You are on page 1of 102

Hengam Offshore Development Project EPCI For

Topsides and Infield Pipelines and Subsea Cables


Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 1 of 102

STRUCTURAL FABRICATION
SPECIFICATION

B4 18.Oct.2013 Re-Issue as AFD J.W.LIM PUREE ARUN H.KARIMI
B3 12.Mar.2013 Re-Issue as AFD S.M.ROH M.Y.SHIN Puree
B2 07.Jan.2013
Approved for
Design
S.M.ROH M.Y.SHIN
B1 21.Sep.2012
Issued for
Approval
S.M.ROH M.Y.SHIN
B0 11.Jul.2012
Issued for
Comment
S.M.ROH M.Y.SHIN
Rev. Date Purpose of Issue
Prep. Checked/Approved Approve Approve
ISI / Ocean Development GS Offshore IOOC

Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 2 of 102




INPUTS
Document Number Title Status






















REVISONS & HOLDS
Revision Description of Changes & Holds




















Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 3 of 102

TABULATION OF REVISED PAGES
Sheet
Revisions
Sheet
Revisions
B0 B1 B2 B3 B4 B0 B1 B2 B3 B4
1 X X 36 X X
2 X 37 X
3 X 38 X
4 X 39 X
5 X 40 X
6 X 41 X
7 X 42 X
8 X 43 X
9 X X 44 X
10 X X 45 X
11 X 46 X
12 X X 47 X
13 X X 48 X
14 X X 49 X
15 X X 50 X
16 X X 51 X
17 X X 52 X
18 X X 53 X
19 X X 54 X
20 X X 55 X
21 X 56 X
22 X X 57 X
23 X 58 X
24 X 59 X
25 X 60 X
26 X 61 X
27 X 62 X
28 X 63 X
29 X 64 X
30 X 65 X
31 X 66 X
32 X 67 X
33 X 68 X
34 X 69 X
35 X 70 X

Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 4 of 102

TABULATION OF REVISED PAGES
Sheet
Revisions
Sheet
Revisions
B0 B1 B2 B3 B4 B0 B1 B2 B3 B4
71 X 106
72 X 107
73 X 108
74 X 109
75 X 110
76 X 111
77 X 112
78 X 113
79 X 114
80 X 115
81 X 116
82 X 117
83 X 118
84 X 119
85 X 120
86 X 121
87 X 122
88 X X 123
89 X 124
90 X 125
91 X 126
92 X 127
93 X 128
94 X 129
95 X 130
96 X 131
97 X 132
98 X 133
99 X 134
100 X 135
101 X 136
102 X 137
103 138
104 139
105 140

Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 5 of 102


Table of Contents
1. GENERAL ................................................................................................................................. 9
1.1 Scope of Specification ..................................................................................................................................9
1.2 Definitions and Abbreviations ................................................................................................................. 10
1.3 Applicable Codes and Standards ............................................................................................................ 12
1.4 Structural Classes ....................................................................................................................................... 15
1.5 Materials ...................................................................................................................................................... 16
2. WELDING .............................................................................................................................. 17
2.1 General ......................................................................................................................................................... 17
2.2 Definitions ................................................................................................................................................... 17
2.3 Weld Class ................................................................................................................................................... 18
2.4 Welding Processes ..................................................................................................................................... 18
2.5 Consumables ............................................................................................................................................... 20
2.6 Storage and Handling of Consumables ................................................................................................. 22
2.7 Documentation ........................................................................................................................................... 24
2.8 Welding Book ............................................................................................................................................. 25
3. WELDING PROCEDURES .................................................................................................... 27
3.1 General ......................................................................................................................................................... 27
3.2 Welding Procedure Specifications .......................................................................................................... 28

Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 6 of 102

3.3 Qualification of Welding Procedures ..................................................................................................... 29
3.4 Qualified Principal Positions .................................................................................................................... 30
3.5 Validity of Welding Procedures (essential variables) .......................................................................... 30
3.6 Testing .......................................................................................................................................................... 33
3.7 Special Test.................................................................................................................................................. 41
4. WELDERS AND WELDING OPERATORS ......................................................................... 46
4.1 General ......................................................................................................................................................... 46
4.2 Qualifications .............................................................................................................................................. 47
4.3 Retests .......................................................................................................................................................... 49
5. PRODUCTION WELDS ........................................................................................................ 50
5.1 General ......................................................................................................................................................... 50
5.2 Welding Sequences .................................................................................................................................... 53
5.3 Temperature ................................................................................................................................................ 53
5.4 Repairs .......................................................................................................................................................... 53
5.5 Closure Welds ............................................................................................................................................. 56
5.6 Stress Relieving Post Weld Heat Treatment ......................................................................................... 59
5.7 Welding Parameter Checking .................................................................................................................. 61
6. FABRICATION ...................................................................................................................... 62
6.1 General ......................................................................................................................................................... 62
6.2 Forming ........................................................................................................................................................ 62

Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 7 of 102

6.3 Welded Connections .................................................................................................................................. 64
6.4 Welded Attachments ................................................................................................................................. 68
6.5 Site Assembly .............................................................................................................................................. 68
6.6 Manufactured And Miscellaneous Items ............................................................................................... 69
6.7 Finishing of Surfaces ................................................................................................................................. 69
6.8 Rat Holes ..................................................................................................................................................... 70
6.9 Bolted Connections .................................................................................................................................... 70
7. PREFABRICATED ITEMS TOLERANCES ........................................................................... 71
7.1 Fabricated Tubular Nodes and Cones .................................................................................................... 71
7.2 Rolled or Fabricated Beam ....................................................................................................................... 76
7.3 Stiffened Plate Panels ............................................................................................................................... 78
7.4 Other Fabrication Details .......................................................................................................................... 80
8. FINAL FABRICATION TOLERANCES ................................................................................ 82
8.1 Position of Nodes ...................................................................................................................................... 82
8.2 Deck Plans ................................................................................................................................................... 82
8.3 Handrails ...................................................................................................................................................... 84
8.4 Walkways, Landings and Stairways ........................................................................................................ 84
9. INSPECTION OF WELDMENTS ......................................................................................... 85
9.1 General ......................................................................................................................................................... 85
9.2 Definitions ................................................................................................................................................... 85

Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 8 of 102

9.3 Reference Standards .................................................................................................................................. 86
9.4 Methods of NDT ........................................................................................................................................ 86
9.5 Extent of NDT ............................................................................................................................................. 87
9.6 Edge Inspection .......................................................................................................................................... 88
9.7 Qualification of NDT Procedures ............................................................................................................ 88
9.8 Qualification of NDT Personnel .............................................................................................................. 90
9.9 Visual Inspection Execution ..................................................................................................................... 91
9.10 Radiographic Testing Execution .......................................................................................................... 91
9.11 Ultrasonic Testing Execution ................................................................................................................ 92
9.12 Magnetic Particle Inspection Execution ............................................................................................. 94
9.13 Standards of Acceptability ................................................................................................................... 96
9.14 Reports ..................................................................................................................................................... 99
10. TESTING OF FIELD INSTALLED COMPONENTS .......................................................... 101
10.1 Preassembly Testing ............................................................................................................................ 101
10.2 Hydraulic and Pneumatic Testing ..................................................................................................... 101
10.3 Testing of Packers System.................................................................................................................. 102



Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 9 of 102

1. GENERAL
The Hengam Field is located in the Persian Gulf at approximately 45 km south of Qeshm Island. Iranian
Offshore Oil Company (IOOC) has awarded HENGAM offshore development EPCI project to Intelligent
Solutions Inc. and Ocean development LLC. Joint Venture to perform Basic & Detailed Engineering, as
well as procurement, fabrication, installation, pre-commissioning & commissioning for:
Topside facilities of three offshore wellhead platforms
Infield pipe lines
Submarine composite Cable (Power, Control, Fiber optic) from offshore to onshore facilities.

1.1 Scope of Specification
This specification covers the minimum requirements for fabrication and construction of WHP
Topside decks of the Hengam Offshore Development Project..
This specification contains general requirements: construction drawings shall prevail over this
specification.

As such, the contents of this specification define the minimum requirements for the fabrication but does
not cover the inspectors activity during phases of qualification, fabrication and testing such activity
procedure shall be produced during detail design and fabrication stage.

The detailed specification shall be subject to approval by the Company.
The following topics shall be addressed:
i. Definition of structural classes.
ii. Handling, control, quarantine and storage of materials, including receipt.
iii. Inspection, conformity with specification and unidentified materials.
iv. Gases for gas shielded processes.
v. Requirements for welding procedure qualifications including essential variables.
vi. Preparation and fit-up joint.
vii. Drawings and fabrication documents.
viii. Ring stiffeners, cones and splices where applicable.
ix. Rat holes.
x. Fabrication of nodes where applicable.
xi. Local fabrication tolerances, circumference, ovality, out-of-straightness, mismatch etc.
xii. Girders, plate sections.
xiii. Fabrication tolerances (global).
B4
B4
B4

Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 10 of 102

xiv. Decks and modules.
xv. Piles.
xvi. Conductors, J tubes and risers.
xvii. Handrails, landings, floor plate and secondary steel.
xviii. Extent of non-destructive testing.
xix. Attachment of anodes.
xx. Testing of grouting systems.
xxi. Bolted connections.
xxii. Sketches:
Location of test specimens for plate PQR.
Location of test specimens for tubular PQR.
Location of test specimens for T-butt PQR.
PQR for welded joints - location of impact specimens.
Weld toe grinding.
Beam splices allowed zones.
Tolerances on ring stiffeners.
Web stiffeners.
Measuring centre line and best fit line definition.
Tolerances on legs and piles.
Tolerances on shear plate.
xxiii. Temporary work erection sequences and calculations for elements greater than 100 tonnes.
xxiv. Fabrication documents.

1.2 Definitions and Abbreviations
Project HENGAM offshore development EPCI project
Company Iranian Offshore Oil Company (IOOC)
EPCI Contractor means Company mentioned in the Contract as part of the "other part"
and includes its successors and permitted assignees. (ISI/ODCO)
Contract means the Contract made between the Company and the
Contractor and comprises the documents stated in the Agreement to
form the Contract.
Work means the work and other obligations to be performed by Contractor
as described in the Contract.

Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 11 of 102

Vendor means anyone who provides goods or services to the Company. A
vendor often manufactures and/or sells their products to a customer.
Shall / Is to be indicates a mandatory requirement.
Should indicates recommended.
May indicates a freedom of choice.
Fabrication Drawings means drawings by Contractor that contain all the necessary
information required to fabricate items at shop and yard level.
Assembly sequence drawings and temporary support drawings are
considered fabrication drawings
As-built Drawings means fabrication drawings, issued by Contractor, on which are
reported all the information on how the construction has been actually
built. Assembly sequence drawings and temporary support drawings
need no to be issued in as-built version, except that all attachments
left onto the structure shall be reported on as-built drawings.
Fabrication means built-up of single items, generally executed in a shop.
na not applicable
nr not required
Re minimum specified yield strength
Rm tensile strength
t thickness
NDT Non Destructive Test
Parent Plate rolling unit, also mother plate
Material Grade level of yield strength
Material Quality additional measured mechanical characteristics such as Charpy-V,
through thickness properties (Z), guaranteed mechanical
characteristics after stress relieving heat treatment (R)
Closure Weld weld on tubular with inside diameter of 600 mm or greater without back
gouging; generally they are welds made on diagonal tubular after row
roll-up
Insert rolling unit, also mother plate



Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 12 of 102

1.3 Applicable Codes and Standards
For items not specially covered by this specification, the latest editions of the following codes and
standards in the order shown below shall be used:

AWS Structural Welding Code D1.1
API RP 2A Recommended Practice for Planning, Designing and Constructing Fixed Offshore
Platforms Working Stress Deign
API RP 2X Recommended Practice for Ultrasonic Examination of Offshore Structural
Fabrication and Guidelines for Qualification of Ultrasonic Technicians, Standard
1104 NDT (Para. 9
API 2B API Specification for Fabricated Structural Steel Pipe
API 2H API Specification for Carbon Manganese Steel Plate for Offshore platform Tubular
Joints
API 5L API Specification for Line Pipe
API 2W Specification for Steel Plates for Offshore Structures Produced by Thermo
Mechanical Control Processing
API 2Y Specification for Steel Plates, Quenched and Tempered for Offshore Structures
AISC Structural Welding Code-Steel
AWS B1.11 Guide for the Visual Inspection of Welds
AWS A5.5 pecification for Low Alloy Steel Covered Arc Welding Electrodes
AWS A5.12 Specification for Tungsten Arc Welding Electrodes
AWS A5.17 Specification for Carbon Steel Electrodes and Fluxes for Submerged Arc Welding
AWS A5.18 Specification for Carbon Steel Filler Metals for Gas Shielded Arc Welding
AWS A5.20 Carbon Steel Electrodes for Flux Cored Arc Welding
AWS A5.23 Specification for Low Alloy Steel Electrodes and Fluxes for Submerged Arc
Welding
EEMUA 158 Construction specification for fixed offshore structures
IACS Consumable Classification from Institutes members of the IACS International
Association Classification
EN 288 Specification and approval of welding procedures for metallic material (Para. 3)
BSI 709 Methods of destructive testing fusion welded pressure vessel welding
procedures (Para. 3)
BSI 5500 Specification for unfired fusion welded pressure vessel local out roundness
(Para. 7)
B4

Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 13 of 102

EN 287 Approval testing of welders-Fusion welding Part 1 (Para. 5)
EN 10025 Hot rolled products of non-alloy structural steels and their technical delivery
conditions production weld (Para. 5)
EN 10002 Metallic materials-Tensile Testing-Part 1
EN 10045 Charpy impact test on metallic materials, Charpy-V Specimen (Para. 3)
EN 10204 Types of Inspection document
BS 3692 Specification for ISO metric precision hexagon bolts, screws and nuts.
BS 3643 ISO metric screw threads, Part 1 'Thread data and standard Thread series'
BS 4190 Specification for ISO metric black hexagon bolts, screws and nuts
BS 729 Hot Dipped galvanized coatings on iron and steel articles.
BS EN 462 Non-Destructive testing image quality and radiographs Part 1-5
EN 970 Non-Destructive Examination of fusion weld
EN ISO 9934-1 Non-Destructive Testing Magnetic particle
ASNT-TC1A Recommended Practice, Personnel Qualification and Certification in
Non-Destructive Testing
ASTM A6 General Requirements for Rolled Steel Plates, Shapes, Sheet Piling, and Bars for
Structural Use.
ASTM A36 Structural Steel
ASTM A53 Pipe, Steel, Black and Hot-Dipped, Zinc-Coated Welded and Seamless
ASTM A106 Seamless Carbon Steel Pipe for High-Temperature Service
ASTM A120 Pipe, Steel, Black and Hot Dipped Zinc-Coated (Galvanized) Welded and
Seamless, for Ordinary Uses
ASTM A123 Zinc (Hot-Galvanized) Coatings on Iron and Steel Products
ASTM A307 Carbon Steel Externally Threaded Standard Fasteners
ASTM A325 High Strength Bolts for Structural Steel Joints
ASTM A370 Mechanical Testing of Steel Products
ASTM A500 Cold Formed Welded and Seamless Carbon Steel Structural Tubing in Rounds
and Shapes
ASTM A563 Carbon and Alloy Steel Nuts
ASTM A572 High-Strength Low Alloy Columbium-Vanadium Steels of Structural Quality
ASTM B695 Coatings of Zinc Mechanically Deposited on Iron and Steel
ASTM F436 Hardened Steel Washers for Use with High Strength Bolts
ASTM A490 Specification for quenched and tempered alloy steel bolts for structural steel
B4
B4
B4

Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 14 of 102

joints.
ASTM A578 Specification for straight beam ultrasonic examination of plain and clad steel
plates for special applications
ASTM 633 Specification for normalized high strength low alloy structural Steel.
ASTM A193 Alloy steel nuts for bolts for high pressure and high Temperature Service
ASTM A320 Standard Specification for Alloys-Steel bolting Materials for Low Temperature
Service
ASTM F568 Specification for Carbon and Alloy Steel Externally Threaded Metric Fasteners
SA 435/435M Specification for straight beam ultrasonic examination of steel plates.
ANSI B1.1 United Screw Threads (UN & UNR Thread Form)
ANSI B18.22 Square and Hex Nuts
ANSI B 18.22.1 Lock Washers

Materials which shall be certified by Certifying Authority shall be in accordance with the relevant codes
of the Certifying Authority.
B4

Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 15 of 102


1.4 Structural Classes
For the scope of this document the structural elements of the offshore installations are subdivided in
classes. Their definition is as follows:
Structural
Classes
Definition Topside Decks
a Structural elements essential for the safety
of the platform with low structural
redundancy, complex shape and stresses
concentration not easily foreseeable
Not typical nodes with complex geometry
b Structural elements essential for the global
safety of the platform
Typical nodes with simple geometry; Lifting
padeyes and their connection to the deck;
Legs; Tubular and beam elements situated
between two legs; Main girder; Main deck
node & connection; Cans; Crane pedestal;
Flare and bridge supports
c Essential structural elements for the total
structure safety with simple geometry and
with fatigue stress not dimensioning
Beams with height higher or equal to 300mm
or thickness higher than 15mm; Primary
columns and braces; Structural wall; Bridge
structure and flare; Crane boom rest; rotating
equipment support beam; stiffener at node on
primary beam (thicker than 15mm)
d Significant structural elements for the local
safety of the structure
Beams with height lower than 300mm and
thickness up to 15mm; secondary columns
and braces, floor plate and hatch cover for
strength member; sea fastening; equipment
support; Handling support & monorail;
stiffener of secondary structure
e Unimportant structural elements and non-
structural elements
Checkered plates; Stairs and walkway, Not
structural walls; Draining system; Ladder;
Handrail; Grating; Access & service; floor
plate and hatch cover for non-strength
member; Pipe & handling supports
B4

Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 16 of 102


This classification does not consider structural elements that are removed after platform installation, but
includes those items, although removed, they are fundamental (buoyancy tanks, lifting aids etc.).

Appendix-A shows typical decks structural elements relevant class. Construction drawings may indicate
specific information about structural element class. Ambiguous cases relevant to structural element
class shall be cleared by Company.

Structural elements which are removed from the platform after its installation are excluded from this
classification, (i.e. rigging platform, temporary stairs, etc.,). However, those which are removable but
essential for the successful installation of the structures, (i.e. bumpers, guides , lift.ng padeyes,etc.)
shall be included

1.5 Materials
All steels to be used shall comply with HEN-0000-ST-SP-0001, Structural Steel Material Specification.


B4

Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 17 of 102

2. WELDING
2.1 General
All structural welding shall be in accordance with the requirements of this specification and latest of
AWS D1.1, and in case of any deficiency use of other standards shall be subjected of Company
approval.

Steel backing strips, out of closure welds, may be used upon Companys approval only, and in
accordance with the section 3.7.4.

2.2 Definitions
The following definitions are used:
SMAW shielded metal arc welding (using manual equipment)
SAW submerged arc welding (using automatic equipment)
GTAW gas tungsten arc welding (using manual equipment)
GMAW gas metal arc welding
GSFCAW gas shielding flux cored arc welding
SSFCAW self shielding flux cored arc welding
WPS welding procedure specification
WPQR welding procedure qualification record
HAZ heat affected zone
WM weld metal
FL fusion line
KCV set in HAZ Charpy V test set, consisting of three (3) groups of three (3) specimens
each from the following lines: fusion line (FL=50% WM and 50% HAZ),
FL plus 2mm, FL plus 5mm, for a total of 9 specimens
KCV set in WM Charpy V test set, consisting of three (3) specimens in weld centerline
TM thermomechanically controlled rolled (base material):
thermomechanical rolling process carried out with a rigid control of both
plate temperature and rolling grade
Q&T quenched and tempered (base material)

B4

Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 18 of 102

2.3 Weld Class
The welds to be executed are grouped in classes, corresponding to the structural element classes, of
which they maintain the same name.
Different requirements on applicable welding processes, mechanical characteristics, NDT type and
percentage, defects acceptability combinations are defined for each weld class.

In welded joints between elements of different structural classes the higher structural element class
shall govern.
2.4 Welding Processes
2.4.1 Acceptable Welding Processes
The approval is to be obtained prior the use of the process in production begins.
All welding fabrication of structures shall be accomplished with low hydrogen processes.
Welding processes for structural classes of components are listed in table 2.1.
Other welding processes could be employed under Company approval.
Table 2.1 Joint Type and Weld Class

Structural Element Class = Weld Class
a b C d e
Butt
SAW
SMAW
GS/SSFCAW
SAW
1
st
run GS/SSFCAW GTAW SMAW
T butt
SAW
SMAW
GSFCAW
SAW
SMAW
GS/SSFCAW
SMAW
1
st
run GTAW SMAW
Fillet
SAW
SMAW
GSFCAW
SAW
SMAW
GS/SSFCAW
GMAW
GS/SSFCAW
Closure
Na
SMAW
GSFCAW
SMAW
GS/SSFCAW
GMAW
1
st
run GTAW SMAW
Seal SMAW GS/SSFCAW GMAW


Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 19 of 102

The use of GTAW shall be limited to the first passes where second side is not accessible. GTAW shall
be utilized only with direct current, straight polarity.

First run on principal tubular longitudinal double side welds may be carried out by GMAW process
providing it is completed removed prior to back passes are executed.

The use of narrow gap welding processes is permitted only upon Companys approval. In this case
full details about the process, the consumables, the NDT techniques, the relevant applications and the
previous experience are to be documented.

2.4.2 Restrictions of Welding Processes
The following procedures require the following positions:
SMAW all positions, except vertical down
SAW flat position in general, horizontal position for fillet weld only
GMAW flat position in general, horizontal position for fillet weld only and with
spray arc technique
GS/SSFCAW all positions (except the vertical down for class e structures only),
under Companys approval only, after a documented experience is
furnished to Companys satisfaction

Welding procedures shall not exceed the following limits:
SMAW for heat input exceeding 3 kJ/mm; bead width exceeding 16mm or
4 times the core wire diameter
SAW for heat input exceeding 3 kJ/mm
GTAW when adequate environmental shielding is not provided
GSFCAW for heat inputs exceeding 3 kJ/mm: when adequate environmental
shielding is not provided
SSFCAW shall not be used with heat inputs exceeding 1.5 kJ/mm or less than
0.6 kJ/mm.
shall not be used without the voltage and wire-feed speed set and
locked.
shall not be used in combination with SAW without special
prequalification tests supervised by the Companys representative, and
shall only be used using the vertical down, stringer bead technique.
B4
B4

Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 20 of 102

ALL welding on materials less than 30mm thickness with a heat input
exceeding 3 kJ/mm; square edge butt welds greater than 8mm
thickness; welding on second side of a joint without back gouging
except for SAW procedures using the punch-through technique; single-
ass fillet welds (other than by submerged arc) with a leg length greater
than 7mm; use of ceramic inserts.

The following are permitted only with the Companys approval:
The use of other welding processes.
The use of narrow gap welding.
The use of supplementary consumables (powder additions, hot wire additions etc).
The use of ceramic inserts.
The use of backing strips.
Single-pass fillet welds.

In such cases, full details about the process, the consumables, the NDT techniques, the intended
application and the Vendors previous experience in meeting the requirements of this specification with
the proposed process are to be documented. The approval is to be obtained prior to the submission of
the WPS.
2.5 Consumables
All consumables shall be subject to approval by the Companys representative.
The use of consumables is subject to meeting the welding procedure qualification requirements.

Consumables to be used shall have chemical composition similar to and have a yield strength not lower
than the base material. The use of consumables with yield strength higher than 100MPa of base
material are not allowed.

Consumables to be used for welded joints between steels having different yield strength shall be those
applicable to the higher strength steel.

The use of filler metals giving a low diffusible hydrogen deposit (less than 5 cm
3
per 100g of weld metal,
carried out with mercury measurement method, or humidity equal to 0.2% of the weld metal weight,
according to AWS D1.1.) is compulsory when one of the following conditions is fulfilled:

B4
B4

Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 21 of 102

Welds in classes a, b, c
Weld thickness greater than 10mm
Specified Minimum Yield Strength of one of the parts to be joined equal to or greater
than 275MPa

Electrodes in sealed boxed shall have the hydrogen level certified.

Electrodes classification shall conform to AWS. Electrodes classified conform to other specifications or
codes are accepted provided correspondence and in that case the WPQ has in the name an essential
variable All electrodes, according to the reference code or specification, shall be marked.

2.5.1 SMAW
Electrodes for SMAW shall conform to AWS specification A5.5 classification E7015-A1, or E7016-A1,
E7018-A1, E8016-C3, E8018-C3, and AWS A5.1 classification E7015, E7016, E7018 and E7028 (the
last one for fillet weld only).

2.5.2 SAW
Wires and fluxes for SAW shall conform to AWS specification A5.17 classification F7XX-EXXX or
F6XX-EXXX or AWS specification A5.23 classification F7XX-EXXX-Al or FSXX-EXXX-Al.

2.5.3 GTAW
Rods for GTAW shall conform to AWS specification A5.18 and electrodes shall conform to AWS
specification A5.12.

2.5.4 GMAW
GMAW consumables shall be in accordance with AWS specification A5.18 (classes ER 70S2, ER
70S3, ER 70S6, ER 70S7). Processes with 100% CO
2
are not allowed; gas mixtures with 80% Ar and
20% C02 are acceptable.


Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 22 of 102

2.5.5 GSFCAW and SSFCAW
Consumables shall be in accordance with AWS specification A5.20 (classes E70nl-T6 E70nl-T8). Gas
mixture normally used is that with 80% Ar and 20% CO
2
, with consumables classes E70nl-Tl and E
70nl-T5. Other type of gas mixture may be applied after Company approval.

2.5.6 Gases
CO
2
is to have a purity grade not lower than 99.8% and a dew point not higher than 45C below zero.

Argon and Helium are to have a purity grade not lower than 99.99% and a dew point not higher than
45C below zero.

Gases are to be supplied in bottles where type is to be clearly indicated. Fixed distribution networks
are to be clearly identified in their content. Heaters for CO
2
are to be used.

2.6 Storage and Handling of Consumables
The Contractor shall obtain manufacturers test certificates of welding consumables used on the project.
The certificates shall include the following information:
Chemical composition
Tensile and charpy properties (if applicable)
Particle size distribution (if applicable)

All consumables shall be supplied in sealed moisture proof containers capable of maintaining the
consumables free from moisture for at least six months.

Unopened containers shall be stored in a dry location where the temperature shall not be less than
20C and the relative humidity shall not exceed 50%.

Electrodes, fluxes and wires that have been contaminated by water, oil, grease, or all other deemed
unsuitable, or unmarked consumables shall not be employed in the work and shall be removed from the
worksites.

Company may require an additional monthly test (or two months in shop) and whenever he
considers that the consumable baking and maintaining procedure are applied in wrong way.
B4
B4

Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 23 of 102


On any electrode batch and on any flux lot, a moisture test in accordance with AWS specification A5.5,
may be carried out at Company's discretion. Samples shall be taken from ovens where electrodes and
fluxes are stored, ready for production use. The maximum moisture content by weight for low hydrogen
consumables shall be 0.2% for electrodes and 0.1% for fluxes.

Company reserves the right to verify the consumables chemical and mechanical characteristics by
destructive testing.

2.6.1 Electrodes
Low hydrogen electrodes shall be baked for 2 hours at 350/450C, unless otherwise recommended by
the supplier. Thermocouple, which shall be previously calibrated shall be placed at midheight owen.
Initial drying may be omitted in case the electrodes are supplied in fully sealed packs with a
guaranteed hydrogen level content.

After withdrawing from ovens for use, electrodes shall be contained in heated portable quivers at a
temperature not lower than 70C and shall be used within 4 hours. (manufacturer or supplier
recommendation shall be considered)

Electrodes not used within above time limit may be rebaked, provided they are in good conditions.
Redrying is generally acceptable to a maximum of 2 times.

Electrodes that shall not be immediately applied may be stored in ovens at a temperature not lower
than 100C after baking.

In alternative electrodes characterized by a low hydrogen level maintainment after box opening may
be used. Those electrodes are commercially available in packages equal to a workday or half workday.
Anyway Company may require a test to verify the characteristical performance of those electrodes.

If these electrode types are used, those unemployed, at the day end, shall not be employed again.




Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 24 of 102

2.6.2 Fluxes
Low hydrogen fluxes storage, usage and rebaking requirements shall be as for electrodes.

The maximum amount of recycled flux used for welding shall not exceed 30% of the total (70%
minimum new flux). Fluxes may be recycled aspirating from welding and filtered to eliminate impurity
before mixing with new one.

The Contractor shall provide a handling and recycling procedure including details of baking, use of
heated hoppers, recovery system and circumstances in which flux is deemed unsuitable and scrapped.

2.6.3 Wires
Wires storage, usage and re baking shall be the same as for electrodes.

To avoid porosity, gas holes, hot cracking and low electrical contact, wires shall be free from grease
and moisture.

Current swing avoidance during welding shall be avoided through a regular coil speed.

At the workday end all the automatic welding coil winders shall be emptied as to avoid wire moisture
contamination.

2.7 Documentation
Prior to commencement of any part of the fabrication, the Contractor shall submit the following
documentation for approval by the Company:

Fabrication procedures, welding sequence and erection sequence;
Fabrication drawings including plate seam arrangement drawings and plate cutting drawings
with weld details;
Drawings and calculations of temporary works, inclusive of support points, jacking points and
sling points;
List of proposed welding consumables and Supplier;
Qualified welding procedures and repair welding procedures;
Certificates of welded and welding operators qualified;
Certificates of any fabricator supplied material;

Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 25 of 102

Key plans showing unambiguous member identification and weld making scheme;
Procedure for heat treatment of welds and their areas of applications;
Procedures for non-destructive testing and inspection and associated personnel qualification;
Cold Forming and straightening procedure;
Identification and control procedures for material;
Procedure for dimension control of tolerances during fabrication.

In accordance with the provisions given in following sections.

2.8 Welding Book
Before the beginning of the works, the Contractor shall prepare a welding book covering all the welding
operations to be performed. This book shall be permanently available to the Company on the site where
the welding is to be carried out.

It shall comprise:

Identification sketches or a list of welded joints per type
A summary of the accepted welding procedures with their qualifications
All welding procedure specifications which shall be applied
Destructive and non destructive testing, specifying the technique used for the latter

WPQ and WPS that shall be carried out during fabrication shall be added to be welding book.

For each welding procedure qualification shall be indicated:

the references(s) of the qualification certificate(s) specifying the range of thicknesses and
covered diameters together with maximum CEV qualified for steels with Re > 275MPa
the welding procedure qualification records, with the testing record certificates and inspection,
during fabrication, certificates of the base and filler metals
the chemical composition and the carbon equivalent CEV of the test pieces (for steels with a
minimum specified yield strength higher than or equal to 275MPa only)
For each welding procedure specification shall be indicated:


Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 26 of 102

base material grade (when the grade actually used is be different from that initially foreseen
on the drawings, this shall be indicated)
the joint configuration before and after welding (size and tolerance); passes number; if a
temporary or permanent backing is used; the grade of the backing material, the precision of the
backing fit, the method of removal (if foreseen)
conditions and special measurements, e.g. preheating and post heating temperature
(soaking time), maximum interpass temperature
if stress relieving treatment is foreseen: the procedure, the temperature, the hold time, the
heating and cooling rates, and the tolerances for each of these parameters

For each pass the following indications shall be given:

the welding process specifying, if necessary, whether it is a manual, a semi-automatic or
an automatic process
the welding position
the consumables used (standard name, trade name, diameter)
welding parameters with tolerances (voltage, speed of travel, current, heat input, flow rate
and type of gas)
welding technique detailing polarity and nature of current; welding direction; type of
protection (gas); weave bead or stringer bead; whether or not back welding is carried out
after gouging and/or grinding



Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 27 of 102

3. WELDING PROCEDURES
3.1 General
Welding of weld classes "a, b, c" shall be carried out in accordance with approved and qualified welding
procedures only.

All welding procedures applied shall be qualified unless Contractor procedures have already been
qualified.
Welding of weld class "d" may be executed with procedure previously qualified by Contractor, without
the need of new qualification.

Welding of weld class "e" may be carried out without qualified processes.

Prior to beginning work, the Contractor shall qualify all the required welding procedures for the various
materials and welded seams of the structures to be fabricated.

The information indicated on each WPS shall be consistent and shall not leave the welder to choose
within different combinations of parameters.

3.1.1 Preheating and Interpass
Tacking and welding shall be carried out with preheating temperatures ranges stated in table 3.1.
Carbon Equivalent formula is (llW):

CEV = C+ Mn/6 + (Mo + Cr + V)/5 + (Ni + Cu)/15

Table 3.1 Minimum Preheating Temperature
CEV
Weld Thickness
20mm 30mm > 30mm
0.39 20 20 50 (20)
0.41 20 20 75 (50)
0.43 20 50 (20) 100 (75)
0.45 50 (20) 100 (75) 125 (100)
Note: values in brackets refer to SAW only.

Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 28 of 102


Arc air gouging and oxicutting may be carried out without preheating.

Preheating temperature is to be measured on bevels and at 50mm minimum from bevels at both sides.

Working interpass temperature shall not be lower than preheating one, nor higher than 250"C.
Preheating and interpass values differing from the above stated may be used provided measured
during the execution of welding procedure qualification.

3.1.2 Heat Input
Welding heat input shall be calculated with one of the following formulas:

HI= 0.6VA/ s
HI= 0.001 VAT / (ROL)

where: HI= heat input in J/m; V =arc voltage in Volts; A= arc current in Ampere;
s = welding speed in em/min; T = arc time in second;
ROL = electrode run-out-length in mm.

Heat input value for filling passes and for any process on TM steel may be higher than those
considered in the section 2.4.2, provided adequate welding procedure qualification demonstrates it is
not detrimental to the mechanical characteristics of welded joint.

3.2 Welding Procedure Specifications
Welding procedure specifications (WPS) shall specify the EN 288 requirements in addition to the
following information (as recorded on relevant Procedure Qualification Record):

company name and unique WPS number
welding process, or processes when more than one is used in making a complete joint;
steel type, and whether it is normalised or TM, thickness, length, width and pipe diameter (when
applicable) used for procedure qualification;
sketch of joint showing plate edge preparation (specifying if oxygen cutting or machining) and joint
fit-up tolerances;
thickness and diameter ranges qualified;

Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 29 of 102

welding position and welding direction (for vertica1 position);
the make, trade name, classification and size of welding consumable and fluxes.
Any pretreatment of electrode/consumable;
name, type and flow rate for gas shielding, and backing if applicable;
sketch showing number of beads, welding sequence and relevant consumables and welding
parameters for each joint zone;
for each run: the current type, polarity, arc current and voltage, welding speed, or electrode run-
out length and relevant burning time;
treatment to second side;
actual preheat and maximum interpass temperature used in the qualification test weld, and
those to be used in production; method of temperature measurement;
for semi-automatic processes: torch position, wire protrusion, frequency and waving amplitude;
post weld heat treatments (for avoiding hydrogen cracking and for stress relieving)
if applicable;
any deposition augmentation system used;
tack welding procedure;
Removal methods for weld defects.

3.3 Qualification of Welding Procedures
Qualification of welding procedures shall comply with AWS D1.1, EN 288, and RINA and as specified in
the following.
The welding procedures shall be certified by an Approved Body accepted by the Company.

Prequalified joints foreseen by AWS Dl.1 apply only to weld class "e".

The qualification of the welding procedures performed may be used for any other workshop or worksite.

The execution of procedure qualifications for SAW shall be done using the maximum value of the
allowable recycled flux percentage (Section 2.6.2).

Where tack welds in production will remain in final joint and are done by a different process to that used
for weld body, the procedure test plate shall be similarly tack welded and one macro section taken
through a tack location.


Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 30 of 102

3.4 Qualified Principal Positions
Qualified principal positions shall be in accordance with table 4.1 of AWS D1.1.

3.5 Validity of Welding Procedures (essential variables)
A qualified welding procedure is to be used within the limitation of essential variables as stated below.
The changes described below are to be considered essential and are to initiate a new procedure
qualification test.

When a combination of welding processes is used, the essential variables applicable to each process
shall be applied.

WPQ carried out on base material of quality not "Z" may be applied to other similar steels, including
quality "Z" or lower grade.

3.5.1 Material
Base Material: change of grade of steel, change of steel quality. Increase in product CEV above
0.02% (for Re > 300MPa only), and Pcm above 0.01% of maximum nominal value of steel in
comparison with the value of WPS. Change in manufacturing route. The qualification obtained for a
normalized materials is accepted also for TM materials, and not vice versa.

Groove preparation: presence of bevels protective coat. Oxycutting without grinding to sound metal.

3.5.2 Weld Geometry and Position
Groove angle: change of included angle greater than +10 or -5.

Components angle: where acute angles in the stub to node can welds are below 45 weld processes
are to be qualified by the test of TKY joints. The bevel angle in this test is to be the smallest used in
fabrication.

Root face and root gap: changes of root face and root gap shall be in accordance with AWS D1.1,
either for double side weldings and for single side weldings.


Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 31 of 102

Groove design: change from double side welding to single side welding and vice versa; change in
groove weld preparation shape (V groove, U groove, etc. except that a single half V bevel qualifies a
single V, K qualifies X, and 2:1 and 1:1 preparations qualify each other and all intermediate
geometries).

Thickness: outside the qualified range listed in EN 288-3.

Misalignment: values exceeding the, lesser of 5mm or 10%t on double sided joints, 3mm or 10%t on
single sided joints. Misalignment of 2mm is permitted, regardless of other parameters.

Diameter: outside the qualified range listed in EN 288-3.

Welding Positions: outside the qualified range listed in Table 5.4 of AWS D1.1..

3.5.3 Consumables and Equipment
Welding consumables: change of electrode trade name; electrode and wire type are considered
equivalent on condition that they belong to the same certification class and are approved by a
Certifying Authority, in that case they do not have to be requalified.

Power: changes are made to pulsed power welding parameters.

Welding parameters: change from AC to DC or vice versa; change in DC polarity.

3.5.4 Procedures
Welding process: any change in welding process.

Preheating/working temperature: for preheating the lower limit of approval is the nominal preheat
temperature applied at the start of the welding procedure test, with a tolerance of -10C/+50C. For
interpass the upper limit of approval is the nominal interpass temperature reached in the welding
procedure test.

Post weld heat treatment: added or omitted; change beyond specified temperature range; soaking
time increased more than 25%; increasing or decreasing speed more than 20%.


Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 32 of 102

Gas shielding: gas type change from active to inert and vice versa; change of 10% or beyond in gas
composition; change +27% or -10% in flow rate.

Grinding: if grinding between passes is omitted.

Back-gouging: each reduction in depth of back-gouging in comparison with the qualified one for
automatic process; each increase higher than 10mm of qualified depth.

Back welding: if omitted.

Welding direction: change from uphill to downhill, and vice versa.

3.5.5 Welding Parameters
Voltage and current: change beyond 10% of mean values.

Bead: if each bead width increase, for any electrode diameter.

Speed: if wire feed speed setting for any pass is changed by more than 5%.

Heat input: change beyond 10% (tolerance applies to mean heats input values measured during
qualification in root, fill and weld cap passes) for weld class "a" and nodes of class "b". Welding of all
other elements of class "b" and of every other class is considered a change beyond 20%. Where heat
inputs in two positions are different, qualification in both positions qualifies all intermediate heat inputs.

3.5.6 Specific for SMAW
Measured current for any electrode diameter is changed by more than 20%.
Run out length for any electrode size is changed by more than 10%; where the runs out lengths in two
positions are different, qualification in both positions qualifies all intermediate run out lengths.

Core diameter of an electrode used for capping passes is reduced. All passes in the cap of the
qualifying weld shall use the same electrode diameter.


Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 33 of 102

3.5.7 Specific for SAW
Number of wires used for any pass is changed.

Separation of tandem arcs, transverse or longitudinal, is changed by more than 10%.

Feeding direction is changed by more than 5 transverse or 3 longitudinal to the weld.

3.5.8 Specific for GTAW
Root gap exceeding 3mm is to be qualified with separate procedure.

Tungsten wire changing diameter.

3.5.9 Specific for FCAW (GS and SS)
If the mean voltage for any pass deposited by other automatic or semi-automatic process is changed
by more than 10%.

Change of contact tip-to-workpiece distance.

3.6 Testing
The qualification of welding procedures is based upon visual examination, non- destructive testing and
mechanical testing on test samples. Type and number of tests are those specified in Table 7 of RINA
Rules For Classification for Fixed Offshore Platform effective from 1
st
January 2004..

If different welding consumables or welding processes are applied for the same joint, impact tests
required are to be carried out for the related regions of the weld. If SAW tandem process is used and
fills passes have width over 19mm one KCV set is required at depth of 8mm.
Size and shape of specimens and test execution for Charpy-V are to comply with EU10045.

3.6.1 Test Coupon
The test plates used for procedure qualification (samples location) shall have the rolling direction
parallel to the test weld.


Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 34 of 102

CEV shall be not less than 0.02% and Pcm than 0.01% in comparison with the maximum of the
specification of the steel to be welded.

For Z quality material beams, samples taken for WPQ shall have welding direction parallel to the
rolling direction; for materials of other quality the welding direction can be perpendicular to the rolling
direction. (fig. 3.1)

Figure 3.1 Beam Weld, WPQ Test Sample


Test conditions shall be a realistic simulation of the actual conditions that will be experienced.

When PWHT of nodes or other sub-assemblies is required, all relevant procedures qualifications shall
include PWHT over the full range of material thickness.
The dimensions of the test plates (coupons) shall be in accordance with EN 288-3, paragraph 6.

When plate thickness to be tested is over 36mm or the power of tensile testing machine is not
sufficient, tensile specimens may be cut into a number of approximately equal strips not exceeding
36mm (or the machine strength equivalent thickness whichever is the greater) with a minimum overlap
of 2mm. Test shall be performed on each strip and the results averaged.

Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 35 of 102


3.6.2 Acceptance Criteria
The welding procedure is qualified when the soundness and mechanical properties comply with the
requirements hereafter indicated:

Non-destructive tests:
Welded joints soundness is to comply with the prescriptions of Section 9.13. Any PWHT, when
required, and following NDT shall be carried out not prior than 48 hours from weld completion. Repairs
are not allowed.

