METHOD STATEMENT

REPAIR OF DOORS & WINDOWS


PROJECT NAME


PROJECT CLIENT
PROJECT NAME CLIENT NAME
DOCUMENT NUMBER REV DATE DOCUMENT TITLE SHEET
1 19-03-14 METHOD STATEMENT FOR REPAIR OF DOORS & WINDOWS 2 of 16

Rev Location of Change Brief Description of Change
0 First issue

















0 Issued for approval
REV
ISSUE OR REVISION
DESCRIPTION
ORIG
BY
DATE
CHKD
BY
DATE
APPD
BY
DATE

PROJECT CLIENT
PROJECT NAME CLIENT NAME
DOCUMENT NUMBER REV DATE DOCUMENT TITLE SHEET
1 19-03-14 METHOD STATEMENT FOR REPAIR OF DOORS & WINDOWS 3 of 16


CONTENTS
1.0 OBJECTIVES 1-4
2.0 GENERAL INFORMATION 2-4
2.1 PROJECT CONTRACTUAL INFORMATION 2-4
3.0 DEFINITIONS AND ABBREVIATIONS 3-4
4.0 SCOPE OF WORK 4-4
5.0 SEQUENCE OF EXECUTION AT SITE 5-6
6.0 TOOLS AND EQUIPMENT 6-6
7.0 RESPONSIBILITIES 7-6
7.1 PROJECT COORDINATOR 7-7
7.2 SUPERVISOR / FOREMAN 7-7
7.3 SUPPORT SERVICES FACILITATOR (CLIENT) 7-7
7.4 MOBILIZATION & PRE-CONSTRUCTION PROCEDURES 7-7
8.0 ACCOMMODATION, FOOD AND TRANSPORTATION OF COMPANY STAFF 8-8
9.0 WASTE SKIP, RIGGING AND CRANE ASSISTANCE 9-8
10.0 COMFORT AND SAFETY FOR THE PLATFORM CREW WHILE CONSTRUCTION 10-8
10.1 NOISE & VIBRATION MITIGATION PROGRAM 10-8
10.2 HOUSEKEEPING PRACTICES 10-9
10.3 WASTE MANAGEMENT 10-9
11.0 WORK METHODOLOGY 11-10
11.1 INSTALLATION OF DOORS MANUFACTURER 11-10
11.2 INSTALLATION OF DOORS (MANUFACTURER) 11-10
11.3 INSTALLATION OF WINDOWS (MANUFACTURER) 11-12
11.4 REPLACING WINDOW GLASS (MANUFACTURER) 11-12
12.0 INSPECTION 12-13
12.1 CLOSE OUT / COMPLETION REPORTS 12-13
13.0 ATTACHMENTS / REFERENCE 13-13
14.0 ENVIRONMENTAL, SAFETY AND HEALTH 14-13
14.1 RISK ASSESSMENT 14-13
14.2 SPECIFIC EMERGENCY PROCEDURES 14-13
14.3 TOOL BOX TALK 14-13
14.4 PERSONAL COMMITMENT 14-14





PROJECT CLIENT
PROJECT NAME CLIENT NAME
DOCUMENT NUMBER REV DATE DOCUMENT TITLE SHEET
1 19-03-14 METHOD STATEMENT FOR REPAIR OF DOORS & WINDOWS 4 of 16

INTRODUCTION
The purpose of this document is to provide a standard set of instructions and to outline the
measures needed to ensure successful completion of the job within the target time frame, on to
budgeted cost and in accordance contract requirements. If any part or complete document
contradicts with existing client documents, the Conditions mentioned in the client document will
prevail.
1.0 OBJECTIVES
The purpose of this method statement is to
Specify the installation procedures, codes of practice and standards to be applied during the
entire job.
To establish the authorities, responsibilities and operating controls of the method statement
that will ensure all team members perform in accordance with the project requirements /
contract requirements.
2.0 GENERAL INFORMATION
2.1 PROJECT CONTRACTUAL INFORMATION
Project :
Client :
Contractor :
3.0 DEFINITIONS AND ABBREVIATIONS
ABBREVIATION DEFINITIONS / DESCRIPTIONS
MANUFACTURER
MANUFACTURER
MANUFACTURER
HSE Health Safety and Environment
LCR To be filled at site
LER Local Equipment Room
PAT Portable Appliances Test
PPE Personal Protective Equipment




