PRICE SCHEDULE FOR SUPPLY OF 132 KV DOUBLE

CIRCUIT TANSMISSION LINE MATERIALS USING PANTHER


CONDUCTOR ON PER KM BASIS

FINAL - ABSTRACT

Sl.No. Description Amount

1 132 KV DC Line - SUPPLY 3017540.00

2 132 KV DC Line - ERECTION 205535.00

3 CIVIL WORKS 455000.00

GRAND TOTAL per KM 3678075.00

Note : The above estimate is on Per KM basis


Right of way is not included
Any clearence required from forest department is not included
Supply rates are inclusive of duties & taxes, delevery Ex- Project site
For Erection & Civil works : Service tax prevailing at the time of billing shall
be extra to your account

Cost of 132 KV DC line with Panther Conductor for


approx 15 KMs of Length in Bajana, Khambalia,
Jam Nagar Dist. 55171125.00
PRICE SCHEDULE FOR CIVIL WORKS 0n Per KM Basis
SL.NO. Description Unit Qty Total Unit Total
erection Cost in Rs.
Cost in Rs.
1 2 3 7 8

Foudation of 132 KV DC Towers


including excavation, stub setting ,
concrete, back filling, coping etc
complete. Note:
The quoted foundations are valid for
DFR, WBC & hard rock soil conditions
only. Any other type of soil like fully
submerged etc or any special design of
foundation required is not included in
our offer.
1.1 'A' type Towers Nos. 1 95000 95000
1.1.1 'B' type Towers Nos. 1 115000 115000
1.2 'C' type Towers Nos. 1 115000 115000
1.2.1 'D' type Towers Nos. 1 130000 130000
TOTAL 455000.00

Note : The above estimate is on Per KM basis


Right of way is not included
Any clearence required from forest department is not included in our offer
PRICE SCHEDULE FOR ERECTION / LABOUR OF 132 KV DOUBLE CIRCUIT
TANSMISSION LINE MATERIALS ON PER KM BASIS
Sl.No. Description Unit Qty Unit Total
Rate Amount
in Rs. in Rs.
Fabrication, Proto testing and supply of
66KV galvanised towers as per
1 Kalpatharu designs and drawings
'A' type Towers including stubs MT 2.4
'B' type Towers including stubs MT 4
'C' type Towers including stubs MT 5
'D' type Towers including stubs MT 6
'D' type 3 mtre extension MT 1.2
Total Weight of Tower Per KM MT 18.6 5800.0 107880.00
Step bolts, bolts and nuts, washers etc.
fully galvanized required for the above
2 towers. MT 0.6 4500.0 2700.00
3 Tower Accessories
a] Phase Plates Nos. 1 60.0 60.00
b] Caution Plates Nos. 1 60.0 60.00
c] Circuit Plates Nos. 1 60.0 60.00
d] Number Plates Nos. 1 60.0 60.00
e] Grounding Sets
I Pipe type Nos. 1 1000.0 1000.00
f] Anti climbing devices Nos. 1 750.0 750.00
g] Earth Bonds
I. 300mm long Nos. 1 110.0 110.00
ii 450mm long Nos. 3 135.0 405.00
4 Conductor and ground wire
PANTHER ACSR Conductor with 1.5%
a] sag. Km 6.3 9000.0 56700.00
Over head ground wire 7/3.15 mm
galvanizes iron, steel, reinforced [with
b] 1.5% sag] Km 1.05 3900.0 4095.00
Insulator with Hardware for PANTHER
5 ACSR conductor
Single Suspension fittings with 4 Nos.
a] 90KN insulators and Hardware. Set 6 200.0 1200.00
Single tension fittings with 5 Nos. 90KN
b] insulator and hardware Set 30 200.0 6000.00
Double Suspension fittings with 8 nos. 90
c] KN insulators and hardware.
Double tension fittings with 10 nos. 90 KN
d] insulators and hardware. Set 6 200.0 1200.00
Accessories for PANTHER ACSR
6 conductor
a] Mid span compression joint Nos. 2 450.0 900.00
b] Repair Sleeves Nos. 1 115.0 115.00
c] Vibration dampers Nos. 48 140.0 6720.00
d] PG clamp Nos. 36 60.0 2160.00
e] Preformed armour rods Nos. 6 115.0 690.00

