Bill of Quantity National Cement Factory Coppound Storm Drainage Work

Specifi
cation
Ref.No Description
Unit Quantity Rate Amount
1 Excavation for open drains (channel excavation)
1.1
Trench excavation in ordinary soil from reduced level to a
depth not excedding 1 m m
3
4413.513 50 220,675.65
1.2
Trench excavation in ordinary soil from reduced level to a
depth not excedding 2 m 9354.1514 60 561,249.08
1.3
Trench excavation in harden eathen material from
reduced level to a depth of not exceeding 1cm . m
3
778.85523 60 46,731.31
1.4
Trench excavation in harden eathen material from
reduced level to a depth of not exceeding 2 m . m
3
1650.7326 70 115,551.28
1.5
Back fill at the side of masonary ditch with selected
material brought from out side and well ram in layers not
exceeding 20cm . m
3
4312.885 95 409,724.08
Sub-Total -1 1,353,931.40
2 Masonary work
2.1
40 cm thick hard trachytic or equivalent stone masonry
ditch wall beded in cement sand mortar (1:3)
m
3
6004.616 1200 7,205,539.20
2.2
20cm thick basaltic or equivalent stone hard core well
rolled and consolidated with crushed stone. m
2
4503.462 120 540,415.44
2.3
Provide and palce riprap 20cm thick for Cemented stone
pitching, the cost include pointing of the exposed pitch
surface m
2
1020 250 255,000.00
3 Concret for structures
3.1
Provide and form5 cmthick lean concrete classC-5, with a
minimum cement content of 150 kg cement/ M
3
under
masonary structures m
2
6004.616 60 360,276.96
3.2
provide of 10cm thick c-20 mass concrete above the hard
core with the specified in the typical cross section in the
drawing m
2
4503.462 180 810,623.16
3.3
5 cm thick C- 15 concrete cooping on the top of open
masonry ditch m
2
6004.616 120 720,553.92
3.4
10cm thick pre cast Concrete ditch cover using C-25
reinforced concrete as sown detail in the drawing.Cost
including reinforcement, formwork and instalation.
3.4.1 120 cm wide ml 31.9 500
3.4.2 130 cm wide ml 15 600 9,000.00
3.4.3 140 cm wide ml 24.7 700 17,290.00
3.4.4 150 cm wide ml 10.7 800 8,560.00
3.5
C- 25 reinforced concrete heavy duty road crossing as
shown detail in the drawing.Cost including reinforcement,
formwork and instalation.
3.5.1 150 cm wide ml 403.67357 2000 807,347.14
3.5
Supply and Install of pipe culvert with all associated works
as per the drawing:( the associated works include but not
limited to earth work, end walls, inlet and out lets )
3.5.1 Nominal diameter of 1200mm(in one place) ml 22.8 2200 50,160.00
3.5.2 Nominal diameter of 900mm(in two place) ml 35.3 2000 70,600.00
Sub Total-2 10,855,365.82
Total Amount 12,209,297.22
Main Amount 12,209,297.22
contingency(10%) 1,220,929.72
15%VAT 1,831,394.58
total including contingency and VAT 15,261,621.52
National cement Factory compund storm drainage work
Drainage Bill of Quantity
Earth Works
Structures