Uong Bi 300MW Extension Power Plant Goshu Kohsan Co., Ltd.
M4/5/6 Water and Wastewater Treatment
Pre-Com and Commissioning Manual Page 1 of 71 09 Jan., 06 Rev. A PRE-COMMISSIONING AND COMMISSIONING MANUAL
1. GENERAL
This manual covers the general requirements for the Pre-Commissioning and Commissioning Works of Water and Wastewater Treatment Plants for Uong Bi 300MW Extension Power Plant, under the EPC contractor Vietnam Machinery Erection Corporation (LILAMA), which consists of Raw Water Treatment System, Demineralization System, Wastewater Treatment Plant, and Domestic Wastewater Treatment Plant. These works shall commence after the completion of installation work.
Uong Bi 300MW Extension Power Plant Goshu Kohsan Co., Ltd. M4/5/6 Water and Wastewater Treatment Pre-Com and Commissioning Manual Page 2 of 71 09 Jan., 06 Rev. A 2. PRE-COMMISSIONING
The purpose of pre-commissioning work is to check the actual condition of the plant and to perform necessary adjustments on the equipments in preparation for the commissioning work.
Mechanical Equipment Pre-Commissioning includes the following steps: 1. Flushing and Cleaning 2. Chemical Preparation 3. Filter Media Loading 4. Resin Loading 5. Oil Interceptor Check 6. Trial Run
Electrical & Instrument Equipment Pre-Commissioning includes the following steps: 1. MCC Power Energize 2. MCC Function Test 3. Motor No-Load Test 4. On-Off Valve Loop Test 5. Instrument Loop Test 6. System Function Test 7. Input-Output Test 8. Sequence Test
Uong Bi 300MW Extension Power Plant Goshu Kohsan Co., Ltd. M4/5/6 Water and Wastewater Treatment Pre-Com and Commissioning Manual Page 3 of 71 09 Jan., 06 Rev. A 2.1. MECHANICAL EQUIPMENT PRE-COMMISSIONING
1. FLUSHING and CLEANING Flush inside of pipe with water for few minutes until effluent is clear. Open valves slowly to flush all dirt, debris, excess sealant and scale. Clean inner surface of filters and exchanger vessels.
2. CHEMICAL PREPARATION
Pre-caution: 1. Person who prepares harmful or dusty chemicals should wear suitable protective equipment. 2. Training and advises shall be given to workers in order to understand the cause of harm that would occur while working with chemicals. Method of prevention and measures to be used in tending to the accident should be explained clearly to the workers. 3. Provide water for cleaning within the place of preparation. 4. Consider which chemical uses service water for dilution, and which one uses filtered water.
Preparation: 1. Alum is prepared as per the following procedure; 1.1. Coagulation dissolving tank (10GBN10BB001) Fill the tank with filtered water until half of required level H Load 255.5 kg/day of alum (flake) into the tank via electrical hoist manually Further fill the tank with filtered water until required level H = 1,600 mm Start Agitator (10GBN10AM001) for 1 hour or until alum is dissolved 1.2. Coagulation Feed Tank (10GBN10BB002) Open On-off valve (10GBN10AA301) manually from local SVB to transfer dissolved alum at 10% concentration into feed tank by gravity. 1.3. Illustration M H COAGULATION DISSOLVING TANK (10GBN10BB001) COAGULATION FEED TANK (10GBN10BB002) 10GBN10AA301 COAGULATION FEED PUMP 1A/B (10GBN11/12AP001) CLARIFIER TANK A (10UGE11BB001) COAGULATION DISSOLVING TANK AGITATOR (10GBN10AM001) ALUM 10%
Uong Bi 300MW Extension Power Plant Goshu Kohsan Co., Ltd. M4/5/6 Water and Wastewater Treatment Pre-Com and Commissioning Manual Page 4 of 71 09 Jan., 06 Rev. A 2. Sodium Hypochlorite is loaded by 8% NaOCl Tank Truck into NaOCl Tank (10GBN20BB001). Automatic feeding operation shall be referred to Functional Logic Description in Appendix C. 3. Polymer is prepared in the Polymer Preparing Unit (10GBN30BB001) as per the following procedure: Manually load polymer (flake) into the Polymer Powder Hopper (10GBN30AF001) Automatic feeding and mixing operation shall be referred to Functional Logic Description in Appendix C, to produce polymer 0.05% solution. 4. Hydrochloric Acid is loaded by a 30% HCl Tank Truck into HCl Tank (10GCN10BB001). Automatic feeding operation shall be referred to Functional Logic Description in Appendix C. 5. Sodium Hydroxide is loaded by 50% NaOH Tank Truck into NaOH Tank (10GCN20BB001). Automatic feeding operation shall be referred to Functional Logic Description in Appendix C. 6. Table 1 shows the list of chemicals and specification to be prepared for this project.
Table 1: List of Chemical to be Prepared: No Chemical Name Form Percent Specific Gravity 1 Alum Flake 14% Al 2 (SO 4 ) 3 1.72 2 Polymer (C-3310) Liquid 0.05% ~ 1.0 3 Sodium Hypochlorite: NaOCl Liquid 8% 1.2 4 Sodium Hydroxide: NaOH Liquid 50% (45%) 1.53 (1.48) 5 Hydrochloric Acid: HCl Liquid 30% 1.15
3. FILTER MEDIA LOADING
Precautions: 1. Open manholes and check that inner equipment has no damage. 2. Confirm leakage in nozzle and sight glass by filling water into the vessel and check leakage. If no leaks were found, perform cleaning and flushing of vessel. 3. Confirm that there is no undesirable matter in the vessel. 4. Confirm the size and quantity of filter media. 5. Arrange and distinguish each kind of filter media.
Procedure: 1. Care shall be taken to load media into the filter. Avoid direct pouring of media from the top manhole as inner paint could be severely damaged. 2. After each layer of media is loaded, the top surface shall be spread evenly and smoothly by forking or any other means as to prevent leading through of media. After spreading, check elevation. 3. Type of filter media top layer shall depend on media classification. Quantity of media shall conform to the spec. 4. After loading, inspect inside of vessel. Take out foreign matter and contaminants. Properly seal the top manhole. 5. Backwashing of media shall be carried out to remove any floating defective media. 6. Media to be loaded are listed in Table 2. Uong Bi 300MW Extension Power Plant Goshu Kohsan Co., Ltd. M4/5/6 Water and Wastewater Treatment Pre-Com and Commissioning Manual Page 5 of 71 09 Jan., 06 Rev. A Table 2: List of Filter Media: NO VESSEL TO BE LOADED KKS NO FILTER MEDIA QUANTITY 1 Auto Gravity Filter 10GBB11/12AT001 Gravel 5.04 m 3
Sand 7.56 m 3
2 A/C Filter (Potable) 10GBB20AT001 Gravel 0.48 m 3
Activated Carbon 0.90 m 3
3 A/C Filter (Demin) A/B 10GCB11/12AT001 Gravel 1.2 m 3
Activated Carbon 2.34 m 3
4 A/C Filter (WWTP) 10GNB10AT001 Gravel 1.92 m 3
Activated Carbon 3.78 m 3
4. RESIN LOADING
Precautions: 1. It is important to cross check the resin volumes loaded into each vessel. Record the actual resin level in delivery form after backwashing and settling. 2. A careful measurement of the freeboard (in delivery form) should be made, reported, and checked with the original design. If necessary, corrective action should be undertaken to either load resin or download some. 3. Whenever possible, avoid the direct contact of the active resin with the nozzles. 4. Resins to be loaded are listed in Table 3.
Procedure: 1. Remove the top head of the vessel and top nozzle plate. 2. Fill 1/3 of the vessel with water. Loading resin into water ensures that any air and dirt are floated off the resin and come out to the surface of the water. This will allow the resin bed to sit evenly & homogeneously throughout the height of column. 3. Load the active resin as per the specified quantity. 4. Load inert resin as per the specified quantity. 5. Close the top head of the vessel.
Table 3: List of Resin: NO VESSEL TO BE LOADED VESSEL TAG NO RESIN QUANTITY 1 Cation Exchanger A/B 10GCF11/12AT001 Dowex Mono C-600 1,725 Liters Dowex IF-62 150 Liters 2 Anion Exchanger A/B 10GCF21/22AT001 Dowex Mono A-500 2,225 Liters Dowex IF-62 225 Liters 3 M/B Exchanger A/B 10GCF31/32AT001 Dowex Marathon C 375 Liters Dowex Marathon A 475 Liters
5. OIL INTERCEPTOR CHECK
5.1. Make sure that all internal equipments are in place and no tools or other loose items are left in the interceptor. 5.2. With the automatic closure device in oil chamber feed, fill all interceptor compartments with clear water to the outlet level. 5.3. Check that the stainless steel automatic device follows the level of the water. Uong Bi 300MW Extension Power Plant Goshu Kohsan Co., Ltd. M4/5/6 Water and Wastewater Treatment Pre-Com and Commissioning Manual Page 6 of 71 09 Jan., 06 Rev. A 6. TRIAL RUN
General: The following equipments shall undergo trial run to demonstrate that they can operate safely and satisfactorily under the required operating conditions. 1. Clarifier tank A/B (RWTS) 2. Gravity filter A/B Manual backwash Auto backwash 3. Demin Train A A/C filter A (Demin) soaking Manual regeneration Auto regeneration 4. Demin Train B A/C filter B (Demin) soaking Manual regeneration Auto regeneration 5. Clarifier tank (WWTP) 6. Sludge receiver tank 7. A/C filter (WWTP) Soaking Manual backwash Auto backwash
Manual Backwash: It is very essential to perform manual backwash operation on each of Auto Gravity and Carbon Filters before operating to auto-mode so that foreign particle present in the media during delivery are washed out from the vessel. In this operation, preliminary adjustments of manual & actuator-operated valves, instrument set points, flowrate, etc. should also be done.
Auto Backwash: When all necessary adjustments are completed, it is important to perform a trial run in auto mode for one cycle before performing the commissioning proper in order to counter-check the adjustments made. Final adjustments shall be done after one cycle, when necessary. Operation is the same as the commissioning operation (Refer to the section COMMISSIONING).
Activated Carbon Soaking: Activated carbon is filled with internal pores where air may exist. Before backwashing, bed must be set in completely submerged condition to allow carbon pores to fill with water. Otherwise, the reduced density of carbon due to air in the pores may result in excessive backwash losses.
Manual Regeneration: It is very essential to first perform manual regeneration and backwashing before setting to auto- mode so that preliminary adjustments in the plant can be done; such as manual and actuator- operated valves adjustment, instruments set points, flowrate adjustment, chemical dosing adjustment, etc. This is also essential for the resin in order to wash away foreign particles present during delivery. This step shall prepare the correct ionic exchanging capacity of resin. Manual regeneration literally means regeneration of each step of every unit in manual operation.
Uong Bi 300MW Extension Power Plant Goshu Kohsan Co., Ltd. M4/5/6 Water and Wastewater Treatment Pre-Com and Commissioning Manual Page 7 of 71 09 Jan., 06 Rev. A Automatic Regeneration: When all necessary adjustments and preparations are completed, it is important to perform a trial run in auto mode for one cycle before performing the commissioning proper in order to counter-check the adjustments made. Final adjustments shall be made after one cycle, when necessary. Operation is the same as the commissioning operation (Refer to the section COMMISSIONING).
Initial Resin Regeneration: Irrespective of the form delivered, the resin bed should receive at least a double amount of regenerant compared to the design level. This means a double-injection-time only, while displacement and rinse should be performed as per original design.
First Run: Expected high water quality will be achieved only after final rinsing, after Mixed Bed Exchanger in the case of Demineralizer, but provided that endpoint is monitored correctly and the plant is not overrun.
Procedure: A. Manual and Auto Backwash Operation 1. Set following pumps & blowers to manual mode operation in MCC and Local Control Panel; Freshwater Supply Pump (10GAF10AP001) Backwash Water Pumps A/B (10GBK11/12AP001) Air Blowers A/B (10GBC11/12AN001) Filtered Water Transfer Pumps A/B (10GBK41/42AP001) Demin Feed Pumps A/B (10GCK11/12AP001) Clarified Water Transfer Pumps A/B (10GNK31/32AP001) Backwash Pumps A/B (10GNK61/62AP001) 2. Set all actuator-operated valves used in Auto Gravity and Carbon filtering process into manual mode operation in the Local Control Panel. 3. Perform manual preliminary washing in each filter in order to wash away foreign particles present in the media during delivery until the effluent is clear. 4. Perform manual backwash operation in accordance with the Operation Chart and Sequence of Auto Gravity and Carbon Filters, and P&ID. 5. Make necessary adjustments in order to meet the required water quality. 6. Perform backwash operation again, this time in auto backwash operation. 7. Make final adjustments as required.
