BOQ

Project : PROPOSED COMMERCIAL COMPLEX


Client : Mr. SANJIV M
Location : KML LAYOUT, BANGALORE.
Date : 07-07-2012
DESCRIPTION OF WORK
QUANTIT
Y
UNIT RATE AMOUNT
1 EXCAVATION
Note : The rates quoted for the
relevant excavation items, shall
include for the following :
Shorting, strutting, protecting the
sides of excavation trenches
wherever required and dewatering
with pups wherever required and
diverting the water etc,.
Earthwork excavation in ordinary
and /or hard soil for isolated column
footings,SSM,plinth beams up to
2.5m depth. and Mass earth work
excavation at site using J.C.B
668.93 Cum
2
REFILLING
Refilling in foundation trenches and
below flooring with the excavated
earth including watering,
compacting and consolidating in
layers not exceeding 150mm thk
using 10 ton rollers or mechanical
compaction machines to obtain
95% modified proctors density and
lead upto 200 m.
301.00 Cum
Remarks and notes
3 ANTI-TERMITE
Anti-termite for footing area 600.77 Sqm
4 PLAIN CEMENT CONCRETE
Providing and laying PCC 1:4:8
using 40mm granite aggregate
below foundation and below flooring
as leveling course including
nominal edge shuttering, form work,
ramming, compacting and curing.
46.37 Cum
5
REINFORCED CEMENT
CONCRETE
ITEM
NUMBE
R
Providing, and laying READY
MIXED CONCRETE / cast-in-situ
of Grade M20 from approved
locally available MIX using 20 mm
and down grade stone aggregate
laid in layers and compacted
including pumping, vibration, curing,
lead, lift etc. and excluding steel
reiforcement, insert plates,
centering, shuttering, form work
either straight or tapered which will
be measured separately under
relevant items.
5.1
Do- as above item but for
Column Footing 156.86 Cum
5.2 Do- but for columns
a. Basement floor and below PB 15.84 Cum
b. Ground floor 12.60 Cum
c. Mezzanine floor 12.60 Cum
d. First floor 10.64 Cum
e. Second floor 10.64 Cum
f. Staircase head room 1.51 Cum
5.3 Do- but for plinth beam 4.66 Cum
5.4 Do- but for roof beam
a. Basement floor 25.00 Cum
b. Ground floor 25.00 Cum
c. Mezzanine floor 25.00 Cum
d. First floor 26.00 Cum
e. Second floor 26.00 Cum
f. Staircase head room 1.98 Cum
5.5 Do- but for roof slab
a. Basement floor 36.10 Cum
b. Ground floor 36.10 Cum
c. Mezzanine floor 28.08 Cum
d. First floor 36.90 Cum
e. Second floor 36.90 Cum
f. Staircase head room 3.06 Cum
5.6 Do- but for lintel
a. Basement floor 0.71 Cum
b. Ground floor 0.71 Cum
c. Mezzanine floor 0.71 Cum
d. First floor 0.71 Cum
e. Second floor 0.71 Cum
f. Staircase head room 0.18 Cum
5.7 Do- but for Chajja
a. Basement floor 0.48 Cum
b. Ground floor 0.48 Cum
c. Mezzanine floor 0.48 Cum
d. First floor 0.48 Cum
e. Second floor 0.48 Cum
f. Staircase head room 0.15 Cum
6 WATER TANK
a) Sump tank 8000.00 Litre
b) Over head tank 6000.00 Litre
7 MASONRY
7.1
Providing and laying size stone
masonry (S.S.M) in CM 1:8 in
courses not less then 200 high for
foundation and plinth with through
bond intervals including dressing,
raking, out and flushing the joints,
scaffolding and curing.
