You are on page 1of 3

1

DEWA shop drawing / load schedule preparation / modifications/ site survey, online submissions
, DEWA engineer visits, technical discussions, revisions etc 12,550
2 Inspection application follow up with DEWA, enginner availability etc 4,500
3 Supervision of other electrical contractors work and to check compliance with DEWA regualtions 4,500
3 MBBs, Meter panel, related main cables, cable tray, works complete. 23,500
4 Lighting works in data centre. 27 points 6,750
5 Water and drain proviosnons at 2 locations with valve and necessary terminations 3,450
7 Removal of duct work and making good 1,250
8 Earth pits 2 nos with boring, copper earth rods, earth cover 16,500
9 Integration of fire suppression with main panel with dedicated wiring 2,800
10 Builders work inside data centre like coring, wall chasing, etc 4,900
11
Builders work for main cable laying, including interlock / external tile removal, excavation, slab
coring, wall openings, excavation for earth pits etc 12,300
12 Fire rated Aluminium suspension panel ceiling 13,043
Sub total 106,043
Exclusions
1 Power cabling works from MDB to related DBs.
2 Any comment by DEWA on office area works and related modifications.
3 Meter panel and MDB is assumed to be in external electrical room
4 Any kind of modifiations / additions to existing DBs cables etc
Variation for MEP works related to Data center - Mavarid
1
DEWA shop drawing / load schedule preparation / modifications/ site survey,
online submissions , DEWA engineer visits, technical discussions, revisions etc 14,433
2 Inspection application follow up with DEWA, enginner availability etc 5,175
3
Supervision of other electrical contractors work and to check compliance with
DEWA regualtions 5,175
3 MBBs, Meter panel, related main cables, cable tray, works complete. 27,025
4 Lighting works in data centre. 27 points 7,763
5
Water and drain proviosnons at 2 locations with valve and necessary
terminations 3,968
7 Removal of duct work and making good 1,438
8 Earth pits 2 nos with boring, copper earth rods, earth cover 18,975
9 Integration of fire suppression with main panel with dedicated wiring 3,220
10 Builders work inside data centre like coring, wall chasing, etc 5,635
11
Builders work for main cable laying, including interlock / external tile removal,
excavation, slab coring, wall openings, excavation for earth pits etc 14,145
12 Fire rated Aluminium suspension panel ceiling to Data room 15,000
TOTAL AMOUNT OF VARIATION AED. 121,952
Exclusions
1 Power cabling works from MDB to related DBs.
2 Any comment by DEWA on office area works and related modifications.
3 Meter panel and MDB is assumed to be in external electrical room
4 Any kind of modifiations / additions to existing DBs cables etc
1. Variation for MEP works related to Data center
Item Description Qty Unit Rate Amount
1 Floor finish FF-03 - 600x600 tiles for the Card room
flooring
24.00 m2 94.00 2,256.00
2 Skirting finish- porcelain skirting 25.00 Rm 31.00 775.00
3 Gypsum Fire rated dry wall to cver the window openings 18.00 m2 275.00 4,950.00
3 Fire rated paint finish to the card room walls 71.00 m2 28.00 1,988.00
4 Fire rated Aluminium suspension panel ceiling 24.00 m2 150.00 3,600.00
5 All MEP related works- such as rerouting of AC ducting,
lighting, power, cabling, etc
1.00 LS 8,000.00
TOTAL AMOUNT OF VARIATION AED. 21,569.00
Exclusions
1 Power cabling works from MDB to related DBs.
2 Any comment by DEWA on office area works and related
3
Meter panel and MDB is assumed to be in external
electrical room
4
Any kind of modifiations / additions to existing DBs cables
etc
Variation for Card room works