B. Manual and Auto Regeneration Operation 1. Set the following pumps and blowers into manual mode operation in the MCC and Local Control Panel; Demin Feed Pumps A/B (10GCK11/12AP001) Booster Pumps A/B (10GCK21/22AP001) Regeneration Pumps A/B (10GCK31/32AP001) Degasifier Blowers A/B (10GCH11/12AN001) HCl Feed Pumps A/B (10GCN11/12AP001) NaOH Feed Pumps A/B (10GCN21/22AP001) 2. Set all actuator-operated valves used in Demineralizer into manual mode operation in the Local Control Panel. Uong Bi 300MW Extension Power Plant Goshu Kohsan Co., Ltd. M4/5/6 Water and Wastewater Treatment
Pre-Com and Commissioning Manual Page 8 of 71 09 Jan., 06 Rev. A 3. Perform manual regeneration of Demineralizer in accordance with Operation Chart and Sequence of Demineralization Train A & B by train and P&ID, sequentially as follows; A/C Filters A/B (10GCB11/12AT001) Cation Exchangers A/B (10GCF11/12AT001) Degasifier Tower & Sump A/B (GCH11/12AW001 & GCH11/12BB001) Anion Exchangers A/B (10GCF21/22AT001) Mixed Bed Exchangers A/B (10GCF31/32AT001) 4. Make necessary adjustments in order to meet the required water quality. 5. Perform regeneration operation again, this time in auto mode regeneration. 6. Make final adjustments, as necessary.
Uong Bi 300MW Extension Power Plant Goshu Kohsan Co., Ltd. M4/5/6 Water and Wastewater Treatment
Pre-Com and Commissioning Manual Page 9 of 71 09 Jan., 06 Rev. A FILTER BACKWASH WATER PIT (10UGH10BB001) FRESHWATER PUMP HOUSE STATION AUTO-GRAVITY FILTER (10GBB11/12AT001) 10GBD11/12AA301 CLARIFIER TANK A (10UGE11BB001) 10GAC21AA001 10GAC21QP001 M CLARIFIER TANK A AGITATOR (10GBD11AM001) NaOH FEED PUMP (10GBN41/42AP001) POLYMER FEED PUMP (10GBN31AP001) COAGULATION FEED PUMP (10GBN11/12AP001) pH QT TRIAL RUN PACKAGE M4:
Steps of Clarifier Tank A (UGE11BB001) Trial Run:
1.) Fill Water Purpose: To supply raw water from Freshwater pond to Clarifier A (RWTS) Operation: Receive freshwater from Freshwater pump house station Open Control valve (10GAC21AA001) manually from local SVB Start Chemical feed pumps simultaneously with raw water flow in manual operation o Coagulation feed pump 1A/B (10GBN11/12AP001) o NaOH feed pump 2A/B (10GBN41/42AP001) o Polymer feed pump 1A/B (10GBN31AP001) Flow rate: 106.5 m 3 /hr Duration: Until water level is 100mm below overflow line, then close control valve and stop chemical feed pumps Illustration:
Uong Bi 300MW Extension Power Plant Goshu Kohsan Co., Ltd. M4/5/6 Water and Wastewater Treatment
Pre-Com and Commissioning Manual Page 10 of 71 09 Jan., 06 Rev. A FILTER BACKWASH WATER PIT (10UGH10BB001) FRESHWATER PUMP HOUSE STATION AUTO-GRAVITY FILTER (10GBB11/12AT001) 10GBD11/12AA301 CLARIFIER TANK A (10UGE11BB001) 10GAC21AA001 10GAC21QP001 M CLARIFIER TANK A AGITATOR (10GBD11AM001) NaOH FEED PUMP (10GBN41/42AP001) POLYMER FEED PUMP (10GBN31AP001) COAGULATION FEED PUMP (10GBN11/12AP001) pH QT 2.) Agitation Purpose: To create disturbance inside Clarifier to enhance coagulation and flocculation Operation: Start Clarifier tank A agitator (10GBD11AM001) manually from LOP Duration: ~2 hours or until floc is formed (Note: Agitation continues until shutdown.) Illustration:
Uong Bi 300MW Extension Power Plant Goshu Kohsan Co., Ltd. M4/5/6 Water and Wastewater Treatment
Pre-Com and Commissioning Manual Page 11 of 71 09 Jan., 06 Rev. A FILTER BACKWASH WATER PIT (10UGH10BB001) FRESHWATER PUMP HOUSE STATION AUTO-GRAVITY FILTER (10GBB11/12AT001) 10GBD11/12AA301 CLARIFIER TANK A (10UGE11BB001) 10GAC21AA001 10GAC21QP00 1 M CLARIFIER TANK A AGITATOR (10GBD11AM001) NaOH FEED PUMP (10GBN41/42AP001) POLYMER FEED PUMP (10GBN31AP001) COAGULATION FEED PUMP (10GBN11/12AP001) pH QT 3.) Start Operation Purpose: To further receive freshwater from Freshwater pump house station Operation: Open Control valve (10GAC21AA001) manually from local SVB Flow rate: 50% of 106.5 m 3 /hr until sludge blanket is 500 mm lower than overflow 100% of 106.5 m 3 /hr Duration: Continues operation Illustration:
Uong Bi 300MW Extension Power Plant Goshu Kohsan Co., Ltd. M4/5/6 Water and Wastewater Treatment
Pre-Com and Commissioning Manual Page 12 of 71 09 Jan., 06 Rev. A AUTO-GRAVITY FILTER A/B (10GBB11/12AT001) CLARIFIER TANK A/B (10UGE11/12BB001) 10GBB11/12AA301 10GBB11/12AA302 FILTERED WATER PIT (10UGG10BB001) BACKWASH WATER PUMP (GBK11/12AP001) AIR BLOWER (10GBC11/12AN001) 10GBB11/12AA303 10GBB11/12AA306 10GBB11/12AA304 10GBB11/12AA305 FILTER BACKWASH WATER PIT (10UGH10BB001) Steps of Auto-Gravity Filter A/B (10GBB11/12AT001) Manual Preliminary Operation:
1.) Washing Purpose: To wash away foreign particles from gravel in preparation for the filter operation Operation: Open On-off valve (10GBB11/12AA301) manually from local SVB Open On-off valve (10GBB11/12AA305) manually from local SVB Other On-off valves are closed Flow rate: 105 m 3 /hr Duration: Until effluent is clear Illustration:
Uong Bi 300MW Extension Power Plant Goshu Kohsan Co., Ltd. M4/5/6 Water and Wastewater Treatment
Pre-Com and Commissioning Manual Page 13 of 71 09 Jan., 06 Rev. A AUTO-GRAVITY FILTER A/B (10GBB11/12AT001) CLARIFIER TANK A/B (10UGE11/12BB001) 10GBB11/12AA301 10GBB11/12AA302 FILTERED WATER PIT (10UGG10BB001) BACKWASH WATER PUMP (GBK11/12AP001) AIR BLOWER (10GBC11/12AN001) 10GBB11/12AA303 10GBB11/12AA306 10GBB11/12AA304 10GBB11/12AA305 FILTER BACKWASH WATER PIT (10UGH10BB001) FILTERED WATER TANK (10GBL10BB001) 2.) Service Purpose: To produce filtered water Operation: Keep On-off valve (10GBB11/12AA301) open Close On-off valve (10GBB11/12AA305) manually from local SVB Open On-off valve (10GBB11/12AA302) manually from local SVB Other On-off valves are closed Start Filtered water pump A/B (10GBK31/32AP001) manually from LOP when water level in Filtered water pit (10UGG10BB001) is at desired level Flow rate: 105 m 3 /hr Duration: Until water level in Filtered Water Tank is 1/3 of height Illustration:
Uong Bi 300MW Extension Power Plant Goshu Kohsan Co., Ltd. M4/5/6 Water and Wastewater Treatment
Pre-Com and Commissioning Manual Page 14 of 71 09 Jan., 06 Rev. A AUTO-GRAVITY FILTER A/B (10GBB11/12AT001) CLARIFIER TANK A/B (10UGE11/12BB001) 10GBB11/12AA301 10GBB11/12AA302 FILTERED WATER PIT (10UGG10BB001) BACKWASH WATER PUMP (GBK11/12AP001) AIR BLOWER (10GBC11/12AN001) 10GBB11/12AA303 10GBB11/12AA306 10GBB11/12AA304 10GBB11/12AA305 FILTER BACKWASH WATER PIT (10UGH10BB001) Steps of Auto-Gravity Filter A/B (10GBB11/12AT001) Manual Backwash Operation:
1.) Water Drain Purpose: To reduce water level in vessel to prevent overflowing of media Operation: Open On-off valve (10GBB11/12AA304) manually from local SVB Other On-off valves are closed Flow rate: 0 m 3 /hr Duration: 10 minutes Illustration:
Uong Bi 300MW Extension Power Plant Goshu Kohsan Co., Ltd. M4/5/6 Water and Wastewater Treatment
Pre-Com and Commissioning Manual Page 15 of 71 09 Jan., 06 Rev. A AUTO-GRAVITY FILTER A/B (10GBB11/12AT001) CLARIFIER TANK A/B (10UGE11/12BB001) 10GBB11/12AA301 10GBB11/12AA302 FILTERED WATER PIT (10UGG10BB001) BACKWASH WATER PUMP (GBK11/12AP001) AIR BLOWER (10GBC11/12AN001) 10GBB11/12AA303 10GBB11/12AA306 10GBB11/12AA304 10GBB11/12AA305 FILTER BACKWASH WATER PIT (10UGH10BB001) 2.) Air Backwash Purpose: To polish the media to remove foreign particles that attached to the media Operation: Keep On-off valve (10GBB11/12AA304) open Start Air blower A/B (10GBC11/12AN001) manually from LOP Open On-off valve (10GBB11/12AA306) manually from local SVB Other On-off valves are closed Flow rate: 12.6 Nm 3 /min Duration: 10 minutes Illustration:
Uong Bi 300MW Extension Power Plant Goshu Kohsan Co., Ltd. M4/5/6 Water and Wastewater Treatment
Pre-Com and Commissioning Manual Page 16 of 71 09 Jan., 06 Rev. A AUTO-GRAVITY FILTER A/B (10GBB11/12AT001) CLARIFIER TANK A/B (10UGE11/12BB001) 10GBB11/12AA301 10GBB11/12AA302 FILTERED WATER PIT (10UGG10BB001) BACKWASH WATER PUMP (GBK11/12AP001) AIR BLOWER (10GBC11/12AN001) 10GBB11/12AA303 10GBB11/12AA306 10GBB11/12AA304 10GBB11/12AA305 FILTER BACKWASH WATER PIT (10UGH10BB001) 3.) Water Backwash Purpose: To remove foreign particles detached from the media out of the vessel Operation: Keep On-off valve (10GBB11/12AA304) open Close On-off valve (10GBB11/12AA3046) manually from local SVB Stop Air blower A/B (10GBC11/12AN001) manually from LOP Start B/W water pump A/B (10GBK11/12AP001) manually from LOP Open On-off valve (10GBB11/12AA303) manually from local SVB Other On-off valves are closed Flow rate: 500 m 3 /hr Duration: 10 minutes Illustration:
Uong Bi 300MW Extension Power Plant Goshu Kohsan Co., Ltd. M4/5/6 Water and Wastewater Treatment
Pre-Com and Commissioning Manual Page 17 of 71 09 Jan., 06 Rev. A AUTO-GRAVITY FILTER A/B (10GBB11/12AT001) CLARIFIER TANK A/B (10UGE11/12BB001) 10GBB11/12AA301 10GBB11/12AA302 FILTERED WATER PIT (10UGG10BB001) BACKWASH WATER PUMP (GBK11/12AP001) AIR BLOWER (10GBC11/12AN001) 10GBB11/12AA303 10GBB11/12AA306 10GBB11/12AA304 10GBB11/12AA305 FILTER BACKWASH WATER PIT (10UGH10BB001) 4.) Stop Purpose: To remove foreign particles detached from the media out of the vessel Operation: Close On-off valve (10GBB11/12AA304) manually from local SVB Stop B/W water pump A/B (10GBK11/12AP001) manually from LOP Close On-off valve (10GBB11/12AA303) manually from local SVB Other On-off valves are closed Flow rate: 0 m 3 /hr Duration: 10 minutes Illustration:
Uong Bi 300MW Extension Power Plant Goshu Kohsan Co., Ltd. M4/5/6 Water and Wastewater Treatment
Pre-Com and Commissioning Manual Page 18 of 71 09 Jan., 06 Rev. A AUTO-GRAVITY FILTER A/B (10GBB11/12AT001) CLARIFIER TANK A/B (10UGE11/12BB001) 10GBB11/12AA301 10GBB11/12AA302 FILTERED WATER PIT (10UGG10BB001) BACKWASH WATER PUMP (GBK11/12AP001) AIR BLOWER (10GBC11/12AN001) 10GBB11/12AA303 10GBB11/12AA306 10GBB11/12AA304 10GBB11/12AA305 FILTER BACKWASH WATER PIT (10UGH10BB001) 5.) Washing Purpose: To remove foreign particles detached from the media out of the vessel Operation: Open On-off valve (10GBB11/12AA301) manually from local SVB Open On-off valve (10GBB11/12AA305) manually from local SVB Other On-off valves are closed Flow rate: 105 m 3 /hr Duration: 10 minutes Illustration:
Note: Repeat Manual Backwash Operation Until Effluent Is Clear.
