You are on page 1of 20

Basic Process Design

720 m/day

Airlift MBR Ultra Filtration







Client
GET Water solutions Pvt. Limited
Project name
720 KLD
Project No.
STP MBR
Norit company
X-Flow
Document status
Rev. Date Description Prepared Checked Approved
0 Nov 3
rd
, 2009 First issue PCGanesh





This document is property of X-Flow in Enschede. Nothing from this document may be duplicated and/or published without written
approval of the owner. 2007 X-Flow.


X-Flow Client: GET Water Solutions Pvt. Ltd.,
Know-How Centre Project: STP MBR



Basic Process Design Page 2 of 20
Revision 0, 09-91-TBA

Disclaimer
All information in this document is based on enquiry information and assumptions supplied by the
customer and not independently confirmed by X-Flow. X-Flow does not warrant the accuracy,
timeliness, completeness, adequacy or fitness of the information or the membrane design which
is based on this information and shall not be held liable to the customer or any third party with
respect to any alleged inaccuracy, incompleteness, inadequacy or lack of merchantability or
fitness for the purpose listed in this document.

X-Flow Client: GET Water Solutions Pvt. Ltd.,
Know-How Centre Project: STP MBR



Basic Process Design Page 3 of 20
Revision 0, 09-91-TBA

Revision History

Revision Description
0 First issue




Related documents

Doc. No. Originator Description Rev. Date











List of abbreviations

Abbreviation Description
AL Air Lift
BW Backwash
CA Citric Acid
CEB Chemical Enhanced Backwash
DC Drain
HC Hydraulic Clean
Lmh Litre/m
2
.h (membrane flux)
MBR Membrane Bioreactor
MLD Megalitres per day
MLSS Mixed liquor suspended solids
n.a. Not applicable
NaOCl Sodium hypochlorite
Nm
3
/h Airflow in normal cubic meters per hour (1bara, 20C)
TMP Trans Membrane Pressure
TSS Total suspended solids
VSD Variable Speed Drive
UF Ultra Filtration


X-Flow Client: GET Water Solutions Pvt. Ltd.,
Know-How Centre Project: STP MBR



Basic Process Design Page 4 of 20
Revision 0, 09-91-TBA

Contents
1 Introduction ______________________________________________________________________ 6
1.1 Project definition ______________________________________________________________ 6
1.2 Objective Basic Process Design __________________________________________________ 6
2 Basis of Design ___________________________________________________________________ 7
2.1 UF influent quality (mixed liquor)__________________________________________________ 7
2.2 Typical UF permeate quality _____________________________________________________ 7
2.3 Design capacity _______________________________________________________________ 7
3 Process Design ___________________________________________________________________ 8
3.1 Process summary _____________________________________________________________ 8
3.1.1 Filtration ______________________________________________________________ 9
3.1.2 Backwashing during filtration _____________________________________________ 9
3.1.3 Drain procedure ________________________________________________________ 9
3.1.4 Chemically enhanced backwash (CEB) ____________________________________ 10
3.1.5 Relaxation/ Stand-by ___________________________________________________ 11
3.2 UF plant design ______________________________________________________________ 12
3.2.1 Configuration UF plant _________________________________________________ 13
3.2.2 Main operational parameters ____________________________________________ 14
3.2.3 Chemical consumptions ________________________________________________ 16
3.2.4 Main process equipment ________________________ Error! Bookmark not defined.
4 Design Specifications _____________________________________________________________ 17
4.1 Pre-treatment _______________________________________________________________ 17
4.2 Bioreactor __________________________________________________________________ 17
4.3 Hydraulic design _____________________________________________________________ 17
4.3.1 Feed and permeate piping ______________________________________________ 17
4.3.2 Feed flow control during filtration, backwash and relaxation ____________________ 18
4.3.3 AirLift flow control _____________________________________________________ 18
4.3.4 Permeate flow control __________________________________________________ 18
4.3.5 Backwash flow control __________________________________________________ 18
4.3.6 UF skid pressures _____________________________________________________ 18
4.4 Permeate tank design _________________________________________________________ 19
4.5 Backwash strainers ___________________________________________________________ 19
4.6 Air ingress __________________________________________________________________ 19
4.7 Automatic valves _____________________________________________________________ 19
4.8 Chemical dosing for CEB ______________________________________________________ 19
4.9 Compressed air ______________________________________________________________ 19
4.10 Membrane storage ___________________________________________________________ 20
4.11 Facilities for commissioning and future operation ____________________________________ 20

