PHASE 1B PSR-1 REJUVENATION PROJECT -

PROVISION OF TECHNICAL WORK SCOPING


AND ENGINEERING SERVICES

Contract No. PTSSB/TC1/TSA/003
Work Order No. PMES-WO-009

PROJECT NAME : PHASE 1B PSR-1 REJUVENATION PROJECT
DOCUMENT TITLE : SCOPE OF WORK FOR PROVISION OF REPLACEMENT
OF DISPLACER LEVEL TRANSMITTERS TO GUIDED
WAVE RADAR LEVELTRANSMITERS
DOCUMENT NO. : PSR1RJV-IN-SOW-0004
PACKAGE NO. : 31





REV
CODE
ISSUE DATE
DOC
STATUS
TPC
PTSSB ACCEPTANCE
AUTHOR CHECKER APPROVER
NAME NAME NAME NAME DATE
A 20-J an-2014 IFR 1 KF Ng
Art Enciso /
YS Cheaw
Uni Krishnan
Kannan
Nor Azlan
B 7-Feb-2014 IFR 2 KF Ng
Art Enciso /
YS Cheaw
Uni Krishnan
Kannan
Nor Azlan
0 17-Feb-2014 AFD Natasha
Art Enciso /
YS Cheaw
Uni Krishnan
Kannan
Nor Azlan

Document Class : B - Confidential ( Should only be shared with staff or contractors who have a need-to-know)
F
o
r

I
n
f
o
r
m
a
t
i
o
n


F. Code
Discipline
Code
Doc Type Doc No.
PSR1RJV IN SOW 0004
Doc. Class : B Confidential
Page 2 of 71

PHASE 1B PSR-1 REJ UVENATION PROJ ECT

TABLE OF CONTENT
EXHIBIT I SCOPE OF WORK
PART A

GENERAL PROJECT INFORMATION
1.0

INTRODUCTION

2.0

DEFINITIONS & ABBREVIATIONS
3.0

GENERAL
PART B

SCOPE OF WORK

1.0

GENERAL SCOPE

2.0

DETAIL SCOPE OF WORK
3.0

HEALTH SAFETY & ENVIRONMENT RULES AND REGULATIONS
4.0

SCHEDULE AND DURATION
5.0

LIAISON WITH OTHER CONTRACTORS
6.0

DESIGN AND ENGINEERING
7.0

PROCUREMENT

8.0

FABRICATION AND CONSTRUCTION
9.0

QUALITY CONTROL AND ASSURANCE
10.0

INSPECTION, TESTING AND COMMISSIONING
11.0

DOCUMENTATION

12.0

WORK COMPLETION AND START-UP
13.0

SPARE PARTS AND SPECIAL TOOLS
14.0

WARRANTY AND DEFECT LIABILITY NOTICE
15.0

COMPANYS SCOPE

16.0 ATTACHMENTS

EXHIBIT II SPECIFICATIONS
PART A PROCEDURES AND REQUIREMENTS
1.0 GENERAL PROCEDURES
2.0 CONTRACTORS OBLIGATION
3.0 INSPECTION OF SITE
PART B STANDARD AND SPECIFICATIONS
1.0 APPLICABLE CODES AND STANDARDS
2.0 EQUIPMENT SPECIFICATIONS AND DATASHEETS
3.0 ENGINEERING SPECIFICATIONS

F
o
r

I
n
f
o
r
m
a
t
i
o
n


F. Code
Discipline
Code
Doc Type Doc No.
PSR1RJV IN SOW 0004
Doc. Class : B Confidential
Page 3 of 71

PHASE 1B PSR-1 REJ UVENATION PROJ ECT
















EXHIBIT I - SCOPE OF WORK
PART A: GENERAL PROJECT INFORMATION







F
o
r

I
n
f
o
r
m
a
t
i
o
n


F. Code
Discipline
Code
Doc Type Doc No.
PSR1RJV IN SOW 0004
Doc. Class : B Confidential
Page 4 of 71

PHASE 1B PSR-1 REJ UVENATION PROJ ECT

1.0 INTRODUCTION


PETRONAS Penapisan (Melaka) Sdn. Bhd, is a wholly owned subsidiary of PETRONAS
[hereinafter to as PP(M)SB] which operates a refinery complex to produce high quality refined
petroleum products which include LPG, Petrochemical Naphtha, Motor Gasoline, Dual Purpose
Kerosene, Diesel, Low Sulphur Waxy Residue, Fuel Oil, Lubricant Base Stocks.

PSR-1 was commissioned in 1994 and would reach its design lifetime by 2014 after twenty (20)
years in operation. PP(M)SB has undertaken Asset Life Study (ALS) to assess the current
condition of the PSR-1 plant and to identify necessary actions to maintain the assets for
continued operation for another 20-25 years.

A Detailed Technical Work Scoping and Engineering Study was conducted to prioritize and
strategically plan in detail all the recommended actions proposed by PSR-1 Asset Life Study.

PSR-1 Rejuvenation Project will be implemented under the following phases:

Phase 1A: FY 2012 FY 2013 (COMPLETED)
Phase 1B: FY 2014 FY 2020

The Scope of Work detailed in this ITB is for the execution for PSR-1 Phase 1B.

The execution will be carried out in plant normal operation i.e. Outside Turn-Around (OSTA)
based on the available window.



F
o
r

I
n
f
o
r
m
a
t
i
o
n


F. Code
Discipline
Code
Doc Type Doc No.
PSR1RJV IN SOW 0004
Doc. Class : B Confidential
Page 5 of 71

PHASE 1B PSR-1 REJ UVENATION PROJ ECT

2.0 DEFINITIONS AND ABBREVIATIONS



2.1 Definitions
The following terms and definitions shall apply throughout the document:
The word shall indicates mandatory requirement
The word should indicates preference

The definitions described herein provide further clarification that will be implemented in this
project to ensure compliance with requirements of this Scope of Work.

Words appearing in capital letters shall have the meaning assigned to them in this Scope of
Work.
No. Terms Definitions
1 COMPANY Means PETRONAS Penapisan (Melaka) Sdn. Bhd. i.e.
PP(M)SB (Company No: 164522-V), a wholly owned
subsidiary company of PETRONAS, which owns and/or
operates the Melaka Refinery Complex located in Mukim
Sungai Udang, Tangga Batu, Melaka comprising of amongst
others the PSR-1, the PSR-2 and the MG3 Plant, and shall
include its successors in title and permitted assigns, and
shall, where the context so admits and requires, also include
its employees, agents or designated representatives.
2 CONTRACT Means the contract entered into between the COMPANY and
the CONTRACTOR for the WORKS in accordance with the
terms and conditions contained herein including all articles,
exhibits and any other documents attached hereto or
incorporated by reference including any subsequent
amendments to them.
3 CONTRACTOR Means Party(ies) entering into this CONTRACT with the
COMPANY for the performance of the WORKS as set forth in
this CONTRACT and includes the CONTRACTORs
personnel, representatives, successors and authorized
parties.
4 EFFECTIVE
DATE
Means [dd/mm/yyyy i.e the date as specified in the Letter of
Award], as further specified in SECTION II, PART A,
ARTICLE 5 CONTRACT DURATION.
5 PROJECT Shall have the similar meaning as per the CONTRACT
Preambles.
6 SITE(S) Means the areas or places as designated by the COMPANY
where the WORKS is to be performed or delivered, as further
specified in EXHIBIT I SCOPE OF WORKS.
7 SUB-
CONTRACTOR
Means Party(ies) including but not limited to supplier, vendor
and/or companies performing construction work(s) that has
or have entered into a contract, directly or indirectly with the
CONTRACTOR, for the performance of any part of the
WORKS.
F
o
r

I
n
f
o
r
m
a
t
i
o
n


F. Code
Discipline
Code
Doc Type Doc No.
PSR1RJV IN SOW 0004
Doc. Class : B Confidential
Page 6 of 71

PHASE 1B PSR-1 REJ UVENATION PROJ ECT





8 WORKS Means the work to be performed and rendered by the
CONTRACTOR or its SUB-CONTRACTOR, as expressly set
forth in this CONTRACT, which is more particularly described
in EXHIBIT I SCOPE OF WORKS and all of
CONTRACTORs and/or its SUB-CONTRACTORs activities
that are reasonably inferable from the description of the said
scope of WORKS, including any other activity which is not
specified in this CONTRACT but which in the course of the
WORKS becomes necessary for completion to be effected.
F
o
r

I
n
f
o
r
m
a
t
i
o
n


F. Code
Discipline
Code
Doc Type Doc No.
PSR1RJV IN SOW 0004
Doc. Class : B Confidential
Page 7 of 71

PHASE 1B PSR-1 REJ UVENATION PROJ ECT

2.2 Abbreviations
2.2.1 General
AESP Authorized Entrant and Standby Person
AFC Approved for Construction
AFD Approved for Design
ALS Asset Life Study
API American Petroleum Institute
BG Bank Guarantee
BOMBA J abatan Bomba dan Penyelamat
BS British Standard
CAD Computer-Aided Design
CCC Contract Closure Certificate
CEP Construction Execution Plan
DCS Distributed Control System
DOE Department of Environment
DOSH Department of Occupational Safety and Health
EPCC Engineering, Procurement, Construction & Commissioning
ESD Emergency Shutdown System
FAT Factory Acceptance Test
FOB Free On Board
GWR Guided Wave Radar
HSES Health, Safety, Environment and Security
IEC International Electrotechnical Commission
I.S. Intrinsic Safety
ITP Inspection and Test Plan
J B J unction Box
J KDM J abatan Kastam Diraja Malaysia
J MS J ob Method Statement
J SA J ob Safety Analysis
MBMB Majlis Bandaraya Melaka Bersejarah
MCB Main Control Building
MWCC Mechanical Work Completion Certificate
MIDA Malaysian Investment Development Authority
NDT Non-Destructive Test
NIOSH National Institute Occupational Safety and Health
OSTA Outside Turn Around
P&ID Piping and Instrumentation Diagram
PLC Programmable Logic Controller
PPE Personal Protective Equipment
F
o
r

I
n
f
o
r
m
a
t
i
o
n


F. Code
Discipline
Code
Doc Type Doc No.
PSR1RJV IN SOW 0004
Doc. Class : B Confidential
Page 8 of 71

PHASE 1B PSR-1 REJ UVENATION PROJ ECT

PTS PETRONAS Technical Standards


QA Quality Assurance
QC Quality Control
RFSU Ready For Start-Up
SAT Site Acceptance Test
SD Shutdown
SHO Safety & Health Officer
SPD Surge Protection Device
SPIR Spare Parts and Interchangeability Record
ST Suruhanjaya Tenaga
TA Turn Around
TPIA Third Party Inspection Agency
VDRL Vendor Data Requirement List
WCC Work Completion Certificate



F
o
r

I
n
f
o
r
m
a
t
i
o
n


F. Code
Discipline
Code
Doc Type Doc No.
PSR1RJV IN SOW 0004
Doc. Class : B Confidential
Page 9 of 71

PHASE 1B PSR-1 REJ UVENATION PROJ ECT

3.0 GENERAL
3.1 This Contract calls for Lump Sum basis for the provision of design, engineering, manufacturing,
material procurement, fabrication, documentation, inspection, delivery, decommissioning,
demolition, disposal, installation, termination, testing and commissioning for replacement of
Displacer Level Transmitters to Guided Wave Radar Level Transmitters for PSR-1 Rejuvenation
Project Phase 1B.
3.2 CONTRACTOR shall be required to execute the rejuvenation works on the above items 3.1 in
order to meet COMPANYs target objectives i.e. to maintain the assets for continued operation
for another 20-25 years.
3.3 This document along with all attachments, codes, standards, etc. is for PSR-1 Rejuvenation
Project Phase 1B. The WORKS are to be performed during plant Outside Turn-Around (OSTA)
period in year 2015 and 2016.


F
o
r

I
n
f
o
r
m
a
t
i
o
n


F. Code
Discipline
Code
Doc Type Doc No.
PSR1RJV IN SOW 0004
Doc. Class : B Confidential
Page 10 of 71

PHASE 1B PSR-1 REJ UVENATION PROJ ECT


















EXHIBIT I - SCOPE OF WORK
PART B: SCOPE OF WORK





F
o
r

I
n
f
o
r
m
a
t
i
o
n


F. Code
Discipline
Code
Doc Type Doc No.
PSR1RJV IN SOW 0004
Doc. Class : B Confidential
Page 11 of 71

PHASE 1B PSR-1 REJ UVENATION PROJ ECT

1.0 GENERAL SCOPE



CONTRACTORs general scope of works shall include but not limited to the following:
1.1 CONTRACTOR shall perform the WORKS in accordance to the applicable PTS, International
codes, the governing codes, industry best practices and in compliance with the Malaysian
regulations in force.
1.2 CONTRACTOR shall provide all safety items for his workers and follow the safety rules of
COMPANY.
1.3 CONTRACTOR shall provide management, supervision, manpower, materials, machinery,
equipment, tools, consumables, transportation and all necessary resources for satisfactory
completion of the WORKS.
1.4 CONTRACTOR shall submit project history record of similar nature in Oil and Gas industry.
1.5 The CONTRACTOR shall develop the project organization chart for the purpose of this contract.
1.6 CONTRACTOR shall maintain strict quality procedures in accordance to PTS to ensure
compliance to codes, specifications, drawings and instruction issued by COMPANY during
installation process.
1.7 CONTRACTOR shall practice good housekeeping at all times during the execution of the
WORKS.
1.8 CONTRACTOR shall procure all materials required for the completion of the WORKS. The
procurement function shall include issuing of purchase orders, expediting delivery, performing
the necessary inspection and test to ensure quality and quantity, shipping, unloading, custom
clearance and transportation to the work SITE.
1.9 CONTRACTOR shall familiarize themselves thoroughly with all the reference drawings and
documents for assessment of all works that need to be carried out in this project.
1.10 CONTRACTOR shall perform site visits and thoroughly inspect the SITE with COMPANYs
engineer to discuss and decide upon the modification works and other requirements before
submission of their quote.
1.11 CONTRACTOR shall submit site visit checklist to COMPANY for information/review before visit.
During site visit, CONTRACTOR shall identify the detail modifications required for the
replacement work.



F
o
r

I
n
f
o
r
m
a
t
i
o
n


F. Code
Discipline
Code
Doc Type Doc No.
PSR1RJV IN SOW 0004
Doc. Class : B Confidential
Page 12 of 71

PHASE 1B PSR-1 REJ UVENATION PROJ ECT

1.12 CONTRACTOR shall check and ensure that the material is suitable and adequate for the
WORKS. CONTRACTOR shall notify COMPANY of any discrepancy found in package and to
obtain interpretation and/or description from COMPANY on discrepancies prior to
commencement of WORKS.
1.13 CONTRACTOR shall confirm the feasibility of implementation include the availability of spaces
and areas for the purpose of the WORKS. Any space constraint, discrepancy, error and
omission in the WORKS details shall be notified to COMPANY for resolution prior to
commencement of WORKS.
1.14 CONTRACTOR shall perform site verification to the existing facilities and installation prior to
commencement of WORKS. In no case shall the WORKS be subjected to any future variation,
resulting from failure of CONTRACTOR to verify the services.
1.15 CONTRACTOR shall be responsible for vendor drawing submission, installation procedures,
QA/QC program, detail work plan/schedule, monitoring, progress reporting, manpower loading
and all other necessary procedures and documents which shall include project co-ordination
procedure as stipulated in this Scope of Work.
1.16 CONTRACTOR shall coordinate, expedite and resolve any problem that arises in providing
materials and services in compliance to COMPANY requirement.
1.17 CONTRACTOR shall furnish all documents for COMPANY approval prior to executing emergent
work for verification purpose.
1.18 CONTRACTOR shall update all the related drawings to SITE As-Built drawings.
1.19 CONTRACTOR shall conduct site verification to confirm the constructability of the proposed
facilities and to identify any form of obstruction that may be encountered during construction.
Any space constraint, discrepancies, error or omission between the drawings and actual SITE
condition shall be brought to the attention of COMPANY for resolution prior to pre-fabrication
and installation works. All additional work due to overlooked discrepancies shall be borne by the
CONTRACTOR.
1.20 CONTRACTOR shall supply complete materials, labour, tools, equipment, etc. and all
necessary items required to carry out surveying, fabrication, inspection, transportation,
construction and installation of the WORKS.
1.21 All works shall strictly follow the AFD / AFC drawings supplied by COMPANY. Any deviations
from the AFD / AFC drawings shall be notified to COMPANY at least three (3) days prior to
executing the WORKS. CONTRACTOR shall obtain COMPANYs approval prior to execution of
the deviations.
1.22 CONTRACTOR shall perform the WORKS as specified in this document and also in accordance
with the mark-up drawings specifically marked in ATTACHMENT-4.
F
o
r

I
n
f
o
r
m
a
t
i
o
n


F. Code
Discipline
Code
Doc Type Doc No.
PSR1RJV IN SOW 0004
Doc. Class : B Confidential
Page 13 of 71

PHASE 1B PSR-1 REJ UVENATION PROJ ECT

1.23 CONTRACTOR shall ensure all waste inclusive but not limiting to scrapped material, tools etc.
were completely removed upon completion of the installation works.
1.24 CONTRACTOR shall perform all site installation works as required and as shown in the relevant
drawings. To minimize fieldworks, all materials are pre-fabricated at factory.
1.25 Where scaffolding is required for the installation work at SITE, only tubular scaffolding
(complying with BS standard) shall be allowed to be used inside COMPANY plant. Only
qualified and DOSH certified scaffolding supervisor is allowed to supervise the scaffolding
installation. All scaffolding shall be in accordance with COMPANY requirements and must be
inspected and approved by COMPANY scaffolding inspector. All scaffolding workers and
helpers shall attend a scaffolding induction session in COMPANY.
1.26 The use of safety harness shall be mandatory for working at elevated position, including during
erection of scaffolding. Safety Belt shall not be used.
1.27 CONTRACTOR shall provide sufficient vehicle to ensure efficient worker mobilization to site
location. The vehicles provided shall meet the COMPANY requirements.
1.28 CONTRACTOR shall bear any cost of temporary removal and re-installation of any structure
foreseen obstruction during execution of the WORKS.
1.29 CONTRACTOR shall repair, reconstruct, reinstate and make good any damaged facilities due to
execution of the WORKS to the satisfaction of COMPANY.
1.30 All materials supplied shall be original and unused, accompanied by relevant manufacturer
document such as mill certificate, test certificate, etc. Without those documents, COMPANY
has all the right to reject such materials.
1.31 CONTRACTOR shall submit a weekly work progress report to COMPANY indicating the
percentage of work completed, portion of work currently in progress and highlighting any
constraints that may exist with mitigation plan.
1.32 The replacement work shall be carried out during OSTA in year 2015 and 2016.

