You are on page 1of 76

Project Title: PROPOSED TWO (2) STOREY LTO BUILDING

Project Location: BRGY. POBLACION, URDANETA CITY, PANGASINAN


Owner: LAND TRANSPORTATION OFFICE (Urdaneta Branch)
14 GENERAL REQUIREMENTS
Qty 1.00 lot
1.0 Mobilization/Demobilization Php
2.0 Temporary Facilities
a.) Bunkhouse/Office/Warehouse Php
b.) Temporary Lightings Php
c.) Temporary Water Php
Php
II. EARTHWORKS
1.0 Excavation Works/Backfill and Compaction
Qty 52.13 cu.m
A. LABOR COST
1 Project Engineer @ Php 600.00 /day Php
1 Construction Foreman Php 450.00 /day Php
1 H.E. Operator Php 400.00 /day Php
6 Laborer Php 250.00 /day Php
Php
Php 2,950.00 x 1.5 day Php
B. EQUIPMENT EXPENSES (RENTAL)
1 unit Backhoe/Loader Php 7,000.00 /day Php
Fuel, oil, lub.,etc Php 1,750.00 /day Php
Php
Php 8,750.00 x 1.5 days Php
A. LABOR COST Php
B. EQUIPMENT EXPENSES (RENTAL) Php
Php
plus: 7% OCM Php
8% CP Php
12% VAT Php
Php
Unit Cost = Php 20,182.50 / 52.13 cu.m Php
Total Item Cost = Php 387.15 x 52.13 cu.m Php
III. CONCRETE WORKS
Qty 30.22 cu.m
A. MATERIAL COST
303.0 bags Portland Cement @ Php 225.00 /bag Php
32.0 cu.m Screened Gravel Php 400.00 /cu.m Php
16.0 cu.m Washed Sand Php 450.00 /cu.m Php
Php
B. LABOR COST
1.0 Project Engineer @ Php 600.00 /day Php
1.0 Construction Foreman Php 450.00 /day Php
2.0 Mason Php 375.00 /day Php
8.0 Laborer Php 250.00 /day Php
Php
Php 3,800.00 x 8.0 days Php
C. EQUIPMENT EXPENSES (RENTAL)
1 unit One Bagger Concrete Mixer Php 400.00 /day Php
Fuel, oil, lub.,etc Php 100.00 /day Php
Php
Php 500.00 x 8.0 days Php
S U M M A R Y
A. MATERIAL COST Php
B. LABOR COST Php
C. EQUIPMENT EXPENSES (RENTAL) Php
Php
plus: 7% OCM Php
8% CP Php
12% VAT Php
Php
Unit Cost = Php 140,961.25 / 30.22 cu.m Php
Total Item Cost = Php 4,665.27 x 30.22 cu.m Php
IV. REINFORCE STEEL BARS
Qty 4,171.30 kgs
A. MATERIAL COST
2,157.6 kgs 16mm Def. bars Php 40.00 /kg Php
381.9 kgs 12mm Def. bars Php 40.00 /kg Php
1,631.8 kgs 10mm Def. bars Php 40.00 /kg Php
75.2 kgs # 16 G.I. tie wire Php 60.00 /kg Php
Php
B. LABOR COST
1.0 Project Engineer @ Php 600.00 /day Php
1.0 Construction Foreman Php 450.00 /day Php
4.0 Steelman Php 300.00 /day Php
9.0 Laborer Php 250.00 /day Php
Php
Php 4,500.00 x 12.0 days Php
C. EQUIPMENT EXPENSES (RENTAL)
1 unit Bar cutter Php 200.00 /day Php
Php
Php 200.00 x 12.0 days Php
A. MATERIAL COST Php
B. LABOR COST Php
C. EQUIPMENT EXPENSES (RENTAL) Php
Php
plus: 7% OCM Php
8% CP Php
12% VAT Php
Php
Unit Cost = Php 261,926.60 / 4,171.30 kgs Php
Total Item Cost = Php 62.79 x 4,171.30 kgs Php
V. FORMS AND SCAFFOLDINGS
Qty 1.00 lot
A. MATERIAL COST
25.0 pcs 1/2"x4'x8' Form Plywood @ Php 560.00 /pc Php
4,000.0 bd.ft Asst. Form lumber @ Php 24.00 /bd.ft Php
80.0 kgs Asst. CWNail @ Php 75.00 /kg Php
20.0 bd.ft # 16 G.I. tie wire @ Php 60.00 /kg Php
Php
B. LABOR COST
1 Project Engineer @ Php 600.00 /day Php
1 Construction Foreman @ Php 450.00 /day Php
4 Carpenter @ Php 375.00 /day Php
S U M M A R Y
S U M M A R Y
3 Laborer @ Php 250.00 /day Php
Php
Php 3,300.00 x 12.0 days Php
A. MATERIAL COST Php
B. LABOR COST Php
Php
plus: 7% OCM Php
8% CP Php
12% VAT Php
Php
Unit Cost = Php 180,320.00 / 1.00 lot Php
Total Item Cost = Php 180,320.00 x 1.00 lot Php
VI. MASONRY WORKS (CHB laying w/ Plastering)
Qty 185.14 sq.m
A. MATERIAL COST
350.0 bags Portland Cement @ Php 225.00 /bag Php
29.0 cu.m Washed sand @ Php 400.00 /cu.m Php
2,450.0 pcs 5" CHB @ Php 10.50 /pc Php
518.0 kgs 10mm Def. bars @ Php 40.00 /kg Php
6.0 bd.ft # 16 G.I. tie wire @ Php 60.00 /kg Php
Php
B. LABOR COST
1 Project Engineer @ Php 600.00 /day Php
1 Construction Foreman Php 450.00 /day Php
4 Mason Php 375.00 /day Php
6 Laborer Php 250.00 /day Php
Php
Php 4,050.00 x 12.0 day Php
A. MATERIAL COST Php
B. LABOR COST Php
Php
plus: 7% OCM Php
8% CP Php
12% VAT Php
Php
Unit Cost = Php 213,618.25 / 185.14 sq.m Php
Total Item Cost = Php 1,153.82 x 185.14 sq.m Php
VII. TILE WORKS
Qty 82.40 sq.m
A. MATERIAL COST
15.0 bags Tile Adhessive @ Php 190.00 /bag Php
3.0 cu.m Washed sand @ Php 400.00 /cu.m Php
4.0 pc 4" Diamond cutter @ Php 450.00 /pc Php
428.0 pcs 16"x16" Granite tile @ Php 85.00 /pc Php
60.0 pcs 16"x16" Outdoor tile @ Php 65.00 /pc Php
20.0 kgs Tile Grout @ Php 25.00 /kg Php
Php
S U M M A R Y
S U M M A R Y
B. LABOR COST
1 Project Engineer @ Php 600.00 /day Php
1 Construction Foreman @ Php 450.00 /day Php
3 Mason @ Php 375.00 /day Php
4 Laborer @ Php 250.00 /day Php
Php
Php 3,175.00 x 5.0 day Php
C. EQUIPMENT EXPENSES (RENTAL)
1 unit Electric Grinder Php 150.00 /day Php
Php
Php 150.00 x 5.0 days Php
S U M M A R Y
A. MATERIAL COST Php
B. LABOR COST Php
C. EQUIPMENT EXPENSES (RENTAL) Php
Php
plus: 7% OCM Php
8% CP Php
12% VAT Php
Php
Unit Cost = Php 72,743.25 / 82.40 sq.m Php
Total Item Cost = Php 882.81 x 82.40 sq.m Php
VIII. CARPENTRY AND JOINERY WORKS (2ND Floor Ceiling only)
Qty 82.40 sq.m
A. MATERIAL COST
16.0 pcs Hardiflex ceiling board @ Php 420.00 /pc Php
48.0 pcs 0.40mm 19mm x 50mm x 5m @ Php 115.00 /pc Php
Double furring channel
8.0 pcs 0.80mm 12mm x 38mm x 5m @ Php 140.00 /pc Php
Carrying Channel
15.0 pcs 0.40mm 25mm x 25mm x 3m @ Php 85.00 /pc Php
Wall angle
290.0 pcs
W-Clip
@ Php 8.00 /pc Php
1.0 kgs 1-1/2" Concrete nail @ Php 90.00 /kg Php
2.0 pcs 4" Diamond grinding disc @ Php 65.00 /pc Php
2.0 box Blind rivets @ Php 500.00 /box Php
800.0 bd.ft Asst. Form lumber (Scaffoldings) @ Php 24.00 /bd.ft Php
Php
B. LABOR COST
1 Project Engineer @ Php 600.00 /day Php
1 Construction Foreman @ Php 450.00 /day Php
3 Carpenter @ Php 375.00 /day Php
2 Laborer @ Php 250.00 /day Php
Php
Php 2,675.00 x 5.0 days Php
C. EQUIPMENT EXPENSES (RENTAL)
1 unit Electric Grinder Php 150.00 /day Php
Php
Php 150.00 x 5.0 days Php
S U M M A R Y
A. MATERIAL COST Php
B. LABOR COST Php
C. EQUIPMENT EXPENSES (RENTAL) Php
Php
plus: 7% OCM Php
8% CP Php
12% VAT Php
Php
Unit Cost = Php 59,225.00 / 82.40 sq.m Php
Total Item Cost = Php 718.75 x 82.40 sq.m Php
IX. DOORS AND WINDOWS
Qty 1.00 lot
A. MATERIAL COST
2.0 sets D-1, Panel type door w/ 2"x 6" jamb with @ Php 5,300.00 /set Php
Complete accessories (0.90x2.10mts.)