X-Flow Client: GET Water Solutions Pvt. Ltd.,
Know-How Centre Project: STP MBR



Basic Process Design Page 5 of 20
Revision 0, 09-91-TBA

Tables
Table 2-1: UF influent quality ___________________________________________________________________ 7
Table 2-2: UF permeate quality _________________________________________________________________ 7
Table 2-3: UF capacity assumptions ______________________________________________________________
Table 3-1: Configuration UF plant ________________________________________________________________
Table 3-2: Main operational parameters per skid (filtration, backwash, drain and CEB)
Table 3-3: Typical chemical consumptions per skid __________________________________________________
Table 3-4: Main process equipment UF plant ________________________________________________________

X-Flow Client: GET Water Solutions Pvt. Ltd.,
Know-How Centre Project: STP MBR



Basic Process Design Page 6 of 20
Revision 0, 09-91-TBA

1 Introduction
1.1 Project definition
This document outlines the design for an Airlift MBR to be installed at projected site for the
purification of municipal waste water. The Airlift MBR process consists of an activated sludge
process combined with a side stream Ultra Filtration membrane system for the separation of
activated sludge (mixed liquor) from treated effluent. As an out of basin solution (not being
submerged in the reactor), maintenance and cleanability are simple, safe and allow full
automation. The UF membrane system is 100% efficient at separating mixed liquor from treated
effluent. Only the UF part is described in this document. The engineering of the pre-treatment
and bioreactor is the responsibility of Prakruti.

The overall process consists of the following treatment steps:
Pre-treatment
Pre- screen *)
Oil and grease removal *)
Sand removal *)
Fine- screen *)
Bioreactor
AirLift UF unit
Post chlorination

The UF stage comprises the following units and equipment:
UF mixed liquor recirculation pumps
UF air supply for airlift
UF skids
UF permeate extraction
UF permeate tank
UF drain tank and pumps
UF backwash pumps (incl. manual UF backwash strainer)
Chemical dosing units
Air compressor (instrument air)
*) to be optimised
1.2 Objective Basic Process Design
The Basic Process Design document provides the basic process design information of the UF
plant. The following items are described:
Basis of design
Process design
Design specifications
X-Flow Client: GET Water Solutions Pvt. Ltd.,
Know-How Centre Project: STP MBR



Basic Process Design Page 7 of 20
Revision 0, 09-91-TBA

2 Basis of Design
2.1 UF influent quality (mixed liquor)
The influent quality design envelope for the UF plant is presented in Table 2-1.
Table 2-1: UF influent quality
Parameter Units Min Avg Max Comment Note
Temperature C 20 - 40 1)
pH - 6 - 8.5 1)
Oil & grease [mg/l] n.p. n.p. n.p. n.p.: not present 3)
MLSS [g/l] g/l 8 10 14 Range between 8 14 g/l 2)
Filterability ml > 15 - -
Filterability is based on filtered amount
through C5- paper during 5 minutes
2)
1) X-Flow assumption of UF feed water quality;
2) Based on UF feed water quality data according to enquiry document (see related documents);
3) Oil& grease must be emulsified. Higher concentrations will have impact on cleaning frequency and plant capacity.
Free O&G is not allowed, since this can irreversibly foul the membranes. Soluble O&G will pass the membranes.
2.2 Typical UF permeate quality
The typical UF permeate quality for the UF plant is presented in Table 2-2.
Table 2-2: UF permeate quality
Parameter Units Min Avg Max Comment Note
Temperature C 20 - 40 Same as UF feed water quality.
pH - 6 - 9
TSS mg/l - - 0.5 95%ile on daily composite sample 1)
Turbidity NTU - - 0.5 95%ile on daily composite sample 1)
SDI - - 3 1)
1) X-Flow specification of permeate quality, based on historical data. No warranty figures.
2.3 Design capacity
The membrane system with the proposed amount of membrane modules is designed to
accommodate the capacity assumptions as presented in Table 2-3 at the feed water conditions
as specified in Table 2-1.
Table 2-3: UF capacity assumptions
Parameter Units Design Comment
Average flow operation flow m3/h 31
UF design is based on maximum flow
Average flow duration h/d 24
Maximum operation flow m3/h 31