F
o
r

I
n
f
o
r
m
a
t
i
o
n


F. Code
Discipline
Code
Doc Type Doc No.
PSR1RJV IN SOW 0004
Doc. Class : B Confidential
Page 14 of 71

PHASE 1B PSR-1 REJ UVENATION PROJ ECT

2.0 DETAIL SCOPE OF WORK


2.1 CONTRACTOR shall be responsible, but not limited to, the design, material, engineering,
procurement, manufacture, supply, fabrication, installation, supervision, inspection, testing,
commissioning, decommissioning, demolition, disposal, project management and documentation
for the replacement of existing Displacer level transmitters to Guided Wave Radar level
transmitters. The WORKS shall be in strict accordance with this specifications, attachments, PTS
and applicable codes and standards.
2.2 CONTRACTORs scope shall include but not limited to the following:-
i) CONTRACTOR shall supply, design, engineer, install, deliver, test and commission sixty
six (66) sets of Guided Wave Radar level transmitters to replace existing Displacer level
transmitters at PSR-1 complete with all required accessories, pipe or tubing & fittings
associated with the transmitters. Refer to ATTACHMENT- 5 for Tag Number List.
ii) CONTRACTOR shall dismantle existing Displacer Level transmitters and install the
Guided Wave Radar level transmitters complete with associated accessories i.e.
Chamber, vent/drain connections, termination cables etc. up to commissioning.
iii) CONTRACTOR shall return the transmitters electronic together with the displacer to
COMPANY for safe keeping. However, for the chamber shall be disposed to designated
area defined by COMPANY.
iv) CONTRACTOR shall perform site visit to confirm the existing cable length sufficiency for
the connection of Guided Wave Radar level transmitters. CONTRACTOR shall supply and
install intermediate junction box and cable (refer to PTS 32.37.20.10 Section 3.5) if
existing cable lengths are found not adequate during detailed engineering design. Cable
splicing is prohibited.
v) CONTRACTOR shall ensure all materials and equipment shall meet the process design
and environmental conditions as per the existing requirement and shall be new, free of
defects and of the quality as specified herein.
vi) CONTRACTOR shall verify the existing SPD and barrier suitability to drive the required
power to the transmitters. CONTRACTOR shall propose and supply new suitable barrier if
the existing barriers deemed not suitable. CONTRACTOR shall obtain COMPANYs
approval on the barriers model and make prior to supply. COMPANY only accepts MTL or
P&F make for barriers.
vii) CONTRACTOR shall provide a transmitter remote mounted local indicator for area where
no accessible platform for operation and maintenance personnel is available.
viii) CONTRACTOR shall ensure the new chamber provided with level measurement reference
marking. The marking shall permanently show 0%, 25%, 50%, 75% and 100% of level
measurement. CONTRACTOR is to propose the marking material for COMPANYs
approval.
ix) CONTRACTOR shall submit the required Bill of Materials for the replacement WORKS.
F
o
r

I
n
f
o
r
m
a
t
i
o
n


F. Code
Discipline
Code
Doc Type Doc No.
PSR1RJV IN SOW 0004
Doc. Class : B Confidential
Page 15 of 71

PHASE 1B PSR-1 REJ UVENATION PROJ ECT

x) CONTRACTOR shall provide experienced Project Engineer for the WORKS who shall be
responsible for providing technical guidance, direction and installation during execution of
the PROJ ECT.
xi) CONTRACTOR shall provide sufficient manpower during site execution to ensure that the
WORKS can be completed within specified windows in year 2015 and 2016.
xii) CONTRACTOR shall provide Factory Acceptance Test (FAT) and Site Acceptance Test
(SAT) procedure for COMPANYs approval.
xiii) CONTRACTOR shall provide a GWR specialist to be part of the commissioning team.
xiv) Any conflicts or differences arising from any omission, error, or misinterpretation by
CONTRACTOR shall be rectified by CONTRACTOR in a timely manner, at no cost to
COMPANY.
xv) CONTRACTOR shall provide the final and As-Built detailed drawings/documents,
calculations, operating manual and maintenance manual approved by COMPANY for
information and records as per the VDRL.
xvi) CONTRACTOR shall ensure the maintainability criteria, maintenance philosophy and
spares requirements are fully considered in the development of the detailed design.
xvii) CONTRACTOR shall conduct physical and technical surveys to verify all connections to
existing facilities are correct.
xviii) CONTRACTOR shall comply with latest revision of PTS and all the existing Project
Specification, as applicable.
xix) CONTRACTOR shall be responsible to ensure that all instrumentations are working
properly.
xx) CONTRACTOR shall prepare detail design WORKS package which consist of but not
limited to:
Main specification for design, fabrication, supply, installation testing and
commissioning
Instrument Index with Tagging Numbers.
Wiring Termination Details
Loop Drawing
Hook-up drawings
General Arrangement Drawing
Specification for Guided Wave Radar level transmitters and accessories.
Test Certification And Material with Inspection (i.e. Mill, NDT, etc.)
Inspection and Test Plan (ITP)
FAT / SAT Procedure / Report
F
o
r

I
n
f
o
r
m
a
t
i
o
n


F. Code
Discipline
Code
Doc Type Doc No.
PSR1RJV IN SOW 0004
Doc. Class : B Confidential
Page 16 of 71

PHASE 1B PSR-1 REJ UVENATION PROJ ECT

Grounding / Nameplate / Tagging Details


Installation, Modification and Demolition Drawings/Documents
Consolidated Bill of Materials
Other Associated Document/Drawings (Warranty, Certification and etc.)
Master Deliverable List
xxi) CONTRACTOR shall be responsible for the cabling (if any) and termination for Guided
Wave Radar level transmitters.
xxii) CONTRACTOR shall prepare all installation and demolition drawings required for
installation and removal work respectively.
xxiii) CONTRACTOR shall prepare detail schedule for pre-installation, installation and post-
installation activities and submit to COMPANY for approval.
xxiv) CONTRACTOR shall be responsible to provide new documentation or update related As-
Built drawings and documents for the WORKS.
xxv) CONTRACTOR shall be responsible to set up a proper project organization consisting of
all necessary manpower and shall be approved by COMPANY.
xxvi) A work progress report shall be submitted to COMPANY on monthly basis during the
engineering stage and on daily basis during execution stage, indicating the percentage of
work completed, portion of work currently in progress and highlighting any constraints that
may exist.
xxvii) The CONTRACTOR project management responsibilities shall include but not limited to:
Interfacing with COMPANY and COMPANYs other contractors working at SITE.
Co-ordination of the design, engineering, manufacturing, assembly, testing and
delivery of the equipment.
Progress control, including co-ordination of progress control meetings, progress
reporting, catch-up plan (if required) and critical path monitoring.
Quality Control.
2.3 Specific Equipment Requirement:
2.3.1 The Guided Radar level transmitters and its associate components shall be off-the-shelve with
proven track records. CONTRACTOR shall submit project history record of supply and
installation in PETRONAS subsidiaries and other Oil and Gas industries.
2.3.2 The transmitters features and functions shall include but not limited to the following :
F
o
r

I
n
f
o
r
m
a
t
i
o
n


F. Code
Discipline
Code
Doc Type Doc No.
PSR1RJV IN SOW 0004
Doc. Class : B Confidential
Page 17 of 71

PHASE 1B PSR-1 REJ UVENATION PROJ ECT

i) All transmitters shall be SIL2 certified per IEC 61508, as minimum.


ii) All transmitters shall be equipped with integral LCD with user configurable engineering
units
iii) The transmitter shall be 2-wire with 4-20 mA signals with HART and shall be capable to
interface with HART Handheld Communicator.
iv) Cable entry to each transmitter shall be provided with Ex certified conduit suitable for
bottom entry.
v) All transmitters shall be provided with weather shield.
vi) The housing material for the transmitter shall be aluminum (standard).
vii) The transmitter shall be painted and coated as per manufacturer standard. However, for
safeguarding transmitters housing shall be Red in colour.
viii) Accuracy of the overall level instrument shall be +/-10mm or better.
ix) Ingress Protection of the transmitter shall be to IP65 of IEC 60529 as a minimum.
x) The power supply for the transmitter shall be loop powered from 4-20mA signal.
xi) Tubing and fittings supplied shall be suitable for the process design conditions and shall
be 316 Stainless Steel as minimum of Swagelok make, with imperial size.
xii) The chamber material, process connection and rating shall be as per existing Displacer
level transmitter specification. CONTRACTOR to verify GWR suitability for new chamber
for COMPANY approval.
xiii) Transmitter shall not be affected by radio frequency interference such as Walkie-Talkie,
wireless paging system and other power and communication equipment. Transmitters
should have built-in filters for immunity to RFI / EMI (as per IEC 61000 and PTS
33.64.10.33).
xiv) Transmitter shall be equipped with SPD.
2.3.3 The preferred manufacturer for Guided Radar Level Transmitter is Emerson or Endress +
Hauser.
2.3.4 CONTRACTOR shall re-design new chamber process connection, if necessary. The re-design
process connection shall be submitted to the COMPANY for approval.
2.3.5 CONTRACTOR shall ensure internal surface of the chamber is smooth during manufacturing to
ensure no signal interruption. CONTRACTOR to provide technical data to prove the smoothness
of the chamber for COMPANYs review.
2.3.6 CONTRACTOR shall modify (if required) existing connections and drain point in order for
successful installation and commission of the transmitters.
2.3.7 The Guided Wave Radar level transmitter shall be labelled with the following information:
Name and address of manufacturer
Manufactured date
Model and serial number
2.3.8 As a minimum, the Guided Wave Radar level transmitter assembly shall be EExib certified,
F
o
r

I
n
f
o
r
m
a
t
i
o
n


F. Code
Discipline
Code
Doc Type Doc No.
PSR1RJV IN SOW 0004
Doc. Class : B Confidential
Page 18 of 71

PHASE 1B PSR-1 REJ UVENATION PROJ ECT

suitable for hazardous area classification for respective level instrument location, by an
authorized certifying authority (ATEX or equal).
2.3.9 Permanent nameplates or labels shall be provided to identify the individual equipment
assemblies. In addition, labels should be provided as appropriate to convey operating
instructions, warning plates, rating data and other general information.
2.3.10 Name, identification, instruction and warning plates and their fixing materials shall be of durable,
corrosion resistant material (stainless steel). They shall be provided with indelible inscriptions in
English language. Plates mounted on the outside of the equipment shall be fixed by means of
durable self-threading screw or pop rivets.
2.3.11 CONTRACTOR shall provide name plate with engraved equipment tag number on a 316SS
plate with 1mm stainless steel wire.
2.3.12 Chamber surface preparation and painting shall be in accordance to PTS 30.48.00.31. The paint
system applied shall provide adequate protection against the adverse effects of the climate
specified.
2.3.13 Provision of commissioning spares and special tools, if required.
2.3.14 All other additional accessories as required shall be under CONTRACTOR scope of supply. (i.e.
steam tracing, insulation, etc.)
2.3.15 CONTRACTOR shall propose detailed WORKS execution plan and numbers of days required
together with manpower loading plan in order to perform the execution, as followings;
Removal, demolition and disposal of existing instrument
Installation of new level instrument
Wiring and termination
Loop check from field instrument up to Control System

2.3.16 CONTRACTOR shall include three (3) training session namely; operation and maintenance
training consist of classroom and site training. The number of the participants for the training per
session shall be 15 personnel. The training shall be conducted in Malaysia by specialist(s) who
must be fully conversant with the offered equipment. Training shall cover basic theory,
equipment construction, operating procedures, maintenance and troubleshooting procedures.
Training material shall be suitable for maintenance personnel.
F
o
r

I
n
f
o
r
m
a
t
i
o
n


F. Code
Discipline
Code
Doc Type Doc No.
PSR1RJV IN SOW 0004
Doc. Class : B Confidential
Page 19 of 71

PHASE 1B PSR-1 REJ UVENATION PROJ ECT

2.4 Preservation, Storage & Transportation


2.4.1 CONTRACTOR shall be responsible for the correct coordination before delivering to SITE. Any
cost related to Preservation, Storage and Transportation until site installation shall be borne by
the CONTRACTOR.
2.4.2 It shall be ensured that during transport, storage, and installation, cable ends are suitably sealed
to avoid ingress of water.
2.4.3 All Handling / Shipping & Delivery to SITE including All Risk Transit Insurance shall be included
under CONTRACTORs scope of supply.
2.5 Exception to Requirements
CONTRACTOR is responsible for meeting all the requirements described in this document.
Only exceptions specifically agreed and authorized by COMPANY in writing shall be considered
accepted and valid.

3.0 HEALTH SAFETY & ENVIRONMENT RULES AND REGULATIONS
3.1 General
3.1.1 CONTRACTOR shall provide comprehensive HSES Plan to perform the WORKS in accordance
to the requirement of COMPANYs HSEMS and HSES Plan which is detailed in Section II
Exhibit V. The HSES Plan is to be submitted to COMPANY for review and approval prior to
commencement of WORKS at site. As a minimum, the HSES Plan shall include the following:

i. Organizational structure for HSE management showing clear reporting, communication
and interfacing with COMPANY HSES Representative.
ii. Identify required supervisory positions according to the job risk; for site HSES
surveillance
iii. A schedule of regular meetings to discuss HSE interface matters
iv. CriteriaforselectionofSUBCONTRACTOR(S)includingHSESperformance
v. Strategies/plantoensureSUBCONTRACTORStomeetCOMPANYsHSESstandard
vi. Implementation of PPE program, HSE program (including audit) for this contract scope
(includingspotchecks,inventory)
vii. Environmental Management Plan which include but not limited to environmental
management system, resources (organization), waste, wastewater and hazardous waste
management plan.
viii. Environmental hazards associated with operations including system(s) to be applied to
controlthesehazards
F
o
r

I
n
f
o
r
m
a
t
i
o
n


F. Code
Discipline
Code
Doc Type Doc No.
PSR1RJV IN SOW 0004
Doc. Class : B Confidential
Page 20 of 71

PHASE 1B PSR-1 REJ UVENATION PROJ ECT

ix. All equipment, tools and materials for the contract scope activity are correctly certified,
registered, controlled and maintained in a safe working condition.

3.1.2 Requirement for Safety Officer shall be identified based on Scope of Work and if there is a
requirement to have a Safety Officer, Safety Officer shall have a valid registration with DOSH.

3.1.3 All CONTRACTOR activities shall be supervised by dedicated Safety Supervisors at SITE
throughout the duration of the WORKS.

3.1.4 CONTRACTOR shall comply and prepare Mandatory Control Frame (MCF) checklist and
submit to COMPANY for approval. Sample of MCF checklist as per Section II Exhibit V.

3.1.5 All manpower involved in the WORKS shall be required to undergo baseline Medical
Examination and urine test prior to and after completion of the job and records shall be
submitted to COMPANY doctor for approval. Medical Examination shall be conducted by
qualified COMPANY panel doctors.

3.1.6 CONTRACTOR shall adhere to COMPANY HSES Rules and Regulations at all times as per
Section II Exhibit V. Non-compliance to the rules and regulation will cause the Contractors
personnel and the COMPANY to be subjected to disciplinary action.

3.1.7 In addition to safety, CONTRACTOR personnel shall abide to any security rules and other
special /in- house rules which may be implemented and issued by COMPANY from time to time.

3.1.8 All CONTRACTOR personnel shall pass OGSP training by NIOSH before attending mandatory
HSE briefing/training to be organized by COMPANY HSES Department before being allowed to
enter or work inside the Plant premises. CONTRACTOR shall be required to observe the
briefing schedule closely. Request for such briefing shall be forwarded via proper request form
to the COMPANY Representative and HSE Department three (3) working days in advance.
Only personnel who attend HSE Briefing will be provided with Safety Visa to allow entrance
inside the Plant.

3.1.9 All CONTRACTOR personnel who are involved to work inside the confined space area shall
undergo and pass medical examination to ensure their fitness for work. CONTRACTOR shall
provide a copy of the medical certificate as proof for each applicable person prior to Execution
period. Only personnel with NIOSH Certificate of Confined Space (AESP Level 1) will be
allowed to work inside the area. In addition, those working in confined space entry shall also be
familiar and fully trained in handling and using Breathing Apparatus (BA) verified by COMPANY
HSES Department. All cost of NIOSH Certification shall be borne by the CONTRACTOR.


F
o
r

I
n
f
o
r
m
a
t
i
o
n


F. Code
Discipline
Code
Doc Type Doc No.
PSR1RJV IN SOW 0004
Doc. Class : B Confidential
Page 21 of 71

PHASE 1B PSR-1 REJ UVENATION PROJ ECT

3.1.10 CONTRACTOR shall provide the basic Personal Protective Equipment (PPE) for all personnel
which not limited to:

i. Fire Retardant (NOMEX IIIA) coveralls
ii. TYVEX or chemical suits
iii. Safety helmet (hard-hat)
iv. Working gloves
v. Safety shoes (steel toe required)
vi. Eye protection (safety glasses or goggles suitable for job)
vii. Full body safety harnesses for working at height with double layard
viii. Breathing apparatus (include back-up units) if require based on job requirement
ix. Full face/half face respirator come with approved type of cartridge for working in confine
space.
x. Dust mask
xi. Escape respirators (to be approved by COMPANY prior to use)
xii. Portable (10 minutes) emergency escape set for blasting job.
xiii. Vests for standby person and fire watcher
3.1.11 All PPE supplied shall meet standard for use in the refinery as defined and approved by the
COMPANY HSE Department.

3.1.12 CONTRACTOR shall to equip its personnel with H2S Escape Respirators to be used during the
execution of WORKS at plant SITE. CONTRACTOR shall equip its Safety Officer and Work
Supervisor with H2S Gas Badges. CONTRACTORs Safety Officer shall be the focal person for
weekly calibration of the gas badges and report to COMPANYs Safety Representative.

3.1.13 CONTRACTOR shall ensure that all the machinery working at COMPANY premises shall be in
good working condition complete with safety devices such as spark arrester, reverse
alarm, fire extinguisher, etc.

3.1.14 CONTRACTOR shall provide detail work schedule and work procedure complete with J ob
Safety Analysis (J SA) to COMPANY for review and approval during planning stage. The details
of work procedure complete with J SA for each item mentioned in the Scope of Work shall be
submitted 4 weeks prior to start of work. CONTRACTOR shall comply all with J SA findings at no
additional cost to COMPANY.

F
o
r

I
n
f
o
r
m
a
t
i
o
n


F. Code
Discipline
Code
Doc Type Doc No.
PSR1RJV IN SOW 0004
Doc. Class : B Confidential
Page 22 of 71

PHASE 1B PSR-1 REJ UVENATION PROJ ECT

3.1.15 CONTRACTOR shall ensure that all electrical equipment and vehicles have been inspected and
approved by COMPANY prior to use for the work. CONTRACTOR shall comply with COMPANY
Portable Electrical Equipment and Temporary Electrical Installation (PETI) Standard.

3.1.16 CONTRACTOR shall comply with all PTW requirements and shall commence work after
authorization from COMPANY via Permit to Work (PTW) system.

3.1.17 CONTRACTOR shall produce a Safety Performance Report which consists of Contractor Safety
Management Program, Weekly Contractor Performance Report and Contractor Safety
Performance Report. The safety performance report shall be submitted together with the
Execution Report at the conclusion of the WORKS.

3.1.18 CONTRACTOR shall provide standby boat (including qualified and valid helmsman) as per
safety requirement for working at J etty (above water level).

3.2 Requirement of Scaffolding are as follows:
3.2.1 All works not accessible more than 2 meter from ground level or from elevator platform require
proper scaffolding.
3.2.2 Scaffolding shall be provided with safe means of access and it shall be provided with hoist arms
or block/tackle for hoisting material or tools when necessary.
3.2.3 Frame type scaffolding are not allowed to be used in COMPANY. All scaffolding material shall
be confirmed to BS 1139 and approved by DOSH. Wooden platform are not allowed to be used
unless with approval from Area Manager.
3.2.4 All scaffolding shall be inspected and tagged with an approved scaffold tag by competent
person before used and re-inspected at weekly intervals during use.
3.2.5 All scaffolds shall be tagged with approved scaffold tag to indicate that they are safe for use.
Scaffolding without scaffold tag will not be allowed to be used.
3.2.6 Any scaffold which is modified due to removal of equipment shall be re-inspected and tagged
with scaffold tag before reuse.
F
o
r

I
n
f
o
r
m
a
t
i
o
n


F. Code
Discipline
Code
Doc Type Doc No.
PSR1RJV IN SOW 0004
Doc. Class : B Confidential
Page 23 of 71

PHASE 1B PSR-1 REJ UVENATION PROJ ECT

3.2.7 Any scaffold not safe for use shall be labelled with a Not Safe To Use or they are
INCOMPLETE AND NOT SAFE TO USE.
3.3 Effluent and Emissions
3.3.1 CONTRACTOR shall comply with requirement of local regulations on disposal of all waste
during construction.
3.3.2 CONTRACTOR shall control and minimize dust emissions during construction using damping
down, wind barriers and other measures as appropriate.
3.3.3 CONTRACTOR shall ensure that the use of asbestos in any form, including gaskets, insulation
and fireproofing materials is not permitted in the project.
3.4 Noi se
3.4.1 CONTRACTOR shall exercise noise reduction rather than noise control policy to meet the noise
emissions criteria in the project equipment and construction machinery selection. Noise control
shall only be considered to ensure compliance of noise emissions criteria after all effort on noise
reduction had been exercised.
3.4.2 CONTRACTOR shall note the particular requirement for limiting the noise contribution from the
project. CONTRACTOR shall ensure current noise level in the plant and at the perimeter fence
will not be increased. CONTRACTOR shall note the requirement to specify proposed Hearing
Protection Area.