Uong Bi 300MW Extension Power Plant Goshu Kohsan Co., Ltd. M4/5/6 Water and Wastewater Treatment
Pre-Com and Commissioning Manual Page 19 of 71 09 Jan., 06 Rev. A Steps of A/C Filter Potable (10GBB20AT001) Manual Backwash Operation:
1.) Soaking Purpose: To saturate the carbon with water in order to optimize backwashing Operation: Open manhole MH manually Start Filtered water transfer pump A/B (10GBK41/42AP001) manually from LOP Open On-off valve (10GBB20AA301) manually from local SVB, then close valve when water reaches top distributor level by looking through the manhole MH Other On-off valves are closed Close manhole MH manually Duration: 1 hour or until activated carbon is fully saturated (Note: If some carbon still found floating on water surface, use any wooden paddle to sweep or disturb floating carbon so that water may enter into the available pores) Illustration: AA301 FILTERED WATER TRANSFER PUMP A/B (10GBK41/42AP001) A/C FILTER (10GBB20AT001) POTABLE WATER TANK (10GKB10BB001) P AA304 AA302 AA305 AA303 P FI (10GBK35CF501) CP501 CP502 MH FILTER B/W WATER PIT (10UGH10BB001) AA501
Uong Bi 300MW Extension Power Plant Goshu Kohsan Co., Ltd. M4/5/6 Water and Wastewater Treatment
Pre-Com and Commissioning Manual Page 20 of 71 09 Jan., 06 Rev. A 2.) Washing Purpose: To wash away foreign particles from gravel Operation: Keep Filtered water transfer pump A/B (10GBK41/42AP001) running Keep On-off valve (10GBB20AA301) open Open On-off valve (10GBB20AA305) manually from local SVB Other On-off valves are closed Flow rate: 10 m 3 /hr Duration: Until effluent is clear Illustration: AA301 FILTERED WATER TRANSFER PUMP A/B (10GBK41/42AP001) A/C FILTER (10GBB20AT001) POTABLE WATER TANK (10GKB10BB001) P AA304 AA302 AA305 AA303 P FI (10GBK35CF501) CP501 CP502 MH FILTER B/W WATER PIT (10UGH10BB001) AA501
Note: Open Air Vent valve (10GBB20AA501) once a day, anytime of the day, to release some air trapped in vessel
Uong Bi 300MW Extension Power Plant Goshu Kohsan Co., Ltd. M4/5/6 Water and Wastewater Treatment
Pre-Com and Commissioning Manual Page 21 of 71 09 Jan., 06 Rev. A 3.) Backwashing Purpose: To remove foreign particles of filter media Operation: Keep Filtered water transfer pump A/B (10GBK41/42AP001) running Close On-off valve (10GBB20AA301, 10GBB20AA305) manually from local SVB Open On-off valve (10GBB20AA303, 10GBB20AA304) manually from local SVB Other On-off valves are closed Flow rate: 10 m 3 /hr Duration: 10 minutes Illustration: AA301 FILTERED WATER TRANSFER PUMP A/B (10GBK41/42AP001) A/C FILTER (10GBB20AT001) POTABLE WATER TANK (10GKB10BB001) P AA304 AA302 AA305 AA303 P FI (10GBK35CF501) CP501 CP502 MH FILTER B/W WATER PIT (10UGH10BB001) AA501
Uong Bi 300MW Extension Power Plant Goshu Kohsan Co., Ltd. M4/5/6 Water and Wastewater Treatment
Pre-Com and Commissioning Manual Page 22 of 71 09 Jan., 06 Rev. A 4.) Stop Purpose: To allow floating filter media to settle by gravity Operation: Stop Filtered water transfer pump A/B (10GBK41/42AP001) manually from LOP Close On-off valve (10GBB20AA303, 10GBB20AA304) manually from local SVB Other On-off valves are closed Flow rate: 0 m 3 /hr Duration: 10 minutes Illustration: AA301 FILTERED WATER TRANSFER PUMP A/B (10GBK41/42AP001) A/C FILTER (10GBB20AT001) POTABLE WATER TANK (10GKB10BB001) P AA304 AA302 AA305 AA303 P FI (10GBK35CF501) CP501 CP502 MH FILTER B/W WATER PIT (10UGH10BB001) AA501
Uong Bi 300MW Extension Power Plant Goshu Kohsan Co., Ltd. M4/5/6 Water and Wastewater Treatment
Pre-Com and Commissioning Manual Page 23 of 71 09 Jan., 06 Rev. A 5.) Washing Purpose: To remove foreign particles remaining in the bottom of filter bed Operation: Start Filtered water transfer pump A/B (10GBK41/42AP001) manually from LOP Open On-off valve (10GBB20AA301, 10GBB20AA305) manually from local SVB Other On-off valves are closed Flow rate: 10 m 3 /hr Duration: 10 minutes or until effluent does not show activated carbon powder Illustration: AA301 FILTERED WATER TRANSFER PUMP A/B (10GBK41/42AP001) A/C FILTER (10GBB20AT001) POTABLE WATER TANK (10GKB10BB001) P AA304 AA302 AA305 AA303 P FI (10GBK35CF501) CP501 CP502 MH FILTER B/W WATER PIT (10UGH10BB001) AA501
Uong Bi 300MW Extension Power Plant Goshu Kohsan Co., Ltd. M4/5/6 Water and Wastewater Treatment
Pre-Com and Commissioning Manual Page 24 of 71 09 Jan., 06 Rev. A 6.) Service Purpose: To produce potable water Operation: Keep Filtered water transfer pump A/B (10GBK41/42AP001) running Keep On-off valve (10GBB20AA301) open Close On-off valve (10GBB20AA305) manually from local SVB Open On-off valve (10GBB20AA302) manually from local SVB, and start NaOCl feed pump 1A/B (10GBN21/22AP001) simultaneously for chlorination Other On-off valves are closed Flow rate: 10 m 3 /hr Duration: 540 minutes (90 m 3 /day) Illustration: AA301 FILTERED WATER TRANSFER PUMP A/B (10GBK41/42AP001) A/C FILTER (10GBB20AT001) POTABLE WATER TANK (10GKB10BB001) P AA304 AA302 AA305 AA303 P FI (10GBK35CF501) CP501 CP502 MH FILTER B/W WATER PIT (10UGH10BB001) AA501 NaOCl FEED PUMP 1A/B (10GBN21/22AP001)
Uong Bi 300MW Extension Power Plant Goshu Kohsan Co., Ltd. M4/5/6 Water and Wastewater Treatment
Pre-Com and Commissioning Manual Page 25 of 71 09 Jan., 06 Rev. A TRIAL RUN PACKAGE M5:
Steps of Demineralization Train A/B Manual Regeneration Operation
For A/C Filter A/B:
1.) Soaking Purpose: To saturate the carbon with water in order to optimize backwashing Operation: Open manhole MH manually Start Demin feed pump A/B (10GCK11/12AP001) manually from LOP Open On-off valve (10GCB11/12AA301) manually from local SVB, then close valve when water reaches top distributor level by looking through the manhole MH Other On-off valves are closed Close manhole MH manually Duration: 1 hour or until carbon is fully saturated (Note: If some carbon still found floating on water surface, use any wooden paddle to sweep or disturb floating carbon so that water may enter into the available pores) Illustration: AA301 DEMIN FEED PUMP A/B (10GCK11/12AP001) A/C FILTER A/B (10GCB11/12AT001) 10UGV10BB001 CATION EXCH. A/B (10GCF11/12AT001) P AA304 AA302 AA305 AA303 P FI (10GCK13CF501/502) CP501 CP502 MH AA501
Uong Bi 300MW Extension Power Plant Goshu Kohsan Co., Ltd. M4/5/6 Water and Wastewater Treatment
Pre-Com and Commissioning Manual Page 26 of 71 09 Jan., 06 Rev. A 2.) Washing Purpose: To wash away foreign particles from gravel Operation: Keep Demin feed pump A/B (10GCK11/12AP001) running Open On-off valve (10GCB11/12AA301) manually from local SVB Open On-off valve (10GCB11/12AA305) manually from local SVB Other On-off valves are closed Flow rate: 41 m 3 /hr Duration: Until effluent is clear Illustration: AA301 DEMIN FEED PUMP A/B (10GCK11/12AP001) A/C FILTER A/B (10GCB11/12AT001) 10UGV10BB001 CATION EXCH. A/B (10GCF11/12AT001) P AA304 AA302 AA305 AA303 P FI (10GCK13CF501/502) CP501 CP502 MH AA501
Note: Open Air Vent valve (10GCB11/12AA501) once a day, anytime of the day, to release some air trapped in vessel
Uong Bi 300MW Extension Power Plant Goshu Kohsan Co., Ltd. M4/5/6 Water and Wastewater Treatment
Pre-Com and Commissioning Manual Page 27 of 71 09 Jan., 06 Rev. A 3.) Backwashing Purpose: To remove foreign particles of filter media Operation: Keep Demin feed pump A/B (10GCK11/12AP001) running Close On-off valve (10GCB11/12AA301) manually from local SVB Close On-off valve (10GCB11/12AA305) manually from local SVB Open On-off valve (10GCB11/12AA303) manually from local SVB Open On-off valve (10GCB11/12AA304) manually from local SVB Other On-off valves are closed Flow rate: 41 m 3 /hr Duration: Until effluent is clear Illustration: AA301 DEMIN FEED PUMP A/B (10GCK11/12AP001) A/C FILTER A/B (10GCB11/12AT001) 10UGV10BB001 CATION EXCH. A/B (10GCF11/12AT001) P AA304 AA302 AA305 AA303 P FI (10GCK13CF501/502) CP501 CP502 MH AA501
Uong Bi 300MW Extension Power Plant Goshu Kohsan Co., Ltd. M4/5/6 Water and Wastewater Treatment
Pre-Com and Commissioning Manual Page 28 of 71 09 Jan., 06 Rev. A 4.) Stop Purpose: To allow floating filter media to settle by gravity Operation: Stop Demin feed pump A/B (10GCK11/12AP001) manually from LOP Close On-off valve (10GCB11/12AA303) manually from local SVB Close On-off valve (10GCB11/12AA304) manually from local SVB Other On-off valves are closed Flow rate: 0 m 3 /hr Duration: 10 minutes Illustration: AA301 DEMIN FEED PUMP A/B (10GCK11/12AP001) A/C FILTER A/B (10GCB11/12AT001) 10UGV10BB001 CATION EXCH. A/B (10GCF11/12AT001) P AA304 AA302 AA305 AA303 P FI (10GCK13CF501/502) CP501 CP502 MH AA501
Uong Bi 300MW Extension Power Plant Goshu Kohsan Co., Ltd. M4/5/6 Water and Wastewater Treatment
Pre-Com and Commissioning Manual Page 29 of 71 09 Jan., 06 Rev. A 5.) Washing Purpose: To remove foreign particles remaining in the bottom of filter bed Operation: Start Demin feed pump A/B (10GCK11/12AP001) manually from LOP Open On-off valve (10GCB11/12AA301) manually from local SVB Open On-off valve (10GCB11/12AA305) manually from local SVB Other On-off valves are closed Flow rate: 25 m 3 /hr Duration: 10 minutes or until effluent does not show activated carbon powder Illustration: AA301 DEMIN FEED PUMP A/B (10GCK11/12AP001) A/C FILTER A/B (10GCB11/12AT001) 10UGV10BB001 CATION EXCH. A/B (10GCF11/12AT001) P AA304 AA302 AA305 AA303 P FI (10GCK13CF501/502) CP501 CP502 MH AA501
