Nos. % Nos. % Nos. % 1 AMANA 3 18% 16 12% 19 13% 2 ARCC 1 6% 5 4% 6 4% 3 ASYAD 1 6% 3 2% 4 3% 4 FCN 0 0% 1 1% 1 1% 5 GACC 0 0% 4 3% 4 3% 6 IKK 0 0% 3 2% 3 2% 7 KCC 2 12% 10 8% 12 8% 8 PSCL 0 0% 1 1% 1 1% 9 PCMC 0 0% 2 2% 2 1% 10 SENDAN 0 0% 7 5% 7 5% 11 SENDAN/DAELIM 0 0% 1 1% 1 1% 12 TCC 1 6% 12 9% 13 9% Subtotal 8 47% 65 50% 73 50% DAELIM 1. Engineering: - Eng. 6 35% 14 11% 20 14% - Inst. 0 0% 1 1% 1 1% - Mech. 0 0% 8 6% 8 5% 2. Construction: - Civil 0 0% 1 1% 1 1% - Elect 1 6% 3 2% 4 3% - Mech. 1 6% 13 10% 14 10% 3. Procurement: - Mat'ls 0 0% 14 11% 14 10% - Mech. 0 0% 5 4% 5 3% 4. Mat. Deprt.: - Mat'ls 0 0% 1 1% 1 1% - Mech. 1 6% 0 0% 1 1% - Preservation 0 0% 2 2% 2 1% 5. Preservation - Telecom 0 0% 1 1% 1 1% 6. Mat & Pro. Dept - Mat'ls/Pro. 0 0% 1 1% 1 1% Subtotal 9 53% 64 50% 73 50% 17 100% 129 100% 146 100% 13 GRAND TOTAL TOTAL (PN & VAF) S/N Proactive Notification (PN) Violation After Fact (VAF) Contractor/ Subcontractor LOG BOOK ENTRY (LBE) SUMMARY As of July 30, 2014 DUE DATE Issued corrective action to Company Target Date LBE-AMA-ELECT- 001 AMA VAF ELECT Electrical 23-Mar-12 26-Mar-12 06-Apr-12 07-May-12 Closed LBE-AMA-ELECT- 002 AMA VAF ELECT Electrical 23-Mar-12 26-Mar-12 06-Apr-12 07-May-12 Closed LBE-AMA-CIVIL-001 AMA VAF CIVIL Civil 24-Mar-12 27-Mar-12 07-Apr-12 05-May-12 Closed LBE-AMA-CIVIL-002 AMA VAF CIVIL Civil 24-Mar-12 27-Mar-12 07-Apr-12 16-Jun-12 Closed LBE-AMA-CIVIL-003 AMA VAF CIVIL Civil 24-Mar-12 27-Mar-12 07-Apr-12 12-May-12 Closed LBE-AMA-CIVIL-004 AMA VAF CIVIL Quality Management 24-Mar-12 27-Mar-12 07-Apr-12 04-Apr-12 Closed LBE-AMA-CIVIL-005 AMA VAF CIVIL Civil 26-Mar-12 29-Mar-12 09-Apr-12 04-Apr-12 Closed LBE-AMA-CIVIL-006 AMA VAF CIVIL Civil 29-Mar-12 01-Apr-12 12-Apr-12 15-Apr-12 Closed LBE-AMA-CIVIL-007 AMA PN CIVIL Civil 02-Apr-12 05-Apr-12 16-Apr-12 10-Apr-12 Closed LBE-AMA-CIVIL-008 AMA VAF CIVIL Civil 03-Apr-12 06-Apr-12 17-Apr-12 07-Apr-12 Closed LBE-AMA-CIVIL-009 AMA PN CIVIL Civil 03-Apr-12 06-Apr-12 17-Apr-12 15-Apr-12 Closed LBE-AMA-CIVIL-010 AMA VAF CIVIL Civil 04-Apr-12 07-Apr-12 18-Apr-12 12-Apr-12 Closed LBE-AMA-CIVIL-011 AMA VAF CIVIL Civil 04-Apr-12 07-Apr-12 18-Apr-12 13-Apr-12 Closed LBE-AMA-CIVIL-012 AMA VAF CIVIL Civil 05-Apr-12 08-Apr-12 19-Apr-12 15-Apr-12 Closed LBE-AMA-CIVIL-013 AMA VAF CIVIL Civil 08-Apr-12 11-Apr-12 22-Apr-12 15-Apr-12 Closed LBE-AMA-CIVIL-014 AMA VAF CIVIL Civil 10-Apr-12 13-Apr-12 24-Apr-12 22-Apr-12 Closed LBE-AMA-CIVIL-015 AMA VAF CIVIL Civil 17-Apr-12 20-Apr-12 01-May-12 22-Apr-12 Closed LBE-DLM-CIVIL-016 DAELIM VAF CIVIL Quality Records 24-Apr-12 27-Apr-12 08-May-12 08-May-12 Closed LBE-AMA-CIVIL-017 AMA VAF CIVIL Civil 25-Apr-12 28-Apr-12 09-May-12 07-Jul-12 Closed LBE-AMA-CIVIL-018 AMA PN CIVIL Civil 25-Apr-12 28-Apr-12 09-May-12 20-May-12 Closed LBE-AMA-CIVIL-019 AMA VAF CIVIL Civil 01-May-12 04-May-12 15-May-12 20-May-12 Closed LBE-AMA-CIVIL-020 AMA VAF CIVIL Civil 01-May-12 04-May-12 15-May-12 07-May-12 Closed LBE-AMA-CIVIL-021 AMA PN CIVIL Civil 01-May-12 04-May-12 15-May-12 09-May-12 Closed LBE-AMA-CIVIL-022 AMA VAF CIVIL Civil 05-May-12 08-May-12 19-May-12 20-May-12 Closed During surveillance inspection at the Concreted Gas Furnace foundation F1170, at 0840 hrs., 17/04/12, it was observed that the surface of the newly & concreted foundation is dry without plastic sheeting or burlap covering. The water truck delivering curing water was just arriving at the time. Concrete pouring was completed around 2200 hrs. on 16/04/12. This is in violation of RT25-3001-01 Section 9. Batch Plant QC Inspector from Contractor Daelim & Sub-contractors are not issuing RFIs to SADARA for Batch Plant Management at Qanbar RMC during scheduled hours. This is in violation of Inspection & Test Plan and concrete specifications. No RFIs were issued on 23/04/12, 22/04/12. PN: Due to the onset of summer hot days, concreting should be scheduled by the rise in ambient temperature. Today, measured ambient temperature exceeds 43C at 1400hours, while rebar temperatures exceeds 50C. Contractor to follow section 5.2 of RT2S-3001-01. During surveillance inspection, it was found out that the Contractor has carried out concrete repairs at Liquid Furnace FDNs F-1250. There was no submission yet of concrete repair procedure to Company which requires approval. This is in violation of section 11 of RT2S-3001-01. PN: It was observed that there are numerous surface defects on the completed Liquid Furnace FDN F- 1250 after removal of formworks. Contractor to submit concrete repair procedure with Materials to be used for approval. Inadequate water covering at the Gas Furnace FDNs F1130, F1160 and Liquid FDNs F1240, which are less than 7 days old concrete. These are gaps in the plastic sheet and are blown by wind. For F1240, the side forms have been removed and sides of the concrete FDN are totally exploded without any form of concrete curing. Violations to Section 9 of RT25-3001-01. During material receiving for FBE coated reinforcing bars, bundles of 25 mm bars were found with excessive uncoated lugs on the rebar exceeding the 2% max. allowed for coating damages. As advised to the QC Inspectors of both Contractor & Sub-contractor, the rejected bars are required to be quarantined and separated from the accepted bars. Reference to Site Quality Deficiency Report (SQDR-AMA-CI-008) the test frequencies as stipulated in the Concrete Specification have not been complied with for the concrete ingredients per sections 2.4.7 and 2.2.15. These are repeated violations of these sections. The SQDR-AMA-CI-008 has been closed without valid documents to prove closure. S/N LBE NO. PID SUBCON/ CONTRACTOR VAF / PN The contractor has started concreting activities (Lean Concrete pouring) however, an approved Concrete Quality Control Engineer (CQCE) is not available. This is in violation of RT25-3001-01 Concrete Specification section 1.5.2 The quality control program which shall be prepared by the CQCE is also not available. (Required by RT25-3001-01 section 1.5.3. The contractor has no approved batch plant QC Inspector as required by Schedules of attachment 1, during the batching of lean concrete for liquid furnace FDN. During inspection at site, it was found out that there are two revision drawings in circulation at the site. Drawing nos. A554-E-103-CV-DWG-C30-331 to 343 Rev. 1 are being used by the construction team. Violation to schedule Q section 3.2 The contractor has issued RFIs which includes concrete pouring of lean concrete. The contractor however has no approved (ITP) Inspection & Test Plans and Checklist. The work activities require ITPs for Earthwork Concrete and Earthing. A violation of schedule Q, section 3.3. The contractor has issued RFIs which includes concrete pouring of lean concrete. The contractor however has no approved (ITP) Inspection & Test Plans and Checklist. The work activities require ITPs for Earthwork Concrete and Earthing. A violation of schedule Q, section 3.3. The contractor has proceeded with the Lean Concreting of Liquid Furnace FDN without approved Mix Design. RT25-3001-01 Concrete Specification section 3.5.3 specifies that No concrete pouring shall commence before trial mixes, 28 days compression test and all other test in this specifications are completed and approved by Owner. LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason Company comment Approved Close LBE by Company STATUS The contractor has issued RFIs which includes concrete pouring of lean concrete. The contractor however has no approved (ITP) Inspection & Test Plans and Checklist. The work activities require ITPs for Earthwork Concrete and Earthing. A violation of schedule Q, section 3.3. During preliminary inspection of reinforcing bars installation for FDN F-1250, Liquid Furnace area, it was found out that the concrete cover along the perimeter of the foundation are less than the minimum requirements reveal readings of down to 30mm only. Violation to IFC drawing # A554-E-103-CV-DWG- C30-334 Rev. 2. During inspection the vertical S. No. 14 (LH) for pedestals P7 at Liquid Furnace do not comply with IFC DWG # A554-E-103-CV-DWG-C30-315 rev. 2. The bar bending schedule & details DWG # AMA- SMFCP-CV-001 shows different bending detail for s.no. 14 than that is required in the IFC drawing. During inspection of M30 & M36 anchor bolts for furnace, no measuring tool for checking diameter of bolts. The nuts for M36 bolts are grade 105, ASTM A563, while DWG A554-E-103-CV-DWG-599-402 requires grade DH ASTM A563. PN: Contractor has to provide sufficient curing water meeting the requirements of concrete mixing water at site for curing of concrete structures. It is recommended that records of that test maintained at site. During receiving of reinforcing bars for gas furnace FDN, tags are only found on one end of the bundles and are not traceable to the mill certificate batch numbers. RT25-3001-01 section 2.5.4.3 requires tags at each end of bundles. During surveillance, it was observed that newly delivered inspection reinforcing bars without receiving inspection are being installed at gas furnace FDN F1140. The mill test certificates are not yet available for review & verification relative to the reinforcing bar deliveries. Violation to ITP & RT25-3001-01 section 2.5. Contractor has started installing reinforcing bars at Liquid Furnace Area FDN L17-L20 while the tests for tensile/elongated and bend/re-bend tests have not yet been done as required by RT25-3001-01 section 2.5 PN: Reinforcing bars installation at Gas Furnace area tooting F1170 were observed with inclined position of some bars and irregular spacing. Contractor to rectify to comply with placement as shown on IFC drawings and as per section 7.1.1/7.1.2 RT25-3001-01. During inspection for receiving, storage and presentation of reinforcing bars, it was observed that some bundles were laid directly on the concrete slab, in violation of section 2.5.4.4 RT25-3001-01. Unbundled bars were also observed scattered on the concrete slab. CONTRACTOR'S CORRECTIVE ACTION PLAN Page 2 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 30, 2014 DUE DATE Issued corrective action to Company Target Date S/N LBE NO. PID SUBCON/ CONTRACTOR VAF / PN LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason Company comment Approved Close LBE by Company STATUS CONTRACTOR'S CORRECTIVE ACTION PLAN LBE-AMA-CIVIL-023 AMA VAF CIVIL Quality Records 05-May-12 08-May-12 19-May-12 08-May-12 Closed LBE-KCC-CIVIL-024 KCC VAF CIVIL Quality Management 08-May-12 11-May-12 22-May-12 20-May-12 Closed LBE-DLM-CIVIL-025 DAELIM VAF CIVIL Civil 09-May-12 12-May-12 23-May-12 20-May-12 Closed LBE-KCC-CIVIL-026 KCC VAF CIVIL Civil 09-May-12 12-May-12 23-May-12 07-Jun-12 Closed LBE-AMA-CIVIL-027 AMA VAF CIVIL Civil 10-May-12 13-May-12 24-May-12 17-Jun-12 Closed LBE-AMA-CIVIL-028 AMA VAF CIVIL Civil 10-May-12 13-May-12 24-May-12 02-Jun-12 Closed LBE-AMA-CIVIL-029 AMA VAF CIVIL Civil 10-May-12 13-May-12 24-May-12 23-Jun-12 Closed LBE-AMA-CIVIL-030 AMA VAF CIVIL Civil 12-May-12 15-May-12 26-May-12 06-Jun-12 Closed LBE-DLM-CIVIL-031 AMA VAF CIVIL Quality Management 14-May-12 17-May-12 28-May-12 26-May-12 Closed LBE-AMA-CIVIL-032 AMA VAF CIVIL Civil 17-May-12 20-May-12 31-May-12 16-Jul-12 Closed LBE-AMA-CIVIL-033 AMA PN CIVIL Civil 20-May-12 23-May-12 03-Jun-12 23-May-12 Closed LBE-AMA-CIVIL-034 AMA VAF CIVIL Civil 20-May-12 23-May-12 03-Jun-12 16-Jul-12 Closed LBE-AMA-CIVIL-035 AMA VAF CIVIL Civil 22-May-12 25-May-12 05-Jun-12 26-May-12 Closed LBE-AMA-ELECT- 003 AMA VAF ELECT Electrical 24-May-12 27-May-12 07-Jun-12 03-Jun-12 Closed LBE-KCC-CIVIL-036 KCC VAF CIVIL Civil 04-Jun-12 07-Jun-12 18-Jun-12 09-Jun-12 Closed LBE-KCC-CIVIL-037 KCC VAF CIVIL Civil 06-Jun-12 09-Jun-12 20-Jun-12 09-Jun-12 Closed LBE-AMA-CIVIL-038 AMA VAF CIVIL Civil 06-Jun-12 09-Jun-12 20-Jun-12 17-Jul-12 Closed LBE-AMA-ELECT- 004 AMA VAF ELECT Electrical 10-Jun-12 13-Jun-12 24-Jun-12 13-Jun-12 Closed LBE-AMA-ELECT- 005 AMA VAF ELECT Electrical 21-Jun-12 24-Jun-12 05-Jul-12 25-Jun-12 Closed LBE-KCC-CIVIL-039 KCC VAF CIVIL Civil 23-Jun-12 26-Jun-12 07-Jul-12 07-Jul-12 Closed LBE-AMA-CIVIL-040 MR. YAP AMA VAF CIVIL Civil 27-Jun-12 30-Jun-12 11-Jul-12 01-Oct-13 Closed LBE-AMA-CIVIL-041 AMA VAF CIVIL Civil 27-Jun-12 30-Jun-12 11-Jul-12 24-Jul-12 Closed PN: During surveillance inspection, it was observed that the bottom bent bars of E-W pipe rack A FDN F3 at gridline GL 21-23 GL 18-20 and GL 24-26 (Amana) have less than 75 mm concrete cover with some bars touching the lean concrete along the slopes. Violates section 7.1.8 RT2S-3001-01. Surveillance inspection at Gas Furnace FDN F-1170 Pedestals, it was found out that anchor bolts at Pedestal F3 at GL 26/GF and P18 at GL GL/GH exceeded the 1:100 plumbness tolerance limit in violation of section 8.1 RT2S-3001-01 (Random Measurement 15mm: 295 mm) During review of calibrations, it was found out that Calibration Certificates of Batch Plant (Qanbar Satorp) ice, water, cement and admixtures weighing/batching equipment have already expired. Last calibration was on March 30, 2012. Per RT2S-3001-01, section 4.1.3.i required frequency of calibration is 6 weeks. The applied bituminous coating at Liquid Furnace FDNs F-1250 and F-1240 do not comply with Document No. A554-K-PRG-PI-SPC-VIA-150 Protective Coatings for Industrial Concrete Structures, Section 5.1 where RTAPCS-3, Coal Tar Epoxy System and RTAPCS-3, High Build Liquid Epoxy System for Buried Concrete and Steel, are the required coating systems. This is also subject of LBE No. 028 with Nitoproof 100 bitominous coating used; in violation of standard A554-K-PRG-PI-SPC-VIA-150 requirements. Due to the day & night schedules of work for concrete as a result of high temperature (ambient) in the daytime, Daelim has insufficient QC Inspector for FDN/concrete works. At present only one QC Inspector for FDN/Concrete is available to cover day & night concrete works. Violation of schedule Q, section 3.2. During surveillance inspection at Liquid Furnace F-1250 pedestals, it was observed that anchor bolts on pedestals P6 at L6/L18; P5 at LA/L18; P19 at GL/PS2 and P4 at La/L19, (2 each on P6, P5 and P19 and 1 pc on P4) have exceeded the plumbness tolerance; In violation of RT2S-3001-01 section 8.1 where limit is 1:100. Foundation F1170 Gas Furnace pedestal P7 (2 units) were concreted on 09 May 2012. The block-out shown on DWG # A554-E-103-DWG-C30-341 Rev. 1 with dimension of 550W X 300L X 150# clashes with the standard hooks reimbursements as shown on section drawing A-554-103-DWG-C30-335 Rev. 1. This should be resolved with the designer and drawings revised prior to concreting. During surveillance inspection, it was found out that the Contractor has started concrete coating on the east side vertical faces of Liquid Furnace foundations F-1250 and F1240. There were no approved repair procedures, there was no repair performed and there was no approved ITP for concrete coating. Likewise, the applicators have no training as the Coating was applied without surface preparations. Violation to schedule Q, section 3.2. During surveillance inspection, TPER joints were found damaged at Gas Furnace foundations F-1130 (2 pcs) and F-1140 (1 pc). The damages were at the joints of the factory prepared T-joints. During Surveillance, it was found out that the Column ties for the on-going fabrication of reinforcing bars for columns at the N-S Main Pipe Rack are not as per IFC Drawings, A554-E-103-CV-DWG-C40-002, CI Column detail. Hoop bars and DH bars do not have hooks and are being installed. During Surveillance inspection at 1100-1130 hours, 24/06/12, it was observed that the finishing works on E-W Pipe Rack B FDN F-7 is still on-going with visible cracks on surfaces that had already dried-out. Per records of Concrete delivery, the last truck mixer delivered on site at 23:40 hours 26 June 12 and had completed pouring at around 01:00 hours, 27/06/12. Workers were observed adding water (re- tempering) to the concrete surface to facilitate finishing, as the concrete had already hardened due to more than 10 hours elapsed after deposition. There are violations to Sections 9.14.2 and 5.4.17 of RT2S- 3001-01. Subcon: Work Cannot proceed due to TCC activities Surface preparation shall be undertaken by Contractor/ Subcontractor upon completion of the on-going installation of pipe rack super structure by TCC. Reinforcing bars 10mm for stirrups and ties do not have bar bending schedule and were delivered near pipe rack B foundation F8 covered by RFI # CI-529. Violation to Section 2.5.5.1 RT2S-3001-01. It also noted that the bars bent were without hooks on ends. The rebar are recommended to be quarantined. During Surveillance inspection at the Gas Furnace F-1150 Pedestals, it was found out that curing was inadequate as the surfaces of the pedestals were dry, without burlaps and plastic covering. Repeated violation of Section 9, RT2S-3001-01 (F1150 poured on 04 June 12). The Contractor has issued RFIs without at least 24 hours notification to the Company as standard procedure which violated schedule Q, attachment IV, section 1.1.3. On June 20, Wednesday afternoon, it was found out that Amana has prepared grounding cable installation for the eye shower in furnace pipe rack A (F6) without informing the Company for final inspection. The work done is not complying on the approved IFC drawing E-016103-AFOOZ-EL-EHZ- 001. There was a concrete pouring on site on that day and we cannot find the presence of Mr. Nabil Mr. Nabil, Amana Electrical QC Inspector was observed and found out the he has not been always on site and only been seen where there is an inspection. His job must be 100% dedicated to SADARA project only. This is in violation of Schedule Q Sec. 5.9/5.10. During surveillance, it was found out that bituminous coating was applied at the N-S pipe rack foundations F7 and F6 (GL AA-CA/53A-58A) without RFI issued for the coating application inspection which is a "hold point" for contractor and full inspection by Subcontractor QC. This is in violation of ITP and schedule Q, section 3.2. Note: Application was done during sandstorm. Test reports of concrete compressive strength tests are not available for KCC area pipe rack foundations. With the first concreting done on 5th May 2012, until today, no records of concrete compressive strength tests are available. As of May 27, 2012 nine foundations for the N-S Pipe rack were concreted. Violation to Schedule Q, section 3.2. Mr. Jere Asas, KCC QC Supervisor has not been seen on the site for the past one-week. As per information from KCC acting Site QC Manager, he is on emergency leave, however, there was no notification to Company of his leave. This is in violation of Schedule Q section 5.14 Mr. Roger Lopez, Daelim Batch Plant Inspector was observed and found not attending to his duties as Batch Plant Inspector. He has not attended inspection at the Qanbar Batch Plant at SATORP where the current concrete is supplied from for major concrete pouring since April 30, 2012, Violation to Schedule Q sections 5.9/5.10. During concrete pouring at KCC N-S pipe rack foundation F-5, there were delays in the delivery of concrete and long gaps in arrivals of truck mixers at site recorded as from 12:26 to 13:30 hours and from 14:34 to 16:02 hours. At the middle North to South section, the first layer has hardened due to more than 3-hour time elapsed before the next layer is poured. Cracks in the first layer have already appeared on the hardened concrete. The next layer poured was more than 150mm thick and initial vibrations were observed hitting the hardened concrete of first layer. Violation to section 5.4 of RT2S- 3001-01. During attendance of inspection at site for receiving of reinforcing bars, the QC inspectors from Contractor (Amana) Sub-contractor do not have a copy of the approved bar bending schedule for use as reference, despite reminders to ensure that this small be available during inspection for rebar receiving violation to schedule Q section 3.2. Page 3 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 30, 2014 DUE DATE Issued corrective action to Company Target Date S/N LBE NO. PID SUBCON/ CONTRACTOR VAF / PN LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason Company comment Approved Close LBE by Company STATUS CONTRACTOR'S CORRECTIVE ACTION PLAN LBE-DLM-MECH- 001 DAELIM VAF MECH Structural 03-Jul-12 06-Jul-12 17-Jul-12 6-Nov-12 Closed LBE-DLM-MECH- 002 DAELIM VAF MECH Structural 04-Jul-12 07-Jul-12 18-Jul-12 11-Feb-13 Closed LBE-KCC-CIVIL-042 KCC VAF CIVIL Civil 07-Jul-12 10-Jul-12 21-Jul-12 25-Jul-12 Closed LBE-DLM-MECH- 003 DAELIM PN MECH Structural 12-Jul-12 15-Jul-12 26-Jul-12 25-Jul-12 Closed LBE-KCC-MECH- 004 MR. NOOR KCC VAF MECH Structural 23-Jul-12 26-Jul-12 06-Aug-12 26-Jul-12 Closed LBE-AMA-CIVIL-043 AMA VAF CIVIL Civil 29-Jul-12 01-Aug-12 12-Aug-12 04-Sep-12 Closed LBE-KCC-CIVIL-044 KCC PN CIVIL Civil 29-Jul-12 01-Aug-12 12-Aug-12 08-Aug-12 Closed LBE-KCC-CIVIL-045 KCC PN CIVIL Civil 31-Jul-12 03-Aug-12 14-Aug-12 11-Oct-12 Closed LBE-DLM-MECH- 005 DAELIM VAF MECH Structural 31-Jul-12 03-Aug-12 14-Aug-12 6-Aug-12 Closed LBE-DLM-MECH- 006 DAELIM VAF MECH Structural 01-Aug-12 04-Aug-12 15-Aug-12 6-Aug-12 Closed LBE-KCC-MECH- 007 MR. NOOR KCC VAF MECH UG-RTR 05-Aug-12 08-Aug-12 19-Aug-12 15-Aug-12 Closed LBE-DLM-MECH- 008 DAELIM VAF MECH Structural 11-Aug-12 14-Aug-12 25-Aug-12 15-Aug-12 Closed LBE-KCC-CIVIL-046 KCC VAF CIVIL Civil 12-Aug-12 15-Aug-12 26-Aug-12 08-Aug-12 Closed LBE-KCC-MECH- 009 MR. NOOR KCC VAF MECH UG-RTR 13-Aug-12 16-Aug-12 27-Aug-12 23-Aug-12 Closed LBE-KCC-CIVIL-047 KCC VAF CIVIL Civil 20-Aug-12 23-Aug-12 03-Sep-12 04-Sep-12 Closed LBE-ARCC-MECH- 010 ARCC VAF MECH Structural 21-Aug-12 24-Aug-12 04-Sep-12 20-Sep-12 Closed LBE-KCC-MECH- 011 MR. NOOR KCC VAF MECH UG-RTR 30-Aug-12 02-Sep-12 13-Sep-12 3-Sep-12 Closed LBE-KCC-MECH- 012 MR. NOOR KCC VAF MECH UG-RTR 02-Sep-12 05-Sep-12 16-Sep-12 3-Sep-12 Closed LBE-AMA-ELECT- 006 AMA VAF ELECT Electrical 03-Sep-12 06-Sep-12 17-Sep-12 09-Sep-12 Closed LBE-DLM-MECH- 013 DAELIM PN MECH Structural 03-Sep-12 06-Sep-12 17-Sep-12 15-Sep-12 Closed LBE-KCC-MECH- 014 MR. NOOR KCC VAF MECH UG-RTR 03-Sep-12 06-Sep-12 17-Sep-12 13-Sep-12 Closed LBE-KCC-CIVIL-048 KCC VAF CIVIL Civil 04-Sep-12 07-Sep-12 18-Sep-12 11-Oct-12 Closed LBE-KCC-CIVIL-049 KCC VAF CIVIL Civil 05-Sep-12 08-Sep-12 19-Sep-12 17-Sep-12 Closed LBE-KCC-MECH- 015 MR. NOOR KCC VAF MECH UG-RTR 09-Sep-12 12-Sep-12 23-Sep-12 15-Sep-12 Closed PN: During surveillance inspection at 1530 hours, 28 July 2012, it was observed that the formworks for column including support for the beams of N-S Main Pipe rack F7 and F6 were anchored to (connected) to the scaffold system. It is recommended that the contractor to verify the stability/capability of the supports to the structures to be connected as per section 6.1.2 RT2S-3001-01. PN: It was noted during the inspection of N-S Main Pipe rack at 6/LBA/54A-58A CI & 61, the plates on top of beam do not have weep holes which is required as per the requirement of RT2S-3001-01 Para. 8.2.4. Ensure that all succeeding installation of these plates, weep holes are already provided. F-1160. Radiant Box section installed without receiving inspection. All other Radiant Box sections arranged for receiving inspection at the trailer prior to erection.' PN: Plan to install HT Mastic for Furnace Joints; Provide a Method Statement to detail the application that has to be strictly controlled. E.g. 1.Schedule a mock-up joint to ensure effectiveness. 2. Provide proper tools, spatulas, wet film gauge. 3. Record/document each joint completed, etc. RFI-MFCM-KCC-Mech-001. Embedded shear connectors were manually welded without qualified WPS and JCC, and components were hot dipped galvanized. Violation of IFC drawing specifically A554-E-103- DO:C2080 and section 2.30 FRT8S-65001. During surveillance inspection 28/07/12 at Column rebar fabrication near E-W pipe rack B, F1, it was observed that the column reinforcement are being fabricated in a Metal frame (scaffolds and 32mm rebar). The frame, however, was not provided with padding for the protection of the FBE Coating despite reminders. Violation of ACI 301 Section 3.1.2.2. Radiant Panel F-1250: Fire Damage. Evaluation in progress. 1 st step: Hardness checks complete 15 points; Report awaiting Company evaluation. 2 nd step: Metallurgy Replication, 3 rd STEP: party to be scheduled ASAP prior to re-locating to site. Radiant Panel F-1250: Pre-receiving inspection of unit shows numerous locations of weld discrepancies for example: incomplete welds, poor finish/worm holes, members missing welds, etc. Contactor to provide to Company a) Corrective Action Plan, b) Root Cause Analysis and c) Preventive Action Plan to improve and eliminate repeating same defects on all other sections released from Vendor. During surveillance inspection at KCC site, it was observed that bar bending on improvised bending assembly is being done by workers. The DH 10 bars (10mm) were being bent to produce the hooks on 16mm mandrel using metal pipe. The mandrel was not provided with pads to protect the coating of rebar from damage. Violation to ASTM-775 & ASTMC 615. CWR-093031-02 Joint No. FW-04. During the inspection of the lamination, there were air bubbles found which is unacceptable. Contractor to ensure that repair grind and eliminate that air bubbles area. During surveillance inspection at the Southside of E-W Pipe rack for Liquid Furnace near F2 & F3 Foundations, the Contractor stores the fabricated reinforcing bars for columns without sufficient protection and some portions directly to the ground. This violates ASTM-A-775 Para. 15.4 which states that Coated Steel reinforcing bars shall be stored off at the ground on protective cribbing. Also no padding on contact areas per Para. 15.1. During the inspection of FRP/RTR Line in Cooling Water and B2 area (Sub-station), some debris and sand were found inside of pipe during the bonding of lamination. As per standard, the Contractor has to ensure that the assembly of the installation of FRP/RTR should be cleaned prior to laying in the trench. During inspection of columns and beams at N-S Main Pipe rack at GL BA,57A-58A, CA 57A-58A (CI) & AA-CA/57A-58A (65), it was noticed that safe access to the working platforms were not provided. Some planks were not secured from movements. Several obstructions are hazardous to workers along the way. Contractor to ensure safe access is provided for safety of workers and inspection personnel while performing their jobs. F-1160 2nd section of Radiant Panel. Box on to structural member (east side) 2 locations were damaged (as marked on site) during transportation/installation time. Required rectification as per approved procedure and re-schedule final inspection/acceptance before start installation of 3rd section. Poor housekeeping in Cooling Tower main header beside of trench. Materials were released (FMIR NO. 0071) RFI0AKF-SS-0019 to site without prior to inspection/approval. Violated schedule "Q" attachment IV, sec. 2.31. ARCC has installed the Furnace Radiant Panel Module of F-1250 (Completed), F-1240 - three (3) sections. F-1170 - two (2) sections and F-1160 - one (1) section; all of which are without proper Method of installation as mentioned in the SADARA approved Procedure. It is clear violation of A554-E-103-QA- GEN-PRO-017, Para. 7.3.5 and 7.3.6. On August 30, 2012, KCC's FRP lamination crew has started the work at 3:00 PM until 4:00 PM which during this production time there was no QC Inspector. Said Inspector came only at 4:00 PM. A clear violation as per schedule "Q". Received test report for aggregates base coarse for structural backfill for upper C3 splitter & upper C3 splitter reboiler and lower C3 splitter & lower C3 splitter reboiler but there is no test report for CBR. Contractor to submit test report as a requirement for aggregate base coarse designation. It was noticed during surveillance at the N-S Main Pipe rack that the proper curing method was not implemented on the top of the girder at GL. AA-CA -56-57. This violates RT2S-300-01 regarding the use of Poly-Othylene sheets with burlap. The Contractor utilized burlap only and some portions were exposed and dry during the inspection. Subcontractor has to be advised to comply accordingly. It was observed that the material of FRP in cooling water area shelter inside without average boxes as SADRA document no A554-E-103-QA-GEN-PRO-008, and Para. 9.4.4 as SADRA Procedure. On Sept. 2, 2012, it was observed that the presence of Mr. Nabil (Amana Electrical QC Inspector) was again not on site. There is an urgent inspection to be raised on that day but his presence to perform his duties and responsibilities as a subcontractor's quality personnel is not performed. This is a repeated violation of Schedule "Q", sec. 5.9 and 5.10. PN: Violation of RT-5S-1821: All flanges face. Nozzle shall be protected from damage. Install Radiant Module Flanges nozzles to be protected immediately by contractor (F-1250, F-1240, F-1170 & F-1160). It was observed that the Contractor did not cover the end protection of FRP Pipes at the completion, installation and of the workday. All openings shall be sealed to protect from all foreign matter including dust, dirt, water, etc. as per G85-6015-04, Para 3.3.1 Page 4 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 30, 2014 DUE DATE Issued corrective action to Company Target Date S/N LBE NO. PID SUBCON/ CONTRACTOR VAF / PN LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason Company comment Approved Close LBE by Company STATUS CONTRACTOR'S CORRECTIVE ACTION PLAN LBE-AMA-ELECT- 007 AMA VAF ELECT Electrical 10-Sep-12 13-Sep-12 24-Sep-12 06-Oct-12 Closed LBE-KCC-CIVIL-050 KCC VAF CIVIL Civil 17-Sep-12 20-Sep-12 01-Oct-12 10-Oct-12 Closed LBE-AMA-MECH- 016 AMA VAF MECH Preservation 19-Sep-12 22-Sep-12 03-Oct-12 25-Sep-12 Closed LBE-AMA-MECH- 017 AMA VAF MECH Plumbing 19-Sep-12 22-Sep-12 03-Oct-12 16-Oct-12 Closed LBE-KCC-MECH- 018 MR. NOOR KCC VAF MECH UG-RTR 20-Sep-12 23-Sep-12 04-Oct-12 25-Sep-12 Closed LBE-KCC-CIVIL-051 KCC VAF CIVIL Civil 25-Sep-12 28-Sep-12 09-Oct-12 11-Oct-12 Closed LBE-AMA-CIVIL-052 AMA VAF CIVIL Civil 25-Sep-12 28-Sep-12 09-Oct-12 20-Oct-12 Closed LBE-KCC-ELECT- 009 KCC VAF ELECT Electrical 25-Sep-12 28-Sep-12 09-Oct-12 07-Nov-12 Closed LBE-AMA/KCC- CIVIL-053 AMA/KCC PN CIVIL Civil 26-Sep-12 29-Sep-12 10-Oct-12 20-Nov-12 Closed LBE-AMA/KCC- CIVIL-054 AMA/KCC PN CIVIL Civil 30-Sep-12 03-Oct-12 14-Oct-12 20-Nov-12 Closed LBE-AMA/KCC- CIVIL-055 AMA/KCC VAF CIVIL Civil 30-Sep-12 03-Oct-12 14-Oct-12 20-Nov-12 Closed LBE-KCC-CIVIL-056 KCC VAF CIVIL Civil 01-Oct-12 04-Oct-12 15-Oct-12 14-Oct-12 Closed LBE-AMA-ELECT- 008 AMA VAF ELECT Electrical 01-Oct-12 04-Oct-12 15-Oct-12 06-Oct-12 Closed LBE-ARCC-MECH- 019 ARCC VAF MECH Structural 06-Oct-12 09-Oct-12 20-Oct-12 7-Oct-12 Closed LBE-DLM-MECH- 020 DAELIM VAF MECH Structural 07-Oct-12 10-Oct-12 21-Oct-12 30-Apr-13 Closed LBE-KCC-CIVIL-057 KCC VAF CIVIL Civil 11-Oct-12 14-Oct-12 25-Oct-12 20-Nov-12 Closed LBE-AMA/KCC- CIVIL-058 AMA/KCC PN CIVIL Civil 11-Oct-12 14-Oct-12 25-Oct-12 20-Nov-12 Closed LBE-KCC-MECH- 021 MR. NOOR KCC VAF MECH UG-RTR 13-Oct-12 16-Oct-12 27-Oct-12 16-Oct-12 Closed LBE-KCC-MECH- 022 MR. NOOR KCC VAF MECH UG-RTR 14-Oct-12 17-Oct-12 28-Oct-12 16-Oct-12 Closed LBE-AMA/KCC- CIVIL-059 AMA/KCC VAF CIVIL Civil 20-Oct-12 23-Oct-12 03-Nov-12 20-Nov-12 Closed LBE-KCC-CIVIL-060 KCC VAF CIVIL Civil 20-Oct-12 23-Oct-12 03-Nov-12 18-Nov-12 Closed LBE-AMA/KCC- CIVIL-061 AMA/KCC VAF CIVIL Civil 21-Oct-12 24-Oct-12 04-Nov-12 12-Apr-12 Closed During site surveillance and inspection at 8:30 AM on September 10, 2012, again it was found out that Amana's QC Electrical Inspector (Mr. Nabil) has not been on site. His presence and responsibilities to perform his duties are again not performed. This is another repeated violation of Schedule "Q", sec. 5.9 and 5.10. It was observed in several occasions that during inspection of columns, the nelson stud of angular embedded items were not fully embedded in the inside of the column ties. There is a tendency that these angular embedment will be removed from the column during the installation f connectors once the member connection is subject to tension. Advice QC personnel to ensure full embedment of this type of embedded items. Observed that Contractor Amana has stored embedded material (galvanized) directly to the ground without proper wooden supports. Shall be taken special precautions to avoid damage any steel structure by wood support or alternative method. Violation of SADARA Doc. A554-E-103-QA-GEN-PRO-012. PN: Please verify it is not required to have the activity in the battery problems of substation G 1120 & G 1121 the painted with acid resistant paint. In the finish schedule only the walls are required to be painted with acid resistant paint. It was noticed during inspection at substation building G 1121, that the drain pipe for AHU G 1121 -AHU 001A and G 1121-AHU-001B are located away from the foundation there is a tendency that the pipe going to the drain from both units will be trip hazards and will be safety item punch list in the future MCC. please evaluate location of this drain in the future installation of substation G 1120 Ref. RFI # MCF-DLM-KCC-CI-861. Schedule Q for inspection at 1800H on Sept. 30, 2012 for Foundation of T-2210, T-2220 & C2 Splitter Equipment Structure is hereby rejected due to major finding. 28 25mm reinforcing bars (14 at bottom and 14 at top) were not installed, which require to remove forms and already installed reinforcing bars. Concrete placement as scheduled was postponed. It was noticed that the embedded plate with least dimension greater than 300 mm installed at the corner of beams & columns have no sufficient weep holes located at the E-W pipe rack. This violates the requirement of RT2S-3001-01, Para. 8.2.4. It was learned that Mr. Jayson Tabilisima electrical QC inspector has already on vacation leave without informing or giving notification to company at least 30days in advance on KCC annual Leave plan his vacation is on dec.10.2012 but the contractor did not advise the company and changes of personnel for qualify coverage .a violation of "SCHED-Q, Attachment Q-4,SEC.5.14" PN: Please verify the requirements of floor drain and eye wash in the battery rooms of substation G 1120 & G 1121. The drawing for both substations do not reflect that it should be provided. The reinforcing bars installation in substation G 1121 is almost complete and this requirement shall be resolved before concreting. Observed that Contractor Amana was done plumbing (drainage system sub-station no. G-1121) activities and done the gravity test without approved ITP, Plumbing Inspector and not approved drawing (IFC), not approved work procedure bonders/personnel without compaction and survey report, not approved gravity test procedure which have been doing for more than 50 joints for gravity test. During inspection of RFI no. MFC-DLM-KCC-UG-PIPING-002 and Hydro test package no. 1481HT017, the test manifold was not tested as per schedule "Q" requirements. The Contractor should comply with the standard as per document no. A554-E-103-QA-GEN-PRO-009, Para. 1 (General). With reference to Log Book Entry #050, it was again noted that some nelson stands were not properly embedded in the concrete columns during the inspection at N-S main pipe rack at several locations although subcontractors has repaired these deficiencies some locations way have been missed and this could lead to removal of embedment (angular plate) in the future during installation of connection please advise the subcontractor to properly rectify method of embedment installation It was observed that KCC FRP/GRP installers are grinding and shaving without JCC, which in violation to SADARA Standard (G8S-6010-00). During site visit at the Liquid furnace area below furnace F-1250 the contractor did not were the newly grouted foundation utilized as mock up for grouting this violates G25-3050-01 Para 3.4.1 which requires concrete to be required for minimum of 5 days. During Inspection after the repair of all leaks at sump fit #0636. some leak were still not repaired in two locations it was also observed that there are deposits of water just below the wall on the east side of the foundation/wall leak investigate the water if where is the origin since the leaks are required on the wall There is a possibility that there wafers leaks from the bottom slab. It was noticed that the contractor filled the two sump pits (S-0636 & S-0642) with water for leak test without submitting RFI. Several leaks were observed during the time the sump pits were already filled. Later on the leaks disappeared, no information was received from the contractor to know these leaks were required as per Document A554-E-103-PA-GEN-PRO-011 this stages of work shall be inspected. PN: It was noted that some girder/beams curing were not properly undertaken due to removal of polyethylene sheet are wrapped all over the members of the subject structure by using tape or tie wires to secure polyethylene sheets on the surface. It was observed that the Contractor did not cover the end protection of FRP Pipes at the completion, installation and of the workday. All openings shall be sealed to protect from all foreign matter including dust, dirt, water, etc. as per G85-6015-04, Para. 3.3.1 During the Surveillance of monitoring at site, it has been Found out that one PVC Conduit(4" D/A)of the communication duct bank at G-1121 S/STN area were damaged and this Damaged may cause the accumulation of water & dirt inside the conduit .This is violates design and standards G7C-0311-03 & G7C-0305-04. During the surveillance inspection at F-1250, it was observed that ARCC was installing Handrail at site which the material (Hand Rails) was not inspected by SADARA. Violation of Schedule "Q", attachment A, IV, section: 2.31. During Material Receiving Inspection we have found damage paint require touch up paint as per SMITP- M-001-01 item No. 4.12 touch up Coating & Painting Daelim: Contractor shall repair the damaged paint as per approved procedure and in accordance to the Touch-up Coating and Painting SMIC-H-2032. The Contractor does not submit test results for compressive strength of concrete this violates schedule Q attachment N Para 3.3 which states contractor must submit its test reports and review and submit the test reports of its sub contractors to the company representative as specified by the applicable standard. Page 5 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 30, 2014 DUE DATE Issued corrective action to Company Target Date S/N LBE NO. PID SUBCON/ CONTRACTOR VAF / PN LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason Company comment Approved Close LBE by Company STATUS CONTRACTOR'S CORRECTIVE ACTION PLAN LBE-AMA-CIVIL-062 AMA/KCC PN CIVIL Civil 21-Oct-12 24-Oct-12 04-Nov-12 02-Oct-13 Closed LBE-AMA/KCC- CIVIL-063 AMA/KCC VAF CIVIL Civil 30-Oct-12 02-Nov-12 13-Nov-12 28-Nov-12 Closed LBE-DLM-MECH- 023 DAELIM VAF MECH Structural 30-Oct-12 02-Nov-12 13-Nov-12 10-Nov-12 Closed LBE-ARCC-MECH- 024 ARCC VAF MECH Structural 30-Oct-12 02-Nov-12 13-Nov-12 8-Nov-12 Closed LBE-ARCC-MECH- 025 ARCC VAF MECH Structural 01-Nov-12 04-Nov-12 15-Nov-12 28-Apr-13 Closed LBE-KCC-CIVIL-064 KCC VAF CIVIL Civil 03-Nov-12 06-Nov-12 17-Nov-12 28-Nov-12 Closed LBE-CTS-ELECT- 010 CTS VAF ELECT Electrical 05-Nov-12 08-Nov-12 19-Nov-12 07-Nov-12 Closed LBE-ARCC-MECH- 026 ARCC VAF MECH Structural 05-Nov-12 08-Nov-12 19-Nov-12 10-Nov-12 Closed LBE-DLM-CIVIL-065 DAELIM VAF CIVIL Civil 06-Nov-12 09-Nov-12 20-Nov-12 28-Nov-12 Closed LBE-ARCC-MECH- 027 ARCC PN MECH Structural 11-Nov-12 14-Nov-12 25-Nov-12 11-Feb-13 Closed LBE-PSCL-MECH- 028 PSCL PN MECH Tank 11-Nov-12 14-Nov-12 25-Nov-12 11-Dec-12 Closed LBE-KCC-CIVIL-066 KCC VAF CIVIL Civil 17-Nov-12 20-Nov-12 01-Dec-12 28-Nov-12 Closed LBE-KCC-ELECT- 011 KCC VAF ELECT Electrical 17-Nov-12 20-Nov-12 01-Dec-12 28-Nov-12 Closed LBE-AMA-CIVIL-067 AMA VAF CIVIL Civil 20-Nov-12 23-Nov-12 04-Dec-12 02-Dec-12 Closed LBE-KCC-CIVIL-068 KCC VAF CIVIL Civil 20-Nov-12 23-Nov-12 04-Dec-12 28-Nov-12 Closed LBE-AMA-CIVIL-069 AMA VAF CIVIL Civil 21-Nov-12 24-Nov-12 05-Dec-12 Closed 04-Dec-12 Closed LBE-AMA-CIVIL-070 AMA VAF CIVIL Civil 25-Nov-12 28-Nov-12 09-Dec-12 12-Apr-12 Closed LBE-AMA/KCC- ELECT-012 AMA/KCC PN ELECT Electrical 26-Nov-12 29-Nov-12 10-Dec-12 01-Dec-12 Closed LBE-DLM-ELECT- 013 DAELIM PN ELECT Electrical 27-Nov-12 30-Nov-12 11-Dec-12 05-Dec-12 Closed LBE-DLM-MECH- 029 DAELIM PN MECH Structural 27-Nov-12 30-Nov-12 11-Dec-12 4-Dec-12 Closed On Nov 1.2012 as per requested RFI for Formworks, Embedment and rebar inspection prior to concrete placement it was found out that two(2)numbers Q25 mm re Enforcing bars were missing located at the bottom of girder type G5 at GC AB-37/38.This missing reinforcing bars could effect the structure stability of the girder. Contractor shall effort more effort in their inspective process and reply to this log book entry shall include preventive action this a respected violence. Regarding The Inspection today(Nov.5.2012)RFI # CTS-EL-001,The Representative from corrpro Arabia Cathodic production co was not able to attend the visual inspection for the HDPE Secondary containment liner @ Spent caustic storage tank,V-0500A due to sickness and not sending anybody for the substitute a violation of "SCHED-Q,ATTACH.IV.SEC.3.4/3.7 During Material inspection at ARCC laydown yard, it was found out that the Contractor has started Hot dipped galvanized structural members (Furnace) were kept on contaminated steel support and rest of the members were laid on the ground. ARCC has to store galvanized material free from dirt and other foreign materials. A violation of RT-2S-2120-01. F-1130 at Radiant Box section was installed without Material Receiving Inspection. Repeated violation on previous logbook entry no. 005. During surveillance inspection at F-1130 area, it was found out that ARCC welder (W-AR-2045) was welding on plate washer without baked electrode. It is clear violation to RT-8-S-65000-1, section 5.3. During Material Receiving Inspection on Furnace Radiant Box (F-1110), some defects were observed. *Worm hole porosity on weld at difference area (as marked on site) (RFI for 1120). *Deep grinding on (Material lose) Main Structure (1 beam). *Base column lashed with chain without proper protection. * Coating damaged during handling of Transportation time. Subcontractor: Hauling group of ARCC provided softeners (used cut to size nylon) to prevent scratches on steel structures, photos attached. ARCC QC Conducted orientation on material handling & preservation to the person involves in hauling & warehousing, attached attendance sheet. Final inspection shall be conducted prior to final acceptance. RFI shall be raised upon released from welding repair when it is completed. PN: Please advise all sub contractors that prior to removed of water sump pits being tested for leak test or similar structures approved by Sadara quality group shall be obtained and down enter as required by ITP, removal of water without documentation shall be considered retest and another RFI shall be submitted. Please be informed that a logbook entry was made in OSAIMI LAB, MFC site regarding the following in accordance with ASTMC 39M-12 Para 7.3 all test specimens for a given test age shall be broken within the permissible time tolerance Prescribed as follows.7 days -6h or 3.6%,28 days -20h or 3%..the following as cylinder sample were not broken in accordance with the above requirement. Sample #268 to 276-Amana, sample # 185-KCC,The above samples were note Crushed on OCT 27 and 28 for 28-day compressor strength test requirement for 7 (Seven) days crushing of Samples .Sample #303-For Amana, Sample # 229 to 232-For KCC. Please advise Third Party of the above Violation. Rejected RFI No. MFC-DLM-KCC-CI-1224, as per RFI requested, at E-W C3 Splitter Pipe Rack @ GL- AD-CD/22D-29D the following comments were noted during inspection. 1. The column ties located at the Girder side were not tied on all columns. 2. Some of the angle bolts nelson studs were not fully embedded on the concrete and supported by reinforcing bars (repeated violation). 3. Toe boards on some plat bars were not installed. During monitoring of activities at spent caustic tank area, the contractor mixes the sand cement mix ratio of 1:33 with wet sand from stock piles which had been wet during the rain. This is a violation of the requirement shown on DWG. # A554-103-CV-DWG-C30-295 Note 9 (d) which require sand to have not more than 2% free-moisture content by weight of dry soil. It was also observed that the workers are directly mixing the sand-cement-mix without the proper proportion as mentioned in the approved procedure. Please investigate the sand-cement mixture at Tank (Spent Caustic Tanks, Process Holding Tank and Pad Water Tank) due to rain which maybe had contaminated with water yesterday. These tanks are covered with polyethylene sheets but water may sip at joints since it had been raining heavily. During the leak testing of sump 0635, it was noticed that the portion at the bottom of the north side of sump where the transition of slab to sump have been damped. This location shall be dry and Contractor shall investigate the damped area and shall be repaired prior to final acceptance. All the three sides of the pit have been inspected and all leaks were repaired and accepted. It has been noted that the subcontractor (KCC) continued with their Electrical activities without Electrical QC Inspector and continuously concrete pouring on various locations without RFI and electrical clearance from electrical QC dept. in spite of receiving two (2) NCR from the Contractor (DAELIM), again, continued their violation for the third time. A repeated violation of "Schedule Q, attachment Q-1, sec. 1.6". As per RT2S-3050-01 Sec. 3.7.5. water for grouting shall be checked for chloride and sulfate weekly. Subcontractor should be advised to submit report as specified in the standard. As per the requirement of RT2S-3001-01 Rev. 4, Table 7, Total chlorides per sulfates per BS 1881, Part 124 Method 10.2 and total method 10.3 shall be performed every month for the first 3 months and every 3 months thereafter. Contractor to advise the subcontractor/batching plant to comply with the requirement and submit report. PN: Material Inspection (Receiving) of Transition Duct Lower part (TM-1120, to TM-1170 Gaff) and TM- 1210, To 1250 Gaff) shown several locations weld discrepancies on duct, example: Crack, bend, incomplete weld, worm holes, members cracked, etc. Vendor to provide: *Corrective action plan *Root cause analysis & preventive action *Extension of damage report with repair procedure for rectification. PN: During witness inspection of material and qualification of Coating & Blasting personnel at Petro Steel Facility, the following were observed: *Blasting Equip. And associated attachment were not adequately earthed to avoid electrical static discharge. *Dead-Man shot-off coated were arrested with to prevent the control system. *Air hose were damaged and broken. *Missing calibrated pressure R/valves and pressure gauges on Air receiver Tank. * The Contractor to advise Petro Steel to take necessary safety precaution and project requirement as per Sadara procedure RT-16-0101-xy and Schedule "Q" requirements. PN: Contractor shall perform continuity testing (point-to-point test) between installed main grounding system to all grounding riser prior to the final backfilling and concreting to confirm that there are no damages in the grounding cable during backfilling and consequently, to avoid re-work in the future. PN: During routine site visit, it was found out that there are 18 MV motors arrived at DAELIM warehouse, In connection with this, Contractor shall provide preservation plan and shall preserve the motors as per manufacturer's recommendation, i.e. energization of the motors space heater to prevent accumulation of moisture inside the motor. PN: During Inspection at Furnace Radiant Box and Open Structural for Transition and Convention Module, it was found out that Elevation variance in all column J+ was above the Tolerance allowable limit. *Daelim Engineering Team has to verify the subject issue and submit the rectification Method to Sadara for review and approval. Page 6 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 30, 2014 DUE DATE Issued corrective action to Company Target Date S/N LBE NO. PID SUBCON/ CONTRACTOR VAF / PN LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason Company comment Approved Close LBE by Company STATUS CONTRACTOR'S CORRECTIVE ACTION PLAN LBE-DLM-MECH- 030 DAELIM PN MECH Mechanical 28-Nov-12 01-Dec-12 12-Dec-12 11-Dec-12 Closed LBE-KCC-MECH- 031 MR. NOOR KCC VAF MECH UG-RTR 28-Nov-12 01-Dec-12 12-Dec-12 3-Dec-12 Closed LBE-KCC-MECH- 032 MR. NOOR KCC VAF MECH UG-RTR 29-Nov-12 02-Dec-12 13-Dec-12 3-Dec-12 Closed LBE-KCC-MECH- 033 MR. NOOR KCC VAF MECH UG-RTR 29-Nov-12 02-Dec-12 13-Dec-12 4-Dec-12 Closed LBE-DLM-CIVIL-071 DAELIM PN CIVIL Civil 04-Dec-12 07-Dec-12 18-Dec-12 22-Jan-13 Closed LBE-DLM-CIVIL-072 DAELIM PN CIVIL Civil 04-Dec-12 07-Dec-12 18-Dec-12 22-Jan-13 Closed LBE-DLM-CIVIL-073 DAELIM PN CIVIL Civil 05-Dec-12 08-Dec-12 19-Dec-12 12-Dec-02 Closed LBE-DLM-CIVIL-074 MR. GERALD DAELIM PN CIVIL Civil 05-Dec-12 08-Dec-12 19-Dec-12 15-Sep-13 Closed LBE-DLM-ELECT- 014 DAELIM VAF ELECT Electrical 05-Dec-12 08-Dec-12 19-Dec-12 22-Jan-13 Closed LBE-DLM-MECH- 034 DAELIM PN MECH Material 05-Dec-12 08-Dec-12 19-Dec-12 6-Jun-13 Closed LBE-PSCL-MECH- 035 PSCL PN MECH Tank 05-Dec-12 08-Dec-12 19-Dec-12 27-Jul-13 Closed LBE-DLM-MECH- 036 DAELIM VAF MECH Mechanical 05-Dec-12 08-Dec-12 19-Dec-12 25-Apr-13 Closed LBE-DLM-MECH- 037 DAELIM VAF MECH Structural 08-Dec-12 11-Dec-12 22-Dec-12 9-Dec-12 Closed LBE-DLM-MECH- 038 DAELIM VAF MECH Quality Records 08-Dec-12 11-Dec-12 22-Dec-12 9-Dec-12 Closed LBE-DLM-MECH- 039 DAELIM VAF MECH Structural 10-Dec-12 13-Dec-12 24-Dec-12 11-Dec-12 Closed LBE-ARCC-MECH- 040 ARCC VAF MECH Structural 11-Dec-12 14-Dec-12 25-Dec-12 25-Apr-13 Closed LBE-KCC-MECH- 041 MR. NOOR KCC VAF MECH UG-RTR 11-Dec-12 14-Dec-12 25-Dec-12 16-Dec-12 Closed LBE-AMA-CIVIL-075 AMA VAF CIVIL Civil 13-Dec-12 16-Dec-12 27-Dec-12 31-Dec-12 Closed LBE-AMA-CIVIL-076 MR. JERRY AMA VAF CIVIL Civil 13-Dec-12 16-Dec-12 27-Dec-12 02-Oct-13 Closed During the surveillance inspection, KCC RTR/FRP crown did not provide end protection of FRP Pipe in cooling water area and some areas at package no. 14, 04, etc. Violation as per standard G8S-6010-00 & G8S-6015-04 and as per Procedure Para. No. 3.3.1. PN: It was observed that the cold season has started and the temperature has gone down this morning at 8'C. Contractor/Subcontractor is informed that the Batch Plant will be reduced the amount of admixtures to compensate the retardation time of concrete. Contractor/Subcontractor to ensure that the reduced amount of admixture is reflected in the concrete delivery ticket and water is not increased or added and the water cement ratio is not affected. Batch Plant Inspector has to be aware of the requirement. PN: It was observed that some testing requirements for concrete were not submitted since they are not included in the ITP and/or checklist. These requirements mentioned in RT2S-3001-01 such as Rebar mechanical testing Para 2.5.6.1 Compressive strength test, table 7 total chlorides table 7, total sulfates table 7, reactive silica table 6 shall be included in the ITP/Checklist to ensure requirements of specification are complied. Revise ITP and checklist for SMIC-Q-1001 and SMITP-Q-001-01 to reflect said requirements. PN: Daelim Painting and Refractory Teams to verify the Coating requirements (appropriate) prior to apply Refractory on Transition Module (Lower part). Coating QA/QC Inspector shall make action to prevent inorganic zinc from coming in contact with stainless steel anchor. It was observed that KCC did not follow the SADARA standard G85-6015-04 Para 3.1.4 & procedure handling and storage. Daelim/KCC, FRP/Pipes fittings are placed through directly on the ground in various locations: package #04, 15, 19 and near the cooling water line. Contractor/subcontractor should not store FRP Pipe and fittings directly on the ground and avoid rough handling of FRP Pipes and During inspection, it was observed that KCC's certified laminator Mr. Sher Khan, with RTR ID No.011, has allowed his helpers to do lamination job without JCC in his presence and keeps an eye on foxiness, keep under surveillance knowing that his supervisor is also on the site. This is a standard violation as per G85-6010-00 and G85-6115-01 Para 1.3.2, a repeated violation and as per ISO 14692-4, annex D. During Material Receiving Inspection of Fabricated steel structural members manufactured by Yoong Hwa at Daelim Laydown Yard, some were observed: * Material were damaged due to improper bonding; *Galvanized surface were scratched, peeled, etc. Daelim, Material receiving team has to take extra care on handling and storing of galvanized material. Violation of RT-2S-2120-01) Sadara procedure. Weld discrepancies: On structural member, Daelim QA/QC Team has to prepare necessary rectification method to control weld defects prior to start installation on site. During Material Receiving inspection of storage tank (V.0500A/B) Annular Plate at site: It was observed that Petrol steel had failed to submit proper document as per material receiving procedure and also violated the Proactive Notification requirement: (PR:Entex-35). Daelim QA/QC Team to verify all required documents if they are available prior to offer RFI to SQI. TCC started the erection of Pipe Rack Column at N-S Pipe Rack area without Structural QC Inspector. The Mech. Supervisor is monitoring the activity at site. TCC should comply with Sadara Quality requirement as per schedule "Q" and Daelim to advise KCC to follow quality requirement as per schedule "Q" and specifications. PN: Combustion Air Duct (Vendor Metaphil) observed that following defects on subject Material Receiving Inspection: 1 Coated externals showing poor application, excess thickness and scratched surface. 2. Air Control System (Dumper) not working properly due to improper alignment. 3. Uncoated internal areas exhibiting serious oxidization. Daelim QA/QC Team to rectify all damaged coating. Alignment of bumpers and working properly prior to delivery to site. Daelim should take Material Clearance prior to install duct on site. Daelim: As per request of SQIT/SPMT greasing of damper mechanism was performed including those with damage are segregated with corresponding marks/tags. Further mechanism "open" & "close "marking started stencil printing as per proper location of damper opening & closing. Spray paint was used for stencil marking. On-going. PN: During the Focus assessment on Petrol Steel Fab. Shop in regards to 7 tanks will be erected at site, the following discrepancies were recorded: 1. No release not "ARN" from steel plate and flanges manufacturer for level "2" Inspection material were presented. 2. The ITP utilized did not have any Company involvement. Daelim to ensure all documentations are complete and contact the QR to ensure/confirm the proper involvement of the Company in all the P.O.'s placed by Petrol Steel. Subcon: 1.) IRN's are prepared and attached with the materials that are shipped from shop to site. 2.) The ITP has been revised fro Company involvement and also it has been approved. Contractor Inspector is in charge for the activities in the shop. PSCL confirms that all the documents for the materials that are being released to site will be required. During witness inspection for surface preparation prior to application on the Radiant Box internal floor (bottom) F-1250 were found that the Mechanical cleaned area even exceeded (100 sq.) as allowable acceptance limit as per Sadara Painting procedure: G-163-0101-54 Daelim: The issue was addressed to Mr. Gerald F. and replied that the affected area is just small & impractical to do blasting, in which he didn't find any major issue with power brushing to remove the rust, mill scale & any grease. Just that it has to be ensured after repair is completed, the area must be cleaned and bitumastic coating must be applied. PN: During surveillance inspection @ cooling tower basin @ GL: 1D-6D, some prepared area for lean concrete applications were not conforming to 50mm thickness requirement as shown in the IFC drawing. The actual thickness is ranging only from 30mm up to 35mm. Contractor/Subcontractor is advised to rectify the deficiencies prior to final inspection. PN: It was observed that RFI'S execution or implementation of Contractor/Subcontractor, some are already been inspected and the structure had been poured. But, more than one (1) week time slot, the said RFI's with attachments are not yet submitted for signature & comment. Contractor is therefore advised to submit RFI's on time for proper documentation. Subcon: RFI's are now prepared and given to inspectors to be available on site during inspection with SQIT. Despite of the Proactive Notification (LBE-E-013) done last November 27, 2012, the Contractor is still not energizing the Space Heater of the 18 MV Motors arrived at Daelim Warehouse last Nov. 25, 2012, which is a violation as per RT7D-0665-00, section 13.1.2. It was observed that the TPER located at the southern most portion of the Spent Caustic Tank Pipe rack was severely damaged. Contractor/subcontractor to provide method of statement and include sketch how to repair the damaged TPER and the affected FND to maintain the required sealant on each joint. Subcon: Access road, repair will proceed after cleared by Contractor. M/S was submitted for repair of TPER's & it was decided in quality meeting (MOM-54) that each Subcon required to protect TPER with steel plate. During surveillance inspection at ARCC yard for inspecting Transition Duct (Lower), it was observed that GIWI (Blasting painting contractor) has started blasting activities on transition duct without informing the QA/QC Team of Daelim and Sadara. Also found the following: *Coating inspection/Crew Supervisor was not available at site. *Wet garnet was using at site.*Failed to conduct climatic condition, *Failed to conduct moisture % at air supply (battery test). Daelim QA/QC Team has to closely monitor KCC if activities are meeting the Sadara specification and Schedule. Violation of Schedule "Q" and RT-168-01 and 54. Subcon: Coating inspector & crew supervisor (ARCC) are warned to be present on site always. Wet garnet was replaced with new garnet QA/QC personnel is advised to strictly monitor and keep log of all ambient readings and conduct readings and conduct blotter test during cash shift. During inspection, it was observed that subcontractors KCC & PTS workers are doing bonding & lamination of FRP without JCC: Drawing no. Five Water Line:FW:071004-02, Joint No. 46, Drawing No. Fire Water Line: FW:017111-01, Joint: 22,23,24; and they are using contaminated and rusted material of FRP lamination with woven roving and boal tape. This is a standard violation as per G8S-6115-01 & G8S-6010-00 & ISO 14692-04 Annex-D. The Contractor/Subcontractor did not install the schedule 80, 40 mm dia. Pipe for leak detection as shown on drawing # A554-E-103-CV-DWG-C-30-295, rev. 3 and other drawings for Spent Caustic Tank storage tanks V-0500 A/B, Pad Water Tank and Process Holding tank. This requirement was discussed two weeks ago with Contractor QC Supervisor and Amana QC Supervisor. Contractor/Subcontractor is advised to comply with this requirement prior to install tanks. Subcontractor: Subcontractor Already Installed The Schedule 80 Pipes in all the tanks in compliance with IFC Drawings. Page 7 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 30, 2014 DUE DATE Issued corrective action to Company Target Date S/N LBE NO. PID SUBCON/ CONTRACTOR VAF / PN LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason Company comment Approved Close LBE by Company STATUS CONTRACTOR'S CORRECTIVE ACTION PLAN LBE-PSCL-MECH- 042 PSCL VAF MECH Tank 13-Dec-12 16-Dec-12 27-Dec-12 20-Apr-13 Closed LBE-DLM-MECH- 043 DAELIM VAF MECH Structural 13-Dec-12 16-Dec-12 27-Dec-12 24-Apr-13 Closed LBE-AMA-CIVIL-077 AMA VAF CIVIL Quality Management 16-Dec-12 19-Dec-12 30-Dec-12 01-Jan-13 Closed LBE-SEN-ELECT- 015 SENDAN VAF ELECT Electrical 17-Dec-12 20-Dec-12 31-Dec-12 23-Jan-13 Closed LBE-DLM-ELECT- 016 DAELIM VAF ELECT Electrical 23-Dec-12 26-Dec-12 06-Jan-13 22-Jan-13 Closed LBE-ARCC-MECH- 044 ARCC VAF MECH Structural 23-Dec-12 26-Dec-12 06-Jan-13 5-Jan-13 Closed LBE-ASYAD-INST- 017 MR. SHABIRUL ASYAD VAF INST Instrumentation 25-Dec-12 28-Dec-12 08-Jan-13 22-Jan-13 Closed LBE-ARCC-MECH- 045 ARCC VAF MECH Structural 25-Dec-12 28-Dec-12 08-Jan-13 28-Apr-13 Closed LBE-DLM-MECH- 046 DAELIM VAF MECH Mechanical 26-Dec-12 29-Dec-12 09-Jan-13 12-Jan-13 Closed LBE-AMA-CIVIL-078 AMA VAF CIVIL Civil 27-Dec-12 30-Dec-12 10-Jan-13 08-Jan-13 Closed LBE-DLM-MECH- 047 DAELIM VAF MECH Preservation 29-Dec-12 01-Jan-13 12-Jan-13 2-Jan-13 Closed LBE-AMA-CIVIL-079 AMA VAF CIVIL Civil 01-Jan-13 04-Jan-13 15-Jan-13 07-Jan-13 Closed LBE-AMA-CIVIL-080 AMA PN CIVIL Civil 02-Jan-13 05-Jan-13 16-Jan-13 28-Jan-13 Closed LBE-KCC-CIVIL-081 KCC PN CIVIL Civil 02-Jan-13 05-Jan-13 16-Jan-13 21-Jan-13 Closed LBE-DLM-ELECT- 018 DAELIM PN ELECT Electrical 03-Jan-13 06-Jan-13 17-Jan-13 08-Jan-13 Closed LBE-KCC-ELECT- 019 KCC VAF ELECT Electrical 05-Jan-13 08-Jan-13 19-Jan-13 08-Jan-13 Closed LBE-ARCC-MECH- 048 ARCC VAF MECH Quality Management 05-Jan-13 08-Jan-13 19-Jan-13 26-Jan-13 Closed LBE-KCC-ELECT- 020 KCC VAF ELECT Electrical 06-Jan-13 09-Jan-13 20-Jan-13 10-Jan-13 Closed LBE-KCC-ELECT- 021 KCC VAF ELECT Electrical 06-Jan-13 09-Jan-13 20-Jan-13 12-Mar-13 Closed LBE-ARCC-MECH- 049 ARCC VAF MECH Structural 06-Jan-13 09-Jan-13 20-Jan-13 21-Apr-13 Closed It was observed that the QC Manager of Amana has not been available for the past several days. During the quality meeting he was also not present. It was also heard from Contractor's QC Personnel that the QC Manager has left the project. Contractor to verify the authenticity of the report. As per requirement of Schedule Q, Para. 5.14 regarding quality personnel charges. Subcontractor (SENDAN) for Electrical works is still not submitting their quality documents, i.e. )PQP, ITP, Method Statement, CV's of QC personnel) to the Company for review and approval more than 30 days from now since the kick-off meeting in Nov. 4, 2012. A violation of Schedule "Q", attach. Q-2, para.3. Focus assessment was conducted for the Preservation of 18 MV motors at Daelim Warehouse and found out that the Contractor has not taken any action regarding the Energization of Space Heaters for these MV motors despite of the Pro-active Notification and standard Violation issued by the Company. During surveillance inspection at Field Erected Tank area, Petrol Steel were installing the Annular and Bottom plate at site and observed the following violations: *Welders were tacking alignment clip on annular/Bottom plate without JCC for conducting the activities at site. Violation of Sched. "Q" and SADARA Spec:RT2S-600-1. * The electrode used by welder was not dried and not properly conditioned for use at job. *Electrode/Filler Material was not inspected and approved as per Sch. "Q" requirement and approved welding consumable handling flow chart. * Petrol Steel QC, Welding and Mech Inspectors have to take more care on the aforementioned violations and shall meet the Company Quality requirements. The Subcontractor GIWI had been started structural erection activities at site prior to obtaining approval of quality plan and quality requirements as per Sadara Specs. It is clear violation of schedule "Q", Para. 1.6 and Para. 3. During surveillance inspection at base slab cooling tower basin (Part C), it has been observed that curing of newly casted base slab, only polyethylene sheet & water without burlap or hessian. This is a violation to RT2S-300-01 (Rev.3) Para. 9.1.4. Contractor to advise Amana to comply. PN: During surveillance inspection at cooling tower basin (base slab) part-A & part C, it has been observed that south portion of (part A & North portion of part C) they are using as a stored area for shutter and form works materials, wherein can cause or resulted to damage for the newly poured structure. Said structure has been casted last (29 & 31 Dec. '12) respectively. Contractor/subcontractor to ensure that concretes are sufficient enough to carry the load of shuttering materials. Subcontractor must be advised to make immediate action on the issue. PN: It was noticed that the backfilling of vertical car pump (P2571) was undertaken without consideration of removal of support and backfilling of the adjacent ground. There is a tendency that the ground backfilled will collapse when the support is removed and it not removed the support will be very hard to remove. Contractor to advise subcontractor to reconsider that condition while the adjacent ground is still not backfilled. Perforated plates of combustion air duct are exposed to the open atmosphere & rusted in Daelim yard. Duct frame & duct inlet openings are not properly closed in Daelim yard. Some metallic materials are directly in contact with the ground like galvanized studs & structural items, etc. in the Daelim yard. Contractor shall submit method statement for rust cleaning & offer for the SADARA inspection, necessary actions required ASAP. During surveillance inspection at substation G1121, it was observed that partial delivery of concrete masonry unit (CMU) at north side of substation G1121, were not properly stored & rest on the ground without proper protection. This is a violation to G25-4300-01, Para. 3.1.1. Contractor to advise the subcontractor to comply the violation. During the Material Receiving Inspection for Radiant Coil-F-1170, following violations of Material Preservation: Stainless steel alloy on radiant coil were directly stored on row woods. There is a chance to collect dew point condensation on subject material. There is a chance to contact with soil, potential corrosive blowing sand and etc. Violation of Material & Equipment Protection & Preservation Plan: RTG- OCS, Para. 2.15. During surveillance Inspection at Furnace area, it was observed that ARCC has used Fastener (High Strength Bolt) by different manufacturer which were not informed or conduct Material Receiving Inspection. Repeated violation of schedule "Q" and RT25-5210. Daelim QA/QC Team has to investigate the discrepancy occurred at site; Take necessary rectification action on subject matter. Subcontractor (ASYAD) for Instrumentation works is still not submitting their Quality Documents such as PQP, ITP, Method Statement, CV's of QC Personnel to Company for review & approval. It has been more than 30 days since the kick-off meeting was held in Aug. 5, 2012 and until now the Company has not received any of its QC documents which is violation of Schedule "Q", attachment Q-2, Para. 3. It was observed that ARCC has installed the Transition Duct (Lower Part) at F-1250 after rectification of column Elevation variance. The activities were conducted without final inspection of plumbness alignment & elevation which is violation of Repair Procedure inspection sequence: Document # A554-E- 103-MECH-GE-008, Para. 5.3. It was observed that the grounding Pad installed in deethanizer structure (D-2055) and D-2152 off gas compensation suction are not complying with a minimum distance of 150mm above the ground level. A violation with IFC DWG. # A554-E-103-EL-DWG-EHA-499, sht. no. 34, rev. 2. During routine visit, it was found out that the grounding cable and grounding rod at the east side of C2 splitter equipment structure area was damaged during excavation as per schedule Q, attachment IV, sec. 3.2. During the surveillance inspection at Furnaces area: F-1170, it was observed that ARCC was installing Radiant coil on F-1170. The crew members were handling the Radiant coil with improper method and carelessly done. Company & Daelim had conducted a workshop regarding handling and preservation on SS & SS Alloy material at ARCC yard. ARCC team to re-evaluate the material preservation implementation plan according to site condition. Violation of material preservation procedure: RT-6-ICS. PN: Contractor shall verify the installation of grounding cable from power transformers to the grounding grid as per the requirement of G7-104-00 sec. 6.5.2. As of now, there is only one connection of grounding cable to the local ground grid. During site surveillance on Jan. 3, it was found out that one PVC stub-up in cold box structure foundation was damaged, and also not complying as per project specifications and standards. A violation of equipment specs. 67D-0311-03 Para. 2.2.3/4.4.1/4.4.2. During surveillance inspection, it was observed that Contractor's subcontractor (ARCC) has started the refractory works without its QA/QC Refractory Inspector. A standard violation as per schedule "Q". Page 8 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 30, 2014 DUE DATE Issued corrective action to Company Target Date S/N LBE NO. PID SUBCON/ CONTRACTOR VAF / PN LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason Company comment Approved Close LBE by Company STATUS CONTRACTOR'S CORRECTIVE ACTION PLAN LBE-AMA-ELECT- 022 AMA VAF ELECT Electrical 09-Jan-13 12-Jan-13 23-Jan-13 14-Jan-13 Closed LBE-DLM-MECH- 051 DAELIM VAF MECH Structural 09-Jan-13 12-Jan-13 23-Jan-13 30-Apr-13 Closed LBE-ARCC-MECH- 068 ARCC PN MECH Refractory 09-Jan-13 12-Jan-13 23-Jan-13 20-Apr-13 Closed LBE-KCC-CIVIL-082 KCC VAF CIVIL Civil 10-Jan-13 13-Jan-13 24-Jan-13 21-Jan-13 Closed LBE-AMA-CIVIL-083 AMA VAF CIVIL Civil 10-Jan-13 13-Jan-13 24-Jan-13 08-Jul-13 Closed LBE-PSCL-MECH- 052 PSCL PN MECH Tank 10-Jan-13 13-Jan-13 24-Jan-13 17-Jan-13 Closed LBE-AMA-CIVIL-084 AMA PN CIVIL Civil 12-Jan-13 15-Jan-13 26-Jan-13 26-Mar-13 Closed LBE-AMA-CIVIL-085 AMA VAF CIVIL Civil 13-Jan-13 16-Jan-13 27-Jan-13 20-Jan-13 Closed LBE-ARCC-MECH- 050 ARCC PN MECH Structural 13-Jan-13 16-Jan-13 27-Jan-13 21-Apr-13 Closed LBE-ARCC-MECH- 053 ARCC VAF MECH Material 14-Jan-13 17-Jan-13 28-Jan-13 11-Feb-13 Closed LBE-PSCL-MECH- 054 PSCL PN MECH Tank 15-Jan-13 18-Jan-13 29-Jan-13 17-Jan-13 Closed LBE-DLM-MECH- 055 DAELIM PN MECH Refractory 16-Jan-13 19-Jan-13 30-Jan-13 10-Jun-13 Closed LBE-AMA-CIVIL-086 AMA VAF CIVIL Civil 19-Jan-13 22-Jan-13 02-Feb-13 05-Feb-13 Closed LBE-AMA-CIVIL-087 AMA PN CIVIL Civil 20-Jan-13 23-Jan-13 03-Feb-13 28-Jan-13 Closed LBE-DLM-CIVIL-088 DAELIM VAF CIVIL Civil 21-Jan-13 24-Jan-13 04-Feb-13 Closed 29-Apr-13 Closed LBE-KCC-CIVIL-089 KCC VAF CIVIL Civil 21-Jan-13 24-Jan-13 04-Feb-13 Closed 18-Feb-13 Closed LBE-AMA-ELECT- 023 AMA VAF ELECT Electrical 21-Jan-13 24-Jan-13 04-Feb-13 27-Feb-13 Closed It was observed that the grounding cable installed in substation G-1120 transformer yard for grounding bus bar is 70 mm instead of 120mm as per the IFC drawing. A violation in IFC DWG. No. E-016103-AA- 00Z-EL-EHZ-001 Rev. 4. During the inspection for Bolt Tightening at open structure at F-1220, following violations were observed: The Lower Transition Duct was installed at position without conducting Final Bolt tightening verification by Daelim & Company (SADARA), violation of procedure: A554-E-QA-GEN-PRO-012 sec. 7.3. The Installed open structure members Piece Marks are not matching as per IFC drawing of F-1220. Violation to Sched. "Q" , attachment IV, sec. 4.2 & RT-25-5120, Para. 4.1.3 & 4.1.4. Contractor to verify the discrepancy and forward the remedy action to SADARA. PN: It is observed at site F-1140 Gas Furnace that the left portions of temporary angles after cutting are still not yet grinded up to smooth surface in the Lower Transition Duct. Contractor is advised to grind all of these left portions of angles up to smooth surface of the Trans. Duct as per RT SAES-N-110 Para. No. 8.1, A554-T-103-MB5-827, Para. No. 7.1.4. During Material Receiving inspection of welding consumable at ARCC yard, the following Filler materials were rejected; The subject brand Filler Materials are not meeting the requirement of SADARA specs: RT:8S-6500-3., Sect: 3.3. A Flag Tag indication as per AWS0-ASME Specs shall be affixed to both ends of all SS and All nickel-chromium based and titanium alloy cut-length filler material. The Materials brand & classifications are *ER-309L.2.4 mm BD-CN-231-21G24 *ER-308L.2.4mm BD-EAS2IG2,4 (BOHLER Brand). PN: During inspection of the tank, it is observed that jigs and fixtures for temporary attachments are not properly handled by Petrol Steel. A. Storage at tank bottom shall not be in direct contact to the bottom plates to avoid mechanical damages. B. Wedges and channels surfaces must be smooth grounded t avoid mechanical damages on the tank bottom and shell plates. C. Direct hammering on the plates must be averted to avoid the mechanical damages. PN: During surveillance inspection, it was found out that air set mortar dry 50 lbs. bags for refractory application stored in the Daelim laydown yard (warehouse) inside have been expired on Dec. 4, 2012. As per SADARA Standard, expired materials must be shifted to the quarantine area to ensure that it will not be used,RTSAES-N-110, Point 7.3. PN: During Surveillance inspection at cooling tower basin (RC-Wall), it has been observed that presence of Laitance for the rebar @ RC-Walls & some portion of water stopper need to be aligned and proper cleaning is needed. Contractor is advise to take action concerning the issue prior to second lift execution or implementation for the structure. During surveillance inspection at roof slab for substation G-1120, it was found out that water curing application & protection for the newly casted slab was insufficient enough. Please note that this structure was casted last 9 Jan. '13 which means only 5 days after casting. This is a violation to RT2S-3001-01, Para. 9.1.1 and 9.1.4.1. Contractor has to advise Amana to comply on the issue. PN: It was observed that Radiant Coil installation at F-1170 in progress, Contractor and ARCC to take more care on following work sequence at Furnace. Application of Castable at Bottom (Radiant Box) and corbel part (side) by Gunning which will produce heavy dust and water spray. There will be a chance to be contaminated the Radiant Coil. ARCC to take extra care for SS & SS Alloy Material as per procedure & take more attention to protect the SS Alloy material by using alternative method as agreed in the meeting by polyethylene sheet/or equivalent. During the surveillance at East-West Dryer Pipe Rack GL 10,9.7/DC, it was found out that these locations have honey combs on the columns of the newly removed formworks. These locations shall be checked prior to repair. Since other columns formworks were not yet removed, ensure that other locations with typical concrete defects shall be inspected prior to repair. The Contractor cut the main reinforcing bars of N-S cable tray rack at location near G-1121/Foundation type F1 in three locations. The Contractor shall provide method statement and sketch of the existing pedestal and location of the newly revised location as shown in the IFC drawing. Subcon: Work in progress, completion date will be on 07 June 2013. PN: For inspection of 2nd shell course vertical fit-up joints of Tank V-500 A,B provided access was only monkey ladder and below that the scaffolding platform was also unsafe. Instead to provide the proper access for inspection one more RFI raised for the other tank with the same type of access. Ref. RFI nos. are MFC-DLM-PS-ME-215-055, 066 which are rejected. SADARA Safety officer Mr. Joseph also rejected the scaffolding and the monkey ladder for the use of inspection. Ref. FAR No. 02. During site surveillance at dry flare super heater drum (D-0307) structure & dry flare drum (D-0301) at North side of dryer pipe rack, it has been observed that installation of filler board are using nail in which can damage some portions of birimen coating. This is a violation to RT2S-3001-01 Para. 11.1.1. Contractor is advised to take immediate action concerning the issue in order not to repeat the same in other structures. During site surveillance on Jan. 21, it was found out that the grounding pad damaged & grounding cable were cut after the installation of equipment no. V-0955 at the cooling tower area. A violation of Equipment specs, G7D-0104-00 Para. 5.13.2.1, 5.13.3.2 and 5.13.3. During site surveillance at V-0955 & sump 0906 areas, it was noticed that the end cuts of delivered reinforcing bars located between these structures were not coated with epoxy paint patch up materials. Some of the reinforcing bars might have been installed and since the cut ends are facing downward, cannot be seen anymore. Contractor to advise the Contractor to repair cut ends and other damages on epoxy coating prior to delivery on site to avoid rejection for violation of ASTM A-775, Para. 11. PN: During surveillance inspection at substation G1121 GL A/1-11 at newly installed CMU. It was found out some vertical rebar in some locations were not properly fixed or tied- up to the existing dowel bars (12mm). Note that SADARA has a standard for splicing at vertical rebar, and mock-up sequence has to be followed and implemented. Contractor is advised to take remedial action & proper supervision in order not to be repeated in other areas. During site surveillance at substation G1121 GL A/1-11, for on-going concrete masonry unit (civil) installation & execution, it has been observed the following: 1. Contractor shall assign a permanent QC Inspector to control & monitor the work to assure proper implementation of standard and IFC drawing. 2. Contractor should submit testing of aggregates for mortar & grout in accordance to ASTM C-33 (REF. G25-4300-01 Para 2.6.1) 3. Contractor should provide mixing boards at site in order that mortar & grout mixing are not contaminated. 4. Subcontractor is not using measuring box for proper mix proportion as per SADARA Standard. Page 9 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 30, 2014 DUE DATE Issued corrective action to Company Target Date S/N LBE NO. PID SUBCON/ CONTRACTOR VAF / PN LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason Company comment Approved Close LBE by Company STATUS CONTRACTOR'S CORRECTIVE ACTION PLAN LBE-ARCC-MECH- 056 ARCC VAF MECH Structural 22-Jan-13 25-Jan-13 05-Feb-13 13-Jul-13 Closed LBE-ARCC-MECH- 057 ARCC VAF MECH Structural 22-Jan-13 25-Jan-13 05-Feb-13 27-Feb-13 Closed LBE-ARCC-MECH- 058 ARCC PN MECH Structural 22-Jan-13 25-Jan-13 05-Feb-13 21-Apr-13 Closed LBE-PSCL-MECH- 059 PSCL PN MECH Tank 23-Jan-13 26-Jan-13 06-Feb-13 27-Jul-13 Closed LBE-AMA/KCC- ELECT-024 AMA/KCC PN ELECT Electrical 24-Jan-13 27-Jan-13 07-Feb-13 04-Feb-13 Closed LBE-DLM-MECH- 061 DAELIM PN MECH Preservation 24-Jan-13 27-Jan-13 07-Feb-13 27-Jul-13 Closed LBE-PSCL-MECH- 062 PSCL PN MECH Tank 24-Jan-13 27-Jan-13 07-Feb-13 Closed 1-Jun-13 Closed LBE-DLM-MECH- 060 MR. HARIKUMAR DAELIM PN MECH UG-RTR 26-Jan-13 29-Jan-13 09-Feb-13 Closed 23-Oct-13 Closed LBE-ARCC-MECH- 063 ARCC PN MECH Refractory 26-Jan-13 29-Jan-13 09-Feb-13 Closed 25-Apr-13 Closed LBE-PSCL-MECH- 064 PSCL VAF MECH Tank 26-Jan-13 29-Jan-13 09-Feb-13 Closed 14-May-13 Closed LBE-DLM-MECH- 065 DAELIM PN MECH Refractory 26-Jan-13 29-Jan-13 09-Feb-13 Closed 25-Apr-13 Closed LBE-DLM-ELECT- 025 MR. MARK DAELIM PN ELECT Electrical 28-Jan-13 31-Jan-13 11-Feb-13 06-Oct-13 Closed LBE-DLM-MECH- 066 DAELIM PN MECH Refractory 28-Jan-13 31-Jan-13 11-Feb-13 25-Apr-13 Closed LBE-ARCC-MECH- 067 ARCC PN MECH Structural 28-Jan-13 31-Jan-13 11-Feb-13 6-Jun-13 Closed LBE-ARCC-MECH- 069 MR. AMIN ARCC PN 2 MECH Quality Records 29-Jan-13 01-Feb-13 12-Feb-13 Incomplete response (130201) Make sure cylinder regulators 10-Feb-14 Closed LBE-DLM-MECH- 070 DAELIM PN MECH Quality Management 29-Jan-13 01-Feb-13 12-Feb-13 2-Apr-13 Closed LBE-KCC-MECH- 071 MR. NOOR KCC PN MECH UG-RTR 29-Jan-13 01-Feb-13 12-Feb-13 7-Feb-13 Closed LBE-DLM-ELECT- 026 DAELIM VAF ELECT Electrical 30-Jan-13 02-Feb-13 13-Feb-13 17-Feb-13 Closed During surveillance inspection at Furnace are observed that: F-1220. *Stair case open structural was installed at site without conducting elevation verification at site. Violation to RT2S-51200-01. PN: Observed that Transition Duct upper part installation at F-1170 is on progress. Daelim and ARCC to take more care on following work sequence. *The erection joint flange face of LTD were uneven at radiant box side. *The LTD erection flange surface were rested and conducted-need cleaning prior to apply mastic. *Scallop hole rectified are end plated welded area need flush grinding. *L/T duct flanges face is not matching with radiant section' flanges. PN: It is observed in Tank area of shell Daelim/Petrol Steel that the welding of 2nd shell course of Tank V-500A, V-500B, V-1425, V-0615 and its horizontal joint of tank V-500B has been completed but Contractor/Subcontractor is willing to collect more joints welded and then they will get its RT. Due to this strategy, RT back log may increase and welders may not be judged parallel to the production. So it is advised to get RT for all the Tanks parallel to the production. Subcon: Petrol Steel has noted the proactive notification, and will to be steps to submit the RT Report to submit ASAP to Company. RT computed as mentioned. During surveillance inspection at Furnace observed that the following dimensional discrepancies at site: F-1250, F-1240. *Duct alignment, centering & leveling are deviated by more that allowable tolerance limit. *The elevation joints flanges of UTD were not rested on end plates and gap bet.UTD & LTD more than allowable tolerance limit. *Misalignment on duct wall with UTD/LTD. *The erection joint bolt hole are not matching. *Shim plate requirement (installed at site) at erection joints of side plate are not mentioned on IFC drawing. *ARCC was started rectification activities without approved method of statement by Company. Subcon: ARCC put shims to make level the both sides of upper transition module & lower transition module, refer to RFI #MFC-ARCC-MECH-0062 & 0063. F-1250 & F-1240 Erection from Radiant Box up to Convection Breech are already done. Continuous monitoring for the alignment, plumbness and other quality issues shall be implemented. Daelim: F-1250 &F-120 erection from radiant box up to convection breach are already done. Alignment (Final) shall be raised upon the other repair such as welding and bolt tightening is done. Continuous monitoring for the alignment, plumbness and other quality issues shall be implemented. PN: It is observed that Contractor QC Representatives are not submitting the RFI's on time for closing and final acceptance. After the inspection, RFI's must be submitted to Company as per Schedule "Q". Attachment IVV, Para. No. 1.1.3. PN: Contractor shall verify the installation of the Transformer. As of now, the foundation of the transformer is already approximately 1.3 meters in height. And the auxiliary cabinet for the transformer will be approximately 1 meter above the foundation as per G7D-0920-00 which means that the auxiliary cabinet will be located approximately 2.3 meters above the floor which very high. As per Electrical design philosophy A554-K-PRG-EL-GEN-PHL-005, Sec. 23.16 Pedestal PN: During surveillance inspection at site on F-1250 Liquid Furnace area, it is observed that the Refractory mixing activities are in-process but in morning time and the temperature measurement comes below 10c. But Contractor/Subcontractor Quality Team must be aware that the temperature should be maintained from 10c to 32c or as per manufacturer's recommendation and/or SADARA Standard: RTSAES-n-110, Para. 9.1.12. PN: It was observed that Daelim laydown area, the piping materials were stocked in an improper method and mixed with carbon steel & LTC. It is not acceptable as per Sadara procedure and specifications. Daelim Material handling team has to segregate the piping materials based on class, type specs. QC Material Receiving and Piping team to follow approved material preservation plan. Contractor: All the material was segregated and placed as per approved procedure. Warehouse department was instructed and actions shall be taken accordingly. PN: It is observed that expansion joints around the Burner tiles and doors are on-going. Therefore, Contractor/Subcontractor's RB Hilton QC representatives must ensure that these joints are meeting the requirements of SADARA Standard (G58-1805-01) Para. No. 5.15.9 & RT-SAES-N-130 Para. No. 6.1. It is observed that during cutting of temporary attachments from the 2nd shell of Tank V-500B, grinder cut marks are made by poor practice of grinder crew. After removal of temporary attachments, grinding on the shell plates is not smooth and uniform. Some point also show that temporary attachments are removed by hammer without proper grinder cutting. It is a violation as per API.650 Para. No. 5.8.1.1 & 7.1.6. Subcon: The temporary attachment removed areas were built-up and ground smooth as to the requirement as per API 650, Para 5.8.1.2 , 7.1.6 and the same was inspected by the Contractor/Company inspector and found acceptable at the time of inspection against RFI no. MFC-DLM-PS-ME-215-142. Petrol Steel construction team was also advised regarding the discrepancy to avoid the recurrence of the same in the future. PN: The Contractor shall educate / remind their subcontractors' workers who are doing chipping works at the foundations to take care and not to damage the insulation of the grounding cables during chipping works. PN: During Surveillance inspection at Daelim MFC warehouse, it was observed that RESIN (Epoxy Vinyl Ester 411-45) material was stocked at Laydown facility which will be expiring on Jan. 28, 2013. As per manufacturing data sheet, it was manufactured on June 28, 2012 and self-life is 6 months only. Daelim is advised to shift the subject materials to quarantine area after expiration date. This proactive notification is issued to avoid the usage of expired material. Daelim: Vinyl ester and epoxy resin which we are using at site, it will be used before its expiry date, some of the resin drums expire 28/01/13 and some drums expire date 29/01/13. Expired resin will not be used at site. Necessary action are taken to ensure the material which we are using at site for lamination is within its expiry date. Expired resin already transferred to the quarantine area. PN: It is observed that the welding of vertical and horizontal joints is on-going on the Tanks (V-500A, V- 500B, V-142, V-0615) and their welding sequence needed a strong monitoring by Daelim & Petrol Steel Quality team at each shell stage to ensure the following: A. Alignment of the vertical and horizontal joints is meeting the requirements of API-650 Para. No. 7.2.3.1, 7.2.3.2 respectively. B. Plumbness of the top of the shell shall not exceed 1/200 of the total tank height as per API-650 Para. No. 7.5.2. C. Peaking of vertical joints and banding of horizontal joints shall not exceed 13mm as per API-650 Para. No. 7.5.4. PN: During the surveillance inspection, it was observed that Contractor/Subcontractor's workers are doing the shaving and lamination on FRP line in cooling water area without JCC. Contractor Quality Team must ensure and advise Subcontractors that all FRP fabricators/installers have their JCC with them whenever an activity is carried out. During site surveillance on Jan. 29, it was found out in Substation G-1120 near transformer yard that the lighting protection cable (120mm bare copper) were not properly protected from physical damages and dirt. A violation of checklist no. SMIC-P-3756. PN: During Inspection at Furnace area, observed that ARCC team were installing Burner Assembly at F- 1250 without conducting Final Alignment Inspection and the Refractory contractor also installed and fixed the Burner tile stream (Balcony side): The Bolt activities shall be synchronized and fixed the final alignment between burner and burner tile assembly. Violation of ITP-A554-E-103-QA-GEN-PLN-039. DAELIM QC team to coordinate with ARCC activities and fix the final alignment accordingly. Subcon: ARCC aware on alignment of burners. ARCC will raised RFI once it is ready for inspection (aligned). PN: Daelim & ARCC is advised to display WPS always near the welding job site and that WPS must be approved. Cylinder pressure gauges must be calibrated and heating torchers & cylinders must have flash back arrester. Subcon: ARCC advised welding department that WPS always available at welding area and be displayed. Calibration of gauge at argon cylinder is not required Company to provide which standard/reference requirements to calibrate the pressure/level gauge of gas cylinder. Flash back arrestor was provided. PN: It is observed that sometimes Daelim inspector raising RFI without proper and complete information, required for that inspection like location, ITP no, etc. Contractor QC Inspectors must ensure that RFI's have a complete information and activity no of ITP is perfectly referenced on the RFI and checklist. Page 10 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 30, 2014 DUE DATE Issued corrective action to Company Target Date S/N LBE NO. PID SUBCON/ CONTRACTOR VAF / PN LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason Company comment Approved Close LBE by Company STATUS CONTRACTOR'S CORRECTIVE ACTION PLAN LBE-TCC-MECH- 072 TCC PN MECH Piping 31-Jan-13 03-Feb-13 14-Feb-13 8-Jun-13 Closed LBE-ARCC-MECH- 073 ARCC PN MECH Refractory 31-Jan-13 03-Feb-13 14-Feb-13 20-Feb-13 Closed LBE-AMA/KCC- CIVIL-090 AMA/KCC PN CIVIL Civil 02-Feb-13 05-Feb-13 16-Feb-13 06-May-13 Closed LBE-AMA-CIVIL-091 AMA VAF CIVIL Civil 02-Feb-13 05-Feb-13 16-Feb-13 26-Mar-13 Closed LBE-AMA-CIVIL-092 AMA PN CIVIL Civil 02-Feb-13 05-Feb-13 16-Feb-13 26-Mar-13 Closed LBE-PSCL-MECH- 074 PSCL PN MECH Tank 02-Feb-13 05-Feb-13 16-Feb-13 1-Jun-13 Closed LBE-AMA-CIVIL-093 AMA VAF CIVIL Civil 03-Feb-13 06-Feb-13 17-Feb-13 12-Feb-13 Closed LBE-AMA-CIVIL-094 AMA VAF CIVIL Civil 04-Feb-13 07-Feb-13 18-Feb-13 06-May-13 Closed LBE-DLM-ELECT- 027 DAELIM VAF ELECT Electrical 04-Feb-13 07-Feb-13 18-Feb-13 06-Feb-13 Closed LBE-KCC-CIVIL-095 KCC VAF CIVIL Civil 06-Feb-13 09-Feb-13 20-Feb-13 08-Apr-13 Closed LBE-AMA-ELECT- 028 AMA PN ELECT Electrical 06-Feb-13 09-Feb-13 20-Feb-13 12-Mar-13 Closed LBE-DLM-MECH- 076 MR. HARIKUMAR DAELIM PN MECH Structural 06-Feb-13 09-Feb-13 20-Feb-13 23-Oct-13 Closed LBE-ARCC-MECH- 077 ARCC PN MECH Structural 06-Feb-13 09-Feb-13 20-Feb-13 6-Jun-13 Closed LBE-ARCC-MECH- 078 ARCC PN MECH Structural 06-Feb-13 09-Feb-13 20-Feb-13 20-Apr-13 Closed LBE-DLM-MECH- 075 MR. AMIN DAELIM PN MECH Quality Records 07-Feb-13 10-Feb-13 21-Feb-13 10-Oct-13 Closed LBE-ARCC-MECH- 079 ARCC PN MECH Refractory 07-Feb-13 10-Feb-13 21-Feb-13 25-Apr-13 Closed LBE-ARCC-MECH- 080 MR. NOOR ARCC PN MECH Refractory 09-Feb-13 12-Feb-13 23-Feb-13 12-Sep-13 Closed LBE-AMA-CIVIL-096 AMA VAF CIVIL Civil 10-Feb-13 13-Feb-13 24-Feb-13 26-Mar-13 Closed LBE-ARCC/TCC- MECH-081 ARCC/TCC PN MECH Piping 12-Feb-13 15-Feb-13 26-Feb-13 27-Mar-13 Closed PN: During surveillance, it was observed that second layer of Castable Refractory on Lower Transition duct F-1140 was on-going during rain and was not properly covered which may affect the density & strength of refractory. Contractor/Subcontractor has to ensure to take preventive measures during adverse weather condition. PN: It was noticed that during inspection by SADARA Quality Group, some major items that affects the structural integrity of the structure were missed by Contractor/Subcontractors' inspectors. Contractor/Subcontractors shall inspect specially the items that are critical to the structural integrity of the structure keenly to avoid recurrence. During site surveillance at substation G-1120 transformer yard, it was found out that newly casted concrete was not properly protected; without burlap & polyethylene sheet, and insufficient water curing application. This is a violation to T2S-3001-01, Para. 9.1.1 & 9.1.4.1. Contractor was advised to take remedial action on the issue. PN: During the inspection of TCC's first activity at their Fab. Shop, it was observed that TCC has to improve their preservation of piping materials. Especially in rainy environment, all piping materials must be properly handled with suitable covering. Contractor/Subcontractor's QC inspection team must ensure that proper inspection tools are available at the time of inspection. Ensure that large bare pipe spools have proper clamps for fit-up, proper spool stands and proper lifting equipment which will be involved in inspection. Subcon: Inspections tools are available spools properly covered during rain. Further during inspections spools are on stands. TCC inspector must be with all inspective tools. Agreed and action has been taken. PN: Contractor/Subcontractor shall provide protection for the underground PVC conduit for communication duct bank at operator building G-1122 as these conduits were exposed to mechanical damage. PN: During Material Receiving Inspection, it is observed that (Convection Module: Sec.1) Convection Tube weld joint was rested on the support. Daelim Engineering Team has to verify the strained impact on convection tube during operation. Contractor: Already informed DAELIM Engineering team. Necessary action has been taken cared of. PN: After inspection of convection module (part-3), it was observed that several Elevation & plumbness variance on site: Daelim Engr. & QC Teams have to verify the variance and fix the elevation variance according to approved recommendation method by SME of SADARA. During site surveillance at Transformer FDN (Substation G1120), it was found out that three (2) span of RC wall FDN were already removed the burlap & polyethylene sheet without proper water curing application. Note that the structure was only four (4) days after the concrete was casted. This is a violation to RT2S-3001-01 Para. 9.1.2, Contractor is advised to take remedial & immediate action on the issue. During routine site visit , it was found out