4.0 SCOPE OF WORK
Scope of work includes repairing of doors by replacing components, removal of existing doors,
window glasses, reconstruction by use of new doors and window glasses. Repair and reconstruction
carried out in accordance with Client documents and manufacturer installation procedures.
List of all major activities below:-

PROJECT CLIENT
PROJECT NAME CLIENT NAME
DOCUMENT NUMBER REV DATE DOCUMENT TITLE SHEET
1 19-03-14 METHOD STATEMENT FOR REPAIR OF DOORS & WINDOWS 5 of 16

Location Removal & Replacement Activities Qty
11KV Switch Room
Counter frame 1
Door Gasket 2
Door Handle 3
Door Lock 3
Lever Handle 1
Vision Panel 1
2nd Floor Bridge Passage A60 Window Glass 4
2nd Level Passage Door A60 Weather Tight External Door-Bolted Type 1
2nd Level Switch Gear Room #105 Door Lock 1
3rd Floor Room # 311 A60 Window 1
3rd Floor Room # 322 A60 Window 1
3rd Floor Room # 327 A60 Window 1
3
rd
Floor Bridge Entrance
Counter frame 1
Door Handle 1
Door Lock 1
Lever Handle 1
Panic Bar 1
4th Floor Bridge Entrance Vision Panel 1
4th Floor Bridge Entrance-Double door Door Gasket 1
4th Floor Bridge Passage double door A60 Internal Door 1
6th Floors near Toilet Exit Door
Door Gasket 1
Door Handle 1
6th Floors near Toilet Exit Door Lock
Door Closers 1
Panic Bar 1
AC Store A60 Weather Tight External Door-Bolted Type 1
Battery Room
A60 Internal Door 1
Door Closers 2
Door Gasket 2
Door Handle 2
Door Lock 2
Lever Handle 2
Cable Room A60 Weather Tight External Door-Bolted Type 1
Caravan B1 A60 Weather Tight External Door-Bolted Type 1
Center Control Room Double Door A60 Weather Tight External Door-Bolted Type 1
CO2 /Halon Room A60 Internal Door 2
Computer Engineer Room A60 Weather Tight External Door-Bolted Type 1
Electric Supervisor Office A60 Internal Door 1
Emergency Door Lock near Room # 503
Door Closers 1
Panic Bar 1
Emergency Door near Room # 503
Door Gasket 1
Door Handle 1
Emergency Exit Door 421 A60 Weather Tight External Door-Bolted Type 1
Floor Bridge 6mm Glass 1
Floor Bridge Main Entrance double door A60 Internal Door 1
LCR Inside Door B15 Internal Door 1
LER 1
Door Gasket 1
Door Handle 2
Lever Handle 1
Panic Bar 1
Level Switch Gear Room #105 adjacent to workshop A60 Internal Door 1
Near Old House Set Door A60 Weather Tight External Door-Bolted Type 1

PROJECT CLIENT
PROJECT NAME CLIENT NAME
DOCUMENT NUMBER REV DATE DOCUMENT TITLE SHEET
1 19-03-14 METHOD STATEMENT FOR REPAIR OF DOORS & WINDOWS 6 of 16

