You are on page 1of 3

Activity ID Activity Name Original

Duration
Early Start Early Finish
100-429-01 - Juicy Couture @Yas Mall, Abu Dhabi - IF Programme 100-429-01 - Juicy Couture @Yas Mall, Abu Dhabi - IF Programme
150 08-Jun-14 04-Nov-14
General General
5 08-Jun-14 12-Jun-14
A2140 Work order confirmation 1 08-Jun-14 08-Jun-14
A2160 Receipt of client drawings & documents 1 09-Jun-14 09-Jun-14
A2150 Kick off meeting 1 10-Jun-14 10-Jun-14
A2270 Site survey 2 11-Jun-14 12-Jun-14
Pre-construction Pre-construction
97 14-Jun-14 18-Sep-14
Shop drawing approval Shop drawing approval
34 18-Jun-14 04-Aug-14
Fit out drawings Fit out drawings 34 18-Jun-14 04-Aug-14
A2170 Shop drawing preparation 25 18-Jun-14 22-Jul-14
A2180 Shop drawings submission 16 08-Jul-14 29-Jul-14
A2190 Shop drawing approval 16 14-Jul-14 04-Aug-14
Authority approvals Authority approvals
19 14-Jun-14 05-Jul-14
A2390 Submission of drawings to mall 8 14-Jun-14 22-Jun-14
A2400 Receipt of mall approval 6 23-Jun-14 29-Jun-14
A2410 Apply for temporary power 1 30-Jun-14 30-Jun-14
A2420 Receipt of temp power connection 3 01-Jul-14 03-Jul-14
A2430 Safety induction 1 05-Jul-14 05-Jul-14
Sample approval Sample approval
20 16-Jun-14 13-Jul-14
A2200 Sample preparation 15 16-Jun-14 06-Jul-14
A2210 Sample submission 1 07-Jul-14 07-Jul-14
A2220 Samples approval 4 08-Jul-14 13-Jul-14
Procurement & production Procurement & production
67 13-Jul-14 18-Sep-14
A2250 Procurement of materials 42 13-Jul-14 24-Aug-14
A2260 Joinery production 45 04-Aug-14 18-Sep-14
Construction Construction
122 05-Jul-14 04-Nov-14
General General
3 05-Jul-14 08-Jul-14
A2230 Site access 0 05-Jul-14
A2240 Mobilization 3 05-Jul-14 08-Jul-14
Civil works Civil works
69 05-Jul-14 12-Sep-14
A1280 Installation of hoarding 2 05-Jul-14 07-Jul-14
A1300 Installation of graphics over hoarding 1 07-Jul-14 08-Jul-14
A1000 Screed laying & drying 5 14-Jul-14 19-Jul-14
A1270 Self leveling 2 10-Sep-14 12-Sep-14
MEP works MEP works
57 08-Jul-14 03-Sep-14
Electrical Electrical 57 08-Jul-14 03-Sep-14
A2350 Installation of floor conduits & boxes 6 08-Jul-14 14-Jul-14
P4LP102 Wiring for Lighting and Power 16 19-Jul-14 04-Aug-14
P4LP101 Conduit laying, tray & support 16 20-Jul-14 05-Aug-14
P4LC100 Wiring for Fire Alarm 16 20-Jul-14 05-Aug-14
01 08 15 22 29 06 13 20 27 03 10 17 24 31 07 14 21 28 05 12 19 26 0209
June July August September October November
2014
08-Jun-14 08-Jun-14
09-Jun-14 09-Jun-14
10-Jun-14 10-Jun-14
11-Jun-14 12-Jun-14
18-Jun-14 22-Jul-14
08-Jul-14 29-Jul-14
14-Jul-14 04-Aug-14
14-Jun-14 22-Jun-14
23-Jun-14 29-Jun-14
30-Jun-14 30-Jun-14
01-Jul-14 03-Jul-14
05-Jul-14 05-Jul-14
16-Jun-14 06-Jul-14
07-Jul-14 07-Jul-14
08-Jul-14 13-Jul-14
13-Jul-14 24-Aug-14
04-Aug-14 18-Sep-14
05-Jul-14
05-Jul-14 08-Jul-14
05-Jul-14 07-Jul-14
07-Jul-14 08-Jul-14
14-Jul-14 19-Jul-14
10-Sep-14 12-Sep-14
08-Jul-14 14-Jul-14
19-Jul-14 04-Aug-14
20-Jul-14 05-Aug-14
20-Jul-14 05-Aug-14
Project Start: 08-Jun-14
Date: 23-Jun-14
Actual Work
Remaining Work
Critical Remaining Work
