SL

NO
DRAWING / DOCUMENT
NUMBER
REV
NO
DESCRIPTION
LAHMEYER COMMENTS
DATED: 06/07/2011
Approv
al
Status
REPLY DATED : 04/08/2011
3
11kV VCB Board GA,BOM & SLD General
Comments
i) Please note that this drawing shall be revised after finalisation of 11kV SLD.
ii) Please note that Tricolite is not an approved vendor as per the vendor list submitted to LII/ICML.
iii) Please submit the credentials of Tricolite make consisting the following:
Manufacturing plant capacity.
List of Clients.
Quantity supplied till date.
financial credentials.
iv) Technical data sheets of all protection relays/meters & other equipments shall be submitted for our review.
i) Accepted
II) It is equivalent vendor to that list.
iii) We are submitting that.
Iv)Catalogues has been attached with it.
TEIM3E12U0136---L01 0 Legends & Notes i) Design ambient temperature shall be 55 deg.
Ii) Please mention the colour of Door earthing wire.
iii) Fault level shall be as per the GETCO specification.
i)Agreed
ii) It would be Green.
iii) For 66 kv we refer GETCO specification & for 11
KV we taken the fault level 26.3 kA for 3 sec.
TEIM3E12U0136---01G01 0 General
Arrangement
d i
i) Ammeter with Selector switch should be considered in all incomer panels.
i)Ammeter & MFM are provided in all incomer &
outgoing panel.
ii) All equipment designations marked in GA drawing should also be reflected in the BOM.
Accepted
iii) Schematic drawings should also be submitted for proper review of this document.
Accepted
iv) Individual drawings for typical bays consisting of GA,BOM & schematic for various bays should be submitted for our
review. Accepted
v) Since now there is only one outgoing transformer, there is no need for providing Bus coupler, Transformer-2 and Bus PT-
2 panel.
Accepted
vi) REF protection and overfluxing protection relays should be provided in outgoing feeder.
vi) We have provided REF 615 relay withprotection
(50/50N,51/51N,67/67N) and overfluxing protection
relay shall be provided in C&R panel.
vii)Sheet 3 of 4:
a) Please confirm the panel location of synchronising relay.
B) REF and O/F relay to be added in the legends.
a)We will not provided Synchronising relay.
B)Only REF relay is provided in this panel.O/F
relay is provide in C&R Panel.
viii) Fault level mentioned in all the sheets to be updated as per the GETCO specification.
vii)Accepted.
ix)Sheet 4 of 4:
Separate door/cover should be shown for accessing the CT's without disturbing the busbar chamber. ix)Accepted
TEIM3E12U0136---01S01 Single Line
Diagram
i)Polarity of CT's should be mentioned in all the Bay's.
ii) Ammeter with selector switch should be shown in series with the MFM in all the incomer bays.
iii) All PT inputs to metering circuit shall be fed from single PT.
iv)Determination of Vk,Im & Rct shall have to be justified in the separate submittal.
v) The CT ratio and sizing of other parameters of CT shall be decided on the basis of final rating of the 11/66kV
Transformer.
vi) Sizing of surge arrestor should be submitted for our review.
i)Accepted
ii) Accepted
iii)Accepted
iv)We will submit it in later submission.
v) Accepted
vi) 9 KV 10 KA surge arrestor.
GEOE11055- Owners Engineering Services for 9 MWp Grid-Interactive Solar PV Power Project in Gujarat.
Comments on " Proposal for Cables , Axis Tracking Mounting System and 11kV VCB Board GA,BOM & SLD"
A2
A2
Page 1 of 2
SL
NO
DRAWING / DOCUMENT
NUMBER
REV
NO
DESCRIPTION
LAHMEYER COMMENTS
DATED: 06/07/2011
Approv
al
Status
REPLY DATED : 04/08/2011
GEOE11055- Owners Engineering Services for 9 MWp Grid-Interactive Solar PV Power Project in Gujarat.
Comments on " Proposal for Cables , Axis Tracking Mounting System and 11kV VCB Board GA,BOM & SLD"
vi) Sheet No 3 of 5:
a) Since now there is only single transformer, the following bays can be removed:
- Buscoupler Bay.
- Tranformer-2 Bay.
- Bus PT-2.
b) Class of accuracy for Bus PT should be 0.2.
c) Core-2 of Bus PT should be wired upto the terminal block through MCB.
d) Initiation (from 50/51N relay) and tripping path of 86 relay to breaker should be shown for all the bays in SLD.
e) Overfluxing and REF protection relay should be shown in SLD for transformer outgoing bay.
vi)
a)All removed
b)Accepted
c)Accepted
d) Accepted
TEIM3E12U0136---01B01 Bill of material Quantity & type of equipments shown in BOM shall be finalised after review of schematic drawings & relevant catalogues.
i)Make of all equipments should be fixed.
ii) Master trip relay shall be of hand & electrical reset type.
iii) CT rating should be mentioned in all the equipment specifications.
iv) Pg 3 of 3: Detailed rating of surge arrestor should be mentioned in BOM.
v) Please confirm the type of Energy management system i.e. 3P,3W 1 element/2 element/3 element??
A2
i)It is fixed
ii)Master trip relay should be hand reset type.
iii)Accepted.
iv)Accepted
v) Load Manager EM 6400 will be 3 ph, 3Wire,
electronic type and has no element system.
Approval Status (This approval status shall not relieve the Contractor from his contractual obligations):
A1: Approved
A2: Approved subject to incorporation of Comments/modifications as noted. Resubmit revised drgs./docs after Incorporating the comments
A3: Not approved. Resubmit revised drgs/ Docs. Incorporating comments/Modifications, as noted, for approval.
I: Information
A2
Page 2 of 2