A.

For Roads and Drainage


1.0 Site Clearance
1.1 Grader (14 G) =3150 M/Day
(20 cms thick layer)
1.2 Wheel Loader (966) to load (Stock pile within 20M) =1260 M/Day
(7 minuter per truck)
1.3 Haulage by Dump Trucks (25tonnes) =110M/Day
(One way 25 kms) 7 trips
or
1.4 Haulage by Trailer (60 tonnes) =220M/Day
1.5 Bull Dozer (D8) =893M/Day
or
1.6 Bull Dozer (D6) =630M/Day
2.0 Borrow Pit Excavation (Material Collection)
2.1 Bull Dozer (D8) =893M/Day
2.2 Wheel Loader (966) =893M/Day
3.0 Borrow Excavation (Haulage & Compaction) (Considering Loose materials)
3.1 Dump Truck (25 tones) =110M/Day
(Average haul 25 km one way
3.2 Grader (14 g) =630M/Day
3.3 Water Tanker (4000 Glns) =8400 Glns/Day
3.4 Vibratory Roller (25 tones) =2100 M/Day
Average depth (150 mm)
4.0 Sub-Base and Road Base (Compaction) (Considering Loose materials)
4.1 Grader 14 G (150 mm thick layer) =630M/Day
4.2 Water Tanker (4000 Glns) =8400 Glns/Day
4.3 Vibratory Roller (25 tones) =4200M/Day
4.4 PTR Roller (25 tonnes)
5.0 Bituminous Paving (Laying and Compaction)
(based on 42 tonnes/Hr. average production)
5.1 Dump Truck =2 hrs/42 tonnes
5.2 Finisher =1/2 hrs/42 tonnes
5.3 Water Tanker =1 hr / 42 tonnes
5.4 Vibratory Roller =2 hrs/42 tonnes
5.5 PTR =2 hrs /42 tonnes
6.0 Prime Coat
6.1 Bitumen Tanker (600 Glns) =2625 M/Day
7.0 Interlocking Tiles
STANDARD PRODUCTIVITY RATES
(based on 10 hrs per day)
STANDARD PRODUCTIVITY RATES
(based on 10 hrs per day)
7.1 Compactor (1No.) =210 M/Day
7.2 Mason (4 Nos.) =105 M/Day or
7.3 Helper (6 Nos.) =10.50 M/Man Day
8.0 Kerb Stones (excluding concrete)
8.1 Mason (2 Nos.) =95 M/Day or
8.2 Helpers (4 Nos.) =16M/Man Day
9.0 Trench Excavation
9.1 Excavator 225 =158 M/Day
(Trench width 1.8M and avarage 5M depth)
9.2 JCB =74 M/Day
(Trench width 1.0M and average 3M depth)
9.3 Shovel (Loading) =893 M/Day
9.4 Trench Sheeting after boxing (using excavator) =210 Nos. Day
9.5 Boxing for Sheeting (3 to 5M depth) =3 Nos./ Day
(With 1 Welder and 2 Helpers)
9.6 Back Filling
9.6.1 Baby Roller (1 No.) =53M/Day
9.6.2 Plate Compactor (1 No.)
9.6.3 Water Tanker (4000 Glns) = 0.25 No
10.0 Structural Excavation (Open Area)
10.1 Excavator 225 =263M/Day
Dozer D8 =893M/Day
Shovel 966 =893M/Day
Dump Truck (25 tonnes) =105M/Day
(25 km Haul)
11.0 Manhole Construction
11.1 Concrete Pouring =6.50M/Day
(without pump)
Mason =1 No
Labour =4 Nos.
Vibrator =1 No.
11.2 Formwork
11.2.1 Preparation and Forming =13M/Day
Carpenter =2 No
Helper =1No
Average = (13/6) = 2.10 M/Man Day
P.S. For circular man holes difficulty factor for preparation and forming to be considered as 0.45
STANDARD PRODUCTIVITY RATES
(based on 10 hrs per day)
12.0 Laying Pipework/Ductwork
Pipe Fitters = 2 Nos.
Helpers = 4 Nos.
PIPE SIZE QTY /GANGDAY
100 mm UPVC/AC Pipes 101 Meters
150 mm UPVC/AC Pipes 95 Meters
200 mm UPVC/AC Pipes 88 Meters
250 mm UPVC/AC Pipes 82 Meters
300 mm UPVC/AC Pipes 76 Meters
400 mm AC/GRP Pipes 69 Meters
450 mm AC/GRP Pipes 63 Meters
500 mm AC/GRP Pipes 57 Meters
550 mm AC/GRP Pipes 50 Meters
600 mm AC/GRP Pipes 44 Meters Use of
700 mm AC/GRP Pipes 38 Meters Mobile
800 mm AC/GRP Pipes 32 Meters Crane
850 mm AC/GRP Pipes 32 Meters allowed.