The locations of all imperfections exceeding 50% of the reference level shall be marked, and the
cutting of tests pieces shall be arranged to avoid these imperfect regions.

Destructive tests:
Transverse tensile tests: the tensile strength of the welded joint is to be in accordance with EN 288-3
paragraph 7.4.1; in case of welding between steels of different grades the tensile strength shall be
equal to the lower steel grade.

All weld metal tensile test: specimens shall be taken out from full weld metal, and shall take the form
of the "reduced transverse test" piece to BS 709; the tensile strength of the welded joint is to be at
least equal to the minimum specified tensile strength.

Bend tests: test conditions and acceptability limits shall be in accordance with EN 288-3 paragraph
7.4.2; bending angle test shall be of 180.

Toughness tests: the average and minimum Charpy V-notch energy absorption recorded at each
specified position in WM and HAZ is to comply with the requirements in the Project specification
Structural Steel Material Specification, HEN-0000-ST-SP-0001:








Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 36 of 102

Impact Test Energy (Joule)

ZTA ZF MB
Designation
Test
Temperature
Average
Energy
Test
Temperature
Average
Energy
Test
Temperature
Average
Energy
Pr EN 10113 S355 NL
Pr EN 10113 S275 NL
31(Long,a -40)
20(trans,a -40
-40
22
14
-40 31 Var.
Pr EN 10113 S355 N
Pr EN 10113 S275 N
40(Long,a -20)
20(trans,a -20
-20
28
14
-20 40 Var.
EN 10025 S355 J2 27 -20 20 -20 27 -20
EN 10025 S355 JO
EN 10025 S275 JO
27 0 20 0 27 0

Note: Minimum values obtain by a single specimen must be greater than 70% of the average value
required.

Table 3.2 Impact Test Set Location
Thickness Location Double Side Welding
t 45mm
cap WM + HAZ
root WM + HAZ
t > 45mm
cap WM + HAZ
root WM + HAZ
Note: Cap: 2mm +/- 0.5mm below external weld cap surface.
Root: in root region of back welding.
WM: weld metal in the center of weld.
HAZ: heat affected zone.
HAZ means: FL, FL+2mm, FL+5mm.

Macro section: EN 288-3 paragraph 7.4.3, test condition and acceptability shall be applied.
Hardness: the maximum hardness in any part across the welded joint shall not exceed 350 HV5.

3.6.3 Charpy-V Requirements
The Charpy-V requirement for specimens taken from WM and HAZ are shown in fig. 3.2, fig. 3.3, fig.
3.4 and fig. 3.5.

B4

Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 37 of 102


Figure 3.2 Plate Butt Weld, Charpy-V Sets for t45



Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 38 of 102


Figure 3.3 Plate Butt Weld, Charpy-V Sets for t >45



Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 39 of 102


Figure 3.4 T joints, Charpy-V Sets for t45



Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 40 of 102


Figure 3.5 Plate Butt Weld, Charpy-V Sets for t >45




Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 41 of 102

3.6.4 Retesting
Retesting shall be in accordance with EN 288-3, paragraph 7.5 with the following amendements.

Tensile: when the failure, on one or both the specimen, occurs for a load value that is less than 95%
of the tensile strength, the procedure will be rejected. When the failure, on one or both the specimen,
occurs for a load value that is between 95% and 100% of the tensile strength, two additional tests will
be carried out for the interested specimen.

Bends: two other specimens of similar type (face, root or side), located as near as possible to the
failed specimen, shall meet specification.

Macro and hardness: the surveys on two more sections of the coupon have to meet specification.

Toughness: in case one specimen tested gives an energy value below the specified minimum single,
or more than one value is lower than the minimum average, one further set shall be tested from the
same location. The new set shall meet the specified minimum values and conditions, and in addition
the mean value of all the two tested sets (the new and the failed) shall attain the specified minimum
average value. In case of any additional failure the welding procedure shall be rejected.

3.7 Special Test
3.7.1 TKY Joints
The joint qualification shall be carried out in accordance with EN 288-3 paragraph 6.2.4. The can shall
be positioned with vertical axis and brace acute angle downward (fig. 3.6).
Welding shall be carried out with a qualified T-butt procedure, or with a qualified butt weld procedure.
In this case the required mechanicals to qualify the T-butt procedure shall be carried out.

Testing shall be 100% NDT, WM and HAZ toughness at 12 and 3 o'clock positions, macro and
hardness's at 12, 3 and 6 o'clock positions. Acceptability shall be in accordance with applicable
requirements of this specification.


Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 42 of 102


Figure 3.6 Special Test for TKY joints



3.7.2 Welding Repair
Special qualification for repair of excavated welds is required in case the repair process differs from
the filling used.

The qualification shall be carried out in the worse position, through the utilisation of parameteres which
are worse than the expected ones.

Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 43 of 102


HAZ of both parent material and original weld shall be tested.

The Contractor shall issue standard WPQ repair that may be applied in various cases, including the
applied methodology, length and maximum excavation depth, cleaning and NDT methods, preheat
temperature and weld re shaping, if any. The previous methodology shall be exactly applied.

3.7.3 Buttering
Buttering procedure carried out with the same process and parameters as for the filling weld need not
to be qualified.

In case buttering is done with a different welding process, or with same process but different
parameters, from main weld, the buttered area and HAZ shall be tested as for a different process weld.
Both HAZ on base material induced by buttering and HAZ on buttered area induced by main weld shall
be KCV tested. In case one KCV set position coincides with another KCV set, one may be superseded.

Welding procedure shall be carried out with maximum allowed root gap conditions.

Buttering thickness shall be 6mm and 5mm width on each bevel; buttering shall apply only to
weldments having thickness 15mm and above. Buttering area shall be MT inspected.

3.7.4 Permanent Backing Strip Welds
Contractor may apply this technique providing a special WPQ including the insertion of steel backing
strip into the fit-up joint and its tightening against bevel root, first passes, filling passes and relevant
NDT execution.

This procedure is not applied in stub-can joints.

The test is carried out by welding 1a joint, at scale 1:1, built up by two tubular pieces with diameter
equal to the minus on which the process is intended to be applied (fig.3.7). A macro graphic
examination shall be executed on the weld root.


Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 44 of 102


Figure 3.7 Permanent Backing Strip Weld



Tacking shall be carried out inside the bevel all over the weld root: tacking shall never be done outside
bevel.

Air gap between the bevel root and backing strip shall be the minimum, before root welding starts.

Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 45 of 102

A special UT procedure shall be defined and applied to verify the bevel fusion, the absence of tacking
between base material and backing strip, and to recognize the root discontinuity caused by backing
strip. The actual bevel inclination shall be considered for choosing UT probes. The procedure shall
include the execution of an identification mark on base material at 100mm from joint, to verify the root
gap dimensions and the centre of backing strip in every point before weld execution.

"Backing strip" welds shall be indicated on "as-built" drawings. Maximum root gap variation shall not
exceed 6mm. Backing strip weld is allowed with root gap values higher than 12mm but not exceeding
20mm.

Overall procedure produced by Contractor shall be approved by the Company before its application.

3.7.5 Grout Beads
Mechanical tests required on grout weld beads shall be two macros, with hardness survey on fusion
line and HAZ under bead, one KCV set in HAZ and WM as shown in figure 3.8.

Figure 3.8 Charpy-V Set Grout Bead



KCV temperature test shall be equal to the test temperature utilised for the parent material and shall
conform with the minimum energy requirements for this last one.



Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 46 of 102

4. WELDERS AND WELDING OPERATORS
4.1 General
All welding on the structures shall be performed by welders or operators qualified by an Approved Body
accepted by the Company.

All qualified welder shall have a certification that witnesses the qualification. The certification shall be in
accordance with EN 287 code.

The purpose of welder performance tests is to verify that the welders may produce welds in accordance
with these specification requirements using a qualified welding procedure.

Welder qualification tests shall be carried out to an approved welding procedure specification. Welders
having successfully performed the welds of qualification tests of a qualified process are automatically
qualified for the same procedure.

All welders shall be qualified with at least one of the qualification tests indicated in Table 7 of EN 287-1
1992 "Approval testing of welders - Fusion welding Part 1: Steels".

All welds using SMAW process are to be conducted with low hydrogen electrodes. At least one
stop/start has to be produced in each run.

The welders are generally to be qualified for all positions butt welding. For welding occurring only in one
or limited number of positions, performance test may, after agreement with Company, be performed
only in this (these) position(s). Welders, to be qualified for GSFCAW/SSFCAW or GMAW fillet, are to be
qualified in all positions

The welder can be qualified for mixed welding process by only one test, or by two tests as for EN 287-1
ch. 6.2.

Semi killed or fully killed C-Mn steels are normally to be used for welder qualification tests.


Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 47 of 102

4.1.1 Certification Validity
The certification validity shall be submitted to the Company approval when fabrication starts, and it
shall be in accordance with EN 287-1 with the following amendements.

A welder or welding operator may be required to be re-qualified if inspection during fabrication reveals
that extensive repairs are due to poor performance. This shall be done following a period of
supervised retraining. The length of this period shall be at Company discretion but shall be not less
than one week. The Contractor shall record details of retraining.

Company may review existing welder qualification meeting the requirements of this specification:
existing qualifications may be accepted at his solely discretion.

4.1.2 Categories of Qualification and Test Requirement
The fundamental categories that the Company will recognize are listed in the following paragraphs of
this section.

The coupons to be welded are indicated in the same paragraphs. The coupons shall be checked in
accordance with Table 8 of EN 287-1. NDT acceptability shall be as per more stringent requirements
of this specification.

Requalification is necessary if a different welding AWS classification consumable is used. It shall be in
compliance with EN 287-1 paragraph 6.5.

4.2 Qualifications
All the qualifications listed in EN 287-1 page 11, paragraph 6.3, will be applied. The extensions of the
welders qualifications shall be in compliance with Table 3 of EN 287-1.

4.2.1 Automatic Welding
Welding operators using the submerged automatic arc welding (SAW) process shall be qualified as
per AWS D1.1 Section 4 Part C and shall mark their welds for identification purposes.

Qualification with more than one wire qualifies one wire weld according to AWS D1.1 code.


Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 48 of 102

4.2.2 Manual Double-Side Welding
WPQ test welds shall be carried out in accordance with EN 287-1, Table 7.

4.2.3 Manual Single-Side Welding
WPQ test welds shall be carried out in accordance with EN 287-1, Table 7.

4.2.4 Closure Butt Welds
This qualification is required for all welders using the closure butt weld procedure. The qualification
requirements are the same as per manual single side welding, except that the root gap value shall be
as per relevant WPQ.

The strong-backs shall be sufficiently strong so that the gap between bevels does not reduce
significantly during welding.

The extension of the qualification is ruled by EN 287-1, Table 3.

4.2.5 Fillet Welds
Fillet welder qualification shall be carried out according to EN 287.

The extension of the qualification is ruled by EN 287-1, Table 3.

4.2.6 Carbon Arc-air Gougers
Carbon arc-air gougers, for structural class "a, b", shall demonstrate their ability to remove metal to a
uniform depth in a workmanlike manner.

A register of approved arc-air gougers shall be provided and up-dated on a monthly basis. If all
manual welders are qualified as gougers, no list is required.

4.2.7 Tackers
Tackers, for structural class "a, b", shall be qualified as per AWS D1.1 Part C Section 4.31 unless
already qualified for manual welding.


Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 49 of 102

4.3 Retests
Retest applicability requirements shall be in accordance with EN 287-1 paragraph 9 requirements.

Welders failing tests shall follow a congruous training period before retest. Such a training must be
proved by documents.


Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 50 of 102

5. PRODUCTION WELDS
5.1 General
5.1.1 Technique
The width of individual deposited weld beads in flat, horizontal and overhead position, with GMAW and
SMAW process, shall not exceed three times the electrode wire diameter or 16mm, whichever is the
less. In vertical position the width shall not exceed 15mm. For SAW tandem process only fill beads
may be 24mm. Vertical down welding is an acceptable technique only for GSFCAW and SSFCAW
process, for weld class "e".

Run-out tabs are recommended to have a length greater than 150mm, depending if single wire or twin
wire technique is used. Such tabs shall be positioned on both sides of each longitudinal weld. The arc
shall only be struck on the bevel faces only and not on base material.

Each run of weld metal shall be thoroughly cleaned from flux, spatter and all slag removed, by brush,
prior to deposit the next run. For double side butt weld the second side shall be cleaned to sound
metal prior to deposit the second side runs.

Should carbon arc air gouging be used, carbon and other residual debris shall be completely removed
by grinding or other approved mechanical methods.

The welding procedure for a single side butt weld shall provide 100% fusion of the root and be such
that distortion or contraction of the weld metal is minimized.

Peening of welds shall not be permitted.

Preheating temperature shall be raised by 50C above that qualified, for fillet and T butt welds with
root gap exceeding 20mm.

Welding joints shall be fully protected by shelters from the effects of inclement weather (wind, air
draughts or chimney effects). Gas metal arc welding (GMAW) shall be permitted in workshop only and
special care shall be exercised to protect the weld arc from air draughts.


Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 51 of 102

5.1.2 Preparation and Fit-up
Surfaces to be joined by welding and extended adjacent areas shall be thoroughly cleaned to remove
all material or substance detrimental to welding.

Whenever practicable, clamps, magnets, holding devices or other setting-up fixtures shall be used in
assembling structural members in order to avoid tack welding.

Mechanical grinding of oxycut surfaces to be welded is required (see also Section 9.6).

Arc gouging to open tight grooves are permitted, provided is followed by grinding to bright metal.

Before welding the stub to node can, the relevant welding area on the can shall be 100% UT to detect
for laminations. If laminations shall be found Contractor shall try the node chord in such a way to find
an area without laminations. A similar control shall be performed on plates in the position of joint
between pad- eyes and main beams.

5.1.3 Tack Welding
Otherwise spacers shall be employed prior to tack welding to ensure correct root gap spacing.

Tacking shall be done within the bevels. Tack welding shall be performed by qualified tack welders
and an approved qualified welding procedure, including preheating requirements.

Steel bars tacked inside the bevel shall be permitted if their position is clearly marked on base material
and that Company may verify their removal. Steel bar material shall be similar to base material type or
lower grade.

