TOURISM BUILDING TO BE KNOWN AS THE NATIONAL MUSEUM

NATURAL HISTORY
LOCATION : RIZAL PARK, MANILA
SUBJECT PROJECTED MANPOWER SCHEDULE FOR DEMOLITION WORKS
1.1 6th Floor
- Remaining Perimet exterior walls,beams and columns
- Removal of all existing windows
- Demolition of Helipad
31-Mar 6-Apr 10
- Demolition of Stairs @ courtyard
31-Mar 6-Apr 10
- Hauling of Debris Wing E&C 17-Mar 24-Mar 10
- Demolition of Suspended Slabs For New Elev. & Stairs Opening
- Balance Works
Removal of Ceiling Insulations
Removal of Remaining Condenser @ Helipad
Removal of Panel Boards 17-Mar 18-Mar
Transfering of Salvageable Materials for Turnover 17-Mar 21-Mar
Lowering of Waste and other used materials 17-Mar 21-Mar
1.2 5th Floor
- Demolition of RC Walls @ Wing C 17-Mar 23-Mar
- Demolition of Slabs For New Elev. Shaft & Stairs Opening
- Hauling of Debris 17-Mar 23-Mar 50
- Balance Works
Removal of Existing Windows and walls for New Hallway Opening 22-Mar 26-Mar
Demolition of Stairs Support Beams and Walls 22-Mar 26-Mar
1.3 4th Floor Ceiling Systems
- Installation of Goosenecked Drum Connection for Chutes 15-Mar 17-Mar 6
- Demolition of RC Walls @ Wing C 24-Mar 30-Mar
- Demolition of Suspended Slab for new Elevator Shaft
- Hauling of Dedris 24-Mar 30-Mar 40+10=50
ITEM Finish
PROJECT : ADAPTIVE RE-USE AND RETROFIT OF THE OLD DEPARTMENT OF
31-Mar 6-Apr 20
Group for
Chute
Start
DESCRIPTION
Manpower DEMOLITION WORKS
17-Mar 18-Mar
- Balance Works
Transfering of Salvageable Materials for Turnover 27-Mar 29-Mar
Removal of Existing Grills Along Hallways 27-Mar 29-Mar
Removal of Existing Windows and walls for New Hallway Opening 27-Mar 31-Mar
Lowering of Waste and other used materials 27-Mar 31-Mar
1.4 3rd Floor Ceiling Systems
- Installation of Goosenecked Drum Connection for Chutes 18-Mar 20-Mar 6
- Demolition of RC Walls @ Wing C and Hallways 31-Mar 6-Apr
- Demolition of Suspended slab @ Wing C
- Demolition of Suspended Slab @ Courtyard Elev Lobby
- Demolition of Suspended Slab For new Elevator Shaft
- Hauling of Dedris 31-Mar 8-Apr 50
- Balance Works
Transfering of Salvageable Materials for Turnover 1-Apr 3-Apr
Removal of Existing Grills Along Hallways 1-Apr 3-Apr
Removal of Existing Windows and walls for New Hallway Openeing 1-Apr 5-Apr
Lowering of Waste and other used materials 1-Apr 5-Apr
1.5 2nd Floor Ceiling Systems
- Removal of Exisiting Floor Finish @ Wing C Terrace 17-Mar 18-Mar 5
- Installation of Gooseneck Drum Connection for Chutes 21-Mar 23-Mar 6
- Removal of Existing Entrance Canopy Npdc Area 19-Mar 21-Mar 5
- Removal Pebble Washout finish @ Main Entrance Stairs Wing A 21-Mar 27-Mar
- Floor Stripping 21-Mar 27-Mar
- Removal of Existing Kiosk And Counter At Marble Hall 28-Mar 30-Mar 5
- Demolition of RC Walls @ Wing C and Hallways 31-Mar 6-Apr 5
- Demolition of Suspended Slab @ Courtyard Elev Lobby
- Demolition of Suspended Slab For new Elevator Shaft
- Hauling of Dedris 9-Apr 12-Apr 50+20= 70
- Balance Works
Transfering of Salvageable Materials for Turnover 6-Apr 8-Apr
Removal of Existing Grills Along Hallways 6-Apr 8-Apr
Removal of Existing Windows and walls for New Hallway Opening 6-Apr 10-Apr
Lowering of Waste and other used materials 6-Apr 10-Apr
Removal of Existing Windows and walls for New Openings Wing A 11-Apr 12-Apr
1.6 Ground Floor Ceiling Systems
- Demolition of Existing Ceiling 17-Mar 22-Mar 6
- Demolition of Existing Floors 17-Mar 22-Mar 6