1.0 sets D-2, Flush type door w/ 2"x 5" jamb with @ Php 4,000.00 /set Php
Complete accessories (0.80x2.10 mts.)
2.0 sets W-1, Steel casement window with 3/16" @ Php 3,780.00 /set Php
thk. Clear glass (1.80x1.40mts)
2.0 sets W-2, Steel casement window with 3/16" @ Php 2,520.00 /set Php
thk. Clear glass (1.20x1.40mts)
Php
B. LABOR COST (Installation only)
1 Project Engineer @ Php 600.00 /day Php
1 Construction Foreman @ Php 450.00 /day Php
1 Carpenter @ Php 375.00 /day Php
1 Welder @ Php 375.00 /day Php
1 Glass Installer @ Php 300.00 /day Php
5 Laborer @ Php 250.00 /day Php
Php
Php 3,350.00 x 2.0 days Php
C. EQUIPMENT EXPENSES (RENTAL)
1 unit Electric Grinder Php 150.00 /day Php
Php
Php 150.00 x 2.0 days Php
S U M M A R Y
A. MATERIAL COST Php
B. LABOR COST Php
C. EQUIPMENT EXPENSES (RENTAL) Php
Php
plus: 7% OCM Php
8% CP Php
12% VAT Php
Php
Unit Cost = Php 39,330.00 / 1.00 lot Php
Total Item Cost = Php 39,330.00 x 1.00 lot Php
X. PAINTING WORKS (Concrete wall & Hardiflex Ceiling board)
Qty 460.08 sq.m
A. MATERIAL COST
5.0 tin Flat Latex paint @ Php 1,810.00 /tin Php
10.0 tin Semi-gloss Latex paint @ Php 2,370.00 /tin Php
4.0 lits Latex color @ Php 120.00 /lit Php
4.0 gal. Masonry putty @ Php 15.00 /gal Php
20.0 kgs Patching compound @ Php 15.00 /lit Php
8.0 lits Stickwel @ Php 195.00 /lit Php
7.0 pcs Roller brush @ Php 100.00 /pc Php
17.0 pcs Paint brush @ Php 45.00 /pc Php
100.0 pcs Sandpaper @ Php 25.00 /pc Php
15.0 pcs Stupa Rag @ Php 20.00 /kg Php
Php
B. LABOR COST
1 Project Engineer @ Php 600.00 /day Php
1 Construction Foreman @ Php 450.00 /day Php
3 Painter @ Php 350.00 /day Php
4 Laborer @ Php 250.00 /day Php
Php
Php 3,100.00 x 5.0 day Php
A. MATERIAL COST Php
B. LABOR COST Php
Php
plus: 7% OCM Php
8% CP Php
12% VAT Php
Php
Unit Cost = Php 63,152.25 / 460.08 sq.m Php
Total Item Cost = Php 137.26 x 460.08 sq.m Php
XI. TRUSS WORKS
Qty 1.00 lot
A. MATERIAL COST
23.0 pcs 1.5mm x 2"x6" CEE purlins (truss) @ Php 650.00 /pc Php
12.0 pcs 1.0mm x 2"x4" CEE purlins @ Php 397.00 /pc Php
3 5.0 pcs 10mm Plain Round bar @ Php 138.00 /pc Php
9.0 pcs 1/4" x 10"x10" Base plate @ Php 250.00 /pc Php
3.0 box Welding rod @ Php 1,200.00 /box Php
36.0 pcs 12mm x 10" Anchor bolts w/
Nut and washer @ Php 120.00 /pc Php
Php
B. LABOR COST
1 Project Engineer @ Php 600.00 /day Php
1 Construction Foreman @ Php 450.00 /day Php
2 Welder @ Php 375.00 /day Php
2 Laborer @ Php 250.00 /day Php
Php
Php 2,300.00 x 4.0 day Php
1 unit Welding Machine Php 450.00 /day Php
Php
Php 450.00 x 4.0 days Php
S U M M A R Y
A. MATERIAL COST Php
B. LABOR COST Php
C. EQUIPMENT EXPENSES (RENTAL) Php
Php
plus: 7% OCM Php
8% CP Php
12% VAT Php
Php
S U M M A R Y
Unit Cost = Php 47,810.10 / 1.00 lot Php
Total Item Cost = Php 47,810.10 x 1.00 lot Php
XII. ROOFING WORKS
Qty 48.50 l.m
A. MATERIAL COST
48.5 l.m Rib-type Roofing sheet (.5mm thk.) @ Php 420.00 /l.m Php
48.5 l.m One sided Alum. Insulation (9mm thk) @ Php 450.00 /l.m Php
5.0 pcs Wall flashing @ Php 450.00 /pc Php
5.0 pcs 3" PVC pipe @ Php 460.00 /pc Php
6.0 pcs 3" PVC Elbow 1/4 bend @ Php 53.00 /pc Php
3.0 pcs Gutter @ Php 450.00 /pc Php
300.0 pcs Tekscrew @ Php 1.75 /pc Php
4.0 tube Silicon Sealant @ Php 150.00 /tube Php
1.0 box Blind Rivets @ Php 500.00 /box Php
Php
B. LABOR COST
1 Project Engineer @ Php 600.00 /day Php
1 Construction Foreman @ Php 450.00 /day Php
3 Roof Installer @ Php 350.00 /day Php
4 Laborer @ Php 250.00 /day Php
Php
Php 3,100.00 x 4.0 day Php
S U M M A R Y
A. MATERIAL COST Php
B. LABOR COST Php
Php
plus: 7% OCM Php
8% CP Php
12% VAT Php
Php
Unit Cost = Php 71,803.70 / 48.50 l.m Php
Total Item Cost = Php 1,480.49 x 48.50 l.m Php
XIII. TINSMITRY WORKS (Stair Railings)
Qty 1.00 lot
A. MATERIAL COST
4.0 pcs 2" Stainless Steel pipe @ Php 3,250.00 /pc Php
4.0 pcs 3/16"x1" Flat bar @ Php 235.00 /pc Php
15.0 pcs 3/4"x3/4" Square bar @ Php 245.00 /pc Php
1.0 lot Welding rod/Accessories @ Php 3,000.00 /lot Php
2.0 pc 4" Grinding disk @ Php 65.00 /pc Php
Php
B. LABOR COST
1 Project Engineer @ Php 600.00 /day Php
1 Construction Foreman @ Php 450.00 /day Php
1 Welder @ Php 375.00 /day Php
3 Laborer @ Php 250.00 /day Php
Php
Php 2,175.00 x 3.0 day Php
C. EQUIPMENT EXPENSES (RENTAL)
1 unit Welding Machine Php 450.00 /day Php
Php
Php 450.00 x 3.0 days Php
A. MATERIAL COST Php
S U M M A R Y
B. LABOR COST Php
C. EQUIPMENT EXPENSES (RENTAL) Php
Php
plus: 7% OCM Php
8% CP Php
12% VAT Php
Php
Unit Cost = Php 32,913.00 / 1.00 lot Php
Total Item Cost = Php 32,913.00 x 1.00 lot Php
XIV. ELECTRICAL WORKS
Qty 1.00 lot
A. MATERIAL COST
6.0 sets 2x40W FL lamp w/ housing @ Php 1,500.00 /set Php
5.0 sets 25W CFL @ Php 60.00 /set Php
5.0 sets 4"x4" Pinlight @ Php 250.00 /set Php
6.0 pcs Receptacle 4" @ Php 50.00 /pc Php
2.0 sets Single pole switch @ Php 120.00 /set Php
3.0 sets Two pole switch @ Php 165.00 /set Php
2.0 sets 3-Way switch @ Php 210.00 /set Php
11.0 pcs 4"x4" Junction box @ Php 35.00 /pc Php
15.0 pcs 2"x4" Utility box @ Php 35.00 /pc Php
34.0 pcs 1/2" PVC pipe x 3.00 mts. @ Php 61.00 /pc Php
2.0 rolls 3.5mm THHN wire @ Php 3,207.50 /roll Php
20.0 mts 14mm THHN wire @ Php 85.84 /mt Php
4.0 pcs 1' PVC pipe x 3.00 mts. @ Php 102.00 /pc Php
2.0 pcs 1" Long sweep elbow @ Php 38.00 /pc Php
22.0 pcs 1/2" PVC Long sweep elbow @ Php 25.00 /pc Php
1.0 pc 1" RSC pipe x 3.00 mts. @ Php 420.00 /pc Php
1.0 sets 1" Entrance cap @ Php 65.00 /set Php
1.0 set 3-Pole secondary rack @ Php 285.00 /set Php
1.0 pc 1" Long sweep elbow (RSC) @ Php 85.00 /pc Php
10.0 rolls Electrical tape @ Php 45.00 /roll Php
Php
B. LABOR COST
1 Project Engineer @ Php 600.00 /day Php
1 Construction Foreman @ Php 450.00 /day Php
1 Electrician @ Php 325.00 /day Php
3 Laborer @ Php 250.00 /day Php
Php
Php 2,125.00 x 4.0 day Php
C. EQUIPMENT EXPENSES (RENTAL)
1 unit Electric drill Php 150.00 /day Php
Php