All tack welds, on structural class "a, b, c", shall have a minimum length of 4 times the weld thickness,
with a minimum of 100mm; all other structural classes the minimum length is 2 times the weld
thickness or 50mm whichever are the major. Tack welds may be incorporated into double side main
butt welds provided they are sound, have been executed by qualified welders (not tack welders), and
have their ends grounded and feathered.

Tack welds with a length of 50mm or greater that have shown cracks and when the crack is believed
to extend to the bevels, shall be MT on all the interested areas after removal of defective points and
before commence welding.

Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 52 of 102


5.1.4 Weld Interruption
Welding shall be a continuous operation as far as practical. For components of class "a, b, c" very
constrained and for mud-mats, preheating shall never be discontinued before at least 1/3 of the joint
thickness bas been welded. When the above limit is reached the weld joint may be allowed to cool
down to room temperature: the cooling rate shall be minimized by wrapping the weld areas with dry
insulating blankets. After any interruption and before continuation of welding, the weld is to be
inspected visually for cracks.

5.1.5 Weld Profiles
As a minimum, weld profiles and weld finish shall comply with AWS D1.1 Section 5.24; in the case of
lack of fusion, incomplete penetration or for marginal indentation, the values shown in section 9.13 of
this specification shall not be exceeded.

The external and internal weld reinforcement must not exceed 3mm for welding thicknesses up to
25mm, 4mm for thicknesses up to 50mm and 5mm for thicknesses over 50mm. The excess
penetration in root welding, with GTAW process, shall not exceed 2mm

Weld profiles shall not interfere with the NDT technique specified: reshaping shall be carried out to this
purpose, if necessary. Weld profiles shall not be re shaped by use of a gas torch, or by other
unapproved means to change their appearance.

When specified on the Project Drawings the weld toes shall satisfied API RP2A Sect.11 requirements.
If necessary, the weld toe can be grinded to obtain the required profile as shown figure 5.1. Grinding
shall produce a smooth concave profile at the weld toe with the depth of depression penetrating into
the plate surface to at least 0.5mm below the bottom of any undercut, but not deeper than 2mm or 5%
of the thickness, whatever the bigger, below the surface.

Localized unacceptable undercuts at the weld toe region of any stub to node can welds shall be
removed by the technique mentioned above.

Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 53 of 102

5.2 Welding Sequences
Contractor shall develop welding sequences to control tolerances within specification and prevent the
build-up of excessive residual internal stresses in the structure. No welding shall be carried out between
pretension parts.

Welding sequences are to be defined, to the Company's approval, for complex items (e.g. nodes with
more than four stubs, pile clusters, etc.) including:

WPS to apply;
sequence of items welding and welding direction and way;
number and location of welders at each stage of assembly;
position of preheaters and shelters;
post heating (if applied).

5.3 Temperature
Welding is not allowed if weldment temperature is lower than 5C. In these cases preheating is
mandatory to the required minimum temperature prior to begin welding. Preheating shall be applied to
an area of 100mm minimum from bevel borders.

Definite methods and procedures shall be established for all operations involving preheat and interpass
temperature control. Thermic crayons shall be used only outside the weld bevel. Temperature check or
measurements shall be done at 50mm minimum from bevel borders and on back side where
accessible; temperature reading on weld bead is for interpass temperature measurement only.

5.4 Repairs
Contractor shall prepare a written repair weld procedure, for each repair, including details of removal
methods, weld area preparation, etc. Repair shall be carried out as per qualified procedures only.

Defects removal for repair shall be carried out by any method foreseen by this specification and shall
produce a clean uncontaminated surface for the repair weld execution.


Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 54 of 102

5.4.1 Repair of Finished Welds
Defects in weld metal may be repaired without Company's approval provided the repair
procedure is qualified.

A register shall be kept by Contractor that details the location of all repairs, the defects, the names of
the original welders, dates and repair procedures.

Contractor shall have a relevant NDT documentation to identify the exact defect position. Minimum
excavation length shall be 100rnm. Excavations closer than 10mm shall be linked into a single
excavation.

Serious failures, like cracks, will be treated in a proper way. When detected, they will be examined in
order to establish the originating reasons; then they will be repaired.

The crack shall be removed by either grinding or arc-air gouging plus grinding to sound metal; grinding
shall be carried out in a 50mm area from both ends of the crack, which is determined by MT or PT.
The MT shall be extended to base material surface to detect possible propagation. UT shall be used to
assure defect removal. All NDT shall be carried out in optimum conditions of accessibility.

Preheating temperature for repairs shall be 50C higher than the relevant WPS temperature
requirement.

Re-inspection shall be as per the original inspection technique and shall include all weld metal within
100mm of the repair. The areas interested to the cracks, after the repair, shall be UT detected.

All weld repairs shall be executed prior to any stress relieving heat treatment, when required.

In case that, after repair completion, NDT shows the presence of new unacceptable defects, the
reasons are to be cleared up and reported to the Company prior to proceed with the new repair. In any
case the excavation for the new repair is to be widened in order to reduce residual stress
concentrations.

Cosmetics grinding for eliminating shape defects on cap layers are permitted only if necessary, but are
not considered repairs.


Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 55 of 102

5.4.2 Bevel Repairs
Local grinding may be used to remove notches up to 5mm deep in order to give an even profile.
Notches deeper than 5mm shall be ground out and the face buttered according to the applicable
requirements of this specification.

5.4.3 Buttering
Buttering shall be applied as a corrective action only. Buttering shall be done using qualified welding
procedure.

Following buttering bevel preparations shall be re-established by grinding or machining to the
acceptable limits. Buttered area of double side welding shall be 100% MT prior the execution of root
pass, if applicable.

Buttering on stub to can node welds may be applied to the node can side instead of stub side.

The exact root opening shall allow the closure with a single pass by the qualified procedure.

5.4.4 Base Metal Repair
All corrective action shall be in accordance with the approved procedure.

All boundaries of cavities resulting from removal of detrimental defects shall be faired to a slope of at
least 4 to 1.

The repair of failures by grinding shall follows the procedures set in EU163 rules with the following
limitations:

the residual thickness after grinding shall be not less than 93% of the nominal thickness;
the maximum depth of the grinded area shall not be greater than 3 mm;
the depressions shall be radiused to the other surfaces;
the maximum extension of the grinded area shall not be greater than 5% for each m
2
of surface.

To verify the complete removal of discontinuities, the grinded areas shall be MTI tested.


Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 56 of 102

The repair by welding is allowed only if previously authorized by the Company and if executed in
conformity with EU163, with the following limitations:

the repair by welding is carried out by qualified welders and in accordance with qualified
procedures. Reference is made to Cap. 3. and 4. for what concerns the qualification of procedures
and welders;
the weld is MTI and UT tested. The acceptance criteria of the UT test are as described in
paragraph 9.13.3.

For Z quality products no repair is accepted.

5.5 Closure Welds
Qualified root gap values, including qualified tolerance, may be difficult to be reached during assembly
phase. In this case only class "a, b" closure welds shall be carried out in accordance with the following
requirements. WPS to apply shall be chosen by the Contractor considering actual situations and bevel
mismatch. Special and limit situations shall be approved by Company. All other weld class may be
carried out with subscribed WPQ.

Considered welds are single side only. These welds shall be carried out with a special WPQ
considering a greater root gap, or with a different WPQ. The following table indicates the various
possibilities.

Table 5.1 High Root Gap
Element Thickness (mm)
Actions t 20 t 40
Limit root gap values (mm)
4 4 Normal
10 12 Buttering
18 20 Backing Strip
> 18 > 20 Insert


Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 57 of 102

Following possibilities (fig 5.2) apply whenever root gap exceeds qualified value:

Figure 5.1 High Root Gap




Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 58 of 102

6mrn buttering on each bevel with 12mm as maximum root gap (see Section 3.7.3.);
otherwise GTAW process may be used both for buttering and air closure. In this case only
Charpy-V test, in root region, 1mm under surface is required;

permanent backing strip with root gap values higher than 12mm up to 20mm (Section 3.7.5.)
with root gap higher than 20mm an insert is required, following the tolerance values indicated in
Section 6.3.8 and 6.3.9.

Welders qualification for first pass shall be carried out accordingly, following the relevant requirements
of this specification.

Contractor shall identify all closure welds on fabrication drawings, indicating the applied procedures.

5.5.1 Normal and Buttering Actions
The requirements are relevant to joints with root gap between 3mm and 12mm. SMAW and GTAW
process may be used to carry out the first two passes.

GTAW root process used both for buttering and filling, follows mixed process requirements including
KCV test in WM and HAZ, two macro sections, hardness and bends.

Buttering carried out by SMAW process does not require qualification with thickness up to 6mm.

First pass with root gap exceeding 4mm, with SMAW process is not allowed.

5.5.2 Permanent Backing Strip
In this case the following requirements shall be fulfilled:

backing strip shall not be tack welded to member outside of bevel, otherwise joint shall be cut,
even if completed;
backing strip dimension should not be greater than 4mm thickness and 40mm wide.
Strip interruptions shall not be wider than 1mm. For a girth weld a maximum of three continuous
strips may be used.


Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 59 of 102

Backing strip material shall be EN 10025 S235JR, or equivalent, in as rolled conditions. No KCV are
required on base material.

WPQ shall be qualified according to requirements of Section 3.7.5.

5.6 Stress Relieving Post Weld Heat Treatment
Stress relieving is to be performed in accordance with a PWHT procedure specification. This
specification is to detail heating and cooling rates, temperature gradients, soaking temperature range
and time, heating facilities, insulation, control devices and recording equipment. The procedure is to be
submitted to the Company's approval.

For every application procedure shall include a drawing of the items, supporting method and location of
all thermocouples. Support positioning shall be defined assuming a yield strength of 35MPa at soaking
temperature. Additional temporary stiffeners shall be used to avoid any final distortion of the items free
ends when D/t ratio is above 40.

All temperature charts shall be signed, dated at both start and finish points, marked with a clear
identification, and filed.

The stress relieving post weld heat treatment is required in the following cases;

Welds in tubular nodal joints of class a and b

For the whole pre-fabricated node if chord wall thickness is greater than 50mm or any of the stubs has
wall thickness greater than 40mm.

Welds of Class b

When reference weld thickness is greater than 50mm.

Post weld heat treatment of thermo mechanical control process streels (TMCP) shall be avoided as far
as practicable. In case post weld heat treatment of TMCP is absolutely required, it can be achieved at
elevated temperature not exceeding 590C10C.


Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 60 of 102

5.6.1 Heat Treatment Conditions
Soaking temperature is to be within the range 590C10C: therefore temperature all over the points
of the item to be treated shall be within this range.

Soaking time is to be 2.5 minutes for each millimetre of thickness of the thickest member in item, with
a minimum of 1.5 hours.

Soaking time begins when the lowest measured temperature value is within soaking temperature
range.

The heat treatment may be done introducing the item in the furnace, or in local manner; this choice
depends by the item dimension only.

5.6.2 Furnace Heat Treatment
The item may be introduced in the furnace if this has not a temperature over 300C. The same may
not be taken out from furnace if its temperature is over 300C. Cooling down below 300C shall be in
air.

Item temperature shall be recorded from introduction in the furnace until taking out. Rate of increasing
and decreasing temperature is to be 55C per hour maximum for temperatures above 300C. The
temperature difference on the item, during heating and cooling phases, measured along symmetry
lines and planes shall not exceed 50C; between the outside and the inside surface is not to exceed
50C; between any point of the item far not less than 4500mm shall not exceed 150C.

Temperature shall be recorded continuously and automatically. Thermocouple locations shall be
selected to ensure that the whole item, or item part, being treated is within the range specified;
additional pyrometers should be used to check that undesirable thermal gradients do not occur.

During the stress relieving heat treatment the furnace atmosphere shall be controlled so as to avoid
excessive oxidation of the surface of the item. There shall be no direct impingement of flame on the
item. No parts of the item shall be closer than 200mm from furnace sole plate, or closer than 300mm
from inside walls.


Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 61 of 102

5.6.3 Local Heat Treatment
Local heat treatment is to be carried out by electrical heating: resistance or induction.

The procedure specification for stress relieving shall contain the calculations of the necessary heat
power and insulation, the temperature measurement point, the actions to take in case of temperature
difference exceeding the above values and in case of any thermocouple damage. Any local stress
relieving heat treatment is subject to Companys approval.

In circumferential seams the width of the heated band shall be not less than 5(Dt/2), with weld in the
centre. Sufficient insulation shall be fitted to ensure that the temperature at the edge of the heated
band is not less than half the peak temperature. The adjacent portion of the item outside the heated
zone shall be thermally insulated such that the temperature gradient is in accordance with above
paragraph. A minimum total insulated band width of 10(Dt/2) is recommended for this purpose.

5.7 Welding Parameter Checking
Welding parameter check may be applied after to have verified the first production coupon weld
soundness.

Before starting fabrication Contractor shall submit to Company's approval the procedure and checking
methods that he intends to use to this purpose. Welding parameters checks shall be continuous all over
the production. Company anyway may require a production test coupon whenever he considers
necessary.

Acceptability of welding parameter checking procedure is solely to Company.



Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 62 of 102

6. FABRICATION
6.1 General
All fabrication and erection shall be in accordance with these specification requirements.

Work shall not be performed when weather does not permit satisfactory workmanship or when particular
conditions prevent adequate inspection.

6.1.1 Dimensional Control
Fabrication shall proceed on a flat and level surface and frequent checks shall be made on the
supports and blocking, and any movement out of the level shall be immediately rectified by appropriate
shimming to re establish a level plane.

The Contractor shall survey and control dimensions before fit-up for welding of additional components
and sections. Dimensions shall be checked at each stage in accordance with the fabrication procedure,
tolerances (if given) and the final survey shall meet the defined tolerances. The Contractor shall
submit his dimensional control procedures indicating proposed methods of monitoring dimensions,
their tolerances compatibility and construction method philosophy to the Company before commencing
fabrication.

6.2 Forming
6.2.1 Tubular Fabrication
Tubular may be formed with calendar rolls axis both parallel or orthogonal to the longitudinal axis of
the plate (plate rolling direction).

Tubular may be re rolled after welding in order to reduce deformations. Re-rolling carried out with an
equipment type different from that used for forming shall be subject to Company's approval.

6.2.2 General
Contractor is to qualify each complete forming process, including final re-forming calibration process,
when forseen.


Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 63 of 102

Qualification shall be carried out within the terms and as specified in the section 6.2.7.

The forming shall be not carried out in the temperature range from 200 to 450C or above 800C. TM
steel shall not be hot formed, i.e. above 580C.

6.2.3 Surface Preparation
Plates having surface condition that may impair the forming operation or which may have scale
incorporated into its surface shall be restored by blasting, SA 2 level, before forming. All defects that
may appear after forming shall not exceed 0.3mm in depth.

6.2.4 Cold Forming
Cold forming is considered the forming carried out at ambient temperature.

When the cold forming is executed on plates which have already pass successfully through an ageing
test, with a strain value of 5% and the true deformation is higher, the plate shall be submitted to a new
ageing test with a strain value not less than the real one, or to a thermal relieving treatment. For
assembled elements, the relieving treatment can be executed just before the start of operations.

When the cold forming is executed on a plate which has not been submitted to any ageing test, and
the strain value is above 3%, the plate shall be submitted to an ageing test with a deformation value
not less than the real value; as an alternative, the item shall be submitted to a thermal relieving
treatment before the start of operations.

In all the other cases, cold forming can be carried out on plates without any additional test.

6.2.5 Warm Forming
Warm forming is carried out from 450C up to 600C.

TM steels should not be formed at temperature greater than 580C.
6.2.6 Hot Forming
Hot forming is carried out beyond 600C up to 800C.


Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 64 of 102

Forming process shall be followed by normalization heating treatment to restore the mechanical steel
characteristics

6.2.7 Hot Straightening
Hot straightening may be applied to recover excessive deformations caused by welding or stress
relieving. All class "a" elements, deck legs, padeyes and so on shall not be submitted to hot
straightening in any care. Hot straightening shall be carried out to a Company's approved procedure.

The following requirements shall be fulfilled:

gas torch may be used, but heated areas shall not be larger than 60mm;
maximum temperature shall not be greater than 550C and shall be kept under full control at
least by means of portable contact thermocouple;
steels with 500MPa tensile strength, or higher, shall not be fast cooled, by water or other means.

All hot straightening operations shall be witnessed by Company.

6.3 Welded Connections
6.3.1 Double Side Welding
Double side welding shall be carried out whenever possible. In particular:

In longitudinal and circumferential joints of tubular and node cans having diameter 800mm and
greater. Limitations to this statement are permitted only in case of non accessibility to back side
of the weld;
In brace-to-can welds where brace has internal diameter 600mm or greater.

6.3.2 Welding Grooves
Contractor is to prepare his own standard weld joint groove preparation in accordance with the
indications given on the fabrication drawings and WPS qualified.

Where the joint is accessible from both sides, double side groove preparation, X or K type, maybe
used to join members with thickness greater than 25mm; one side groove preparation, V or 112 K,

Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 65 of 102

may be used to join members with thickness 25mm or less. Contractor may choose a desired welding
groove provided all full penetration requirements are fulfilled.

Bevel inspection shall be in accordance with the section 9.6.

Root back gouging is always required in double side joints.

6.3.3 Mismatch
The butt joint mismatch of welded plate, pipe or structural shape edges shall not exceed the table 6.2
values:

Table 6.2 Mismatch Values
Joint Type
Mismatch:
The lesser of 0.1t or:
Double Side
Longitudinal
Circumferential
4mm
3mm
Single Side
Longitudinal
Circumferential
3mm
3mm

When members of unequal size are joined, the larger member shall be prepared with a 1/4 tapered
transition. The requirements apply both to thickness and width (e.g. beams flanges) dimensions.
Worked taper in double sided joints are not required when thickness difference is 1.15t or less.

6.3.4 Longitudinal Seams
When tubular members are fabricated from two or more welded barrels, the longitudinal seams axes
of adjacent sections shall be staggered at least 300mm.

6.3.5 Node Can Welds Intersecting Stubs
Longitudinal and circumferential chord welds shall be separated from stub to chord welds as indicated
in construction drawings, typical node. Otherwise the following requirements are to be fulfilled.

flush grinding of the outside area of chord welds intersecting the stub, extended for 150mm at
least on both stub sides;

Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 66 of 102

MT and UT on ground area;

The distance between longitudinal stub seam and any node can seam type measured between weld
toe and weld toe should be in any case not less than 51mm.

6.3.6 Node Can Welds and Ring Stiffeners
The distance between ring stiffeners welds toe and circumferential chord weld toe is to be at least the
chord thickness or 75mm, whichever is greater.
6.3.7 Cones
Circumferential welds within cone are not allowed, unless approved by Company or specified on the
construction drawings. All cones shall be right conic frustum.

6.3.8 Pipe and Node Splices
The minimum distance between two circumferential welds shall be 1m or two diameters, whichever is
greater.

There shall not be more than 2 splices in any 4m of pipe.

Company's approval shall be necessary for circumferential welds within cones and node stubs.

6.3.9 Beam Splices
In cantilever beams no splice shall be located closer to the point of support than 1/2 of the cantilever
length.

In beams with two or more supports there shall not be splices in following positions (fig.6.1):

in the middle 1/4 of the span;
in the 118 of the span nearest to any supports;.
not closer than 1m to any support or node.

When beam shall be welded on flange beam, the flange beam area shall be UT tested to verify the
laminations absence.

Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 67 of 102


Figure 6.1 Beam Splices





Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 68 of 102

6.4 Welded Attachments
Welded attachments to the structure not shown on the construction drawings shall not be permitted
except for temporary and non-structural attachments. In this last case too they must be maintained at a
minimum number.

In these cases welding shall be allowed, provided that the attachment thickness is not greater than
20mm and the welds location are not closer than 51mm from any weld.

All attachments shall be welded to the structure according to these specification requirements and
approved procedures.

Temporary attachments welding to nodes or PWHT elements are not allowed.

After the structure completion, all welded attachments shall be removed by flame cutting 5mm from the
base material, followed by smoothing corners.

Where paint is foreseen flush grinding is required.

Attachments shall not be removed by hammering or any other method that may cause mechanical
damage to the surface.

The interested area shall be visually controlled and testing maybe carried out to demonstration of
material soundness).

6.5 Site Assembly
Contractor shall consider, during site assembly, all temporary erection loads imposed on the structure
from supports, jacking and slinging at each stage of the structure assembly.

Contractor shall consider, during site assembly, the local or overall stability from self weight and
environmental loads. These include scaffolding, staging, temporary cranes, welding shelters and
temporary works, at each stage of the structure assembly.

Contractor shall provide during the assembly phase storage for all items, to prevent their damage from
environmental.

Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 69 of 102


Contractor shall make provision for alignment correction at each stage of the structure assembly.

6.6 Manufactured And Miscellaneous Items
6.6.1 Bar Grating
Bar grating shall be cut to dimension and installed as shown on the construction drawings.

Unless otherwise restricted by construction drawings, bar grating may be attached by either tack
welding or bolting.

If tack welded, each bar shall be pressed in firm contact with the underlying structure and secured with
a minimum 50mm line tack weld. The tack weld and the surrounding heated area of zinc galvanised
bar grating shall be touched-up according with the relevant painting specification or as per procedure.

6.6.2 Steel Floor Plate
All butt type joints shall be welded to produce an 85% fused joint minimum. All floor plate under-side
shall be 100% seal welded to deck stringers and other supporting, to seal all facing surfaces from
corrosion. Seal fillet welds shall have a minimum leg length of 4mm.

Seal welds and butt joints shall be staggered at least 50mm.

Steel floor plate shall not present subsidence higher than 3mm measured with a 1200mm length
gouge.

6.7 Finishing of Surfaces
As fabrication of various items or portions of the structure is completed, the Contractor shall remove all
welds, burrs, tack welds and other marks made by scaffolds or temporary bracing used in the
fabrication procedure.
All arc-strikes and burn marks shall be ground smooth, visual and MT inspected. The areas of
components "a, b and c" interested shall be carefully examined.


Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 70 of 102

6.8 Rat Holes
Rat holes are required when shown on construction drawings and whatever they are necessary to full
penetration weld execution. In this case only Contractor shall define the relevant solution, with
Company's approval.

Rat holes radius shall be as small as possible, but in conformity with the necessity to carry out adequate
operations. The surfaces shall be smooth and without any indentation.

Full penetration welded stiffeners shall blend onto parent material inside rat hole.

Fillet weld shall be returned through the rat hole.

When weld joint crossed is fillet welded, a 45 clip of sufficient width may be provided on stiffener comer
in order to shape it onto weldment and facilitate complete stiffener fillet welding.

Rat holes in structural elements to be painted; otherwise iron mastic approved by Company may be
applied. In these cases the use of rat holes shall be minimized.

6.9 Bolted Connections
Bolt holes shall be drilled at right angles to the metal surface and shall have at least a diameter 1.5mm
larger than the bolt diameter.

Bolts shall be freely insertable into the holes without damage to the thread. Bolt heads and nuts shall
rest squarely against the metal surface.

Unfinished bolts transmitting shear shall be threaded to such a length that no more than one thread will
be within the grip of the structural members.

All bolts shall be of a length such that they will extend entirely through but no more than 6mm beyond
the nut and locknut.

After final tightening, nuts shall be locked by tab washer, cotter pin or locknut. Equipments, bolt material
and tightening torque shall meet the requirements specified on construction drawings.


Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 71 of 102

7. PREFABRICATED ITEMS TOLERANCES
The Contractor shall provide personnel with qualified surveyors, equipment and instruments, with
current valid calibration certificates, necessary for monitoring and controlling dimensions and tolerances.

The following sections give the admitted tolerances for every measurable dimension and shape of
structural elements.

7.1 Fabricated Tubular Nodes and Cones
7.1.1 Circumference
Circumference measured with tape shall not differ from theoretical value more than 1% of nominal
circumference or 10mm, whichever is less.

The measurement shall be carried out at 600mm from any tubular splice and at tubular ends.
Intermediate measured values shall not differ more than 1.5 times the above.

The circumferential tolerance shall not be reason for increasing the mismatch tolerated by this
specification.

7.1.2 Ring Stiffeners out of Circularity
For each ring stiffener shall be checked the difference between the actual radius and the average
radius, in different points.

This difference shall not be greater than 0.25% of the external ring stiffener diameter.

The average radius defined by optimum centre and the radius measurements, in various position,
relevant to the optimum centre shall be calculated in accordance with a procedure, approved by
Company, based on EEMUA 158 optimum centre out of circularity.

7.1.3 Ovality (General)
Ovality is intended as the difference between the maximum and the minimum diameters, measured
either internally or externally, at the same section.


Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 72 of 102

Ovality shall be checked at each item end, at each 3m interval, at each circumferential seam, and at
midway between two ring stiffeners.

The following table applies.

Table 7.1 Ovality Values and Measurement Numbers
Diameter Value Number of Measures (*)
600 1% of diameter Two diameters
2000 Greater of 6mm or 0.75% D Four diameters
> 2000 Greater of 15mm or 0.75% D Six diameters

Two diameter measurements may not be at 90 between them, but carried out in the position with
maximum and minimum value.

Measuring method, with more than two diameters, may be equally spaced instead of maximum and
minimum position.

7.1.4 Local out of Roundness
Local out of roundness shall be measured by means of a 20 gauge having a theoretical tubular form,
and the measurement is verified all over the circumference (360).

Local out of roundness shall not be greater than 0.4% of the diameter. This control shall be carried out
on tubular elements with diameter greater or equal than 1000mm.

7.1.5 Local out of Straightness
Local out of straightness is the deviation of the shell plate from its axis.

This value shall not exceed 20% of the wall thickness.

Local out of straightness shall be checked on tubes with nominal outside diameter greater than
2000mm or with nominal outside diameter/wall thickness ratio greater than 65. The check shall be
either on the inside or outside, and the positions shall be those indicated in table along all tubular
element.

Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 73 of 102

Table 7.2 Local out of Straightness
Type of Joint Check Location
Unstiffened tubular
45 intervals of arc with template
L=3000mm
Stiffened tubular node barrels
20 intervals of arc with template
L = distance between stiffeners or 3000mm in other uses
Manways after welding at the centre and manway quarter points with template L = 1000mm

7.1.6 Out of Straightness
Structural classes "a, b, c" members, excluded piles, out of straightness tolerance is the greater of
0.1%L or 3mm, but not greater than 12mm.

Straightness shall be checked in at least two perpendicular planes.

7.1.7 End Perpendicularity
End perpendicularity shall be held within 3mm. This tolerance shall not be cumulated with weld root
gap tolerance (fig.7.1).

Figure 7.1 End Perpendicularity




Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 74 of 102

7.1.8 Prefabricated Nodes
Length tolerance of node cans, stubs and cones shall be within 0 + 100mm from length shown on
fabrication drawings.

Actual stub centre line is intended as the intersection of two orthogonal diameters at both ends of the
stub; one of the diameters is parallel to the longitudinal axis of the node chord.

Each actual stub centre line shall be kept within 10mm cylinder from its theoretical position shown on
the fabrication drawings (fig 7.2).

Figure 7.2 Node Working Point



7.1.9 Ring Stiffeners
Rings stiffeners in node cans and cones shall be fitted, with respect to their theoretical location shown
on fabrication drawings to an accuracy of 1/3 stiffener thickness but not more than 6mm. Stiffeners in
tubulars shall be fitted with an accuracy of 12mm.

Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 75 of 102

The internal or external ring stiffeners inclination shall be within 1% of the nominal web depth but not
more than 6mm. For ring stiffeners in nodes and in node cones the same tolerance is 0.5%h with
maximum value of 3mm.

The maximum bow in the web of an internal or external ring stiffener shall be within 1% of the nominal
web depth, but not more than 3mm.

The deviation of the flange edge, of an internal or external ring stiffener, from the diameter measured
at the flange centerline shall be within 5% of the nominal flange width.

If ring stiffener is fabricated in two or more pieces and if flange is required the buttwelds mismatch
shall not exceed 0.1 stiffener web or flange thickness nor 3mm (fig 7.3).

Figure 7.3 Ring Stiffener



Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 76 of 102

7.2 Rolled or Fabricated Beam
Fabricated structural steel section tolerances shall comply with AWS D1.1 Section 5.23.
For permissible variations from flatness of web see AWS D1.1 paragraph 3.5.1.6.
All other tolerances not considered here shall be in accordance with EEMUA 158, section 6.2.2.1.