- Demolition of Exisiting Windows For New Door Openings 23-Mar 29-Mar 6+6+12
- Demolition of Exisiting Walls 30-Mar 5-Apr 6+6+12
- Demolition of Exisiting Courtyard Elevator Shaft
- Hauling of Waste, Debris and used Materials @ courtyard 6-Apr 12-Apr 30
- Demolition of Exisiting Power House
-
total manpower 117 6
Upon Completion of
Scaffolding
Upon Completion of
Scaffolding
Awaiting Retrofit Plans
2
3
3
6
Awaiting Retrofit Plans
5
5
6
Awaiting Retrofit Plans
to be transfer to the next
floor upon completion
PROJECT : ADAPTIVE RE-USE AND RETROFIT OF THE OLD DEPARTMENT OF
Upon Completion of
Scaffolding
Remarks Group
to be transfer to the next
floor upon completion
2
2
2
3
3
6
Awaiting Retrofit Plans
Awaiting Retrofit Plans
Awaiting Retrofit Plans
2
2
3
3
5
5
Awaiting Retrofit Plans
Awaiting Retrofit Plans
2
2
3
3
10
Awaiting Retrofit Plans
26 149
overall total
manpower 149
TOURISM BUILDING TO BE KNOWN AS THE NATIONAL MUSEUM
NATURAL HISTORY
LOCATION : RIZAL PARK, MANILA
SUBJECT PROJECTED MANPOWER SCHEDULE FOR DEMOLITION WORKS
1.1 6th Floor
- Remaining Perimet exterior walls,beams and columns
- Removal of all existing windows
- Demolition of Helipad 10 31-Mar 6-Apr
Upon Completion of
Scaffolding
- Demolition of Stairs @ courtyard 10
31-Mar 6-Apr
Upon Completion of
Scaffolding
- Hauling of Debris Wing E&C 10 17-Mar 24-Mar
- Demolition of Suspended Slabs For New Elev. & Stairs Opening Awaiting Retrofit Plans
- Balance Works
Removal of Ceiling Insulations
Removal of Remaining Condenser @ Helipad
Removal of Panel Boards 2 17-Mar 18-Mar
Transfering of Salvageable Materials for Turnover 2 17-Mar 21-Mar
Lowering of Waste and other used materials 3 17-Mar 21-Mar
1.2 5th Floor
- Demolition of RC Walls @ Wing C 6 17-Mar 23-Mar
- Demolition of Slabs For New Elev. Shaft & Stairs Opening Awaiting Retrofit Plans
- Hauling of Debris 50 17-Mar 23-Mar
- Balance Works
Removal of Existing Windows and walls for New Hallway Opening 5 5 22-Mar 26-Mar
Demolition of Stairs Support Beams and Walls 5 5 22-Mar 26-Mar
1.3 4th Floor Ceiling Systems
- Installation of Goosenecked Drum Connection for Chutes 6 15-Mar 17-Mar
- Demolition of RC Walls @ Wing C 6 24-Mar 30-Mar
- Demolition of Suspended Slab for new Elevator Shaft Awaiting Retrofit Plans
- Hauling of Dedris 40+10=50 24-Mar 30-Mar
- Balance Works
Transfering of Salvageable Materials for Turnover 2 27-Mar 29-Mar
Removal of Existing Grills Along Hallways 2 27-Mar 29-Mar
Removal of Existing Windows and walls for New Hallway Opening 3 27-Mar 31-Mar
Lowering of Waste and other used materials 3 27-Mar 31-Mar
1.4 3rd Floor Ceiling Systems
- Installation of Goosenecked Drum Connection for Chutes 6 18-Mar 20-Mar
- Demolition of RC Walls @ Wing C and Hallways 6 31-Mar 6-Apr
- Demolition of Suspended slab @ Wing C Awaiting Retrofit Plans
- Demolition of Suspended Slab @ Courtyard Elev Lobby Awaiting Retrofit Plans
- Demolition of Suspended Slab For new Elevator Shaft Awaiting Retrofit Plans
to be transfer to the next
floor upon completion
week 1 mar 17-
23
week 2 mar 24-
30
week 3 march 31-
apr 6
week 4 april 7-
12
20
2
Remarks
31-Mar 6-Apr
Upon Completion of
Scaffolding
17-Mar 18-Mar
to be transfer to the next
floor upon completion
PROJECT : ADAPTIVE RE-USE AND RETROFIT OF THE OLD DEPARTMENT OF
DESCRIPTION
ITEM DEMOLITION WORKS Start Finish
- Hauling of Dedris 50 31-Mar 8-Apr
- Balance Works
Transfering of Salvageable Materials for Turnover 2 1-Apr 3-Apr
Removal of Existing Grills Along Hallways 2 1-Apr 3-Apr