that the contractor is shutting-off the power supply for the space heater of the MV induction motors at laydown yard which is a violation as per manufacturer's instruction and G7D-0665-00, section 13.1.2. With reference to RFI Nos. 2014 & 2016, Contractor/Subcontractor was not able to complete the concreting of girder at 6L BB/18-BL/18 and Conditional beam at 6L BL19-18 and columns at 6L 18 BB & 18 BC. The location of the construction joints were not in accordance with requirements of RT2S-3001- 01 section 5.4.7 which requires to be at the bottom of the element supported for columns and at mid- span for girders & beams. Anchor bolts and other embedded items were spattered with concrete including the reinforcing bars. Contractor/Subcontractor to provide method statement for Company approval prior to proceed with succeeding activity including root cause and preservative actions. PN: During site surveillance at cooling tower RC wall (Part-A) along north & east sides, it has been observed that the Tie-Rod lock and some horizontal & vertical bracings were removed which can affect the newly casted RC wall. Note that the structure was casted last 31 Jan. '13 at around 5 pm. Contractor is advised to take remedial action concerning the issue. PN: It is observed that R.T. is on-going on Daelim/Petrol Steel MFC Tanks & welders are repairing the four welds (W-985, W-816, W-046, W-333) which are still pending, and Contractor/Subcontractor Quality Teams must ensure the following: A. All repairs must be done as soon as possible & RFI must be raised for its inspection as per SMITP-M-001-02 Rev.02, activity no. 6.7. B. Repair rate must be controlled for During surveillance inspection at cooling tower basin along east side, it was observed that backfilling works did not conformed to the standard of (200mm,thk) layer by layer as stated on RT2S-2200-01, Para. 3.4.9. But Subcontractor has backfilled the area at 400mm thk. at one time. PN: During surveillance, it is observed at F-1240 Convection Breech Module prior to installation inspection activities, it was found out that the Refractory was damaged in some locations and broken near the flange. Daelim/ARCC quality team must ensure that the repair activities is perform as per manufacturer's recommendation, RTSAE-N-110. Para. Nos. 9.1.8 & 11.5. Daelim: Contractor raised an internal logbook (LBE (54) pertaining this issues. Further portions have been marked as well. These defects shall be repaired with PID presence as soon as possible. Subcontractor: ARCC to repair the damaged refractory as per issued site instruction. During surveillance inspection at substation G1120 along transformer yard, it was found out that partial delivery of concrete masonry units (CMU) 250mm thk. re not properly protected, without cover and some are rested on the ground. This is a violation to G2S-4300-01 Para. 3.1.1. PN: It is observed that during welding ARCC/TCC welders are needed to be monitored more closely by the TCC/ARCC/DAELIM QC Team for the following: Only qualified welders will tack & weld the joint. Welder will not weld the joint without Fit-up inspection acceptance. Weld shielding must be proper to avoid air entrapment during welding. Welder will not weave the welding lead more that 3 times the electrode diameter during filling and capping. Welder will not exceed the limit of weld deposition from his qualified thickness for the relevant welding process. Final weld cap reinforcement profile must be smoothed and with proper each weld layer overlapping avoiding all visual defects as per ASME B313. Ensure the welder shall not proceed the welding if Fit-up tack is already cracked during his root pass welding. Ensure that all welders have passed the 1st three production welds by RT prior to proceed for continuous welding. PN: It was observed that sealing plate of convection module, section 03 at header box was damaged and the part was dismantled. Daelim QA/QC Team has to closely monitor the repair activities and carried-out in accordance with the approved procedure and method. PN: All WPS, PQR, Weld maps and Weld line description matrix should be available at each work site any time for verification by the Company Inspector. Contractor Inspection team has to provide these documents at site and off-site Sadara Jobs. Ref. TR8S-6500-01. Contractor: Situation complying with the requirement. PN: It was found out that the Subcontractor R.B Hilton has been fixing the ceramic board (50mm) in corbel area F-1250 Liquid Furnace prior to summing application. But still there were gaps around the tile clip extension and gusset plates. These gaps should be filled with ceramic blanket prior to installation of C-clip, tile anchor. Page 11 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 30, 2014 DUE DATE Issued corrective action to Company Target Date S/N LBE NO. PID SUBCON/ CONTRACTOR VAF / PN LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason Company comment Approved Close LBE by Company STATUS CONTRACTOR'S CORRECTIVE ACTION PLAN LBE-PSCL-MECH- 082 MR. AMIN PSCL PN 2 MECH Tank 12-Feb-13 15-Feb-13 26-Feb-13 19-Feb-14 Closed LBE-ARCC/TCC- MECH-083 ARCC/TCC PN MECH Preservation 12-Feb-13 15-Feb-13 26-Feb-13 27-Feb-13 Closed LBE-ARCC-MECH- 084 ARCC VAF MECH Refractory 13-Feb-13 16-Feb-13 27-Feb-13 2-Jun-13 Closed LBE-ARCC-MECH- 085 ARCC VAF MECH Structural 13-Feb-13 16-Feb-13 27-Feb-13 22-Apr-13 Closed LBE-AMA-CIVIL-097 AMA PN CIVIL Civil 14-Feb-13 17-Feb-13 28-Feb-13 25-Mar-13 Closed LBE-AMA-CIVIL-098 AMA VAF CIVIL Civil 14-Feb-13 17-Feb-13 28-Feb-13 26-Mar-13 Closed LBE-KCC-CIVIL-099 KCC VAF CIVIL Civil 14-Feb-13 17-Feb-13 28-Feb-13 08-Apr-13 Closed LBE-AMA-CIVIL-100 AMA PN CIVIL Civil 14-Feb-13 17-Feb-13 28-Feb-13 26-Mar-13 Closed LBE-TCC-MECH- 086 TCC PN MECH Mechanical 14-Feb-13 17-Feb-13 28-Feb-13 28-Apr-13 Closed LBE-AMA-CIVIL-101 AMA PN CIVIL Civil 16-Feb-13 19-Feb-13 02-Mar-13 01-May-13 Closed LBE-ARCC-MECH- 087 ARCC PN MECH Piping 17-Feb-13 20-Feb-13 03-Mar-13 3-Mar-13 Closed LBE-DLM-MECH- 088 DAELIM PN MECH Refractory 18-Feb-13 21-Feb-13 04-Mar-13 16-Jun-13 Closed LBE-AMA-CIVIL-102 AMA PN CIVIL Civil 23-Feb-13 26-Feb-13 09-Mar-13 18-Aug-13 Closed LBE-AMA-CIVIL-103 MR. GERALD AMA PN CIVIL Civil 25-Feb-13 28-Feb-13 11-Mar-13 16-Oct-13 Closed LBE-KCC-MECH- 089 KCC VAF MECH Mechanical 25-Feb-13 28-Feb-13 11-Mar-13 9-Mar-13 Closed LBE-AMA-ELECT- 029 AMA VAF ELECT Electrical 26-Feb-13 01-Mar-13 12-Mar-13 03-Mar-13 Closed LBE-PSCL-MECH- 090 PSCL PN MECH Tank 27-Feb-13 02-Mar-13 13-Mar-13 2-Jun-13 Closed LBE-PSCL-MECH- 091 PSCL PN MECH Tank 27-Feb-13 02-Mar-13 24-Oct-13 4-Mar-14 Closed LBE-AMA-CIVIL-104 AMA PN CIVIL Civil 28-Feb-13 03-Mar-13 14-Mar-13 22-May-13 Closed PN: It observed that distortion control on Petrol Steel Tanks is needed close concentration for vertical and horizontal shell weld joints. Petrol Steel/Daelim needed to submit a separate distortion control welding sequence procedure for SADARA approval. It is advised to Daelim/Petrol Steel QC team to monitor closely for peaking , banding and weld joints misalignment, etc. as per API-650 requirements. Subcon: The proactive notification has been noted, the welding sequence for vertical and horizontal joints are already mentioned in the approved general erection procedure. Petrol Steel is working closely to avoid this violation in the on-going progress. PN: DAELIM/ARCC/TCC QC team to ensure that welding electrodes are color coded with high temperature heat resistant paint prior to re-baking to avoid re-baking the electrode twice. Dont allow any kind of paint material for this purpose which is flammable at the oven temperature. During material receiving inspection, it was observed that Refractory Lining was damaged at splice joint between Convection Module and Breech Module. Daelim & ARCC teams have installed the modules on position without correcting the repair activities. Daelim/ARCC team to propose rectification method to Company and take this concern seriously in order to avoid further interruption during operation. Violation of pro-active notification log #80 and RTSAES-N-110 & RT-6-ICS. Daelim: F-1250 Convection Breech Module has been repaired with Sadara witness. Rectification & repair for the refractory lining defects are already done. PN: Contractor submitted RFI # AMA-CI-1856, dated 18/12/12 & RFI # AMA-CI-1860 dated 18/12/12 concerning concrete sampling testing & placement insp. (CI.C2 & MGI) its lift (Substation G1120), the required strength for this structure is 4000 PSI with micro silica. But the attachment is only 2000PSI/type 1, as per submitted RFI. And also, it has conflict with location & structure. Contractor should investigate & check the attachment & explain to SADARA QC personnel on what to the said RFI's. PN: It is observed that Piping work is on-going for different line classes and ASME standards at off-site Fabrication of ARCC. Daelim/ARCC QC team is advised to ensure the following: Proper material & spool segregation as per line class, B31.1, B31.3 & approved drawings. Fittings are used as per latest approved drawings. Color coding system is implemented. Proper identification for SADARA MFC designated areas. PN: During Material Receiving Inspection on Convection Module, it was observed that Refractory Lining was severely damaged at F-1160 & F-1170. At F-1160 the north flange area & F-1170 the west side: Brazing location. Daelim/Subcontractor shall rectify the defects with proper Refractory rectification method approved by SADARA prior to start further installation at site. RT-SAES-N-110 & RT-6-ICS. Subcon: As per SME, damages happened to refractory surface would be a big concerned (as per attached photos of SME for verification) AS this damages are happened mainly in the flange area which was already covered with mastic and thick ceramic fiber blanket , no leakage or not spot is expected. Leakage is not expected since enough and thick patching material of C. F Blanket was provided to between CM-1240-2 and 3. Then Subcontractor would like to close this issue. With reference to today's RFI # MFC-DLM-KCC-CI-2204-0A and RFI # MFC-DLM-KCC-CI-2205-0A, the following are observed: GL 65, 66, 67, 68/AB - column ties were bent and hooks not properly embedded. No pouring access of concrete pump hose to columns below the beams at first lift at GL 66/13B & GL 67/BB. This is a violation to RT2S-3001-01 Section 5.6.10 which states "Concrete shall not be allowed to fall free from a height more than 1.0m. Heights greater than 1.0m shall require approved down pipe tremie or chute" Bolt offset of more that 3mm at GL 65/BC and 68/BB. PN: During site surveillance at substation G1120, it has been observed that some portions for CMU installation are not using fish tail for proper anchoring at columns and also chipping at columns are not properly implemented prior to CMU installation. Contractor is advised to take immediate action concerning the issue & also properly monitored as per IFC drawing. PN: During surveillance of TCC fabrication, it has been observed that there is no 24 hours power supply for electrode holding oven. TCC has been advised to maintain 24 hours supply to sustain temperature in the holding oven. It is observed that ARCC Fabrication team was fabricating shim plate on gratings at Furnace area (ELC:3S.4). The area was contaminated, spread grinding debris around & occurred corrosion on adjacent structure and gratings. ARCC team to rectify the surface of immediately and control the corrosion where it occurred. ARCC QA/QC team is advised to use proper protection during rectification or fabrication at site. PN: The Contractor submitted RFI # AMA-CI-1645 dated 22/11/2012 regarding leak testing for unit sump # 4 (Sump 634) already signed by sub-contractor and Contractor QC personnel. This Sump is still pending and needs further leak test due to non-completion of the repair at the West-Side portion of the wall. Contractor shall review RFI's prior to sending for approval and ensure activities are in compliance with SADARA specification and the ITP. During site surveillance at substation G1120, it has been observed that mixing of mortar & grout intended for CMU installation. AMANA is not using measuring box for proper proportioning or ratio of comment & sand. This is a violation to G2S-4300-01 Para. 2.4.2 & 3.2.14.1. Contractor was advised to control & monitor properly not to repeat the issue. PN: During inspection at Mid-Wall 3, 4, 5, & 6 at Cooling Tower (Part-B), it was found out that construction joints were provided but such does not follow IFC drawings. The Contractor was advised to justify this const. joints by confirmation from the engineering of Daelim and to submit shop drawing for proper documentation. Subcontractor: Drawing Confirmed & Signed by Daelim It was observed that the stub-up grounding cable in area are now in bad shape and some of the cable are already damaged because of no protection and not secured from physical damage. A violation of schedule 'Q', attachment Q-1, sec. 1.2. PN: Petrol Steel has erected the last shell course of 2 tanks V-500A & V-500B and its maximum inspection like weld visual, NDE, Peaking, Banding & Plumbness inspections are still balance. Also many inspections are still remaining for lower shell courses and bottom as well. Daelim inspection team must ensure that all required inspections are completed prior to roof or compression plate erection on the last upper shell course. PN: Daelim drawings for Tanks are showing the weld joint of compression plate to tank roof overlapped instead of under lap as per design calculation don no. V-1425-103-9004-01-215. Its joint design is under lapped which may be a more stringent. Daelim QC team is advised to ensure the final joint design from engineering prior to activity start-up. PN: During site surveillance at Cooling Tower (Part-B) base slab, it was observed that some portions of slab are having hairline cracks. Contractor/Subcontractor has to investigate the said cracks prior to repair works. Subcon: Hairline cracks to be repaired using approval repair material. A method statement was submitted for repair of cracks. PN: During site surveillance at substation G1121 along (CMU) perimeter wall, it was observed that the installation of CMU wall's IFC drawing was not followed where there is no installed weep holes. Contractor is advised to take immediate action concerning the issue that proper monitoring of the works must be observed. Subcon: Weed holes already installed. Contractor QC will be conducting internal inspection prior to Company inspection. RFI will be raised. During surveillance, it was found out that Daelim/KCC started "PIV" valves installation on-going without Testing the 5 water lines, packages no. 04,05,15,18,20 and valves no. 0708, 0709, 0706, 0702, 0705, 0707. As per A554-0-PRG-IC-GEN-DOC-001, Daelim/KCC QA/QC Team must ensure that the valve installation activities as per Company document as above. Page 12 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 30, 2014 DUE DATE Issued corrective action to Company Target Date S/N LBE NO. PID SUBCON/ CONTRACTOR VAF / PN LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason Company comment Approved Close LBE by Company STATUS CONTRACTOR'S CORRECTIVE ACTION PLAN LBE-ARCC-MECH- 092 ARCC VAF MECH Refractory 28-Feb-13 03-Mar-13 14-Mar-13 20-Apr-13 Closed LBE-AMA-CIVIL-105 AMA PN CIVIL Civil 03-Mar-13 06-Mar-13 17-Mar-13 05-May-13 Closed LBE-TCC-MECH- 093 TCC PN MECH Mechanical 03-Mar-13 06-Mar-13 17-Mar-13 5-Jun-13 Closed LBE-ARCC-MECH- 094 ARCC VAF MECH Structural 03-Mar-13 06-Mar-13 17-Mar-13 13-Jul-13 Closed LBE-AMA-CIVIL-106 AMA PN CIVIL Civil 04-Mar-13 07-Mar-13 18-Mar-13 21-Mar-13 Closed LBE-ARCC-MECH- 095 ARCC VAF MECH Piping 05-Mar-13 08-Mar-13 19-Mar-13 13-Jul-13 Closed LBE-DLM-MECH- 096 DAELIM VAF MECH Quality Records 05-Mar-13 08-Mar-13 19-Mar-13 08-Jun-13 Closed LBE-KCC-MECH- 097 MR. NOOR KCC VAF MECH UG-RTR 05-Mar-13 08-Mar-13 19-Mar-13 Closed 19-Mar-13 Closed LBE-KCC-MECH- 098 MR. NOOR KCC VAF MECH UG-RTR 05-Mar-13 08-Mar-13 19-Mar-13 01-Jan-14 Closed LBE-TCC-MECH- 099 TCC VAF MECH Piping 07-Mar-13 10-Mar-13 21-Mar-13 Closed 22-Apr-13 Closed LBE-TCC-MECH- 100 MR. NASSAR TCC PN MECH Coating/ Painting 07-Mar-13 10-Mar-13 21-Mar-13 Closed 22-Apr-13 Closed LBE-PSCL-MECH- 101 MR. AMIN PSCL VAF MECH Tank 07-Mar-13 10-Mar-13 21-Mar-13 22-Oct-13 Closed LBE-KCC-CIVIL-107 KCC VAF CIVIL Civil 10-Mar-13 13-Mar-13 24-Mar-13 09-Apr-13 Closed LBE-AMA-CIVIL-108 AMA PN CIVIL Civil 10-Mar-13 13-Mar-13 24-Mar-13 08-May-13 Closed LBE-AMA-CIVIL-109 AMA PN CIVIL Civil 10-Mar-13 13-Mar-13 24-Mar-13 09-Apr-13 Closed LBE-TCC-MECH- 102 MR. NASSAR TCC VAF MECH Quality Management 10-Mar-13 13-Mar-13 24-Mar-13 22-May-13 Closed LBE-ARCC-MECH- 103 ARCC VAF MECH Mechanical 10-Mar-13 13-Mar-13 24-Mar-13 22-Jun-13 Closed LBE-DLM-MECH- 104 MR. NASSAR DAELIM VAF 2 MECH Coating/ Painting 11-Mar-13 14-Mar-13 25-Mar-13 17-Feb-14 Closed It was observed that ARCC Construction team has installed the Burner Assembly at F-1250 in improper way and no proper protection on Burner tip. Burner tips are open Refractory material & all debars were occurred on Burner tip. Delay to install Burner tress. Tips were damaged and bended. Daelim QA/QC team to closely monitor the installation of sensitive part of the equipment at Furnace and coordinate with the Subcontractor's activities as per approved procedure and specification. Violation of Proactive Notification #67 ITP-A554-GE-PLA-039. PN: It was observed that the area to be epoxy grouted at the Compressor shelter at the compressor shelter are wide enough that may crack due to expansion of the epoxy grout. It is recommended that the manufacturer of the epoxy grout shall be consulted to advise location of expansion joints on adjacent area of the sole plates to avoid cracking of the epoxy grout. During inspection of valve installation of fire water line: FW-071206-09-02 area no B1 valve # PIV-0720 on site. It is observed that the Contractor/Subcontractor is using nut, bolts and gaskets in fire water line without material receiving inspection. As per relevant ITP, SMITP-M-350-01 activity no. 2.3, 2.4 its inspection level is witness for Company and this is a violation of schedule "Q", Para. 1.6. Subcon: KCC Construction was instructed to ensure proper documentation on supplied materials before using on site. Daelim: The activity at the site on hold the material receiving RFI for bolt and nuts on hold due to dishwashing's are not done as per the ASTM F436 and this issue was already informed to Daelim Material Department to solve said problem as soon as possible and we are not giving to use this washer until this issue is solved and packed already and further inspected by SADARA Inspectors. During surveillance, it was observed that TCC welder (TCC-001) was found welding in an open atmosphere. In spite of the tool box meeting conducted by TCC QC and Daelim QC to all TCC welders, said welder is still welding in an open atmosphere. Contractor/Subcontractor is advised to welding a controlled atmosphere to avoid weld discrepancies. PN: It is observed that the weather conditions are severe which can cause problem for sand blasting and coating. Therefore, Contractor/Subcontractor is advised to ensure that sand blasting & coating activities are carried out in a controlled environment. Subcon: No any blasting and coating activity allowed in sandy weather. Crew supervisor and Painting inspector are ensure it regularly basis. Daelim: It is observed that during WQT qualification at site, 6 welders has started the WQT but DAELIM, ARCC & Third party were not having any measuring device for Pre-Heat, Inter-pass temp. measurement and Clamp meter for heat input measurement and clamp meter for heat input measurement as per relevant WPS. This has been a repeated violation that welders are doing welding without ensuring the WPS parameters. Subcon: The WPQT-009 cancelled on that day 5 March 2013, only this day 12 May 2013 conducting WPQT for 14 welders, while the third party inspection (AMSYCO) have been provided his instrument for measuring temperature & every now & then, AMSYCO aware on Sadara's requirement. Daelim: The RFI for WPQT is cancelled by Daelim. Action have been already taken by raising Logbook Entry to ARCC/AMSYCO. During ITP review, Daelim inspection team doesnt have proper document tracking system, and ITP preparing personnel also not caring to edit a reference document number in ITP for quality procedure reference. Daelim inspection team must ensure the proper corrective action and Preventive measures in the future. During inspection of bolts torqueing prior to pressurization of fire water line FRP, test bolts were over Torqued for the "PIV" valve and blind flanges by spanner instead of using calibration torque wrench which is violation to SADARA Standard (G85-8010-47) for over torqueing the FRP, which may damage or leave potential defect in the flange material. Daelim: All the Bolts of the blind flanges in package no.:20 & 21 are removed after completion of the hydro test of both "pkg" after hydro test "PIV" bolts are also loosed and when we will do bolt tightening for "PIV" Contractor will issue RFI for SQIT witness. PN: TCC has started welding activities (Tack Weld) on structure at site without notification. The following violations are observed: 1. Welder was welding without proper tools (oven, etc.) 2. Welding consumables were not inspected or approved for site. 3. Welding Inspector was not available at site. Daelim QA/QC team shall closely monitor the TCC welding activities at site. Subcon: One welding inspector for TCC site welding activities had been already approved by Company. Safety orientation and get pass in process. After getting SADARA gate pass said Inspector will be available at TCC site. Mr. Imran taking care for MFC Project site welding activities. Action has been taken and welding Inspector is present at site. The following violations were observed on the installation of grating and stairway at Furnace area: Stairways were released for construction activities without final Bolt tightening. Gratings were laid on the platform in improper way and not fixed/aligned properly. Grating panels are provided with a minimum of 2 fasteners at each support with minimum of 4 fasteners per panel. ARCC/Daelim shall follow the minimum requirement as specified on RT2S-5120 and construction drawing for installation of platforms and stairways. Subcon: ARCC installed bolts/fasteners on structural members, grating clips and pictures were taken as proof of the actions were undertaken..(photos sent to DAELIM) PN: During site surveillance at substation G1121 (Soffit Slab Structure) along switch gear area, it was found out that Contractor/Subcontractor has started application of primer paint without Material Receiving Inspection done on the paint material and an approved Method of Statement for Interior Painting (Building) submitted to Company for review and approval. Contractor/Subcontractor is advised to submit first RFI for material receiving inspection with its valid supporting documents for proper documentations. During surveillance on fire water valves, it has been observed that delamination (adhesion failure & flaking, coating damage and blasting application) or dirt inclusions of paint surface was noted in the bonnet flange. The post indicator valve was manufactured by waters. Daelim shall conduct root cause analysis including corrective action. These valves affected and implications of a continued coating breakdown. Contractor need to ensure the effective implementation of preservation requirements for all equipment and materials during storage installation. Daelim: Daelim Material Team shall feedback the item to the vendor and shall obtain the repair procedure for the item. Daelim Coating team shall repair the item with Company approved procedure and applicable standards. PN: During inspection at (slab & Haunch) portion at Cooling tower "East of Pump Sump", it was found out that the location of water stopper was adjusted and did not follow the IFC drawing. Contractor is advised to submit shop drawing showing the actual location of water stopper with the confirmation of Daelim Engineering team. During surveillance, it was noticed that the Contractor/Subcontractor carried out the job without informing SADARA SQIT. When visited the site, there was no Contractor QC Inspector but surface preparation and painting application were going-on during sand storm and intermittent rain. The crew members who applied the coating did not hold JCC with them. A violation to the Standard and as per schedule "Q" attachment IV section 2 & work procedure A554-E-103-QA-GEN-PRO-041, Para. 5.2.1.2 & 5.2.1.3. Photos were provided. Subcon: Performance test was done on 23 Feb. 2013, waiting for JCC to come out. Daelim: It is observed that the weld repair rate of Daelim/ARCC has increased, violating the Sched. "Q" Attach. IV, Para. 3.9 at ARCC off-site Fabrication. Daelim & ARCC quality team to provide root cause analysis, corrective action and preventive measures as soon as possible. Sch. "Q" weld rejection rate requirement is up to <5% only but ARCC's actual weld reject is 11.764%. Subcon: ARCC conducted electrodes test/verification & found out that some porosities were visible for "GEKA" brand. ARCC fabrication shop are utilizing Bohler brand. ARCC submitted corrective & preventive action plan via email & officially transmitted. Daelim: Misalignment is observed at third horizontal weld joint at 03 locations. Actual measurement .07 misalignment is 1.7-3mm which is not acceptable as per API-650 Para. 7.2.3.2. Additional RT might be required for assurance of the weld joint integrity. Proper corrective action is required from Daelim/Petrol Steel. Subcon: The misalignment area has been rectified and the weld integrity has been assured by taking additional RT spots in the rectified misalignment area. (Ref. RT report no. J28323, J28324, & J28520 & J28521). The rectified area was also offered for Contractor/Company inspection and it was found acceptable. After removal of formworks at Pipe rack A, it was noticed that excessive honeycombs are prominent on the West side portion of the column at first level 9+ 6L 6/AB. The honeycombs at the surface of the column is about 3.45 m high. Contractor/Subcontractor is advised to provide Method Statement of how to repair the excessive honeycombs and preventive action so that it will not happen again. PN: It was observed that repetitive inspection has been undertaken at Floor Pipe rack area due to conflict in between details in the drawing. DWG. No. A554-E-104-CV-DWG-C40-383, rev. 2B has 2 conflicting details. One detail shows: Top of grout to be 155mm while the other shows 155mm Top of concrete projection. Contractor shall verify first with Engineering prior to finalize setting out of anchor Page 13 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 30, 2014 DUE DATE Issued corrective action to Company Target Date S/N LBE NO. PID SUBCON/ CONTRACTOR VAF / PN LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason Company comment Approved Close LBE by Company STATUS CONTRACTOR'S CORRECTIVE ACTION PLAN LBE-TCC-MECH- 105 TCC VAF MECH Piping 16-Mar-13 19-Mar-13 30-Mar-13 22-Apr-13 Closed LBE-ARCC-MECH- 106 MR. NASSAR ARCC VAF MECH Quality Management 16-Mar-13 19-Mar-13 30-Mar-13 22-May-13 Closed LBE-ARCC-MECH- 107 MR. NASSAR ARCC PN MECH Coating/ Painting 16-Mar-13 19-Mar-13 30-Mar-13 23-May-13 Closed LBE-TCC-MECH- 108 MR. NASSAR TCC PN MECH Coating/ Painting 16-Mar-13 19-Mar-13 30-Mar-13 22-May-13 Closed LBE-ARCC-MECH- 109 ARCC VAF MECH Piping 16-Mar-13 19-Mar-13 30-Mar-13 18-May-13 Closed LBE-AMA-CIVIL-110 AMA PN CIVIL Civil 17-Mar-13 20-Mar-13 31-Mar-13 15-Apr-13 Closed LBE-DLM-MECH- 110 MR. NOOR DAELIM VAF 2 MECH Material 17-Mar-13 20-Mar-13 31-Mar-13 12-Feb-14 Closed LBE-AMA-CIVIL-111 AMA PN CIVIL Civil 18-Mar-13 21-Mar-13 01-Apr-13 18-Aug-13 Closed LBE-DLM-MECH- 111 MR. AMIN DAELIM VAF 2 MECH Quality Records 18-Mar-13 21-Mar-13 01-Apr-13 10-Feb-14 Closed LBE-ARCC-MECH- 112 ARCC VAF MECH Quality Records 18-Mar-13 21-Mar-13 01-Apr-13 18-May-13 Closed LBE-TCC-MECH- 113 MR. NASSAR TCC VAF MECH Coating/ Painting 18-Mar-13 21-Mar-13 01-Apr-13 22-May-13 Closed LBE-DLM-MECH- 114 MR. NOOR DAELIM VAF MECH Preservation 18-Mar-13 21-Mar-13 01-Apr-13 01-Jan-14 Closed LBE-PSCL-MECH- 115 MR. AMIN PSCL VAF MECH Tank 19-Mar-13 22-Mar-13 02-Apr-13 27-Oct-13 Closed LBE-ARCC-MECH- 116 MR. NASSAR ARCC VAF MECH Coating/ Painting 19-Mar-13 22-Mar-13 02-Apr-13 22-May-13 Closed LBE-TCC-MECH- 117 TCC VAF MECH Quality Records 20-Mar-13 23-Mar-13 03-Apr-13 22-Apr-13 Closed LBE-AMA-CIVIL-112 AMA PN CIVIL Civil 23-Mar-13 26-Mar-13 06-Apr-13 18-Aug-13 Closed LBE-KCC-MECH- 118 MR. NOOR KCC VAF MECH UG-RTR 23-Mar-13 26-Mar-13 06-Apr-13 9-May-13 Closed LBE-KCC-CIVIL-113 KCC VAF CIVIL Civil 24-Mar-13 27-Mar-13 07-Apr-13 08-May-13 Closed During routine inspection at TCC off-site fabrication facility, it is observed that 2 LTCS 36" pipe of random length are found stored with normal CS material which is a violation against Sadara Preservation Plan RT-6-ICS. TCC & Daelim QC have not been notified regarding the arrival of LTCS at TCC facility, moreover on factory. During routine inspection on Furnace 1250; RFI #MFC-DLM-ARCC-H-0192 it has been observed that the responsible coating Inspector of ARCC Mr. Christopher Ofiaza was doing the job without approval from Sadara. This is violating the Standard as per schedule "Q" attachment I, Para. 5.6. Subcon: ARCC submitted CV of Mr. JJ Buendia Painting Inspector, interviewed and approved conditionally.Mr. Bundia is raising RFI & conducting inspection. Chris Ofiaza is assist on Painting Inspection activities under supervision of JJ Buendia. It is observed that Daelim Quality team is not reviewing and approving the subcontractor welder's certification & submitting to Company directly. It is violation of Sadara procedure A554-O-PRG-QA-GEN- PRO-012, Rev.2 Para. No. 5.0. Daelim quality team needs to comply with the Sadara requirements. Subcon: Daelim: Contractor apologizes for the clerical errors found in the welder qualification records with mentioned transmittal, Contractor is not doing any violation against the as per standard and specifications of the Company. Further, after Company approved third party certification. Contractor reviewing and if there is any errors found after rectification only we submit to the Company. However Contractor will give more attention to avoid this will happen again in the future. WQT done at off-site ARCC welding academy without approved WPS (WPS No. 1148/09A, rev.1) against the RFI No. ARCC-PIP-WE-0057 dated 12th March 2013, WPS was stamped on the additional top page only by Mr. J.H. An but Daelim QC representative told that it is approved by Sadara Welding Specialist Mr. Adnan but actually that is not approved by him. This is a violation of Schedule Q, Atta. IV, Para. 2.1. Daelim Quality needs to comply with the Sadara requirements. During routine inspection on the external coating touch-up/repair for pipes & spools as per RFI No. TCC- H-046, it has been observed that painters applied touch-up on the defected area by roller in front of Company Inspector. This is violation of the Standard as per GI6S-0202-02, section 4, Para. 4.2. Subcon:TCC Painting Inspector will make sure to follow any repair in painting surface as per approved Procedure and Sadara specifications. Initial application of Prime shall not be allowed with roller, only brush shall be used & subsequent coats shall follow manufacturer's PN: During witness crushing of cubes at site laboratory (third party) for cement mortar intended for substation G1121 GL-1G/A, 1/A-B, it was found out that at 28 days compressive test result the average is 2487.5psi in which as per requirement is 2500psi. Contractor is advised to take corrective action on the issue. During Material Receiving inspection found that material identification on washers are missing which is violation against schedule "Q" attachment IV Para. 4.2. Contractor must ensure that the materials should be complied as per project specification's requirements before installation of PIV valve for underground system. Subcon: Daelim: Regarding the material identification on washing, Contractor informed to material distributor to solve this issue and Contractor will take care that such type of actions will be repeated again. All the washers were conducted by Third Testing party. Only 4 packet were found rejected. All other found accepted. The rejected washers were segregated and will be replaced. PN: During inspection at cooling tower "Wall 9a", it was found out the splicing from starter bar for vertical rebar 2.5mm is not in accordance with Sadara' s standard. Note that the actual splicing dimension is only 1500mm, and as per standard requirement dimension at 1650mm. Contractor is advised to submit shop drawing & confirm by Daelim's Engineering team for proper documentation. Subcon: Daelim reviewed the drawing and found acceptable. Please see attached drawing signed by Daelim. PN: During routine inspection at inside Furnace-1110, it has been observed that uniform pock marked appearance in particular of spray applied coating in which the surface of the paint film resembles the skin of an orange (orange peel). The probable cause - failure of the paint film to flow-out, usually caused by poor application techniques, by incorrect solvent blend or too high ahrotropy. Other defect is bubbles without paint film appear as small blisters. PN: During routine inspection for external primer Coating for pipes and spools at TCC facilities, it has been observed that mechanical damage for pipe no. N016103C2A-CUR; the depth of this damage is 1mm. Subcon:TCC Piping inspector will make sure for no damage on receiving materials. Before final spool release RFI piping inspector is responsible to rectified any mechanical damage. Daelim: It is observed that some welders at off-site ARCC fabrication are violating the allowable weld bead width by GTAW & SMAW Processes more than 03 times the core wire or filler wire dia. It is notified 2nd time to Daelim welding inspector but told that he allowed the welders himself. Subcon: ARCC QC Inspector conducted orientation tool box meeting on welders and welding staff with regards to wide bead. Daelim has already taken action by raising log-book entry to ARCC and subcontractor has taken also corrective action by conducting tool box meeting to the welders. During the review of RFI's submitted for Sadara Quality Group's signature, it was noticed that RFI No. MFC-DLM-KCC-CI-2531 (3/18/13) has attachment with laboratory test report without reference number. The contents of the test report are also in conflict with the requirements. The specification requirements for relative density is 75% while the result of 71.3% & 70.7% were marked as pass. Computation of % density is also wrong. Contractor/Subcontractor to investigate root cause and corrective action. Subcon: Osaimi technician admitted his lapses and asked for consideration on the matter, promised not to repeat the same mistake in the future. Contractor/Subcontractor QC will be more careful in double checking 3rd party's reports. Compaction testing shall then be HOLD point inspection for Contractor. Lean concrete, however, was removed & conducted re-testing on the affected area. Compaction testing passed and poured lean concrete again. During routine inspection at White Nile fabrication, it is observed that incorrect & irrelevant WPS(WN- WPS-A-03, Rev. 0 & WN--WPS-A-02, Rev.1 was displayed at the facility area, violating Sadara specification RT8S-6500-01. Pro-active notification was also logged as LBE No. 75 on 7 Feb. 2013. Subcon: All Rev. WPS was removed from the site & approval of WPS was there . All job location only. Approved WPS will be their. Daelim: PN: During surveillance inspection at cooling tower "Perimeter Wall" part A,B,&C internal portion, it was found out some portion of walls have presence of hairline cracks in several locations. Contractor is advised to check and investigate said hairline cracks and take corrective & preventive action on the issue. Subcon: Subcontractor had been submitted method statement for repair of hairline cracks at the perimeter walls of the cooling tower. A violation has been noted for over-torqueing of valves which exceeded more than 345N-M for 10" & 20" and 150-210 N-M for 6" dia pipes but as per Sadara specification G8S-810-47, maximum torque limit for 10" is 105 N-M, for 20" maximum 185 N-M and for 6" maximum torque limit is 70 N-M. Daelim quality team must take corrective action and preventive measures. Subcon: The over Torque Flange was already removed after the Hydro test. Succeeding Torqueing shall be closely monitored by Inspectors to ensure correct torqueing. Found that Nuts, Bolts and Washers stored in Daelim Laydown yard in open atmosphere. As per Company Material Preservation plan & Project requirement as per "RT-6-1CS" states that Nuts, Bolts & washers should be kept in sealed water tight containers if stored outside. Daelim: All the Nuts, Bolts, and washers were packed back in wooden boxes. All stored properly. After inspection it is found satisfactory. During inspection of 5th horizontal & vertical weld joints found the following standard violations: Misalignment violations on weld joint # TV5BH5=2.1, 2.8mm, # TV5DH5=2.1mm & TV6DH5=2.0mm. Banding violations between V5C and V6C at horizontal weld joint = -14 mm & between V6C & V5D at horizontal weld joint = 14.6mm. These violations are as per API.650 Para. 7. Sadara LBE no. 101 logged for same type of violations. PN #62,82. Subcon: The Misalignment areas TV5BH4, TV5DH, TV6DH5, were rectified according to the requirement in API 650 para 7.2.3.2 and Banding discrepancy between V5C and V6C,, and V5D was also been rectified according to the requirement in API 650 para 7.5. (b). As assurance for the weld integrity, additional RT spots has been taken in selected areas (Ref. RT report no. J27194 & J27193). The same was offered for inspections to the Contractor/ Company Inspector and was found acceptable. Daelim: During routine inspection on the external coating touch-up/repair for weld joints of F-1250 as per RFI No. H-0201, it has been observed that too many defects on the coating and weld joints. ARCC coating Inspector, started, welding department has been released weld joints for coating. This is violating the standard as per Doc. No. A554-E-103-QA-GEN-PRO-043, Rev. 1, Para. 6.2.7 & 6.2.8. Subcon:ARCC raised RFI for weld defects prior to painting activities, then ARCC painting group raised RFI for surface preparation & primer, but other areas are under Daelim Scope. (Painting at Shop). Daelim: Page 14 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 30, 2014 DUE DATE Issued corrective action to Company Target Date S/N LBE NO. PID SUBCON/ CONTRACTOR VAF / PN LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason Company comment Approved Close LBE by Company STATUS CONTRACTOR'S CORRECTIVE ACTION PLAN LBE-KCC-CIVIL-114 KCC VAF CIVIL Civil 24-Mar-13 27-Mar-13 07-Apr-13 09-Jul-13 Closed LBE-TCC-MECH- 119 TCC PN MECH Piping 24-Mar-13 27-Mar-13 07-Apr-13 22-Apr-13 Closed LBE-DLM-ELECT- 030 DAELIM PN ELECT Electrical 25-Mar-13 28-Mar-13 08-Apr-13 25-Mar-13 Closed LBE-PSCL-MECH- 120 MR. AMIN PSCL VAF MECH Tank 25-Mar-13 28-Mar-13 08-Apr-13 27-Jul-13 Closed LBE-PSCL-MECH- 121 PSCL VAF MECH Tank 25-Mar-13 28-Mar-13 08-Apr-13 14-May-13 Closed LBE-PSCL-MECH- 122 PSCL VAF MECH Tank 25-Mar-13 28-Mar-13 08-Apr-13 14-May-13 Closed LBE-PSCL-MECH- 123 MR. NASSAR PSCL PN MECH Coating/ Painting 25-Mar-13 28-Mar-13 08-Apr-13 22-May-13 Closed LBE-PSCL-MECH- 124 MR. NASSAR PSCL VAF MECH Coating/ Painting 25-Mar-13 28-Mar-13 08-Apr-13 23-May-13 Closed LBE-ARCC-MECH- 125 MR. NASSAR ARCC VAF MECH Coating/ Painting 25-Mar-13 28-Mar-13 08-Apr-13 23-May-13 Closed LBE-TCC-MECH- 126 TCC VAF MECH Quality Management 25-Mar-13 28-Mar-13 08-Apr-13 22-Apr-13 Closed LBE-DLM-MECH- 127 MR. HARIKUMAR DAELIM VAF MECH Preservation 26-Mar-13 29-Mar-13 09-Apr-13 24-Oct-13 Closed LBE-TCC-MECH- 128 TCC PN MECH Piping 28-Mar-13 31-Mar-13 11-Apr-13 21-Apr-13 Closed LBE-TCC-MECH- 129 MR. NASSAR TCC PN MECH Coating/ Painting 28-Mar-13 31-Mar-13 11-Apr-13 23-May-13 Closed LBE-TCC-MECH- 130 MR. NASSAR TCC VAF MECH Preservation 30-Mar-13 02-Apr-13 13-Apr-13 23-May-13 Closed LBE-PSCL-MECH- 131 PSCL VAF MECH Tank 30-Mar-13 02-Apr-13 13-Apr-13 14-May-13 Closed LBE-PSCL-MECH- 132 PSCL VAF MECH Tank 30-Mar-13 02-Apr-13 13-Apr-13 14-May-13 Closed LBE-KCC-CIVIL-115 KCC VAF CIVIL Civil 01-Apr-13 04-Apr-13 15-Apr-13 13-May-13 Closed LBE-PSCL-MECH- 133 PSCL VAF MECH Tank 01-Apr-13 04-Apr-13 15-Apr-13 14-May-13 Closed LBE-ARCC-MECH- 134 ARCC VAF MECH Piping 01-Apr-13 04-Apr-13 15-Apr-13 8-Jun-13 Closed LBE-PSCL-MECH- 135 PSCL VAF MECH Tank 01-Apr-13 04-Apr-13 15-Apr-13 14-May-13 Closed LBE-AMA-CIVIL-116 MR. GERALD AMA VAF CIVIL Civil 02-Apr-13 05-Apr-13 16-Apr-13 15-Aug-13 Closed During the review of RFI Nol. 2690 (KCC), the following items were noticed. 1.Request was for sump pit #9 (SUM 0639) dated 03/03/13. 2. Attachment is sum 0906-dwg. No. A554-E-103-CV-DWG-C30-204. Rev. 2A. 3. Attachment for Test report is Sum 0632 dated 28/02/13. These conflicts in attachment were signed by sub-contractor and Contractor QC. To review all RFI including attachment prior to submission to Company QC group. Subcon: Correct attachment and test report to be submitted. PN: During routine inspection at TCC off-site fabrication facility, it was observed that fit-up and inspection of joints were completed 1 month before and still have no welding were performed on the pipes spools welding in common. Contractor must ensure prior to welding surplus to be welded & adjacent surplus, both inside & outside diameter of the pipe, for It was observed that during routine inspection on furnace F-1140, ARCC has been advised to bring DFI gauge during inspection phase but ARCC was performing the job without complying the procedure. It is violation against A554-E-103-CPA-GEN=PRO-036. Subcon: The DFI is not possible to check for applied mastic due to very thick 300mm. Just only WFT which was using by ARCC. During routine inspection at TCC off-site fabrication facility, it is observed that TCC quality personnel are not monitoring and implementing traveler's remark for fabricated spools. Violating spec. A554-E-103-QA- GEN-PRO-042., Para. 6.4.2. During Material Receiving of pipe spool at laydown yard observed that numerous pipe spools were exhibiting severe oxidation on internal area due to improper preservation, violation to RT6-ICS, Para. 2.19.3 & 5. Implement remedy action on subject matter. Daelim: Action has been taken. All pipes on wooden support. All ends were covered. It is found that acceptable and satisfactory. It is observed that roof plate to compression plate calculation for tank V-1425 and drawing # V-1425-103- 9004-01-215 rev.2. as per reply of Petrol Steel against the Sadara LBE #091 (of dated 27-2-13) reply of Engineering shall be followed but activity has been proceeded without engineering response. Fit-up of joints is not acceptable due to 12mm gap between compression plates and roof plates and due to conflict mentioned above. Daelim quality team must ensure the corrective action and preventive measures to avoid the discrepancies and delay in job. PN: During surveillance, it was noticed that Petrol Steel has kept the coated angles on the ground without wooden skids which caused damage to the coated tank anchor chairs stored in a very bad condition. Subcontractor: Corrective action was taken. Angles are keeping on the wooden skids. Daelim: During surveillance, it has been noticed that coated sumps for spent caustic storage tank, pad water tank & process condensate holding tank have been damaged due to poor handling and lifting execution. And coating defects (orange peels, pinholes & dirt inclusions) on the parent coating due to improper Subcon: Handling damages was rectified. Once completed before installation raise RFI for inspection. For tank 0500A already inspection done by Company Inspector. Another 3 tanks on process for RFI. Ref. RFI-MFC-DLM-PS-H-012,13,14 PN: Focus assessment was conducted for the installation of grounding pad for the transformer foundation at substation G-1121 and found out to be in compliance with project specification and standard. It is noted that Daelim & Petrol Steel inspectors are not doing inspection prior to Company which is a violation of Sched. "Q" Atta. IV, Para.#3. It is observed during inspection of material receiving of anchor chairs at tank V-1425 (RFI # MFC-DLM-PS-ME-215-329). This material released from workshop to site with post weld inspection acceptance but actually anchor chairs are only tack welded. Welding for them is already started at site but Daelim & Petrol Steel inspectors raised RFI with closed eyes. Daelim & Petrol Steel quality teams must perform inspections prior to Company and after their satisfaction they can raise RFI for Company inspection. Subcontractor: The anchor chair material has been offered for Contractor/Company inspection again by raising new RFI (RFI no. 136) and the same was found and acceptable. The rectification was carried out at the site by welding the anchor chair with required alignments. Preventive measures have been taken to avoid the recurrence of these kinds of discrepancies in the future. Daelim: During Fit-up inspection of Tank's anchor chairs for RFI No. MFC-DLM-PS-215-330 found the following discrepancies: Anchor chairs don't have part no. identification reflecting the cross reference of material release inspection reports. Some dimensions are not as per approved drawings and inspection report prepared by workshop inspectors. Anchor plate hole is not as per drawing. Pad plates & Rib plates are not prepared as per drawing no. V-1425-103-9003-18-215, Rev.3. It is noticed that Petrol Steel quality team is violating the inspection requirements and not raising RFI's for material receiving which are already arrived at site since 2 days before during surveillance at site, it was informed and suggested to Petrol Steel to raise RFI for (Tank V-500B) anchor chair material receiving prior to erect on shell but next day it has seen that they already fitted and tack welded with the tank shell without material inspection. Violation to schedule Q and ITP. It is observed that ARCC material (pipe spools) segregation and traceability in spool staging & RT area, is not proper and spools are mixed with some other project spools & materials. This is a violation of schedule Q Para. 4.2. Daelim quality needs to ensure proper segregation and traceability for Sadara pipe spools. Subcon: Spools/Materials were segregated and separate area and proper signage's were provided to avoid mixed up with other materials. (photos sent to DAELIM) It is found out that Petrol Steel welded the angles between the roof rafters of Tank V-1425 without material receiving and fit-up inspection. This is a repeated violation as per schedule Q & ITP. Daelim quality needs to ensure the quality requirements with corrective action and preventive measures. It is observed that Daelim & Petrol Steel quality team have a lack of interest for inspection responsibilities as repeated violations are in routine. Anchor chairs of tank V-500A are fitted with tank shell without material receiving inspection. This is a violation of schedule Q, att. IV, Para. no. 3. Daelim quality team needs t take corrective action & preventive measures. It is observed that Daelim & Petrol inspectors are raising RFI's without their inspection and at the time of Company inspection oftentimes job is not ready to inspect. Examples are RFI # MFC-DLM-PS-ME-215, 237, 238, 239, 352 & 353. This is a violation of schedule "Q" Attach. IV, Para. 1 & 3. Daelim Quality team needs to take corrective action and preventive measures. During inspection observed that on top of embedded plate of concrete girder beam of east-west pipe rack, El : 25200, 31-35A, A/AB, BB (Inspected 5 location) were showing inclination, level variation and improper installation of embedded top plate as per ISO drawing. A554-E-103-CV-DWG-S10-248 Rev.3 the elevation variance exceeded up to 23mm, this will cause uneven surface levels during installation of platform/gratings. Violation RT2S-5120-01. Daelim QA and engineering team shall verify and establish a remedy action with appropriate approved method in order to avoid any further discrepancy. Subcon: Joint survey by DAELIM, KCC and TCC surveyors was conducted and witnessed by its QC Inspectors respectively. Gathered AS-Built elevations of elevations of embedded plates is now under review of DAELIM Construction/Engineering team to establish corrective action. PN: Observed that TCC has installed pipe spools in an uncompleted structure at NS column:48 area. Daelim shall comply Sadara specs & requirements as per RT25-5120-01, Para. 3.4.2. PN: During routine inspection, it was noticed that TCC's storage coated pipes & spools after coating activities without proper protection between it. This caused damaged to the coating during lifting & transportation. Subcon: TCC Coating inspector will make sure that all painted pipes/spools are in a proper storage. Daelim: During surveillance, it has noticed that galvanized structure materials (T-section, Beams, U-channels & Angles) keeping in very poor storage without proper protection and left them in the ground without wooden skids, this cause coating damage. These materials located in East West pipe rack. It is violation against materials & equipment protection and preservation plan (RT-G-1CS). During surveillance inspection at substation G1120 & G1121, found out some materials are not properly protected, such as cement, CMU, etc. This is a violation to 625-4300-01, Para 3.1.1 and also observed that some CMU are scattered on some locations of building. Contractor was advised to backload some extra materials in order to maintain good housekeeping at site. And also needs provide proper protection & handling of the said materials. Subcon: Work in progress, completion date will be on 07 June 2013. The scattered materials shall be removed from the site. Page 15 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 30, 2014 DUE DATE Issued corrective action to Company Target Date S/N LBE NO. PID SUBCON/ CONTRACTOR VAF / PN LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason Company comment Approved Close LBE by Company STATUS CONTRACTOR'S CORRECTIVE ACTION PLAN LBE-AMA-CIVIL-117 AMA PN CIVIL Civil 03-Apr-13 06-Apr-13 17-Apr-13 14-May-13 Closed LBE-AMA-CIVIL-118 AMA VAF CIVIL Civil 03-Apr-13 06-Apr-13 17-Apr-13 05-May-13 Closed LBE-AMA-CIVIL-119 AMA VAF CIVIL Civil 03-Apr-13 06-Apr-13 17-Apr-13 23-Jun-13 Closed LBE-AMA-CIVIL-120 AMA VAF CIVIL Civil 03-Apr-13 06-Apr-13 17-Apr-13 28-May-13 Closed LBE-DLM-ELECT- 031 DAELIM PN ELECT Electrical 03-Apr-13 06-Apr-13 17-Apr-13 20-Apr-13 Closed LBE-ARCC-MECH- 136 ARCC VAF MECH Structural 04-Apr-13 07-Apr-13 18-Apr-13 21-Apr-13 Closed 1 LBE-AMA-MECH- 137 AMA VAF MECH Hvac 04-Apr-13 07-Apr-13 18-Apr-13 9-May-13 Closed LBE-DLM-MECH- 138 DAELIM VAF MECH Material 07-Apr-13 10-Apr-13 21-Apr-13 20-Apr-13 Closed LBE-TCC-MECH- 139 TCC VAF MECH Piping 08-Apr-13 11-Apr-13 22-Apr-13 22-Apr-13 Closed LBE-DLM-MECH- 140 DAELIM VAF MECH Quality Management 10-Apr-13 13-Apr-13 24-Apr-13 22-Apr-13 Closed LBE-DLM-ELECT- 032 DAELIM VAF ELECT Electrical 11-Apr-13 14-Apr-13 25-Apr-13 28-Apr-13 Closed LBE-DLM-ELECT- 033 DAELIM VAF ELECT Electrical 11-Apr-13 14-Apr-13 25-Apr-13 28-Apr-13 Closed LBE-DLM-MECH- 141 DAELIM VAF MECH Quality Records 13-Apr-13 16-Apr-13 27-Apr-13 18-May-13 Closed LBE-TCC-MECH- 142 TCC PN MECH Preservation 13-Apr-13 16-Apr-13 27-Apr-13 13-Jul-13 Closed LBE-TCC-MECH- 143 MR. NASSAR TCC VAF MECH Coating/ Painting 13-Apr-13 16-Apr-13 27-Apr-13 23-May-13 Closed LBE-AMA-CIVIL-121 AMA PN CIVIL Civil 14-Apr-13 17-Apr-13 28-Apr-13 22-Apr-13 Closed LBE-TCC-MECH- 144 MR. NASSAR TCC PN MECH Preservation 14-Apr-13 17-Apr-13 28-Apr-13 23-May-13 Closed LBE-ARCC-MECH- 146 ARCC VAF MECH Mechanical 14-Apr-13 17-Apr-13 28-Apr-13 13-Jul-13 Closed LBE-KCC-CIVIL-122 KCC PN CIVIL Civil 15-Apr-13 18-Apr-13 29-Apr-13 26-May-13 Closed LBE-DLM-ELECT- 034 DAELIM VAF ELECT Electrical 15-Apr-13 18-Apr-13 29-Apr-13 28-Apr-13 Closed Observed at Furnace area F-1250, ARCC structural team was assembling open structure members at site without proper protection. The hot dip galvanized materials were handled with improper method and kept directly to the. Most of the materials were damaged (coating) due to improper handling. ARCC shall store/handle the galvanized material properly and reduce the damage during erection and assembling at site. It is noticed that Daelim/Amana inspectors are not doing inspection prior to Company which is a violation of schedule Q, attachment IV, Para. 3., It is observed during inspection of HVAC galvanized dusts installation and volume damper inspection at switch gear room; G-1121, RFI # MFC-DLM-AMA-HV- 0013, 0014. Daelim & Amana Quality team must perform inspection prior to Company and after their satisfaction, Contractor/Subcontractor can raise RFI for the activity. During Material Inspection based on RFI-MFC-DLM-JNK-003 dated 4 April 2013 for Convection Crossover Pipe & Manifold at Lay down yard, observed that Daelim/ARCC Team were shifted in Material to site and partially installed/positioned at site. Daelim/ARCC material team has been repeating the same violation & challenging the Company quality programs, schedule Q and approved procedure. Violation of A554-E-103-QA-GEN-PRO-055, Para. 6, Sch. Q, sec. 3 Para. 3, sec 4, LBE 05, 23 & 84. During routine inspection/monitoring at ground flare area, it was noticed that the inside walls of sump 0380 has honeycombs at several locations. This deficiency shall be re-inspected after all the loose portion of aggregate has been removed by SADARA QC using the approved repair material. Subcon: Work in progress, completion date will be on 07 June 2013. The Honeycombs to be repaired and inspection to be conducted after repair. It was noticed during site monitoring that the two columns at 1st lift of the dilution structure being supported by a girder has congested rebar which made concrete not positive to enter the center of the columns. The reinforcing bars are all over the top and the 4 sides of the columns. Contractor to discuss with its Engineering team to revise the bar arrangement for constructability and will give better strength to the columns. Subcon: Congested rebar to be rectified to acceptable spacing PN: Contractor shall re-seal the cable ends of the cables after the on-reel cable testing with heat shrinkable, self sealing end caps to prevent the entrance of moisture into the cable as per 67D-0404-00, sec. 7.3. PN: During inspection @ Operator building, it was noticed that Contractor wanted to concrete the roof slab, girder & beams, including the wall & column one time only. Contractor was advised to submit Method Statement for concrete pouring of operator building simultaneously for Company revise & comment. During inspection at ground flare area for leak test for sump 0380, it was noticed that the bottom slab area has no more leaks. Upon further inspection, it was found out that there is no water inside the sump. The three sides have been previously inspected and the remaining water to check the bottom slab as agreed was not maintained. Contractor shall undertake proper preparation prior to inviting QG as required by ITP. Subcon: The leak test to be conducted again once the sump repaired During routine inspection on TCC facilities for pipe spools, it has been observed an incorrect coating thickness. The dry film thickness measurements for the final coat; average is 520 microns and the maximum dry film thickness, as per standard requirement shall be 325+ 20% microns. Reference: A554- E-103-QA-GEN-PRO-041 & G16S-0201-10. Subcon: As per paint manufacturer, there no problem with DFT average 520 microns for epoxy paint. Daelim: PN: During routine Inspection imitating XT end portion of cooling tower pumps (P09016& P0901 H).That newly casted lean concrete was already stamped for rubber installation in which only one day after casting and also no paper caring application had run done (as per construction standard)Construction was advised to take remedies arias concerning this issue. PN: During Surveillance at site on spent caustic storage tanks manholes flanges it has been observed that weld spotted stuck on the flange serrated surface due to inappropriate protection during welding activities. This is for information ,root cause & corrective action. Subcon: PSCL taken corrective action on that issue and also inform construction team to protect all manholes, flanges and serration area need to covered. Daelim: Referenced to LBE-E-032, the Contractor did not report the damage of the cable trays to the Company in timely manner which is a violation as per schedule G, attachment 11, section 14.3.16. Daelim: Overage, shortage, incorrectness, damage report (OSID) was initiated by Contractor Material department as part of Sched. "G". Report will issue to Company for closure of this LBE. It is found that Daelim welding inspector (Mr. C. Viswanathan) is not raising RFI's for Pre-welding & In- process welding inspections as per relevant ITP (SMITP-M-001-02) rev. 3 for tank's job at MFC Daelim/Petrol Steel tank area. Also, the welding on tank V-1425 roof rafter to roof started without fit-up & in-process welding inspection RFI. It is a violation as per schedule "Q" attach. IV, Para. 3. Daelim quality team must ensure the implementation of approved ITP. Company comments are still not incorporated in ITP, rev. 3. PN: It is observed that TCC (White Nile) Quality team needs to ensure the proper storage and handling of Pipe flanges and fittings with more concentration to void damages. Flange faces must be covered with suitable non-metallic blinds or covers during all the activities of fabrication, welding and transportation. Subcon: Noted all flange face protective with plywood will be provided new material receiving time. Inspector will make sure that all flange faces protected and place in proper way. All pipe spools which from transport NDT must be end closed and flange face cover with plywood. During routine inspection at TCC (White Nile) fabrication facility, porosity has been observed at fit-up joint for 12" pipe due to inadequate protection to weld area from wind & dust, violating Sadara specs. RT- -8S-6500-01, Para. 12.1 & A554-E-103-QA-GEN-PRO-056, Para. 16.1. During surveillance, it is found that Daelim Welding Inspector (Mr. Satish) was not available at off-site TCC (White Nile) fabrication since morning to 10:30 AM while the inspection time was 9:30 AM. It is violation per Sched. "Q" attach. IV, Para. 3. Daelim Quality team must ensure the availability of inspectors is full time at off-site fabrication facilities during on-going activities. During routine site visit, it was observed that some cable trays were damaged at the laydown yard due to an accident. These cable trays were hit by a vehicle, causing a physical damaged to these cable trays. This is a violation as per schedule G, attachment 11, sec. 14.2.5. Daelim: Contractor shall comply as per 67D-0404-00, section 7.3 After several periodic instructions it is observed that cylinders gauges and flow meters are not calibrated at off-site ARCC Fabrication WQT & Procedure qualification testing shops. It is a violation as per "Q" attach. If Para # 7.DAELIM and ARCC quality team must ensure the corrective action with preventive measures. Subcon: Calibration of cylinder gauges and flow meters are not possible. (ARCC already inquire to 3rd party laboratory) PN: During Concrete placement of vertical pump are the compressor are the inner casing hole where concrete was started to vibrated. It was noticed laser or that there is no support for the inner casing to placement floatation. This practice of fixing the support has been practice in the past painting of the same structure. But forget at this time. Contractors shall always repetitive work of this kind shall be treated as first time always to avoid repetition as first time always to avoid repetition of work (proactive). It was Found out During material Receiving and Cable Testing that the cables on cable drum nos. 30276544 and 30276544 and 30276799 were damaged on it's cable jackets. And cable drum nos.30276812 and 30276880 were also received without end cap. A repeated violation of Sched. G, Attach. II , sec.14.3.16 (SEE LBE # 033) on which contractor should report any damage to company without delay and in timely manner. The contractor should implement remedy action as per Sched. G attach. II, Sec.14.3.5. Daelim: For the damage cable, the OSID was already issued to Company by Contractor Material Department as part of Sched. "G"'s concerns and the disposition for repair will be by Vendor Supplier & Procurement. Page 16 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 30, 2014 DUE DATE Issued corrective action to Company Target Date S/N LBE NO. PID SUBCON/ CONTRACTOR VAF / PN LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason Company comment Approved Close LBE by Company STATUS CONTRACTOR'S CORRECTIVE ACTION PLAN LBE-ARCC-MECH- 145 ARCC PN MECH Piping 15-Apr-13 18-Apr-13 29-Apr-13 6-Jun-13 Closed LBE-TCC-MECH- 147 MR. NASSAR TCC VAF MECH Coating/ Painting 15-Apr-13 18-Apr-13 29-Apr-13 23-May-13 Closed LBE-ARCC-MECH- 148 MR. NOOR ARCC PN MECH Refractory 16-Apr-13 19-Apr-13 30-Apr-13 12-Sep-13 Closed LBE-ARCC-MECH- 149 ARCC VAF MECH Material 16-Apr-13 19-Apr-13 30-Apr-13 28-May-13 Closed LBE-ARCC-MECH- 150 MR. NASSAR ARCC VAF MECH Quality Management 17-Apr-13 20-Apr-13 01-May-13 Closed 25-May-13 Closed LBE-DLM-MECH- 151 DAELIM VAF MECH Piping 17-Apr-13 20-Apr-13 01-May-13 Closed 1-Jun-13 Closed LBE-PSCL-MECH- 152 MR. NASSAR PSCL PN MECH Coating/ Painting 17-Apr-13 20-Apr-13 01-May-13 23-May-13 Closed LBE-PSCL-MECH- 153 PSCL VAF MECH Tank 18-Apr-13 21-Apr-13 02-May-13 14-May-13 Closed LBE-TCC-MECH- 154 MR. NASSAR TCC VAF MECH Coating/ Painting 18-Apr-13 21-Apr-13 02-May-13 25-May-13 Closed LBE-TCC-MECH- 155 MR. NASSAR TCC VAF MECH Preservation 18-Apr-13 21-Apr-13 02-May-13 25-May-13 Closed LBE-AMA-CIVIL-123 AMA PN CIVIL Civil 20-Apr-13 23-Apr-13 04-May-13 14-May-13 Closed LBE-DLM-ELECT- 035 DAELIM VAF ELECT Electrical 20-Apr-13 23-Apr-13 04-May-13 13-May-13 Closed LBE-DLM-ELECT- 036 DAELIM PN ELECT Electrical 20-Apr-13 23-Apr-13 04-May-13 14-May-13 Closed LBE-AMA-CIVIL-124 AMA PN CIVIL Civil 21-Apr-13 24-Apr-13 05-May-13 14-May-13 Closed LBE-ARCC/TCC- MECH-156 MR. AMIN ARCC/TCC VAF 2 MECH Mechanical 21-Apr-13 24-Apr-13 05-May-13 20-Jan-14 Closed LBE-TCC-MECH- 157 TCC VAF MECH Piping 22-Apr-13 25-Apr-13 06-May-13 25-May-13 Closed LBE-TCC-MECH- 158 TCC VAF MECH Preservation 22-Apr-13 25-Apr-13 06-May-13 13-Jul-13 Closed LBE-DLM-ELECT- 037 DAELIM PN ELECT Electrical 25-Apr-13 28-Apr-13 09-May-13 28-Apr-13 Closed LBE-DLM-INST-038 DAELIM PN INST Preservation 25-Apr-13 28-Apr-13 09-May-13 13-May-13 Closed During Material Inspection of convection module F.1220-1 observed that numerous serious weld defect occurred on Module: i.e. : worm hole, porosity, incomplete fusion, slag inclusion, spatters etcand placed on position: Daelim Eng.: & QC Team shall verify the root cause of discrepancies and take remedy action on subject matter. Subcon: Contractor already forwarded and addressed the issue to the Construction team to send the report to the Vendor/Manufacturer (JNK) with photos. (By DAELIM) During notice inspection at F# 1250; RFI # MFC-DLM-ARCC-H-0242 it has been noted that there was no ARCC QC inspector in prior to SQIT.As per SMITP-H-100-032 the level of inspection for sub contractor QC Inspector in hold point (H). Standard violation # 106 was entered before related this practices. Reference # A554-E-103-QA-GEN-PLN-033 Subcon: ARCC raised new RFI (RFI# MFC-DLM-ARCC-H-0246) Final inspection was conducted by ARCC approved painting inspector and witness & accepted by contractor & company inspector. During Fit up Inspection of :(IP: 241502.24"HCF) process line for T.2410.observed that 24"dia 4 EA of end spools were welded with end cap for Hydro Test purpose. The activities were conducted without inspections performed by Daelim and company Quality team. Contractor must perform Inspections and test in accordance with the approved ITP identifies test and Inspections. Violation of Sched.: 'Q' Sec. IV: 3.7 and ITP - A554 - E103 - QA - GEN - PLN - 046. Daelim: The end Caps of 24" dia pipe were cut. After proper surface preparation. The end caps were fit-up and welded as per approved procedure. The line was Hydro tested. It found acceptable, after hydro test. The end caps were cut and line were installed properly. PN: During pre- Cleaning Inspection (Prior to Installation of Pipe spools of Pipe Rack) observed the exhibiting sever oxidation on internal aria of pipe spools. Daelim,TCC & ARCC shall establish a appropriate method for internal cleaning and Make sure any forging substances dropped on spods Refer SADARA specification.G4S-0210-1 Subcon: If required, TCC will provide foam dump for internal cleaning of pipe spools. ARCC to provide a dry air filter to make sure that the air to be use for internal cleaning is dry & clean. During routine inspection on TCC facilities for pipe spools, it has been observed that dust inclusions defect on the finished coat(silicon coat) due to blowing the dust during vehicles and fork lift movement and wind during coating activities since the aria close to painting workshop. This is for information & Corrective action. Reference .A554-E-103CPA-GEN-PRO-041 & RT16S-0203-06. Subcon: The pipes & spools were re-blasted on 09 May 2013 and repainted. To prevent dust in future, the entire area is sprayed by water and aggregates are poured. Daelim: PN: During Surveillance it is found that following refractor. Material are expiring room stored @ the Daelim laydown and ARCC laydown yard.(I) - Refractory material cost *L-135 shipment no.MFC - 19 will be expired on 24th April 2013. (II) - Refractory material cost F-50 G3 Shipment no MFC - 19 WILL BE EXPIRED ON 23 rd. April 2013. (III) - Refractory material cost M / W -144 Shipment no MFC - 19 will be expired on 07 'the' May 2013.Daelim and Subcontractor Quality must ensure to avoid the use of expired material and to shift it in Quarantine area upon expiry. Contractor: During Castable application, Subcontractor are maintain a log sheet in which material expiry date is also getting noted and recorded. Further any expiry material during pre-application inspection shall be segregated. So far, all materials have been used which where shelf life. Subcontractor: ARCC will monitor the expiration of the refractory materials & will not be used. PN: As discussed last weekly Quality meeting, The contractor shall store are 96 cable trays to quarantine aria as these cable trays were already subjected to mechanical stress and lost its integrity to hold the load requirement as per C7D-0322-00 PN: During surveillance inspection at operator building for concreting of RC wall & columns, it was noticed that some presence of laitance along perimeter beam and some portions of perimeter RC beam the concrete level up to the bottom portion of beam in which not in accordance with M/S & preservation conducted by Amana. Contractor was advised to do chipping some excess concretes and remove of laitance no to apply paint to rebar with laitance, ensure all cements must be properly implemented by the Contractor prior to submit RFI. It is found that weld rejection sate of ARCC (of welders) and TCC (03 welders) has been exceeded than 5% while is a violation as per Sched. "Q" all.iv,para # 3.9 & A554-E-103-GEN-PRO-056 Para 19.2.Daelim quality team must ensure the corrective action and preventive measures. Subcon: ARCC Quality & Welding Team to conduct presentation to SADARA and DAELIM QA/QC Team for root cause of High rejection, corrective action and preventive measures. Implementation already done at fabrication shop and rejection rate is slowly going down. TCC Tool box and Presentation training program with welders done. Rejection rate slowed down and continue training program with welders is on-going. During Surveillance it has been noticed TCC contractor keeping coated pipes & spools carelessly without proper protection (padding) this cause coating damage. It is violation against motionless & equipment protection & preservation plan (RT-6-ICS). Subcon: Corrective action has been taken and conducted tool box meeting regarding the proper handling of materials using proper padding on contact point. Daelim: PN: During surveillance/monitoring inspection at roof slab of substation G1121, concerning installation of 8 plywood prior to installation of EPDM for water proofing works. It was observed that some installed plywood are uneven and some portions are with gaps. Contractor was advised to take corrective action on the issue prior to submit RFI. Display of the Proactive Notification, Given by the company last weekly meeting for quality (Apr.14.2013), That the damaged cable trays shall be stored in the quarantine area. The contractor did not follow and they just serrated the damaged cable trays bot still lying the same aria watch is a violation as per RT-4-105 Sec 2.2.11. Daelim: As agreed in construction meeting between Company & Contractor, the proposal for the damaged materials shall be surrounded by warning tape and provide with Tag "Do not Used" for awareness of issuing/releasing the damaged material. PN: During Surveillance at roof for spent caustic Storage Tanks ( V-0540 A & V-0500 B) it has been noted that u beam / u-shopped of umbrella roof type was fitted without blast & coating for coiners,bolts,riverts & roofter side. This is for information & corrective action. Subcon: U-beams & channels are using for roof lifting purpose only. Once lift the roof, temporary materials are removed by grinding. Daelim: It is found that petrol steel welder (ice# 315, w# 759 was welding on the tank V-500 B without shielding which is a violation of RT8S-66500-01 PARA # 1201 and A554-E-103-QA-GEN-PRO-056 Para # 16.1,Also find that Daelim inspectors was not available at site and petrol steel welding inspector was sitting in their site office. Daelim quality team must ensure the proper shielding availability of inspectors at site. During routine inspection of TCC blasting & coating facilities for pipes & spools, it has been observed that dart & dust inclusion defect are found on the finished coat of 80" pipes due to stored very close to ground during coating activities result in adhered dirt & dist. on srfoce.This is for information root cause analysis and corrective action. Reference :-A554-E-103-QA-GEN-PRO-041& G16S-0202-10. Subcon: Corrective action has been taken and Pipes was inspected and released. RFI# MFC- DLM-TCC-H-097 Daelim: PN: Contractor shall provide for the base copper grounding cable at cooling tower area exposed to mechanical damage. Provide to wooden box to cover all grounding cable. During routine inspection at gate no. 18 for fit-up & post-weld inspection of 36" LTU pipe, it was observed that portable oven used for storing LTCS electrodes were not maintained at minimum temperature of 65c, violating SADARA Specs. A554-K-PRG-CE-SPC-DES-009, att. 1 Subcon: Electrode are disregard and welding inspector will make sure required temperature for portable oven. During surveillance at TCC fabrication facilities it has been noticed that TCC contractor keeping galvanized structure materials carelessly on the ground without proper protection and sand rocked up it. It is violation against materials & equipment protection & preservation plan (RT-6-1CS). Subcon: Noted, action will be taken. All galvanized structure materials preserved properly. PN: During material receiving inspection of materials and equipment, all found damaged materials must be isolated and quarantined immediately until corrective action is applied. Ref. Doc. No. RT-6-1CS, sec. 2.2.11. Page 17 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 30, 2014 DUE DATE Issued corrective action to Company Target Date S/N LBE NO. PID SUBCON/ CONTRACTOR VAF / PN LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason Company comment Approved Close LBE by Company STATUS CONTRACTOR'S CORRECTIVE ACTION PLAN LBE-DLM-MECH- 159 DAELIM VAF MECH Quality Management 27-Apr-13 30-Apr-13 11-May-13 18-May-13 Closed LBE-DLM-MECH- 160 MR. AMIN DAELIM PN MECH Quality Records 27-Apr-13 30-Apr-13 11-May-13 13-Oct-13 Closed LBE-TCC-MECH- 161 TCC VAF MECH Quality Management 27-Apr-13 30-Apr-13 11-May-13 25-May-13 Closed LBE-TCC-MECH- 162 TCC VAF MECH Mechanical 27-Apr-13 30-Apr-13 11-May-13 25-May-13 Closed LBE-DLM-MECH- 163 DAELIM VAF MECH Refractory 27-Apr-13 30-Apr-13 11-May-13 2-May-13 Closed LBE-AMA-CIVIL-125 MR. GERALD AMA PN CIVIL Civil 28-Apr-13 01-May-13 12-May-13 16-Oct-13 Closed LBE-ARCC-MECH- 164 ARCC VAF MECH Piping 29-Apr-13 02-May-13 13-May-13 13-Jul-13 Closed LBE-DLM-MECH- 165 DAELIM VAF MECH Quality Management 29-Apr-13 02-May-13 13-May-13 Closed 12-Jun-13 Closed LBE-DLM-MECH- 166 DAELIM VAF MECH Piping 29-Apr-13 02-May-13 13-May-13 18-May-13 Closed LBE-DLM-MECH- 167 DAELIM VAF MECH Piping 29-Apr-13 02-May-13 13-May-13 6-Jun-13 Closed LBE-DLM-MECH- 168 MR. AMIN DAELIM VAF MECH Mechanical 29-Apr-13 02-May-13 13-May-13 13-Oct-13 Closed LBE-PSCL-MECH- 169 PSCL VAF MECH Preservation 30-Apr-13 03-May-13 14-May-13 14-May-13 Closed LBE-AMA-MECH- 170 AMA VAF MECH Quality Management 30-Apr-13 03-May-13 14-May-13 13-May-13 Closed LBE-ARCC-MECH- 171 ARCC VAF MECH Refractory 30-Apr-13 03-May-13 14-May-13 19-May-13 Closed LBE-TCC-MECH- 172 TCC VAF MECH Quality Records 03-May-13 06-May-13 17-May-13 25-May-13 Closed LBE-TCC-MECH- 173 MR. NASSAR TCC VAF MECH Coating/ Painting 04-May-13 07-May-13 18-May-13 25-May-13 Closed LBE-TCC-MECH- 174 MR. NASSAR TCC VAF MECH Preservation 04-May-13 07-May-13 18-May-13 Closed 9-Jun-13 Closed LBE-DLM-CIVIL-126 MR. JERRY DAELIM PN CIVIL Civil 06-May-13 09-May-13 20-May-13 06-Oct-13 Closed LBE-DLM-CIVIL-127 MR. JERRY DAELIM VAF CIVIL Civil 06-May-13 09-May-13 20-May-13 01-Oct-13 Closed During routine inspection at TCC-2 Fabrication facility, it is observed that only one TCC Welding inspector is deputed for welding inspection & activities of 24 welders of TCC-2 Fabrication which is a violation against Sched. "Q", attach. VI, table VI-1. During routine inspection at TCC NASCO Fabrication facility, it is observed that rebake oven used for electrodes do not have temperature gauge to continuously monitor the temperature, which is a violation against SADARA specs. A554-K-PRG-CE-SPC-DES-009, Para. 3. During surveillance, found that the Refractory Material missing the ambient temperature was 34c and found that during mixing material, the water temperature was up to 34c instead of 10c to 32c as per SADARA project specification RTSAES-N-110 and G8S-1540-01. Daelim Quality team must ensure that the Sadara requirements are implemented. It is noticed that Daelim quality team released a welding inspector without notifying the Company in advance. It is violation as per Sched. "Q", section 5.14. Contractor must advise the Company representative at least 30 days in advance of scheduled absences or changes to personnel and quality coverage or within 72 hours. Daelim quality must ensure the corrective action and preventive measures. Subcon: Noted action will be undertaken. All galvanized structure materials preserved properly. PN: In a format acceptable to the Company representative, Contractor must have a records retention system which enables the identification, retention and retrieval of all construction phase inspection records at all times. Daelim quality needs to ensure for all records of Daelim & subcontractors. Contractor: Noted and all related information will be collected and keeping with tracking system. Found that Petro Steel Tank's area welding consumables' control is improper and electrode holding oven temperature was 80C instead of 120. Another consumable store at same site was having holding oven & some portable quivers with some have Hydrogen electrodes inside there without power connection. It is a violation as per RT85-6500-03. Attach.1 corrective action with preventive measures is required. Found that AMANA HVAC Inspector not available at site during HVAC Duct and damper installation activities and inspection time since last month 25 April-2013. Corrective action with Preventive measures are required. Schedule "Q" AH IV para #3. During Surveillance inspection at MFC ARCC Laydown yard and Furnace area found that the Refractory Castable material "Cast F 50 G3" was stocked at Furnace area. As per Manufacturing Data Sheet. It was manufactured on April 30, 2012 and self-life is 06 months only. Daelim is advised to shift the subject material to Quarantine area after expiration date. Daelim advised to Subcontractor ARCC/R.B. Hilton to avoid the usage of expired material. It is noticed that I.T.P. for Welding of on plot Piping Transmittal #IK-MFC-T-DJ-CJ-QM-0500, was rejected on 14th Feb.2013 but welding activities and inspection are in routine. It has been reminded several times to Daelim Quality but still it is not revised and resubmitted for Company review and approval. Daelim Quality team must ensure that all ITP's and procedures being used approval by Company. Ref. ITP # SMITP-W-011-01 Rev.0. Company Transmittal Ref. IK-MFC-CJ-DJ-CM-0708. SCH. "Q" Attached !V Section 1. During pre-cleaning Inspection of Pipe Spools at N-S Pipe Rack CL-3 area observed that following discrepancy's. * Wooden planks stocked on 20" spools. * Spools Beveled were dent and damaged. * Daelim and Subcontractor Q/C Personnel shall be verify and accepted all scheduled Inspection activities provide to offer RFI to Company violation of Schedule "Q" IV: 3.7 and cleaning procedure. Daelim: Proper cleaning is done by TCC and damaged pipe has been rectified. Inspection had been done and accepted. (Ref. RFI # TCC-PIP-0042 at 02 may 2013). Proper Inspection shall be carried out prior to Company Inspection. Found repeated violation that Daelim Welding Inspector not available at off-site ARCC Fabrication shop during welding activities and inspection time since morning 06:00 a.m. to 10:30 a.m. Corrective action with preventive measures are required. Ref. Violation : Schedule "Q" attached IV para #3. RFI-#MFC- DLM-ARRCC-PIP-WE-0127 (Rejected) Daelim: After the long shift of Daelim QC not available only at 6:00AM to 10:00AM. In this regard, Subcontractor SADARA approved QC available at shop. However, Contractor will change to Daelim QC available time. In addition, Contractor will assign one (1) QC Welding Inspector as soon as earlier time. PN: During surveillance/monitoring inspections at roof slab of Substation G-1121, regarding installation of EPDM Membrane. It was observed that some installed EPDM Membrane are not properly paste to plywood and cause some irregular/plot of surface. Contractor was advised to take corrective action concerning this issue, prior to proceed to other areas. Subcon: The portion of EPDM which is irregular/plot of the surface was not accepted has been rectified/repaired. The repair activity has not been accepted by Company but re-work shall be started rectify repairs on 15.nov.2013. It is found that ARCC Pipe Spools Preservation, Segregation & Traceability in RT areas is not proper and SADARA Pipe Spools are mixed with some others Project spools. This is a repeated violation like SADARA WBE #134. Some Pipe Spools and their Flanges were also directly placed on the ground. Also found that a heavy duty 36'' Flange is damaged a little on its edge of circumference due to improper staging of Pipe Spools with each other. Relevant Daelim or ARCC Piping Inspector might be revoked due to repeated violations. Proper corrective action and preventive measures are required. Location - ARCC Offsite Fabrication Shop Ref. Schedule Q attached # IV para #4, RT-6-ICS-Rev.3, Para # 2.19.17, 2.16 Subcon: 1. Presently ARCC RT Area was divided into two areas to separate SADARA pipe spools to pipe spools from other project (photos sent to DAELIM) 2. Tag/mark with the respective drawing & spool number was provided on all SADARA spools to serve as identification. Currently all SADARA spools are properly stored at ARCC-SADARA staging area with end cover and every flanges face are protected with wood cover. (photos sent to DAELIM) 3. For the 36 inches flange the damage is minor/acceptable which is outside or not on the serration area. It is found that Contractor Welding Inspectors was not available at ARCC Fabrication shop during welding activities from morning 06:00 a.m. to 10:00 a.m. Similarly it is also found that Piping Inspectors of Daelim was not available at inspection time at Daelim laydown TCC Facility even I have been waiting their 40 minutes. These are violations of Schedule "Q" Attached IV Para #3 Corrective Action & Preventive measures are required. Daelim: Daelim has been taken corrective action against this issue, currently one (1) assigned QA Welding Inspector for each shift at the ARCC Fabrication shop. Furthermore, Daelim QC will be available for every activity in accordance with ITP. QC will not allowed to absent prior to inform concern SADARA Inspector. PN: During inspection of Dilution Structure on 24/04/13, two sets of anchor bolts at GL 2 & 3 E at DL 25.63 had wrong orientation. Contractor shall ensure that survey has been done accurately and verification of the Subcontractor's surveying activities are undertaken independently to avoid recurrence. Daelim: Daelim surveyor to check and submit survey report to ensure correction of the Subcontractor report. Despite discussion and on-going verbal instruction to provide protection to all exposed TPER, Contractor still has not provided sufficient and acceptable protection to avoid damage TPER. This is a violation of Document No. A554-K-PRG-CV-SPC-C20-047 Rev.a that states "suitable guards shall be provided to protect exposed projecting edges and end of partially embedded water stops when concrete has been discounted. Daelim: Attachment will show protective action being undertaken by the Contractor for exposed TPER to prevent from damage. Wooden box installed as protection to damage. Further protective action is continuously being done for exposed TPER. Concerned subcontractors in areas with exposed TPER has also been advised to undertake proper protective measures for the TPER. During Inspection of TCC NASCO fabrication facility, it was observed that pre-heat requirements are not being followed respect to WPS, violating RT85-6500-01, para 6 & A554-E-103-QA-GEN-PRO-056 para 12.1 requirements. Moreover NASCO facility do not have source for pre-heat prior to welding. TCC has been started installation of grinder beam on main column at N-S Pipe Rack area without surface preparation and coating of Gusset plate welded area. TCC shall carried out proper cleaning and coating of for damaged Hot dip Galvanized embedded plate and gusset plate welded area with approved coating repair procedure prior to commence further installation activities. Violation of RT-25- 2120 and procedure of A554-E-103-QA-GEN-PRO-0021. Subcon: During installation of gusset plate welding will be grinded properly by removing the galvanized material damaged galvanized and welded area will be touched up with approved Coating repair procedure. Daelim: Touch-up repair procedure for galvanized structure materials should be submitted to the Company for review and approval. It has been noted that too many locations on the shell and pipelines of Splitter # T-2410 has been damaged due to transportations and handling. This is for information & corrective action. It is violation against materials & equipments & protect preservation plan (RT-6-ICS). Subcon: Noted, tool box meeting will be arranged with rigger for proper handling of painted pipe spools. TCC Coating/Painting Inspector will submit minutes of tool box. Damage area will be rectified as per approved Touch-up and repair procedure. Daelim: Damage area will be rectified as per approved touch-up and repair procedure. Page 18 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 30, 2014 DUE DATE Issued corrective action to Company Target Date S/N LBE NO. PID SUBCON/ CONTRACTOR VAF / PN LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason Company comment Approved Close LBE by Company STATUS CONTRACTOR'S CORRECTIVE ACTION PLAN LBE-AMA-CIVIL-128 MR. GERALD AMA PN CIVIL Civil 06-May-13 09-May-13 20-May-13 24-Sep-13 Closed LBE-TCC-MECH- 175 TCC VAF MECH Piping 06-May-13 09-May-13 20-May-13 25-May-13 Closed LBE-ARCC-MECH- 176 MR. NASSAR ARCC VAF MECH Coating/ Painting 06-May-13 09-May-13 20-May-13 9-Jun-13 Closed LBE-DLM-MECH- 177 DAELIM VAF MECH Quality Management 06-May-13 09-May-13 20-May-13 01-Jun-13 Closed LBE-TCC-MECH- 178 TCC PN MECH Quality Records 08-May-13 11-May-13 22-May-13 8-Jun-13 Closed LBE-ARCC-MECH- 179 ARCC VAF MECH Quality Management 11-May-13 14-May-13 25-May-13 13-Jul-13 Closed LBE-AMA-ELECT- 039 AMA PN ELECT Electrical 13-May-13 16-May-13 27-May-13 04-Jun-13 Closed LBE-TCC-MECH- 180 MR. AMIN TCC VAF 2 MECH Piping 13-May-13 16-May-13 27-May-13 Disagreed (23/05/13) lack of skill, action not acceptable (25/05/13) 14-Mar-14 Closed LBE-ARCC-MECH- 181 ARCC VAF MECH Refractory 13-May-13 16-May-13 27-May-13 18-May-13 Closed LBE-KCC-MECH- 182 MR. NOOR KCC VAF MECH UG-RTR 13-May-13 16-May-13 27-May-13 Closed 1-Jun-13 Closed LBE-DLM-MECH- 183 MR. HARIKUMAR DAELIM PN MECH Piping 13-May-13 16-May-13 27-May-13 Closed 23-Oct-13 Closed LBE-ARCC-MECH- 184 ARCC PN MECH Structural 13-May-13 16-May-13 27-May-13 Closed 10-Jun-13 Closed LBE-ARCC-MECH- 185 ARCC VAF MECH Mechanical 13-May-13 16-May-13 27-May-13 Closed 13-Jul-13 Closed LBE-TCC-MECH - 186 TCC VAF MECH Piping 13-May-13 16-May-13 27-May-13 Closed 1-Jun-13 Closed LBE-KCC-CIVIL-129 KCC VAF CIVIL Civil 15-May-13 18-May-13 29-May-13 24-Jun-13 Closed LBE-DLM-INST-040 MR. SHABIRUL DAELIM PN INST Material 15-May-13 18-May-13 29-May-13 15-Sep-13 Closed LBE-DLM-ELECT- 041 DAELIM PN ELECT Electrical 15-May-13 18-May-13 29-May-13 02-Jun-13 Closed LBE-KCC-MECH- 187 MR. NOOR KCC VAF MECH UG-RTR 15-May-13 18-May-13 29-May-13 2-Jun-13 Closed LBE-TCC-MECH- 188 MR. NASSAR TCC VAF MECH Coating/ Painting 15-May-13 18-May-13 29-May-13 28-May-13 Closed During routine Inspection at TCC NASCO Fabrication facility, it was observed that flange facing on all piping or not protected at all times during fabrication & construction activities, violating SADARA Specification RT-6-ICS Para 2.16 & 2.19.6 During inspection at painting fabrication equipment at ARCC Fabrication shop prior to close-out NCR- ARCC-MECH-008, it has been observed that equipment's used for blasting of pipes & spools were not calibrated. Violating SADARA Specification A554-E-103-QA-GEN-PRO-041. Contractor advised to verify & attached calibration certificates prior to Company inspection. Subcon: Equipment used at ARCC Fabrication shop were sent to Calibration Laboratory currently all Equipment are Calibrated and certificates were provided. Final Inspection for ARCC Painting shop facilities was done and accepted (Refer to RFIT # MFC-DLM-ARC-H-0293) Found that Daelim Welding Inspector not available at MFC Daelim Laydown TCC activates. Corrective action with preventive measures are required. Reference Sch. Q Attach. IV Para # 3. PN: During surveillance/monitoring inspections at roof beam of Substation G-1120, some locations of anchorage are not yet installed as per IFC Drawing, in this regards please check properly the detailed drawing for the said anchorage. Contractor was advised to take corrective action concerning this issue, prior to re-inspection. Subcon: Anchorage installed and inspected by SADARA. PN: During Material Receiving Inspection observed that numerous Quality of defective Pipe Fitting (A420/420A) 2" 90 Shedule:40 Elbow found at Laydown Yard. Those Material are to be placed on hold and placed to Quarantine area for further evaluation by Third Party (HDE) to asses to Eastern of damage. Daelim shall be released the subject Materials for Fabrication until get final acceptance by Company/Third Party. Contractor: All the damage materials were shifted to quarantine area. A list has been provided. OSI & D was issued to the Vendor. The subjected material will be replaced. PN: During surveillance at Furnace #1250 it has been observed spot corrosion in different locations of galvanized structure. This is for information, root cause analysis & corrective action. Subcon: ARCC QC & DAELIM QC conduct investigation on installed packer plates with corrosion and the initial agreement for correction is to clean the affected areas and apply touch up paint using applicable painting system (RFI to be endorsed to DAELIM) During surveillance at Furnaces it has been observed that all galvanized guide plate of concrete pedestal has been rusted, therefore SQIT is request to touch-up and repair all rusted areas before installation. This is for information, root cause analysis & corrective action. Subcon: Surface preparation inspection was completed and accepted with RFI # MFC-DLM- ARCC-H-370-A. Primer coat for final inspection tomorrow 19 June 2013. LBE 185. to be closed tomorrow after final inspection of primer coat. Found entirely wrong Fabrication at TCC facility #1 for 48" Flange to pipe, instead to resolve the ovality problem, two helpers grinding the 10mm thickness of the pipe from one side of the joint. Two joints were observed with the same condition. Pipe spools were also not having any identification for Drawing or joint numbers. Daelim Inspection team must ensure the quick corrective action with preventive measures. Violation Reference TRS-6500-01 Para # 5.3 (a) Sch. "Q" Attach. IV Para #4. Subcon: 48'' pipe sch. Xcs thickness is 12.7'' only. After fit-up inspection accepted by TCC Piping Inspector RFI will be for Daelim/Company. During fit-up of large dial pipe ovality measured and divided equally to all around dia-inch. As per SADARA/Daelim/TCC Tool Box meeting in work shop 1, all Fabricators, Fitters and Supervisors were advised regarding the mismatch/HI-LO fit-up. During surveillance inspection at MFC F-1140 Gas Furnace area found that Refractory Castable Material (F-50-G3) was stocked in area. As per manufacturing data sheet. It was manufactured on April 30, 2012, Self-;if is one year only. Daelim is advised to shift the subject material to Quarantine area. Daelim advised to Subcontractor R. B. Hilton to avoid the usage of expired material. During surveillance, it is noted that the Daelim Subcontractor (PTS) carried out U/G five water FRP joints preparation and fit up without informing Company inspection team. Found that above activity was on-going without presence of any Contractor & Subcontractor QC Inspectors. Found that FRP (eights joints were already completed and further fit-up was ongoing also. It is violation as per Schedule "Q" attachment IV section 3 and A-554-E-103-QA-GEN-PRO-008. Reference pictures are also attached. Daelim: The Contractor Daelim issued RFI to the Company Inspection Department for all fit-up joints which is KCC done fit-up on the site. And strictly inform to Subcontractor that before they start any kind of activity they must be inform Daelim/Sadara Inspection which joints is already done laminations. Contractor will be issue RFI> PN: found that Sprit levels are not calibrated at all the Fabrication facilities under the Daelim Subcontractors. Some are giving false readings and not matching with each other's measurements. It is observed during Flange to pipe Fit-up inspection at TCC Fabrication Facility # 01. One Sprit level was showing misalignment while the other shown acceptable alignment. So Daelim have to ensure that all measuring and testing equipments or tools are calibrated. Subcon: Noted, all measuring tools will be calibrated soon. During surveillance inspection at Furnace area observed that following serious quality violation is on- going at Construction site. 1) ARCC is carried out Pipe Fabrication installation and welding activities at site without Piping Quality Inspector at site. 2) One (1) Mechanical Inspector is not sufficient to control this on-going activities as per Manpower ratio as specified in Schedule "Q" Requirement. 