Uong Bi 300MW Extension Power Plant Goshu Kohsan Co., Ltd. M4/5/6 Water and Wastewater Treatment
Pre-Com and Commissioning Manual Page 30 of 71 09 Jan., 06 Rev. A 6.) Service Purpose: To produce filtered water Operation: Keep Demin feed pump A/B (10GCK11/12AP001) running Keep On-off valve (10GCB11/12AA301) open Close On-off valve (10GCB11/12AA305) manually from local SVB Open On-off valve (10GCB11/12AA302) manually from local SVB Other On-off valves are closed Flow rate: 41 m 3 /hr Duration: 1,200 minutes Illustration: AA301 DEMIN FEED PUMP A/B (10GCK11/12AP001) A/C FILTER A/B (10GCB11/12AT001) 10UGV10BB001 CATION EXCH. A/B (10GCF11/12AT001) P AA304 AA302 AA305 AA303 P FI (10GCK13CF501/502) CP501 CP502 MH AA501
Uong Bi 300MW Extension Power Plant Goshu Kohsan Co., Ltd. M4/5/6 Water and Wastewater Treatment
Pre-Com and Commissioning Manual Page 31 of 71 09 Jan., 06 Rev. A For Cation Exchanger A/B:
1.) SAC Compaction Purpose: To lift the bed without reclassification of cation resin layers and pushes out any solids or fines that have accumulated on top of the bed. Operation: Start Regen pump A/B (10GCK31/32AP001) manually from LOP Open On-off valve (10GCF11/12AA303) manually from local SVB Open On-off valve (10GCF11/12AA304) manually from local SVB Other On-off valves are closed Flow rate: 29 m 3 /hr Duration: 5 minutes Illustration: AA301 AA302 A/C FILTER A/B (10GCB11/12AT001) AA304 CATION EXCH A/B (10GCF11/12 AT001) PI DEGASIFIER TOWER A/B (10GCH11/12AW001) PI AA305 REGEN PUMP A/B (10GCK31/32AP001) HCl FEED PUMP A/B AA303 AA801 10GCK62AA801 FT (10GCK14/15CF001) FI (10GCK63CF001) 10GCN78AA801 FI (10GCN78CF501) 10UGV10BB001 FI (10GCK62CF502)
Uong Bi 300MW Extension Power Plant Goshu Kohsan Co., Ltd. M4/5/6 Water and Wastewater Treatment
Pre-Com and Commissioning Manual Page 32 of 71 09 Jan., 06 Rev. A 2.) Regenerant HCl 30% Injection Purpose: To regenerate exhausted cation resin Operation: Keep Regen pump A/B (10GCK31/32AP001) running Close On-off valve (10GCF11/12AA303) manually from local SVB Keep On-off valve (10GCF11/12AA304) open Open On-off valves (10GCK62AA801, 10GCF11/12AA801) manually from local SVB Start HCl feed pump A/B (10GCN11/12AP001) manually from LOP Open On-off valve (10GCN78AA801) manually from local SVB Other On-off valves are closed Flow rates: HCl 30% = 1.20 m 3 /hr, Regen water = 7.1 m 3 /hr Duration: 35 minutes Illustration: AA301 AA302 A/C FILTER A/B (10GCB11/12AT001) AA304 CATION EXCH A/B (10GCF11/12 AT001) PI DEGASIFIER TOWER A/B (10GCH11/12AW001) PI AA305 REGEN PUMP A/B (10GCK31/32AP001) HCl FEED PUMP A/B (10GCN11/12AP001) AA303 AA801 10GCK62AA801 FT (10GCK14/15CF001) FI (10GCK63CF001) 10GCN78AA801 FI (10GCN78CF501) 10UGV10BB001 FI (10GCK62CF502)
Uong Bi 300MW Extension Power Plant Goshu Kohsan Co., Ltd. M4/5/6 Water and Wastewater Treatment
Pre-Com and Commissioning Manual Page 33 of 71 09 Jan., 06 Rev. A 3.) Acid Displacement (Slow rinse) Purpose: To push active regenerant from bottom to top of resin bed and start rinsing out Operation: Keep Regen pump A/B (10GCK31/32AP001) running Keep On-off valves (10GCF11/12AA304, 10GCK62AA801, ) open Close On-off valve (10GCN78AA801) manually from local SVB Stop HCl feed pump A/B (10GCN11/12AP001) manually from LOP Keep On-off valve (10GCF11/12AA801) open Other On-off valves are closed Flow rates: 7.1 m 3 /hr Duration: 30 minutes Illustration: AA301 AA302 A/C FILTER A/B (10GCB11/12AT001) AA304 CATION EXCH A/B (10GCF11/12 AT001) PI DEGASIFIER TOWER A/B (10GCH11/12AW001) PI AA305 REGEN PUMP A/B (10GCK31/32AP001) HCl FEED PUMP A/B (10GCN11/12AP001) AA303 AA801 10GCK62AA801 FT (10GCK14/15CF001) FI (10GCK63CF001) 10GCN78AA801 FI (10GCN78CF501) 10UGV10BB001 FI (10GCK62CF502)
Uong Bi 300MW Extension Power Plant Goshu Kohsan Co., Ltd. M4/5/6 Water and Wastewater Treatment
Pre-Com and Commissioning Manual Page 34 of 71 09 Jan., 06 Rev. A 4.) Resin Bed Settling Purpose: To allow floating resin to settle by gravity Operation: Stop Regen pump A/B (10GCK31/32AP001) manually from LOP Close On-off valves (10GCF11/12AA304, 10GCK62AA801, 10GCF11/12AA801) manually from respective local SVBs Other On-off valves are closed Flow rates: 0 m 3 /hr Duration: 10 minutes Illustration: AA301 AA302 A/C FILTER A/B (10GCB11/12AT001) AA304 CATION EXCH A/B (10GCF11/12 AT001) PI DEGASIFIER TOWER A/B (10GCH11/12AW001) PI AA305 REGEN PUMP A/B (10GCK31/32AP001) HCl FEED PUMP A/B (10GCN11/12AP001) AA303 AA801 10GCK62AA801 FT (10GCK14/15CF001) FI (10GCK63CF001) 10GCN78AA801 FI (10GCN78CF501) 10UGV10BB001 FI (10GCK62CF502)
Uong Bi 300MW Extension Power Plant Goshu Kohsan Co., Ltd. M4/5/6 Water and Wastewater Treatment
Pre-Com and Commissioning Manual Page 35 of 71 09 Jan., 06 Rev. A 5.) Rinsing Purpose: To finally rinse out remaining regenerant and to arrange resin layer Operation: Start Demin feed pump A/B (10GCK11/12AP001) manually from LOP to feed filtered water through A/C filter A/B (10GCB11/12AT001) Open On-off valves (10GCF11/12AA301, 10GCF11/12AA305) manually from respective local SVBs Other On-off valves are closed Flow rates: 41 m 3 /hr Duration: 7 minutes Illustration: AA301 AA302 A/C FILTER A/B (10GCB11/12AT001) AA304 CATION EXCH A/B (10GCF11/12 AT001) PI DEGASIFIER TOWER A/B (10GCH11/12AW001) PI AA305 REGEN PUMP A/B (10GCK31/32AP001) HCl FEED PUMP A/B (10GCN11/12AP001) AA303 AA801 10GCK62AA801 FT (10GCK14/15CF001) FI (10GCK63CF001) 10GCN78AA801 FI (10GCN78CF501) 10UGV10BB001 FI (10GCK62CF502)
Uong Bi 300MW Extension Power Plant Goshu Kohsan Co., Ltd. M4/5/6 Water and Wastewater Treatment
Pre-Com and Commissioning Manual Page 36 of 71 09 Jan., 06 Rev. A 6.) Service Purpose: To produce soft water Operation: Keep Demin feed pump A/B (10GCK11/12AP001) running to feed filtered water through A/C filter A/B (10GCB11/12AT001) Keep On-off valve (10GCF11/12AA301) open Close On-off valve (10GCF11/12AA305) manually from respective local SVBs Open On-off valve (10GCF11/12AA302) manually from respective local SVBs Other On-off valves are closed Flow rates: 41 m 3 /hr Duration: 1,228 minutes Illustration: AA301 AA302 A/C FILTER A/B (10GCB11/12AT001) AA304 CATION EXCH A/B (10GCF11/12 AT001) PI DEGASIFIER TOWER A/B (10GCH11/12AW001) PI AA305 REGEN PUMP A/B (10GCK31/32AP001) HCl FEED PUMP A/B (10GCN11/12AP001) AA303 AA801 10GCK62AA801 FT (10GCK14/15CF001) FI (10GCK63CF001) 10GCN78AA801 FI (10GCN78CF501) 10UGV10BB001 FI (10GCK62CF502)
Uong Bi 300MW Extension Power Plant Goshu Kohsan Co., Ltd. M4/5/6 Water and Wastewater Treatment
Pre-Com and Commissioning Manual Page 37 of 71 09 Jan., 06 Rev. A For Degasifier A/B
Uong Bi 300MW Extension Power Plant Goshu Kohsan Co., Ltd. M4/5/6 Water and Wastewater Treatment
Pre-Com and Commissioning Manual Page 38 of 71 09 Jan., 06 Rev. A For Anion Exchanger A/B:
1.) SBA Compaction Purpose: To lift the bed without reclassification of anion resin layers and pushes out any solids or fines that have accumulated on top of the bed. Operation: Start Regen pump A/B (10GCK31/32AP001) manually from LOP Open On-off valve (10GCF21/22AA303) manually from local SVB Open On-off valve (10GCF21/22AA304) manually from local SVB Other On-off valves are closed Flow rate: 29 m 3 /hr Duration: 5 minutes Illustration: AA301 AA302 MIXED BED EXCH A/B (10GCF31/32AT001) AA304 ANION EXCH A/B (10GCF21/22 AT001) PI BOOSTER PUMP A/B (10GCK21/22AP001) PI AA305 REGEN PUMP A/B (10GCK31/32AP001) NaOH FEED PUMP A/B AA303 AA801 10GCK62AA803 FT (10GCK37/38CF001) FI (10GCK63CF001) 10GCN91AA801 FI (10GCN91CF501) 10UGV10BB001 FI (10GCK62CF504)
Uong Bi 300MW Extension Power Plant Goshu Kohsan Co., Ltd. M4/5/6 Water and Wastewater Treatment
Pre-Com and Commissioning Manual Page 39 of 71 09 Jan., 06 Rev. A 2.) Regenerant NaOH 50% Injection Purpose: To regenerate exhausted anion resin Operation: Keep Regen pump A/B (10GCK31/32AP001) running Close On-off valve (10GCF21/22AA303) manually from local SVB Keep On-off valve (10GCF21/22AA304) open Open On-off valves (10GCK62AA803, 10GCF21/22AA801) manually from local SVB Start NaOH feed pump A/B (10GCN21/22AP001) manually from LOP Open On-off valve (10GCN91AA801) manually from local SVB Other On-off valves are closed Flow rates: NaOH 50% = 0.41 m 3 /hr, Regen water = 7.30 m 3 /hr Duration: 45 minutes Illustration: AA301 AA302 MIXED BED EXCH A/B (10GCF31/32AT001) AA304 ANION EXCH A/B (10GCF21/22 AT001) PI BOOSTER PUMP A/B (10GCK21/22AP001) PI AA305 REGEN PUMP A/B (10GCK31/32AP001) NaOH FEED PUMP A/B (10GCN21/22AP001) AA303 AA801 10GCK62AA803 FT (10GCK37/38CF001) FI (10GCK63CF001) 10GCN91AA801 FI (10GCN91CF501) 10UGV10BB001 FI (10GCK62CF504)
Uong Bi 300MW Extension Power Plant Goshu Kohsan Co., Ltd. M4/5/6 Water and Wastewater Treatment