Maximum flow duration h/d 4
Daily throughput m3/d 739

X-Flow Client: GET Water Solutions Pvt. Ltd.,
Know-How Centre Project: STP MBR



Basic Process Design Page 8 of 20
Revision 0, 09-91-TBA

3 Process Design
3.1 Process summary
The AirLift UF membrane system is a part of the MBR process and is applied to separate the
mixed liquor from treated effluent. The UF membrane system is fed with the mixed liquor from the
bioreactor by means of a recirculation pump. This recirculation pump is also used to maintain a
relatively constant flow of mixed liquor from the bottom to the top side of the vertically positioned
UF membranes. The three meter high membrane elements comprise tubular membranes with a
typical diameter of 5.2 mm. with a total of 33 m
2
of membrane area. These membrane tubes are
operated inside-out, i.e. mixed liquor is introduced at the lumen of the tubular membranes and
extracted as permeate at the shell side. The bottom side as well as the top side of the membrane
element are covered by an end cap. The bottom end cap is equipped with an air distribution
system (aerator). See below figure for a schematic layout of the AirLift MBR system.

Figure 3-1: Schematic representation of the AirLift MBR concept.



An AirLift membrane system is a modification of the conventional cross-flow membrane system
design in which the membrane modules are horizontally positioned. In an AirLift membrane
system the membrane modules are vertically positioned. This vertical orientation of the
membrane modules allows using air injection in the bottom end cap to maintain a gentle cross
flow through the membrane module. Due to this principle the mixed liquor is transported via an
Air-Lift pump through the membrane modules. In addition the injected air causes a very high
turbulence at the membrane surface and this ensures a continuous cleaning action and
subsequent constant system flux at a very low trans membrane pressure. While using the reliable
and proven technology of cross-flow tubular membranes the benefit of this AirLift system design
is that the energy consumption is significantly lower than the cross-flow system.

Back wash
Feed flow
De aeration
Air Lift
Drain
Permeate control
Chemical dosing
Bio reactor
X-Flow Client: GET Water Solutions Pvt. Ltd.,
Know-How Centre Project: STP MBR



Basic Process Design Page 9 of 20
Revision 0, 09-91-TBA

The filtrate (permeate) production of the AirLift system is measured by a flow transmitter and
controlled by an automatic control valve and/or permeate pump to meet the set-point production
flow. A part of the produced permeate is used for backwashing and cleaning operations of the UF
membrane elements in the system. For this purpose the system is equipped with a backwash
pump and dosing pumps.

3.1.1 Filtration
During production (filtration) operation of the plant, mixed liquor is pumped from the bioreactor
into the UF system by the recirculation pump. The recirculation pump ensures that a relatively
constant flow of mixed liquor from the bottom to the top of the membrane modules is established.
Air is injected via the bottom end cap air distribution system. The mixed liquor will be transported
upwards by air bubbles. In addition, each tubular membrane is scrubbed by the rising air bubbles
under turbulent conditions. The permeate production is controlled by an automatic control valve
and/or a permeate extraction pump to reach a constant permeate flow out of the AirLift system.

3.1.2 Backwashing during filtration
During operation (filtration) solids are retained by the membrane and some accumulate on the
membrane surface (inside) of the tubular membranes. These solids must be periodically removed
via backwashing to maintain system performance. For backwashing the flow direction through
the membranes is reversed. UF permeate is pumped into the membrane modules from outside to
inside of the tubular membranes by means of a variable speed backwash pump at a constant
preset flow. During this backwash the mixed liquor recirculation pump and air injection are kept
running to enhance solids removal and cleaning performance. Backwash waste is returned to the
bioreactor.

When using multiple skids, each skid is backwashed in a stream backwash. This means that
each skid in a section of skids is backwashed consecutively. A stream backwash is initiated after
a pre-set filtration time.