Sl.No. Description Unit Qty Unit Total


Rate Amount
in Rs. in Rs.
Hardware and Accessories for
7 Groundwire.
a] Mid span compression joint Nos. 1 340.0 340.00
b] Compression type tension clamp Nos. 6 300.0 1800.00
c] Suspension clamps Nos. 1 115.0 115.00
d] Repair Sleeves Nos. 1 115.0 115.00
e] PG Clamp Nos. 6 50.0 300.00
8 Check Survey KM 1 10000 10000

Total 205535.00

Note : The above estimate is on Per KM basis


Right of way is not included
Any clearence required from forest department is not included in our offer
PRICE SCHEDULE FOR SUPPLY OF 132 KV DOUBLE CIRCUIT TANSMISSION
LINE MATERIALS ON PER KM BASIS
Sl.No. Description Unit Qty Unit Total
Rate Amount
in Rs. in Rs.

Fabrication, Proto testing and supply


of 132 KV galvanised towers as per
1 Kalpatharu designs and drawings
'A' type Towers including stubs MT 2.4
'B' type Towers including stubs MT 4
'C' type Towers including stubs MT 5
'D' type Towers including stubs MT 6
'D' type 3 mtre extension MT 1.2
Total Weight of Tower Per KM MT 18.6 82200.0 1528920.00
Step bolts, bolts and nuts, washers
etc. fully galvanized required for the
2 above towers. MT 0.6 125600.0 75360.00
3 Tower Accessories
a] Phase Plates Nos. 1 325.0 325.00
b] Caution Plates Nos. 1 325.0 325.00
c] Circuit Plates Nos. 1 325.0 325.00
d] Number Plates Nos. 1 325.0 325.00
e] Grounding Sets
I Pipe type Nos. 1 4200.0 4200.00
f] Anti climbing devices Nos. 1 5100.0 5100.00
g] Earth Bonds
I. 300mm long Nos. 1 480.0 480.00
ii 450mm long Nos. 3 900.0 2700.00
4 Conductor and ground wire
PANTHER ACSR Conductor with
a] 1.5% sag. Km 6.3 155900.0 982170.00
Over head ground wire 7/3.15 mm
galvanizes iron, steel, reinforced [with
b] 1.5% sag] Km 1.05 45000.0 47250.00
Insulator with Hardware for PANTHER
5 ACSR conductor

Single Suspension fittings with 4 Nos.


a] 90KN insulators and Hardware. Set 6 5050.0 30300.00
Single tension fittings with 5 Nos.
b] 90KN insulator and hardware Set 30 5950.0 178500.00

Double Suspension fittings with 8 nos.


c] 90 KN insulators and hardware. UR 9450.0
Double tension fittings with 10 nos. 90
d] KN insulators and hardware. Set 6 11400.0 68400.00

Sl.No. Description Unit Qty Unit Total


Rate Amount
in Rs. in Rs.
Accessories for PANTHER ACSR
6 conductor
a] Mid span compression joint 2 630.0 1260.00
b] Repair Sleeves 1 550.0 550.00
c] Vibration dampers 48 1100.0 52800.00
d] PG clamp 36 650.0 23400.00
e] Preformed armour rods 6 900.0 5400.00
Hardware and Accessories for
7 Groundwire.
a] Mid span compression joint 1 320.0 320.00
b] Compression type tension clamp 6 950.0 5700.00
c] Suspension clamps 1 950.0 950.00
d] Repair Sleeves 1 320.0 320.00
e] PG Clamp 6 360.0 2160.00

Total 3017540.00