3) Quality Supervisor not yet assigned at site. A minimum of one (1) QC Supervisor shall be assigned for each position if is number of workers/QC Personnel performing the activities is specified in Sched. Q. A clear violation of Sched. Q attachment IV. Subcon: For Item (1) Mr. Albert Bumal-o (ARCC Approved Piping & Welding Inspector) was utilized as piping inspector and currently performing site piping inspection activities. Item ((2) Presently our mechanical inspector is still sufficient base on schedule Q requirements Ratio 1:25 actual manpower at site for mechanical works is 19 workers including foreman, 1 additional mechanical inspector will be mobilized @ site on June 8, 2013 in preparation with rotating equipments works. Item (3) Currently ARCC have 2 approved supervisors 1 for Structural and 1 for Mech./Piping for welding QC supervisor already requested CV to be submitted. PN: During routine site visit, it was noticed that the expansion bolt installed for the 2.5 MVA Transformers at Substation G-1120 were only four (4) expansion bolt each while it shows in the vendor drawing that six (6) expansion bolt shall be clarify with the vendor if this installation is acceptable. PN: During routine site visit at Furnace area, it was noticed that the Contractor is installing support for the Expansion Splice Plate on one side only. The Contractor shall follow the installation of support for the expansion Splice Plates as per NEMA VE-2 Sec. 4.3.2 and figure 4.12. Daelim: During the last meeting dated 28 May 2013, it was discussed that Supports will be provided per standard, 2 feet distance from the splice plates as well as from the joint expansion plate. Subcon has already been informed regarding the issue. During inspection, it was noticed that the Daelim Contractor (KCC) carried out the Hydro Test of UG/ fire water system 1401 Area-A-Unit-S2- (Hydro Test Package #0720). After 24 hour pressure holding found that pressure has been dropped and caused the test failure. Test must be carried out again ensuring that SADARA requirements are fulfilled. Violation reference: A554-E-103-QA-GEN-PRO-008 and G45- 6423-01 It has been noticed that, TCC subcontractor has been applied the primer coat on weld joints for 20 pipes & spools without RFV from the company (Sadara), this is violation against Sadara General Requirements for Pressure Testing (A554-O-PRG-QA-GEN-PRO-014 Sect.6.1). This is for information, root cause & corrective action. Subcon: Subcontractor assured that no more painting on weld area. TCC get reply MFC-T-DJ-TC- CM-0591. During routine Inspection at TCC NASCO Fabrication facility, it was observed that all fabricated pipe spools &assemblies are kept directly on ground & pipe openings or not protected from entry of sand & foreign matter, violating SADARA Spec. TR-6-ICS para 2.19.17. Subcon: Noted and one group assigned. All pipe end covers and flange face protection. During surveillance/monitoring inspection at E-2070 Pedestals north side of common compressor, it was observed that concreting works for this structure has no slump & temperature testing has been done by third party. The transit mixer used are the following : (TM #204, 206, & 210) This is a violation to RT25- 3001-01 Para 3.6.2 (Table 7) & schedule "Q" Quality requirements para 1.3. In this regards, Contractor was advised to take corrective action concerning this issue, in order not happen again in other areas. Subcon: Anchorage installed and inspected by SADARA. Daelim: Contractor will send letter to third party regarding the issue and will advise that slump and temperature testing shall be limited to provisions stated in concrete specification RT25-3001-01 para 3.6.2 (table 7) but also maybe required anytime during concreting works by any contractor QC personnel or by SDARA SQIT. PN: During material receiving of Skid package compressor C-1601 AB cracked Gas Compressor CR- 2301 CR2 missing serial numbers Purchase Order numbers on the data sheets. Contractor provide revised data sheets during pre-commissioning. Daelim: Compress packages C-1601 & C-2301 was already coordinated to Vendor regarding the incomplete SN on data sheet. Contractor will inform Company once the Vendor response. Page 19 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 30, 2014 DUE DATE Issued corrective action to Company Target Date S/N LBE NO. PID SUBCON/ CONTRACTOR VAF / PN LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason Company comment Approved Close LBE by Company STATUS CONTRACTOR'S CORRECTIVE ACTION PLAN LBE-DLM-ELECT- 042 DAELIM VAF ELECT Electrical 19-May-13 22-May-13 02-Jun-13 27-Jul-13 Closed LBE-DLM-MECH- 189 DAELIM PN MECH Piping 19-May-13 22-May-13 02-Jun-13 8-Jun-13 Closed LBE-ARCC-MECH- 190 ARCC VAF MECH Refractory 19-May-13 22-May-13 02-Jun-13 23-May-13 Closed LBE-DLM-MECH- 191 DAELIM PN MECH mechanical 20-May-13 23-May-13 03-Jun-13 24-Jun-13 Closed LBE-AMA-CIVIL-130 MR. GERALD AMA VAF 1 CIVIL Civil 21-May-13 24-May-13 04-Jun-13 24-Apr-14 Closed LBE-AMA-CIVIL-131 AMA VAF CIVIL Civil 21-May-13 24-May-13 04-Jun-13 06-Jun-13 Closed LBE-AMA-CIVIL-132 AMA VAF CIVIL Civil 21-May-13 24-May-13 04-Jun-13 06-Jun-13 Closed LBE-AMA-CIVIL-133 AMA PN CIVIL Civil 21-May-13 24-May-13 04-Jun-13 18-Aug-13 Closed LBE-AMA-CIVIL-134 AMA VAF CIVIL Civil 21-May-13 24-May-13 04-Jun-13 06-Jun-13 Closed LBE-DLM-ELECT- 043 DAELIM VAF ELECT Electrical 21-May-13 24-May-13 04-Jun-13 02-Jun-13 Closed LBE-DLM-MECH- 192 MR. HARIKUMAR DAELIM VAF MECH Material 21-May-13 24-May-13 04-Jun-13 23-Oct-13 Closed LBE-DLM-MECH- 193 MR. AMIN DAELIM VAF MECH Quality Management 21-May-13 24-May-13 04-Jun-13 05-Oct-13 Closed LBE-KCC-MECH- 194 MR. NOOR KCC VAF MECH UG-RTR 21-May-13 24-May-13 04-Jun-13 7-Jun-13 Closed LBE-DLM-CIVIL-135 DAELIM VAF CIVIL Civil 22-May-13 25-May-13 05-Jun-13 23-Jun-13 Closed LBE-TCC-MECH- 195 TCC VAF MECH Piping 22-May-13 25-May-13 05-Jun-13 6-Jun-13 Closed During routine site visit at Daelim Laydown yard, it was observed that the Contractor still not energizing the space heater for the fourteen (14) Electric motors for fan skid arrived at site last May 08, 2013 which is a violation as per RTYD-0665 sec 13.1.2. Daelim: Contractor has coordinated to Vendor regarding the Preservation of Motor unfortunately no response received yet. Contractor shall notify Company once the Vendor responded. PN: Contractor must submit pressure test packages for piping, pipeline and equipment including limiting factor, for Company review and approval at least 72 hours prior to the planned conduct of the pressure tests. The pressure test must comply with all Company requirements. All pending items from pre- pressure test line punch list must be clear and verified by SQIT. Ref. Sch. Q IV para 3.13. Occasionally observation about he Temperature requirements of Castable refractory are as under F- 1120. 1) Observed that the weather temperature Castable refractory during mixing and application was 40 C instead of 32C. 2) Observed that the water Temperature during mixing of Castable refractory was above 33C instead of 27C. 3) Observed that temperature of the backing surface during Castable lining application was also above 34 instead of 32C.Daelim Quality Team need to ensure that requirements meet SADARA Specification and cod & ITP as per SADARA SP A554-E-103-QH-GEN-PRO-047 para 4.2.7, A554-T-103-MB--SPC-MB-B27 (SP-0-0127) API 936 Para 4.4.2 and RTSAES-N-110-para 9.17. Subcon: Additional Fan/Blower was provided on Castable mixing and application area to maintain acceptable ambient temperature. Water with ice was used for mixing of Castable refractory to maintain acceptable temperature. Closed monitoring and daily checking of ambient, metal/backing surface and Castable mixing temperature were conducted to ensure conformance with the requirement. During routine visit, it was noticed that the Contractor was using a 316 stainless steel spline bolt for the installation of splice plate and expansion splice plate for cable tray which is a violation as per G70-0322- 00 sec 4.1 in which, hot dipped galvanized fasteners shall be used. During Material receiving Inspection, It was observed the following quantity of defect of pipes such as PIPE, BE, EFW, ASTM, A671-CC70 CL.12 S2, etc. as per attached in LBE 192. Daelim shall shift above listed material to quarantine area. Contractor: All the damaged materials were shifted to quarantine area. A list was provided to Company. All the damage items will be repaired as per approved M.O.S. after inspection the materials will be accepted. Found that Daelim Welding Inspector not available at MFC tanks area since few days and Tank Inspector is raising RFI's for welding inspections. RFI's might be rejected due to violation of Sch. "Q" attachment IV para #3, corrective action with preventive measures is required. Daelim: Corrective action has been taken, assigned approved Daelim welding inspector to Petrol Steel tank area, hence, the situation presently -Complying with the quality requirement. It was noticed that curing of flare pipe rack pedestal is not continuously under taken. The pedestal was poured on May 16, 2013 and at 5:30 pm (19/05/13), the pedestal was delay, the formwork has been loosened from the structure. There is no schedule of concrete curing on all structures poured and without advise of the engineer in charge, the curving truck did not come to cure those structures in this location. A violation of RTS25-3001-01 section 9. Subcon: Provided drawing to support at flare area. PN: During surveillance/monitoring inspection at cooling tower (RC wall) along S/E corner, it has been observed that piece of wood was inside RC wall, in which prior to concreting works, must see to it that proper cleaning and all debris must be remove, and also con container slab along west portion near expansion joint. Found out that hairline crack on soffit slab. Contractor was advised to the corrective and preventive action, in order not to happen again on others structure. Subcon: Method Statement was submitted for the repair of cooling tower surface defects. With reference to LBE #132, some pedestals were exposed open without burlap and poly ethylene sheet. In accordance with the Project Engineer his workers left the pedestal open since it is time for them to go. S, at 5pm till the next day, the Subcontractor did not undertake curing of these pedestals. Contractor shall reply to what action to take since this is already a repeated violation. Contractor QC and Subcontractor QC Inspectors are witnesses of this violation. Subcon: Subcontractor will assigned curing team to be responsible for the curing of concrete structures and to monitor curing. PN: During alignment verification of Oil Quench Tower T-1310, it has been observed the following discrepancy, 1) Washer plate for anchor bolt were not matching due to hold down bolt hole are not centered, which is insufficient to distribute the bolt damping force to equipment foot, cause of deflection on yielding on washer. 2) Columns of shim plate were installed on several location to control alignment and leveling. 3) Daelim shall follow project specification and code and rectify no occurred discrepancy with proper Engineering support. AP-1686, A554-E-103-QA-GEN-PLN-056, A554-E-103-QA-GEN-PRO- 035. Subcontractor: Fabricated new square washers were replaced for the oil quench tower T-1310, anchor bolt's location were required. The equipment base anchor bolt opening locations are fully covered with square washer without any issue. After installation of new washers, temporary bolt tightening (anchor bolt) completed. During surveillance and monitoring inspection at switchgear/MCC room and transformer yard C substation G1120 & G1121. It has been observed the following items to be repair or rectify A) transformer yard a.1) All chamber columns, firewalls, and beams shall be minimize 25x25mm to the true line and dimension as per IFC drawing a.2) Removal of loose concrete or laitance on floor slab & repair damage of WS even surfaces. a.3) All joint groove between columns and cmu wall shall be out & filled uniformly depth and width as per IFC drawing. a.4) Complete installation of weed holes on cmu walls as per detailed drawings, and ensure are not blocked of loose concrete or laitance.a.5) some portions of exterior cmu cement textured finished should be rectify & removal of loose plaster prior to repaint. a.6) Rectify some portion's of firewall with bulging and apply putty prior to repaint. a.7) Complete finishing provision for HVAC & Electrical openings on substation cmu wall, as per IFC drawing. a.8) All exterior surface of all columns c1 should be flush & straight to roof beam as per IFC drawing. a.9) Ensure painting works after all repair are finished or completed. a.10) Trim excess concrete at expansion joint on flour (TPER) & removal of loose concrete or laitance on TPER. a.11) ALl faded paint on exterior columns, beams, and wall should be repainted. B) ) Switchgear/MCC Room b.1) ALl joint groove between column, beams, and cmu walls shall be cut & filled uniformly depth & width as per IFC drawing. b.2) Repair uniformly all internal corners of columns & beams to the dimension as per IFC drawing. b.3) Ensure flatness of floor slab, provide sample for approval prior proceed with repair as per the approved method statement. b.4) Roof beams and soffit slab exposed to view shall be chipped and grounded of excess concrete to form an even and smooth surface finished as per paint schedule. b.4) Ensure all uneven form joints of all columns should be grinded & repair to attain smooth & straight surface finished. b.5) All faded paint on columns, beams, walls soffit should be repainted. b.6) All CMU wall with pinholes should be repair & apply paint (as per approved sample). b.7) Internal CMU wall at 6L 8/B-C along ducting level up to roof beam. should be repair prior to painting. b.8) Repair uneven surface of CMU wall & columns. b.9) All chip ends & uneven surface around CMU wall openings shall be properly repaired.b.10) Ensure painting works after all repair are finished/completed. b.11) Installed door tabs as detailed on the drawing. Provide method statement on how to fill door tabs with grout. In this regard, Contractor was advised to rectify all items above prior to installation of electrical equipments and other discipline involved. Subcon: Work in progress, completion date will be on 30 June 2013. Assigned a group of workers to close punch lists in the substations. The first target schedule does not meet due to huge numbers of punch items. in this regards contractor need to increase manpower to close the punch lists in order to meet the 2nd contraction schedule on 30.Jan.2014. It was noticed that spent caustic train A & B, some of the top bars (25mm) of the foundation was cut due to intersection with anchor bolts. Please provide justification to resume concrete placement after the anchor bolts are installed on the anchor box. Subcon: Daelim to provide new drawing showing modifications. FRP UG fire water line found damage elbow from shaving during joint fit-up & assembly inspection. It is observed that Daelim and KCC Quality team have a lack of interest for inspection responsibilities as repeated violation are in routine. It is observed that Daelim/KCC Inspectors are raising RFI's without their inspection. An example is RFI no. MFC-DLM-KCC-UG-RTR-1218. Drawing No. FW-7100-5-3. This is a violation of Schedule "Q" Atch. IV para 3. Daelim/KCC Quality must perform Inspection prior to Company and after their satisfaction/ Contractor/Subcontractor can raise RFI for the activity. Daelim Quality team need to take corrective action and preventive measures is required. Daelim: Total insertion depth of the elbow is 130mm and the damaged area due to impact during transportation is less than 25mm in dept. and it is about 3 inches in width. As the affected are was small so the Contractor/Subcontractor Inspector have allowed that elbow for fit-up. But when SADARA Inspector come for fit-up inspection he said that the affected elbow will not be accepted. There was another elbow available in spare and was replaced with the damage elbow and fit-up inspection was accepted. Contractor/Subcontractor Inspectors are doing inspection of each item before issuing RFI to Company. Contractor QC Civil Supervisor left the project without a written notification and approval replacement. This is a violation to Schedule Q para 5.14 which require quality personnel changes required coverage notice 30 days in advance or 72 hours for Daelim: Contractor has given late notification on the absence of its Contractor QC Civil Supervisor. Contractor has submitted MR. J. H. Lee as temporarily replacement and was approved as evidenced via transmitted Company letter # IK-MFC-L-CJ-DJ-0093. Contractor shall propose a candidate for the position. Contractor shall also make proper notification to Company for any future QC personnel absence. During routine inspection at TCC-2 fabrication facility, found that only one welder is welding 36" butt joint instead of two welders, violating A554-E-103-QA-GEN-PRO-056 para # 17.1.4 Spec. TCC & Daelim Inspectors must ensure the corrective action with preventive measures. Subcon: Tic Welding Inspector will make sure all 12'' above welds assign tow welder. Page 20 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 30, 2014 DUE DATE Issued corrective action to Company Target Date S/N LBE NO. PID SUBCON/ CONTRACTOR VAF / PN LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason Company comment Approved Close LBE by Company STATUS CONTRACTOR'S CORRECTIVE ACTION PLAN LBE-TCC-MECH- 196 TCC VAF MECH Quality Management 22-May-13 25-May-13 05-Jun-13 1-Jun-13 Closed LBE-PSCL-MECH- 197 PSCL VAF MECH Preservation 22-May-13 25-May-13 05-Jun-13 Closed 27-Jul-13 Closed LBE-TCC-MECH- 198 TCC VAF MECH Piping 22-May-13 25-May-13 05-Jun-13 1-Jun-13 Closed LBE-DLM-MECH- 199 MR. HARIKUMAR DAELIM VAF MECH Quality Records 25-May-13 28-May-13 08-Jun-13 13-Oct-13 Closed LBE-AMA-CIVIL-136 AMA VAF CIVIL Civil 27-May-13 30-May-13 10-Jun-13 01-Jul-13 Closed LBE-AMA-CIVIL-137 AMA VAF CIVIL Civil 27-May-13 30-May-13 10-Jun-13 09-Jul-13 Closed LBE-DLM-INST-044 MR. SHABIRUL DAELIM PN 1 INST Instrumentation 27-May-13 30-May-13 10-Jun-13 27-Jul-13 Closed LBE-ARCC-MECH- 200 ARCC VAF MECH Piping 27-May-13 30-May-13 10-Jun-13 6-Jun-13 Closed LBE-TCC-MECH- 201 TCC VAF MECH Piping 27-May-13 30-May-13 10-Jun-13 6-Jun-13 Closed LBE-TCC-MECH- 202 MR. NASSAR TCC VAF MECH Coating/ Painting 27-May-13 30-May-13 10-Jun-13 Closed 9-Jun-13 Closed LBE-AMA-CIVIL-138 MR. GERALD AMA PN CIVIL Civil 28-May-13 31-May-13 11-Jun-13 02-Oct-13 Closed LBE-DLM-ELECT- 045 MR. MARK DAELIM VAF ELECT Electrical 28-May-13 31-May-13 11-Jun-13 29-Aug-13 Closed LBE-DLM-MECH- 203 MR. AMIN DAELIM PN MECH Quality Records 28-May-13 31-May-13 11-Jun-13 13-Oct-13 Closed LBE-TCC-MECH- 204 TCC PN MECH Mechanical 29-May-13 01-Jun-13 12-Jun-13 18-Aug-13 Closed LBE-AMA-CIVIL-139 AMA VAF CIVIL Civil 30-May-13 02-Jun-13 13-Jun-13 02-Oct-13 Closed LBE-DLM-MECH- 205 MR. AMIN DAELIM VAF MECH Piping 01-Jun-13 04-Jun-13 15-Jun-13 8-Oct-13 Closed LBE-DLM-MECH- 206 MR. AMIN DAELIM VAF 2 MECH Piping 01-Jun-13 04-Jun-13 15-Jun-13 Disagreed (06/06/13) Provide corrective action (12/2/14) 04-Mar-14 Closed LBE-DLM-MECH- 207 MR. AMIN DAELIM VAF MECH Piping 01-Jun-13 04-Jun-13 15-Jun-13 29-Sep-13 Closed Observed that Civil drawing and structural drawing is conflicting on EW and NS pipe rack area. Embedded plot locations were not matching with structural drawing were showing inclination, level variance dimensions discrepancy location and etc. Guest plate installation and welding activities on hold at several location. 1) Daelim Civil structural, Quality and Engineering team shall verify and propose a remedy method with engineering for final acceptance. 2) Daelim Quality team shall move vigilant on subject matter and avoid further discrepancy on platform erection. Subcon: Noted. Activities will be taken. The issue was informed to Engineering team. During routine monitoring activities at spent caustic area, it was noticed that the steel attachments to the anchor bolt to hold the anchor bolts in a correct bolt and to be embedded in the concrete is rusty without casting. This is a violation of RTS-3001-01 para 8.2.7 which anchors these items to the concrete shall be similarly galvanized. Subcon: Anchor bolts & embedded steel supplied by Contractor. During routine inspection at N-S pipe rack, the curving of pump foundation G-1311 C and G-1321 were not properly undertaken. Only polyethylene sheet without burlap covers the foundation and since part of the foundations are dry. This is a violation of RT25-3001-01 para 9.1.4.2 Subcon: Assigned curing team to be responsible for the curing of concrete structures. During Inspection at TCC NASCO fabrication facility , it has been observed that no approved QC (Welding & Piping) Inspectors are available at their facility, two RFI's have been raised for the inspections of fit-up and post welding which is Hold point for TCC QC Inspector as per relevant I.T.P. Subcon: Piping Inspector for NASCO interview was accepted and approve dry Company. After required documentation Piping Inspector assigned fulltime. Two Welding Inspector assigned for Construction activates. Found that welding electrodes E-7018 (2.6mm not #3998 7 packet each 20kg), (3.2mm lot #2850, 21 pkts each 20kg), (4mm lot #3542, 18pkts each 20kg) are stored in high humidity 66.5% instead of below 40% at Petrol Steel Tanks consumable store. Available A/C in the store was out of order and switch-off. High humidity causes moisture in electrode coatings. It is a violation as per QCP PSC_103-1008-07-21- Rev.0 Atch. 1 para # 1.1. Corrective action and preventive measures are required. Subcon: The electrode storage area has been rectified, the air conditioner which was not working has been replaced by another air conditioner. It was also inspected by the Contractor/Company Inspector and the same was found acceptable.. The electrodes were stored inside a plastic sealed base, which reduce the effect of moisture and also During routine inspection at TCC-2 fabrication facility. It is observed that flange forcing on all piping or not protected at all times during fabrication & construction activities, violating SADARA Spec RT-6-ICS- para 2.16 & 19.4 Subcon: TCC QA/QC Manager give instruction to TCC QC Piping Inspector to ensure that all flange face protected during fabrication activity, flange face protected with duct tape/masking tape. PN: Daelim quality needs to ensure that the date tracking system(s) shall be maintained and kept current and available for MFC project Quality Group's review at all times. The data shall be available on a daily basis for both current and cumulative data. Data shall be retrievable by date for any given day from commencement of the work trough project completion. Ref. A554-O-PRG-QA-GEN-PRO-013 Rev.2 Para # 5.2. Contractor: Noted and follow as per procedure and requirements. PN: TCC had started pad plates preparation of Rotating and static equipment. Observed the following violation; a.) Improper preparation of ground material (pre-installation activities.) b.) Lack of caring after pouring of grouting material. C.) Crack observed after installations of equipment. d.) Daelim/TCC shall follow manufacture instructions for grout/padding plat proportion. e.) Verify the root cause of cracked pad plate and remedy action to repair subject pad. T-2410,1310. Subcon: NCR-TCC-MECH-012 received from Contractor. After action taken and closure of NCT copy will be attached. It has noticed that the slab of Cooling Tower located at North side span 1 & 2 have chipping marks in preparation for the installation of cooling tower superstructure/equipment. Contractor shall inform the Company of such activities. If there is a deviation on the IFC drawing or the Contractor shall issue NCR to record the violation. Please investigate and provide corrective action. During routine inspection at TCC-1 it has been noticed that blasting and coating activities are on-going without qualified crew painting supervisor. This is a violation against Schedule Q. Subcon: One (1) crew supervisor interviewed by Daelim, waiting for Company interview. TCC painting and coating inspector available in work shop 1 laydown. PN: During routine inspection activities at operator building (external RC wall), found out some portions of RC wall have presence of hairline crack and waily walls, also some uneven surface of RC wall due to exceeded used of formworks. Contractor was advised to investigate and take corrective action concerning this issue. Subcon: All minor surface defects in the operator building shall be repaired with approved repair material. All formworks to be replaced to improve the concrete surface finishes. During material receiving, it has been noticed that the bolts used for the fiber glass cable tray fittings were 316 stainless steel bolts which is a violation as per G7D-0323-00 sec. 4.1.5. Also, it has been noticed that the hold down clamp was made of 316 stainless steel which is a violation as per G7D-0323- 00 sec. 4.14. Contractor: It has been confirmed from the vendor regarding the replacement of exiting stainless bolts/nuts on the reducer fitting delivered on site. Vendor to replace with silicon bronze equivalent of the fitting assembly hardware and will advise Company upon the arrival of replacement hardware. (email received from vendor dated 12 June 2013). PN: During surveillance to the Daelim Laydown yard it was found that the Contractor is fixing the lifting seeing at wrong place and it might be cause the damage of the cable. Contractor is advise do not repeat the same mistake during the lifting & transportation. Manufacturer's to be mandatory. Daelim: Notified and informed Subcontractor (ASYAD) personnel who unloaded the instrument cable that they were not following the proper procedure as per schedule Q of sec.6 on handling of materials and equipments that may result in damaging the materials and equipments. Contractor already instructed not to repeat the improper handling of materials and equipments. They agreed to follow and comply with proper procedure to prevent damages and violation in the future. During routine inspection at ARCC fabrication shop. It has been observed that all fabricated pipe spools & mumbles are filed up and not maintained in shipping properly to prevent mechanical damages. Violating SADARA Spec. RT-G-ICS para 2.19.17 C. During routine inspection at TCC NASCO fabrication facility. It has been observed that no tagging system for fabricated pipe spools memblast has been implemented for traceability, violating Schedule Q para 6.29 & A554-E-103-QA-GEN-PRO-042 para 6.51.3 & 6.51.6 requirements. Subcon: Spool trucking systems implementation travel sheet equipment in W.N. work shop will ensure by TCC Piping Inspector before shifting spools from W.N. to the work shop. All tags, flange face protection end caps will be verified by TCC piping Inspector. It is found that pipe spools and flanges preservation and handling in TCC facility #1 is not proper, some pipe spools found in direct contact with ground and flanges barrier in the sand. Some flange faces are observed with lot of scratches welding one intense scratched flange. Relevant piping inspector (Mr. Rico) of Daelim might be revoked due to his lack of responsibilities to avoid huge loss of project. Preservation problems were highlighted to him several times before but he is not capable to handle the job. Corrective action and preventive measures are required Ref. RT-6-ICS para 2.16, 2.19.17, 2.19.12. PFI-ES-31-para 2.3. Daelim: With respect to the SADARA PID Mr. AMIN, this LBE #205 is already being highlighted by DAELIM QC Piping Inspector (Mr. Rico) through NC issued to TCC (NCR-TCC-MECH-008) dated May 22, 2013. As to date June 06, 2013 this NCR is still open & TCC is still solving this issues, the material handling and preservation. During surveillance at TCC #1 it has been found that TCC have utilized one pipe spool which was hold due to over grinding and ovality problem. Two pipe spools were hold against the ovality and grinding issues and SADARA LBE #180 was also logged for this. After Company enquiry it is observed Daelim Piping Inspector (Mr. Rico) is not aware about that spools location or condition. Ref. LBE-180,. RT8S- 6500-01 para # 5. 3(a). Daelim: The spool that was mentioned in this LBE 206 was not being utilized. I t was mistakenly welded by the welding group without the signature and release from TCC piping inspector as well as the Daelim QC Piping Inspector assigned (MR. Raja). Nevertheless, Mr. Rico knows about that issue and instructed TCC to recover that spool from their yard to replace the pipe which has been hold for welding due to excessive grinding. During surveillance at TCC #1 it has been fond that Daelim Piping Inspector (Mr. Rico) is passing the pipes joints fit-up with 4mm and 5mm high-low. Three joints of 42'', 48'' dia found already welded with above mentioned discrepancy passed by him. Post weld usual inspection still not carried out by Daelim and TCC Inspectors. As highlighted before also that Daelim Piping Inspector is not capable to handle the job. So now it is recommended to revoke his approval. Daelim Quality needs to ensure the corrective action with preventive measures. Daelim: This issue about the HI-LO of 4-5mm is due to the contraction of the welding process. Daelim QC advised the welder to be careful on removing tack welds or distortion control to avoid this kind of problems. This 4-5mm HI-LO one side is not tolerated. We are also assuring that the HI-LO was divided along the pipes' circumference. Page 21 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 30, 2014 DUE DATE Issued corrective action to Company Target Date S/N LBE NO. PID SUBCON/ CONTRACTOR VAF / PN LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason Company comment Approved Close LBE by Company STATUS CONTRACTOR'S CORRECTIVE ACTION PLAN LBE-ARCC-MECH- 208 MR. NASSAR ARCC VAF MECH Coating/ Painting 01-Jun-13 04-Jun-13 15-Jun-13 15-Jun-13 Closed LBE-ARCC-MECH- 209 MR. NASSAR ARCC VAF MECH Coating/ Painting 01-Jun-13 04-Jun-13 15-Jun-13 Closed 15-Jun-13 Closed LBE-KCC-CIVIL-140 KCC PN CIVIL Civil 02-Jun-13 05-Jun-13 16-Jun-13 Closed 23-Jun-13 Closed LBE-DLM-CIVIL-141 DAELIM PN CIVIL Civil 02-Jun-13 05-Jun-13 16-Jun-13 27-Jul-13 Closed LBE-DLM-CIVIL-142 DAELIM VAF CIVIL Civil 03-Jun-13 06-Jun-13 17-Jun-13 Closed 25-Jun-13 Closed LBE-DLM-MECH- 210 MR. AMIN DAELIM PN MECH Quality Records 03-Jun-13 06-Jun-13 17-Jun-13 06-Oct-13 Closed LBE-AMA-MECH- 211 AMA VAF MECH Coating/ Painting 03-Jun-13 06-Jun-13 17-Jun-13 27-Jul-13 Closed LBE-DLM-INST-046 MR. SHABIRUL DAELIM PN INST Instrumentation 04-Jun-13 07-Jun-13 18-Jun-13 08-Oct-13 Closed LBE-DLM-MECH- 212 DAELIM VAF MECH UG-RTR 04-Jun-13 07-Jun-13 18-Jun-13 27-Jul-13 Closed LBE-DLM-MECH- 213 MR. AMIN DAELIM VAF MECH Piping 05-Jun-13 08-Jun-13 19-Jun-13 11-Oct-13 Closed LBE-DLM-MECH- 214 DAELIM VAF MECH Piping 05-Jun-13 08-Jun-13 19-Jun-13 30-Jun-13 Closed LBE-ASYAD-MECH- 215 MR. HARIKUMAR ASYAD VAF MECH Mechanical 05-Jun-13 08-Jun-13 19-Jun-13 06-Jan-14 Closed LBE-SEN-MECH- 216 MR. HARIKUMAR SENDAN PN MECH Quality Management 05-Jun-13 08-Jun-13 19-Jun-13 31-Oct-13 Closed LBE-TCC-MECH- 219 TCC VAF MECH Preservation 05-Jun-13 08-Jun-13 19-Jun-13 25-Jun-13 Closed LBE-DLM-MECH- 217 DAELIM PN MECH Refractory 06-Jun-13 09-Jun-13 20-Jun-13 11-Jun-13 Closed LBE-TCC-MECH- 218 TCC VAF MECH Mechanical 06-Jun-13 09-Jun-13 20-Jun-13 25-Jun-13 Closed LBE-DLM-MECH- 220 MR. NOOR DAELIM VAF MECH Quality Records 06-Jun-13 09-Jun-13 20-Jun-13 6-Aug-13 Closed LBE-DLM/KCC- MECH-221 MR. NOOR DAELIM/KCC VAF MECH UG-RTR 06-Jun-13 09-Jun-13 20-Jun-13 11-Jul-13 Closed PN: It has been observed that starting June 01, 2013. All concrete cylinder & cubes sampled at MFC site by Third Party (OSAIMI) they are bringing the sample at OSAIMI (Jubail Branch), for crushing the said specimen, in which no info or proper documentation and approval from the Company. Contractor was advised to take corrective action concerning this issue. and to ensure that all documentation/approval was properly done. Contractor: Company already approved the third party laboratory (Al-Osaimi) Jubail branch During the inspection of pump foundation P4215 A/B, near splitter the 4 NDS-RSB-Q12mm which are supposed to be embedded in the pump foundation. During installation of reinforcing beams are drilled to the pump foundation as shown on the drawing. Subcon: The FDN P-2415 A/B at pedestal. PN: Daelim Quality needs to ensure that the Contractor/Subcontractors shall track welding activities on a daily basis and submit to QR each week a weld for tracking and welder performance report for that weeks work. Cut-off date for submitting weekly performance report shall be agreed to by Contractor and QR. Output for cumulative weld data and welder data required by this document is to be reported weekly in the weld tracking and welder performance report. Shop and field and welder data may be included on the same report. Ref. A554-O-PRG-QA-GEN-PRO-13-Rev.2 para # 5.3 Contractor: Will provide the required data as per the sample format. During routine inspection at ARCC/OTC blasting painting facility. It has been noticed that empty paint cans has been stored in the paint storage. This is violation against A554-E-103-QA-GEN-PRO-041. Subcon: Empty paints cans removed on OTC paint storage area, ARCC to continuous monitor on painting facilities of OTC to avoid re-occurrence violation. It has been noticed that yellowing defect on the phenolic epoxy top coat at ARCC blasting/coating facility due to improper protect from sunlight. This is violation against A554-E-103-QA-GEN-PRO-041. Subcon: International protective coating's representative confirmed that the changes of interthem 228 color to yellow is normal as stated on product date sheet & clarification of Mr. James Donoghue (IPC Representative) during visit at ARCC painting shop. See attached letter. PN: During surveillance/monitoring inspection at compressor C-2301 & C-2001 along pedestal E-2370 & E-2070), found out some portion surface of pedestals having honeycomb/voids after removal of formworks. Contractor w3as advised to investigate the cause of honeycomb void and take corrective action. Please advice the Company Representative to check whether the surface preparation is ready to received repair materials with approval. Honey comb (voids are repaired as per approved method statement). See attached photos PN: Daelim subcontractor M/S Sendan conducted WQT for structural welding with 4 conductor. Observed that third party inspector has rejected all test coupon due to discrepancy founded. Daelim Quality (welding team) shall instruct to subcontractor welder have got Engr. training prior to perform qualification test. Subcontractor: Noted. Daelim Welding QC team discussed with Sendan Welding QC inspector and agreed before that WPQT will arrange good training as for all welders. During inspection at TCC-2 fabrication facility, it has been observed that 24" dia fabricated flanges were rolled with foot. Contractor must ensure proper handling and storages at the fabrication facilities as per SADARA RT-6-ICS. Daelim: On the spot that works was on-hold. It has been giving warning that all TCC QA/QC Inspectors are more vigilant at site now. In future if it is found that the person will be removed from site. PN: Found that Daelim Refractory Inspector not available at site during casting and gunning activities and inspection time since May 25th 2013. Corrective actions are required.Ref. violation Schedule" attachment IV para #3. Daelim: Because of emergency vacation I could not attend some of the inspections. On 10th June 2013 I have been rejoined for the inspections. It is found that Daelim Inspector (Mr. Rico) is irresponsible for the following I.) Fit-up inspection accepting 3-5mm high-low. II.) Pipes openly in direct contact with ground. III.) Flanges mixed with lot of debris and scrap materials. IV.) Handling of measuring pools is very poor. V.)Damaged pipes mixed with the fabricated spools. CNB3130K328.4.3, Fig.K328.4.3), RT8S-6500-01 RT-6-ICS, (SMIC-W-2005 (820). Subcontractor: ARCC already segregated the spool found with 3mm & 2 mm HI-LO. During daily inspection on TCC, ARCC found that TCC piping group is carefully preserving the piping materials. Further during daily fit-up inspection, ARCC check all the accurateness of each measuring tools upon inspection. Crossover pipe were damaged at header nozzle area of #(HTC-4). At F-1170: CM-1170-3 (HTC-2 IN LET-PASS-3) Daelim shall propose repair procedure with approved recommendation of SME for further action. Contractor: After discussion with Company SQIT, Daelim agreed to repair/rectify work at F-1170 CM-03 HTC-2 Inlet Pass-3. Pipe damaged shall be carried-out with approved procedure/method the repair work activities will be informed to the Company through RFI. It has been observed that Daelim subcontractor ASYAD started pre-fabrication and welding activities without proper information to quality team. Daelim shall instruct to subcontractor to follow Schedule Q requirement and Daelim Quality team shall closely monitor all related activities and meet the schedule Q requirements. Subcontractor: ARCC will be immediately stopped, then submit resume for Welding Inspector (ASYAD) and be interviewed by Contractor, CV of said Inspector was forwarded to SADARA for final interviewed and approval. Once Inspector approved by Company, ASYAD Welding Inspector will closely monitor and communicate to Daelim Welding Inspector. Further, materials receiving for consumables will be raised, when comply the requirements Fabrication will resume with the final instruction from the client. During routine inspection it has been observed that anchor support proms of spent caustic crystal has been applied the coating on the rusted surface without surface preparation & installed it. This lead must crack defect for all frames. This is for information, root cause analysis and corrective action. Contractor: Duplication of item No. 136 Civil LBE, work completed and closed PN: During material receiving inspection, it has been observe that Instrument cable drum # 13-0079E size 24Px20 AWG has damage insulation jacket around 24 inches from the end cap. Contractor is advised to coordinate with the vendor's to replace the damage cable drum. Daelim: Cable drum # 13-0079E 24 P X 20 AWG shall be tested on reel once the cable passed the IR test & Contractor will offer this PN to Company for closure. During witness inspection of FRP U/G line street reinforcement lamination joint. It is found that Daelim Inspector (S. Khalid Basha) did not inspect the joint prior to Company Inspection. It has been found that he has accepted the joint and reported without his inspection which has lot of visual defects such as voids, air bullies from down side of the tee. Daelim Quality team needs to take corrective action preventive measures. Ref. RTI # MFC-DLM-KCC-UG-RTR-1233 and drawing joint #No16103 AAB=FW- 071004-04-02 joint #960. This is a violation of Schedule "Q" attachment IV para #3 and G85-6115-01 para # 39. Subcontractor: Daelim FRP U/G inspector Mr. S.K. Basha resigned from Daelim Company. Daelim assigned Mr. Raja as FRP/RTR UG inspector, approved by Sadara as per schedule "Q", Att. I, Para 2.2.3. Daelim Quality team make sure that Pre-inspection will be done prior to Company inspection. During routine inspection at TCC fabrication facility, it has been observed that open SAW floor were not stored continuously in ovens at 65C minimum temperature, violating SADARA Spec. RT85-6500-03 AH # 2 & A554--E-103-QA-GEN-PRO-056- para 15.5.1.6 requirements. Contractor must insure that open SAW flu shall be stored continuously in ovens at 65 C at all time. Daelim: The flux was discovered and further a tool box conducted with welders and welding inspectors. TCC welding inspector will monitor all kind of flux storage for smooth and defect free weld. Repeated violation found that the Daelim Refractory Inspector is not submitting the RFI's timely to Company after the inspection. Approximately 400 RFI's are still awaiting for which inspection has been done already. This is a violation as per schedule "Q" attachment IV para #3. Daelim: All pending RFI's have been submitted except those RFIs need sample test results from third party laboratory. And those RFIs shall be submitted as soon as the result arrived. During Inspection. It was noticed that the Daelim and Subcontractor (KCC) carried out Hydro Test of U/G fire water system 1481 area-A-Unit-SI (hydro Test Package #0714). After 24 hours pressure holding found that pressure has been dropped. Daelim Quality team needs to take corrective action with preventive measures and provide root cause analysis for that test failure. Test must be carried out again ensuring that SADARA requirements are fulfilled. Violation reference : A554-E-103-QA-GEN-PRO-008 and GAS-6423-01. para #65. Daelim: Re-Hydrotest has been carried out on 9 June 2013 and accepted. RFI # MFC-DLM-KCC- UG-RTR-1241 (Package # 1481-HT-0714) Page 22 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 30, 2014 DUE DATE Issued corrective action to Company Target Date S/N LBE NO. PID SUBCON/ CONTRACTOR VAF / PN LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason Company comment Approved Close LBE by Company STATUS CONTRACTOR'S CORRECTIVE ACTION PLAN LBE-TCC-MECH- 222 TCC VAF MECH Mechanical 06-Jun-13 09-Jun-13 20-Jun-13 30-Jun-13 Closed LBE-AMA-CIVIL-143 AMA PN CIVIL Civil 08-Jun-13 11-Jun-13 22-Jun-13 22-Jul-13 Closed LBE-DLM-ELECT- 047 DAELIM VAF ELECT Electrical 10-Jun-13 13-Jun-13 24-Jun-13 29-Aug-13 Closed 2 LBE-AMA-MECH- 223 MR. NOOR AMA VAF 2 MECH Hvac 10-Jun-13 13-Jun-13 24-Jun-13 16-Mar-14 Closed LBE-DLM/TCC- MECH-224 MR. HARIKUMAR DAELIM PN 2 MECH Mechanical (Equipment) 10-Jun-13 13-Jun-13 15-Jun-13 25-Feb-14 Closed LBE-AMA-CIVIL-144 MR. JERRY AMA VAF CIVIL Civil 11-Jun-13 14-Jun-13 25-Jun-13 15-Sep-13 Closed LBE-AMA-CIVIL-145 AMA VAF CIVIL Civil 11-Jun-13 14-Jun-13 25-Jun-13 25-Jul-13 Closed LBE-TCC-MECH- 225 MR. NASSAR TCC VAF MECH Coating/ Painting 11-Jun-13 14-Jun-13 25-Jun-13 13-Jul-13 Closed LBE-ARCC-MECH- 226 ARCC VAF MECH Refractory 11-Jun-13 14-Jun-13 25-Jun-13 13-Jul-13 Closed LBE-KCC-MECH- 227 MR. NOOR KCC VAF 2 MECH UG-RTR 11-Jun-13 14-Jun-13 25-Jun-13 12-Feb-14 Closed LBE-SEN-MECH- 228 MR. HARIKUMAR SENDAN VAF MECH Quality Management 11-Jun-13 14-Jun-13 25-Jun-13 31-Oct-13 Closed LBE-DLM-MECH- 229 MR. AMIN DAELIM PN MECH Preservation 11-Jun-13 14-Jun-13 25-Jun-13 05-Oct-13 Closed LBE-DLM-MECH- 230 MR. AMIN DAELIM PN MECH Piping 11-Jun-13 14-Jun-13 25-Jun-13 06-Oct-13 Closed LBE-DLM-MECH- 231 MR. AMIN DAELIM VAF MECH Quality Management 15-Jun-13 18-Jun-13 29-Jun-13 8-Oct-13 Closed LBE-DLM-MECH- 232 MR. AMIN DAELIM PN MECH Quality Management 15-Jun-13 18-Jun-13 29-Jun-13 08-Oct-13 Closed LBE-DLM-CIVIL-146 DAELIM PN CIVIL Civil 17-Jun-13 20-Jun-13 01-Jul-13 28-Jul-13 Closed LBE-TCC-MECH- 233 TCC VAF MECH Preservation 17-Jun-13 20-Jun-13 01-Jul-13 30-Jun-13 Closed During material receiving inspection (RFI #AMA-HV-0022) found that fire pumpers don't have "UL Label Fire Rating" Identification marking to demonstrate fire rating. It is a violation against " RT-LPP-10.18 and document # A554-K-PRG-AR-SPC-LPP-064 para#2. Corrective action and preventive measures are required. Contractor: Contractor QC informed Amana regarding the highlighted issue. Amana decided to replace the material (Fire, smoke damper) that was delivered on the site without requirements of "UL listed and re-submitted the new specification of (Fire smoke damper with required "UL" listed as per standard specification of Sadara. PN: TCC/Daelim installed PSA drum (absorber vessels) D-2611 to D2616, it has been observed that during lifting time Construction team depressurized preserved N2 and Equipment end nozzle aged as lifting device, presently no N2 level is showing zero. The N2 level as recommended by vendor in order to avoid any further corrosion internal shell and accessories. Subcontractor: TCC noted and further to check with Equipment Inspector pertaining this issue. During concrete placement of Pump Foundation (P-1321 B), the forms collapsed. It was noticed that the concrete is almost full at the time of collapsed. Contractor shall investigate and provide corrective action to avoid recurrence. There are still 2 remaining foundations which require concrete placement and contractor shall ensure that the remaining foundation will not suffer the same consequence. Subcon: During concrete pouring of pump foundation (P-1321B) was collapsed, it was totally removed and cleaned. Amana has already installed new rebar and formwork and the work has been done, photos are attached. During surveillance found that TCC helper (Mr. Liu Chaoyang Badge # 037038) was doing the track welding on the pipe joint with GTAW welding process. Also found that welders are tack welding in atmosphere without any wind & sand protection during high velocity sand storm. Daelim Quality notified about above violations. Ref. RT85-6500--01 para #5.5,12.1. Corrective action with preventive measures, are required. Subcontractor: TCC to checked with TCC QC Welding Inspector concerning on this issues. PN: During surveillance/monitoring activities at Sub-station G-1120 along mechanical room, it was found that some partial deliveries of Timber were defective (not solid wood), intended to be used for Roof Slab System. Contractor is advised to remove immediately and quarantine said defective timbers for proper material disposition, and replace with solid wood. Subcon: All defective black timber has been removed from mechanical room. Pictures attached. PN: During routine site visit at Daelim's Laydown yard, it was noticed that some of the cable trays and fittings were already stuck in sand as a result of the sandstorm. The Contractor shall remove the sand and make sure that the cable trays were stored off the ground. Daelim: Cable trays & fittings will be cleaned and transferred to an elevated area. PN: Based on the violations already logged (LBE#180, 2016, 207, 213) it is advised that Quality Team must ensure that II joints weld joints of excess of High-Low and 02 flanges of deep scratched has been segregated for corrective action. Fit-up inspection and preservation should be monitored more closely to avoid above-mentioned discrepancies. Daelim Inspector have detailed list of above-mentioned rejected joints and flanges. Contractor: Noted and will follow the activities only as per the procedure. It is found that Daelim Quality team don't have Inspector for Material Receiving inspection at MFC Daelim Laydown. Piping Inspector (Mr. Melchor) was raising RFI's since many days on temporary permission but he is also involved in different activities at site for piping inspection. It is observed that he is not capable to handle the material receiving inspections. Furthermore, Company had been observed that many mechanical material damages and deep grinded spots on different large bore pipe fittings which were accepted by him. As per Schedule Q Att. VI table VI-I Mechanical and Piping material receiving inspector requirement is 1 per work at site. Daelim Quality team needs to fulfill the Sch. Q requirements. Also prepare and submit the detail report of imperfections on the large bore pipe fittings. Contractor: Daelim got the approved piping material inspector. All the material receiving activity is done by approved QC Inspector Mr. Ludiveco. PN: Daelim quality team must provide heat treatment (PWHT) Inspector prior to start of any heat treatment activity. As per Schedule Q Attach. IV Table VI-1 requirement, for Contractor is 1 inspector per 4 localized heat treatment machines or 2 furnaces and 1 for 5 Subcontractors inspectors. Contractor: Daelim provided PWHT Inspector for the PWHT activities and future more inspectors will be provided. Found that during removal of the collapsed concrete with excavator from pump foundation (P-1321B) FRP Schedule Q fire water line FW-071053-02 broken while removing the concrete. The line was already visually inspected and hydro tested against the test package # HT-004 activity was performed by Subcontractor AMANA under supervision of Daelim. Daelim Quality team needs to care corrective action with preventive measures. Subcontractor: Fire water line (FW-071053-02) damaged pipe has been removed and fabricate with new spool and fit-up & pipe laying is completed, dated July 9, 2013, reference RFI #MFC- DLM-KCC-VG-RTR-1281. Subcontractor SENDAN started welding activities (Tack Welding on cable tray support) at site & it has been observed that welding inspectors was not available at site. Subcontractor: Sendan welding inspector entry pass was not ready, within 3 days will arrange the gate pass and then started the welding activities. The corrective action has been taken, Sendan's welding QC Inspector has been interviewed, approved and mobilized at site. PN: Based on the violations already logged (LBE#180, 206, 207 & 213) it observed that Daelim Quality team must ensure that 11 joints weld joints of excess High - Low and 02 Flanges of deep scratched has been segregated for corrective action. Fit-Up inspection and preservation should be monitored more closely to avoid above mentioned discrepancies. Daelim inspector already had detailed list of above mentioned rejected joints and flanges. Subcontractor: Noted and will be taken care to avoid recurrence in the future. During surveillance/monitoring activities at operator building on June 10, 2013 (inside portion) found out that installation of CMU "First Layer" had been done without submitting first "RFI" for surface preparation & proper layout. Contractor is advised to remove the said CMU instn. And to ensure proper documentation, and also repair Subcon: Surface preparation done by chipping the area before laying of CMU. Raise RFI to close LBE-145 During routine inspection at TCC-02 offsite blasting & coating facility, it has been observed that coating activities carried out during sand storm, violating SADARA Spec. A554-E-103-QA-GEN-PRO-041, para 5.21. Subcontractor: TCC Painting Inspector already informed Construction group that weather condition especially sand storm is not allowed to undergone work for painting, otherwise work will be stopped during sand storm. TCC to check with painting inspector assigned on that area or regarding this issues. During surveillance Inspection at MFC ARCC Furnace Area found that Refractory material cast (F50-G3) was stocked in area as manufacturing data sheet. It was manufactured on June 11, 2012 and self life only year. Daelim is advised to shift the material to Quarantine area. Daelim Quality team need to take corrective action and preventive measure are require. Daelim: Material has been shifted to quarantine area and said material are not used for application. A log sheet is being maintained for verification for gunning & blasting activities. PN: During surveillance and monitoring inspection at MFC site Laboratory, it has been noticed that Laboratory Technician in-charge will be leaving this coming 20 June 2013 (last working days) for final exit in his company. In this regard, Contractor was advised to have a replacement for said technician, for proper hand-over and documentation concerning our site MFC Laboratory status. Contractor: Contractor already advised third party (Al-Osaimi) the replacement of site laboratory technician and Company already approved by third party laboratory Jubail-1 branch During routine at TCC-2 Fabrication facility, it has been observed that LTCS Material is not segregated from normal material during storage. Violating SADARA Specification RT-6-ICS, para 2.19.8b TCC Piping Inspector assigned for LTCS workshop and he will make sure that all precaution will be taken cared of regarding LTCS materials Page 23 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 30, 2014 DUE DATE Issued corrective action to Company Target Date S/N LBE NO. PID SUBCON/ CONTRACTOR VAF / PN LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason Company comment Approved Close LBE by Company STATUS CONTRACTOR'S CORRECTIVE ACTION PLAN LBE-TCC-MECH- 234 TCC VAF MECH Piping 17-Jun-13 20-Jun-13 01-Jul-13 30-Jun-13 Closed LBE-DLM-MECH- 235 MR. NOOR DAELIM PN MECH UG-RTR 18-Jun-13 21-Jun-13 02-Jul-13 21-Aug-13 Closed LBE-DLM-MECH- 236 DAELIM PN MECH Quality Records 18-Jun-13 21-Jun-13 02-Jul-13 21-Jul-13 Closed LBE-DLM-MECH- 237 MR. NOOR DAELIM VAF 2 MECH Quality Management 18-Jun-13 21-Jun-13 02-Jul-13 12-Feb-14 Closed LBE-DLM-MECH- 238 MR. NOOR DAELIM VAF MECH Refractory 18-Jun-13 21-Jun-13 02-Jul-13 22-Jul-13 Closed LBE-DLM-CIVIL-147 MR. GERALD DAELIM PN CIVIL Civil 19-Jun-13 22-Jun-13 03-Jul-13 28-Jul-13 Closed LBE-TCC-MECH- 239 MR. NASSAR TCC VAF MECH Coating/ Painting 21-Jun-13 24-Jun-13 05-Jul-13 27-Jul-13 Closed LBE-TCC-MECH- 240 TCC VAF MECH Piping 22-Jun-13 25-Jun-13 06-Jul-13 18-Aug-13 Closed LBE-ARCC-MECH- 241 ARCC VAF MECH Piping 22-Jun-13 25-Jun-13 06-Jul-13 16-Jul-13 Closed LBE-DLM-ELECT- 048 MR. MARK DAELIM PN 1 ELECT Electrical 23-Jun-13 26-Jun-13 07-Jul-13 09-Mar-14 Closed LBE-TCC-MECH- 242 TCC VAF MECH Piping 23-Jun-13 26-Jun-13 07-Jul-13 18-Aug-13 Closed LBE-TCC-MECH- 243 TCC VAF MECH Quality Management 23-Jun-13 26-Jun-13 07-Jul-13 Closed 27-Jul-13 Closed LBE-DLM-MECH- 244 MR. HARIKUMAR DAELIM VAF MECH Preservation 23-Jun-13 26-Jun-13 07-Jul-13 Closed 24-Oct-13 Closed LBE-TCC-MECH- 245 TCC VAF MECH Piping 23-Jun-13 26-Jun-13 07-Jul-13 Closed 30-Jun-13 Closed LBE-AMA-CIVIL-148 MR. GERALD AMA PN CIVIL Civil 24-Jun-13 27-Jun-13 08-Jul-13 Closed 10-Oct-13 Closed LBE-DLM-MECH- 246 MR. KHAN DAELIM VAF MECH Quality Management 24-Jun-13 27-Jun-13 08-Jul-13 Closed 19-Oct-13 Closed LBE-DLM-MECH- 247 MR. KHAN DAELIM VAF MECH Quality Management 24-Jun-13 27-Jun-13 08-Jul-13 19-Oct-13 Closed LBE-TCC-MECH- 248 MR. NASSAR TCC VAF MECH Coating/ Painting 25-Jun-13 28-Jun-13 09-Jul-13 6-Jul-13 Closed LBE-DLM-ELECT- 049 DAELIM PN ELECT Electrical 25-Jun-13 28-Jun-13 09-Jul-13 27-Jul-13 Closed LBE-AMA-CIVIL-149 MR. GERALD AMA PN CIVIL Civil 26-Jun-13 29-Jun-13 10-Jul-13 30-Jul-13 Closed During inspection, it has been found that the Contractor & Subcontractor not following the drawing (KCC- 108-1084-07-137) for refractory brick lining in F-1170 gas furnace. Daelim quality team must ensure that work is carried for Construction drawings. Corrective action & preventive measures are required. Contractor: As per SME (Mr. Jerald), the lining is acceptable as per his verification upon his visit at the site. This variation was happened due to the extra tie-back plate provided on the side walls of F-1170 which will eventually give more support for the brick lining. This would happen in F- 1250 & F-1160 also. PN: It has been noticed that testing of total chlorides and total sulfates conducted by our third party laboratory (OSAIMI), found out that there is no updated test records submitted to Company. In this regard, Contractor was advised to updates all records that frequencies of the various test has been comply wit RT-25-3001-01 para 3.6.2 for proper documentation. Contractor: The testing of total chlorides and total sulfates, the updated test reports are already submitted by Contractor, see updated test report. Weekly reports submitted to the Company based on the results released by Third Party Lab. Test frequencies as per RT2S-3001-01 is being complied by concrete supplier. During routine inspection, it has been noticed that TCC-01 offsite coating & blasting facility doing the job without crew supervisor. This is violating the SADARA standard & schedule. Subcontractor: Crew Supervisor CV submitted to Daelim & waiting for Sadara Interview. Crew supervisor was approved by company. NCR #20 closed. PN: Contractor must submit pressure test packages for piping under ground and above ground line including limiting factor, for Company review and approval at least "72" hours prior to the planned conduct of pressure test. The pressure test must comply with all Company requirements. All pending items from pre pressure test line punch list must be clear and verified by Company Inspector as per Sch. "Q" Att. IV para # 3.13. Subcontractor: Noted and will be taken care of in order to Comply the project specs. Requirement. PN: Contractor must submit each week to the Company representative a fourteen (14) day loo-ahead schedule of all planned Quality activities during Construction phase and pre-commissioning. The schedule must be sent electronically in a format acceptable to Company. Daelim Quality team needs to take corrective action with preventive measures as per schedule "Q". 2-weeks look ahead inspection schedule has already been sent to PID and shall be followed up in the future. It is noticed that Daelim Quality Team released HVAC Inspector Mr. Shaik Khalid Basha without Company advised or information. It is violation as Sch. "Q" section 5.14. Contractor must advise the Company Representative at least thirty (30) days in advance of scheduled absences or changes to personnel and Quality coverage or within seventy (72) hours for unscheduled leave. Daelim quality team must ensure the corrective actin and preventive measures. Contractor: New HVAC Inspector Mr. Ruperto Vermug is already approved. All activities of HVAC has been conducted as per ITP. During routine inspection at TCC-2 fabrication facility shop, it has been observed that invite fabricated spools & assembly, pipe opening are not copped or covered, violating SADARA Specs. RT-6-ICS, para 2.19.4 & 2.19.5 TCC Piping Inspector will make sure all welded spool, proper preservation as per Sadara specs. Found that welders are welding more than 24mm, violating the WPS (PI-PI-04) and SADARA Specifications at White Nile TCC fabrication shop. Also there is no welder identification on large bore pipe joints weld by two different welders. Noted on DWG # C016103VIA-SH-011342-03A joint # SW.11 daily 24" Schedule 60. Corrective action with preventive measures are required. Subcontractor: Warning was issued to welder and 2 days deductions for the violation done. PN: During surveillance & monitoring inspection at base slab, around pump foundation along east side portion of cooling tower. Found out that some portions of base slab (finished) are not properly done especially perimeter of pump foundation and comments between old and new slab concrete. In this regards, Contractor was advised to take corrective action concerning this issue. Please note that this area needs guiding and touch-up for proper finishing work. Subcontractor: finish work between new concrete and old concrete has been grinded to make both concrete in same level(please see attached picture) repair work will be done as per approved method statement or recommended by third party. Daelim did not submit table lifting each joint requiring heat treatment, prior to start of PWHT activities at ARCC Office Fabrication shop, violating RT8S-6500-01 para 8 and ITP checklist SMIC-W-2006 requirement. Contractor: Daelim has submitted PWHT Table request on 25/06/13 prior to start the work 7 coordinates submitted to Company. During material inspection, it has been observed that Subcontractor TCC were installed PSA unit (Valve skid PU-2610) at site. Pressure transmitter manifold and piping system ( PT-261059 & 58) were damaged during handling on lifting time. A.) Daelim shall investigate with extents of damage occurred on piping and instrument system and establish vendor recommended remedy action in order to avoid and further action of discrepancy on system. b.) Daelim shall re-instate the preservation (N2 purging) system immediately to avoid corrosion on valve skid. Subcon: Noted Activities will be taken. N2 has been purged. MOM-68. 11/7/13 Closed During inspection at TCC-2 fabrication facility, it has been observed that there is no Piping Inspector has been deployed for Hold point inspection for the fit-up and spools release inspection. Violation ITP (SMITP-F-001-009) & Schedule Q. Daelim: TCC workshop 2 assigned 4 Piping Inspectors and all inspection done as per approved ITP. 4 pipe inspectors are all available in TCC workshop-2 During Material Receiving Inspection for loose part of PSA unit (FU-2610) it has been observed the following a.) SS and SS alloy material and butterfly valve were directly stored on row wooden box, those material had contacted with potential corrosive blowing sand. b.) Fitter Element (Cellulose) protection cover were destroyed and had open position. c.) Daelim Material and preservation Dept., shall implement a corrective action and take more care to preserve the sensitive material parts at Daelim facility. Violation of equipment protection and preservation plan: RT6-ICS para 215. Contractor: All the inspected valves are put back in the wooden carton. All required preservation protection has been taken. It is found that Pipe spools at TCC-1 are almost completely buried under the sand. Some pipe spools might be already burred and hidden in the sand. Preservation is entirely failed even violations are repeated several times with same problem and always highlighted by Company Inspector. Also found pipes with direct contact with ground with out heat no transferring while cutting into pieces. Relevant Piping Inspector (Mr. Rico) again recommended for revoke. Corrective action with preventive measures are required. Subcontractor: Activities taken. Activity on-going after completion will be informed and pictures will be attached. During fit-up inspection at Furnace F-1160 area, it has been observed that a.) Dimensional discrepancy between vendor fabricated pipe spools. (FPH, economized and conventional coil nozzle. b.) Tack weld were cracked due to over stress and improper fabrication method. c.) ARCC shall verify the orientation and dimensional verification prior to install vendor fabricated pipe spools at site. Subcontractor: ARCC will cut & adjust the Vendor pipe for fit-up alignment and welding as per SI # MFC-SI-DJ-AR-134. PN: During routine site vest, it has been noticed that one of the fastener at radiator isolation valve of transformer TR-103H202A was not fully tighten. Contractor shall re-tighten the fastener prior for the final installation of the transformer. Daelim: Contractor will check the said fastener at the radiator isolation valve if it can be easily tightened but if it's not possible, Vendor shall be contacted and addressed this issue. PN: During surveillance & monitoring activities at Operator Building, it was found out that Subcontractor is not using "measuring box" for proper proportioning of sand & cement mixtures "mortar" but in stead has used shovel only. Subcontractor: Strictly advised to Engineer and Foreman to follow the approved method. Construction has removed the person from site. Advised to Building QC to check time to time and reminded its men. Contractor & Subcontractor did not have heat treatment inspector for ongoing PWHT activities at ARCC office fabrication shop. Violating Sch. Q Attach. VI & ITP (SMITP-W-011-01) requirements. Proactive- Notification was already raised by Company Inspector prior to start of activity Contractor: Both Contractor & Subcon have been assigned PWHT Inspectors in the specified work locations. It has been noticed that coated pipes & spools at TCC-01 off-site coating & blasting facility are almost completely buried under the sand, some pipe spools are contacted with ground without any protection. This is violation against SADARA preservation plan. Root cause analysis & corrective action shall be taken. Subcontractor: One crane is mobilized with rigger crew assigned for the activity after all pipe spools come out from sand and properly preserved, inspection will be offered. PN: Contractor shall verify the Chemical properties of the cable tray splice plates, expansion splice plates and other cable tray accessories of these fittings were alloy 3105 which does not met the requirement as per G7D-0322-00, section 4.3.2. Daelim: Alloy 3105 already accepted by Dow Company Page 24 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 30, 2014 DUE DATE Issued corrective action to Company Target Date S/N LBE NO. PID SUBCON/ CONTRACTOR VAF / PN LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason Company comment Approved Close LBE by Company STATUS CONTRACTOR'S CORRECTIVE ACTION PLAN LBE-TCC-MECH- 249 TCC VAF MECH Piping 29-Jun-13 02-Jul-13 13-Jul-13 18-Aug-13 Closed LBE-TCC-MECH- 250 MR. NASSAR TCC VAF MECH Preservation 29-Jun-13 02-Jul-13 13-Jul-13 4-Aug-13 Closed LBE-TCC-MECH- 251 MR. AMIN TCC VAF 2 MECH Piping 30-Jun-13 03-Jul-13 14-Jul-13 17-Mar-14 Closed LBE-KCC-CIVIL-150 MR. JERRY KCC VAF CIVIL Civil 01-Jul-13 04-Jul-13 15-Jul-13 01-Oct-13 Closed LBE-KCC-CIVIL-151 KCC VAF CIVIL Civil 01-Jul-13 04-Jul-13 15-Jul-13 27-Jul-13 Closed LBE-TCC-MECH- 252 TCC VAF MECH Piping 01-Jul-13 04-Jul-13 15-Jul-13 6-Jul-13 Closed LBE-TCC-MECH- 253 TCC PN MECH Quality Records 01-Jul-13 04-Jul-13 15-Jul-13 14-Jul-13 Closed LBE-TCC-MECH- 254 MR. NASSAR TCC VAF MECH Coating/ Painting 01-Jul-13 04-Jul-13 15-Jul-13 04-Dec-13 Closed LBE-TCC-MECH- 255 MR. HARIKUMAR TCC PN MECH Material 02-Jul-13 05-Jul-13 16-Jul-13 24-Oct-13 Closed 1 LBE-TCC-INST-050 MR. SHABIRUL TCC PN 1 INST Instrumentation 03-Jul-13 06-Jul-13 17-Jul-13 16-Jul-14 Closed LBE-AMA-ELECT- 051 AMA PN ELECT Electrical 03-Jul-13 06-Jul-13 17-Jul-13 27-Jul-13 Closed LBE-TCC-MECH- 256 MR. NASSAR TCC VAF MECH Coating/ Painting 05-Jul-13 08-Jul-13 19-Jul-13 4-Aug-13 Closed LBE-DLM-MECH- 257 DAELIM PN MECH Preservation 05-Jul-13 08-Jul-13 19-Jul-13 1-Sep-13 Closed LBE-KCC-CIVIL-152 KCC PN CIVIL Civil 06-Jul-13 09-Jul-13 20-Jul-13 02-Sep-13 Closed LBE-TCC-MECH- 258 TCC PN MECH Piping 06-Jul-13 09-Jul-13 20-Jul-13 27-Jul-13 Closed LBE-TCC-MECH- 259 MR. AMIN TCC PN MECH Piping 06-Jul-13 09-Jul-13 20-Jul-13 10-Nov-13 Closed LBE-TCC-MECH- 260 MR. AMIN TCC VAF MECH Piping 06-Jul-13 09-Jul-13 20-Jul-13 08-Nov-13 Closed LBE-AMA-CIVIL-153 AMA VAF CIVIL Civil 08-Jul-13 11-Jul-13 22-Jul-13 05-Sep-13 Closed It is found that activity fit-up being performed by TCC team at TCC facility #1 is inadequate especially for large bore pipes & fittings. In stead to rectify the ovality, equally dividing the HI-LO, tampering the excess thickness as per requirements & using proper clamps or jacks, fabricators and fitters are just grinding and reducing the thickness of loose metal. Subcontractor: On-going. TQ with Daelim. Piping QC Supervisor. Excessive grinded pipe has already replaced. High-Low TQ is on-going. With reference clarification from SME (Subject Matter Expert), Bed Color above paving of U/G electrical cables is required per RT2S-3001-01, section 2.6.7. Please advise and discuss with your Construction group this requirement. One slab is already poured north of Flare pipe racks where this situation occurred despite of previous discussion. Contractor: Drawing was already issued to Subcontractor (A554-E-103-CV-SPC-C99-001, REV. 3) It was noticed during monitoring that the installed HDPE liner for containment slab of Equipment V-1690 area has punctured. The HDPE liner shall be checked and tested again to ensure no damage has been done on the membrane prior to install R & B. Contractor: The installed HDPE liner that was damaged was already rectified. Welding and vacuum tests were done, pictures attached. During routine inspection at TCC-2 off-site fabrication facility for Stainless Steel (SS) pipes, it was observed that oxygen analyses are not used to verify purging in the SS pipe around the joints, violating project procedure A554-E-103-QA-GEN-PRO-056, Para. 14.3.11 & WPS requirements. Subcontractor: TCC QC team has informed Construction group and will be provided soon. O2 analyzer is available at workshop-2 During inspection at site (T-1910) observed that following Coating damages on 6" HC-35 (P- 19140505C). Coating adhesion is doubtful, several damaged observed due to improper handling/transportation. Advised for adhesion test prior to install subject pipe spools on T-1910, Equipment. Verify remaining coated spools for conforming in-adhesion with same coating system. Subcon: Noted. Test - on-going. After getting report, copy will be provided or attached. Test was failed. All pipe related with this LBE will be re-blasted. It has been noticed that TCC subcontractor has applied coating on the damaged area for T-1910 by another manufacturer's product (interthem) instead of original manufacturer's product (Amer coat91). This is violating Sadara specs. #G16S-0201-11. Subcon: Noted. Action will be taken. next time all touch-up and repair will be carried out with same manufacture. PN: During Material Receiving inspection of splash deck trays for F-1410 (Internal Parts). *SS & SS alloy materials were stored on broken/damaged wooden box. Those SS Materials have had conducted with potential corrosive blowing sand. * Daelim Quality & Preservation Team to take necessary corrective action and more care of sensitive material handling. Contractor: Sand has been removed inside the affected wooden bozes and tarpaulin are placed to cover the damaged wooden boxes to avoid sand entry PN: With regards to surface preparation of internal or sumps prior to painting with RT-APCS-2B waiting system, please be aware of the requirements of document no. A554-K-PRG-PI-SPC-VIA-142 (RT-APCS- 2B) Para. 3 "Surface Preparation requirements". Contractor: As per SAES-H-003, Para. 7.2.1.1 for surface preparation requirements for concrete, scouring the surface to remove any protrusions and sharp edges by using an abrasive bricks (carborundum), power grinding or power brushing. For old concrete surface preparation, as per SAES-H-003, Para. 7.3.1, remove all loose concrete, surface contaminations, sealants & old coatings by abrasive blistering (or other mechanical means) and or hot water with pressure washing as appropriate, prior to making concrete repairs and coating application, pictures attached. RTAPCS-2B. PN: During material receiving inspection of acetylene reactors (R-2025, R-2030 & R-2035) observed the following discrepancies: CJ2 Procedure Lose observed on R-2035. (Pressure level is showing zero); An open punch item was not yet closed during orientation of Heck nozzle; for R-2030 and R-2035); Daelim/TCC shall provide corrective action for Re-orientation of nozzle spools as per GA/IFC drawing and re-establish the original purging state for all Equipment to comply with the project preservation requirements (SP:RT-6-ICS). Subcon: Noted. Action will be taken. PN: During surveillance at TCC site, installed PSA unit valve skid PU-2610 A/B observed that Pressure Transmitter Manifold and Piping system PT-261059 & PT-261079 and solenoid valve air exhaust filter were damaged due to improper handling & lifting. Daelim shall investigate the extents of damage occurred on piping & instrument system with Vendor recommended method in order to avoid any further functional discrepancy. Daelim: Contractor has already issued NCR and Company will be notified regarding the corrective action and response of Vendor's recommendation for the said damaged. PN: During surveillance, it was noticed that Installed Grounding cable is damaged at several locations under E/W Furnace Pipe rack. Forklift was continuously passing through grounding cable . Column #43, 44 provide wooden box for grounding cable protection and avoid any damaged grounding cable. Daelim: Subcontractor already notified regarding the cable (grounding) that needs protection which will be provided by them. During surveillance at TCC-2 off-site fabrication facility, it was observed that pipe spools are not welded as per IFC drawing No. N016103L4A-CA-280101-01 & 02 the material grade given in IFC & fabricated spools do not match. As per IFC drawing method of pipe is 106-hv.B where fabricated spool is A106.hv & NACE. The color coding & IFC has not been followed during fabrication. Daelim: This issue was noted and made a log in Contractor Internal Logbook, LBE # TCC-FS-2- 28, on 26/6/2013, as a corrective action from Contractor all the joints will be cut out and re- fabricated as per approved ITP and IFC drawing. PN: During review for welding RFI (MFC-DLM-TCC-WE-453) It was observed that unauthorized Daelim Contraction personnel is making changes in IFC approved drawing (016103A-PR-250601-01, Rev.1) without involvement of Daelim Engineering for red marking of modification of changes to the drawing. Subcon: For revise the ISO drawing. Sadara approved procedure will be followed. Construction group already informed. During routine inspection at TCC-1 Off-site blasting & coating facility, it has been observed that blowing dust during vehicles & forklift movement and wind since the area close to priority to painting workshop. Therefore, SQIT representative requested from Subcontractor to put concrete or aggregate on the floor to avoid blowing the dust. Subcon: Construction group has been informed and action will be taken. Small stone are already layer on main entrance of workshop T-1 painting works. During inspection of foundation for FL-1423 A/B for Formworks, rebar and embedment's, the installed Anchor Bolts cannot be explained by both Amana & Daelim surveyors with regards to the Orientation as shown in Dwg. # A554-E-103-CV-DWG-C30-159, Rev. 1B. The filter foundation schedule shows various orientation in degrees of all anchor bolt as detailed in various types. Contractor: With regards to this issue, Daelim & Amana surveyors counter-check the Anchor bolt orientation. PN: It is found that fabrication team @ TCC-1 has started the fabrication for NACE piping, therefore, Daelim quality needs to make sure that different materials are segregated and identified separately in all stages to avoid mishandling & measure of NACE materials with CS or LTCS materials. Subcontractor: Noted. TCC all piping and welding inspectors are informed about new activity in workshop 1, all required precautions will be taken. PN: It is found that Fabrication team @ TCC-1 has started the fabrication for SS Piping, therefore, Daelim quality team needs to ensure that following activities are being performed as per Sadara & relevant standards and specs: 1. Preservation before, during and after fabrication; 2. Cutting works; 3. Fab. and Fit-up under tolerance; 4. Welding, interpass temperature, Heat input; 5. Purging + O2 monitoring by calibrated oxygen analyzers inside the SS joints; 6. Marking by Low Chloride markers; 7. Piping, Fittings and Spools staging, etc. Subcontractor: Noted and one tool box meeting was held in TCC workshop #1 regarding S.S. Pipe work starts. All required precautions will be taken during and after fabrication of S.S. pipe materials and spools. During surveillance at TCC Fab. Facility-2 found following violations: 1. Welder (TCC-ISS/JCC#489) was using the portable quiver without power cable for low hydrogen electrodes; 2. 36" dia. Flange to pipe joint found welded joints having 6.5mm & 3mm high-lo in different two locations and accepted by TCC & Daelim Quality inspectors. Subcontractor: Noted. Working given to the welder. TCC welding inspector will improve their surveillance and make sure all welders make their portable ovens, plug-in wind protection. This point will be discussed in the coming tool box meeting with welding supervisor and welders in TCC workshop 2. Page 25 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 30, 2014 DUE DATE Issued corrective action to Company Target Date S/N LBE NO. PID SUBCON/ CONTRACTOR VAF / PN LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason Company comment Approved Close LBE by Company STATUS CONTRACTOR'S CORRECTIVE ACTION PLAN LBE-GLOBAL- MECHL-261 MR. NASSAR GLOBAL VAF 2 MECH Quality Management 08-Jul-13 11-Jul-13 22-Jul-13 23-Feb-14 Closed LBE-KCC-MECH- 262 MR. NOOR KCC VAF MECH UG-RTR 08-Jul-13 11-Jul-13 22-Jul-13 27-Jul-13 Closed LBE-PSCL-MECH- 263 MR. AMIN PSCL VAF MECH Mechanical 08-Jul-13 11-Jul-13 22-Jul-13 8-Oct-13 Closed LBE-PSCL-MECH- 264 MR. AMIN PSCL PN MECH Quality Records 08-Jul-13 11-Jul-13 22-Jul-13 8-Oct-13 Closed LBE-TCC-MECH- 265 TCC VAF MECH Mechanical 10-Jul-13 13-Jul-13 24-Jul-13 27-Jul-13 Closed LBE-TCC-MECH- 266 TCC VAF MECH Mechanical 10-Jul-13 13-Jul-13 24-Jul-13 27-Jul-13 Closed LBE-TCC-MECH- 267 MR. KURIAN TCC PN 2 MECH Mechanical (Equipment) 10-Jul-13 13-Jul-13 17-May-13 20-Jul-13 Closed LBE-AMA-CIVIL-154 AMA PN CIVIL Civil 11-Jul-13 14-Jul-13 25-Jul-13 05-Aug-13 Closed LBE-KCC-CIVIL-155 KCC VAF CIVIL Civil 13-Jul-13 16-Jul-13 27-Jul-13 01-Aug-13 Closed LBE-TCC-MECH- 268 TCC VAF MECH Piping 14-Jul-13 17-Jul-13 28-Jul-13 27-Jul-13 Closed LBE-AMA-CIVIL-156 AMA VAF CIVIL Civil 16-Jul-13 19-Jul-13 30-Jul-13 29-Jul-13 Closed LBE-ASYAD-MECH- 269 MR. KURIAN ASYAD VAF MECH Instrumentation 16-Jul-13 19-Jul-13 30-Jul-13 06-Jan-14 Closed LBE-ASYAD-MECH- 270 MR. KURIAN ASYAD PN MECH Quality Records 16-Jul-13 19-Jul-13 30-Jul-13 06-Jan-14 Closed LBE-TCC/ARCC- MECH-271 TCC VAF MECH Coating/ Painting 17-Jul-13 20-Jul-13 31-Jul-13 4-Aug-13 Closed LBE-ARCC-MECH- 272 MR. NASSAR ARCC VAF 2 MECH Preservation 17-Jul-13 20-Jul-13 31-Jul-13 16-Feb-14 Closed LBE-ARCC-MECH- 273 MR. NASSAR ARCC VAF MECH Preservation 17-Jul-13 20-Jul-13 31-Jul-13 29-Sep-13 Closed LBE-TCC-MECH- 274 MR. AMIN TCC VAF MECH Piping 18-Jul-13 21-Jul-13 01-Aug-13 Closed 28-Aug-13 Closed LBE-KCC-CIVIL-157 MR. GERALD KCC VAF CIVIL Civil 21-Jul-13 24-Jul-13 04-Aug-13 27-Jul-13 Closed LBE-ASYAD-INST- 275 MR. KURIAN ASYAD VAF 2 INST Instrumentation 22-Jul-13 25-Jul-13 22-Feb-14 Closed LBE-AMA-CIVIL-158 MR. GERALD AMA PN CIVIL Civil 22-Jul-13 25-Jul-13 05-Aug-13 24-Sep-13 Closed LBE-ARCC-MECH- 276 MR. NASSAR ARCC VAF MECH Coating/ Painting 22-Jul-13 25-Jul-13 05-Aug-13 29-Sep-13 Closed During witness inspection of Plumbness found that some temporary curvature plate attachments are not removed prior to inspection & found a buckle at 2nd horizontal joint near temporary attachments. Also measured Banding at buckle area is more than the acceptance criteria of API-650. Buckle/distorted area to be checked for plumbness, flatness and banding measurements. Subcontractor: Company representative has witnessed and inspected the buckle area of Tank V0500A. The reports are submitted to Company for approval. PN: It is advised to Daelim & Petrol Steel to close all the lob book entries logged by Quality team of Subcontractor, Contractors and Company about MFC Tanks prior to Hydrotest to avoid any discrepancy and delay in job. Also recommended to complete all the quality documents and their data status of all the inspection and NDE requirements as per applicable standards and specification making sure that none of the activity or inspection is overlooked. Subcontractor: Noted. Petrol Steel has submitted prior to Hydrotest all the documents for review. During routine inspection at TCC-2 fabrication facility, it was observed that low chloride are not used for heat number & other data transfer on NACE or LTCS pipes. This is a clear violation against Sadara procedure A554-E-103-QA-PRO-056. Subcontractor: Noted and one tool box meeting was held with Piping Group in workshop 2 relative to the issue. Piping Supervisor and TCC Piping Inspectors will make sure use proper marker for transferring data on LTCs and NACE's pipes. During routine inspection, it was observed that insulation Crew Supervisor is not available at site during insulation activities at T-1910 Debutanizer, violating Schedule "Q" requirements. During witness inspection of FRP-U/G Line stress reinforcement lamination defects on items such as voids, air bubbles and improper lamination at T intersection point for up and down side. Found that Contractor/Subcontractor have accepted the joints and raised RFI's without inspection. Corrective action with preventive measures is required. Subcontractor: The defects that was found were re-grinding and re-shaving to remove the air bubbles & voids and do the proper lamination. RFI was raised and accepted by the Company. KCC QC inspector was informed to check & inspect the area before raising the RFI. During the surveillance at PIB Building, ASYAD welders (no. W#3160, 2268) were found using quivers without calibration and not heated to 65c with welding rods in it. Violation as per A554-E-103-QA-GEN- PRO-056, Para. 9.2. Subcontractor: Asyad Welder is welding with calibrated quiver and maintain minimum temperature of 65c as per A554-E-103-QA-GEN-PRO-056. PN: During inspection at PIB structural support for cable tray were found modified without AS-Built which can be done with proper technical query. Drawing E-016103-DB-00A-IC-135-001, revision 2. Subcontractor: In PIB Structural support for cable tray, Asyad is using modified with As-Built drawing No. DRW-E-016103-DBOOA-IC-135-001. During surveillance at site, it has been observed too many coating damages for pipes & spools due to poor handling & internal transpiration of pipes & spools done by truck without proper protection such rubber pads. Subcontractor: TCC Construction group has been informed. More precautions will be taken curing painting the pipe spools shifted at site. ARCC Construction group had been advised & will do some precaution to avoid damage on painted spools. During inspection of D-2190 (Perimeter Wall) as west side of N-s Pipe rack, it was found out that anchor bolt length was not shown on the detailed drawing, wherein the diameter & projection are reflected on the plan. Contractor is advised to clarify the anchor bolt length for the Engineering point of view and tale corrective action prior to place/pouring of concrete for the said structure. Subcontractor: In the drawing of D-21090 (Perimeter wall) the Anchor Bolt projection, size & type were shown. The length of Bolt can be found in drawing # A554-E-103-CV-599-402 Rev. 2 (Standard details of Anchor Bolts schedule). During inspection at TCC-2 fabrication facility, it was observed that damaged pipe was used for fit-up without Company notification. Moreover, damaged pipe was not kept in quarantine area or separated from other non-damaged pipes 35" damaged pipe was used for fir-up without following approved procedure. Subcontractor: Noted. All damaged pipes will be transferred in quarantine area. Piping Inspector will make sure during Fit-Up inspection, all pipe lengths and fittings should be free from any damage. All inspectors will be informed by TCC QC Manager. During monitoring & surveillance inspection at air compressor shelter (pedestals), found but newly casted pedestal & removal renewal of formworks are insufficient. Concrete curing application. This is a violation to RT2S-3001-01, Para. 9.1.2. Contractor is advised to take corrective action on this issue. Contractor shall provide drum for stock of water for easy curing application. Subcontractor: Monitoring of curing for newly casted concrete , Amana has assigned a person to monitor all concrete which is under curing period. Advised Construction to provide empty drums to have small structure cured by this drum water. Also, extended the during period from 7 days to 9 days. During the Material Receiving inspection for tail Gas silencer (SL:2610) water found collected waste the equipment also the nitrogen pressure found (0.01) both are violation as per RT-6-ICS and A554-E-103- QA-GEN-PRO-035 Subcontractor: Noted. Action will be taken accordingly. PN: Heat Exchange installed on anchor bolt whose thread not extended to the base plate of support (leg) which have a standard washer 3mm only. Clarification required for rectification. Subcontractor: Noted. Action will be taken accordingly. PN: During inspection of Pedestal at Liquid Furnace area F-1240, F-1250 and Gas Furnace area F-1140 3 nos. small pedestals, found out that some pedestals have insufficient spacing prior to ground works. Contractor is advised to take corrective action concerning this issue. Contractor is reminded that prior to inspection, materials should be prepared the same like ice & others prior to execute the works. Subcontractor: Advised Grouting group to monitor sealing properly prior to inspection and grouting. It has been noticed that ARCC/OTC blasting/coating facility stored blasting activity without approval of blasting facilities. Ref RFI No. MFC-DLM-ARCC-H-0551. Subcontractor: The issue has been elevated/escalated to NCR-ARCC-MECH-012, issued by Contractor to ARCC. During surveillance and monitoring inspection at G-1123 Expander Building along Roof sub-station, it was found out that newly casted "Screening" has no sufficient water curing application and also burlap & polyethylene sheet are not properly arranged. Contractor: Burlap and plastic sheet were arranged together with container full of water. Mason crew was assigned to do the curing continuously. Curing period was extended for 2 more days. During surveillance at SENDAN & ASYAD consumable control room is found without humidity measuring instrument. This is violation as per 15.8.1 of A554-E-103-QA-GEN-PRO-056. Corrective action is required as per the Standard's requirements. Subcontractor: ASYAD has to arrange the digital temperature with calibration properly. PN: During inspection at foundation for ground flare (FS-0353) row 16 to 19 (SP-4 & SP-15) 12 nos. has been observed that some formworks being used are not in good quality "Old Formworks". In oder to maintain good quality of concrete surface, Contractor/Subcon needs to use new and good quality of formworks. Subcontractor: Damage formwork being used are replaced with good plywood. Work has been done and inspected against RFI No. During routine inspection at ARCC/OTC blasting/Coating facility for pipes & spools, it has been observed that inadequate dust management or protection during vehicles & forklift movement operation and strong wind condition. Subcontractor: The issue has been elevated/escalated to NCR-ARCC-MECH-011, issued by Contractor to ARCC. It has observed that OTC blasting/coating facility mixed with coating materials of MFC Project with some other project. This is violation against schedule "Q". Subcontractor: The issue has been elevated/escalated to NCR-ARCC-MECH-011, issued by Contractor to ARCC. It is observed that TCC-1 welding SS joints without proper monitoring of purging and heat input. TCC do not have O2 analyzer and heat input measuring tools. It is a violation as per A554-E-103-QA-GEN-PRO- 056 Para. 14.3.11 and WPS requirements. Corrective action with [preventive measures are required. Subcontractor: Noted. Action will be taken accordingly. Page 26 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 30, 2014 DUE DATE Issued corrective action to Company Target Date S/N LBE NO. PID SUBCON/ CONTRACTOR VAF / PN LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason Company comment Approved Close LBE by Company STATUS CONTRACTOR'S CORRECTIVE ACTION PLAN LBE-TCC-MECH- 277 MR. AMIN TCC VAF MECH Piping 23-Jul-13 26-Jul-13 06-Aug-13 8-Oct-13 Closed LBE-DLM-MECH- 278 MR. NOOR DAELIM VAF MECH Preservation 26-Jul-13 29-Jul-13 09-Aug-13 24-Aug-13 Closed LBE-DLM-MECH- 003 MR. IMTIYAZ DAELIM VAF 1 MECH Preservation 21-Jul-13 24-Jul-13 04-Aug-13 Closed 12-Jan-14 Closed LBE-ARCC-MECH- 004 MR. IMTIYAZ ARCC VAF 1 MECH Preservation 21-Jul-13 24-Jul-13 04-Aug-13 Closed 12-Jan-14 Closed LBE-DLM-ELEC- 001 MR. MARK DAELIM VAF 1 ELECT Preservation 27-Jul-13 30-Jul-13 10-Aug-13 Closed 11-Nov-13 Closed LBE-DLM-MECH- 279 MR. AMIN DAELIM VAF MECH Preservation 28-Jul-13 31-Jul-13 11-Aug-13 8-Oct-13 Closed LBE-ARCC-MECH- 280 MR. NASSAR ARCC VAF MECH Coating/ Painting 28-Jul-13 31-Jul-13 11-Aug-13 29-Sep-13 Closed 1 LBE-DLM- MECH-281 MR. KURIAN DAELIM (Procurement) VAF 2 MECH Material 28-Jul-13 31-Jul-13 11-Aug-13 Open LBE-AMA-CIVIL-159 AMA PN CIVIL Civil 29-Jul-13 01-Aug-13 12-Aug-13 07-Aug-13 Closed LBE-KCC-CIVIL-160 MR. GERALD KCC PN CIVIL Civil 29-Jul-13 01-Aug-13 12-Aug-13 15-Aug-13 Closed LBE-TCC-INST-052 MR. SHABIRUL TCC VAF INST Instrumentation 31-Jul-13 03-Aug-13 14-Aug-13 15-Sep-13 Closed 2 LBE-DLM- MECH-283 MR. KURIAN DAELIM (Procurement) VAF 2 MECH Material 01-Aug-13 04-Aug-13 20-Jul-14 Open LBE-GLOBAL- MECH-282 MR. NASSAR GLOBAL VAF 2 MECH Insulation 02-Aug-13 05-Aug-13 16-Aug-13 23-Feb-14 Closed LBE-KCC-CIVIL-161 MR. GERALD KCC PN CIVIL Civil 05-Aug-13 08-Aug-13 19-Aug-13 21-Aug-13 Closed LBE-SEN-ELECT- 053 MR. MARK SENDAN PN ELECT Electrical 05-Aug-13 08-Aug-13 19-Aug-13 10-Nov-13 Closed LBE-ARCC-MECH- 284 MR. NASSAR ARCC VAF MECH Quality Records 05-Aug-13 08-Aug-13 19-Aug-13 29-Sep-13 Closed LBE-AYTB-MECH- 285 MR. KHAN AYTB VAF MECH Piping 05-Aug-13 08-Aug-13 19-Aug-13 19-Oct-13 Closed LBE-AMA/KCC- CIVIL-162 MR. GERALD AMA/KCC PN CIVIL Civil 06-Aug-13 09-Aug-13 20-Aug-13 01-Oct-13 Closed Discoloration is ovserved on SS weld joints at TCC-1 Fab. Facility which is a violation to AWS C5.5, D10.4 and D18.2 corrective action with preventive measures are required. Subcontractor: Preservation will be provided prior to spool release for Blasting & Painting. During surveillance inspection at Daelim MFC warehouse observed that Resin (Total 64 drums of epoxy vinyl ester 411-45) material was stock piled at MFC Laydown Facility in open area under direct sunlight @ 44c. As per manufacturer data sheet, Resin shall be stored indoor in dry place away from direct sunlight between the temperatures 10c to 25c. Contractor: Noted. All the epoxy resin drums are stored inside the A/C room andd also lamination kits stored inside the A/C room. Room temperature is monitored and noted. The wearehouse people are advised to take care the materials. PN: During inspection at transformer foundation prior to grouting at substation G1121 along four locations, it was found out that (4) installaed anchor bolt were imporperly installed, touching the upper portion. Subcontractor: Subcontractor has already rectify the anchor bolt for the transformer pad. PN: During inspectionfor rebar & formworks at lightning pole footing at KCC pre-cast area, it was found out that some formwork materials used are not in good quality and/or condition where an old formwork was re-utilized which has resulted to poor workmanship. Contractor: Overused form works were segregated and sent to KCC central warehouse for dumping. Good & still usable forms were installed & applied form oil. During site surveillance, it has been noticed during pipe erection of TCC at north/south pipe rack, columns #33, 34, 36, 37, installed Instrument cable tray was damaged by TCC. A violation as per Schedule "Q", Para. 3.6, attachment IV. Daelim: SQDR has been issued by Contractor and under discussion with the concerned party who damaged the cable trays as well as the replacement. Company will be notified on the action, sonnest. Several violations observed at Daelim Laydown yard. 1. Daelim does not have material receiving inspector, 2. Some SS Pipe Fittings are kept in open atmosphere without protection from cross- contamination. 3. Some CS Pipe Fittings are not elevated above the ground and above the max water run-off. 4. Some pipe ends are not covered and protected from entry of rain and foriegn matters. 