3.1.3 Drain procedure
The drain procedure is vital for proper operation of an Airlift MBR plant. It is also a feature that
makes the system unique because it ensures that no solids build-up (e.g. hairs) occurs at the
membranes. During the drain procedure the UF membrane skid is completely drained followed
by a automatic backwash. This sequence on the empty module is very effective; all material that
may have accumulated on the membrane surface and at the inlet (bottom side) of the membrane
module is drained and flushed out by this procedure. The subsequent backwash is very effective
because there is no re-circulation flow, the membrane feed side is empty. In addition, the air
distribution system in the bottom end cap and the air supply line to the distribution system is
flushed with UF permeate to prevent clogging. This drain procedure is typically executed 4 to 6
times a day. The collected mixed liquor from the drain procedure is routed back to the inlet
X-Flow Client: GET Water Solutions Pvt. Ltd.,
Know-How Centre Project: STP MBR



Basic Process Design Page 10 of 20
Revision 0, 09-91-TBA

strainer of the bioreactor, where any large particulate matter that may have formed in front of the
modules is removed from the system.

The drain sequence is also performed as:
Pre-step for chemical cleaning
After certain alarms or emergency stops
Pre-step before idle mode.

3.1.4 Chemically enhanced backwash (CEB)
Not all retained material can easily be removed by backwashes and drain procedures. Through
accumulation of absorbed substances onto the membrane surface, the pressure drop across the
membrane may increase gradually over the course of weeks or months. To remove these
substances and to restore the membrane performance a chemical enhanced backwash (CEB) is
required. The fully automatic CEB program is typically performed once per 1 to 3 months and if
possible during low flow hours, most likely at night, when full capacity is not required. Each skid
is cleaned separately while the other skids remain in production (filtration).

Before starting the CEB program the drain sequence is performed. After this drain sequence the
backwash pump is started at low flow, pumping UF permeate back into the membrane module.
At the same time cleaning chemicals (typically sodium hypochlorite or citric acid) are dosed in the
backwash line and transported into the membrane modules. After the membrane modules of the
skid are filled the backwash pump is stopped and the soak timer is started, typically between 30
to 240 minutes. After the soak timer has elapsed the membrane modules are drained. The
drained chemical solution is typically fed back to the bioreactor because the activity of the
chemicals is strongly reduced after the soak period and the total volume is relatively small in
respect of the bioreactor volume.

The CEB program is performed with two chemicals consecutively, sodium hypochlorite and citric
acid. CEB1 is typically performed with sodium hypochlorite at a concentration of 200 to 400 mg/l .
CEB 2 is typically performed using citric acid to pH ca. 3 to remove foulants and scaling.

Figure 3-2 shows an example of the change in Trans Membrane Pressure (TMP), during the
process. Stretches A depict the filtration, stretches B the backwashes or drain and stretch C
a Chemically Enhanced Backwash (CEB).
X-Flow Client: GET Water Solutions Pvt. Ltd.,
Know-How Centre Project: STP MBR



Basic Process Design Page 11 of 20
Revision 0, 09-91-TBA


Figure 3-2: Trans Membrane Pressure change during operation.
0,00
0,04
0,08
0,12
0,16
0,20
0,0 5,0 10,0 15,0 20,0 25,0 30,0
Time
T
r
a
n
s

m
e
m
b
r
a
n
e

P
r
e
s
s
u
r
e

(
B
a
r
)
A
B
A
B
Production
period
(2-10 wks)
C
A
A
B
B
A

3.1.5 Relaxation/ Stand-by
The total membrane system might consist of more than one membrane skid. During low feed flow
periods, skids are taken off line in order to reduce the energy consumption of the total plant.
Taking a skid off line means that the skid goes into relaxation mode. The recirculation pump and
air supply are kept running as for normal filtration, however the permeate abstraction (via control
valve or permeate pump) is de-activated. This means that all the feed water fed to the membrane
modules is returned to the bioreactor. Due to this fact there is no driving force across the
membrane surface (as the permeate production is stopped), hence the recirculation flow will
clean the membrane surface due to the shear force in combination with air scrubbing. During this
relaxation program the skid can be taken on-line at any moment. When a skid has been in
relaxation for a certain period of time (i.e. its capacity is not required by the process) the skid will
be drained and filled with permeate after which it will be waiting in stand-by mode.
X-Flow Client: GET Water Solutions Pvt. Ltd.,
Know-How Centre Project: STP MBR



Basic Process Design Page 12 of 20
Revision 0, 09-91-TBA


3.2 UF plant design
The UF plant consists of one or more sections. Each section comprises several membrane skids
with one dedicated backwash pump serving all the skids in that one section. See below Figure
3-3 for a graphical presentation of a section with membrane skids.

