The document discusses the process of constructing underground 400kV cables. It describes the key components of the cables, including their diameter, materials, and need for joints. It then outlines the steps of construction, including preparing the work area, excavating trenches, laying the cables, joining sections, and reinstating the ground. Periodic inspections and potential repairs after approximately 40 years are also mentioned. Sealing end compounds are discussed as the connection points between overhead lines and underground cables.
Original Description:
tech
Original Title
National Grid Underground Cable Construction Presentation FINAL
The document discusses the process of constructing underground 400kV cables. It describes the key components of the cables, including their diameter, materials, and need for joints. It then outlines the steps of construction, including preparing the work area, excavating trenches, laying the cables, joining sections, and reinstating the ground. Periodic inspections and potential repairs after approximately 40 years are also mentioned. Sealing end compounds are discussed as the connection points between overhead lines and underground cables.
The document discusses the process of constructing underground 400kV cables. It describes the key components of the cables, including their diameter, materials, and need for joints. It then outlines the steps of construction, including preparing the work area, excavating trenches, laying the cables, joining sections, and reinstating the ground. Periodic inspections and potential repairs after approximately 40 years are also mentioned. Sealing end compounds are discussed as the connection points between overhead lines and underground cables.
corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line. 400kV Underground Cable Construction Tim Inglehearn 2 Contents Underground cable components Access and preparation for construction Underground cable construction Reinstatement Inspection and maintenance Sealing end compounds 3 Underground Cable Components 150mm diameter cables, made up of copper core, cross linked polyethylene insulation, seamless corrugated aluminium sheath and PVC outer sheath Max. 18 cables would be needed, laid in 6 x groups of 3 Separation required to allow heat to dissipate Joints required every 500 800m (depends on cable manufacture) Sealing end compounds required at either end of underground section 4 Access for Construction Approx. 65m wide working area, protected by post and wire fencing Temporary trackway provide vehicle access along entire route Vegetation clearance across working area Drainage improvement works Temporary soil storage Access, Working Areas and Ground Preparation 5 Underground Cable Construction Excavators to clear working area, dig trenches and improve drainage Delivery of materials to site using 38 tonne lorries (cables on drums) Tractors and other smaller vehicles used to transport materials within cable route Backfill delivered to site and surplus spoil removed Machinery Required 6 Cable trenches and laying Excavation of 6 trenches within working area Timber reinforcement to trench sides Cement Bound Sand bed Cables laid at a depth of 1.1m on CBS bed and surrounded by an additional CBS layer Concrete protective tiles Warning tapes Underground Cable Construction 7 Underground Cable Construction Cable trenches and laying example of section through a working area 8 Underground Cable Construction Cable jointing Joints required every 500 800m depending on length of cables Joints are made in controlled clean conditions Technically demanding and labour intensive Copper conductors joined with a compression ferrule Insulation hand wrapped Protected by glass fibre box filled with resin or bitumen 9 Reinstatement Reinstatement of soil above cable trench and across working area Temporary access tracks and site fencing removed Care needs to be taken with replacement of hedgerows and fencing restrictions apply Permanent tree loss over cable swathe 10 Inspection and Maintenance Inspection is carried out at a min. every 3 years using test equipment carried in vans Monitoring is carried out via fibre optic cables installed with the power cables Excavation required to carry out cable repairs Cable replacement every 40 years (approx.) 11 Sealing End Compounds SEC provides connection between overhead line and underground cables Area protected by 2.4m high pallisade fence with electrified fence inside Permanent vehicle access required Terminal overhead line tower with downleads Cable sealing ends emerge from ground 12 Sealing End Compounds 2.4m palisade fence with electrified fence above Surge arrestor Downlead from OHL tower Cable sealing end Insulated post Height barrier 13 Any Questions?