CENTRAL UTAH PROJ ECT COMPLETION ACT

UINTA BASIN REPLACEMENT PROJ ECT


BIG SAND WASH RESERVOIR ENLARGEMENT


CONSTRUCTION PROGRESS REPORT NO. 2

APRIL 2004



OWNER:
CENTRAL UTAH WATER CONSERVANCY DISTRICT

CONTRACTOR:
W.W. CLYDE/OBAYASHI, J V
-i-
Uinta Basin Replacement Project
Big Sand Wash Reservoir Enlargement

Construction Report for April 2004

This monthly construction progress report provides a summary of work performed during the
previous period and its relationship to the overall projects.

TABLE OF CONTENTS
General Project Data.................................................................................................................... ii

Progress of Work
Description of Work........................................................................................................................1
Planned Activities for May..............................................................................................................4
Work Plan........................................................................................................................................5
Planned Expenditures.......................................................................................................................6
Progress of Work Summary Table...................................................................................................7

Financial Data
Current Month Payment Estimate Summary...................................................................................8
History of Contractor Earnings/Payment.........................................................................................9
History of Engineer Earnings/Payment.........................................................................................10

Project Photographs
Progress of Work ..........................................................................................................................11

-ii-
General Project Data

Uinta Basin Replacement Project
Big Sand Wash Reservoir Enlargement

Project .................................................................................Big Sand Wash Reservoir Enlargement
Owner ............................................................................. Central Utah Water Conservancy District
General Contractor..................................................................................W.W. Clyde/Obayashi, J V
Construction Manager....................................................................H. Lee Wimmer, P.E., CUWCD
Project Manager..................................................................................Kirk Beecher, P.E., CUWCD
Resident Engineer...................................................................................Kent Kofford, P.E., USBR
Chief Inspector...............................................................................................Terry Despain, USBR

Bids Opened.......................................................................................................... J anuary 21, 2004
Notice to Proceed...................................................................................................... March 1, 2004
Original Contract Time...................................................................................... 639 Calender Days
Original Contract Completion Date...................................................................November 30, 2005
Approved Time Extensions................................................................................................... 0 Days
Current Contract Completion Date ...................................................................November 30, 2005

Original Contract Amount...................................................................................... $ 31,439,000.00
Approved Change Order Amount.............................................................................................$0.00
Current Contract Amount....................................................................................... $ 31,439,000.00
Approved Change Orders as a Percentage of Original Contract................................................. 0%



Big Sand Wash Reservoir Enlargement

Construction Progress Report No. 2
April 2004
1
D De es sc cr ri ip pt ti io on n o of f W Wo or rk k

The following statements describe the work performed from
April 1, 2004 to April 30, 2004.

Highway Relocation SR-87 Roadway

On April 5, 2004, the contractor utilized a Cat 330L excavator and two D400E rock trucks to
complete the clearing and grubbing of trees and vegetation inside the right-of-way for the
highway relocation. Clearing and grubbing debris were hauled to and stockpiled at the right
abutment staging area.

On April 13, 2004, a Cat 330L excavator, Cat D8N dozer, and two D400E rock trucks were
used to complete the stripping of topsoil inside the right-of-way for the highway relocation.
The topsoil was hauled to and stockpiled at the right abutment staging area.

During the topsoil stripping, the contractor encountered several springs surfacing on the
uphill side of the right-of-way. If not taken care of, this water which runs down across the
right-of-way would saturate the subgrade and future road embankment construction, and
jeopardize the road stability. Therefore, on April 22, 2004, COPR No. 1 was issued to the
contractor for installing 6-inch perforated pipe, drain rock, and filter fabric to collect and
route the water away from the road construction area.

On April 26, 2004, installation of the 6-inch perforated drain pipe, drain rock, and filter
fabric began at station 20+50.

East Saddle Dam Flow Control Access Road

On April 2, 2004, the contractor began clearing and grubbing of trees and vegetation for the
Flow Control Access Road between stations 1+00 and 28+00. Clearing and grubbing debris
were hauled to and stockpiled in the staging area downstream of the East Saddle Dam for
future chipping operations.

On April 16, 2004, the contractor completed excavation and embankment construction to
subgrade for the East Saddle Dam Flow Control Access Road between stations 1+00 and
28+00.
East Saddle Dam

On April 7, 2004, subcontractor, Epic Engineering completed slope staking for rough
excavation/overburden removal between stations 8+00 and 39+00.

On April 12, 2004, a Cat 330L excavator and two D400E rock trucks were used to complete
the clearing and grubbing of trees and vegetation for the East Saddle Dam excavation
between stations 8+00 and 39+00. Clearing and grubbing debris were hauled to and
stockpiled in the staging area downstream of the East Saddle Dam.