Figure 3-3: UF section


Each membrane skid comprises a fixed amount of membrane positions, not all of whom are
necessarily filled with membrane modules. See Figure 3-4 for a picture of one membrane skid.

Figure 3-4: UF skid (example with 10, 20 & 30 modules)


Each membrane skid is controlled individually, i.e. all operating programs such as filtration,
backwash, drain procedure and CEB are performed on a skid level. All the membrane skids in
one section are backwashed consecutively, i.e. in a so called stream backwash.
Section
comprises ten
membrane skids
Skid
with membrane
modules

X-Flow Client: GET Water Solutions Pvt. Ltd.,
Know-How Centre Project: STP MBR



Basic Process Design Page 13 of 20
Revision 0, 09-91-TBA


3.2.1 Configuration UF plant
Table 3-1: Configuration UF units
Parameter Units Design Actual Comment
No. of sections - 1 -
No. of skids per section - 1 -
No. modules per skid - 30 23 7 spare modules per unit
Membrane area per module m
2
33 -
Total membrane area m
2
990 759

Reference is made to the UF projections; see section related documents. Typically two
situations apply:

1. Scenario for Design: UF design values based on full skids. UF equipment is always sized to
accommodate full skids (i.e. skids with all modules installed).
2. Scenario for Actual: UF design based on 19 modules installed in one skid, to reflect actual
operating parameters.

In the paragraphs below the projection data is presented in tables including additional information
such as assumptions and conditions.

Note: All UF projections are based on a 24 hours daily operation and are theoretical values at skid flange
level. To select equipment safety margins have to be included!

X-Flow Client: GET Water Solutions Pvt. Ltd.,
Know-How Centre Project: STP MBR



Basic Process Design Page 14 of 20
Revision 0, 09-91-TBA

3.2.2 Main operational parameters
In Table 3-2, the operational settings per skid for each of the programs are presented.

Table 3-2: Main operational parameters per skid (filtration, backwash and drain)
Parameter Units Design Actual Comment
Gross permeate flow m
3
/h t.b.d. 38
Current flow during filtration
Net permeate flow m
3
/h t.b.d. 31

Feed (recirculation) flow m
3
/h 684 (1) 525 (2)

AirLift flow nm
3
/h 300 (1) 230 (2)
AirLift pressure bar 0.6 0.6
To be applied at skid connections
Filtration period min n.a. 7-10

Typical TMP during filtration bar 0.03-0.5 0.1-0.3
Operational TMP range for
filtration, based on extended
historical operational data.
Backwash flow per skid m
3
/h 297 228
Flux: 300 lmh (max 1bar!)
Backwash duration per skid sec n.a. 7-10
At full capacity
Trans Membrane Pressure (TMP)
during backwash
bar 0.5-1 0.5-1
Operational TMP range for
backwash, based on extended
historical operational data.
Drain procedure interval hr. 3 t.b.d.
Expected program time sec 60 40-60 T.b.d. during commissioning
Backwash flow per skid m
3
/h 297 228 Flux : 300 lmh
CEB1 chemical
- NaOCl -
For concentration and
consumption, see Table 3-3.
CEB2 chemical
- Citric Acid -
For concentration and
consumption, see Table 3-3.
CEB 1+2 interval per skid
days 24 30-120
Typical duration CEB 1
min 60 -
Typical duration CEB 2
min
>240
-
When possible overnight soaking
is advised
Backwash flow CEBs
m
3
/h 149 114 Flux :150 lmh