Php 150.00 x 4.0 days Php
S U M M A R Y
A. MATERIAL COST Php
B. LABOR COST Php
C. EQUIPMENT EXPENSES (RENTAL) Php
Php
plus: 7% OCM Php
8% CP Php
12% VAT Php
/set Php
Main ACB/ 6-branches, w/ 1-20 AT, 2P, 5-
20 AT, 2P
Php 1,850.00 1.00 sets @
Php
Unit Cost = Php 41,871.27 / 1.00 sets Php
Total Item Cost = Php 41,871.27 x 1.00 sets Php
TOTAL CONSTRUCTION COST Php
20,000.00
50,000.00
30,000.00
10,000.00
110,000.00
600.00
450.00
400.00
1,500.00
2,950.00
4,425.00
7,000.00
1,750.00
8,750.00
13,125.00
4,425.00
13,125.00
17,550.00
1,228.50
1,404.00
2,106.00
20,182.50
387.15
20,182.50
302.15
68,175.00
12,800.00
7,200.00
88,175.00
600.00
450.00
750.00
2,000.00
3,800.00
30,400.00 0.344768925
400.00
100.00
500.00
4,000.00
S U M M A R Y
88,175.00
30,400.00
4,000.00
122,575.00
8,580.25
9,806.00
14,709.00
140,961.25
4,665.27
140,961.25
86,302.10
15,276.32
65,273.76
4,510.08
171,362.26
600.00
450.00
1,200.00
2,250.00
4,500.00
54,000.00 0.315121897
200.00
200.00
2,400.00
171,362.26
54,000.00
2,400.00
227,762.26
15,943.36
18,220.98
27,331.47
261,926.60
62.79
261,926.60
14,000.00
96,000.00
6,000.00
1,200.00
117,200.00
600.00
450.00
1,500.00
S U M M A R Y
S U M M A R Y
750.00
3,300.00
39,600.00 0.337883959
117,200.00
39,600.00
156,800.00
10,976.00
12,544.00
18,816.00
180,320.00
180,320.00
180,320.00
78,750.00
11,600.00
25,725.00
20,720.00
360.00
137,155.00
600.00
450.00
1,500.00
1,500.00
4,050.00
48,600.00 0.354343626
137,155.00
48,600.00
185,755.00
13,002.85
14,860.40
22,290.60
213,618.25
1,153.82
213,618.25
ground floor/second floor stairs
2,850.00 12.50 13.00 80
1,200.00 20.00 20.00 260 2.4
1,800.00 14.70 15.00 82.4
36,380.00
3,900.00 12.50 13.00 195
500.00 5.00 5.00
46,630.00 5.33 6.00 60
S U M M A R Y
S U M M A R Y
600.00
450.00
1,125.00
1,000.00
3,175.00
15,875.00 0.340446065
150.00
150.00
750.00
46,630.00
15,875.00
750.00
63,255.00
4,427.85
5,060.40
7,590.60
72,743.25
882.81
72,743.25
ground floor/second floor
6,720.00 12.50 13.00
5,520.00 20.00 20.00
1,120.00 14.70 15.00
1,275.00
2,320.00 12.50 13.00 35.42 53.13
90.00 5.00 5.00 17.71
130.00
1,000.00 5.00 5.00
19,200.00
37,375.00 5.33 6.00
600.00
450.00
1,125.00
500.00
2,675.00
13,375.00 0.357859532
150.00
150.00
750.00
37,375.00
13,375.00
750.00
51,500.00
3,605.00
4,120.00
6,180.00
59,225.00
718.75
59,225.00
10,600.00 5,300.00
4,000.00 4,000.00
7,560.00 2.52 1500 3,780.00
5,040.00 1.68 1500 2,520.00
27,200.00
600.00
450.00
375.00
375.00
300.00
1,250.00
3,350.00
6,700.00 0.246323529
150.00
150.00
300.00
27,200.00
6,700.00
300.00
34,200.00
2,394.00
2,736.00
4,104.00
39,330.00
39,330.00
39,330.00
9,050.00 12.34267
23,700.00
480.00
60.00
300.00
1,560.00
700.00
765.00
2,500.00
300.00
39,415.00
600.00
450.00
1,050.00
1,000.00
3,100.00
15,500.00 0.3932513
39,415.00
15,500.00
54,915.00
3,844.05
4,393.20
6,589.80
63,152.25
137.26
63,152.25
14,950.00
4,764.00 16.57
690.00 9.94
2,250.00 6.62
3,600.00
3.31
4,320.00 1
30,574.00 37.44 6.24
600.00
450.00
750.00
500.00
2,300.00
9,200.00 0.300909269
450.00
450.00
1,800.00
30,574.00
9,200.00
1,800.00
41,574.00
2,910.18
3,325.92
4,988.88
47,810.10
S U M M A R Y
47,810.10
47,810.10
20,370.00
21,825.00
2,250.00
2,300.00
318.00
1,350.00
525.00
600.00
500.00
50,038.00
600.00
450.00
1,050.00
1,000.00
3,100.00
12,400.00 0.247811663
50,038.00
12,400.00
62,438.00
4,370.66
4,995.04
7,492.56
71,803.70
1,480.49
71,803.70
13,000.00 0.625
940.00 16.57 8.333333
3,675.00 13.25
3,000.00 9.94
130.00 6.62
20,745.00 46.38 7.73
600.00
450.00
375.00
750.00
2,175.00
6,525.00 0.314533623
450.00
450.00
1,350.00
20,745.00
S U M M A R Y
6,525.00
1,350.00
28,620.00
2,003.40
2,289.60
3,434.40
32,913.00
32,913.00
32,913.00
9,000.00 0.625
300.00 16.57 8.333333
1,250.00 13.25
300.00 13.25
240.00 13.25
495.00
420.00 13.25
13.25
13.25
385.00
525.00
2,074.00
6,415.00
1,716.80
408.00
76.00
550.00
420.00
65.00
285.00
85.00
450.00
27,309.80 96.07 16.01167
600.00
450.00
325.00
750.00
2,125.00
8,500.00 0.311243583
150.00
150.00
600.00
27,309.80
8,500.00
600.00
36,409.80
2,548.69
2,912.78
4,369.18
1,850.00
41,871.27
41,871.27
41,871.27
1,355,857.17
26.25
27
9
27
9
3
1
0.333333
0.111111
0.037037
Project Title: PROPOSED TWO (2) STOREY LTO BUILDING
Project Location: BRGY. POBLACION, URDANETA CITY, PANGASINAN
Owner: LAND TRANSPORTATION OFFICE (Urdaneta Branch)
Item No. UNIT QTY UNIT COST AMOUNT
I GENERAL REQUIREMENTS lot 1.00 110,000.00 110,000.00
II EARTHWORKS cu.m 52.13 387.15 20,182.50
III. CONCRETE WORKS cu.m 30.22 4,665.27 140,961.25
IV REINFORCE STEEL BARS kgs 4,171.30 62.79 261,926.60
V FORMS AND SCAFFOLDINGS lot 1.00 180,320.00 180,320.00
VI MASONRY WORKS sq.m 185.14 1,153.82 213,618.25
VII TILE WORKS sq.m 82.40 882.81 72,743.25
VIII CARPENTRY AND JOINERY WORKS sq.m 82.40 718.75 59,225.00
IX DOORS AND WINDOWS lot 1.00 39,330.00 39,330.00
X PAINTING WORKS sq.m 460.08 137.26 63,152.25
XI TRUSS WORKS lot 1.00 47,810.10 47,810.10
XII ROOFING WORKS l.m 48.50 1,480.49 71,803.70
XIII TINSMITRY WORKS lot 1.00 32,913.00 32,913.00
XIV ELECTRICAL WORKS lot 1.00 41,871.27 41,871.27
TOTAL PROJECT COST 1,355,857.17
BILL OF QUANTITIES
DESCRIPTION
EARTHWORKS
EXCAVATION WORKS
F-1 1.50 1.50 1.50 6.00 20.25
FTB 5.00 0.25 1.10 3.00 4.13
4.00 0.25 1.10 4.00 4.40
GB 5.00 0.20 0.25 3.00 0.75
4.00 0.20 0.25 4.00 0.80
TOTAL 30.33
BACKFILL/COMPACTION
F-1 1.50 1.50 0.30 6.00 4.05
FTB 5.00 0.25 0.30 3.00 1.13
4.00 0.25 0.30 4.00 1.20
GB 5.00 0.20 0.25 3.00 0.75
4.00 0.20 0.25 4.00 0.80
COLUMN 0.30 0.30 1.10 6.00 0.59
TOTAL 8.52
Excavation = 30.33
Backfill/Compaction 21.81 cu.m
GRAVEL BEDDING
F-1 1.50 1.50 0.10 6.00 1.35
FTB 5.00 0.25 0.10 3.00 0.38
4.00 0.25 0.10 4.00 0.40
GB 5.00 0.20 0.10 3.00 0.30
4.00 0.20 0.10 4.00 0.32
Area-1 8.00 5.00 0.10 1.00 4.00
Area-2 2.00 1.20 0.10 1.00 0.24
TOTAL 6.99
MARK
FOR ONE (1) STRUCTURE NO. OF
SIMILAR
STRUCTURE
TOTAL
VOLUME
(m)
LENGTH
(m.)