Location Removal & Replacement Activities Qty
Police Man Office A60 Weather Tight External Door-Bolted Type 1
Pump Room A60 Internal Door 1
Room 189 A60 Weather Tight External Door-Bolted Type 1
Sea Water Tank Room A60 Weather Tight External Door-Bolted Type 1
Switch Room Door Closers 4
Telemetry Room A60 Weather Tight External Door-Bolted Type 2
Transformer Room
Counter frame 2
Door Closers 4
Door Gasket 4
Door Handle 4
Door Lock 4
Hinges 1
Vision Panel 2
USNGTP -LCR TOILET DOOR B15 Internal Door 1
USPGP-Ven Fan Room
Counter frame 1
Door Closers 3
Door Gasket 2
Door Handle 3
Door Lock 3
Lever Handle 1
Vision Panel 1
USWIP Mod 6-7 (instrument workshop)
A60 Weather Tight External Door-Bolted Type 1
A60 Window Glass 3
Vent Fan Room A60 Weather Tight External Door-Bolted Type 1
5.0 SEQUENCE OF EXECUTION AT SITE
As far as practically possible, the sequence of operation shall be as per agreed steps. In case of any
changes from the agreed sequence or steps are required for the safe and easy execution, then
necessary prior approval from Client to be obtained.
6.0 TOOLS AND EQUIPMENT
Common tools required to carry out this project are: - ladders, drill machines, Grinders and tool box
contain general tools like:
Hammer, Duct sealant gun, Measuring Tape, Nylon Rope, Glass catcher, Rivet gun, Spanner set,
Screw Drivers, Spirit Level Indicators Plumb, Markers, Scissors, Grip Player Multi-meter, Wire cutter,
Crimping tool, Insulation tester and other tools not referred here shall be mentioned under
appropriate section of this document.
All electrical tools / equipment are subject to periodic servicing and stamps maintenance record on
equipment. Maintenance log is controlled by Maintenance Department (Plant & Equipment
Department). Random site inspection is conducted to ensure proper servicing of relevant equipment
/ tools.
All personnel are instructed to check tools prior to usage and send unsafe equipment if any, for
servicing immediately
Toolbox talk is given at site and address above mentioned maintenance requirements to all
operatives.
Valid test certificates / tag shall be available on all relevant tools / equipment. Valid calibration
certificates shall be kept with HSE personnel and ensure availability of the same at site to ensure
HSE compliance upon tools usage at site. Valid calibration certificates shall be accompanied with
tested date and expiry date.
7.0 RESPONSIBILITIES

PROJECT CLIENT
PROJECT NAME CLIENT NAME
DOCUMENT NUMBER REV DATE DOCUMENT TITLE SHEET
1 19-03-14 METHOD STATEMENT FOR REPAIR OF DOORS & WINDOWS 7 of 16

7.1 PROJECT COORDINATOR
Coordinator role is to ensure proper coordination between COMPANY Project Team and Client
effectively. This is so essential that project is delivered on time with agreed quality standards.
He is acting as central contact point for Project team, COMPANY Operations Manager and site
supervisors. He is also responsible to maintain progress at site as per project schedule and report to
Project Manager.
Coordinates site activities to minimize - amount of night shift, extended work hours and number of
personnel involved in such activities
Inform Client regarding if any planned overtime or night shift activity happened at site. He also has
to look into risk factors in every jobs and ensure risk assessment have been maintained.
7.2 SUPERVISOR / FOREMAN
Supervisor is directly responsible for scheduling day-to-day activities on site. He ensures, work is
executed as per project specifications and project quality requirements. Follow-up and updating
construction schedule to project coordinator. Prepare material requisitions and follow-up for timely
material delivery at site. He ensures welfare and safety of personnel working under him.
Supervisor is responsible for managing their work together with other discipline teams and
supporting project coordinator to ensure that project is delivered on time with approved quality
standards.
He is responsible for resolving any quality issues raised during QC site inspections and assists Quality
Control department to ensure timely closeout of comments raised.
7.3 SUPPORT SERVICES FACILITATOR (CLIENT)
All Hot works, Painting & Coating works, Scaffolding, Craenage, Rigging, waste skip and
accessibility, Ventilation / Heating / Lighting at construction facility to be arranged by Client. All
site utilities are inspected, tested and maintained periodically by Client.
7.3.1 WASTE SKIP, RIGGING AND CRANE ASSISTANCE
All material delivered to site by COMPANY are packed and labeled for easiness of identification,
handling and transportation. Material transference at worksite is with careenage and rigging
assistance by yard. On-board material transference from crane dropping point to work location is
with rigging assistance by Client / Yard.
Rigging and mobilizing of heavy items at site to be done by on-board riggers. COMPANY supervisor
will coordinate if required.
Waste skips are arranged by Client at a nearest location to dispose construction waste. Client shall
dispose waste from skip as necessary by regulatory requirement.
7.4 MOBILIZATION & PRE-CONSTRUCTION PROCEDURES
The appropriate date for the actual start of first phase construction operations at the site will be
determined by the Project Coordinator, after consultation with the Client.
Accommodation for personnel and other containers for tools & equipment storage at site will be
planned prior to the start of Construction by project Coordinator as per agreement with Platform
in-charge.
Consideration will be given to the location of storage container, tool rooms, change rooms and plan
rest rooms to minimize walking by employees.
Care will be taken to locate office and material storage containers to minimize liability to damage
from fires or explosions which might occur from other works nearby.
Construction is controlled by the Project Coordinator who will delegate the administration of the
different construction activities to Supervisor.