Big Sand Wash Reservoir Enlargement

Construction Progress Report No. 2
April 2004
2

On April 21, 2004, the contractor completed stripping topsoil between stations 8+00 and
39+00. This topsoil was hauled to and stockpiled in the staging area downstream of the East
Saddle Dam.

On April 19, 2004, silt fencing was installed on the downstream side of the stockpile staging
area for the East Saddle Dam construction activities.

On April 22, 2004, the contractor utilized a Cat 320BL excavator and two D400E rock trucks
to begin removal of overburden material to bedrock on the East Saddle Dam at station 39+00.
By the end of the month, the overburden material was removed between stations 26+00 and
39+00. The material was hauled to and stockpiled in the staging area downstream of the East
Saddle Dam.

West Saddle Dam

On April 13, 2004, the contractor completed stripping topsoil between stations 26+50 and
37+50 using a D8N dozer and 14G grader.

Temporary Diversion Pipeline

On April 1, 2004, the contractor installed the first 20-foot section of 72-inch HDPE pipe for
the temporary diversion pipeline. The diversion pipeline will be 72 inches in diameter for the
first 45 feet and then reduce to 60 inches in diameter for the remaining 452 feet.

On April 5, 2004, the contractor placed 2- cubic yards of concrete for an inlet transition
wall at the downstream end of the existing outlet works stilling basin.

On April 20, 2004, the contractor completed the installation of the temporary diversion
pipeline and the installation of riprap at the outlet end.

On April 21, 2004, Moon Lake Water Users Association started releasing water through the
temporary diversion pipeline.

Dike on Natural West Ridge Drain at Toe of Ridge

On April 23, 2004, the contractor completed excavating a bench for the intermediate french
drain between stations 23+50 and 40+20 using a D8N dozer.

Aggregate Borrow Area

On April 26, 2004, subcontractor, Geary Construction began processing 3-inch minus
granular borrow material at the Fieldsted Pit near Altamont.




Big Sand Wash Reservoir Enlargement

Construction Progress Report No. 2
April 2004
3
Environmental

The contractor had a two man crew install silt fencing and fiber rolls throughout the
construction site.

On April 28, 2004, the contractor utilized B&G Crane Service from Altamont to set the fuel
storage tanks in the fuel storage containment area.

Subcontractors

Epic Engineering provided quality control testing for concrete and soil compaction.

Epic Engineering provided construction surveying.

Geary Construction began mobilizing for sand and gravel materials production at the
commercial Fieldsted Pit.

Financial

No change orders were issued this period.

Payment was made to the contractor for the amount of $362,535.13. The completed amount
to date is $2,116,741.35 with $102,237.07 (approximately 4.8 percent) being held in
retention.

The contractor has completed approximately 6.7% of the project in 9.5% of the time.


Big Sand Wash Reservoir Enlargement

Construction Progress Report No. 2
April 2004
4
Planned Activities for May

Activities to be performed during May on the Big Sand Wash
Reservoir Enlargement project by the contractor will include:

Continue clearing, grubbing, and stripping of topsoil throughout the construction site.

Continue construction on the SR-87 Highway Relocation.

Develop the Portal outlet.

Continue East Saddle Dam overburden excavation to bedrock.
Construction of the Flow Control Structure Access road.
Contractor design and complete the Value Engineering proposal of the outlet works tunnel.
Continue processing aggregate materials at the Fieldsted Pit.


Big Sand Wash Reservoir Enlargement

Construction Progress Report No. 2
April 2004
5
W Wo or rk k P Pl la an n

Big Sand Wash Reservoir Enlargement Original Contract $31,439,000.00
Planned Planned Total Total
Work Planned Retainage Planned To Date To Date
Month Completed Retainage to Date Budget Actual Planned Actual
Mar-04 - $ - $ - $ - $ 1,651,969.16 $ - $ 1,651,969.16 $
Apr-04 - $ - $ - $ - $ 362,535.13 $ - $ 2,014,504.29 $
May-04 - $ - $ - $ - $ - $ - $
Jun-04 - $ - $ - $ - $ - $ - $
Jul-04 - $ - $ - $ - $ - $ - $
Aug-04 - $ - $ - $ - $ - $ - $
Sep-04 - $ - $ - $ - $ - $ - $
Oct-04 - $ - $ - $ - $ - $ - $
Nov-04 - $ - $ - $ - $ - $ - $
Dec-04 - $ - $ - $ - $ - $ - $
Jan-05 - $ - $ - $ - $ - $ - $
Feb-05 - $ - $ - $ - $ - $ - $
Mar-05 - $ - $ - $ - $ - $ - $
Apr-05 - $ - $ - $ - $ - $ - $
May-05 - $ - $ - $ - $ - $ - $
Jun-05 - $ - $ - $ - $ - $ - $
Jul-05 - $ - $ - $ - $ - $ - $
Aug-05 - $ - $ - $ - $ - $ - $
Sep-05 - $ - $ - $ - $ - $ - $
Oct-05 - $ - $ - $ - $ - $ - $
Nov-05 - $ - $ - $ - $ - $ - $
2,014,504.29 $
Approval of payment schedule pending.