F
o
r

I
n
f
o
r
m
a
t
i
o
n


F. Code
Discipline
Code
Doc Type Doc No.
PSR1RJV IN SOW 0004
Doc. Class : B Confidential
Page 24 of 71

PHASE 1B PSR-1 REJ UVENATION PROJ ECT

3.5 Environmental Protecti on


3.5.1 CONTRACTOR shall protect all existing vegetation surrounding the WORKS, from the effects of
its own and its SUB-CONTRACTORs construction operations.
3.5.2 CONTRACTOR shall follow all Malaysian Environmental Regulation to abate and avoid noise
production and air, water and soil pollution during the execution of the construction WORKS.
3.5.3 CONTRACTOR shall not use asbestos products or product containing asbestos.
3.5.4 CONTRACTOR shall make necessary arrangements for disposal of waste material during
construction. The arrangement shall meet the requirements of the local authorities.
3.5.5 CONTRACTOR shall comply with the latest DOSH requirement for any blasting activities using
GMA Garnet blasting media. All blasting works shall be performed by DOSH approved
CONTRACTOR.

3.6 Disposal of Construction Waste
3.6.1 CONTRACTOR shall adhere to all Authorities laws and regulations in performing the disposal
activities.
3.6.2 CONTRACTOR shall monitor and record all movement of the Disposal activities and shall
submit the record to COMPANY upon request.
3.6.3 CONTRACTOR shall segregate and dispose metal and non-metal waste into two
separate containers with proper labelling.
3.6.4 CONTRACTOR shall segregate the Scheduled-Waste and Non-Scheduled Waste and to
transport the waste to a designated area in plant which to be identified by COMPANY.
3.6.5 Any waste contaminated with chemical, oil, etc. (scheduled waste) such as filter elements,
containers, etc., shall be disposed-off as Scheduled waste.
3.6.6 CONTRACTOR shall bear all costs, including royalties, imposed by local authorities for dumping
of domestic waste.
3.7 House Keeping and Site Cleaning
3.7.1 CONTRACTOR shall ensure its personnel maintain a high standard of safety and hygiene while
working at the work SITE. Rest shelters, and site cabins shall always be kept tidy and
comfortable for the workers.
3.7.2 At the conclusion of the Execution of work, COMPANY will arrange for a series of joint
housekeeping exercise between all CONTRACTOR to perform the overall housekeeping. This
housekeeping exercise shall be repeated until COMPANY is satisfied with the condition of the
plant.
F
o
r

I
n
f
o
r
m
a
t
i
o
n


F. Code
Discipline
Code
Doc Type Doc No.
PSR1RJV IN SOW 0004
Doc. Class : B Confidential
Page 25 of 71

PHASE 1B PSR-1 REJ UVENATION PROJ ECT

3.7.3 CONTRACTOR shall maintain good housekeeping throughout the duration of the WORKS.
COMPANY shall stop all on-going work if necessary to facilitate the total housekeeping work.
3.7.4 CONTRACTOR shall ensure that all machinery including cables for welding machines, power
tools, lighting etc. are grouped and laid out in a neat and orderly arrangement throughout the
WORKS.
3.7.5 CONTRACTOR shall dismantle and remove all temporary wiring, plumbing, etc. and shall
dispose-off all waste and scrapped to locations agreed by COMPANY, leaving the SITE in a
clean and orderly condition to the satisfaction of COMPANY and local authorities, if applicable.
4.0 SCHEDULE AND DURATION
4.1 The WORKS is scheduled to be completed within nine (9) months from EFFECTIVE DATE
which is the Contract Award Date.
4.2 All WORKS shall be executed on 12-Hour basis during OSTA window.
4.3 CONTRACTOR shall conduct an Interactive Planning Workshop for the Critical Path activities.
CONTRACTOR is to make provision for COMPANY to attend this workshop.
4.4 CONTRACTOR shall submit Level 2 Project Schedule within thirty (30) days after the
EFFECTIVE DATE and Level 3 Project Schedule with forty-five (45) days of EFFECTIVE DATE
with Critical Path Method (CPM). The Project Schedule submitted by CONTRACTOR shall
comply with CONTRACTORs Proposal Bid Submission and / or as agreed during the Techno-
Commercial Meeting.
4.5 Primavera P6, MS Project or equivalent as deemed acceptable to COMPANY during the
CONTRACTORs bid submission shall be used for the Schedule.
4.6 The schedule minimum shall include all activities and assigned resources (all the phases e.g.
planning and execution) as follow:
i. Kick off Meeting
ii. Level 3 Schedule & MDR for AFC
iii. Engineering Detail Design Activities for AFC
iv. Procurement Activities
v. FAT
vi. Equipment Delivered On-Site
vii. All Site Preparation Activities
viii. Installation / Construction Activities including mobilization and demobilization
ix. WCC
x. SAT
xi. Pre-Commissioning & Commissioning
xii. Ready for Start-up / Handover
xiii. Project Closure
F
o
r

I
n
f
o
r
m
a
t
i
o
n


F. Code
Discipline
Code
Doc Type Doc No.
PSR1RJV IN SOW 0004
Doc. Class : B Confidential
Page 26 of 71

PHASE 1B PSR-1 REJ UVENATION PROJ ECT

4.7 CONTRACTOR is required to provide man-power and machinery histogram for all phases of the
WORKS.
4.8 CONTRACTOR shall submit Progress Report on weekly basis to update COMPANY on
progress of WORKS. CONTRACTOR shall develop catch up plan if there is any delay of
WORKS.
4.9 CONTRACTOR shall also provide a two (2) weeks look ahead plan as part of the Progress
Report.
4.10 CONTRACTOR shall provide a dedicated full time Project Planner/Project Control during the
execution of WORKS. The work progress shall be update routinely minimum on 12-hour basis.
4.11 WORKS shall be completed at the earliest time possible. CONTRACTOR is expected to work
during outside normal working hours, weekends and public holidays to meet the limited windows
allocated by COMPANY.
4.12 CONTRACTOR shall obtain COMPANY Operation Schedule which to be used for the weekly
construction planning.
4.13 Work permit shall be submitted before 4 pm one day before the plan execution day.

F
o
r

I
n
f
o
r
m
a
t
i
o
n


F. Code
Discipline
Code
Doc Type Doc No.
PSR1RJV IN SOW 0004
Doc. Class : B Confidential
Page 27 of 71

PHASE 1B PSR-1 REJ UVENATION PROJ ECT

5.0 LIAISON WITH OTHER CONTRACTORS


5.1 CONTRACTOR may encounter other contractors assigned by COMPANY engaged for other
project working in same location(s)/ area(s). CONTRACTOR shall cooperate fully with the other
contractors employed by COMPANY and shall afford reasonable access and facility for the
execution of their work.
5.2 CONTRACTOR shall identify the interfacing activities during the planning and execution phase
among themselves and define and agree the sequence of activities prior to the execution e.g.
crane, scaffolding, integration testing, staging area, and other activities which to be developed
during the OSTA communication planning.
5.3 CONTRACTOR shall attend all integrated planning activity conducted by COMPANY as to
ensure smooth planning and minimize interfacing between various other contractors.
5.4 CONTRACTOR shall ensure that any part of the SITE which is to be shared with other
contractors/Projects is cleaned up and left in reasonable conditions for use by others.

6.0 DESIGN AND ENGINEERING
6.1 General
CONTRACTOR's engineering work shall cover all disciplines and includes, but not limited to the
preparation of all necessary documents and drawings, such as data/requisition sheets, Project
Specifications, requisitions, instruction and detailed drawings, reports, calculations, within the
Scope of Work as required:
i. To ensure a smooth and uninterrupted execution of the project phases, i.e. procurement
of materials and equipment, construction, start-up and operation.
ii. To fulfill the requirements of the WORKS and COMPANY's instructions.
iii. To fulfill the requirements of local law and statutory authorities for granting of permits,
inspection and safety.
iv. To provide COMPANY's with sufficiently detailed instructions and records of the new
facilities to allow safe and efficient operation and maintenance of the WORKS.

6.1.1 CONTRACTOR shall produce and submit Detailed Engineering drawings and Bill of Material for
review and approval by COMPANY.

6.1.2 CONTRACTOR engineering works shall include but not limited to:
i. Perform engineering analysis and review for verification of existing installation.
ii. Produce engineering and documentation inclusive but not limited to engineering
calculation, specification and datasheet, layout and schematic drawings, isometrics, and
detailed drawings.
iii. Where applicable, constructability review, drawing content review and clash checking
shall be conducted. CONTRACTOR's procedures and planning shall allow for field
F
o
r

I
n
f
o
r
m
a
t
i
o
n


F. Code
Discipline
Code
Doc Type Doc No.
PSR1RJV IN SOW 0004
Doc. Class : B Confidential
Page 28 of 71

PHASE 1B PSR-1 REJ UVENATION PROJ ECT

verification of COMPANY issued as-built drawings/mark-up drawings and all activities


required for incorporating revised information throughout the CONTRACT period.
iv. CONTRACTOR shall provide inputs to support any modification in accordance to
COMPANY Procedures and shall also include review of any Execution Strategy
developed for the WORKS.
v. CONTRACTOR shall produce final as-built drawings incorporating all the changes as part
of the Project Close Out.
vi. Lifting, accessibility and rigging studies as required by the WORKS and/or as directed by
COMPANY.
vii. Fabrication, demolition & installation drawings.
viii. Tie in methods.
ix. Temporary power supply for pre-commissioning and commission activities.
x. Review electrical and instrumentation support design, electrical and instrumentation cable
and tubing tray routing design, review relevant drawings and recommend adjustment due
to space limitations, review system compatibility in meeting the design and operational
intent.
xi. Final design check and revalidation of engineering data provided herein so that the
completeness of WORKS specified shall comply with its functional requirement and its
intended purposes.
xii. Temporary work; including special purpose spreader beams and supports during
constructions
xiii. All necessary corrective measures during fit up and all engineering required for site- run
installation clash checks.
xiv. Testing procedures and documentation.

6.2 Preparation of Design and Engineering Documents
Drafting (2-Dimensional)
CONTRACTOR shall confirm the actual condition at SITE prior to drafting works. All 2D drafting,
shall be executed on Micro station / AutoCAD.

F
o
r

I
n
f
o
r
m
a
t
i
o
n


F. Code
Discipline
Code
Doc Type Doc No.
PSR1RJV IN SOW 0004
Doc. Class : B Confidential
Page 29 of 71

PHASE 1B PSR-1 REJ UVENATION PROJ ECT

6.2.1 Standard Forms


In general, CONTRACTOR shall use the latest PSR-1 Rejuvenation Phase1B standard forms,
template sheets and title blocks for all documents and drawings prepared for the PROJ ECT. In
a situation where the use of COMPANY's standard procedures and standard forms is not
applicable, CONTRACTOR may use its own procedures and forms, subject to prior written
agreement from COMPANY.

6.2.2 Symbols on Drawings and Schemes
The symbols and identifications to be used on drawings and flow sheets shall be in accordance
with PSR-1 Rejuvenation Phase1B standards.

6.2.3 Document Numbering & Revisions
Documents and transmittal shall be identified and coded in accordance with PSR-1
Rejuvenation Phase1B J ob Procedure for Numbering System for Technical Documents.

6.2.4 Use of Computer Systems and Electronic Data Handover
CONTRACTOR shall use the following COMPANY standards for electronic data:
Database Files Microsoft Access
Spreadsheet Files Microsoft Excel
Text Files Microsoft Word
Drawing AutoCAD /Microsoft Access Database
Others To be agreed with COMPANY

In all cases the version of software shall be approved by COMPANY before use, and shall
preferably be the latest proven release of software. The software version shall not be changed
during project execution unless prior approval has been obtained from COMPANY.

F
o
r

I
n
f
o
r
m
a
t
i
o
n


F. Code
Discipline
Code
Doc Type Doc No.
PSR1RJV IN SOW 0004
Doc. Class : B Confidential
Page 30 of 71

PHASE 1B PSR-1 REJ UVENATION PROJ ECT

6.3 Review and Approval of Design & Engineering Documents


6.3.1 CONTRACTOR shall submit relevant documents for COMPANY review and approval. This
includes statutory authorization, and to satisfy specific requirements as prescribed in the
PROJ ECT.
6.3.2 Approval by COMPANY shall not relieve CONTRACTOR of any of its responsibilities under the
CONTRACT to provide safe, operable, reliable and efficient system suitable to meet the design
intent and in full compliance with the Project Specification.
6.3.3 CONTRACTOR shall arrange and provide for all engineering approvals, of equipment within the
Scope of Work, and must obtain all necessary authority certificates and approvals of documents
in time.
6.3.4 The fact that a document may or may not have been commented upon, in no way relieves
CONTRACTOR of its liabilities and obligations for the full compliance with the WORKS under
the CONTRACT.

6.4 Issue of Release Documents
6.4.1 CONTRACTOR's documents which are ready for subsequent action (i.e. for procurement and
for construction) and in which all comments have been incorporated shall be issued marked
Approved for Construction (AFC)'.
6.4.2 In cases where significant modifications and/or revisions have to be made on released AFC
documents, these documents shall then be re-issued for comments, clearly marked 'Re-Issued
for Construction'.


F
o
r

I
n
f
o
r
m
a
t
i
o
n


F. Code
Discipline
Code
Doc Type Doc No.
PSR1RJV IN SOW 0004
Doc. Class : B Confidential
Page 31 of 71

PHASE 1B PSR-1 REJ UVENATION PROJ ECT

7.0 PROCUREMENT
7.1 General
7.1.1 CONTRACTOR shall be responsible for the procurement of materials, equipment and
services in order to complete the WORKS unless specified otherwise. All materials,
equipment and services supplied by CONTRACTOR shall comply with the relevant
specifications and standards.
7.1.2 CONTRACTOR shall perform all procurement and related activities as necessary to complete
the WORKS. The procurement function shall inclusive of procurement of material and/or
services, packaging and shipping, permitting and licensing, handling and warehousing and all
kinds associated with procurement of the material and/or services.
7.1.3 CONTRACTOR shall warrant that all material and/or services supplied shall be new, un-used,
fit for the intended purposes and shall conform to the project requirements.
7.1.4 CONTRACTOR shall:
Comply with applicable laws, and sound business practices.
Search the material and/or service sources from trusted financial organizations with proven
performance suitable to the requirements of the WORKS.
Communicate effectively with Suppliers, the COMPANY, and other Contractors.
Ensure that COMPANYs rights and CONTRACTORS obligations shall not be affected by
acceptance of bid application letter, subcontracts, or by other bidding activities carried out
by CONTRACTOR.
Manage procurement processes and deliver goods to meet PROJ ECT schedule
requirements.
Develop procurement documents that accurately describe the materials to be bid or the
services to be subcontracted and the terms under which such materials or services shall be
procured.
CONTRACTOR shall provide a copy of Purchase Order format with terms and conditions to
COMPANY as reference (upon request only). The Purchase Order structure should cover,
at a minimum:
1. Project Supplier identification data.
2. Description of the scope of work and schedule.
3. Technical and Quality requirements.
4. COMPANY has rights to make plant/shop visits for testing, witnessing, and general
process verification.
5. Expediting, delivery (logistics and transportation) processes.
6. Reporting requirements.
7.1.5 CONTRACTOR shall provide a detailed Procurement Plan included in Project Implementation
Plan.

F
o
r

I
n
f
o
r
m
a
t
i
o
n


F. Code
Discipline
Code
Doc Type Doc No.
PSR1RJV IN SOW 0004
Doc. Class : B Confidential
Page 32 of 71

PHASE 1B PSR-1 REJ UVENATION PROJ ECT

7.2 Sub- Contracting


7.2.1 CONTRACTOR shall submit the list of potential subcontract(s) for the WORKS for
COMPANYs approval.
7.2.2 CONTRACTOR shall maximize Malaysian participation and resources a SUB-CONTRACTOR
in the execution of the WORKS.
7.2.3 CONTRACTOR shall identify COMPANY from and against any claims from SUB-
CONTRACTOR arising in connection with CONTRACTORs inquiry and/or selection of SUB-
CONTRACTOR.
7.2.4 COMPANY shall have the right to approve or to reject any proposed SUB-CONTRACTOR by
the CONTRACTOR without assigning any reason for the rejection. Any rejection by
COMPANY shall not have impact on overall PROJ ECT schedule.
7.2.5 Sub-Contracting of scope of work that includes engineering, and/or supply of materials, shall be
contracted in full recognition of COMPANYs procedures and requirements. Engineering and
Procurement documents shall be distributed accordingly.
7.2.6 CONTRACTOR remains responsible for the quality, capability and performance of the SUB-
CONTRACTOR. CONTRACTOR shall be responsible for obtaining the best possible
guarantees and warranties from all SUB-CONTRACTOR.
7.3 Purchase Orders
7.3.1 CONTRACTOR shall update enquiry requisitions to order status to include all details agreed
with supplier and COMPANY prior to order commitment. If a change in design or specification
is made after issue of the Purchase Order, CONTRACTOR shall issue a revised requisition,
together with appropriate revised drawings and documents. The revised requisition shall
clearly indicate the scope of the revision.
7.3.2 COMPANY shall be shown as consignee for all procurement from outside Malaysia, in order
for COMPANY to qualify for tax or import duty exemption from Malaysian Investment
Development Authority (MIDA). All material procured by CONTRACTOR shall not include the
import duty and tax in the cost.
COMPANY will be responsible to apply tax exemption. The Purchase Order for all item
procured from outside Malaysia shall be placed based on Delivery At Place (DAP).
7.3.3 CONTRACTOR is required to extend one copy of un-priced Purchase Order for every
procurement package complete with all attachments and any variations thereto for
COMPANYs review and approval.
7.3.4 The Purchased Order shall include, where appropriate, a statement that the material and
services concerned is subjected to inspection by COMPANY or their nominee and that they
shall have full access to Vendor shop/ works during all stages of manufacturing and testing.
7.3.5 Purchase Order shall state, by means of the requisition for engineering document,
drawings, cross sectional drawings, fabrication drawings, calculation, certificates, data
instruction book, operating/ maintenance manual, spare parts list and other documents
requirements and submission schedule.
F
o
r

I
n
f
o
r
m
a
t
i
o
n


F. Code
Discipline
Code
Doc Type Doc No.
PSR1RJV IN SOW 0004
Doc. Class : B Confidential
Page 33 of 71

PHASE 1B PSR-1 REJ UVENATION PROJ ECT

7.3.6 CONTRACTOR shall prepare a documented query for any proposal of deviation for
COMPANYs review and approval prior to approval is granted.
7.4 Sub-Contractor Documents
7.4.1 CONTRACTOR shall be responsible to secure, assemble and distribute to COMPANY the
Sub-Contractor documents. CONTRACTOR shall obtain manufacturing drawings and data in
sufficient quantities as per project requirement. CONTRACTOR shall include in Procurement
Plan, a procedure for control, handling and processing of SUB-CONTRACTORs documents.
7.4.2 The Purchase Order or Purchase Requisition shall specify requirement of drawings,
calculations, fabrication, inspection and test plans, test procedure, spare parts lists (SPIR) and
other documents from the Supplier.
7.4.3 CONTRACTOR shall be responsible for the timely receipt, logging and issuance of all
documents for internal review, recording of the approval status and transferal of these
documents to and from SUB-CONTRACTOR, CONTRACTOR and COMPANY.
7.4.4 CONTRACTOR shall be responsible for ensuring the drawings received from Supplier in a
certified as fabricated status and the drawings are revised to As Built status after installation
stage.
7.4.5 CONTRACTOR shall be responsible to review, comment and correct the Supplier drawings,
calculations, quality plan, fabrication, inspection and test plans, and other documents. Marked-
up copies shall be sent to COMPANY for information/ review. CONTRACTOR shall
demonstrate that COMPANYs comments have been incorporated by the Suppliers.
7.5 Expediting
7.5.1 CONTRACTOR shall submit a detailed expediting plan as part of the Procurement Plan. The
expediting plan shall provide a systematic method of ensuring that material and services are
delivered and received. The procedure shall include a procurement tracking system and list of
expediting activities with schedule to meet the required delivery.
7.5.2 CONTRACTOR shall provide COMPANY with a copy of Expediting Status Reports on material
and services on weekly and monthly basis or as requested by COMPANY. Any deviation from
the schedule on any procured items must be reported immediately to COMPANY with
explanation for each deviation and proposed remedial action plan.
7.5.3 CONTRACTOR is responsible for the expediting of the above mentioned documents and
tracking their status via the Supplier Document Register.
7.5.4 CONTRACTOR shall keep up-to-date records on all visits or contacts with the SUB-
CONTRACTOR and shall file the same with the appropriate Purchase Order.