PROJECT CLIENT
PROJECT NAME CLIENT NAME
DOCUMENT NUMBER REV DATE DOCUMENT TITLE SHEET
1 19-03-14 METHOD STATEMENT FOR REPAIR OF DOORS & WINDOWS 8 of 16

7.4.1 MOBILIZATION OF EQUIPMENT
Equipment required for the job execution will be identified by concerned department and intimated
to COMPANY Plant & Equipment department.
Plant & Equipment department will make sure necessary checks and tests are done as per COMPANY
procedures and Client / yard requirements prior to mobilizing to construction site.
Tagging / labelling to indicate validation status will be provided on all portable equipment, lifting
equipment & accessories, welding machines and measuring instruments.
7.4.2 GENERAL SERVICES
All construction utilities and services shall be arranged by client as per platform safety regulations.
In the absence of established arrangements, temporary utilities shall be made available as follows:
ELECTRICAL POWER & LIGHTING
Power requirements to support all planned and anticipated needs shall be discussed with Client
SITE MEDICAL FACILITIES
Project Coordinator in consultation with Client shall ensure that arrangements are available within
platform to provide medical assistance for injured employees.
FIRE FIGHTING
COMPANY in consultation with Client shall ensure appropriate arrangements for firefighting
equipment and shall develop emergency response plan specific to construction area.
PERMITS - WELDING, WORK AND FLAME
If any hot work required to be carried out by COMPANY, then Project Coordinator shall determine
and communicate to all concerned the policy of the Client related to welding, work and flame
permits.
8.0 ACCOMMODATION, FOOD AND TRANSPORTATION OF COMPANY STAFF
It is anticipated that, during construction, Client will provide accommodation and catering.
Necessary assistance for daily conveyances (if any) from accommodation to work location and back
to accommodation from work location shall be arranged by Client.
9.0 WASTE SKIP, RIGGING AND CRANE ASSISTANCE
Construction waste and household waste shall be handled as per approved waste management
procedure. Waste skips shall be arranged by Client at a nearest location in order to dispose
construction waste and the removed existing installation components. Client shall make necessary
arrangement to dispose waste from skip as necessary by regulation.
Materials delivery to work location shall be by Client and shall be in accordance with list furnished
by COMPANY with necessary segregation and location wise identification for easiness of usage.
Rigging and mobilizing of heavy materials at site near to the installation location shall be done by
Client representative. COMPANY supervisor shall coordinate as necessary.
10.0 COMFORT AND SAFETY FOR THE PLATFORM CREW WHILE CONSTRUCTION
10.1 NOISE & VIBRATION MITIGATION PROGRAM
While carrying out removal / refurbishment works, COMPANY will ensure that risk due to exposure
to noise is either eliminated at source or, where this is not reasonably practicable, reduced to as
low a level as is reasonably practicable using suitable work planning and adopting proper work
methods.

PROJECT CLIENT
PROJECT NAME CLIENT NAME
DOCUMENT NUMBER REV DATE DOCUMENT TITLE SHEET
1 19-03-14 METHOD STATEMENT FOR REPAIR OF DOORS & WINDOWS 9 of 16