Big Sand Wash Reservoir Enlargement

Construction Progress Report No. 2
April 2004
6
P Pl la an nn ne ed d E Ex xp pe en nd di it tu ur re es s


Big Sand Wash Reservoir Enlargement Project
Planned Expenditures
$ 0
$ 1,000,000
$ 2,000,000
$ 3,000,000
$ 4,000,000
$ 5,000,000
Mar-04 J un-04 Sep-04 Dec-04 Mar-05 J un-05 Sep-05
$ 0
$ 10,000,000
$ 20,000,000
$ 30,000,000
$ 40,000,000
$ 50,000,000
Planned Budget Actual Billings Cumulative Budget Cumulative Billings

Approval of payment schedule pending.

Big Sand Wash Reservoir Enlargement

Construction Progress Report No. 2
April 2004
7
P Pr ro og gr re es ss s o of f W Wo or rk k S Su um mm ma ar ry y T Ta ab bl le e

Big Sand Wash Reservoir Enlargement Period to: April 30, 2004
Item Previous Amount Total Percent
No. Description Value Amount Earned This Month To Date Complete
100 Mobilization 2,326,782.50 $ 202,644.90 $ 90,047.45 $ 292,692.35 $ 12.58%
200 Main Dam 11,584,305.00 $ 802,937.00 $ 57,505.00 $ 860,442.00 $ 7.43%
300 West Saddle Dam 2,979,614.00 $ 202,435.00 $ - $ 202,435.00 $ 6.79%
350 Highway 87 Relocation 906,767.50 $ 70,370.00 $ 20,000.00 $ 90,370.00 $ 9.97%
360 Class C Canal Inlet 211,687.00 $ - $ - $ 0.00%
400 West Ridge Dam 1,421,738.00 $ 96,592.00 $ - $ 96,592.00 $ 6.79%
500 East Saddle Dam 5,356,737.00 $ 363,936.00 $ 135,774.00 $ 499,710.00 $ 9.33%
600 Spillway 1,187,730.00 $ - $ - $ 0.00%
700 Inlet - Microtunnel 3,243,312.00 $ - $ - $ 0.00%
750 Outlet 1,756,127.00 $ 2,500.00 $ 2,500.00 $ 0.14%
800 Electrical & Instrumentation 426,000.00 $ - $ - $ 0.00%
900 Ranch Ponds 38,200.00 $ - $ - $ 0.00%
COPR#1 Highway 87 Drainage - $ 72,000.00 $ 72,000.00 $
Total Project Cost 31,439,000.00 $ 1,738,914.90 $ 377,826.45 $ 2,116,741.35 $ 6.73%



Big Sand Wash Reservoir Enlargement

Construction Progress Report No. 2
April 2004
8
C Cu ur rr re en nt t M Mo on nt th h P Pa ay ym me en nt t E Es st ti im ma at te e S Su um mm ma ar ry y

Big Sand Wash Reservoir Enlargement
Contractor: W.W. Clyde/Obayashi, J .V.
HC 65 Box 119
M.P. 27, Highway 87
Bluebell, Utah 84007
Period To: April 30, 2004
Contract Amount
Amount of Original Contract 31,439,000.00 $
Number of Approved Change Orders 0
Amount of Change Orders - $
Current Contract Amount 31,439,000.00 $
Payment Summary
This Month Total to Date
Earnings for Work and Materials 377,826.45 $ 2,116,741.35 $
Less: Retainage 15,291.32 $ 102,237.06 $
Total: Net Earnings 362,535.13 $ 2,014,504.29 $
Less: Previous Net Earnings - $ 1,651,969.16 $
Plus: Reduction of Retainage - $ - $
Net Payment this Estimate 362,535.13 $ 362,535.13 $
Contract Time
Notice to Proceed Date March 1, 2004
Original Contract Completion Time November 30, 2005
Approved Time Extensions (Days) 0
Current Contract Completion Date November 30, 2005
Percent Complete
% Contract Time Elapsed 9.5%
% Work Completed (Based upon cost) 6.7%