900 mm AC/GRP Pipes 25 Meters
1000 mm AC/GRP Pipes 19 Meters
1200 mm AC/GRP Pipes 13 Meters
90 , 100 mm PVC Ducts 189 Meters
150 mm PVC Ducts 158 Meters
B. BUILDINGS
1.0 Excavation and Get Out (Manual)
1.1 upto 1.50 M deep =3.70 M/Day/Labour
1.2 upto 2.0 M deep =2.90 M/Day/Labour
1.3 upto 3.0 M deep =2.10 M/Day/Labour
2.0 Hand Backfilling and compaction
Plate Compactor =1 No
Labour =3 Nos
21 M/Day
3.0 Machine excavation including disposal
Shovel =1 No.
Trucks =2 Nos.
Labour =6 Nos.
210 M/Day
4.0 Cutting of Pile Heads
Compressor unit with Jack Hammer =0.5 No.
Labour =3 Nos.
STANDARD PRODUCTIVITY RATES
(based on 10 hrs per day)
3..> 2.50 piles/day
5.0 Concrete Works
5.1 Blinding Concrete (Mixing by us)
Plant =1 No
Mixer machine (14/10) =1 No
Dumper
Labour for Mixing
Mixer Operator =1 No
Labour for Aggregates =2 Nos
Labour for Sand =2 Nos
Labour for Cement =1 No.
Labour for Placing
Labour for Dumper to Trolley =1 No
Labour on Wheel Barrow =3 Nos
Helper for mason =1 No
Mason =2 Nos
Production =16 M/Day
5.2 Blinding Concrete (unsing Ready Mixed Concrete)
Labour for shifting and pouring =6 Nos
Mason =2 Nos
Dumper =1 No.
Production =16 M/Day
5.3 Concrete for Columns, Walls & Parapet (using Pump)
Labour =3 Nos
Mason =2 Nos
Carpenter =1 No
Pump =1 No
Vibrator =1 No
Production =17 M/Day
5.4 Concrete for columns, Walls & Parapet (without Pump)
Labour for shifting and pouring =6 Nos
Mason =2 Nos
Carpenter =1 No
Vibrator =1 No
Dumper =1 No
Production 13 M/Day
STANDARD PRODUCTIVITY RATES
(based on 10 hrs per day)
5.5 Concrete for beams, slabs and big sections (using pump)
Labour for signalling =1 No
Labour for pump chute =2 Nos
Labour for vibrators =5 Nos
Labour for concrete spreading =5 Nos
Masons (4+1) =5 Nos
Carpenters =2 Nos
Steel Fixer =1 No
Scaffolder =1 No
Vibrators =2 Nos
Production 105 M/ 4 Hrs
5.6 Form work
6.1 For Foundations and Tie Beams
6.1.1 Preparations and Forming 26 M/Day
Carpenter =2 Nos
Helper =1 No
6.1.2 Fixing, stripping and cleaning 26 M/Day
Carpenter =2 Nos
Helper =1 No
P.S. Average Production Rate of complete operation shall be 4.40 M/Man Day
6.2 For Columns and Walls
6.2.1 Preparation and Forming 21 M/Day
Carpenter =2 Nos
Helper =1 No
6.2.2 Fixing, stripping and cleaning 21 M/Day
Carpenter =2 Nos
Helper =1 No
P.S. Average Production Rate of complete operation shall be 3.40 M/Day
STANDARD PRODUCTIVITY RATES
(based on 10 hrs per day)
6.3 For Beams and Slabs
(Based on area 2 x 4 x 4 M: total forms area 54 M
6.3.1 Preparation and Forming 57 M/Day
Carpenter =4 Nos.
Helper =2 Nos.
6.3.2 Fixing, stripping and cleaning
Carpenter =4 Nos
Helper =2 Nos
6.3.3 Scaffolding Erection
(2 x 4 x 4 x 3.40 M) =107 M
Considering Average Production =2.83M /1.60 Hrs.
Scaffolders =5 Nos
Helpers =3 Nos
P.S. Average Production Rate of complete operation shall be 2.90 M/Man Day
7.0 Steel Reinforcement
Steel Fixers =3 Nos
Helpers =3 Nos
P.S.
1) Average production rate for complete operation including
cutting, bending, handling, placing and tying =147 kg/ Man Day
2) Average production rate for handling placing and tying =263 kg/Man Day
8.0 Masonry
Mason =1 No
Helper =1.5 No
Average Production =5.3 M/Man Day
9.0 Plaster Works
STANDARD PRODUCTIVITY RATES
(based on 10 hrs per day)
9.1 Internal Plaster
Mason =1 No
Helper =2 Nos.
Average Production =6.3 M/Man Day
9.2 External Plaster
Mason =1 No
Helper =2 No
Average Production =4.7 M/Man Day
10.0 Screening (Trowel Finish)
Mason =1 No
Helper = 2 Nos
Production =25 M/Man Day
= 8.4 M/Man Day
11.0 Ceramic Tiles
Mason =1 No
Helper =1 No
Production for big size tiles =6.3 M/Man Day or
3.2 M/Man Day
Production for small size tiles =4.7 M/Man Day or
2.4 M/Man Day
12.0 Terrazo Tiles
Mason =1 No
Helper =1 No
Production =13 M/Man Day
6.3 M/Man Day
13.0 Vinyl Tiles
Mason =1 No
Helper =1 No
Production =18 M/Man Day
7.4 M/Man Day
14.0 Skirtings
Mason =1 No
Helper =1 No
Production =19 M/Day or
9.5 M/Man Day