You are on page 1of 1

PT.

Truba Jurong Engineering


Flexible Project Management
Tripatra - Flour

S-CURVE PROGRESS PLANNING


FOR 5R STEAM STATION ABANDONMENT
No.

Description

Qty

1 Inventory
- Inventory before dismantling
- Inventory before Transport to Junc Yard
Sub total
Pipe and pipe support dismantling (under and above ground, including non
2 used valves)

a. Cut and dismantle these equipment for ease to be transported


- Pipe (2" - 24")
- Pipe Insulation (2" - 24")
- Pipe Support (include pulling out of footer)
b. Blind active pipeline with flange material
c. Clean / flush pipe and valve before transported to Dumai Junk Yard
Sub total
Electrical and instrumentation dismantling
a. Dismantle electrical equipment
- Electrical switch rack & power centre
- Cable (under & above ground)
- Control Room Building
- Power Pole
- Transformer
Sub total
Steam Generator Dismantling
a. Unit dismantling (radian, convection, stack, transition, pump & instrument)
b. Removal of Steam Generator Insulation
Sub total
Tank Dismantling (1000 Bbls & 20000 Bbls)
a. Clean Fuel Oil Tanks from their fluid content
b. Clean Water Tanks from Rust
b. Cut and dismantle all tanks for ease to be transported
Sub total
Waste Handling
a. Insulation Materials
- Transport to Minas B3 temporary storage
b. Send oily waste (Sand and fluid) to SFI
Sub total
Equipment Dismantling
a. Dismantle steam station equipments
- Steam separator
- Gas Pilot
- Air Compressor
- Fuel Pump
- Heat Exchanger
- Softener
- Fencing removal & relocation
Sub total
Concrete foundation and drainage removal
a. Break concrete into smaller or movable size (approx 1mx1m)
- Steam Generator foundation
- Fuel Oil Tank Concrete
- Water Tank (Ring Wall)
- Ditch & Drainage
b. Transport Concrete to designated site and off-load for use by others, or backfill a
Sub total
Site grading and re-grading
a. Conduct survey for grading plan
b. Earthwork cut
c. Back Fill & Houling Soil < 15 Km (soil input) from Harapan Baru Brow Pit
d. COCS hauling to Darling Site
e. Grade the site properly to match with the contour of the sorrounding area to
prevent erosion
g. Soil sampling & testing (by third party lab)
h. Haul and spread top soil of 10 Cm thick for re-greening

i. Plant native grass sods of 20cmx20cm every 50cm distance to cover the area
Sub total
Loading, Transportation and Unload at Dumai Junk Yard and obtain signed
10 receiving inventory of all delivered materials
a. Transportation (incld Loading & Unloading)
Sub total
Total

Unit

Weight (%)

Prog %

Lot
Lot

0.56%
0.67%
1.23%

100.00%
0.56%
0.67%
1.23%

1,100 Mtr
1,100 Mtr
50 Pcs
10 Pcs
115 Hr

1.46%
0.31%
1.65%
0.57%
2.03%
6.02%

90.00%
1.46%
0.31%
1.65%
0.57%
2.03%
6.02%

4
1,000
450
8
-

Pcs
Mtr
M2
Pcs
Pcs

1.45%
3.41%
2.08%
0.56%
7.5%

7.5%
70.00%

10
10

Unit
Unit

17.54%
2.46%
20.00%

17.54%
2.46%
20.00%

1,000
20,000
21,000

Bbls
Bbls
Bbls

2.21%
0.70%
16.70%
19.61%

2.21%
60.00%
0.70%
16.70%
19.61%

410
100

M3
M3

4.41%
0.34%
4.75%

4.41%
0.34%
50.00%
4.75%

Unit
Unit
Unit
Unit
Unit
Unit
Mtr

0.00%
0.00%
0.27%
0.92%
0.00%
0.48%
1.78%
3.44%

0.00%
0.00%
0.27%
0.92%
40.00%
0.00%
0.48%
1.78%
3.44%

M3
M3
M3
M3
M3

9.21%
0.33%
0.36%
2.67%
2.66%
15.24%

30.00%
9.21%
0.33%
0.36%
2.67%
2.66%
15.24%

1
1

Week
22/07/06 28/07/06

Week
29/07/06 04/08/06

0.08%

Week
05/08/06 11/08/06

0.28%

Week
12/08/06 18/08/06

Week
19/08/06 25/08/06

Week
26/08/06 01/09/06

Week
02/09/06 08/09/06

Week
09/09/06 15/09/06

Week
16/09/06 22/09/06

Week
23/09/06 29/09/06

Week
30/09/06 06/10/06

Week
07/10/06 13/10/06

Week
14/10/06 20/10/06

Week
21/10/06 27/10/06

Week
28/10/06 03/11/06

Week
04/11/06 10/11/06

Week
11/11/06 17/11/06

0.20%

0.29%

0.45%
0.34%

0.11%
1.69%

0.39%
0.68%

0.68%
1.19%

0.20%

0.23%

0.23%

0.41%
0.11%

0.41%
0.11%
0.83%

0.35%
0.09%
0.83%

80.00%

2
6
3
600

1,000
36
40
290
1,326

1.45%
3.41%
2.08%
0.56%

1
1,000
500
120

Lot
M3
M3
M3

0.72%
0.61%
0.54%
0.17%

20.00%
0.72%
0.61%
0.54%
0.17%

8,000
4
1,000

M2
Ea
M3

3.52%
1.13%
1.08%

3.52%
10.00%
1.13%
1.08%

8,000

M2

4.19%
11.96%

4.19%
11.96%

Trip

10.25%
10.25%

10.25%
0.00%
10.25%

100.00%

100.00%

53

0.39%
1.19%

0.34%
0.52%

0.73%
0.42%

0.10%

2.76%

2.76%

2.10%

0.35%

1.27%
0.74%

2.76%
0.86%

2.76%
0.86%

1.03%

1.03%

0.15%

0.47%
0.17%

0.23%
1.96%

3.01%

3.01%

3.01%

3.01%

2.22%

0.33%

0.24%
0.34%

1.71%

1.71%

0.73%

0.27%
0.31%

0.36%

0.32%

0.16%

2.76%

0.73%
0.14%

0.26%

2.93%

2.93%
0.22%

2.93%
0.11%

0.36%

0.62%

0.62%

0.18%

0.26%
0.59%
0.30%

0.10%
1.04%
1.03%

1.04%
1.03%

0.30%

0.42%

0.31%
0.10%

0.41%
0.51%
0.15%
0.17%

0.97%

0.00%
0.00%

0.08%
0.08%

4.79%
4.87%

10.87%
15.74%

10.47%
26.21%

0.77%

2.32%

3.10%

2.32%

1.35%

13.20%
39.41%

14.34%
53.75%

14.77%
68.52%

8.88%
77.40%

4.28%
81.68%

0.38%

1.23%
0.16%

1.23%

1.06%

0.76%

0.32%
1.68%

2.51%

3.06%
97.49%

2.51%
100.00%

0.39%

2.80%
84.48%

3.11%
87.59%

3.08%
90.67%

1.78%
92.44%

1.99%
94.43%

Week
18/11/06 24/11/06

Remarks