7.2.1 Global Tolerances
Structural class "a, b" members, no hollow sections, out of straightness and verticality is the greater of
0.1%L or 3mm, but not greater than 12mm.
The out of straightness and verticality tolerance for girder and beam with hollow section is the greater
of 0.2%L or 5mm but not greater than 25mm.

7.2.2 Local Tolerances
Flange eccentricity shall be equal to 0.02b, with maximum value equal to 6mm. Tilt and roof shape
shall be equal to (1+0.01b)mm but not greater than 6mm, with b is the flange width and t the thickness.
(fig. 7.4)

Figure 7.4 Roof Shape



Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 77 of 102

Web girder twisting shall be equal to (1+0.01h)mm, but not greater than 10mm, where his the web
height in millimetre. Web bow shall be equal to 0.01h with maximum value equal to 0.5t, where t is the
web thickness.

7.2.3 Web Stiffener
Web stiffeners location between girders flanges shall be within tolerances values.
Web stiffeners shall be fitted with respect to their theoretical location to an accuracy of half stiffener
thickness, but not greater than 6mm. Web stiffener out of straightness shall be within 0.15%L, but not
more than 3mm. The outstand of web stiffener under load bearing surfaces shall be within 0.5% of the
maximum web height but not more than 3mm of a perpendicular set out from two girders flanges3mm
(fig. 7.5).

Figure 7.5 Web Stiffener



7.2.4 Fillet Welds Execution
Weld passes shall be continuous to prevent any risk of crevice corrosion. Welds shall be returned
through the rat hole, when present.

Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 78 of 102

7.3 Stiffened Plate Panels
The following applies, with reference to fig. 7.6:

Figure 7.6 Roof Shape



Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 79 of 102

Table 7.3 Tolerances for Plate Panel
Tolerance Type Tolerance Value Limiting Value (mm)
Plane out of position 0.3%L 10
Global lateral deflection between
principal stiffeners
0.5%L
1
10
Global lateral deflection between
secondary stiffeners
0.15%L 15

Table 7.4 Tolerances for Plate Panel Stiffener
Tolerance Type Tolerance Value Limiting Value (mm)
Inclination a
y
2.5%h 5
Out of position P
y
5%h 10
Nodal out of position P
y
5%h 3
Out of straightness S
v
both orthogonal
and lateral the plate plane
0.5%L
1
5
Where, L
1
is the distance between two consecutive stiffeners
h is height of the stiffeners

7.3.1 Stiffeners Forming Cruciform Arrangements
Where a combination of stiffeners (ring, diaphragm, web) from a cruciform arrangement with other
member or stiffener the mismatch of the alignment through the joint shall be according to table 7.5.

Table 7.5 Mismatch Value
Thickness Mismatch
t
3
> t
1
and t
2
T
3
/ 2; max 10mm
t
2
> t
3
and t
1
T
2
/ 2; max 6mm
For t
1
, t
2
and t
3
identification, see fig. 7.7.

Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 80 of 102

As-built dimensions shall be used to align members. UT check shall be performed where external
measurement can not guarantee the alignment.

Figure 7.7 Mismatch on Cruciform Joints



7.4 Other Fabrication Details
7.4.1 Weld Beads for Grouting
Weld beads position and size shall be in accordance with the construction drawings. The weld beads
pitch is to be constant throughout the zone where weld beads are required and are to be kept equal
between sleeves and piles.

Tolerance on position of each weld bead is 5mm with respect to what required on fabrication
drawings.

Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 81 of 102

The height of the bead shall to be a tolerance of 0 to +2mm.

Weld beads distance from circumferential barrels butt welds shall not be less than 51mm, measured at
weld toes. The barrels length shall therefore be defined also taking into account the above
requirements. However, not more than one weld bead per sleeve may be out of pitch.

7.4.2 Opening and Penetration Holes
The centerline point of any opening and penetration shall be within a tolerance of 10mm of the
theoretical central point.

The actual size of any opening shall be within a tolerance of 2mm of the theoretical dimensions.

See fig.7.8 for indication.

Figure 7.8 Openings and Penetrations





Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 82 of 102

8. FINAL FABRICATION TOLERANCES
Final fabrication tolerances shall be within the tolerance values specified here below.

8.1 Position of Nodes
The node working point (intersection point among items axis measured on structure) (fig. 7.2) shall be
positioned within the error sphere whose radius is indicated in Table 8.1, relevant to the theoretical
position shown on fabrication drawings.

Table 8.1 Nodes Positions
Node Type Tolerance
Jacket and Deck Matching Nodes 6mm
Other Leg Nodes 10mm
Other Nodes 15mm

Table 8.2 shows the tolerance values of some structural dimensions, as an example of said above.

Table 8.2 Distance Tolerances
Measures Tolerance ()
Length between first and last node working points on Jacket Legs 16mm
Distance between working point not involving one leg nodes 30mm
Placed on the same plane involving one leg nodes 25mm
Distance between abutting Jacket and Deck node working point 12mm

8.2 Deck Plans
8.2.1 Deck Section Columns
The columns intersections centre (item axes intersection centre) measured on the structure shall be
within the error sphere, whose radius is indicated in Table 8.3, relevant to theoretical fabrication
drawings position.

Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 83 of 102


Table 8.3 Header Position
Node Type Error Sphere Radius
Beams on column
6mm Beams on stringer
Beams on principal beams

As said above, Table 8.4 gives, as an example, the overall distances and elevations tolerances
measured on structure.

Table 8.4 Structure Measurement
Measures Tolerance ()
Column distance
12mm Header distance
Header elevation difference

Indicated tolerance shall not be higher than bevel mismatch. Tolerance among same level column
shall not be higher than planarity and bevels mismatch limit.

8.2.2 Deck Section Plate
Plates on deck beams shall not have sags higher than 3mm relevant to theoretical bearings level.

8.2.3 Working Plane Position
Deck and modules working plane position shall have a vertical outstand lower than R/500, with 9mm
as maximum, relevant to the theoretical plane; R is the distance from reference point.

The maximum number of water collectors shall be defined on construction drawing and Company shall
define their position after welding of steel floor plates.


Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 84 of 102

8.3 Handrails
Fabrication and erection shall be performed to a degree of accuracy that the top rail shall be level to the
eye, and the handrail shall be plumb.

8.4 Walkways, Landings and Stairways
Walkways, landing and stairway shall be located within the following tolerances, relevant to the
fabrication drawings.

Table 8.5 Tolerance for Landing and Stairway
Elevation 12mm
Planarity 6mm each 3m length
Planimetric Position 12mm

Distance among steps shall not be more than 3mm from theoretical position.



Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 85 of 102

9. INSPECTION OF WELDMENTS
9.1 General
All welds are to be subjected to non destructive examination (NDT)as fabrication and construction
proceed, as per a proper schedule and relevant drawings supplied by the Contractor.

NDT on weld class "a, b, c" shall be carried out only 48 hours after completion of welding. The same
requirement for weld class "d" with thickness higher than 20mm.

NDT on weld class "e" and on all other classes not considered above may be carried out 24 hours after
welding completion.

Inspection and NDT prior to PWHT shall be at the Contractor discretion and shall not avoid further tests.

All NDT reports are to include all data that allows to repeat the examination in the same conditions.

Contractor shall formulate a quality control plan that shall contain mandatory NDT inspection and the
time when they shall be done. This plan shall be submitted to Company's approval.

9.2 Definitions
The following definitions are used:

NDT Non Destructive Testing
VI Visual Inspection
MT Magnetic Particles Inspection
PT Dye Penetrant Inspection
UT Ultrasonic Testing
RT Radiographic Testing
DAC Distance Amplitude Correction
HD Maximum Amplitude of Flaw Echo Height


Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 86 of 102

9.3 Reference Standards
The standards and codes of practice called up by this specification are considered at the latest edition
at time of contract award. They are:

API RP 2X
API Standard 1104
BS EN 462
EN 970
BS EN ISO 9934-1
ASNT-TC1A

Contractor shall equip themselves with copies of all the standards and codes referred to in this
specification and shall make them readily available to all inspection personnel involved on work.

9.4 Methods of NDT
Accepted NDT methods are RT, UT, MT, and PT. Their applicability shall conform to the following table.
UT may be used instead of RT on a case by case to be submitted to Company for approval prior to
commencement of UT.

Table 9.1 NDT Applicability
Weld Classes a, b, c, d e
Joint t 12mm 12 < t 38mm T > 38mm all thickness
Butt
RT
MT
UT
MT
UT
MT
MT
PT
T-butt MT UT MT
Fillet MT

Table shall be integrated with the following requirements.

The indicated thicknesses are those referred to welding thickness.

Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 87 of 102

9.4.1 RT
For filing reasons the RT inspection is preferred to UT inspection, even if thicknesses are greater than
38mm, for reporting. UT shall be carried out for deck and modules beams, when the joint geometry is
such that RT is unappropriate.
Thickness limits are relevant to complete one crossed by rays.
RT in shop are to be preferably executed by X ray equipment. Gamma rays may be applied on yard
only or on large prefabricated items. Following isotopes do not require Company's approval: Y
t
up to
t=12mm; Ir for thickness from 10mm to 19mm with qualification of the procedure test; I
r
and Y
t
up to
t=38mm; X rays for thickness above 38mm. The use of Co 60 is generally not acceptable.
Phased aray testing method may be substituted with RT & A scans UT due to more advantages, such
as above mentioned method (phase aray) capabilities, safety requirements, projects construction
progress and etc.

9.4.2 UT
UT may be applied for chevron cracks checks on SAW welds with thickness above25mm.

UT shall be applied when RT inspection is not possible (i.e. T joints) or when exposition time is higher
than reasonable values, and anyway after Company's approval.

Fillet welds class "a, b, c" mainly submitted to tensile stress, may be UT inspected against lamellar
tears and to verify the weld discontinuity; test percentage shall be 100%.
New UT procedures that permit both to correlate echoes with position on piece through scanner use
and to record on magnetic support may be submitted to Company's approval. Change of NDT
procedure based on these new techniques is solely at NDT level III acceptance.

9.4.3 MT
MT is the reference surface NDT methods for all welds of classes "a, b, c, d". The substitution with PT
for parent materials with minimum yield strength not greater than 275MPa requires Company's
approval. For weld class "e" and all classes bevel inspection, PT may substitute MT without approval.

9.5 Extent of NDT
Extent of NDT shall be as per following table.


Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 88 of 102

Table 9.2 Extention of Not On Weld Classes
a b, c d e
VI 100% 100% 100% 100%
UT/RT 100% 100% 20% -
MT 100% 20% (1) 20% -
PT/MT - 100% - 20%
(1) The MT test for joints and closure welds adjacent to nodes shall be 100%.
(2) Use of RT or UT and PT or MT and required percentage shall be accepted by Company

9.6 Edge Inspection
Prior to assembly for welding, all edges shall be inspected to find any eventual defects.
The inspection of the bevel edges shall be carried out with VI/MPI
Some times after beveling and before fit up its mandatory to verify bevel quality using MPI
examination, it shall be addressed in this specification.

Any discontinuity extending 5mm and above shall be repaired.

9.7 Qualification of NDT Procedures
The Contractor shall prepare procedures for each of the NDT techniques he proposes to use, and
submit these to the Company's approval prior to commence any testing.

Company may require the qualification of some or all of the procedures, by demonstration of their
capability to detect known flaws.

9.7.1 Radiographic Testing (RT)
The procedure specification for the radiographic testing is to include at least the following information:

radiation source (X-rays or gamma rays. If gamma rays, type of isotope);
technique (equipment rating in voltage or curie, external or internal equipment single wall, double
wall/single image, double wall/double image);
B4
B4
B4

Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 89 of 102

geometric relationships (film focus distance, object film distance, radiation angle with respect
to weld and film, focal spot);
film type (trade name and designation);
intensifying screens (front and/or back material, thickness);
exposure conditions (kV, rnA, min, Bequerel, min);
processing (developing time and temperature, stopbath, fixation, washing, drying, etc.);
image Quality Indicator sensitivities in percent of the wall weld metal thickness based on sources
and film side indicators respectively;
density (the radiographs density measured on the sound weld metal image);
film coverage.

The representative radiographic procedures are to be qualified by making two radiographic exposures
of a welded joint with the same or typical configuration and dimensions, on a material equal to or
similar to that which is to be used in the structure.

In order to check the sensitivity, the above requirements apply also for double walls images.

9.7.2 Ultrasonic Testing (UT)
A procedure specification for the ultrasonic testing according API RP 2X is to be established, which is
at least to include the following information:

type of instrument
type of transducer;
frequencies;
calibration details;
surface requirements;
type of couplants;
scanning techniques;
recording details;
reference to applicable welding procedures;
material thickness and curvature range;
check of calibration.

The qualification test is to be performed under normal working conditions and at Company presence.

Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 90 of 102


The test pieces are to be available as reference all over the inspection work.

UT carried out by automatic equipment is generally acceptable, but submitted to Company's approval.

9.7.3 Magnetic Particle Inspection (MT)
A procedure specification for the magnetic particle testing is to be established which is to include at
least the following information:

materials and dimensions;
type of equipment;
surface preparation including background paint;
wet or dry method;
make and type of magnetic particle and contrast paint;
magnetizing current (for prod magnetizing: the prod type and spacing are to be stated).

No special procedure qualification test is required. The procedure is considered qualified based on
approval of the testing procedure specification.

9.8 Qualification of NDT Personnel
Radiographic, ultrasonic, and magnetic particle operators shall be qualified to EN 473 or an equivalent
rule. Moreover all ultrasonic operators shall be especially qualified in accordance with API RP 2X
paragraph 2.3.

A scheme for qualification of operators conforms to EN 473 or an equivalent rule shall be established by
Contractor. Contractor is responsible for manufacturing suitable test joints, including artificial and
natural flaws, representative of the construction configuration that must be carried out. Operators shall
examine the number of test plates defined by the above scheme and shall set a written examination.

The internal qualification of NDT personnel shall comply with EN 473.

EN 473 or equivalent level ill, as supervisor, is required within the project and within yard or shop
organization.


Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 91 of 102

If the qualification of the personnel is in doubt, the Company may require their interdiction to production
activities until their ability has been satisfactorily demonstrated.