WIDTH
(m.)
HEIGHT
(m.)
MARK
FOR ONE (1) STRUCTURE NO. OF
SIMILAR
STRUCTURE
TOTAL
VOLUME
(m)
LENGTH
(m.)
WIDTH
(m.)
HEIGHT
(m.)
MARK
FOR ONE (1) STRUCTURE NO. OF
SIMILAR
STRUCTURE
TOTAL
VOLUME
(m)
LENGTH
(m.)
WIDTH
(m.)
HEIGHT
(m.)
5.00
16.67
13.33
16.67
13.33
5.00
16.67
13.33
1.00
V - MASONRY WORKS
GROUND FLOOR
perimeter wall 26.00 3.50 1.00 91.00
less opening 7.29 7.29
Total area 83.71
185.14
perimeter wall 26.00 3.50 1.00 91.00
4.40 1.00 1.00 4.40
5.00 3.00 1.00 15.00
less opening 8.97 8.97
Total area 101.43
No. of pcs 6 CHB 2,406.82 say 2,450.00 pcs
Cement 187.55 say 190.00 bags
Sand 15.63 say 17.00 m
Vert. Reinforcement 394.35
Hor. Reinforcement 398.05
792.40 / 5.7m = 139.0174035
say 140 pcs 10mm 518.00
GI Tie Wire 4.44 say 6 kgs
Plastering
perimeter wall 83.71 101.43 1.00 185.14
370.28
370.28
Cement 159.22 say 160 bags
Sand 9.26 say 12 cu.m.
Summary
Cement 350.00
Sand 29.00
No. of pcs 6 CHB 2,450.00
RSB Reinforcement 518.00
GI Tie Wire 6.00
kgs
10MM
0.616 6.00 3.70
0.616 7.50 4.62
0.616 9.00 5.54
0.616 10.50 6.47
0.616 12.00 7.39
REBAR WORKS
F1 top-tranverse 16 1.50 8.00 6.00 48.00
bottom-longitudinal 12 1.50 8.00 48.00
Footing
C1 vertical bar 16 9.00 8.00 2.00 16.00
8.30 outer ties 10 1.20 49.80 99.60
inner ties 10 1.00 49.80 99.60
C2 vertical bar 16 9.00 8.00 2.00 16.00
8.45 outer ties 10 1.20 50.70 101.40
inner ties 10 1.00 50.70 101.40
C3 vertical bar 16 9.00 8.00 2.00 16.00
8.61 outer ties 10 1.20 51.66 103.32
inner ties 10 1.00 51.66 103.32
FTB straight bars 16 6.00 6.00 3.00 18.00
5.00 stirrups 10 1.10 36.00 108.00
FTB straight bars 16 4.50 6.00 4.00 24.00
4.00 stirrups 10 1.20 27.00 108.00
GB straight bars 16 6.00 4.00 3.00 12.00
5.00 stirrups 10 0.90 36.00 108.00
GB straight bars 16 4.50 4.00 4.00 16.00
4.00 stirrups 10 0.90 27.00 108.00
B-1 straight bars 16 6.00 4.00 2.00 8.00
5.00 top cut bars 16 1.50 2.00 4.00
MARK LOCATION
BAR
SIZE
FOR 1 STRUCTURE
NO. OF
SIMILAR
STRUCT
URE
TOTAL
NO.OF
PCS
ONE BAR
LENGTH
NUMBER OF
PCS
bott. Cut bars 16 3.00 1.00 2.00
stirrups 10 1.20 36.00 72.00
B-1 straight bars 16 4.50 4.00 4.00 16.00
4.00 top cut bars 16 1.20 2.00 8.00
bott. Cut bars 16 2.50 1.00 4.00
stirrups 10 1.20 27.00 108.00
B-2 straight bars 16 6.00 4.00 1.00 4.00
5.00 top cut bars 16 1.50 4.00 4.00
bott. Cut bars 16 3.00 2.00 2.00
stirrups 10 1.40 36.00 36.00
B-3 straight bars 16 6.00 4.00 1.00 4.00
5.00 top cut bars 16 1.50 2.00 2.00
bott. Cut bars 16 3.00 1.00 1.00
stirrups 10 1.10 36.00 36.00
B-4 straight bars 16 2.50 4.00 1.00 4.00
2.12 top cut bars 16 0.75 2.00 2.00
bott. Cut bars 16 1.50 1.00 1.00
stirrups 10 0.90 15.00 15.00
LB-1 straight bars 12 2.50 4.00 1.00 4.00
2.00 stirrups 10 1.00 15.00 15.00
CB-1 straight bars 12 1.50 4.00 1.00 4.00
1.20 stirrups 10 1.00 9.00 9.00
RB-1 straight bars 12 6.00 4.00 2.00 8.00
5.00 top cut bars 12 1.50 2.00 4.00
bott. Cut bars 12 3.00 1.00 2.00
stirrups 10 0.90 36.00 72.00
straight bars 12 4.50 4.00 4.00 16.00
4.00 top cut bars 12 1.20 2.00 8.00
bott. Cut bars 12 2.50 1.00 4.00
stirrups 10 0.90 27.00 108.00
RB-2 straight bars 16 6.00 4.00 1.00 4.00
5.00 top cut bars 16 1.50 2.00 2.00
bott. Cut bars 16 3.00 1.00 1.00
stirrups 10 1.10 36.00 36.00
RB-3 straight bars 12 6.00 4.00 1.00 4.00
5.00 stirrups 10 0.70 36.00 36.00
straight bars 12 2.50 4.00 1.00 4.00
2.12 stirrups 10 0.70 15.00 15.00
LB-2 straight bars 12 2.50 4.00 1.00 4.00
2.00 stirrups 10 0.80 15.00 15.00
CB-2 straight bars 12 1.50 4.00 2.00 8.00
1.20 stirrups 10 0.80 9.00 18.00
SLAB ON FILL longitudinal 10 8.00 20.00 1.00 20.00
cross section 10 5.00 12.50 12.50
SUSPENDED SLAB top bars(longitudinal) 10 5.00 16.67 1.00 16.67
top bars (cross section) 10 8.00 26.67 26.67
cut bars(longitudinal) 12 1.25 10.00 10.00
cut bars (cross section) 12 4.00 10.00 10.00
bent up bars(longitudinal) 10 5.00 16.67 16.67
two way bent up bars (cross section) 10 8.00 26.67 26.67
MB-1 (30.00m) straight bars 16 30.83 4.00 3.00 12.00
@ GL A web bars 12 30.83 2.00 6.00
stirrups 10 1.40 784.00 2,352.00
MB-2(20.00m) straight bars 16 20.83 4.00 3.00 12.00
@ GL 1 web bars 12 20.83 2.00 6.00
stirrups 10 1.40 162.00 486.00
MB (30.00m) straight bars 16 30.83 4.00 1.00 4.00
@ GL A web bars 12 30.83 2.00 2.00
stirrups 10 1.40 184.00 184.00
Midbeam
RB-1 (20.00m) straight bars 16 20.83 4.00 1.00 4.00
@ GL 1 web bars 12 20.83 2.00 2.00
top cut bars-end support 16 0.93 2.00 2.00 4.00
top cut bars-middle support 16 1.65 2.00 2.00 4.00
top cut bars-middle support 16 2.90 2.00 1.00 2.00
top cut bars-middle support 16 2.28 2.00 2.00 4.00
bottom cut bars 16 1.50 2.00 4.00 8.00
bottom cut bars 16 3.00 2.00 2.00 4.00
stirrups 10 1.40 162.00 162.00
RB-1 (30.00m) straight bars 16 30.83 4.00 1.00 4.00
web bars 12 30.83 2.00 2.00
top cut bars-end support 16 1.98 2.00 1.00 2.00
top cut bars-middle support 16 1.78 2.00 1.00 2.00
top cut bars-middle support 16 1.90 2.00 23.00 46.00
top cut bars-middle support 16 1.55 2.00 7.00 14.00
bottom cut bars 16 1.80 2.00 24.00 48.00