Pre-Com and Commissioning Manual Page 40 of 71 09 Jan., 06 Rev. A 3.) Acid Displacement (Slow rinse) Purpose: To push active regenerant from bottom to top of resin bed and start rinsing out Operation: Keep Regen pump A/B (10GCK31/32AP001) running Close On-off valve (10GCF21/22AA303) manually from local SVB Keep On-off valve (10GCF21/22AA304) open Keep On-off valves (10GCK62AA803, 10GCF21/22AA801) manually from local SVB Close On-off valve (10GCN91AA801) manually from local SVB Stop NaOH feed pump A/B (10GCN21/22AP001) manually from LOP Other On-off valves are closed Flow rates: 7.30 m 3 /hr Duration: 40 minutes Illustration: AA301 AA302 MIXED BED EXCH A/B (10GCF31/32AT001) AA304 ANION EXCH A/B (10GCF21/22 AT001) PI BOOSTER PUMP A/B (10GCK21/22AP001) PI AA305 REGEN PUMP A/B (10GCK31/32AP001) NaOH FEED PUMP A/B (10GCN21/22AP001) AA303 AA801 10GCK62AA803 FT (10GCK37/38CF001) FI (10GCK63CF001) 10GCN91AA801 FI (10GCN91CF501) 10UGV10BB001 FI (10GCK62CF504)
Uong Bi 300MW Extension Power Plant Goshu Kohsan Co., Ltd. M4/5/6 Water and Wastewater Treatment
Pre-Com and Commissioning Manual Page 41 of 71 09 Jan., 06 Rev. A 4.) Resin Bed Settling Purpose: To allow floating resin to settle by gravity Operation: Stop Regen pump A/B (10GCK31/32AP001) manually from LOP Close On-off valves (10GCF21/22AA304, 10GCK62AA803, 10GCF21/22AA801) manually from respective local SVBs Other On-off valves are closed Flow rates: 0 m 3 /hr Duration: 10 minutes Illustration: AA301 AA302 MIXED BED EXCH A/B (10GCF31/32AT001) AA304 ANION EXCH A/B (10GCF21/22 AT001) PI BOOSTER PUMP A/B (10GCK21/22AP001) PI AA305 REGEN PUMP A/B (10GCK31/32AP001) NaOH FEED PUMP A/B (10GCN21/22AP001) AA303 AA801 10GCK62AA803 FT (10GCK37/38CF001) FI (10GCK63CF001) 10GCN91AA801 FI (10GCN91CF501) 10UGV10BB001 FI (10GCK62CF504)
Uong Bi 300MW Extension Power Plant Goshu Kohsan Co., Ltd. M4/5/6 Water and Wastewater Treatment
Pre-Com and Commissioning Manual Page 42 of 71 09 Jan., 06 Rev. A 5.) Rinsing Purpose: To finally rinse out remaining regenerant and to arrange resin layer Operation: Start Booster pump A/B (10GCK21/22AP001) manually from LOP Open On-off valves (10GCF21/22AA301, 10GCF21/22AA305) manually from respective local SVBs Other On-off valves are closed Flow rates: 41 m 3 /hr Duration: 15 minutes Illustration: AA301 AA302 MIXED BED EXCH A/B (10GCF31/32AT001) AA304 ANION EXCH A/B (10GCF21/22 AT001) PI BOOSTER PUMP A/B (10GCK21/22AP001) PI AA305 REGEN PUMP A/B (10GCK31/32AP001) NaOH FEED PUMP A/B (10GCN21/22AP001) AA303 AA801 10GCK62AA803 FT (10GCK37/38CF001) FI (10GCK63CF001) 10GCN91AA801 FI (10GCN91CF501) 10UGV10BB001 FI (10GCK62CF504)
Uong Bi 300MW Extension Power Plant Goshu Kohsan Co., Ltd. M4/5/6 Water and Wastewater Treatment
Pre-Com and Commissioning Manual Page 43 of 71 09 Jan., 06 Rev. A 6.) Service Purpose: To produce demin water Operation: Keep Booster pump A/B (10GCK21/22AP001) running Keep On-off valve (10GCF21/22AA301) open Open On-off valve (10GCF21/22AA302) manually from local SVB Other On-off valves are closed Flow rates: 41 m 3 /hr Duration: 1228 minutes Illustration: AA301 AA302 MIXED BED EXCH A/B (10GCF31/32AT001) AA304 ANION EXCH A/B (10GCF21/22 AT001) PI BOOSTER PUMP A/B (10GCK21/22AP001) PI AA305 REGEN PUMP A/B (10GCK31/32AP001) NaOH FEED PUMP A/B (10GCN21/22AP001) AA303 AA801 10GCK62AA803 FT (10GCK37/38CF001) FI (10GCK63CF001) 10GCN91AA801 FI (10GCN91CF501) 10UGV10BB001 FI (10GCK62CF504)
Uong Bi 300MW Extension Power Plant Goshu Kohsan Co., Ltd. M4/5/6 Water and Wastewater Treatment
Pre-Com and Commissioning Manual Page 44 of 71 09 Jan., 06 Rev. A For Mixed Bed Exchanger A/B:
1.) Backwashing Purpose: To separate anion and cation resin layers Operation: Start Regen pump A/B (10GCK31/32AP001) manually from LOP Open On-off valves (10GCF31/32AA805, 10GCF31/32AA806) manually from respective local SVBs Other On-off valves are closed Flow rate: 8.4 m 3 /hr Duration: 20 minutes Illustration: ANION EXCH A/B (10GCF21/22AT001) AA806 DEMIN WATER TANK A/B (10GCL11/12BB01 PI REGEN PUMP A/B (10GCK31/32AP001) NaOH FEED PUMP 1A/B (10GCN21/22AP001) AA305 10UGV10BB001 AA804 AA302 AA306 AA803 AA801 AA805 AA802 MIXED BED EXCH A/B (10GCF31/32 AT001) FI (10GCK63CF001) FI (10GCK62CF503) 10GCK62AA804 10GCN90AA801 FI (10GCN90CF501) FI (10GCK62CF501) 10GCK62AA802 FI (10GCN77CF501) 10GCN77AA801 HCl FEED PUMP 1A/B (10GCN11/12AP001) AIR RECEIVER (10QEF10BB001) 10GCF21/22AA302 PI
Uong Bi 300MW Extension Power Plant Goshu Kohsan Co., Ltd. M4/5/6 Water and Wastewater Treatment
Pre-Com and Commissioning Manual Page 45 of 71 09 Jan., 06 Rev. A 2.) Stop Purpose: To allow floating resins to settle by gravity Operation: Stop Regen pump A/B (10GCK31/32AP001) manually from LOP Close On-off valves (10GCF31/32AA805, 10GCF31/32AA806) manually from respective local SVBs Other On-off valves are closed Flow rate: 0 m 3 /hr Duration: 10 minutes Illustration: ANION EXCH A/B (10GCF21/22AT001) AA806 DEMIN WATER TANK A/B (10GCL11/12BB01) PI REGEN PUMP A/B (10GCK31/32AP001) NaOH FEED PUMP 1A/B (10GCN21/22AP001) AA305 10UGV10BB001 AA804 AA302 AA306 AA803 AA801 AA805 AA802 MIXED BED EXCH A/B (10GCF31/32 AT001) FI (10GCK63CF001) FI (10GCK62CF503) 10GCK62AA804 10GCN90AA801 FI (10GCN90CF501) FI (10GCK62CF501) 10GCK62AA802 FI (10GCN77CF501) 10GCN77AA801 HCl FEED PUMP 1A/B (10GCN11/12AP001) AIR RECEIVER (10QEF10BB001) 10GCF21/22AA302 PI
Uong Bi 300MW Extension Power Plant Goshu Kohsan Co., Ltd. M4/5/6 Water and Wastewater Treatment
Pre-Com and Commissioning Manual Page 46 of 71 09 Jan., 06 Rev. A 3.) Regenerant NaOH 50% Injection Purpose: To regenerate exhausted anion resin Operation: Start Regen pump A/B (10GCK31/32AP001) manually from LOP Open On-off valves (10GCF31/32AA801, 10GCF31/32AA802, 10GCF31/32AA804, 10GCK62AA804, 10GCK62AA802) manually from respective local SVBs Start NaOH feed pump A/B (10GCN21/22AP001) manually from LOP Open On-off valve (10GCN90AA801) manually from local SVB Other On-off valves are closed Flow rate: NaOH 50% = 0.16 m 3 /hr, Downward = 2.10 m 3 /hr, Upward = 2.20 m 3 /hr Duration: 25 minutes Illustration: ANION EXCH A/B (10GCF21/22AT001) AA806 DEMIN WATER TANK A/B (10GCL11/12BB01) PI REGEN PUMP A/B (10GCK31/32AP001) NaOH FEED PUMP 1A/B (10GCN21/22AP001) AA305 10UGV10BB001 AA804 AA302 AA306 AA803 AA801 AA805 AA802 MIXED BED EXCH A/B (10GCF31/32 AT001) FI (10GCK63CF001) FI (10GCK62CF503) 10GCK62AA804 10GCN90AA801 FI (10GCN90CF501) FI (10GCK62CF501) 10GCK62AA802 FI (10GCN77CF501) 10GCN77AA801 HCl FEED PUMP 1A/B (10GCN11/12AP001) AIR RECEIVER (10QEF10BB001) 10GCF21/22AA302 PI
Uong Bi 300MW Extension Power Plant Goshu Kohsan Co., Ltd. M4/5/6 Water and Wastewater Treatment
Pre-Com and Commissioning Manual Page 47 of 71 09 Jan., 06 Rev. A 4.) Displacement of NaOH 50% (Slow rinse) Purpose: To displace active NaOH 50% residual from the line before ends of spray nozzle Operation: Keep Regen pump A/B (10GCK31/32AP001) running Keep On-off valves (10GCF31/32AA801, 10GCF31/32AA802, 10GCF31/32AA804, 10GCK62AA804, 10GCK62AA802) open Close On-off valve (10GCN90AA801) manually from local SVB Stop NaOH feed pump A/B (10GCN21/22AP001) manually from LOP Other On-off valves are closed Flow rate: 2.10 m 3 /hr Duration: 30 minutes Illustration: ANION EXCH A/B (10GCF21/22AT001) AA806 DEMIN WATER TANK A/B (10GCL11/12BB01) PI REGEN PUMP A/B (10GCK31/32AP001) NaOH FEED PUMP 1A/B (10GCN21/22AP001) AA305 10UGV10BB001 AA804 AA302 AA306 AA803 AA801 AA805 AA802 MIXED BED EXCH A/B (10GCF31/32 AT001) FI (10GCK63CF001) FI (10GCK62CF503) 10GCK62AA804 10GCN90AA801 FI (10GCN90CF501) FI (10GCK62CF501) 10GCK62AA802 FI (10GCN77CF501) 10GCN77AA801 HCl FEED PUMP 1A/B (10GCN11/12AP001) AIR RECEIVER (10QEF10BB001) 10GCF21/22AA302 PI
Uong Bi 300MW Extension Power Plant Goshu Kohsan Co., Ltd. M4/5/6 Water and Wastewater Treatment
Pre-Com and Commissioning Manual Page 48 of 71 09 Jan., 06 Rev. A 5.) Regenerant HCl 30% Purpose: To regenerate exhausted cation resin Operation: Keep Regen pump A/B (10GCK31/32AP001) running Keep On-off valves (10GCF31/32AA801, 10GCF31/32AA802, 10GCF31/32AA804, 10GCK62AA804, 10GCK62AA802) open Start HCl feed pump A/B (10GCN11/12AP001) manually from LOP Open On-off valve (10GCN77AA801) manually from local SVB Other On-off valves are closed Flow rate: HCl 30% = 0.39 m 3 /hr, Upward = 2.20 m 3 /hr, Downward = 2.10 m 3 /hr Duration: 20 minutes Illustration: ANION EXCH A/B (10GCF21/22AT001) AA806 DEMIN WATER TANK A/B (10GCL11/12BB01) PI REGEN PUMP A/B (10GCK31/32AP001) NaOH FEED PUMP 1A/B (10GCN21/22AP001) AA305 10UGV10BB001 AA804 AA302 AA306 AA803 AA801 AA805 AA802 MIXED BED EXCH A/B (10GCF31/32 AT001) FI (10GCK63CF001) FI (10GCK62CF503) 10GCK62AA804 10GCN90AA801 FI (10GCN90CF501) FI (10GCK62CF501) 10GCK62AA802 FI (10GCN77CF501) 10GCN77AA801 HCl FEED PUMP 1A/B (10GCN11/12AP001) AIR RECEIVER (10QEF10BB001) 10GCF21/22AA302 PI
Uong Bi 300MW Extension Power Plant Goshu Kohsan Co., Ltd. M4/5/6 Water and Wastewater Treatment
Pre-Com and Commissioning Manual Page 49 of 71 09 Jan., 06 Rev. A 6.) Displacement of HCl 30% (Slow rinse) Purpose: To displace active HCl 30% residual from the line before ends of spray nozzle Operation: Keep Regen pump A/B (10GCK31/32AP001) running Keep On-off valves (10GCF31/32AA801, 10GCF31/32AA802, 10GCF31/32AA804, 10GCK62AA804, 10GCK62AA802) open Close On-off valve (10GCN77AA801) manually from local SVB Stop HCl feed pump A/B (10GCN11/12AP001) manually from LOP Other On-off valves are closed Flow rate: 2.20 m 3 /hr Duration: 25 minutes Illustration: ANION EXCH A/B (10GCF21/22AT001) AA806 DEMIN WATER TANK A/B (10GCL11/12BB01) PI REGEN PUMP A/B (10GCK31/32AP001) NaOH FEED PUMP 1A/B (10GCN21/22AP001) AA305 10UGV10BB001 AA804 AA302 AA306 AA803 AA801 AA805 AA802 MIXED BED EXCH A/B (10GCF31/32 AT001) FI (10GCK63CF001) FI (10GCK62CF503) 10GCK62AA804 10GCN90AA801 FI (10GCN90CF501) FI (10GCK62CF501) 10GCK62AA802 FI (10GCN77CF501) 10GCN77AA801 HCl FEED PUMP 1A/B (10GCN11/12AP001) AIR RECEIVER (10QEF10BB001) 10GCF21/22AA302 PI