5. Few shipping containers are damaged under the other over layered containers. After removal from downside, detail inspection shall be required for any kind of damage. Contractor: Material Inspection is approved and already doing the work. All the SS materials were kept properly. Maximum were issued to Fab.Shops. Wooden piece were provided with all pipes at ground. All pipe ends were covered. Damaged pipes shifted to quarantine area. During routine inspection at ARCC/OTC blasting/coating facility, it has been observed that said facility is using recycled garnet for blasting. This is violating Sadara Standard and Q.C workshop procedure. Subcontractor: OTC removed the contaminated & used garnet in blasting . ARCC raised RFI for the cleanliness of blasting pot. Escalated/elevated to Daelims NCR-ARCC-MECH-014 Material receiving inspection at Daelim laydown yard revealed cooling tower accessories supplied bt SPIG (internal & external plates) were found damaged. Square tubes were stocked improperly. All these accessories are made of FRP materials without proper maintainance. Contractor: These items were verified with Sadara Inspector in the presence of SPIG of personnel that external/Internal plates material with damaged parts shall be repaired as per procedure. SPIG will submit the work procedure to Daelim and Sadara prior to start the repair work. Target date: 3 weeks. The following Equipment are lacking the preservation requirements from the TCC scope in site. The N2 level is "zero", Daelim Construction/TCC has to take immediate necessary corrective action for these lacking equipment. The tag nos. are D-1530, D-1607, E-1606, FL-0905 A/C/D, D-0627 & D-2509. Contractor: Equipment have been verified and confirmed by Vendor/manufacturer that N2 is only for shipping and long storage, once the equipment installed at site, N2 are no longer required as per Vendor recommendation. The Steam Drum D-1210 and D-1230 are found with "zero" N2. This is a preservation violation. ARCC has to take immediate corrective action for filling the N2 to meet the preservation requirements. Contractor: Furnace SME Mr. Frederick Gerald verified and confirmed that all Steam Drums, TLE's and other Static Equipment installed at site were no longer required N2 as per email converstaion/query. During routine site visit at Daelim's warehouse, it was noticed that the Contractor has not yet energized the space heater of the motor control center that arrived last July 23, 2013 which is a violation as per RT- 6-1CS, section 2.9.1c in which the equipment with furnished space heater shall be connected to a continuous power source upon arrival at site. Contractor: Not required. MCC has no space heater. PN: During surveillance & monitoring activities at site, it has been observed that some newly casted structures have no "marking or signboards" wherein can easily monitor or check proper curing application for the said structure.Contractor is advised to take corrective action in this issue and must provide signage with structure name if when it was casted date and when is the 7 days finish for proper curing application or implementation at site. Subcontractor: Curing tags were present for the newly casted areas. PN: During inspection at substation G-1121 transformer yard, it was found out during the bolt tightening that once of the bolts for transformer anchorage was loose thread. RFI was rejected and Contractor was advised to replace the bolt and raise new RFI for the final acceptance for the installation of transformer TR-103H201A. Daelim: Anchor bolts will be replaced and Company will be notified again thru RFI. It has been repeatedly observed that ARCC is not paying attention in preparing reports with reference to NCR No. 15 & 16 issued by Contractor and it has come to notice that ARCC painted 75 spools during adverse weather condition and un-acceptable temperatures. ARCC is advised to submit immediate corrective action on the issue. Subcontractor: ARCC corrected the wrong data & used the approved format & resubmitted the report to Daelim. Escalated/elevated to NCR-ARCC-MECH-016. During inspection at AYTB fabrication shop, it was observed that damaged pipes are used for fit-up without notifying Company Inspector. LBE-268 was already looged for the same issue. Contractor: NCR was issued by Daelim to Material department . Corrective action has been taken by Daelim warehouse group. TQ has been issued by Engineering and will response some time in Nov. 2013. During material receiving inspection at site revealed that plates with plates secondary transfer live exchanger (E1122) supplied by ALSTDM having distorted nameplate occurred due to improper lifting or transportation violation as per A555-E-103-QA-GEN-PRO-0353, para 8.2.1. Contractor: Regarding ladder rung which has corroded at sump pit #645, Company has already issued NCR to Contractor. As per advice by Sadara Inspector, Amana has started the cleaning/grinding work of ladder rung of sump-0645. Amana will rectify the coating as per recommendation od Company. During routine inspection at T-1510 Process Condensate Stripper has been observed that Insulation activities are going-on during sandstorm. PN: During inspection for formworks at (Center & West side wall) open ditch (0635-D1500-014) at south side of sump pit # 0636, it has been observed that some forworks installed are not in good quality "old formworks". Contractor is advised to take corrective action to make sure that after removal of formworks, the surface of concrete is acceptable or good quality & properly implemented. Subcontractor: Overused forms were segregated so that it can not be used anymore. Forms that are still usable were applied by form releasing agent. Page 27 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 30, 2014 DUE DATE Issued corrective action to Company Target Date S/N LBE NO. PID SUBCON/ CONTRACTOR VAF / PN LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason Company comment Approved Close LBE by Company STATUS CONTRACTOR'S CORRECTIVE ACTION PLAN 3 LBE-DLM- MECH-286 MR. KURIAN DAELIM (Procurement) VAF 2 MECH Material 06-Aug-13 09-Aug-13 20-Aug-13 Open LBE-DLM-MECH- 287 MR. KURIAN DAELIM VAF 2 MECH Mechanical (Equipment) 06-Aug-13 09-Aug-13 20-Aug-13 31-Mar-14 Closed LBE-SEN-ELECT- 054 SENDAN VAF ELECT Electrical 07-Aug-13 10-Aug-13 21-Aug-13 29-Aug-13 Closed LBE-ARCC-MECH- 288 MR. KURIAN ARCC VAF MECH Structural 07-Aug-13 10-Aug-13 21-Aug-13 31-Oct-13 Closed LBE-DLM-MECH- 289 DAELIM VAF MECH Material 07-Aug-13 10-Aug-13 21-Aug-13 11-Aug-13 Closed LBE-TCC-MECH- 290 MR. KURIAN TCC PN 2 MECH Structural 07-Aug-13 10-Aug-13 21-Aug-13 18-Feb-14 Closed LBE-TCC-MECH- 291 MR. KURIAN TCC PN 2 MECH Structural 07-Aug-13 10-Aug-13 21-Aug-13 23-Mar-14 Closed LBE-TCC-MECH- 292 MR. KURIAN TCC PN 2 MECH Piping 07-Aug-13 10-Aug-13 21-Aug-13 18-Feb-14 Closed LBE-KCC-MECH- 293 MR. NOOR KCC VAF MECH UG-RTR 11-Aug-13 14-Aug-13 25-Aug-13 21-Aug-13 Closed LBE-DLM-CIVIL-163 MR. GERALD DAELIM PN CIVIL Civil 11-Aug-13 14-Aug-13 25-Aug-13 02-Oct-13 Closed LBE-DLM-CIVIL-164 MR. GERALD DAELIM PN CIVIL Civil 13-Aug-13 16-Aug-13 27-Aug-13 15-Sep-13 Closed LBE-SEN-ELECT- 055 MR. MARK SENDAN PN ELECT Electrical 13-Aug-13 16-Aug-13 27-Aug-13 11-Sep-13 Closed LBE-SEN-ELECT- 056 MR. MARK SENDAN VAF ELECT Electrical 14-Aug-13 17-Aug-13 28-Aug-13 11-Sep-13 Closed LBE-TCC-MECH- 294 MR. AMIN TCC VAF 2 MECH Piping 14-Aug-13 17-Aug-13 28-Aug-13 Send spool storage plan through Daelim. (29/09/13) 23-Mar-14 Closed LBE-AMA/KCC- CIVIL-165 MR. GERALD KCC VAF CIVIL Civil 15-Aug-13 18-Aug-13 29-Aug-13 09-Sep-13 Closed LBE-DLM-MECH- 295 MR. KURIAN DAELIM VAF 2 MECH Material 15-Aug-13 18-Aug-13 29-Aug-13 17-Feb-14 Closed 4 LBE-DLM- MECH-296 MR. KURIAN DAELIM (Mat. Dept) PN 2 MECH Mechanical (Equipment) 17-Aug-13 20-Aug-13 15-Jul-14 Info LBE-DLM-MECH- 297 MR. KURIAN DAELIM PN MECH Preservation 17-Aug-13 20-Aug-13 31-Aug-13 14-Sep-13 Closed LBE-SEN-ELECT- 057 MR. MARK SENDAN VAF ELECT Electrical 17-Aug-13 20-Aug-13 31-Aug-13 11-Sep-13 Closed LBE-AMA-CIVIL-166 MR. GERALD AMA PN CIVIL Civil 18-Aug-13 21-Aug-13 01-Sep-13 24-Sep-13 Closed During Material receiving inspection of C3R 4th stage suction drum (D2508) supplied by DOOSAN found corroded in the skill portion of the equipment which require better preservation to avoid further degradation as per A554-E-103-QA-GEN-PRO-035, Para. 8.2.5. Corrective action required. Contractor: Noted. Action shall be taken and as per Construction Plan for the corrosion, painting touch-up repair shall be commenced/implemented. Target Date: 25 Nov. 2013. Most of the equipment foundation at MFC site found with achor bolt threads not covered with duct tapes or suitable means to keep them clean and to prevent any damage. Violation as per A554-E-103-QA- GEN-PRO-035 Para. 10.1.5. Corrective action is required. Subcontractor: Noted. Actions will be taken. Anchor bolt for the equipment foundation shall be covered with duct tape and plastic for protection to dirt and damage. Target date: 25th of October 2013. Site container storage for FRP Materials found following violations: *External shaded: NHO Bitumastic Drum open. The storage temp req. is 5C to 30C unopenned. *Internal container storage: No power *Temp gauge reading 117F = 47-22C. Derakane Resin storage req. 10C to 25C *Log, not maintained. *Housekeeping poor potential fire hazard, reference Sadara Spec RT-6-ICS, Para. 2.9.10 and manual Recomemended storage req. Subcontractor: Nitoproof 100 & BASF materials are already transferred to other container van with air-conditioning. PN: During inspection of foundation E-1602 at south side of C, G compressor, it was found out that No Contractor Surveyor to double check or counter check the survey data from subcontractor if it does comply with IFC drawing. Subcontractor: Contractor surveyor I s absent, during the inspection but the IFC drawing reference used was corrent as per contractors record. On the following afternoon contractor surveyors had cross checking . PN: During surveillance and monitoring activities at site, it was noticed that from Aug. 8 - 13, 2013, no one from Contractor represetative witnessed the crushing/breaking of concrete cylinder & cube samples at Osaimi, Jubail branch as confirmed by Osaimi staff and its assigned Technicians. Contractor: QCI for Batch Plant, Mr. Ronald, has been assigned to witness daily compressive strength testing at Al-Osaimi, Jubail 1 Satellite Lab. PN: During surveillance at E-W pipe rack structural welder (TCC-60) found using quiver without calibration sticker on it. Subcontractor: Noted. TCC welding inspector will monitor continuously for all calibration stickers which may be old or unable to recharge. PN: Mismatching of the dimension between embeded and gusset plate structural causing extended point of the gusset plate outside embeded plate without welding at E-W pipe rack near CU compressor. Engineering clarification required. Subcontractor: Noted. Action will be taken accordingly. PN: Pipe spool welded for T-1820 were found with joints without welder no. (identification). Subcontractor: Noted and area inspectors will make sure for all weld's uniform action. During routine site inspection of installation of EMT conduits inside substation G-1120, it was noticed that the EMT conduits were not reamed-off by the Contractor during cutting of conduits which is violation as per NEC 358.28(A). Daelim: Subcontractor already informed to ream the edge of EMT conduit. Once the activity is done, RFI will be raised to Company for the closure of the LBE. Angle piece provided between lower transition duct and upper tansition duct to prevent mis-alignment between bottom flange of upper transition duct nd upper and lower erection joint. F-1120 are found tack welded without sanblasting and aluminum painting (for high temp). Corrective action required. Subcontractor: Angle piece installed transmission duct F-1120 was removed and sent to painting shop for sand blasting & painting. Sand blasting & painting of angle piece were completed (refer to painting RFI # MFC-DLM-ARCC-H-1112 & 1131). 3004 Gasket Kam profile, SS 316L with loose locating ring and flexible graphite filler on both sides found damage material receiving these gaskets where equipment are D-1095 supplied by MISA- the damage may have been occurred due to improperly handled by poor material supplied by manufacturer. Damaged materials (Gasket) to be moved to quarantine area. Contractor: Gaskets will be replaced by supplier with a newly made gaskets. OSID report has already been prepared by Material Department for the replacement of gaskets, reference OSID No.: OSID-0358 PN: Preservation and storage of FRG material for cooling tower in the west side is not proper, it is violation as per A554-E-103-MY-DOF-MUG-48, erection manual, para. 3.0. Contractor: Preservation and storage of cooling tower FRP materials (square tube, channel & FRP plate) are re-arranged properly and stored all FRP items above the ground level with proper supports. During routine site visit, it was noticed that there isno QC personnel monitoring the Electrical activities of SENDAN which is a violation as per schedule "Q", section 3.2 & 5.9. A repeated violation of LBE-EL- 056. Subcontractor: The correction action has been taken cared that the one new QC Inspector has been approved and already mobilized at site and another inspector who is on vacation will be at site on 5 Sept. '13 to meet the Sch. "Q" requirements. PN: During surveilance & monitoring activities at Dilution steam generation structure along GL:2 El+18,700, it was found out that some embedded plates are incorporated for repair works of column & rebar while in IFC drawing it shows that the embedded plated are exposed to beam/column for some structural supports attachment. Subcontractor: Amana has already scrapped and cleaned all repair materials, all embedded plates were already grinded and cleaned. During inspection of formworks and surface preparation for (18) columns and (2) stair pedestals at E-W furnace area "B" at GL:BB-CB/69B-77B and GL:AO/65-66 prior to grouting works, it was found out the some chipping preparations of some columns did not meet the required thickness and some column squareness of formworks are not properly alligned to the edge of base plates. Subcontractor: Additional chipping was already done in areas that did not meet the required depth. As for the squareness of plate to the column, KCC already discussed to Contractor mechanical/structural discipline and advised to proceed grouting for it was already released for grouting & accepted by Company. During the material receiving inspection for Turbo expander ECM 2.5 (Exp 2151/C2151), it is found that the consumable kit has several items were noted. Contractor: Expired loctite threaded lacker 421, loctite primer T-7471 & Bostik NEVERSEEZ fro turbo expander ECM 2.5 will be replaced with a new one. RFI will be raised for another inspection when the newly material arrives. PN: During the Material Receiving inspection for Turbo expander: Unit counter panel (21392-3) box with the indicator with showing red color. (Showing shock occurrence due to handling improperly) hence inspection for damages require as per manufacturer advice if damaged imidiate inspection request from carrier within 15 days of delivery. 2. Spare rotating assembly is N2 purged container with O reading in the gauge and red light indication piece no. (21392-1) Contractor: It was completed for inspection works with Mr. Kurian and already installed at site few months ageo. Daelim already closed the issue. 2 spare rotating containers had been changedN2 in container and already been installed at the rotor storage area. PN: During routine site visit inside substation G-1121, the Contractor has already installing cable tray and it was noticed that the supports for the cable tray fittings and straight runs did not meet the requirements of Sadara specs 67C-0324-05 & 67C-0324-06. Subcontractor: The correction action has already been started as per Sadara specification 067C- A324-05EI67C-0324-06 & NEMA VE2, RFI will follow upon the completion of work. During routine site visit, it was noticed that there is no QC personnel for subcontractor Sendan to monito the activities at site which is a violation as per schedule "Q" section 3.2 & 5.9. Subcontractor: The correction action has been taken cared that the one new QC Inspector has been approved and already mobilized at site and another inspector who is on vacation will be at site on 5 Sept. '13 to meet the Sch. "Q" requirements. Found that pipes and pipes spools are not properly traceably stored, segregated and identified at TCC facility #1. Spools are not traceable that which lot came from which Fab Facility and whoch not NDT is remaining. Some spools found without identification tags and some spools were incomplete inside the completed spools. Subcontractor: During spool releasing for blasting and painting every spool detail attched with RFIs. Spool stored is in workshop 1 as per provided spool storage plan. NASCO & white nile have been closed two months back. NCR No. 8 is closed. Page 28 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 30, 2014 DUE DATE Issued corrective action to Company Target Date S/N LBE NO. PID SUBCON/ CONTRACTOR VAF / PN LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason Company comment Approved Close LBE by Company STATUS CONTRACTOR'S CORRECTIVE ACTION PLAN LBE-ARCC-MECH- 298 MR. NASSAR ARCC VAF MECH Coating/ Painting 18-Aug-13 21-Aug-13 01-Sep-13 29-Sep-13 Closed LBE-PSCL-MECH- 299 MR. AMIN PSCL VAF MECH Tank 18-Aug-13 21-Aug-13 01-Sep-13 8-Oct-13 Closed LBE-PSCL-MECH- 300 MR. AMIN PSCL VAF MECH Tank 18-Aug-13 21-Aug-13 01-Sep-13 8-Oct-13 Closed LBE-AYTB-MECH- 301 MR. KHAN AYTB VAF MECH Piping 24-Aug-13 27-Aug-13 07-Sep-13 8-Oct-13 Closed LBE-ARCC-MECH- 303 MR. KURIAN ARCC VAF 2 MECH Piping 24-Aug-13 27-Aug-13 07-Sep-13 24-Mar-14 Closed LBE-PSCL-MECH- 304 MR. AMIN PSCL PN MECH Tank 24-Aug-13 27-Aug-13 07-Sep-13 8-Oct-13 Closed LBE-DLM-MECH- 305 MR. KHAN DAELIM (Construction) VAF 2 MECH Piping 24-Aug-13 27-Aug-13 09-May-14 10-May-14 Closed LBE-ARCC-MECH- 302 MR. KHAN ARCC VAF MECH Piping 25-Aug-13 28-Aug-13 08-Sep-13 19-Oct-13 Closed LBE-DLM-MECH- 306 MR. HARIKUMAR DAELIM VAF 2 MECH Mechanical (Equipment) 26-Aug-13 29-Aug-13 09-Sep-13 31-Mar-14 Closed LBE-DLM-MECH- 308 MR. KURIAN DAELIM VAF MECH Material 27-Aug-13 30-Aug-13 10-Sep-13 06-Nov-13 Closed LBE-ASYAD-INST- 058 MR. SHABIRUL ASYAD VAF INST Quality Management 27-Aug-13 30-Aug-13 10-Sep-13 15-Sep-13 Closed LBE-AMA-CIVIL-167 MR. JERRY AMA VAF CIVIL Civil 27-Aug-13 30-Aug-13 10-Sep-13 31-Aug-13 Closed LBE-AMA-CIVIL-168 MR. GERALD AMA PN CIVIL Civil 27-Aug-13 30-Aug-13 10-Sep-13 01-Oct-13 Closed LBE-ARCC-MECH- 307 MR. HARIKUMAR ARCC PN MECH Mechanical 28-Aug-13 31-Aug-13 11-Sep-13 27-Oct-13 Closed LBE-DLM-MECH- 309 MR. KURIAN DAELIM VAF MECH Material 28-Aug-13 31-Aug-13 11-Sep-13 29-Sep-13 Closed LBE-TCC-MECH- 310 MR. KURIAN TCC VAF 2 MECH Piping 28-Aug-13 31-Aug-13 11-Sep-13 23-Mar-14 Closed LBE-TCC-MECH- 313 MR. KURIAN TCC VAF 2 MECH Mechanical 28-Aug-13 31-Aug-13 11-Sep-13 19-Feb-14 Closed LBE-DLM-ELECT- 059 MR. MARK DAELIM VAF ELECT Electrical 29-Aug-13 01-Sep-13 12-Sep-13 10-Nov-13 Closed Observed that Contractor/Subcontractor carried out fabrication and welding activities at their respective sites/facilities without conducting project specified PMI Test requirements for welding filler materials and electrode. Violating project PMI procedure A554-E-103-QA-GEN-PRO-075 and Sadara project specifications RT8S-4001-61 Para. 4.1. and 4.2 (Each batch has lot of filler metal shall be tested in accordance with Table 4.1 of RT8S-4001-61.) Contractor's Welding & Piping team shall investigate the discrepancies and implement the remedy action to Subcontractors all facility and site. Contractor: The issue was noted and all the consumables were PMI tested for each NDT and found accepted. Contractor will monitor all incoming High and Low alloy consumable and mae sure all are PMI tested prior to start (each NDT). Please the copy of RFI and close this LBE. During routine inspection at ARCC fabrication shop, poor preservation for pipes, fittings, fabricated spools were observed, violating Sadra Specs, RT-6-ICS, Sec. 2.19.16 & 2.19.117. Contractor: All the spools were placed properly. Action has been taken. Observed that Contractor/Subcontractor teams (TCC) are installing an incoming Equipment/Material (E- 2119 & E-2222) directly on place/location without conducting Material receiving Inspection released by Contractor and Company Quality teams. Repeated violation of Sch. "Q" attachment IV, Para. 3.2.33 & project procedure A554-E-103-QA-GEN-PRO-035 and ITP A554-E-103-QA-GEN-PLN-056. Subcontractor: Noted. TCC will check with Construction group. All equipment required RFI as per ITP. TCC equipment inspector will be made. During inspection at AYTB fabrication shop, it was observed that Joint 2 & 4 for spool nos. N016103V3A- TW-250249-02-08 & N016103V3A-TW-250312-02-08 are misalligned up to 6mm after completion of full welding. Damaged out of roundness pipes beyond acceptance criteria from quarantine have been used. Also refer to LBE No. 285. Violation ref. ASME B31.3. Contractor: A technical memorandum (MFC-TM-QA-0005) has been issued to the Company for approval. Action will be taken as per approved TQ in Nov. 2013. During fir-up inspection at F-1250, F-1240 & F-1230 the HPSSH-1 outlet and HPSSH-2 inlet (both having parent material grade SA234 WP91) connecting with elbow of parentmaterial SA234PB22 (10") having a ID mismatch of 25mm and this loop is not in alignment with the outlet and inlet of convection module. Joint no. J17 & J18. Reference O-A554-E-103-MEC-GEN-006 Subcontractor: Rectification and re-inspection of Fit-Up on affected joints were done and accepted (refere to ARCC-FW-FUR-0188 & ARCC-FW-FUR-0174). PN: During surveillance, two locations observed representing distortion on east (near V3A & west side - on 4D- of the Tank V-0500B which shall be measured separately as per API-650 requirements for plumbness, flatness, peaking and banding inspections whichever is applicable. Locations have been shown to Contractor/Subcontractor quality and construction group. Subcontractor: Noted. Company representatives have witnessed the discrepancy and reports are submitted to Company for approval. During routine inspection at ARCC/OTC blasting/coating faciity, it has been observed that the facility is using recycled garnet for blasting second time within two weeks. Subcontractor: Contaminated garnetwas removed in blasting pot & new garnet was placed in blasting pot. The removal & replacement of garnet were verified by ARCC, Daelim & Sadara QC Inspectors, RFI No. MFC-DLM-ARCC-H-0692. Distortion out of tolerance as per API-620, ASTM A20/20m in-between the 145-215 different locations of third shell course at Tank-V-0500A. It shall be inspected again after recitification. A suitable metod statement might be required for its proper rectification to avoid more complications. Subcontractor: Company representative has witnessed and inspected Dent area and reports are submitted to Company for review & approval. Found following violations at Tank site under Daelim/Petrol Steel. 1. Low hydrogen electrodes in a portable quiver without power connction inside the Tank-V-0500A. Violation Ref. RT8S--6500-03 2. Tank area do not have welding inspector from Daelim which may result to lot of problems. Schedule "Q" attachment IV. Subcontractor: After investigation against this LBE, welder brought electrode from store & kept on down side the tank & went top side at the tank to lift the oven by using rope. The same time it was noticed by Sadara Inspector.Welders are advised to follow the requirementw without any discrepancies. During visual inspection on N-S pipe rack 2" pipes welded together is out of alignment with each other (see line no. NH 041802-2) the subcontractor/contractor are not checking the alignment of the pipe during and before in zig-zag position over the pipe rack as it is to be fitted and welded in a straight way. Subcontractor: TCC welding inspector will make sure that all weld visual inspection will be completed prior to RFI. Spatters, slag misalignment underfell ext. Rectification done. During surveillance at southern end of the N-S pipe reack found Subcontractor using welding machines without calibration sticker out of 5 welding machines & two of them were without calibration sticker. A554- E-103-QA-GEN-PRO-056, Para. 9. Subcontractor: Welding equipment has calibration certificates in office. Sticker maybe removed due to heat, new sticker will be provided. Despite of the Proactive Notification issued by the Company, the Contractor did no action to remove all the sand that was stacked in the cable trays that were stored at Daelim's Laydown yard which is a violation as per NEMA VE-2, Section 3. Daelim: Removal of cable tray that was stacked in sand due to sandstorm is on-going. Contractor will notify Company once the activity is finished. PN: During surveillance & monitoring activities at cooling tower RC Wall (interior portion) along south side, it was observed that some preparation works done by Amana are not acceptable. Contractor is advised to supervise properly the activitiesand must take corrective action concerning the issue. Subcontractor:Already assign one QC inspector to monitor surface preparing of cooling tower to avoid any mistake again. South side interfrior wall already inspected and appear to start repairing work PN: During RT film interpreatation on weld joint for Radiant Coil to Crossover /Piping, NDT level III Mr. Troller reported that following comments: *weld joints were rejected due to surface indication on base metal *debris are entrapped on weld joints *evidence of mismatch & misalignment *third party RT reports are not clear and not specified in defect (reason for rejection). Daelim and ARCC Subcontractor: Action has been taken. NET coordination and NCT Third Party will do proper precautions. During material receiving inspection at Laydown yard (Daelim) for FD fan for the furnace (B-1174) found with shaft connecting bearing and fan part rusted which is a cause for poor preservation, cleaning of the rusted part is required. Ref: RT-6-ICS, 2.6.C.2. & Appendex 1-5, 19. Subcontractor: Rusted portion of the shaft has been cleaned and removed. Continous preservation will be done on the equipment in order to prevent such non-conforming condition. Also, inspection has been carried-out with Sadara Inspection. Material receiving inspection shown F.D. fan for liquid furnace (B-1244) with damaged expansion chambers part no.(63) in drawing no. 974.03. (Assembly drawing with parts list) It is supplied by bolorachi, the damage may have caused due to poor handling/transportation. This is a violation as per A554-E-103-QA-GEN-PRO-034, Oara. 8.1.3. Contractor: Damaged expansion chamber/breather for F.D (B-1244) will be replaced by Vendor. Bold Rochi when the new material arrived another RFI will be raised for inspection. Target date of deilivery: Two months. During site surveillance, it was noticed that there is no QC personnel monitoring the Instrumentation Activities of Contractor/Subcontractor (ASYAD) which is a violation as per schedule "Q", section 3.2 & 5.9. Daelim: Due to miscommunication, QC Personnel of Contractor & Subcontractor were not seen by Company but Contractor assures that the monitoring & attendance of QC Personnel at site is within the schedule "Q". QC Inspector shall be given respective area in the on-going activities as of present. During inspection of LFU stripper (T1330) foundation prior to grouting, it was noticed that the drain is not in accordance with the drawing. Contractor to clarify with designer (Engineering) if the location is acceptable and As-Built the location if accepted. Daelim: Drawing has already been revised. Page 29 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 30, 2014 DUE DATE Issued corrective action to Company Target Date S/N LBE NO. PID SUBCON/ CONTRACTOR VAF / PN LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason Company comment Approved Close LBE by Company STATUS CONTRACTOR'S CORRECTIVE ACTION PLAN LBE-ARCC-MECH- 311 MR. HARIKUMAR ARCC PN MECH Mechanical 31-Aug-13 03-Sep-13 14-Sep-13 24-Oct-13 Closed LBE-TCC-MECH- 312 MR. AMIN TCC VAF MECH Piping 31-Aug-13 03-Sep-13 14-Sep-13 9-Oct-13 Closed LBE-TCC-MECH- 314 MR. KURIAN TCC PN MECH Piping 31-Aug-13 03-Sep-13 14-Sep-13 28-Sep-13 Closed LBE-TCC-MECH- 315 MR. KURIAN TCC VAF MECH Piping 31-Aug-13 03-Sep-13 14-Sep-13 28-Sep-13 Closed LBE-DLM-MECH- 316 MR. KURIAN DAELIM VAF MECH Mechanical (Equipment) 01-Sep-13 04-Sep-13 15-Sep-13 15-Sep-13 Closed LBE-ARCC-MECH- 317 MR. NASSAR ARCC VAF MECH Coating/ Painting 01-Sep-13 04-Sep-13 15-Sep-13 20-Nov-13 Closed LBE-DLM-ELECT- 060 MR. MARK DAELIM VAF ELECT Electrical 01-Sep-13 04-Sep-13 15-Sep-13 06-Oct-13 Closed LBE-DLM-ELECT- 061 MR. MARK DAELIM VAF ELECT Electrical 01-Sep-13 04-Sep-13 15-Sep-13 06-Oct-13 Closed LBE-AMA-CIVIL-169 MR. GERALD AMA PN CIVIL Civil 01-Sep-13 04-Sep-13 15-Sep-13 14-Oct-13 Closed LBE-DLM-MECH- 318 MR. AMIN DAELIM VAF 2 MECH Tank 03-Sep-13 06-Sep-13 17-Sep-13 18-Feb-14 Closed LBE-DLM/PSCL- MECH-319 MR. AMIN DAELIM/ PSCL VAF 2 MECH Tank 04-Sep-13 07-Sep-13 18-Sep-13 18-Feb-14 Closed LBE-KCC-CIVIL-170 MR. JERRY KCC VAF CIVIL Civil 05-Sep-13 08-Sep-13 19-Sep-13 10-Sep-13 Closed 5 LBE-DLM- INST-062 MR. PERVEZ DAELIM (Procurement) VAF 1 INST Material 05-Sep-13 08-Sep-13 17-Sep-13 24-Jul-14 Open LBE-TCC-MECH- 320 MR. KURIAN TCC VAF 2 MECH Piping 07-Sep-13 10-Sep-13 21-Sep-13 23-Mar-14 Closed LBE-AMA-CIVIL-171 MR. GERALD AMA PN CIVIL Civil 08-Sep-13 11-Sep-13 22-Sep-13 24-Sep-13 Closed 6 LBE-DLM- MECH-321 MR. KURIAN DAELIM (Construction) VAF 2 MECH Mechanical (Equipment) 09-Sep-13 12-Sep-13 23-Sep-13 Open LBE-GLOBAL- MECH-322 MR. NASSAR GLOBAL VAF 2 MECH Preservation 09-Sep-13 12-Sep-13 23-Sep-13 16-Feb-14 Closed During Material Receiving Inspection of Hot Dipped Galvanized channel cable tray and fittings at Daelim's Laydown yard, it was noticed that the zinc coating for the HDG channel cable tray and fittings were grinded in some protions causing the metal to corrode, It also resuces the thickness of the zinc layer coating which is a violation as per G165-0205-03, Section 3.1 and ASTM A 123, Table 1. Daelim: HDG channel tray & filltings shall be quarantined; and Company will be informed for further soclutions. During Material Receiving Inspection of Hot dipped galvanized channel cable tray and fittings at Daelim's Laydown yart, it was noticed that the manufacturer is Wahah Electrical Supply Co., (WESCOSA) was not included in the RTIP project supply plan, A554-K-PRG-PU-LIS-DOC-009. Contractor: Contractor submitted FMAR for HDG channel tray where WESCOSA is the proposed manufacturer. FMAR was approved by Company. PN: During surveillance & monitoring inspections along East side of substation 1121 & cooling tower, it was found out some door frames are already deformed cue to mishandling and without proper protection at site. Contractor is advised to take coorective & presventive action. Subcontractor:deformed door frame already removed from site and send it to suppiler for rectfication. Amana will resubmit RFI for inspection once door frame will arrive at site. During welding in-process inspection, welders were found using permanent markers for Identification on the SS pipe/spools which is prohibited on SS as low chloride Sulfur markers are required for SS & LTCS spool/pipe marking. Subcontractor: Noted. Action will be taken accordingly. During inspection of equipment foundation pads leveling of equipment there was an excess building of the concrete surface below the pad plate, also with excess projecting rebars the distance between the concrete surface and pad plate should be 25mm. Further, chipping required to maintain the distance. Ref: A554-E-103-QA-GEN-PRO-034/035, Rev.4, Para. 10.2.2.4. Subcontractor: Additional chipping was done & reinforcing bars were bend to meet the concrete covering requirement, damaged coating of rebars were touched-up. It has been observed that during the past eight days, the rejection rate for pipes & spools at ARCC/OTC blasting & coating facility has increased due to coating defects resulting from bad performance & follow- up from ARCC/OTC quality team. Subcontractor: Problem on painting defects were settled during ARCC meeting with Contractor QC ^ Construction Team and presently production quality was improved and defects on painted spools were controlled. PN: Daelim & ARCC quality team shall plan to conduct Ferrite Testing for Completed Weld joint for 304H 308H classified lines (HC-68) as per requirement of line class and project spec: G4S-7600-1. Daelim/ARCC shall confirm the Ferrite Content of weld metal shall be controlled, and content of all as deposited weld metal shall be within the range of 2FN to 6FN at individual measurements. Contractor: Action will be taken. Noted. During surveillance at TCC-1 found that welder was using high amperage (145 amps instead of max. of 113 amps) for SS welding even instructed several times. Discoloration (Dark Blue) also deserved on the subject weld joints and notified to Daelim & TCC inspectors. Also WPS parameters must be followed. Corrective action with preventive measures is required. Subcontractor: Noted. Action will be taken accordingly. TCC welding inspector give instruction to all SS welders that WPS. Parameters should be followed. TCC welding inspector has 02 analyzer, Amps motor with him in SS workshop 1. PN: During surveillance at N-S pipe (TCC) rack SS welding were carried-out without high frequency welding machine as it is required. For GTAW welding of Pno. 5A/5B/5C base material for a quick start. Confirmation of high frequency welding which is using ate site is required. Ref. RT8S-6500-02, para. 3.1. Subcontractor: Noted. Action will be taken accordingly. During Material Receiving at site for inspection of Ground Flare Auxiliary and spare parts. Supports found with bolts welded to the support, have threads exposed without proteection. It is a violation as per RT-^-ICS, 2.19A4C. Subcontractor: Noted. Action will be taken. During routine inspection at E/W Piperack (Dryer area), it has been noticed that insulation materials kept in a very poor storage without proper protection & kept some materials on the ground without wooden skids. This behaviour cause accummulate sand on it & insulation mnaterials damage. During Material Receiving inspection of Compressor, it was observed that compressor instrument & Junction Box (JB) are not as per Standard. Compressor C-02501 documents are not available such as FAT Report, MTR, Calibration report. Grounding is not connected to JB Instrument and not completed. This violates G06A-0003-17 & G06A-41-00. Contractor: Contractor will provide the documents; and RFI shall be resubmitted to Company for review and approval. Related to NCR. NCR-ARCC-INST-001, ARCC requested Daelim to provide MOV then ARCC shall install. Inspection of Fit-up at North-south pipe rack shown tack weld made outside the weld groove bridge tack shall be above the root area but within the groove area and shall be completely removed prior to completion. Ref. A554-E-103.QA-GEN-PRO-056, Rev.1, Para 17.4.5. Line OW-064002-4" PU35. Subcontractor: TCC welding and piping inspectors conducted tool box meeting with Piping group and taught them regarding tacking requiements. TCC welding and piping inspectors will make sure for proper tacking as per Sadara Specifications. Company informed Contractor/Subcontractors concerning GROUT TEMPERATURE USING MASTERFLOW 524L intended for Substation G-1121 transient UPS System-Equipment/Concrete Pad where during inspection prior to grouting the materials were already exposed to sunlight and without proper protection/handling resulting to increase of temperature after mixing to water with cube ice. Contractor to take corrective and preventive action in order not to reject the grouting activities and to ensure that grout temperatures are complying with the manufacturers recommendation. Subcontractor:All grouting material shifted the shade area to avoid delary of inspection/rejection It is observed that Contractor's Tank QC Inspector has shown poor performance on his assigned discipline. Some of his shortcomings are the followings: Tank ITP, Rev.3 not revised and resubmitted since 7th March 2013; Accepting Tank distortions which are not acceptable as looged in LBE #299 and repairing is on going; Raised RFI for V-500B distortion measurements after half inspection and after three days did not offer inspection for the remaining half to Company final inspection. Reference: Sch. "Q", A20M & LBE. Violations are found at Tank MFC Area: *Petrol Steel has fixed some temporary curvature plates and channels to rectify the distortion on the last shell of Tank V-0615 at 225 degre around a nozzle. *After Company enquired from Contractor QC Tank Inspector about the issue, said Inspector has not initiated an inspection due to Subcontractor did not offer for inspecttion. *Different Welders found welding on Tanks V-0500B, V-0615 without any wind shielding. Contractor QC Welding inspector also not at site. Contractor Quality team needs to take necessary actions for the above violations. Ref: RT8S-6500-1, Sch. "Q" & A554-E-103-QA-GEN-PRO-056. It was noticed that some of the equipment structures have exposed top bars after the chippings for grouting were completed by the equipment installer. These portion of te top of the foundation shall be chipped more deeply to lower down the reinforcing bars to meet the cover requirements of the stardards or as shown on the drawing. Subcontractor:Additional chipping was done & reinforecing bars were band to meet the concrete covering requirement, damaged coating of rebars were touched up Page 30 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 30, 2014 DUE DATE Issued corrective action to Company Target Date S/N LBE NO. PID SUBCON/ CONTRACTOR VAF / PN LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason Company comment Approved Close LBE by Company STATUS CONTRACTOR'S CORRECTIVE ACTION PLAN LBE-ARCC-MECH- 323 MR. KHAN ARCC VAF MECH Quality Records 10-Sep-13 13-Sep-13 24-Sep-13 19-Oct-13 Closed LBE-ARCC-MECH- 324 MR. KHAN ARCC VAF MECH Piping 10-Sep-13 13-Sep-13 24-Sep-13 19-Oct-13 Closed LBE-ARCC-MECH- 325 MR. KHAN ARCC VAF MECH Piping 10-Sep-13 13-Sep-13 24-Sep-13 27-Oct-13 Closed LBE-AMA-CIVIL-172 MR. GERALD AMA PN CIVIL Civil 10-Sep-13 13-Sep-13 24-Sep-13 14-Oct-13 Closed LBE-DLM-MECH- 326 MR. AMIN DAELIM PN MECH Quality Records 11-Sep-13 14-Sep-13 25-Sep-13 19-Oct-13 Closed LBE-PSCL-MECH- 327 MR. AMIN PSCL PN MECH Tank 11-Sep-13 14-Sep-13 25-Sep-13 09-Dec-13 Closed LBE-DLM-MECH- 328 MR. AMIN DAELIM VAF MECH Piping 11-Sep-13 14-Sep-13 25-Sep-13 10-Oct-13 Closed LBE-DLM-MECH- 329 MR. KURIAN DAELIM VAF MECH Mechanical 11-Sep-13 14-Sep-13 25-Sep-13 06-Oct-13 Closed LBE-TCC-MECH- 331 MR. KURIAN TCC VAF 2 MECH Mechanical (Equipment) 11-Sep-13 14-Sep-13 25-Sep-13 03-Apr-14 Closed LBE-DLM-ELECT- 063 MR. MARK DAELIM VAF 1 ELECT Electrical 11-Sep-13 14-Sep-13 25-Sep-13 13-Feb-14 Closed 7 LBE-DLM- MECH-330 MR. KURIAN DAELIM (Procurement) VAF 2 MECH Material 11-Sep-13 14-Sep-13 25-Sep-13 Open LBE-DLM-MECH- 332 MR. SAYED DAELIM PN 2 MECH Material 14-Sep-13 17-Sep-13 29-Sep-13 25-Feb-13 Closed LBE-DLM-ELECT- 064 MR. MARK DAELIM PN 1 ELECT Electrical 16-Sep-13 19-Sep-13 30-Sep-13 13-Feb-14 Closed LBE-AMA-CIVIL-173 MR. JERRY AMA VAF CIVIL Civil 16-Sep-13 19-Sep-13 30-Sep-13 27-Oct-13 Closed LBE-AMA-CIVIL-174 MR. JERRY AMA VAF 1 CIVIL Civil 16-Sep-13 19-Sep-13 30-Sep-13 10-May-14 Closed LBE-AYTB-MECH- 333 MR. KHAN AYTB VAF MECH Piping 17-Sep-13 20-Sep-13 01-Oct-13 19-Oct-13 Closed During routine inspection of ARCC fab.shop, it was observed that material of material SS spools are not matching with the materials of the pipe listed in the BOM of the IFC drawing, materials of the pipe observed at the shop is 3062 whereas the requested material as per IFC drawing is 304H. Contractor: Daelim shall perform the PMI for SS material especially for pipe. The PMI report was 304H, based on the PMI report During material receiving inspection at Laydown for C3R first stage suction drum. (D2505) accessories liner plates and companion flanges found corroded. No galvanizing was found on the liner plates to resist the corrosion. Galvanizing is required as per the drawing D-2505-103-9003-03-205 (Res) the accessories are supplied by DOOSAN. Ref: A554-E-103-QA-GEN-PRO-035, Para. 8.2.1, 8.1.11, 8.1.12, RT-6-ICS, 2.19.3. Contractor: As we discussed with Construction team, corroded diner plates for D-2505 will not be used by TCC for equipment erection and these materials were shifted in the quarantine area. In the case of Companion Flange corrossion will be cleaned and it shall be done as per prevention team schedule. Target date of completion: 2 weekds. During Equipment Installation Alignment and plumbness inspection for T-2220 TEC found placed shim under the equipment with a total of five nos. ofshims exceeding total stalk height of 12mm in which more than one shim is greater than 3mm. This alignment shim used on centerline or near centerline support, extend beyond the support pads. Subcontractor: Activities taken. Plumbness inspected and accepted. Alignment inspected and accepted. During routine site inspection at substation G-1121, it was found out that the Contractor installed EMT Conduits for Fire Alarm System inside the battery room which is a violation as per G7C-0311-06, Section 3.3. Subcontractor: We discussed the issue with DAELIM Engineering and they will raise the RFC to SADARA upon the approval we follow accordingly. It is found that subcontractors replying SADARA LBEs sometimes incorrectly and Daelim Quality is not acknowledging the replies for agreement o disagreement. After Daelim quality is satisfied for the closure of any LBEs, Company inspector must be informed immediately for final acceptance without any delay. PN: Observed following at Tank V-500A,B: 1.Roof nozzle's flange faces are getting rusty and needs proper cleaning and protection. 2. Galvanized roof walkway gratings are needed some rectifications by cutting and welding. Proper coating shall be required. RFI's MFC-DLM-SOSTA-PIP-018, SEAH-PIP-064, BASSI-PIP-008, BASSI-PIP-009 & BASSI-PIP-010 are submitted to Company after acceptance of Daelim QC and Company found following discrepancies: 1. Wrong Heat number marking on pipes 2. Wrong size marking on pipes 3. RT, Hydro Test reports attached are of A516-70 instead of A234 Fittings MTC. 4. MTCs of Materials A335, A182 submitted instead of A234 CS Fittings. Approval of RFV and PMI and PMI is required for all of above. Contractor: NCR is issued to the Vendor SOSTA by Company. All the pipes were conducted PMI. The test result is satisfactory. During routine inspection at ARCC fabrication shop, discoloration is observed on the weld disposition & HAZ. As per AWS (5.5, D10.6 & D12.2), this discoloration is not acceptable & will affect the condition resistance. Contractor: ARCC Welding inspector had been taken immediate action regarding the highlighted issue; before started the welding, Contractor checks the purging level and during the welding also, checking the heat input and inter-pass temperature. During inspection for Post Welding of SS joints, it was observed that some joints are partially welded which is not allowed as per approved WPS at ARCC fab.shop. Contractor: Naction has been taken. Tool box meeting given to welders to follow the WPS. It has been noticed that some RFI's had been submitted late by Contractor/Subcontractors for more that two months back are still pending. Contractor/Subcontractor has to expedite submission to Company all pending RFI's to ensure that proper documentations are secured. Subcontractor: Amana is ongoing doing all pending RFI and make sure that by end of October 2013 already submitted to Daelim QC Office. The Contractor repaired the corner bottom slab of Sump 0906 (near the Cooling Tower) without chipping or removing the honeycombs and other loose concrete. Repair should not be undertaken without approval of Company as required by RT2S-3001-01 Sec. 11. Subcontractor: Amana is ongoing chipping and removing the repaired materials after all chip, Amana will raise RFI prior to start repair. Spent Caustis Foundation V500A & B have circumferential non-uniform finish with regards to circumferential plate of the tank above the sloop portion of the foundation. Please advise the subcontractor to follow the detail shown in the drawing after the tank settlement activities. Subcontractor: Amana is waiting to release spent caustic foundation from Petro steel to start repairing work as per IFC drawing slope During routine inspection at AYTB fabrication shop, it was observed that specified material of 2" pipe in BOM of IFC drawing is ASTM A312-TP304/304 L SMIS but the materials used for fabrication is ASTM A312-TP 304/306L welded, violating design requirements. Contractor: The pipes were shifted to AYTB by mistake. Corrective action has been taken. All the welded pipes were removed. All the joints made on welded joints were rejected. During Material Receiving inspection for Equipment (W1720) & (W1721) at site, the Equipment W1720 found with flanges corroded, external surface of the equipment especially place were saddle was attached and other surface of the equipment, some internal pipes connection to the flange were also also found corroeded. Equipment W1721 found with corroded flanges. The equipment is also found errected without proper preservation for corrotion deterioration. This is a violation as per A554-E-103-QA-GEN- PRO-035, Para 8.2.1, 8.1.11, 8.1.12, RT--6-ICS, 2.19.3. These equipment are supplied by DOOSAN Engineering. Subcontractor: Noted. Action shall be taken and as per construction plan for the corrossion, painting touch up repair will be implemented. Target date: 25 Nov. 2013. PN: During Material Receiving Inspection for CS Pips ASTM A53B, it was found out that 23 nos. of pipes of different sizes are not matching with MTC. (P.O. No. 100532-42-P02-005 AO1, Manufacturer - Seah Steel, Korea): 1. In the MTC of 12" pipe, heat no. SB76608 is not matching with MTC (Total 19) 2. IN the MTC of 20" pipe, heat no. SB74629 were physically on 4 nos. of pipes heat no SB72061, as per Sched. "Q", att. II, para.2.3. Contractor: All the pipe without proper tag were shifted to quarantine area. PN: During routine site visit inside operator building G-1122, it was noticed that the Contractor was about to install EMT conduits embedded in concrete which is a violation as per G7C-0311-06 Sec. 3.5. Subcontractor: The issue already under discussion with SADARA PID and DAELIM. We will follow the result of final discussion. Page 31 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 30, 2014 DUE DATE Issued corrective action to Company Target Date S/N LBE NO. PID SUBCON/ CONTRACTOR VAF / PN LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason Company comment Approved Close LBE by Company STATUS CONTRACTOR'S CORRECTIVE ACTION PLAN LBE-DLM-MECH- 334 MR. AMIN DAELIM PN MECH Piping 17-Sep-13 20-Sep-13 01-Oct-13 12-Oct-13 Closed LBE-AMA-CIVIL-175 MR. GERALD AMA VAF CIVIL Civil 17-Sep-13 20-Sep-13 01-Oct-13 31-Dec-13 Closed LBE-SDN-ELECT- 002 MR. PERVEZ SENDAN VAF 1 ELECT Preservation 18-Sep-13 21-Sep-13 02-Oct-13 Closed 19-Sep-13 Closed LBE-AYTB/TCC- MECH-335 MR. AMIN AYTB/TCC VAF MECH Piping 18-Sep-13 21-Sep-13 02-Oct-13 8-Oct-13 Closed 8 LBE-DLM- MECH-338 MR. KURIAN DAELIM (Procurement) VAF 2 MECH Material 18-Sep-13 21-Sep-13 22-Jul-14 Open LBE-DLM-MECH- 339 MR. KURIAN DAELIM VAF 2 MECH Piping 18-Sep-13 21-Sep-13 02-Oct-13 19-Feb-14 Closed LBE-AMA-CIVIL-176 MR. JERRY AMA VAF CIVIL Civil 18-Sep-13 21-Sep-13 02-Oct-13 Closed 27-Oct-13 Closed LBE-GLOBAL- MECH-336 MR. NASSAR GLOBAL VAF 2 MECH Quality Management 19-Sep-13 22-Sep-13 03-Oct-13 Closed 16-Feb-14 Closed LBE-DLM-MECH- 340 MR. KURIAN DAELIM PN 2 MECH Piping 20-Sep-13 23-Sep-13 29-Sep-13 29-Sep-13 Closed LBE-DLM-MECH- 337 MR. AMIN DAELIM PN MECH Piping 21-Sep-13 24-Sep-13 05-Oct-13 20-Oct-13 Closed LBE-DLM-MECH- 341 MR. SAYED DAELIM PN 2 MECH Material 22-Sep-13 25-Sep-13 08-Oct-13 04-Mar-14 Closed LBE-AMA-CIVIL-177 MR. JERRY AMA VAF 1 CIVIL Civil 23-Sep-13 26-Sep-13 07-Oct-13 Closed 30-Jan-14 Closed 9 LBE-DLM- MECH-342 MR. HARIKUMAR DAELIM (Construction) VAF 2 MECH Mechanical (Equipment) 23-Sep-13 26-Sep-13 Open PN: Daelim has started the PWHT since 12th September 2013 at TCC fab. facility #1 but until now Hardness Testing has not been started yet. Contractor needs to arrange Hardness testing as soon as possible to ensure that PWHT result is satisfactory. Contractor: Noted. Action will be taken accordingly. During inspection & monitoring activities at Operator Building, we found out the following: A) At monitoring area and permit issue area, installation of electrical piping / electrical boxes are already started, wherein the repair works for the perimeter RC wall are not yet finished. In this regards, please expedite the repair works for the said structure, including touch-up for soffit beam and slab; B) at sample preparation room and corridor, it has been observed that after cutting of concrete prior to installation of electrical piping/junction bixes, we found out that some "block mesh" truss type was affected due to preparation works done by the electrical discipline. COntractor was advised to take corrective and prventive action concerning this issue, in which proper coordination between other discipline involved and not to encounter problems for the future. Subcontractor: This LBE is for Sendan. Amana will repair all damaged block mesh and will install wire mesh along connection of two blocks but Amana will claim additional payment. Amana is waiting to get the handing over from sendan to start repair work. Once sendan wil hand over the building amana will start rectification work. Amana can rectify work on 28 OCT.2013. During routine site visit at Substation G-1121, it was observed that Contractor installed panel without information of Company and building was not ready and panel not reserved. Air conditioner not on, room temperature not maintained, building full of dust. These violates project specification A554-E-103-CM-GEN-PLN-002. Subcontractor: The action has been taken. Sendan is maintaining the room temperature as per project Standard requirements, temperature gauge is already requested for continuous monitoring the temperature. Vaccume cleaner already provided to control the accumulation of dust. Contractor: Panels are now installed as per procedure and preservation are now maintained such as temperature and humidity requirements. PN: Prior to PWHT, Contractor/Subcontractor shall ensure the following: 1. All welding and repairs shall be performed before PWHT. 2. PWHT shall be performed prior to Hydrotest. 3. Ensure that all rusted paints are removed and proper supports are provided. 4. PWHT charts should be marked prior to PWHT with identification number of welds and start time. 5. All machined surfaces such as flange faces, threaded bolts, threads, etc. shall be protected from oxidation during the Heat Treatment bu coating with deoxaliminate or other suitable material. 6. PWHT shall be perfromed before NDE is conducted. 7. After PWHT, all TCs shall be removed and attachment area shall be ground smooth to clean and sound metal. PN: During the material receiving inspection for Lateral Reducing Tee 14" x 10" Sch XS x Sch 20 ASTM 358 304 43 (Tag No. EPI-205 RFI No. DLM-MFC-BASSI-PIP-011) it was found that material offered for inspection without MTC. Ref. (per Sch. "Q" Att. III Para. 2.3 ) Contractor: Noted and action will be taken. All the materials will be offered for inspection after MTC. The anchor bolt at flare area pipe rack with 36mm diameters (M36) was cut since it was hit by the equipment. The 2nd anchor bolt was also hit but was not cut. The 2nd anchor bolt shall be verified if still fit to be used since it tilted from its original position. Contractor shall provide method statement for repair as removal of the foundation and the replacement. Subcontractor: Amana submitted Method Statement of repair and waiting for approval before starting of repair. It was observed that during finishing stage of concrete foundation slabs and paving, the Contractor do not comply with the requirements of SMIC-Q-1015-A2 regarding planeness of surface with a 3000mm straight edge applied at not less than two different angles. This requirement prior to apply broom finish shall be monitored by COntractor QC. Please check usual concrete surface finish. Subcontractor: Advised to construction & concrete pouring team to use always 3000mm straight aluninum bar and two different angles. Qc inspector and surveyor to recheck slope level and finishing, During routine inspection for insulation activities at Debutanizer Reboiler (D-1977) reactor (R-2025) & primary demethanizer (T-2110), it has been noticed that the insulation Inspector of Globar Suhaimi is not available at site during insulation activities. This is violation against Schedule "Q". Subcontractor: Global Suhaimi removed the previous QC Inspector from site and replaced with new QC Inspector. PN: During weld visual inspection of welded joints (FW1) for line CP-151123-10 HC 87 welder ID was missing from the weld information box written on the pipe shall write there IDs or welder no. on the respective joint they have welded. Ref. A554-E-103-QA-GEN-PRO-056, 8.8 (In-Process Weld Inspection). Contractor: Noted. Action will be taken. Found that SS pipe spools of line class HC-61, HC-70, transferred from AYTB Fab.shop to TCC #1 and are painted already without RFI and Inspection. It is hold point activity for Contractor and Witness for Company. Corrective action & Preventive measures are required. Ref. SMITP-F-001-04, Rev. 4 activity #4.7. PMI of above mentioned painted spools is also balance. Contractor: PMI has been conducted as per RFI. All the spools were documented. RFI was issued for spools release for blasting. Strict actions have been taken. Material Receiving inspection of the flare runner at laydown yard shown the supports welded to the runners for attaching heat shield found bended. This can damage the welded portion and also may have taken place during transportation mishandled the equipment. The supplier of this equipment is ZEECO Industries, Korea. P.O. No. is 100532-14-216-001- A01, violation as per Ref. A554-E-103-QA-GEN-PRO-035, Para. 8.2.1, 8.1.11, 8.1.12. Contractor: The bended material already repaired and installed at site. During surveillance in the North-south pipe rack beveled ends of the joints and fittings found exposed to the atmosphere for long days, as no grinded bevel or open pipes and fittings to be exposed to the atmosphere without covering which can corrode or damage it, hence, to be covered. Ref. A554-E-103- QA-GEN-PRO-059, rev.0, para. 9.3, 7.3, A554-E-103-QA-GEN-PRO-056, para. 10.7.8, 11.1.1, 16.1, 17.1.2. Subcontractor: Noted. Action will be taken.End opening of the pipes at pipe rack, all pipe spools and flange faces protection have been done. TCC piping inspectors are checking on daily basis and reporting to QC Supervisor. During surveillance inspection at furnace F-1160, Radiant crossover piping installed on position observed that numerous discrepancies on pass 1 and 2 header lines. Example: Inclination of levelness, plumbness, dimensional discrepancy on pipe supports and sidtoration due to improper fabrication method etc. by Vendor JNK, Korea. Daelim/ARCC shall verify occured discrepancy and propose corrective action in accordance with appropriate Engineering Method. Page 32 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 30, 2014 DUE DATE Issued corrective action to Company Target Date S/N LBE NO. PID SUBCON/ CONTRACTOR VAF / PN LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason Company comment Approved Close LBE by Company STATUS CONTRACTOR'S CORRECTIVE ACTION PLAN LBE-DLM-MECH- 343 MR. AMIN DAELIM PN MECH Piping 24-Sep-13 27-Sep-13 08-Oct-13 29-Sep-13 Closed LBE-DLM-MECH- 344 MR. AMIN DAELIM PN MECH Piping 24-Sep-13 27-Sep-13 08-Oct-13 13-Oct-13 Closed LBE-ARCC-MECH- 345 MR. NOOR ARCC VAF MECH Refractory 24-Sep-13 27-Sep-13 08-Oct-13 13-Oct-13 Closed 10 LBE-DLM- MECH-346 MR. HARIKUMAR DAELIM (Enginnering) VAF 2 MECH Mechanical (Equipment) 25-Sep-13 28-Sep-13 09-Oct-13 Open LBE-DLM-INST-065 MR. SHABIRUL DAELIM PN INST Instrumentation 26-Sep-13 29-Sep-13 10-Oct-13 08-Oct-13 Closed 11 LBE-DLM- MECH-347 MR. SAYED DAELIM (Procurement) VAF 2 MECH Material 28-Sep-13 01-Oct-13 12-Oct-13 Verified 20-Jul-14 Closed LBE-TCC-MECH- 348 MR. AMIN TCC VAF MECH Preservation 29-Sep-13 02-Oct-13 13-Oct-13 11-Oct-13 Closed LBE-DLM-MECH- 349 MR. AMIN DAELIM VAF MECH Quality Records 29-Sep-13 02-Oct-13 13-Oct-13 29-Sep-13 Closed LBE-TCC-MECH- 350 MR. AMIN TCC VAF MECH Piping 30-Sep-13 03-Oct-13 14-Oct-13 Closed 10-Oct-13 Closed LBE-AMA-CIVIL-178 MR. JERRY AMA VAF 1 CIVIL Civil 01-Oct-13 04-Oct-13 15-Oct-13 On-going. 27/10/13 28-Apr-14 Closed LBE-AMA-CIVIL-179 MR. JERRY AMA VAF 1 CIVIL Civil 01-Oct-13 04-Oct-13 15-Oct-13 28-Apr-14 Closed LBE-DLM-MECH- 351 MR. AMIN DAELIM VAF MECH Piping 01-Oct-13 04-Oct-13 15-Oct-13 10-Oct-13 Closed LBE-KCC-CIVIL-180 MR. JERRY KCC VAF CIVIL Civil 02-Oct-13 05-Oct-13 16-Oct-13 7-Oct-13 Closed LBE-AMA-CIVIL-181 MR. GERALD AMA PN CIVIL Civil 02-Oct-13 05-Oct-13 16-Oct-13 12-Oct-13 Closed Observed several locations Anchor bolt holes were extended during equipment installation due to misalignment/dimensional discrepancy with fabrication/GA drawing and trimmed hole are extended as specifying tolerance limit by Vendor. The anchor bolts hole shall not be extended/reduced in diameter nor offset to facilitate modification of the mounting plate to facilitiate alignment is not permitted unless authorized by designated vendor. Violation of A554-E-103-QA-GEN-PLN-056. Trimmed area shall be coated with paints material.specifications. Contractor: As per discussion with Construction Mech. Superintendent Mr. E.M. Choi, Engineering Query shall be released in support for the bolt hole enlargement. (Field Engineering Personnel Mr. Chan Ho Park will be available on the 2nd of November 2013) Target date: 1st week of November. -> Received approval from Company on Daelim's corrective action. So this shall be closed. During material receiving inspection at Daelim yard, it is observed that 285 nos. of CS pipe ASTM A103 Gr. B Galvanized (1 1/2 x Sch. 80 size) received with no marking of material specification on the pipe. RFI no. MFC- DLM-GERAB-PIP-003, P.O. No. 100532-42-P01-008-A01, Supplier: Gerab National Enterprise. This is violation of schedule "Q" Attachment 4, Para. 4.4, which stated that traceability shall be maintained on equipment, materials, part and components, as specified in the Company Standard and Manufacturer's specification. Contractor: All the materials without tag were rejected. It was shifted to quarantine area. It will be returned and will be replaced soon. Preservation, storage & handling of SS Piping material at Fab. Facility-1 (TCC) may cause damages on Elbows and Flanges. Also found some SS material which does not belonged to MFC project at the same location. Material shall be re-inspected for mechanical damages after corrective action. Corrective action with Preventive measures is required. Violation Ref: RT6-1GS Para. 2.15, 2.16, 2.19. Contractor: Some materials found at Laydown shop #1 was removed from the location. All SS piping materials were segregated; proper protection has been provided. Preservation corrective action were taken at shop #1. No damage found during re-inspection. Found that Daelim doesn't have proper control of weld map/number changing on IFC drawings. Subcontractor/Contractor Construction team is overwriting on the approved IFC drawings without getting signed by Daelim Engineering. Although found that JCR (Joint Change Request) format being used is not a part of Daelim internal quality system. Construction representative is making changes in JCR, IFC Drawings whenever they like. Some JCRs showing signature place for Daelim Field Engineering and from some have been deleted. Quick corrective action with preventive measures is required. Contractor: Weld joints are indicated in spool drawing generated in Daelim's own program. If there is a joint change request from Contractor or subcon, the joint change request to be confirmed/signed by Daelim Construction representative. Weld joint is not related to Engineering works so Daelim's field engineering does not involve weld joint change. Found discrepancy (Dull Sound) at bullnose area during final hammer test inspection of applicant of Castable/Gunning Refractory as per RTSAES-N-110-01 at F-1170. Marked and identified area shall be rectified and offered for re-inspection by Company. Contractor: Dull sound area has been chipped and applied new refractory and was accepted by Sadara as per RTSAES-N-110-01 PN: During surveillance at Daelim's laydown yard, it was found out that Subcontractor is lifting at the wrong place at drum and it might cause the damage of the Instrument cable. Contractor is advised not to repeat the same mistake during the cable drum lifting and transportation. This has been a repeated violation on LBE-044. Subcontractor: Asyad material in-charge was reprimanded. Written final warning has been issued and received by Asyad material-in-charge. Both agreed that if repeated , appropriate disciplinary action will be undertatken. The written final warning was also served to the "Rigger" who facilitated the lifting. PN: It is advised to Daelim Quality team to ensure that thirdt parties coming for MFC, NDE, PMI, PWHT and Hardness testing are using only calibrated tools and quipment including calibration blocks with their certification. Contractor: Noted. Action will be taken. PN: Found that some sort of Daelim piping materials are quarantined at Daelim lay-down yard due to mechanical damages and ovality. Company Construction approved Mecthod Statement only for removal of damaged parts from the entire length at least about Quarantined Fittings and Oval Pipes still there is no action plan from Daelim. However, quality Daelim needs to make sure that after removal of damaged portion, rejected or quarantined material shall be used only after acceptance of material receiving inspection by Company. Contractor: Noted. Action will be taken. During JCC review found welder JCC #1513 (TCC-384) approved by third party and Daelim QC for dia. CS Pipe qualification without meeting the standard requirements of ASME IX Para. No. QW-302.2. For dia qualification minimum 4 test coupons or (min. 6" weld length) are required to be tested coupon accepted by Daelim and third party (NDTCCS). RT report for said welder shows 3 test coupons acceptance instead of one welded by him. Also WQT RF Films are not being reviewed by Daelim and Sadara NDT Level III. Daelim must provide justification and corrective action for above discrepancies with preventive measures. Contractor: A violation may be recorded when there is any findings of deviation from the code or specification but TCC has conducted WQT with Sadara approved Third party in accordance with code and standard (ASME sec IX) required for minimum of 150mm weld made by each welders. Here, is it attained with 1/2" 60X5 Sch. 3 test coupon and its WQT & RT report has been submitted to Company. Therefore, this WQT is complying with the application code and standard. Moreover, in the WQT visual inspection report showing the welder is visually accept or not, hence, Contractor emphasizes to Company that this shall not be considered as a violation. With reference to RFI No. MFC-DLM-KCC-CI-4638, the slope of the requested area does not comply with the requirements of Civil Project Instructions document no. A554-T-103-CV-SPC-BOD-001, clause 3.2, the RFI was rejected. Subcontractor:with reference to the RFI no #MFC-DLM-KCC-CL-4638-0A, all ready accepted PN: During surveillance inspection at Cooling Tower Basin along "RC Wall", found out some locations or portions are ready for injection but the materials intended for the area were not available at site suc as "Packer" for injection, concresive 2020. Contractor is advised to expedite delivery of said materials in order not to dealy the schedule of repair works. Corrective actions should be taken by Contractor. Subcontractor: Amana already issued Purchased Order but unfortunately Supplier has no available materials. TCC reply on Sadara LBE #277 and commented on RFIs to perform passivation on Heat sensitized discolored (bluish) joints. Instead to perform passivation as agreed, TCC grinded some SS weld joints inside the area around the root by inappropriate stone grinder and hide the discoloration band. The grinded portion can get rust easily like Heat sensitized joints. Daelim quality team must ensure proper corrective action with preventive measures. Contractor: The discoloration of the SS spool joints were removed by buffing and wire brushed. The joint inspections by Company Welding Engineer along with Company Inspector is done and found satisfactory. In addition to LBE No. 040 (clsoed) to reflect on this Logbook, there are several locations where the top surfaces of concrete foundations and pavings have footmarks and the finish is not in accordance with the requirements. Contractor/Subcontractor to provide schedule of repair and mock-up to meet the requirements mentioned in the logbook entry no. 176. Subcontractor: Amana proposed to chip 5 cm for whole area and re-concrete by 4000 Psi concrete to attain same color and same finish of existing paving. With reference to LBE # 127, there are several locations at site where the TPER's protection has not been completed. Contractor shall ensure that protection of TPER is undertaken in accordance with doc. no. A554-E-PRG-CV-SPC-E20-047, Rev.1. Subcontractor: Amana & KCC is ongoing making protection board for all exposed TPER. Page 33 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 30, 2014 DUE DATE Issued corrective action to Company Target Date S/N LBE NO. PID SUBCON/ CONTRACTOR VAF / PN LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason Company comment Approved Close LBE by Company STATUS CONTRACTOR'S CORRECTIVE ACTION PLAN LBE-AMA-CIVIL-182 MR. GERALD AMA PN CIVIL Civil 02-Oct-13 05-Oct-13 16-Oct-13 15-Oct-13 Closed LBE-DLM-MECH- 352 MR. KHAN DAELIM VAF 2 MECH Engineering 02-Oct-13 05-Oct-13 31-Oct-13 04-Mar-14 Closed LBE-ARCC-MECH- 353 MR. KHAN ARCC VAF MECH Material 02-Oct-13 05-Oct-13 16-Oct-13 27-Oct-13 Closed LBE-ARCC-MECH- 354 MR. HARIKUMAR ARCC VAF 2 MECH Piping 05-Oct-13 08-Oct-13 19-Oct-13 23-Mar-14 Closed LBE-ARCC-MECH- 355 MR. KHAN ARCC VAF 2 MECH Piping 06-Oct-13 09-Oct-13 13-Oct-13 04-Mar-14 Closed LBE-DLM-MECH- 005 MR. SAYED DAELIM VAF 1 MECH Preservation 06-Oct-13 09-Oct-13 30-Mar-14 19-Apr-14 Closed LBE-SEN-ELECT- 066 MR. MARK SENDAN VAF 1 ELECT Electrical 07-Oct-13 10-Oct-13 21-Oct-13 26-Jan-14 Closed LBE-KCC-MECH- 356 MR. NOOR KCC VAF 2 MECH UG-RTR 07-Oct-13 10-Oct-13 21-Oct-13 12-Feb-14 Closed LBE-PCMC-MECH- 357 MR. NASSAR PCMC VAF 2 MECH Coating/ Painting 07-Oct-13 10-Oct-13 21-Oct-13 16-Feb-14 Closed LBE-GLOBAL- MECH-358 MR. NASSAR GLOBAL VAF 2 MECH Insulation 08-Oct-13 11-Oct-13 22-Oct-13 23-Feb-14 Closed 11 LBE-DLM- MECH-359 MR. AMIN DAELIM (Enginnering) VAF 2 MECH Engineering 09-Oct-13 12-Oct-13 17-May-14 Company still awaits reply from Constractor Mar.2, 2014 Open LBE-DLM-MECH- 360 MR. AMIN DAELIM VAF 2 MECH Piping 09-Oct-13 12-Oct-13 26-Oct-13 Submit the welder performance report & return the revoked 20-Apr-14 Closed LBE-GLOBAL- MECH-361 MR. NASSAR GLOBAL VAF 2 MECH Quality Management 10-Oct-13 13-Oct-13 24-Oct-13 18-Feb-14 Closed LBE-DLM-INST-067 MR. PERVEZ DAELIM PN INST Material 13-Oct-13 16-Oct-13 27-Oct-13 14-Dec-13 Closed LBE-TCC-MECH- 363 MR. KURIAN TCC PN 2 MECH Mechanical (Equipment) 13-Oct-13 16-Oct-13 27-Oct-13 23-Mar-14 Closed PN: During surveillance and monitoring inspection at Operator Building, it was noticed that some materials scattered such as block mesh, CMU & cement located near at the north & west area which these materials are spare used. Contractor/Subcontractor is advised to remove/transfer to the warehouse for proper housekeeping and handling. Subcontractor: Amana already start removing and housekeeping the said area. Amana already removing material(14/Oct/2013) During routine inspection at ARCC fab.shop, it was observed that the listed reference drawing for fabricated lateral fitting in the BOM of IFC drawing (1016103BEA-P-124315-01) is not available with Daelim Engineering. Daelim provided another drawing for fabricated lateral fitting which is not approved and the material given is not matching with control material stamped. The material given in the drawing is ASTM A240 GR304H whereas control material is ASTM A358 304H. Contractor: During material receiving inspection, it was made clear that SS ASTMA 358 GR 304H cl3 were equivalent to A240TP304H. The materials were inspected and after acceptance, it was issued. During routine inspection at ARCC fab.shop, it was observed that SS material for MFC project is stored along with CS material for other project. This is a clear violation against RT-6-ICS & Project requirement. Subcontractor: Re-arrangement of stainless steel spools was carried out on staging/storage area of Sadara MFC spools with proper distance from storage area of other materials. During surveillance, it has been noticed that cold insulation activity has been carried out for Dryer Feed KO Drum (D-1718) during bad weather (Sand storm). Also QC Inspector & crew Supervisor not available at that time. This is clear violation against Sadara Standard & Schedule "Q". Found that Isometric IFC Drawings of Daelim are showing one of the notes in the left bottom corner for "FFW" (indicates Field Fir Weld, Pipe at this joint shall be fabricated 150mm longer) but actually on drawings it is not marked on any required locations. Discrepancy also enquired from Daelim Quality & Engineering Departments and Contractor also acknowledged. It is a violation of G4D-0140-10. Daelim Quality must ensure FFW markings on IFC drawings to avoid any discrepancy while connecting pipe joints to the rotating equipment. Some Ref. Dwg. Nos. are 054703-02, 051703-02 & 131109-01. Contractor: Daelim applies the following method to field welding around rotating equipment. 1. The tack weld requirement in G4D-0140- 10 at flange adjacent to rotary equipment nozzle is applied for both suction and discharge nozzle. 2. In case the fabricated spool length is not enough according to site condition, then Daelim judges whether it can be managed with specified FW or not. If it is judged that could not be managed then the pipe is to be cut and welded with additional longer pipe piece. 3. To make sure not to cause strain on the flange conncetion to rotary equipment nuzzle, Daelim checks the flange position and parallel condition nozzle without bolting after pipe piece installation is completed. 4. Daelim ensures the pipe strain on the rotating equipment nozzle does not exceed the limit of coupling movement specified in G4D-0140-10 and G5S-5321-02. 5. If any heating repair is conducted without prior written approval, Daelim re- fabricates the certain spool. Found that weld repair rates of ARCC, TCC, AYTB & PCMC have been increased more than 5% joint basis, violating Scheduule "Q" Attch. IV, Para. 3.9. Daelim Quality must provide the root cause analysis, corrective action and preventive measures as soon as possible. Rejection rate weekly & cumulative found excessive between 6% to 13%. Contractor: The welder whoever uses the limit of the allowable repair rate had been revoked and more precautions will be taken to control the weld repair. During routine site inspection, it was noticed that the Contractor installed type DB-120 PVC sleeve at Operator Building which is a violation as per G7D-0311-03 section 2.2, in which, type EB shall be used to be encased in concrete. Subcontractor: It is investigated and Construction agree to replace the conduit sleeve DB-120 to EB type sleeve as project per standard requirements. During inspection, it is found that the Contractor/Subcontractor carried out U/G Fire Water Line joint Fit- up and assembly. Contractor did not follow follow the drawing. Contractor Quality team must ensure that work is carried out as per approved & issued for construction drawings. Corrective action & preventive measure are required. Reference: Drawing No. FW-071005-03, Rev. 02, RFI No. MFC-DLM-KCC-UG- RTR-1815. Subcontractor: AS-Built drawing was already provided. In case and in order to carry out inspection, Subcontractor shall sue RED line drawing for Company inspection prior to As- Build drawing. It has been obsereved during bad weather (high wind & sand storm), liquid Coating activities has carried out at PCMC blasting/coating facility for Pipes & spools. Subcontractor: Work was stopped immidiately and affected areas were rectified and inspection was done and accepted against RFI No. PCMC-M-0109. Observed that ARCC welder W-AR-1828 performed Welding (Tacking) activities on Furnace F-1240. Radiant coil to primer TLE without appropriate qualification. On subject materials (35-45 Ni-Cu), violation: Sch. "Q" and Project Specification recommendation or RT8S-6500-1. Contrcator shall investigate the root cause of the subject descripancy and implement appropriate corrective action. Subcontractor: Qualification/JCC of Welder W-AR-1828 was revoked and presently was removed from Sadara MFC project. During routine inspection at ARCC fabrication shop, two welders were found welding more than the maximum allowable weld bead width for welds made with GTAW process (3 times (3x) the core wire or filler metal dia) as per RT-85-6500-01 & approved WPS. MOreover, one of the welder ACRR-613 was along two filler wire during production welding instead of one. Contractor: Action shall be taken regarding the issue of excess weaving: Weld layer. ARCC QC shall remove the weld layer and again re-weld it in accordance with the approved WPS. *613 welder should be removed from Sadara project. During surveillance inspection at Daelim laydown, it was observed that FRP Spool and fittings store without protection of end cores due to this sand accumulate inside the spool and fittings. This is violation of G85-6015-04 requirement stated in 3.2.1. Pipe Material at laydown such as FRP Spools, Carbon Steel and Fittings During routine inspection at Equipment D-1827, D-1917, E-2026, R-2025, R-2030 & R-2035, it has been noticed that the insulation Inspector of Global Suhaimi is not available at site during inspection activities. This is violation against schedule "Q". Subcontractor: The former QC Inspector assigned in the site/area has been removed from site and placed new QC to continue the work assignment. PN: During Material Receiving inspection of cable tray, it was found that Contractor released few 90 horizontal bend without inspection of material receiving of tray, this violates Schedule "Q". Thru misccommunication of material inspector and material department the said cable tray was released and it was noticed also that FMIR not yet signed. Contractor shall raise RFI and rest assured that cable trays are ingood condition. PN: During the pre-welding inspection at the Equipment C2 Splitter (12220), the square washer at the Anchor Bolts found grinded/removed of cap to 10mm length which were projection out of the bottom compression . Any deviation or modification, shall be approved by Engineering department of SME of both Contractor and Sadara (client). Ref: RFI-WE-0273 DRawing No. 72220-103-90003-44-230. Subcontractor: Noted. Construction group was informed regarding the issue. Page 34 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 30, 2014 DUE DATE Issued corrective action to Company Target Date S/N LBE NO. PID SUBCON/ CONTRACTOR VAF / PN LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason Company comment Approved Close LBE by Company STATUS CONTRACTOR'S CORRECTIVE ACTION PLAN LBE-TCC-MECH- 364 MR. KURIAN TCC PN 2 MECH Engineering 13-Oct-13 16-Oct-13 27-Oct-13 19-Feb-14 Closed LBE-TCC-MECH- 365 MR. KURIAN TCC VAF 2 MECH Structural 13-Oct-13 16-Oct-13 27-Oct-13 Engineering clarification note to be attached. 26-May-14 Closed 12 LBE-DLM- MECH-367 MR. HARIKUMAR DAELIM (Construction) VAF 2 MECH Mechanical (Equipment) 14-Oct-13 17-Oct-13 22-Oct-13 Open LBE-AMA-CIVIL-183 MR. JERRY AMA VAF CIVIL Civil 14-Oct-13 17-Oct-13 28-Oct-13 31-Dec-13 Closed LBE-AMA-CIVIL-184 MR. GERALD AMA PN CIVIL Civil 14-Oct-13 17-Oct-13 28-Oct-13 24-Oct-13 Closed 14 LBE-DLM- MECH-366 MR. SAYED DAELIM (Procurement) VAF 2 MECH Material 14-Oct-13 17-Oct-13 20-Jul-14 Verified 20-Jul-14 Closed LBE-SEN-ELECT- 068 MR. MARK SENDAN VAF ELECT Electrical 16-Oct-13 19-Oct-13 30-Oct-13 10-Nov-13 Closed LBE-TCC-MECH- 368 MR. SAYED TCC VAF 2 MECH Mechanical 20-Oct-13 23-Oct-13 03-Nov-13 20-Feb-14 Closed LBE-AMA-CIVIL-185 MR. JERRY AMA VAF 1 CIVIL Civil 20-Oct-13 23-Oct-13 03-Nov-13 On-going., to be closed upon implementation. 27/10/13. 26-Mar-14 Closed LBE-AMA-CIVIL-186 MR. GERALD AMA PN CIVIL Civil 20-Oct-13 23-Oct-13 03-Nov-13 24-Oct-13 Closed 13 LBE-DLM- MECH-369 MR. KURIAN DAELIM (Procurement) VAF 2 MECH Mechanical (Equipment) 21-Oct-13 24-Oct-13 04-Nov-13 Open LBE-DLM-MECH- 370 MR. KURIAN DAELIM VAF MECH Mechanical (Equipment) 21-Oct-13 24-Oct-13 04-Nov-13 17-Nov-13 Closed LBE-TCC-MECH- 371 MR. SAYED TCC VAF 2 MECH Piping 21-Oct-13 24-Oct-13 04-Nov-13 20-Feb-14 Closed LBE-AYTB/PCMC- MECH-372 MR. KHAN AYTB/PCMC VAF MECH Quality Management 21-Oct-13 24-Oct-13 04-Nov-13 06-Jan-14 Closed LBE-AYTB-MECH- 373 MR. AMIN AYTB PN MECH Piping 21-Oct-13 24-Oct-13 04-Nov-13 27-Nov-13 Closed LBE-DLM-ELECT- 069 MR. MARK DAELIM VAF ELECT Electrical 22-Oct-13 25-Oct-13 05-Nov-13 10-Nov-13 Closed LBE-ASYAD-INST- 070 MR. PERVEZ ASYAD VAF 1 INST Mechanical 22-Oct-13 25-Oct-13 05-Nov-13 25-Jan-14 Closed During surveillance work at Flare Area Pipe rack, it was discovered that two anchor bolts were cut in one foundation due to equipment working in the area doing backfilling works hit the foundation. This is a second incident where anchor bolts were cut due to equipment being near the foundation . It was previously discussed during the QC meeting that heavy equipment should not work near foundation to avoid damage to foundation. This is a recurring incident and Contractor shall implement proactive action to avoid recurrence, see LBE # 177. Subcontractor: Advised to Contruction to use or install hard barricade to avoid accident in the future. Amana will submit Method of Statement for approval and will start repairing work as per approved method statement. PN: During inspection at diesel generator building along column C & C2 (2nd lift) and beam. We found out that some installed formworks are not acceptable "old formworks". In this regards, Contractor was advised to remove & replace with new one for good surface finish after concerning was done or implemented. Subcontractor: Advised to Constrruction and Civil QC Inspector to check formworks condition, used plywood are acceptable or not if any damage plywood used, immediately replace with new one.(see attched picture) During Material Receiving inspection, it was again found that 1/2" CS ASTM A106 GR Galvanized pipes without material identification mark on the pipe or tag on the bundle. RFI No. GERAB-PIP-004 P.O. No. LPO- 100532-42-POI-008-A01, Supplier GERAB National Enterprises. This is violation of Sch. "Q", attachment 4 Para. 4.4. Verfied. PN: A gap of 20mm and 25mm found on horizontal beams at C13 8 C10, Rf. Dwg. (2676-083) Structural) Engineering solution is required. Subcontractor: Noted. Action will be taken accordingly. During Fit-up inspection for Structural Steel Air Cooler support near N-S cable rack Suuper (G013) was tack welded to the embedded plate with a gap of 15mm, the embedded plate was not positioned in "Straight" to the beam which cause the gap. There should not be gap in between filled weld member (plate). Ref. B31-3,3288.5.2, 328.5.2A fig.) Ref. Dwg. A554-E-103-CV-DWG-S20-641, Rev. 3. Subcontractor: Noted. Action will be taken accordingly. Observed that Surface Condensater (CG Compressor #2301) pressure parts. (Vendor clossed part) were open for easy installation which is not designed for Contractor activities. Daelim/TCC team is not authorized to open/relocate the PCE without proper approval, elsewhere it has be to be designed for further Constraction. Violation of Sch. "Q" and ITP and required corrective action. Contractor: Noted: Contractor Engineering Dept. will issue documents to primarily support this aactivity. Target date: 1st week of Nov. 2013. During surviellance inspection at TCC site area, it was found that Welders (ID Nos. 213 & 394) were performing Welding of 36" pipe joint with cold low hydrogen eleectrodes. This is violation of Sadara Specification RT8S-6500-03, Att.1. Submit warning letter to Company. Subcontractor: Tool box meeting was conducted to welders on 22nd October 2013, regarding the issue. Welder Nos. 213 & 394 were issued with warning letter for said violation. RT was carried out at AYTB & PCMC fabrication shops during Eid Holidays by NDT Service provider "RAWABI" non of the procedures & NDT technicians are approved by Company. Also, prior to start of any activity, Contractor shall initiate Kick-Off Meeting as per Sch. "Q" requirement. PN: Found that SS pipe spools are not preserved/covered properly at AYTB Fab. shop and getting environmental effects shich may cause corrossion. Also AYTB needs to improve storage arrangements to avoid cross contamination. Contractor QC team must ensure quick correctve action with Preventive measures. Ref. RT-6-1CS, Rev. 3, Para. 2.15, 2.19.9, 2.19.2. Contractor: AYTB QCs & its Construction team were advised that all the SS Spools must be protected. Action will be taken. PN: During inspection at Cooling tower sum-pump area "external wall" (North side) along wall 6 & 8, found out that filler board is already installed without conducting first DFT (second coat application) by Third party. Contractor is advised to remove first the installed filler board and conduct DFT prior to re- install said filler board. Subcontractor: Advised to Construction that before starting installation of filler board, coordination with QC Inspector has to be confirmed that coating thickness checking is done or not. (see attached picture) At surveillance, it is observed that Equipment E-2303 bottom side of the supporting leg is not painted as per the required painting specs. Also this part is corroded which may damage the metal support. This is the improper following of painting spec. The equipment is supplied by Doosan Engineering with P.O. No. 100532-13-231-001. Contractor: Noted. Action shall be taken and as per Construction Plan for the corrosion, painting touch-up repair shall be commenced/implemented. Target Date: 25 Nov. 2013. During surveillance, it's being observed that Equipment E2110 (Demethanizer reboiler) with incorrect paint (different specs) on the equipment body which is wrong as per the drawing. Equipment is supplied by Dossan Engineering. During routine inspection, it was found out that the Contractor installed Fastener for expansion splice plates without a Flat Washer and Self-Locking Nut which is a violation as per G7C-0324-01, Note 4. During surveillance inspection at TCC site (near Dryer pipe rack), it was noticed that pipe spool connected to Equipment (FL-2041, FL-1723 & E-2026) prior to Mechanical clearance (like flange face inspection, etc.) This is violation against Company Procedure A554-E-103-QA-GEN-PRO-059, Rev. 3, Para. 9.3.3.3. Subcontractor: Noted. Action will be taken accordingly. RFI will be raised for flange face inspection. It was noticed that the backfilling of foundations at flare area is goin on without proper compaction and moisture content of soil is not in accordance with RT2S-2200-01, Rev. 4, Para. 3.4.9. The subcontractor is backfilling the area without compaction record of each foundation layer by layer since the foundations were excavated individually. Contractor to provide record of compaction testing for each foundation layer by layer. Subcontractor: Advised to Construction that before preparing subgrade, remove 200mm top loose soil and recompact below soil before layinf next layer. Amana will raise RFI for final layer inspection prior to start gravel bedding. During routine site inspection, it was found out that the Contractor already pulled and laid a cable to the cable tray without final acceptance of the cable tray from the Company inspector which is a violation as per approved ITP and schedule Q. Also, it was found out, in the inspection of the said cable tray, several standard violations occured. First, the vertical interval support was measured with 3,000mm and the maximum shall be 2440 mm as per 67C-0324-04 note 4. Secondly, there is no support before and after vertical elbow fitting which is a violation as per 67C-0.24-04. And lastly, at expansion splice plate During site surveillance, it was noticed that Contractor/Subcontractor installed Junction box on column and not as per standard, instead of Bolt connector but was welded on beam. This is standard violation of G-07C, 0326-64. Contractor submit RFC to Company for clarification. Company answered thru transmittal no. MFC-T-CJ-DS-IC-0560. Page 35 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 30, 2014 DUE DATE Issued corrective action to Company Target Date S/N LBE NO. PID SUBCON/ CONTRACTOR VAF / PN LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason Company comment Approved Close LBE by Company STATUS CONTRACTOR'S CORRECTIVE ACTION PLAN LBE-DLM-INST-071 MR. PERVEZ DAELIM PN 1 INST Instrumentation 22-Oct-13 25-Oct-13 05-Nov-13 25-Jan-14 Closed LBE-DLM-MECH- 374 MR. AMIN DAELIM PN MECH Preservation 22-Oct-13 25-Oct-13 05-Nov-13 27-Nov-13 Closed LBE-SEN- TELE-001 MR. RODNEY SENDAN VAF 1 TELECOM Telecomunication 22-Oct-13 25-Oct-13 05-Nov-13 20-Jan-14 Closed LBE-SEN- TELE-002 MR. RODNEY SENDAN VAF 1 TELECOM Telecomunication 22-Oct-13 25-Oct-13 05-Nov-13 20-Jan-14 Closed LBE-SEN-TELE-003 MR. RODNEY SENDAN VAF 1 TELECOM Telecomunication 22-Oct-13 25-Oct-13 05-Nov-13 01-Feb-14 Closed 16 LBE-DLM- TELE-004 MR. RODNEY DAELIM (Enginnering) PN 1 TELECOM Telecommunica tion 22-Oct-13 25-Oct-13 20-Feb-14 20-Jul-14 Closed LBE-AMA- TELE-005 MR. RODNEY AMA VAF 1 TELECOM Telecomunication 23-Oct-13 26-Oct-13 06-Nov-13 13-May-14 Closed LBE-ARCC-MECH- 375 MR. KHAN ARCC VAF 2 MECH Piping 24-Oct-13 27-Oct-13 31-Jan-14 04-Mar-14 Closed LBE-DLM-MECH- 376 MR. SAYED DAELIM PN 2 MECH Material 26-Oct-13 29-Oct-13 15-Feb-14 28-Feb-14 Closed LBE-TCC-MECH- 377 MR. AMIN TCC PN MECH Piping 26-Oct-13 29-Oct-13 09-Nov-13 06-Jan-14 Closed LBE-KCC-CIVIL-187 MR. JERRY KCC VAF CIVIL Civil 26-Oct-13 29-Oct-13 09-Nov-13 17-Nov-13 Closed LBE-AMA-CIVIL-188 MR. GERALD AMA VAF CIVIL Civil 26-Oct-13 29-Oct-13 09-Nov-13 04-Nov-13 Closed 17 LBE-TCC- MECH-378 MR. SAYED TCC VAF 2 MECH Piping 27-Oct-13 30-Oct-13 10-Nov-13 20-Jul-14 Verified 20-Jul-14 Closed 18 LBE-DLM- MECH-379 MR. SAYED DAELIM (Procurement) PN 2 MECH Material 27-Oct-13 30-Oct-13 03-Mar-14 Verified 20-Jul-14 Closed LBE-PCMC-MECH- 380 MR. KURIAN PCMC PN 2 MECH Piping 27-Oct-13 30-Oct-13 10-Nov-13 Still Company waiting for reply Mar.2, 2014 21-Oct-13 Closed LBE-TCC-MECH- 381 MR. NASSAR TCC VAF 2 MECH Preservation 27-Oct-13 30-Oct-13 10-Nov-13 16-Feb-14 Closed LBE-GLOBAL- MECH-382 MR. NASSAR GLOBAL VAF 2 MECH Preservation 27-Oct-13 30-Oct-13 10-Nov-13 16-Feb-14 Closed At Bdlg. G-1122 Operator building the Contractor uses the outlet box as a oullbox. This in violation of RT- SAES-T-916 Para. 4.8.18.2 states that in commentary note, the outlet box shall not sevre as a pull point. Contractor shall comply as per specifications. PN: At the TER of Bldg # G-1121, no enough space to install the 3/4" backboard. And no 38mm clearance in between the conduits inside the TER. Contractor: Backboard was rectified to accommodate the sub-duct. At building # G-1120 adjacent to pipe rack, communication conduits not using inproper end plugs. Advised to construction to replace the end cap with correct material. AMANA has already replaced trge conduits end caps and work has been done and approved. PN: Found that alloy & LTCS pipes are shifted to PCMC Fab. Shop which needs proper identification and segregation arrangements to avoid mix-up and misuse of different materials. Ref. TR-6-1CS Para. 2.19.8. Contractor: QC & Construction team were informed. Proper corrective action will be taken. Observation noted. Contractor installed different types of cable tray to be used to distribution system. Contractor is advised to change rge cable tray with perforated tyoe and must be capable enough to house the numbers of IWA for Buildings requirements. See IFC details for cable tray for telecoms. G1122 MFC/Daelim Contractor shall replace the cable tray as per specifications and Company will be informed thru RFI. Contractor already removed the installed cable ladder type tray. Once the aactivity started, Company will be notified and also for the compliance of materials and installation. Contractor offer the LBE to company for closure. In building (G1122 Operator Bldg.) Contractor installed cable tray at the height of almost 4m and it is not accessible because it will be on top of the HVAC ducting. This in violation of Sadara standard SAES-T- 916 stating that the cable tray must be accessible for maintenance and operation work force RT-SAES-T- 916 Para. 4.3.5.1 The cable tary height is should be 30cm from the ceiling as per RT-SAES-T-916 4.3.5.1 Contractor shall replace the cable tray as per specifications and Company will be informed thru RFI. Contractor already removed the installed cable ladder type tray. Once the aactivity started, Company will be notified and also for the compliance of materials and installation. Contractor offer the LBE to company for closure. PN: During line inspection for Material Receiving at Daelim Laydown yard, it was observed that Tray was not preserved but kept together without separation. This violates NGM- VA2, & Schdule "Q". Contractor QC informed already and coordinated as well to material department regarding this PN. Company will be informed for action. PN: During Material Receiving inspection at Daelim laydown, it was observed that ASTM A106 GR B Pipe of different sizes received without performing Hydrotest at Manufacturer and no marking of Hydrotest on pipes. RFI No. MFC-DLM-TEN-PIP-021, Shipment No. MFC-05-1, P.O. No. 100532-42-P01-006-A01. This is violation of ASTM A106, Para. 13.1 & Para. 25, Table 4. Contractor: Hydrotest reports were provided by Vendor. It was submitted to Company. PN: During Surveillance at PCMC (East-West) pipe rack pipes were found with open ends. This is a violation as per A554-E-103-QA-GEN-PRO-059, Rev.2, Para. 7.3.5 G4S-4210-01, Para. 3.1.4. Subcontractor: Noted, and PCMC shall take the preventive action, all the pipe ends are closed and it is on-going. It has been noticed that at Blasting/Painting facility (TCC-1), Spools are released to blasting/painting facility before RT examination & PWHT on the welded joints. Those spools already blasted and painted. Contractor: Noted and action will be taken. Four spools were shifted to painting workshop without spool relaeasing inspection prior to blasting and painting. Painted spool was returned ti PWHT area for complete balance activity. After completing PWHT, RFI will be attached. Daelim NCR # 040 for same issue. With reference to RFI # MFC-DLM-KCC-CI-4770, the attached weekly materials test report is the same as the weekly materials test report of the previous week. This is a violation of RT2S-3001-01 Table 1 regarding weekly testing if raw materials for concrete for the specified test. Contractor/Subcontractor to review all materials test report prior to submission. Said RFI is rejected. Contractor: Due to the delayed release of weekly test results from Third party laboratory, subcontractor KCC attached same results from the previous week which was overlooked by Contractor QC Inspector. RFI will be resubmitted with the Third party. Contractor asks for Company consideration and assure the same will not happen again in the future. During surveillance inspection at diesel generator building G1124 along newly casted concrete on roof slab, it was noticed that insufficient water curing applciation has been done by subcontractor which violates RT2S-3001-01, Section 9, Para. 9.1.2. Contractor is advised to take corrective action concerning the issue. Subcontractor: Already advised to Constructiona and already implemented that Amana had extended the curing of water up to 8 days. Also make sure that curing of water on structure at 3 times per day to control the abrupt evaporation of water. During Surveillance inspection at TCC site area, it was noticed that 19 nos. of Fabricated pipes of 2", 3" & 4" found distorted after welding. (e.g. 3" - N016103N2A-SSLD-075303-01 joint No. 2 & 4" -NO16103N2A-NL-041202- 01 joint no. 03). This is violation of ASME B31.3 Para. 321.1.1 which states that "The design of piping and its supporting elements shall be directed towards preventing excessive distribution or sag in the pipe. Noted and action will be taken. Some of deffective weld joints are rectified and found acceptable. Work is on-going. During routine inspection at ARCC Fab. Shop, it was observed that PMI has not been performed on weld joints for line class PU74 prior to PWHT, 12 joints have been not treated without performing PMI. As per Sadara requirement (RT8S-4001-61) PMI shall be conducted before any PWHT. Contractor: Issue has been notified to ARCC and PMI will be contacted before PWHT. PN: During Material Receiving inspection at Daelim laydown, it was found that the Gasket offered for inspection without color code. Approximately 30,000 Metallic Gasket without color code. This is violation against Sadara Specs G4S-3240-60 and Contractor Procedure. A554-E-103-QA-GEN-PRO-059. PN: Found mishandled released pipe spools for site at TCC Fabrication Facility #1. Pain is damaged on different locations of the spools by rigging team and transferring spools to site without involvement of TCC & Daelim Quality. It is also happened because spools were not transferred to site on the same date when inspected. Also trailer driver was not having any kind of document to handover to site people like spool release report signed by Quality. Noted and action will be taken. Tool box meeting has been conducted with riggers for proper use of lifting tools and wood packing on trailer during shifting of pipe spools to MFC site. During normal inspection at MFC site, it was noticed that Insulation on daddle supports for Equipment T- 1910, T-1510 & T-1820 have not been completed yet and those areas did not protect properly against weather condition (sandstorm, rain, humidity, fog, etc) which leads to insulation damage. Subcontractor: Subcontractor already covered all saddle support by venture clad and complete it. Page 36 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 30, 2014 DUE DATE Issued corrective action to Company Target Date S/N LBE NO. PID SUBCON/ CONTRACTOR VAF / PN LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason Company comment Approved Close LBE by Company STATUS CONTRACTOR'S CORRECTIVE ACTION PLAN LBE-DLM-MECH- 383 MR. AMIN DAELIM PN 2 MECH Quality Records 27-Oct-13 30-Oct-13 23-Mar-14 Closed 20 LBE-ARCC-MECH- 384 MR. HARIKUMAR ARCC VAF 2 MECH Piping 27-Oct-13 30-Oct-13 10-Nov-13 14-Jul-14 Closed LBE-TCC-MECH- 385 MR. AMIN TCC VAF MECH Piping 27-Oct-13 30-Oct-13 10-Nov-13 06-Jan-14 Closed LBE-DLM-ELECT- 006 MR. PERVEZ DAELIM VAF 1 ELECT Preservation 30-Oct-13 02-Nov-13 13-Nov-13 Company: According to Contractor response, it's not clear regarding Preservation Plan, Contractor has to follow as per LBE or has to provide 19-Nov-13 Closed LBE-DLM/KCC- MECH-386 MR. NOOR DAELIM/KCC VAF MECH UG-RTR 03-Nov-13 06-Nov-13 17-Nov-13 25-Nov-13 Closed LBE-DLM-MECH- 387 MR. AMIN DAELIM VAF MECH Quality Records 03-Nov-13 06-Nov-13 17-Nov-13 06-Jan-14 Closed LBE-AMA-CIVIL-189 MR. JERRY AMA VAF CIVIL Quality Management 03-Nov-13 06-Nov-13 17-Nov-13 16-Dec-13 Closed LBE-DLM-ELECT- 007 MR. MARK DAELIM PN 1 ELECT Preservation 03-Nov-13 06-Nov-13 17-Nov-13 Closed 19-Nov-13 Closed LBE-DLM-MECH- 388 MR. AMIN DAELIM VAF MECH Preservation 04-Nov-13 07-Nov-13 18-Nov-13 28-Nov-13 Closed LBE-AMA-CIVIL-190 MR. JERRY AMA VAF 1 CIVIL Civil 04-Nov-13 07-Nov-13 18-Nov-13 Closed LBE-DLM-CIVIL-191 MR. JERRY DAELIM VAF CIVIL Civil 04-Nov-13 07-Nov-13 18-Nov-13 14-Dec-13 Closed 19 LBE-ARCC- INST-072 MR. PERVEZ ARCC VAF 1 INST Instrumentation 05-Nov-13 08-Nov-13 19-Nov-13 16-Jul-14 Closed LBE-PCMC- MECH-389 MR. KHAN PCMC VAF MECH Piping 06-Nov-13 09-Nov-13 20-Nov-13 02-Jan-13 Closed LBE-ASYAD-INST- 073 MR. PERVEZ ASYAD VAF 1 INST Instrumentation 07-Nov-13 10-Nov-13 11-Nov-13 31-Mar-14 Closed LBE-ASYAD-INST- 074 MR. PERVEZ ASYAD VAF 1 INST Instrumentation 07-Nov-13 10-Nov-13 11-Nov-13 31-Mar-14 Closed LBE-ASYAD-INST- 075 MR. PERVEZ ASYAD VAF 1 INST Instrumentation 07-Nov-13 10-Nov-13 17-Nov-13 08-Apr-14 Closed LBE-TCC- MECH-390 MR. KURIAN TCC VAF 2 MECH Piping 07-Nov-13 10-Nov-13 21-Nov-13 28-May-14 Closed Found that Daelim Quality not revising and resubmitting the qulaity documents like QCP of welding activities and consumable control procedure & ITP for Welding of On Plot Piping whose dates are overdue since March, May 2013. Severally instructed but still noaction carried out. It is a violation of Sched. Q Para. 3.5 Also found that joint identification numbering for repairs and rewelds by CIMS is conflicting with DAELIM QCP and Company Procedure A554-O-PRG-QA-GEN-PRO-013. Corrective action with preventive measure is required. Contractor: QCP for Welding and Consumable Quality Control ProcedureRev. 