bottom cut bars 16 1.50 2.00 8.00 16.00
stirrups 10 1.40 784.00 784.00
RB-2 (20.00m) straight bars 16 20.83 4.00 4.00 16.00
web bars 12 20.83 2.00 8.00
top cut bars-end support 16 0.93 2.00 2.00 16.00
top cut bars-middle support 16 1.65 2.00 2.00 16.00
top cut bars-middle support 16 2.90 2.00 1.00 8.00
top cut bars-middle support 16 2.28 2.00 2.00 16.00
bottom cut bars 16 1.50 2.00 4.00 32.00
bottom cut bars 16 3.00 2.00 2.00 16.00
stirrups 10 1.40 162.00 648.00
S.Angle (20.00m) straight bars 16 20.83 4.00 4.00 16.00
@ GL A web bars 12 20.83 2.00 8.00
top cut bars-end support 16 0.93 2.00 2.00 16.00
top cut bars-middle support 16 1.65 2.00 7.00 56.00
bottom cut bars 16 1.50 2.00 8.00 64.00
stirrups 10 1.40 184.00 736.00
roofbeam
Ground Slab transverse 12 92.00 41.00 1.00 41.00
92 x 20 longitudinal 12 20.00 185.00 185.00
Ground Slab transverse 12 42.00 41.00 1.00 41.00
42 x 20 longitudinal 12 20.00 85.00 85.00
Ground Slab
12MM 16MM
0.888 6.00 5.33 1.578 6.00 9.47
0.888 7.50 6.66 1.578 7.50 11.84
0.888 9.00 7.99 1.578 9.00 14.20
0.888 10.50 9.32 1.578 10.50 16.57
0.888 12.00 10.66 1.578 12.00 18.94
72.00 6.00 12.00 12.00 384.00 227.23 2.17
72.00 6.00
227.23 2.17 86
16MM 227.23
TIE WIRE 2.17
144.00 9.00 16.00 16.00 1,593.60 227.23 9.02
119.52 6.00 19.92 20.00 73.92
99.60 6.00 16.60 17.00 62.83
144.00 9.00 16.00 16.00 1,622.40 227.23 9.18
121.68 6.00 20.28 21.00 77.62
101.40 6.00 16.90 17.00 62.83
144.00 9.00 16.00 16.00 1,653.12 227.23 9.36
123.98 6.00 20.66 21.00 77.62
103.32 6.00 17.22 18.00 66.53
1,103.04 27.56
16MM 681.70
10MM 421.34
TIE WIRE 27.56
108.00 6.00 18.00 18.00 648.00 170.42 3.67
118.80 6.00 19.80 20.00 73.92
108.00 9.00 12.00 12.00 648.00 170.42 3.67
129.60 6.00 21.60 22.00 81.31
496.08 7.34
16MM 340.85
10MM 155.23
TIE WIRE 7.34
72.00 6.00 12.00 12.00 432.00 170.42 2.45
97.20 6.00 16.20 17.00 62.83
72.00 9.00 8.00 8.00 432.00 113.62 2.45
97.20 6.00 16.20 17.00 62.83
409.70 4.89
16MM 284.04
10MM 125.66
TIE WIRE 4.89
48.00 6.00 8.00 8.00 504.00 75.74 2.85
6.00 6.00 1.00 1.00 9.47
TOTAL NO. OF
COMML
LENGTH
COMML
LENGTH
NO. OF
VER/LONG
BAR
NO. OF
HOR/TRANS
BAR
TOTAL BAR
INTERSECTIO
N
6.00 6.00 1.00 1.00 9.47
86.40 6.00 14.40 15.00 55.44
72.00 9.00 8.00 8.00 756.00 151.49 4.28
9.60 6.00 1.60 2.00 18.94
10.00 7.50 1.33 2.00 18.94
129.60 6.00 21.60 22.00 81.31
24.00 6.00 4.00 4.00 360.00 37.87 2.04
6.00 6.00 1.00 1.00 9.47
6.00 6.00 1.00 1.00 9.47
50.40 6.00 8.40 9.00 33.26
24.00 6.00 4.00 4.00 252.00 37.87 1.43
3.00 6.00 0.50 1.00 9.47
3.00 6.00 0.50 1.00 9.47
39.60 6.00 6.60 7.00 25.87
10.00 7.50 1.33 1.50 105.00 17.75 0.59
1.50 6.00 0.25 0.50 4.73
1.50 6.00 0.25 0.50 4.73
13.50 6.00 2.25 3.00 11.09
10.00 7.50 1.33 1.50 60.00 6.93 0.34
15.00 6.00 2.50 3.00 11.09
6.00 6.00 1.00 1.00 36.00 5.33 0.20
9.00 6.00 1.50 2.00 7.39
48.00 6.00 8.00 8.00 504.00 42.62 2.85
6.00 6.00 1.00 1.00 5.33
6.00 6.00 1.00 1.00 5.33
64.80 6.00 10.80 11.00 40.66
72.00 9.00 8.00 8.00 756.00 85.25 4.28
9.60 6.00 1.60 2.00 10.66
10.00 6.00 1.67 2.00 10.66
97.20 6.00 16.20 17.00 62.83
24.00 6.00 4.00 4.00 252.00 37.87 1.43
3.00 6.00 0.50 0.50 4.73
3.00 6.00 0.50 0.50 4.73
39.60 6.00 6.60 7.00 25.87
24.00 6.00 4.00 4.00 144.00 21.31 0.82
25.20 6.00 4.20 5.00 18.48
10.00 7.50 1.33 2.00 60.00 13.32 0.34
10.50 6.00 1.75 2.00 7.39
10.00 7.50 1.33 1.50 60.00 9.99 0.34
12.00 6.00 2.00 2.00 7.39
12.00 6.00 2.00 2.00 72.00 10.66 0.41
14.40 6.00 2.40 2.50 9.24
1,096.91 22.19
16MM 472.22
12MM 227.38
10MM 397.32
TIE WIRE 22.19
100.00 5.60 17.86 18.00 250.00 66.53 1.42
100.00 6.00 16.67 17.00 62.83
133.33 6.00 22.22 23.00 988.89 85.01 5.60
133.33 5.60 23.81 24.00 88.70
40.00 6.00 13.33 14.00 74.59
12.50 6.00 4.17 5.00 26.64
133.33 6.00 22.22 23.00 85.01 0.00
133.33 5.60 23.81 24.00 88.70
578.02 7.01
12MM 101.23 18.99
10MM 476.78 128.86
TIE WIRE 7.01
16MM 151.52
12MM 53.30
10MM 55.50
TIE WIRE 4.00
168.00 7.50 6.00 784.00 14,112.00 1,988.70 95.86
84.00 7.50 559.65
588.00 6.00 2,175.60
24.00 12.00 6.00 162.00 2,916.00 454.56 19.81
12.00 12.00 127.92
41.00 6.00 151.70
8.00 12.00 6.00 184.00 1,104.00 151.52 7.50
4.00 12.00 42.64
46.00 6.00 170.20
5,822.49 387.48 69
8.00 12.00 8.00 162.00 1,296.00 151.52 8.80
4.00 12.00 42.64
1.00 6.00 9.47
1.00 7.50 11.84
1.00 6.00 9.47
1.00 10.50 16.57
2.00 6.00 18.94
2.00 6.00 18.94
41.00 6.00 151.70
56.00 7.50 8.00 784.00 6,272.00 662.90 42.60
28.00 7.50 186.55
1.00 7.50 11.84
0.00
16.00 6.00 151.52
2.00 12.00 37.88
10.00 9.00 142.05
4.00 6.00 37.88
196.00 6.00 725.20
32.00 12.00 8.00 162.00 5,184.00 606.08 35.21
16.00 12.00 170.56
4.00 6.00 37.88
4.00 7.50 47.35
4.00 6.00 37.88
4.00 10.50 66.29
8.00 6.00 75.76
8.00 6.00 75.76
41.00 6.00 151.70
32.00 12.00 8.00 41.00 1,312.00 606.08 8.91
16.00 12.00 170.56
16.00 6.00 151.52
8.00 12.00 151.52
16.00 6.00 151.52
184.00 6.00 680.80
5,568.17 95.53 92
328.00 12.00 41.00 185.00 7,585.00 3,496.48 51.52
370.00 10.50 3,451.18
246.00 7.50 41.00 85.00 3,485.00 1,638.98 23.67
170.00 10.50 1,585.68
10,172.31 75.19 76
#REF!
#REF!
