You are on page 1of 3

University of Guyana, Faculty of Technology

Structural Modelling, Analysis and Design of The Conceptual Science Pentagon Building Model from the University Of Guyana Turkeyen Campus Master Developmental Plan
Draft Project Schedule
ID

Task Name

Duration

Start

Finish
July
E

0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43

Structural Modelling, Analysis and Design of Science Pentagon

239 days

Mon 26/08/13

Mon 21/07/14

1 Project Selection
1.1 Topic Research
1.2 Project Supervisor Selection
1.3 Submission of Project Selection Form

20 days
15 days
15 days
5 days

Mon 26/08/13
Mon 26/08/13
Mon 26/08/13
Mon 16/09/13

Fri 20/09/13
Fri 13/09/13
Fri 13/09/13
Fri 20/09/13

2 Preliminary Design Stage

26 days

Mon 23/09/13

Mon 28/10/13

2.1 Data Collection


2.1.1 Conceptual Model Collection
2.1.2 Building Information Collection
2.1.3 Site Data Collection (Weather Conditions)
2.1.4 Grades of Steel Members available locally
2.1.5 Concrete Mix Designs availably locally

8 days
5 days
5 days
8 days
7 days
7 days

Mon 23/09/13
Mon 23/09/13
Mon 23/09/13
Mon 23/09/13
Mon 23/09/13
Mon 23/09/13

Wed 02/10/13
Fri 27/09/13
Fri 27/09/13
Wed 02/10/13
Tue 01/10/13
Tue 01/10/13

2.2 Selection of Building and Design Codes


2.3 Selection of Building Materials (Available Locally)

7 days
7 days

Thu 03/10/13
Mon 23/09/13

Fri 11/10/13
Tue 01/10/13

15 days
15 days
15 days

Mon 30/09/13
Mon 30/09/13
Mon 30/09/13

Fri 18/10/13
Fri 18/10/13
Fri 18/10/13

4 days
2 days

Mon 21/10/13
Fri 25/10/13

Thu 24/10/13
Mon 28/10/13

50 days

Mon 09/09/13

Fri 15/11/13

39 days
5 days
5 days
5 days
5 days
5 days
5 days
5 days
5 days
4 days
5 days
5 days
3 days

Mon 09/09/13
Mon 09/09/13
Mon 14/10/13
Wed 11/09/13
Thu 03/10/13
Mon 14/10/13
Thu 26/09/13
Wed 18/09/13
Tue 10/09/13
Mon 23/09/13
Tue 17/09/13
Thu 17/10/13
Tue 29/10/13

Thu 31/10/13
Fri 13/09/13
Fri 18/10/13
Tue 17/09/13
Wed 09/10/13
Fri 18/10/13
Wed 02/10/13
Tue 24/09/13
Mon 16/09/13
Thu 26/09/13
Mon 23/09/13
Wed 23/10/13
Thu 31/10/13

1 day
1 day

Fri 01/11/13
Fri 15/11/13

Fri 01/11/13
Fri 15/11/13

2.4 Modelling of chosen building


2.4.1 Concept Model displaying temperature based data
2.4.2 Concept Model displaying wind based data
2.5 Compiling of structural element schedule
2.6 Compiling of a preliminary estimate for structural members
3 Project Proposal
3.1 Design
3.1.1 Title Page
3.1.2 Abstract
3.1.3 Table of Contents, List of Figures, List of Tables
3.1.4 Introduction
3.1.5 Scope of Works
3.1.6 Literature Review
3.1.7 Plan of Implementation
3.1.8 Format
3.1.9 Budget
3.1.10 Schedule
3.1.11 Reference
3.1.12 Appendices
3.2 Submission of Project Proposal
3.3 Oral Presentation

Project:StructuralModelling,Ana
Date:Thu03/10/13

3rd Quarter
September
E

November
E

January
E

1st Quarter
March
E

20/09

01/11
15/11

Task

ProjectSummary

InactiveMilestone

ManualSummaryRollup

Deadline

Split

ExternalTasks

InactiveSummary

ManualSummary

Progress

Milestone

ExternalMilestone

ManualTask

Startonly

Summary

InactiveTask

Durationonly

Finishonly

Page1

May
E

July
E

University of Guyana, Faculty of Technology


Structural Modelling, Analysis and Design of The Conceptual Science Pentagon Building Model from the University Of Guyana Turkeyen Campus Master Developmental Plan
Draft Project Schedule
ID