2 and ITP for Welding On-Plot Piping Rev. 2 have been submitted to Company on 6 Nov. 2013. Weld identification numbering also revised as per CIMS requirements in Rev. 2 of Welding and Consumable Quality Control Procedure, also procedure for Welding Repair (A554-E-103-QA-GEN- PRO-119) Rev. 1 submitted to Company on 11 Nov. 2013. All due date ITP and QCP already submitted to Company. It was observed that during the concrete placement of paving south of E-W pipe rack/ air cooling area, there are no QC inspectors for the subcontractor and Contractor monitoring the testing of concrete and concrete placement of the paving. This is a violation to SMITP-Q-001-02 which is a witness point for the Contractor. Contractor: The Contractor has arranged with the QC Civil Inspectors to make sure that one Inspector will be present at the Concrete testing checkpoint and one inspector in the concreting location area. PN: During routine site surveillance at Daelim laydown yard, it was noticed that new variable frequency diliveries arrived at site. These control equipment shall be store inddors as per RT-6-1CS, section 2.9.1. Contractor: VFDs are now transferred to site and already inside of each substation to comply on its Preservation requiremetns. Found that TCC fabrication team did some lettering (60mm wide & > 12mm thick) around the CS80" dia. pipe branch connection to fire the wrong (short or distorted radios) RF pad on it. RF pad internal and external edges were not able to fit on the main pipe due to approx. 2" gap. TCC was also using an unapproved and wrong drawing sketch for branch connection & RF pad Fit-up detail. Above violations shall be avoided to repeat. Daelim Quality must ensure the corrective action with preventive measures. Noted and action will be taken. DPT has been done and found acceptable. During Surveillance at laydown yard, it was observed that 7 nos. of Analyzer shelter have arrived and kept outside the warehouse without airconditioned and temperature not maintained as per IEC-60079 part II. The door of Shelter is open and inside temperature is hot and humid. These violate IEC-60079 part II. Contractor: Daelim is waiting for the documents/manual of the Analyzer which include the specific/Applicable preservation requirements on the shelter unit. As per Project specific requirement RT-6-ICS Rev.3, section 2.12.4: Analyzer shelters and complex analyzer shall be stored as per the recommendations of the suppliers. During inspection, it is found that the Contractor/Subcontractor (KCC) performed joint assenbly butt and wrap instead of bell and spigot joint of UG fire water line 8" dia, violating the IFC isometric drawing # FW- 071065-01-02. Three (3) joints no. (FW-06, FW-07 and FW-11) found with the same discrepancy by Company. Preventive measures are required. Ref: ES17, Para. 3, P,PSES1701. Noted: Contractor received approval from the Daelim Engineer on the line drawing for Butt- wrap joints instead of Bell & Spifot joint. The joint has been made as per FRI receive and infomed CIMS for the As-Built drawing. PN: Contractor shall forward records of all non-conformances to Company within 48 hours of issue. Contractor shall provide the Company representative with an explaination for non-conformances that will require more that 14 days to resolve. Contractor shall respond in writing, including proposed corrective action, to all non-conformance issued by Company within three (3) business days of receiving notification of the non-conformance. Ref. Sch. Q, Para No. 7.3.3, 7.3.4 & 7.3.6. Subcontractor: Action will be taken informed to all concern and will comply with the given notification to the company. During surveillance inspection at ARCC area (Furnace and East-West pipe rack area observed the following discrepancy. (Ref: HC-35 3"). Distortion occurred on weld joints due to improper method of fabrication and lack of temporary supports. Random spools were inclining/uneven or sag in position during Fit-up and welding . Alignment, leveling and strengthness were not followed during Fit-uop and welding time. Daelim shall take necessary action to control the implemented method at site. Distoration occured spools shall be rectified with approved repair method. Subcontractor: ARCC construction group to be rectified the distorted joints, will provide proper supports prior to full welding to avoid distortion. Cut & weld. During site surveillance at furncae pipe rack, it was observed that cable pulled in improper way not in a good engineering practice cable layed in scaffolding pipe and ibstruct with support. This is project standard violation of NEC-70 Article 110.12, Method of statement & Schedule Q. Subcontractor : Cable will be supported properly with a wooden flanks with softener above, to protect the cable from stressed. Also, obstructions will be removed. During time of site surveillance, it was observed that cable tray has been damage after inspection of cable tray at furnace pipe rack & wrong bolt used in vertical drop of tray support. This is standard violation of Schedule Q, G-7C-3024-04, G-07-0321-01 & NEMV-V2 Subcontractor : Cable tray (damaged) has been replaced including the bolts from hexagonal to mushroom type. During surveillance SHOW sub-contractor TCC lifting spool to attach flange nozzle of equipment E2020 in a wrong way, which can damage the equipment. Also, the equipment is position to the correct alignment tolerance previously which can be effected due to this way of lifting by putting full load or stress than fall on the equipment. Realignment of the equipment is to be scheduled with new RFI to re-assure the centering, elevation and plumbness. Contractor: Noted and action will be taken. Tool Box meeting has been completed with Equipment group regarding the issue. Next time it will be taken cared properly. During site surveillance, it was observed that Actuator dial damage for 36" MOV D.D.B. valve during the installation of F-1170. This is standard violation of Schedule Q. Contractor requested to take preventive action. Contractor: Contractor has issued NCR to ARCC for corrective action. ARCC requested to Daelim Construction for the replacement. Daelim escalated to NCR, No. NCR-ARCC-INST-001. ARCC requested Daelim to provide MOV in which ARCC shall install. During routine inspection at PCMC fabrication shop it was observed that SS pipes are stored along with CS pipes, violation of SADARA specs. RT-6-1CS. During inspection of cable tray, it was observed that on furnace pipe rack cable tray support was not as per standard support installed on more than 3 meters and hold down clamp missing. This is standard violation of G7C-0324-04 Subcontractor : Additional support will be installed in order to mee the 3m. Maximum distance between supports. Complete accessories will be installed. Found that preservation and storage of SS, LTCS & Alloy Piping material is improper even in the rainy environment. Pipes and fittings are in non-drainable positions without end covers having little water stagnant in them with improper storage. Company instructed severally and also logged LBE#373 but still no action taken. Daelim quality must ensure the corrective action and preventive measures. Ref. RT-6- 1CS. Rev. 3 Para. 2.15, 2.19.9, 2.19.12, 2.19.4, 2.19.16. Contractor: Noted. Action will be taken. Action has been taken. Pictures were send by email. The LBE # 373 was also closed. During inspection of paving at substation G-1120 area, it was noticed that some of the joints of TPER were not welded properly Welding of TPER joints shall be performed by trained personnel as required by Manufacturer's Recommendation/Instructions. Subcontractor: Persons who did not undergo the proper training of installation and welding of TPER were already removed from the group. Only trained personnel are allowed to conduct the said activity. During inspection of paving front of Expander Building, the Contractor cut the TPER at the ramp. Contractor shall submit revise drawing and/or method Statement to provide continuity of TPER as recommended by the Manufacturer. Subcontractor : Daelim Engineering will issue drawing regarding the TPER that has been cut at Expander Building. Method of Statement shall follow upon the issuance of the drawing. Page 37 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 30, 2014 DUE DATE Issued corrective action to Company Target Date S/N LBE NO. PID SUBCON/ CONTRACTOR VAF / PN LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason Company comment Approved Close LBE by Company STATUS CONTRACTOR'S CORRECTIVE ACTION PLAN LBE-TCC- MECH-391 MR. AMIN TCC VAF 2 MECH Piping 07-Nov-13 10-Nov-13 21-Nov-13 10-Feb-14 Closed LBE-AMA-CIVIL-192 MR. GERALD AMA PN CIVIL Civil 09-Nov-13 12-Nov-13 23-Nov-13 31-Dec-13 Closed LBE-AMA- MECH-392 MR. SAYED AMA VAF 2 MECH Hvac 10-Nov-13 13-Nov-13 24-Nov-13 24-Apr-14 Closed LBE-AMA-CIVIL-193 MR. JERRY AMA VAF 1 CIVIL Civil 11-Nov-13 14-Nov-13 10-Mar-14 06-May-14 Closed LBE-SEN-ELECT- 076 MR. MARK SENDAN VAF ELECT Electrical 11-Nov-13 14-Nov-13 25-Nov-13 27-Nov-13 Closed LBE-GLOBAL- MECH-393 MR. HARIKUMAR GLOBAL PN 2 MECH Mechanical (Equipment) 11-Nov-13 14-Nov-13 25-Nov-13 23-Mar-14 Closed LBE-ARCC-MECH- 394 MR. HARIKUMAR ARCC PN 2 MECH Mechanical (Equipment) 11-Nov-13 14-Nov-13 25-Nov-13 23-Mar-14 Closed LBE-ASYAD-INST- 008 MR. PERVEZ ASYAD VAF 1 INST Preservation 11-Nov-13 14-Nov-13 25-Nov-13 Closed 01-Feb-14 Closed LBE-SEN-ELECT- 077 MR. MARK SENDAN PN ELECT Electrical 12-Nov-13 15-Nov-13 26-Nov-13 28-Nov-13 Closed 14 LBE-DLM- MECH-395 MR. HARIKUMAR DAELIM (Enginnering) VAF 2 MECH Mechanical (Equipment) 12-Nov-13 15-Nov-13 17-May-14 Open LBE-ASYAD-INST- 078 MR. PERVEZ ASYAD VAF 1 INST Instrumentation 14-Nov-13 17-Nov-13 28-Nov-13 25-Jan-14 Closed LBE-AMA- MECH-396 MR. GLENN AMA VAF 2 MECH Mechanical 14-Nov-13 17-Nov-13 28-Nov-13 26-Jan-14 Closed LBE-ASYAD-INST- 079 MR. PERVEZ ASYAD VAF 1 INST Instrumentation 16-Nov-13 19-Nov-13 30-Nov-13 25-Jan-14 Closed PN: Equipment are releasing to construction activities. Daelim advised to implement appropriate action to control debris, grinding and welding particles etc. . . Are entrap in the exchanger tube and other accessories. * Implement cleaning method prior and after hydrotest for pipe circute directly connected to equipment. Implement cleaning Method for Furnace Radiant Tube and cross over piping system and liner exchanger. It shall be got prior approval from Company SME. Subcontractor: ARCC Construction group will provide proper protection on equipment, tubes and other structures around the area with grinding and welding activities. During site surveillance, it was observed that at G-1121 area Contractor kept all Instrument Panel without information of Company and not preserved. No airconditioned and kept outside in Sun without proper preservation. This violates project specification A554-E-103-CM-GEN-PLN- 002. Contractor: Installed instrument panel are now preserved and temperature and humidity are maintained as per approved Preservation Plan. PN: During routine site inspection, it was observed that the installation of cable tray at the transformer yard going to substation (G-1120 & G-1121) may not meet the required bending radius of the cables. The Contractor shall verify and confirm that the installation of cable in this area shall meet the bending radius requirement of the cable. Contractor : Based on design aid of Sadara installation of Cable tray at substation G-1121 & 1120 will accommodate the bending radius of power cables. It was noticed that the slope of the open ditch south of Sump 0906 Open ditch 0636-D750-026 is not in accordance with the drawing. Water/drainage will not flow on the east portion of the branch of the ditch because it is lower than the adjacent elevation. Contractor shall rectify elevation. Contractor: Regarding open ditch 0635-D750-026, Amana already started the chipping of ditch slab to maintain the slope as per IFC drawing. Once chipping finish, Amana will submit RFI to start grouting. During routine site inspection, it was noticed that the Contractor already puled a cable in a cable tray that was not yet inspected and accepted by Company inspector which is a violation as per approved ITP and Schedule Q Attachment IV Section 3.7. Contractor : There was a miscommunication between the Contractor & Subcontractor regarding the installed cable tray. This resulted to the not inclusion of the said cable tray installation activity in previously raised RFIs. - Contractor raised RFI to Company and was accepted. PN:Observed that Daelim and Subcontractor started insulation activities for static equipment (tower, Column, exchanger drum, etc.) at ground level prior to position on foundation. Daelin shall advised to implement appropriate option for alignment and plumbness verification for vertical and horizontal equipment according to Sadara Specification : G9G-1000-01,k G9G-1000-02 and ITP A554-E-103-QA-GEN-PLN-056. Contractor: Noted. Action will be taken. TCC Equipment Inspector will be making sure all works as per approved ITP & Procedure Found that two rejected elbows (102" dia.) transferred to inside the sandblasting area of TCC # 1. As per Daelim M/S of Repair for Damaged Fittings Doc. # A554-E-103-CM-GEN-PI-006, these elbows were supposed ti be shifted in the segregated quarantine area for buildup by welding rectification but TCC still dont have specified any quarantine area. Corrective action with preventive measures are required. Ref. Sched. Q Attch. IV Para. # 3, 4 & RT-6-1CS Para. # 2.2.11, 2.1.9.2 Contractor: Noted and action will be taken. After Built-up activity complete accepted report will be attached. PN: During surveillance inspection at Cooling Tower Basin "internal portion" for repair works, it has been observed that no proper curing compound application using "Masterkure: for the newly repair areas or portion. In this regards, Contractor was advised to take corrective action concerning this issue. In order to comply with the repair procedure. Subcontractor: Advised to Site Engineer and QC Inspector to monitor curing compound application properly to avoid any problem in future. In substation G1121, AMANA had completed blarzing of 60 joints without isometric drawing and brazing activity was carried out in the absence of HVAC inspector. This violates Sched. Q Item 1.2 & 5.9 On the specific issue an NCR (NCR-AMA-HVAC-002 dated 2/11/13) was issued to AMANA. Still waiting to close the NCR from subcontractor. NCR was closed and accepted. During site surveillance, it was noticed that Contractor installed MCt at substation without approved Method Statement & ITP & QCP. This is violation of Schedule Q. Subcontractor: Method staement & ITP have been prepared and submitted and waiting for its approval. Installation process of Incinerator at spent caustic area noted the following discrepancy: * Alignment process of smelt dissolver and incinerator sole and filler plate height exceed up to 70: as recommended by gvendor it shall be 20mm. *Incinerator holding structure (secondary girder beam @ 23050) are showing inclination level variance and gusset plate are slightly bend. * Bolt length are not sufficient to engage lock nut as per vendor design. * Daelim shall advised to re-evaluate the structural integrity and fix the discrepancy with prior approved Method by Company. Contractor: This item already have been solved. Please note as below description. Although the alignment height is approx. 20mm as per vendor print, Contractor will adjust the alignment through inserting the more filler plate at site. Hence, Contractor eill request vendor to confirm whether 70mm height for alignment is suitable; and receive the confirmation letter. Also, Daelim will officially receive the revised drawing as per site adjustment. The exact slightly in AISC Code, Flange-tilt tolerance are allowed to 8mm, in case depth exceeds 300mm. The depth of W12x40 is 303 mm, which means the tilt tolerances could be approved by 8mm. So the case of support beam for IN-0510 is no problem. During Site surveillance it was observed rgar rge installation of cable tray at C3 Splitter pipe rack not as per standard, cable tray supports under the expansion splice plate required 200mm wide as per approved RFC Document No. A554-RFC-PRG-060. Subcontractor: Already discussed with Mr. Lee/Daelim with Asyad Construction and both agreed and conformed to follow as per A554-RFC-PRG-060. Non-compliant Duct Insulation : It was observed that duct board insulation installed in MCC/PIB G-1121 Mechanical room and other use rooms per IFC drawing A554-E-103-HV-DWG-A30-003 with specification 24kg/cu.m x 25mm thick and K value of 0.035 W/m-deg. C (0.24 Btu-in / Sq. Ft-hr-deg. F) with thermal resistance value less than R-5 is not meeting the following Company requirements: - RT5S-5051-01 para. 3.8.1.1 unless otherwise specified, external insulation shall be a minimum of 0.024 g/cu.m (1.5 lb/cu. ft.), a minimum of 40mm (1 1/2 inich) thickness of flexible fiberglass duct wrap insulation with aluminum foil scrim kraft (FSK) facing. All supply & return ducts and plenums shall be insulated with a minimum of R-5 insulation when located in unconditional spaces and with a minimum of R-8 insulation when located outside the building. -RT5S-5051-01 para. 3.8.2.1 All ducts specified to be insulated and exposed in equipment room shall be insulated with 0.032 g/cu.m. (2.0 lb/cu.ft.) minimum of 25mm (1inch) thickness fiberglass rigid board, All supply and return ducts and plenums shall be insulated with a minimum of R-5 insulation when located in unconditioned spaces and with a minimum of R-8 insulation when located outside the building. Contractor: Contractor submitted the RFV (Request for Variance) to Sadara to close the highlighted issue regarding the duct insulation used in substation G-1120 & G-1121. Sadara responded on RFV and approved. Page 38 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 30, 2014 DUE DATE Issued corrective action to Company Target Date S/N LBE NO. PID SUBCON/ CONTRACTOR VAF / PN LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason Company comment Approved Close LBE by Company STATUS CONTRACTOR'S CORRECTIVE ACTION PLAN LBE-ASYAD-INST- 080 MR. PERVEZ ASYAD VAF 1 INST Instrumentation 16-Nov-13 19-Nov-13 30-Nov-13 25-Jan-14 Closed LBE-SEN-ELECT- 081 MR. FELOMINO SENDAN VAF 1 ELECT Electrical 17-Nov-13 20-Nov-13 01-Dec-13 30-Mar-14 Closed LBE-AMA-CIVIL-194 MR. GERALD AMA VAF 1 CIVIL Civil 17-Nov-13 20-Nov-13 01-Dec-13 20-Feb-14 23-Feb-14 Closed LBE-AMA-CIVIL-195 MR. JERRY AMA VAF CIVIL Civil 17-Nov-13 20-Nov-13 01-Dec-13 31-Dec-13 Closed LBE-AMA-CIVIL-196 MR. GERALD AMA VAF CIVIL Civil 17-Nov-13 20-Nov-13 01-Dec-13 31-Dec-13 Closed LBE-AMA-CIVIL-197 MR. GERALD AMA VAF 1 CIVIL Civil 18-Nov-13 21-Nov-13 02-Dec-13 01-Apr-14 Closed LBE-DLM-MECH- 397 MR. AMIN DAELIM PN 2 MECH Piping 18-Nov-13 21-Nov-13 02-Dec-13 10-Feb-14 Closed LBE-TCC-MECH- 398 MR. KURIAN TCC VAF 2 MECH Piping 19-Nov-13 22-Nov-13 03-Dec-13 02-Mar-14 Closed 15 LBE-DLM- MECH-399 MR. KURIAN DAELIM (Enginnering) VAF 2 MECH Structural 19-Nov-13 22-Nov-13 03-Dec-13 Open 16 LBE-DLM- MECH-400 MR. KURIAN DAELIM (Enginnering) VAF 2 MECH Structural 19-Nov-13 22-Nov-13 03-Dec-13 28-Jul-14 Closed- 22 LBE-DLM- MECH-401 MR. SAYED DAELIM (Procurement) VAF 2 MECH Material 19-Nov-13 22-Nov-13 20-Jul-14 20-Jul-14 Closed LBE-DLM- MECH-402 MR. AMIN DAELIM PN 2 MECH Piping 21-Nov-13 24-Nov-13 05-Dec-13 10-Feb-14 Closed LBE-DLM-ELECT- 082 MR. MARK DAELIM VAF 1 ELECT Electrical 21-Nov-13 24-Nov-13 05-Dec-13 26-Jan-14 Closed During surveillance inspection at Cooling Tower pump sump @ "wall-5" along GL : BD/10, concerning water stop installation does not conform to IFC drawing wherein half portion should be embedded to existing concrete. In this regards, Contractor was advised to submit Method Statement concerning this issue, prior to continue for RC wall formworks. Contractor: As per Daelim Engineering concern that no need to install water stop at stated area and it is not mentioned on IFC drawing. Depsite several verbal instruction to provide burlap on the surface of the completed paving near the cooling tower area, the Contractor still did not comply. The pavement was poured on 12 Nov. 2013 and as of this writing still there is no burlap. It was observed that the polyethylene sheet covering the top surface has been blown by the wind leaving the surface open and dry several times and the attention of the QC inspectors were called to comply with the requirements. This is violation to RT2S-3001-01 Para 9.1.4. Contractor shall provide evidence that the concrete is the same as the compressive strength of the laboratory test result. Contractor : Subcontractor (Amana) already secured burlaps and polythylene sheets for the newly casted concrete will be strictly implemented , newlt poured areas will be closely monitored. During Material Receiving inspection at AMANA Laydown area/warehouse, it was noticed that some repair materials intended for cooling tower was not properly stored on container, instead put only outside the container. In this regards, Contractor violates ITP checklist (SMIC-R-1001) "Material Handling & Storage" and manufacturer recommendation. Contractor was advised to take corrective action concerning this issue & comply with Manufacturer's instruction. Contractor : Subcontractor (Amana) alreadyremoved the materials and transferred to a close container, proper material handling & storage is done. During inspection at site of JB - installation it was observed that Contractor installed JB without proper use of rubber clamp between supports and JB bolt. This may caused galvanic corrosion. This violates NEC. Art. 342.14 Contractor/Subcontractor: installed rubber or equivalent material between JB and Supports to avoid Gavanic reaction. Contractor raised RFI and accepted with regards of this violation. During site surveillance, it was observed that Contractor pulled the cable on tray at Furnace pipe rack sub tray 1240, without inspection of tray. This is not the first time repeated violation done by Contractor. This violates Schedule Q, Para 3.7. and approved ITP. Contractor : Contractor issued NCR to sub-contractor for this violation, 17 Nov. 2013. Contractor raised RFI to close the NCR. RFI was inspected and accepted by Company. PN: 1. Daelim must ensure that only SADARA approved NDT service providers are being utilized. 2. RTFI must review the NDT Assessment reports properly to avoid mistakes like welding process and RT report number etc. 3. RTFI must interpret the WQT films 100% to avoid any overlook from weld defects. 4. Contractor Quality must follow-up closely for getting the WQT results timely. 5. Any JCC shall not be submitted without RT interpretation of SADARA NDT Level III. 6. JCC having any disagreement in RT assessment report for film or weld quality shall not be submitted without SADARA NDT Level III final review. 7. Daelim must inform all NDT companies for write down the location and size of defects on the RT & assessment reports for WQT and Production welds. Ref.: ARCC-AMY-RT-WQT-001, AYTB-FURO-WQTAR-01, TCC-NDTCCS-DAR-002 (Assessment reports) Subcontractor: Action has been taken accordingly. During routine site visit at Daelim's Laydown yard, it was noticed that some of the cables stored do not have an approved end cap at cable ends which is a violation as per G7D-0404-00, Section 7.3. Contractor : Scontractor will provide the approved end caps and Company will be notified for the action will be taken. During surveillance above the 2nd lyre of the EW pipe rack of the east side from column 10 onwards were found in inclined position ladder fixed as it is fauling with the beams. Contractor: TQ raised for approval from Daelim Engineering department. During surveillance, pipe rack in between liquid furnace and G1120 MCE/PIB were found with structure have vertical blogging positioning diagonally with ladder fixed to it without toe clearanc. The clearance there found is 40mmm and 11mm but the required is 225mm. It is a violation as per ref: RT2G-5515-01 drawing. Subcontractor: Noted. Action shall be taken. Engineering issue. Engineering issue. This item already been solved. The orientation of vertical brace has been rotated 180 degree which means the clearance of ladder has been retained. During material receiving jnspection, it was found that CS welded pipe 42" x 12.70 (XS) ASTM A672 CL70-CI-22 with H.No.: LK669412 is not comply as per the purchase order PO-100532042-PO2-005-A01. The requirement as per PO was NACE MR-0103 pipe BE ASTM 672-CL-20 but the actual material received and the MTC was not compliance with NACE-MR-0103. This violates Sched. "Q" Para. 1.3 which states that "All materials and equipment meet the requirement of the Contract and the applicable purchase order. Verified. During surveillance inspection at substation G1121, it has been observed that some steel door frames are installled without issuing first "RFI" request for inspection, and some are grouted already. This is in violation to Schedule "Q" attachment IV section 1 para. 1.1.3 and also as per G2S-4300-01 Section 2.4 Para. 2.4.1 "Grout shall have a minimum strength of 3750psi." In this regards, Contractor was advised to take corrective action and remedial action concerning this matter, And also Contractor are required to submit proof of compressive testing that the grout being used for the steel door frames are comply with our specification requirements. Subcontractor: Subcontractor shall submit RFI for final inspection after installation of all accessories regarding grouting. Report on crushing is attached. PN: Because of raining and start of cold seasons, Daelim Quality must ensure that: 1 - Piping materials are properly preserved and stored in drainable positions. 2 - SS material are properly covered by water repllent sheet. 3 - End covers are in place and proper space is maintained from the ground. 4 - Welding consumables are stored in controlled temperature and humidity. 5 - Pre-heating and metal surface temperatures are monitored closely to avoid welding on moistened base metals. 6 - Relevant inspectors and welders are using a suitable temperature measuring sticks or pyrometers. Contractor: Noted and action will be taken. NCR #41 is related to this issue and now closed. During inspection of flange face of P4 2131 Nozzle with below type connection (G vent) on the cold box north side found bented and the top of the south side of the cold box nozzle were connected to the piping with no proper piping support (temporary) as it can cause an extra load on these nozzle than the specified tolerance limit by the manufacturer. It is a violation as per A554-E-103-QA-GEN-PRO-034 para 8.1.3 & A554-E-103-QA-GEN-PRO-035 para 8.2.1 Subcontractor: Noted. Action shall be taken. All piping connection has been complied Page 39 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 30, 2014 DUE DATE Issued corrective action to Company Target Date S/N LBE NO. PID SUBCON/ CONTRACTOR VAF / PN LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason Company comment Approved Close LBE by Company STATUS CONTRACTOR'S CORRECTIVE ACTION PLAN LBE-AMA-ELECT- 083 MR. FELOMINO AMA PN 1 ELECT Electrical 21-Nov-13 24-Nov-13 05-Dec-13 28-Jun-14 Closed 24 LBE-DLM- INST-084 MR. SHABIRUL DAELIM (Procurement) PN 1 INST Instrumentation 23-Nov-13 26-Nov-13 07-Dec-13 16-Jul-14 Closed 16 LBE-DLM- MECH-403 MR. SAYED DAELIM (Procurement) VAF 2 MECH Material 24-Nov-13 27-Nov-13 14-Jul-14 Open LBE-AMA-MECH- 404 MR. GLENN AMA VAF MECH Hvac 24-Nov-13 27-Nov-13 08-Dec-13 18-Dec-13 Closed LBE-AMA-MECH- 405 MR. GLENN AMA VAF MECH Hvac 25-Nov-13 28-Nov-13 09-Dec-13 18-Dec-13 Closed 17 LBE-DLM- ELECT-085 MR. FELOMINO DAELIM (Mat. Dept & Procurement) VAF 1 ELECT Material (Procurement) 26-Nov-13 29-Nov-13 10-Dec-13 Open LBE-DLM-ELECT- 086 MR. FELOMINO DAELIM VAF 1 ELECT Electrical 26-Nov-13 29-Nov-13 10-Dec-13 23-Feb-14 Closed LBE-DLM-MECH- 406 MR. HARIKUMAR DAELIM VAF 2 MECH Mechanical (Equipment) 28-Nov-13 01-Dec-13 23-Mar-14 Closed LBE-AMA-CIVIL-198 MR. JERRY AMA VAF CIVIL Civil 28-Nov-13 01-Dec-13 12-Dec-13 16-Dec-13 Closed LBE-AMA-CIVIL-199 MR. GERALD AMA PN CIVIL Civil 28-Nov-13 01-Dec-13 12-Dec-13 31-Dec-13 Closed 6 LBE-AMA-MECH- 407 MR. GLENN AMA PN 2 MECH Hvac 02-Dec-13 05-Dec-13 12-Feb-14 22-Apr-14 Closed LBE-DLM-MECH- 408 MR. AMIN DAELIM PN 2 MECH Quality Management 03-Dec-13 06-Dec-13 17-Dec-13 10-Feb-14 Closed 19 LBE-DLM- MECH-409 MR. HARIKUMAR DAELIM (Enginnering) VAF 2 MECH Mechanical (Equipment) 04-Dec-13 07-Dec-13 17-May-14 22-Jul-14 Closed LBE-SEN-ELECT- 087 MR. FELOMINO SENDAN PN 1 ELECT Electrical 05-Dec-13 08-Dec-13 19-Dec-13 23-Feb-14 Closed PN: During site surveillance at G-1120 & G-1121 substations, it was observed that the metal door frame of substation building don't have provision for grounding connection. This violates as per G7C-0104-00, section 6.12.2. Contractor : As per construction coordination, cable grounding will be from the top and exposed for metal door frame. According to 67C-0114-16 note 9, that the PVC along the wall to a substation ground bos is Acceptable instead of the cable through the concrete foundation. Observed that Mechanical Inspector is not available at site Daelim and Subcontractor shall be fully responsible for the performance and control of the on-going activities and work process violation of Schedule "Q" attachment 3 and ITP-A554-E-103-QA-GEN-PLAN-022. According to the schedule Daelim will provide more inspectors as soon as possible It was noticed that the reinforcing bars of the pedestal near cold structure area was bent to provide access to equipment of the other subcontrcator working on the same area. Contractor/Subcontractor to provide protection to all exposed reinforcing bars of all pedestals to avoid recurrence of the incident. Also to provide corrective action on the Ben reinforcing bars of the pedestal. This is a violation to the minimum bending readiness required by AC1318 and 315. Subcontractor: Rebars were rebend and returned to its plumbness. Damaged coating has been touched-up. PN: During Surveillance inspection & monitoring activities at cooling tower sturcture, Sump pump area & basin have been observed that after raining in few days, it was found out the presence of the water. Contractor advised to make dewatering the said structure in oder to continue the repair work especially the Internal portion of the RC wall. Subcontractor: Amana has already removed the water from sump pump area and repairing work is on-going. Supply air elevation higher than requirement. It was observed in MCC/PIB G-1120 (Typical to G-1121) that 2 nos. supply air outlets are located around 7.2m above floor in Battery room. This violates RT52- 500-01 section 6.11.4.3 Supply air 150mm above floor or lower and exhausr at ceiling or at high point of any flammable gas pocket. Contractor: As per the comments, during start of any activities or work for HVAC, Construction MFC Daelim they have submitted shop drawing to Sadara for review or approval. This is the one of Sadara comments to provide at least one air device above and that was complied by Daelim MFC Engineering as the revised drawing. During material receiving inspection of RFI # CCHINDS-EL-024 at Daelim Laydwon area, it was observed that the 2" Hot dip galvanized PVC coated conduit and 2" X 3/4" reducer fittings has no labeled and not listed. This violates as per G7C-0311-01, Para 1.2. Contractor: Daelim will provide certificate from Vendor for proof. Contractor will not use anymore these materials as per construction and it was already quarantined at the laydown yard. During Inspection at East West main piperack, it was observed that the cable tray was installed using temporary support and cable pulling activities were on-going. This violates G7C-0321-01, Para. 4.1. Construction: Subcontractor's Construction team was aware of this issue, as Daelim Construction team avised them to provide temporary support due to structural issues. Company to be notified during the weekly quality meeting as soon as Contractor receives the schedule from structural to provide structures at the E-W main pipe rack. PN: During site surveillance, it was observed that the Gear box of MOV 103-EBV 116417 has been damaged during lifting time. Contractor to report Vendor or replace part of the damage gear box of MOV-30. Contractor : Contractor will issue OSID to notify the Vendor regarding the damage neither inoformation nor notification will be given by Contractor to Company for the action. During material receiving inspection of Valves, it has been noticed that failure of paint bwtween prime coat and top coat. P.O. No. U31-002-A02- 42, Vendor: NEWMANS, RFI No. MFC-DLM-NEWMAN-PIP-001. No of Valve approximately 54 nos. This violates Sadara Specification G16S-0202- 04 which mandates "each coat shall be of the correct colour, free of defects such as but not limited to pinholes, blisters, dry spray, detrimental runs and sags, excessive or inadequate film built, improper recoat times, foriegn inclussion and adhesion between Coat and to the substrate shall equal the manufacturer's limit. Contractor shall verify occured discrepancy and propose Corrective action. Contractor: Daelim Material Dept. already completed the repair works at the painting shop. Incorrect duct support- It is observed in MCC/PIB G-1120 & G-1121 that angle bars are used to support ducts in mechanical room. This violates RT5S-5052-01, Para. 4.41.1. In Equipment room use 42mm (1 5/8") Unistrut with M12 (1/2") threaded rod. Hanger spacing not to exceed 1.5m. Purpose of this hanger type is to allow other disciplines a place to hanger attachment. (Ypical to G-1120). Contractor: Daelim designed and installed the type 2 duct hanger supporting arrangement as per "RT5G-5051-10 Typical duct hanger (Refer to attachment #1). Specification RT5S-5051-01, Para. 4.14.1 describes "Purpose of Unitrust hanger type is to allow other disciplines a place for hanger attachment. In general HVAC practice, the ducting needs in individual hangers support. Therefore, Type 2 hangers arrangement is installed to support the individual application like ducting and not to be paired with any other disciplines. Hence, the Unistrut type hanger supports are not envisaged for equipment room. PN: During surveillance at all area of main piperack for installation of cable tray expansion splice plate, it was observed that the length of splicing bolt was insufficient length tha actual length is 16mm. Some of the bolts are loosen and if the bolts are fully tighened the splicing plate were fixed permanently to the side rail of cable tray. Contractor: Splicing Bolt used for splicing plate was changed from 16mm to 19mm from the day the Contractor received the comment. PN: It was observed in MCC/PIB G-1120 inspection for Electric Duct Heater installtion that no access door provided and airflow sensor not installed. This violates RT5S-5051-01 Para. 4.9, All ductwork enclosed equipment to have access door installed on up-stream and down-stream with respect to air flow and section 1.5.6.1.4 Airflow switch sensor provided by manufacturer to be installed. Contractor: Daelim already informed to Amana regarding the issue raised by Company and Subcontractor shall provide access door for every duct work enclosed equipment that allowing maintenance work. PN: Found that Daelim Piping and Welding inspectors duputed at offsite fabrication shops (AYTB & PCMC) are not reaching there in time. Shift starts at 06:00 AM but Daelim inspectors are reaching at 8:00 AM. This schedule is entirely unacceptable and needs immediate correction action. Cold season has been started and mornig activities are much important now than hot season. During High rejection rate full time close monitoring is very important. Contractor: Contractor inspectors are going to Daelim office the morning time for the purpose of completing the documents of the daily activities. However, Contractor Inspectors will try to reach and join with subcontractors QC in the off-site as early as possible. Dimentional and Elevation discrepancy observed at Debutinizer area on E- 1920 A and E 1920. Grinder Beams are conflicting with Equipment Nozzle and limited space for piping installation. Daelim Engineering team to re- evaluate the connection and implement the appropriatee corrective action in accordance with Engineering approval by Company E-1920AB-103-9002- 01 - 209. Contractor: Company inquiry already been solved. The clashed girder has been cut 25mm at site to install the pipe in accordance with "E- 1920AB-103-9002-01 - 209". The structural calculation considering 25mm cutting on girder has been also done, whos result is no problem. Page 40 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 30, 2014 DUE DATE Issued corrective action to Company Target Date S/N LBE NO. PID SUBCON/ CONTRACTOR VAF / PN LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason Company comment Approved Close LBE by Company STATUS CONTRACTOR'S CORRECTIVE ACTION PLAN LBE-ARCC-MECH- 410 MR. HARIKUMAR ARCC VAF 2 MECH Piping 07-Dec-13 10-Dec-13 26-Feb-14 28-Mar-14 Closed LBE-TCC-MECH- 411 MR. NASSAR TCC VAF 2 MECH Coating/ Painting 07-Dec-13 10-Dec-13 21-Dec-13 Closed LBE-PCMC-MECH- 412 MR. NASSAR PCMC VAF 2 MECH Coating/ Painting 07-Dec-13 10-Dec-13 21-Dec-13 16-Feb-14 Closed LBE-AMA-CIVIL-200 MR. JERRY AMA VAF 1 CIVIL Civil 09-Dec-13 12-Dec-13 23-Dec-13 08-Apr-14 Closed LBE-PCMC-MECH- 413 MR. NASSAR PCMC VAF 2 MECH Preservation 09-Dec-13 12-Dec-13 23-Dec-13 16-Feb-14 Closed 8 LBE-DLM- MECH-417 MR. KURIAN DAELIM (Enginnering) VAF 2 MECH Mechanical (Equipment) 09-Dec-13 12-Dec-13 17-May-14 23-Jul-14 Closed LBE-GLOBAL- MECH-414 MR. NASSAR GLOBAL VAF 2 MECH Coating/ Painting 10-Dec-13 13-Dec-13 24-Dec-13 16-Feb-14 Closed 18 LBE-DLM- MECH-418 MR. KURIAN DAELIM (Enginnering) VAF 2 MECH Mechanical (Equipment) 10-Dec-13 13-Dec-13 17-May-14 Open LBE-SEN-ELECT- 088 MR. FELOMINO SENDAN VAF 1 ELECT Electrical 10-Dec-13 13-Dec-13 24-Dec-13 04-Mar-14 Closed LBE-DLM-ELECT- 089 MR. FELOMINO DAELIM VAF 1 ELECT Electrical 10-Dec-13 13-Dec-13 24-Dec-13 30-Mar-14 Closed LBE-AMA-MECH- 415 MR. GLENN DAELIM (Enginnering) PN 2 MECH Hvac 11-Dec-13 14-Dec-13 25-Dec-13 Engineering response id for exhaust fan only, bleed fan in equipment room is not responded. 10-May-14 Closed LBE-AMA-MECH- 416 MR. GLENN AMA PN 2 MECH Hvac 11-Dec-13 14-Dec-13 25-Dec-13 12-Feb-14 Closed LBE-SEN-MECH- 419 MR. KURIAN SENDAN VAF 2 MECH Mechanical 11-Dec-13 14-Dec-13 25-Dec-13 07-Mar-14 Closed LBE-ASYAD-INST- 090 MR. PERVEZ ASYAD VAF 1 INST Instrumentation 11-Dec-13 14-Dec-13 01-Jan-14 04-May-14 Closed During routine inspection at PCMC blasting & coating facility, it has observed that dust inclusions and dry spray due to applying the paint during high wind. Subcontractor: Action was taken and all area where over spry was rectified and inspected and accepted through RFI PCMC-M-0269 With reference to RFI # MCF-DLM-AMA-CI-5428 located at Ground Flare Area for gravel 1 1/2 inch, the Contractor shall provide test results that the materials comply with the requirements of RT2S-2200-01 Para. 2.7. Sadara QG shall be involved during taking of samples of this materials. Subcontractor: Regarding Grand Flare area gravel, Amana has already submitted RFI for sample collection and Test result already submitted which sill send back to supplier to replace with new material. During surveillance, it was observed during transportation and handling the pipes and spools, some pipes & spools have been damaged due to pipe poor transportation and handling. Those pipes and spools found at MFC site (E/W pipe rack) Tank Farm # V-500B. Subcontractor: Noted. PCMC advice the spool release team for the proper caring of the spools and following proper preservation. ARCC has ignored to implement Welding parameter as per WPS-1400-WMS-PSA-005A for line class HpssH-1, the provision version was followed until oct. 26 and as per production data sheet. 8 joints were welded at site after 2nd revision of subjected WPS (G4N-HM-001. G5N-HM-001, G6H-HM-0001 and G7N-HM-001). which is showing significant variance to addition of extra requirement for maintenance intermediate pout heat and sok time. Violation of project specification RT8S-G500-1 and WPS-1400- WMS-PSA-005A. Daelim Welding Engineering Team shall investigate and propose corrective action in accordance with SME approval. Subcontractor: A change of pre-heat maintenance is a non-essential variable as per OW-406.2. Therefore, it does not affect the mechanical properties of the weldment. During routine inspection at TCC-01 blasting & coating facility, it has observed that dust inclusions and pinholes due to applying the paint during blasting progress. Subcontractor: Noted. Action shall be taken. PN: Air intake elevation not meeting erquirement. During surveillance in MCC/PIB G-1121 (typical to G- 1120), it was observed that bottom of outside air intake is 7m above grade. (0.5m short to requirement). This violates RT52-5000-01, Para. 6.7.4 The air intake of a pressurized building shall be located in a non-classified area 4.5m minimum above any classified area and 7.5m above grade. Contractor: As per Proactive Notification which is clearly mentioned in SADARA Standard, RT5Z- 5000-01, additional section 6.3.1.3 "Fresh Air intakes shall be located a minimum of 2.4 m (7Ft- 10in) above grade, with sand trap louver, birs screen, manual volume damper and internal dust filter. An intake stack may be necessary but not required to achieve intake minimum height above grade. No need to provide RFC again to close the LBE M-416 since this is already mentioned in this section of Sadara Standard. With respect to the PN regarding the Height of outside air intake, Contractor's Construction and QC teams had verified the issue with below finidngs: Building on the top of concrete = EL. 24400 (high point) GR.FL.=+14700(T.O.C), Size of building beam = 800mm Height of opening: 1500, Weight of opening: 1800 BOL EL: 21700 Intake sand trap louver; Therefore, 24400-14700=9700mm (Height of building), 9700-800=8900mm, 8900-1500=7400mm. Which means the elevations are 7000mm only, we still have clearance from the beam to upper opening. In this case, we cannot reach 7500mm as per required standard grabe because the building is less in height. Reference IFC drawings: *A554-E-G1121-DWG-A02-206 *A554-E-G1121-DWG-A03-243 *A554-E-103-HV-DWG-A30-032 During regular visit to SENDAN Fabrication shop found the holiday oven is not maintaining the required Temperature of 120C and the Welders were found not using quiver. This is violation as per RT-8S-6500- 03, Para. 2 (Storage & Reconditioning), (Note 2) A554-E-103-QA-GEN-PRO-050, Para. 9 Recalibration/Replacement of holding oven and quiver is required as per the Sadara specification. Subcontractor: The holding oven maintaining the temperature at 120c as well as every welders using quiver. During inspection of cable tray, it was observed that Contractor installed splice plate on supports +- 300mm. This violates G7C-0324-03. According to Standard, Contractor shall install heavy duty splice plate +-300 on support. Contractor: Subcontractor's and Daelim Construction team were informed about this violation and advised to rectify the same. After receiving the comments from Company, immediately informed concerned parties to follow typical installation details, maximazing the distance of the splice plate and support to 600mm. During Surveillance at operator building G-1122 for lightning conduit installation, it was observed that the flexible conduit was installed directly to junction box plate cover. This violates NEC article 300.15 (A). Contractor: Subcontractor's QC department and Daelim's Construction team were already informed regarding the violation of the NEC standard pertaining to the installation of the flexible conduit directly to the JB plate cover and advised to rectify the same. During Inspection at Gas Furnace area F-1160 for cabnle tray installation, ir was observed that vertical outside ao elbow cable tray fitting is not installed. This violates G7C 0321-01, Para. 6.1.2. Contractor: This issue was already addressed to Daelim Engineering Team for review and necessary action. PN: Missing motorized damper. During verification of IFC drawing for MCC/PIB G-1121 (Typical to G- 1120) it was observed that backdraft damages are provided in battery room exhaust outlet and bleed or outlet. This violates RT52-50001-01 Para. 8.2.8 Motorized dampers that closed when the system is not operating shall be provided for outdoor air intakes and exhaust openings to eliminate infiltration. Use of gravity damper is not recommended due to their short life and reliability. Contractor: Mottorized damper is not required in battery EF outlet, since the fan is continuously running whole year round. In case the duty fails, the back-up fan will operate. Thus, infiltration is imposible. In the event of system shutdown, it will only occur in very short span of time. During emergency cases only. So BDD can serve its purpose by eliminating ingress of outside air. Surveillance show P-2320-B (Ethylene product pump) with damaged 0.75" pipe (Vent connection) connected to the discharge nozzle flange. The pump is from vendor Flowserve, the damage may have happened during installation at site as there was no damage physically during material receiving inspection. This is violation as per A554-E-103-QM-GEN-PRO- 034, Para. 8.1.3 & A554-E-103-QA-GEN-PRO-035, Para. 8.2.1.8.1.11 & 8.1.1. Contractor: P2320 was already sent to Supplier's repair shop. After repair of damaged nozzle, Contractor will inspect and erect P-2320-B. -> P-2320 was repaired at vendor shop after inspection. It is reinstalled at site During routine inspection at Global Suhaimi, blasting/coating facility has been noticed that pinholes defect on the top coat surface. Applied paint code is G16S-0203-03 (P2-2). The number of valves are 8 24" Dia. Subcontractor: All the items having the pin holes are already repaired and accepted by QC of Daelim and SADARA. Surveillance shown the equipment P42131 (Cold box) the nozzle "GVENTI" found bended due to mishandling or may be during installation at site, this is a violation as per A554-E-103-QA-GEN-PRO-034, Para. 8.1.3. and A554- E-103-QA-GEN-PRO-035, Para. 8.2.1. & 8.1.11.8.1.1. Contractor: Contractor cannot recognize this issue for Cold Box (PU 2131). Please expalin or provide the picture for bended nozzle to us. Page 41 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 30, 2014 DUE DATE Issued corrective action to Company Target Date S/N LBE NO. PID SUBCON/ CONTRACTOR VAF / PN LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason Company comment Approved Close LBE by Company STATUS CONTRACTOR'S CORRECTIVE ACTION PLAN LBE-AMA-CIVIL-201 MR. JERRY AMA VAF 1 CIVIL Civil 14-Dec-13 17-Dec-13 28-Dec-13 08-Apr-14 Closed LBE-AMA-CIVIL-202 MR. JERRY AMA VAF CIVIL Civil 14-Dec-13 17-Dec-13 28-Dec-13 31-Dec-13 Closed LBE-AMA-CIVIL-203 MR. JERRY AMA VAF CIVIL Civil 15-Dec-13 18-Dec-13 29-Dec-13 31-Dec-13 Closed LBE-AMA-CIVIL-204 MR. JERRY AMA VAF 1 CIVIL Civil 15-Dec-13 18-Dec-13 29-Dec-13 02-Feb-14 Closed 20 LBE-AMA- CIVIL-205 MR. JERRY AMA VAF 1 CIVIL Civil 16-Dec-13 19-Dec-13 11-Feb-14 19-Jul-14 16-Jul-14 Closed- LBE-DLM-MECH- 420 MR. KURIAN DAELIM (Construction) PN 2 MECH Mechanical (Equipment) 17-Dec-13 20-Dec-13 31-Dec-13 03-Jun-14 Closed LBE-GLOBAL- MECH-421 MR. NASSAR GLOBAL VAF 3 MECH Coating/ Painting 17-Dec-13 20-Dec-13 31-Dec-13 12-Apr-14 Closed LBE-GLOBAL- MECH-422 MR. NASSAR GLOBAL VAF 3 MECH Coating/ Painting 17-Dec-13 20-Dec-13 25-Feb-14 12-Apr-14 Closed LBE-KAF-MECH- 423 MR. NASSAR KAEFER VAF 3 MECH Fireproofing 17-Dec-13 20-Dec-13 12-Apr-14 12-Apr-14 Closed LBE-AMA-CIVIL-206 MR. JERRY AMA VAF 1 CIVIL Civil 18-Dec-13 21-Dec-13 01-Jan-14 07-Jan-14 Closed LBE-DLM-CIVIL-207 MR. JERRY DAELIM VAF 1 CIVIL Civil 19-Dec-13 22-Dec-13 22-Apr-14 22-Apr-14 Closed LBE-DLM-ELECT- 091 MR. FELOMINO DAELIM VAF 1 ELECT Electrical 19-Dec-13 22-Dec-13 02-Jan-14 30-Mar-14 Closed LBE-GLOBAL- MECH-424 MR. NASSAR GLOBAL VAF 3 MECH Quality Management 19-Dec-13 22-Dec-13 02-Jan-14 23-Feb-14 Closed 19 LBE-AMA- CIVIL-208 MR. JERRY AMA VAF 1 CIVIL Civil 20-Dec-13 23-Dec-13 19-Jul-14 Open LBE-DLM-MECH- 425 MR. AMIN DAELIM PN 3 MECH Quality Records 21-Dec-13 24-Dec-13 04-Jan-14 10-Feb-14 Closed During normal inspection at Global Sujami workshop, it has been noted no subcontrcator coating inspector is assigned at the time of inspection. Inspection has been verified in presence of Daelim inspector. Logbook entry will be escalated to NCR when lack of action by Daelim to provide the required project ITP. Subcontractor: QC Inspector is already informed to be present at site and if repeated, he will be removed from approval. At Global Suhaimi workshop, it was noticed more than 128 gate valves 2" dia already coated with wrong paint code (G16S-0203-03) Silicon Aluminum Finish and as per tag (P-1) which is installed the paint code required in G16S-0201-11 (Epoxy Phepolic). This is violation against coating procedure for field application on valves *CM-2029). Subcontractor: Painted and changed the paint code system as per Daelim advice through email on Dec. 24, 2013. It has been noticed that existing coating (HB surface tolerant epoxy of uninsulated parts and Equipment tag has been damaged due to overspray of zinc phosphate (Primer color) and Fireproofing intumescent coating. The cause of damages was poor protection for un-insulated parts prior to coating application. Contractor: Item Closed as per NCR-KFR-MECH-001 Balst resistance doors delievered shall be inspected during installation as per Company comments in Contractor transmittal nos. IK-MFC-T-CJ-DJ-CM-0529 and Company reply IK-MFC-T-DJ-CJ-QM-0403 dated 22 Dec. 2012. Subcontractor: Delivered Blast Door has been Installed and Inspected (See Attached Photos) The repaired concrete surface of the Cooling Tower External Walls have different color compared to the existing concrete surfaces. The color of the concrete surfaces around the external walls shall be repaired as required by RT2S-3001-01, Section 11, Para 11.1.1 including color of the repaired materials. Subcontractor: Advised to Construction to discuss with Daelim Construction and finalize which material to be used for external well. Waiting from Daelim to get approval to start painting works. PN: EQ106 (Primary demethanizer feed/secondary demethanizer bottom exchanger) is found with no painting after welding of sole plate at left plate at sole plate with base plate of the saddle support. Subcontractor: As per PN 420 already took action regarding the sole plate welding. It was noticed during monitoring activities that the reinforcing bars of Open Ditch wall sout-east of substation G-1120 has been exposed and there is no more bar cover. There are about 11 nos. where cover did not comply with specification. This is a violation of RT2S-3001-01, Para. 6.1.10. Subcontractor: Advised to Construction to make shop drawing to adjust rebar where they have spacing problem. Daelim approved the shop drawing. The curing of foundation at Flare area is not being done properly. The contractor provided burlap and poleyethylene sheets at the sides of the foundation but left the pedestal area without burlap and poleyethylene sheet. The area inside the reinforcing bars of pedestal is wider and larger than the side of foundation. Subcontractor: Subcontractor already placed the burlap and polyethylene sheet on pedestal area and curing has been placed. The alignment of open ditch, east of substation G-1120, to the sump pit southeast of substation G-1120 is not straight. Please verify which of the two structures is misaligned (sum0644 or ditch) prior to pour concrete wall of the ditch submit shop drawing for approval. Subcontrctor: Subcontractor Already Make the shop drawing and Approved by Daelim Engineering team. Work has been Inspected and approved. IFC Revised. No subcontractor coating inspector is assigned at the time of inspection. As per project ITP, inspection sctivities for subcontractor inspector is Hol point. Daelim should raised NCR and take positive action with Subcontractors to maintain the quality prior to, during and after activities without any defects. Subcontractor: The QC inspector has been changed. The Conrractor started to erect equipment/structural support without submitting RFI at Air Cooler Structures area and Fresh Ethane Structure area. Some deficiencies noted on the structures are the following: No chamfer on exposed corners, chamfers were not uniformly trimmed, blowholes and small honeycombs were not repaired, beams have irregular shapes, some color of the repaired structures were not uniform, the top portion of the beams were not properly cleaned prior to repair. Contractor did not submit RFI to cover Item 3.6 of ITP SMITP-Q-001-02. PN: It is observed that Daelim RFI's submission process as per Sadara RFI guideline QA-F-001-R1, transmittal # IK-MFC-T-CJ-DJ-CM-1899. Also, the Rfis shall be filled completely and properly with all required attachments as per latest approved ITPs. Contractor: All QC inspectors are informed. It was noticed that the reinforcimng bars at the sumps area of the cooling tower, has been submerged under water for a long time (near the screen) and rust has been developing on the open coats of the re- bars. The water on the surface shall be removed and rebars shall be inspected prior to apply repair materials. Subcontractor: For RFI MFC-DLM-AMA-CI-5504 & 5505, Amana QC will secure the latest drawings of each area of inspection and other structures adjacent to it. QC will make sure that IFC drawing is followed before calling for PID inspection. For RFI MFC-DLM-AMA-CI-5542, Missing rebars were re-installed. All reinforcements shown in IFC drawings were installed correctly. For RFI MFC-DLM-AMA-CI-5530C, Daelim issued revised IFC drawing to correct the slope of the paving. Slope of the paving was rectified as per revised IFC drawing. All area are re-inspected and approved for concrete pouring. The Contractor is not submitting RFI for final acceptance of concrete structure as per Daelim ITP # SMITP-Q-001-02 Item 3.6 which is "H" for the Contractor. Some of the structures have surface deficiencies but the equipment are already installed. This is also a violation of Schedule Q Sec. 3.7 Subcontractor: Subcontractor has stated in the RFI for final Acceptance of Concrete structure some structure has been checked and accepted. During inspection at MCC room substation G-1121 for cable tray installation, it was observed that the vertical spacing os cable tray is not maintained the cable spacing requirement the actual space was 150mm from top to bottom of the tray. This violates G7C-U321-01, Para. 5.2 & G7C-0302-00, Para. 3.7.1. Contractor: The issue has already been addressed to Daelim Engineering team for review and necessary action since the 150mm spacing was reflected in the design drawing. Page 42 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 30, 2014 DUE DATE Issued corrective action to Company Target Date S/N LBE NO. PID SUBCON/ CONTRACTOR VAF / PN LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason Company comment Approved Close LBE by Company STATUS CONTRACTOR'S CORRECTIVE ACTION PLAN LBE-DLM-MECH- 426 MR. AMIN DAELIM PN 3 MECH Piping 21-Dec-13 24-Dec-13 04-Jan-14 10-Feb-14 Closed LBE-DLM-MECH- 427 MR. AMIN DAELIM PN 3 MECH Mechanical 22-Dec-13 25-Dec-13 05-Jan-14 10-Feb-14 Closed LBE-AMA-MECH- 428 MR. GLENN AMA VAF 3 MECH Hvac 23-Dec-13 26-Dec-13 06-Jan-14 LBE will be closed when replacement arrive on site. 17-Mar-14 Closed LBE-TCC-MECH- 429 MR. NASSAR TCC VAF 3 MECH Coating/ Painting 23-Dec-13 26-Dec-13 06-Jan-14 23-Feb-14 Closed LBE-AMA-CIVIL-209 MR. JERRY AMA VAF 1 CIVIL Civil 23-Dec-13 26-Dec-13 29-Mar-14 28-Apr-14 Closed LBE-DLM-ELECT- 092 MR. FELOMINO DAELIM PN 1 ELECT Electrical 24-Dec-13 27-Dec-13 07-Jan-14 12-Feb-14 Closed LBE-DLM-ELECT- 093 MR. FELOMINO DAELIM PN 1 ELECT Material 24-Dec-13 27-Dec-13 01-Jan-14 04-Mar-14 Closed LBE-AMA-CIVIL-210 MR. JERRY AMA VAF 2 CIVIL Civil 24-Dec-13 27-Dec-13 07-Jan-14 01-Apr-14 Closed LBE-GLOBAL- MECH-430 MR. NASSAR GLOBAL VAF 3 MECH Quality Management 25-Dec-13 28-Dec-13 08-Jan-14 23-Feb-14 Closed LBE-TCC-MECH- 431 MR. NASSAR TCC VAF 3 MECH Preservation 25-Dec-13 28-Dec-13 08-Jan-14 17-Feb-14 Closed LBE-AMA-CIVIL-211 MR. JERRY AMA VAF 2 CIVIL Civil 25-Dec-13 28-Dec-13 08-Jan-14 20-Jan-14 Closed LBE-TCC-MECH- 432 MR. NASSAR TCC VAF 3 MECH Coating/ Painting 26-Dec-13 29-Dec-13 09-Jan-14 16-Feb-14 Closed LBE-KCC-MECH- 433 MR. GLENN KCC VAF 3 MECH Quality Management 26-Dec-13 29-Dec-13 09-Jan-14 QC Inspector Rafique has been seen only once at site 24-Feb-14 Closed LBE-DLM-MECH- 434 MR. HARIKUMAR DAELIM VAF 3 MECH Mechanical (Equipment) 26-Dec-13 29-Dec-13 03-Apr-14 02-Apr-14 Closed LBE-DLM-MECH- 435 MR. HARIKUMAR DAELIM VAF 3 MECH Structural 26-Dec-13 29-Dec-13 23-Mar-14 Closed PN: It is observed that daily RT requested weld joints must be cleaned from outside and inside especially PWHT joints to avoid RT re-shoots. NDT coordinator or welding inspector shall ensure that welder and joint identification is present for RT purpose. RT crew must write down the date of RT on each weld joint to be RT'd. Repair joint should be marked and informed immediately to contractor aqnd Company quality team. Daily based RT result coming from TRP shall be shared and communicated with sub-contractor, Contractor and Company inspectors. Repair tracing/amrking shall be done by approved welding inspector. Contractor: Noted, action has been taken RAWABI and AMSYCO has been instructed to write date on joint. PN: Welder's rejection rate must be monitored closely on daily basis by Daelim Quality team. Questionable skilled and High rejection rate welders shall be revoked. After revoked, they may be allowed to resume welding if they received a minimum 8 hours training in the revoked welding process and take and pass a WQT as specified in the governing codes, statndards or regulations. This training must be documented and a copy of the documentation shall be submitted to Company. Ref. RT8S-6500- 001, Para. 2.5, 2.5.1, 2.5.2. Contractor: Agree with proactive notification, Daelim team is monitoring repair rate daily basis. Contractor revoked few welders and few stopped and sent for training. Observed that Contractor proceeded with the installation of rejected fire and smoke dampers FSD model manufactured by SAFID is not UL listed and labeled. This violates RT5S-5051-01/3.11.4 CFSD's shall be multiple blade type with galvanized steel blacks and frame labelled in accordance with UL standards 555 & 5555 for 1 1/2 hour rating. RT52-5000-01/6.2.4 Provide CFSD in duct penetrations where the exterior or enterior walls are 2 hours fire rated. Schedule "Q" Para. 7.3.2 Contractor shall establish and maintain control to restrict further processing or installation of nonconforming or defective items. Contractor: Noted. The rejected temporary fire/damper shall be replaced by Contractor/subcontractor as soon as the new materials arrive. It has been observed at TCC-2 workshop, some spools have been rusted. TCC handled and shifted the spools to site for installation. This is for information, root cause analysis and corrective action. Subcontractor: IK-MFC-T-DJ-CJ-QM-1854, DAELIM NCR closed. RFI No. MFC-DLM-AMA-CI-5643/5645. During the FDT of bottom of foundation of FD-Fan Foundation and F# Type foundation (North of Liquid Furnace F-1240 & F-1250) the Technician (Osaimi) perform the test without calibrating the nuclear gauge against the standard block since it was already calibrated. After the FDT, the backscatter serial number was checked and found to be different from the serial no. of the nuclear gausge (38778 for nuclear gauge and 32720 for the bacscatter) Also, the serial number of the bacskcatter is not clear. This is a violation of ASTM-D-6938 regarding calibration as explained in Annex A1 of this standard. The test performed is not acceptable and a warning shall be given to Technician and Laboratory. Contractor: Third party laboratory was notified of the said issue and they have replied as stated in the attached letter. Contractor and subcontractors shall monitor and follow-up the corrective & preventive action herein stated by the third party laboratory. Contractor and Subcontractor QC inspectors shall check reference blocks prior to use. It has been noticed that during blasting activities, TCC has not installed remote control shut-off "dead- man" on the blasting hose. This is violation against work procedure and safety requirements during blasting activities. Subcontractor: IK-MFC-T-DJ-CJ-QM-1856, DAELIM NCR-046 closed. PN: During surveillance at substation 1120, it was observed that the MCC panel and VFD panel were started installation without Material Receiving inspection. This violates as per schedule "Q", Para. 3.2. Contractor: Subcontractor and Daelim Construction team were advised not to fix/anchor the panel until material receiving inspection is done. The said panelws inside SS G-1120 were set-up for positioning and arrangment pusposes to protect and preserve the panels from workers working and coming in and out of the substation. There are wood embedment at the top portion of the wall of Cooling Tower located at North-East portion of Sump. The wood shall be removed and inspected prior to conduct any repair. These woods were used as spacers. Subcontractor: Amana Construction has started chipping work to remove embedded wood at top portion of cooling tower. Once wood is removed, QC will raise RFI for inspection. On-going. During routine inspection at MFC site for Insulation activities, it has be noticed that Global Suhaimi Insulation Inspector always not available at site during insulation inspection activities since a month. Corrective Action shall be taken by Contractor to avoid any mistake during quality process. Subcontractor: QC Inspector was in emergency vacation due to some family issues. But, it was informed to QC department and other QC Inspector was already covered in the site all the time. During surveillance at TCC-2 blasting/coating facility, it has been noted that TCC used contaminated recycled garnet for surface preparation on spools. This violated Sadara Standards and approved Work Procedure. Subcontractor: Recycled garnet third party tent was here. Again, the surface finish of pavements west of sub-station G-1121 are irregular with light brown finish and grinded to level with the adjacent surface. The appearance of the grounded portion is not accpetable as is differs from the adjacent surface finish. Also the edlge of the adjacent scale are not properly trimmed against the slope and the paving. Subcontractor: The Affected area mistake done by the site foreman due to misunderstanding between site engineer and foreman, subcontractor do agreed to rectify effected area. The corrective action is mentioned below: 1. Effected Area will be Marked and cut/chip the concrete minimum depth of 50mm deep. 2. once chipping has done, subcontractor to submit RFI for Inspection. 3. After getting the approval prior to casting concrete we do apply bonding agent and cast approved concrete. PN: During surveillance at DAELIM laydown area, it was observed that the MCC Panel was stored outside. This violates Contractor's Preservation Plan, Para. 2.9.1. Contractor: MCC panel which was observed stored outside in laydown yard already transverred to MFC site. New arrival of panels will be coordinated to Material department for proper preservation as per plan. No Subcontractor UG-Piping QC Inspector. Observed that KCC has no approved Underground Piping (RTR) QC Inspector on site for over 2 months. This violates Schedule "Q" atta. VI, section 1.1 As a minimum Contractor shall assign or require its Subcontractor to assign approved full time Quality personnel/inspector to the work in accordance with table VI-1. Subcontractor shall provide one U/G Piping Inspector per 15 installers. Subcontractor: KCC approved UG-Piping QC Inspector Mr. Rafique will be available on the site 1st week of February 2014. During pre-assemble verification of internal tray for T-2410 C# splitter observed that numerous tray and accessories exhibiting severe oxydation, vapor corrosion and the preserved coating were damaged due to improper preservation method. Contractor must visually inspect all incoming Materials and Equipment damage and for conformance to all appilcable requirements. Violation of A554-E-103-QA-GEN-PRO- 035. RT-6LCS, Para. 2.19.3. All Internal Tray Corrosion has been clean and rectified as per company/vendor recommendation capor phase sorrosion inhibator any internal tray subject for the installation shall be checked first prior to installation, for preventive measures, all trays shall be covered and protected as per approved materials such as polytheline sheets and VPCI Lack of inspection coverage for Structural Inspection: Observed that one QC Inspector. All inspection activities at Eastern MFC areas. Quality discrepancy is repeated frequently and not enough surveillance covereage for Subcontractors (ARC, TCC, SENDAN & ASYAD). Daelim shall take necessary corrective action in order to avoid further adverse effect at site. Company has revised NCR on the same Corrective action will be taken accordingly as per NCR. Page 43 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 30, 2014 DUE DATE Issued corrective action to Company Target Date S/N LBE NO. PID SUBCON/ CONTRACTOR VAF / PN LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason Company comment Approved Close LBE by Company STATUS CONTRACTOR'S CORRECTIVE ACTION PLAN 20 LBE-ARCC- MECH-436 MR. HARIKUMAR ARCC VAF 3 MECH Piping 26-Dec-13 29-Dec-13 09-Jan-14 Open LBE-ARCC-MECH- 437 MR. NASSAR ARCC VAF 3 MECH Coating/ Painting 26-Dec-13 29-Dec-13 23-Feb-14 04-Mar-14 Closed LBE-TCC-MECH- 438 MR. NASSAR TCC VAF 3 MECH Preservation 26-Dec-13 29-Dec-13 09-Jan-14 16-Feb-14 Closed LBE-AMA-CIVIL-212 MR. JERRY AMA VAF 2 CIVIL Civil 26-Dec-13 29-Dec-13 09-Jan-14 22-Apr-14 Closed LBE-AMA-CIVIL-213 MR. JERRY AMA VAF 2 CIVIL Civil 26-Dec-13 29-Dec-13 09-Jan-14 28-Apr-14 Closed LBE-AMA/KCC- CIVIL-214 MR. JERRY AMA VAF 2 CIVIL Civil 26-Dec-13 29-Dec-13 09-Jan-14 26-Mar-14 Closed LBE-AMA-CIVIL-215 MR. JERRY AMA VAF CIVIL Civil 26-Dec-13 29-Dec-13 09-Jan-14 05-Jan-13 Closed LBE-DLM-ELECT- 094 MR. FELOMINO DAELIM VAF 1 ELECT Material 28-Dec-13 31-Dec-13 01-Jan-14 26-Mar-14 Closed LBE-KAF-MECH- 439 MR. NASSAR KAEFER VAF 3 MECH Fireproofing 29-Dec-13 01-Jan-14 12-Apr-14 Closed 21 LBE-DLM- MECH-440 MR. NASSAR DAELIM (Enginnering) VAF 3 MECH Mechanical (Equipment) 29-Dec-13 01-Jan-14 19-Mar-14 Open LBE-TCC-MECH- 441 MR. AMIN TCC VAF 3 MECH Preservation 31-Dec-13 03-Jan-14 14-Jan-14 Still waiting for corrective action 15/2/2014 17-Mar-14 Closed LBE-DLM-MECH- 442 MR. AMIN DAELIM VAF 3 MECH Piping 31-Dec-13 03-Jan-14 Still waiting for corrective action Mar. 2, 2014 28-Apr-14 Closed LBE-DLM-MECH- 443 MR. AMIN DAELIM (QA/QC) VAF 3 MECH Piping 01-Jan-14 04-Jan-14 28-Apr-14 Still waiting for reply & corective action, Mar. 2, 2014. 25-Jun-14 Closed LBE-KCC-CIVIL-216 MR. JERRY KCC VAF 2 CIVIL Civil 02-Jan-14 05-Jan-14 26-Feb-14 14-May-14 Closed LBE-AMA-CIVIL-217 MR. JERRY AMA VAF 2 CIVIL Civil 02-Jan-14 05-Jan-14 16-Jan-14 04-Mar-14 Closed It was noticed that the trench/open ditch south-east of Fresh-Ethane structure was backfilled without completing the seven days cuting period. This is a violation of RT2S-3001-01, Para. 9.1.2. Also, the Structure was backfilled for access of heavy equipment (Crane). The structure sahll be investigated for damage during removal of backfilled materials. Contractor: Open ditch located at south east of fresh ethane structure was backfilled by KCC and advised by Daelim construction team. Amana has seen the removal of backfilling material to investigate the structure. Open ditch is totally covered by polythylene sheet. During site monitoring, the slab of fresh ethane structure was noticed to have irregular surface finish. Some of the area were roughly finish instead of light brown finish. The Contractor/Subcontractor shall include this structure in the list of structure to be repaired for top surface finish irregularities. This is a violation of RT2S-3001-01, Para. 11.1.1. Subcontractor: Construction is agree to do repair work after completion of TCC work. Contractor/Subcontractors are advised to utilized forms from sound materials properly made in accordance with RT2S-3001-01, Para. 6.1. It was noticed that the Subcontractors are utilizing form with split ends, creating incorrect shapes, lines and dimensions shown in the drawing. Subcontractor: Advised to Construction team to use sound material and use form oil to maintain correct shape of structure Misalignment, distortions, offset at weld joint observed at ARCC field installaed piping system. Weld joints weredistorted, misaligned and pipe cocked to one side after welding which is caused by *Weld joint strength reduction factor *Detrimental strain in Equipment, piping of components is prohibited. *Excessive piping sag/or desctruction subject to cause of creep under condition of repeated internal cycle. Subcontractor: ARCC rectified the distortion joint by cut & reweld. Refer to attached RFI - 359, 425 & 439. It has been noted that GIC-ARCC Coating inspector is not assigned during painting activities and inspection time at GIC workshop. This vioates schedule "Q" attach. VI. Wopkshop has been verified in the presenece of Daelim inspector and found to be satisfactory. The documented logbook entry will beescalated to NCR when lack of action by Contractor During surveilllance at TCC-2 fabrication facilities, it has been noticed that TCC is keeping their stain less materials and carbon steel materials together and did not segregated. Stainless steel materials have been kept on ferrous support and have not protected from environtmental conditions. In addition, stainless shall be stored , segregated from ferrous materials such as carbon steel. This violates Material and Equipment protection and preservation plan, item 2.15. Subcontractor: IK-MFC-T-DJ-CJ-QM-1854 DAELIM NCR-046 closed. It is observed that repairs and penalities RT Backlog has increased since many days of all subcontractors. In this situation if welder's previous result of backlog appears deffective then welders cannot be judged at exact time parallel to his production and repair rate cannot be controlled. Daelim must update and record the pending repairs and penalties of each welder and compare their present RT Rejection rate to retain or revoke them. Also update the welder's performance report which shows that how many repairs and penalties are pending for each welder since what date and welder's present status that he is still working or already revoked. Ref. ASME B31.1 Para # 341.3.4, A554-E103-GEN- PRO-056 Para # 19.4, p19.5, & RT8S-6500-01 Rev. 03. Contractor Closely Monitoring all welders in MFC and whenever there is any welder exceeds the specified limit the welders are susupended for first time as per SADARA site notice and stop all productions for the welders. Contractor is working on backlog repair and penalty for the welders to complete as soon as possible. Regarding the corrective action for theabove-mentioned matter, Daelim is monitoring the welders day by day RT basis by daily RT assessment and if anyone exceeds the specified R/R, he will be suspended from work/project. The Contractor/Subcontractor cut the concrete beam of Debutanizer Structure clashing with the pipe. This reduces the cover of the reinforcing bars and violates RT2S-3001-01, section 7, Para. 7.1.8 where the cover for exposed to weather for beams is 75mm. Subcontractor: KCC received site instruction from Daelim to chip/grind portion of beam to give way for the pipe installation. After the installation and alignment inspection of mechanical piping, KCC will do the cementitious grouting to cover the exposed rebars. The area was already repaired and painted with expoxy paint as additional protection for rebars. It was observed that the top of pedestal of vessel B-2058 has been hit during installation of Vessel creating a crack on the upper edge of the pedestal. An investigation has to be done. Contractor: Already inspected and grouted the pedestal. During routine inspection for insulation activities of Water Quence Towe (T- 1410), it has been noticed that there is no adequate distance between step ladder of ladder cage and insulation ring (approx. 2"). As per standard requirement the distance required is 230mm. This is for your information and corrective action required. Subcontractor: This isue is related to Daelim Engineering. Reply fom Daelim Engineeing attached. Contractor: Contractor will modify the ladder for expanding distance between ladder rung and insulation ring. For this issue, we already received the confirmation for repair procedure from Company. Found that SS pipe spools are not preserved/covered at TCC Fab facility 1 and getting environmental effects which represents the start of rust on them. Also TCC needs to improve storage arrangements to avoid cross contamination between CS and SS materials. may pipes ends are open and lying with ground in direct contact and shown to TCC and Daelim QC inspectors. TCC to provide list of all SS spools in TCC 1 whch can explain that these spools requires sand blasting and coating or not. Subcontractor: Noted. Action will be taken. Found that Daelim Piping Inspector doesn't have close monitoring on In-Process Fit-Up activities. During surveillance, Company found Fit-up joints: 1.Bevels angle of joining components was not uniform. 2. Bevels were damaged by deep grinder cuts. 3. There was zero root face of the light and heavy thickness Fit-up joints. 4. Tack Welding performed on heavy thickness (42"dia 22.5mm thick) joint without preheating as the metal temperature was less than the required temperature as per WPS and ASME B31.3 The Affected joints was rejected QC Inspector was given strong warning now in future a cross check and close monitoring will be observed. AMANA RFI No. 811 (MFC-DLM-AMA-CI-5555-0B). During inspection of the above RFI, the following deficiencies were noted: 1. Rebars installed at the opening is missing. (16mm - 8 members) only 2 were installed instead of 4 as shown on the drawing. 2. The location of the puling iron is wrong. The location should be at the opposite side of the opening. This RFI is rejected. Contractor: Already rectified and complied the comments and re-inspected. RFI No. MFC- DLM-AMA-CI-55555-0C During Material Receiving inspection of RFI No. MFC-DLM-SIEMENS-EL-005 at Daelim laydown area for FACP, it was observed that the fire alarm control panels color do not comply to Company color selection desigN aid compared to the actual color of panel are light gray and black. This violates as per RT16D-0120-01. Contractor: This issue was already coordinated to Engineering for answered & clarification. It has been noticed that Kaefer Fireproofing QC Inspector is not assfined during painting activities and inpsection time at MFC site. This violates Schedule "Q" and ITP. The documented logbook entry will be escalated to NCR when lack of action by Daelim. Subcontractor: The assigned QC Inspector for the activity gone for emergency vacation so there was delay all activities, QC inspector will be available at site during all activities. Page 44 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 30, 2014 DUE DATE Issued corrective action to Company Target Date S/N LBE NO. PID SUBCON/ CONTRACTOR VAF / PN LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason Company comment Approved Close LBE by Company STATUS CONTRACTOR'S CORRECTIVE ACTION PLAN LBE-DLM-MECH- 444 MR. AMIN DAELIM VAF 3 MECH Quality Records 02-Jan-14 05-Jan-14 16-Jan-14 02-May-14 Closed LBE-AMA-CIVIL-218 MR. JERRY AMA VAF 2 CIVIL Civil 04-Jan-14 07-Jan-14 02-Apr-14 15-Apr-14 Closed LBE-AMA-CIVIL-219 MR. JERRY AMA VAF 2 CIVIL Civil 04-Jan-14 07-Jan-14 18-Jan-14 13-May-14 Closed LBE-AMA-CIVIL-220 MR. JERRY AMA VAF 2 CIVIL Civil 04-Jan-14 07-Jan-14 18-Jan-14 02-Feb-14 Closed 22 LBE-DLM- MECH-445 MR. SAYED DAELIM (Procurement) VAF 3 MECH Material 05-Jan-14 08-Jan-14 Open LBE-TCC-MECH- 446 MR. SAYED TCC VAF 3 MECH Quality Management 05-Jan-14 08-Jan-14 19-Jan-14 10-Mar-14 Closed LBE-KCC-MECH- 447 MR. GLENN KCC VAF 3 MECH UG-RTR 05-Jan-14 08-Jan-14 19-Jan-14 22-Apr-14 Closed LBE-KCC-MECH- 448 MR. NASSAR KCC VAF 3 MECH Coating/ Painting 05-Jan-14 08-Jan-14 12-Apr-14 12-Apr-14 Closed LBE-DLM-MECH- 449 MR. KURIAN DAELIM VAF 3 MECH Mechanical (Equipment) 05-Jan-14 08-Jan-14 19-Jan-14 14-Apr-14 Closed 23 LBE-DLM- MECH-450 MR. KURIAN DAELIM (Mat. Dept) VAF 3 MECH Preservation 06-Jan-14 09-Jan-14 Open 24 LBE-DLM- MECH-451 MR. KURIAN DAELIM (Construction) PN 3 MECH Mechanical (Equipment) 07-Jan-14 10-Jan-14 Info LBE-TCC-MECH- 452 MR. KURIAN TCC VAF 3 MECH Mechanical (Equipment) 07-Jan-14 10-Jan-14 11-Mar-14 11-Mar-14 Closed LBE-AMA-CIVIL-221 MR. JERRY AMA VAF 2 CIVIL Civil 07-Jan-14 10-Jan-14 27-Feb-14 15-Apr-14 Closed Test Fluid not removed at low spot. It was observed that test water at low spots was not removed after hydrotesting of firewater lines HT-007 conducted on 21 Dec. 2013. This violates Company General Requirements for Pressure Testing and Lay-up (A554-0-PRG-QA-GEN-PRO-014) section 11.1...No test fluid shall remain in low spots. Typical to HT-011. Subcontractor: Test fluid retained at low spots after hydro testing shall be removed during the pre-commissioning time. KCC will be responsible for the flushing out of water. It was noticed that KCC did not assigned Coating Inspector for Tape Wrapping activities and Holiday test examination. This is violation against Sch. "Q", Attachment IV. Daelim needs to comply with Company relevant standard requirements and need to provide corrective action necessary to rectify this failure. Subcontractor: KCC Inspector was on emergency leave vacation & Daelim Inspector was covering for the activity Holiday test activities were performed by TCC Inspector. During inspection of orientation, centering and plumbness of the Equipment FL-1304 A/B and FL 1316A, it is detected that these equipment were installed with a displacement of rear about 10 deg. from designed orientation in IFD drawing. It is also impacted a vast difference in centering measurement tolerance contrary to the specification requirement of 3mm. These variations of orientation & centering can cause mis-match of piping connection with the equipment nozzle also can adversely affect the equipment with increased stress area and interupted flow during process. Violations as per A554-E-103- QA-GEN-PRO-035 Para. 12.2.7, 13.8.2, A554-E-103-QA-GEN-PLN-056, SMIC-D-2007-01, 41, A2, A3. Subcontractor: Noted. Check with equipment group and come up with answer. TCC Construction is waiting for Engineering reply At the N-S Cable tray for FIB type foudnation East of substation G-1121 N/W pedestal was chipped after the installation of structural steel. Contractor shall advise ither Subcontractors to install carefully the equipment/structural steel to avoid damage on existing foundation or pedestal. Contractor: already advised to sub-contractor to carefully install the structure/equipment to avoid damage of pedestal foundation. Already grouted the N-S Cable tray foundation FIB. During inspectionof Valve leak testing at NASICO, leakage observed at Seat of a 18 nos of butterfly valves supplied by Zero Engr. And it is beyond the acceptable limit. Hence, valve is rejected. This violates API S98 para. 3.9.2. The Contractor shall follow up with the issue and notify the supplier for repair or replacements. There are shortage of Subcontractor Welding Inspector in TCC site area at present 66 welders are on site, and only 3 Welding inspectors assigned covering the 66 welders. This is violation against Sch. "Q" Att. VI, table VI-1 which calls for one inspector per 15 welders. Subcontractor: The MFC site welding inspector is at 27/1/2014, 4 welding inspectors. It is observed that Daelim needs to revise the preheat temperature of some WPS which are not meeting the B31.3 requirements. Two examples ate WPS # TCC-WPS-P1/P1-08 Rev. 0 and TCC-WPS-P1/P1- 04 Rev. 0. Preheat requirement as per B31.3 for P1 CS < 25mm thick is 10 deg. C and for > 25mm is 80 deg. C but above mentioned WPS, are requiring only 21 deg. C or 10 deg.C regardless of the thickness not meeting. Contractor: The affected WPSs shall be revised to include B31.3 Preheating requirements. However, regarding mentioning para no. 6.2.3 (RT8S-6500-01) on WPS, Contractor agrees that the same can be done on any new WPSs (or on any new revisions). But revising the approved WPSs solely for that reason will be very tedious and unnecessary. During inspection/survey of S-wall and paving at north of East-West pipe rack/south of substaion G- 1120, the drawing shows a slope of only .102% (DWG No. E-015103-A0002-CV-C-10-001 Rev. 6B) The slope is a violation to Technical Memorandum #TM-CV-043 and RT2D-K100-00, 4.1.24. The S-wall must be redesigned to meet the requirements of this standard. (RFI-MFC-DLM-AMA-CI-5740). Subcontractor: Regarding the Slope of swale and paving sub-contractor has adjusted the slope as per requirement, Daelim to revised the IFC drawing work has been executed and approved the IFC Drawing Already Revised with Drawing No. A554-E-016013-AD00Z-CV-C10-001 Rev. 6B RFI # MFC-DLM-AMA-CI-5762. During inspection of Cooling Tower Wall at Stop logs area room #4, BASIN, it was noticed that the adjacent wall connecting the stop logs have a thickness of 450mm while the design requirement is only 400mm. Contractor shall rectify the wall existing thickness to meet the design requirements. Subcontractor: As per Daelim advised, Amana to maintain 400mm thickness after that were wall thickness above 400nn, Amana agrees to chip those area and repair with repair material. After the rain, it was noticed that some portion of paving have water of about 1" depth located at 6L-21- 22 west side of N-S piperack and in another location at E-1428/NS pipe rack-west site, at the Cooling Tower area several construction joints are leaking and some portion of the foundation slab shows leakage bur there were no marking for the area to be injected. An email was sent with pictures of the leaking part of the cooling tower and concern regarding patching only of extended side which cannotcover the leak of the inernal portion of cracks or honeycombs. Contractor is advised to provide corrective action plan for this concern. Contractor: Subcontractor advised to QC and Site Engineer to mark those leakage area to start repairs/ injection. Construction already marked those and started the chipping to find out leak point. As per meeting with BASF tha all construction joint need to be chipped and inject before lining work. During surveillance at MFC laydown yard shown equipment Secondary demethanizer OUHD condenser (E-2123) were preserved in a wrong way by keeping the equipment in direct contact with the ground. Outdoor storage requires separation from sand/mud or areas subjected to pouring of water. Cross-cut timber with specific dimensions may be used as recommended in the specification. The equipment is supplied bu vendor Fives Cryos. This activity is found to be a violation as per A554-E-103-QA- GEN-PRO-035, para. 8.2.1, 8.2.3, 8.2.4. PN: Received an equipment D21-24 (Reflex drum) this with three others. T- 2120 (Secondary Demethanizer) E-2121 (Interncondenser) & 2123 will be installed one over the other vertically with T-2120 at the bottom. E-2121 & E-2123 are yet to arrive but SME, Engineering and Vendor guidance instruction required to whether to carry out a combined hydrotest to prove the integrity of the bolted flange joints of these equipment. The general arrangement drawing is also mentioning of field hydro test for about 21.047 bar. Equipment E-2330, E-2331 having washers (16mm) welded with extra some thickness of metal piece in order to compensate the shortness in length of the threads in anchor bolts for nuts, required hi bolt tightening. Engineering classification were not provided during bolt tightening. On enquiry, it is found that the welding was done without the information of welding inspector for witnessing the job, hence without an RFI rasing. Subcontractor: After getting Engineering remarks for the use of 32mm thick washer was carried out and RFI has been served and accepted. Page 45 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 30, 2014 DUE DATE Issued corrective action to Company Target Date S/N LBE NO. PID SUBCON/ CONTRACTOR VAF / PN LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason Company comment Approved Close LBE by Company STATUS CONTRACTOR'S CORRECTIVE ACTION PLAN LBE-AMA-CIVIL-222 MR. JERRY AMA VAF 2 CIVIL Civil 07-Jan-14 10-Jan-14 04-Mar-14 04-Mar-14 Closed LBE-DLM-ELECT- 095 MR. FELOMINO DAELIM (Enginnering) VAF 1 ELECT Engineering 12-Jan-14 15-Jan-14 26-Jan-14 12-Jul-14 Closed LBE-AMA-CIVIL-223 MR. JERRY AMA VAF 2 CIVIL Civil 13-Jan-14 16-Jan-14 27-Jan-14 01-Apr-14 Closed LBE-KCC-CIVIL-224 MR. JERRY KCC VAF 2 CIVIL Civil 13-Jan-14 16-Jan-14 29-Apr-14 29-Apr-14 Closed LBE-AMA-MECH- 453 MR. GLENN AMA VAF 3 MECH Hvac 13-Jan-14 16-Jan-14 27-Jan-14 30-Jan-14 Closed LBE-AMA-MECH- 454 MR. GLENN AMA VAF 3 MECH Hvac 13-Jan-14 16-Jan-14 27-Jan-14 23-Feb-14 Closed LBE-AMA-MECH- 455 MR. GLENN AMA PN 3 MECH Hvac 13-Jan-14 16-Jan-14 27-Jan-14 23-Feb-14 Closed LBE-AMA-CIVIL-225 MR. JERRY AMA VAF 2 CIVIL Civil 15-Jan-14 18-Jan-14 29-Jan-14 20-Jan-14 Closed LBE-AMA-CIVIL-226 MR. JERRY AMA VAF 2 CIVIL Civil 15-Jan-14 18-Jan-14 29-Jan-14 02-Feb-14 Closed LBE-AMA-CIVIL-227 MR. GERALD AMA VAF 2 CIVIL Civil 15-Jan-14 18-Jan-14 29-Jan-14 21-Jan-14 Closed LBE-AMA-CIVIL-228 MR. GERALD AMA VAF 2 CIVIL Civil 15-Jan-14 18-Jan-14 02-Apr-14 29-Apr-14 Closed LBE-AMA-CIVIL-229 MR. GERALD AMA VAF 2 CIVIL Civil 16-Jan-14 19-Jan-14 30-Jan-14 04-Feb-14 Closed LBE-AMA-MECH- 456 MR. GLENN AMA VAF 3 MECH Hvac 18-Jan-14 21-Jan-14 07-Apr-14 Closed LBE-AMA-MECH- 457 MR. GLENN AMA PN 3 MECH Hvac 18-Jan-14 21-Jan-14 23-Feb-14 17-Mar-14 Closed LBE-TCC-MECH- 458 MR. NASSAR TCC VAF 3 MECH Coating/ Painting 18-Jan-14 21-Jan-14 01-Feb-14 23-Feb-14 Closed It was noticed during monitoring of Cooling Tower corridor that the honeycomb near the construction joint/expansion joint (East side) is excessive. There is no more concrete holding the waterstop and the dowels are exposed. The reinforcing bars are also exposed. The Contractor was advised to seek recommendation from the manufacturer of the right grout and method to repair this excessive honeycomb. Contractor: As per manufacturer recommendation, the excessive honeycomb area should be filled with micro concrete (Master Emaco Sch33). The surface area to receive the grout is ready and inspected by the Contractor and Company. At GL-72/73 of East-West Pipe Rack it was noticed that the beam located at the east side (GL 73) North has a crack. The crack looks as if the plate was subjected to strain since the area affected is the plate. Please investigate. The Cracked area on the beam was already repaired by capping & removing the Loose concrete & grouted using non-shrink cementitious grout. Isolation valves without union. During inspection in operator building G-1122, it was observed tjat valves are installed in PW lines without union. This violates RTSAES-S-060, Para. 605.8.b, a union shall be installed adjucent to each threaded valve in metallic systems. Subcontractor: Union will be provided adjacent to the isolation valves for maintenance and servicing. This will be revised in the drawing accordingly. Union will be installed and Daelim Construction team and QC Team will ensure the insulation. It was noticed that during monitoring the effect of heavy rainfall at site yesterday, several excavated area have eroded such as sump pits, pad water tank foundation and excavated pipe adjacent to the structures, Air Cooler area and adjacent pipe excavation, Fire monitor and fire hydrant excavated area, etc. and the eroded soil covered the area. This soil shall be removed and shall be replaced with approved materials for backfilling since the soil contains mud exceeding the limit of the standard requirement and these is no record of backfilling and compaction test. Subcontractor: The mud on the pipe and flange were already removed and cleaned and already backfilled with the approved backfilling materials. Embeded sand already remobed from sump area, leak test work on going, once area test is approved, backfilling will be started by approved backfilling materials. During inspection of Power Transformer installation tag # TR-103G101A and TR-103G101B at Substation G-1120, it was observed that the terminal connection pads of primary connection was not tin plated and secondary connection pads were not properly tin plated coating. This violates as per G7D- 0930-00 Para. 6.3 Contractor: Contractor shall coordinate to procurement & engineering teams on this issue. The issue was coordinated to Engineering for some clarification so that it will be closed. With reference to RFI No. AMA-CI-5885-OA & AMA-CI-5886-0A. For roof slab (Concrete Block area) at generator building G-1124, it was noticed that the area is not ready for inspection and the documents intended for the RFI are incomplete. In this regards, Contractor is advised to inspect internally first and see to it the all documents are prepared prior to invite SQG for inspection for proper documentations. Sub-contractor: It is advised to QC Inspector before going for any inspection to arrange the RFI and related documents to avoid rejection of inspection. Also, advised to check the area properly that the area is ready for final inspection or not. HVAC duct overhead communication room. It was observed in MCC/PIB G-1120 that AC ducts are routed above communications room. This violates RTSAES-T-916 Sec. 4.4.2 Minimum design requirements for telecommunications room. Overhead routing of other utilities shall be avoided to prevent obstruction of telecomms room above ceiling access. Provide SME concurrence. If approved, both wall penetrations shall have CFSD to maintain fire rating of the calls. Subcontractor: in regards to HVAC duct Overhead in Communication room which located @ the duct upper portion and theirs no obstruction that can violates to the RTSAES-T-916 Sec. 4.4.2 PN: Missing FD/CFSD in fresh air duct. It was observed in MCC/PIB E-1120 that FA duct penetrating fire rated wall between DCS & Mechanical room has no CFSD. This is not compliant to the following requirements: RT52-5001-01 Sec. 9.16 Provide FD or CFSD at all duct penetration of firerated walls in accordance with KSA Safety & Fire Protection Directories. IMC or other local code enforced. NFPA 90A sEC. 4.2.1.3.1 Outside air intakes shall be equipped with an approved fire equipped with an approved fire damper when not located to meet the requirement of 4.2.1.3. NFPA 90A Sec. 4.2.1.4.1 - Outside intakes shall be equipped with an approved smoke damper when not located to meet the requirement of 4.2.1.4. Use correct abbreviations to identify FD or CFSD in the IF drawing. Contractor: Noted. Daelim QC inspector already discussed and informed to Construction group regarding the issue. With reference to RFI No. AMA-CI-5853-0A for open ditch near substation bldg. G1120, it was found out during the witnessing of survey that the actual survey slope is less than the requirement of .123% of the design and .120% Company minimum requirements. Contractor to ensure that prior survey is conducted and the requirements of Project Specification and design drawing are met prior to invite SQG for witnessing. Also, Contractor surveyor shall check first the work by Subcontractor to ensure requirements with regards to location and elevation are in accordance with the IFC drawing. Contractor: Already counter-checked both by Daelim and Amana Surveyor. Already rectified the slope of open ditch (0631-D1100-0005) the requirements of 0.123%. During surveillance and monitoring activities at Operator building, along corridor area, it was found out that no proper curing and burlap application on newly grout applied on the floor. In which as of yesterday only one (1) after grout application. In this regards, Contractor is advised to take corrective action concerning this issue for proper implementation. Subcontractor: Subcontractor alreadyplaced the burlap and plastic and proper curing has been done at same day. With reference to LBE No. 175 at Operator building along monitoring area and permit issue area. As per surveillance and monitoring, the remaining repair works/trust up at soffit slab and beams are not implemented as of date. Since some electrical piping are already installed. In this regards, Contractor is advised to expedite the repair works for the saind structure. Subcontractor: regarding soffit slab anf beams subcontractor already remove all loose concrete and clean the area, subcontractor is going to install false ceiling those area soffit slab and beam will be covered by false ceiling. Janitor room without service sink provision. During inspection in operator building G-1122, it was observed that water and drainage lines are not provided for service sink in Janitor room. This does not conform to RTSAES-S-060 Sec.1.1 / IPC sec. 403.1 Plumbing fixture shall be provided for the type of occupancy and in minimum number shown in Table 403.1 nd Feed drawing A554-T-103-AR-DWG-A10- 004. Janitor room has to be provided with service sink for cleaning of janitorial equipment. Subcontractor: Service sink provision will be provided based on the approved IFC drawing. PN: Missing water hammer arrestors. During inspection in operator building G-1122, it was observed that water hammer arrestors (WHA) are not provided nor indicated in IFC drawing. This violates RTSAES-S-060, sec. 1.1/lpc 604.9 The flow velocity of the water distribution system shall be controlled to reduce the possibility of water hammer. A water hammer arrestor shall be installed where quick- closing valves are utilized. The arrestor shall be located within an effective range of the quick closing valve. WHA shall conform to ASSE 1010. Access shall be provided to WHA. Subcontractor: Water hammer arrestor will be provided after the approval of IFC Drawing. Drawing has been submitted to Sadara for approval. During the torquing of the mechanical coupler for the column extension of P-1321 Piperack, the torque capacity was checked and it was found out that it is less than the requirement of 185 ft-lbs as required by the manufacturer. Contractor shall check first the equipment prior to inviting SQ group for witnessing. Torquing is still pending. Subcontractor: Already replaced torque and set by 185 ft. lbs It has been noticed that TCC released too many coated pipes & spools from workshops (TCC-1 & TCC- 2) to MFC site for installation without informing or offering SADARA QIT for inspection. Furthermore, all those pipes & spools were blasted by recycled garnet which used for blasting without provide Lab tests certificates (Chlorides & sulfate contamination test, sieve analysis. Water soluble contamination test and conductivity & oil content test) as per SSPC AB1 & SSPCAB2. This is violation against schedule Q and work procedure for Garnet recycle system. Note: Blasting & Coating activities have started on 13th Jan. 2014. Subcontractor: Noted. Test report will be submitted. Page 46 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 30, 2014 DUE DATE Issued corrective action to Company Target Date S/N LBE NO. PID SUBCON/ CONTRACTOR VAF / PN LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason Company comment Approved Close LBE by Company STATUS CONTRACTOR'S CORRECTIVE ACTION PLAN LBE-TCC-MECH- 459 MR. KURIAN TCC VAF 3 MECH Mechanical (Equipment) 18-Jan-14 21-Jan-14 14-Jan-14 12-May-14 Closed LBE-TCC-MECH- 460 MR. KURIAN TCC VAF 3 MECH Mechanical (Equipment) 18-Jan-14 21-Jan-14 01-Feb-14 03-Apr-14 Closed 25 LBE-TCC- MECH-461 MR. KURIAN TCC VAF 3 MECH Mechanical (Equipment) 19-Jan-14 22-Jan-14 19-Mar-14 Open LBE-PCMC-MECH- 462 MR. KURIAN PCMC VAF 3 MECH Piping 19-Jan-14 22-Jan-14 24-Mar-14 26-Mar-14 Closed LBE-TCC-MECH- 463 MR. KURIAN TCC VAF 3 MECH Mechanical (Equipment) 19-Jan-14 22-Jan-14 02-Feb-14 23-Mar-14 Closed LBE-KAF-MECH- 464 MR. KURIAN KAEFER VAF 3 MECH Fireproofing 20-Jan-14 23-Jan-14 23-Jan-14 12-Apr-14 Closed LBE-SEN-ELECT- 096 MR. MARK SENDAN VAF 1 ELECT Electrical 20-Jan-14 23-Jan-14 03-Feb-14 13-Feb-14 Closed LBE-DLM-INST-097 MR. PERVEZ DAELIM (Procurement) VAF 1 INST Instrumentation 22-Jan-14 25-Jan-14 05-Feb-14 24-Jun-14 Closed LBE-AMA-CIVIL-230 MR. GERALD AMA VAF 2 CIVIL Civil 23-Jan-14 26-Jan-14 06-Feb-14 06-Feb-14 Closed 26 LBE-DLM- MECH-465 MR. SAYED DAELIM (Construction) VAF 3 MECH Piping 23-Jan-14 26-Jan-14 06-Feb-14 Open 27 LBE-AMA- CIVIL-231 MR. GERALD AMA VAF 2 CIVIL Civil 25-Jan-14 28-Jan-14 20-Jul-14 10-Aug-14 Open 28 LBE-DLM- INST-098 MR. PERVEZ DAELIM (Enginnering) VAF 1 INST Instrumentation 26-Jan-14 29-Jan-14 09-Feb-14 24-Jul-14 Open LBE-DLM-INST-099 MR. PERVEZ DAELIM VAF 1 INST Instrumentation 26-Jan-14 29-Jan-14 02-Mar-14 Contractor to provide full time QC Inspector 18-Mar-14 Closed LBE-ASYAD-INST- 100 MR. SHABIRUL ASYAD VAF 1 INST Instrumentation 26-Jan-14 29-Jan-14 02-Mar-14 08-Apr-14 Closed LBE-DLM-ELECT- 009 MR. MARK DAELIM (Mat. Dept) VAF 1 ELECT Preservation 27-Jan-14 30-Jan-14 15-May-14 02-Jun-14 Closed 29 LBE-AMA- CIVIL-232 MR. JERRY DAELIM (Construction) VAF 2 CIVIL Civil 28-Jan-14 31-Jan-14 Open During routine inspection for applied fireproofing (2nd Coat of chartek) at E-W pipe rack, it has been noticed that poor (eneven) of surface finish, as per Sadara specification, Surface texture of the fireproofing material shall be "smooth". This is happened due to application of coating by unqualified personnel. A logbook entry has been made for information, root cause analysis & corrective action. Note: RFI-DLM-KAF-H-0426. Subcontractor: JCC and Card Holders were temporary transfer other site, JCC card holders where brought back at MFC site surface was repaired, shall make sure there is sufficient qualities manpower at all times. Contractor performs oil sampling test for transformers at substations G-1120 and G-1121 in which they will utilize the laboratory of SGS for the testing which is not approved by Sadara. This is a violation as per schedule "Q", Attachment IV, Section 7.3. Contractor: Contractor submitted on January 23, 2014 the Company profile that will perform the testing of oil sampling for power xmer as per transmittal no IK-MFC-T-DJ-CJ-CM-2070, waiting for approval. During surveillance at site, it was observed that Contractor installed Analyzer at site 5 nos. at different locations but all the tray supports have been cracked and with welding defect by vendor. Contractor: Contractor matrerial department already issued OSID on 05-01-2014 with OSID no. 0677 to notify vendor regarding the damage. Company will notify as soon as vendor give response. Contractor at MFC site raised RFI TCC-SS-WE-0608 for the Post welding inspection Structural Support T--1810 but inspection showed the support were only tack welded which made the RFI's to cancel. The Structures attached to this were there never inspected after this and the equipment is already been erected. The Inspector for pipe welding was on 25/12/2014. Subcontractor: Supporting drawing was revised. Accepted RFI is attached, PCMC is unable to cover the pipe end in the entire E-W pipe rack and unwanted materials were found inside the pipe. Immediate response is required. This is violation of A554-E-103-QA-GEN-PRO-046, Para. 7.44. Subcontractor: We have already taken action special crew is implemented in site for the preservation of pipe by the PCMC Construction. During surveillance of E-2210, 2322 A/B, it is noted that almost or several flanges of the Horizontal exhangers found covered with mere plastic sack and water colleted in it and this damaged sacks may have caused the water to move through it into the equipment during the rain causing corrosion, hence, damage to the eqipment. Violation as per G95-8000-08, Para. 3.1.2.1, 4.1.1.1, A554-E-103-QA-GEN- PRO-035, Para. 8.2.2. Subcontractor: Corrective action shall be taken. TCC already taken action as per log book, all have been covered as per recommended plan. During isntallation at MFC site by TCC, the following descripancies recorded during the erection of common Shell D-2304 for E-2304 (C2R Condenser) and E-2213 (Dethanizer Condenser), manufactured and certified by Ellimental for D-2304 and Five Cryons for E-2304, E-2213 bearing P.O. No. 2122351. 