Removal of Existing Windows and walls for New Hallway Openeing 3 1-Apr 5-Apr
Lowering of Waste and other used materials 3 1-Apr 5-Apr
1.5 2nd Floor Ceiling Systems
- Removal of Exisiting Floor Finish @ Wing C Terrace 5 17-Mar 18-Mar
- Installation of Gooseneck Drum Connection for Chutes 6 21-Mar 23-Mar
- Removal of Existing Entrance Canopy Npdc Area 5 19-Mar 21-Mar
- Removal Pebble Washout finish @ Main Entrance Stairs Wing A 5 21-Mar 27-Mar
- Floor Stripping 6 21-Mar 27-Mar
- Removal of Existing Kiosk And Counter At Marble Hall 5 28-Mar 30-Mar
- Demolition of RC Walls @ Wing C and Hallways 5 31-Mar 6-Apr
- Demolition of Suspended Slab @ Courtyard Elev Lobby Awaiting Retrofit Plans
- Demolition of Suspended Slab For new Elevator Shaft Awaiting Retrofit Plans
- Hauling of Dedris 50+20=70 9-Apr 12-Apr
- Balance Works
Transfering of Salvageable Materials for Turnover 2 6-Apr 8-Apr
Removal of Existing Grills Along Hallways 2 6-Apr 8-Apr
Removal of Existing Windows and walls for New Hallway Opening 3 6-Apr 10-Apr
Lowering of Waste and other used materials 3 6-Apr 10-Apr
Removal of Existing Windows and walls for New Openings Wing A 11-Apr 12-Apr
1.6 Ground Floor Ceiling Systems
- Demolition of Existing Ceiling 6 17-Mar 22-Mar
- Demolition of Existing Floors 6 17-Mar 22-Mar
- Demolition of Exisiting Windows For New Door Openings 6 23-Mar 29-Mar
- Demolition of Exisiting Walls 6 6 30-Mar 5-Apr
- Demolition of Exisiting Courtyard Elevator Shaft `
Awaiting Retrofit Plans
- Hauling of Waste, Debris and used Materials @ courtyard 10+10+10=30 6-Apr 12-Apr
- Demolition of Exisiting Power House
-
total manpower/week 114 98 107 100 114
Prepared By: Arch. Erickson C. Dominguez/ Site Architect Noted by: Engr. Angelito G. Lagmay/ Asst. Project Manager
Engr. Harrie H. Mactal/Site Engineer
Approved by: Engr. Wilfredo S. Salcedo/Project Manager
TOURISM BUILDING TO BE KNOWN AS THE NATIONAL MUSEUM
NATURAL HISTORY
LOCATION : RIZAL PARK, MANILA
SUBJECT PROJECTED MANPOWER SCHEDULE FOR DEMOLITION WORKS
1.1 6th Floor
- Remaining Perimet exterior walls,beams and columns
- Removal of all existing windows
- Demolition of Helipad
- Demolition of Stairs @ courtyard
- Hauling of Debris Wing (A,B,C,D)
- Demolition of Suspended Slabs For New Elev. & Stairs Opening
- Balance Works
Removal of Ceiling Insulations
Removal of Remaining Condenser @ Helipad
Removal of Panel Boards
Transfering of Salvageable Materials for Turnover
Lowering of Waste and other used materials
1.2 5th Floor
- Demolition of RC Walls @ Wing C
- Demolition of Slabs For New Elev. Shaft & Stairs Opening
- Hauling of Debris (D:C&B)
- Balance Works
Removal of Existing Windows and walls for New Hallway Opening
Demolition of Stairs Support Beams and Walls
1.3 4th Floor Ceiling Systems
- Installation of Goosenecked Drum Connection for Chutes
- Demolition of RC Walls @ Wing C
- Demolition of Suspended Slab for new Elevator Shaft
- Hauling of Debris
- Balance Works
Transfering of Salvageable Materials for Turnover
Removal of Existing Grills Along Hallways
Removal of Existing Windows and walls for New Hallway Opening
Lowering of Waste and other used materials
1.4 3rd Floor Ceiling Systems
- Installation of Goosenecked Drum Connection for Chutes
- Demolition of RC Walls (B,D,E Hallway)
- Demolition of Suspended slab @ Wing C
- Demolition of Suspended Slab @ Courtyard Elev Lobby
PROJECT : ADAPTIVE RE-USE AND RETROFIT OF THE OLD DEPARTMENT OF