X-Flow Client: GET Water Solutions Pvt. Ltd.,
Know-How Centre Project: STP MBR



Basic Process Design Page 15 of 20
Revision 0, 09-91-TBA

Table 3-4: Main process equipment UF plant
Equipment No. Size Design basis
(Note 1) (Note 1)
UF recirculation pump 1
684 m3/h,
Head
t.b.d. by
client
UF feed supply at max. gross flux (see Table 3 2)
based on max. UF unit configuration (see Table 3 1).
Required head is max. UF unit pressure drop during
filtration (see Table 3 2) plus max. additional system
pressure drop (piping, strainer, static height
difference between suction and discharge, etc).
UF AirLift Blower 1
300
Nm3/h per
section,
Head
t.b.d. by
client
UF Airlift supply at max. gross flux (see Table 3 2)
based on max. UF unit configuration (see Table 3 1).
Required head is max. UF unit pressure drop (see
Table 3 2) plus max. additional system pressure drop
(piping, flow transmitter, etc). Maximum air
temperature at skid flange: 60 C.
UF permeate pump 1
50 m3/h,
Head
t.b.d. by
client
UF permeate based on max. UF unit configuration
(see Table 3 1). Required head is max. UF unit
pressure drop during filtration (see Table 3 2) plus
max. additional system pressure drop (piping, static
height difference between suction and discharge,
etc).
BW pump 1
297m3/h,
Head
t.b.d. by
client
UF BW supply at BW flux (see Table 3 2). Capacity
based on max. UF unit configuration (see Table 3 1).
Required head is max. UF unit pressure drop during
BW (see Table 3 2) plus max. additional system
pressure drop (piping, strainer, static height
difference between suction and discharge, etc).
BW Strainer 1
297 m3/h,
max.
screen 2
mm
Manual basket filter.
CEB NaOCl dosing pump 1
591 ltr/h
@ min. 3
bar
Achieving required CEB working concentration (see
Table 3 7) at BW flux during chemical dosing (see
Table 3 4). Capacity based on max UF unit
configuration (see Table 3 1) and 50% safety margin.
CEB CA dosing pump 1
3588 ltr/h
@ min. 3
bar
Achieving required CEB working concentration (see
Table 3 7) at BW flux during chemical dosing (see
Table 3 4). Capacity based on max UF unit
configuration (see Table 3 1) and 50% safety margin.
UF Permeate tank 1 18 m3 (2)
Minimum hold-up volume required to perform CEB
1+2 for one skid per section during the low flow
periods. Additional permeate storage volume is not
included.
UF Drain tank 1 14 m3 (2)
Buffer to control the drain unit, based on 2 times a
drain volume per skid, per section (incl. permeate
consumption).
X-Flow Client: GET Water Solutions Pvt. Ltd.,
Know-How Centre Project: STP MBR



Basic Process Design Page 16 of 20
Revision 0, 09-91-TBA

UF Drain pump 1
5 m3/h,
Head
t.b.d. by
client (1)
Based on minimal drain frequency per skid and 100%
safety margin.
3.2.3 Chemical consumptions
Table 3-3: Typical chemical consumptions per skid
Chemical Stock Working
conc. conc. Projection
l/CEB

% Design Actual
NaOCl (typical) 12.5 400 mg/l 12 9


All consumptions based on operational parameters as per Table 3-2 without any design margin.

Typical drain volumes
Program Step Volume (m3) Comment
Drain volume per skid
Drain 4.1
BW 2.9
Total 7.0 Based on 23 modules per skid
Drain volume total installation
Drain incl.
BW
2.1 Based on minimal drain frequency, see Table 3-3
at full capacity.


Typical permeate consumptions per skid per program.
Program Volume (m3) Comment
BW 0.8 Based on 30 modules per skid
Drain 2.2 Based on 30 modules per skid
CEB 1+2 13.2 Based on 30 modules per skid
Drain-Fill 6.3 Based on 30 modules per skid, before IDLE status






1 Numbers and capacities are based on duty only. Redundancy is not incorporated and should be addressed as per
customer redundancy philosophy
2 All tank sizes indicated above are net working volumes, i.e. volume between high and low level. For gross tank sizes,
additional volume to be included for low-low and high-high level, inlet and outlet piping, pump suction (avoiding vortex),
level switches, tank over flow, etc

X-Flow Client: GET Water Solutions Pvt. Ltd.,
Know-How Centre Project: STP MBR



Basic Process Design Page 17 of 20
Revision 0, 09-91-TBA

4 Design Specifications
Apart from the process design as described in the previous chapter, the following UF plant
design specifications apply which are described in subsequent sections. In addition, a short
description about membrane storage and commissioning and possibly future expansion of the UF
plant is given.