1) 290mm lifting trunion of D-2304 were found removed by 85mm with only acetylene gas cutting, ref. drawing no. D2304-103-9003-01, D2304-103-9003 - Name plate were reverted. These activities were violations as per 1. G5S-5350-50 Para. 51.1.8, 51.1.9. 2. RT 96.-300-02. Subcontractor: Noted. Corrective action will be taken. NCR has been closed and/or corrective action has been done. MFC site Daelim's Subcontractor found erected equipment (E-2233 & D2304) without undergoing structural foundation grouting process and getting Civil handover note to proceed mechanical activities. The structural assembly to be fixed and grouted for the further mechanical construction and inspection activities to yield precision alignment tolerance as specified in the specification. The once aligned structural can also be disturbed due to continues construction activities in and around its premises of not grouted. This is a violation as per A554-E-103-QA-GEN-PRO-035, Para. 9.3. Subcontractor: Noted. Corrective action will be taken. During routine site visit, it was noticed that the Contractor shifted MV Motors to the site from the Laydown yard but did not energized its Space Heater which is a violation as per RT7D-0665-00, section 13.1.2. The Contractor is maintaining the space heater evergization at laydown yard prior to shifting it at site. Installed MV Motors at site from laydown yard are now space heater Energized and bi-weekly preservation is maintained preservation maintenance Log Sheet were provided to record all activities including shaft rotation and etc. The Contractor did not continue the grouting of foundation of the inside portion of the oil quench and water quence structures. Only the outside portions wre grouted. The Contractor shall ensure that space between plates shall also be fully filled with grout. During the time of cable tray inspection, it was observed that Contractor installed wrong splice plate. Instead of round type connector, installed was slotted type. This violates NEMA VEZ, project specs G-07C-301. Subcontractor: Splice plate shall be replaced when the material is available. Waiting for Daelim supplied material to be available at site. During routine surviellance and inspection, it was observed the unavailability of Contractor QC presence at calibration shop. Contractor shall be full-time presence at lab. This violates schedule "Q" and project approved ITP. Contractor: The action of this LBE was settled between the contractor & subcontractor by means of continuing the activity in calibration shop when contractor QC is only available. During site surveillance, it was observed Contractor doing cable termination at JB side without cable laying inspection. This is a standard violation of schedule "Q" and project approved ITP. Contractor: Construction already instructed and be aware of its so thata this violation will not be repeated. RFI will be submitted to close this LBE. During Material Receiving inspection at Amana storage area. Concerning metal runner size (100mmx0.06x3000mm) intended to be used in operator building. It was noticed suring inspection that this materials are not properly protected or stored. Contractor is advised to arrange these materials with good storage with proper handling in order not to damage. Sub-contractor: Contruction has already shifted the material in shaded area (G-1120). Materials were arranged properly and covered by tarpauline sheet. During surveillance, it was found that Vendor's Spools (R-2030 & R-2035) has been cut without providing detail method of statement which WPS and NDE to be used. This is violation against schedule "Q". Contractor needs to provide a full detail report on the incident. Subcontractor: Noted. Corrective action will be taken. During surveillance & monitoring inspection at operator building along blast type door along north side. It was found out that sub-frame of blast door was not align properly and squareness of the said sub-frame. Contractor is advised to submit shop drawing and details on how to rectify or repair the squareness and alignment of sub-frame. Contractor: contractor has assigned ARCC welder for welding work activities and kindly check with Contractor construction group. Page 47 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 30, 2014 DUE DATE Issued corrective action to Company Target Date S/N LBE NO. PID SUBCON/ CONTRACTOR VAF / PN LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason Company comment Approved Close LBE by Company STATUS CONTRACTOR'S CORRECTIVE ACTION PLAN LBE-AMA-CIVIL-233 MR. JERRY AMA VAF 2 CIVIL Civil 28-Jan-14 31-Jan-14 11-Feb-14 02-Feb-14 Closed LBE-AMA-CIVIL-234 MR. GERALD AMA VAF 2 CIVIL Civil 28-Jan-14 31-Jan-14 11-Feb-14 03-Feb-14 Closed LBE-ARCC-MECH- 466 MR. GLENN ARCC VAF 2 MECH Refractory 28-Jan-14 31-Jan-14 11-Feb-14 04-Feb-14 Closed LBE-KCC-MECH- 467 MR. GLENN KCC VAF 2 MECH UG-RTR 28-Jan-14 31-Jan-14 11-Feb-14 01-Feb-14 Closed LBE-AMA-CIVIL-235 MR. JERRY AMA VAF 2 CIVIL Civil 29-Jan-14 01-Feb-14 12-Feb-14 30-Jan-14 Closed LBE-AMA-CIVIL-236 MR. GERALD AMA VAF 2 CIVIL Civil 29-Jan-14 01-Feb-14 12-Feb-14 03-Feb-14 Closed LBE-AMA-MECH- 468 MR. GLENN AMA VAF 2 MECH Hvac 30-Jan-14 02-Feb-14 07-Apr-14 Closed 32 LBE-DLM- MECH-469 MR. NASSAR DAELIM (Construction) VAF 2 MECH Insulation 30-Jan-14 02-Feb-14 19-Apr-14 24-Jul-14 Closed- LBE-SEN-ELECT- 101 MR. MARK SENDAN VAF 1 ELECT Electrical 01-Feb-14 04-Feb-14 15-Feb-14 04-Mar-14 Closed LBE-KCC-CIVIL-237 MR. JERRY KCC VAF 2 CIVIL Civil 02-Feb-14 05-Feb-14 04-Mar-14 01-Apr-14 Closed LBE-TCC-MECH- 470 MR. NASSAR TCC VAF 3 MECH Coating/ Painting 02-Feb-14 05-Feb-14 04-Mar-14 12-Apr-14 Closed LBE-DLM-ELECT- 010 MR. MARK DAELIM VAF 1 ELECT Preservation 02-Feb-14 05-Feb-14 31-Mar-14 31-Mar-14 Closed 30 LBE-DLM- MECH-471 MR. SAYED DAELIM (Procurement) VAF 3 MECH Piping 03-Feb-14 06-Feb-14 27-Jul-14 Open LBE-TCC-MECH- 472 MR. KURIAN TCC VAF 3 MECH Mechanical (Equipment) 04-Feb-14 07-Feb-14 19-Mar-14 23-Mar-14 Closed During inspection of LFO/HFO segregation structure foundation, the dowel bar is contact with concrete in some locations are already rusted. The Contractor shall check other area to show some rusted dovel that were painted/touched-up were not corroded and prior to to painting inspection shall be undertaken to ensure these dowel bars are free of rust and proper type of coating materials shall be applied. RFI #MFC-DLM-AMA-CI-6050. Contractor: Construction already clean the rusted rebars by using wire brush and touched-up paint has been applied. During surveillance at site for Equipment # W-1720/1721 & W-2040 insulation activities, it has been noticed that there are no adequate distance to complete cold insulation activities between platform supports (I- beam) and shell equipment. The actual distance between them approximately is 70mm and the distance required for insulation is 150mm. The numbers of I-beams are six (6). Contractor: LBE-DAELIM-MECH-469: 1.The revised drawing were issued last february. The modification work will be followed by construction team. 2. LBE-DAELI<-MECH-440 & LBE-DAELIM-MECH-473 the modification design is agreed as attached. the further commincation with sadara QC is being done. once investigation is complete, site instruction will be issued through constrution team. During routine site visit, it was noticed that the Contractor is pulling a MV cable from switchgear going to Transformer at substation G-1121 without the usage of cable rollers which I a violation as per NEMA VE- 2, section 5.4. Subcontractor: Sendan has been issued internal NCR for the Subject issue. The corrective action will be taken as per the project requirements. As discussed and as per the actual survey regarding centerline of pump foundation and for pump P- 2417 A/B where the centerline of the pump is offest by 10cm., the Contractor needs to provide computation to show dynamic response of foudnation against pump rotation is acceptable. Submit computation to Sadara MFC structural Engineer for approval. Subcontractor: KCC is waiting for the design calculation from Daelim. During attendance of RFI # MFC-DLM-AMA-CI-6080 at Flare area, it was found out that out of 5 foudnations requested for inspection, 3 of the foundations have bolts out of location by 16mm, the requirement is, 920m between group of Anchor bolts while installed is only .906. RFI was rejected. Contractor: As per RFI# MFC-DLM-AMA-CI-6080, the achor bolt was rectified and put in the correct location and re-inspected on the next day by Contractor and Company. With refe4rence to RFI #MFC-DLM-AMA-CI-6101 at substation G-1121 along (SDG-MECH-ROOM). It was noticed during inspection that four (4) anchorage at the top portion door frame are incomplete installation and also one anchor at door frame only by hand it remove not properly fixed. In this regards, Contractor is advised to counter check the alignment and plumbness and also installation for the said door prior to final inspection. RFI was rejected. Sub-Contractor: Advised and instructed to QC Inspector to inspect internally with Daelim Inspector to confirm inspection acceptance before calling SADARA PID. Work has been rectified and inspected and approved. Outdoor air intake motorized damper w/o seals and access doors. During surveillance in MCC/PIB G- 1120 (Typical to G-1121) Hvac duct installation, it was observed that motorized damper in the outside air intake has no seals and access doors. This violates the following: RT52-50001-01, section 11.6 Gas detectors, where required in RT-LPP-12.1 & RT-LPP-12.2 shall be installed in the outdoor air intake and shall be connected to the control room alarm system. A quick closing damper with seals shall be installed i9n the air intake to prevent the entry of contaminated air into the building. RT52-500-01, sec. 8.2.7. Provide access doors near heating coils, cooling coils, outside air intakes, automatic dampers, motors, filters, fan wheels, fire dampers and other locations where conditions demand accesibility for service. Contractor: Motorized damper with seal was already installed on the outdoor air intake duct to prevent the entry of contaminated air which is requirements as per RT5Z5000-01 sec. 11.6 in SADARA STD. During inspection at paving area along sub-station G-1120. It was noticed that the calibration certificates of the surveyor did not comply or the same to the survey instrument that have been using for the said paving. Contractor is advised to check the survey instrument at site. Sub-Contractor: Advised and instructed to Surveyor to keep calibration certificate the instrument used. Before starting any work at site check properly equipment and calibration certificate. Incorrect refractory Anchors- During inspection in Furnace F-1240, it was observed that anchors for RCF Modules were provided at south end wall (radiant bottom) instead of the required anchors for castable refractory. This violates Vendor drawing no. E-11155, 04-2. Contractor: Correct Refractory anchors have been welded on south end wall (Radiant bottom) in order to continue castable application. Subcontractor: RB Hilton replaced the wrong anchor & used the correct one. FRP pipe manually tapered- During inspection of UG-Firewater piping installation for HT-006, line nos FW-071034-8 and FW-071026-6, it was observed that 4 nos. 5 pigots were manually tapered using grinder instead of the shaving machine per manufacturing procedure. This violates manufacturer installation procedure section 4, to use shaving machine to obtain the taper angle requirement for Taper- Taper adhesive bonded joint. J13, 15, 16 & 21 - manually tapered. Manual tapering shall be disconnected. Use shaving machine to do the taper. During verification of Internal Tray T-2410 (C-3 Splitter) observed that downcomer pannel holes are mismatching as per site condition and Vendor GA drawing. TCC/Daelim team has modified some pannel hole without appropriate approval from vendor and company. Violation of sched. "Q" and approved ITP (A554-E-103-QA-GEN-PLN-103) Daelim Engineering/Quality team shall verify the discrepancy occured at site and submit the appropriate rectification method by Vendor to Company. Subcontractor: This is related to Daelim Engineering. Not for TCC. During complete absence of Subcontractor Coating Inspector, Coating application activity is on-going at TCC-1 workshop. As per schedule Q and ITP, this activity is hold point for Subcontractor. For information and corrective action of Daelim. Subcontractor: As per request from Sadara communication, TCC QC went to site for urgent holiday testing from 8:00 - 9:00 AM. At that time, Sadara PID came to TCC shop-1 and noticed some activities were performed without TCC QC. During that time, Daelim QC was present at shop-1. Also, holiday inpsection at site, QC immediately came back to shop-1 and resumed the works. During routine surveillance at Daelim's laydown yard, it was noticed that there are some MV motors's space heaters that were not energized which is a violation as per RT7D-0665-00, section 13.1.2. All MV Motors stored at laydown yard are now energized its space heater, in addition, preservation maintenance log sheet were attached to record the all preservation activities. During Material Receiving inspection of pipe fittings under P.O. 100532-42- K04-005-A01, it was noted that fitting internally coated with rust prevention paint. This is violation against DOW specification G4S-0210-01 para 2.1.5 which states that "If the piping was coated with a light coating of mineral oil to prevent corrosion, the coating shall be removed by pulling a swab saturated in cleaning solution through the piping". Contractor shall investigate and provide corrective and preventive action. Contractor: The fittings were internally coated in order to preserved and to avoid corrosions.Company acknowledged the close the issues. Page 48 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 30, 2014 DUE DATE Issued corrective action to Company Target Date S/N LBE NO. PID SUBCON/ CONTRACTOR VAF / PN LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason Company comment Approved Close LBE by Company STATUS CONTRACTOR'S CORRECTIVE ACTION PLAN 31 LBE-DLM- MECH-473 MR. NASSAR DAELIM (Enginnering) VAF 3 MECH Mechanical (Equipment) 04-Feb-14 07-Feb-14 19-Apr-14 Open LBE-KCC-CIVIL-238 MR. GERALD KCC VAF 2 CIVIL Civil 04-Feb-14 07-Feb-14 18-Feb-14 03-Mar-14 Closed LBE-SEN- TELE-006 MR. RODNEY SENDAN PN 1 TELECOM Telecomunication 04-Feb-14 07-Feb-14 05-Apr-14 05-Apr-14 Closed LBE-ARCC-MECH- 474 MR. HARIKUMAR ARCC VAF 3 MECH Piping 05-Feb-14 08-Feb-14 13-Feb-14 23-Mar-14 Closed LBE-SEN/DLM- ELECT-102 MR. FELOMINO SENDAN/ DAELIM VAF 1 ELECT Material 06-Feb-14 09-Feb-14 15-Feb-14 26-Apr-14 Closed LBE-SEN-ELECT- 103 MR. FELOMINO SENDAN VAF 1 ELECT Electrical 06-Feb-14 09-Feb-14 18-Feb-14 03-Jun-14 Closed LBE-SEN- TELE-007 MR. RODNEY SENDAN PN 1 TELECOM Telecomunication 06-Feb-14 09-Feb-14 05-Apr-14 05-Apr-14 Closed LBE-DLM-MECH- 475 MR. HARIKUMAR DAELIM VAF 3 MECH Mechanical (Equipment) 09-Feb-14 12-Feb-14 02-Apr-14 03-Apr-14 Closed LBE-AMA-CIVIL-239 MR. GERALD AMA VAF 2 CIVIL Civil 09-Feb-14 12-Feb-14 15-Feb-14 16-Feb-14 Closed LBE-AMA-CIVIL-240 MR. GERALD AMA VAF 2 CIVIL Civil 10-Feb-14 13-Feb-14 02-Mar-14 02-Mar-14 Closed LBE-AMA-CIVIL-241 MR. GERALD AMA VAF 2 CIVIL Civil 12-Feb-14 15-Feb-14 02-Mar-14 02-Mar-14 Closed 32 LBE-SEN- ELECT-104 MR. FELOMINO DAELIM (Enginnering) PN 1 ELECT Engineering 12-Feb-14 15-Feb-14 26-Feb-14 Info LBE-DLM-MECH- 476 MR. GLENN DAELIM (Construction) VAF 3 MECH Refractory 13-Feb-14 16-Feb-14 02-Mar-14 08-Jun-14 Closed LBE-DLM-MECH- 477 MR. GLENN DAELIM PN 3 MECH Hvac 13-Feb-14 16-Feb-14 27-Feb-14 23-Feb-14 Closed LBE-KCC-CIVIL-242 MR. GERALD KCC VAF 2 CIVIL Civil 15-Feb-14 18-Feb-14 01-Mar-14 21-Feb-14 Closed 33 LBE-DLM- MECH-478 MR. SAYED DAELIM (Procurement) VAF 3 MECH Piping 16-Feb-14 19-Feb-14 Open Contractor is advised to provide and approved PCDD started in Operator building IFC drawing as per stated in RT-SAES-T-916, Para. 4.1.1. All IFC which Attached in RFI's and used by Construction are all improved and stamped by RCDD. Numerous weld defect/discontinuity observed at Liquid Furnace (Field Piping System) during or semilar inspections: Weld joint are wrinkled and buldged to one side (up to 7mm). (01603.BEM-P-124318.03). Misalignment or distorted due to improper welding technique. (01603.BEM.P.124318-01 TO 05). Back welded without supporting WPS (C-016103 BEA-P-123318-03 to 07). Base Metal deeply grinded, removed for internal alignment. On Daelim, welding and NDE team shall verify and advise appropriate corrective and preventive action to ARCC. Subcontractor: ARCC cute & re-aligned the fitted joints then cut and reweld the distribution joints. During Material receiving inspection of RFI No. MFC-DLM-EATON-EL-006 for Low Voltage MCC Panel No. MCC-103H106 at substation G-1120, it was observed that the Bus Lean Insulator support was broken and Panel enclosures were having deformation caused by improper handling during shipment. This violates schedule Q attachement IV sec. 3.2. Contractor: OSID has been prepared to inform the Vensor regarding the damaged item. Construction follow up that Vendor will replace the insulator and waiting for feedback. During surviellance at site, it has been noticed that there is no adequate space between step ladder of vertical ladder and insulation rings for oil quence tower (T-1310). The distance between them approximately is 60mm. The distance required as per standard is 230mm after insulation. Logbook entry has been logged for root cause analysis and corrective action prior to biginning insulation activities. Contractor: LBE-DAELIM-MECH-469: 1.The revised drawing were issued last february. The modification work will be followed by construction team. 2. LBE-DAELI<-MECH-440 & LBE-DAELIM-MECH-473 the modification design is agreed as attached. the further commincation with sadara QC is being done. once investigation is complete, site instruction will be issued through constrution team. With reference to RFI No. MFC-DLM-KCC-CI-5821 & 5822 at Cooling Tower pump (P-0901A-H) "pocket", it was noticed that during inspection, found out that some pockets are not properly cleanedand not ready to receive grout. In this regards, Contractor is advised to inspect it properly and see to it that the area for inspection is ready prior to invite the PID in order not to hamper the inspection as per schedule. Sub-Contractor: The area to receive grout was cleaned properly prior to grouting. Inspection was done & released. RFI shall be attached. PN: During surveillance for electrical cable tray installation at East-West main pipe rack, it was observed that the installations of splice plate are closed to support and less than 300mm. As per G7C-0324-03, splice plate on support is +- 300 is required to use of a heavy duty splice plate. Subcontractor: The issue has been investigated & corrective action plan preprared by Construction. NCR was issued to Daelim Construction team. Missing Nuts in hanging modules. It was observed in Gas Furnace Refractory that one of the double nuts in the hanging modules are not installed in furnaces F-1130, F-1140, F-1150, F-1160 & F-1170. This deviated vendor drawing E-11154-05-01 which requires double nut to secure the bolt-on hanging modules. Contractor: Nuts supplied fo module installation wee not sufficient. So Daelim will purchase more nuts in order to complete the installation. PN: It was observed in MCC/PIB G-1120 & 1121 that Bleed Air Outlet is located about 5m above fan outlet centerline. This bleed carried sand being removed from the outside air. Contractor must ensure that sand extracted from the inertial separator/filter can be blown out and not build-up in the ducting system. Contractor: Daelim assured that this bleed fan carries sand and other solid particles. Bleed Fan: Static Pressure: 700 PA During surveillance and monitoring activities at Operator Building and substation G-1121. It was noticed that some materials are scattered around the building, such as steel structure, cement and other materials intended for Operator building. Contractor is advised to arrange the materials accordingly with proper protection and also proper house keeping shall be maintained in order not to damage the materials at site. Subcontractor: All excess materials are removed from operator building. Other materials which are using at site were already arranged proeprly. During surveillance and monitoring activties at operator building G-1122, it was found out that some internal walls installation of insulation board was already started without submitting first the RFI for proper checking as per checklist. Contractor therefore is advised to take corrective acations about the issue for proper documentation. Contractor: Subcontractor has started insulation work without submitting the RFI to Company because of shop drawing was not approved by Daelim after approval of shop drawing, subcontractor submitted the RFI for inspection With reference to the RFI # MFC-DLM-AMA-CI-6295 (Operator Building G-1122), it was noticed in some interior walls that during inspection, no anchorage connected to the RC wall to support vertical and horizontal frames and some insulation board are already installed. Contarctor is advised to provide shop drawing or details showing the anchorage to the perimeter RC wall for proper implementation. Contractor: Subcontractor QC has provided approved shop drawings and work is implemented as per approved drawing. Subcontractor provided anchorage braket to attain the streght vertically and horizontally alignment. Subcontractor submitted the RFI for inspection of achorage and it is inspected and accepted to start next activity. During surveillance inspection at East-West side of main piperack for 24.5 kV incoming line cable tray, it was observed that the cable tray ring was deformed. This violates schedule Q, attachment IV, sec. 3.2. Contractor: The issue was discussed in the weekly meeting and furhter discussions with the management on how to solve the problem as it was damaged by other Contractor. Contractor is advised to raise RFI for any communication related work in all MFC buildings. This will prevent reworks expecially on EMT conduits installation. Take note that EMT conduits shall not be covered or closed without RFI, it must be exposed during RFI. RFI's was raised unfortunately it was rejected, contractor will raised RFI again for said activities after comes out the rev. During surveillance inspection at site observed the following violations on field installed equipment P2415AB & 2411 AB. *No proper protection provided to prevent contamination from blowing sand and debris. *Lack of appropriate utility in-place for equipment such as space heaters, etc. Daelim preservation team shall take immediate action to control such kind of violation at site. Deviation of project requirement and procedure (RT-6-ICS, RT-55-7801 and A554-E-103-QA-GEN-PRO-039. Installed Pumps (P-2411 A/B & 2415 A/B) are now fully protected from any foreign debris such as sands and fulling objects by installing scaffolding and wood flanks Reference to RFI No. MFC-DLM-KCC-CI-5928 Pedestal Rebar Installation "Hilti Anchoring" for T- support at East & West side of dike wall, it was noticed during inspection that some "Hilti Anchoring's depth requirements do not conformed to the latest IFC drawing wherein some depths are ranging from 110mm up to 125mm only, in which the minimum requirement is 130mm depth. Contractor/Subcontractor is advised to check properly and see to it that the depth requirement must meet and/or comply with the latest IFC drawing. Subcontractor: In some areas, the depth of HILTI Anchoring can not be met as per the IFC drawing because it touches the rebar reinforcement of the paving. Relocation of the hole has been done in order to meet the required depth. During valve testing, it was noted that butterfly valve (103-EBV-113051) 12"X150 Flanged face serrration damaged due to pitting. This is violation against Sadara Spec G14-S-3230-01 Para. 2.4. Contractor shall provide corrective and preventive action. Page 49 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 30, 2014 DUE DATE Issued corrective action to Company Target Date S/N LBE NO. PID SUBCON/ CONTRACTOR VAF / PN LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason Company comment Approved Close LBE by Company STATUS CONTRACTOR'S CORRECTIVE ACTION PLAN 34 LBE-DLM- MECH-479 MR. KURIAN DAELIM (Construction) VAF 3 MECH Mechanical (Equipment) 16-Feb-14 19-Feb-14 Open LBE-DLM-INST-011 MR. PERVEZ DAELIM VAF 1 INST Preservation 16-Feb-14 19-Feb-14 30-Mar-14 19-Apr-14 Closed 35 LBE-DLM- MECH-480 MR. KURIAN DAELIM (Construction) VAF 3 MECH Mechanical (Equipment) 18-Feb-14 21-Feb-14 Open 36 LBE-SEN- ELECT-105 MR. FELOMINO SENDAN/ DAELIM VAF 1 ELECT Electrical 18-Feb-14 21-Feb-14 04-Mar-14 30-Jul-14 Open LBE-DLM-INST-106 MR. PERVEZ DAELIM VAF 1 INST Instrumentation 18-Feb-14 21-Feb-14 24-Feb-14 04-Mar-14 Closed 37 LBE-DLM- MECH-481 MR. SAYED DAELIM (Construction) VAF 3 MECH Piping 19-Feb-14 22-Feb-14 Open LBE-AMA-CIVIL-243 MR. GERALD AMA VAF 2 CIVIL Civil 19-Feb-14 22-Feb-14 04-Mar-14 08-Mar-14 Closed LBE-DLM-MECH- 482 MR. GLENN DAELIM (Enginnering) VAF 3 MECH Hvac 20-Feb-14 23-Feb-14 09-May-14 14-Jun-14 Closed LBE-DLM-MECH- 483 MR. GLENN DAELIM VAF 3 MECH Hvac 20-Feb-14 23-Feb-14 07-Apr-14 Closed LBE-DLM-MECH- 484 MR. KHAN DAELIM VAF 3 MECH Piping 20-Feb-14 23-Feb-14 22-Mar-14 23-Mar-14 Closed 49 LBE-SEN- TELE-008 MR. RODNEY SENDAN PN 1 TELECOM Telecommunica tion 22-Feb-14 25-Feb-14 25-Feb-14 30-Jul-14 20-Jul-14 Closed LBE-ASYAD-INST- 107 MR. PERVEZ ASYAD VAF 3 INST Instrumentation 22-Feb-14 25-Feb-14 25-Feb-14 04-May-14 Closed LBE-ASYAD-INST- 108 MR. PERVEZ ASYAD VAF 3 INST Instrumentation 22-Feb-14 25-Feb-14 08-Apr-14 Closed During site surveillance, it was observed that Contractor stored Instrument panel at substation without inspection of material receiving and proper preservation. This violates project ITP and project Specification A554-E-103-CM-GEN-PLN-002 & smitp-j-902-06, item no. 2.2. Schedule "Q". Contractor: Material receiving was not done because of document are not available & lack of coordination between QC and material department. That is why it was transferred to site. RFI raised to Company & it was inspected and accepted. During line inspection for package no. 1681-00-HT-017 (T) line no. P- 210602-30"-HC11, it was noted that 4 nos. of socket joints (between two dissimilar material A182-F308-304L & LTCSA671-CC70/Nipple A333-6) welded without approved WPS. This is violation against RT8S-6500-01, para. 2.2. Contractor shall provide Corrective & Preventive action. With reference to RFI # MFC-DLM-AMA-CI-6387 about Leak Test for water retaining structure (Construction Joint of Slab & Wall) at Cooling Tower basin "Room 9" heigh of water is 150mm, it was noticed that during inspection that some portion or areas of RC wall are found with leaks at west side wall of cooling tower cell #9 and interior wall between 9 & 8 cell. Contractor is advised to investigate the said leaks and take remedial action on the issue. Note: RFI was rejected. Subcontractor: During leak test at cooling tower room 9, Amana started injection work those with leakage area as per approved method statement and by approved material. Once injection work is done, another RFI will be submitted for inspection. During Daelim warehouse surveillance, it was observed that all instrument (Level transmitter) stored outside in direct sun light and no preservation. As per project preservation plan, all Instrument shall be kept in in-door and temperature shall be controlled to prevent the condensation of humidity. This violates Preservation Plan, doc. no. A554-E-103-CM-GEN-PLN- 002. All Instrument material such as transmitter and other devices for instrumentation shall be kept indoor to avoid direct sunlight exposure, playdown personnel are now aware and corrective action is done by means of training anf reminders at tool box meeting (daily) During inspection at Cooling Tower Basin area (PS-V7) El-19530, west side of the cooling tower for structural padding elevation, it is observed the anchor bolt for column support for 2" piping were bent damage and mismatching with the column nameplate holes. It is a violation as per A554- E-103-QA-GEN-PRO-012 Para. 7.1.3, 7.1.4, 7.1.5. Daelim should also attach survey reports to the mech (structural RFI) for anchor bolts syrvey from subcontractor surveryor. Ref.: A554-E-103-QA-GEN-PRO-012. para. 7.1.14, 7.1.15. During surveillance at East-West main pipe rack near in the Furnace Area, it was observed the following violations: 1. The LV power cable was damaged the outer insulation and other are twisted due to improper cable pulling activities. This violates schedule "Q" attachment IV, sec. 3.2. 2. The cable tray splicing joint was already deflected during cable pulling activities. This violates NEMA VE2, sec. 4.2.1. Subcontractor: 1. It is investigated and the damage portion of the cable will be repair and also cable. 2. Tray splicing joint, the deflected part will be repaired as per repair procedure. NCR was issued to Daelim Construction team. On inspection of process condensale. Shipped tower (T1510) internals, found that super-heated steam inlet (A2-24") pipe is not rested on the support. A gap of approx. 15mm is having between the pipe and support. This may have as adverse impact on the process functioning of the equipment as the feed pipe is subjected to super heated steam flow causing the material expansion contraction and mechanical vibration during operation aslo full load and acting directly on one side of its bolted flange. An Engineering/Desing solution required. Ref: 115105-D003, RT 5093-01, Para 14 (D). PN: For conduits (EMT) installation, Contractor is advised not to or prevent installing it in reverse way or having a more 2 (90 deg. Bend). There is a lot of way to avoid this type of method as much as possible not do any installation that will need a pullbox. Contractor Engineering will submit to company RFV. During time of surveillance and inspection, it was observed that Contractor/Subcontractor installed wrong tie for cable protector of tray. According to standard, all the cable shall be fasten with nylon coated 316 SS tie but Contractor/Subcontractor installed pre-coated tie instead of nylon coated ss tie. This violates project specification RT6E-802-01. Subcontractor: Asyad, Daelim and Sadara PMT agreed that these cable tie are being installed are temporary, just to continue the site work especially cable pulling when availability of SS cable tie will be replaced. During time of inspection, it was observed that Contractor/Subcontractor installed improper nut & bolt in open channel tray, instead of silicon bronze, Contractor installed not dip galvanized. This violates project specification RT6E-0802-01. Contractor: 1. RFV was officially asubmitted on Feb 19, 2014 regarding the usage og HDG Bolts & Nuts. 2. Contractor Receives the RFV with no comments regarding the usage of HDG on March 22, 2014. Missing CFSD in Operator building. It was observed in Operation building G-1122 that combination fire/smoke dampers are missing in air ducts penetrating fire rated walls electrical roo & communication room. This deviated Company requirements as follows: -RT52-5000-01 sec. 9.16Pro FD or CFSD at all duct penetration of fire rated walls; -RT52-5000-01 sec. 6.2.4-Provide CFSD for duct penetration in 2 hour fire rated wall (Elec) -RT-SAES-T-916, sec. 4.4.2. Telecommunication room shall have a minimum of one hour fire rated walls. Provide the required FD or CFSD which ever is applicable and correctly identified in the drawings. Contractor: Daelim Engineering dept. updated new revision of IFC in operator building G-1122 which are mentioned the CFSD or FD in Electgrical room and communication room. IFC no. A554- E-103-HV-DWG-A30-041, Rev. 6. attached. Incorrect VAV heater capacity. During MRI for VAV & CAV for operator building G-1122, it was observed that VAV-002 & VAV-006 heating capacities are not compliant to equipment schedule A-554-E-103-HV- DWG-A30-013. Design Airflow/Heater: VAV-002, 120lps/3kw but actual Airflow/Heater is 120lps/5.5kw and VAV-006, 131lps/3.2kw but actual is 131lps/3 kw. Daelim HVAC Engineer and Material vendor was responsed regarding raised violation, there no problem about the heating capacities for the materials VAV-002 and VAV-006 SADARA PID Agreed installed VAV with 5.5 KW heater & communication room which has a higher heating load. Contractor proceeded with water filling and hydro test without closer of punch A Test package no. 1621- 01-HT-030, required PWHT has not been performed on support S13 (Dwg. No. (C016103H1A-P-131002- 02) Violating SADARA RT8S-6500-01 Para. 8.11 and ASME B31.3 Para. 345.2.2 (b) requirements. Contractor: Company has reviewed the requirement of the PWHT for this specification line class it was agreed and confirmed by Company that PWHT is not required for such of saddle support pads. Page 50 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 30, 2014 DUE DATE Issued corrective action to Company Target Date S/N LBE NO. PID SUBCON/ CONTRACTOR VAF / PN LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason Company comment Approved Close LBE by Company STATUS CONTRACTOR'S CORRECTIVE ACTION PLAN LBE-DLM-MECH- 485 MR. GLENN DAELIM VAF 3 MECH Hvac 23-Feb-14 26-Feb-14 13-Apr-14 14-Apr-14 Closed LBE-AMA-MECH- 486 MR. GLENN AMA VAF 3 MECH Hvac 23-Feb-14 26-Feb-14 20-Apr-14 20-Apr-14 Closed 38 LBE-DLM- ELECT-109 MR. FILOMENO DAELIM (Enginnering) VAF 3 ELECT Engineering 23-Feb-14 26-Feb-14 25-Feb-14 Open LBE-KCC-CIVIL-244 MR. GERALD KCC VAF 1 CIVIL Civil 23-Feb-14 26-Feb-14 26-Feb-14 01-Mar-14 Closed 51 LBE-DLM- MECH-487 MR. GLENN DAELIM (Enginnering) VAF 3 MECH Hvac 24-Feb-14 27-Feb-14 15-Jul-14 20-Jul-14 Closed LBE-KCC-MECH- 488 MR. GLENN KCC PN 3 MECH Quality Management 24-Feb-14 27-Feb-14 04-Mar-14 10-Mar-14 Closed 39 LBE-DLM- MECH-489 MR. SAYED DAELIM (Construction) VAF 3 MECH Piping 25-Feb-14 28-Feb-14 Open 40 LBE-DLM- MECH-490 MR. KURIAN DAELIM (Construction) VAF 3 MECH Mechanical (Equipment) 25-Feb-14 28-Feb-14 Open LBE-TCC-MECH- 491 TCC VAF 3 MECH Mechanical (Equipment) 25-Feb-14 28-Feb-14 19-Mar-14 23-Mar-14 Closed LBE-TCC-MECH- 492 TCC VAF 3 MECH Mechanical (Equipment) 25-Feb-14 28-Feb-14 11-Mar-14 11-Mar-14 Closed LBE-ARCC-MECH- 493 MR. NASSAR ARCC VAF 3 MECH Quality Management 25-Feb-14 28-Feb-14 04-Mar-14 12-Apr-14 Closed LBE-AMA-CIVIL-245 MR. GERALD AMA VAF 2 CIVIL Civil 25-Feb-14 28-Feb-14 29-Mar-14 03-Apr-14 Closed LBE-ARCC-MECH- 494 MR. NASSAR DAELIM VAF 3 MECH Coating/ Painting 27-Feb-14 02-Mar-14 13-Mar-14 12-Apr-14 Closed LBE-TCC-MECH- 495 MR. NASSAR TCC VAF 3 MECH Coating/ Painting 27-Feb-14 02-Mar-14 04-Mar-14 12-Apr-14 Closed LBE-DLM-ELECT- 110 MR. MARK DAELIM VAF 1 ELECT Electrical 27-Feb-14 02-Mar-14 01-Mar-14 30-Mar-14 Closed No hose bib for AHU & ACCU. During surveillance in MCC/PIB G-1120 & G-1121, it was observed that no hose BIBS were provided for AHU's and ACCU's. This violates Company requirement RT5S-5050- 01, section 1.5.1.11. A service water or portable water hose BIB with vaccum breaker shall be provided within close proximity (not to exceed 3M or 10 feet) of HVAC equipment that require periodic washing. Comply hose BIB requirement. Contractor: Attached Reply Came from Daelim Regarding the Raised Violation of Hose BIB in Mechanical Room. Cleanout without access and trap without vent. It was observed in O.B G-1122 that cleanout has no access and trap without vent. This violates plumbing code as follows: -IPC. Sec 708.9 cleanouts on 6-inch and smaller pipes shall be provided with clearance not less than 18 inches for rodding. -IPC sec. 708.10 Access shall be provided to all cleanouts -IPC 901.2.1 every trap and trapped fixture shall be vented in accordance with one of the venting method specified. Subcontractor: Isometric Drawing was Submitted to DAELIM Engineering and was approved wherein no cleanout provided for the fixture (Service sink) See Attached Drawing - Accepted RFI for these issued: MFC-DLM-AMA-B-038 - Vent was already provided on the trap fixture (Service Sink) During site surveillance at substation G-1120, it was observed that the cable tray installation is close to the inter-pacing relay panel tag no. IRP- 103J101 & IRP-103J102. Actual vertical distance from equipment to the bottom of the tray is 300mm. This violates as per G7C-0321-01, para 3.12. Contractor: It was discussed to Engineering and feedback will be followed-up regarding the issue. -> Discussed and agreed with Company. NCR was issued to Daelim construction team. Inspection for the bolt torquing for internal panels for tower 1510, the subcontractor is found using uncalibrated torque wrench. All the instruments and measuring equipment used at site should be calibrated and coumented. Subcontractor: Calibration Certificate provided It has been noticed that field coating activities has been covered by unqualified coating inspector. This is violation of Schedule Q and ITP. Subcontractor: ARCC submitted the CV of Painting Inspector Mr. Posadas last 23 Feb. 2014 with transmittal # 1235, awaiting for Interview and approval. During surveillance and monitoring inspection at Cooling Tower (West Side Portion), we have noticed chipping and preparation works at six (6) pedestals and some reinforcing bars has been cut due to re- installation of anchor bolts for the said pedestals. In this regards, Contractor was advised to investigate this chipping and preparation works and also corrective action concerning this issue for proper implementation. Subcontractor: has been executed the work as approved shop drawing which is signed by Daelim Engineer, corrective action has been taken as follows 1. Cut/Chip the concrete up to required depth to fix the anchor bolt. 2. additonal reinforcement is approved shop drawing. 3. contractor has submitted the RFI for Inspection and it is inspected and approved. During pre-punching for package no. 1652-00HT-007 (T) line No. P- 172601-18"-4C01, it was noted that water filling started in the line without internal cleaning & flushing. This violates against G4S-G421-02, para. 4.9. Material receiving inpsection of overhead crane hoist for common compressor having a name plate no. CR 1695 with capacity of 100/15 ton double girder top STAHL manufactured, has damaged rolly plat form. Which may have occurred due to improper handling and the rail on which the crane will be mounted and rolled is corroded. Painting is required on all surfaces. Other than trail-trolly wheel contact surface as per the manufacturer drawing. Ref. RTBICS, para. 2.2.11, 2.4.1, A554-E-103-QA- GEN-PRO-035, para. 8.1.9, 8.1.11, 8.2.6 & 8.1.11. During surveillance, it is noticed that near C2 Splitter Goulds manufactured pump P2122A, P2215 A/B were found with an oil leakand without cleaning of mud due to rain on the skid top. Preliminary inspection of the pump and its parts show oil leak is from oil level indicator bottom. Further investigation need to be done after complte removal of the spilled oil on skid to ensure that there is no oil from any parts of the pump. Other corrective actions are required from Daelim. Ref. RT61CS Para. 2.5.3.b , Para 2.6.b.1 , 2.6.b.c Subcontractor: All leak had been recrificed. With reference ro RFI # MFC-DLM-KCC-CI-6001 & 6002 Local Platform and T-Support, it was noticed during inspection that some pedestals for "HILTI ANCHORING" are not conform to latest IFC drawings. In this regards, Contractor was advised to check internally/properly based on the approved DWG. The anchoring & general cleaning of holes. Prior to invite SQIT in order not to hamper inspection schedule. Please note that this RFI was rejected. Subcontractor: Relocation of drilling hole was done to get the required depth. Non-compliant inertial filter housing and bleed fan. Supplied inertial filters manufactured by Filtrotechnical Italia (3 nos.) are not compliant to project specifications RT5S-5035-01 sections 2.4.1.3 & 2.2.1.1 (for G-1120/E- 1121/G-1122): Filter housing is made of corten steel instead of the required stainless steel or high density polypropylene. Bleed fans by CIMME are manufactured and tested per ISO Standards instead of AMCA99 & AMCA 210. Submit RFV for SME approval. Contractor: RFV was already submitted to Sadara and found approved with comment. Incomplete subcontractor QC coverage of UG-RTR Piping activities- it has been observed that UG- Piping activities such as gasket verification, bolt tightening and hydrotesting are not covered by KCC UGP QC Inspector. This violates schedule Q, sec. 5.9. Contractor's quality personnel will be dedicated to perform and complete all quality functions as described in this schedule Q. Subcontractor: UG-Piping Inspector was informed to be full time on site during inspection and all related activities regarding UG-Piping. Mr. Denny villareal approved Hydrostatic testing coordinator will take care all inspections related to UG-Piping activities such as gasket verification, bolt tightening and hydrotesting. Mr. Rafique will take care of the laminiation. During surveillance, it was observed during internal transportation of piping from storage yard to site (spent caustic area) by truck, there are no means of protection such as rubber pads provided between the coated pipes & side U-channel. This leads to friction and damage to the coating film. Subcontractor: Construction and Piping team are advised to take special care while transporting coated pipes to site. All repairs and damages covered during transportation and handling shall be repaired using Sadara approved Field Tou-up Procedure. A554-E-QA-GEN-PRO-036. during routine inspection on surface preparation of pipes weld joints it has been noticed that TCC subcontractor using power wire brushes for surface preparation. The area of weld joint is more than 25 sq. cm., this being a violation of SADARA requirement and lat letter # MFC-T-CJ-DJ-PI-0799 which issued by SADARA "Power wire brushes or sanding dics when used alone may not produce the required surface profile to an unacceptable level.: SUrface preparation was done for 16 weld joints on to 30" diameter. Weld joints found in line ID C016103W4A-P-241012-01 & C016103W4A-P-242009-01 30" diameter. Subcontractor: From Mar. 3, 2014 onwards TCC shall provide full-time QC for site activities. This RFI was rejected by Sadara. On Mar. 3, 2014 TCC again done the Surface Preparation for weld joints with bristle blast and accepted by Sadara. Note: RFI No. MFC-DLM-H-L-733, 734 are attached. During site testing, it was noticed that the Contractor was conducting impedance testing for transformer without an approved procedure which is a violation as per Schedule Q Attachment IV Sec. 7.1 Contractor: Procedure will be revised as it was approved already to include impedance testing. Page 51 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 30, 2014 DUE DATE Issued corrective action to Company Target Date S/N LBE NO. PID SUBCON/ CONTRACTOR VAF / PN LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason Company comment Approved Close LBE by Company STATUS CONTRACTOR'S CORRECTIVE ACTION PLAN 46 LBE-SEN- ELECT-111 MR. MARK SENDAN VAF 1 ELECT Electrical 01-Mar-14 04-Mar-14 03-Mar-14 30-Jul-14 22-Jul-14 Closed LBE-TCC-MECH- 496 MR. NASSAR TCC VAF 4 MECH Quality Management 01-Mar-14 04-Mar-14 19-Mar-14 12-Apr-14 Closed LBE-AMA-CIVIL-246 MR. GERALD AMA VAF 2 CIVIL Civil 02-Mar-14 05-Mar-14 02-Apr-14 24-Apr-14 Closed LBE-AMA-CIVIL-247 MR. GERALD AMA VAF 2 CIVIL Civil 03-Mar-14 06-Mar-14 29-Mar-14 03-Apr-14 Closed LBE-TCC-MECH- 497 MR. NASSAR TCC VAF 3 MECH Quality Management 03-Mar-14 06-Mar-14 10-Mar-14 12-Apr-14 Closed LBE-PSCL-MECH- 498 MR. NASSAR PSCL VAF 3 MECH Tank 04-Mar-14 07-Mar-14 20-Apr-14 Closed LBE-DLM-ELECT- 112 MR. FELOMINO DAELIM (Construction) VAF 1 ELECT Material 04-Mar-14 07-Mar-14 06-Mar-14 12-Jul-14 Closed LBE-SEN-ELECT- 113 MR. MARK SENDAN VAF 1 ELECT Electrical 05-Mar-14 08-Mar-14 06-Mar-14 30-Mar-14 Closed 41 LBE-DLM- ELECT-114 MR. MARK DAELIM (Construction) VAF 1 ELECT Electrical 06-Mar-14 09-Mar-14 08-Mar-14 Open 42 LBE-DLM- MECH-499 MR. HARIKUMAR DAELIM (Enginnering) PN 3 MECH Engineering 06-Mar-14 09-Mar-14 Refer to Company LBE additional comments Info 43 LBE-DLM- MECH-500 MR. HARIKUMAR DAELIM (Construction) VAF 3 MECH Mechanical (Equipment) 06-Mar-14 09-Mar-14 Open LBE-PCMC-MECH- 501 MR. AMIN PCMC VAF 3 MECH Quality Records 06-Mar-14 09-Mar-14 08-May-14 13-May-14 Closed LBE-KAF-MECH- 502 MR. NASSAR KAEFER VAF 3 MECH Fireproofing 06-Mar-14 09-Mar-14 09-Apr-14 08-Jun-14 Closed LBE-DLM-INST-001 MR. PERVEZ DAELIM (Construction) VAF 1 INST Instrumentation 06-Mar-14 09-Mar-14 05-Jun-14 05-Jun-14 Closed LBE-AMA-CIVIL-248 MR. JERRY AMA VAF 2 CIVIL Civil 08-Mar-14 11-Mar-14 29-Mar-14 01-Apr-14 Closed During monitoring & surveillance activities at cooling tower basis "Cell #7" concerning leak test, height of water is only 150mm from top of slab. It was noticed that some portion of Mid-Wall-6 (North side) having visible leak. In this regards, Contractor is advised to investigate the said visible leak and take remedial action on the issue. Subcontractor: has been rectify the leave portion by using approved injection material, work has been done executed and inspected by Daelim and Company Inspector. The RFI reference No is MFC-DLM-AMA-CI-6618 It has been observed that KCC Coating Inspector not available during Inspection activities. As per inspection and test plan and schedule Q, Coating Inspector should attend all application activities and inspection time. Inspection level for Subcontractor is hold point for all activities. Subcontractor:Tape wrapping and holiday test inspection is not KCC scope. This is the scope of TCC. KCC is only prepairing the RFI. In the absence of TCC Inspector, Daelim inspector attended the activity and performed the inspection and was found acceptable. During inspection time for RFI # MFC-DLM-PS-H-0075 on spent Caustic storage tank (V-500A), it has been noticed the dimensions of Arabic letters doesn't provided in approved IFC drawing. Furthermore, letters (Arabic & English) degree intervals doesn't meet Sadara specification (RT9S-2500-01 section 8) The degree intervals required between every letter ( Arabic & English) is 90 deg. around the tank. The violation also repeated in Tank V-500B. This violation has been logged for information and corrective action. Contractor: Drawing were Revised to mention the required dimensions & informations RFI was raised for the activity and accepted by sadara. During routine site visit at the east of debutanizer structure area, it was noticed that the Contractor already pulled a cable for street lighting without the usage of PVC bushings ar all conduit termination which is a violation as per NEC Article 352.46. Subcontractor: Installation done as per IFC Drawing and Conduit Exceeded more than 150mm the same will go inside the electrical street lighting pole. During surveillance, it has been noticed that TCC Subcontractor Inspector unavailable at site during surface preparation. Weld joints found in line ID C016103W4A-P-241012-01 & C016103W4A-P-242009- 01 30" diameter. Surface preparation was done for 16 weld joints in the absence of complete for Subcontractor inspector. Note: Subcontractor inspector name is Jishnu N.P. ; RFI # MFC-DLM-TCC-H-L-714 & MFC-DLM-TCC-H- L-715 Subcontractor: TCC has three (3) Painting and Coating Inspectors approved by SADARA. No more issue for Paitning shortage at TCC. With reference to RFI # MFC-DLM-AMA-CI-6542 during inspection for metal door frame & leaf (pre- installation), we have noticed that no "label for fire rating" both door frame & leaf. In this regard, Contractor was advised to investigate why they delivered at site without this fire rated "labels" & not conforming to our requirement and should take corrective action concerning this issue. Please note counter check also some door frame and leaf (This RFI was rejected). Subcontractor: Regarding the Lable for fere rating subcontractor already contact to vendor, as per vendor those door cannot be fere rated due to over size, and base an approved shop drawing its mentioned. During surveillance, it has been observed that aluminum jacketing has been damaged for E-2050, D- 171B, D-1914, E-0235 and E-2051 during construction activities and erection of scaffolding. Furthermore, EQ # E-2051, cladding has been damaged due to downfall of the cement on the top of equipment during fireproofing application activities. Logbook entry has been logged for root cause analysis and corrective action. Contractor: all overspray were removed equipment tags area cleaned and repair was done for damaged areas, damages was not covered due to fireproofing activities KAEEFER has verified all stated equipments and found no damaged caused due to fireproofing activity. During Material Receiving inspection of Panel, it was observed that 3 nos. of Instrument Cabinet I/O Grd found damaged and not fixed properly and one panel has damage. This violation to project specification and schedule "Q", attach. IV, Sec. 1.1. and G6A-0041-00 sec. 61.5.4.2. Contractor requested to take a preventive action plan. Contractor: 3 number of instrument cabinet which are having problem in inspection have been done with RFI No. INST-022-023. With reference to RFI # MFC-DLM-AMA-CI-6571, it was noticed that there is no anchor bolt or plate embedded on the sliding of the pedestal. The civil dawing shall be reviewed in coordination with mechanical installation drawing as it is always required that a plate or anchor bolt is necessary to limit any movement during the production phase. This RFI is rejected unless design can prove that no anchor bolt or plate is necessary. Subcontractor has been Executed the work as per civil IFC drawing there was conflict between mechanical and civil IFC Drawing, Subcontractor confirm with Mechanical team and rectify the anchor bolt as per mechanical IFC Drawing, Executed work is Inspected and approved the RFI reference No is MFC-DLM-AMA-CI-6570-0A and 6571-0B PN: Gas Furnace: Area furnace box sleeves are not centered/defected as per actual arrangement drawing A554-7-103-MB-DWG-MB-2-002. It is string with radiant coil which will be cause of damage during the operation. Daelim shall propose appropriate method to fix the discrepancies with Engineering approved method.
Furnace pipe rack observed that weld joint were distorted and flange face is off-set up: 10mm due to improper fabrication method and welding technique on BFV-123501-6P007. Violation of Fabrication drawing and procedure A554-E-103-QA-GEN-PRO-046. It is found that PCMC Supervisor and DAELIM Inspector signed the blank report for internal cleaning enclosed with one test package for Mar. 8, 2014 on dated Mar. 6, 2014, violating and ignoring the inspection requirements. Daelim quality management should implement the Company standard's minimum inspection requirements. Ref.: Sch. "Q" attac. 0, para. 3.7, 7.2, attch. IV, para. 3, 4. Subcontractor: PCMC supervisor filled the report after confirmation, now every format fill first the signature. We have now the quality system as per approved. Now it is made sure that all the reports must be filled at site. Noreports will be filled-up after work completion. During material receiving inspection of RFI No. MFC-DLM-RYD-EL-075, it was observed the following violations: 1. LV cables are not new and these cables were taken from subcontractor. This violates as per schedule G. para. 2.1. 2. LV cables have no markings for flame retardant in the outer sheet of the cable. This violates as per RT7D-0430-00, para. 1.7 3. The cable reels have no stainless steel tag which is violation as per RT7D-0430-10, para. 5.3. Contractor: Engineering/Construction was already informed with this discrepancies. As per Engineering, RFV already submited to Company During routine site visit, it was noticed that the Contractor installed PVC conduit for the protection of bare copper grounding conductor for lightning protection system but uses as unapproved fittings which is a violation as per G7-C-0311-03, section 1.4.1 at operator building G-1122. Contractor: Subcontractor already instructed to remove the un-approved materials and replaced with the approved one. Action has already been taken. During routine site inpsection, it was noticed that the Contractor installed lighting fixtures and used the channel tray as a support inside operator building and battery room of substation G-1121. This is a violation as per G7C-0321-01, section 1.2 and RT7C-1822-06. Subcontractor: The installation done as per IFC drawing but the same has been conveyed to Engineering, waiting for reply. After Enginering decision, it will be rectified accordingly. Contractor: Contractor submits TM/RFC to Company. RFC was acknowledged already by the Company and approved buy SME has comments to change the revision of RFV. Page 52 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 30, 2014 DUE DATE Issued corrective action to Company Target Date S/N LBE NO. PID SUBCON/ CONTRACTOR VAF / PN LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason Company comment Approved Close LBE by Company STATUS CONTRACTOR'S CORRECTIVE ACTION PLAN 58 LBE-KCC- CIVIL-249 MR. JERRY KCC VAF 2 CIVIL Civil 09-Mar-14 12-Mar-14 29-Apr-14 Closed 50 LBE-DLM- CIVIL-250 MR. GERALD DAELIM (Enginnering) VAF 2 CIVIL Civil 09-Mar-14 12-Mar-14 02-Apr-14 Included in the Punchlist 22-Jul-14 Closed 51 LBE-AMA- CIVIL-251 MR. GERALD AMA VAF 2 CIVIL Civil 09-Mar-14 12-Mar-14 29-Mar-14 25-Jul-14 Included in the Punchlist 22-Jul-14 Closed LBE-DLM-ASYD- INST-002 MR. SHABIRUL ASYAD/ DAELIM VAF 1 INST Instrumentation 09-Mar-14 12-Mar-14 14-Mar-14 09-Apr-14 Closed LBE-DLM-MECH- 503 MR. GLENN DAELIM (Construction) VAF 3 MECH Plumbing 09-Mar-14 12-Mar-14 01-Jun-14 21-Jun-14 Closed 47 LBE-TCC- MECH-504 MR. KURIAN TCC VAF 3 MECH Mechanical (Equipment) 09-Mar-14 12-Mar-14 13-Apr-14 26-Jul-14 23-Jul-14 Closed 44 LBE-DLM- MECH-505 MR. KURIAN DAELIM (Procurement) VAF 3 MECH Material 09-Mar-14 12-Mar-14 Open LBE-TCC-MECH- 506 MR. KURIAN TCC PN 3 MECH Mechanical (Equipment) 09-Mar-14 12-Mar-14 15-Apr-14 15-May-14 Closed 45 LBE-DLM- MECH-507 MR. KURIAN DAELIM (Construction) VAF 3 MECH Mechanical (Equipment) 09-Mar-14 12-Mar-14 Open LBE-DLM-MECH- 508 MR. KURIAN DAELIM (Enginnering) PN 3 MECH Engineering 10-Mar-14 13-Mar-14 12-Mar-14 03-Jun-14 Closed LBE-AMA-CIVIL-252 MR. GERALD AMA VAF 2 CIVIL Civil 10-Mar-14 13-Mar-14 29-Mar-14 01-Apr-14 Closed LBE-KCC-CIVIL-253 MR. GERALD KCC VAF 2 CIVIL Civil 10-Mar-14 13-Mar-14 02-Apr-14 02-Apr-14 Closed LBE-AMA-CIVIL-254 MR. GERALD AMA VAF 2 CIVIL Civil 10-Mar-14 13-Mar-14 24-Apr-14 26-Apr-14 Closed LBE-DLM-MECH- 509 MR. KURIAN DAELIM (Enginnering) PN 3 MECH Engineering 11-Mar-14 14-Mar-14 12-Mar-14 03-Jun-14 Closed 46 LBE-DLM- MECH-510 MR. KURIAN DAELIM (Mat. Dept) VAF 3 MECH Preservation 11-Mar-14 14-Mar-14 23-Mar-14 Open 47 LBE-DLM- MECH-511 MR. HARIKUMAR DAELIM (Enginnering) VAF 3 MECH Engineering 12-Mar-14 15-Mar-14 Open During material receiving of Back wash water pup (P 0589) by powerking system found an instrumentation part attached to the seal reservoir is being damaged by it support attaching it to the reservior by welding. The damage may havehappened due to poor handling and preservation. This is violation as per A554-E-103-QA-GEN-PRO-034, Para. 8.1.3 & A554-E-103-QA- GEN-PRO-035, Para. 8.2.1.11 & 8.11. PN: During surveillance at site for T-2220 Downcomers Stiffner without holes were found drilling without proper safely measures abd with CS clamps (scaffolding clamps and pipes). This may cause condonation of the SS stiffeness. Corrective measures required from the Contractor. Subcontractor: Noted I will chck with equipment inspector and let you know regarding these issue During tray leveling inspection for the tower T1510, it is noticed that tray no. 2with downcommer pannel (EB-102) is having a scattered corrossion on its surface. Corrective ation is required. Ref. RTSS-5093-01, Para. 1.37, 1.3.8., RT 6-1CS. During site surveillance, it was observed Contractor installed Channel cable tray using SS nuts and Bolts, as per standard RTGE-0802-01 required silicon bronze nuts and bolts. This is violation against standard RTGE-0802-01 Contractor: submitted RFV to Company for review regarding usage of HDC for channel tray as per transmittal no. MFC-T-D-CJ-IC-1185, dated 19 Feb. 20143. During MRI of Fire protection materials, it was observed that Stud Bolts have developed corrosion due to damaged galvanized coating by cutting ends ad no traceability to comply specification for low alloy carbon steel bolting G45-3251-00, sec. 1.1.1 ASTM A 193 grade B7/B16/ ASTM A 320 grade L7 and ASTM A 194, grade 2H/4/7 plus S4, sec. 1.2 The marking shall be done by means of die stamping. Contractor:All the rejected stud bolts which are not completed were replaced with new studs. During pad-leveling inspection at Cooling Tower and ground flare area, the foundation bolts for T supoort and column support of ground flare wind fence found bented. At ground flare wind fence column no. 13 from south to north of the east site found bented and later it was heated to make it straight (plates available). These are violations as per ALSCC303 para. 7.5.1. A554-103-QA-GEN-PRO-001 Subcontractor: There was cicil problem, TCC construction group fix the issue. Pictures are attached. Need hardness test. With reference to RFI-MFC-DLM-KCC-CI-16134. Mixing, placement and sampling inspection for Epoxy grouting of Cooling Tower Pump (P-0901B) First part (SKID), it was noticed that the epoxy grouting procedure has not been complied. Instead of pouring the epoxy in one (1) direction, the other side of the pump was also poured, thus, creating a void in the middle of the skid. The Contractor shall demonstrate further on how to totally fill the inside of the skid prior to procceed grouting of other portion. Subcontractor: The materials were already replaced with EP 150 which is more flowable compaired to EP 160 which was used on that grouting. The hollow portion will be filled when the next day will be poured. With reference to LBE #246, dated 2 Mar 2014, during surveillance inspection & monitoring activities, it was found out the door & frames without fire rated labels: a. Substation G1121 SD5 at switchgear room; b. Substation G1121 SD6 at mechanical room; c. Substation G1120 SD2 at Battery room; d. substation G1120 SD4 at Switchgear room e. Substation G1120 SD5 at Mechanical room Regarding the Fire Rated Labels, as per vendor those door cannot be fire rated due to over size, please see attached approved door and frame schedule. During surveillance& monitoring activities at substations, it was observed that mostof the internal door & frames for substation G1120 & G1120 are already installed without providing RFI to the Company first. This violates (as per ITP) SMIC-M-1047. Contractor is advised to take corrective and Subcontractor Submitted the RFI for the Door Installation and some door already Inspected, Remaining Installed door have Comments, Once all Comments will Rectify Sub Contractor will raise the RFI for Inspection, Inspection Door RFI Reference is MFC-DLM-AMA-CI-6031- During inspection at Cooling Water Tower observed that partition walls grinder beam (intermediate) obstructed or on cross on walkway platform. Daelim/SPIG shall redesign the structural arrangement and provide proper access without any obstruction on walkway and re-evaluate the structural integrity if any significant modification required. Reference to RFI No. MFC-DLM-AMA-CI-6614-0A, during material receiving inspection for galvanized steel angular bars for canopy substation G1120 & G1121, found that one (1) piece of delivered steel canopy was deformed due to handling or delivery discrepancy. Contractor to replace or backload the said material and not to install or not use at site. Regarding Galvanized Steel cannopy which was deformed at site it is already recitified or repair. PN: During the Tray level inspection for the internals of equipment T-1210, it is observed that Seal pan 1st tray support rig and tray # 1 is having a level difference of 14 to 15 (slop) mm toward one side of the Tower. Engineering solution required. Noted: Work will be done accordingly During surveillance at site, it is noticed the pump P2320, C2701, C2711 were found without proper covering and temporary shelter protection over it as these are critical. After Cleaning The Pumps Fix Will be Attached PN: During the internal tray level inspection for the Tower (T-2220) it is observed that Seal pan tray arrangement is not as per the actual orientation shown in the provided tray arrangment drawing. Engineering solution is required. Noted: Work will be done accordingly During surveillance & monitoring activities at operator building along south side "outside area" found out some materials scattered around the building. Contractor is advised to put the materials in the designated area with prooper handling and protection to avoid damaging the items and Contractor to observe proper housekeeping. Subcontractor has taken the action all scattered material already shifted from operator building and the area is clean. It is advised to construction team that not to do same practice in future. With reference to RFI No. MFC-DLM-KCC-CI-6108 & 6109, during material receiving inspection for metal roofing and siding intended for truck loading shelter and lube oil shed, noticed that the materials are not properly protected and poor preservation was observed. Contractor is advised to cover the materials properly to protect from any damage. Materials were already Covered and Protected Page 53 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 30, 2014 DUE DATE Issued corrective action to Company Target Date S/N LBE NO. PID SUBCON/ CONTRACTOR VAF / PN LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason Company comment Approved Close LBE by Company STATUS CONTRACTOR'S CORRECTIVE ACTION PLAN LBE-DLM-ASYD- INST-003 MR. PERVEZ ASYAD/ DAELIM VAF 1 INST Instrumentation 13-Mar-14 16-Mar-14 15-Mar-14 28-Apr-14 Closed LBE-TCC-MECH- 512 MR. SAYED TCC VAF 3 MECH Piping 15-Mar-14 18-Mar-14 19-Mar-14 Closed LBE-AMA-CIVIL-255 MR. GERALD AMA VAF 2 CIVIL Civil 16-Mar-14 19-Mar-14 02-Apr-14 03-Apr-14 Closed 48 LBE-DLM- MECH-513 MR. SAYED DAELIM (Mat. Dept) VAF 3 MECH Material 17-Mar-14 20-Mar-14 Open LBE-KCC-CIVIL-256 MR. GERALD KCC VAF 2 CIVIL Preservation 17-Mar-14 20-Mar-14 02-Apr-14 02-Apr-14 Closed LBE-SEN-ELECT- 115 MR. MARK SENDAN PN 1 ELECT Electrical 17-Mar-14 20-Mar-14 20-Mar-14 31-May-14 Closed LBE-DLM-MECH- 514 MR. SURESH DAELIM (QA/QC) VAF 3 MECH Mechanical 18-Mar-14 21-Mar-14 28-Apr-14 Refer to Company LBE for further comments 03-Jun-14 Closed LBE-DLM-MECH- 515 MR. SURESH DAELIM (Mat. Dept) VAF 3 MECH Preservation 19-Mar-14 22-Mar-14 29-Jun-14 Closed LBE-DLM-TELE-009 MR. RODNEY DAELIM (Enginnering) VAF 1 TELECOM Telecomunication 19-Mar-14 22-Mar-14 29-May-14 01-Jun-14 Closed LBE-KCC-MECH- 516 MR. GLENN KCC VAF 3 MECH UG-RTR 19-Mar-14 22-Mar-14 26-Mar-14 13-Apr-14 Closed 58 LBE-SEN- ELECT-116 MR. MARK SENDAN VAF 1 ELECT Electrical 20-Mar-14 23-Mar-14 30-Jul-14 22-Jul-14 Closed 49 LBE-DLM- CIVIL-257 MR. JERRY DAELIM (Enginnering) VAF 2 CIVIL Engineering 20-Mar-14 23-Mar-14 Open LBE-DLM-CIVIL-258 MR. JERRY DAELIM VAF 2 CIVIL Civil 20-Mar-14 23-Mar-14 01-Apr-14 01-Apr-14 Closed LBE-SEN-ELECT- 012 MR. FELOMINO SENDAN VAF 1 ELECT Preservation 20-Mar-14 23-Mar-14 26-Apr-14 26-Apr-14 Closed LBE-ASYAD-INST- 004 MR. PERVEZ ASYAD VAF 1 INST Instrumentation 20-Mar-14 23-Mar-14 03-Apr-14 08-Apr-14 Closed LBE-KCC-CIVIL-259 MR. JERRY KCC VAF 2 CIVIL Civil 21-Mar-14 24-Mar-14 25-Mar-14 26-Mar-14 Closed LBE-ASYAD-INST- 005 MR. PERVEZ ASYAD PN 1 INST Preservation 22-Mar-14 25-Mar-14 23-Apr-14 07-Jun-14 Closed During inspection, it was noticed that Contractor installed JB not according to Standard & typical drawing, JB supports weld or handrails, which is not allowed. This violates Project Specification G-6A- 0041-00, Para. 61.6.5 & typical drawing G-07C-0326. Contractor to take preventive action, Contractor: Contractor submit RFV to company for review regarding mounting of support for FJB on handrail as per transmittal no. MFC-T-DS-CJ-CI-1243, dated 14 Mar. 2014. During Surviellance at TCC Site Area, It has been observed that rejected fit-up joint was welded without joint preparation for root gap, root face & bevel angle, Line No. 24"-PR-171702-HC35 Joint No. 015. This is Violation against A554-K-PRG-CE-SPC-DES-045 para 5.1, Contractor shall provide corrective action & Preventive action. TCC QC Manager and QC Supervisor Conducted one Tool Box Meeting with TCC Piping and Welding Inspector and strictly inform to all QC Inspector 100% Fit-up Inspection and full time monitoring for Construction Activities. At Building G-1122 (Operator Building) the Opening for Instrumentation route in the telecom outside wall is not allowed as per TIA/EIA 569B Para. 7.11.1 states that the telecommunication room shall be dedicated to the telecommunications function and related support facilities, in RT-SAES-T-916 Para. 4.3.7.1 overhead routing of other utilities through the telecommunications room space shall be avoided to prevent obstruction to communication equipment. Engineering was informed regarding this issue including civil, violation will be updated what is the action of contractor. RFV no. A554-RFV-103-284 was already approved by the Company regarding this violation. Contractor request to Company to close this violation. It was Obsereved that RTR Firewater Piping FW-071282 (HT-010) Near Sump Pit G-1121 was damaged due to excavation this line has been leak tested and passed damaged line shall re-tested after completion of repair to comply G4S-G423-01 Sec. 7 a new test shall be applied after repairs & corrections have been made. The Damaged pipe was already repair, waiting for the hydrotest before backfilling. During Routine Site Visit, it was noticed that the cable tray (HV-27-001) was already reflected due to installation of cable which is a violation as per NEMA VE-2 Section 4.2.1 at E-W Piperack near battery Limit. Contractor: Reply same with LBE No. 115 Company will inform after discussion/rectification has been done. PN: Contractor Shall replace all cable trays with damaged rungs acquired during cable fulling specially by other contractor to avoid delays for the energization of electrical equipments in both substations G- 1120 & G-1121 Contractor: The issue was already addressed to Contraction as it was damaged by other contractor during cable pulling. WRONG PWHT CHART Recorder: During Surviellance Inspection at splitter Pipe rack area, found contractor has been using the wrong PWHT Chart recorder, single point/channel recorder using local PWHT, instead of Multipoint recorder., This PWHT chart are not clearly differentiate each channel/point by use different colored inks or automatic number stamping. this is violation against RT8S-6500-01 Para. 8.16 which states that, " Multipoint chart recorders shall clearly differentiate/identify each channel/point by use different coloroed inks or automatic numbering stamping". ISO Drawing No. N016103V6A-CWS-093032-01, Joint No. FW-01 (PWHT Vendor: M/S AMSYCO) Please find attached approved RFI copy and report copy which is clearly Differentiate each channel by use of different colored inks. Equipment and Materials Improper Preservation: During Surviellance at daelim laydown yard the following violations. 1. All Equipment has not been displayed" maintenance Preservation Log Sheet" as per Preservation Plan. 2. galvanized structural Materials and Coated Ladders Improperly stored on the sand. 3. Many furnace Duct Flanges have not been protected with protected covering or tarps. (see Attached photos), this is violation against preservation plan Document No. A554-E-103-CM-GEN-PLN- 002 Para 2.3, 2.19.16, and 2.5 with reference to RFI # MFC-DLM-AMA-CI-6392A and 6393A, Pre-Installation Inspection (Inner Wall) Prior to Instruction of Insulation board, & Inspection of Metal Track Prior to Installa Gypsum board (Above 1.2 Mts, Heaight) and Wall tiles, @ (Operator Building G-1122) Sample Preparation room, it was observed that no shop DRWG, or connection details, termination for wall tiles installation, in this regards, contractor was advised to submit/provide shop drawing & deatails for the said wall tiles installation for (North & West Side) of Sample Preparation Room. for Proper Documentation and Regarding the Operator Building Sample preparation room subcontractor has already submitted the shop drawing. Shop drawing has been approved by Daelim, Please see attached Approved Drawing. During Valve Receiving Inspection, It has benn Observed that some supplies are Violation DOW Spec for Tagging. According to G4R-7200-01 Each Valve Shall be tagged by vendor with a brass tag with monel wire and crimped with each other onto the wire end to avoid loses of tags, VENDOR NAME: 1. Bonney forged Italy, 2. Pantair Vanessa, 3. Zero Engg., All vendors provided valve tag without the monel crimp sleeve that may cause of lost tag. Contractor: Company accepted Contractor's TM indicating that stainless steel 18 gauge wire and using crimp sleeves of same base netal of wire is acceptable. (MFC-T-CJ-DS-PI-0976) With Reference to RFI # MFC-DLM-KCC-CI-6211 Material Receiving Inspection of Varipanel 65 (VP-65) Metal Deck Intended for Common Compressor shelter, it was observed that during Inspection this materials have no proper cover or protections., In this regards, contractor was advised to take corrective action concerning this issue for proper preservation & material Handling for the said materials. Materials were already Covered and Protected During Site Surviellance at cooling tower piperack it was noticed that contractor use stainless steeel wire instead of nylon coated 316 SS tie, it may damaged the outer sheath of cable, this vioaltion project specification, RT6E-0802-01 & A554-O-PRG-IC-GEN-BOD-003., Contractor Request to take a Preventive action. Subcontractor: Stainless Steel wire @ Cooling tower Pipe rack was already replace with the stainless steel Nylon Coated 316SS Tie, Cable Pulling Inspection it was Already Accepted. Review of RFI # MFC-DLM-KCC-UG-2235, 2227 & 2228, the frequency of test and backfilling and compaction timing are not probable due to location, please provide expalnation and timing each FDT test result. With Reference to the RFI # MFC-DLM-KCC-UG-2235, 2227 & 2228, The testing was done, time to time. (See Attached RFI'S) PN: During Surviellance at Site it was Observed that installed JB in not Protected all the JB is Un- covered, which is not good it may caused damage of junction box will be full of from dust dust, this Violation NEC-110-12 and G-06A-0041-00, Contractor request to take Preventive action. It has been informed to the concerned authorities, they have started the process of covering all the JB's which are not properly covered in uncovered state. Now, it is completed all junction and also covered. It was notice that during inspection at G1120 and G1124 Paving Area, the slope design of the paving is not in accordance with the project specification RT2S-2700 Section 8. also the actual elevation of the existing paving is not in accordance with the design. As discussed with Company PMT, Non-process area can be less than 1% slope it was noticed that in the drawing of pump FDN, details (A554-E-103-CV-DWG-C30-373 Rev. 3B) the grout specified the drawing is non-shrink grout, this is a violation of RT5S-5311-02 Section 2.3 status "Epoxy Grout Should be used to grout all rotating equipment covered by this specification" and RT5S- 5303-01 Section 1.2 Drawing was Revised, those Epoxy grout installed at non shrink grout. During Site Surviellance Inspection of Power Transformer Tag # TR-103 G101A & TR-103 G101B at Substation G-1120, it was observed that the transformer main tank oil pressure gauges are having low gas pressure. This violates as per contractor preservation plan Doc. No. A554-E-103-CM-GEN-PLN- 002. Para. 2.8 (e) & Schedule Q Attachement IV Para. 6 Power Transformer with A Tag TR-103G101A/B of Substation G-1120 were now purged/Pressurized with Nitrogen (N2) Monitoring for the establishing of pressure shall be observed Page 54 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 30, 2014 DUE DATE Issued corrective action to Company Target Date S/N LBE NO. PID SUBCON/ CONTRACTOR VAF / PN LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason Company comment Approved Close LBE by Company STATUS CONTRACTOR'S CORRECTIVE ACTION PLAN 60 LBE-AMA- CIVIL-260 MR. GERALD AMA VAF 2 CIVIL Civil 25-Mar-14 28-Mar-14 20-Jul-14 30-Jul-14 Included in the Punchlist 22-Jul-14 Closed LBE-DLM-INST-006 MR. PERVEZ DAELIM (Enginnering) VAF 1 INST Instrumentation 26-Mar-14 29-Mar-14 15-Jun-14 16-Jun-14 Closed 50 LBE-DLM- ELECT-117 MR. FELOMINO DAELIM (Construction) VAF 1 ELECT Electrical 26-Mar-14 29-Mar-14 27-Mar-14 Open 51 LBE-DLM- ELECT-118 MR. MARK DAELIM (Construction) VAF 1 ELECT Electrical 26-Mar-14 29-Mar-14 29-Mar-14 Open LBE-ASYAD-INST- 007 MR. PERVEZ ASYAD VAF 1 INST Instrumentation 29-Mar-14 01-Apr-14 09-Apr-14 05-Jun-14 Closed 56 LBE-DLM- CIVIL-261 MR. GERALD DAELIM (Enginnering) VAF 2 CIVIL Civil 30-Mar-14 02-Apr-14 Included in the Punchlist 22-Jul-14 Closed LBE-SEN/DLM- ELECT-119 MR. MARK SENDAN/ DAELIM PN 1 ELECT Electrical 31-Mar-14 03-Apr-14 01-Apr-14 07-Apr-14 Closed 64 LBE-AMA- MECH-517 MR. NASSAR AMA VAF 3 MECH Coating/ Painting 31-Mar-14 03-Apr-14 05-Aug-14 22-Jul-14 Closed LBE-DLM-ELECT- 013 MR. MARK DAELIM VAF 1 ELECT Preservation 31-Mar-14 03-Apr-14 26-Apr-14 26-Apr-14 Closed LBE-KCC-CIVIL-262 MR. JERRY KCC VAF 2 CIVIL Civil 01-Apr-14 04-Apr-14 02-Apr-14 08-Apr-14 Closed LBE-AMA-CIVIL-263 MR. JERRY AMA VAF 2 CIVIL Civil 01-Apr-14 04-Apr-14 28-Jun-14 30-Jun-14 Closed LBE-AMA-CIVIL-264 MR. JERRY AMA PN 2 CIVIL Civil 01-Apr-14 04-Apr-14 05-May-14 05-May-14 Closed 52 LBE-DLM- ELECT-120 MR. MARK DAELIM (Enginnering) VAF 1 ELECT Engineering 02-Apr-14 05-Apr-14 Open LBE-DLM-ELECT- 121 MR. MARK DAELIM (QA/QC) VAF 1 ELECT Electrical 02-Apr-14 05-Apr-14 09-Apr-14 31-May-14 Closed LBE-SEN-ELECT- 122 MR. MARK SENDAN VAF 1 ELECT Electrical 02-Apr-14 05-Apr-14 03-Apr-14 12-Jul-14 Closed LBE-SEN-ELECT- 123 MR. FELOMINO SENDAN VAF 1 ELECT Electrical 02-Apr-14 05-Apr-14 05-Apr-14 28-Jun-14 Closed During Surviellance & Monitoring Activities at Operator Building, It has been observed that mostly of rooms have already installed suspension system and hangers in which some opening for internal wall and penetrating sleeves are not yet repair of retouch. It is Violate also STD G2S-9510-01 Section 3.4 Para 3.4.1 up to 3.4.3, in this regards contractor was advised to take corrective action & Preventive Action concerning this issue for proper sequencing and scheduling of works. Subcontractor: Amana has started the rectifiation work suspension ceiling system and openning work. Amana will submit the RFI room by room inspection. During Inspection at Site in PIB-1121 Operator Building it was observed that contractor Installed ^" Open Channel tray, which is not allowed as per SADARA Specification, Contractor Shall use only 3" & 4" open channel tray, This Violates RT6E-802-01, Contractor Request to Take a Preventive Action. Contractor: Contractor issued RFV for 6" channel cable tray, RFV accepted by Company. During Site Surviellance at Electrical Room Substation G-1120 it was Observed that the cable tray Installation is closed and insufficient clearance to the grounding Busbar, This is Violates as per G7C-0104-00 Para. 5.7 contractor: Discrepancies of Installation with regards to the standards will address to engineering for Clarification and action. NCR issued to Daelim Construction team. The Contractor Stopped Curing of the Ditches at the west side of common compressor area without completing the 7 day requirement specified in RT25-3001-01 Section 9. Para. 9.12 which states not less than 7 days water curing, Please provide Corrective Action to this violation. Subcontractor: Burlap Were already & Contineous the curing. It was Noticed that some existing angle bars for tranch covers at North east Side of Furnace and west side of the flare area open ditches were already corroded, please investigate the coating or the galvanization process as the adjacent location does not show sign of corrosion of the source material, provide corrective action and identified corroded materials. Contractor: Regarding the corroded angle bars, Company has already issued an NCR to Contractor/Subcontractor. With Ref # MFC-DLM-AMA-CI-6999-0A Metal Flushing & Trim Pre-Installation inspection at south & eastside of Sub station Building G-1120 "Roof Slab" we found out that installation of Flashing 5" & not conform to the latest IFC Drawing (as Shown on the detail 1) Drwg # A554-E-G1120-DWG-A03-450 Rev. 3 in this regards, contractor should investigate and take corrective action concerning this issue for proper implementation at site. Contractor: Amana has submitted the shop drawing and approved by Daelim. Contractor shall connect to grounding cable between the apparatus ground bus and the local ground grid as per 67C-0104-00 Section 6.4.1, for switchgears and MCC's at S/S G-1120 & G-1121 Noted: Engineering will be Informed to attest what will be the action. During Surviellance it has been noticed that projecting Steel Item angles embedded plate or gravity angles open ditch was corroded due wrong paint code system, system coating required as per SADARA Specification RT2S- 3001-01 is hot dip galvanizing in accordance with ASTM A123, Grating angles were installed & found in two Locations right now, North East of Furnace # 1250 & North West of Ground Flare area of Piperack, this is for Information and Corrective Action shall be taken by Daelim/Amana Company NCR has been issued to Contractor. Contractor Shall Energized the Space heater for all the Switchgear at substation G-1120 & G-1121 as of now, the space Heaters of these Switchgear are not yet energized which os a violation as per RT-6-1CS Sectionb 2.9.C. Controlling Temperature Inside the Two (2) Substations G-1120 & G-1121 is the main solution by installation Air conditioning Unit (4 Nos) as per construction plans & action, also Please Attached file for the discussion of company & Contractor top Management. During routine site surviellance, it was noticed that the installation of battery disconnect was located outside the battery room which is a violation as per G7C-1816-00 Section 3.11 and NEC Article 480.5. Contractor: Issue Will be addressed to engineering for further assessment regarding this violation. As per Engineering team, it was installed outside the battery room to prevent splashing of electropolyte and same principle of 67C-1816-00, Spec. 6.2 installation. During Site Surviellance at NS Piperack it was observed that 300mm wides cable tray has been damage by Mechanical crane. This Violation Project Specification SCH Q" Attachment IV Para. 5 G-070-0322 - 00, Contractor Request a preventive Action. Subcontractor: The Incharge supervisor in that particular area was already coordinate to the TCC. After completion of job erection, they will rectify the seal cable tray damage. Contractor: Damage cable tray already replaced and inspection has been done. During Surviellance and Monitoring Activities at Sub-station G-1120, it was noticed that contractor was installed "stainless" Steel Gutter & Downspot" at west side wherein the downspot holder and gutter support are galvanized materials, it violates STD RT20-7004-74 Section 5.2.3 Para. 5.2.3.1 States that "Fascia Trim", Flashing and Other exposed metal work should be one of the following: 1. For all now Sxposed uses - 24 ga " Paint Grip" Galvanized Steel. 2. For all Exposed Uses - 24 ga " Stainless steel" and RT2D-7004-04 Section 3.11 Para 3.11.1, in this regards contractor must takes corrective concerning this issue for proper implementation. During Surviellance at Battery Room Substation, G-1120, it was observed that the Battery was energized and the eyewash were using is temporary portable type personal eyewash. This violates as per G7C-1816-00 Para. 6.1.1.3 Contractor: as part of safety first and during pre-commissioning stage personal eyewash has been provided within the vianity and it will be replaced with acceptance eyewash as per specification. During Material Receiving Inspection, it was Noticed that one cubicle was damaged. Contractor shall replace the damage cubicle at its components inside motor control center MCC-103H204 at Substation G-1121. Contractor: Contractor issue to vendor for replacment of damage part in MCC-103H204 -> Replaced with new component During Routine Site visit this morning, it was Noticed that there is no QC Inspector coverage for S/S G- 1121 from the main contractor which is a Violation as per Schedule Q Attachment VI, Section 1.1 Contractor: The Assign QC Contractor QC in G-1121 has been return to day shift schedule. During routine site Inspection that the Contractor Installed clamp for EMT conduit that tdoes not comply with NEC Requirements and not UL Listed which is a Vioaltion as per 67C-0311-06 Section 1.1 Subcontractor: The subjected matter has been informed to construction team, the same will be replaced approved clamp. Page 55 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 30, 2014 DUE DATE Issued corrective action to Company Target Date S/N LBE NO. PID SUBCON/ CONTRACTOR VAF / PN LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason Company comment Approved Close LBE by Company STATUS CONTRACTOR'S CORRECTIVE ACTION PLAN 53 LBE-DLM- ELECT-124 MR. FILOMENO DAELIM (Enginnering) VAF 1 ELECT Engineering 02-Apr-14 05-Apr-14 Open LBE-ASYAD/DLM- INST-008 MR. PERVEZ ASYAD/ DAELIM VAF 1 INST Instrumentation 03-Apr-14 06-Apr-14 28-Apr-14 28-Apr-14 Closed LBE-ASYAD-INST- 009 MR. PERVEZ ASYAD PN 1 INST Preservation 03-Apr-14 06-Apr-14 07-May-14 07-May-14 Closed 76 LBE-DLM- TELE-010 MR. RODNEY DAELIM (Enginnering) VAF 1 TELECOM Telecommunica tion 05-Apr-14 08-Apr-14 09-Apr-14 20-Jul-14 Closed 54 LBE-DLM- MECH-518 MR. SAYED DAELIM (Procurement) VAF 3 MECH Material 05-Apr-14 08-Apr-14 Open 55 LBE-ARCC- MECH-519 MR. HARIKUMAR ARCC VAF 3 MECH Mechanical (Equipment) 05-Apr-14 08-Apr-14 12-Apr-14 Open 56 LBE-DLM- MECH-520 MR. HARIKUMAR DAELIM (Construction) VAF 3 MECH Mechanical 05-Apr-14 08-Apr-14 Open LBE-DLM-TELE-011 MR. RODNEY DAELIM (QA/QC) VAF 1 TELECOM Telecomunication 06-Apr-14 09-Apr-14 09-Apr-14 13-May-14 Closed 80 LBE-DLM- TELE-012 MR. RODNEY DAELIM (Enginnering) VAF 1 TELECOM Telecommunica tion 06-Apr-14 09-Apr-14 09-Apr-14 20-Jul-14 Closed 25 LBE-DLM- ELECT-125 MR. MARK DAELIM (Enginnering) VAF 1 ELECT Engineering 07-Apr-14 10-Apr-14 10-Apr-14 22-Jul-14 Closed LBE-DLM-ELECT- 126 MR. MARK DAELIM (QA/QC) VAF 1 ELECT Qaulity Management 07-Apr-14 10-Apr-14 12-Jul-14 Closed 57 LBE-DLM- MECH-521 MR. SURESH DAELIM (Enginnering) VAF 1 MECH Mechanical 09-Apr-14 12-Apr-14 Open During surviellance at site it was observed that contractor pulled the cable in improper way cable laid on walk way worker walk on the cable & there is no preservation of cable this Violation of Schedule Q" NEC Article 110.12, Contractor request Preventive Action. Subcontractor: Cable was already laid on the cable tray and some area: was already provide a protection cover. Contractor in advised to verified the height of lighting fixtures installed inside the TER at G-1122 operator building, the standard states at RT- SAES-T-916 Para. 4.4.2.12 that the lighting fixtures shall be located at the minimum height of 2.6m from the finich floor. Contractor already issued SQDR to addressed the sub-contractor for verification & Rectification. During review of material test certificate of LTCS Pipes A333 Gr. 6 (PO No. - 100532-B-PIP-0037-01) it is observed that mill certificate does not have the impact test details, this is violation of ASTM A333 Gr. 6 Para. 14 which specifies all materials furnished under LTCS soecification shall be tested for impact resistance at all temp for the respective grade.
During Surviellance at Electrical Room Substation G-1120, it was observed that the power panel and Dry Type Teransformer was installed along with LV Switchgear is forture space for LV Switchgear. This is Violates as per G7C-1811-00 Para. 6.1.2 & 6.1.8 Contractor: Engineering was informed regarding this matter/Issue, company will be informed of contractor action. -> Discussed and agreed with Company. NCR was issued to Daelim Construction team. During Inspection at Operator Building G-1122 it was noticed that contractor installed the conduit & covered by gypsum board prior to inspection of conduit installation. This is violation of Project ITP & Schedule Q" Attach # IV Para. 3.7 & SMITP-J-106-06 Note 3 Contractor Already Provided Photos that conduits are installed as per standard, next time, work will be inspected prior proceeding to the next work. WRONG TEMPERATURE CHARPY TESTED PIPES: The piping Class HC72 and HC35 used pipe Material size NPS 30" and 64" has been charpy tested at 29C (-20F), Instead of (-45C (-50F) at manufacturer Place. Pipe material ASTM A671 GR CC70 CL. 12, S2., This is Violation against piping Material Specification RTIP, HC72-103 and HC35-103, common general note P-LC04PE625, states that charpy Test shall be for -50F (- 45C). Pipe Manufacturer; SEAH Steel Corp, KOREA, MTC No. D20121- 1123-024263(1305656) Dated 21 Dec-12, D201210-1268-020252 Dated 22-OCT-14, Found Heat No. SF23532 (30"), SP36974 (64") Contractor has confirmed to take corrective action at site, remaining available same heat number stock pipes, carry out retest or alternative solution for this vioaltion.
Contractor is advised to follow the correct type of cable runway to be used inside the telecom room as per I.C-038 (See Photos Attached) take note that the (IT) is using chatworth racks therfore it is important to use a cable runway with the same type as chatworth of equivalent. Contractor: This Issue was already addressed to engineering & meeting also, action of EPC will be inform to company. During Routine site inspection, it was obeserved that the contractor already energized the battery at substation G-1121 without the acceptance of the cable power from the battery to the disconnect switch. The power cable do not pass the material receiving inspection and without cable testing which is a violation as per schedule Q" attachement IV Section 3.7 Contractor: Contractor will submit RFV to company for variation of cable's specs, cable was tested in the drum and after cable pulling once the RFV will be approved by the company activities which is covered by this cable shall be closed. -> Discussed and Agreed with Company on the installed cables During routine site visit, it was noticed that there is neither contractor QC nor subcontractor no present QC Witnessing the on-going battery testing at battery room in substation G-1121 which is a violation as per schedule Q Section 1.2 Contractor: If the Activity was filling of battery QC Monitoring only. The assign QC in G-1121 at that date was in night shift thats why one of QC Contractor was temporary assigned during testing in G-1121, April 9, 2014 the assign QC Contractor was already shift to day shift. Observed that ARCC is modify combustion air duct/stack without confirmed support document or approval following discrepancy Noted: F 1240 area, * Duct was damaged due to improper fabrication method * gas was burned by gas cutting flame. DAELIM/ARCC shall propose appropiate corrective action for rectifying the damaged part and replace damaged gasket * DAELIM shall obtain proper approval for rectifying any vendor supplied eqpt. prior to start activity by company, Violation of Sch Q and Material management plan. Subcontractor: ARCC to Rectify this violation as per submitted & Approved method Statement. Attached photo of rectified conbustion duct. Observed the following violation discrepancy 1. Third discharge drum D- 1607 nozzle LIB 2" flange has damaged or distorted and out of squireness due to improper material boundary. 2. Flange space seration damaged on steam vent silencer on F-1170 (1030-SI-117) DAELIM shall verify the extention damage and propose appropraite rectification method to company approval.