F
o
r

I
n
f
o
r
m
a
t
i
o
n


F. Code
Discipline
Code
Doc Type Doc No.
PSR1RJV IN SOW 0004
Doc. Class : B Confidential
Page 34 of 71

PHASE 1B PSR-1 REJ UVENATION PROJ ECT

7.6 Inspection and Surveillance


7.6.1 CONTRACTOR shall be responsible to provide an inspection and quality assurance program/
procedure to ensure that COMPANY is provided with products that meet the requirements of
the project.
7.6.2 CONTRACTOR shall provide Vendor verification program/ procedure for quality of material
and services to ensure that COMPANY is provided with product that meet the project
requirement. The Vendor verification program/ procedure shall inclusive but not limited to
identification of quality surveillance requirements, quality surveillance planning, and processes
for surveillance implementation and procedure for controlling of non- conformance.
7.6.3 CONTRACTOR shall carry out a receiving inspection on all procurement item.
7.6.4 CONTRACTOR shall notify COMPANY on the arrival of procured items at CONTRACTORs
receiving designated point prior to CONTRACTORs Material Receiving Inspection.
COMPANY shall have the right to carry out inspection on all procured items.
7.6.5 CONTRACTOR shall confirm in writing the material and services conform to the
acceptance and testing criteria as per project specification. COMPANY may also carry out an
inspection at CONTRACTORs Vendor and Sub-Vendor manufacturing facilities and at the
time of receiving of the procured items.
7.7 Shipping and Transportation
7.7.1 CONTRACTOR shall be responsible for coordinating and arranging the forwarding and
shipping of procured items both inside and outside Malaysia. CONTRACTOR shall appoint
COMPANYs approved agency for freight forwarding services and inland transportation.
7.7.2 CONTRACTOR shall obtain all necessary insurances from reputable and financially secure
companies licensed or incorporated in Malaysia and approved by COMPANY.
7.7.3 CONTRACTOR shall become familiar with the importing and exporting laws of Malaysia.
7.7.4 CONTRACTOR shall become familiar with the requirements of the transportation of procured
items to the job site.
7.7.5 CONTRACTOR shall receive, transport and warehouse all procured items in a manner as to
prevent damage and to ensure that only new materials are supplied for the project.
7.7.6 CONTRACTOR shall provide, prepare, maintain and re-store all sites and facilities necessary
for storage and handling of procured items during shipping and transportation.
7.7.7 CONTRACTOR shall advise COMPANY with a reasonable notification period for all import
shipment being planned to enter Malaysia under COMPANY consignee. CONTRACTOR shall
also provide COMPANY with all documentation required for materials imported into Malaysia.
CONTRACTOR shall inform COMPANY on any changes in shipping program

F
o
r

I
n
f
o
r
m
a
t
i
o
n


F. Code
Discipline
Code
Doc Type Doc No.
PSR1RJV IN SOW 0004
Doc. Class : B Confidential
Page 35 of 71

PHASE 1B PSR-1 REJ UVENATION PROJ ECT

7.7.8 CONTRACTOR shall give COMPANY a special notice for the shipping and transportation of
engineered materials involving critical lifting.
7.7.9 CONTRACTOR shall submit COMPANY for information a copy of the shipping and
transportation procedure.
7.8 Packing and Marking
7.8.1 CONTRACTOR shall provide appropriate shipping protection for all procured items to prevent
damage and contamination.
7.8.2 All material shall be marked or have tags attached indicating details of the material such as
equipment name and quantity, purchase order number, project details, dimensions, gross
and net weight, special handling, lifting and storage instruction, country of origin and any other
relevant information.
7.8.3 CONTRACTOR shall ensure that each purchase inquiry and Purchase Order and all
correspondence, specification, drawings, spare parts information, data on special tools, or
other papers pertaining to procurement shall bear specific identification system.
7.8.4 All tags and marking shall be fade resistant and able to withstand extended periods of
storage in bright sunlight and other atmospheric conditions prevalent at the job-site.
7.8.5 Any assembly drawings, operating manuals, packing slips, import documents, etc. shall be
sealed and securely attached or enclosed with the shipment.
7.9 Custom Clearance and Government Tax Exemption
7.9.1 CONTRACTOR shall acquire the necessary licenses from the Government of Malaysia for the
import of the procured items into Malaysia.
7.9.2 Custom clearance in Malaysia shall be performed by CONTRACTOR who shall have all the
appropriate and necessary permits and approvals from the relevant authorities.
7.9.3 CONTRACTOR shall source all material and equipment locally. If the material and equipment
is not available locally, CONTRACTOR may source the material from outside Malaysia and
COMPANY will bare all the impose taxes. However, if the tax exemption rejected by MIDA
due to the item and equipment is available in Malaysia, CONTRACTOR shall bare all the cost
related to import and sale taxes.
7.9.4 CONTRACTOR shall arrange for all import and/ or customs formalities at Port of Entry. The
most appropriate/ lowest tariff rate shall be applied and COMPANY reserves the right to check
the rates applied.
7.9.5 CONTRACTOR shall also maintain an inventory listing on the status of all imported
materials and shall advice COMPANY of any access and of any disposal to be made.

F
o
r

I
n
f
o
r
m
a
t
i
o
n


F. Code
Discipline
Code
Doc Type Doc No.
PSR1RJV IN SOW 0004
Doc. Class : B Confidential
Page 36 of 71

PHASE 1B PSR-1 REJ UVENATION PROJ ECT

7.9.6 In order to qualify for tax exemption of import duties and sale tax, COMPANY shall at its own
expenses apply for the tax exemption of import duties and taxes to the Malaysia Federal
Government Treasury Department on the material to be imported into Malaysia. All credit from
import duties and taxes will belong to COMPANY.
7.9.7 CONTRACTOR shall ensure the information contained in the shipping documents and the
Custom Declaration Forms and Import Duty Exemption Form are matching.
7.9.8 CONTRACTOR shall be responsible to ensure that the procured items imported under
Government Tax Exemption shall be used and stored at job-site only. CONTRACTOR
shall not sell, transfer ownership, export or move from job-site the said materials approved by
the Malaysia Federal Government Treasury Department through COMPANY.
7.9.9 The importation of material under the Government Tax Exemption shall be made on the
required quantity and shall be used for the project only. CONTRACTOR shall advise
COMPANY of any surplus and cost of duties and taxes for the surplus shall be the
responsibilities of CONTRACTOR.
7.9.10 CONTRACTOR shall prepare tax exemption documentation and submit to COMPANY within
one (1) week after date of Purchase Order to supplier.
7.9.11 CONTRACTOR shall bear the cost of tax and duty to Customs should the application of tax
exemption be rejected by MIDA due to failure of CONTRACTOR to provide correct and
complete information as required by MIDA; e.g. wrong declaration of quantity, specification,
fail to provide photo and drawing etc.
7.9.12 In the event of tax exemption yet to be approved, CONTRACTOR shall forward a request to
COMPANY for Bank Guarantee (BG) two (2) weeks before the arrival of material/equipment at
port.
7.9.13 CONTRACTOR shall be responsible for BG redemption from customs on behalf of
COMPANY. CONTRACTOR shall update BG status to COMPANY every two (2) weeks.
7.9.14 CONTRACTOR shall be responsible to hand over all original documents related to customs
clearance, tax exemption, MITI, SIRIM and etc.to COMPANY.
7.9.15 CONTRACTOR shall inform COMPANY two (2) weeks in advance for all movement of tax
exempted materials / equipment outside COMPANY premises; e.g. movement to fabrication
yard etc.
7.9.16 CONTRACTOR shall appoint COMPANY panel forwarding agent i.e. MISC or Kontena
Nasional for customs clearance and transportation to COMPANY premise.
7.9.17 CONTRACTOR shall prepare accountability report for J abatan Kastam Diraja Malaysia
(Melaka) to COMPANY progressively.
7.9.18 In the event of COMPANY has to pay tax and duty in advance of MIDA tax exemption
approval, CONTRACTOR shall be responsible to liaise with J abatan Kastam Diraja Malaysia
(J KDM) for tax and duty reimbursement claim on behalf of COMPANY, upon approval of tax
exemption from MIDA.
F
o
r

I
n
f
o
r
m
a
t
i
o
n


F. Code
Discipline
Code
Doc Type Doc No.
PSR1RJV IN SOW 0004
Doc. Class : B Confidential
Page 37 of 71

PHASE 1B PSR-1 REJ UVENATION PROJ ECT

7.9.19 CONTRACTOR shall be responsible to arrange for material inspection by SIRIM or


authorized third party as part of J KDM requirement for imported material (e.g. pipe, steel
plate etc.). All cost related to the requirement shall be borne by CONTRACTOR.
7.10 Procurement Status Report
7.10.1 CONTRACTOR shall issue a copy of Procurement Status Report periodically to COMPANY
which include for each Purchase Order.
7.11 Material Control
7.11.1 CONTRACTOR shall be responsible for the control of procured items,
7.11.2 CONTRACTOR shall submit to COMPANY a copy of Material Control Procedure to describe in
detail control functions which shall inclusive but not limited to receiving of shipment, inventory
control, issuing of material, return of surplus, warehousing, etc.
7.11.3 CONTRACTOR shall at all-time maintain records detailing the material that have been
received, stored, or issued for construction and shall make such records available to
COMPANY upon request by COMPANY.
7.12 Procurement Close Out
7.12.1 CONTRACTOR shall transfer to COMPANY copy of all files relating to procurement of each
item upon completion of procurement activities. The file shall contain, but not limited to:

1. Purchase Order and any amendments thereto
2. Purchase Requisition
3. Import, Packing and Shipping Documents
4. Catalogues and specification
5. Manufacturer Routine Test Report
6. Type Test Certificate for equipment & associate components.
7. Final Acceptance Testing Reports/ Mill Certificates, and
8. Any other specific procurement documentation as requested by COMPANY.



F
o
r

I
n
f
o
r
m
a
t
i
o
n


F. Code
Discipline
Code
Doc Type Doc No.
PSR1RJV IN SOW 0004
Doc. Class : B Confidential
Page 38 of 71

PHASE 1B PSR-1 REJ UVENATION PROJ ECT

8.0 FABRICATION AND CONSTRUCTION


8.1 General
8.1.1 CONTRACTOR shall be responsible for all works related to the Construction of the PROJ ECT as
described in the Scope of Work, Project Specification, PTS and proven accepted practices and
procedures. The construction work shall be performed in safely manner, reliable and suitable for
their intended purpose.
8.1.2 CONTRACTOR shall strictly comply with the HSE requirement as stipulated by COMPANY.
CONTRACTOR shall take utmost precautions on all safety aspects in coordinating, performing
and completing the construction work within and adjacent to live Plant(s).
8.1.3 CONTRACTOR shall provide all supervision, labour, construction equipment, tools and tackles,
materials and consumable, temporary facilities, construction utilities such as power, nitrogen, air,
water, etc., and render all support services necessary for the Construction activities.
8.1.4 CONTRACTOR is deemed to have full knowledge of all applicable laws and regulation,
conditions of labour, local condition, site conditions and environmental aspects and shall comply
with the requirements thereof.
8.2 Construction Execution Plan
8.2.1 CONTRACTOR shall produce a Construction Execution Plan (CEP) prior to commence the
construction and submit to COMPANY for approval. The CEP shall identify the key critical
construction strategies and key issues that will require detailed risk assessment and
constructability review.
8.2.2 Construction Execution Plan shall include but not limited to the following:
i) CONTRACTOR's manpower and man-hours histogram by major section and by discipline.
ii) Major Construction Equipment mobilization plan on monthly basis with short description
iii) CONTRACTORs plan and procedures to be submitted prior to start of the activities (J ob
Method Statement etc.). The plan and procedures shall inclusive but limited to heavy
transport and lifting, prefabrication plan, tie-in plan, work plan during shutdown, regulatory
and local agencies permitting procedure and approval plan etc.
F
o
r

I
n
f
o
r
m
a
t
i
o
n


F. Code
Discipline
Code
Doc Type Doc No.
PSR1RJV IN SOW 0004
Doc. Class : B Confidential
Page 39 of 71

PHASE 1B PSR-1 REJ UVENATION PROJ ECT

8.2.3 CONTRACTOR shall establish a site management organization with sufficient responsibility and
authority for all activities up to Work Completion.
8.2.4 CONTRACTOR shall appoint one full time Construction Manager responsible for all its
Construction activities. The Construction Manager shall always be contactable at all times.
8.2.5 CONTRACTORs site Management Organization shall be established with reference to
COMPANYs site Organization to facilitate communication and work arrangement as best as
reasonably practical. CONTRACTOR shall provide and submit to COMPANY for approval, a
detailed Organization chart of its proposed site Organization, including names, roles and
responsibilities, terms of reference for the various job functions and their respective reporting
relationships.
8.2.6 CONTRACTOR shall ensure that the numbers of its skilled Construction Supervisory Personnel
are adequate to ensure effective direct control and coordination of all construction activities of
both its and its SUB-CONTRACTOR, and are present on SITE at all times throughout the
PROJ ECT. COMPANY reserves the right to instruct CONTRACTOR to increase the levels of its
and/ or its SUB-CONTRACTORs Supervisory Personnel, at CONTRACTORs cost, in the event
that safety, quality or progress of the WORKS warrants such action to be taken.
8.2.7 CONTRACTOR shall ensure its site management team is available on SITE at all times including
adequate and experienced engineering personnel from each discipline for a prompt response in
resolving all engineering issues arising on SITE during the Construction period up to Work
Completion.
8.2.8 CONTRACTOR shall be responsible for the direct management of all its SUB-CONTRACTOR
activities at SITE, in particular for ensuring their construction progress and the quality of the work
performed by them as per Project Specification. CONTRACTOR shall follow operational
constraints, which may arise from time to time due to actual conditions in the plant. COMPANY
reserves the right to attend any meetings held between CONTRACTOR and its SUB-
CONTRACTOR.
8.3 Construction Schedule
8.3.1 CONTRACTOR shall prepare a detailed Construction Schedule. CONTRACTOR shall control the
schedule of the construction work at SITE. CONTRACTOR shall ensure that the Project
Execution Schedule and other Project Planning and Control Tools are sufficient to control the
activities and resources during the Construction.
8.3.2 CONTRACTOR shall consider preparing a detailed Construction schedule in order to meet the
given OSTA window.
8.3.3 CONTRACTOR shall monitor the progress and delayed area, analyzed the reason of the delay
and forecast the influence of such delay. CONTRACTOR shall be responsible to take effective
counter measure immediately to recover the time delay, upon endorsement by COMPANY.
8.3.4 CONTRACTOR shall obtain COMPANYs approval to work any hours outside normal working
hour and shall identify safety and supervisory personnel required to control such work.
F
o
r

I
n
f
o
r
m
a
t
i
o
n


F. Code
Discipline
Code
Doc Type Doc No.
PSR1RJV IN SOW 0004
Doc. Class : B Confidential
Page 40 of 71

PHASE 1B PSR-1 REJ UVENATION PROJ ECT

CONTRACTOR shall also identify any requirements for COMPANY personnel to support and
inspect / witness the work during such working hours.
8.4 Construction Personnel
8.4.1 CONTRACTOR shall provide all necessary management personnel, labour and SUB-
CONTRACTOR in adequate numbers in order to execute the WORKS in accordance with this
ITB. CONTRACTOR shall submit list of name of its and its SUB-CONTRACTORs personnel
including workers/labour to COMPANY at least two (2) months in advance prior to SITE entry for
screening purpose.
8.4.2 COMPANY shall have the right to assess and accept any CONTRACTORs
personnel/workers and its SUB-CONTRACTORs personnel/workers before engagement for
works, and to refuse without explanation, any particular person permission to enter or to perform
work on SITE. COMPANY shall have the right to exclude from SITE any person(s) who infringe
Malaysian laws or the regulations in forced.
8.4.3 Persons failing qualifications of conduct and/or ability in the opinion of COMPANY shall be
immediately removed from the PROJ ECT and repatriated (if expatriates). CONTRACTOR is not
entitled to COMPANYs reasons in this instance. CONTRACTOR shall make provision for the
timely and adequate replacement of all such personnel.
8.4.4 CONTRACTORs and its SUB-CONTRACTORs personnel, both technical and direct labour,
shall have all the required technical skills and qualifications required for the performance of the
work to which they are assigned and shall have in their possession all needed licenses and
certificates needed to substantiate this. COMPANY reserves the right to conduct technical
interviews with any personnel presented to COMPANY for their acceptance.
8.4.5 Once CONTRACTOR personnel and its SUB-CONTRACTORs key personnel have been
accepted by COMPANY, they shall not be removed / replaced unless alternative persons,
accepted by COMPANY, are made available on SITE, allowing at least one (1) week overlapping
for both personnel for task handing-over process.
8.4.6 CONTRACTORs and SUB-CONTRACTORs supervisory personnel and Supplier
Representatives shall be fully conversant with Bahasa Melayu and/or English language, both
written and spoken.
8.4.7 CONTRACTOR and its SUB-CONTRACTOR shall maintain complete personnel records on all
persons employed on SITE.
8.4.8 Visas, Work Permits, Rules, Licenses and Notices.
a) CONTRACTOR shall make timely arrangements, and be responsible for the necessary
passports, Malaysian visas and work permits for any expatriates personnel and labour to
be employed by it and its SUB-CONTRACTOR. CONTRACTOR shall keep accurate and
updated personnel registration and administration and keep COMPANY informed of any
new intake or whenever requested.
F
o
r

I
n
f
o
r
m
a
t
i
o
n


F. Code
Discipline
Code
Doc Type Doc No.
PSR1RJV IN SOW 0004
Doc. Class : B Confidential
Page 41 of 71

PHASE 1B PSR-1 REJ UVENATION PROJ ECT

b) CONTRACTOR shall ensure that all expatriate person(s) to be employed on SITE are
registered with relevant government agencies prior work on SITE.
c) CONTRACTOR shall obtain all permits and licenses and bear all fees necessary as
required by law for the proper execution of WORKS. A copy of each permit or license
shall be submitted to COMPANY for acknowledgement and record keeping.
8.4.9 CONTRACTOR shall make timely arrangements, and be responsible for the necessary
passports, Malaysian visas and work permits for any expatriates personnel and labour to be
employed by it and its SUB-CONTRACTOR. CONTRACTOR shall keep accurate and updated
personnel registration and administration and keep COMPANY informed of any new intake or
whenever requested.
CONTRACTOR shall ensure that all expatriate person(s) to be employed on SITE are
registered with relevant government agencies prior work on SITE.
CONTRACTOR shall obtain all permits and licenses and bear all fees necessary as
required by law for the proper execution of the WORKS. A copy of each permit or license
shall be submitted to COMPANY for acknowledgement and record keeping.
8.4.10 CONTRACTOR shall arrange all relevant site induction, training of labour to perform the WORKS
in accordance with applicable codes, supervision of trade qualification tests, and maintenance of
test records.
8.4.11 Personnel Transportation
CONTRACTOR shall provide all the necessary transport for its and its SUB-
CONTRACTORs personnel to/from and within SITE at all times.
Access for CONTRACTORs vehicles to the SITE shall be strictly limited and shall require
an Entry Permit issued by COMPANYs security department. Private vehicles shall not be
permitted in the Plant. CONTRACTOR shall designate its vehicles, subject to
COMPANYs approval, necessary for transportation and construction purposes for Plant
entry.
Prior to Plant entry, all vehicles shall be fitted with a spark arrestor and be
subjected to inspection by COMPANY.