Big Sand Wash Reservoir Enlargement

Construction Progress Report No. 2
April 2004
9
H Hi is st to or ry y o of f C Co on nt tr ra ac ct to or r E Ea ar rn ni in ng gs s/ /P Pa ay ym me en nt t

Big Sand Wash Reservoir Enlargement Contractor: W.W. Clyde/Obayashi, JV
Applic. No. Date From Through Earned Retained Payment
1 08-Apr-04 01-Mar-04 31-Mar-04 1,738,914.90 $ 86,945.74 $ 1,651,969.16 $
2 06-May-04 01-Apr-04 30-Apr-04 377,826.45 $ 15,291.32 $ 362,535.13 $
Total 2,116,741.35 $ 102,237.06 $ 2,014,504.29 $

Big Sand Wash Reservoir Enlargement

Construction Progress Report No. 2
April 2004
10
H Hi is st to or ry y o of f E En ng gi in ne ee er r E Ea ar rn ni in ng gs s/ /P Pa ay ym me en nt t

History of Construction Management Costs Big Sand Wash Reservoir Enlargment
U.S. Bureau of Reclamation (Provo Office)
Date From Through Weeks Amount
13-Apr-04 01-Mar-04 20-Mar-04 3 5,211.45 $
04-May-04 21-Mar-04 17-Apr-04 4 32,131.06 $
Total 37,342.51 $


Uinta Basin Replacement Project
Big Sand Wash Reservoir Enlargement
Construction Progress Report No. 1
March 2004
Pr Progr ogress of ess of W Work ork
11
Contractor excavating the Flow Control
Access Road near station 9+00.
Contractor utilizing a 330L excavator and a
D-400E rock truck for clearing and grubbing
for the SR-87 Highway Relocation at station
17+50.
Contractors carpenters finishing the top of
the inlet transition wall at the temporary
diversion pipeline.
Uinta Basin Replacement Project
Big Sand Wash Reservoir Enlargement
Construction Progress Report No. 1
March 2004
Pr Progr ogress of ess of W Work ork
12
Contractor placing a diesel power water pump
into a containment trough located next to the
Big Sand Wash Reservoir.
View of the contractor utilizing a D8N dozer for
stripping topsoil from the SR-87 Highway
Relocation between stations 17+50 and 21+00.
Placement of concrete for the inlet wall
transition at the inlet to the temporary
diversion pipeline.
Uinta Basin Replacement Project
Big Sand Wash Reservoir Enlargement
Construction Progress Report No. 1
March 2004
Pr Progr ogress of ess of W Work ork
13
Contractor utilizing a 815F sheep-foot
compactor and a 4,000-gallon water
truck on the East Saddle Dam Flow
Control Access Road at station 12+00.
Subcontractor, Epic Engineering, taking a
density test of the Flow Control Access Road
located at station 12+05.
Big Sand Wash Reservoir spilling
on April 12, 2004.
Uinta Basin Replacement Project
Big Sand Wash Reservoir Enlargement
Construction Progress Report No. 1
March 2004
Pr Progr ogress of ess of W Work ork
14
Contractors compaction operation on the
Flow Control Access Road located between
stations 10+50 and 13+00.
View of the Big Sand Wash Reservoir
spillway channel.
Water spilling from the existing spillway
on April 12, 2004.
Uinta Basin Replacement Project
Big Sand Wash Reservoir Enlargement
Construction Progress Report No. 1
March 2004
Pr Progr ogress of ess of W Work ork
15
Contractor installing silt fencing downstream
of the East Saddle Dam.
Contractor utilizing a 320BL excavator for
placement of cobble riprap at the outlet of
the temporary diversion pipeline.
View of the contractor installing the
72-inch to 60-inch HDPE temporary
diversion pipeline.
Uinta Basin Replacement Project
Big Sand Wash Reservoir Enlargement
Construction Progress Report No. 1
March 2004
Pr Progr ogress of ess of W Work ork
16
Contractor utilizing a 330L excavator and
two D400E rock trucks for overburden
removal to the top of bedrock at station
37+00, East Saddle Dam.
View of the contractor utilizing a 330L
excavator for removal of the overburden to
bedrock at station 37+50, East Saddle Dam.
Uinta Basin Replacement Project
Big Sand Wash Reservoir Enlargement
Construction Progress Report No. 1
March 2004
Pr Progr ogress of ess of W Work ork
17
Contractor utilizing a TH-63 Telescopic
Handler for placement of the drain rock over
the top of the 6-inch perforated drain pipe
located in the SR-87 Highway Relocation.
Contractor installing 6-inch perforated
drainpipe on the SR-87 Highway Relocation
located at station 19+20.