At Telecom room building G-1120, G-1121 & G-1122 contractor is advised to provide and installed a # 5/0 AWG ground wire connected to the building ground grid with five(S) meters coiled in the TER and /OR TR, see the Typical drawing for the location of grounding sleeve - A554-F-760-15-DWG-E64-018, IC-038. # 4/0 AWG was already provided for other contractor purposes & as per scope of work. Page 56 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 30, 2014 DUE DATE Issued corrective action to Company Target Date S/N LBE NO. PID SUBCON/ CONTRACTOR VAF / PN LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason Company comment Approved Close LBE by Company STATUS CONTRACTOR'S CORRECTIVE ACTION PLAN LBE-AMA-CIVIL-265 MR. JERRY AMA VAF 2 CIVIL Civil 10-Apr-14 13-Apr-14 24-Apr-14 28-Apr-14 Closed 58 LBE-GACC- MECH-522 MR. KURIAN GACC VAF 3 MECH Mechanical 10-Apr-14 13-Apr-14 18-Apr-14 Open 59 LBE-DLM- MECH-523 MR. KURIAN DAELIM (Procurement) VAF 3 MECH Mechanical 10-Apr-14 13-Apr-14 Open 60 LBE-DLM- MECH-524 MR. KURIAN DAELIM (Enginnering) PN 3 MECH Engineering 10-Apr-14 13-Apr-14 17-May-14 Info 61 LBE-DLM- MECH-525 MR. KURIAN DAELIM (Procurement) VAF 3 MECH Mechanical 10-Apr-14 13-Apr-14 17-May-14 Open LBE-ASYAD-INST- 010 MR. PERVEZ ASYAD VAF 1 INST Instrumentation 12-Apr-14 15-Apr-14 28-Apr-14 28-Apr-14 Closed LBE-ASYAD-INST- 011 MR. PERVEZ ASYAD PN 1 INST Instrumentation 12-Apr-14 15-Apr-14 28-Apr-14 28-Apr-14 Closed LBE-AMA-CIVIL-266 MR. GERALD AMA PN 2 CIVIL Quality Records 12-Apr-14 15-Apr-14 22-Apr-14 05-May-14 Closed LBE-AMA-CIVIL-267 MR. GERALD AMA PN 2 CIVIL Quality Records 13-Apr-14 16-Apr-14 24-Apr-14 26-Apr-14 Closed 76 LBE-SEN- ELECT-127 MR. MARK SENDAN VAF 1 ELECT Electrical 14-Apr-14 17-Apr-14 17-Apr-14 30-Jul-14 22-Jul-14 Closed LBE-SEN-ELECT- 128 MR. MARK SENDAN VAF 1 ELECT Electrical 14-Apr-14 17-Apr-14 17-Apr-14 28-Jun-14 Closed 65 LBE-DLM- ELECT-129 MR. MARK DAELIM (Enginnering) VAF 1 ELECT Engineering 15-Apr-14 18-Apr-14 18-Apr-14 24-Jul-14 Closed- LBE-DLM-ELECT- 014 MR. MARK DAELIM VAF 1 ELECT Preservation 15-Apr-14 18-Apr-14 26-Apr-14 26-Apr-14 Closed LBE-DLM-CIVIL-268 MR. JERRY DAELIM (Enginnering) VAF 2 CIVIL Civil 16-Apr-14 19-Apr-14 28-Jun-14 29-Jun-14 Closed LBE-AMA-CIVIL-269 MR. JERRY AMA VAF 2 CIVIL Civil 16-Apr-14 19-Apr-14 16-Jun-14 17-Jun-14 Closed LBE-DLM-CIVIL-270 MR. JERRY DAELIM (Enginnering) PN 2 CIVIL Quality Records 16-Apr-14 19-Apr-14 08-May-14 14-Jun-14 Closed Despite of Logbook Entry # 263, the Contractor continue to utilize non-galvanized angle frames for the sump located North of D-0950 during Inspection today of paving, this is a violation to RT2S-300-01 Para 8.2.7 which is requires that this item shall be not be dip galvanized in accordance with ASTM A123. The Installed non galvanized angle frames mistake done by the site foreman, subcontractor do agree to not happen again in future, subcontractor has replace the angle frames which is hot dip galvanized. During Surviellance at MFC Daelim Site it is noticed/observed that the dilution steam generator structure, Strcutural Brazing welded to the embedded plate were half/incompletely welded is found at all the different elevation of the dilution steam generator structure TCC has an inspection point with Daelim with witness point as per the ITP. Hence it is violation of ITP and Procedure. Ref.# A554-E-103-QA-GEN-PLN-021 Rev. 3 Para. 4.2, 4.11, 4.9 Subcontractor: 1. Noted I will check with structure inspector and let you know regarding this issue. With Reference to LBE # 250 (Dated 09,03, 2014) Subcontractor replied concerning fire rated "Labels at door & frames, as per vendor clarification those door cannot be "fire rated" due to oversize (See attached approved door & frame schedule) in this regards, contractor shall provide of submit shop drawing, and details showing "CMU" size and fire rating for both exterior and interior CMU wall @ (Sub- station G-1120 & G-1121), for Proper Documentation & Implementation @ Site. Subcontractor is requesting to close this log book entry because its repeated. During Routine Site Inspection, it was noticed that the contractor used hog bolts and nuts in the installation of outdoor enclosures which is vioalation as per A554-K-PRC-EL-GEN-PHL-005 Section 3.4.4 Subcontractor: The Subjected matter has been informed to construction group to coordinate with engineering, the installation done as per IFC drawing, Contractor will submit TM for the same. During Surviellance Inspection of Electrical room Substaion G-1120, it was observed the following Violation: 1). Power and control cable was installed in cable tray and cable dressing has completed in vertical and horizontal capability without inspection the tray this violates as per schedule Q Attachement Q IV. PAra. 3.7. 2). During Inspection of LV Power Cables were Installed in Cable Tray # EH-112-104, EH-114-107 and EH-115-109, Power Cables not Properly dressed. this violates as per schedule Q Subcontractor: 1). After Receiving asbuilt drawing from engineering subcontractor will raise RFI for the same. 2). Subcontractor will complete the cable dressing as per ITP and RFI will raise for the same. During Site Surviellance it was observed that in cooling tower pipe rack JB inspection not cleared and Contractor Claud this cable, this is not the 1st time happened, repeated violation done by contractor. This violates Schedule Q" Attachment IV Para 3.7 and Project ITP Contractor requested to take a Preventive Action. RFI # MFC-DLM-ASY-INST-990A to 998A already submitted and accepted, cable installation will not be done unless JB's are inspected & Accepted. During Surviellance at PIB-1121 it was observed that improper installation of cable pulling at building and worker sitting an tray and used as walkways, this vioalate Schedule Q" AVEMV-VE2 and NEC Article 40.12, Contractor request to take a Preventive Action. Subcontractor: Subcontractor already provided temporary access/Scaffolding planks in order not to use the cable tray as walkway During the Surviellance and Monitoring Activities at Operator Building (G-1122) along sample preparation room, it was noticed that wall tiles installation has been started, wherein no RFI of shop drawing submitted by contractor, in this regards, contractor shall be provide "Shop Drawing" Showing Layout of Wall & Floor Tiles, for Proper Documentation and Implementation at Site. Subcontractor: Amana has submited the shop drawing and approved by Daelim. During Material Receiving Inspection E222313 Exchange it is noticed that its Leg (Jointed to the foundation) is bented makes it difficult in equipment align also the boday of the equipment is found damage (Corroded and broken - external body part), this may have happened in trnasportation and material handling, proper action to be taken by the contractor with the vendor recommendation for the rectification of the equipment. Ref #. A554- 103-QA-GEN-PRO-034 Para. 8.1.3 A554-E-103-QA-GEN-PRO-035 Para. 8.2.1 & 11.8.11
PN: During Surviellance it is Observed that P-0126B, P2320A, P2411A, P2415A/B, P1311A/B/C, P1302A/B, 1711A, P2122B by ITT goulds found Leaking. Leaking is from the oil drum out valve thread connections, Daelim should take appropraite corrective action by consulting the recommendation of vendor manufacturer. Contractor: Vendor site visit being arranged. The expected visit date is within 23 May 2014. -> NCR with coorective action was sent to Company through TR no. MFC-T-DS-CJ-QA-1567 dt July 14. During Inspection it is found that in tower (T2110 Primary Demethanizer) for internal tray Installation flange down condencer brazing suppor for the false down commer plate is not welded to the tower shell, also for lower T1810, HP depropanizer bolt for tray 31 placed BW feed pipe at beneath tray 31 is not founded welded. contractor shall take corrective action consulting with the tower manufacturer and SME. Ref. KOCH-GLI-TSCH Drwg. No. 115108-D000, 115111-D001. Contractor: Contractor already discussed the issue with Company and will submit the site work procedure for missing clips to Company. After receiving the confirmation from Company, Contractor will do site work. Contractor: Contractor is now procuring the required material for T- 1810 & T-2110. (1) T-2110 : Required Material (SA 537 Cl.1+S5, -48) is arrived at site. (2) T-1810 : Contractor is continuously expediting Tower fabricator to supply the reqruied material (SA 537 Cl.1 + S5, -59 Impact Tested) It was noticed that in the V-0555 (Sodium Hypochhlorite) tank area, the Paving Located at the sout side has a construction joint without a TPER. TPER shall be installed as required by Document # A554-K- PRG-CV-500-CON-001, Section 16.4, Contractor shall submit a method statement or shop drawing for approval by company See also Doc. No. A554-K-PRG-CV=SPC-C20-047. Contractor: Already rectified the area as per shop drawing. See attachments. It was noticed that sometimes contractor does not have the complete drawing to verify slope during survey. There is no assurance that the survey done by sub-contractor personnel are they updated IFC. Please Advise surveyor to be independent from the sub-contractor survey data and must provide their own computation to compare data with Contractor to ensure proper checking during survey work to avoid erromous survey result (Pro-Active). Contractor: Contractor noted the the notification, Contractor surveyor was informed to bring drawing everytime there is on-going inspection & compare his survey report to subcontractor surveyor for counter checking. During routine site inspection, it was noticed that the IFC Drawings for fire alarm System, Dont have an approval from fire department which is vioaltion as per A554-F-PRG-SE-GEN-BOD-002 Section 1.4. Contractor: Engineering team shall clarify the issue to Sadara regarding the scope of work or the design issue. Government approval is out of Contractor's work scope During routine site visit, it was observed that the temperature inside the electrical room of substation G- 1121 was already 28.6C, which is violation as per 67C-1811-00 Section 12.3.3 Controlling Temperature Inside the Two (2) Substations G-1120 & G-1121 is the main solution by installation Air conditioning Unit (4 Nos) as per construction plans & action, also Please Attached file for the discussion of company & Contractor top Manageme With Ref. to RFC (Request for Certificate # A554-RFC-149-131 Regarding Clarification for Epoxy grouting Centrifugal Pump" for Equipment (PUMPS) pocket holes already grouted with non-shrink cementitious grout" the response was all Non-shrink cementitious grout that was used on rotating equipment shall be removed and replaced with epoxy grout to comply with SADARA Specification" Please identify the pumps where Non-cementitious grout was used also, Please refer to Logbook Entry # 258. Contractor: Already identified the area of non-curing grout and epoxy grout. Page 57 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 30, 2014 DUE DATE Issued corrective action to Company Target Date S/N LBE NO. PID SUBCON/ CONTRACTOR VAF / PN LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason Company comment Approved Close LBE by Company STATUS CONTRACTOR'S CORRECTIVE ACTION PLAN LBE-DLM-MECH- 526 MR. GLENN DAELIM PN 3 MECH Hvac 16-Apr-14 19-Apr-14 26-Apr-14 26-Apr-14 Closed LBE-AMA-CIVIL-271 MR. GERALD AMA PN 2 CIVIL Civil 19-Apr-14 22-Apr-14 24-Apr-14 26-Apr-14 Closed LBE-SEN-ELECT- 015 MR. FELOMINO SENDAN VAF 1 ELECT Preservation 22-Apr-14 25-Apr-14 01-Jun-14 02-Jun-14 Closed LBE-ASYAD-INST- 012 MR. PERVEZ ASYAD VAF 1 INST Qaulity Management 22-Apr-14 25-Apr-14 07-Jun-14 15-Jun-14 Closed LBE-ASYAD-INST- 013 MR. PERVEZ ASYAD VAF 1 INST Instrumentation 22-Apr-14 25-Apr-14 07-Jun-14 15-Jun-14 Closed LBE-KCC-CIVIL-272 MR. JERRY KCC VAF 2 CIVIL Civil 22-Apr-14 25-Apr-14 08-May-14 14-May-14 Closed LBE-KCC-MECH- 527 MR. GLENN KCC VAF 3 MECH Plumbing 22-Apr-14 25-Apr-14 24-Apr-14 24-Apr-14 Closed LBE-KCC-MECH- 528 MR. GLENN KCC VAF 3 MECH UG-RTR 22-Apr-14 25-Apr-14 04-May-14 04-May-14 Closed 62 LBE-KCC- MECH-529 MR. GLENN KCC VAF 3 MECH UG-RTR 23-Apr-14 26-Apr-14 23-Jul-14 Open 63 LBE-DLM- MECH-530 MR. HARIKUMAR DAELIM (Enginnering) VAF 3 MECH Mechanical 23-Apr-14 26-Apr-14 17-May-14 Open LBE-AMA-MECH- 531 MR. GLENN AMA VAF 3 MECH Hvac 24-Apr-14 27-Apr-14 09-Jun-14 11-Jun-14 Closed 64 LBE-TCC- MECH-532 MR. SAYED TCC VAF 3 MECH Piping 24-Apr-14 27-Apr-14 28-Apr-14 20-Jul-14 Daelim to rectify all joints Open 69 LBE-TCC- MECH-533 MR. NASSAR TCC VAF 3 MECH Coating/ Painting 26-Apr-14 29-Apr-14 10-May-14 20-Jul-14 26-Jul-14 Closed- LBE-ASYAD-INST- 014 MR. PERVEZ ASYAD VAF 1 INST Instrumentation 27-Apr-14 30-Apr-14 05-Jun-14 05-Jun-14 Closed 72 LBE-KCC- CIVIL-273 MR. JERRY KCC VAF 1 CIVIL Civil 28-Apr-14 01-May-14 08-May-14 Included in the Punchlist 22-Jul-14 Closed 94 LBE-DLM- TELE-013 MR. RODNEY DAELIM (Enginnering) VAF 1 TELECOM Telecommunica tion 29-Apr-14 02-May-14 09-Apr-14 20-Jul-14 Closed 95 LBE-SEN- TELE-014 MR. RODNEY SENDAN VAF 1 TELECOM Telecommunica tion 29-Apr-14 02-May-14 29-Apr-14 30-Jul-14 20-Jul-14 Closed During Surviellance and Monitoring Activities at operator building (G-1122), Internal rooms it has been observed that mostly of rooms, had been already installaed suspension system and hangers in which some internal wall and sleeves were not properly sealed or repaired as per (SADARA Standard G2G- 4300-41 requirement) a Pro-active notification was issued to the contractror for further action. Subcontractor: Subcontractor is requesting to close this log entry because its repeated, Please see the log book entry # 260 During Site Surviellance Inspection at Transformer yard substation G-1120, it was observed that the power tnasformer tag # TR=103H101A has oil leakage from grounding bushing. This violates as per contractor preservation plan document # A554-E-103-CM-GEN-PLN-002, Para 2.8 (D) Schedule "Q" Attachment IV Para 6.6 Transformer for G-1120 with a tag number of TR-103H101A is now rectified and re-tightened to ensure that leaks (oil leaking) are prevented. This substation is now energized and final leak test for installed tranformers were done. Sub-contractor QC Manager Absence for job site from last one month & he left for annual leave without proper notification & procedure and from last one month sub contractor don't have any QC manger, Its violation of Schedule "Q" Attachment VI Contractor Request to take Preventive action ASAP. Subcontractor: Subcontractor QC manager interview has been completed and safety orientation is finished. Waiting for SADARA ID. Subcon QC Manager has been mobilized to the site on June 13, 2014. Equipment Defeciencies the following accu deficiences were observed in G-1120. 1. 3 Nos. Pressure gauges are defective for ACCU-001 A/B/C. 2. Isolation valve of ACCU-001A has leakage hindering connection of piping to header. 3. No charging valve available for circuit 1 for each suction Line ACCU-001A/B/C. all noted Deficiencies shall be rectified by vendor to prepare the equipment for the pre-commissioning. Equipment Defeciences already rectified by zamil vendor. 1. Deffective pressure gauge already Replaced @ ACCU-001 A/B/C in substation G-1120 2. Isolation valve of ACCU-001A was already replaced by Zamil 3. as per Zamil Technicain Instruction charging valve shall be available to used in the compressor portion. Incorrect VD material observed in G-1121/G-1120 battery room exhauset ductwork that volume dampers are made of galvanized steel, these will be exposed to corrosive environment and non-complaint to RT5S-5051 Sec. 3.1.3 were specified for use in conveying corrosive or moisture ladder fumes or gases. stianless steel ductwork shall be fabricated of type 316 sheets. Contractor: Rectification for volume damper already done. Contractor applied paint coated in coulume damper inside and outside of material to protect corrosion 127 Nos. of joints welded with wrong consumable in TCC shop 1 @ 2 for CAO9 and CA85 line class as per specification filler material shall contain 0.5% moly (ER80S-D2, E7010-AI & E7018-A1) but TCC used ER70S2 as per WPS-TCC-P1/P1-01, which has Molydenum 0.15% Daelim should take appropiate corrective action. Contractor: The same issue was not noted and raised SQDR dated 9/12/13. TCC-WPS-P1/P Rev. 2 has been approved for CA-09 & CA- 47 line class 90% joints are cut and rewelded. It has been noticed that during material receiving Inspection, 48 PCS of Stainless steel Themowell flanges has been coated using Modified silicons paint at TCC without any notification to contractor & company, this is vioaltes schedule Q" Attachment IVV, this is information & corrective action shall be taken by contractor. Contractor: Thermo couplers were inspected and accepted by SARADA. RFI No. MFC-DLM-TCC-H-L-849. UG Piping backfilled w/o stress reinforcement accepte4d & SS flange wrapping UG piping DVA line under package No. HT-0727 has been backfilled without completing the underground piping works as follows: -Stress reinforcement Spot No. 65 thickness per ISO drawing N01610AAB-FW-072054-01. -SS Flange was backfilled without wrapping for corrosion protection. Comply Project Specification Reply to Inspection Comments Spot # 65 has been excavated, tape wrapping and stored reinforcement lamination done, Line # FW-072054-4"-ES17 Pipe TE 8mm, Inspection carried out are accepted by SADARA RFI # MFC-DLM-KCC-UG-2410 Dated. 01.05.2014. CUT FRP Piping Firewater line FW-071102-20 was cut and 2 added 2 joints to fit the PIV IP-P-1031735-004859 under test pack HT-015, this line has been hydrostatically tested and Passed. Modified line shall be re-tested to comply 64S-6423-01 Sec. 7 a new test shall be applied after repair and convections have been made. Subcontractor: This matter was already addressed to top management, waiting for advice from Daelim. Observed that the spent caustic unit T-0523 scrobber tower nozzle B1 observed imperfection of flange face (Serration damaged) is exceed as permissible tolerance limit of ASME 16.47 Table: 29 Daelim QC and Engineering team shall propose Rectification method and obtain company approval prior to comments any activities in subjected nozzle. Contractor: Vendor recommends to make smooth finish by sand paper, then to use liquid paste together with gasket. During routine site surviellance, it was observed the subcontractor store all the calibrated Instrument in one container where no Air conditioning and temperature not maintain, Contractor shall provide proper quarantine are for all the instrument, this is Vioaltion preservation plan A554-E-103-CM-GEN-PLN-002, Contractor requested to take preventive action. Subcontractor: ASYAD will provide AC for the temperature maintaining of all calibrated instruments in the store room. The Existing foundatrion of common piperack located at the corner of south west of spent caustic area is lower than the open ditch elevation adjacent to it. The drained water cannot flow to the open ditch on this area. (Near Vessel V-05 66/V-0567) contractor shall provide method statement of shop drawing to ensure the design requiments for drainage is complied for company approval. Contractor: New revision drawing was already issued. Unplumbed fire monitor riser observed that fire monitor riser from FW-071275-6 to FM-0738 is out of Plumbness. This is not complaint to installation detailed drawing A554-E-103-CN-SPC-C99 Sht 006, Rectify Plumbness Prior conducting Hydrostatic Test. Under ground fire water line SS riser for fire water monitor (FW-071275-6 to FM-0738 is already rectified. Fixed the SS riser within the acceptable limit. Plumbness of the SS for water monitor riser found satisfactory & accepted. During site surviellance at EW piperack it was observed that instrument open channel tray damage by mechanical crew (crane) this violate Schedule "Q" attachment IV Para 5 G-07D-0322-00, Contractor request to take preventive action. Contractor: The damage cable tray already replaced and inspection has been done. The attached Drawing are locations of uneven or irrgular top surface of foundations or paving, the contractor shall rectify the concrete curfaces to comply with the requirements of RTS-3004-01 Section 10. Subcontractor: KCC area shall be repaired later because the area was temporarily used by other discipline for stacking of materials. At Building G-1122 at Telecom room contractor is advised to follow the requirement stated on RT-SAES-T-916 Para. 4.4.2 is locate the light fixtures a minimum of 2.6 meters (8ft, 6 inches) above the finished floor. Contractor: Same with LBE no. 010. For Building G-1120, G-1122 & G-1121 at all Telecom Room, Contractor is advised that all overhead pathways (Trays, Conduits, Trunks, ETC) Entries into the TR shall Protrude into the room a distance of 5 centimeters (2 inches) maximum at a minimum height of eight (8) feet. Contractor: This issue has been conveyed already to Construction team to follow standards. Company will be informed of Contractor's action. Page 58 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 30, 2014 DUE DATE Issued corrective action to Company Target Date S/N LBE NO. PID SUBCON/ CONTRACTOR VAF / PN LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason Company comment Approved Close LBE by Company STATUS CONTRACTOR'S CORRECTIVE ACTION PLAN 65 LBE-DLM- MECH-534 MR. SAYED DAELIM (Procurement) VAF 3 MECH Material 30-Apr-14 03-May-14 17-May-14 Open LBE-KCC-CIVIL-274 MR. JERRY KCC PN 1 CIVIL Civil 01-May-14 04-May-14 14-Jun-14 17-Jun-14 Closed LBE-AMA-CIVIL-275 MR. ENDRANO AMA PN 1 CIVIL Quality Records 01-May-14 04-May-14 08-May-14 13-May-14 Closed 66 LBE-AMA- CIVIL-276 MR. ENDRANO AMA VAF 1 CIVIL Material 01-May-14 04-May-14 26-May-14 30-Apr-14 Open 67 LBE-AMA- CIVIL-277 MR. ENDRANO AMA PN 2 CIVIL Civil 06-May-14 09-May-14 20-Jul-14 Info LBE-DLM-ELECT- 130 MR. FELOMINO DAELIM (Enginnering) VAF 1 ELECT Electrical 03-May-14 06-May-14 15-May-14 14-Jun-14 Closed 68 LBE-AMA- INST-015 MR. PERVEZ AMA VAF 2 INST Instrumentation 06-May-14 09-May-14 19-Jun-14 30-Jul-14 Open LBE-KCC-CIVIL-278 MR. JERRY KCC VAF 2 CIVIL Civil 08-May-14 11-May-14 12-May-14 26-Jun-14 Closed LBE-KCC-CIVIL-279 MR. JERRY KCC VAF 2 CIVIL Civil 14-May-14 17-May-14 14-Jun-14 17-Jun-14 Closed LBE-KCC-CIVIL-280 MR. JERRY KCC PN 2 CIVIL Civil 15-May-14 18-May-14 14-Jun-14 17-Jun-14 Closed 69 LBE-DAELIM- CIVIL-281 MR. JERRY DAELIM (Enginnering) VAF 2 CIVIL Engineering 15-May-14 18-May-14 20-Jul-14 Open 70 LBE- DLM/AMA- MECH-535 MR. HARIKUMAR DAELIM (Enginnering) VAF 3 MECH Engineering 15-May-14 18-May-14 Open During Leak testing of Manual Butterfly valve in NAISCO Testing Facility Jubail, it was observed that there was contineous leak found in the 14" x 150 butterfly valve in low pressure closure test due to crack in heating area. This is vioaltes API 598 Table 6., DAelim Should take Appropiate action and corrective action, Contractor: It is under process to send back to vendor shop for this repair. PN: Due to the change in paln for the transfer of foundations P-2417 A/B, the demolished paving shall be returned to its original location, however there is a construction left by the demolition which make the joint not water tight anymore, Contractor shall provide watership on the joint in accordance with Doc. No. A554-K-PRG-CV-CON-001, Section 16.4 Contractor: The demolished paving in the particular area around the P-2417 A/B foundation. After inspection with the Company inspector, the concreting of paving was done to its original location/elevation as shown in the attached picture. Subcontractor: Advised to QC Inspector to check the area before submitting RFI to Daelim or Company. During Surviellance and monitoring acivities at sub-sation G-1120, along transient lips sytem, we found out that "steel door" SDG was deformed or damaged, in this regards, contractor was revised to check or investigate the said steel door and replace with good materials as per latest IFC Drwg./Door Schedule. Subcontractor: The deformed dorr "SDG" is already repaired and re- installed at site. PN: During surveillance and monitoring actiivities at substation G-1121, found out that gutter support (FB.50X6) has already been installed without submitting first the "RFI" for Material Receiving inpsection to ensure that the material complied with Sadara standard prior to inspection. Contractor is advised to submit material receiving inspection to counter-check by Company Coating Inspector for proper documentation and acceptance. Contractor: Subcontractor will raise/submit RFI for the material receiving to check the installed gutter support randomly at G-1121 to confirm installed gutter are meet as per Sadara standard. During surveillance, obseerved that following discrepancies: G #1122 Operator building (Amana): * Embedded door frame for blastering door are inclined and gaps bowing more than the acceptable limit - as per GA drawing (A554-E-G-11-22-GWA-402302) * Welding activities carry out with unqualified welder and WPS. Improper sequence of weld and crack - leak of fusion-undercut . * Daelim quality team to investigate and propose appropriate remedy action with Engineering support to fix the occured discrepancies. It was noticed that the Surveyor damaged the instrument survey level, SN LEICA NAK-2 5048521 with LEICA AUTO LEVEL NAK-2 SN 5549201 during the checking of elecvation at battery limit after founding out a difference of 1cm in the reading of location of walls of open different conneting the MFC and Outside Battery limit. Upon investigation, it was found that the survey level SN LEICA NAK-2 5048521 this errneous reading. It was also found out that LEICA AUTO LEVEL NAK-2 SN 5549201 is the one listed in the survey sheet. Contractor shall provide corrective action to this violation is order not to repeat this violation. Contractor: It was strictly advised to the Surveyor that they must be consistent. The instrument name and serial number must be mentioned in the data sheet result. And in order to assure the accuracy of the instrument where submitted the following calibration certificate, refer to the attachment. PN: During attendance of RFI # MFC-DLM-KCC-CI-7101, it was found out that the dimension of the erected structure steel reinforcement of the Pedestal at area P-A Paving is not in accordance with the drawing. Upon further verification of the dimension, it was clasified that the drawing utilized for construction is superseded by a new drawing. Please advise subcontractor to utilize always updated revised drawing in their construction to avoid rework. Contractror: During inspection, the error of dimension to the said pedestal reinforcment was rectified as early as commented by Company inspector. And it was advised to the Construction team to use always the latest approved drawing. It was noticed on site that the Structural Column for Foundation F1-025 is clashing with the equipment E1805. The beam connecting the steel columns therefore cannot be connected. Also the erected column (one side only) is tilting because the equipment is inside the column vertical alignment/plumbness. The foundation is very near the construction joint also. Contractor to investigate and provide corrective action. Contractor: Already Fit-025 structural colomn supports are accepted, refer to attached drawing. During Surviellance Inspection at Substation G-1120 & G-1121 for MV & LV Swithcgear, it was observed that the grounding conductor was installed and undersized that actual size is 70sq. Mm and main buses rated amper of MV switchgear is 2000 A and LV switchgear is 3200A, This is violates as per G7C-0104- 00, Para. 6.4.3. Contractor: Contractor shall add two more 70mm grounding cable to the existing installation to comply as per G7C-0104-00. Company will be informed once the activity is finish for the closure of the issue. During inspection at site at PIB G-1121, following violation has been has been noticed during cable tray inspection. Splice over support, field fabricated fitting used instead of factory made. Improper nut and bolts used in tray, wrong splice plate used, slotted hole joint plate used instead of round hole. There is no clearance between two layers of tray, provide proper separation between tray, Contractor used 150mm open channel tray instead of 100mm maximum allowed. This violation RTGE-0802-01, NEMA VE2, G-07C-0321-G07C--0324. Subcontractor: The Subcontractor wil rectify the field fabricated items and splash plate to be repalced with Standard Materials at the earliest. It was observed that during the removal of burlap and polythylene sheets at several location at paving west of common compressor and spent caustic areas, the broom finish of the paving were not uniformly rendered. Please advice the finishing in0charge to properly perform finishing in accordance with RT2S- 3001-01, Para. section 10. Subcontractor: The mason group was informed to take good care on the finishing after the concrete has been consolidated and leveled. With Ref #. To RFI # MFC-DLM-AMA-CI-7467, 7468 & 7469 (Dated 27-Apr-2014) it has been observed that some RFI's by our Sub-con (AMANA) they are submitting up to (3) times prior to Inspection, it means the area is not ready for inspection, in this regards, contractor must see to it that the area is completed or ready for inspection, prior to submit the RFI and also will proper coordination to construction for proper documentation. Page 59 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 30, 2014 DUE DATE Issued corrective action to Company Target Date S/N LBE NO. PID SUBCON/ CONTRACTOR VAF / PN LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason Company comment Approved Close LBE by Company STATUS CONTRACTOR'S CORRECTIVE ACTION PLAN LBE-INST-ASYAD- 016 MR. SHABIRUL ASYAD VAF 1 INST Quality Management 17-May-14 20-May-14 07-Jun-14 08-Jun-14 Closed 71 LBE-PCMC- MECH-536 MR. SURESH PCMC VAF 3 MECH Piping 18-May-14 21-May-14 26-Jul-14 Open 90 LBE-SEN- ELECT-131 MR. SHAMSHER SENDAN VAF 1 ELECT Electrical 19-May-14 22-May-14 04-Jun-14 30-Jul-14 24-Jul-14 Closed- 72 LBE-DLM- ELECT-132 MR. SHAMSHER DAELIM (Procurement) VAF 1 ELECT Material 19-May-14 22-May-14 24-May-14 Open 73 LBE-AMA- CIVIL-282 MR. GERALD AMA VAF 2 CIVIL Civil 20-May-14 23-May-14 Open 74 LBE-AMA- CIVIL-283 MR. GERALD AMA VAF 2 CIVIL Civil 20-May-14 23-May-14 30-Jun-14 Open 75 LBE-TCC- MECH-537 MR. SURESH TCC VAF 3 MECH Piping 21-May-14 24-May-14 24-Jul-14 20-Jul-14 Open 76 LBE-DLM/ SEN-ELECT- 133 MR. SHAMSHER DAELIM (Construction) PN 1 ELECT Electrical 21-May-14 24-May-14 24-May-14 Info LBE-AMA-CIVIL-284 MR. JERRY AMA VAF 2 CIVIL Material 22-May-14 25-May-14 26-Jun-14 26-Jun-14 Closed 85 LBE-PCMC- MECH-538 MR. NASSAR PCMC VAF 3 MECH Coating/ Painting 26-May-14 29-May-14 10-Jun-14 20-Jul-14 Should attached copy of RFI after rectification 23-Jul-14 Closed 77 LBE-TCC- MECH-539 MR. SAYED TCC VAF 3 MECH Piping 27-May-14 30-May-14 24-Jul-14 20-Jul-14 Open LBE-TCC-MECH- 540 MR. SAYED TCC VAF 3 MECH Piping 30-May-14 02-Jun-14 10-Jun-14 16-Jun-14 Closed During surviellance inspection in TCC area, it was observed that the pipe is clashing with Equipment E-2331 and there is no sufficient clearance for the application of 130mm insulation on pipe. This is violation against Sadra spec: G4D-0142-01 & GAZ-0010-00 Para. 6.10.2. Contractor shall take necessary action. Subcontractor: This is Engineering issue. TCC already get JCR approval. The pipe length will be added soon. The job alreadt compelted. Subcontractor: Warning letter has been issued to Personnel. Tool box meeting was conducted regarding the matter. During witness of Hydrotest, it was found that the check valve flabber was not removed (Pkg. No. 1147- 0-PRG-GEN-PRO-014, Para. 9.4.3. which states that "unless the check valve has a bypass valve, the disk of the check valve shall be removed. Subcontractor QC Inspector left the site from last week without proper notification and procedure, this is violation of schedule Q, attachtment VI. Contractor requested to take preventive action ASAP. Subcontractor: QC Inspector file for emergency exit due to family problem so ASYAD has no enough time to inform the client. During srveillance inspection at MFC site all over areas, it was observed that, Contractor has installed the Variable height clamp type Pipe shoe; separator barrier has not overlapped itself and overlap orientation in wrong position, such as 2 clock, 4 clock and 10 clock position. This is violation against G4G-1420-21, Note 3, which states that, "The separator material shall overlap itself on the bottom center line of the pipe. Due to lack and material traceability, in the MFC-TCC site, V# area, it was observed that, Subcontractor TCC has wrongly assembled and welded the ASTM A53 Gr, ERW pipes instead of Seamless pipe ASTM A106 Gr. B for Caustic service piping line class CA09. This violation against CA-09M, Note P-CSO1PEXS and Isometric IFC drawing. ISO drawing # N016103V3A-CA-179013-02, J # FW 08 & 09. N016103V3A-CA-179028- 01, J # FW 01. Subcontractor:Due to material shortage, the Construction using ASTM A53GR GRW Pipe instead of ASTM A106 GR.B without confirming the class required. TCC already cut-out all wrong joints and applied PT. ISO drawing new revision. Subcontractor: Rectification has been done. Sadara has inspected and accepted for line #1404-00HT-001 & 1617-00-HT-001. RFI mentioned attached, please refer to the LBE. During inspection for surface preparation prior to primer coat for line # 1404- 00-HT-001 & 1617-00HT-001 as per request for Inspection # PCMC-H-S- 0379 & PCMC-H-S-0380, it has been observed that PCMC has applied primer coat prior to inspection time. This is non-conformance with schedule Q. During surveillance at substation 1120/1121. It was found that the grounding cables are connected to earth bar without numbered or marker. This violation to G7C-0104-00, section 5.8 which states that " all eathing bars including the connected cables shall be numbered or marked. Contractor: It is already communicated to Daelim engineering to assign & generate the tag no. of each ground bus bars. During Material Receiving Inspection of the Thermal Fire Detector at Daelim laydown yard, it was found that the thermal fire detection (P/N 27120) are not matching with Pusrcahse Order. Note. This is violation to attached documents and schedule "Q", attachment III, Section 3. Contractor: This issue will be forwarded to procurement for further investigation regarding traceabiity of materials. This LBE will be updated once the action of procurement is given. PN: During Inspection of FRP cable tray at spent caustic area, it was observed that the cable tray installation are using temporary nut-bolt for fasteners/hold down stainless steel materials. This is violation to G7D-0323- 00, section 4.1.5 and data sheet G7D-0323-A required silicon bronze. Contractor: For the time being that the materials which are approved to install in FRP cable tray is notavailable, stainless steel was installed temporarily to proceed on the next activity. Once the approved materials arrived in the site, it will be replaced. Contractor: Already replcaed the anules of hot dip galvanized for the location of sump in the area. With reference to RFI #MFC-DLM-AMA-CI-7762, Roof leak testing on roof of substation G-1120. (GL G-11/AC), at around 2:20 pm starting spray of water using two (2) water truck using hose, continuously after and hour around 3:20 pm, they finshied spray of water and thats the time we found out that there are some areas with stagnant water, 2.40 meter from the edge of gutter and also four (4) locations at gutter connection with leaks. In this regards, Contractor shall rectify or repair the area with stagnant water and seal-off the gutter conncetion with leak and should take corrective action on the issue. (RFI has been rejected). During surveillance and monitoring activities at sum-0645 south side of substation G1121, it was noticed that the installed ladder rung some are preserve with corrosion. This is a violation to SADARA specification RT- 3001-01, section 8.2, Para. 8.2.7. In this regards, Contractor should investigate these materials and take corrective action about the issue. Contractor: Regardimg ladder Rung which is coordinated @ sump pit #645 Company has already issued an NCR to Contractor. RFI # MFC-DLM-AMA-CI-7767/7768 were attended and during the Inspection, it was noticed that the angle frame of thesump for the TOTES was not hot dip galvanized upon testing into sharp object. The QC personnel of Amana insist they have certificate but cannot provide. The coating inspector of Daelim was called to verify the angle frame coating whether painted only or hot dip galvanized. The coating inspector confirmed the angle frame is not hot dip galvanized. This is the third logbook entry that galvanized paint are applied by the same subcontractor and despite repetitive violation, the same subcontractor continues this same violation. Provide corrective action no to repeat the same violation. Page 60 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 30, 2014 DUE DATE Issued corrective action to Company Target Date S/N LBE NO. PID SUBCON/ CONTRACTOR VAF / PN LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason Company comment Approved Close LBE by Company STATUS CONTRACTOR'S CORRECTIVE ACTION PLAN 78 LBE-KCC- CIVIL-285 MR. GERALD KCC VAF 2 CIVIL Civil 02-Jun-14 05-Jun-14 14-Jun-14 Open LBE-KCC-CIVIL-286 MR. GERALD KCC VAF 2 CIVIL Civil 02-Jun-14 05-Jun-14 14-Jun-14 17-Jun-14 Closed 79 LBE-DAELIM- CIVIL-287 MR. JERRY DAELIM (Enginnering) PN 2 CIVIL Engineering 03-Jun-14 06-Jun-14 12-Jul-14 15-May-14 Info 100 LBE-IKK- MECH-541 MR. NASSAR IKK VAF 3 MECH Coating/ Painting 03-Jun-14 06-Jun-14 22-Jul-14 Closed 101 LBE-IKK- MECH-542 MR. NASSAR IKK VAF 3 MECH Coating/ Painting 03-Jun-14 06-Jun-14 22-Jul-14 Closed LBE-AMA-CIVIL-288 MR. JERRY AMA VAF 2 CIVIL Civil 04-Jun-14 07-Jun-14 28-Jun-14 29-Jun-14 Closed 80 LBE-INST- ASYAD-017 MR. PERVEZ ASYAD PN 2 INST Instrumentation 04-Jun-14 07-Jun-14 30-Jul-14 Info LBE-INST-ASYAD- 018 MR. PERVEZ ASYAD VAF 2 INST Instrumentation 07-Jun-14 10-Jun-14 10-Jun-14 23-Jun-14 Closed 81 LBE-KCC- MECH-543 MR. GLENN KCC PN 3 MECH UG-RTR 08-Jun-14 11-Jun-14 23-Jul-14 Info 82 LBE-IKK- MECH-544 MR. NASSAR IKK VAF 3 MECH Coating/ Painting 08-Jun-14 11-Jun-14 Open LBE-ARCC-MECH- 545 MR. RAMO ARCC VAF 3 MECH Piping 08-Jun-14 11-Jun-14 15-Jun-14 15-Jun-14 Closed 105 LBE-IKK- CIVIL-289 MR. JERRY IKK VAF 2 CIVIL Civil 08-Jun-14 11-Jun-14 22-Jul-14 Closed 83 LBE-KCC- CIVIL-290 MR. GERALD KCC PN 2 CIVIL Civil 08-Jun-14 11-Jun-14 12-Jul-14 Info Contractor: The previous installed gutter was already removed, and KCC construction team was advised to purchase a new one lgalvanized gutter as per approved drawing. And KCC will raise RFI for material receiving inspection prior to installation. Contractor: The mason curing group was informed to make an immediate action that the casted deck slab must be properly covered by burlap and polythelene sheet and continouos curing will be for 7 days. Contractor: Discussed to civil construction and engineering action granted that they will provide ab approved drawing on how the proposal to be accepted by Company. An sketch is attached. During surveillance and monitoring activities at expander building (61123), found out that the gutter was already installed, without submitting first RFI for material receiving inspection for proper documentation and checking. Contractor should take corrective action on this issue and for proper implementation. This is violation to SMIC-M-1031-1 (Metal Roofing Receiving and Storage Inspection). During monitoring and surviellance activities at Crack Gas Compressor' Deck slab, it was noticed that the newly casted slab has insufficient water curing, burlaps and improper covering of polythelene sheet. These are violations to RT2S-3001-01, section 9, para. 9.1.2 which states that water curing shall be continues until the compressive strength has reached to 70% of the specific strength but not less than 7 days after placement. Contractor should take corrective and preventive action on the issue. PN: It was noticed that some of pipe support, not yet erected in many locationsare directly located in the TPER (expansion joint), please note that the foundation/pedestals of these pipe supports are sugject to verification by Daelim Design Engineering for proper design and possible demobilization of paving to erect new foundation. It is recommended that the location of these pipe support shall be identified in advance by Daelim for proper disposition. The following RFI's were received very late b the Company. The RFI's were submitted one (1) month later after the activities are completed. This is a violation of schedule Q, Para. 3. RFI No. MFC-DLM-AMA-CI-5547 17/12/13, CI-5509 15/12/13, CI-5429 09/12/13, CI-5552 18/12/13, CI- 5561 19/12/13, CI-5624 24/12/13, CI-5606 23/12/13, CI-5589 22/12/13, CI-5589 22/12/13, CI-5571 21/12/13. The RFI's were received on 29 May 2014. Contractor: The RFIs were submitted one month later due to third party report. Subcontractor to assure not to repeat in the future. PN: During site surviellance at EW Pipe rack, it was observed that Contractor installed open channel tray in improper way. Tray below the flange and un-avoidable . This violates G-07C-0321-01, Para. 3.8 & NEMA- VE-2 and NEC 110.12. Contractor requested to take a necessary action. Subcontractor: Channel Cable tray will be provided with cover that serves as cable protection and any falling debris. Subcontractor: Contractor QC already issue the SQDR for the violation of cable pulling. Now cable tray inspection has been done. During site surviellance, it was observed that Contractor installed the tray and without inspection, cable has been pulled and grounded and terminated without inspection of tray. This is repeated violation done by Conractor. This violates project ITP and schedule Q, attachment IV, Para. 3.7. Contractor requested to take a preventive action. During surviellance at cooling tower room #7. floor lining , it has been noticed that IKK subcon has applied primer coat prior to repairing the cracks as per proper concrete repair method statement (A554-E-103-CM- GEN-PLN-024) & Sadara Specs. (RT2S-3001-01, Section 11.1.4), Coating applicators are just filling the cracks using MasterBrace ADH 2200 after applied primer coat. Furthermore, lining was applied in contravention of approved work procedure, applicator was fixed tissue mark on the dry primer coat prior to apply second coat of Master protect 1815. This is for During routine inspection for surface preparation at cooling tower room #06 floor, it has noticed that long cracks, width is greater than 1mm which exceeds the limiting value in the Sarada specs (RT2S-3001-01, Section 11.1.4). Cooling applicators were just filling the cracks using Masterbrace PN: Fire hydrant FH-0707 (under FW-HT-002) was hit by a PCMC truck causing minor damaged and scratches on fire hydrant with condition of buried RTR piping unknown until put to service. Ensur all fire fighting equipment are guarded against damaged to comply LPP 103-6R8. Temporary guards must be provided where permanent guards are still not in place. Verify RTR UG Piping of FH-0707 to ensure no crack developed during the impact. Subcontractor: The area cannot be excavated for checking & verification because it is being used as an access. KCC shall excavate and check as soon as the area is clear. During line checking of Test package 1504-02 HT-002 at Furnace area were observed the Globe Valve socket weld type against the flow direction as per IFC drawing No. CO16103AFA-CF-114040-02 Rev.3F1. This vioklates G4S-7200-01, Para. 2.1.5 and and not accoradnace with G4S-727-01, Para 5.4 "Manufacturer" instruction, welding for all socket welded" Contactor shall provide necessary CAR. It was noticed that the foundation slab of cooling tower basin have cracks greater than .10mm which extends from the jump to the center of the fouundation slab and some to the other side of the wall. The coating applicators are just filling the cracks and proper method of repair as per the approved method statement is not being complied. Contractor: ARCC Operation group already cut and reweld JT-FW-21 & FW-22 to correct wrong flow direction of globe valve and also NDE/PT done. Contractor: At crack gas compounf (deck slab), the cutting of concrete was already done and there is a small balance portion that cannot be proceeded to cut it because the area is still use by other subcon and work can proceed after the removal of scaffolding suport. PN: During monitoring and surviellance activities at Crack Gas Compressor "Deca Slab", it was noticed that after casting the slab the control joint was not implemented after 10 days wherein the concrete was already hardened. Contractor shall take corrective and remedial action on this issue. During routine inspection at cooling tower room #7 & 3, it has been observed that IKK had no treatment expansion joint as per approved method statement (A554-E-103-CM-GEN-PLN-024) section 3.2 of applied only Materbrace ADH 2200. Page 61 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 30, 2014 DUE DATE Issued corrective action to Company Target Date S/N LBE NO. PID SUBCON/ CONTRACTOR VAF / PN LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason Company comment Approved Close LBE by Company STATUS CONTRACTOR'S CORRECTIVE ACTION PLAN 84 LBE-TCC- MECH-546 MR. RAMO TCC VAF 3 MECH Piping 09-Jun-10 12-Jun-10 Open 85 LBE-PSCL- MECH-547 MR. KURIAN PSCL VAF 3 MECH Coating/ Painting 10-Jun-14 13-Jun-14 Open 86 LBE-KCC- CIVIL-291 MR. JERRY KCC VAF 2 CIVIL Civil 10-Jun-14 13-Jun-14 21-Jul-14 Open LBE-ARCC-MECH- 548 MR. RAMO ARCC VAF 3 MECH Piping 12-Jun-14 15-Jun-14 16-Jun-14 07-Jul-14 Closed 87 LBE-DLM- MECH-549 MR. SAYED DAELIM (Construction) VAF 3 MECH Piping 12-Jun-14 15-Jun-14 Open 111 LBE-IKK- CIVIL-292 MR. BUCASAS IKK VAF 2 CIVIL Civil 12-Jun-14 15-Jun-14 22-Jul-14 Closed 88 LBE-ASYAD- INST-019 MR. PERVEZ ASYAD VAF 1 INST Qaulity Management 14-Jun-14 17-Jun-14 21-Jun-14 24-Jul-14 Open 89 LBE-AMA- MECH-550 MR. NASSAR AMA VAF 3 MECH Coating/ Painting 15-Jun-14 18-Jun-14 20-Jul-14 Open 90 LBE-GACC- MECH-551 MR. RAMO GACC VAF 3 MECH Preservation 15-Jun-14 18-Jun-14 15-Jul-14 20-Jul-14 Open 95 LBE-PCMC- MECH-552 MR. NASSAR PCMC VAF 3 MECH Coating/ Painting 16-Jun-14 19-Jun-14 23-Jul-14 20-Jul-14 24-Jul-14 Closed- 91 LBE-AMA- CIVIL-293 MR. RAHMAN AMA VAF 2 CIVIL Civil 16-Jun-14 19-Jun-14 20-Jul-14 Open During surveillance, it was noticed that AMANA has repaired corroded hot dip galvanized ladder rungs in Sump pit #644 without notification for inspection for SQIT Coating, still not dry since one week due to improper surface preparation & coating application. This is for information & corrective action by Contractor. During surveillance at GACC (W5) area were found the piping materials are laying on the ground without any protection or cover end of the check valve. This violates RT-6-1CS Material and Equipment protection and Preservation Plan Rev. 3, Sec. 2.19, Para. 2.19.1 "All materials shall be suitably stored and protected from the site conditions" Para. 2.19.12 )d). Storage methods shall protect materials from infiltration of water, dust, dirt, vermin, insect, etc. Contractor shall provide necesary CAR. Contractror: The following LBE No. 551 has been noted and the necessary corrective action has been taken for the same. Tool box meeting was conducted. During routine inspection on test package #1625-00-HT-044 (RFI No. MFC- DLM-PCMC-H-S-S-0418) it has been noticed that applied paint didn't dry yet. Application was done one day before inspection. Application paint not fully dry due to improper mixing ratio. This is ofr information, corrective and preventive action shall be taken by contractor/subcontractor to avoid mistakes in the furture. Subcontractor: Applied wet paint was removed and did surface preparation and applied top coat as per Sadara requirement. RFI (0418) was inspected and accepted by Daelim for Package No. 1625- 00HT-004. During surveillance, it was noted that the Contractor has started external coating Renderoc FC on west side without any RFI for cooling tower. 1. Concrete repair work acceptance, 2. Surface preparation for concrete coating pre-application inspection. As per ITP. Subcontractor: Due to misunderstanding, Amana did not raised RFI for surface preparation for Rooms # 1 & 2, effectively from 17th of June Amana has raised RFI for surface preparation for Room # 3, 4, 5, 6, 7, 8 & 9 which are approved by Sadara Inspector. During surveillance at Compressor area were observed the 3" CVA-237114- 02" TW-237040-01-A. This violates G4Z-0010-00, Sec. 6.10, Para. 6.10.2 "Clearance shall be maintained" and G4D-0142-01, Pipe spacing chart Notes: 6 table. During surviellance at site , it is observed that subcontractor erected structural members (Column & its hanging) for Clarifier tank (V-0568) supplied by Tsukishima Kankyo Eng. Without final chemical protective coating (only primary coating found). In A554-E-103-MJ-REQ-MU4-115 states that it is the responsible of the Contractor to apply complete final coat if the mechanicm is shop blasted and poured with manufacturers' procedures. See Para. (coating 1, 2, 3). Contractor: Required revised drawing. During witness Hydrostatic test of test package (1504-02-HT-002) at ARCC area were found the water is contaminated of "Deminerailzed Water" as per actual sample of DMW with attached certificate. This is violates to General Requirements for pressure testing and Lay-up, Sec. 8.2, Para. 8.2.1 to 8.2.8. Contractor shall provide necessary CAR. Contractor: ARCC operation group re-test the the test pack AGES TP-1504-02-HT-002. See attached RFI No. MFC-DLM-ARCC-PIP-0483 and Water lab test result. During surveillance at cooling tower corridor wall near basin oom 7 and sump area A, it was found out that some repaired concrete wall tie rod holes, honecombs, etc are still soft until to date. This is a violation to schedule "Q" , General requirement sec. 1.3. Contractor shall investigate root cause and initiate corrective action. The Contractor was reminded of the requirements of Hot weather concreting prior to concrete placement of pavement as per RFI No. MFC- DLM-KCC-CI-7691 (Paving area B-A Span 65 & 66). The contractor continued to place concrete in spite of violation of RT2S-3001-01, section 5.4.8 which states: a. Shade temperature exceeds (110F) 43C at the job site combined with a mean speed of 10 mph or over. No measure to prevent exercise moisture loss before the final curing procedure are accompanied in the requirement of RT2S-3001-01, Para. 5.1. The shade temperature at 10:30 AMis 44.5. No apparatus to measure the wind velocity, relative humidity, etc. to check the rate of evaporation per table 2.1.5 of sec. 1305. Contractor: All concrete pouring shall start now at 5:00 PM onwards (July 21, 2014). During Site surveillance, it was observed that ASYAD has a shortage of QC Inspector. Contractor has 6 Inspectors while ASYAD has only 3 Inspectors and its Manpower is more than 200. This violates Schedule "Q" Contractor is requested to take preventive action. Contractor: Recently, ASYAD has 4 QC Inspector & waiting for SADARA approval for 1 remaining QC Inspector. Contractor will arrange additional QC Inspector as per Sch. "Q" within two weeks. During field leak testing of resilient seated butterfly valves in NASICO testing facilitiy Jubail, it is observed that there is a continues bubbles found in 8 nos of EBV during all 7 valves all rejected. This violates API 598 Table 6 which states that "These shall be no leakage for the minimum required test duration for all soft seated valves. Page 62 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 30, 2014 DUE DATE Issued corrective action to Company Target Date S/N LBE NO. PID SUBCON/ CONTRACTOR VAF / PN LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason Company comment Approved Close LBE by Company STATUS CONTRACTOR'S CORRECTIVE ACTION PLAN 92 LBE-AMA- CIVIL-294 MR. RAHMAN AMA VAF 2 CIVIL Civil 16-Jun-14 19-Jun-14 25-Jul-14 Open 93 LBE-FCN- CIVIL-295 MR. JERRY FCN VAF 2 CIVIL Civil 17-Jun-14 20-Jun-14 Open 94 LBE-DAELIM- CIVIL-296 MR. JERRY DAELIM (Enginnering) PN 2 CIVIL Engineering 17-Jun-14 20-Jun-14 15-Jul-14 Info 95 LBE-DAELIM- CIVIL-297 MR. JERRY DAELIM (Enginnering) PN 2 CIVIL Engineering 17-Jun-14 20-Jun-14 15-Aug-14 Info 96 LBE-AMA- CIVIL-298 MR. GERALD AMA VAF 2 CIVIL Civil 17-Jun-14 20-Jun-14 20-Jul-14 Open 97 LBE-TCC- CIVIL-299 MR. GERALD TCC PN 2 CIVIL Civil 17-Jun-14 20-Jun-14 20-Aug-14 Info 98 LBE-SEN- ELECT-016 MR. PERVEZ SENDAN VAF 1 ELECT Preservation 18-Jun-14 21-Jun-14 30-Jul-14 Open LBE-ASYAD-INST- 020 MR. PERVEZ ASYAD VAF 1 INST Instrumentation 18-Jun-14 21-Jun-14 22-Jun-14 13-Jul-14 Closed LBE-ASYAD-INST- 021 MR. S.KHAN ASYAD VAF 1 INST Instrumentation 18-Jun-14 21-Jun-14 20-Jun-14 23-Jun-14 Closed LBE-KCC-CIVIL-300 MR. BUCASAS KCC VAF 2 CIVIL Civil 19-Jun-14 22-Jun-14 28-Jun-14 29-Jun-14 Closed 99 LBE-KCC- CIVIL-301 MR. GERALD KCC VAF 2 CIVIL Civil 21-Jun-14 24-Jun-14 Open 100 LBE-AMA- CIVIL-302 MR. GERALD AMA PN 2 CIVIL Civil 21-Jun-14 24-Jun-14 20-Jul-14 Info LBE-DLM-INST-022 MR. S.KHAN DAELIM VAF 1 INST Instrumentation 21-Jun-14 24-Jun-14 22-Jun-14 26-Jun-14 Closed During surveillance, it was noted that Amana is doing External Concrete Coating for Cooling Tower west side without any QC Civil Inspector coverage. This is a violation to Schedule "Q", attachment VI, VI-1, PQP Personnel requirements. It was observed that after the fireproofing of vessel using Pyrocrete 241, the cementious fireproofing developed cracks on several locations of the structure. Please investigate the causes and provide corrective measures to avoid recurrence. PN: The dowels for the arbwall at the southside and of T-1710, D-1715 and Pumps area were not placement for foundation of adjacent piperacks. Please investigate and verify location since the drawing shows, it crosses the TPER by several inches only and confirm in the Enfineering to relocate to avoid cracks in future. PN: The evaluation of Paving in between the piperacks at North of Cooling Tower and Southeast by Building East 6-1121 is not level with the foundation of the piperack. The cover of the open trench in that location, therefore, will have a different elavations. Please advise Engineering for the remedial works on this location. Subcontractor: Amana already assigned the inspector to monitor the external concrete coating work at cooling tower. Contractor: Daelim shall provide drawing regarding this issue. During surveillance and monitoring activities at Operator building (6-1122), it was observed that mostly of the rooms are already installed acoustical ceiling (SMIC-M-1053), Inspection checklist for acoustic suspension ceiling system installation inspection also check some opening on walls. In this regards, Contractor should take corrective action concerning this issue for proper documentation. Contractor: Contractor will provide the lugs instrument side after completed the work and resubmit the RFI for inspection. Subcontractor: ASYAD will provide additional support in between splice plate for the cable tray. During inspection at site (cooling tower), it was noticed that Contractor terminate the cable instrument side without lugs. This violates G-070-0401-12, Para. 5.2. Contractor is requested to take preventive action. During inspection of 300mm ladder cable installation at Liquid Furnace (F-1250) area, it was observed that there were two (2) splice between support. This is violation to NEMA V-2, Section 4.3.1 which states that to ensure no more than one splice is located between supports. From field Junction box to cabinet not require the wire marker as per RT6E-0804-01. Note: 2 and IFC drawing A554-E-103-IC-DWG-1D3-001, This is SPI format engineering can not change because it is standard format. During surveillance, it was observed that the primary instrument cable in field junction box and cabinets has terminated without wire tag/ wire marker. This is violation to approved IFC Drawing A554-E-103-IC- DWG-ID3-001, page 4 of 4, not-2, which states that each terminated pair shall have a printed wire marker. KCC grouted the anchor bolt at North south side top wall of pump sump no. 7 of cooling tower without raising RFI's for the following inspections: 1. Surface Preparation 2. Forworks installation inspection 3. Grout sampling, testing & placement Violation to RT2S-3050-01, section 3, schedule Q, general requirements, sections 1.1 & 1.6, attachment IV, section 1.1.3 & 1.1.9. Contractor: Already rectified and chipped the area of North-South side of cooling tower pump sump, room # 7. Raised RFI for this area and inspected by Sadara representative. Subcontractor: Amana has started the rectification work sspension ceilling system and opening work. Amana will raise/submit RFI room by room inspection. PN: During surveillance at flare area, it was noticed that two (2) pedestals was deformed or bent the acnhor bolts. Contractor should investigate and take corrective action about the issue for proper implementation. During site surveillance inspection at decoke area, it was observed that the 4.16 KV provision voltage motor of air compressor tag # MC-2701 and MC- 2711, were installed at site without energizing the motor space heater. This violates as per material and Equipment Protection and Preservation Plan doc. #RT-6-1CS, Para. 2.7.2. PN:During surveillance & monitoring at Sub-station G-1120 & G-1121. It was noticed that most of the doors's accessories have already been installed but Contractor did not submit Final Acceptance Inspection (SMIC- M-1051) ITP Checklist. Contractor shall submit RFI for proper checking of those accessoties and proper documentation. Subcontractor: Amana has started the door rectification work and they will submit the RFI once the soor is totally sccepted by internal inspector. (On-going). With reference to RFI #MFC-DLM-KCC-CI-7890-0A & F7932, installation of epoxy coated steel bars & embeded item/floor closure inspection (deck slab) at area D-G common computer shelter GL 13-16/A-D, Contractor did not submit RFI and no advice from Daelim Inspectors to Company for proper checking of repair arrangement and diameter as per latest IFC drawing and also this RFi was "Hold" point. This is a violation to Schedule "Q" attachment IV, Para. 1.1.3 & 1.1.9/3.7. Contractor should take corrective & remedial action on the issue. (RFI was rejected). Page 63 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 30, 2014 DUE DATE Issued corrective action to Company Target Date S/N LBE NO. PID SUBCON/ CONTRACTOR VAF / PN LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason Company comment Approved Close LBE by Company STATUS CONTRACTOR'S CORRECTIVE ACTION PLAN 126 LBE-IKK- MECHI-553 MR. NASSAR IKK VAF 3 MECH Mechanical 21-Jun-14 24-Jun-14 26-Jul-14 Closed- 106 LBE-PCMC- MECH-554 MR. NASSAR PCMC VAF 3 MECH Coating/ Painting 21-Jun-14 24-Jun-14 23-Jul-14 20-Jul-14 24-Jul-14 Closed- 101 LBE-DLM- ELECT-134 MR. FELOMINO DAELIM (Enginnering) VAF 1 ELECT Engineering 22-Jun-14 25-Jun-14 25-Jun-14 Open 102 LBE-SEN- ELECT-135 MR. FELOMINO DAELIM (Enginnering) VAF 1 ELECT Engineering 22-Jun-14 25-Jun-14 25-Jun-14 Open 103 LBE-AMA- CIVIL-303 MR. RAHMAN AMA PN 2 CIVIL Civil 23-Jun-14 26-Jun-14 20-Jul-14 Info 104 LBE-TCC- CIVIL-304 MR. BUCASAS TCC VAF 2 CIVIL Civil 24-Jun-14 27-Jun-14 Open 146 LBE-DLM- INST-023 MR. PERVEZ DAELIM (Enginnering) PN 1 INST Engineering 23-Jun-14 26-Jun-14 22-Jun-14 16-Jul-14 Closed 107 LBE-SEN- ELECT-017 MR. S.KHAN SENDAN VAF 2 ELECT Preservation 23-Jun-14 26-Jun-14 20-Jul-14 30-Jul-14 30-Jul-14 Closed- 108 LBE-DLM-TEL- 018 MR. S.KHAN DAELIM (Preservation) VAF 1 TELECOM Preservation 23-Jun-14 26-Jun-14 20-Jul-14 30-Jul-14 Closed- 109 LBE-ARCC- MECH-555 MR. S.KHAN ARCC VAF 3 MECH Piping 23-Jun-14 26-Jun-14 24-Jul-14 Closed- PN: During surveillance and work monitoring, it was noted that the repair material is not fully bonded to the surface after recommended curing time b manufacturer. Contractor is pro-actively advised to take Pull of Test to determine the Tensile Strength of repair material as per Approved ITP for coating/waterproof lining. 1. Document No. A554-E-103-QA-GEN-PLN-119, checklist no. SMIC-R-103, item no. a4, E6. 2. Concrete repair guide - ACI- 546R-04, Para no. 2.7 "In-place-tensile pull-off tests are recommended to evaluate that bonding of repair materials is adequate. 3. Document no. A554-K-PRG-PI-DPC-VIA-150, aProtective Coatings for Industrial concrete structures, Para. 8.6.4. During routine inspection at room #5, it as been observed loss of adhesion has occurred due to poor or inadequate repair of honeycomb defect prior to surface preparation. Consequently, coating not obtain the required adhesion to concrete surface. Coating layers including repair materilas can be removed easily by finger. This defect loated in the different locations and rooms. Subcontractor: Mid-Coat was removed and primer coat was inspected and accepted by Daelim prior to apply mid-coat for Package No. 1441-00-HT-002 & 1625-00-HT-016. During routine inspection for Package # 1441-00-HT-002 & 1625-00-HT- 016, it has been noticed that PCMC has applied Mid-Coat prior to inspection time. This is non-conformance with Schedule "Q". During surveillance, it was noticed that after epoxy grouting on foundations of pump 1411C located at south side of east-west piperack, pumpsump area foundations of cooling tower 901C, 901E, 901F, 901G & 901H that cracks developed on the surface of the foundations. Contractor shall investigate the root cause and initiate corrective action to avoid recurrence. Electrical cables at site are now covered & protected with end caps after cutting activity at site. SENDAN is now aware and well-informed of the importance of end cap protection after cutting. During site surveillance, it was found that the electrical cables are not protected with end caps after cutting at site near substation 1120. This is violation to G7C-0305-02, Para. 4.4. which states that the cables shall be carefully protected from normal field construction hazards. Cable ends shall be sealed using heat shrinkable end caps to prevent entrance of moisture. PN: During site surveillance at site, near caustic tank NS pipe rack D-1090, it was observed that transmitter obstructs with the fire water pipe, no maintenance access for Instruments. This violates G0GA-041-00 Para. 61.3.3.3. Contractor requested to take preventive action. Subcontractor: Instrument was temporarily fixed before issuing RFI, subcontractor will rectify and submit RFI for inspection. Contractor: Engineering will coordinate to Riyadh Cable for investigation on how this issue will be solved. -> TM or RFV shall be issued. Meanwhile, we received from vendor statung that there is no problem. Contractor: Contractor will coordinate to Zamil for explanation in this failed result During surveillance inspection of Substation G-1120 & G-1121 & North South and near cooling tower, it was observed that the LV power cables were install underground trench for street ligting is above grand type of cable the outer sheath of cable is color black. This violates RT70-0430-00, Para. 37.2 and 3.8. During winding installation resistance test of RFI #MFC-DLM-SND-EL-1610 for compressor notor #1, G-1120-ACCU-001A at Mechanical room substation G-1120, it was observed that the test result has failed the actual valve was 10.7 mega-ohms. This violates as per Company Pre- commissioning Porcedure G7M-0020-08, which is the acceptable valve of winding installation test shall be 100 me ohms. During routine inspection at CI area, ARCC welders were found welding 2" pipe with unapproved WPS for CA-09 / caustic line clay. 5 joints were identified for approval of WPS. C016103C1A-CA-059703 JT. No. 10, 12, 14. C016103CIA-CA-171315-02, 07. During site surveillance, it was found that the Fiber Optic cable end has exposed at site for all analyzer. This is violation to RTIP-A554-R-001-IS- SPC-EG4-508, Para. 7.6.2 which states that "all FO cable ends are to be effectively sealed (waterproof) at all stages of use. Sealing shall be performed immediately after a length of cable has been cut from a drum. Exposed part of Fiber Optic cable (end part) has now covered and protected by using tape for sealing against water. Other contractor (WIPRO) is now well informed regaqrding protection of fiber optic cable end. Page 64 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 30, 2014 DUE DATE Issued corrective action to Company Target Date S/N LBE NO. PID SUBCON/ CONTRACTOR VAF / PN LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason Company comment Approved Close LBE by Company STATUS CONTRACTOR'S CORRECTIVE ACTION PLAN 105 LBE-ARCC- MECH-556 MR. RAMO ARCC VAF 3 MECH Piping 23-Jun-14 26-Jun-14 Open 106 LBE-GACC- MECH-557 MR. KURIAN GACC VAF 3 MECH Mechanical (Equipment) 24-Jun-14 27-Jun-14 20-Jul-14 Open 107 LBE-TCC- MECH-558 MR. SAYED TCC VAF 3 MECH Piping 25-Jun-14 28-Jun-14 24-Jul-14 20-Jul-14 Open 117 LBE-PSCL- MECH-559 MR. NASSAR PSCL VAF 3 MECH Tank 25-Jun-14 28-Jun-14 23-Jul-14 24-Jul-14 Closed- 108 LBE-ARCC- MECH-560 MR. RAMO ARCC VAF 3 MECH Piping 25-Jun-14 28-Jun-14 Open 109 LBE-SEN- ELECT-136 MR. MARK SENDAN VAF 1 ELECT Electrical 25-Jun-14 28-Jun-14 27-Jun-14 30-Jul-14 Open 110 LBE-AMA- CIVIL-137 MR. MARK AMA VAF 1 CIVIL Civil 25-Jun-14 28-Jun-14 28-Jun-14 30-Jul-14 Open LBE-ASYAD-INST- 024 MR. PERVEZ ASYAD PN 1 INST Instrumentation 25-Jun-14 28-Jun-14 25-Jun-14 12-Jul-14 Closed 111 LBE-ASYAD- INST-025 MR. PERVEZ ASYAD VAF 1 INST Instrumentation 25-Jun-14 28-Jun-14 25-Jun-14 Two Weeks Open 142 LBE-ASYAD- INST-026 MR. PERVEZ ASYAD VAF 1 INST Qaulity Management 25-Jun-14 28-Jun-14 26-Jun-14 19-Jul-14 22-Jul-14 Closed LBE-ASYAD-INST- 027 MR. PERVEZ ASYAD PN 1 INST Instrumentation 26-Jun-14 29-Jun-14 17-Jul-14 12-Jul-14 Closed LBE-ASYAD-INST- 028 MR. PERVEZ ASYAD PN 1 INST Instrumentation 26-Jun-14 29-Jun-14 01-Jul-14 12-Jul-14 Closed 112 LBE-SEN- ELECT-138 MR. MARK SENDAN VAF 1 ELECT Electrical 26-Jun-14 29-Jun-14 27-Jun-14 30-Jul-14 Open Contractor: Conractor already provided the Gas detector blind plug. During site surveillance at C3 Splitter pipe rack, it was noticed that Branch Cable laid in was improper way of cable hanging on scaffolding. As observed, JB cable not protected from machines. This violates NEC Article 110.12 and Schedule Q, Contractor requested to take a preventive action. Contractor: Durign cable pulling, cables were hanging so that it will not be damaged and use as walkway. Dressing is done. PN: During site surveillance at cooling tower side filter unit, it was noticed that Level Transmitter (Capillary type) not Preserved. Capillary hanging and kept on walk ways. This violates Project Specs G06A--0041-00, Para. 61.3.3.3, Installation deatil G-06E-04010-01, Contractor requested to take preventive action. Contractor: ASYAD will rectify installation of level transmitter (capillary type) in proper ways and inform to construction to keep away on the walkways to maintain preservation or protections. During site surveillance (all area) at site (general), it was noticed that Contractor installed PVC tie instead of 316 Nylon cooled ties. This violation RT6E-0802-01, Para. Note-10, Contractor requested to take a preventive action. Contractor: SS 316 Nylon coated ties are not available as of now but the material shall be ordered and as soon as it available, Contractor/Subcontractor will change the temporary ties to SS316 Nylon coated ties. During routine site inspection at Operator building G-1122, it was noticed that the contractor installed felxible metallic conduit that was more than 1.8 meters in length which is a violation as per NEC, Article 348.20 (A) (2) c. Contractor: The installation done as per IFC drawings for corrective action and proposal, Contractor/Subcontractor will coordinate with Engineering. During routine site visit at Operator building 6-1122, it was found out the Contractor used the cable tray as a support for the T-runner of the false ceiling which is a violation as per 67C-0321-01, section 1-2. Contractor: Construction already instructed to remove the tie wire which connected to channel tray During line checking and inspection at Furnace area were found the piping flanges with spectacle blinds was installed without hole for jack screw twelve (12) locations and EL+15400 TP (1615-01-HT-003) This violates Project Specification for Mechanical Completion and Acceptance Rev.2 (A554-K-PRG-CM-GEN-DOC-005) Attachment 4, sec. 4, Para. 4.1.5 Install jacking bolts on all flanges with spectacle blinds. A logbook entry was made and informed to PMT/Contractor. During surveillance, it is noticed that during night shifts in tower T-1710, the subcontractor is installing tray and TSR without inspection of levelness, no RFI's were raised for the installation levelness inspection scale pan, tray 1,2,3. Also no subcontractor QC was available during this inspection. Daelim should ensure that concerened QC is raising RFI of the installation of internal activities of tray with the presence and/or involvement of subcontractor QC. It is a violation as per A554-E-103-QA-GEN-PLN-103, Para. 3.39, 3.33 Sch. Q, attachment VI. Contractor: Already one QC Inspector has been assigned for the night shift and has been attending inspection in the night shift from 2nd of July onwards. The Trays 1,2,3 have already ben completed and RFI's for the same already been submitted. The concerned RFI nos. are MFC-DLM-GA-ME-0060, 061, 062, 0063 & 0064. All the inspections are now goin in line with the requirements and in the presence of QC Inspector. During surveillance inspection at TCC area cold box, it was fond that triunion support directly welded to pipe is not in the center of run pipe. This is not accordance of support standard drawing GF31P-F4-005 & DF33P-F- 3-002 which shown run pipe and triunion support pipe center are in on line. Subcontractor: Already cut-out and refit-up. Welding RFI already accepted. During surveillance at Process condensatre holding tank V-1425, it has been observed that PSCL has applied primer coat zinc richepoxy (interzinc 22) for roof top area which is not meeting with Mechanical dataa sheet. As per Mechanical data sheet, the required paint code system is GI6S-0202- 02 (Inorganic zinc primer, epoxt mid coat and Polyurehane) and applied paint socd system is G16S-0202-10 (Zinc rich epoxy 1 epoxy mid coat and polyurethane finished. A log book entry was issued to require corrective and preventive action. Contractor: As per SADARA transmittal No. MFC-T-CJ-DC-VP-5354. The variance is accepted. During line checking of test package (1601-02-HT-021) at ARCC (F-1110) were found the marking of welding joint identification and welder symbol is away to the exact location FW-04. This violates In addition to LBE No. 22, subcontractor failed to provide Quality Manager while the works are on-going, aside from its lack of QC inspectors at site. This violates schedule "Q", attachment VI. Contractor is requested to take actiojn as soon as possible. Contractor: For the corrective action for the same, Contractor/Subcontractor will use unistrut channel below the cable tray flange at both sides. Tha sample will be inspected and if it' is required any more recrification, it will be corrdinated with the Engineering. During routine site visit at East side of substation G-1121 & cooling tower, it has been coticed that the aluminum and fiberglass cable trays were deflected at the splice plates next to expansion splice plate. This is violation as per NEMA VE-2, Section 4.2.1. Contractor: Contractor already issue NCR to Asyad. During inspection, it was observed that Gas detector installed without blind plug. This violates RT-61CS, appendix 3, Contractor requested to take preventive action. Page 65 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 30, 2014 DUE DATE Issued corrective action to Company Target Date S/N LBE NO. PID SUBCON/ CONTRACTOR VAF / PN LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason Company comment Approved Close LBE by Company STATUS CONTRACTOR'S CORRECTIVE ACTION PLAN 113 LBE-SEN- ELECT-139 MR. MARK SENDAN VAF 1 ELECT Electrical 27-Jun-14 30-Jun-14 28-Jun-14 30-Jul-14 Open 124 LBE-PCMC- MECH-561 MR. NASSAR PCMC VAF 3 MECH Coating/ Painting 28-Jun-14 01-Jul-14 23-Jul-14 28-Jul-14 24-Jul-14 Closed- 125 LBE-TCC- MECH-562 MR. NASSAR TCC VAF 3 MECH Coating/ Painting 29-Jun-14 02-Jul-14 23-Jul-14 20-Jul-14 24-Jul-14 Closed- 114 LBE-PCMC- MECH-563 MR. KHAN PCMC VAF 3 MECH Piping 30-Jun-14 03-Jul-14 28-Jul-14 Open 148 LBE-IKK- MECH-564 MR. NASSAR IKK VAF 3 MECH Coating/ Painting 30-Jun-14 03-Jul-14 22-Jul-14 Closed 127 LBE-PSCL- MECH-565 MR. HARIKUMAR PSCL VAF 3 MECH Tank 30-Jun-14 03-Jul-14 15-Jul-14 26-Jul-14 Closed- 1145 LBE-GACC- MECH-566 MR. RAMO GACC VAF 3 MECH Piping 30-Jun-14 03-Jul-14 15-Jul-14 20-Jul-14 Open 116 LBE-ARCC- MECH-305 MR. BUCASAS ARCC PN 3 MECH Mechanical 30-Jun-14 03-Jul-14 Info 165 LBE-KCC-CI- 306 MR. ENDRANO KCC VAF 2 CIVIL Civil 02-Jul-14 05-Jul-14 Closed 130 LBE-GACC- MECH-567 MR. RAMO GACC VAF 3 MECH Piping 03-Jul-14 06-Jul-14 15-Jul-14 25-Jul-14 26-Jul-14 Closed- Contractor: The LBE No. 566 has been noted and the valve has been preserved and installed to its respective line. PN: During surveillance at North side of furnace area, it was noticed that excessive crack appears on the surface of epoxy grouted FD Fan foundations F-1164, F-1174, F-1244 & F-1254. This a repeated violation and Contractor should take immediate action to resolve this issue. Contractor is proatively advised to call for the attention of the epoxy grout manufacturer for any recommendations/action to avoide resurrence. During surveillance & monitoring activities at Deck Slab area D-6 common compressor shelter GL: 1-6/A-D at elevation 27,200, noticed that newly casted deck slabs have insufficient water curing application and some burlap/polythylene sheets are not properly covered with some materials on top of the slab. This is a violation of Sadara Standard RT2S-3001-01, Section 9, Para. 9.1.2. states that "Water curing shall be continuous until the compressive strength has reached 70% of the specific strenght but not less than 7 days after placement. Contractor must take corrective/remedial action on the issue for proper implementation. During surveillance at Compressor area W5 were observed the "6-CWS pipe spool was erected ad not maintained the clearance from concrete foundation. This violates G4Z-0010-00, Sec. 6.10, Para. 6.10.2 "Clearance shall be mainatined" and G4D-0142-01, Pipe Spacing Chart Notes: See Table,. A logbook Entry was made and informed to PMT/Contractor. Contractor shall provide necessary C.A.R. Subcontractor: LBE No. 567 has been noted and in this 2 joints will be cut and line shall be deducted to 50mm. It has been informed and shown to DAELIM Construction Piping Supervisor of W5 area and they will issue JCR and then need to be followed. TCC did this before so needs to be closed. During routine site visit, it was noticed that the Contractor used a HDG bolt for the installation of enclosure at the lightning pole at the west side od substation G-1121 which is a violation as per A554-K-PRG-EL-GEN-PHL- 005, Section 3.4.4. Contractor: The HDG bolt of enclosure will be replaced by SS bolt. The replacement of bolts are already in progress. During scheduled inspection for shaft alignment for V-056 and V-0567 Flocalation mixing tank)., observed the following violation: *Tank bottom is not rested on base structure which is showing 50mm gap between base structure and bottom of tank. *Anchor bolt hole fabricate an improper method and exceeded the hole size more than allowable limit. * Daelim Engineering shall investigate and prepare appropriate corrective action to controll the elevation variance on subjected tank. During surveillance at GACC (W5&K1) area were found the butterfly valve was on the ground and without any cover or protection end of the Butterfly valve and visible the dust / grit blasting materials and foreign object. This violates Material & Equipment Protection and Preservation Plan -3 (RT- 61CS) Sec. 2.13, Para. 2.13.1 (a) "Valves stored outdoors must be protected from blowing sand and salt spray", Para. 2.19.12 and (d). Storage methods shall protect materials from infiltration of water, dust, dirt, vermin, insect, etc. A logbook enrty was made and informed to PMT/Contractor. Contractor shall provide necessadry C.A.R. Subcontractor: LBE No. 566 has been noted and the valve has been installed to its respective line. Therefore, please verify and close this LBE. During surveillance at MFC site during field trouch up/repair for weld joint, it has been noticed that PCMC using an improper method for mixing (Pepsi can); mixing ratio for two component always mixed partially. As per Sadara spec (G1651-0101-54), partial mixing is a two-component and multi- component coating is probihited. An immediate action be taken by Daelim. During surveillance at MFC site during filed touch-up/Repair, it has been noticed that TCC using improper method for mixing ratio for two- component always mixed partially. As per Sadara specs (G16S-0101-S4), partial mixing in two components and multi-components coating prohibited. Immediately action shall be taken by Daelim. Contractor: Subcontractor advised to use measuring cups while doing partial mixing for Touch ups as per attached letter from manufacturer. Contractor: Subcontractor advised to use measureing cupas while doing partial mixing for Touch ups as per manufacturer letter. Found that PCMC welders were welding 10" Pipe joint of drawing # N016103T1A-CH-012209-01 without fit-up inspection, violating the ITP's hold point for PCMC. Last warning letter should be issued by Daelim Quality to welders (JCC #1318, 1391) and their welding Foreman. Subjected joint must be cut-out or RT'd without counting it is RT Percentatge. Daelim/PCMC QC needs to get corrective action immediatelywith preventive measures. AT Cooling Tower Room # 3 floor lining, it has been detected loss of adhesion for applied top coat. Loss of adhseion (cohesion failure) was found in between two layers. This is found defect in different locations of the floor. Immediate action shall be taken by Daelim. Page 66 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 30, 2014 DUE DATE Issued corrective action to Company Target Date S/N LBE NO. PID SUBCON/ CONTRACTOR VAF / PN LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason Company comment Approved Close LBE by Company STATUS CONTRACTOR'S CORRECTIVE ACTION PLAN 117 LBE-AMA- CIVIL-307 MR. RAHMAN AMA VAF 2 CIVIL Civil 05-Jul-14 08-Jul-14 20-Jul-14 Open 118 LBE-DLM- MECH-568 MR. KURIAN DAELIM (Enginnering) VAF 3 MECH Engineering 07-Jul-14 10-Jul-14 27-Jul-14 Open 119 LBE-DLM- MECH-569 MR. KURIAN DAELIM (Enginnering) VAF 3 MECH Engineering 07-Jul-14 10-Jul-14 21-Jul-14 Open 120 LBE-KCC- MECH-570 MR. RAMO KCC VAF 3 MECH UG-Piping 07-Jul-14 10-Jul-14 23-Jul-14 Open 121 LBE-KCC- CIVIL-308 MR. BUCASAS KCC VAF 3 CIVIL Civil 08-Jul-14 11-Jul-14 21-Jul-14 Open 122 LBE-IKK- MECH-571 MR. NASSAR IKK VAF 3 MECH Coating/ Painting 08-Jul-14 11-Jul-14 Open 123 LBE-TCC- MECH-572 MR. RAMO TCC VAF 3 MECH Mechanical 08-Jul-14 11-Jul-14 Open 124 LBE-KCC- MECH-573 MR. RAMO TCC VAF 3 MECH Mechanical 08-Jul-14 11-Jul-14 Open 125 LBE-KCC- CIVIL-309 MR. BUCASAS KCC VAF 3 CIVIL Civil 09-Jul-14 12-Jul-14 15-Jul-14 Open Contractor: Materials are already approved. The old materials was replaced by Emaco S85 instead of Emaco 301. During surveillance, it has been noticed that IKK has applied primer coat & using for Pump Sump A101, 02 & 03 at Cooling Tower without notifying the Company for inspection of surface preparation prior to apply coating and lining. As per Sch. "Q" and approved ITP, RFI notification shall be required. During Surveillance at Cooling Water Pump area were found the peel-off the expansion (rubber) due to excessive during bolt tihgtening at eight (8) locations pump nozzles. This violates G8S-8005-00, Sec. 6, Para. 6.2 "Cracking in this area indicates excessive stress and will need to be addresses before the flanged joint is re-assembled and 6.4.2.1 "Flanges should not have to be forced into alignment, friction, load and relaxation effects will be magnified during the preloading process if fasteners are used to force flanges into alignment". A logbook entry was made and informed to PMT/Contractor. Contractor shall provide necessary CAR. Reference to PRO-ACTIVE LBE #303, dated 23 June 2014, Contractor did not has not performed any Pull-of-Test as required before Coating for surface soundness. This is violation to Sadara Specs A554-K-PRG-PI-SPS- VIA-150, Para. 8.6.4. Contractor has proceeded without the required test, coating is on ongoing in Pump basin #03 & 04 whihc has violated the same Sadra specs. During TSR inspection for Tray-1310, it is noticed that the tray is without bracing for the beam support for all the tray throughtout the TSR. Engineering clarification required with proper approved repair procedure and its documentation for rectification. Surveillance inspection at Cooling Tower Pump Sump #8 for moch-up grout filling of opennings. However, it was found out that after removal of formworks, there were portions or gap not filled with grout. Actual measurement was checked and approximately 10cm depth or thickness of the wall not grouted. This is a violation to Sch. "Q", section 1.2, Sadara dcoument no. A554-E-103-CM-GEN-PLN-031. Contractor shall investigate the root cause and initiate corrective action. Subcontractor: After the removal of forms, the hollow portion of the grouted area was cleaned bt removing all loose materials & laittance. Formworks were re-installed, making sure no leakage will appear by putting sealant on the edge. After the preparation, the area was grouted using approved Materials masterflo 526. During work monitoring and surveillance, it was observed that KCC begun with the tie-rod holes repair at least side wall of cooling tower pump sump area using not approved material EMCO 301.Clear violation to Sadara document no. A554-E-103-WA-GEN-PLN-095, checklist SMIC-12-1003, ite, A. ITP for repair of cooling tower. Contactor is advised to rectify and comply as required. Contractor : DAELIM already issued technical memorandum for repair work of bracing to SADARA. And now we are communicating with SADARA's welding SME, Plummer, Robert for the welding of bracing. And we'll offcially issue the completed repair procedure after discussion with SADARA. Tower F1710 is found with the TSR down by 7 to 10mm down, Engineering clarification reuired with proper rectification. All rectification and repair work shouild be approved and documented. Contractor: For T-1710, we already got the approval of the repair work for leveling of TSR from SADARA. Now we are installing shim plate and adjusting the level of TSR and internal trays at site. During surveillance at Cooling Tower Water Pump area were found the crack at flanges corner radius of 48"-CWS line (FRP) due of excessive stress during bolt tightening at several location with six (6) flanges. This is violates G8S-8005-00, Sec. 6, Para. 6.2 "Cracking in this area indicates excessive stress and will need to be addressed before the flanged joint is a re-assembled" and 6.4.2.1 "Flanges should not have to be forced into alignment, Friction, load and relaxation effects will be magnified during the preloading process if factners are used to force flanges into alignment". A logbook entry was made and informed to PMT/Contractgor. Contractor shall provide necessary CAR. Subcontractor: The area was already visited by FPI representative and assured that it is a surface crack. FPI will submit a written report to Company to close this issue. During surveillance at V2 Compressor area were found the serration of raise face was damage with line number PR-250905-04-A. This is violation to Flanged Joints - an overwiew (G4D-4250-01), Sec. 8, Para. 8.1 "The gasket faces of flanged joints which have been opened and cleaned should be visually inspected for corrosion (pitting and oxidation) and for defects (such as scracthes, cracking. Finish damage, etc) & 8.2 "Flangeswith nicks, scrathes, cuts or finish damage must be repalced". A logbook entry was made nd informed to PMT/Copntractor. Contractor shall provide necessary CAR. Page 67 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 30, 2014 DUE DATE Issued corrective action to Company Target Date S/N LBE NO. PID SUBCON/ CONTRACTOR VAF / PN LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason Company comment Approved Close LBE by Company STATUS CONTRACTOR'S CORRECTIVE ACTION PLAN 126 LBE-DLM- MECH-574 MR. SURESH DAELIM (Procurement) VAF 3 MECH Material 10-Jul-14 13-Jul-14 Open 177 LBE-ASYAD- INST-029 MR. PERVEZ ASYAD VAF 1 INST Instrumentation 12-Jul-14 15-Jul-14 15-Jul-14 16-Jul-14 21-Jul-14 Closed LBE-ASYAD- INST-030 MR. PERVEZ ASYAD VAF 1 INST Instrumentation 12-Jul-14 15-Jul-14 16-Jul-14 16-Jul-14 Closed 127 LBE-ASYAD- INST-031 MR. PERVEZ ASYAD VAF 1 INST Instrumentation 13-Jul-14 16-Jul-14 24-Jul-14 Open 128 LBE-AMA- CIVIL-575 MR. NASSAR AMA VAF 3 CIVIL Civil 14-Jul-14 17-Jul-14 Open 129 LBE-DLM- MECH-576 MR. HARIKUMAR DAELIM (Procurement) VAF 3 MECH Material 14-Jul-14 17-Jul-14 Open 130 LBE-SEN- ELECT-140 MR. MARK SENDAN VAF 1 ELECT Preservation 14-Jul-14 17-Jul-14 17-Jul-14 30-Jul-14 Open 131 LBE-KCC- CIVIL-310 MR. BUCASAS KCC VAF 2 CIVIL Material 14-Jul-14 17-Jul-14 Open 132 LBE-AMA- CIVIL-311 MR. GERALD AMA VAF 2 CIVIL Civil 15-Jul-14 18-Jul-14 Open 133 LBE-DLM- MECH-577 MR. S.KHAN DAELIM (Enginnering) VAF 3 MECH Engineering 15-Jul-14 18-Jul-14 Open 134 LBE-IKK- MECH-578 MR. NASSAR IKK VAF 3 MECH Coating/ Painting 16-Jul-14 19-Jul-14 Open During Site Surveillance at EW Pipe rack column no 58, it was noticed that open channel tray was damaged by Electrical crew. This violates schedule Q, attachment VI para. 5 and G078-0322. Contractor requested to take preventive action and re-offer inspection to Company after modification. During site surveillance, it was noticed that in Gas Furnace area Contractor installed open-channel tray with two splice between support. This violates NEMA-VE-2 Para. 4.31, which states that "to ensure no more than one (1) splice between the supports. Contractor requested to take preventive action. Contractor: ASYAD already provided the support between two splice-joints for the channel cable tray. Please inform Contractor of applicable equipment numbers. Contractor: Subcontractor already advised to repair the PVC damaged. Company will be advised for the action taken. The Contractor/Subcontractor installed the Pre-fabricated gratings cover on ditches without the proper issuance of RFI for the Material receiving inspection. It was also noted that there was a variance of size on the cross bar from 10mm as per required to 8mm actual size delivered. This violates schedule Q section 3.2 and Standard drawing. QC inspector shall initiate the RFI in a timely manner per approved ITP. Contractor shall investigate the root cause and initiate corrective action regarding the size variance on cross bar gratings. During site inspection at Gas Furnace, it was observed that Open channel tray observed with piping and clading on going after insulation trap will be damaged, there is no clearance between tray and pipe. This violates G07C- 0321-3. & NEMA VE-2. Contractor requested to take a preventive action. Contractor: Rectification on going. It will be competed tomorrow, July 16, 2014. During Line inspection in Gas Furnace area, it was observed that Pipe used as a support to other Pipe or supportingone pipe on the top of another pipe. This is violation against with G4Z-0010-00, Para. 9.6.6 states that "all inside battery limit piping, supporting one pipe on the Top of another pipe or hanging a pipe from an overhead pipe is strictly prohibited". Line # SVH-117507-10-PU74, ISO drawing # N016103ACA-SVH-117507- 03, Support Type/No.: EPS-120. Note: This violation is aslo applicable for all 7 Gas Furnaces SHV piping, similar type supports. During surveillance at Cooling Tower, it has been noticed that dusting on the concrete surface during coating application at corridor (Wall GF: 4A & 5A) middle portions, non-clean surface causes loss of adhesion between concrete section shall be taken prior to apply final coat. During surveillance inspection at Diedsel generator building (G-1124), found out that gutter & support was already installed without raising RFI to Company. This is a violation Sadara inspection checklist (SMIC-M-1031-1) "Metal roofing/Flashing and trim material receiving inspection". Contractor should take corrective action. During surveillance inspection in Liquid furnace area, it was observed that, Contractor has been procuring wrong material Flow element Vnturi and welded with high pressure steam piping PU74. The material specification found A 183 Grade F11, instead of A182 Grade F22. This is violation as per PU74 Pipig Material Specfication (Base metal P22) and construction ASME B 31.3. FE Tag Numbers: FE121552, FE223552, FE123552, FE124552 and FE125552. Line Number SVH-122504-12 PU74 and application each lighuid frncaces. Contractor: New venturi flowmeter was ordered and fabrication is on- going During surveillance, it has been detected of Loss of adhesion for concrete coating at Sump Pit #645. Loss of adhision was found on the wall. The reason of failure is improper mixing ratio for repair materials during surface preparation. During Material Receiving inspection and pre-alignment verfication of Sump pump (vertical 7 unit) observed that significant defirence on RPM with Manufacturer name plate data and project data sheet. (Enbossed RPM on motor is 3480 instead of 3560) which couild be impact on efficiency time and dischargearation, etc. Daelim Engineering shall investigate and propose the corrective action prior to final alignment of subject of 7 units of pumps. During routine visit, it was noticed that the PVC conduits installed at the manhole at north side of substation G-1121 were already damaged due to cable pulling of power cables and the conduits do not have PVC end bells for the protection of the cables which is a violation as per NEC 352.46. Page 68 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 30, 2014 DUE DATE Issued corrective action to Company Target Date S/N LBE NO. PID SUBCON/ CONTRACTOR VAF / PN LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason Company comment Approved Close LBE by Company STATUS CONTRACTOR'S CORRECTIVE ACTION PLAN 149 LBE-ASYAD- INST-032 MR. SHABIRUL ASYAD VAF 1 INST Instrumentation 17-Jul-14 20-Jul-14 26-Jul-14 27-Jul-14 Closed- 135 LBE-KCC- CIVIL-312 MR. GERALD KCC VAF 2 CIVIL Civil 17-Jul-14 20-Jul-14 Open 136 LBE-SEN- ELECT-141 MR. FELOMINO SENDAN VAF 1 ELECT Electrical 19-Jul-14 22-Jul-14 23-Jul-14 Open 137 LBE-DLM- ELECT-142 MR. FELOMINO DAELIM (Enginnering) VAF 1 ELECT Engineering 20-Jul-14 23-Jul-14 Open 138 LBE-AMA- CIVIL-313 MR. BUCASAS AMA VAF 2 CIVIL Civil 21-Jul-14 24-Jul-14 Open 139 LBE-AMA- CIVIL-314 MR. ENDRANO AMA VAF 2 CIVIL Civil 22-Jul-14 25-Jul-14 Open 140 LBE-ARCC- MECH-579 MR. NASSAR ARCC VAF 3 MECH Coating/ Painting 20-Jul-14 23-Jul-14 Open 141 LBE-TCC- MECH-580 MR. RAMO TCC VAF 3 MECH Piping 21-Jul-14 24-Jul-14 Open 142 LBE-TCC- MECH-581 MR. NASSAR TCC VAF 3 MECH Coating/ Painting 22-Jul-14 25-Jul-14 Open During routine inspection on package # TP-1505-01-HT-027 & TP-15015- 01-HT-028, found at F1180 Top Level, it has been noticed that much cracking and loss of adhesion due to improper surface preparation. This is for necessary corrective action. During witness of Bolt Torquing and Butterfly valve, gasket verification at Cooling Water (TCC) V6 area were found the following violation. * Gasket missing between Butterfly Valve and Flange. * Double nuts were installed both side. This is violation to G4D-4250-01, Sec. 3, Para. 3.3 and G8S-8005-00, Sec. 3, Para. 3.1.1/3.1.2/3.1.3. * Wrong color coding of Butterfly Vavle (RED) This vis violation to RT16D-0120-01, Sec. 6, Para. 6 (a). Contractor shall provide necessary C.A.R. During routine inspectionm, it has been noticed that TCC coating applicator not cleaned the pipeline surface for process line (P-172702) at dryer Piperack prior to apply the coating. Shoes marks were detected in diferrent locations & coating applicator was applied for final coat without cleaning dirtied areas. Daelim inspector has witnessed this violation. This is for necessary corrective action. During surveillance & monitoring activities at North side of sub-station G- 1121 (Open Ditch) or SW due Type-1, found out that finishing work and alignment of this open ditch is not properly done and poor workmanship, especially on finishing touches. Contractor shall take remedial action on the issue in order that the work must be acceptable. This is violation to RT2S- 3001-01, section 10 & DWG # A554-E-CV-DWG-C70-038, Rev.2. During inspection at Cooling Tower Pump sump no. 7 with RFI No. MFC- DLM-AMA-CI-8011, it was found out that some areas on floor slab have surface irregularities, sharp edge projections which might damage the tissue mat lining system installation. This is a violation to Sadara document No. A554-K-PRG-SPC-VIA-150, section 6.1.3 the subcontractor shall rectify the surface irregularities with approved materials prior to coating application. The RFI is Rejected. During site surveillance, it was noticed Contractor installed wrong bolt and nut fasteners for Instrument channel tray. Once the correct materials are received, Contractor needs to change correct HDG M6 bolts. Location shall be identified properly to avoid mixing SEICO-103-6000-01-492-002 Rev. 002, MF-HW02 Subcontractor: It was tried to install but already removed. Installation was not being continued. Correct HDG MG Bolts were installed in all areas. During inspection of RFI # MFC-DLM-SDN-EL-1893 for cable pulling of Motor RTD cable was installed in the same cable tray of LV power cables. This violates as per G7C-0302-00, Para. 3.4.2. During surveillance inspection of LV control cables, 4Cx6mm2, 5CX2MM2, 30Cx2.5mm2 and ITRx2.5mm2 CU/XLPE/PVC, 0.6/1KV (MESC Cable) and 2PRX2.5MM2 (Dekoron cable), for Generator panel cable (GCP- 103H101) at Substation G-1120, it was observed the following violations: 1. LV Control has been installing at site without material receiving inspection. This violates as per Sch. "Q", Attachment IV, Para. 3.2. 2. LV Control cable has no marking per flame retardant in the outer sheath of the cable. This violates as per RT70-0430-00, Para. 1.7. Contractor: Engineering/Construction were advised on the necessary action on or remedy for this issue. During concrete placement, on July 16, 2014 at around 7:30 PM for (DVA 703-708) Fire wall, the forms collapsed. The side forms were removed on July 17, 2014. It was observed that the concrete placement was more than one (1) meter in height from the base slab, which is located at southwest potion of fire wall. This is a violation to Sadara RT2S-3001-01, section 6.1, Para. 6.1.2 & 6.1.3. Note that the fire wall must be monolithic or massive concrete. Contractor shall investigate the root cause and initiate corrective action to avoid recurrence. Page 69 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 30, 2014 DUE DATE Issued corrective action to Company Target Date S/N LBE NO. PID SUBCON/ CONTRACTOR VAF / PN LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason Company comment Approved Close LBE by Company STATUS CONTRACTOR'S CORRECTIVE ACTION PLAN 143 LBE-KCC- CIVIL-315 MR. GERALD KCC VAF 2 CIVIL Civil 26-Jul-14 29-Jul-14 Open- 144 LBE-TCC- MECH-582 MR. SURESH TCC VAF 3 MECH Piping 27-Jul-14 30-Jul-14 Open- During surveillance and monitoring activities at South side of Subtation G- 1122 (Operator Bldg.) Car Park shelter foundation on 2 (two) units, found out that Bitume coating applications are already done without RFI, which caused improper checking of Company especially on the required docomentations. This is a violation to schedule "Q", attachment IV, Section 1, Para. 1.1.3 & 1.1.9 and Sadara MFC inspection checklist (SMIC-H-1003) "Surface Preparation for concrete & building painting pre-applciation inspection. Contractor shall take remedial action on the issue in order that the work will be accepted. At Gas Furnace area, it was observed that Contractor has installed the wrong type of support and welded with Run Pipe instead of "EPS-105" type support. Reinforcing pad does not exist on installed support. As per ISO drawing, EPS-105 Support, reinforcing pas is required. This is violation against IFC Isometric drawing. Page 70 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 09, 2014 1 LBE-AMA- CIVIL-208 MR. JERRY AMA VAF 1 CIVIL Civil 20-Dec-13 2 LBE-AMA- CIVIL-231 MR. GERALD AMA VAF 2 CIVIL Civil 25-Jan-14 3 LBE-AMA- CIVIL-232 MR. JERRY DAELIM (Constructio n) VAF 2 CIVIL Civil 28-Jan-14 4 LBE-AMA- CIVIL-277 MR. ENDRAN O AMA PN 2 CIVIL Civil 06-May-14 5 LBE-AMA- CIVIL-282 MR. GERALD AMA VAF 2 CIVIL Civil 20-May-14 With reference to RFI #MFC-DLM-AMA-CI-7762, Roof leak testing on roof of substation G-1120. (GL G-11/AC), at around 2:20 pm starting spray of water using two (2) water truck using hose, continuously after and hour around 3:20 pm, they finshied spray of water and thats the time we found out that there are some areas with stagnant water, 2.40 meter from the edge of gutter and also four (4) locations at gutter connection with leaks. In this regards, Contractor shall rectify or repair the area with stagnant water and seal-off the gutter conncetion with leak and should take corrective action on the issue. (RFI has been rejected). PN: During surveillance and monitoring actiivities at substation G-1121, found out that gutter support (FB.50X6) has already been installed without submitting first the "RFI" for Material Receiving inpsection to ensure that the material complied with Sadara standard prior to inspection. Contractor is advised to submit material receiving inspection to counter-check by Company Coating Inspector for proper documentation and acceptance. Contractor: Subcontractor will raise/submit RFI for the material receiving to check the installed gutter support randomly at G-1121 to confirm installed gutter are meet as per Sadara standard. The Contractor did not continue the grouting of foundation of the inside portion of the oil quench and water quence structures. Only the outside portions wre grouted. The Contractor shall ensure that space between plates shall also be fully filled with grout. During surveillance & monitoring inspection at operator building along blast type door along north side. It was found out that sub-frame of blast door was not align properly and squareness of the said sub-frame. Contractor is advised to submit shop drawing and details on how to rectify or repair the squareness and alignment of sub-frame. Contractor: contractor has assigned ARCC welder for welding work activities and kindly check with Contractor construction group. The Conrractor started to erect equipment/structural support without submitting RFI at Air Cooler Structures area and Fresh Ethane Structure area. Some deficiencies noted on the structures are the following: No chamfer on exposed corners, chamfers were not uniformly trimmed, blowholes and small honeycombs were not repaired, beams have irregular shapes, some color of the repaired structures were not uniform, the top portion of the beams were not properly cleaned prior to repair. Contractor did not submit RFI to cover Item 3.6 of ITP SMITP-Q-001-02. LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason VAF / PN S/N LBE NO. PID SUBCON/ CONTRACTOR Page 71 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 09, 2014 LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason VAF / PN S/N LBE NO. PID SUBCON/ CONTRACTOR 6 LBE-AMA- CIVIL-283 MR. GERALD AMA VAF 2 CIVIL Civil 20-May-14 7 LBE-KCC- CIVIL-285 MR. GERALD KCC VAF 2 CIVIL Civil 02-Jun-14 8 LBE-KCC- CIVIL-290 MR. GERALD KCC PN 2 CIVIL Civil 08-Jun-14 9 LBE-KCC- CIVIL-291 MR. JERRY KCC VAF 2 CIVIL Civil 10-Jun-14 10 LBE-AMA- CIVIL-293 MR. RAHMAN AMA VAF 2 CIVIL Civil 16-Jun-14 11 LBE-AMA- CIVIL-294 MR. RAHMAN AMA VAF 2 CIVIL Civil 16-Jun-14 During surveillance, it was noted that Amana is doing External Concrete Coating for Cooling Tower west side without any QC Civil Inspector coverage. This is a violation to Schedule "Q", attachment VI, VI-1, PQP Personnel requirements. Subcontractor: Amana already assigned the inspector to monitor the external concrete coating work at cooling tower. During surveillance, it was noted that the Contractor has started external coating Renderoc FC on west side without any RFI for cooling tower. 1. Concrete repair work acceptance, 2. Surface preparation for concrete coating pre-application inspection. As per ITP. Subcontractor: Due to misunderstanding, Amana did not raised RFI for surface preparation for Rooms # 1 & 2, effectively from 17th of June Amana has raised RFI for surface preparation for Room # 3, 4, 5, 6, 7, 8 & 9 which are approved by Sadara Inspector. The Contractor was reminded of the requirements of Hot weather concreting prior to concrete placement of pavement as per RFI No. MFC- DLM-KCC-CI-7691 (Paving area B-A Span 65 & 66). The contractor continued to place concrete in spite of violation of RT2S-3001-01, section 5.4.8 which states: a. Shade temperature exceeds (110F) 43C at the job site combined with a mean speed of 10 mph or over. No measure to prevent exercise moisture loss before the final curing procedure are accompanied in the requirement of RT2S-3001-01, Para. 5.1. The shade temperature at 10:30 AM is 44.5. No apparatus to measure the wind velocity, relative humidity, etc. to check the rate of evaporation per table 2.1.5 of sec. 1305. Contractor: All concrete pouring shall start now at 5:00 PM onwards (July 21, 2014). PN: During monitoring and surviellance activities at Crack Gas Compressor "Deca Slab", it was noticed that after casting the slab the control joint was not implemented after 10 days wherein the concrete was already hardened. Contractor shall take corrective and remedial action on this issue. Contractor: At crack gas compounf (deck slab), the cutting of concrete was already done and there is a small balance portion that cannot be proceeded to cut it because the area is still use by other subcon and work can proceed after the removal of scaffolding suport. During surveillance and monitoring activities at sum-0645 south side of substation G1121, it was noticed that the installed ladder rung some are preserve with corrosion. This is a violation to SADARA specification RT- 3001-01, section 8.2, Para. 8.2.7. In this regards, Contractor should investigate these materials and take corrective action about the issue. Contractor: Regardimg ladder Rung which is coordinated @ sump pit #645 Company has already issued an NCR to Contractor. During surveillance and monitoring activities at expander building (61123), found out that the gutter was already installed, without submitting first RFI for material receiving inspection for proper documentation and checking. Contractor should take corrective action on this issue and for proper implementation. This is violation to SMIC-M-1031-1 (Metal Roofing Receiving and Storage Inspection). Contractor: The previous installed gutter was already removed, and KCC construction team was advised to purchase a new one lgalvanized gutter as per approved drawing. And KCC will raise RFI for material receiving inspection prior to installation. Page 72 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 09, 2014 LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason VAF / PN S/N LBE NO. PID SUBCON/ CONTRACTOR 12 LBE-FCN- CIVIL-295 MR. JERRY FCN VAF 2 CIVIL Civil 17-Jun-14 13 LBE-AMA- CIVIL-298 MR. GERALD AMA VAF 2 CIVIL Civil 17-Jun-14 14 LBE-TCC- CIVIL-299 MR. GERALD TCC PN 2 CIVIL Civil 17-Jun-14 15 LBE-KCC- CIVIL-301 MR. GERALD KCC VAF 2 CIVIL Civil 21-Jun-14 16 LBE-AMA- CIVIL-302 MR. GERALD AMA PN 2 CIVIL Civil 21-Jun-14 PN:During surveillance & monitoring at Sub-station G-1120 & G-1121. It was noticed that most of the doors's accessories have already been installed but Contractor did not submit Final Acceptance Inspection (SMIC- M-1051) ITP Checklist. Contractor shall submit RFI for proper checking of those accessoties and proper documentation. Subcontractor: Amana has started the door rectification work and they will submit the RFI once the soor is totally sccepted by internal inspector. (On-going). With reference to RFI #MFC-DLM-KCC-CI-7890-0A & F7932, installation of epoxy coated steel bars & embeded item/floor closure inspection (deck slab) at area D-G common computer shelter GL 13-16/A-D, Contractor did not submit RFI and no advice from Daelim Inspectors to Company for proper checking of repair arrangement and diameter as per latest IFC drawing and also this RFi was "Hold" point. This is a violation to Schedule "Q" attachment IV, Para. 1.1.3 & 1.1.9/3.7. Contractor should take corrective & remedial action on the issue. (RFI was rejected). PN: During surveillance at flare area, it was noticed that two (2) pedestals was deformed or bent the acnhor bolts. Contractor should investigate and take corrective action about the issue for proper implementation. During surveillance and monitoring activities at Operator building (6-1122), it was observed that mostly of the rooms are already installed acoustical ceiling (SMIC-M-1053), Inspection checklist for acoustic suspension ceiling system installation inspection also check some opening on walls. In this regards, Contractor should take corrective action concerning this issue for proper documentation. Subcontractor: Amana has started the rectification work sspension ceilling system and opening work. Amana will raise/submit RFI room by room inspection. It was observed that after the fireproofing of vessel using Pyrocrete 241, the cementious fireproofing developed cracks on several locations of the structure. Please investigate the causes and provide corrective measures to avoid recurrence. Page 73 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 09, 2014 LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason VAF / PN S/N LBE NO. PID SUBCON/ CONTRACTOR 17 LBE-AMA- CIVIL-303 MR. RAHMAN AMA PN 2 CIVIL Civil 23-Jun-14 18 LBE-TCC- CIVIL-304 MR. BUCASA S TCC VAF 2 CIVIL Civil 24-Jun-14 19 LBE-AMA- CIVIL-137 MR. MARK AMA VAF 1 CIVIL Civil 25-Jun-14 20 LBE-AMA- CIVIL-307 MR. RAHMAN AMA VAF 2 CIVIL Civil 05-Jul-14 21 LBE-KCC- CIVIL-308 MR. BUCASA S KCC VAF 3 CIVIL Civil 08-Jul-14 Surveillance inspection at Cooling Tower Pump Sump #8 for moch-up grout filling of opennings. However, it was found out that after removal of formworks, there were portions or gap not filled with grout. Actual measurement was checked and approximately 10cm depth or thickness of the wall not grouted. This is a violation to Sch. "Q", section 1.2, Sadara dcoument no. A554-E-103-CM-GEN-PLN-031. Contractor shall investigate the root cause and initiate corrective action. Subcontractor: After the removal of forms, the hollow portion of the grouted area was cleaned bt removing all loose materials & laittance. Formworks were re-installed, making sure no leakage will appear by putting sealant on the edge. After the preparation, the area was grouted using approved Materials masterflo 526. Reference to PRO-ACTIVE LBE #303, dated 23 June 2014, Contractor did not has not performed any Pull-of-Test as required before Coating for surface soundness. This is violation to Sadara Specs A554-K-PRG-PI-SPS- VIA-150, Para. 8.6.4. Contractor has proceeded without the required test, coating is on ongoing in Pump basin #03 & 04 whihc has violated the same Sadra specs. During routine site visit at Operator building 6-1122, it was found out the Contractor used the cable tray as a support for the T-runner of the false ceiling which is a violation as per 67C-0321-01, section 1-2. Contractor: Construction already instructed to remove the tie wire which connected to channel tray PN: During surveillance and work monitoring, it was noted that the repair material is not fully bonded to the surface after recommended curing time b manufacturer. Contractor is pro-actively advised to take Pull of Test to determine the Tensile Strength of repair material as per Approved ITP for coating/waterproof lining. 1. Document No. A554-E-103-QA-GEN-PLN-119, checklist no. SMIC-R-103, item no. a4, E6. 2. Concrete repair guide - ACI- 546R-04, Para no. 2.7 "In-place-tensile pull-off tests are recommended to evaluate that bonding of repair materials is adequate. 3. Document no. A554-K-PRG-PI-DPC-VIA-150, aProtective Coatings for Industrial concrete structures, Para. 8.6.4. During surveillance, it was noticed that after epoxy grouting on foundations of pump 1411C located at south side of east-west piperack, pumpsump area foundations of cooling tower 901C, 901E, 901F, 901G & 901H that cracks developed on the surface of the foundations. Contractor shall investigate the root cause and initiate corrective action to avoid recurrence. Page 74 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 09, 2014 LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason VAF / PN S/N LBE NO. PID SUBCON/ CONTRACTOR 22 LBE-KCC- CIVIL-309 MR. BUCASA S KCC VAF 3 CIVIL Civil 09-Jul-14 23 LBE-AMA- CIVIL-575 MR. NASSAR AMA VAF 3 CIVIL Civil 14-Jul-14 24 LBE-AMA- CIVIL-311 MR. GERALD AMA VAF 2 CIVIL Civil 15-Jul-14 25 LBE-KCC- CIVIL-312 MR. GERALD KCC VAF 2 CIVIL Civil 17-Jul-14 26 LBE-AMA- CIVIL-313 MR. BUCASA S AMA VAF 2 CIVIL Civil 21-Jul-14 27 LBE-AMA- CIVIL-314 MR. ENDRAN O AMA VAF 2 CIVIL Civil 22-Jul-14 During surveillance & monitoring activities at North side of sub-station G- 1121 (Open Ditch) or SW due Type-1, found out that finishing work and alignment of this open ditch is not properly done and poor workmanship, especially on finishing touches. Contractor shall take remedial action on the issue in order that the work must be acceptable. This is violation to RT2S- 3001-01, section 10 & DWG # A554-E-CV-DWG-C70-038, Rev.2. During surveillance inspection at Diedsel generator building (G-1124), found out that gutter & support was already installed without raising RFI to Company. This is a violation Sadara inspection checklist (SMIC-M-1031-1) "Metal roofing/Flashing and trim material receiving inspection". Contractor should take corrective action. During concrete placement, on July 16, 2014 at around 7:30 PM for (DVA 703-708) Fire wall, the forms collapsed. The side forms were removed on July 17, 2014. It was observed that the concrete placement was more than one (1) meter in height from the base slab, which is located at southwest potion of fire wall. This is a violation to Sadara RT2S-3001-01, section 6.1, Para. 6.1.2 & 6.1.3. Note that the fire wall must be monolithic or massive concrete. Contractor shall investigate the root cause and initiate corrective action to avoid recurrence. During inspection at Cooling Tower Pump sump no. 7 with RFI No. MFC- DLM-AMA-CI-8011, it was found out that some areas on floor slab have surface irregularities, sharp edge projections which might damage the tissue mat lining system installation. This is a violation to Sadara document No. A554-K-PRG-SPC-VIA-150, section 6.1.3 the subcontractor shall rectify the surface irregularities with approved materials prior to coating application. The RFI is Rejected. During work monitoring and surveillance, it was observed that KCC begun with the tie-rod holes repair at least side wall of cooling tower pump sump area using not approved material EMCO 301.Clear violation to Sadara document no. A554-E-103-WA-GEN-PLN-095, checklist SMIC-12-1003, ite, A. ITP for repair of cooling tower. Contactor is advised to rectify and comply as required. Contractor: Materials are already approved. The old materials was replaced by Emaco S85 instead of Emaco 301. During surveillance, it has been detected of Loss of adhesion for concrete coating at Sump Pit #645. Loss of adhision was found on the wall. The reason of failure is improper mixing ratio for repair materials during surface preparation. Page 75 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 09, 2014 LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason VAF / PN S/N LBE NO. PID SUBCON/ CONTRACTOR 28 LBE-KCC- CIVIL-315 MR. GERALD KCC VAF 2 CIVIL Civil 26-Jul-14 During surveillance and monitoring activities at South side of Subtation G- 1122 (Operator Bldg.) Car Park shelter foundation on 2 (two) units, found out that Bitume coating applications are already done without RFI, which caused improper checking of Company especially on the required docomentations. This is a violation to schedule "Q", attachment IV, Section 1, Para. 1.1.3 & 1.1.9 and Sadara MFC inspection checklist (SMIC-H-1003) "Surface Preparation for concrete & building painting pre-applciation inspection. Contractor shall take remedial action on the issue in order that the work will be accepted. Page 76 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 09, 2014 DUE DATE Issued corrective action to Company Target Date 23-Dec-13 19-Jul-14 Open 28-Jan-14 20-Jul-14 10-Aug-14 Open 31-Jan-14 Open 09-May-14 20-Jul-14 Info 23-May-14 Open Contractor: Subcontractor will raise/submit RFI for the material receiving to check the installed gutter support randomly at G-1121 to confirm installed gutter are meet as per Sadara standard. Contractor: contractor has assigned ARCC welder for welding work activities and kindly check with Contractor construction group. Company comment Approved Close LBE by Company CONTRACTOR'S CORRECTIVE ACTION PLAN STATUS Daelim/Subcontractor Response / Reason Page 77 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 09, 2014 DUE DATE Issued corrective action to Company Target Date Company comment Approved Close LBE by Company CONTRACTOR'S CORRECTIVE ACTION PLAN STATUS Daelim/Subcontractor Response / Reason 23-May-14 30-Jun-14 Open 05-Jun-14 14-Jun-14 Open 11-Jun-14 12-Jul-14 Info 13-Jun-14 21-Jul-14 Open 19-Jun-14 20-Jul-14 Open 19-Jun-14 25-Jul-14 Open Subcontractor: Amana already assigned the inspector to monitor the external concrete coating work at cooling tower. Subcontractor: Due to misunderstanding, Amana did not raised RFI for surface preparation for Rooms # 1 & 2, effectively from 17th of June Amana has raised RFI for surface preparation for Room # 3, 4, 5, 6, 7, 8 & 9 which are approved by Sadara Inspector. Contractor: All concrete pouring shall start now at 5:00 PM onwards (July 21, 2014). Contractor: At crack gas compounf (deck slab), the cutting of concrete was already done and there is a small balance portion that cannot be proceeded to cut it because the area is still use by other subcon and work can proceed after the removal of scaffolding suport. Contractor: Regardimg ladder Rung which is coordinated @ sump pit #645 Company has already issued an NCR to Contractor. Contractor: The previous installed gutter was already removed, and KCC construction team was advised to purchase a new one lgalvanized gutter as per approved drawing. And KCC will raise RFI for material receiving inspection prior to installation. Page 78 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 09, 2014 DUE DATE Issued corrective action to Company Target Date Company comment Approved Close LBE by Company CONTRACTOR'S CORRECTIVE ACTION PLAN STATUS Daelim/Subcontractor Response / Reason 20-Jun-14 Open 20-Jun-14 20-Jul-14 Open 20-Jun-14 20-Aug-14 Info 24-Jun-14 Open 24-Jun-14 20-Jul-14 Info Subcontractor: Amana has started the door rectification work and they will submit the RFI once the soor is totally sccepted by internal inspector. (On-going). Subcontractor: Amana has started the rectification work sspension ceilling system and opening work. Amana will raise/submit RFI room by room inspection. Page 79 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 09, 2014 DUE DATE Issued corrective action to Company Target Date Company comment Approved Close LBE by Company CONTRACTOR'S CORRECTIVE ACTION PLAN STATUS Daelim/Subcontractor Response / Reason 26-Jun-14 20-Jul-14 Info 27-Jun-14 Open 28-Jun-14 28-Jun-14 30-Jul-14 Open 08-Jul-14 20-Jul-14 Open 11-Jul-14 21-Jul-14 Open Subcontractor: After the removal of forms, the hollow portion of the grouted area was cleaned bt removing all loose materials & laittance. Formworks were re-installed, making sure no leakage will appear by putting sealant on the edge. After the preparation, the area was grouted using approved Materials masterflo 526. Contractor: Construction already instructed to remove the tie wire which connected to channel tray Page 80 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 09, 2014 DUE DATE Issued corrective action to Company Target Date Company comment Approved Close LBE by Company CONTRACTOR'S CORRECTIVE ACTION PLAN STATUS Daelim/Subcontractor Response / Reason 12-Jul-14 15-Jul-14 Open 17-Jul-14 Open 18-Jul-14 Open 20-Jul-14 Open 24-Jul-14 Open 25-Jul-14 Open Contractor: Materials are already approved. The old materials was replaced by Emaco S85 instead of Emaco 301. Page 81 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 09, 2014 DUE DATE Issued corrective action to Company Target Date Company comment Approved Close LBE by Company CONTRACTOR'S CORRECTIVE ACTION PLAN STATUS Daelim/Subcontractor Response / Reason 29-Jul-14 Open- Page 82 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 09, 2014 1 LBE-IKK- MECH-544 IKK VAF 3 MECH Coating/ Painting 08-Jun-14 2 LBE-PSCL- MECH-547 PSCL VAF 3 MECH Coating/ Painting 10-Jun-14 3 LBE-AMA- MECH-550 AMA VAF 3 MECH Coating/ Painting 15-Jun-14 4 LBE-IKK- MECH-571 IKK VAF 3 MECH Coating/ Painting 08-Jul-14 5 LBE-IKK- MECH-578 IKK VAF 3 MECH Coating/ Painting 16-Jul-14 6 LBE-ARCC- MECH-579 ARCC VAF 3 MECH Coating/ Painting 20-Jul-14 7 LBE-TCC- MECH-581 TCC VAF 3 MECH Coating/ Painting 22-Jul-14 During routine inspectionm, it has been noticed that TCC coating applicator not cleaned the pipeline surface for process line (P-172702) at dryer Piperack prior to apply the coating. Shoes marks were detected in diferrent locations & coating applicator was applied for final coat without cleaning dirtied areas. Daelim inspector has witnessed this violation. This is for necessary corrective action. During routine inspection on package # TP-1505-01-HT-027 & TP-15015- 01-HT-028, found at F1180 Top Level, it has been noticed that much cracking and loss of adhesion due to improper surface preparation. This is for necessary corrective action. During surveillance at Cooling Tower, it has been noticed that dusting on the concrete surface during coating application at corridor (Wall GF: 4A & 5A) middle portions, non-clean surface causes loss of adhesion between concrete section shall be taken prior to apply final coat. During surveillance, it was noticed that AMANA has repaired corroded hot dip galvanized ladder rungs in Sump pit #644 without notification for inspection for SQIT Coating, still not dry since one week due to improper surface preparation & coating application. This is for information & corrective action by Contractor. During surveillance, it has been noticed that IKK has applied primer coat & using for Pump Sump A101, 02 & 03 at Cooling Tower without notifying the Company for inspection of surface preparation prior to apply coating and lining. As per Sch. "Q" and approved ITP, RFI notification shall be required. During surviellance at site , it is observed that subcontractor erected structural members (Column & its hanging) for Clarifier tank (V-0568) supplied by Tsukishima Kankyo Eng. Without final chemical protective coating (only primary coating found). In A554-E-103-MJ-REQ-MU4-115 states that it is the responsible of the Contractor to apply complete final coat if the mechanicm is shop blasted and poured with manufacturers' procedures. See Para. (coating 1, 2, 3). Daelim/Subcontractor Response / Reason VAF / PN During routine inspection at cooling tower room #7 & 3, it has been observed that IKK had no treatment expansion joint as per approved method statement (A554-E-103-CM-GEN-PLN-024) section 3.2 of applied only Materbrace ADH 2200. S/N LBE NO. SUBCON/ CONTRACTOR LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Page 83 of 139 LOG BOOK ENTRY (LBE) SUMMARY As of July 09, 2014 DUE DATE Issued corrective action to Company Target Date 11-Jun-14 Open 13-Jun-14 Open 18-Jun-14 20-Jul-14 Open 11-Jul-14 Open 19-Jul-14 Open 23-Jul-14 Open 25-Jul-14 Open Company comment Approved Close LBE by Company STATUS Daelim/Subcontractor Response / Reason CONTRACTOR'S CORRECTIVE ACTION PLAN Page 84 of 139 LOG BOOK ENTRY (LBE) SUMMARY As of July 09, 2014 1 LBE-SEN- ELECT-105 SENDAN/ DAELIM VAF 1 ELECT Electrical 18-Feb-14 2 LBE-DLM- ELECT-114 DAELIM (Constructio n) VAF 1 ELECT Electrical 06-Mar-14 3 LBE-DLM- ELECT-117 DAELIM (Constructio n) VAF 1 ELECT Electrical 26-Mar-14 4 LBE-DLM- ELECT-118 DAELIM (Constructio n) VAF 1 ELECT Electrical 26-Mar-14 5 LBE-DLM/ SEN-ELECT- 133 DAELIM (Constructio n) PN 1 ELECT Electrical 21-May-14 6 LBE-SEN- ELECT-136 SENDAN VAF 1 ELECT Electrical 25-Jun-14 7 LBE-SEN- ELECT-138 SENDAN VAF 1 ELECT Electrical 26-Jun-14 During routine site visit at East side of substation G-1121 & cooling tower, it has been coticed that the aluminum and fiberglass cable trays were deflected at the splice plates next to expansion splice plate. This is violation as per NEMA VE-2, Section 4.2.1. Contractor: For the corrective action for the same, Contractor/Subcontractor will use unistrut channel below the cable tray flange at both sides. Tha sample will be inspected and if it' is required any more recrification, it will be corrdinated with the Engineering. During routine site inspection at Operator building G-1122, it was noticed that the contractor installed felxible metallic conduit that was more than 1.8 meters in length which is a violation as per NEC, Article 348.20 (A) (2) c. Contractor: The installation done as per IFC drawings for corrective action and proposal, Contractor/Subcontractor will coordinate with Engineering. PN: During Inspection of FRP cable tray at spent caustic area, it was observed that the cable tray installation are using temporary nut-bolt for fasteners/hold down stainless steel materials. This is violation to G7D-0323- 00, section 4.1.5 and data sheet G7D-0323-A required silicon bronze. Contractor: For the time being that the materials which are approved to install in FRP cable tray is notavailable, stainless steel was installed temporarily to proceed on the next activity. Once the approved materials arrived in the site, it will be replaced. During routine site surviellance, it was noticed that the installation of battery disconnect was located outside the battery room which is a violation as per G7C-1816-00 Section 3.11 and NEC Article 480.5. Contractor: Issue Will be addressed to engineering for further assessment regarding this violation. As per Engineering team, it was installed outside the battery room to prevent splashing of electropolyte and same principle of 67C-1816-00, Spec. 6.2 installation. During Site Surviellance at Electrical Room Substation G-1120 it was Observed that the cable tray Installation is closed and insufficient clearance to the grounding Busbar, This is Violates as per G7C-0104-00 Para. 5.7 contractor: Discrepancies of Installation with regards to the standards will address to engineering for Clarification and action. NCR issued to Daelim Construction team. During routine site inpsection, it was noticed that the Contractor installed lighting fixtures and used the channel tray as a support inside operator building and battery room of substation G-1121. This is a violation as per G7C-0321-01, section 1.2 and RT7C-1822-06. Subcontractor: The installation done as per IFC drawing but the same has been conveyed to Engineering, waiting for reply. After Enginering decision, it will be rectified accordingly. Contractor: Contractor submits TM/RFC to Company. RFC was acknowledged already by the Company and approved buy SME has comments to change the revision of RFV. During surveillance at East-West main pipe rack near in the Furnace Area, it was observed the following violations: 1. The LV power cable was damaged the outer insulation and other are twisted due to improper cable pulling activities. This violates schedule "Q" attachment IV, sec. 3.2. 2. The cable tray splicing joint was already deflected during cable pulling activities. This violates NEMA VE2, sec. 4.2.1. Subcontractor: 1. It is investigated and the damage portion of the cable will be repair and also cable. 2. Tray splicing joint, the deflected part will be repaired as per repair procedure. NCR was issued to Daelim Construction team. LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason VAF / PN S/N LBE NO. SUBCON/ CONTRACTOR Page 85 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 09, 2014 LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason VAF / PN S/N LBE NO. SUBCON/ CONTRACTOR 8 LBE-SEN- ELECT-139 SENDAN VAF 1 ELECT Electrical 27-Jun-14 9 LBE-SEN- ELECT-141 SENDAN VAF 1 ELECT Electrical 19-Jul-14 During inspection of RFI # MFC-DLM-SDN-EL-1893 for cable pulling of Motor RTD cable was installed in the same cable tray of LV power cables. This violates as per G7C-0302-00, Para. 3.4.2. Contractor: Engineering/Construction were advised on the necessary action on or remedy for this issue. During routine site visit, it was noticed that the Contractor used a HDG bolt for the installation of enclosure at the lightning pole at the west side od substation G-1121 which is a violation as per A554-K-PRG-EL-GEN-PHL- 005, Section 3.4.4. Contractor: The HDG bolt of enclosure will be replaced by SS bolt. The replacement of bolts are already in progress. Page 86 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 09, 2014 DUE DATE Issued corrective action to Company Target Date 21-Feb-14 04-Mar-14 30-Jul-14 Open 09-Mar-14 08-Mar-14 Open 29-Mar-14 27-Mar-14 Open 29-Mar-14 29-Mar-14 Open 24-May-14 24-May-14 Info 28-Jun-14 27-Jun-14 30-Jul-14 Open 29-Jun-14 27-Jun-14 30-Jul-14 Open Contractor: For the corrective action for the same, Contractor/Subcontractor will use unistrut channel below the cable tray flange at both sides. Tha sample will be inspected and if it' is required any more recrification, it will be corrdinated with the Engineering. Contractor: The installation done as per IFC drawings for corrective action and proposal, Contractor/Subcontractor will coordinate with Engineering. Contractor: For the time being that the materials which are approved to install in FRP cable tray is notavailable, stainless steel was installed temporarily to proceed on the next activity. Once the approved materials arrived in the site, it will be replaced. Contractor: Issue Will be addressed to engineering for further assessment regarding this violation. As per Engineering team, it was installed outside the battery room to prevent splashing of electropolyte and same principle of 67C-1816-00, Spec. 6.2 installation. contractor: Discrepancies of Installation with regards to the standards will address to engineering for Clarification and action. NCR issued to Daelim Construction team. Subcontractor: The installation done as per IFC drawing but the same has been conveyed to Engineering, waiting for reply. After Enginering decision, it will be rectified accordingly. Contractor: Contractor submits TM/RFC to Company. RFC was acknowledged already by the Company and approved buy SME has comments to change the revision of RFV. Subcontractor: 1. It is investigated and the damage portion of the cable will be repair and also cable. 2. Tray splicing joint, the deflected part will be repaired as per repair procedure. NCR was issued to Daelim Construction team. Company comment Approved Close LBE by Company STATUS CONTRACTOR'S CORRECTIVE ACTION PLAN Daelim/Subcontractor Response / Reason Page 87 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 09, 2014 DUE DATE Issued corrective action to Company Target Date Company comment Approved Close LBE by Company STATUS CONTRACTOR'S CORRECTIVE ACTION PLAN Daelim/Subcontractor Response / Reason 30-Jun-14 28-Jun-14 30-Jul-14 Open 22-Jul-14 23-Jul-14 Open Contractor: Engineering/Construction were advised on the necessary action on or remedy for this issue. Contractor: The HDG bolt of enclosure will be replaced by SS bolt. The replacement of bolts are already in progress. Page 88 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 09, 2014 1 LBE-DLM- MECH-359 DAELIM (Enginnerin g) VAF 2 MECH Engineering 09-Oct-13 2 LBE-SEN- ELECT-104 DAELIM (Enginnerin g) PN 1 ELECT Engineering 12-Feb-14 3 LBE-DLM- ELECT-109 DAELIM (Enginnerin g) VAF 3 ELECT Engineering 23-Feb-14 4 LBE-DLM- MECH-499 DAELIM (Enginnerin g) PN 3 MECH Engineering 06-Mar-14 5 LBE-DLM- MECH-511 DAELIM (Enginnerin g) VAF 3 MECH Engineering 12-Mar-14 During inspection at Cooling Water Tower observed that partition walls grinder beam (intermediate) obstructed or on cross on walkway platform. Daelim/SPIG shall redesign the structural arrangement and provide proper access without any obstruction on walkway and re-evaluate the structural integrity if any significant modification required. PN: Gas Furnace: Area furnace box sleeves are not centered/defected as per actual arrangement drawing A554-7-103-MB-DWG-MB-2-002. It is string with radiant coil which will be cause of damage during the operation. Daelim shall propose appropriate method to fix the discrepancies with Engineering approved method.