4.1 Pre-treatment
Although the Airlift system is much less susceptible to large particulate matter in the feed, the
final pretreatment step before the bioreactor shall consist of a reliable screen with a mesh no
larger than 800 m (typical a drum screen is used).

4.2 Bioreactor
The performance of the UF installation is directly related to the stability/ quality of the biomass in
the bioreactor. This requires a proper bioreactor design. For example the following points are
highlighted:
- Equal mixing
- Proper biomass control
- Proper Oxygen control
- Type of anti-foam (if used, it needs to be checked by X-Flow)
- Covering (if necessary for e.g. leaves and other dirts)

4.3 Hydraulic design
For safe and proper operation of the UF plant, serious attention shall be paid to the hydraulic
design of the UF plant during detailed engineering. In the subsequent sections important points
of attention are highlighted. Final responsibility for hydraulic UF plant design is with the customer.
However, as part of detailed engineering services, X-Flow can perform a review of the UF plant
layout drawings and advise on any potential required modifications or improvements.

4.3.1 Feed and permeate piping
The maximum pressure drop across the individual UF skid during filtration and backwash (flange
to flange, provided the maximum flow velocities are met) are specified in Table 3-2 of this
document. The acceptable velocities in the pipes associated with skids are as follow:

Water:
Feed/permeate piping (feed pump pressure side) : < 2 m/s
Backwash/concentrate piping (backwash pressure side) : < 3 m/s
Feed & backwash pump suction side : 0.5- 1 m/s


X-Flow Client: GET Water Solutions Pvt. Ltd.,
Know-How Centre Project: STP MBR



Basic Process Design Page 18 of 20
Revision 0, 09-91-TBA

Air:
Blower pressure side: < 20 m/s

Note:
The above specified velocities are not a guarantee for an equal flow distribution to the individual UF skids. It is
Important to choose a proper pipe size for the central header of a section in relation to each individual skid. An equal
air distribution to the UF skids is the responsibility of the costumer.

4.3.2 Feed flow control during filtration, backwash and relaxation
Each individual UF skid requires a feed flow control device with flow transmitter. Preferably this is
a dedicated centrifugal feed pump with variable speed drive (VSD) per UF skid. Accepted pump
speed is < 1000 rpm.

4.3.3 AirLift flow control
The air supply for the AirLift must be supplied by a frequency controlled blower, since the flow of
air will vary with required plant capacity. The air flow is measured in the central air supply line by
a flow transmitter. An equal flow distribution of the air to the individual skids is the responsibility
of the customer.

4.3.4 Permeate flow control
The permeate flow is controlled at each skid individually by means of an automatic flow control
valve and flow transmitter per skid. A frequency controlled permeate pump is/maybe required per
section of skids.

4.3.5 Backwash flow control
Each section of the total UF plant shall be equipped with a centrifugal frequency controlled
backwash pump. The frequency control on the pump motors is required for smooth ramping-up
(max ramp up time < 8 sec) and ramp down to the different flow setpoints for backwash and
CEB. Moreover, the frequency control is required for maintaining the required backwash flux
during the (short duration) backwash period. Since the membrane modules require backwashing
at a fixed flux a flow transmitter is required for backwash flow measurement.

4.3.6 UF skid pressures
The backwash pressure at the UF skid inlet flange shall be kept below max 1 bar.
Hydraulic shocks and pressure/flow surges must be avoided at all times. Hence, an appropriate
hydraulic profile shall be established for the UF plant during detailed engineering. During
commissioning, valve opening and closing times and pump ramp-up and ramp-down times have
to be carefully set and monitored. For large and complex UF plants, a hydraulic surge analysis is
advised.
X-Flow Client: GET Water Solutions Pvt. Ltd.,
Know-How Centre Project: STP MBR



Basic Process Design Page 19 of 20
Revision 0, 09-91-TBA

4.4 Permeate tank design
The permeate tank has to be constructed from non-corroding materials that will not leach
contaminants into the water. The water in the permeate tank has to be protected from direct
sunlight in order to minimize bacterial and/or algae growth.