F
o
r

I
n
f
o
r
m
a
t
i
o
n


F. Code
Discipline
Code
Doc Type Doc No.
PSR1RJV IN SOW 0004
Doc. Class : B Confidential
Page 42 of 71

PHASE 1B PSR-1 REJ UVENATION PROJ ECT

8.5 Construction Tool and Machi nery/ Equipment


8.5.1 All CONTRACTORSs tools and equipment shall be fit for purpose, and maintained in a safe
working condition. Guards and electrical trip switches must work effectively and must not be
removed or bypassed. Any substandard tools are strictly prohibited.
8.5.2 CONTRACTOR shall provide all tools and machinery necessary for the effective execution
of the WORKS. All construction equipment intended for use on SITE shall conform to
COMPANYs requirements.
8.5.3 CONTRACTOR shall carry out scheduled inspection and testing of construction machinery in
accordance with relevant local authoritys safety regulation or manufacturer requirements, as a
minimum. CONTRACTOR shall keep records of these inspections and make available to
COMPANY whenever requested.
8.5.4 CONTRACTOR shall not allow the use of any machinery, which is unsafe or unsuitable for any
specific task. COMPANY shall have the right to stop any work if found using any machinery
deemed unsafe or incapable of performing the work to the required standard. Such machinery
shall be replaced immediately by CONTRACTOR and no schedule or cost impact can be claimed
by CONTRACTOR.
8.5.5 CONTRACTOR shall provide machinery servicing and repair facilities and a stock of spare parts
and consumables at SITE, to minimize down-time in case of any machinery breakdown.
8.6 Risk Assessment and Method of Statement
8.6.1 CONTRACTOR shall carry out a full Risk Assessments with regards to all its Construction
activities on SITE. This activity is expected to be at least one (1) month before site execution
activities are expected to begin.
8.6.2 Risk Assessment methodology shall be used to identify and assess Health, Safety and
Environmental hazards during Construction and pre-commissioning and commissioning phases.
These hazards may be identified at any stage of the project; e.g. COMPANY data, existing
drawings, site survey investigations, design and Constructability reviews, or information that may
emerge during the work execution.
8.6.3 The risk assessment shall characterize the risk in terms of severity and probability. The risk
assessment shall be the platform for development of method statement and shall be guideline for
eliminating or minimized the risk to an acceptable level.
8.6.4 CONTRACTOR shall prepare detailed Method of Statements for all works which has risks to
HSE as determined by Risk Assessment. The method of statement shall describe the work
procedures, sequence of operation and the controls necessary to achieve effective management
of risk, and efficient execution of WORKS. Detailed Method Statements shall be prepared for all
critical tasks.
8.6.5 Method statements shall be submitted to COMPANY at least one (1) week prior to the
anticipated commencement of the work. The method statement shall be reviewed by COMPANY.
F
o
r

I
n
f
o
r
m
a
t
i
o
n


F. Code
Discipline
Code
Doc Type Doc No.
PSR1RJV IN SOW 0004
Doc. Class : B Confidential
Page 43 of 71

PHASE 1B PSR-1 REJ UVENATION PROJ ECT

Audits of method statements shall be carried out by the CONTRACTORs Safety Management
Team.
8.7 Tie-In and Shutdown Works
8.7.1 CONTRACTOR scope shall include tie-in works which need to be undertaken during normal
operation as well as during plant shutdown. CONTRACTOR shall develop Tie-in Plans and
Method Statement for all tie-in work.
8.7.2 CONTRACTOR shall ensure that the tie-in work are thoroughly planned well ahead of the
construction phase and shall, discuss and plan with COMPANY the necessary tie-in
activities to the existing plants. CONTRACTOR shall maximize installation of tie-ins during
normal operation to minimize the shutdown workload.
8.7.3 CONTRACTOR shall plan and identify all works requiring shutdown especially the tie-in work.
CONTRACTOR shall ensure that the tie-in work are thoroughly planned well ahead of the
construction phase and shall, discuss and plan with COMPANY the necessary tie-in activities to
the existing plants.
8.7.4 CONTRACTOR shall complete the tie-in work timely as planned. The plan shall identify the tie-in
category with a time schedule. CONTRACTOR shall ensure minimum interference with the
existing plant and operating facilities.
8.7.5 CONTRACTOR shall discuss with COMPANY on isolation plan etc. prior to execution of the
WORKS.
8.7.6 CONTRACTOR shall submit the energization procedure to COMPANY at least three (3) weeks
prior to the replacement scope.
8.7.7 CONTRACTOR shall be responsible to supply and provide all necessary materials, consumable,
manpower and tools etc. to execute all tie-in activities. CONTRACTOR shall report directly to and
working under the directive of COMPANYs Plant Operation Personnel during tie-in activities until
the completion and normalizing of the affected systems.
8.7.8 CONTRACTOR shall consider maximize pre-assembly of items, as practicable. The split of the
work scope between the shop and work SITE shall be fully detailed in the method statements
provided in the CONTRACTORs Execution Plan.
8.7.9 CONTRACTOR shall take note that COMPANY may not be able to shutdown the process unit for
installation and tie in works. In the event COMPANY is not able to shutdown the process,
CONTRACTOR shall execute the tie-in work(s) via hot-tapping/live-tapping method. For such
case CONTRACTOR shall be responsible to prepare J ob Safety Analysis (J SA) and obtained the
approval from COMPANYs designated approver.
8.7.10 All tie-In work shall be performed in accordance with relevant codes and standards and Project
Specification.

F
o
r

I
n
f
o
r
m
a
t
i
o
n


F. Code
Discipline
Code
Doc Type Doc No.
PSR1RJV IN SOW 0004
Doc. Class : B Confidential
Page 44 of 71

PHASE 1B PSR-1 REJ UVENATION PROJ ECT

8.8 Scaffolding
8.8.1 CONTRACTOR shall ensure that all personnel associated with erection, alteration, modification,
dismantling and supervision activities must have attended the appropriate training skill and
accreditation by approved body.
8.8.2 CONTRACTOR inspection personnel shall conduct all necessary inspection prior to
commencement of any scaffolding erection. Proper signage shall be displayed prominently and
affected areas shall be barricaded.
8.8.3 All scaffolding erection shall only be used upon authorization by responsible personnel the
erected scaffolding shall be green tagged.
8.9 Protection of Plant Facilities
8.9.1 CONTRACTOR is responsible to ensure no damage to existing equipment and plant facilities
during WORKS execution. CONTRACTOR shall employ all suitable means of protection to avoid
any damage to the existing plant asset.
8.9.2 CONTRACTOR shall report to COMPANY any property damage or near misses.
8.9.3 CONTRACTOR shall repair and/ or replace all damaged asset at no cost to COMPANY within
stipulated time, unless otherwise specified.
8.10 De-Commissioning
8.10.1 CONTRACTOR shall be responsible for the equipment isolation, de-isolation in preparation for
the decommissioning work.
8.10.2 CONTRACTOR shall conduct risk assessment to assist with hazard identification and risk control
identification prior to the decommissioning work.
8.10.3 CONTRACTOR shall perform site audit to identify/anticipate potential hazards during
decommissioning operation. CONTRACTOR shall be responsible to develop hazardous material
removal plan before commissioning from the activities.
8.10.4 CONTRACTOR shall conduct the demolition phase with supervisory by COMPANY
representative.
8.10.5 CONTRACTOR shall be responsible to dismantle the equipment into its component parts. The
parts has to be secured and with proper packaging for transportation to the storage area.
8.10.6 CONTRACTOR shall discuss with COMPANY on the dismantling and disposal/storage
requirement of the de-commissioned equipment.




F
o
r

I
n
f
o
r
m
a
t
i
o
n


F. Code
Discipline
Code
Doc Type Doc No.
PSR1RJV IN SOW 0004
Doc. Class : B Confidential
Page 45 of 71

PHASE 1B PSR-1 REJ UVENATION PROJ ECT

9.0 QUALITY CONTROL AND ASSURANCE


9.1 General
9.1.1 CONTRACTOR shall develop and implement relevant QA program for all activities involved in
the project to ensure quality planning and the quality control throughout the project
implementation. The QA activities shall be incorporated into Scope of Works of the project and
are scheduled and monitored through the Project Quality Plan. The applicable QA programmes
all inclusive but not limited to:
a. Quality Assurance Program for Project Management
b. Quality Assurance Program for Engineering and Design
c. Quality Assurance Program for Procurement
d. Quality Assurance Program for Construction
e. Quality Assurance Program for Commissioning
f. Quality Assurance Program for Project Closed Out and Turnover

a. Quality Assurance for Project Management
A project control plan that serve as an overall project implementation document that
describe the organisation, define specific roles and responsibilities, prescribe delegation
of technical and commercial authorities, provide a schedule for reviews and specify
participation in such activities.
The procedure shall covers as a minimum the establishment of Project Quality Plan,
Design Contractor Quality Plan, Supplier Quality Plan, and Construction Contractor
Quality Plan.
b. Quality Assurance for Engineering and Design
The QA program for development of engineering and design specifications shall provide
guideline for implementation of quality assurance activities such that the development are
being properly monitored and controlled and the adequacy of the design is verified before
being implemented.
The program shall be inclusive but not limited to specification control, interface control,
engineering/design change controls, design reviews including constructability reviews,
design verification and approval, reliability, operability and maintainability engineering.
c. Quality Assurance for Procurement
The QA program for Procurement function shall provide guideline for implementation of
quality assurance activities during the performance of procurement of equipment,
materials and/ or services to ensure compliance with project standards and specification.
The QA activities shall be inclusive but not limited to development of specification,
selection of Supplier or Contractor, quality plan, COMPANYs involvement, vendors
performance monitoring, quality audits and reviews, control of deviations and
F
o
r

I
n
f
o
r
m
a
t
i
o
n


F. Code
Discipline
Code
Doc Type Doc No.
PSR1RJV IN SOW 0004
Doc. Class : B Confidential
Page 46 of 71

PHASE 1B PSR-1 REJ UVENATION PROJ ECT

concessions, control of standard and document verification and approval, materials


control, quality control, inspection requirements and shipment/delivery requirements.
The program shall applicable to procurement of new equipment and replacement
equipment and materials and it activities covers design, fabrication and shipment and
delivery of the equipment and/or materials to the work SITE.
d. Quality Assurance for Construction
The QA program for construction stages shall provide guideline for implementation of
quality assurance activities during the construction and installation to ensure compliance
with design specifications and the equipment are installed in accordance with
manufacturers instructions.
The QA activities shall inclusive but limited selection of Construction Contractor,
Construction equipment and material control, Document control, Pre-Fabrication and
construction control, Handover control of completed works
The program shall applicable for all construction stages inclusive pre-fabrication, erection
and installation of new facilities, installation of new equipment removal and re-installation
of existing equipment and any other construction or installation works implemented for the
project.
e. Quality Assurance for Commissioning and Decommissioning
The QA program for Commissioning and De-Commissioning shall provide guideline to
assure the facilities and/or equipment are commissioned or de-commissioned properly,
without risk to the safety of personnel or environment and minimal disruption to the
operation of existing facilities with any necessary changes having been suitably
authorized and recorded, and the facilities or equipment are safely handed over to
COMPANY
De-commissioning of process equipment applies to physically and permanently taken the
process equipment out of service, removed from the facility and will not be returned to
service.
f. Quality Assurance for Project Close Out and Turnover
The QA program for Project Close-Out and Turnover shall provide guideline for a proper
project close out and turnover after the completion of the project. The QA activities shall
inclusive but limited to development of lessons learned, contract close-out, document and
records turnover, post-implementation review and close-out report.
9.1.2 CONTRACTOR shall operate a quality system satisfying the applicable provision of ISO 9000 or
BS 5750 (series), or agreed equivalent, commensurate with the goods and services provided.
9.1.3 COMPANY reserves the right to carry out Quality and Technical Review at CONTRACTORs
works including review of quality documentation.
9.1.4 CONTRACTOR shall be responsible at all times provide dedicated competent and qualified
personnel approved by COMPANY.
F
o
r

I
n
f
o
r
m
a
t
i
o
n


F. Code
Discipline
Code
Doc Type Doc No.
PSR1RJV IN SOW 0004
Doc. Class : B Confidential
Page 47 of 71

PHASE 1B PSR-1 REJ UVENATION PROJ ECT

9.1.5 Where CONTRACTOR subcontracts the whole or main parts of the WORKS or materials, then
these requirements shall be applied in full to SUB-CONTRACTOR.
9.1.6 Control of CONTRACTOR and SUB-CONTRACTOR shall encompass measures to verify that
progress and quality requirements are met. Surveillance/audit of SUB-CONTRACTOR shall be
performed by CONTRACTOR as necessary.

9.2 Quality Surveillance
COMPANY may perform quality audits, technical reviews, test witnesses and inspections at
source in order to verify compliance with the CONTRACT requirements. CONTRACTOR shall
provide free access to COMPANY and co-operate with COMPANY in the performance of all
testing, witnessing and audits.

9.3 Audits/Reviews
COMPANY reserves the right to audit at source at any time during the duration of the
CONTRACT and will give two (2) weeks notice. CONTRACTOR shall undertake to close out
any findings raised as part of such an audit.
CONTRACTOR shall co-operate in the provision of information and the supply of all necessary
CONTRACTOR personnel to allow COMPANY or their delegated authority to perform a
meaningful audit/review.
The results of any internal audits/reviews conducted by CONTRACTOR shall be documented
and made available to COMPANY within one (1) week after completion of CONTRACTOR
audit/review.

9.4 Non-conformity and Correcti ve Action
CONTRACTOR shall notify COMPANY immediately when a non-conforming WORKS is
identified which requires repair, rework, replacement or a concession. COMPANY will review
the non-conformance and either agrees with CONTRACTOR's proposed repair procedure or
agree with a concession or reject the WORKS. Non-conformities and proposed corrective
actions shall be properly and systematically documented for COMPANY's appraisal/approval.
CONTRACTOR shall implement corrective action plans as soon as possible.

9.5 Preventing Action
Preventing action/mitigation action shall be proactively initiated against for all non-conformities
shall be detected from various sources of works execution.

F
o
r

I
n
f
o
r
m
a
t
i
o
n


F. Code
Discipline
Code
Doc Type Doc No.
PSR1RJV IN SOW 0004
Doc. Class : B Confidential
Page 48 of 71

PHASE 1B PSR-1 REJ UVENATION PROJ ECT

10.0 INSPECTION, TESTING AND COMMISSIONING


10.1 General
10.1.1 CONTRACTOR shall develop detailed Inspection and Testing Plan for all activities, which
includes acceptance criteria for each activities and submit for COMPANYs approval prior to
procurement. This Inspection and Testing Plan shall be in accordance to PTS 63.10.08.11.
10.1.2 CONTRACTOR shall conduct FAT & SAT for all relevant equipment. CONTRACTOR shall notify
COMPANY at least two (2) weeks before the test for COMPANY to assign the relevant
personnel. COMPANY has the right to witness the test.
10.1.3 CONTRACTOR shall prepare proper documentation such as datasheets, specifications and
forms to be used during testing. Copies of the documents shall be made available to COMPANY.
10.1.4 CONTRACTOR shall provide reports of all necessary inspection/tests in accordance with
statutory requirements, insurance party and the project requirements. These reports shall be in a
form meeting the requirements of such other parties or government agencies, as applicable.
10.1.5 COMPANY may appoint a Third Party Inspection Agency (TPIA) services for the equipment
inspection. TPIA/COMPANY shall have free access to the CONTRACTORs and his SUB-
CONTRACTORs work SITE during execution of the WORKS. CONTRACTOR shall extend the
Inspector in all the possible assistance to witness the tests and to satisfy himself that the
materials furnished in accordance with specification and relevant documents and that
workmanship is satisfactory in every aspect. Inspection by COMPANY or his Inspector will in no
way relieve CONTRACTOR of any of his responsibilities for ensuring that the system supplied
meets all the requirements of this document and its attachments.
10.1.6 CONTRACTOR shall maintain acceptance/rejection forms for all types of inspection and testing,
as specified. These documents shall contain all details as required by the code including details
such as item number, quantity, specification, date of inspection, type of inspection, result, third
party inspection, certificate etc.
10.1.7 All inspection and acceptance tests shall be carried out on the equipment at CONTRACTORs
works and may be witnessed by COMPANY. Inspection by COMPANY or his representatives
shall in no way relieve CONTRACTOR of any of his responsibilities for ensuring that the system /
equipment meets all the requirements and conforms in full to the contents of Scope of Work.
10.1.8 CONTRACTOR shall give COMPANY or his representatives, without charge, all facilities and
access evidences for satisfying himself that the equipment is being manufactured in accordance
with the relevant datasheets, sketches, codes and standards.
10.1.9 Any manufactured part, which does not comply with the requirements, or material which shows
defects during inspection will be rejected. When a part of the unit is rejected, CONTRACTOR
shall be notified in writing. If any rectification work is required to be done, it shall be carried out by
CONTRACTOR at his own expense and without delay to the WORKS.
10.1.10 CONTRACTOR shall prepare complete inspection and report within one (1) week after the event
for COMPANYs review.
F
o
r

I
n
f
o
r
m
a
t
i
o
n


F. Code
Discipline
Code
Doc Type Doc No.
PSR1RJV IN SOW 0004
Doc. Class : B Confidential
Page 49 of 71

PHASE 1B PSR-1 REJ UVENATION PROJ ECT

10.1.11 The required inspections are shown in the following table as minimum:
NO. DESCRIPTION COMPANY

1 Manufacturing Progress Inspection as per request Yes

2 Factory Acceptance Test Procedure Review Yes

3 Factory Acceptance Test Yes

4 Factory Acceptance Test - Punch List Inspection Yes

5 Site Delivery Inspection Yes

6 Site Acceptance Test Procedure Review Yes

7 Site Acceptance Test Yes

8 Site Acceptance Test - Punch List Inspection Yes

9 System Performance Test and Reliability Test Yes

10 Commissioning Yes

10.2 Factory Acceptance Test (FAT)
10.2.1 CONTRACTOR shall ensure the equipments are ready for testing complete with tools,
temporary facilities and consumables necessary for the tests.
10.2.2 CONTRACTOR shall ensure the personnel responsible to conduct testing is competent readily
available and able to brief all relevant personnel before commencement of the tests.

F
o
r

I
n
f
o
r
m
a
t
i
o
n


F. Code
Discipline
Code
Doc Type Doc No.
PSR1RJV IN SOW 0004
Doc. Class : B Confidential
Page 50 of 71

PHASE 1B PSR-1 REJ UVENATION PROJ ECT

10.2.3 For FAT that to be conducted outside of Malaysia, CONTRACTOR shall assign its relevant
personnel and allocate minimum two (2) seats for attendance by COMPANYs personnel.
Travelling and lodging cost for COMPANYs personnel shall be borne by COMPANY. The
notification of the test shall be done at least three (3) weeks before the test.
10.2.4 Apart from visual and mechanical testing, functional testing shall include the simulation of each
input and output to verify proper system response for analogue and digital signals as a
minimum.
10.3 Site Acceptance Test (SAT)
10.3.1 CONTRACTOR shall carry out all site inspections and tests necessary to comply with Project
Specification and to satisfy the requirements to achieve Ready For Start-Up (RFSU).
10.3.2 CONTRACTOR shall inform COMPANY at least two (2) working days in advance before any
site testing and inspection due to commence. CONTRACTOR shall provide the necessary
testing, measuring and calibration facilities and tools prior to any inspection and testing.
10.3.3 CONTRACTOR shall provide proof of proper Construction, with routine checks on the quality
of the WORKS, is in accordance with the Project Specification. If during testing the WORKS is
deemed to be unsatisfactory, CONTRACTOR shall remedy the defects immediately at its own
cost. COMPANY will consider no schedule impact.
10.3.4 COMPANY reserves the right to request, at no cost, any additional tests/inspections during
construction by giving notice in writing to CONTRACTOR, who shall carry out the
test/inspections including the preparatory/restoring works, to prove the WORKS has been
satisfactorily executed.
10.3.5 COMPANY shall be allowed access to inspect all underground WORKS installations prior to
backfill. Any backfills performed prior to such inspection, CONTRACTOR shall re-excavate to
allow inspection to be carried out.
10.3.6 CONTRACTOR shall provide CONTRACTOR specialist to supervise final adjustments and to
inspect and advise during testing, starting-up and running-in, of the equipment installed.
10.3.7 In addition CONTRACTORs representatives shall be present during installation, final
adjustments, testing, running-in, starting-up and initial operation of equipment, in accordance
with purchase agreement.
10.3.8 CONTRACTORs site inspections shall take in account of any local authorities (e.g. DOSH,
DOE), insurance or third party inspection requirements.
10.4 Testing Certificates
10.4.1 Records of all calibrations, testing and conformity checks shall be provided by the
CONTRACTOR. The testing certificates shall be made available by the CONTRACTOR and
approved by COMPANY prior to commissioning. The procedure for site testing and witnessing
shall be agreed in writing by the COMPANY prior to commencement of WORKS.