FINISHING WORKS
PLASTERING WORKS
walls
Exterior/Interior Plastering
Total
Computation:
Cement 834.98 say 835.00 bags
Sand 46.39 say 50.00 m
TILE WORKS
Ground Floor
24"x24"Homogenous floor tiles
Library 10.00 7.00 16.67 17.00
Moot Court 9.30 7.00 15.50 16.00
SBO/SAS office 4.25 7.00 7.08 8.00
Deans office 6.75 5.00 11.25 12.00
12"x12"Homogenous floor tiles
Comport room (floor) 6.75 5.00 22.50 23.00
Comport room (floor) 6.75 5.00 22.50 23.00
Comport room (wall) 14.00 2.20 46.67 47.00
Comport room (wall) 10.00 2.20 33.33 34.00
Comport room (wall) 4.60 2.20 15.33 16.00
Comport room (wall) 5.00 2.20 16.67 17.00
24"x24"Homogenous floor tiles
Class room 10.00 7.00 16.67 17.00
4.00 10.00 6.67 7.00
9.30 7.00 15.50 16.00
9.30 7.00 15.50 16.00
hallways 3.00 50.00 5.00 5.00
lobbies 5.15 7.00 8.58 9.00
porch 2.00 6.00 3.33 4.00
platform 10.00 4.20 16.67 17.00
balcony 6.20 6.00 10.33 11.00
Entry along canopy area 6.00 6.00 10.00 10.00
MARK LENGTH WIDTH
(length) no. of
pcs.
say
MARK LENGTH HEIGHT
NO. OF
SIMILAR
FACE
fire scape areas 2.00 5.00 3.33 4.00
stair & landing 7.00 4.50 11.67 12.00
3.70 4.50 6.17 7.00
2nd Floor
24"x24"Ceramic floor tiles
area-1 8.00 7.00 13.33 14.00
cement fin. w/ h2o proofing
area-1 3.00 4.50
3rd Floor
24"x24"Ceramic floor tiles
area-1 8.00 7.00 13.33 14.00
cement fin. w/ h2o proofing
area-1 3.00 4.50
roof deck
cement fin. w/ h2o proofing 8.00 7.00
area-1 3.00 4.50
CEILING WORKS
2nd floor hardiflex ceiling board
open ceiling 8.50 5.00
1.20 2.00
total
2nd floor double furring channel
open ceiling 8.50 5.00 21.25 22.00
1.20 2.00 1.20 2.00
total
2nd floor wall angle
open ceiling 42.40 3.00 14.13 15.00
total
2nd floor carrying channel
open ceiling 8.50 5.00 7.08 8.00
total
PAINTING WORKS ceiling area 89.80
mark 1st coating 2nd coating 3rd coating
MARK LENGTH WIDTH
(length) no. of
pcs.
say
MARK LENGTH comm'l. length
(length) no. of
pcs.
say
MARK LENGTH WIDTH
(length) no. of
pcs.
say
MARK LENGTH WIDTH
(length) no. of
pcs.
say
Flat latex paint 3.59 2.99 2.57
Masonry putty 4.49
latex color 0.45
sand paper 5.99
roller brush
paint brush
stupa rug
PAINTING WORKS wall area 370.28
mark 1st coating 2nd coating 3rd coating
Flat latex paint 14.81
Semi-gloss Latex 14.81 12.34 12.34
Easytite with hardener
latex color 3.70
sand paper 74.06
roller brush
paint brush
stupa rug
Painting door area 27.00
mark 1st coating 2nd coating 3rd coating
QDE paint 0.90 0.54
Easytite with hardener 0.36
Paint thinner 0.50
tinting color 0.11
sand paper 5.40
roller brush
paint brush
stupa rug
Painting Metal 336.34
mark 1st coating 2nd coating 3rd coating
QDE paint 11.21 6.73
Easytite with hardener 3.36
Paint thinner 84.09
tinting color
sand paper
roller brush
paint brush
stupa rug
Painting Exterior wall 1,640.16
mark 1st coating 2nd coating 3rd coating
Flat latex paint 54.67
Semi-gloss Latex 54.67 41.00 32.80
latex color 8.20
Patching Compound
sand paper 164.02
roller brush
paint brush
stupa rug
Painting Exposed Conc. 56.89
mark 1st coating 2nd coating 3rd coating
Flat latex paint 1.90
Semi-gloss Latex 1.90 1.42 1.14
latex color 0.28
sand paper 5.69
roller brush
paint brush
stupa rug
TOILET PARTITIONS
Phenolic board
female 1.50 1.60 4.00 20.16
0.20 1.60 2.00 1.34
0.40 1.60 3.00 4.03
male 1.50 1.60 2.00 10.08
0.20 1.60 2.00 1.34
0.40 1.60 1.00 1.34
urinal partitions 0.45 0.90 6.00 5.10
total 43.41
DOORS
Phenolic board
female 0.60 1.60 4.00 8.06
male 0.60 1.60 2.00 4.03
total 12.10
DECORATIVE STONE
wall angle
Area-1 9.00 1.00 36.00 36.00
Area-2 1.75 5.00 17.50 18.00
Area-3 9.50 2.00 38.00 18.00
MARK LENGTH WIDTH total Area (m) say
MARK LENGTH WIDTH total no. of unit
total
Area (m)
MARK LENGTH WIDTH total no. of unit
total
Area (m)
Area-4 9.50 1.00 19.00 19.00
Area-5 9.00 0.60 10.80 11.00
total 102.00
25.50
ALUM. CLADDING
wall angle
Area-1 5.70 1.50 34.20 18.00
5.70 0.50 11.40 3.00
Area-2 17.70 1.50 53.10 54.00
total 75.00
FINISHING WORKS(Second floor)
PLASTERING WORKS
walls
Exterior/Interior Plastering #REF! #REF! #REF! 2.00
Total
Computation:
Cement #REF! say 500.00 bags
Sand #REF! say 35.00 m
TILE WORKS
Ground Floor
concrete pavers
27.50 2.40
24"x24"Granite tiles
gen. merch. 10.00 4.00 16.67 17.00
asessment area 5.00 5.20 8.33 9.00
souvinir area 7.00 4.20 11.67 12.00
photocopy/printing 12.00 8.00 20.00 20.00
300x300mm tile
1.60 1.50 5.33 6.00
Toilet 5.90 1.60
400x400mm tile 1.60 1.50 5.33 6.00
Stairs
Peeble washed out 11.00 2.00
mezz. Floor
concrete pavers
27.50 2.40
24"x24"Granite tiles
open room storage 4.00 3.00
1,2,3,4 16.00 6.00
Corridor
MARK LENGTH WIDTH
(length) no. of
pcs.
say
MARK LENGTH HEIGHT
NO. OF
SIMILAR
FACE
MARK LENGTH WIDTH total Area (m) say
plain cement fin. 29.00 2.25
Stairs
Peeble washed out 11.00 2.00
2nd floor
plain cement fin.
corridor-1 27.50 2.25
corridor-2 27.50 2.40
24"x24"Granite tiles
dig./audio visual 8.00 8.00
photo studio 4.00 8.00
wellness room 4.00 8.00
office 4.00 8.00
300x300mm tile
toilet 1.50 1.45 5.00 5.00
Toilet 5.90 1.60
CEILING WORKS
4th floor
.19mx3mts long
Hall way-1 37.40 2.00
Hall way-2 20.70 2.00
Hall way-3 32.00 2.00
Hall way-4 13.00 2.00
Hall way-5 10.00 4.00
1/4"thk. Hardiflex
hall way 2.00 2.00 6.00
MARK LENGTH WIDTH
(length) no. of
pcs.
say
total
double furring channel
hallway 280.00 2.00 2,800.00 5.00
total
wall angle
hallway 560.00 3.00 186.67 187.00
total 560.00 187.00
total area(m) length/sq.m comm'l. length
carrying channel 24.00 1.50 5.00 7.20
double furring clip 5.00 15.00
total area(m) no. of pcs./sq.m
blind rivets 24.00 20.00 480.00
total lenght(l.m) kgs./l.m
1" conc. Nail 560.00 0.03 14.00
Painting ceiling area 24.00
mark 1st coating 2nd coating 3rd coating
Flat latex paint 0.80
Semi-gloss Latex 0.80 0.60 0.40
Easytite with hardener 0.24
latex color 0.12
sand paper 2.40
roller brush
paint brush
stupa rug
Painting door area #REF!
mark 1st coating 2nd coating 3rd coating
QDE paint #REF! #REF!
Easytite with hardener #REF!
Paint thinner 0.75
tinting color #REF!
sand paper #REF!
roller brush
paint brush
stupa rug
MARK LENGTH
comm'l.
length(m)
total length
(l.m)
say
MARK LENGTH WIDTH
total length
(l.m)
comm'l.
length(m)
Painting Metal 139.20
mark 1st coating 2nd coating 3rd coating
QDE paint 4.64 2.78
Easytite with hardener 1.39
Paint thinner 0.46
tinting color
sand paper
roller brush
paint brush
stupa rug
Painting Interior wall #REF!
mark 1st coating 2nd coating 3rd coating
Flat latex paint #REF!