Task Name

Duration

Start

Finish
July
E

44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87

4 Final Design Stage

129 days

Tue 24/12/13

Tue 17/06/14

4.1 Material Definition


4.1.1 Defining of Concrete Parameters
4.1.2 Defining of Steel Parameters
4.1.3 Defining of Other Material Parameters (Floor Deck Materials)

10 days
5 days
5 days
5 days

Tue 24/12/13
Tue 24/12/13
Fri 27/12/13
Tue 31/12/13

Mon 06/01/14
Mon 30/12/13
Thu 02/01/14
Mon 06/01/14

4.2 Model Creation


4.2.1 Modeling of Grid Lines and Levels

12 days
2 days

Wed 01/01/14
Wed 01/01/14

Thu 16/01/14
Thu 02/01/14

10 days
5 days
5 days
5 days
5 days
5 days

Fri 03/01/14
Fri 03/01/14
Fri 10/01/14
Fri 03/01/14
Mon 06/01/14
Fri 03/01/14

Thu 16/01/14
Thu 09/01/14
Thu 16/01/14
Thu 09/01/14
Fri 10/01/14
Thu 09/01/14

4.3 Load Definitions


4.3.1 Dead Loads (Non material)
4.3.2 Live Loads
4.3.3 Wind Loads
4.3.4 Temperature Loads
4.3.5 Accidental Loads
4.3.6 Seismic Loads

13 days
5 days
7 days
10 days
10 days
7 days
7 days

Tue 24/12/13
Tue 24/12/13
Thu 26/12/13
Tue 24/12/13
Tue 24/12/13
Fri 27/12/13
Wed 01/01/14

Thu 09/01/14
Mon 30/12/13
Fri 03/01/14
Mon 06/01/14
Mon 06/01/14
Mon 06/01/14
Thu 09/01/14

4.4 Load Assignment


4.4.1 Dead Loads (Non material)
4.4.2 Live Loads
4.4.3 Wind Loads
4.4.4 Temperature Loads
4.4.5 Accidental Loads
4.4.6 Seismic Loads

9 days
2 days
5 days
5 days
5 days
5 days
5 days

Fri 17/01/14
Fri 17/01/14
Tue 21/01/14
Wed 22/01/14
Tue 21/01/14
Thu 23/01/14
Tue 21/01/14

Wed 29/01/14
Mon 20/01/14
Mon 27/01/14
Tue 28/01/14
Mon 27/01/14
Wed 29/01/14
Mon 27/01/14

4.5 Load Combinations Generation

7 days

Thu 30/01/14

Fri 07/02/14

30 days

Fri 28/02/14

Mon 07/04/14

24 days
10 days
10 days
10 days
10 days
10 days

Fri 28/02/14
Fri 28/02/14
Tue 04/03/14
Thu 06/03/14
Mon 10/03/14
Wed 12/03/14

Sun 30/03/14
Wed 12/03/14
Sun 16/03/14
Tue 18/03/14
Thu 20/03/14
Mon 24/03/14

4.2.2 Modelling of Structural Elements


4.2.2.1 Columns
4.2.2.2 Beams
4.2.2.3 Floor Slabs
4.2.2.4 Roof Slabs
4.2.2.5 Walls/Shear Walls

4.6 Model Analysis


4.6.1 Dynamic Analysis
4.6.1.1 Modal frequency analysis
4.6.1.2 Floor vibration analysis
4.6.1.3 Response Spectrum Analysis
4.6.1.4 Time History Analysis
4.6.1.5 P-Delta Analysis

Project:StructuralModelling,Ana
Date:Thu03/10/13

3rd Quarter
September
E

November
E

January
E

1st Quarter
March
E

Task

ProjectSummary

InactiveMilestone

ManualSummaryRollup

Deadline

Split

ExternalTasks

InactiveSummary

ManualSummary

Progress

Milestone

ExternalMilestone

ManualTask

Startonly

Summary

InactiveTask

Durationonly

Finishonly

Page2

May
E

July
E

University of Guyana, Faculty of Technology


Structural Modelling, Analysis and Design of The Conceptual Science Pentagon Building Model from the University Of Guyana Turkeyen Campus Master Developmental Plan
Draft Project Schedule
ID