F
o
r

I
n
f
o
r
m
a
t
i
o
n


F. Code
Discipline
Code
Doc Type Doc No.
PSR1RJV IN SOW 0004
Doc. Class : B Confidential
Page 51 of 71

PHASE 1B PSR-1 REJ UVENATION PROJ ECT

10.5 Site Inspection of Electrical & Instrument Works


10.5.1 Site Installation, Inspection and Testing of Instruments shall be in strict accordance with the
PSR-1 Project Specification and relevant Instrument Standards and Codes.
10.5.2 All test and calibration equipment shall be certified and tested by Standard Industrial Research
Institute of Malaysia (SIRIM) or any third party accredited by SIRIM and shall be approved by
COMPANY.
10.5.3 CONTRACTOR shall supply all necessary calibrated testing equipment and instruments.
10.5.4 All test results shall be recorded in an agreed format with the COMPANYs Construction Team.
Certified copies (signed by a competent person approved by COMPANYs Construction Team)
of the record shall be forwarded to the COMPANYs.
10.5.5 COMPANYs Construction Team shall witness all instrument loop functional tests.

11.0 DOCUMENTATION
11.1 General
11.1.1 CONTRACTORs responsibilities for documentation required as minimum, are outlined in this
section. The documents listed are intended to inform CONTRACTOR as to the level of
documentation submittal required. Specific document requirements shall be as specified by
COMPANY and these requirements will evolve over the course of the project. CONTRACTOR
shall submit Master Document List (MDL) for COMPANY review and approval.
11.1.2 All documentation shall be in English language hardcopy and electronic media.
11.1.3 CONTRACTOR shall furnish documents in native file where applicable upon request by
COMPANY.
11.1.4 CONTRACTOR shall be responsible to update and supersede existing documents from the
original plant design book. This activity shall be clearly supervised by COMPANY personnel.
11.1.5 CONTRACTOR shall furnish documents/drawings that are of suitable first generation quality.
Drawings that are not, in COMPANY's opinion, of suitable quality will be returned to
CONTRACTOR for re-submission or at COMPANY's option may be redrafted by COMPANY or
his representatives to CONTRACTOR's account.
11.1.6 CONTRACTOR will be held liable for all COMPANY costs resulting from errors in
CONTRACTOR's certified prints. CONTRACTOR is cautioned against submitting certified
drawings and data, which have not been checked.
11.1.7 CONTRACTORs responsibilities for documentation required as minimum, are outline in this
section.
11.1.8 Approval by COMPANY shall not relieve CONTRACTOR of any of its responsibilities under the
CONTRACT to provide safe, operable, reliable and efficient system suitable to meet the design
intent and in full compliance with the Project Specification.

F
o
r

I
n
f
o
r
m
a
t
i
o
n


F. Code
Discipline
Code
Doc Type Doc No.
PSR1RJV IN SOW 0004
Doc. Class : B Confidential
Page 52 of 71

PHASE 1B PSR-1 REJ UVENATION PROJ ECT

11.2 Design Books


CONTRACTOR shall provide Design Books which shall contain reference information for the
design and engineering of project and all other parts of the WORKS. The Design Books shall
reflect the WORKS As-Built and contain equipment information As-Built.

11.3 Operating Manual
CONTRACTOR shall provide Operating Manuals, which shall contain the necessary data and
information to operate the equipment.

11.4 QA/QC Manuals
CONTRACTOR shall provide QA/QC Manuals, which shall contain the necessary data and
information of quality control, inspection test plan (ITP), etc.
.
11.5 Supplier Data Books / Manufacturing Data Records
CONTRACTOR shall provide Suppliers Data Books / Manufacturing Data Records for all
purchased equipment and bulk materials including, but not limited to, Supplier Installation,
Operation and Maintenance Manual, Vendor Drawings, Bill of Material, Mill Certificate, NDT
Certificate, Performance and Test Data, Factory Acceptance Test Report (FAT), Type Test
Certificate, Explosion Proof Certificate, any International Body Certification, Local
Authorities/Statutory Approval, etc.

11.6 Construction Data Report
11.6.1 CONTRACTOR shall provide record of J ob Method Statement (J MS), J ob Safety Analysis
(J SA), test procedure, inspection test record, SAT, calibration records, progress reports,
construction drawings, shop drawings, etc.
11.6.2 CONTRACTOR shall submit Work Completion report upon completion of WORKS for
COMPANYs approval.
11.6.3 After completion of the works, all drawings and specifications related to the WORKS shall be
updated and As-Built according to the actual WORKS done at SITE.
11.6.4 COMPANY has made a diligent effort to ensure the accuracy of drawings and documents.
However, it shall be the responsibility of the CONTRACTOR to verify and confirm the accuracy
of the drawings and documents to ensure satisfactory execution of the WORKS.

11.7 Commissioning Manuals
11.7.1 CONTRACTOR shall provide a Commissioning Manual for all equipment, which shall contain the
schedules and procedures for all Commissioning activities.

F
o
r

I
n
f
o
r
m
a
t
i
o
n


F. Code
Discipline
Code
Doc Type Doc No.
PSR1RJV IN SOW 0004
Doc. Class : B Confidential
Page 53 of 71

PHASE 1B PSR-1 REJ UVENATION PROJ ECT

11.8 Commissioning Data Report


11.8.1 CONTRACTOR shall provide a Commissioning Data Report for all equipment, which shall
contain Commissioning Record and Performance Test Record for all Commissioning activities.

11.9 Spare Parts and Interchangeability Record (SPIR)
11.9.1 CONTRACTOR submission of spare parts list shall be in two (2) copies of the completed SPIR
form in accordance with PTS 70.10.90.11, Appendix 1, Guide to Completion of the Spare Parts
List and interchangeability Record SPIR.
11.9.2 CONTRACTOR shall complete all the relevant records as required, such as material
specification, dimension, sizes etc. Completed SPIR forms shall be submitted to COMPANY
three (3) months after the issuance of purchase order of the respective equipment and material.

11.10 Two (2) Years Operational Spare Parts List
11.10.1 CONTRACTOR shall submit a list of spare parts (optional) for the equipment and material, which
are adequate for two (2) years operation and maintenance of the project by COMPANY. The
recommended list complete with schedule of prices shall be submitted along with bid proposal for
review by COMPANY.

11.11 Final Electronic Record
11.11.1 CONTRACTOR shall provide a Final Electronic Record for all the documents and drawings
included in the Design Books, Supplier Data Books, Operating Manuals, QA/QC Manuals,
Construction Data Report, Commissioning Manuals, Commissioning Data Report, Spare parts
and Interchangeability Record (SPIR) and Two (2) Years Operational Spare Parts List.
11.11.2 CONTRACTOR shall ensure the production of all drawings and documents are compatible with
COMPANY electronic format.
11.11.3 All final drawings and documents shall be supplied in CD-ROM in native as well as pdf format.
11.11.4 CONTRACTOR shall provide all documentations in format of one (1) original copy, two (2)
hardcopies and five (5) electronic copies.

11.12 Miscellaneous
11.12.1 All files not formally handed over to COMPANY shall be kept by CONTRACTOR for ten (10)
years after Work Completion, together with supporting software, with provision for reasonable
access by COMPANY. After that time, CONTRACTOR shall consult COMPANY concerning the
disposal of such archived documents.


F
o
r

I
n
f
o
r
m
a
t
i
o
n


F. Code
Discipline
Code
Doc Type Doc No.
PSR1RJV IN SOW 0004
Doc. Class : B Confidential
Page 54 of 71

PHASE 1B PSR-1 REJ UVENATION PROJ ECT

11.13 Document Numbering


CONTRACTOR shall refer to COMPANYs document numbering PMPMS 20114 Technical
Document Numbering System Procedure in ATTACHMENT-1.
11.14 Document Rights
All information/calculation, datasheets/deliverables produced by CONTRACTOR shall be
accessible and belongs to COMPANY and be able to retained by COMPANY in its native
format.
11.15 Punch Listing
11.15.1 CONTRACTOR and COMPANY shall jointly perform Punch listing activities before the
scheduled Work Completion date. The Punch Lists shall cover all items, which have not yet
been fully completed or deviated from the requirements of the project.
11.15.2 CONTRACTOR shall categorize all the Punch Listing in Category A, B, C and D in line with
Punch Listing Procedure in Attachment 2 and 3.





























F
o
r

I
n
f
o
r
m
a
t
i
o
n


F. Code
Discipline
Code
Doc Type Doc No.
PSR1RJV IN SOW 0004
Doc. Class : B Confidential
Page 55 of 71

PHASE 1B PSR-1 REJ UVENATION PROJ ECT

12.0 WORK COMPLETION AND START UP


12.1 Requirements for Pre-Commissioning and Commissioning
CONTRACTOR shall develop a Work Completion, pre commissioning and commissioning/start
up database with check sheets and procedures including punch lists categorization each system
at each stage to ensure that the plant is not attempted to be pre-commissioned, energized or
commissioned/started up with any detrimental defect in the individual systems.

Each of the above stages are to be fully documented and witnessed by the COMPANY and
Third Party inspectorate where required.

12.2 Pre-Commissioning
12.2.1 Pre-Commissioning activities include the preparation of the project for equipment Ready for
Start-Up (RFSU).
12.2.2 Pre-Commissioning refers to activities before Work Completion of the project, to ensure the
project is ready for commissioning. Pre-Commissioning activities shall be performed according
to system priority and systemwise completion.
12.2.3 CONTRACTOR shall notify COMPANY of any planning for Pre-Commissioning activities at least
one or two days in advance. CONTRACTOR shall provide evidence that all appropriate
procedures safety plans/permit to work/safety procedures are in place, and are approved by
COMPANY. Activities which have operational implications shall be conducted under COMPANY
supervision and control.
12.2.4 CONTRACTOR shall prepare detailed procedures for all Pre-Commissioning activities. The
procedure shall be submitted to COMPANY for approval at least three (3) weeks prior to
commencement date of that activity.
12.2.5 The Pre-Commissioning activities on each system/ unit between Work Completion and RFSU
shall be recorded in the system/ unit Completion Manual for each system/ unit.
12.2.6 CONTRACTOR shall ensure the availability of CONTRACTOR specialist at SITE to supervise
activities during pre-commissioning and commissioning activities.
12.2.7 CONTRACTOR shall provide evidence that the system/ unit dossier records are up to date.
12.2.8 COMPANY shall review and sign the report three (3) days after completion of each Pre-
Commissioning activities. CONTRACTOR shall keep complete and accurate records of all Pre-
Commissioning activities and submitted for issuance of MWCC by COMPANY. Issuance of
MWCC is mandatory to ensure that the equipment is ready for smooth startup.
12.2.9 Issuance of MWCC for an equipment/system shall occur when it has been erected, tested and
inspected in accordance with the project requirement, together with complete QA/QC support
documentation as required and the equipment/system is ready for commissioning.


F
o
r

I
n
f
o
r
m
a
t
i
o
n


F. Code
Discipline
Code
Doc Type Doc No.
PSR1RJV IN SOW 0004
Doc. Class : B Confidential
Page 56 of 71

PHASE 1B PSR-1 REJ UVENATION PROJ ECT

12.3 Commissioning
12.3.1 Commissioning of a unit, or section, or an individual system of the PROJ ECT will occur as soon
as it has been pre-commissioned i.e. upon issuance MWCC. Commissioning shall mean those
activities performed by CONTRACTOR after RFSU which include any operating adjustments,
satisfactory completion of which is required to achieve Work Completion in accordance with the
provisions of the conditions of CONTRACT.
12.3.2 CONTRACTOR shall ensure the availability of key personnel at SITE to supervise activities
during pre-commissioning and commissioning activities which include technical support i.e.
manpower, specialist, tools & equipment for initial start-up and commissioning of each system/
equipment following RFSU until the unit has achieved smooth startup with stable operation of
minimum 72 hours.
12.3.3 Commissioning shall be part of CONTRACTORs Scope of Work, which may include simulation,
running, and preparation activities required which is not limited to, e.g.
No load running of mechanical equipments, if applicable, with corresponding adjustments
Simulation of circuits using water, if applicable, with corresponding adjustments
Tests of alarms and interlocks
12.3.4 CONTRACTOR shall provide to COMPANY a detailed commissioning schedule and status
monitoring method.

12.4 Work Completion
12.4.1 Work Completion for all equipment/system is considered to be achieved, after acceptance by
COMPANY and issuance of approval by relevant Local Authority, where applicable.
12.4.2 All documents, forms and procedures required for Work Completion shall be submitted and
approved by COMPANY prior to the application for WCC.
12.4.3 CONTRACTOR shall provide and maintain a single Work Completion Dossier for each system/
equipment, which shall encompass all the requirements from Construction phase up to Work
Completion. The Work Completion Dossier shall include but not limited to the following:
Work Completion Checklist
Equipment List, Factory and Site Acceptance Test Report
Certificates (e.g. MWCC, QA/QC Declaration, etc.)
Punch Listing
Inspection Test Plan records (Summary)
Drawings (e.g. Wiring diagrams, etc.)

F
o
r

I
n
f
o
r
m
a
t
i
o
n


F. Code
Discipline
Code
Doc Type Doc No.
PSR1RJV IN SOW 0004
Doc. Class : B Confidential
Page 57 of 71

PHASE 1B PSR-1 REJ UVENATION PROJ ECT

12.4.4 CONTRACTOR shall inform COMPANY in writing by means of Notice of Work Completion
upon completion of all Punch List items for issuance of WCC.
12.4.5 CONTRACTOR shall complete all the housekeeping in accordance to COMPANYs satisfaction.

12.5 Equipment Performance Test(s)
12.5.1 CONTRACTOR shall perform Performance Test(s) to demonstrate that the project is capable to
meet performance guarantee. All Performance Test(s) shall be conducted by CONTRACTOR
based upon criteria defined by the CONTRACTOR and approved by COMPANY.
CONTRACTOR shall meet the PSR-1 specifications, PTS and/or recognized international
standard for testing requirement and criteria. COMPANY reserves the right to request additional
test deemed necessary for the project at no cost to COMPANY.
12.5.2 The Performance Test(s) shall be lead, coordinated and managed by CONTRACTOR and
assisted by COMPANY. The Performance Test(s) shall be conducted in the presence of
COMPANY.
12.5.3 The Performance Test(s) shall be conducted only after the completion of commissioning works.
12.5.4 CONTRACTOR shall produce Performance Test(s) procedures and submitted to COMPANY for
approval one (1) month before the proposed start date of the test(s). CONTRACTOR shall liaise
closely with COMPANY in developing this procedure to ensure that the test(s) can be carried
out safely within live plant.
12.5.5 CONTRACTOR shall ensure that all instrumentations and ancillary equipment, permanent and
or temporary, required to perform and monitor the Performance Test(s) are ready for prior to the
test(s).
12.5.6 CONTRACTOR shall submit the Performance Test(s) report within one (1) week after the
completion date of the test. COMPANY shall review the report and revert to CONTRACTOR no
later than two (2) weeks from the date of receipt. COMPANY shall officially issue the WCC
backdated to the date of testing upon acceptance and approval of the report. Should there be
defects or deficiencies in the project identified during Performance Test(s), those defects/
deficiencies shall be remedied by CONTRACTOR. The system/ unit shall not be considered to
have passed the Performance Test(s) until the defects/ deficiencies are remedied to the
satisfaction of the COMPANY. CONTRACTOR shall re-conduct the performance test after the
remedial work is completed.
12.5.7 CONTRACTOR shall consolidate and compile all related documents at the end of the WORKS
in a form of a Manufacturing Data Report (MDR) Book and submit to COMPANY for approval.


F
o
r

I
n
f
o
r
m
a
t
i
o
n


F. Code
Discipline
Code
Doc Type Doc No.
PSR1RJV IN SOW 0004
Doc. Class : B Confidential
Page 58 of 71

PHASE 1B PSR-1 REJ UVENATION PROJ ECT

13.0 SPARE PARTS AND SPECIAL TOOLS


13.1 General
13.2 CONTRACTORs responsibilities with regard to provision of spare parts, special tools and
associated services shall inclusive but not limited to the following;
i) Construction and Pre-Commissioning Spare Parts
ii) Commissioning Spare Parts
iii) Spare Part Interchangeability Records
iv) Special Tools

13.3 Construction and Pre-Commissioning Spare Parts
Construction and Pre-Commissioning spare parts covers all spare parts, consumable,
catalysts, chemical and lubricants etc. required for the construction, pre-commissioning,
and commissioning of the project. CONTRACTOR shall include the necessary construction
and pre-commissioning spare parts as part of the WORKS.

13.4 Commissioning Spare Parts
i) CONTRACTOR shall provide commissioning spare parts during the commissioning
period.
ii) CONTRACTOR shall provide all consumable required for the pre-commissioning and
commissioning of the project as part of the WORKS.

13.5 Special Tools
i) CONTRACTOR shall supply to COMPANY all special tools (i.e. HART Handheld
communicator 475) required for operation and maintenance of the project; minimum of
one set of special tool shall be supplied for the WORKS package. The special tools shall
be supplied in a proper enclosure i.e. small box/container with engrave tagging. All
special tools supplied by CONTRACTOR shall be identified by a number system in
accordance standard coding procedure.
ii) All Special Tools shall be handed over to COMPANY prior to the issuance of the WCC.
iii) In the event of CONTRACTOR may need to use the special tools during WORKS
execution, COMPANY may authorize CONTRACTOR for the usage with the
understanding that the CONTRACTOR shall promptly replace the tools if damaged.

F
o
r

I
n
f
o
r
m
a
t
i
o
n


F. Code
Discipline
Code
Doc Type Doc No.
PSR1RJV IN SOW 0004
Doc. Class : B Confidential
Page 59 of 71

PHASE 1B PSR-1 REJ UVENATION PROJ ECT

14.0 WARRANTY AND DEFECT LIABILITY NOTICE


14.1 The Warranty period is twelve (12) months upon issuance of WCC by COMPANY.
14.2 CONTRACTOR shall warrant and guarantee that the WORKS will be performed in a
professional manner, in accordance with good industrial practices, executed to the highest
quality of workmanship, free from defect, fault and fully comply with the requirements stipulated
in the Contract.
14.3 Upon detecting of any defects or fault COMPANY will issue the defect notification and
CONTRACTOR shall expeditiously make good such defect or fault at its own expenses at the
acceptable duration agreed by COMPANY.
14.4 Should CONTRACTOR fail to take expeditious measures to make good such defect or fault,
COMPANY may its discretion make good the defect by itself or employ a third party.
CONTRACTOR shall reimburse all the costs incurred thereby.

15.0 COMPANYS SCOPE
15.1 COMPANY will assign focal person to assist the CONTRACTOR to comply with related permits
and documents required.
15.2 COMPANY will provide limited First Aid medical treatment to CONTRACTOR personnel when
required.
15.3 COMPANY may provide utilities and facilities listed in the followings:
Limited supply of water and steam.
Electricity and assistance for any work requiring electricity. CONTRACTOR shall notify
relevant COMPANY Representative at least one day in advance should CONTRACTOR
require assistance.
Laydown area for the CONTRACTORs usage for their storage area, office area
(Cabin/Field office), etc.
Limited assistance of any form provided the CONTRACTOR notify COMPANY at least
one day in advance.
15.4 COMPANY will conduct final inspection and clearance upon completion of SITE work before
box-up.