Semi-gloss Latex #REF! #REF! #REF!
latex color #REF!
sand paper #REF!
roller brush
paint brush
stupa rug
TOILET PARTITIONS
Phenolic board
female 1.50 1.60 4.00 20.16
0.20 1.60 2.00 1.34
0.40 1.60 3.00 4.03
male 1.50 1.60 2.00 10.08
0.20 1.60 2.00 1.34
0.40 1.60 1.00 1.34
urinal partitions 0.45 0.90 6.00 5.10
total 43.41
DOORS
Phenolic board
female 0.60 1.60 4.00 8.06
male 0.60 1.60 2.00 4.03
total 12.10
DECORATIVE STONE
MARK LENGTH WIDTH total Area (m) say
MARK LENGTH WIDTH total no. of unit
total
Area (m)
MARK LENGTH WIDTH total no. of unit
total
Area (m)
wall angle
Area-1 9.00 1.00 36.00 36.00
Area-2 1.75 5.00 17.50 18.00
Area-3 9.50 2.00 38.00 18.00
Area-4 9.50 1.00 19.00 19.00
Area-5 9.00 0.60 10.80 11.00
total 102.00
25.50
ALUM. CLADDING
wall angle
Area-1 1.50 16.00 48.00 48.00
Area-2 1.50 14.00 42.00 42.00
Area-3 7.00 4.00 28.00 28.00
total 118.00
MARK LENGTH WIDTH total Area (m) say
Quantity of cement and sand for plaster per square meter area
Mixture
class 8 mm 12mm
A 0.144 0.216
B 0.096 0.144
C 0.072 0.108
D 0.06 0.09
Sand 0.008 0.012
1,855.51
-
11.67 12.00 204.00 70.00
11.67 12.00 192.00 65.10
11.67 12.00 96.00 29.75
8.33 9.00 108.00 600.00 33.75
-
16.67 17.00 391.00 391.00 33.75
16.67 17.00 391.00 391.00 33.75
782.00
7.33 8.00 376.00 30.80 58.23
7.33 8.00 272.00 22.00
7.33 8.00 128.00 10.12
7.33 8.00 136.00 912.00 11.00
11.67 12.00 204.00 70.00
16.67 17.00 119.00 40.00
11.67 12.00 192.00 65.10
11.67 12.00 192.00 65.10
83.33 84.00 420.00 150.00
11.67 12.00 108.00 36.05
10.00 10.00 40.00 12.00
7.00 7.00 119.00 42.00
10.00 10.00 110.00 37.20
10.00 10.00 100.00 36.00
say
total no.
of pcs.
total no. of
pcs.
total area
(m)
(width) no.
of pcs.
Cement in bags Thickness of Plaster
AREA (m)
8.33 9.00 36.00 10.00
7.50 8.00 96.00 31.50
7.50 8.00 56.00 1,792.00 16.65
-
11.67 12.00 168.00 56.00
168.00
13.50
-
11.67 12.00 168.00 56.00 182.00
168.00
#REF!
13.50 #REF!
56.00
13.50 69.50
42.50 14.76 15.00
2.40 0.83 1.00
44.90 16.00 pcs
21.25 22.00 44.00 21.25 12.50 265.63 270.00
1.20 2.00 4.00 3.00 5.00 15.00 20.00
48.00 pcs 290.00 pcs
15.00
- 15.00
42.50 8.00
42.50 8.00
3rd coating gal say unit
say
total no.
of pcs.
total area
(m)
no. of
pcs.
say
(width) no.
of pcs.
say
total no.
of pcs.
total area
(m)
no. of
pcs.
say
(width) no.
of pcs.
say
total no.
of pcs.
no. of
pcs.
say furring clip
(width) no.
of pcs.
say
total no.
of pcs.
total area
(m)
no. of
pcs.
say
(width) no.
of pcs.
9.15 4.00 0.90 1.00 tin
4.00 - 4.00 gal
1.00 lits
20.00 pcs 5,716.80 114.34
2.00 pcs
5.00 pcs
5.00 kg
1 Acrylic semi-gloss latext paint finish, boysen white
3rd coating gal say unit
4.00 3.70 4.00 tin
39.50 4.00 9.87 10.00 tin
4.00 lits
80.00 pcs 5,716.80 114.34
5.00 pcs
12.00 pcs
10.00 kg
1 Acrylic semi-gloss latext paint finish, boysen white
2 Flat latex paint boysen white
3 Flat wall enamel paint
3rd coating gal/tin say unit 4 Q.D.E. Paint Boysen
1.44 2.00 gal 5 Masonry putty
1.00 gal 6 Easytite w/ Hardiner
1.00 gal 7 Perlite (patching compound)
0.50 lits 8 Stikwel
20.00 pcs 9 Sand paper
pcs 10 Paint Rower
4.00 pcs 11 Paint Brush
2.00 kg 12 Paint Thinner
13 Consumable like tinting colors
3rd coating gal/tin say unit
17.94 4.00 4.48 5.00 tin
gal
5.00 gal
2.00 lits
pcs
4.00 pcs
10.00 pcs
5.00 kg
3rd coating gal say unit
4.00 13.67 14.00 tin 15.00
128.48 4.00 32.12 35.00 tin 37.00
9.00 lits
2.00 sacks
200.00 pcs
8.00 pcs
15.00 pcs
10.00 kg
3rd coating gal say unit
4.00 0.47 1.00 gal
4.46 4.00 1.11 2.00 gal
10.00 lits
10.00 pcs
1.00 pcs
2.00 pcs
3.00 kg
m
unit
say
say
917.40
811.80
224.40
26.00 6.80 1,953.60
7.00
m
m
#REF!
#REF!
#REF!
66.00
6.67 7.00 119.00 40.00
8.67 9.00 81.00 26.00
7.00 7.00 84.00 29.40
13.33 14.00 280.00 96.00
191.40 sq.m
5.00 5.00 30.00 2.40 sq.m
9.44 sq.m
5.00 5.00 30.00 2.40 sq.m
11.84
22.00 sq.m
66.00
12.00
96.00
108.00
say
total no.
of pcs.
total no. of
pcs.
total area
(m)
(width) no.
of pcs.
AREA (m)
unit
65.25
65.25 sq.m
22.00 sq.m
61.88
66.00
127.88 sq.m
64.00
32.00
32.00
32.00
160.00 sq.m
4.83 5.00 25.00 2.18 sq.m
9.44 sq.m
11.62 sq.m
Quantity of cement and sand for plaster per square meter area
Mixture
class 8 mm 12mm
A 0.144 0.216
B 0.096 0.144
C 0.072 0.108
D 0.06 0.09
Sand 0.008 0.012
74.80 131.23 132.00
41.40 72.63 73.00
64.00 112.28 113.00
26.00 45.61 46.00
40.00 70.18 71.00
246.20 435.00
24.00 8.33 9.00
say
(width) no.
of pcs.
say
total no.
of pcs.
total area
(m)
no. of
pcs.
Cement in bags Thickness of Plaster
24.00 8.33 9.00 pcs
560.00 560.00 pcs 560.00 3,500.00 907.00
560.00 pcs
pcs
pcs
4.00 pcs
75.00
240.00 pcs
0.50 kgs
3rd coating gal say unit
4.00 0.20 2.00 gal
1.80 4.00 0.45 4.00 gal
4.00 gal
2.00 lits
30.00 pcs 5,716.80 114.34
2.00 pcs
5.00 pcs
5.00 kg
1 Acrylic semi-gloss latext paint finish, boysen white
2 Flat latex paint boysen white
3 Flat wall enamel paint
3rd coating gal/tin say unit 4 Q.D.E. Paint Boysen
#REF! 4.00 #REF! 3.00 tin 5 Masonry putty
4.00 gal 6 Easytite w/ Hardiner
4.00 gal 7 Perlite (patching compound)
1.00 lits 8 Stikwel
50.00 pcs 9 Sand paper
pcs 10 Paint Rower
8.00 pcs 11 Paint Brush
10.00 kg 12 Paint Thinner
13 Consumable like tinting colors
unit
total no. of
pcs.