23.90 Cum
7.2
Providing and constructing 200mm
thick solid block masonry in cement
mortar [1:5] all complete including
racking of joints, scaffolding, curing
etc. complete.
a. Basement floor 200.25 Sqm
b. Ground floor 244.08 Sqm
c. Mezzanine floor 244.08 Sqm
d. First floor 244.08 Sqm
e. Second floor 244.08 Sqm
f. Staircase head room 72.75 Sqm
g. Parapet wall 58.85 Sqm
8 PLASTERING
Note: For the following items the
rates quoted shall include for all
drip moulds, throating arises etc.,
as and where directed. The rates
quoted shall also include for making
good chases, patches, etc., made
by other agencies.
providing and laying 15 to 20mm
thick cement plaster in CM 1:6 to
brick masonry walls, stone masonry
walls, beams, projections including
hacking the surface and sponge
finish etc.
8.1 Plastering inside
a. Basement floor 413.03 Sqm
b. Ground floor 413.03 Sqm
c. Mezzanine floor 413.03 Sqm
d. First floor 413.03 Sqm
e. Second floor 413.03 Sqm
f. Staircase head room 55.05 Sqm
8.2 Plastering outside
a. Basement floor 263.72 Sqm
b. Ground floor 263.72 Sqm
c. Mezzanine floor 263.72 Sqm
d. First floor 263.72 Sqm
e. Second floor 263.72 Sqm
f. Staircase head room 61.23 Sqm
g. Parapet wall 129.47 Sqm
9 FORM WORK
Note: With reference to the
following form work items, the rates
quoted shall include propping,
bracing, shoring, strutting, bolting,
wedging, oiling and all temporary
supports with 4mm thick steel
sheets stiffened with angle iron
frame made out of M.S angle
40X40X6 for slabs and 12mm thick
film faced water proof plywood for
beams,columns,lintel or wherever
recommended. Cost to include
sealing the joints with heavy duty
brown self adhesive tape.
Formwork to be removed after
taking permission from Engineer -in
-charge.
9.1 Do- but for column
a. Basement floor and below PB 119.04 Sqm
b. Ground floor 94.74 Sqm
c. Mezzanine floor 94.74 Sqm
d. First floor 94.74 Sqm
e. Second floor 94.74 Sqm
f. Staircase head room 24.20 Sqm
9.2 Do- but for Plinth beam 79.65 Sqm
9.3 Do- but for roof beam
a. Basement floor 163.78 Sqm
b. Ground floor 163.78 Sqm
c. Mezzanine floor 163.78 Sqm
d. First floor 163.78 Sqm
e. Second floor 163.78 Sqm
f. Staircase head room 24.20 Sqm
9.4 Do- but for roof slab
a. Basement floor 246.00 Sqm
b. Ground floor 246.00 Sqm
c. Mezzanine floor 246.00 Sqm
d. First floor 246.00 Sqm
e. Second floor 246.00 Sqm
f. Staircase head room 24.45 Sqm
9.5 Do- but for Lintel
a. Basement floor 9.52 Sqm
b. Ground floor 9.52 Sqm
c. Mezzanine floor 9.52 Sqm
d. First floor 9.52 Sqm
e. Second floor 9.52 Sqm
f. Staircase head room 1.76 Sqm
9.6 Do- but for Chajja
a. Basement floor 10.71 Sqm
b. Ground floor 10.71 Sqm
c. Mezzanine floor 10.71 Sqm
d. First floor 10.71 Sqm
e. Second floor 10.71 Sqm
f. Staircase head room 1.98 Sqm
10 REINFORCEMENT
Supplying, fabricating and fixing in
position MS Bars confirming to IS-
432/ High yield strength deformed
bars (Tor steel) confirming to IS-
1786 of Fe415 grade of all dia for
reinforcement in all RCC in situ
works including flooring and precast
works at all levels and heights
including cost of straitening, cutting
bending to shape fabricating and
tying with 18G binding wire,
providing and fixing cement cover
blocks, dewatering wherever
necessary etc., all complete as per
drawings and specifications. The
rate to include cost of binding wire,
cement cover blocks etc,.
70.00 MT
TOTAL