Uong Bi 300MW Extension Power Plant Goshu Kohsan Co., Ltd. M4/5/6 Water and Wastewater Treatment
Pre-Com and Commissioning Manual Page 50 of 71 09 Jan., 06 Rev. A 7.) Water Drain Purpose: To reduce water level in vessel to prevent separation of resin during air mixing Operation: Stop Regen pump A/B (10GCK31/32AP001) manually from LOP Close On-off valves (10GCF31/32AA801, 10GCF31/32AA802, 10GCF31/32AA804, 10GCK62AA804, 10GCK62AA802) manually from local SVB Open On-off valves (10GCF31/32AA305, 10GCF31/32AA801) manually from local SVB Other On-off valves are closed Flow rate: 0 m 3 /hr Duration: 10 minutes Illustration: ANION EXCH A/B (10GCF21/22AT001) AA806 DEMIN WATER TANK A/B (10GCL11/12BB01) PI REGEN PUMP A/B (10GCK31/32AP001) NaOH FEED PUMP 1A/B (10GCN21/22AP001) AA305 10UGV10BB001 AA804 AA302 AA306 AA803 AA801 AA805 AA802 MIXED BED EXCH A/B (10GCF31/32 AT001) FI (10GCK63CF001) FI (10GCK62CF503) 10GCK62AA804 10GCN90AA801 FI (10GCN90CF501) FI (10GCK62CF501) 10GCK62AA802 FI (10GCN77CF501) 10GCN77AA801 HCl FEED PUMP 1A/B (10GCN11/12AP001) AIR RECEIVER (10QEF10BB001) 10GCF21/22AA302 PI AA801
Uong Bi 300MW Extension Power Plant Goshu Kohsan Co., Ltd. M4/5/6 Water and Wastewater Treatment
Pre-Com and Commissioning Manual Page 51 of 71 09 Jan., 06 Rev. A 8.) Resin Air Mixing Purpose: To mix back cation and anion resins Operation: Close On-off valve (10GCF31/32AA305) manually from local SVB Open On-off valve (10GCF31/32AA803) manually from local SVB Other On-off valves are closed Flow rate: 47.1 Nm 3 /hr Duration: 10 minutes Illustration: ANION EXCH A/B (10GCF21/22AT001) AA806 DEMIN WATER TANK A/B (10GCL11/12BB01) PI REGEN PUMP A/B (10GCK31/32AP001) NaOH FEED PUMP 1A/B (10GCN21/22AP001) AA305 10UGV10BB001 AA804 AA302 AA306 AA803 AA801 AA805 AA802 MIXED BED EXCH A/B (10GCF31/32 AT001) FI (10GCK63CF001) FI (10GCK62CF503) 10GCK62AA804 10GCN90AA801 FI (10GCN90CF501) FI (10GCK62CF501) 10GCK62AA802 FI (10GCN77CF501) 10GCN77AA801 HCl FEED PUMP 1A/B (10GCN11/12AP001) AIR RECEIVER (10QEF10BB001) 10GCF21/22AA302 PI
Uong Bi 300MW Extension Power Plant Goshu Kohsan Co., Ltd. M4/5/6 Water and Wastewater Treatment
Pre-Com and Commissioning Manual Page 52 of 71 09 Jan., 06 Rev. A 9.) Vessel Filling Purpose: To fill the vessel with water until required level Operation: Start Booster pump A/B (10GCK21/22AP001) manually from LOP to feed demin water through Anion Exchanger A/B (10GCF21/22AT001) Open On-off valve (10GCF21/22AA302) manually from local SVB Open On-off valve (10GCF31/32AA801) manually from local SVB Other On-off valves are closed Flow rate: 20.0 m 3 /hr Duration: 2 minutes Illustration: ANION EXCH A/B (10GCF21/22AT001) AA806 DEMIN WATER TANK A/B (10GCL11/12BB01) PI REGEN PUMP A/B (10GCK31/32AP001) NaOH FEED PUMP 1A/B (10GCN21/22AP001) AA305 10UGV10BB001 AA804 AA302 AA306 AA803 AA801 AA805 AA802 MIXED BED EXCH A/B (10GCF31/32 AT001) FI (10GCK63CF001) FI (10GCK62CF503) 10GCK62AA804 10GCN90AA801 FI (10GCN90CF501) FI (10GCK62CF501) 10GCK62AA802 FI (10GCN77CF501) 10GCN77AA801 HCl FEED PUMP 1A/B (10GCN11/12AP001) AIR RECEIVER (10QEF10BB001) 10GCF21/22AA302 PI AA801
Uong Bi 300MW Extension Power Plant Goshu Kohsan Co., Ltd. M4/5/6 Water and Wastewater Treatment
Pre-Com and Commissioning Manual Page 53 of 71 09 Jan., 06 Rev. A 10.) Rinsing Purpose: To fill the vessel with water until required level Operation: Keep Booster pump A/B (10GCK21/22AP001) running to feed demin water through Anion Exchanger A/B (10GCF21/22AT001) Keep On-off valve (10GCF21/22AA302) open Open On-off valve (10GCF31/32AA306) manually from local SVB Other On-off valves are closed Flow rate: 20.0 m 3 /hr Duration: 15 minutes Illustration: ANION EXCH A/B (10GCF21/22AT001) AA806 DEMIN WATER TANK A/B (10GCL11/12BB01) PI REGEN PUMP A/B (10GCK31/32AP001) NaOH FEED PUMP 1A/B (10GCN21/22AP001) AA305 10UGV10BB001 AA804 AA302 AA306 AA803 AA801 AA805 AA802 MIXED BED EXCH A/B (10GCF31/32 AT001) FI (10GCK63CF001) FI (10GCK62CF503) 10GCK62AA804 10GCN90AA801 FI (10GCN90CF501) FI (10GCK62CF501) 10GCK62AA802 FI (10GCN77CF501) 10GCN77AA801 HCl FEED PUMP 1A/B (10GCN11/12AP001) AIR RECEIVER (10QEF10BB001) 10GCF21/22AA302 PI
Uong Bi 300MW Extension Power Plant Goshu Kohsan Co., Ltd. M4/5/6 Water and Wastewater Treatment
Pre-Com and Commissioning Manual Page 54 of 71 09 Jan., 06 Rev. A 11.) Service Purpose: To further polish demin water Operation: Keep Booster pump A/B (10GCK21/22AP001) running to feed demin water through Anion Exchanger A/B (10GCF21/22AT001) Keep On-off valve (10GCF21/22AA302) open Open On-off valve (10GCF31/32AA302) manually from local SVB Other On-off valves are closed Flow rate: 41.0 m 3 /hr Duration: 10,080 minutes Illustration: ANION EXCH A/B (10GCF21/22AT001) AA806 DEMIN WATER TANK A/B (10GCL11/12BB01) PI REGEN PUMP A/B (10GCK31/32AP001) NaOH FEED PUMP 1A/B (10GCN21/22AP001) AA305 10UGV10BB001 AA804 AA302 AA306 AA803 AA801 AA805 AA802 MIXED BED EXCH A/B (10GCF31/32 AT001) FI (10GCK63CF001) FI (10GCK62CF503) 10GCK62AA804 10GCN90AA801 FI (10GCN90CF501) FI (10GCK62CF501) 10GCK62AA802 FI (10GCN77CF501) 10GCN77AA801 HCl FEED PUMP 1A/B (10GCN11/12AP001) AIR RECEIVER (10QEF10BB001) 10GCF21/22AA302 PI
Uong Bi 300MW Extension Power Plant Goshu Kohsan Co., Ltd. M4/5/6 Water and Wastewater Treatment
Pre-Com and Commissioning Manual Page 55 of 71 09 Jan., 06 Rev. A TRIAL RUN PACKAGE M6:
Steps of Trial Run for pH Adjustment & Mixing Pit, WWTP Clarifier Tank and Sludge Receiver Tank:
1.) pH Adjustment and Mixing Pit Purpose: To fill wastewater into the pH adjustment pit and overflows to Mixing pit from Wastewater pit for coagulation and flocculation process Operation: Start Wastewater pump (10GNK21/22AP001) manually from LOP Start following Chemical feed pumps manually from respective LOPs o Coagulation feed pump 2A/B (10GNN11/12AP001) = 100 mg/L o HCl feed pump 2A (10GNN30AP001) = 50 mg/L o NaOH feed pump 3A (10GNN50AP001) = 100 mg/L o Polymer feed pump 2A/B (10GNN21/22AP001) = 1 mg/L Start following Agitators manually from respective LOPs when wastewater level is over agitators blades o pH adjustment pit agitator (10GNE10AM001) o Mixing pit agitator (10GNE20AM001) Flow rate: 70 m 3 /hr Duration: Until wastewater overflows Illustration: M M WASTEWATER PUMP (10GNK21/22AP001) COAGULATION FEED PUMP 2A/B (10GNN11/12AP001) HCl FEED PUMP 2A (10GNN30AP001) NaOH FEED PUMP 3A (10GNN50AP001) POLYMER FEED PUMP 2A/B (10GNN21/22AP001) pH ADJUSTMENT PIT (10UGP10BB001) MIXING PIT (10UGP20BB001) MIXING PIT AGITATOR (10GNE20AM001) pH ADJUSTMENT PIT AGITATOR (10GNE10AM001) WWTP CLARIFIER TANK (10UGQ10BB001) pH QT
Uong Bi 300MW Extension Power Plant Goshu Kohsan Co., Ltd. M4/5/6 Water and Wastewater Treatment
Pre-Com and Commissioning Manual Page 56 of 71 09 Jan., 06 Rev. A 2.) WWTP Clarifier Tank Purpose: To separate sludge and clear water Operation: Keep Wastewater pump (10GNK21/22AP001) running Keep Chemical feed pumps simultaneously running o Coagulation feed pump 2A/B (10GNN11/12AP001) = 100 mg/L o HCl feed pump 2A (10GNN30AP001) = 50 mg/L o NaOH feed pump 3A (10GNN50AP001) = 100 mg/L o Polymer feed pump 2A/B (10GNN21/22AP001) = 1 mg/L Start WWTP Clarifier tank agitators (10GND10AM001) when wastewater level is over the blades of agitator Start Thinner sludge pump A/B (10GNK41/42AP001) manually from LOP to transfer partially thickened sludge to Sludge receiver tank (10UGT10BB001) Flow rate: 70 m 3 /hr Duration: Continuous Illustration: M WWTP CLARIFIER TANK AGITATOR (10GND10AM001) MIXING PIT (10UGP20BB001) CLARIFIED WASTEWATER PIT (10UGR10BB001) WWTP CLARIFIER TANK (10UGQ10BB001) THINNER SLUDGE PUMP A/B (10GNK41/42AP001)
Uong Bi 300MW Extension Power Plant Goshu Kohsan Co., Ltd. M4/5/6 Water and Wastewater Treatment
Pre-Com and Commissioning Manual Page 57 of 71 09 Jan., 06 Rev. A 3.) Sludge Receiver Tank Purpose: To further thickened sludge for disposal Operation: Keep Wastewater pump (10GNK21/22AP001) running Keep Chemical feed pumps simultaneously running o Coagulation feed pump 2A/B (10GNN11/12AP001) = 100 mg/L o HCl feed pump 2A (10GNN30AP001) = 50 mg/L o NaOH feed pump 3A (10GNN50AP001) = 100 mg/L o Polymer feed pump 2A/B (10GNN21/22AP001) = 1 mg/L Keep Thinner sludge pump A/B (10GNK41/42AP001) running Start Sludge receiver tank agitators (10GND10AM001) when wastewater level is over the blades of agitator Start Thicker sludge pump A/B (10GNK71/72AP001) manually from LOP to dispose thickened sludge to Ash slurry pit Flow rate: 3 m 3 /hr Duration: Continuous Illustration: M SLUDGE RECEIVER TANK AGITATOR (10GNS10AM001) THINNER SLUDGE PUMP A/B (10GNK41/42AP001) WASTEWATER PIT (10UGN10BB001) SLUDGE RECEIVER TANK (10UGT10BB001) THICKER SLUDGE PUMP A/B (10GNK71/72AP001) SLUDGE PUMP A/B (10GRK11/12AP001) UNDERFLOW SLUDGE PUMP A/B (10GBK21/22AP001)
Uong Bi 300MW Extension Power Plant Goshu Kohsan Co., Ltd. M4/5/6 Water and Wastewater Treatment
