Birla Institute of Technology & Science, Pilani

Work Integrated Learning Programme Division


M.S. System software
Second Semester 2013-2014
Assignment No. I

Course No. : BITS ZG 553
Course Title : Real-Time Systems
Weightage : 5%

I nstructions: Please note that, no identical answers will be given credit.
All questions carry equal weightage.


Q 1. Choose any hard real-time system of your choice and model the system. Modeling should
consist of
-- Proper partitioning the system
-- Identifying the various periodic, aperiodic and sporadic tasks
-- Grouping the tasks into task set and identifying proper precedence and dependency among
tasks
-- suggesting suitable scheduling algorithms for various task sets
-- Adding any relevant information, you want to add

Q 2. . A system of three tasks T
1
(4,1) ; T
2
(4,1.5,6) and T
3
(5,0.5) is to be scheduled with
clock-driven cyclic executive algorithm.
a) Draw a neat timing diagram choosing proper frame size.
b) If a stream of aperiodic jobs A
1
(4,1.5), A
2
(9.5,0.5) and A
3
(10.5,2) arrives, how
will you schedule this stream by using cyclic executive method ?
c) Now apply slack stealing. Compare average response time in both cases.

Q 3. Consider a periodic task set consisting of three tasks,
T
i
(p
i
, e
i
,) = {(7,3);(12,3);(20,5)} Where p is period, e is execution time
of the task T
i
. Complete the response time analysis using RM scheduling
algorithm
i. Apply utilization based scheduling test and determine whether the system is schedulable or
not.
ii. Use iterative method of time demand analysis to determine whether the system is schedulable
or not.

Q 4. Consider the following tasks with their resource requirements given as Ti (r
i
, e
i
,
i
[R; t]).
T
1
(10, 4,1 [A; 1]) where task executes for two units of time then requests the resource A.
T
2
(7, 4, 2 [A; 1][B; 1]) where task executes for one unit, then requests A and B.
T
3
(4, 4, 3 [B; 1][C; 1]) where task executes for one unit then requests B and C.
T
4
(0, 11, 4 [A; 5[B; 2][C; 1]]) where task executes for two units of time then requests
A, hold it for one unit of time and makes a nested request for B and C.
i. Construct the schedule for the system using priority-ceiling protocol.
ii. Comment on schedulability .using Priority-Ceiling Protocol.