2
III. Objectives................................................................................................. 2
IV. Reference.................................................................................................. 2
V. Equipments/Tools ................................................................................... 3
1
Project : TJB Exp. Unit 3&4
MES - TSW WIND SPEED MONITORING Ref : EB-STM-SF0004
JOINT OPERATION PROCEDURE Date : 18 Nov 2009
Rev. :0
2
Project : TJB Exp. Unit 3&4
MES - TSW WIND SPEED MONITORING Ref : EB-STM-SF0004
JOINT OPERATION PROCEDURE Date : 18 Nov 2009
Rev. :0
3
Project : TJB Exp. Unit 3&4
MES - TSW WIND SPEED MONITORING Ref : EB-STM-SF0004
JOINT OPERATION PROCEDURE Date : 18 Nov 2009
Rev. :0
4
Project : TJB Exp. Unit 3&4
MES - TSW WIND SPEED MONITORING Ref : EB-STM-SF0004
JOINT OPERATION PROCEDURE Date : 18 Nov 2009
Rev. :0
I. General
a. Wind speed will be potential hazard for lifting, rigging, and at
height activities when exceeding the safe limit. In order to carry out those
activities safely, wind speed need to be monitored to make sure it in safe limit.
5
Project : TJB Exp. Unit 3&4
MES - TSW WIND SPEED MONITORING Ref : EB-STM-SF0004
JOINT OPERATION PROCEDURE Date : 18 Nov 2009
Rev. :0
II. Scope
a. This procedure shall be in effect to MES-TSW JO and subcontractors for
lifting, rigging, and at height activities carried out on shore.
6
Project : TJB Exp. Unit 3&4
MES - TSW WIND SPEED MONITORING Ref : EB-STM-SF0004
JOINT OPERATION PROCEDURE Date : 18 Nov 2009
Rev. :0
b. This procedure is not in effect to barge operation, since barge operation has
its own procedure.
III. Objectives
3.1 To define the safe limit of wind speed for lifting, rigging, and working at
height with reference to an acceptable standard.
7
Project : TJB Exp. Unit 3&4
MES - TSW WIND SPEED MONITORING Ref : EB-STM-SF0004
JOINT OPERATION PROCEDURE Date : 18 Nov 2009
Rev. :0
IV. Reference
8
Project : TJB Exp. Unit 3&4
MES - TSW WIND SPEED MONITORING Ref : EB-STM-SF0004
JOINT OPERATION PROCEDURE Date : 18 Nov 2009
Rev. :0
Wind speed limit for lifting, rigging, and at height activities is 10 m/s or 20 knots.
It means that wind speed below 10 m/s is safe for the said activities. Wind speed
10 m/s or more is not safe for those activities.
9
Project : TJB Exp. Unit 3&4
MES - TSW WIND SPEED MONITORING Ref : EB-STM-SF0004
JOINT OPERATION PROCEDURE Date : 18 Nov 2009
Rev. :0
V. Equipments/Tools
a. Manual Anemometer with scale of m/s.
b. Siren with sound capacity to cover work area.
c. Anemometer and siren shall be located in two places:
1. in a post near boiler area
2. in a post near coal yard area
10
Project : TJB Exp. Unit 3&4
MES - TSW WIND SPEED MONITORING Ref : EB-STM-SF0004
JOINT OPERATION PROCEDURE Date : 18 Nov 2009
Rev. :0
11
Project : TJB Exp. Unit 3&4
MES - TSW WIND SPEED MONITORING Ref : EB-STM-SF0004
JOINT OPERATION PROCEDURE Date : 18 Nov 2009
Rev. :0
12
Project : TJB Exp. Unit 3&4
MES - TSW WIND SPEED MONITORING Ref : EB-STM-SF0004
JOINT OPERATION PROCEDURE Date : 18 Nov 2009
Rev. :0
13
Project : TJB Exp. Unit 3&4
MES - TSW WIND SPEED MONITORING Ref : EB-STM-SF0004
JOINT OPERATION PROCEDURE Date : 18 Nov 2009
Rev. :0
14
Project : TJB Exp. Unit 3&4
MES - TSW WIND SPEED MONITORING Ref : EB-STM-SF0004
JOINT OPERATION PROCEDURE Date : 18 Nov 2009
Rev. :0
15
Project : TJB Exp. Unit 3&4
MES - TSW WIND SPEED MONITORING Ref : EB-STM-SF0004
JOINT OPERATION PROCEDURE Date : 18 Nov 2009
Rev. :0
X. Resume Work
a. In condition high wind over, personnel in charge must take a measurement. If
the results shows that the wind speed below 10 m/s, personnel in charge sound
the siren one time to inform all lifting, rigging, at height activities may resume
work.
b. When Supervisor hearing the siren, he shall instruct to resume work.
16
Project : TJB Exp. Unit 3&4
MES - TSW WIND SPEED MONITORING Ref : EB-STM-SF0004
JOINT OPERATION PROCEDURE Date : 18 Nov 2009
Rev. :0
17
Project : TJB Exp. Unit 3&4
MES - TSW WIND SPEED MONITORING Ref : EB-STM-SF0004
JOINT OPERATION PROCEDURE Date : 18 Nov 2009
Rev. :0
18
Project : TJB Exp. Unit 3&4
MES - TSW WIND SPEED MONITORING Ref : EB-STM-SF0004
JOINT OPERATION PROCEDURE Date : 18 Nov 2009
Rev. :0
19
Project : TJB Exp. Unit 3&4
MES - TSW WIND SPEED MONITORING Ref : EB-STM-SF0004
JOINT OPERATION PROCEDURE Date : 18 Nov 2009
Rev. :0
20
Project : TJB Exp. Unit 3&4
MES - TSW WIND SPEED MONITORING Ref : EB-STM-SF0004
JOINT OPERATION PROCEDURE Date : 18 Nov 2009
Rev. :0
16.00-17.00 PM
17.00-18.00 PM
18.00-19.00 PM
19.00-20.00 PM
20.00-21.00 PM
21