UT operators are to be capable of:

calibrating the equipment;
performing an operational test under production conditions;
interpreting the screen display;
evaluating size and location of reflectors;
classifying reflectors as planar, cylindrical or spherical.

RT operators are to be fully capable of performing an operational test using the qualified radiographic
procedure.

Operators performing MT testing are to be capable of performing an operational test, using the test
method or technique that is to be applied in production.

9.9 Visual Inspection Execution
Visual Inspection shall be carried out in accordance with BS 5289. The stub to node weld inspection
shall be carried out with the aid of clipped disk.

9.10 Radiographic Testing Execution
9.10.1 General
Contractor shall prepare a document in which he indicates the radiation source (X and isotopes) he
intends to use in function of thickness ranges, worksite locations (yard, shops) and relevant to the
whole job conditions.

The film type utilized shall be as per ISO 5579.

The film shall be fine grained type KODAK INDUSTREX C or AGFA D7 or equivalent. However the
inspector and/or company/TPA may require the use of extra fine grained film as KODAK MX or AGFA
D4 or equivalent where a better quality of radiographic image is needed.


Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 92 of 102

Only lead reinforced screens are to be used.
The execution procedures for the radiographic control must be qualified when the source is not
accessible during the production control.

9.10.2 Examination
Image quality indicators shall be of the wire type as recommended by llWIIIS 62-60 or ISO Standard
and are to be placed on the source side. In case that the source side is inaccessible during production
radiography, only film side penetameters are required, but shall be marked with an "F" and the
procedure shall be qualified.

The image quality indicators are to be clearly identified, and the sensitivity of the source side indicator
is to be equal to or better than the requirements given in for "single wall technique". For "double wall
technique" the IQI sensitivity shall be calculated putting the total weld thickness penetrated, i.e. two
times the plate thickness plus the two weld reinforcements, at the denominator of the formula. In this
case the permissible IQI values shall be double of those indicated (ref. BS 3971, table 7). Radiographs
are to have a density at the weld metal image in the range 2.6 to 3.8 for the double images with a
minimum of 1.3. For single images the density shall be in the range 2.0 to 3.0.

If the multiple exposure technique is used, at least one penetrameter is to be recorded on each film. If
the panorama technique is used to include 100% of tubular girth weld in one exposure, a minimum of
three penetrameters are to be equally spaced around the circumference, at 120 one from eachother.

The maximum acceptable film lengths are defined by the film references.

9.11 Ultrasonic Testing Execution
9.11.1 Equipment
The equipment used for ultrasonic testing is to:

be applicable for the pulse echo technique and for the double probe technique;
cover the frequency range from 2 to 6 MHz;
have a flat screen accessible from the front for direction plotting of reference curves;
allow echoes with amplitudes of 5% of full screen amplitude to be clearly detectable under
test conditions;

Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 93 of 102

include straight beam transducers, and angle beam transducers of 45; 60 and 70;
satisfy vertical linearity according to ASME V and horizontal linearity in accordance
with ASTM.

9.11.2 Calibration
Calibration shall be in accordance with API RP 2X requirements.

For portable testing equipment the IIW/ISO calibration block is to be used.

For echo amplitude evaluation, a DAC reference curve is to be established and plotted on the
instrument screen. The reference block for gain calibration and construction of DAC is to be
manufactured from the actual production material and be in accordance with the requirements of API
RP2X for Level A.
DAC curve construction shall be in accordance with the indications of API RP2X. Equipment horizontal
and vertical linearity shall be always calibrated before the any examination beginning. Calibration of
the ultrasonic equipment is to be carried out whenever it has been out of function for any reason, and
whenever there is any doubt concerning proper functioning of the equipment.

9.11.3 Examination
Ultrasonic testing of production welds, shall be carried out in accordance with API RP 2X and with the
following requirements.

The weld is to be examined from at least two sides. T-butt welds are to be examined also from through
member opposite face (if practicable).

For SMAW welds the separate probes for transmitter and receiver method shall be applied when
surface conditions are detrimental to correct inspection. Tandem technique keeping constant the
inclination angle relevant to the weld seam axis may be applied.

Flaw width shall be evaluated with the 6dB technique, flaw length shall be evaluated with the "half-
value-drop" method.

The use of beam path lengths longer than 200mm is not allowed.


Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 94 of 102

Inspection for acceptance of butt welds over 60mm thick, to which access is limited to one side only,
shall include unrestricted scanning from the surface of the weld. Surface shall be grind to an
appropriate standard for the inspection purpose.

For butt welds with bevel angle between 0 and 10, and with thickness above 40mm the tandem
technique maybe used.

9.12 Magnetic Particle Inspection Execution
9.12.1 Equipment
Only AC equipment or DC equipment (with current obtained through half wave rectifier) may be used
for testing. Other DC equipment, permanent magnets or equipment which introduces current directly in
the item shall not be used.

The equipment used for magnetic particle testing is to establish a field strength among 2400 Nm (30
Oersted) and 4000 Aim (50 Oersted). The magnetic field adjustment shall be verified by a relevant
instrument. This need not be proven by measurement in case of coil or prod magnetizing, provided the
following requirements are met:

AC electromagnetic yoke is to have a lifting power of at least 4.5 kg at the pole working spacing;
the coil magnetising current is to be chosen depending on the number of turns of the coil. The
ratio between the ampere turns and the diameter of the pipe work piece to be tested is to be 8
to 16 ampere turns per each nun;
AC electromagnetic yoke is to have a lifting power at least 4.5kg with 300rnm prode spacing, for
surface defects only.
for sections with thickness 20mm or more, the prod spacing is within the range 75-200mm with a
current of 5-6A for each millimeter;
for sections with thickness less than 20mm, the current is to be 3.5 to 4.5 A per each mm prod
spacing, with prode spacing within the range 75-200mm.

Prods tipped with lead, or "soft prods" are required.

Equipment and calibration blocks applied to verify the above requirements shall be available to NDT
personnel and to the Company.


Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 95 of 102

9.12.2 Examination
The surface of the parts subjected to test is to be clean and dry, free from any dirt that may interfere
with the examination.

To ensure detection of discontinuities having axes in any direction, the examination is to be performed
with the magnetic field shifted in at least two directions on each area.

Non-fluorescent wet or dry particles are to provide adequate contrast with the background of the
surface being examined. Surface painting shall be used to improve the detection of flaws: white
background paint is preferred.

Magnetic particle examination is not to be performed on parts with surface temperature exceeding
300C. Wet magnetic particle examination is not to be performed on parts with surface temperature
exceeding 60C. Care is to be taken to avoid local heating of the test surface.

All prod burns shall be ground out and PT.

Demagnetization shall be provided, when necessary.

9.12.3 Magnetic Fluorescent Particles
This control type shall be done in a darkened room using an ultraviolet radiation light with wavelength
within the range 3200/3800 Angstrom.

Before starting the testing the operator shall remain for 5 minutes to accustom his eyes to low
luminosity. Glasses and contact lens shall not be photosensitive. Before light intensity measurement, it
is necessary to wait 5 minutes for a correct heating and for a correct operation. Ultraviolet radiation
light shall be measured by a particular instrument.

There shall be 800 microwatt/cm
2
on the examined surface. Ultraviolet radiation light intensity shall be
measured each 8 hour or whatever the working position is changed.

Wet particles shall be applied on smooth welding surface only.


Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 96 of 102

9.13 Standards of Acceptability
Any weld imperfection that prevents the sizing of, or may prevent the detection of, a weld flaw is itself a
flaw and shall be repaired.

Cracks and lamellar tears found by any of the NOT methods are not admitted in any case and for any
weld classes. All this type of discontinuities shall be inspected to find out the originating cause.

All detected defects that are higher than the following acceptability limits shall be repaired, the weld
restored and a new NDT inspection carried out all over the interested area

9.13.1 Visual Inspection Acceptance Standard
All the outside and inside welds whenever accessible shall be visually inspected. Abutting porosities,
gas cavities, and slag inclusions are to be repaired.

Acceptable undercuts are as follows:

Table 9.3 Acceptable Undercuts
Weld Classes a b, c d e
Depth (mm) 0.25 0.5 0.5 1
Length (mm) intermittent 10 20 40

9.13.2 RT Acceptance Standard
Flaws on films appearing to meet the acceptance standards limits, but having darkness density giving
a doubt on their depth shall be re examined with UT technique.

The lengths of acceptable volumetric flaws are as follows:








Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 97 of 102

Table 9.4 Acceptable Flaws
Defect Type a, b c d
Gas Cavities t/3 or 6mm t/3 or 6mm t/3 or 6mm
Linear Porosity individual
cumulative
0.75t 1.5t
3t
12t or 150mm
Slag Inclusions individual
cumulative
1.5t or 6mm
t or 20mm
1.5t or 6mm
2t or 30mm
6mm
2.5t or 60mm
Lack of fusion individual
cumulative
Not admitted Not admitted
10mm
1.5t over 12t
Incomplete Root penetration
Individual cumulative
Not admitted Not admitted
10mm
1.5t over 12t

Two gas cavities are treated like a linear porosity when the distance between them is less than 6 times
the diameter of the biggest porosity.

The lack of fusion and incomplete penetration acceptance standard for weld class "d" may be applied
to longitudinal double welds class "b, c" as diagonals, deck beams and bracings. All other elements as
nodes, padeyes, buoyancy tanks and their supports are excluded.

9.13.3 UT Acceptance Standard
Any flaw from which echo height exceeds the DAC by 6db shall be repaired and re-examined,
regardless of size.

All flaws classified as planar, like cracks or lamellar tears, shall be repaired whichever is their echo
height.

All echoes that exceed 50% DAC shall be classified and evaluated in size, in accordance with table
9.5.

All transverse defects are to be regarded as defects requiring repair. This requirement does not apply,
where indication can be unequivocally correlated to longitudinal defects.


Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 98 of 102

The lengths of acceptable volumetric flaws are as follows:

Table 9.5 Nonplanar Acceptable Flaws
Maximum HD and DAC a, b c d
HD > DAC (100%) 10mm 30mm 40mm
HD > DAC/2 (50%) 20mm 45mm 60mm
HD = maximum amplitude defect echo.

Planar defects, clearly detected as lack of fusion and incomplete root penetration may be accepted for
weld class d as per Table 9.6

Table 9.6 Flaw Acceptability for Weld Class b, c, d
Flaw Type
Depth
(mm)
Length
(mm)
Max
Individual
Length
Cumulative
Lack of fusion 1.5 t/2 10mm 1.5t over 12t
Incomplete root
penetration
1.5 1.5t 10mm 1.5t over 12t

The lack of fusion and incomplete penetration acceptance standard for weld class "d" may be applied
to longitudinal double welds class "b, c" in diagonals, deck beams and bracings. All other elements as
nodes, padeyes, buoyancy tanks and their supports are excluded.

Two gas cavities are treated like a linear porosity when the distance between them is less than 6 times
the diameter of the biggest porosity.

9.13.4 MT Acceptance Standard
Detected rounded indications shall be classified as elliptical shape if the length is equal to or less than
three times the width, or as circular shape in other cases. Linear indications are the remainders.


Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 99 of 102

All surfaces to be examined shall be free from linear and rounded indications caused by weld defect,
not weld geometry, having the limits indicated below:

linear indications are not acceptable whichever their dimensions;
acceptable rounded indications shall not be greater than 4nnn, and there shall not be more than
three indications in line, separated by 1.5mm or less from edge to edge.

9.14 Reports
Operator shall formalize, in the following 24 hours after test completion, the testing results.

The report is to indicate if the weld quality meets the acceptance standard limits of this specification,
and indicate the flaws to be repaired.

The minimum requirements shown in a NDT report shall be the following:

procedure qualification informations;
weld identification number;
sketch of the welded joint and probable flaw location;
flaw description and dimensions;
repair flaws;
any remark.

The report shall clearly show the type of flaw detected (i.e. lack of fusion, incomplete penetration,
porosity and slag) including a repairing flaws location sketch from a particular point choosen as
reference.

9.14.1 RT Reports
The report shall show, beyond general requirements, the following:

film identification number;
film location.


Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 100 of 102

9.14.2 UT Reports
The report shall show, beyond general requirements, the following:

planar and not planar flaw evaluation.

9.14.3 MT Reports
The report shall show, beyond general requirements, the following:

tested surface conditions;
black light intensity;
powder and solvent types used.



Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 101 of 102

10. TESTING OF FIELD INSTALLED COMPONENTS
10.1 Preassembly Testing
When complex assembly items shall be joined offshore, Contractor shall carry out a yard assembly test
in order to verify the correct fit.

Handrail sections or other similar items shall be stamped or metal tagged so that it is possible easily to
restore their exact position during offshore assembly.

Items such as bolt or pin shall be assembled, fitted and welded so that the connection can be
easily installed or removed.

10.2 Hydraulic and Pneumatic Testing
All equipment, components and piping systems shall be tested both by pressure test and in working
conditions, before the load- out. Testing shall be done according to relevant line service conditions.

Hydraulic and pneumatic tests are required.

Pressure testing shall be done in conditions of minimum temperature variation as per applicable piping
specification. Pressure shall be maintained at least for one hour.

Flooding values shall be hydrotested to detect leaks either from body or trim, and to verify for their
smooth and free operability.

The leak test shall be done by hydrotest at the maximum working pressure. Reach-rods and flooding
valves, when present, operability shall be tested while flooding lines are under pressure.

Flooding valves are to be lubricated and checked before load out to ensure that they are in the closed
position, and that protective caps or other obstructions are not present that would prevent proper valve
operation.


Hengam Offshore Development Project EPCI For
Topsides and Infield Pipelines and Subsea Cables
Contract No. 4405-90-2FG

STRUCTURAL FABRICATION SPECIFICATION
Rev. B4
Proj. Area. Disc Doc. Seq. Page
HEN 0000 ST SP 0002 102 of 102

10.3 Testing of Packers System
10.3.1 Testing of Line
All air lines shall be isolated from the grout packers, to prevent damage to grout packers, before this
testing to be done prior to load out.

Test pressure shall be 40 bars for one hour. There shall be no pressure drop and no leaks. After
testing of all lines, they shall be completely drained, dried and re- connected to the grout packers.

10.3.2 Testing of Packers
When packers are already inside the barrels, the purchaser shall give a certification relevant to the
acceptance test. Contractor shall apply purchaser requirements for acceptance test when previous
certification is not available.

You might also like