Professional Documents
Culture Documents
PROFILE ON PRODUCTION OF
BUTTONS FROM HORN
290-2
TABLE OF CONTENTS
PAGE
I.
SUMMARY
290-3
II.
290-3
III.
290-4
290-4
290-7
IV.
290-8
290-8
290-9
V.
290-9
A. TECHNOLOGY
B. ENGINEERING
290-9
290-10
VI.
290-12
290-12
290-12
VII.
FINANCIAL ANALYSIS
A. TOTAL INITIAL INVESTMENT COST
B. PRODUCTION COST
C. FINANCIAL EVALUATION
D. ECONOMIC BENEFITS
290-13
290-13
290-14
290-15
290-16
I.
SUMMARY
This profile envisages the establishment of a plant for the production of buttones from
horn with a capacity of 200 tonnes per annum.
The present demand for the proposed product is estimated at
290-3
Buttons are items used in garments. Horn buttons are highly durable of all types. Most
of the time, they are used with elegant suits.
III.
A.
MARKET STUDY
1.
Buttons are used by garment manufactures. Therefore, the local demand for the product is
influenced largely by the expansion of the local garment industry. According to the
information from the Ethiopian Investment Agency, investment permits were issued to a
total of 161 projects with a capital of Birr 990 million in the area of garment and related
290-4
articles manufacturing, of which 12 are already operational and 15 are under
implementation. When the licensed projects become operational the local demand for
buttons will increase considerably.
However, since there is no domestic facility for manufacturing buttons, the products are
imported from overseas. Import of button is given in Table 3.1.
Table 3.1
IMPORT OF BUTTON ( TONNE)
Year
2000
2001
2002
2003
2004
2005
2006
Import
11,950
32,906
42,770
72,439
77,563
41,466
46,228
Projected Demand
The demand for buttons is related with the expansion of the garment and leather goods
production.
290-5
Ethiopia has a good potential to expand the garment and the leather sector due to the
availability of the basic raw materials. Moreover, the government has given due attention
to these sectors in its industrial policy. Considering these favourable situations, the
demand for buttons is estimated to grow by an average rate of 8% per annum (see Table
3.2).
Table 3.2
PROJECTED DEMAND FOR HORN BUTTONS ( TONNES)
Year
Projected Demand
2008
2009
2010
2011
2012
2013
2014
2015
2016
1,004
1,084
1,171
1,265
1,366
1,475
1,593
1,720
1,858
290-6
2017
2018
2019
2020
3.
2,007
2,167
2,341
2,528
Based on current retail price of the product and assuming profit margin for distributors
and retailers, the recommended factory-get price of the envisaged project is Birr 5 per
Kg.
The product can be distributed through the existing textile accessories distributes or by
establishing own distribution centers at strategic locations.
B.
1.
Plant Capacity
According to the market study for horn buttons indicated above, the unsatisfied demand
for the year 2008 will be 1004 tonnes, and this figure will grow to 1,720 tonnes by the
year 2015. Therefore, the envisaged plant will have production capacity of 200 tonnes
of horn buttons per annum.
Production can be increased if the plant is made to operate double shift for 16 hours a day
without increasing investment on fixed capital.
2.
Production Programme
A gradual capacity build-up is proposed for the plant so as to allow for manufacturing
skill development and for establishment of sufficient market outlets. The plant, hence,
290-7
will commence production at 65% of full capacity in the first year of operation.
Production will be made to grow to 75% and 85% in the second and third year,
respectively. Full capacity production shall be attained in the fourth year and then after.
Table 3.3 below presents the details of the proposed production programme.
Table 3.3
PRODUCTION PROGRAMME
Year
Capacity utilization (%)
Production (tones)
1
65
130
IV.
A.
2
75
150
3
85
170
The major raw material required for the production of horn buttons is raw horn obtained
from cow, ox and others. The region has a high cattle population; Sidama, Debub Omo
and Hadiya Zones are with the highest cattle population in the region having 1,258,654,
1,114,258 and 879,147 TLU respectively. At woreda level; Kuraz, Awassa Zuria, and
Soro Woredas have the highest cattle population in the region.
In addition to horn, polishing materials are very useful in the production of buttons.
These materials produce polished surface of the buttons thereby enhancing the quality
and appearance of the products. Annual requirement of raw and auxiliary material at full
production capacity is given in Table 4.1 below.
Table 4.1
290-8
ANNUAL REQUIREMENTS OF RAW AND AUXILIARY MATERIALS AND
COST AT FULL CAPACITY
Sr.
Description
Qty
LC
No.
1
2
B.
A. Raw Material
Horns (cow, oxen), etc (Tones)
B. Auxiliary Materials
Polishing materials
Total
TC
205
205
205
Req
-
10
215
10
215
UTILITIES
Electricity and water are utilities required for production of horn buttons. A total of
10,000 kWh electrical energy is required per annum. As regards water the plant will
require a total of 200 m3 water per annum.
At the rate of Birr 0.474 per kWh for electricity and Birr 10 per m 3 for water, annual
expenditure on utilities will be Birr 6,740.
V.
A.
TECHNOLOGY
1.
Production Process
290-9
a)
b)
Hole making
c)
d)
b)
Hole making:- After the horn is cut into circular shape, then the required holes
are formed by a hole making machine.
c)
Finishing and polishing:- This is the process by which the horn button is treated
on a lathe machine where the edge and the button face are properly polished by a
polishing material so as to give the product smooth and good-looking face.
d)
Finally the polished and finished product is properly packed and dispatched to the
market.
