Professional Documents
Culture Documents
Submitted by:
SURAAJ S.CHARANKAR.
OMKAR A.MUKADAM.
[BE MECHANICAL]
LOKMANYA TILAK COLLEGE OF ENGINEERING
2004-05
LITERATURE SURVEY
The following are the world class technique adopted in industries for
their
business solutions:
All at once
Each in turn
5
each hat-round are noted on-line with background of the colour of the
hat to give visual indication of the type of thoughts required.
Generally, Six Thinking Hats meeting does not last more than one
hour. The subject which takes three to four hours of meeting time,
gets resolved within a hour, as there is no argument. Parallel thinking
is like Parallel working which saves a lot of time.
2) VALUE ENGINEERING
The origin of VE:
The credit for the origin of Value Engineering (VE) goes to Lawrence
Miles who, in the 1940s was a purchase engineer with the General
Electric Company (GEC).
It was World War II and the US manufacturing industry was running at
maximum capacity to supply the allies with arms. There were
shortages in raw materials and components like steel, copper,
bronze, nickel, bearings etc. GEC wished to expand its production of
turbo supercharger for B24 bombers from 50 to 1000 per week. Miles
was assigned the task of purchasing the materials to permit this.
Due to the competition for raw materials, products, personnel, and
other resources in a time of war. Miles developed a procedure for
procuring, designing, and using the raw material and components,
using functions as its basis.
His reasoning was, if I cannot obtain the product, I must obtain
an alternative which performs the same function. Miles found
that he could more readily obtain what he needed if he used his new
procedure, rather than specifying standard designed components.
Miles observed that many of the substitutes were providing equal or
better performance at a lower cost. He called the procedure Value
Analysis. The term Value Engineering was coined in 1960s, following
the implementation of the concept in US government organisations.
ii.
10
iv.
11
worthwhile ideas are converted into clear proposals. Also called the
judicial phase or development phase.
7. Evaluation phase The proposals evolved in the last phase are
studied from the financial angle and relative cost both initial and
recurring for the life of the project or team. A comparison and
grading on the basis of both technical aspects and financial
benefits/costs are completed in this phase.
8. Recommendation or presentation phase The team then orally
present their recommendations and findings to all the parties
concerned, especially the top management/decision making levels.
Extensive use is made use of audio-visual aids; models and graphic
presentation should be immediately followed up by a written report
seeking decisions from the management.
9. Implementation phase- Indicates the period when all efforts are
developed to the implementation of the accepted proposals, including
solving of problems faced, if any.
10.
Feedback
and
collateral
application
The
results
13
3) SIX SIGMA
Six Sigma is one of the latest improvement methodologies sweeping
across the business landscape and being adopted by major
corporations and institutions.
Firms are dedicating approximately 2% of their employees full time to
conduct thousands of Six Sigma project implementations per year,
resulting in hundreds of millions of dollars of actual bottom line annual
results from reduced cost and increased revenue. The remainders of
a companys employees (Green Belts) work 10-15% of their time on
Six Sigma projects. The Six Sigma method is well defined and
audited, so it is unlikely that project implementations will deviate from
the proven methodology by being supplanted by other existing
methodologies. However, there are significant opportunities to
improve project implementation by infusing elements of Value
Management (VM).
When a company makes the commitment to become a Six Sigma
Company, it typically drives implementation of Six Sigma at all levels
and in all aspects of its operations. Due to this intense commitment
and total involvement, Six Sigma becomes the way they do their
work. Before any activity is planned, these companies posit How
can we use Six Sigma for this activity? These companies do not first
14
15
DEFINE (D)
MEASURE (M)
ANALYSE (A)
IMPROVE (I)
CONTROL ( C )
The Six Sigma "job plan" consists of five phases: Define, Measure,
Analyze, Improve and Control. Typically each phase takes about
one month to execute, for a total project execution of approximately 5
months. A Six Sigma conducts all of these phases with occasional
input or assistance from a team.
At the macro level, each of these phases answers the following
questions:
Define: What is important to the customer?
Measure: What is our current performance versus what is
important to the customer?
Analyze: What causes variations from the target?
16
Sigma Level
Defect Rate
(PPM)
Yield In %
6
5
3.4
233
99.99966
99.9767
World Class
4
3
6,210
66,807
99.3790
93.3193
Industry Average
2
1
308,537
690,000
69.1462
-----------
Non-Competitive
17
Competitive
Level