During site surveillance at substation G-1120, it was observed that the cable tray installation is close to the inter-pacing relay panel tag no. IRP- 103J101 & IRP-103J102. Actual vertical distance from equipment to the bottom of the tray is 300mm. This violates as per G7C-0321-01, para 3.12. Contractor: It was discussed to Engineering and feedback will be followed-up regarding the issue. -> Discussed and agreed with Company. NCR was issued to Daelim construction team. PN: During surveillance for electrical cable tray installation at East-West main pipe rack, it was observed that the installations of splice plate are closed to support and less than 300mm. As per G7C-0324-03, splice plate on support is +- 300 is required to use of a heavy duty splice plate. Subcontractor: The issue has been investigated & corrective action plan preprared by Construction. NCR was issued to Daelim Construction team. Found that Isometric IFC Drawings of Daelim are showing one of the notes in the left bottom corner for "FFW" (indicates Field Fir Weld, Pipe at this joint shall be fabricated 150mm longer) but actually on drawings it is not marked on any required locations. Discrepancy also enquired from Daelim Quality & Engineering Departments and Contractor also acknowledged. It is a violation of G4D-0140-10. Daelim Quality must ensure FFW markings on IFC drawings to avoid any discrepancy while connecting pipe joints to the rotating equipment. Some Ref. Dwg. Nos. are 054703-02, 051703-02 & 131109-01. Contractor: Daelim applies the following method to field welding around rotating equipment. 1. The tack weld requirement in G4D-0140- 10 at flange adjacent to rotary equipment nozzle is applied for both suction and discharge nozzle. 2. In case the fabricated spool length is not enough according to site condition, then Daelim judges whether it can be managed with specified FW or not. If it is judged that could not be managed then the pipe is to be cut and welded with additional longer pipe piece. 3. To make sure not to cause strain on the flange conncetion to rotary equipment nuzzle, Daelim checks the flange position and parallel condition nozzle without bolting after pipe piece installation is completed. 4. Daelim ensures the pipe strain on the rotating equipment nozzle does not exceed the limit of coupling movement specified in G4D-0140-10 and G5S-5321-02. 5. If any heating repair is conducted without prior written approval, Daelim re- fabricates the certain spool. LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason VAF / PN S/N LBE NO. SUBCON/ CONTRACTOR Page 89 of 142 LOG BOOK ENTRY (LBE) SUMMARY As of July 09, 2014 LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason VAF / PN S/N LBE NO. SUBCON/ CONTRACTOR 6 LBE-DLM- CIVIL-257 DAELIM (Enginnerin g) VAF 2 CIVIL Engineering 20-Mar-14 7 LBE-DLM- ELECT-120 DAELIM (Enginnerin g) VAF 1 ELECT Engineering 02-Apr-14 8 LBE-DLM- ELECT-124 DAELIM (Enginnerin g) VAF 1 ELECT Engineering 02-Apr-14 9 LBE-DLM- MECH-524 DAELIM (Enginnerin g) PN 3 MECH Engineering 10-Apr-14 10 LBE-DAELIM- CIVIL-281 DAELIM (Enginnerin g) VAF 2 CIVIL Engineering 15-May-14 11 LBE- DLM/AMA- MECH-535 DAELIM (Enginnerin g) VAF 3 MECH Engineering 15-May-14 During surveillance, obseerved that following discrepancies: G #1122 Operator building (Amana): * Embedded door frame for blastering door are inclined and gaps bowing more than the acceptable limit - as per GA drawing (A554-E-G-11-22-GWA-402302) * Welding activities carry out with unqualified welder and WPS. Improper sequence of weld and crack - leak of fusion-undercut . * Daelim quality team to investigate and propose appropriate remedy action with Engineering support to fix the occured discrepancies. During Surviellance at Electrical Room Substation G-1120, it was observed that the power panel and Dry Type Teransformer was installed along with LV Switchgear is forture space for LV Switchgear. This is Violates as per G7C-1811-00 Para. 6.1.2 & 6.1.8 Contractor: Engineering was informed regarding this matter/Issue, company will be informed of contractor action. -> Discussed and agreed with Company. NCR was issued to Daelim Construction team. PN: During Surviellance it is Observed that P-0126B, P2320A, P2411A, P2415A/B, P1311A/B/C, P1302A/B, 1711A, P2122B by ITT goulds found Leaking. Leaking is from the oil drum out valve thread connections, Daelim should take appropraite corrective action by consulting the recommendation of vendor manufacturer. Contractor: Vendor site visit being arranged. The expected visit date is within 23 May 2014. -> NCR with coorective action was sent to Company through TR no. MFC-T-DS-CJ-QA-1567 dt July 14. It was noticed on site that the Structural Column for Foundation F1-025 is clashing with the equipment E1805. The beam connecting the steel columns therefore cannot be connected. Also the erected column (one side only) is tilting because the equipment is inside the column vertical alignment/plumbness. The foundation is very near the construction joint also. Contractor to investigate and provide corrective action. Contractor: Already Fit-025 structural colomn supports are accepted, refer to attached drawing. During Material Receiving Inspection, it was Noticed that one cubicle was damaged. Contractor shall replace the damage cubicle at its components inside motor control center MCC-103H204 at Substation G-1121. Contractor: Contractor issue to vendor for replacment of damage part in MCC-103H204 -> Replaced with new component It was notice that during inspection at G1120 and G1124 Paving Area, the slope design of the paving is not in accordance with the project specification RT2S-2700 Section 8. also the actual elevation of the existing paving is not in accordance with the design. As discussed with Company PMT, Non-process area can be less than 1% slope Page 90 of 142 LOG BOOK ENTRY (LBE) SUMMARY As of July 09, 2014 LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason VAF / PN S/N LBE NO. SUBCON/ CONTRACTOR 12 LBE-DAELIM- CIVIL-287 DAELIM (Enginnerin g) PN 2 CIVIL Engineering 03-Jun-14 13 LBE-DAELIM- CIVIL-296 DAELIM (Enginnerin g) PN 2 CIVIL Engineering 17-Jun-14 14 LBE-DAELIM- CIVIL-297 DAELIM (Enginnerin g) PN 2 CIVIL Engineering 17-Jun-14 15 LBE-DLM- ELECT-134 DAELIM (Enginnerin g) VAF 1 ELECT Engineering 22-Jun-14 16 LBE-SEN- ELECT-135 DAELIM (Enginnerin g) VAF 1 ELECT Engineering 22-Jun-14 17 LBE-DLM- MECH-568 DAELIM (Enginnerin g) VAF 3 MECH Engineering 07-Jul-14 18 LBE-DLM- MECH-569 DAELIM (Enginnerin g) VAF 3 MECH Engineering 07-Jul-14 During TSR inspection for Tray-1310, it is noticed that the tray is without bracing for the beam support for all the tray throughtout the TSR. Engineering clarification required with proper approved repair procedure and its documentation for rectification. Contractor : DAELIM already issued technical memorandum for repair work of bracing to SADARA. And now we are communicating with SADARA's welding SME, Plummer, Robert for the welding of bracing. And we'll offcially issue the completed repair procedure after discussion with SADARA. Tower F1710 is found with the TSR down by 7 to 10mm down, Engineering clarification reuired with proper rectification. All rectification and repair work shouild be approved and documented. Contractor: For T-1710, we already got the approval of the repair work for leveling of TSR from SADARA. Now we are installing shim plate and adjusting the level of TSR and internal trays at site. PN: The evaluation of Paving in between the piperacks at North of Cooling Tower and Southeast by Building East 6-1121 is not level with the foundation of the piperack. The cover of the open trench in that location, therefore, will have a different elavations. Please advise Engineering for the remedial works on this location. During surveillance inspection of Substation G-1120 & G-1121 & North South and near cooling tower, it was observed that the LV power cables were install underground trench for street ligting is above grand type of cable the outer sheath of cable is color black. This violates RT70-0430-00, Para. 37.2 and 3.8. Contractor: Engineering will coordinate to Riyadh Cable for investigation on how this issue will be solved. -> TM or RFV shall be issued. Meanwhile, we received from vendor statung that there is no problem. During winding installation resistance test of RFI #MFC-DLM-SND-EL-1610 for compressor notor #1, G-1120-ACCU-001A at Mechanical room substation G-1120, it was observed that the test result has failed the actual valve was 10.7 mega-ohms. This violates as per Company Pre- commissioning Porcedure G7M-0020-08, which is the acceptable valve of winding installation test shall be 100 me ohms. Contractor: Contractor will coordinate to Zamil for explanation in this failed result PN: It was noticed that some of pipe support, not yet erected in many locationsare directly located in the TPER (expansion joint), please note that the foundation/pedestals of these pipe supports are sugject to verification by Daelim Design Engineering for proper design and possible demobilization of paving to erect new foundation. It is recommended that the location of these pipe support shall be identified in advance by Daelim for proper disposition. Contractor: Discussed to civil construction and engineering action granted that they will provide ab approved drawing on how the proposal to be accepted by Company. An sketch is attached. PN: The dowels for the arbwall at the southside and of T-1710, D-1715 and Pumps area were not placement for foundation of adjacent piperacks. Please investigate and verify location since the drawing shows, it crosses the TPER by several inches only and confirm in the Enfineering to relocate to avoid cracks in future. Contractor: Daelim shall provide drawing regarding this issue. Page 91 of 142 LOG BOOK ENTRY (LBE) SUMMARY As of July 09, 2014 LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason VAF / PN S/N LBE NO. SUBCON/ CONTRACTOR 19 LBE-DLM- MECH-577 DAELIM (Enginnerin g) VAF 3 MECH Engineering 15-Jul-14 20 LBE-DLM- ELECT-142 DAELIM (Enginnerin g) VAF 1 ELECT Engineering 20-Jul-14 During surveillance inspection of LV control cables, 4Cx6mm2, 5CX2MM2, 30Cx2.5mm2 and ITRx2.5mm2 CU/XLPE/PVC, 0.6/1KV (MESC Cable) and 2PRX2.5MM2 (Dekoron cable), for Generator panel cable (GCP- 103H101) at Substation G-1120, it was observed the following violations: 1. LV Control has been installing at site without material receiving inspection. This violates as per Sch. "Q", Attachment IV, Para. 3.2. 2. LV Control cable has no marking per flame retardant in the outer sheath of the cable. This violates as per RT70-0430-00, Para. 1.7. During Line inspection in Gas Furnace area, it was observed that Pipe used as a support to other Pipe or supportingone pipe on the top of another pipe. This is violation against with G4Z-0010-00, Para. 9.6.6 states that "all inside battery limit piping, supporting one pipe on the Top of another pipe or hanging a pipe from an overhead pipe is strictly prohibited". Line # SVH-117507-10-PU74, ISO drawing # N016103ACA-SVH-117507- 03, Support Type/No.: EPS-120. Note: This violation is aslo applicable for all 7 Gas Furnaces SHV piping, similar type supports. Page 92 of 142 LOG BOOK ENTRY (LBE) SUMMARY As of July 09, 2014 DUE DATE Issued corrective action to Company Target Date 12-Oct-13 17-May-14 Company still awaits reply from Constractor Mar.2, 2014 Open 15-Feb-14 26-Feb-14 Info 26-Feb-14 25-Feb-14 Open 09-Mar-14 Refer to Company LBE additional comments Info 15-Mar-14 Open
Contractor: It was discussed to Engineering and feedback will be followed-up regarding the issue. -> Discussed and agreed with Company. NCR was issued to Daelim construction team. Subcontractor: The issue has been investigated & corrective action plan preprared by Construction. NCR was issued to Daelim Construction team. Contractor: Daelim applies the following method to field welding around rotating equipment. 1. The tack weld requirement in G4D-0140- 10 at flange adjacent to rotary equipment nozzle is applied for both suction and discharge nozzle. 2. In case the fabricated spool length is not enough according to site condition, then Daelim judges whether it can be managed with specified FW or not. If it is judged that could not be managed then the pipe is to be cut and welded with additional longer pipe piece. 3. To make sure not to cause strain on the flange conncetion to rotary equipment nuzzle, Daelim checks the flange position and parallel condition nozzle without bolting after pipe piece installation is completed. 4. Daelim ensures the pipe strain on the rotating equipment nozzle does not exceed the limit of coupling movement specified in G4D-0140-10 and G5S-5321-02. 5. If any heating repair is conducted without prior written approval, Daelim re- fabricates the certain spool. Company comment Approved Close LBE by Company CONTRACTOR'S CORRECTIVE ACTION PLAN STATUS Daelim/Subcontractor Response / Reason Page 93 of 142 LOG BOOK ENTRY (LBE) SUMMARY As of July 09, 2014 DUE DATE Issued corrective action to Company Target Date Company comment Approved Close LBE by Company CONTRACTOR'S CORRECTIVE ACTION PLAN STATUS Daelim/Subcontractor Response / Reason 23-Mar-14 Open 05-Apr-14 Open 05-Apr-14 Open 13-Apr-14 17-May-14 Info 18-May-14 20-Jul-14 Open 18-May-14 Open Contractor: Engineering was informed regarding this matter/Issue, company will be informed of contractor action. -> Discussed and agreed with Company. NCR was issued to Daelim Construction team. Contractor: Vendor site visit being arranged. The expected visit date is within 23 May 2014. -> NCR with coorective action was sent to Company through TR no. MFC-T-DS-CJ-QA-1567 dt July 14. Contractor: Already Fit-025 structural colomn supports are accepted, refer to attached drawing. Contractor: Contractor issue to vendor for replacment of damage part in MCC-103H204 -> Replaced with new component As discussed with Company PMT, Non-process area can be less than 1% slope Page 94 of 142 LOG BOOK ENTRY (LBE) SUMMARY As of July 09, 2014 DUE DATE Issued corrective action to Company Target Date Company comment Approved Close LBE by Company CONTRACTOR'S CORRECTIVE ACTION PLAN STATUS Daelim/Subcontractor Response / Reason 06-Jun-14 12-Jul-14 15-May-14 Info 20-Jun-14 15-Jul-14 Info 20-Jun-14 15-Aug-14 Info 25-Jun-14 25-Jun-14 Open 25-Jun-14 25-Jun-14 Open 10-Jul-14 27-Jul-14 Open 10-Jul-14 21-Jul-14 Open Contractor : DAELIM already issued technical memorandum for repair work of bracing to SADARA. And now we are communicating with SADARA's welding SME, Plummer, Robert for the welding of bracing. And we'll offcially issue the completed repair procedure after discussion with SADARA. Contractor: For T-1710, we already got the approval of the repair work for leveling of TSR from SADARA. Now we are installing shim plate and adjusting the level of TSR and internal trays at site. Contractor: Engineering will coordinate to Riyadh Cable for investigation on how this issue will be solved. -> TM or RFV shall be issued. Meanwhile, we received from vendor statung that there is no problem. Contractor: Contractor will coordinate to Zamil for explanation in this failed result Contractor: Discussed to civil construction and engineering action granted that they will provide ab approved drawing on how the proposal to be accepted by Company. An sketch is attached. Contractor: Daelim shall provide drawing regarding this issue. Page 95 of 142 LOG BOOK ENTRY (LBE) SUMMARY As of July 09, 2014 DUE DATE Issued corrective action to Company Target Date Company comment Approved Close LBE by Company CONTRACTOR'S CORRECTIVE ACTION PLAN STATUS Daelim/Subcontractor Response / Reason 18-Jul-14 Open 23-Jul-14 Open Page 96 of 142 LOG BOOK ENTRY (LBE) SUMMARY As of July 09, 2014 1 LBE-DLM- INST-098 DAELIM (Enginnerin g) VAF 1 INST Instrumentation 26-Jan-14 2 LBE-AMA- INST-015 AMA VAF 2 INST Instrumentation 06-May-14 3 LBE-INST- ASYAD-017 ASYAD PN 2 INST Instrumentation 04-Jun-14 4 LBE-ASYAD- INST-025 ASYAD VAF 1 INST Instrumentation 25-Jun-14 5 LBE-ASYAD- INST-031 ASYAD VAF 1 INST Instrumentation 13-Jul-14 LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason During Site Surveillance at EW Pipe rack column no 58, it was noticed that open channel tray was damaged by Electrical crew. This violates schedule Q, attachment VI para. 5 and G078-0322. Contractor requested to take preventive action and re-offer inspection to Company after modification. Contractor: SS 316 Nylon coated ties are not available as of now but the material shall be ordered and as soon as it available, Contractor/Subcontractor will change the temporary ties to SS316 Nylon coated ties. PN: During site surviellance at EW Pipe rack, it was observed that Contractor installed open channel tray in improper way. Tray below the flange and un-avoidable . This violates G-07C-0321-01, Para. 3.8 & NEMA- VE-2 and NEC 110.12. Contractor requested to take a necessary action. S/N LBE NO. SUBCON/ CONTRACTOR Subcontractor: Channel Cable tray will be provided with cover that serves as cable protection and any falling debris. VAF / PN During the time of cable tray inspection, it was observed that Contractor installed wrong splice plate. Instead of round type connector, installed was slotted type. This violates NEMA VEZ, project specs G-07C-301. Subcontractor: Splice plate shall be replaced when the material is available. Waiting for Daelim supplied material to be available at site. During site surveillance (all area) at site (general), it was noticed that Contractor installed PVC tie instead of 316 Nylon cooled ties. This violation RT6E-0802-01, Para. Note-10, Contractor requested to take a preventive action. During inspection at site at PIB G-1121, following violation has been has been noticed during cable tray inspection. Splice over support, field fabricated fitting used instead of factory made. Improper nut and bolts used in tray, wrong splice plate used, slotted hole joint plate used instead of round hole. There is no clearance between two layers of tray, provide proper separation between tray, Contractor used 150mm open channel tray instead of 100mm maximum allowed. This violation RTGE-0802-01, NEMA VE2, G-07C-0321-G07C--0324. Subcontractor: The Subcontractor wil rectify the field fabricated items and splash plate to be repalced with Standard Materials at the earliest. Page 97 of 139 LOG BOOK ENTRY (LBE) SUMMARY As of July 09, 2014 DUE DATE Issued corrective action to Company Target Date 29-Jan-14 09-Feb-14 24-Jul-14 Open 09-May-14 19-Jun-14 30-Jul-14 Open 07-Jun-14 30-Jul-14 Info 28-Jun-14 25-Jun-14 Two Weeks Open 16-Jul-14 24-Jul-14 Open STATUS Daelim/Subcontractor Response / Reason Company comment Approved Close LBE by Company CONTRACTOR'S CORRECTIVE ACTION PLAN Contractor: SS 316 Nylon coated ties are not available as of now but the material shall be ordered and as soon as it available, Contractor/Subcontractor will change the temporary ties to SS316 Nylon coated ties. Subcontractor: Channel Cable tray will be provided with cover that serves as cable protection and any falling debris. Subcontractor: Splice plate shall be replaced when the material is available. Waiting for Daelim supplied material to be available at site. Subcontractor: The Subcontractor wil rectify the field fabricated items and splash plate to be repalced with Standard Materials at the earliest. Page 98 of 139 LOG BOOK ENTRY (LBE) SUMMARY As of July 09, 2014 1 LBE-DLM- MECH-281 DAELIM (Procureme nt) VAF 2 MECH Material 28-Jul-13 2 LBE-DLM- MECH-283 DAELIM (Procureme nt) VAF 2 MECH Material 01-Aug-13 3 LBE-DLM- MECH-286 DAELIM (Procureme nt) VAF 2 MECH Material 06-Aug-13 4 LBE-DLM- INST-062 DAELIM (Procureme nt) VAF 1 INST Material 05-Sep-13 5 LBE-DLM- MECH-330 DAELIM (Procureme nt) VAF 2 MECH Material 11-Sep-13 6 LBE-DLM- MECH-338 DAELIM (Procureme nt) VAF 2 MECH Material 18-Sep-13 LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason S/N LBE NO. SUBCON/ CONTRACTOR VAF / PN During Material Receiving inspection for Equipment (W1720) & (W1721) at site, the Equipment W1720 found with flanges corroded, external surface of the equipment especially place were saddle was attached and other surface of the equipment, some internal pipes connection to the flange were also also found corroeded. Equipment W1721 found with corroded flanges. The equipment is also found errected without proper preservation for corrotion deterioration. This is a violation as per A554-E-103-QA-GEN- PRO-035, Para 8.2.1, 8.1.11, 8.1.12, RT--6-ICS, 2.19.3. These equipment are supplied by DOOSAN Engineering. Subcontractor: Noted. Action shall be taken and as per construction plan for the corrossion, painting touch up repair will be implemented. Target date: 25 Nov. 2013. Material Receiving inspection of the flare runner at laydown yard shown the supports welded to the runners for attaching heat shield found bended. This can damage the welded portion and also may have taken place during transportation mishandled the equipment. The supplier of this equipment is ZEECO Industries, Korea. P.O. No. is 100532-14-216-001- A01, violation as per Ref. A554-E-103-QA-GEN-PRO-035, Para. 8.2.1, 8.1.11, 8.1.12. Contractor: The bended material already repaired and installed at site. Material receiving inspection at Daelim laydown yard revealed cooling tower accessories supplied bt SPIG (internal & external plates) were found damaged. Square tubes were stocked improperly. All these accessories are made of FRP materials without proper maintainance. Contractor: These items were verified with Sadara Inspector in the presence of SPIG of personnel that external/Internal plates material with damaged parts shall be repaired as per procedure. SPIG will submit the work procedure to Daelim and Sadara prior to start the repair work. Target date: 3 weeks. During Material Receiving inspection of Compressor, it was observed that compressor instrument & Junction Box (JB) are not as per Standard. Compressor C-02501 documents are not available such as FAT Report, MTR, Calibration report. Grounding is not connected to JB Instrument and not completed. This violates G06A-0003-17 & G06A-41-00. Contractor: Contractor will provide the documents; and RFI shall be resubmitted to Company for review and approval. Related to NCR. NCR-ARCC-INST-001, ARCC requested Daelim to provide MOV then ARCC shall install. During Material receiving inspection of C3R 4th stage suction drum (D2508) supplied by DOOSAN found corroded in the skill portion of the equipment which require better preservation to avoid further degradation as per A554-E-103-QA-GEN-PRO-035, Para. 8.2.5. Corrective action required. Contractor: Noted. Action shall be taken and as per Construction Plan for the corrosion, painting touch-up repair shall be commenced/implemented. Target Date: 25 Nov. 2013. During material receiving inspection at site revealed that plates with plates secondary transfer live exchanger (E1122) supplied by ALSTDM having distorted nameplate occurred due to improper lifting or transportation violation as per A555-E-103-QA-GEN-PRO-0353, para 8.2.1. Contractor: Regarding ladder rung which has corroded at sump pit #645, Company has already issued NCR to Contractor. As per advice by Sadara Inspector, Amana has started the cleaning/grinding work of ladder rung of sump-0645. Amana will rectify the coating as per recommendation od Company. Page 99 of 142 LOG BOOK ENTRY (LBE) SUMMARY As of July 09, 2014 LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason S/N LBE NO. SUBCON/ CONTRACTOR VAF / PN 7 LBE-DLM- MECH-403 DAELIM (Procureme nt) VAF 2 MECH Material 24-Nov-13 8 LBE-DLM- ELECT-085 DAELIM (Mat. Dept & Procuremen t) VAF 1 ELECT Material (Procurement) 26-Nov-13 9 LBE-DLM- MECH-445 DAELIM (Procureme nt) VAF 3 MECH Material 05-Jan-14 10 LBE-DLM- MECH-505 DAELIM (Procureme nt) VAF 3 MECH Material 09-Mar-14 11 LBE-DLM- MECH-513 DAELIM (Mat. Dept) VAF 3 MECH Material 17-Mar-14 During material receiving inspection of Valves, it has been noticed that failure of paint bwtween prime coat and top coat. P.O. No. U31-002-A02- 42, Vendor: NEWMANS, RFI No. MFC-DLM-NEWMAN-PIP-001. No of Valve approximately 54 nos. This violates Sadara Specification G16S-0202- 04 which mandates "each coat shall be of the correct colour, free of defects such as but not limited to pinholes, blisters, dry spray, detrimental runs and sags, excessive or inadequate film built, improper recoat times, foriegn inclussion and adhesion between Coat and to the substrate shall equal the manufacturer's limit. Contractor shall verify occured discrepancy and propose Corrective action. Contractor: Daelim Material Dept. already completed the repair works at the painting shop. During material receiving inspection of RFI # CCHINDS-EL-024 at Daelim Laydwon area, it was observed that the 2" Hot dip galvanized PVC coated conduit and 2" X 3/4" reducer fittings has no labeled and not listed. This violates as per G7C-0311-01, Para 1.2. Contractor: Daelim will provide certificate from Vendor for proof. Contractor will not use anymore these materials as per construction and it was already quarantined at the laydown yard. During inspectionof Valve leak testing at NASICO, leakage observed at Seat of a 18 nos of butterfly valves supplied by Zero Engr. And it is beyond the acceptable limit. Hence, valve is rejected. This violates API S98 para. 3.9.2. The Contractor shall follow up with the issue and notify the supplier for repair or replacements. During material receiving of Back wash water pup (P 0589) by powerking system found an instrumentation part attached to the seal reservoir is being damaged by it support attaching it to the reservior by welding. The damage may havehappened due to poor handling and preservation. This is violation as per A554-E-103-QA-GEN-PRO-034, Para. 8.1.3 & A554-E-103-QA- GEN-PRO-035, Para. 8.2.1.11 & 8.11. During Valve Receiving Inspection, It has benn Observed that some supplies are Violation DOW Spec for Tagging. According to G4R-7200-01 Each Valve Shall be tagged by vendor with a brass tag with monel wire and crimped with each other onto the wire end to avoid loses of tags, VENDOR NAME: 1. Bonney forged Italy, 2. Pantair Vanessa, 3. Zero Engg., All vendors provided valve tag without the monel crimp sleeve that may cause of lost tag. Contractor: Company accepted Contractor's TM indicating that stainless steel 18 gauge wire and using crimp sleeves of same base netal of wire is acceptable. (MFC-T-CJ-DS-PI-0976) Page 100 of 142 LOG BOOK ENTRY (LBE) SUMMARY As of July 09, 2014 LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason S/N LBE NO. SUBCON/ CONTRACTOR VAF / PN 12 LBE-DLM- MECH-518 DAELIM (Procureme nt) VAF 3 MECH Material 05-Apr-14 13 LBE-DLM- MECH-534 DAELIM (Procureme nt) VAF 3 MECH Material 30-Apr-14 14 LBE-AMA- CIVIL-276 AMA VAF 1 CIVIL Material 01-May-14 15 LBE-DLM- ELECT-132 DAELIM (Procureme nt) VAF 1 ELECT Material 19-May-14 16 LBE-DLM- MECH-574 DAELIM (Procureme nt) VAF 3 MECH Material 10-Jul-14 17 LBE-DLM- MECH-576 DAELIM (Procureme nt) VAF 3 MECH Material 14-Jul-14 During review of material test certificate of LTCS Pipes A333 Gr. 6 (PO No. - 100532-B-PIP-0037-01) it is observed that mill certificate does not have the impact test details, this is violation of ASTM A333 Gr. 6 Para. 14 which specifies all materials furnished under LTCS soecification shall be tested for impact resistance at all temp for the respective grade.
During Leak testing of Manual Butterfly valve in NAISCO Testing Facility Jubail, it was observed that there was contineous leak found in the 14" x 150 butterfly valve in low pressure closure test due to crack in heating area. This is vioaltes API 598 Table 6., DAelim Should take Appropiate action and corrective action, Contractor: It is under process to send back to vendor shop for this repair. During Material Receiving inspection and pre-alignment verfication of Sump pump (vertical 7 unit) observed that significant defirence on RPM with Manufacturer name plate data and project data sheet. (Enbossed RPM on motor is 3480 instead of 3560) which couild be impact on efficiency time and dischargearation, etc. Daelim Engineering shall investigate and propose the corrective action prior to final alignment of subject of 7 units of pumps. Please inform Contractor of applicable equipment numbers. During Surviellance and monitoring acivities at sub-sation G-1120, along transient lips sytem, we found out that "steel door" SDG was deformed or damaged, in this regards, contractor was revised to check or investigate the said steel door and replace with good materials as per latest IFC Drwg./Door Schedule. Subcontractor: The deformed dorr "SDG" is already repaired and re- installed at site. During Material Receiving Inspection of the Thermal Fire Detector at Daelim laydown yard, it was found that the thermal fire detection (P/N 27120) are not matching with Pusrcahse Order. Note. This is violation to attached documents and schedule "Q", attachment III, Section 3. Contractor: This issue will be forwarded to procurement for further investigation regarding traceabiity of materials. This LBE will be updated once the action of procurement is given. During surveillance inspection in Liquid furnace area, it was observed that, Contractor has been procuring wrong material Flow element Vnturi and welded with high pressure steam piping PU74. The material specification found A 183 Grade F11, instead of A182 Grade F22. This is violation as per PU74 Pipig Material Specfication (Base metal P22) and construction ASME B 31.3. FE Tag Numbers: FE121552, FE223552, FE123552, FE124552 and FE125552. Line Number SVH-122504-12 PU74 and application each lighuid frncaces. Contractor: New venturi flowmeter was ordered and fabrication is on- going Page 101 of 142 LOG BOOK ENTRY (LBE) SUMMARY As of July 09, 2014 LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason S/N LBE NO. SUBCON/ CONTRACTOR VAF / PN 18 LBE-KCC- CIVIL-310 KCC VAF 2 CIVIL Material 14-Jul-14 The Contractor/Subcontractor installed the Pre-fabricated gratings cover on ditches without the proper issuance of RFI for the Material receiving inspection. It was also noted that there was a variance of size on the cross bar from 10mm as per required to 8mm actual size delivered. This violates schedule Q section 3.2 and Standard drawing. QC inspector shall initiate the RFI in a timely manner per approved ITP. Contractor shall investigate the root cause and initiate corrective action regarding the size variance on cross bar gratings. Page 102 of 142 LOG BOOK ENTRY (LBE) SUMMARY As of July 09, 2014 DUE DATE Issued corrective action to Company 31-Jul-13 11-Aug-13 Open 04-Aug-13 20-Jul-14 Open 09-Aug-13 20-Aug-13 Open 08-Sep-13 17-Sep-13 24-Jul-14 Open 14-Sep-13 25-Sep-13 Open 21-Sep-13 22-Jul-14 Open STATUS Daelim/Subcontractor Response / Reason CONTRACTOR'S CORRECTIVE ACTION PLAN Company comment Approved Close LBE by Company Subcontractor: Noted. Action shall be taken and as per construction plan for the corrossion, painting touch up repair will be implemented. Target date: 25 Nov. 2013. Contractor: The bended material already repaired and installed at site. Contractor: These items were verified with Sadara Inspector in the presence of SPIG of personnel that external/Internal plates material with damaged parts shall be repaired as per procedure. SPIG will submit the work procedure to Daelim and Sadara prior to start the repair work. Target date: 3 weeks. Contractor: Contractor will provide the documents; and RFI shall be resubmitted to Company for review and approval. Related to NCR. NCR-ARCC-INST-001, ARCC requested Daelim to provide MOV then ARCC shall install. Contractor: Noted. Action shall be taken and as per Construction Plan for the corrosion, painting touch-up repair shall be commenced/implemented. Target Date: 25 Nov. 2013. Contractor: Regarding ladder rung which has corroded at sump pit #645, Company has already issued NCR to Contractor. As per advice by Sadara Inspector, Amana has started the cleaning/grinding work of ladder rung of sump-0645. Amana will rectify the coating as per recommendation od Company. Page 103 of 142 LOG BOOK ENTRY (LBE) SUMMARY As of July 09, 2014 DUE DATE Issued corrective action to Company STATUS Daelim/Subcontractor Response / Reason CONTRACTOR'S CORRECTIVE ACTION PLAN Company comment Approved Close LBE by Company 27-Nov-13 14-Jul-14 Open 29-Nov-13 10-Dec-13 Open 08-Jan-14 Open 12-Mar-14 Open 20-Mar-14 Open Contractor: Daelim Material Dept. already completed the repair works at the painting shop. Contractor: Daelim will provide certificate from Vendor for proof. Contractor will not use anymore these materials as per construction and it was already quarantined at the laydown yard. Contractor: Company accepted Contractor's TM indicating that stainless steel 18 gauge wire and using crimp sleeves of same base netal of wire is acceptable. (MFC-T-CJ-DS-PI-0976) Page 104 of 142 LOG BOOK ENTRY (LBE) SUMMARY As of July 09, 2014 DUE DATE Issued corrective action to Company STATUS Daelim/Subcontractor Response / Reason CONTRACTOR'S CORRECTIVE ACTION PLAN Company comment Approved Close LBE by Company 08-Apr-14 Open 03-May-14 17-May-14 Open 04-May-14 26-May-14 30-Apr-14 Open 22-May-14 24-May-14 Open 13-Jul-14 Open 17-Jul-14 Open
Contractor: It is under process to send back to vendor shop for this repair. Please inform Contractor of applicable equipment numbers. Subcontractor: The deformed dorr "SDG" is already repaired and re- installed at site. Contractor: This issue will be forwarded to procurement for further investigation regarding traceabiity of materials. This LBE will be updated once the action of procurement is given. Contractor: New venturi flowmeter was ordered and fabrication is on- going Page 105 of 142 LOG BOOK ENTRY (LBE) SUMMARY As of July 09, 2014 DUE DATE Issued corrective action to Company STATUS Daelim/Subcontractor Response / Reason CONTRACTOR'S CORRECTIVE ACTION PLAN Company comment Approved Close LBE by Company 17-Jul-14 Open Page 106 of 142 LOG BOOK ENTRY (LBE) SUMMARY As of July 09, 2014 1 LBE-DLM- MECH-296 DAELIM (Mat. Dept) PN 2 MECH Mechanical (Equipment) 17-Aug-13 2 LBE-DLM- MECH-321 DAELIM (Constructio n) VAF 2 MECH Mechanical (Equipment) 09-Sep-13 3 LBE-DLM- MECH-342 DAELIM (Constructio n) VAF 2 MECH Mechanical (Equipment) 23-Sep-13 4 LBE-DLM- MECH-346 DAELIM (Enginnerin g) VAF 2 MECH Mechanical (Equipment) 25-Sep-13 5 LBE-DLM- MECH-367 DAELIM (Constructio n) VAF 2 MECH Mechanical (Equipment) 14-Oct-13 Observed that Surface Condensater (CG Compressor #2301) pressure parts. (Vendor clossed part) were open for easy installation which is not designed for Contractor activities. Daelim/TCC team is not authorized to open/relocate the PCE without proper approval, elsewhere it has be to be designed for further Constraction. Violation of Sch. "Q" and ITP and required corrective action. Contractor: Noted: Contractor Engineering Dept. will issue documents to primarily support this aactivity. Target date: 1st week of Nov. 2013. Observed several locations Anchor bolt holes were extended during equipment installation due to misalignment/dimensional discrepancy with fabrication/GA drawing and trimmed hole are extended as specifying tolerance limit by Vendor. The anchor bolts hole shall not be extended/reduced in diameter nor offset to facilitate modification of the mounting plate to facilitiate alignment is not permitted unless authorized by designated vendor. Violation of A554-E-103-QA-GEN-PLN-056. Trimmed area shall be coated with paints material.specifications. Contractor: As per discussion with Construction Mech. Superintendent Mr. E.M. Choi, Engineering Query shall be released in support for the bolt hole enlargement. (Field Engineering Personnel Mr. Chan Ho Park will be available on the 2nd of November 2013) Target date: 1st week of November. -> Received approval from Company on Daelim's corrective action. So this shall be closed. During surveillance inspection at furnace F-1160, Radiant crossover piping installed on position observed that numerous discrepancies on pass 1 and 2 header lines. Example: Inclination of levelness, plumbness, dimensional discrepancy on pipe supports and sidtoration due to improper fabrication method etc. by Vendor JNK, Korea. Daelim/ARCC shall verify occured discrepancy and propose corrective action in accordance with appropriate Engineering Method. During Material Receiving at site for inspection of Ground Flare Auxiliary and spare parts. Supports found with bolts welded to the support, have threads exposed without proteection. It is a violation as per RT-^-ICS, 2.19A4C. Subcontractor: Noted. Action will be taken. PN: During the Material Receiving inspection for Turbo expander: Unit counter panel (21392-3) box with the indicator with showing red color. (Showing shock occurrence due to handling improperly) hence inspection for damages require as per manufacturer advice if damaged imidiate inspection request from carrier within 15 days of delivery. 2. Spare rotating assembly is N2 purged container with O reading in the gauge and red light indication piece no. (21392-1) Contractor: It was completed for inspection works with Mr. Kurian and already installed at site few months ageo. Daelim already closed the issue. 2 spare rotating containers had been changedN2 in container and already been installed at the rotor storage area. LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason VAF / PN S/N LBE NO. SUBCON/ CONTRACTOR Page 107 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 09, 2014 LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason VAF / PN S/N LBE NO. SUBCON/ CONTRACTOR 6 LBE-DLM- MECH-369 DAELIM (Procureme nt) VAF 2 MECH Mechanical (Equipment) 21-Oct-13 7 LBE-DLM- MECH-395 DAELIM (Enginnerin g) VAF 2 MECH Mechanical (Equipment) 12-Nov-13 8 LBE-DLM- MECH-418 DAELIM (Enginnerin g) VAF 2 MECH Mechanical (Equipment) 10-Dec-13 9 LBE-DLM- MECH-440 DAELIM (Enginnerin g) VAF 3 MECH Mechanical (Equipment) 29-Dec-13 10 LBE-DLM- MECH-451 DAELIM (Constructio n) PN 3 MECH Mechanical (Equipment) 07-Jan-14 During routine inspection for insulation activities of Water Quence Towe (T- 1410), it has been noticed that there is no adequate distance between step ladder of ladder cage and insulation ring (approx. 2"). As per standard requirement the distance required is 230mm. This is for your information and corrective action required. Subcontractor: This isue is related to Daelim Engineering. Reply fom Daelim Engineeing attached. Contractor: Contractor will modify the ladder for expanding distance between ladder rung and insulation ring. For this issue, we already received the confirmation for repair procedure from Company. PN: Received an equipment D21-24 (Reflex drum) this with three others. T- 2120 (Secondary Demethanizer) E-2121 (Interncondenser) & 2123 will be installed one over the other vertically with T-2120 at the bottom. E-2121 & E-2123 are yet to arrive but SME, Engineering and Vendor guidance instruction required to whether to carry out a combined hydrotest to prove the integrity of the bolted flange joints of these equipment. The general arrangement drawing is also mentioning of field hydro test for about 21.047 bar. Surveillance shown the equipment P42131 (Cold box) the nozzle "GVENTI" found bended due to mishandling or may be during installation at site, this is a violation as per A554-E-103-QA-GEN-PRO-034, Para. 8.1.3. and A554- E-103-QA-GEN-PRO-035, Para. 8.2.1. & 8.1.11.8.1.1. Contractor: Contractor cannot recognize this issue for Cold Box (PU 2131). Please expalin or provide the picture for bended nozzle to us. Installation process of Incinerator at spent caustic area noted the following discrepancy: * Alignment process of smelt dissolver and incinerator sole and filler plate height exceed up to 70: as recommended by gvendor it shall be 20mm. *Incinerator holding structure (secondary girder beam @ 23050) are showing inclination level variance and gusset plate are slightly bend. * Bolt length are not sufficient to engage lock nut as per vendor design. * Daelim shall advised to re-evaluate the structural integrity and fix the discrepancy with prior approved Method by Company. Contractor: This item already have been solved. Please note as below description. Although the alignment height is approx. 20mm as per vendor print, Contractor will adjust the alignment through inserting the more filler plate at site. Hence, Contractor eill request vendor to confirm whether 70mm height for alignment is suitable; and receive the confirmation letter. Also, Daelim will officially receive the revised drawing as per site adjustment. The exact slightly in AISC Code, Flange-tilt tolerance are allowed to 8mm, in case depth exceeds 300mm. The depth of W12x40 is 303 mm, which means the tilt tolerances could be approved by 8mm. So the case of support beam for IN-0510 is no problem. At surveillance, it is observed that Equipment E-2303 bottom side of the supporting leg is not painted as per the required painting specs. Also this part is corroded which may damage the metal support. This is the improper following of painting spec. The equipment is supplied by Doosan Engineering with P.O. No. 100532-13-231-001. Contractor: Noted. Action shall be taken and as per Construction Plan for the corrosion, painting touch-up repair shall be commenced/implemented. Target Date: 25 Nov. 2013. Page 108 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 09, 2014 LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason VAF / PN S/N LBE NO. SUBCON/ CONTRACTOR 11 LBE-TCC- MECH-461 TCC VAF 3 MECH Mechanical (Equipment) 19-Jan-14 12 LBE-DLM- MECH-473 DAELIM (Enginnerin g) VAF 3 MECH Mechanical (Equipment) 04-Feb-14 13 LBE-DLM- MECH-479 DAELIM (Constructio n) VAF 3 MECH Mechanical (Equipment) 16-Feb-14 14 LBE-DLM- MECH-480 DAELIM (Constructio n) VAF 3 MECH Mechanical (Equipment) 18-Feb-14 15 LBE-DLM- MECH-490 DAELIM (Constructio n) VAF 3 MECH Mechanical (Equipment) 25-Feb-14 Material receiving inpsection of overhead crane hoist for common compressor having a name plate no. CR 1695 with capacity of 100/15 ton double girder top STAHL manufactured, has damaged rolly plat form. Which may have occurred due to improper handling and the rail on which the crane will be mounted and rolled is corroded. Painting is required on all surfaces. Other than trail-trolly wheel contact surface as per the manufacturer drawing. Ref. RTBICS, para. 2.2.11, 2.4.1, A554-E-103-QA- GEN-PRO-035, para. 8.1.9, 8.1.11, 8.2.6 & 8.1.11. During inspection at Cooling Tower Basin area (PS-V7) El-19530, west side of the cooling tower for structural padding elevation, it is observed the anchor bolt for column support for 2" piping were bent damage and mismatching with the column nameplate holes. It is a violation as per A554- E-103-QA-GEN-PRO-012 Para. 7.1.3, 7.1.4, 7.1.5. Daelim should also attach survey reports to the mech (structural RFI) for anchor bolts syrvey from subcontractor surveryor. Ref.: A554-E-103-QA-GEN-PRO-012. para. 7.1.14, 7.1.15. On inspection of process condensale. Shipped tower (T1510) internals, found that super-heated steam inlet (A2-24") pipe is not rested on the support. A gap of approx. 15mm is having between the pipe and support. This may have as adverse impact on the process functioning of the equipment as the feed pipe is subjected to super heated steam flow causing the material expansion contraction and mechanical vibration during operation aslo full load and acting directly on one side of its bolted flange. An Engineering/Desing solution required. Ref: 115105-D003, RT 5093-01, Para 14 (D). During surviellance at site, it has been noticed that there is no adequate space between step ladder of vertical ladder and insulation rings for oil quence tower (T-1310). The distance between them approximately is 60mm. The distance required as per standard is 230mm after insulation. Logbook entry has been logged for root cause analysis and corrective action prior to biginning insulation activities. Contractor: LBE-DAELIM-MECH-469: 1.The revised drawing were issued last february. The modification work will be followed by construction team. 2. LBE-DAELI<-MECH-440 & LBE-DAELIM-MECH-473 the modification design is agreed as attached. the further commincation with sadara QC is being done. once investigation is complete, site instruction will be issued through constrution team. Contractor at MFC site raised RFI TCC-SS-WE-0608 for the Post welding inspection Structural Support T--1810 but inspection showed the support were only tack welded which made the RFI's to cancel. The Structures attached to this were there never inspected after this and the equipment is already been erected. The Inspector for pipe welding was on 25/12/2014. Subcontractor: Supporting drawing was revised. Accepted RFI is attached, Page 109 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 09, 2014 LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason VAF / PN S/N LBE NO. SUBCON/ CONTRACTOR 16 LBE-DLM- MECH-500 DAELIM (Constructio n) VAF 3 MECH Mechanical (Equipment) 06-Mar-14 17 LBE-DLM- MECH-507 DAELIM (Constructio n) VAF 3 MECH Mechanical (Equipment) 09-Mar-14 18 LBE-ARCC- MECH-519 ARCC VAF 3 MECH Mechanical (Equipment) 05-Apr-14 19 LBE-DLM- MECH-520 DAELIM (Constructio n) VAF 3 MECH Mechanical 05-Apr-14 20 LBE-DLM- MECH-521 DAELIM (Enginnerin g) VAF 1 MECH Mechanical 09-Apr-14 WRONG TEMPERATURE CHARPY TESTED PIPES: The piping Class HC72 and HC35 used pipe Material size NPS 30" and 64" has been charpy tested at 29C (-20F), Instead of (-45C (-50F) at manufacturer Place. Pipe material ASTM A671 GR CC70 CL. 12, S2., This is Violation against piping Material Specification RTIP, HC72-103 and HC35-103, common general note P-LC04PE625, states that charpy Test shall be for -50F (- 45C). Pipe Manufacturer; SEAH Steel Corp, KOREA, MTC No. D20121- 1123-024263(1305656) Dated 21 Dec-12, D201210-1268-020252 Dated 22-OCT-14, Found Heat No. SF23532 (30"), SP36974 (64") Contractor has confirmed to take corrective action at site, remaining available same heat number stock pipes, carry out retest or alternative solution for this vioaltion.
Observed the following violation discrepancy 1. Third discharge drum D- 1607 nozzle LIB 2" flange has damaged or distorted and out of squireness due to improper material boundary. 2. Flange space seration damaged on steam vent silencer on F-1170 (1030-SI-117) DAELIM shall verify the extention damage and propose appropraite rectification method to company approval.
Observed that ARCC is modify combustion air duct/stack without confirmed support document or approval following discrepancy Noted: F 1240 area, * Duct was damaged due to improper fabrication method * gas was burned by gas cutting flame. DAELIM/ARCC shall propose appropiate corrective action for rectifying the damaged part and replace damaged gasket * DAELIM shall obtain proper approval for rectifying any vendor supplied eqpt. prior to start activity by company, Violation of Sch Q and Material management plan. Subcontractor: ARCC to Rectify this violation as per submitted & Approved method Statement. Attached photo of rectified conbustion duct. During tray leveling inspection for the tower T1510, it is noticed that tray no. 2with downcommer pannel (EB-102) is having a scattered corrossion on its surface. Corrective ation is required. Ref. RTSS-5093-01, Para. 1.37, 1.3.8., RT 6-1CS. Furnace pipe rack observed that weld joint were distorted and flange face is off-set up: 10mm due to improper fabrication method and welding technique on BFV-123501-6P007. Violation of Fabrication drawing and procedure A554-E-103-QA-GEN-PRO-046. Page 110 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 09, 2014 LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason VAF / PN S/N LBE NO. SUBCON/ CONTRACTOR 21 LBE-GACC- MECH-522 GACC VAF 3 MECH Mechanical 10-Apr-14 22 LBE-DLM- MECH-523 DAELIM (Procureme nt) VAF 3 MECH Mechanical 10-Apr-14 23 LBE-DLM- MECH-525 DAELIM (Procureme nt) VAF 3 MECH Mechanical 10-Apr-14 24 LBE-DLM- MECH-530 DAELIM (Enginnerin g) VAF 3 MECH Mechanical 23-Apr-14 25 LBE-GACC- MECH-557 GACC VAF 3 MECH Mechanical (Equipment) 24-Jun-14 During surveillance, it is noticed that during night shifts in tower T-1710, the subcontractor is installing tray and TSR without inspection of levelness, no RFI's were raised for the installation levelness inspection scale pan, tray 1,2,3. Also no subcontractor QC was available during this inspection. Daelim should ensure that concerened QC is raising RFI of the installation of internal activities of tray with the presence and/or involvement of subcontractor QC. It is a violation as per A554-E-103-QA-GEN-PLN-103, Para. 3.39, 3.33 Sch. Q, attachment VI. Contractor: Already one QC Inspector has been assigned for the night shift and has been attending inspection in the night shift from 2nd of July onwards. The Trays 1,2,3 have already ben completed and RFI's for the same already been submitted. The concerned RFI nos. are MFC-DLM-GA-ME-0060, 061, 062, 0063 & 0064. All the inspections are now goin in line with the requirements and in the presence of QC Inspector. During Inspection it is found that in tower (T2110 Primary Demethanizer) for internal tray Installation flange down condencer brazing suppor for the false down commer plate is not welded to the tower shell, also for lower T1810, HP depropanizer bolt for tray 31 placed BW feed pipe at beneath tray 31 is not founded welded. contractor shall take corrective action consulting with the tower manufacturer and SME. Ref. KOCH-GLI-TSCH Drwg. No. 115108-D000, 115111-D001. Contractor: Contractor already discussed the issue with Company and will submit the site work procedure for missing clips to Company. After receiving the confirmation from Company, Contractor will do site work. Contractor: Contractor is now procuring the required material for T- 1810 & T-2110. (1) T-2110 : Required Material (SA 537 Cl.1+S5, -48) is arrived at site. (2) T-1810 : Contractor is continuously expediting Tower fabricator to supply the reqruied material (SA 537 Cl.1 + S5, -59 Impact Tested) Observed that the spent caustic unit T-0523 scrobber tower nozzle B1 observed imperfection of flange face (Serration damaged) is exceed as permissible tolerance limit of ASME 16.47 Table: 29 Daelim QC and Engineering team shall propose Rectification method and obtain company approval prior to comments any activities in subjected nozzle. Contractor: Vendor recommends to make smooth finish by sand paper, then to use liquid paste together with gasket. During Surviellance at MFC Daelim Site it is noticed/observed that the dilution steam generator structure, Strcutural Brazing welded to the embedded plate were half/incompletely welded is found at all the different elevation of the dilution steam generator structure TCC has an inspection point with Daelim with witness point as per the ITP. Hence it is violation of ITP and Procedure. Ref.# A554-E-103-QA-GEN-PLN-021 Rev. 3 Para. 4.2, 4.11, 4.9 Subcontractor: 1. Noted I will check with structure inspector and let you know regarding this issue. During Material Receiving Inspection E222313 Exchange it is noticed that its Leg (Jointed to the foundation) is bented makes it difficult in equipment align also the boday of the equipment is found damage (Corroded and broken - external body part), this may have happened in trnasportation and material handling, proper action to be taken by the contractor with the vendor recommendation for the rectification of the equipment. Ref #. A554- 103-QA-GEN-PRO-034 Para. 8.1.3 A554-E-103-QA-GEN-PRO-035 Para. 8.2.1 & 11.8.11
Page 111 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 09, 2014 LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason VAF / PN S/N LBE NO. SUBCON/ CONTRACTOR 26 LBE-ARCC- MECH-305 ARCC PN 3 MECH Mechanical 30-Jun-14 27 LBE-TCC- MECH-572 TCC VAF 3 MECH Mechanical 08-Jul-14 28 LBE-KCC- MECH-573 TCC VAF 3 MECH Mechanical 08-Jul-14 During surveillance at V2 Compressor area were found the serration of raise face was damage with line number PR-250905-04-A. This is violation to Flanged Joints - an overwiew (G4D-4250-01), Sec. 8, Para. 8.1 "The gasket faces of flanged joints which have been opened and cleaned should be visually inspected for corrosion (pitting and oxidation) and for defects (such as scracthes, cracking. Finish damage, etc) & 8.2 "Flangeswith nicks, scrathes, cuts or finish damage must be repalced". A logbook entry was made nd informed to PMT/Copntractor. Contractor shall provide necessary CAR. During Surveillance at Cooling Water Pump area were found the peel-off the expansion (rubber) due to excessive during bolt tihgtening at eight (8) locations pump nozzles. This violates G8S-8005-00, Sec. 6, Para. 6.2 "Cracking in this area indicates excessive stress and will need to be addresses before the flanged joint is re-assembled and 6.4.2.1 "Flanges should not have to be forced into alignment, friction, load and relaxation effects will be magnified during the preloading process if fasteners are used to force flanges into alignment". A logbook entry was made and informed to PMT/Contractor. Contractor shall provide necessary CAR. PN: During surveillance at North side of furnace area, it was noticed that excessive crack appears on the surface of epoxy grouted FD Fan foundations F-1164, F-1174, F-1244 & F-1254. This a repeated violation and Contractor should take immediate action to resolve this issue. Contractor is proatively advised to call for the attention of the epoxy grout manufacturer for any recommendations/action to avoide resurrence. Page 112 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 09, 2014 DUE DATE Issued corrective action to Company 20-Aug-13 15-Jul-14 Info 12-Sep-13 23-Sep-13 Open 26-Sep-13 Open 28-Sep-13 09-Oct-13 Open 17-Oct-13 22-Oct-13 Open Contractor: Noted: Contractor Engineering Dept. will issue documents to primarily support this aactivity. Target date: 1st week of Nov. 2013. Contractor: As per discussion with Construction Mech. Superintendent Mr. E.M. Choi, Engineering Query shall be released in support for the bolt hole enlargement. (Field Engineering Personnel Mr. Chan Ho Park will be available on the 2nd of November 2013) Target date: 1st week of November. -> Received approval from Company on Daelim's corrective action. So this shall be closed. Subcontractor: Noted. Action will be taken. Contractor: It was completed for inspection works with Mr. Kurian and already installed at site few months ageo. Daelim already closed the issue. 2 spare rotating containers had been changedN2 in container and already been installed at the rotor storage area. CONTRACTOR'S CORRECTIVE ACTION PLAN Company comment Approved Close LBE by Company STATUS Daelim/Subcontractor Response / Reason Page 113 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 09, 2014 DUE DATE Issued corrective action to Company CONTRACTOR'S CORRECTIVE ACTION PLAN Company comment Approved Close LBE by Company STATUS Daelim/Subcontractor Response / Reason 24-Oct-13 04-Nov-13 Open 15-Nov-13 17-May-14 Open 13-Dec-13 17-May-14 Open 01-Jan-14 19-Mar-14 Open 10-Jan-14 Info Subcontractor: This isue is related to Daelim Engineering. Reply fom Daelim Engineeing attached. Contractor: Contractor will modify the ladder for expanding distance between ladder rung and insulation ring. For this issue, we already received the confirmation for repair procedure from Company. Contractor: Contractor cannot recognize this issue for Cold Box (PU 2131). Please expalin or provide the picture for bended nozzle to us. Contractor: This item already have been solved. Please note as below description. Although the alignment height is approx. 20mm as per vendor print, Contractor will adjust the alignment through inserting the more filler plate at site. Hence, Contractor eill request vendor to confirm whether 70mm height for alignment is suitable; and receive the confirmation letter. Also, Daelim will officially receive the revised drawing as per site adjustment. The exact slightly in AISC Code, Flange-tilt tolerance are allowed to 8mm, in case depth exceeds 300mm. The depth of W12x40 is 303 mm, which means the tilt tolerances could be approved by 8mm. So the case of support beam for IN-0510 is no problem. Contractor: Noted. Action shall be taken and as per Construction Plan for the corrosion, painting touch-up repair shall be commenced/implemented. Target Date: 25 Nov. 2013. Page 114 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 09, 2014 DUE DATE Issued corrective action to Company CONTRACTOR'S CORRECTIVE ACTION PLAN Company comment Approved Close LBE by Company STATUS Daelim/Subcontractor Response / Reason 22-Jan-14 19-Mar-14 Open 07-Feb-14 19-Apr-14 Open 19-Feb-14 Open 21-Feb-14 Open 28-Feb-14 Open Contractor: LBE-DAELIM-MECH-469: 1.The revised drawing were issued last february. The modification work will be followed by construction team. 2. LBE-DAELI<-MECH-440 & LBE-DAELIM-MECH-473 the modification design is agreed as attached. the further commincation with sadara QC is being done. once investigation is complete, site instruction will be issued through constrution team. Subcontractor: Supporting drawing was revised. Accepted RFI is attached, Page 115 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 09, 2014 DUE DATE Issued corrective action to Company CONTRACTOR'S CORRECTIVE ACTION PLAN Company comment Approved Close LBE by Company STATUS Daelim/Subcontractor Response / Reason 09-Mar-14 Open 12-Mar-14 Open 08-Apr-14 12-Apr-14 Open 08-Apr-14 Open 12-Apr-14 Open
Subcontractor: ARCC to Rectify this violation as per submitted & Approved method Statement. Attached photo of rectified conbustion duct. Page 116 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 09, 2014 DUE DATE Issued corrective action to Company CONTRACTOR'S CORRECTIVE ACTION PLAN Company comment Approved Close LBE by Company STATUS Daelim/Subcontractor Response / Reason 13-Apr-14 18-Apr-14 Open 13-Apr-14 Open 13-Apr-14 17-May-14 Open 26-Apr-14 17-May-14 Open 27-Jun-14 20-Jul-14 Open Contractor: Already one QC Inspector has been assigned for the night shift and has been attending inspection in the night shift from 2nd of July onwards. The Trays 1,2,3 have already ben completed and RFI's for the same already been submitted. The concerned RFI nos. are MFC-DLM-GA-ME-0060, 061, 062, 0063 & 0064. All the inspections are now goin in line with the requirements and in the presence of QC Inspector. Contractor: Contractor already discussed the issue with Company and will submit the site work procedure for missing clips to Company. After receiving the confirmation from Company, Contractor will do site work. Contractor: Contractor is now procuring the required material for T- 1810 & T-2110. (1) T-2110 : Required Material (SA 537 Cl.1+S5, -48) is arrived at site. (2) T-1810 : Contractor is continuously expediting Tower fabricator to supply the reqruied material (SA 537 Cl.1 + S5, -59 Impact Tested) Contractor: Vendor recommends to make smooth finish by sand paper, then to use liquid paste together with gasket. Subcontractor: 1. Noted I will check with structure inspector and let you know regarding this issue.
Page 117 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 09, 2014 DUE DATE Issued corrective action to Company CONTRACTOR'S CORRECTIVE ACTION PLAN Company comment Approved Close LBE by Company STATUS Daelim/Subcontractor Response / Reason 03-Jul-14 Info 11-Jul-14 Open 11-Jul-14 Open Page 118 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 09, 2014 1 LBE-ARCC- MECH-436 ARCC VAF 3 MECH Piping 26-Dec-13 2 LBE-DLM- MECH-465 DAELIM (Constructio n) VAF 3 MECH Piping 23-Jan-14 3 LBE-DLM- MECH-471 DAELIM (Procureme nt) VAF 3 MECH Piping 03-Feb-14 4 LBE-DLM- MECH-478 DAELIM (Procureme nt) VAF 3 MECH Piping 16-Feb-14 5 LBE-DLM- MECH-481 DAELIM (Constructio n) VAF 3 MECH Piping 19-Feb-14 6 LBE-DLM- MECH-489 DAELIM (Constructio n) VAF 3 MECH Piping 25-Feb-14 During pre-punching for package no. 1652-00HT-007 (T) line No. P- 172601-18"-4C01, it was noted that water filling started in the line without internal cleaning & flushing. This violates against G4S-G421-02, para. 4.9. During line inspection for package no. 1681-00-HT-017 (T) line no. P- 210602-30"-HC11, it was noted that 4 nos. of socket joints (between two dissimilar material A182-F308-304L & LTCSA671-CC70/Nipple A333-6) welded without approved WPS. This is violation against RT8S-6500-01, para. 2.2. Contractor shall provide Corrective & Preventive action. During valve testing, it was noted that butterfly valve (103-EBV-113051) 12"X150 Flanged face serrration damaged due to pitting. This is violation against Sadara Spec G14-S-3230-01 Para. 2.4. Contractor shall provide corrective and preventive action. During Material Receiving inspection of pipe fittings under P.O. 100532-42- K04-005-A01, it was noted that fitting internally coated with rust prevention paint. This is violation against DOW specification G4S-0210-01 para 2.1.5 which states that "If the piping was coated with a light coating of mineral oil to prevent corrosion, the coating shall be removed by pulling a swab saturated in cleaning solution through the piping". Contractor shall investigate and provide corrective and preventive action. Contractor: The fittings were internally coated in order to preserved and to avoid corrosions.Company acknowledged the close the issues. During surveillance, it was found that Vendor's Spools (R-2030 & R-2035) has been cut without providing detail method of statement which WPS and NDE to be used. This is violation against schedule "Q". Contractor needs to provide a full detail report on the incident. Subcontractor: Noted. Corrective action will be taken. Misalignment, distortions, offset at weld joint observed at ARCC field installaed piping system. Weld joints weredistorted, misaligned and pipe cocked to one side after welding which is caused by *Weld joint strength reduction factor *Detrimental strain in Equipment, piping of components is prohibited. *Excessive piping sag/or desctruction subject to cause of creep under condition of repeated internal cycle. Subcontractor: ARCC rectified the distortion joint by cut & reweld. Refer to attached RFI - 359, 425 & 439. LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason VAF / PN S/N LBE NO. SUBCON/ CONTRACTOR Page 119 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 09, 2014 LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason VAF / PN S/N LBE NO. SUBCON/ CONTRACTOR 7 LBE-TCC- MECH-532 TCC VAF 3 MECH Piping 24-Apr-14 8 LBE-PCMC- MECH-536 PCMC VAF 3 MECH Piping 18-May-14 9 LBE-TCC- MECH-537 TCC VAF 3 MECH Piping 21-May-14 10 LBE-TCC- MECH-539 TCC VAF 3 MECH Piping 27-May-14 11 LBE-TCC- MECH-546 TCC VAF 3 MECH Piping 09-Jun-10 12 LBE-DLM- MECH-549 DAELIM (Constructio n) VAF 3 MECH Piping 12-Jun-14 During field leak testing of resilient seated butterfly valves in NASICO testing facilitiy Jubail, it is observed that there is a continues bubbles found in 8 nos of EBV during all 7 valves all rejected. This violates API 598 Table 6 which states that "These shall be no leakage for the minimum required test duration for all soft seated valves. During surveillance at Compressor area were observed the 3" CVA-237114- 02" TW-237040-01-A. This violates G4Z-0010-00, Sec. 6.10, Para. 6.10.2 "Clearance shall be maintained" and G4D-0142-01, Pipe spacing chart Notes: 6 table. Contractor: Required revised drawing. During surviellance inspection in TCC area, it was observed that the pipe is clashing with Equipment E-2331 and there is no sufficient clearance for the application of 130mm insulation on pipe. This is violation against Sadra spec: G4D-0142-01 & GAZ-0010-00 Para. 6.10.2. Contractor shall take necessary action. Subcontractor: This is Engineering issue. TCC already get JCR approval. The pipe length will be added soon. The job alreadt compelted. Due to lack and material traceability, in the MFC-TCC site, V# area, it was observed that, Subcontractor TCC has wrongly assembled and welded the ASTM A53 Gr, ERW pipes instead of Seamless pipe ASTM A106 Gr. B for Caustic service piping line class CA09. This violation against CA-09M, Note P-CSO1PEXS and Isometric IFC drawing. ISO drawing # N016103V3A-CA-179013-02, J # FW 08 & 09. N016103V3A-CA-179028- 01, J # FW 01. Subcontractor:Due to material shortage, the Construction using ASTM A53GR GRW Pipe instead of ASTM A106 GR.B without confirming the class required. TCC already cut-out all wrong joints and applied PT. ISO drawing new revision. During srveillance inspection at MFC site all over areas, it was observed that, Contractor has installed the Variable height clamp type Pipe shoe; separator barrier has not overlapped itself and overlap orientation in wrong position, such as 2 clock, 4 clock and 10 clock position. This is violation against G4G-1420-21, Note 3, which states that, "The separator material shall overlap itself on the bottom center line of the pipe. 127 Nos. of joints welded with wrong consumable in TCC shop 1 @ 2 for CAO9 and CA85 line class as per specification filler material shall contain 0.5% moly (ER80S-D2, E7010-AI & E7018-A1) but TCC used ER70S2 as per WPS-TCC-P1/P1-01, which has Molydenum 0.15% Daelim should take appropiate corrective action. Contractor: The same issue was not noted and raised SQDR dated 9/12/13. TCC-WPS-P1/P Rev. 2 has been approved for CA-09 & CA- 47 line class 90% joints are cut and rewelded. Page 120 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 09, 2014 LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason VAF / PN S/N LBE NO. SUBCON/ CONTRACTOR 13 LBE-ARCC- MECH-556 ARCC VAF 3 MECH Piping 23-Jun-14 14 LBE-TCC- MECH-558 TCC VAF 3 MECH Piping 25-Jun-14 15 LBE-ARCC- MECH-560 ARCC VAF 3 MECH Piping 25-Jun-14 16 LBE-PCMC- MECH-563 PCMC VAF 3 MECH Piping 30-Jun-14 17 LBE-GACC- MECH-566 GACC VAF 3 MECH Piping 30-Jun-14 During surveillance at GACC (W5&K1) area were found the butterfly valve was on the ground and without any cover or protection end of the Butterfly valve and visible the dust / grit blasting materials and foreign object. This violates Material & Equipment Protection and Preservation Plan -3 (RT- 61CS) Sec. 2.13, Para. 2.13.1 (a) "Valves stored outdoors must be protected from blowing sand and salt spray", Para. 2.19.12 and (d). Storage methods shall protect materials from infiltration of water, dust, dirt, vermin, insect, etc. A logbook enrty was made and informed to PMT/Contractor. Contractor shall provide necessadry C.A.R. Subcontractor: LBE No. 566 has been noted and the valve has been installed to its respective line. Therefore, please verify and close this LBE. During line checking of test package (1601-02-HT-021) at ARCC (F-1110) were found the marking of welding joint identification and welder symbol is away to the exact location FW-04. This violates Found that PCMC welders were welding 10" Pipe joint of drawing # N016103T1A-CH-012209-01 without fit-up inspection, violating the ITP's hold point for PCMC. Last warning letter should be issued by Daelim Quality to welders (JCC #1318, 1391) and their welding Foreman. Subjected joint must be cut-out or RT'd without counting it is RT Percentatge. Daelim/PCMC QC needs to get corrective action immediatelywith preventive measures. During surveillance inspection at TCC area cold box, it was fond that triunion support directly welded to pipe is not in the center of run pipe. This is not accordance of support standard drawing GF31P-F4-005 & DF33P-F- 3-002 which shown run pipe and triunion support pipe center are in on line. Subcontractor: Already cut-out and refit-up. Welding RFI already accepted. During line checking and inspection at Furnace area were found the piping flanges with spectacle blinds was installed without hole for jack screw twelve (12) locations and EL+15400 TP (1615-01-HT-003) This violates Project Specification for Mechanical Completion and Acceptance Rev.2 (A554-K-PRG-CM-GEN-DOC-005) Attachment 4, sec. 4, Para. 4.1.5 Install jacking bolts on all flanges with spectacle blinds. A logbook entry was made and informed to PMT/Contractor. Page 121 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 09, 2014 LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason VAF / PN S/N LBE NO. SUBCON/ CONTRACTOR 18 LBE-TCC- MECH-580 TCC VAF 3 MECH Piping 21-Jul-14 19 LBE-TCC- MECH-582 TCC VAF 3 MECH Piping 27-Jul-14 At Gas Furnace area, it was observed that Contractor has installed the wrong type of support and welded with Run Pipe instead of "EPS-105" type support. Reinforcing pad does not exist on installed support. As per ISO drawing, EPS-105 Support, reinforcing pas is required. This is violation against IFC Isometric drawing. During witness of Bolt Torquing and Butterfly valve, gasket verification at Cooling Water (TCC) V6 area were found the following violation. * Gasket missing between Butterfly Valve and Flange. * Double nuts were installed both side. This is violation to G4D-4250-01, Sec. 3, Para. 3.3 and G8S-8005-00, Sec. 3, Para. 3.1.1/3.1.2/3.1.3. * Wrong color coding of Butterfly Vavle (RED) This vis violation to RT16D-0120-01, Sec. 6, Para. 6 (a). Contractor shall provide necessary C.A.R. Page 122 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 09, 2014 Open Open Open Open Open Open Contractor: The fittings were internally coated in order to preserved and to avoid corrosions.Company acknowledged the close the issues. Subcontractor: Noted. Corrective action will be taken. Subcontractor: ARCC rectified the distortion joint by cut & reweld. Refer to attached RFI - 359, 425 & 439. STATUS Daelim/Subcontractor Response / Reason Page 123 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 09, 2014 STATUS Daelim/Subcontractor Response / Reason Open Open Open Open Open Open Contractor: Required revised drawing. Subcontractor: This is Engineering issue. TCC already get JCR approval. The pipe length will be added soon. The job alreadt compelted. Subcontractor:Due to material shortage, the Construction using ASTM A53GR GRW Pipe instead of ASTM A106 GR.B without confirming the class required. TCC already cut-out all wrong joints and applied PT. ISO drawing new revision. Contractor: The same issue was not noted and raised SQDR dated 9/12/13. TCC-WPS-P1/P Rev. 2 has been approved for CA-09 & CA- 47 line class 90% joints are cut and rewelded. Page 124 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 09, 2014 STATUS Daelim/Subcontractor Response / Reason Open Open Open Open Open Subcontractor: LBE No. 566 has been noted and the valve has been installed to its respective line. Therefore, please verify and close this LBE. Subcontractor: Already cut-out and refit-up. Welding RFI already accepted. Page 125 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 09, 2014 STATUS Daelim/Subcontractor Response / Reason Open Open- Page 126 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 09, 2014 1 LBE-DLM- MECH-450 DAELIM (Mat. Dept) VAF 3 MECH Preservation 06-Jan-14 2 LBE-DLM- MECH-510 DAELIM (Mat. Dept) VAF 3 MECH Preservation 11-Mar-14 3 LBE-GACC- MECH-551 GACC VAF 3 MECH Preservation 15-Jun-14 4 LBE-SEN- ELECT-016 SENDAN VAF 1 ELECT Preservation 18-Jun-14 5 LBE-SEN- ELECT-017 SENDAN VAF 2 ELECT Preservation 23-Jun-14 6 LBE-DLM-TEL- 018 DAELIM (Preservatio n) VAF TELECOM Preservation 23-Jun-14 Daelim/Subcontractor Response / Reason DESCRIPTION ISSUED DATE During surveillance at GACC (W5) area were found the piping materials are laying on the ground without any protection or cover end of the check valve. This violates RT-6-1CS Material and Equipment protection and Preservation Plan Rev. 3, Sec. 2.19, Para. 2.19.1 "All materials shall be suitably stored and protected from the site conditions" Para. 2.19.12 )d). Storage methods shall protect materials from infiltration of water, dust, dirt, vermin, insect, etc. Contractor shall provide necesary CAR. Contractror: The following LBE No. 551 has been noted and the necessary corrective action has been taken for the same. Tool box meeting was conducted. S/N LBE NO. SUBCON/ CONTRACTOR VAF / PN During site surveillance, it was found that the Fiber Optic cable end has exposed at site for all analyzer. This is violation to RTIP-A554-R-001-IS- SPC-EG4-508, Para. 7.6.2 which states that "all FO cable ends are to be effectively sealed (waterproof) at all stages of use. Sealing shall be performed immediately after a length of cable has been cut from a drum. Exposed part of Fiber Optic cable (end part) has now covered and protected by using tape for sealing against water. Other contractor (WIPRO) is now well informed regaqrding protection of fiber optic cable end. During surveillance at site, it is noticed the pump P2320, C2701, C2711 were found without proper covering and temporary shelter protection over it as these are critical. After Cleaning The Pumps Fix Will be Attached During surveillance at MFC laydown yard shown equipment Secondary demethanizer OUHD condenser (E-2123) were preserved in a wrong way by keeping the equipment in direct contact with the ground. Outdoor storage requires separation from sand/mud or areas subjected to pouring of water. Cross-cut timber with specific dimensions may be used as recommended in the specification. The equipment is supplied bu vendor Fives Cryos. This activity is found to be a violation as per A554-E-103-QA- GEN-PRO-035, para. 8.2.1, 8.2.3, 8.2.4. During site surveillance, it was found that the electrical cables are not protected with end caps after cutting at site near substation 1120. This is violation to G7C-0305-02, Para. 4.4. which states that the cables shall be carefully protected from normal field construction hazards. Cable ends shall be sealed using heat shrinkable end caps to prevent entrance of moisture. Electrical cables at site are now covered & protected with end caps after cutting activity at site. SENDAN is now aware and well-informed of the importance of end cap protection after cutting. During site surveillance inspection at decoke area, it was observed that the 4.16 KV provision voltage motor of air compressor tag # MC-2701 and MC- 2711, were installed at site without energizing the motor space heater. This violates as per material and Equipment Protection and Preservation Plan doc. #RT-6-1CS, Para. 2.7.2. LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) Page 127 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 09, 2014 Daelim/Subcontractor Response / Reason DESCRIPTION ISSUED DATE S/N LBE NO. SUBCON/ CONTRACTOR VAF / PN LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) 7 LBE-SEN- ELECT-140 SENDAN VAF 1 ELECT Preservation 14-Jul-14 During routine visit, it was noticed that the PVC conduits installed at the manhole at north side of substation G-1121 were already damaged due to cable pulling of power cables and the conduits do not have PVC end bells for the protection of the cables which is a violation as per NEC 352.46. Contractor: Subcontractor already advised to repair the PVC damaged. Company will be advised for the action taken. Page 128 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 09, 2014 Open Open Open Open Open Open STATUS Daelim/Subcontractor Response / Reason Contractror: The following LBE No. 551 has been noted and the necessary corrective action has been taken for the same. Tool box meeting was conducted. Exposed part of Fiber Optic cable (end part) has now covered and protected by using tape for sealing against water. Other contractor (WIPRO) is now well informed regaqrding protection of fiber optic cable end. After Cleaning The Pumps Fix Will be Attached Electrical cables at site are now covered & protected with end caps after cutting activity at site. SENDAN is now aware and well-informed of the importance of end cap protection after cutting. Page 129 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 09, 2014 STATUS Daelim/Subcontractor Response / Reason Open Contractor: Subcontractor already advised to repair the PVC damaged. Company will be advised for the action taken. Page 130 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 09, 2014 1 LBE-ASYAD- INST-019 ASYAD VAF 1 INST Qaulity Management 14-Jun-14 During Site surveillance, it was observed that ASYAD has a shortage of QC Inspector. Contractor has 6 Inspectors while ASYAD has only 3 Inspectors and its Manpower is more than 200. This violates Schedule "Q" Contractor is requested to take preventive action. Contractor: Recently, ASYAD has 4 QC Inspector & waiting for SADARA approval for 1 remaining QC Inspector. Contractor will arrange additional QC Inspector as per Sch. "Q" within two weeks. LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason VAF / PN S/N LBE NO. SUBCON/ CONTRACTOR Page 131 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 09, 2014 Open Contractor: Recently, ASYAD has 4 QC Inspector & waiting for SADARA approval for 1 remaining QC Inspector. Contractor will arrange additional QC Inspector as per Sch. "Q" within two weeks. STATUS Daelim/Subcontractor Response / Reason Page 132 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 09, 2014 1 LBE-DLM- MECH-399 MR. KURIAN DAELIM (Enginnerin g) VAF 2 MECH Structural 19-Nov-13 During surveillance above the 2nd lyre of the EW pipe rack of the east side from column 10 onwards were found in inclined position ladder fixed as it is fauling with the beams. Contractor: TQ raised for approval from Daelim Engineering department. LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason S/N LBE NO. PID SUBCON/ CONTRACTOR VAF / PN Page 133 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 09, 2014 DUE DATE Issued corrective action to Company 22-Nov-13 03-Dec-13 Open Contractor: TQ raised for approval from Daelim Engineering department. CONTRACTOR'S CORRECTIVE ACTION PLAN Company comment Approved Close LBE by Company STATUS Daelim/Subcontractor Response / Reason Page 134 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 09, 2014 LBE-KCC- MECH-529 MR. GLENN KCC VAF 3 MECH UG-RTR 23-Apr-14 LBE-KCC- MECH-543 MR. GLENN KCC PN 3 MECH UG-RTR 08-Jun-14 LBE-KCC- MECH-570 MR. RAMO KCC VAF 3 MECH UG-Piping 07-Jul-14 During surveillance at Cooling Tower Water Pump area were found the crack at flanges corner radius of 48"-CWS line (FRP) due of excessive stress during bolt tightening at several location with six (6) flanges. This is violates G8S-8005-00, Sec. 6, Para. 6.2 "Cracking in this area indicates excessive stress and will need to be addressed before the flanged joint is a re-assembled" and 6.4.2.1 "Flanges should not have to be forced into alignment, Friction, load and relaxation effects will be magnified during the preloading process if factners are used to force flanges into alignment". A logbook entry was made and informed to PMT/Contractgor. Contractor shall provide necessary CAR. Subcontractor: The area was already visited by FPI representative and assured that it is a surface crack. FPI will submit a written report to Company to close this issue. CUT FRP Piping Firewater line FW-071102-20 was cut and 2 added 2 joints to fit the PIV IP-P-1031735-004859 under test pack HT-015, this line has been hydrostatically tested and Passed. Modified line shall be re-tested to comply 64S-6423-01 Sec. 7 a new test shall be applied after repair and convections have been made. Subcontractor: This matter was already addressed to top management, waiting for advice from Daelim. PN: Fire hydrant FH-0707 (under FW-HT-002) was hit by a PCMC truck causing minor damaged and scratches on fire hydrant with condition of buried RTR piping unknown until put to service. Ensur all fire fighting equipment are guarded against damaged to comply LPP 103-6R8. Temporary guards must be provided where permanent guards are still not in place. Verify RTR UG Piping of FH-0707 to ensure no crack developed during the impact. Subcontractor: The area cannot be excavated for checking & verification because it is being used as an access. KCC shall excavate and check as soon as the area is clear. LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason S/N LBE NO. PID SUBCON/ CONTRACTOR VAF / PN Page 135 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 09, 2014 LBE Vol No. DISCIPLINE Discipline Category (Piping/Mech) (Refractory) (Structural) (Tank) (Quality Mgt) (Others) DESCRIPTION ISSUED DATE Daelim/Subcontractor Response / Reason S/N LBE NO. PID SUBCON/ CONTRACTOR VAF / PN Page 136 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 09, 2014 DUE DATE Issued corrective action to Company 26-Apr-14 23-Jul-14 Open 11-Jun-14 23-Jul-14 Info 10-Jul-14 23-Jul-14 Open Subcontractor: The area was already visited by FPI representative and assured that it is a surface crack. FPI will submit a written report to Company to close this issue. Subcontractor: This matter was already addressed to top management, waiting for advice from Daelim. Subcontractor: The area cannot be excavated for checking & verification because it is being used as an access. KCC shall excavate and check as soon as the area is clear. CONTRACTOR'S CORRECTIVE ACTION PLAN Company comment Approved Close LBE by Company STATUS Daelim/Subcontractor Response / Reason Page 137 of 138 LOG BOOK ENTRY (LBE) SUMMARY As of July 09, 2014 DUE DATE Issued corrective action to Company CONTRACTOR'S CORRECTIVE ACTION PLAN Company comment Approved Close LBE by Company STATUS Daelim/Subcontractor Response / Reason Page 138 of 138