2.
Source of Technology
ENGINEERING
1.
290-10
Machinery and equipment required by the plant and related cost is shown in Table 5.1
below.
Table 5.1
MACHINERY AND EQUIPMENT
Sr.
No.
1
2
3
4
5
6
7
8
9
2.
Description
Qty
(No.)
Horn cutting circular saw
1
Band saw machine
1
High speed circle cutting machine
1
Semi-automatic hole master
1
Double ended polishing lathe
1
Motorized tool post grinder
1
Circular blade and band saw 1
sharpening machine
Special steel borers
2
Tungsten wire hole making machine
1
FOB price
Freight, Insurance charges, material
handling charges, Customs
CIF Landed Cost
Land, Building and Civil Works
LC
18.00
25.00
65.00
110.00
60.00
35.00
75.00
TC
18.00
25.00
65.00
110.00
60.00
35.0
75.0
80
45.00
593
-
75
80.0
45.00
593.0
75.0
593
75
668.0
290-11
The total land required by the plant is 300 m 2, of which 150 m2 is built-up area. At land
lease rate of Birr 1.0 per m 2, the land lease value for 80 years is Birr 24,000. At unit cost
of building (per m2) Birr 2,000 the total cost of built-up area will be Birr 300,000. Thus,
the total investment on of land, building and civil works will be Birr 324,000.
3.
Proposed Location
A.
MANPOWER REQUIREMENT
The plant requires both production and administrative workers. The details of manpower
are given in Table 6.1 below.
B.
TRAINING REQUIREMENT
Two weeks training for three operators is sufficient. Training can be carried out in the
workshop of Federal Micro and Small Enterprises Development Agency (FeMSEDA) in
Addis Ababa. A total of Birr 5,000 is allotted to carry out the training programme.
Table 6.1
MANPOWER REQUIREMENT AND LABOUR COST
Sr.
Job Title
No.
1
A. Administration
Manager (finance & Administration )
Req.
Monthly
Annual
No.
Salary
Wages
1,000
12,000
290-12
2
3
4
5
6
1
2
VII.
Secretary
Sales man
Clerk
General services
Sub total
B. Production
Skilled worker
Unskilled workers
Sub total
Workers benefit (25% BS)
Total
FINANCIAL ANALYSIS
1
1
1
2
6
500
600
350
250
-
6,000
7,200
4,200
6,000
35,400
3
2
5
11
600
250
21,600
6,000
27,600
15,750
78750
The financial analysis of the buttons from horn project is based on the data presented in
the previous chapters and the following assumptions:Construction period
1 year
Source of finance
30 % equity
70 % loan
Tax holidays
3 years
Bank interest
8%
8.5%
Accounts receivable
30 days
30days
90days
Work in progress
5 days
Finished products
30 days
Cash in hand
2 days
Accounts payable
30 days
A.
The total investment cost of the project including working capital is estimated at 1.54
million, of which 13 per cent will be required in foreign currency.
290-13
The major breakdown of the total initial investment cost is shown in Table 7.1.
Table 7.1
INITIAL INVESTMENT COST
Sr.
No.
1
2
3
4
5
6
7
Total Cost
Cost Items
Land lease value
Building and Civil Work
Plant Machinery and Equipment
Office Furniture and Equipment
Vehicle
Pre-production Expenditure*
Working Capital
Total Investment cost
Foreign Share
(000 Birr)
24.0
300.0
668.0
75.0
200.0
229.7
45.5
1,542.1
13
thousand )
training (Birr 5 thousand ) and Birr 120 thousand costs of registration, licensing and formation of the
company including legal fees, commissioning expenses, etc.
B.
PRODUCTION COST
The annual production cost at full operation capacity is estimated at Birr 693,130 (see
Table 7.2).
The material and utility cost accounts for 40.47 per cent, while repair and
290-14
Table 7.2
ANNUAL PRODUCTION COST AT FULL CAPACITY ('000 BIRR)
Items
Raw Material and Inputs
Utilities
Maintenance and repair
Labour direct
Factory overheads
Administration Costs
Total Operating Costs
Depreciation
Cost of Finance
Total Production Cost
C.
FINANCIAL EVALUATION
1.
Profitability
Cost
215.00
67.4
80
43.35
14.18
35.4
455.33
154.3
83.5
693.13
%
31.02
9.72
11.54
6.25
2.05
5.11
65.69
22.26
12.05
100
According to the projected income statement, the project will start generating profit in the
first year of operation. Important ratios such as profit to total sales, net profit to equity
(Return on equity) and net profit plus interest on total investment (return on total
investment) show an increasing trend during the life-time of the project.
The income statement and the other indicators of profitability show that the project is
viable.
2.
Break-even Analysis
290-15
The break-even point of the project including cost of finance when it starts to operate at
full capacity ( year 3 ) is estimated by using income statement projection.
BE =
Fixed Cost
34%
The investment cost and income statement projection are used to project the pay-back
period. The projects initial investment will be fully recovered within 3 years.
4.
Based on the cash flow statement, the calculated IRR of the project is 30 % and the net
present value at 8.5 % discount rate is Birr 1.4 million.
D.
ECONOMIC BENEFITS
The project can create employment for 11 persons. In addition to supply of the domestic
needs, the project will generate Birr 829,610 in terms of tax revenue. The establishment
of such factory will have a foreign exchange saving effect to the country by substituting
the current imports.