F
o
r

I
n
f
o
r
m
a
t
i
o
n


F. Code
Discipline
Code
Doc Type Doc No.
PSR1RJV IN SOW 0004
Doc. Class : B Confidential
Page 60 of 71

PHASE 1B PSR-1 REJ UVENATION PROJ ECT






16.0 ATTACHMENTS
Item Description Document No. Total
Pages
1 Technical Document Numbering
System Procedure
PMPMS20114 14
2 Punch List Procedure for PSR-1
Rejuvenation Project
- 8
3 Punch List Form - 1
4 Work List 15 - MARK-UP Drawings
for Replacement of Displacer Level
Transmitter to Guided Wave Radar
Level Transmitter
PSR1RJ V-IN-TSK-0152 194
5 Guided Wave Radar Level
Transmitters Tag List
- 1



F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n

PROJECT MANAGEMENT & DELIVERY

Author
ABS
Approved By
NAH
Date Approved
23

Jan 2014
Classification
Internal Use Only
Title
PUNCH LIST PROCEDURE FOR PSR-1 REJUVENATION PROJECT
Version
1

Phase 1B PSR1 Rejuvenation Project Punch List Procedure.doc Page 1 of 8

TABLE OF CONTENTS
1.0 OBJECTIVE 2
2.0 DEFINITIONS 2
3.0 PUNCH LIST STRUCTURE 3
4.0 PROCEDURE 4
4.1 Walkdowns 4
4.2 Punch List 4
4.3 Categories 5
4.4 Punch List Coordinator(s) 5
4.5 Punch List Clearance 7
5.0 PUNCH LIST NUMBERING 8
6.0 ATTACHMENTS 8


F
o
r

I
n
f
o
r
m
a
t
i
o
n

PROJECT MANAGEMENT & DELIVERY

Author
ABS
Approved By
NAH
Date Approved
23

Jan 2014
Classification
Internal Use Only
Title
PUNCH LIST PROCEDURE FOR PSR-1 REJUVENATION PROJECT
Version
1

Phase 1B PSR1 Rejuvenation Project Punch List Procedure.doc Page 2 of 8

1.0 OBJECTIVE
The purpose of this procedure is to lay out the method for identification, registration
and clearance of Punch List items for Phase 1B PSR-1 Rejuvenation Project in order
to achieve Mechanical Completion.

2.0 TERMS AND DEFINITIONS
COMPANY Means PETRONAS Penapisan (Melaka) Sdn. Bhd.
(PP(M)SB) (Company No: 164522-v), a wholly owned
subsidiary company of PETRONAS, which owns and/or
operates the Melaka Refinery Complex located in Mukim
Sungai Udang, Tangga Batu, Melaka comprising of
amongst others the PSR-1, the PSR-2 and the MG3 Plant,
and shall include its successors in title and permitted
assigns, and shall, where the context so admits and
requires, also include its employees, agents or designated
representatives.
CONTRACT Means the contract entered into between the COMPANY
and the CONTRACTOR for the WORKS in accordance with
the terms and conditions contained herein including all
articles, exhibits and any other documents attached hereto
or incorporated by reference including any subsequent
amendments to them.
CONTRACTOR Means Party(ies) entering into this CONTRACT with the
COMPANY for the performance of the WORKS as set forth
in this CONTRACT and includes the CONTRACTORs
personnel, representatives, successors and authorized
parties.
MWCC, WCC MWCC is Mechanical Work Completion Certificate. It is a
hand over document to Plant Operation to safely
commission the equipment.
WCC is Work Completion Certificate where the warranty
shall commence from the date stipulated on the certificate.
PROJECT Shall have the similar meaning as per the CONTRACT
Preambles.
Punch List Item Is an item which has not been installed and / or erected
according to the approved specifications and / or erection
documents or that is required to be modified as a result of
safety or operability requirements.
Punch Identification Means identification and registration of Punch List items.
F
o
r

I
n
f
o
r
m
a
t
i
o
n

PROJECT MANAGEMENT & DELIVERY

Author
ABS
Approved By
NAH
Date Approved
23

Jan 2014
Classification
Internal Use Only
Title
PUNCH LIST PROCEDURE FOR PSR-1 REJUVENATION PROJECT
Version
1

Phase 1B PSR1 Rejuvenation Project Punch List Procedure.doc Page 3 of 8

Punch Clearance Is physical completion, correction or rectification of the
identified Punch List items.
SIGN-OFF Is the process of obtaining signatures confirming the
completion of a Punch item and verification for its closure.
SITE(S) Means the areas or places as designated by the
COMPANY where the WORKS is to be performed or
delivered, as further specified in EXHIBIT I SCOPE OF
WORKS.
SUB-CONTRACTOR Means Party(ies) including but not limited to supplier,
vendor and/or companies performing construction work(s)
that has or have entered into a contract, directly or indirectly
with the CONTRACTOR, for the performance of any part of
the WORKS.
WORKS Means the work to be performed and rendered by the
CONTRACTOR or its SUB-CONTRACTOR, as expressly
set forth in this CONTRACT, which is more particularly
described in EXHIBIT I SCOPE OF WORKS and all of
CONTRACTORs and/or its SUB-CONTRACTORs
activities that are reasonably inferable from the description
of the said scope of WORKS, including any other activity
which is not specified in this CONTRACT but which in the
course of the WORKS becomes necessary for completion
to be effected.

3.0 PUNCH LIST STRUCTURE
There shall only be one Punch List for a particular System. Any Punch List item
identified on any walkdown by any party shall be registered into the Punch List of
that particular System.
A Punch List for a System shall exist from the first walkdown onwards, (e.g.
Walkdown No. 1, Walkdown No. 2, and so on) until Provisional Acceptance or until
such time as all items have been cleared, resolved or re-assigned.
It is a condition that all Punch List items shall be cleared prior to the issuance of
WCC, unless deemed otherwise by COMPANY.
Attachment 1 indicates the Punch List form.


F
o
r

I
n
f
o
r
m
a
t
i
o
n

PROJECT MANAGEMENT & DELIVERY

Author
ABS
Approved By
NAH
Date Approved
23

Jan 2014
Classification
Internal Use Only
Title
PUNCH LIST PROCEDURE FOR PSR-1 REJUVENATION PROJECT
Version
1

Phase 1B PSR1 Rejuvenation Project Punch List Procedure.doc Page 4 of 8

4.0 PROCEDURE
4.1 Walkdown
In order to verify the installation of a System has been accomplished
according to Approved For Construction (AFC) drawings, Technical
Specifications and relevant documentation, a number of walkdowns shall be
conducted as follows:
i. Walkdown No. 1 A Construction walkdown involving CONTRACTORs
construction personnel. Among the purposes of the walkdown is to verify
that lines, motor vessels, tanks, etc. are ready to be tested and that all the
necessary work has been completed to allow the subsequent test to be
safely executed. Any Punch List items identified during this walkdown shall
be categorized as Category A, which indicates that the Punch List items
need to be resolved and verified, prior to inviting COMPANY
representative to execute Walkdown No. 2.
ii. Pre-Walkdown No. 2 CONTRACTOR shall issue the Inspection Request
(IR) with Punch List identified for all disciplines including after
Commissioning after completing the Pre-Commissioning system flushing /
blowing, reinstatements and loop checking of the particular System. This
Pre-Walkdown No. 2 shall capture as early as possible category A items
prior to Notice of MWCC. With this approach, the Walkdown No. 2 is only
for COMPANYs verification of category A items cleared, thus expediting
the COMPANYs approval in MWCC Notification.
iii. Walkdown No. 2 Following issuance of Notice of MWCC of a System,
COMPANYs representative shall attend a walkdown in Contractors
presence to satisfy itself that the System is mechanically complete to verify
category A items are cleared.
iv. Walkdown No. 3 - Following issuance of Notice of MWCC, COMPANYs
representative shall attend a walkdown in to satisfy itself that the System is
Ready For Start Up. CONTRACTORs Commissioning Manager shall
attend the walkdown with COMPANYs personnel.
COMPANYs personnel shall only attend the scheduled walkdown(s) through
the IR procedure, after receiving the fully signed-off Punch List items
generated by CONTRACTOR for a particular System.
4.2 Punch Parties
Individual Punch parties consist of the followings:
a) A CONTRACTOR Construction Walkdown (Walkdown No. 1) which will
include: CONTRACTORs Punch List Coordinator, Area Manager,
Discipline Manager, Engineering Discipline representative, SUB-
CONTRACTOR personnel.
F
o
r

I
n
f
o
r
m
a
t
i
o
n

PROJECT MANAGEMENT & DELIVERY

Author
ABS
Approved By
NAH
Date Approved
23

Jan 2014
Classification
Internal Use Only
Title
PUNCH LIST PROCEDURE FOR PSR-1 REJUVENATION PROJECT
Version
1

Phase 1B PSR1 Rejuvenation Project Punch List Procedure.doc Page 5 of 8

b) A joint COMPANY and CONTRACTOR Walkdown (Walkdown No. 2) will
include: COMPANY personnel, Punch List Coordinators, Construction
Managers, Area Manager, Discipline Manager, Commissioning Managers,
Engineering Discipline representative, Supervisors or Operators from
COMPANY.
c) A joint COMPANY and CONTRACTOR Walkdown (Walkdown No. 3) will
include: COMPANY personnel, Punch List Coordinators, Construction
Managers, Area Manager, Discipline Manager, Commissioning Managers,
Engineering Discipline representative, Supervisors or Operators from
COMPANY.
4.3 Punch List
A Punch List item shall be generated if, during any of the walkdown, any item
of outstanding work or error or omission, or if the System has not been built in
accordance with the AFC Engineering drawings, Technical Specifications and
relevant Documentation.
Each Punch List item in a System shall be uniquely numbered and entered
into database for tracking of the clearance process. From the database,
CONTRACTOR shall be able to produce Punch Lists by System. The list shall
constitute a work to go list prior to a System being ready to be taken to the
next phase of the Project.
The Originator of the Punch List items and the date on which the originator
identified the defect will be identified against the Punch List item and shall be
responsible to ensure that the identified Punch List item is cleared or resolved.
4.4 Categorization of Punch List Items
All Punch List items shall be categorized in accordance to the time when the
item shall be cleared. Only when all the items identified by category have been
cleared for a particular System, the next phase of the PROJECT can
commence.
The Punch List categories are:
i. Category A Punch List items for a System shall be cleared and verified,
by CONTRACTOR prior to COMPANYs Acceptance of MWCC.
ii. Category B Punch List items for a System shall be cleared and verified,
by CONTRACTOR prior to Commissioning.
iii. Category C Punch List items for a System shall be cleared and verified,
by CONTRACTOR prior to COMPANYs issuance of WCC.
iv. Category X items that are disputed. A Punch List Resolution Form is
attached in which the scheduled meeting between COMPANY &
CONTRACTOR shall be conducted to determine the agreement before
approval of the MWCC Notification.
F
o
r

I
n
f
o
r
m
a
t
i
o
n

PROJECT MANAGEMENT & DELIVERY

Author
ABS
Approved By
NAH
Date Approved
23

Jan 2014
Classification
Internal Use Only
Title
PUNCH LIST PROCEDURE FOR PSR-1 REJUVENATION PROJECT
Version
1

Phase 1B PSR1 Rejuvenation Project Punch List Procedure.doc Page 6 of 8

Following a walkdown, CONTRACTORs Punch List Coordinator shall issue to
CONTRACTORs Construction Manager or Commissioning Manager all
Punch List items that resulted from the walkdown.
For CONTRACTOR Construction Walkdown, the Punch List Coordinator, the
Commissioning Manager and the Construction Manager shall sit and obtain
consensus on the categories of all Punch List items. In the event of a
disagreement, the matter shall be referred to CONTRACTORs Project
Director / Deputy Project Director for resolution, which their decision will be
final.
For Walkdown that includes COMPANYs personnel, the COMPANYs Punch
List Coordinator shall provide CONTRACTORs Punch List Coordinator with
the Punch List items duly categorized for distribution to CONTRACTORs
Construction Manager or Commissioning Manager.
Should any disagreement arise with COMPANYs Punch List or categorization
of items in COMPANYs Punch List, CONTRACTORs Punch List Coordinator,
Construction Manager and / or Commissioning Manager shall meet with
COMPANYs designated personnel to resolve the issue.
In the event that an agreement failed to be obtained, the matter shall be
referred to CONTRACTORs Project Director / Deputy Project Director, PMT
Project Director and PMC Project Manager for resolution, which their decision
will be final.
Failure to resolve the issue shall constitute a Dispute under the CONTRACT.
4.5 Punch List Coordinator(s)
Both the CONTRACTOR and COMPANY shall nominate a Punch List
Coordinator who shall liaise with each other on all matters related to Punch
List items and shall be responsible to ensure that:
Walkdown are to be scheduled and set up
Punch List items are properly recorded
Any duplications are deleted
Parties who shall be attending the walkdown are duly notified
Punch List items are cleared and signed off by the Originator of the item
Hardcopy and electronic copy of each Punch List item is being maintained
Identify and record all signatures
Each Punch List item is correctly categorized
Reports are issued as required by COMPANY
Note: CONTRACTORs Punch List Coordinator shall be responsible for
Contractor Punch List on all of the above. COMPANYs nominated Punch List
F
o
r

I
n
f
o
r
m
a
t
i
o
n

PROJECT MANAGEMENT & DELIVERY

Author
ABS
Approved By
NAH
Date Approved
23

Jan 2014
Classification
Internal Use Only
Title
PUNCH LIST PROCEDURE FOR PSR-1 REJUVENATION PROJECT
Version
1

Phase 1B PSR1 Rejuvenation Project Punch List Procedure.doc Page 7 of 8

Coordinator shall be responsible for COMPANYs generated Punch List on all
of the above.
4.6 Punch List Clearance
Copies of the discipline Punch List items for each System shall be issued to
CONTRACTORs Discipline Managers who shall be responsible for clearance
of the Punch List items.
Once a Punch List item has been resolved, CONTRACTORs Discipline
Manager shall sign and date the Punch List to confirm that the particular item
has been cleared. It shall be the responsibility of the Originator of a Punch List
item to ensure that the item is cleared, resolved or re-assigned.
Contractors Discipline Manager will then give the original Punch List to
CONTRACTORs Punch List Coordinator who shall register the details into the
database and file the signed off hardcopy Punch List for future reference.
For CONTRACTOR generated Punch List items, CONTRACTORs Punch List
Coordinator shall advise the Originator of the Punch List item that the item has
been cleared. For COMPANY generated Punch List, the responsibility shall be
upon COMPANYs Punch List Coordinator.
If the Originator is satisfied that the Punch List item has been cleared, the
Punch List shall be signed and returned to the Punch List Coordinator who
shall register the details into the database and file the hardcopy Punch List for
future reference.
In the event that the Originator does not agree that the Punch List Item has
been cleared, the issue needs to be resolved with CONTRACTORs Discipline
Manager.

F
o
r

I
n
f
o
r
m
a
t
i
o
n

PROJECT MANAGEMENT & DELIVERY

Author
ABS
Approved By
NAH
Date Approved
23

Jan 2014
Classification
Internal Use Only
Title
PUNCH LIST PROCEDURE FOR PSR-1 REJUVENATION PROJECT
Version
1

Phase 1B PSR1 Rejuvenation Project Punch List Procedure.doc Page 8 of 8

5.0 PUNCH LIST NUMBERING
Predefined and numbered punch lists shall be utilized to record all punch items. This
will ensure that all items, packages and systems are punched and to minimize
duplication.
Punch Lists shall commence with Walkdown No. 1, the same list shall be forwarded
to Pre-Commissioning / Commissioning / Licensor and finally forwarded to the Joint
Inspection Team for the final punch out in Walkdown No.3.
This Punch List shall be the Master Punch List and shall be utilized to control the
punching activity.
- All punch lists shall be predefined and uniquely numbered.
- The unit number, to which the punch list refers, followed by a Discipline Code and
then by a unique number, shall predefine each assigned punch list. As certain
items are not uniquely assignable to a specific unit, PROJECT shall prefix them
instead of the unit number.

Numbering examples:
Unit No Discipline Unique Number Description Item
19 Mechanical K1901 Rotating
equipment
Compressor
19 Mechanical C1901 Static equipment Column
PROJECT XX SCR 8 Common item SCR No.8
19 Piping 19PA01 Piping system Plant air

6.0 ATTACHMENTS
Attachment 1 Punch List Form


End of Document
F
o
r

I
n
f
o
r
m
a
t
i
o
n
INSERT
CONTRACTOR'S PUNCH LIST FORM
LOGO EQUIPMENT/TAG NO: . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
AREA/TESTPACK/ISO . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Page:
PUNCH LIST NO: REV: CONTRACT NO:
DRAWING NO: REV: CONTRACTOR:
CATEGORY COMPLETION
Item Initiator REMEDIAL WORKS CONTRACTOR INITIATOR
DISCIPLINE: DATE SIGN DATE SIGN
"A" - Before acceptance of Mechanical Work Completion Certificate
"B" - Before Commissioning
"C" - Before issuance of Work Completion Certificate
"X" - Disputed Items
Petronas Penapisan (Melaka) Sdn. Bhd.
A B C X
Phase 1B PSR-1 Rejuvenation Project
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n





F. Code Discipline
Code
Doc Type Doc No.
PSR1RJV IN TSK 0152
Doc. Class : B Confidential
Page 2 of 2

PHASE 1B PSR-1 REJ UVENATION PROJ ECT


TABLE OF CONTENT


ITEM DESCRIPTION DOC / DWG NOS. NO. OF SHTS
1 Drawing and Specifications V-2173-P31-A-001 185
2
Project Specification for Displacement
Type Level Instrument
S-00-1373-032 7