say unit area (m)
3rd coating gal/tin say unit
7.42 4.00 1.86 8.00 gal
3.00 gal
5.00 gal
lits
pcs
pcs
5.00 pcs
5.00 kg
3rd coating gal say unit
4.00 #REF! 10.00 tin
#REF! 4.00 #REF! 22.00 tin
6.00 lits
330.00 pcs
15.00 pcs
20.00 pcs
20.00 kg
unit
say
say
m
917.40
811.80
224.40
26.00 6.80 1,953.60
7.00
m
unit
Quantity of cement and sand for plaster per square meter area
16mm 20mm 25mm
0.288 0.36 0.45
0.192 0.24 0.3
0.144 0.18 0.225
0.12 0.15 0.188
0.016 0.02 0.025
59.00 3.67 4.00 472.00
Cement in bags Thickness of Plaster
Acrylic semi-gloss latext paint finish, boysen white
Acrylic semi-gloss latext paint finish, boysen white gals 10.00 5.00 50.00
Flat latex paint boysen white gals 6.00 5.00 30.00
Flat wall enamel paint gals 2.00 5.00 10.00
Q.D.E. Paint Boysen gals 1.00 5.00 5.00
Masonry putty gals 1.00 5.00 5.00
Easytite w/ Hardiner ltrs 2.00 5.00 10.00
Perlite (patching compound) ltrs 10.00 5.00 50.00
lits 1.00 5.00 5.00
Sand paper pcs 150.00 5.00 750.00
Paint Rower pcs 2.00 5.00 10.00
Paint Brush pcs 5.00 5.00 25.00
Paint Thinner gals 2.00 5.00 10.00
Consumable like tinting colors lits 2.00 5.00 10.00
Quantity of cement and sand for plaster per square meter area
16mm 20mm 25mm
0.288 0.36 0.45
0.192 0.24 0.3
0.144 0.18 0.225
0.12 0.15 0.188
0.016 0.02 0.025
Cement in bags Thickness of Plaster
Acrylic semi-gloss latext paint finish, boysen white gals 10.00 5.00 50.00
Flat latex paint boysen white gals 6.00 5.00 30.00
Flat wall enamel paint gals 2.00 5.00 10.00
Q.D.E. Paint Boysen gals 1.00 5.00 5.00
Masonry putty gals 1.00 5.00 5.00
Easytite w/ Hardiner ltrs 2.00 5.00 10.00
Perlite (patching compound) ltrs 10.00 5.00 50.00
lits 1.00 5.00 5.00
Sand paper pcs 150.00 5.00 750.00
Paint Rower pcs 2.00 5.00 10.00
Paint Brush pcs 5.00 5.00 25.00
Paint Thinner gals 2.00 5.00 10.00
Consumable like tinting colors lits 2.00 5.00 10.00
CONCRETE WORKS
F-1 1.50 1.50 0.30 6.00 4.05 4.05
FTB 5.00 0.25 0.30 3.00 1.13
4.00 0.25 0.30 4.00 1.20 2.33
GB 5.00 0.20 0.25 3.00 0.75
4.00 0.20 0.25 4.00 0.80 1.55
C-1 0.30 0.30 8.30 2.00 1.49
C-2 0.30 0.30 8.45 2.00 1.52
C-1 0.30 0.30 8.61 2.00 1.55 4.56
B-1 5.00 0.25 0.35 2.00 0.88
4.00 0.25 0.35 4.00 1.40
B-2 5.00 0.30 0.40 1.00 0.60
B-3 5.00 0.25 0.30 1.00 0.38
B-4 2.12 0.20 0.25 1.00 0.11 3.36
LB-1 2.00 0.20 0.30 1.00 0.12 0.12
CB-1 1.20 0.20 0.30 2.00 0.14 0.14
RB-1 5.00 0.20 0.25 2.00 0.50
4.00 0.20 0.25 4.00 0.80
RB-2 5.00 0.25 0.30 1.00 0.38
RB-3 5.00 0.15 0.25 1.00 0.19
RB-4 2.12 0.15 0.20 1.00 0.06 1.93
LB-2 2.00 0.15 0.25 1.00 0.08 0.08
CB-2 1.20 0.15 0.25 2.00 0.09 0.09
SLAB ON FILL 8.00 5.00 0.10 1.00 4.00
1.20 2.00 0.10 1.00 0.24 4.24
SUSPENDED SLAB 5.00 4.00 0.10 1.00 2.00
5.00 1.88 0.10 1.00 0.94
2.12 2.00 0.10 1.00 0.42
1.20 2.00 0.10 1.00 0.24 3.60
STAIRS 3.20 2.13 0.13 1.00 0.85
1.20 9.00 0.10 1.00 1.08 1.93
Total 27.98 30.22
say
MARK
FOR ONE (1) STRUCTURE NO. OF
SIMILAR
STRUCTURE
TOTAL
VOLUME
(m)
LENGTH (m.)
WIDTH
(m.)
HEIGHT
(m.)
36.45 2.03 4.05
37.00 2.50 5.00
20.93 1.16 2.33
21.00 1.50 3.00
13.95 0.78 1.55
14.00 1.00 2.00
41.08 2.28 4.56
42.00 2.50 5.00
30.20 1.68 3.36
31.00 2.00 4.00
1.08 0.06 0.12
2.00 0.10 0.20
1.30 0.07 0.14
2.00 0.10 0.20
17.33 0.96 1.93
18.00 1.00 2.00
0.68 0.04 0.08
1.00 0.05 0.10
0.81 0.05 0.09
1.00 0.05 0.10
38.16 2.12 4.24
39.00 2.50 5.00
32.44 1.80 3.60
17.39 0.97 1.93
39.00 2.50 5.00
302.15 15.11 30.22
303.00 16.00 32.00 351.00
Rate/day Rate/hour
Proj. Engineer 600.00 75.00
Construction Foreman 450.00 56.25
Mason 375.00 46.88
Carpenter 375.00 46.88
H.E. Operator 400.00 50.00
L.E. Operator 325.00 40.63
Driver 300.00 37.50
Steelman 300.00 37.50
Labor 250.00 31.25
Painter 350.00 43.75
Roof Installer 350.00 43.75
Welder 375.00 46.88
Glass Installer 300.00 37.50
Plumber 325.00 40.63
Electrician 325.00 40.63
Rate/day Rate/hour
Road Grader 7,500.00
Payloader 7,000.00
Road Roller 6,500.00
Water Truck 4,500.00
Transit Mixer 1,500.00
One Bagger Mixer 400.00
Concrete Cutter 400.00
Concrete Vibrator 250.00
Welding Machine 450.00
Electric grinder 150.00
Bar cutter 200.00
Description Amount unit
Portland Cement 225.00 /bags
Screened Gravel 450.00 /cu.m
Washed Sand 400.00 /cu.m
Asphalt Sealant 110.00 /lit
Assorted Nails 75.00 /kg
16mm Def. bars 40.00 /kg
Form Lumber 2"x5"x12' Coco lumber 24.00 /bd.ft
Aggregate Sub-Basecoarse 400.00 /cu.m
#16 G.I. tie wire 60.00 /kg
1/2"x4'x8' Form Plywood 560.00 /pc
Asst. Form lumber 24.00 /bd.ft
6" CHB 10.50 /pc
Tile Adhessive 190.00 /bags
16"x16" Ceramic tile 85.00 /pc
16"x16" Outdoor tile 65.00 /pc
Tile Grout 25.00 /kg
Flat Latex paint 1,810.00 /tin
Semi-gloss Latex paint 2,370.00 /tin
Latex color 120.00 /lit
Patching compound 15.00 /kg
Stickwel 195.00 /lit
Roller brush 100.00 /pc
Paint brush 45.00 /pc
Sandpaper 25.00 /pc
Stupa Rag 20.00 /kg
Tile Roof Roofing sheet (.5mm thk.) 420.00 /sq.m
Ridge roll 450.00 /pc
Gutter 450.00 /pc
Tekscrew 1.75 /pc
Silicon Sealant 150.00 /tube
Blind Rivets 500.00 /box
Touch-up paint 150.00 /lit
1.5mm x 2"x6" CEE purlins 650.00 /pc
1.2mm x 2"x4" CEE purlins 397.00 /pc
1.0mm x 2"x3" CEE purlins 400.00 /pc
10mm Plain Round bar 138.00 /pc
1/4" x 10"x10" Base plate 250.00 /pc
Welding rod 1,200.00 /box
12mm x 10" Anchor bolts w/ 120.00 /pc
8"x8" Glazed tile 32.00 /pc
8"x8" Unglazed tile 32.00 /pc
Tile trim 78.00 /pc
Tile Grout 25.00 /kg
4" Diamond cutter 450.00 /pc
3" PVC pipe 460.00 /pc
3" PVC Elbow 1/4 bend 53.00 /pc
2" Stainless Steel pipe 3,250.00 /pc
3/16"x1" Flat bar 235.00 /pc
3/4"x3/4" Square bar 245.00 /pc
Welding rod/Accessories 2,500.00 /lot
4" Grinding disk 65.00 /pc
Water closets w/ Accessories 2,800.00
Wall hang lavatory w/ Accessories 1,800.00
Soap holder 250.00
Tissue holder 250.00
Towel holder 450.00
4"x4" Floor drain 350.00
Ordinary faucet 65.00
Clean water line pipes and accessories 2,000.00
Sewer pipe line and accessories 3,500.00
2x40W FL lamp w/ housing 1,500.00
25W CFL 60.00
4"x4" Pinlight 250.00
Receptacle 4" 50.00
Single pole switch 120.00
Two pole switch 165.00
3-Way switch 210.00
Main ACB 6-holes 1,850.00
4"x4" Junction box 35.00
2"x4" Utility box 35.00
1/2" PVC pipe x 3.00 mts. 61.00
3.5mm THHN wire 3,207.50
14mm THHN wire 85.84
1' PVC pipe x 3.00 mts. 102.00
1" Long sweep elbow 38.00
1/2" PVC Long sweep elbow 25.00
1" RSC pipe x 3.00 mts. 420.00
1" Entrance cap 65.00
3-Pole secondary rack 285.00
1" Long sweep elbow (RSC) 85.00
Electrical tape 45.00
Hardiflex ceiling board 420.00
0.40mm 19mm x 50mm x 5m
Double furring channel 115.00
0.80mm 12mm x 38mm x 5m
Carrying Channel 140.00
0.40mm 25mm x 25mm x 3m
Wall angle 85.00
W-Clip
8.00
1-1/2" Concrete nail 90.00
Mesh tape 150.00
Blind rivets 500.00

You might also like