Pre-Com and Commissioning Manual Page 58 of 71 09 Jan., 06 Rev. A Steps of A/C Filter WWTP (10GNB10AT001) Manual Backwash Operation:
1.) Soaking Purpose: To saturate the carbon with water in order to optimize backwashing Operation: Open manhole MH manually Start Clarified water transfer pump A/B (10GNK31/32AP001) manually from LOP Open On-off valve (10GNB10AA301) manually from local SVB, then close valve when water reaches top distributor level by looking through the manhole MH Other On-off valves are closed Close manhole MH manually Duration: 1 hour or until activated carbon is fully saturated (Note: If some carbon still found floating on water surface, use any wooden paddle to sweep or disturb floating carbon so that water may enter into the available pores) Illustration: AA301 CLARIFIED WATER TRANSFER PUMP A/B (10GNK31/32AP001) A/C FILTER WWTP (10GNB10AT001) NEUTRALIZATION PIT (10UGU10BB001) P AA304 AA302 AA305 AA303 P FI (10GNK21CF501) CP501 CP502 MH WASTEWATER PIT (10UGN10BB001) BACKWASH PUMP A/B (10GNK61/62AP001) AA501
Uong Bi 300MW Extension Power Plant Goshu Kohsan Co., Ltd. M4/5/6 Water and Wastewater Treatment
Pre-Com and Commissioning Manual Page 59 of 71 09 Jan., 06 Rev. A 2.) Washing Purpose: To wash away foreign particles from gravel Operation: Keep Clarified water transfer pump A/B (10GNK31/32AP001) running Open On-off valve (10GNB10AA301) manually from local SVB Open On-off valve (10GNB10AA305) manually from local SVB Other On-off valves are closed Flow rate: 70 m 3 /hr Duration: 10 minutes or until effluent is clear Illustration: AA301 CLARIFIED WATER TRANSFER PUMP A/B (10GNK31/32AP001) A/C FILTER WWTP (10GNB10AT001) NEUTRALIZATION PIT (10UGU10BB001) P AA304 AA302 AA305 AA303 P FI (10GNK21CF501) CP501 CP502 MH WASTEWATER PIT (10UGN10BB001) BACKWASH PUMP A/B (10GNK61/62AP001) AA501
Note: Open Air Vent valve (10GNB10AA501) once a day, anytime of the day, to release some air trapped in vessel
Uong Bi 300MW Extension Power Plant Goshu Kohsan Co., Ltd. M4/5/6 Water and Wastewater Treatment
Pre-Com and Commissioning Manual Page 60 of 71 09 Jan., 06 Rev. A 3.) Backwashing Purpose: To remove foreign particles of filter media Operation: Stop Clarified water transfer pump A/B (10GNK31/32AP001) manually from LOP Close On-off valve (10GNB10AA301, 10GNB10AA305) manually from local SVB Start Backwash pump A/B (10GNK61/62AP001) manually from LOP Open On-off valve (10GNB10AA303, 10GNB10AA304) manually from local SVB Other On-off valves are closed Flow rate: 70 m 3 /hr Duration: 10 minutes Illustration: AA301 CLARIFIED WATER TRANSFER PUMP A/B (10GNK31/32AP001) A/C FILTER WWTP (10GNB10AT001) NEUTRALIZATION PIT (10UGU10BB001) P AA304 AA302 AA305 AA303 P FI (10GNK21CF501) CP501 CP502 MH WASTEWATER PIT (10UGN10BB001) BACKWASH PUMP A/B (10GNK61/62AP001) AA501
Uong Bi 300MW Extension Power Plant Goshu Kohsan Co., Ltd. M4/5/6 Water and Wastewater Treatment
Pre-Com and Commissioning Manual Page 61 of 71 09 Jan., 06 Rev. A 4.) Stop Purpose: To allow floating filter media to settle by gravity Operation: Stop Backwash pump A/B (10GNK61/62AP001) manually from LOP Close On-off valve (10GNB10AA303, 10GNB10AA304) manually from local SVB Other On-off valves are closed Flow rate: 0 m 3 /hr Duration: 10 minutes Illustration: AA301 CLARIFIED WATER TRANSFER PUMP A/B (10GNK31/32AP001) A/C FILTER WWTP (10GNB10AT001) NEUTRALIZATION PIT (10UGU10BB001) P AA304 AA302 AA305 AA303 P FI (10GNK21CF501) CP501 CP502 MH WASTEWATER PIT (10UGN10BB001) BACKWASH PUMP A/B (10GNK61/62AP001) AA501
Uong Bi 300MW Extension Power Plant Goshu Kohsan Co., Ltd. M4/5/6 Water and Wastewater Treatment
Pre-Com and Commissioning Manual Page 62 of 71 09 Jan., 06 Rev. A 5.) Washing Purpose: To remove foreign particles remaining in the bottom of filter bed Operation: Start Clarified water transfer pump A/B (10GNK31/32AP001) manually from LOP Open On-off valve (10GNB10AA301, 10GNB10AA305) manually from local SVB Other On-off valves are closed Flow rate: 40 m 3 /hr Duration: 10 minutes Illustration: AA301 CLARIFIED WATER TRANSFER PUMP A/B (10GNK31/32AP001) A/C FILTER WWTP (10GNB10AT001) NEUTRALIZATION PIT (10UGU10BB001) P AA304 AA302 AA305 AA303 P FI (10GNK21CF501) CP501 CP502 MH WASTEWATER PIT (10UGN10BB001) BACKWASH PUMP A/B (10GNK61/62AP001) AA501
Uong Bi 300MW Extension Power Plant Goshu Kohsan Co., Ltd. M4/5/6 Water and Wastewater Treatment
Pre-Com and Commissioning Manual Page 63 of 71 09 Jan., 06 Rev. A 6.) Service Purpose: To filtered wastewater Operation: Keep Clarified water transfer pump A/B (10GNK31/32AP001) running Keep On-off valve (10GNB10AA301) open Close On-off valve (10GNB10AA305) manually from local SVB Open On-off valve (10GNB10AA302) manually from local SVB Other On-off valves are closed Flow rate: 70 m 3 /hr Duration: 10 minutes Illustration: AA301 CLARIFIED WATER TRANSFER PUMP A/B (10GNK31/32AP001) A/C FILTER WWTP (10GNB10AT001) NEUTRALIZATION PIT (10UGU10BB001) P AA304 AA302 AA305 AA303 P FI (10GNK21CF501) CP501 CP502 MH WASTEWATER PIT (10UGN10BB001) BACKWASH PUMP A/B (10GNK61/62AP001) AA501
Uong Bi 300MW Extension Power Plant Goshu Kohsan Co., Ltd. M4/5/6 Water and Wastewater Treatment
Pre-Com and Commissioning Manual Page 64 of 71 09 Jan., 06 Rev. A 2.2. ELECTRICAL & INSTRUMENT EQUIPMENT PRE-COMMISSIONING
1. MCC POWER ENERGIZE Procedure: 1. Prior to energizing the MCC, the operator should check selector switches of each MCC module for equipments such as pumps, blowers, agitators, etc., if they are in OFF position. Release to Local signal from MMI shall not be activated (Logic = 0). Below is a list of equipments with their respective local control panels: NO KKS NO EQUIPMENT NAME LOP NO 1 10GBN11AP001 COAGULATION FEED PUMP 1A 10GBY10CX101 2 10GBN12AP001 COAGULATION FEED PUMP 1B 10GBY10CX101 3 10GNN11AP001 COAGULATION FEED PUMP 2A 10GBY10CX101 4 10GNN12AP001 COAGULATION FEED PUMP 2B 10GBY10CX101 5 10GBN10AM001 COAG DISSOLVING TANK AGITATOR 10GBY10CX101 6 10GBN21AP001 NaOCl FEED PUMP 1A 10GBY10CX102 7 10GBN22AP001 NaOCl FEED PUMP 1B 10GBY10CX102 8 10GRN11AP001 NaOCl FEED PUMP 2A 10GBY10CX102 9 10GRN12AP001 NaOCl FEED PUMP 2B 10GBY10CX102 10 10GBN31AP001 POLYMER FEED PUMP 1A 10GBY10CX103 11 10GBN32AP001 POLYMER FEED PUMP 1B 10GBY10CX103 12 10GNN21AP001 POLYMER FEED PUMP 2A 10GBY10CX103 13 10GNN22AP001 POLYMER FEED PUMP 2B 10GBY10CX103 14 10GBD11AM001 CLARIFIER TANK A AGITATOR 10GBY10CX104 15 10GBD12AM001 CLARIFIER TANK B AGITATOR 10GBY10CX105 16 10GBK21AP001 UNDERFLOW SLUDGE PUMP A 10GBY10CX106 17 10GBK22AP001 UNDERFLOW SLUDGE PUMP B 10GBY10CX106 18 10GBK31AP001 FILTERED WATER PUMP A 10GBY10CX106 19 10GBK32AP001 FILTERED WATER PUMP B 10GBY10CX106 20 10GBC11AN001 AIR BLOWER A 10GBY10CX106 21 10GBC12AN001 AIR BLOWER B 10GBY10CX106 22 10GBK11AP001 BACKWASH WATER PUMP A 10GBY10CX107 23 10GBK12AP001 BACKWASH WATER PUMP B 10GBY10CX107 24 10GBK41AP001 FILTERED WATER TRANSFER PUMP A 10GBY10CX107 25 10GBK42AP001 FILTERED WATER TRANSFER PUMP B 10GBY10CX107 26 10GKA11AP001 PORTABLE WATER PUMP A 10GBY10CX108 27 10GKA12AP001 PORTABLE WATER PUMP B 10GBY10CX108 28 10GCK21AP001 BOOSTER PUMP A 10GCY10CX101 29 10GCK22AP001 BOOSTER PUMP B 10GCY10CX101 30 10GCH11AN001 DEGASIFIER BLOWER A 10GCY10CX101 31 10GCH12AN001 DEGASIFIER BLOWER B 10GCY10CX101 32 10GCN11AP001 HCl FEED PUMP 1A 10GCY10CX102 33 10GCN12AP001 HCl FEED PUMP 1B 10GCY10CX102 34 10GNN30AP001 HCl FEED PUMP 2A 10GCY10CX102 Uong Bi 300MW Extension Power Plant Goshu Kohsan Co., Ltd. M4/5/6 Water and Wastewater Treatment
Pre-Com and Commissioning Manual Page 65 of 71 09 Jan., 06 Rev. A NO KKS NO EQUIPMENT NAME LOP NO 35 10GNN40AP001 HCl FEED PUMP 2B 10GCY10CX102 36 10GCN21AP001 NaOH FEED PUMP 1A 10GCY10CX103 37 10GCN22AP001 NaOH FEED PUMP 1B 10GCY10CX103 38 10GBN41AP001 NaOH FEED PUMP 2A 10GCY10CX103 39 10GBN42AP001 NaOH FEED PUMP 2B 10GCY10CX103 40 10GNN50AP001 NaOH FEED PUMP 3A 10GCY10CX103 41 10GNN60AP001 NaOH FEED PUMP 3B 10GCY10CX103 42 10GCK51AP001 NEUT WATER DISPOSAL PUMP A 10GCY10CX104 43 10GCK52AP001 NEUT WATER DISPOSAL PUMP B 10GCY10CX104 44 10GCK41AP001 DEMIN WATER TRANSFER PUMP A 10GCY10CX105 45 10GCK42AP001 DEMIN WATER TRANSFER PUMP B 10GCY10CX105 46 10GCK31AP001 REGENERATION PUMP A 10GCY10CX105 47 10GCK32AP001 REGENERATION PUMP B 10GCY10CX105 48 10GCK11AP001 DEMIN FEED PUMP A 10GCY10CX107 49 10GCK12AP001 DEMIN FEED PUMP B 10GCY10CX107 50 10GNK11AP001 OILY WASTEWATER PUMP A 10GNY10CX101 51 10GNK12AP001 OILY WASTEWATER PUMP B 10GNY10CX101 52 10GNC11AN001 MIXING BLOWER A 10GNY10CX102 53 10GNC12AN001 MIXING BLOWER B 10GNY10CX102 54 10GNK41AP001 THINNER SLUDGE PUMP A 10GNY10CX102 55 10GNK42AP001 THINNER SLUDGE PUMP B 10GNY10CX102 56 10GNK71AP001 THICKER SLUDGE PUMP A 10GNY10CX103 57 10GNK72AP001 THICKER SLUDGE PUMP B 10GNY10CX103 58 10GNK21AP001 WASTEWATER PUMP A 10GNY10CX103 59 10GNK22AP001 WASTEWATER PUMP B 10GNY10CX103 60 10GNK61AP001 BACKWASH PUMP A 10GNY10CX104 61 10GNK62AP001 BACKWASH PUMP B 10GNY10CX104 62 10GNK51AP001 TREATED WATER PUMP A 10GNY10CX104 63 10GNK52AP001 TREATED WATER PUMP B 10GNY10CX104 64 10GNK31AP001 CLARIFIED WATER TRANSFER PUMP A 10GNY10CX104 65 10GNK32AP001 CLARIFIED WATER TRANSFER PUMP B 10GNY10CX104 66 10GNS10AM001 SLUDGE RECIEVER TANK AGITATOR 10GNY10CX105 67 10GND10AM001 WWTP CLARIFIER TANK AGITATOR 10GNY10CX106 68 10GNE10AM001 pH ADJUSTMENT PIT AGITATOR 10GNY10CX107 69 10GNE20AM001 MIXING PIT AGITATOR 10GNY10CX107 70 10GNE30AM001 NEUTRALIZATION PIT AGITATOR 10GNY10CX107 71 10GRK11AP001 DWWTP SLUDGE PUMP A 10GNY10CX108 72 10GRK12AP001 DWWTP SLUDGE PUMP B 10GNY10CX108 73 10GRC11AN001 BLOWER A 10GNY10CX109 74 10GRC12AN001 BLOWER B 10GNY10CX109 Uong Bi 300MW Extension Power Plant Goshu Kohsan Co., Ltd. M4/5/6 Water and Wastewater Treatment
