Dear Team,
Kindly find attached the breakdown for the execution of Nagis works.
I have broken down the works in tasks and asociated costs for everyones review.
I request that we get the material prices for lodwar if they are any different from the ones i have shown.
In that case make changes on the excell document and circulate to all highlighted in different colour.
I note that we need to mobilise the works as the date promised was 16th June 2014.
In my very considered view this work can be completed in very good time if we join hands.
As of now, mobilisation money has not hit the account. Immeaditely we get it we shall notify you.
My suggestion is we get feedback from all copied by this mail today on the way forward.
Over to you guys.
Regards
Eng Kiarie
dear david
thank you for the detail activity breakdown however i have noted that there is difference on the labour charges for activity C & D ie the labour charge for activity C is 50,500 while D which has the same team as indicated on the schedule is 59,500.
Another issue is to why is activity G and H no cost is provided for with regard to them .
regards
Paul
Dear Team,
Kindly find attached the breakdown for the execution of Nagis works.
I have broken down the works in tasks and asociated costs for everyones review.
I request that we get the material prices for lodwar if they are any different from the ones i have shown.
In that case make changes on the excell document and circulate to all highlighted in different colour.
I note that we need to mobilise the works as the date promised was 16th June 2014.
In my very considered view this work can be completed in very good time if we join hands.
As of now, mobilisation money has not hit the account. Immeaditely we get it we shall notify you.
My suggestion is we get feedback from all copied by this mail today on the way forward.
Over to you guys.
Regards
Eng Kiarie
dear david
thank you for the detail activity breakdown however i have noted that there is difference on the labour charges for activity C & D ie the labour charge for activity C is 50,500 while D which has the same team as indicated on the schedule is 59,500.
Another issue is to why is activity G and H no cost is provided for with regard to them .
regards
Paul
Dear Team,
Kindly find attached the breakdown for the execution of Nagis works.
I have broken down the works in tasks and asociated costs for everyones review.
I request that we get the material prices for lodwar if they are any different from the ones i have shown.
In that case make changes on the excell document and circulate to all highlighted in different colour.
I note that we need to mobilise the works as the date promised was 16th June 2014.
In my very considered view this work can be completed in very good time if we join hands.
As of now, mobilisation money has not hit the account. Immeaditely we get it we shall notify you.
My suggestion is we get feedback from all copied by this mail today on the way forward.
Over to you guys.
Regards
Eng Kiarie
dear david
thank you for the detail activity breakdown however i have noted that there is difference on the labour charges for activity C & D ie the labour charge for activity C is 50,500 while D which has the same team as indicated on the schedule is 59,500.
Another issue is to why is activity G and H no cost is provided for with regard to them .
regards
Paul
Item ACTIVITY LOCATION QUANTITY RATE AMOUNT COMMENT NET RETURN PRIORITY
A EXCAVATION This is labour based task.
( Cubic Metre) Intake works 120 Employ a team of say 15 casuals for Lining Main canal 315 one week. Division boxes 20.4 Engage two fundis to work with the casuals 1 Road crossing 10.5 All these to be under experienced River bank protection 48 supervisor. Secondary canal 195 Cost: ( 15x400x10)+(2x800x10)+(1x2500x10) 708.9 300 212,670.00 101,000.00 111,670.00 B HARDCORE ( Cubic Metre) Intake works 6.5 An important task to follow the excavation Lining main canal 157 works. Division boxes 5 We require a total of 20 lorries of 10 cubic Road crossings 4.5 metre each for all the works including 2 173 6500 1,124,500.00 lining floor, gabions etc. Material Cost: 20 lorries x 14,000 = 280,000 Labour cost: 10 days as above = 101,000 743,500.00 C BLINDING ( Cubic Metre) Intake works 2 This work involves cement, sand and ballast. Lining main canal 78 However, in my view this quantity was on Division boxes 1 a higher side. The actual volume will be 50% Road crossings 1 of stated 82cm. Calculation based on 82cm. 82 15800 1,295,600.00 Cement- 280bags @1,200/- =336,000 3 Sand - 8 lorries @ 32,000/- = 256,000 Ballast - 8 lorries @ 32,000/- = 256,000 labour - Same team for 5 days = 50,500 397,100.00 D Mass Concrete ( Cubic Metre) Intake works 7 The works involves cement, sand and ballast. Lining Main canal 78 We must ensure that the quality of this Division boxes 3 exercise is not compromised. Road crossings 2.2 Cement- 500 bags @ 1,200/- = 550,000 5 90.2 18000 1,623,600.00 sand- 9 Lorries @ 32,000 = 288,000 Ballast - 9 lorries @ 32,000 = 288,000 Labour - Same team for 5 days = 59,000 438,600.00 E PLASTER ( Square Metre) Intake works 72 Lining main canals 456 Labour for 5 days = 50,500/- 178,020.00 8 Division boxes 36 Road crossings 18.55 582.55 400 233,020.00 F STONES ( Square Metre) Intake works 53 Stones - 8,300ft @ 45/- =382,500 Lining main canal 480 Sand 533 2000 1,066,000.00 cement 150 bags @1,200 = 180,000 334,000.00 6 Labour; Chiselling: 5 fundis@10 daysx 1,000 Labour; Construction: 10 fundis@10 daysx1,200 G SCREEDING Lining main canal 29 5000 145,000.00 H RIP RAP LINING Division boxes 12 4500 54,000.00 I HARDWARE ITEMS Twisted bars -R6 22 200 4,400.00 R6- 5No @ 220/- = 1,100 3,300.00 5 Twisted bars -Y10 138 500 69,000.00 Y10 - 20No @ 635/- = 12,700 56,300.00 5 Twisted bars - Y8 25 200 5,000.00 Y8 - 6No@ 430/- = 2,580 2,420.00 5 Binding wires roll of 25kg 1 220 5,500.00 1 roll of 25kg @ 2,700/- = 2,700 2,800.00 5 BRC A142 16 11000 176,000.00 16 roll @ 17,000/- = 272,000 (96,000.00) 5 Mild steel 4mm weld mesh 8 270 2,160.00 8no shhets @ 1,300/- = 10,400 8,240.00 5 Angle line- 75x75x6mm 170 1010 1,378,650.00 170No @ 4,400 = 748,000 630,650.00 4 Barbed wire- 610m roll 0 23 roll of 610m length @ 4,550/- = 104,650 (104,650.00) 4 Gabion boxes 56 10000 560,000.00 56 no @5,500/- = 308,000 252,000.00 J FABRICATION 6mm thick metal gate 2 45000 90,000.00 45,000.00 45,000.00 7 Steel gates, 200x 400x4mm 8 10000 80,000.00 32,000.00 48,000.00 7 Steel gates, 500x 550x4mm 2 15000 30,000.00 12,000.00 18,000.00 7 K FENCING WORKS Labour items 20,000.00 (25,000.00) 4 timber, nails, hammers, spades, mattocks L Miscelleneous Construction of site house 150,000.00 (200,000.00) 1 Food, wheel barrors, water