Construction areas will be isolated from the living space; proper barricading and warning signs
will be erected to alert other personnel.
Appropriate work schedules: noise generating activities will be planned for day shifts (to
minimize disturbance to Platform crews, limitation of the duration and intensity of exposure to
noise;
Use of power tools will be limited to minimum to reduce noise levels
Use of appropriate work equipment and tools emitting the least possible noise, taking account
of the work to be done;
Toolbox talks / awareness programs - suitable and sufficient information and training for
employees, such that work equipment may be used correctly, in order to minimize the noise;
Other measures to control noise - ensuring appropriate maintenance programmes for tools &
equipment, safe operating procedures, proper supervision etc.
Noise level assessment will be done (if needed) and corrective measures will be taken to
improve the situation
10.2 HOUSEKEEPING PRACTICES
Housekeeping is a continuous process to prevent accidents to employees and our customers.
Each employee will be responsible for cleaning up his / her own work area.
Aisles, passageways and exit corridors will not be used for the storage of material / tools.
All tools will be collected and returned to their proper places after completing the work.
COMPANY will make sure that no tool or appliance has been left in any place where it might fall
or cause damage when the power is turned on.
Walkways, stairs and fixed ladders shall be kept free of obstructions.
Any surplus materials will be returned to stock or proper storage areas.
Work areas will be kept clean and neat. Supervision will ensure tools and equipment arranged
in a safe, orderly manner.
Rubbish shall be placed only in appropriate containers.
Equipment or materials will be neatly stored when not in use.
Fire and hazard prevention inspections shall be conducted regularly by Safety Officer onboard
Safety Officer will ensure exits are clear at all times.
Exit and fire doors will be unblocked and Operational always.
10.3 WASTE MANAGEMENT
All removed material will be taken out onto designated waste storage area, where it will be
disposed in appropriate waste skips provided by Platform.
Waste storage area shall be properly labeled and warning signs will be erected.
Separate skips are to be provided by the platform according to type and nature of waste as per
Platform waste management procedure
Designated waste storage area shall be free of any fire hazard and shall not pose any
obstruction to personnel or material movement


PROJECT CLIENT
PROJECT NAME CLIENT NAME
DOCUMENT NUMBER REV DATE DOCUMENT TITLE SHEET
1 19-03-14 METHOD STATEMENT FOR REPAIR OF DOORS & WINDOWS 10 of 16

11.0 WORK METHODOLOGY
11.1 INSTALLATION OF DOORS MANUFACTURER
11.1.1 MATERIALS AND TOOLS
A-door, lock systems, door holders (clamps), screws (bolts), steel treatment tools (drill, thread...),
Measure tools, Installation drawing
11.1.2 MANUFACTURER INSTRUCTION
All doors should be installed according to door plan and accommodation drawings.
Cut-outs should be prepared based on door list.
A-door are installed in steel bulkhead. Make sure that doors are levelled during and after
installation.
Pay attention that top line of all doors in common areas are at the same level. Keep in mind to
secure space for additional accessories (door holders, door closers and other if specified). Strictly
follow door plan, door list and lock system scheme.
11.1.3 INSTALLATION PROCEDURE
1. Check that the size of the steel cut out is correctly measured and cut, distance between frame
and cut out to be 15 mm (2 mm)
2. Check that the steel bulkhead is straight and has the correct angles. Tolerance for length in
range 400-2500 mm : 2mm
3. Place the door in the cut out, bulkhead and frame should overlap 40 mm ( 2 mm), once again
check if bulkhead adhere frame (length 400-2500 mm : 2mm).
4. Fasten the hinge side of frame with clamps, after ensuring is vertical and distance between
frame and bulkhead all side is 15 mm, bolt the frame to the bulkhead in position 1 and 2.
5. Check distances between door leaf and door frame, adjust by lifting and lowering the lock side
part of the frame. Check width and diagonals in positions indicated on enclosed drawing and
bolt in pos. 3. Tolerances for lengths 2 mm, tolerance for diagonal difference 4 mm
6. Limited corrections of inequalities can be made before placing 4th bolt by pressing the down
corner inwards or outwards door leaf.
7. Fasten the frame with remaining bolts (max. distance between bolts can not be grater than 300
mm). Force used for screwing can not cause frame or bulkhead deformation! ( we recommend
to stop screwing after reaching first screw resistance when using hand wrench - around 15 Nm).
8. Make opening and closing test, adjust the hinges if necessary.
Note: hinges and locks should be oiled from time to time.
11.2 INSTALLATION OF DOORS (MANUFACTURER)
11.2.1 PRODUCT DESCRIPTION
Hinged Single & Two leaf A60 Rated Hinged Door with a pressed steel frame.
11.2.2 HARDWARE
Emergency exit panic bar operation fitted to the inside face of the door leaf.
Lockable Lever handle fitted to the outside face of the door leaf.
Overhead door closer fitted to the inside face of the door leaf.
Perimeter neoprene rubber seals and seal trims, fitted to the doorframe.