Task Name

Duration

Start

Finish
July
E

88
89
90
91
92
93
94
95
96
97
98
99
100
101
102
103
104
105
106
107
108
109
110
111
112
113
114
115
116
117
118
119
120
121
122
123
124
125
126
127

4.6.1.6 Buckling Analysis


4.6.1.7 Pushover Analysis
4.6.1.8 Concrete Shrinkage and Time Dependent Creep Analysis

10 days
10 days
10 days

Fri 14/03/14
Sun 16/03/14
Tue 18/03/14

Wed 26/03/14
Thu 27/03/14
Sun 30/03/14

10 days

Wed 26/03/14

Mon 07/04/14

4.7 Element Design


4.7.1 Columns
4.7.2 Beams
4.7.3 Floor Slabs
4.7.4 Roof Slabs
4.7.5 Shear Walls
4.7.6 Composite Elements
4.7.7 Connections (Optional)

20 days
5 days
5 days
5 days
5 days
5 days
7 days
5 days

Tue 08/04/14
Tue 08/04/14
Tue 15/04/14
Tue 22/04/14
Tue 29/04/14
Tue 08/04/14
Tue 08/04/14
Tue 22/04/14

Mon 05/05/14
Mon 14/04/14
Mon 21/04/14
Mon 28/04/14
Mon 05/05/14
Mon 14/04/14
Wed 16/04/14
Mon 28/04/14

4.8 Model Optimization

10 days

Tue 06/05/14

Mon 19/05/14

4.9 Documentation
4.9.1 Final Model Generation
4.9.2 Final Structural Model Documentation
4.9.3 Final Analysis Documentation

21 days
7 days
14 days
14 days

Tue 20/05/14
Tue 20/05/14
Thu 29/05/14
Tue 20/05/14

Tue 17/06/14
Wed 28/05/14
Tue 17/06/14
Fri 06/06/14

31 days

Mon 09/06/14

Mon 21/07/14

14 days
1 day
3 days
4 days
1 day
1 day
3 days
7 days
6 days
2 days
6 days
1 day
5 days

Mon 09/06/14
Mon 09/06/14
Mon 09/06/14
Mon 09/06/14
Mon 09/06/14
Mon 09/06/14
Mon 09/06/14
Mon 09/06/14
Mon 09/06/14
Tue 17/06/14
Thu 19/06/14
Mon 09/06/14
Mon 09/06/14

Thu 26/06/14
Mon 09/06/14
Wed 11/06/14
Thu 12/06/14
Mon 09/06/14
Mon 09/06/14
Wed 11/06/14
Tue 17/06/14
Mon 16/06/14
Wed 18/06/14
Thu 26/06/14
Mon 09/06/14
Fri 13/06/14

7 days
1 day

Fri 20/06/14
Mon 21/07/14

Mon 30/06/14
Mon 21/07/14

4.6.2 Construction Sequencing

5 Final Report
5.1 Design
5.1.1 Title Page
5.1.2 Executive Summary
5.1.3 Abstract
5.1.4 Acknowledgements
5.1.5 Table of Contents, List of Figures, List of Tables, etc
5.1.6 Introduction
5.1.7 Method and Design Approach
5.1.8 Results
5.1.9 Conclusion
5.1.10 Recommendations
5.1.11 References
5.1.12 Appendices
5.2 Submission of Project Final Report
5.3 Oral Presentation

Project:StructuralModelling,Ana
Date:Thu03/10/13

3rd Quarter
September
E

November
E

January
E

1st Quarter
March
E

May
E

July
E

30/06
21/07

Task

ProjectSummary

InactiveMilestone

ManualSummaryRollup

Deadline

Split

ExternalTasks

InactiveSummary

ManualSummary

Progress

Milestone

ExternalMilestone

ManualTask

Startonly

Summary

InactiveTask

Durationonly

Finishonly

Page3

You might also like