Professional Documents
Culture Documents
Quay Street
Granite kerbing, placement of
services and the placement of the
new
concrete
pavement
foundation has been completed in
this area.
Granite paving is due to
commence in this area following
the Christmas embargo.
Abbey Street
Completed sections of paving
have been laid along the Castle
Park side of Abbey Street.
Feature paving in the sections
currently
not
paved
is
programmed for commencement
January 2015.
Paving continues to be laid past
the DRD and Translink car parks
and is programmed for completion
th
week commencing 10 November.
Main Street
Works have commenced adjacent
to the Post Office and will continue
in this vicinity up to the 21st
November.
Access to the Post office and all
other trading businesses will be
maintained throughout as will
access to the controlled and
uncontrolled pedestrian crossings
in this area.
UPCOMING WORKS
Abbey Street
Excavation, placement of services,
placement of kerbs and concrete
pavement foundation is due to
commence between Translinks
Terminal and Dufferin Avenue
rd
week commencing 03 November.
Bingham Street
Excavation, placement of services,
placement of kerbs and concrete
pavement foundation is due to
continue from Flawless Nails
towards
High
Street
week
rd
commencing 03 November.
Paving is due to commence week
th
commencing 24 November, and
continue through the Christmas
embargo.
King Street
Excavation, placement of services,
placement of kerbs and concrete
pavement foundation is due to
th
commence week commencing 10
November, and continue through
the Christmas embargo.
Dufferin Avenue
Excavation, diversionary works to
BT, placement of services,
placement of kerbs and concrete
pavement foundation is due to
commence on the North side
th
week commencing 24 November.
Paving is due to commence week
th
commencing 24 November on
the South side and upon
completion move directly to the
north side.
All works will continue through the
Christmas embargo.
Market Street
Excavation, placement of services,
placement of kerbs and concrete
pavement foundation is due to
th
commence week commencing 24
November, and continue through
the Christmas embargo.
Central Avenue
Excavation, placement of services,
placement of kerbs and concrete
pavement foundation is due to
commence during the Christmas
embargo.
Those traders affected will be contacted
by the contractor prior to works
commencing.
We would like to thank all the businesses,
residents
and
shoppers
for
their
understanding and cooperation as the