PROJECT CLIENT
PROJECT NAME CLIENT NAME
DOCUMENT NUMBER REV DATE DOCUMENT TITLE SHEET
1 19-03-14 METHOD STATEMENT FOR REPAIR OF DOORS & WINDOWS 11 of 16

Vision panel fitted to the Active door leaf.
Lift off stainless steel hinges, fitted to the door leaf & frame.
Top & Bottom shoot bolt fitted to the Passive leaf (Two Leaf Door Sets).
11.2.3 INSTALLATION PERSONNEL
Installation should be carried out by experienced door installers under strict supervision.
11.2.4 TOOLS AND EQUIPMENT
All hand tools should be fit for purpose and periodically checked for damage. All electrical tools to
be no greater than 110V and have current PAT test certificates.
All lifting equipment to have current test certificates (Client assistance).
11.2.5 LIFTING EQUIPMENT
The installation should be assisted by mechanical lifting equipment e.g. - crane, fork truck, chain
blocks with lifting beam, etc.
The installation area itself would govern the choice of lifting equipment to be used.
11.2.6 PREINSTALLATION
Barrier off the installation area, as reasonably practical, ensuring emergency access / egress is
always available.
Check the structural opening dimensions against the approved detailed drawings.
Check the supplied door assembly components against the approved detailed drawings.
Any major deviations to the dimensions should be reported to the site supervisor before any other
works are carried out.
11.2.7 INSTALLATION DOORFRAME (WEIGHT 45 KG-APPROX)
The doorframe supplied in one piece and have pre-drilled fixing holes at the required positions.
The hinge pin half of the door hinges will be bolted to the frame ready to install the door leaf
onto them, via the door leaf half hinge.
Manually, insert the frame into the structural opening, and clamp it to the structure temporarily
with suitable G clamps.
M10 x 30mm long hexagon head bolts will be supplied to fix the doorframe to the structure.
The frame fixing holes can now be drilled into the structure using the frame itself as template,
insert the M10 fixings and securely tighten them.
Remove the temporary clamps.
11.2.8 INSTALLATION DOOR LEAF (WEIGHT 161 KG APPROX)
The door leaf should be installed via mechanical lifting equipment where possible.
If mechanical lifting equipment cannot be used due to a restricted / inaccessible area, enough
labour should be available for manual handling.
With the door leaf placed horizontally on the floor, with timber blocks under to support, sling the
door leaf, top to bottom, with a suitably long 1T capacity webbing sling, choking the sling at the
top of the door.
Connect the sling to your chosen mechanical lifting equipment, i.e. fork lift truck, manual genie
lift, etc, and raise it to the vertical position.

PROJECT CLIENT
PROJECT NAME CLIENT NAME
DOCUMENT NUMBER REV DATE DOCUMENT TITLE SHEET
1 19-03-14 METHOD STATEMENT FOR REPAIR OF DOORS & WINDOWS 12 of 16

Manoeuvre the door into position at 90 degrees (door open) to the installed doorframe and engage
the door leaf hinges onto the frame hinge pins.
Remove the lifting equipment.
Repeat the above procedure to install the second door leaf on a Two Leaf Door Set.
Check the operation of the door by opening & closing it.
Check that the door seals are effective. The seals are adjustable by loosening the M6 x 12 long cap
head seal holder trim fixing bolts, adjust as necessary via the slots in the seal holder trim, and re-
tighten the bolts.
Using the door closer installation instructions, supplied with the closer, fit the door closer with the
fixings that are supplied with it.
The door & frame will be already prepared with the fixing holes (drilled & tapped).
The door closer can be adjusted (speed & pressure) as per the closer instructions.
11.3 INSTALLATION OF WINDOWS (MANUFACTURER)
11.3.1 DESCRIPTION
Holes in the plating for windows and portholes should be laid out according to the fixed frames, if
possible. The size of the slit between the edge of the burnt-out hole and the adjacent surface of
the frame must not exceed 1.5 mm.
The plating within the hole should be levelled and checked with a ruler. Straightening of walls after
assembly windows is forbidden. In assembly of screwed-on windows and portholes, particular
attention should be paid to precise sealing of the slit between the wall surface and the window or
porthole frame flange and the holes for clamping screws. Arrangement of holes for clamping screws
should be done according to the pattern or laid out according to the frame.
11.3.2 MODE OF PROCEDURE
1. Clean and degrease the sealing surfaces of the flange and the wall.
2. Place a seal or apply a sealing compound (e.g. Sika 221) on both sides of the clamping holes.
3. Apply the compound to the wall around each clamping hole.
4. Place a window or a porthole in the hole. In case of a porthole, the flange holes should be
placed in the wall holes right in the desired position.
5. Screw on the bolts.
6. Remove excessive sealing compound.
11.4 REPLACING WINDOW GLASS (MANUFACTURER)
Before installing the glass onto the frames, check the thickness of glass (t) and glass laying area (s)
and compare with drawing
Clean the glass laying area on the main frame and check the requirement of surface coating, if
necessary get painted by Client.
Check the gasket for its appropriateness (selected acc. to IBH-038) cut for length off and stick on
frames. Place of joint should be on t op, Seal the joint of gaskets with seawater resistant, flexible
sealant (for ex. SIKA221)
Put glass pane (5) into the frame keep gap between glass and frame approx. 4mm
Align it using wooden (oak tree) spacers (on bottom 3pcs, other sides 2pcs, 1pc. on every radius)
and secure with i.e. IKA221.
Screw glass list using H6x16 screws and set proper torque (for brass screw 4Nm & Steel Screw 8Nm),
Conduct water Hose Test if required by Client.