Pre-Com and Commissioning Manual Page 66 of 71 09 Jan., 06 Rev. A 2. Energizing the MCC Refer to separate manual of MCC for energizing procedure Select the following motor starter modules to remote mode operation
RAW WATER TREATMENT SYSTEM
NO KKS NO EQUIPMENT NAME 1 10GBK31AP001/10GBK32AP001 FITERED WATER PUMP A/B 2 10GBK11AP001/10GBK12AP001 BACKWASH WATER PUMP A/B 3 10GKA11AP001/10GKA12AP001 PORTABLE WATER PUMP A/B 4 10GBK21AP001/10GBK22AP001 UNDERFLOW SLUDGE PUMP A/B 5 10GBC11AN001/10GBC12AN001 AIR BLOWER A/B 6 10GBK41AP001/10GBK42AP001 FILTERED WATER TRANSFER PUMP A/B 7 10GBD11AM001/10GBD12AM001 CLARIFIER TANK A/B AGITATOR 8 10GBN10AM001 COAGULATION DISOVING TANK AGITATOR 9 10GBN11AP001/10GBN12AP001 COAGULATION FEED PUMP 1A/1B 10 10GBN21AP001/10GBN22AP001 NaOCl FEED PUMP 1A/1B 11 10GBN31AP001/10GBN32AP001 POLYMER FEED PUMP 1A/1B 12 10GBN41AP001/10GBN42AP001 NaOH FEED PUMP 2A/2B
DEMINERALIZATION SYSTEM
NO KKS NO EQUIPMENT NAME 1 10GCK11AP001/10GCK12AP001 DEMIN FEED PUMP A/B 2 10GCH11AN001/10GCH12AN001 DEGASIFIER BLOWER A/B 3 10GCK21AP001/10GCK22AP001 BOOSTER PUMP A/B 4 10GCK41AP001/10GCK42AP001 DEMINERALIZED WATER TRANSFER PUMP A/B 5 10GCK31AP001/10GCK32AP001 REGENERATION PUMP A/B 6 10GCN11AP001/10GCN12AP001 HCl FEED PUMP 1A/1B 7 10GCN21AP001/10GCN22AP001 NaOH FEED PUMPS 1A/1B 8 10GCK51AP001/10GCK52AP001 NEUTRALIZED WATER DISPOSAL PUMP A/B
WASTEWATER TREATMENT PLANT
NO KKS NO EQUIPMENT NAME 1 10GNK11AP001/10GNK12AP001 OILY WASTEWATER PUMP A/B 2 10GNC11AN001/10GNC12AN001 MIXING BLOWER A/B 3 10GNK21AP001/10GNK22AP001 WASTEWATER PUMP A/B 4 10GNK31AP001/10GNK32AP001 CLARIFIED WATER TRANSFER PUMP A/B 5 10GNK61AP001/10GNK62AP001 BACKWASH PUMP A/B 6 10GNK51AP001/10GNK52AP001 TREATED WATER PUMP A/B 7 10GNK41AP001/10GNK42AP001 THINNER SLUDGE PUMPS A/B 8 10GNK71AP001/10GNK72AP001 THICKENER SLUDGE PUMPS A/B Uong Bi 300MW Extension Power Plant Goshu Kohsan Co., Ltd. M4/5/6 Water and Wastewater Treatment
3. Energize each equipment in the MCC as per following requirements For equipment with auto-mode/ manual-mode, select of each equipment via MMI Operation mode of each equipment shall be selected to the following;
RAW WATER SYSTEM
NO EQUIPMENT NAME AUTO MANUAL STAND-BY LOP NO. 1 COAGULATION DISSOLVING TANK AGITATOR N/A 10GBN10AM001 - 10GBY10CX101 2 COAGULATION FEED PUMP 1A/1B 10GBN11AP001 SELECTABLE 10GBN12AP001 10GBY10CX101 3 NaOCl FEED PUMP 1A/1B 10GBN21AP001 SELECTABLE 10GBN22AP001 10GBY10CX102 4 POLYMER FEED PUMP 1A 10GBN31AP001 SELECTABLE - 10GBY10CX103 5 POLYMER FEED PUMP 1B 10GBN32AP001 SELECTABLE - 10GBY10CX103 6 NaOH FEED PUMP 2A/2B 10GBN41AP001 SELECTABLE 10GBN42AP001 10GCY10CX103 7 CLARIFIER TANK A AGITATOR 10GBD11AM001 SELECTABLE - 10GBY10CX104 8 CLARIFIER TANK B AGITATOR 10GBD12AM001 SELECTABLE - 10GBY10CX105 9 FILTERED WATER PUMP A/B 10GBK31AP001 SELECTABLE 10GBK32AP001 10GBY10CX106 10 AIR BLOWER A/B 10GBC11AN001 SELECTABLE 10GBC12AN001 10GBY10CX106 11 UNDERFLOW SLUDGE PUMP A/B 10GBK21AP001 SELECTABLE 10GBK22AP001 10GBY10CX106 12 BACKWASH WATER PUMP A/B 10GBK11AP001 SELECTABLE 10GBK12AP001 10GBY10CX107 13 FILTERED WATER TRANSFER PUMP A/B N/A 10GBK41AP001 10GBK42AP001 10GBY10CX107 14 POTABLE WATER PUMP A/B N/A 10GKA11AP001 10GKA12AP001 10GBY10CX108
DEMINERALIZATION SYSTEM
NO EQUIPMENT NAME AUTO MANUAL STAND-BY LOP NO. 1 DEGASIFIER BLOWER A 10GCH11AN001 SELECTABLE - 10GCY10CX101 2 DEGASIFIER BLOWER B 10GCH12AN001 SELECTABLE 10GCH12AN001 10GCY10CX101 3 BOOSTER PUMP A 10GCK21AP001 SELECTABLE - 10GCY10CX101 4 BOOSTER PUMP B 10GCK22AP001 SELECTABLE - 10GCY10CX101 Uong Bi 300MW Extension Power Plant Goshu Kohsan Co., Ltd. M4/5/6 Water and Wastewater Treatment
Pre-Com and Commissioning Manual Page 68 of 71 09 Jan., 06 Rev. A NO EQUIPMENT NAME AUTO MANUAL STAND-BY LOP NO. 5 HCl FEED PUMP 1A/1B 10GCN11AP001 SELECTABLE 10GCN12AP001 10GCY10CX102 6 NaOH FEED PUMP 1A/1B 10GCN21AP001 SELECTABLE 10GCN22AP001 10GCY10CX103 7 NEUTRALIZED WATER DISPOSAL PUMP A/B 10GCK51AP001 SELECTABLE 10GCK52AP001 10GCY10CX104 8 DEMINERALIZED WATER TRANSFER PUMP A N/A 10GCK41AP001 - 10GCY10CX105 9 DEMINERALIZED WATER TRANSFER PUMP B N/A 10GCK42AP001 - 10GCY10CX105 10 REGENERATION PUMP A/B 10GCK31AP001 SELECTABLE 10GCK32AP001 10GCY10CX105 11 DEMIN FEED PUMP A/B 10GCK11AP001 SELECTABLE 10GCK12AP001 10GCY10CX107
Uong Bi 300MW Extension Power Plant Goshu Kohsan Co., Ltd. M4/5/6 Water and Wastewater Treatment
Pre-Com and Commissioning Manual Page 69 of 71 09 Jan., 06 Rev. A 2. MCC FUNCTION TEST
Refer to Appendix __
3. MOTOR NO-LOAD TEST
Procedure The procedure of pre-commissioning works for the above check-items of Electrical and Instrument Equipment shall be based on GKC Standard Procedure. Electric motors of equipments subject for Motor no-load test are listed in table below.
RAW WATER TREATMENT SYSTEM
NO KKS NO EQUIPMENT NAME 1 10GAF10AP001 FRESHWATER SUPPLY PUMP 2 10GBK31AP001/10GBK32AP001 FITERED WATER PUMP A/B 3 10GBK11AP001/10GBK12AP001 BACKWASH WATER PUMP A/B 4 10GKA11AP001/10GKA12AP001 POTABLE WATER PUMP A/B 5 10GBK21AP001/10GBK22AP001 UNDERFLOW SLUDGE PUMP A/B 6 10GBC11AN001/10GBC12AN001 AIR BLOWER A/B 7 10GBK41AP001/10GBK42AP001 FILTERED WATER TRANSFER PUMP A/B 8 10GBD11AM001/10GBD12AM001 CLARIFIER TANK A/B AGITATOR 9 10GBN10AM001 COAGULATION DISOVING TANK AGITATOR
DEMINERALIZATION SYSTEM
NO KKS NO EQUIPMENT NAME 1 10GCK11AP001/10GCK12AP001 DEMIN FEED PUMP A/B 2 10GCH11AN001/10GCH12AN001 DEGASIFIER BLOWER A/B 3 10GCK21AP001/10GCK22AP001 BOOSTER PUMP A/B 4 10GCK41AP001/10GCK42AP001 DEMINERALIZED WATER TRANSFER PUMP A/B 5 10GCK31AP001/10GCK32AP001 REGENERATION PUMP A/B 6 10GCK51AP001/10GCK52AP001 NEUTRALIZED WATER DISPOSAL PUMP A/B
WASTEWATER TREATMENT PLANT
NO KKS NO EQUIPMENT NAME 1 10GNK11AP001/10GNK12AP001 OILY WASTEWATER PUMP A/B 2 10GNC11AN001/10GNC12AN001 MIXING BLOWER A/B 3 10GNK21AP001/10GNK22AP001 WASTEWATER PUMP A/B 4 10GNK31AP001/10GNK32AP001 CLARIFIED WATER TRANSFER PUMP A/B 5 10GNK61AP001/10GNK62AP001 BACKWASH PUMP A/B 6 10GNK51AP001/10GNK52AP001 TREATED WATER PUMP A/B 7 10GNK41AP001/10GNK42AP001 THINNER SLUDGE PUMP A/B Uong Bi 300MW Extension Power Plant Goshu Kohsan Co., Ltd. M4/5/6 Water and Wastewater Treatment
Pre-Com and Commissioning Manual Page 70 of 71 09 Jan., 06 Rev. A NO KKS NO EQUIPMENT NAME 8 10GNK71AP001/10GNK72AP001 THICKENER SLUDGE PUMP A/B 9 10GND10AM001 WWTP CLARIFIER TANK AGITATOR 10 10GNE10AM001 pH ADJUSTMENT PIT AGITATOR 11 10GNE20AM001 MIXING PIT AGITATOR 12 10GNE30AM001 NEUTRALIZATION PIT AGITATOR 13 10GNS10AM001 SLUDGE RECEIVER TANK AGITATOR 14 10GRC11AN001/10GRC12AN001 BLOWER A/B 15 10GRK11AP001/10GRK12AP001 SLUDGE PUMP A/B
4. ON-OFF VALVE LOOP TEST
Refer to Appendix __
5. INSTRUMENT LOOP TEST
Refer to Appendix __
6. SYSTEM FUNCTION TEST
Refer to Appendix __
7. INPUT-OUTPUT TEST
Refer to Appendix __
8. SEQUENCE TEST
Refer to Appendix __
Uong Bi 300MW Extension Power Plant Goshu Kohsan Co., Ltd. M4/5/6 Water and Wastewater Treatment
Pre-Com and Commissioning Manual Page 71 of 71 09 Jan., 06 Rev. A 3. COMMISSIONING
GKC and Lilama Staffs shall together perform the Commissioning Work, or if necessary, with EVN Staff also. GKC Staff shall explain the operation of the Water Treatment Plant and train Lilama and EVN Staffs, as well.
3.1. PERFORMANCE TEST
General: Performance Test shall be done by running the plant for two cycles. Demineralized and Condensate water quality shall be checked with conductivity meters. Commissioning results shall be recorded in the Commissioning Result form. Period of commissioning shall be referred to the Table below;
Table: Commissioning Period ITEMS SYSTEM Treating Capacity x Cycle Analysis (Raw/Treated) Mechanical Electrical Gravity Filter 105 m 3 /hr x 2 2 x 2 x 2 x Carbon Filter (Potable) 90 m 3 /day x 2 2 x 2 x 2 x Carbon Filter (Demin) 41 m 3 /hr x 2 2 x 2 x 2 x Demineralizer Trains 41 m 3 /hr x 2 2 x 2 x 2 x Carbon Filter (WWTP) 70 m 3 /hr x 2 2 x 2 x 2 x
Procedure: 1. Run the plant for 24 hours per day for 2 days. 2. Take data of influent flowrates for Clarifier Tank, Gravity Filter, Carbon Filter, Cation Exchanger, Anion Exchanger, and Mixed Bed Exchanger every hour. 3. Take data of pressures for Gravity Filter, Carbon Filters, Cation Exchanger, Anion Exchanger, and Mixed Bed Exchanger every hour. 4. Take data of conductivity for Anion Exchanger and Mixed Bed Exchanger every hour. 5. Take data of pH in Clarifier Tank every hour. 6. Take sampling at sampling cocks of Gravity Filter, Carbon Filters, Anion Exchanger, and Mixed Bed Exchanger every 4 hours for analysis. GKC and Lilama will take sampling at the same time and perform internal analysis for comparison purposes. 7. Take note of the running time of first on-line Demineralizer train following switched-over of the standby train. 8. Take note of the duration of regeneration period in every regeneration cycle.