DESCRIPTION
ITEM DEMOLITION WORKS
- Demolition of Suspended Slab For new Elevator Shaft
- Hauling of Dedris
- Balance Works
Transfering of Salvageable Materials for Turnover
Removal of Existing Grills Along Hallways
Removal of Existing Windows and walls for New Hallway Openeing
Lowering of Waste and other used materials
1.5 2nd Floor Ceiling Systems
- Removal of Exisiting Floor Finish @ Wing C Terrace
- Installation of Gooseneck Drum Connection for Chutes
- Removal of Existing Entrance Canopy Npdc Area
- Removal Pebble Washout finish @ Main Entrance Stairs Wing A
- Floor Stripping
- Removal of Existing Kiosk And Counter At Marble Hall
- Demolition of RC Walls @ Wing C and Hallways
- Demolition of Suspended Slab @ Courtyard Elev Lobby
- Demolition of Suspended Slab For new Elevator Shaft
- Hauling of Dedris
- Balance Works
Transfering of Salvageable Materials for Turnover
Removal of Existing Grills Along Hallways
Removal of Existing Windows and walls for New Hallway Opening
Lowering of Waste and other used materials
Removal of Existing Windows and walls for New Openings Wing A
1.6 Ground Floor Ceiling Systems
- Demolition of Existing Ceiling (E:D:Rm. 124-125)
- Demolition of Existing Floors
- Demolition of Exisiting Windows For New Door Openings
- Demolition of Exisiting Walls
- Demolition of Exisiting Courtyard Elevator Shaft
- Hauling of Waste, Debris and used Materials @ courtyard
- Demolition of Exisiting Power House
-
total manpower/week
Prepared By: Arch. Erickson C. Dominguez/ Site Architect
Engr. Harrie H. Mactal/Site Engineer
10 31-Mar 6-Apr
10
31-Mar 6-Apr
10 17-Mar 24-Mar
2 17-Mar 18-Mar
2 17-Mar 21-Mar
3 17-Mar 21-Mar
6 17-Mar 23-Mar
50 17-Mar 23-Mar
5 5 22-Mar 26-Mar
5 5
22-Mar 26-Mar
6 15-Mar 17-Mar
6 24-Mar 30-Mar
40+10=50 24-Mar 30-Mar
2 27-Mar 29-Mar
2 27-Mar 29-Mar
3 27-Mar 31-Mar
3 27-Mar 31-Mar
6 18-Mar 20-Mar
6 31-Mar 6-Apr
6-Apr
2
17-Mar 18-Mar
Finish
20
31-Mar
PROJECT : ADAPTIVE RE-USE AND RETROFIT OF THE OLD DEPARTMENT OF
week 1 mar 17-
23
week 2 mar 24-
30
week 3 march 31-
apr 6
week 4 april 7-
12
Start
50 31-Mar 8-Apr
2 1-Apr 3-Apr
2 1-Apr 3-Apr
3 1-Apr 5-Apr
3 1-Apr 5-Apr
5 17-Mar 18-Mar
6 21-Mar 23-Mar
5 19-Mar 21-Mar
5 21-Mar 27-Mar
6 21-Mar 27-Mar
5 28-Mar 30-Mar
5 31-Mar 6-Apr
50+20=70 9-Apr 12-Apr
2 6-Apr 8-Apr
2 6-Apr 8-Apr
3 6-Apr 10-Apr
3 6-Apr 10-Apr
11-Apr 12-Apr
6 17-Mar 22-Mar
6 17-Mar 22-Mar
6 23-Mar 29-Mar
6 6 30-Mar 5-Apr
`
10+10+10=30 6-Apr 12-Apr
5
114 98 107 100
Noted by: Engr. Angelito G. Lagmay/ Asst. Project Manager
Approved by: Engr. Wilfredo S. Salcedo/Project Manager
STATUS
Upon Completion of
Scaffolding
Upon Completion of
Scaffolding
DONE, E-97%
Awaiting Retrofit Plans
DONE
DONE
PENDING
Awaiting Retrofit Plans HOLD
ON GOING
HOLD
DONE
DONE
Awaiting Retrofit Plans
ON GOING
DONE
ON GOING
DONE
Awaiting Retrofit Plans
Awaiting Retrofit Plans
NOT STARTED
100%
NOT STARTED
NOT STARTED
90%
100%
90%
100%
to be transfer to the next
floor upon completion
% ACCOMPLISHMENT
100%
100% DONE
30%
98%
100%
100%
Upon Completion of
Scaffolding
to be transfer to the next
floor upon completion
Remarks
PROJECT : ADAPTIVE RE-USE AND RETROFIT OF THE OLD DEPARTMENT OF
Awaiting Retrofit Plans
ON GOING
DONE
HOLD
ON GOING
HOLD
NOT STARTED
DONE
HOLD (STORAGE AREA OF DOT)
ON GOING
DONE
Awaiting Retrofit Plans
Awaiting Retrofit Plans
ON GOING
ON GOING
ON GOING
NOT STARTED
HOLD
ON GOING
Awaiting Retrofit Plans
ON GOING
114
20%
90%
50%
100%
100%
90%
100%