Page 74

RAJKOT IRRIGATION DIVISION - RAJKOT


NYARI-II IRRIGATION SCHEME
Name of Work: Providing D/S apron of Nyari-II Irrigation Scheme.

SCHEDULE - B
Item Quantities Item of Work. Estimated Rates Unit Total amount
No. estimated but In Figures In Words according to
may be more estimated quantities.
or less.

1 2 3 4 5 6 7
1 1150.00 Preparation of spillway and allied works foundations 3.60 Rupees: Three & Ps. Sqm. 4140.00
incl. removal of loose weathered and hard rock by Sixty Only.
wedging, chiseling with all labours and materials, for
cleaning the foundations with compressed air and
water jetting as required, clearing work, slush, etc.
completed.
2 180.00 Dewatering for head works and allied works, foundation 11.00 Rupees: Eleven Only. 1 1980.00
area, pits, trenches with diesel or electrical pumping HP/hou
arrangements including all cost of pipe line, materials, r.
labours as directed with all lift etc. complete.

3 155.00 Excavation of hard rock including light and controlled 300.00 Rupees: Three Cum. 46500.00
blasting and removal of materials by means of Hundred Only.
wedging, chiseling and depositing the excavated stuff
as and where directed including sorting and stacking of
useful material as required with a lead up to 200 mt.
and all lift etc. complete for body wall, appron, bucket,
key trench etc. complete.
4 45.00 Drilling 50 mm. dia holes at 3 mt. C/C or as specified 263.00 Rupees: Two Hundred Rmt. 11835.00
up to 3 mt. depth in spillway below bucket for anchor Sixty Three Only.
bars including cleaning holes as directed etc.
completed.
Page 75

Item Quantities Item of Work. Estimated Rates Unit Total amount


No. estimated but In Figures In Words according to
may be more estimated quantities.
or less.

1 2 3 4 5 6 7
5 45.00 Fixing 25 mm. dia. anchor bar as per drawing in 50.00 Rupees: Fifty Only. Rmt. 2250.00
foundation below bucket including making ring at
bottom and filling the holes with C.M. 1:1 etc. complete.
excluding cost of steel.
6 Providing and laying in position cement concrete using
cement, sand and crushed aggregate by weigh
batching and mixing including providing and fixing
necessary form works and centering, smooth specified
finishings, vibrating, curing as directed with all lifts etc
comp.excluding cost of steel.
190.00 (g) Key trench, foundation, apron, platform etc. M- 1680.00 Rupees: One Cum. 319200.00
10 (M.S.A.80 MM) Thousand Six Hundred
Eighty Only.
708.00 (b) Bucket and end sill concrete M-20 (M.S.A.- 3000.00 Rupees: Three Cum. 2124000.00
80mm) Thousand Only.
Page 76

Item Quantities Item of Work. Estimated Rates Unit Total amount


No. estimated but In Figures In Words according to
may be more estimated quantities.
or less.

1 2 3 4 5 6 7
7 24.20 Providing and laying reinforcement for R.C.C. works 38775.00 Rupees: Thirty Eight M.T. 938355.00
and anchor bars with providing binding wires including Thousand Seven
cutting, bending, welding, binding in position, hooking, Hundred Seventy Five
placing in position with all leads & lifts etc. complete. Only.
(a) H.Y.S.D. steel bar.
Total Rs… 3448260.00

(Rupees: Thirty Four Lacs, Fourty Eight Thousand Two Hundred Sixty Only)

I/We am/are willing to carry out the work at ……………………….% above / below present (should be written in figures and words)
of the estimated rates mentioned above. An amount of my/our tender works out as under:
* Estimated Amount * Estimated Amount

Put to tender Rs………………….. Put to tender Rs

Deduct ……………………..% below Rs………………….. Add …………..% above Rs…

Net Rs…………………… Total: Rs..

In Words………………………………………………………………………. In Words………………………………………………
(Pease strike out whichever is not applicable)

Note-1: All work should be carried out as per Public Works Department Hand book and other specifications of Division or as directed.
Note-2: All the columns is Schedules should be filled in ink and the total fo the entries in the alst column should be struck as directed.
Note-3: Rates quoted include clerance of site (Prior commencemetn of work and at its close) in all respects and hold good for work.
Note-4: To be continued on additional sheets, if found necessary.

Executive Engineer
Signature of Contractor. Rajkot Irrigation Division,
Rajkot.