PROJECT CLIENT
PROJECT NAME CLIENT NAME
DOCUMENT NUMBER REV DATE DOCUMENT TITLE SHEET
1 19-03-14 METHOD STATEMENT FOR REPAIR OF DOORS & WINDOWS 13 of 16

Protect the Glass if required per site conditions.
12.0 INSPECTION
Ensure all installations are as per Client requirements and in accordance with manufacturer
instructions. Ensure that accessories are not damaged during installation. Make sure level of fittings
is correct.
12.1 CLOSE OUT / COMPLETION REPORTS
With reference to approved Inspection test Plans, at defined stages - all activities carried out by
COMPANY are offered for Client Inspection Personnel.
After completion of entire activities within COMPANY Scope of work- without any outstanding punch
lists or issues and all equipment are ready for operation, this stage is considered as customer
acceptance stage. During this stage, all safety aspects of the project have been satisfactorily
completed, Customer Acceptance Certificate signature obtained on completion report / Job card,
and as a result, the entire process is considered closed out.
13.0 ATTACHMENTS / REFERENCE
SOW MU 173 : Technical Scope of Work for PLATFORM Refurbishment / Repair of Doors and
Windows
Tender Bulletin No.1 for Tender No: 44195- PLATFORM Refurbishment / Repair of Doors and
Windows
Scope of Work document (COMPANY Document) for job number 02110036
Shop drawings and key component catalogues are attached below within this document for review.
14.0 ENVIRONMENTAL, SAFETY AND HEALTH
The HSE rules and regulations at site shall be maintained as per Platform HSE policy and project
specific HSE PLAN (if any).
14.1 RISK ASSESSMENT
Hazards identified, Risks at each stage are evaluated, utilizing the risk rating matrix (table 1) as to
determine the level of significance in terms of likelihood of occurrence and severity of hazard based
on the allocated numerical values.
14.2 SPECIFIC EMERGENCY PROCEDURES
A Certified First aider shall be on site at all times whilst a First Aid Clinic shall be available for
treatment of light injuries.
In the event of an emergency, all workers will assemble at an area which shall be allocated by a
post sign and wait for further instructions. This point will be normally marked with a sign as
MUSTER POINT or ASSEMBLY POINT. The supervisor can assist employees and direct them to the
assembly point.
14.3 TOOL BOX TALK
Supervisor shall conduct daily toolbox talks relevant to work activity prior to commencing daily job.
Before signing the tool box talk sheet (Table-2) supervisor shall ensure the below (when applied) to
the employees involved in the work activity during the TOOL BOX TALK.
No work at height to be undertaken without a safe working platform or suitable fall protection
system.
Work on electrical equipment must only be performed by a qualified electrician.