100-429-01 - Juicy Couture @ Yas Mall, Abu
Dhabi - IF Programme
Page 1 of 3
Date Revision Checked Approved
Activity ID Activity Name Original
Duration
Early Start Early Finish
P4LC103 Wiring for Structured Cabling 14 22-Jul-14 05-Aug-14
P4LC101 Wiring for Emergency lights 12 24-Jul-14 05-Aug-14
P4LP103 Power Cables Installation 9 05-Aug-14 14-Aug-14
P4LP105 Cable Terminations 7 12-Aug-14 19-Aug-14
P4LP106 Wiring Accessories Installation 9 16-Aug-14 25-Aug-14
P4LP104 DB Installation 7 19-Aug-14 26-Aug-14
P4LP100 Installation Of Conduits In Gypsum Walls/Partitions 9 25-Aug-14 03-Sep-14
HVAC works HVAC works 21 22-Jul-14 12-Aug-14
A1950 Installation of main ducts incl insulation 17 22-Jul-14 08-Aug-14
A1960 Installation of branch ducts incl insulation 14 27-Jul-14 10-Aug-14
A1970 Installation of dampers 9 03-Aug-14 12-Aug-14
Fire fighting Fire fighting 37 23-Jul-14 29-Aug-14
A2090 Installation of main fire fighting pipes 17 23-Jul-14 09-Aug-14
A2100 Installation of branch fire fighting pipes 17 26-Jul-14 12-Aug-14
A2120 Pressure test 7 12-Aug-14 19-Aug-14
A2110 Sprinkler pipe dropping 7 22-Aug-14 29-Aug-14
Ceiling finishes Ceiling finishes
23 19-Aug-14 11-Sep-14
A1070 Clearance for ceiling frameworks 0 19-Aug-14
A1080 Framework for gypsum ceiling 14 19-Aug-14 02-Sep-14
A1090 Inspection before ceiling closure 0 25-Aug-14
A1100 Gypsum boarding,taping & jointing 14 25-Aug-14 08-Sep-14
A1190 Installation of curtain rail or recessed track in the drywall ceiling 3 08-Sep-14 11-Sep-14
Shop front works Shop front works
24 18-Sep-14 12-Oct-14
A1030 Installation of shop front entrance portal 7 18-Sep-14 25-Sep-14
A1040 Shop front glass 7 25-Sep-14 02-Oct-14
A1050 Mdf cladding above shop front glass 5 02-Oct-14 07-Oct-14
A1060 Installation of golden electroplated stainless steel cladding with rivets all along the glazing perimeter 5 07-Oct-14 12-Oct-14
Wall finishes Wall finishes
52 19-Aug-14 10-Oct-14
A1110 Framework for gypsum partition 16 19-Aug-14 04-Sep-14
A1120 Installation of gypsum partition 16 23-Aug-14 08-Sep-14
A1130 Installation of MDF partition 12 08-Sep-14 20-Sep-14
A1230 Primer & stucco works 8 10-Sep-14 18-Sep-14
A1250 Painting 1 & 2nd coat 6 18-Sep-14 24-Sep-14
A1140 Installation of moldings 10 20-Sep-14 30-Sep-14
A1290 Final painting 5 30-Sep-14 05-Oct-14
A1160 Installation of fabric back wall paper (free supplied) 5 05-Oct-14 10-Oct-14
A1170 Installation of mirror 2 08-Oct-14 10-Oct-14
Floor finishes Floor finishes
14 08-Sep-14 22-Sep-14
A1020 Installation of ceramic tile flooring 4 08-Sep-14 12-Sep-14
A1010 Installation of wooden flooring 10 12-Sep-14 22-Sep-14
Shop fittings Shop fittings
45 18-Sep-14 02-Nov-14
01 08 15 22 29 06 13 20 27 03 10 17 24 31 07 14 21 28 05 12 19 26 0209
June July August September October November
2014
22-Jul-14 05-Aug-14
24-Jul-14 05-Aug-14
05-Aug-14 14-Aug-14
12-Aug-14 19-Aug-14
16-Aug-14 25-Aug-14
19-Aug-14 26-Aug-14
25-Aug-14 03-Sep-14
22-Jul-14 08-Aug-14
27-Jul-14 10-Aug-14
03-Aug-14 12-Aug-14
23-Jul-14 09-Aug-14
26-Jul-14 12-Aug-14
12-Aug-14 19-Aug-14