F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
F
o
r

I
n
f
o
r
m
a
t
i
o
n
Item Unit TagType SeqNo. ServiceDescription Inst.Type I/OType IS/NonIS PIDNo. Equipment System Remarks
1 11 LICA 025 C1110TankLevel GuidedWaveRadar AI IS 111225023 C1110 DCS
2 11 LZA 053 V1101TankLevel GuidedWaveRadar AI IS 111225008 V1101 ESD
3 11 LICA 015 V1102TankLevel GuidedWaveRadar AI IS 111225016 V1102 DCS
4 11 LICA 002 V1103TankLevel GuidedWaveRadar AI IS 111225004 V1103 DCS
5 11 LISA 010 V1104TankLevel GuidedWaveRadar AI IS 111225012 V1104 DCS
6 11 LIA 017 V1107TankLevel GuidedWaveRadar AI IS 111225017 V1107 DCS
7 11 LZA 057 V1107TankLevel GuidedWaveRadar AI IS 111225017 V1107 ESD
8 11 LICA 018 V1108TankLevel GuidedWaveRadar AI IS 111225018 V1108 DCS
9 11 LICA 021 V1109TankLevel GuidedWaveRadar AI IS 111225020 V1109 DCS
10 11 LIA 027 V1113TankLevel GuidedWaveRadar AI IS 111225025 V1113 DCS
11 11 LICA 005 V1115TankLevel GuidedWaveRadar AI IS 111225011 V1115 DCS
12 11 LICA 503 V1151TankLevel GuidedWaveRadar AI IS 111225056 V1151 DCS
13 11 LIA 506 V1152TankLevel GuidedWaveRadar AI IS 111225058 V1152 DCS
14 11 LICA 507 V1152TankLevel GuidedWaveRadar AI IS 111225058 V1152 DCS
15 12 LIA 001 V1201TankLevel GuidedWaveRadar AI IS 121225001 V1201 DCS
16 12 LICA 004 V1202TankLevel GuidedWaveRadar AI IS 121225004 V1202 DCS
17 12 LICA 005 V1202TankLevel GuidedWaveRadar AI IS 121225004 V1202 DCS
18 12 LIA 007 V1203TankLevel GuidedWaveRadar AI IS 121225005 V1203 DCS
19 12 LZA 057 V1203TankLevel GuidedWaveRadar AI IS 121225005 V1203 ESD
20 12 LIA 008 V1204TankLevel GuidedWaveRadar AI IS 121225005 V1204 DCS
21 12 LZA 058 V1204TankLevel GuidedWaveRadar AI IS 121225005 V1204 ESD
22 12 LIA 009 V1205TankLevel GuidedWaveRadar AI IS 121225005 V1205 DCS
23 12 LZA 059 V1205TankLevel GuidedWaveRadar AI IS 121225005 V1205 ESD
24 12 LICA 011 V1206TankLevel GuidedWaveRadar AI IS 121225011 V1206 DCS
25 12 LIA 013 V1208TankLevel GuidedWaveRadar AI IS 121225012 V1208 DCS
26 13 LICA 004 C1301TankLevel GuidedWaveRadar AI IS 131225006 C1301 DCS
27 13 LZA 014 C1301TankLevel GuidedWaveRadar AI IS 131225006 C1301 ESD
28 13 LICA 002 E1307TankLevel GuidedWaveRadar AI IS 131225005 E1307 DCS
29 13 LICA 001 V1301TankLevel GuidedWaveRadar AI IS 131225004 V1301 DCS
30 13 LICA 003 V1302TankLevel GuidedWaveRadar AI IS 131225005 V1302 DCS
31 13 LICA 006 V1304TankLevel GuidedWaveRadar AI IS 131225008 V1304 DCS
32 13 LIA 008 V1311TankLevel GuidedWaveRadar AI IS 131225010 V1311 DCS
33 13 LIA 007 V1312TankLevel GuidedWaveRadar AI IS 131225009 V1312 DCS
34 13 LICA 437 V1334TankLevel GuidedWaveRadar AI IS 131225056 V1334 DCS
35 14 LIA 002 A1401TankLevel GuidedWaveRadar AI IS 141225002 A1401 DCS
36 14 LICA 007 C1401TankLevel GuidedWaveRadar AI IS 141225004 C1401 DCS
37 14 LICA 010 C1402TankLevel GuidedWaveRadar AI IS 141225005 C1402 DCS
38 14 LZA 014 C1402TankLevel GuidedWaveRadar AI IS 141225005 C1402 ESD
39 14 LICA 001 V1401TankLevel GuidedWaveRadar AI IS 141225001 V1401 DCS
40 14 LZA 013 V1401TankLevel GuidedWaveRadar AI IS 141225001 V1401 ESD
41 14 LICA 003 V1402TankLevel GuidedWaveRadar AI IS 141225002 V1402 DCS
42 14 LICA 004 V1402TankLevel GuidedWaveRadar AI IS 141225002 V1402 DCS
43 14 LICA 008 V1406TankLevel GuidedWaveRadar AI IS 141225004 V1406 DCS
44 14 LICA 009 V1406TankLevel GuidedWaveRadar AI IS 141225004 V1406 DCS
45 14 LICA 011 V1408TankLevel GuidedWaveRadar AI IS 141225006 V1408 DCS
46 14 LIA 012 V1408TankLevel GuidedWaveRadar AI IS 141225006 V1408 DCS
47 14 LISA 005 V1409TankLevel GuidedWaveRadar AI IS 141225003 V1409 DCS
48 15 LICA 003 C1501TankLevel GuidedWaveRadar AI IS 151225002 C1501 DCS
49 15 LIA 004 C1501TankLevel GuidedWaveRadar AI IS 151225002 C1501 DCS
50 15 LISA 001 V1501TankLevel GuidedWaveRadar AI IS 151225001 V1501 DCS
51 15 LICA 002 V1501TankLevel GuidedWaveRadar AI IS 151225001 V1501 DCS
52 16 LICA 002 A1603TankLevel GuidedWaveRadar AI IS 161225004 A1603 DCS
53 16 LZA 005 V1609TankLevel GuidedWaveRadar AI IS 161225008 V1609 ESD
54 16 LZA 006 V1609TankLevel GuidedWaveRadar AI IS 161225008 V1609 ESD
55 51 LICA 002 V5101TankLevel GuidedWaveRadar AI IS 511225002 V5101 DCS
56 51 LICA 003 V5101TankLevel GuidedWaveRadar AI IS 511225002 V5101 DCS
57 51 LICA 004 V5102TankLevel GuidedWaveRadar AI IS 511225003 V5102 DCS
58 51 LICA 501 V5104TankLevel GuidedWaveRadar AI IS 511225007 V5104 DCS
59 51 LIA 006 V5105TankLevel GuidedWaveRadar AI IS 511225007 V5105 DCS
60 51 LICA 005 V5106TankLevel GuidedWaveRadar AI IS 511225004 V5106 DCS
61 58 LISA 003 E5804TankLevel GuidedWaveRadar AI IS 581225001 E5804 DCS
62 58 LIA 004 V5801TankLevel GuidedWaveRadar AI IS 581225004 V5801 DCS
63 64 LICA 001 A6401TankLevel GuidedWaveRadar AI IS 641225004 A6401 DCS
64 64 LISA 002 V6401TankLevel GuidedWaveRadar AI IS 641225004 V6401 DCS
65 64 LISA 005 V6402TankLevel GuidedWaveRadar AI IS 641225004 V6402 DCS
66 66 LSA 016 V6663TankLevel GuidedWaveRadar AI IS 661225006 V6663 DCS
GuidedWaveRadarLevelTransmittersList
Page1of1
F
o
r

I
n
f
o
r
m
a
t
i
o
n


F. Code
Discipline
Code
Doc Type Doc No.
PSR1RJV IN SOW 0004
Doc. Class : B Confidential
Page 61 of 71

PHASE 1B PSR-1 REJ UVENATION PROJ ECT











EXHIBIT II SPECIFICATIONS
PART A: PROCEDURES AND
REQUIREMENTS











F
o
r

I
n
f
o
r
m
a
t
i
o
n


F. Code
Discipline
Code
Doc Type Doc No.
PSR1RJV IN SOW 0004
Doc. Class : B Confidential
Page 62 of 71

PHASE 1B PSR-1 REJ UVENATION PROJ ECT

PART A: PROCEDURES AND REQUIREMENTS


1.0 GENERAL PROCEDURES
1.1 CONTRACTOR is responsible to provide proper design, mechanical reliability and metallurgical
fitness of the materials supplied for the WORKS.
1.2 CONTRACTOR is responsible to include any materials, which are not indicated in the drawings
but are required to complete the WORKS.
1.3 CONTRACTOR shall submit Vendors work application procedure of product (where necessary) to
COMPANYs review and approval.
1.4 All materials supplied by CONTRACTOR shall be as per existing specifications and PTS selected
standards. CONTRACTOR shall highlight and obtain COMPANYs approval for any deviations
from PTS or COMPANY procedures.
1.5 CONTRACTOR shall execute WORKS in compliance with all PTS standards and requirements.
CONTRACTOR shall highlight and obtain COMPANYs approval for any deviations from PTS
standards and requirements.
1.6 CONTRACTOR shall supply Manufacturers Test Certificates for all supplied materials.
1.7 In the event of dimensional or quantity differences occur, reduction or addition in prices shall be
proportionately calculated based on the awarded price. Price variation based on Unit Rates, as
listed in the schedule of rates / prices shall be used.
1.8 CONTRACTOR shall engage COMPANY term contractor for scaffolding services. Scaffolding
shall be part of the Lump Sum cost.
1.9 All scaffolding shall be constructed as per COMPANY refinery standard for scaffolding according
to British Standards BS 1139.
1.10 Scaffold materials and erected scaffolding shall be inspected and approved by COMPANY
Representative before being used. Only metal planks shall be used for the erection of Platform.
1.11 CONTRACTOR shall be fully responsible for the co-ordination within his SUB-CONTRACTOR for
materials and services provided.
1.12 Prior to installation of any instruments/devices, CONTRACTOR shall perform procedure test to
demonstrate its method and equipment will operate in accordance with the design requirements.
The test is to assure adequately represent as per manufacturers requirements.
F
o
r

I
n
f
o
r
m
a
t
i
o
n


F. Code
Discipline
Code
Doc Type Doc No.
PSR1RJV IN SOW 0004
Doc. Class : B Confidential
Page 63 of 71

PHASE 1B PSR-1 REJ UVENATION PROJ ECT

1.13 A successful test qualifies the procedure and workers for installation of the actual
instruments/devices. The demonstration and test shall be proposed by CONTRACTOR and
witnessed by COMPANY Representative.
1.14 CONTRACTOR shall exert his greatest care not to avoid the cause of damaging any nearby
equipment and materials when removing and installing the required instrument/devices eg. to
cover with a wooden plate or other means.
1.15 CONTRACTOR shall provide manpower support through-out the commissioning activity for the
WORKS.
1.16 CONTRACTOR shall constantly check updates on the logistic schedule for WORKS provided by
the COMPANY on a fortnightly basis. CONTRACTOR shall be required to seek approval from the
COMPANY to the jetty berth prior commissioning of WORKS.
1.17 CONTRACTOR shall comply to PTS HSE requirements at all times.
1.18 At the end of each working day, CONTRACTOR is responsible to clear the working area and
dispose all rubbish and debris in properly tied rubbish containers and transport them to location
(temporary storage) within the designated by COMPANY.
1.19 At the end of the WORKS, a joint inspection between CONTRACTOR and COMPANY
representative will be held to determine the completion of the housekeeping activity.
1.20 CONTRACTOR shall comply to Malaysian Laws and applicable regulatory requirements.
1.21 Unless otherwise specified, the CONTRACTOR will be responsible for all contact with governing
regulatory agencies for obtaining all required permits. Any clarifications regarding compliance with
regulatory requirements or technical information required to obtain permits are to be directed to
the CONTRACTOR.
1.22 CONTRACTOR shall submit an Inspection and Test Plan (ITP) for verification and testing of the
WORKS.
1.23 CONTRACTOR shall notify COMPANY for inspection or testing three (3) working days
prior to the planned inspection or testing dates.




F
o
r

I
n
f
o
r
m
a
t
i
o
n


F. Code
Discipline
Code
Doc Type Doc No.
PSR1RJV IN SOW 0004
Doc. Class : B Confidential
Page 64 of 71

PHASE 1B PSR-1 REJ UVENATION PROJ ECT

2.0 CONTRACTORS OBLIGATION


2.1 The CONTRACTOR shall
a) Supply, construct, complete test and commission the WORKS in accordance with the
CONTRACT.
b) Perform the WORKS in a proper manner expected of a CONTRACTOR providing similar
WORKS to ensure that the WORKS comply with the requirements of this CONTRACT.
c) Take all appropriate measures expected of a CONTRACT or providing similar WORKS to
ensure that the WORKS comply with the requirements of this CONTRACT.
d) Perform the WORKS and discharge its obligations as contained in this CONTRACT by
exercising professional judgment and practice, requisite skill, care and diligence. In
performing the WORKS, the CONTRACTOR shall provide well-outlined procedures in the
form agreed by the COMPANY for reporting and co-ordination purposes.
e) At all times perform the WORKS in such manner as will always safeguard and protect the
COMPANYs interest in relation to the WORKS and take all necessary and proper steps
to prevent abuse or uneconomical use of facilities, if any, made available by the
COMPANY to the CONTRACTOR.
f) Inform the COMPANY immediately in writing of the occurrence of any factor or event,
which is likely to affect the WORKS. Such notification shall not be construed as a
discharge of any of the CONTRACTORs obligation under this CONTRACT.
g) Provide and maintain throughout the CONTRACT period such number, categories of
qualified and competent personnel necessary to perform the WORKS.
h) Provide and maintain at its own cost and expense all equipment and materials necessary
for the proper and effective performance of the WORKS.
i) Instruct and supervise its staffs and SUB-CONTRACTOR in carrying out the WORKS
repairs and other works in relation to the WORKS.
j) Make good any defect, imperfection, shrinkage or any other fault whatsoever which may
appear during the defects liability period.
k) Carry out any other obligations and responsibilities under this CONTRACT.


F
o
r

I
n
f
o
r
m
a
t
i
o
n


F. Code
Discipline
Code
Doc Type Doc No.
PSR1RJV IN SOW 0004
Doc. Class : B Confidential
Page 65 of 71

PHASE 1B PSR-1 REJ UVENATION PROJ ECT

3.0 INSPECTION OF SITE


3.1 The CONTRACTOR shall be deemed to have inspected and examined the SITE and its
surroundings and to have satisfied himself before SITE possession as to the following:
a) The nature of the equipment, ground and subsoil.
b) The form and nature of the SITE.
c) Verification of the asset items specified in Exhibit I, Part B herein.
d) The extent and nature of the WORKS, materials and goods necessary for the completion
of the WORKS.
e) The means of communication with and access to the SITE.
f) The accommodation may require.
g) In general to have obtained for himself all necessary information as to risks,
contingencies and all circumstances influencing and affecting his WORKS.
3.2 Any information or document forwarded by the COMPANY to the CONTRACTOR shall not relieve
the CONTRACTOR of his obligations under the provisions of this clause.













F
o
r

I
n
f
o
r
m
a
t
i
o
n


F. Code
Discipline
Code
Doc Type Doc No.
PSR1RJV IN SOW 0004
Doc. Class : B Confidential
Page 66 of 71

PHASE 1B PSR-1 REJ UVENATION PROJ ECT









EXHIBIT II SPECIFICATIONS
PART B: STANDARD AND
SPECIFICATIONS

F
o
r

I
n
f
o
r
m
a
t
i
o
n


F. Code
Discipline
Code
Doc Type Doc No.
PSR1RJV IN SOW 0004
Doc. Class : B Confidential
Page 67 of 71

PHASE 1B PSR-1 REJ UVENATION PROJ ECT

PART B: STANDARD AND SPECIFICATIONS


1.0 APPLICABLE CODES AND STANDARDS
As a minimum, all WORKS / equipment supplied as part of this package shall be designed,
manufactured and delivered in accordance with the relevant sections of the National /
International Codes, Standards and Regulations, whether the equipment or services are
supplied by CONTRACTOR directly or by a SUB-CONTRACTOR. All documents referenced
herein shall be the latest edition, revision or addendum in effect and form an integral part of this
requisition / specification. Equivalent alternatives may be offered and these should be identified
and mutually agreed on CONTRACTOR shall meet or exceed the requirements of the latest
edition of the following codes, regulations and standards, except as superseded herein. In the
event that there are discrepancies or conflicts with items or information contained within the
document specified by COMPANY, the following order of precedence shall applied.
a. Malaysian Law and Regulation, Local Authorities and By-Laws.
b. Purchase Order / Contract
c. Instructions and requirements contained in the project specification
d. PETRONAS Technical Standard (PTS), including Standard Drawings and Standard
Specifications
e. The relevant Group HSE standards
f. PSR-1 Design Specifications
g. Other National and International Codes and Standards

Any resolution of the conflicts or discrepancies shall be brought to COMPANY attention for
review and approval prior to commencement of any pertaining issues.
In cases of conflict in requirements between documents in the same level of the hierarchy, the
most stringent requirement shall apply. CONTRACTOR shall provide its interpretation in writing
for COMPANYs approval. In all such cases of conflict, COMPANYs decision shall be final.
All deviations from the requirements of this specification, its appendices and the referenced
codes and standards shall be described in the proposal. In the absence of such a statement, full
compliance shall be assumed.
Compliance by CONTRACTOR to this specification does not relieve him of the responsibility to
furnish equipment of a proper design for the described service conditions and/or to meet the
equipment of local government regulations concerning health and safety.
1.1 Disclosure of PETRONAS Technical Standards (PTS)
CONTRACTOR is only allowed to divulge PTS publications to its SUB-CONTRACTORs on a
need to know basis for the WORKS with conditions that the party(ies) has entered into a
Secrecy Agreement.
In all other cases, CONTRACTOR shall extract relevant information from the PTSs for inclusion
in the specifications to be prepared.
F
o
r

I
n
f
o
r
m
a
t
i
o
n


F. Code
Discipline
Code
Doc Type Doc No.
PSR1RJV IN SOW 0004
Doc. Class : B Confidential
Page 68 of 71

PHASE 1B PSR-1 REJ UVENATION PROJ ECT

CONTRACTOR is obliged to verified with COMPANY prior to Contract Award that the applicable
PTS publications (including amendments covered in PTS circulars), the Standard Drawings, the
Standard Specifications are complete and up-to-date.
1.2 Legislati ve Documents (as applicable)
Design of equipment shall comply with the requirements of the following Malaysian legislations:
i) Electrical Supply Act 1990
ii) Electrical Regulation 1994
iii) Factories and Machinery Act 1967
iv) Occupational Safety and Health Act 1994
v) Petroleum Safety Measures Act 1984
These shall include subsequent amendments. Areas where specific requirements will apply
shall include lifting equipment, identification and handling of hazardous equipment as well as
guarding of machinery.
1.3 Malaysian Codes and Regulation
i) OSHA 1994

ii) Industry Code Of Practice For Safe Working In A Confined Space 2010 (ICOP)

iii) Environment Quality Act 1974 (EQA)

iv) Factory and Machinery Act 1967 (FMA)

1.4 COMPANYS PROCEDURES
i) PSR-1 Design Specification S-00-13A0-001: Specification for Painting
ii) HSEMS-20200: Waste Management
iii) Requirements To Perform Works Within Sungai Udang Port Limits





F
o
r

I
n
f
o
r
m
a
t
i
o
n


F. Code
Discipline
Code
Doc Type Doc No.
PSR1RJV IN SOW 0004
Doc. Class : B Confidential
Page 69 of 71

PHASE 1B PSR-1 REJ UVENATION PROJ ECT

1.5 Listing of Codes, Standards and Regulations


The latest edition of the following codes, standards and regulations shall be followed as
applicable.
1.5.1 PETRONAS TECHNICAL STANDARDS

PTS 30.10.60.18 Welding of Metals
PTS 30.48.00.31 Protective Coatings and Lining
PTS 31.38.01.11 Piping - General Requirements
PTS 32.31.00.10

Instrumentation Engineering Procedure

PTS 32.31.00.32

Instrumentation for Measurement and Control

PTS 32.31.00.34

Instrumentation Documents and Drawings

PTS 32.37.10.11

Installation of Online Instruments

PTS 32.37.20.10

Instrument Signal Lines

PTS 33.64.10.10 Electrical Engineering Guidelines
PTS 33.64.10.11 Lightning Protection System (LPS) (Supplement to IEC 62305)
PTS 33.64.10.33 Electromagnetic Compatibility (EMC) Requirements
PTS 62.10.08.11

Inspection and Functional Testing of Instruments

PTS 63.10.08.11 Field Commissioning and Maintenance of Electrical Installations and
Equipment
PTS 70.10.90.11

Spare Parts
PTS 82.00.10.10 Project Quality Assurance


































F
o
r

I
n
f
o
r
m
a
t
i
o
n


F. Code
Discipline
Code
Doc Type Doc No.
PSR1RJV IN SOW 0004
Doc. Class : B Confidential
Page 70 of 71

PHASE 1B PSR-1 REJ UVENATION PROJ ECT

1.5.2 INTERNATIONAL CODES AND STANDARDS



IEC 60079 Electrical Apparatus for Explosive Gas Atmosphere
IEC 60529 Degree of Protection provided by Enclosures
IEC 61000 Electromagnetic Compatibility
IEC 61508 Functional Safety of Electrical/Electronic/Programmable Electronic Safety-
Related System
BS EN ISO 9001 Quality Management Systems
BS EN 60529 Specification for Degree of Protection Provided by Enclosure
BS 729 Hot Dip Galvanized Coatings on Iron and Steel Articles
BS 4360 Weld able Structural Steel
BS 1139 Metal Scaffolding
BS 4872 Approval Testing of Welding Procedures
1.6 PSR-1 Project Specifications and Drawings
CONTRACTOR shall review PSR-1 Project Specifications and Drawings related with the
WORKS as enclosed in this document. CONTRACTOR shall retrieve the remaining PSR-1
Project Document deem necessary for execution of the WORKS from COMPANYs Library with
supervision by COMPANYs personnel.
In the event of any of the listed document is not available in COMPANYs Library,
CONTRACTOR shall perform site verification and carry out necessary measurement and
produce as-built document. The As-Built document shall be submitted to COMPANY as part of
the project deliverable.

F
o
r

I
n
f
o
r
m
a
t
i
o
n


F. Code
Discipline
Code
Doc Type Doc No.
PSR1RJV IN SOW 0004
Doc. Class : B Confidential
Page 71 of 71

PHASE 1B PSR-1 REJ UVENATION PROJ ECT

1.7 Regulatory Permit and Approval


Where required, CONTRACTOR shall liaise with the local authority having jurisdiction and the
by-laws to be complied with in order to execute the construction work e.g. Department of
Occupational Safety and Health (DOSH), Department of Environment (DoE), Majlis Bandaraya
Melaka Bersejarah (MBMB), J abatan Bomba dan Penyelamat (BOMBA), Suruhanjaya Tenaga
(ST) and others third parties having jurisdiction or interest in this PROJ ECT as necessary
throughout the execution of the WORKS.
CONTRACTOR shall be responsible to apply for all necessary Permits from governmental
bodies and local authorities. CONTRACTOR shall provide all information and documents
required to enable these permits to be obtained.
CONTRACTOR and its SUB-CONTRACTORs shall be registered with the Construction
Industries Development Board of Malaysia prior to undertaking any Construction Work. All
CONTRACTORs and its SUB-CONTRACTORs personnel working in the Construction SITE
shall possess a valid CIDB Green Card.

2.0 EQUIPMENT SPECIFICATIONS AND DATASHEETS
This section is not applicable.
3.0 ENGINEERING SPECIFICATIONS
This section is not applicable.





END OF DOCUMENT