4.5 Backwash strainers
To avoid any potential damage to the UF membranes, entrance of foreign harmful matter must
be avoided at all times. For this purpose the backwash water to the UF skids shall be pre-filtered
by strainers with a screen size of maximum 2 mm.

4.6 Air ingress
During start-up, and every time the UF plant has been opened for maintenance activities,
attention shall be paid to proper filling and venting of the pipe work, the UF skids and other
process equipment involved.

4.7 Automatic valves
Each skid is equipped with automatic valves. The valve opening and closing times are directly
related to the efficiency of the UF installation. Thats why quick acting valves are strongly advised
(e.g. pneumatic valves).

4.8 Chemical dosing for CEB
During CEB, the chemicals are dosed proportionally to the backwash flow into the backwash
pipe. Thus the chemicals are diluted to the correct CEB working concentration to be applied for
the membranes. For this purpose, a static in-line mixer shall be installed for proper and effective
mixing of the chemicals into the backwash flow.

Check the X-Flow data sheet for the specific chemical resistance of the membrane.

4.9 Compressed air
During UF plant operation, compressed air is required as instrument air (e.g. pneumatic valve
operations) and for the AirLift principle as explained in previous sections. Compressed air shall
meet the following specifications:
Instrument air:
ISO 8573-1, class 2/3/2 (oil/water/particles) @ 6 bar g minimum pressure
AirLift:
ISO 8573-1, class 1/3/1 (oil/water/particles)

X-Flow Client: GET Water Solutions Pvt. Ltd.,
Know-How Centre Project: STP MBR



Basic Process Design Page 20 of 20
Revision 0, 09-91-TBA

4.10 Membrane storage
New membrane modules can be stored as supplied in a dry, ventilated place, away from sources
of heat, ignition and direct sunlight. Store between 0C and 40C and prevent freezing
temperatures at all times.

After unpacking the UF membranes (i.e. removal of the original plastic vacuum bag), the
membranes require to be stored under wet conditions at all times.
To avoid biological growth during shutdowns or storage, wet membranes shall be treated with a
compatible biocide. The membrane is compatible with many common disinfecting agents or
biocidal preservatives. For short-term shutdowns, a daily flush with permeate quality water
containing up to 2.0 ppm free chlorine is adequate for bacteria control. In case of long-term
storage, membranes should be chemically cleaned (CEB) before the disinfection step is carried
out. For disinfection, a 1% sodium metabisulfite solution can be used. In either situation, modules
shall be stored filled with this solution (wet condition).

4.11 Facilities for commissioning and future operation
For commissioning purposes and future operational flexibility, attention shall be paid to
(temporary) facilities consisting of but not limited to the following:
To avoid any potential damage to the UF membranes, entrance of external harmful matter
must be avoided at all times. For this purpose the feed flow (mixed liquor) must be free of
particles > 2mm at the start of the installation and in future operation.
Commissioning connections for membrane flushing:
Prior to start-up, the membranes have to be flushed with drinking water quality to flush out the
preservation chemicals to waste (sodium bisulphite and glycerine = BOD). For this purpose,
drinking water supply to the UF feed tank and/or permeate/backwash shall be available.
Connections/facilities/space for future extensions:
In case future extension of the UF plant is considered, it is advised to reflect upon the
consequences for the overall UF plant design as early as possible. To avoid future
inconvenience and to limit overall investment costs, some measures may already be taken
into account during the initial UF plant design, e.g.
Increase UF unit size by providing space for future installation of additional membranes
Increase BW pump and CEB chemical dosing pumps for future extension of the number
of UF units
Increase pipe work sizes for future increase of capacity
Provide (building) space for future installation of additional UF units
Provide (building) space for future installation of additional feed and/or backwash pumps
Provide (building) space for future installation of an additional CEB dosing unit
Increase size of permeate tank for future increase of capacity.

You might also like