22-Aug-14 29-Aug-14
19-Aug-14
19-Aug-14 02-Sep-14
25-Aug-14
25-Aug-14 08-Sep-14
08-Sep-14 11-Sep-14
18-Sep-14 25-Sep-14
25-Sep-14 02-Oct-14
02-Oct-14 07-Oct-14
07-Oct-14 12-Oct-14
19-Aug-14 04-Sep-14
23-Aug-14 08-Sep-14
08-Sep-14 20-Sep-14
10-Sep-14 18-Sep-14
18-Sep-14 24-Sep-14
20-Sep-14 30-Sep-14
30-Sep-14 05-Oct-14
05-Oct-14 10-Oct-14
08-Oct-14 10-Oct-14
08-Sep-14 12-Sep-14
12-Sep-14 22-Sep-14
Project Start: 08-Jun-14
Date: 23-Jun-14
Actual Work
Remaining Work
Critical Remaining Work
100-429-01 - Juicy Couture @ Yas Mall, Abu
Dhabi - IF Programme
Page 2 of 3
Date Revision Checked Approved
Activity ID Activity Name Original
Duration
Early Start Early Finish
A1150 Installation of door & ironmongeries 5 18-Sep-14 23-Sep-14
A1260 Installation of glass door at entrance 3 23-Sep-14 26-Sep-14
A1210 Filing cabinet installation 3 30-Sep-14 03-Oct-14
A1220 Installation of staff lockers 3 01-Oct-14 04-Oct-14
A1240 Installation of shop fittings 6 03-Oct-14 09-Oct-14
A1180 Installation of signage 3 07-Oct-14 10-Oct-14
A1200 Installation of loose furniture 3 30-Oct-14 02-Nov-14
MEP final fix MEP final fix
9 20-Sep-14 29-Sep-14
A1980 Air outlets installation 9 20-Sep-14 29-Sep-14
P4LP107 Light Fittings Installation 9 20-Sep-14 29-Sep-14
P4LC106 Fire Alarm Devices Installation 9 20-Sep-14 29-Sep-14
A2130 Sprinkler installation 7 22-Sep-14 29-Sep-14
P4LC108 CCTV Devices Installation 7 22-Sep-14 29-Sep-14
Snagging & Handover Snagging & Handover
28 07-Oct-14 04-Nov-14
A1760 Snagging & Desnagging works 8 07-Oct-14 15-Oct-14
A1790 Substantial completion before authority approval 0 15-Oct-14
A1730 ADDC inspection (can be varied) 5 16-Oct-14 21-Oct-14
A1670 Getting permanent power supply 0 21-Oct-14
A1650 Fire alarm testing & commissioning & panel programming 2 22-Oct-14 24-Oct-14
A1680 Electrical testing & commissioning 2 22-Oct-14 24-Oct-14
A1690 A/C air balancing & commissioning 2 22-Oct-14 24-Oct-14
A1740 ADCD inspection 2 26-Oct-14 27-Oct-14
A1780 ADCD completion certificate 0 27-Oct-14
A1750 ADM inspection 2 29-Oct-14 30-Oct-14
A1700 Mall final inspection & approval 1 02-Nov-14 02-Nov-14
A1770 Final cleaning 2 02-Nov-14 04-Nov-14
A1710 Final inspection by client 1 03-Nov-14 03-Nov-14
A1720 Client possession 0 03-Nov-14
01 08 15 22 29 06 13 20 27 03 10 17 24 31 07 14 21 28 05 12 19 26 0209
June July August September October November
2014
18-Sep-14 23-Sep-14
23-Sep-14 26-Sep-14
30-Sep-14 03-Oct-14
01-Oct-14 04-Oct-14
03-Oct-14 09-Oct-14
07-Oct-14 10-Oct-14
30-Oct-14 02-Nov-14
20-Sep-14 29-Sep-14
20-Sep-14 29-Sep-14
20-Sep-14 29-Sep-14
22-Sep-14 29-Sep-14
22-Sep-14 29-Sep-14
07-Oct-14 15-Oct-14
15-Oct-14
16-Oct-14 21-Oct-14
21-Oct-14
22-Oct-14 24-Oct-14
22-Oct-14 24-Oct-14
22-Oct-14 24-Oct-14
26-Oct-14 27-Oct-14
27-Oct-14
29-Oct-14 30-Oct-14
02-Nov-14 02-Nov-14
02-Nov-14 04-Nov-14
03-Nov-14 03-Nov-14
03-Nov-14
Project Start: 08-Jun-14
Date: 23-Jun-14
Actual Work
Remaining Work
Critical Remaining Work
100-429-01 - Juicy Couture @ Yas Mall, Abu
Dhabi - IF Programme
Page 3 of 3
Date Revision Checked Approved