PROJECT CLIENT
PROJECT NAME CLIENT NAME
DOCUMENT NUMBER REV DATE DOCUMENT TITLE SHEET
1 19-03-14 METHOD STATEMENT FOR REPAIR OF DOORS & WINDOWS 14 of 16

No hazardous work to be undertaken without a permit system in place including: electrical
energisation, confined spaces, hot works.
No person to work on scaffolding which has not been inspected and approved for use with a
Green Tag.
All lifting operations shall be controlled by a competent person and all lifting equipment must
be inspected and correctly colour coded (Client scope).
No person will operate plant or equipment unless they have been trained, certified and
authorized to do so.
Do not commence any work activity unless suitable lighting for the task is available.
Any deliberate interference with safety equipment, abusive behaviour, fun or deliberate failure
to comply with site will result in removal from site.
14.4 PERSONAL COMMITMENT
I will wear my PPE at all times.
I will do my best to prevent pollution damage to the environment.
I will use the welfare facilities provided for me.
I will protect the safety of my fellow workers.
If I work safely each day, I will go home each day.


PROJECT CLIENT
PROJECT NAME CLIENT NAME
DOCUMENT NUMBER REV DATE DOCUMENT TITLE SHEET
1 19-03-14 METHOD STATEMENT FOR REPAIR OF DOORS & WINDOWS 15 of 16

TABLE-1 RISK RATING MATRIX


HAZARD SEVERITY
L
I
K
E
L
I
H
O
O
D

/

P
R
O
B
A
B
I
L
I
T
Y

O
F

O
C
C
U
R
R
E
N
C
E

PEOPLE
(S1)
NEGLIGIBLE
Minor first
aid
injury, no
absence
from
work
(S2) SLIGHT
Injury
resulting
in a MTC or
RWC

(S3)
MODERATE
Accident
leading
to a lost
Time
injury (LTI)
(S4) SEVERE
Permanent
disability or
multiple
hospitalizatio
n
(S5) HIGH
Fatality

ENVIRONMENT
No impact
No recovery
required
Localized
within
site
boundaries
Possible
wide
spread
harm
Serious wide
spread effect
Significan
t wide
spread
harm
ASSET DAMAGE <1000 AED <10,000 AED
<100,000
AED
<1000,000
AED
>1000,000
AED
COMPANY REPUTATION
DAMAGE
Slight local
impact
Limited
local impact
Considerab
le local
impact
National
impact
Internatio
nal
impact
(F1) VERY UNLIKELY
A freak combination of
factors would be
required for an incident to
result
LOW
1
LOW
2
LOW
3
MEDIUM
4
MEDIUM
5
(F2) UNLIKELY
A rare combination of
factors would be
required for an incident to
result
LOW
2
MEDIUM
4
MEDIUM
6
MEDIUM
8
MEDIUM
10
(F3) POSSIBLE
Could happen when
additional factors are
present but otherwise
unlikely to occur
LOW
3
MEDIUM
6
MEDIUM
9
MEDIUM
12
HIGH
15
(F4) LIKELY
Not certain to happen but
an additional
common factor is likely to
result in an incident
MEDIUM
4
MEDIUM
8
MEDIUM
12
HIGH
16
HIGH
20
(F5) VERY LIKELY
Almost inevitable that an
incident would result
MEDIUM
5
MEDIUM
10
HIGH
15
HIGH
20
HIGH
25

PROJECT CLIENT
PROJECT NAME CLIENT NAME
DOCUMENT NUMBER REV DATE DOCUMENT TITLE SHEET
1 19-03-14 METHOD STATEMENT FOR REPAIR OF DOORS & WINDOWS 16 of 16

TABLE 2 TOOL BOX TALK SHEET

TOOLBOX TALK
RECORD
It is compulsory that all personnel involved in work activity shall be present in toolbox talk at activity
location and sign as being present
Project: Talk Location:
Work Location: Date: Time
Disciplines:
Conducted by: Signature:
Attendees:
Work activity / talk topic (attach details if required): Area Covered

Sl.no. Name Signature

Sl.no. Name Signature
01

11

02

12

03

13

04

14

05

15

06

16

07

17

08

18

09

19

10

20

Permit to work ref.: Risk / COSHH* Assessment ref.: Current areas of concern / trends:



*COSHH: Control of Substances Hazardous to Health, Task Risk Assessment for routine tasks is available
from HSE Dept. Risk assessments for more complex tasks shall be generated as required by Project
Manager / HSEQ Representative.
General comments / observations / feedback on Toolbox Talk effectiveness and workforce feedback.
Comments: