You are on page 1of 68

Vice President - Mr.

Dilip Solanki
Execution Head - Mr. Shammi Khurana
Project In-charge

Mr. S. C. Dixit
President

Project:- DLF Primus - Group Housing, Gurgoan, Haryana.

Date :
The prestart estimate submitted by you has been approved as follows :-

Sr. No.

Contract Value
a. WCT
Escalation Payable

2
a.
b.
c.
d.
e.
f.
g.
h.

Description

Direct Cost
Material
Labour
Sub-contractor
Plant Depreciation
Operation & Fuel Cost
Wooden Shuttering
Steel Shuttering
MEP & Provisional Sum
Total Direct Cost

Indirect Cost
a. Fixed Overheads
b. Variable Overheads
Total Indirect Cost

Contribution

Percentage Contribution
As per prestart
As per tender

Note:

Pre-start
Estimate
(in lakhs)

Remarks

36274.73
1523.54

11338.84

31.26

6281.15
538.87
613.07
379.81
687.99
10084.70
29924.43

17.32
1.49
1.69
1.05
1.90
27.80
82.49

338.19
2686.19
3024.38

0.93
7.41
8.34

1802.38

4.97

4.97
8.91

The net contribution is arrived at after considering WCT but excluding Service Tax & Labour Cess.
The quality objectives based on PSE are also enclosed herewith. The project will now be monitored
on the approved prestart estimate. The PSE now should be uploaded in ERP by site.

Regards,

Mr. S. C. Dixit
CC : SPM
CC : MDS

SUMMARY SHEET COMPARISON OF TENDER VS PRESTART


Project : DLF Primus - Group Housing

S.No.

Item Description

A.

Structure Works

Earth works

Concrete Works (PCC)

Reinforced Concrete Works

Direct Cost
Tender DC

PSE RO

Difference(PSE-Tender)
PSE HO

Additional cost

Remarks

Saving

144,369

7,694,444

7,550,075

22,726,744

23,266,746

540,002

Due to PNM Cost

1,047,363,601

1,096,942,441

49,578,840

Due to PNM Cost

Water Proofing

31,383,146

30,500,999

Brick Work

90,334,125

112,381,177

Miscellenous

B.

Finishes

22,047,052
-

882,147 Extra Item added of Tie rod filling


176,965

49,201,803

49,024,838

Tiles & Painting

180,921,383

185,876,894

4,955,510

Rough Finishes

123,058,102

155,497,706

32,439,604

Stone Works

163,507,090

167,744,858

4,237,768

Laminated Wooden flooring

20,905,826

20,905,826

Doors - wooden & Fire Doors

77,702,007

78,814,503

Interiors

55,466,891

55,466,891

C.

MEP & Provisional Sums

MEP & Provisonal Sums

1,008,470,282

1,008,470,282

Total Direct Cost

2,878,735,445

2,992,443,237

224,227,050

302,438,376

Total Direct & Indirect Cost

3,102,962,495

3,294,881,613

Total Contract Value

3,627,473,285

3,627,473,285

152,353,878

152,353,878

Indirect Cost

WCT

Labour Cess
Risk & Escalation

Margin

% Margin

1,112,496

114,911,272

78,211,326

1,203,481

Ref IDC Sheet

Payable Extra
47,889,592
324,267,319
8.94

180,237,794
4.97

IDC SUMMARY SHEET COMPARISON OF TENDER VS PRESTART


Project:- DLF Primus - Group Housing, Sector 82 A,Gurgaon, Haryana.
Sr. No.

Codes

1
2
3
4
5

infra
mob
octroi
bg
ins

6
7
8
9
10
11
12
13
14
15
16
17

staff
wage
water
power
monthly
safety
cons
houseke
vehicle
pf
lab
finance

18
19
20
21

plant
repairm
fuel
repairsh
dlp

Item Description

Fixed Cost
Infrastructure
Mobilisation Demobilisation
octroi
Bank Guarantee
Insurance
Variable Cost
Staff Salary
Wages
Water Charges & Distribution
Power Charges & Distribution
Monthly Expenses
Safety Expenses
Consumables Tools & Tackles
Misc. Labour, Gen exp, housekeeping
Vehicle expenses
PF, ESIS
Lab, survey, Testing charges
Financing Cost
General Equipment related Cost
General Plant, Hire charges
Repair & maintenance of machinery
Fuel
Repair of shuttering material
Defect Liability Expenses
Total Indirect Cost

Tender

Direct Cost
Prestart RO

22,354,000
2,050,000
3,750,000
90,249,600
12,556,800
17,080,000
37,844,650
12,792,000
4,075,000
1,800,000
5,856,000
4,680,000
6,480,000
1,000,000
1,659,000

24,434,000
3,010,000
6,375,000
119,715,279
16,014,000
17,080,000
48,476,255
12,315,200
4,075,000
2,400,000
7,920,000
25,719,776
6,480,000
6,764,866
1,659,000

224,227,050

302,438,376

Prestart HO

Difference (PSE - Tender)


Additional Cost
Saving

2,080,000
960,000
2,625,000
29,465,679
3,457,200
10,631,605
600,000
2,064,000
21,039,776
5,764,866
-

476,800
-

Remarks

CAR Policy updated

Refer staff schedule

Add Cost of DG

to be checked
Depr,Fuel & Opr Passengr Hoist

DLF GH P0ject 'The Primus' Sector-82A


INDIRECT COST ANALYSIS SHEET :
Duration for the Project
S.NO
1
a
b
c
d
e
f
g
h
i
j
k

Codes

36.00
ITEM

UNIT

l
m
n

infra
infra
infra
infra
infra
infra
infra
infra
infra
infra
infra
infra
infra
infra
infra

infra

infra

Infrastructure
80%
Site Office - SPCL Charged
Add for Conference, canteen, rest room
80%
Site office for PMC / Client
80%
Stores - SPCL Cement Godown 5000 sft
Platform with concreting for steel
Misc - Lab, curing tank
Site Plumbing Work including chemical toilet
1
Septic tank, connectivity to main sewage
Temporary Approach road
Barricading & Fencing refer barricade sheet
Labour Hutments / facilities
Rent of Land / Room for labours
Rent of Land / Batch Plant
Construction cost of Hutments
1200 labours
Conveyance for labours (If labour camp set up is far
from project site)
Toilet facility for labour at labour camp

q
r

infra
infra

Water for Labour Hutments


Power for Labour Hutments only consumels

infra
infra
infra
infra
infra

Maintenance of Labour camp


Plant Installation
Batching Plant
Tower Crane
Hoist / Mixer machine etc

2
a
b
c

mob
mob
mob

Mobilisation & Demobilisation


PMV - Batching Plant, Tower crane
PMV - others
Shuttering Material

3
a
b
c
d
e
f
g
h
j
k
l
m
n
o

infra
infra
infra
infra
infra
infra
infra
infra
infra
infra
infra
infra
infra
infra

Office, Lab & Survey Equipments


Furniture, Refrigerator, AC - SPCL
Furniture, Refrigerator, AC - Client ( If required to be
provided as per Contract Conditions)
Office Equipments - Computer, Fax, Xerox
Computer
Fax
Printer
UPS
Xerox
ERP
Telephone connection for client
EPBAX System for Client
Autocat along with Plotter
Lab Equipments
Survey Equipments

4
a
b
c
d
e

bg
bg
bg
bg
bg

Bank Guarantee Charges ( Corporate Guarantee)


Earnest Money Deposit
Performance security
Mobilisation Advance CG
Retention Money - CG upto virtual completion
Retention Money CG - Upto DLP

5
a
b

ins
ins

Insurance
Insurance - Contract Value ( CAR Policy)
Insurance - Free Issue material

6
a

water

water

7
a
b
c
d
r
f

power
power
power
power
power
power

power

8
a
b
c
d
e
f

safety
safety
safety
safety
safety
safety

Months

In DC
In DC

Sft
Sft
Sft
Sft
Sft
Sft
LS
Month
LS
LS
Mtr
Months
Months
Sft

RATE

Sft

AMOUNT

TOTAL

2,100.00
600.00
2,100.00
3,000.00
5,000.00

800.00
800.00
900.00
150.00
150.00
50.00

3,000.00

250.00

225.00
400.00

1,680.00
1,800.00

1,344,000
384,000
1,512,000
450,000
750,000
300,000
750,000
100,000
378,000
720,000

200.00

12,000,000

36.0
36.0
60000

Months

25,000.00

1,500.00

150.00

225,000

LS
Months

36.00

35,000.00

500,000
1,260,000

Months

36.0

25,000.00

900,000

LS
LS

900,000
350,000
1,760,000

LS
LS

200,000
250,000

Nos.
Nos.
Nos.
Nos.
Nos.
Nos.
Nos.
Nos.
Nos
Months
Months

850,000
500,000

25,000.00
25,000.00
25,000.00
25,000.00

Land will be free of

Refer in vehicles

18.00
2.00
6.00
18.00
2.00
1.00
5.00
1.00
2.50%
2.50%

30,000.00
10,000.00
10,000.00
2,000.00
105,000.00
50,000.00
2,000.00
40,000.00
800,000.00
20.00
36.00

1.15%
1.15%
1.15%
1.15%

0.50
3.00
1.50
3.00
1.00

21,573,000.00

0.86%

3,010,000.00

0.12%

2,241,000.00

0.09%

540,000
20,000
60,000
36,000
210,000
50,000
425,000
450,000

25,000.00

0.26%
0.26%

6,375,000
-

LS

Water for Drinking + Construction Purpose

Power Charges
Power Installation & Distribution Charges
Power Connection Charges
Distribution Board & Accessories
Site Lighting
Electrical consumables
Power charges (Un productive)
(if DG set is used, Depreciation of DG + Fuel cost to
be considered)

LS
LS
Month
Month

Nos.
Nos.
Nos.
Sqm
LS
LS

868
650

Lakhs
Lakhs

Misc

1000

Lakhs

Total Expenses ( Initial)

2518

Lakhs

Less Mobilisation Advance

2500

Lakhs

Financing required (A-B) for three months

0.26%

17,080,000.00

0.68%

36
36

48,476,255.21

1.94%

4,075,000.00

0.16%

14,580,000

50,000.00

Excluding associates

4
4
2

6,375,000.00
2,500,000
30.00 Tankers in nos.8m3/tanker

Financing cost
Working capital for first 1.25 months
Shuttering Material & Scaffolding

10

QTY.

LS
LS

Water Charges
Storage & Distribution

Safety Expenses
Helmet
Safety Shoes
Safety Belts
Safety Net
Miscellenous safety coverage
Safety Signage + Other

36.00

6,000,000
1,800,000
40,676,255

1,500.00
1,500.00
500.00
1,500.00

18

75.00
300.00
650.00
250.00

450,000
1,800,000
650,000
375,000
300,000
500,000

0.8%

Salaries & Allowances


Nos
Project Manager ( DGM)
Construction Manager - Execution

DLF PRIMUS

C001
E002

Months

Salary PM

Amount
-

IDC

4/71

Manager Structural steel works


Construction Engr - Execution
Assistant Enginneer - Execution
Junior Enginneer - Execution
Manager _ Services
Assistant Enginneer - Services
Site Surveyor
QA/QC Manager
Billing Engineer
Plant Manager
Plant Engineer
Safety Engineer

Safety Stewert
Concrete/ shuttering foremen
Finishing Foreman
Lab Tech
Admn/accounts officer
Accounts Assistant
Store Manager
Store keeper
Store Assst.
Computer Operator
Time Keeper

11
a
b
c
d
e
f
g
12
a
b
c
d
e
f

13
a
b
14
a
b
c
d
e
f
g
h
I
j
k
l
15
a

staff
staff

TOTAL
Add % for Escalation

staff
staff

Project Basrd Staff


Total Amount of Salaries / Allowances
Staff Accomadation
Type I
Type II

monthly
monthly
monthly
monthly
monthly
monthly
wage
wage
monthly

Type III

cons
cons

Mess Facility Maintainence


Cooks
Helpers
Utensils
Total
Misc Wages
Maintenance / Store handling
Mechanic
Electrician
Office boy
Watchman - Guard
Watchman Supervisor
Gunman
Add % for benefits. (for a to d)
Total
Consumables & Tools Tackles
Consumables
Tools & Tackles

monthly
monthly
monthly
monthly
monthly
monthly
monthly
monthly
monthly
monthly
monthly
monthly

Monthly Expenses
Telephone Landline / Fax - SPCL
Telephone Expenses - Client
ERP ISDN Line
Mobile
Computer consumables
Stationery
Photographs
Staff Welfare - Tea/ Lunch
Business promotion + Misc
Local Conveyance
Medical expenses
Testing Charges

vehicle
vehicle

Vehicles
Bus - Depreciation
Fuel cost

wage
wage
wage
wage
wage
wage
wage
wage

vehicle

vehicle

vehicle

vehicle

d
e

Driver
Jeep/ Tata Sumo - Depreciation
Fuel cost
Driver
LCV - Depreciation
Fuel cost
Driver
Car - Depreciation FOR CLIENT
Fuel cost
Driver
Car - Depreciation ( SPCL)
Fuel cost
Driver
Two wheeler
Hrdra Crane - for Shifting
Fuel cost
Driver
Tractors - for shifting
Fuel cost
Driver

16
a
b
c

houseke
houseke
houseke

Housekeeping & Misc expenses


Housekeeping of site
Disposal of Debris
Repairs & Maintenance of Shuttering

17

repairm

Misc. Machinery not loaded in DC

E003
E002
S003
S003
E002

E002

119,715,279
20%
15

1
2
2
1
2
8
8
8

10,000.00

Months
Months
Months
Months
Months

30.0
36.0
28.0
36.0
28.0
35.0
34.0
34.0

Months
Months
LS
Nos
2
2
4
25
3
1

Months

25,000.00
25,000.00
28,000.00
22,000.00
22,000.00
1,000.00
6,500.00
5,000.00

Salary PM

34.0
34.0
34.0
34.0
34.0
34.00

11,000.00
11,000.00
4,000.00
10,000.00
15,000.00
15,000.00

15%

LS
LS

9,850,000.00

0.39%

12,886,000.00

0.52%

2,400,000.00

0.10%

4,993,200.00

0.20%

25,719,776.07

1.03%

3,420,000.00

0.14%

6,764,866.04

0.27%

748,000
748,000
544,000
8,500,000
1,530,000
510,000
306,000

36.0
36.0
36.0
36.0
36.0
36.0
36.0
36.0
36.0
36.0
36.0

7,000.00
8,000.00
8,000.00
32,700.00
8,000.00
7,000.00
3,000.00
25,000.00
5,000.00
10,000.00
20,000.00
20,000.00

288,000
1,177,200
288,000
252,000
108,000
900,000
180,000
360,000
720,000
720,000

2
2

Months

31.0
20.0

45,000.00
45,000.00

2,790,000
1,800,000

Months

Months

Months
21,129,776
2

Months

Months
Months

Months

10.0

Months
LS
LS

36.0

4,500.00

1,620,000
1,000,000
800,000

6,764,866

Defect liability maintenance


Asst.engr.

DLF PRIMUS

4.79%

Amount

Months
Months
Months
Months
Months
Months
Months
Months
Months
Months
Months
Months

119,715,278.69
750,000
1,800,000
1,568,000
792,000
1,232,000
280,000
1,768,000
1,360,000
300,000

1,200,000
1,200,000

repairm

18
a

Months

IDC

12

30,000.00

360,000

5/71

b
c

Jr. Engg
Accountant / store

Add % for benefits


Total

15%

dlp
d

dlp

Replacement of Material if any

19

pf

PF - Labours

20

pf

ESI - 6.5% of 20% Labour Com. (Civil)

21
a
b

infra
monthly
houseke
infra

OTHERS
Mobile Toilets
Creche Expenses
House Keeping during Handing over
Vertical Communication System

Months
Months

12
12

12

Months

75,000.00

600

4,000

20%

2
1
200

4,500

30.00
5.00

IDC

300,000
660,000
99,000
759,000
900,000

15.0%

310,000.00
20,000.00

1,659,000.00

0.07%

6,480,000.00

0.26%

6,480,000

6.50%

15,000.00

Total Indirect Cost

DLF PRIMUS

18.0

25,000.00
10,000.00

620,000
600,000
4,500,000
5,720,000.00

0.23%

302,438,376.01

12.10%

6/71

SUMMARY SHEET COMPARISON OF TENDER VS PRESTART


Project : DLF Primus - Group Housing
Sl.No Item Description

DC Amount

SPCL Amount

PSE Amount

Difference

Structure Works
1

Earth works

7,694,444

10,312,701

7,550,075

-144,369

Concrete Works (PCC)

22,726,744

30,462,354

23,266,746

540,002

Reinforced Concrete Works

1,047,363,601

1,396,638,816

1,096,942,441

49,578,840

Water Proofing

31,383,146

42,055,140

30,500,999

-882,147

Brick Work

90,334,125

121,071,606

112,381,177

22,047,052

Miscellenous

49,201,803

66,126,619

49,024,838

-176,965

1,248,703,863

1,666,667,236

1,319,666,276

70,962,413

Sub Total
Finishes

Tiles & Painting

180,921,383

242,581,885

185,876,894

4,955,510

Rough Finishes

123,058,102

164,924,904

155,497,706

32,439,604

Stone Works

163,507,090

219,134,828

167,744,858

4,237,768

Laminated Wooden flooring

20,905,826

27,970,019

20,905,826

Doors - wooden & Fire Doors

77,702,007

104,126,575

78,814,503

1,112,496

Interiors

55,466,891

74,330,910

55,466,891

621,561,300

833,069,122

664,306,678

42,745,378

1,870,265,163

2,499,736,358

1,983,972,954

113,707,791

Sub Total

Cummulative

DLF GH Project 'The Primus' Sector-82A


BOQ OF STRUCTURE WORKS

ITEM

DESCRIPTION

1.00

EXCAVATION, DISPOSAL, BACK FILLING

1.01

Earth work in manual excavation in foundation trenches in all types of soil

UOM

QTY

R & S.S
Civil
TENDER
DC RATE

1.32700512584
1.34027517710
TENDER
DC AMOUNT

PSE
RATE

Material

PSE AMOUNT

Labour

Sub Contractor

Plant Depric.

Plant Oprn & Fuel

Wooden Shuttering

Steel Shuttering

Testing Charges

upto a depth of 3.0m, dressing of sides, ramming of bottoms, getting out the
excavated soil, disposal / stacking of surplus excavated soil within plot
boundary as directed by the Engineer In charge including all leads and lifts.
a

Item same as above but for depth of 0m to 3m

Cum

2,488.00

90.00

223,920.00

90.00

Item same as above but for depth of 3m to 6m

Cum

3,070.00

105.00

322,350.00

105.00

Item same as above but for depth of 6m to 9m

Cum

4,809.00

120.00

577,080.00

120.00

Item same as above but for depth of 9m to 12m

Cum

1,961.00

240.00

470,640.00

240.00

Extra over item no. 1.02 for additional lead of disposal outside plot
boundary at Owner nominated location as directed by the Engineer In
charge. (For payment One side lead only to be considered)

Cum

Rate Only

80.00

1.02

223,920.00
322,350.00
577,080.00
470,640.00
-

90.0

223920.0

105.0

322350.0

120.0

577080.0

240.0

470640.0

35.0

2238267.5

1.03

All charges for backfilling of available excavated earth in trenches, plinth,


sides of
foundations,behind retaining wall, general area filling for landscape, or for
maintaing

levels in layers not exceeding 200mm in depth including watering, ramming,


compacting, consolidating in deposited layer to achieve 95% Proctor
Density and
transportation of soil, all labour, materials, machinery, tools & tackles etc. for
all lead &
lift to the entire satisfaction of Engineer.
1.04

Cum

63,950.50

50.00

3,197,525.00

50.60

Item same as above 1.07 but earth brought from out side as directed by the
Engineer In charge at all depth and All location for every 3km lead and part
thereof.

3,236,081.04
-

9.0

576758.7

6.6

421054.8

Cum

Rate Only

400.00
-

1.05

a
b
1.06

1.06

Providing & filling good quality of fine sand (free from silt, clay, mica, soil)
for

foundation pits and wherever specified including filling in 150mm layers and

compacting/ saturating to the required levels, including all leads and lifts,

etc.,complete, and in plinth and under floor, above raft, including watering,
ramming and

consolidation, dressing complete to the entire satisfaction of Engineer.

LIFT PIT
Entrance Lobby - Non tower Area
Providing & Filling toilet sunken areas and entrance lobby - non tower area
with Brick
Bat, including the cost of ramming & consolidation at all lead and lifts at all
levels, to
the satisfaction of Engineer.

Cum
Cum

188.31
25.45

1,207.80
1,207.80

227,440.69
30,738.49

1207.80
1207.80

199194.2
26921.0

150.0
150.0

28246.5
3817.5

2405.0

1358825.0

200.0

113000.0

Cum

565.00

2,150.00

1,214,750.00

2605.00

1,471,825.00
-

concentrate (20% concentration) diluted to a water based emulsion of 1%

Sqm

22,000.00

65.00

1,430,000.00

45.00

7,694,444.18
2.00

1057.8
1057.8

Providing Anti Termite Treatment comprising of providing & injecting


chemical
emulsion for Preconstructional Anti-termite treatment with chloropyrifos
emulsifiable

chloropyrifos as per CPWD/IS Specifications in foundation trenches, under


floors,
junction of floors & walls, external perimeter of building & backfilling. Plinth
area only
shall be measured & paid for.

227,440.69
30,738.49
-

REINFORCEMENT
Providing & fixing H.Y.S.D. Reinforcement as specified for R.C.C. work in

990,000.00

45.0

7,550,075.23
-

1,584,940.18

990000.0
4,967,321.50

576,758.71

421,054.83

sub-structure and superstructure including cost of binding wire, cover


blocks,
straightening, cutting, bending, shifting cut & bent bars from steel yard to
work place,
binding and placing in position to correct level & alignment all complete as
directed by
the Engineer In charge at all levels and at all leads. (The rates are inclusive
of
sortening of useable reinforcement steel in specified length & dia.)

2.01

Reinforcement Steel In Fe500 Raft / Foundation, Footings & Sub structure

MT

3,194.00

53,128.58

169,692,682.43 55402.17

176,954,534.21

49682.0

158684308.0

200.0

638800.0

3050.0

9741700.0

1255.1

4008632.2

915.1

2922894.0

300.0

958200.0

2.02

Reinforcement Steel Fe500 in Superstructure

MT

6,819.00

54,828.58

373,876,082.57 57102.17

389,379,704.12

49682.0

338781558.0

200.0

1363800.0

4750.0

32390250.0

1255.1

8558191.4

915.1

6240204.7

300.0

2045700.0

3.00

CENTRING & SHUTTERING

SUB TOTAL

Centring and Shuttering including Strutting, Propping etc. and removal of


formwork
after specified period has elapsed after concreting, hacking of concrete
wherever
applicable with prior approval of the Engineer including all leads & lifts at all
levels,
tools & tackles, nails and other consumables.

10,013.00

543,568,765.00

566,334,238.32
-

497,465,866

2,002,600

42,131,950

12,566,824

9,163,099

3,003,900

ITEM

DESCRIPTION

TENDER
DC RATE

TENDER
DC AMOUNT

PSE
RATE

Material

PSE AMOUNT

Labour

Sub Contractor

Plant Depric.

Plant Oprn & Fuel

Wooden Shuttering

Steel Shuttering

UOM

QTY

3.001 Cent.&Shutt. Foundation, Raft & Footing / Pedestal at all location & levels

Sqm

6,339.00

341.65

2,165,696.41

385.95

2,446,542.17

8.0

50712.0

4.0

25356.0

124.0

786036.0

15.4

97335.4

14.6

92522.8

85.0

538815.0

135.0

855765.0

3.002 Cent.&Shutt. Column at Foundation to First Basement Fl lvl.

Sqm

9,712.00

341.65

3,318,069.65

385.95

3,748,354.25

8.0

77696.0

4.0

38848.0

124.0

1204288.0

15.4

149127.8

14.6

141754.4

85.0

825520.0

135.0

1311120.0

3.003 Cent.&Shutt. Column at First basement to GF

Sqm

11,682.00

341.65

3,991,113.02

463.73

5,417,277.34

8.0

93456.0

4.0

46728.0

201.8

2357168.0

15.4

179377.2

14.6

170508.2

85.0

992970.0

135.0

1577070.0

3.004 Cent.&Shutt. Column GF To 1st Floor

Sqm

6,249.00

337.65

2,109,952.23

463.73

2,897,839.93

8.0

49992.0

4.0

24996.0

201.8

1260909.3

15.4

95953.4

14.6

91209.2

85.0

531165.0

135.0

843615.0

3.005 Cent.&Shutt. Column 1st To 2nd Floor

Sqm

5,792.00

341.65

1,978,815.84

463.73

2,685,915.97

8.0

46336.0

4.0

23168.0

201.8

1168696.9

15.4

88936.2

14.6

84538.9

85.0

492320.0

135.0

781920.0

3.006 Cent.&Shutt. Column 2nd To 3rd Floor

Sqm

5,302.00

345.65

1,832,617.11

463.73

2,458,688.96

8.0

42416.0

4.0

21208.0

201.8

1069825.8

15.4

81412.2

14.6

77386.9

85.0

450670.0

135.0

715770.0

3.007 Cent.&Shutt. Column 3rd To 4th Floor

Sqm

5,473.00

349.65

1,913,614.64

463.73

2,537,986.55

8.0

43784.0

4.0

21892.0

201.8

1104329.8

15.4

84038.0

14.6

79882.8

85.0

465205.0

135.0

738855.0

3.008 Cent.&Shutt. Column 4th To 5th Floor

Sqm

5,491.00

353.65

1,941,872.28

463.73

2,546,333.67

8.0

43928.0

4.0

21964.0

201.8

1107961.8

15.4

84314.3

14.6

80145.5

85.0

466735.0

135.0

741285.0

3.009 Cent.&Shutt. Column 5th To 6th Floor

Sqm

5,207.00

357.65

1,862,264.70

463.73

2,414,634.75

8.0

41656.0

4.0

20828.0

201.8

1050656.9

15.4

79953.5

14.6

76000.3

85.0

442595.0

135.0

702945.0

3.010 Cent.&Shutt. Column 6th To 7th Floor

Sqm

5,207.00

361.65

1,883,092.70

463.73

2,414,634.75

8.0

41656.0

4.0

20828.0

201.8

1050656.9

15.4

79953.5

14.6

76000.3

85.0

442595.0

135.0

702945.0

3.011 Cent.&Shutt. Column 7th To 8th Floor

Sqm

5,207.00

365.65

1,903,920.70

463.73

2,414,634.75

8.0

41656.0

4.0

20828.0

201.8

1050656.9

15.4

79953.5

14.6

76000.3

85.0

442595.0

135.0

702945.0

3.012 Cent.&Shutt. Column 8th To 9th Floor

Sqm

5,207.00

369.65

1,924,748.70

463.73

2,414,634.75

8.0

41656.0

4.0

20828.0

201.8

1050656.9

15.4

79953.5

14.6

76000.3

85.0

442595.0

135.0

702945.0

3.013 Cent.&Shutt. Column 9th To 10th Floor

Sqm

5,207.00

373.65

1,945,576.70

463.73

2,414,634.75

8.0

41656.0

4.0

20828.0

201.8

1050656.9

15.4

79953.5

14.6

76000.3

85.0

442595.0

135.0

702945.0

3.014 Cent.&Shutt. Column 10th To 11th Floor

Sqm

5,207.00

377.65

1,966,404.70

463.73

2,414,634.75

8.0

41656.0

4.0

20828.0

201.8

1050656.9

15.4

79953.5

14.6

76000.3

85.0

442595.0

135.0

702945.0

3.015 Cent.&Shutt. Column 11th To 12th Floor

Sqm

5,100.00

381.65

1,946,396.54

463.73

2,365,015.79

8.0

40800.0

4.0

20400.0

201.8

1029066.7

15.4

78310.5

14.6

74438.6

85.0

433500.0

135.0

688500.0

3.016 Cent.&Shutt. Column 12th To 13th Floor

Sqm

5,100.00

385.65

1,966,796.54

463.73

2,365,015.79

8.0

40800.0

4.0

20400.0

201.8

1029066.7

15.4

78310.5

14.6

74438.6

85.0

433500.0

135.0

688500.0

3.017 Cent.&Shutt. Column 13th To 14th Floor

Sqm

4,903.00

389.65

1,910,436.20

463.73

2,273,661.26

8.0

39224.0

4.0

19612.0

201.8

989316.4

15.4

75285.6

14.6

71563.2

85.0

416755.0

135.0

661905.0

3.018 Cent.&Shutt. Column 14th To 15th Floor

Sqm

4,450.00

393.65

1,751,726.39

463.73

2,063,592.21

8.0

35600.0

4.0

17800.0

201.8

897911.1

15.4

68329.8

14.6

64951.3

85.0

378250.0

135.0

600750.0

3.019 Cent.&Shutt. Column 15th To 16th Floor

Sqm

4,262.00

397.65

1,694,768.87

463.73

1,976,411.23

8.0

34096.0

4.0

17048.0

201.8

859976.9

15.4

65443.0

14.6

62207.3

85.0

362270.0

135.0

575370.0

3.020 Cent.&Shutt. Column 16th To 17th Floor

Sqm

4,262.00

401.65

1,711,816.87

463.73

1,976,411.23

8.0

34096.0

4.0

17048.0

201.8

859976.9

15.4

65443.0

14.6

62207.3

85.0

362270.0

135.0

575370.0

3.021 Cent.&Shutt. Column 17th To 18th Floor

Sqm

3,423.00

405.65

1,388,527.56

463.73

1,587,342.95

8.0

27384.0

4.0

13692.0

201.8

690685.3

15.4

52560.2

14.6

49961.4

85.0

290955.0

135.0

462105.0

3.022 Cent.&Shutt. Column 18th To 19th Floor

Sqm

2,777.00

409.65

1,137,588.00

463.73

1,287,774.28

8.0

22216.0

4.0

11108.0

201.8

560336.9

15.4

42640.9

14.6

40532.5

85.0

236045.0

135.0

374895.0

3.023 Cent.&Shutt. Column 19th To 20th Floor

Sqm

2,777.00

413.65

1,148,696.00

463.73

1,287,774.28

8.0

22216.0

4.0

11108.0

201.8

560336.9

15.4

42640.9

14.6

40532.5

85.0

236045.0

135.0

374895.0

3.024 Cent.&Shutt. Column 20th To 21st Floor

Sqm

2,777.00

417.65

1,159,804.00

463.73

1,287,774.28

8.0

22216.0

4.0

11108.0

201.8

560336.9

15.4

42640.9

14.6

40532.5

85.0

236045.0

135.0

374895.0

3.025 Cent.&Shutt. Column 21st To 22nd Floor

Sqm

2,777.00

421.65

1,170,912.00

463.73

1,287,774.28

8.0

22216.0

4.0

11108.0

201.8

560336.9

15.4

42640.9

14.6

40532.5

85.0

236045.0

135.0

374895.0

3.026 Cent.&Shutt. Column 22nd To 23rd Floor

Sqm

2,777.00

425.65

1,182,020.00

463.73

1,287,774.28

8.0

22216.0

4.0

11108.0

201.8

560336.9

15.4

42640.9

14.6

40532.5

85.0

236045.0

135.0

374895.0

3.027 Cent.&Shutt. Column 23rd To 24th Floor

Sqm

2,777.00

429.65

1,193,128.00

463.73

1,287,774.28

8.0

22216.0

4.0

11108.0

201.8

560336.9

15.4

42640.9

14.6

40532.5

85.0

236045.0

135.0

374895.0

3.028 Cent.&Shutt. Column 24th To 25th Floor

Sqm

2,777.00

433.65

1,204,236.00

463.73

1,287,774.28

8.0

22216.0

4.0

11108.0

201.8

560336.9

15.4

42640.9

14.6

40532.5

85.0

236045.0

135.0

374895.0

3.029 Cent.&Shutt. Column 25th To 26th Floor

Sqm

2,777.00

437.65

1,215,344.00

463.73

1,287,774.28

8.0

22216.0

4.0

11108.0

201.8

560336.9

15.4

42640.9

14.6

40532.5

85.0

236045.0

135.0

374895.0

3.030 Cent.&Shutt. Column 26th To 27th Floor

Sqm

2,777.00

441.65

1,226,452.00

463.73

1,287,774.28

8.0

22216.0

4.0

11108.0

201.8

560336.9

15.4

42640.9

14.6

40532.5

85.0

236045.0

135.0

374895.0

3.031 Cent.&Shutt. Column 27th To 28th Floor

Sqm

2,777.00

445.65

1,237,560.00

463.73

1,287,774.28

8.0

22216.0

4.0

11108.0

201.8

560336.9

15.4

42640.9

14.6

40532.5

85.0

236045.0

135.0

374895.0

3.032 Cent.&Shutt. Column 28th To 29th Floor

Sqm

2,777.00

449.65

1,248,668.00

463.73

1,287,774.28

8.0

22216.0

4.0

11108.0

201.8

560336.9

15.4

42640.9

14.6

40532.5

85.0

236045.0

135.0

374895.0

3.033 Cent.&Shutt. Column 29th To 30th Floor

Sqm

2,777.00

453.65

1,259,776.00

463.73

1,287,774.28

8.0

22216.0

4.0

11108.0

201.8

560336.9

15.4

42640.9

14.6

40532.5

85.0

236045.0

135.0

374895.0

3.034 Cent.&Shutt. Column 30th To 31st Floor

Sqm

2,823.00

457.65

1,291,935.73

463.73

1,309,105.80

8.0

22584.0

4.0

11292.0

201.8

569618.7

15.4

43347.2

14.6

41203.9

85.0

239955.0

135.0

381105.0

3.035 Cent.&Shutt. Column 31st To 32nd Floor

Sqm

2,513.00

461.65

1,160,117.35

463.73

1,165,349.94

8.0

20104.0

4.0

10052.0

201.8

507067.6

15.4

38587.1

14.6

36679.2

85.0

213605.0

135.0

339255.0

3.036 Cent.&Shutt. Column 32nd To 33rd Floor

Sqm

1,958.00

465.65

911,735.61

463.73

907,980.57

8.0

15664.0

4.0

7832.0

201.8

395080.9

15.4

30065.1

14.6

28578.6

85.0

166430.0

135.0

264330.0

3.037 Cent.&Shutt. Column 33rd To 34th Floor

Sqm

1,629.00

469.65

765,053.95

463.73

755,413.87

8.0

13032.0

4.0

6516.0

201.8

328696.0

15.4

25013.3

14.6

23776.6

85.0

138465.0

135.0

219915.0

3.038 Cent.&Shutt. Column 34th To 35th Floor

Sqm

499.72

473.65

236,690.57

463.73

231,734.45

8.0

3997.8

4.0

1998.9

201.8

100832.4

15.4

7673.2

14.6

7293.8

85.0

42476.2

135.0

67462.2

3.039 Cent.&Shutt. of wall at Foundn to First basement floor lvl.

Sqm

11,335.00

341.65

3,872,561.72

385.95

4,374,752.41

8.0

90680.0

4.0

45340.0

124.0

1405540.0

15.4

174049.0

14.6

165443.4

85.0

963475.0

135.0

1530225.0

3.040 Cent.&Shutt. Of wall at first basement floor to GF

Sqm

11,340.00

341.65

3,874,269.95

385.95

4,376,682.17

8.0

90720.0

4.0

45360.0

124.0

1406160.0

15.4

174125.8

14.6

165516.4

85.0

963900.0

135.0

1530900.0

3.041 Cent.&Shutt. Wall overheadwater talk wall 3rd To 4th Floor

Sqm

108.00

373.65

40,353.81

478.73

51,702.69

8.0

864.0

19.0

2052.0

201.8

21792.0

15.4

1658.3

14.6

1576.3

85.0

9180.0

135.0

14580.0

3.042 Cent.&Shutt. Wall overheadwater talk wall 6th To 7th Floor

Sqm

144.00

385.65

55,533.08

478.73

68,936.92

8.0

1152.0

19.0

2736.0

201.8

29056.0

15.4

2211.1

14.6

2101.8

85.0

12240.0

135.0

19440.0

3.042 Cent.&Shutt. Wall overheadwater talk wall 14th To 15th Floor

Sqm

267.00

417.65

111,511.58

478.73

127,820.53

8.0

2136.0

19.0

5073.0

201.8

53874.7

15.4

4099.8

14.6

3897.1

85.0

22695.0

135.0

36045.0

3.043 Cent.&Shutt. Wall overheadwater talk wall 17th To 18th Floor

Sqm

387.00

429.65

166,273.15

478.73

185,267.96

8.0

3096.0

19.0

7353.0

201.8

78088.0

15.4

5942.4

14.6

5648.6

85.0

32895.0

135.0

52245.0

Testing Charges

ITEM

DESCRIPTION

3.043 Cent.&Shutt. Wall overheadwater talk wall 32nd To 33rd Floor

UOM

QTY

TENDER
DC RATE

TENDER
DC AMOUNT

PSE
RATE

Material

PSE AMOUNT

Labour

Sub Contractor

Plant Depric.

Plant Oprn & Fuel

Wooden Shuttering

Steel Shuttering

Sqm

319.00

489.65

156,197.20

478.73

152,714.42

8.0

2552.0

19.0

6061.0

201.8

64367.1

15.4

4898.2

14.6

4656.1

85.0

27115.0

135.0

43065.0

3.044 Cent.&Shutt. Wall overheadwater talk wall 33rd To 34th Floor

sqm

356.00

493.65

175,738.11

478.73

170,427.38

8.0

2848.0

19.0

6764.0

201.8

71832.9

15.4

5466.4

14.6

5196.1

85.0

30260.0

135.0

48060.0

3.045 Cent.&Shutt. Staircases at Foundn to first basement floor lvl.

Sqm

366.07

371.65

136,048.11

483.73

177,077.89

8.0

2928.5

24.0

8785.6

201.8

73864.5

15.4

5621.0

14.6

5343.1

85.0

31115.8

135.0

49419.3

3.046 Cent.&Shutt. Staircases at first basement floor to GF

Sqm

420.37

371.65

156,228.28

483.73

203,344.07

8.0

3362.9

24.0

10088.8

201.8

84820.9

15.4

6454.8

14.6

6135.6

85.0

35731.3

135.0

56749.7

3.047 Cent.&Shutt. Staircases GF To 1st Floor

Sqm

338.02

367.65

124,273.16

483.73

163,511.69

8.0

2704.2

24.0

8112.6

201.8

68205.7

15.4

5190.4

14.6

4933.7

85.0

28732.0

135.0

45633.2

3.048 Cent.&Shutt. Staircases 1st To 2nd Floor

Sqm

360.10

371.65

133,829.78

483.73

174,190.56

8.0

2880.8

24.0

8642.4

201.8

72660.1

15.4

5529.3

14.6

5255.9

85.0

30608.5

135.0

48613.5

3.049 Cent.&Shutt. Staircases 2nd To 3rd Floor

Sqm

350.69

375.65

131,737.23

483.73

169,641.10

8.0

2805.6

24.0

8416.7

201.8

70762.4

15.4

5384.9

14.6

5118.7

85.0

29809.1

135.0

47343.8

3.050 Cent.&Shutt. Staircases 3rd To 4th Floor

Sqm

327.66

379.65

124,396.75

483.73

158,500.83

8.0

2621.3

24.0

7864.0

201.8

66115.5

15.4

5031.3

14.6

4782.5

85.0

27851.5

135.0

44234.7

3.051 Cent.&Shutt. Staircases 4th To 5th Floor

Sqm

327.66

383.65

125,707.41

483.73

158,500.83

8.0

2621.3

24.0

7864.0

201.8

66115.5

15.4

5031.3

14.6

4782.5

85.0

27851.5

135.0

44234.7

3.052 Cent.&Shutt. Staircases 5th To 6th Floor

Sqm

330.69

387.65

128,192.28

483.73

159,966.08

8.0

2645.6

24.0

7936.7

201.8

66726.7

15.4

5077.8

14.6

4826.7

85.0

28109.0

135.0

44643.7

3.053 Cent.&Shutt. Staircases 6th To 7th Floor

Sqm

284.95

391.65

111,598.29

483.73

137,836.80

8.0

2279.6

24.0

6838.7

201.8

57495.9

15.4

4375.4

14.6

4159.0

85.0

24220.5

135.0

38467.8

3.054 Cent.&Shutt. Staircases 7th To 8th Floor

Sqm

284.95

395.65

112,738.08

483.73

137,836.80

8.0

2279.6

24.0

6838.7

201.8

57495.9

15.4

4375.4

14.6

4159.0

85.0

24220.5

135.0

38467.8

3.055 Cent.&Shutt. Staircases 8th To 9th Floor

Sqm

284.95

399.65

113,877.87

483.73

137,836.80

8.0

2279.6

24.0

6838.7

201.8

57495.9

15.4

4375.4

14.6

4159.0

85.0

24220.5

135.0

38467.8

3.056 Cent.&Shutt. Staircases 9th To 10th Floor

Sqm

284.95

403.65

115,017.65

483.73

137,836.80

8.0

2279.6

24.0

6838.7

201.8

57495.9

15.4

4375.4

14.6

4159.0

85.0

24220.5

135.0

38467.8

3.057 Cent.&Shutt. Staircases 10th To 11th Floor

Sqm

284.95

407.65

116,157.44

483.73

137,836.80

8.0

2279.6

24.0

6838.7

201.8

57495.9

15.4

4375.4

14.6

4159.0

85.0

24220.5

135.0

38467.8

3.058 Cent.&Shutt. Staircases 11th To 12th Floor

Sqm

284.95

411.65

117,297.22

483.73

137,836.80

8.0

2279.6

24.0

6838.7

201.8

57495.9

15.4

4375.4

14.6

4159.0

85.0

24220.5

135.0

38467.8

3.059 Cent.&Shutt. Staircases 12th To 13th Floor

Sqm

284.95

415.65

118,437.01

483.73

137,836.80

8.0

2279.6

24.0

6838.7

201.8

57495.9

15.4

4375.4

14.6

4159.0

85.0

24220.5

135.0

38467.8

3.060 Cent.&Shutt. Staircases 13th To 14th Floor

Sqm

284.95

419.65

119,576.80

483.73

137,836.80

8.0

2279.6

24.0

6838.7

201.8

57495.9

15.4

4375.4

14.6

4159.0

85.0

24220.5

135.0

38467.8

3.061 Cent.&Shutt. Staircases 14th To 15th Floor

Sqm

284.95

423.65

120,716.58

483.73

137,836.80

8.0

2279.6

24.0

6838.7

201.8

57495.9

15.4

4375.4

14.6

4159.0

85.0

24220.5

135.0

38467.8

3.062 Cent.&Shutt. Staircases 15th To 16th Floor

Sqm

251.98

427.65

107,758.32

483.73

121,889.91

8.0

2015.8

24.0

6047.5

201.8

50844.0

15.4

3869.2

14.6

3677.8

85.0

21418.3

135.0

34017.3

3.063 Cent.&Shutt. Staircases 16th To 17th Floor

Sqm

251.98

431.65

108,766.24

483.73

121,889.91

8.0

2015.8

24.0

6047.5

201.8

50844.0

15.4

3869.2

14.6

3677.8

85.0

21418.3

135.0

34017.3

3.064 Cent.&Shutt. Staircases 17th To 18th Floor

Sqm

251.98

435.65

109,774.16

483.73

121,889.91

8.0

2015.8

24.0

6047.5

201.8

50844.0

15.4

3869.2

14.6

3677.8

85.0

21418.3

135.0

34017.3

3.065 Cent.&Shutt. Staircases 18th To 19th Floor

Sqm

181.75

439.65

79,905.15

483.73

87,917.03

8.0

1454.0

24.0

4362.0

201.8

36672.8

15.4

2790.8

14.6

2652.8

85.0

15448.6

135.0

24536.1

3.066 Cent.&Shutt. Staircases 19th To 20th Floor

Sqm

181.75

443.65

80,632.14

483.73

87,917.03

8.0

1454.0

24.0

4362.0

201.8

36672.8

15.4

2790.8

14.6

2652.8

85.0

15448.6

135.0

24536.1

3.067 Cent.&Shutt. Staircases 20th To 21st Floor

Sqm

181.75

447.65

81,359.13

483.73

87,917.03

8.0

1454.0

24.0

4362.0

201.8

36672.8

15.4

2790.8

14.6

2652.8

85.0

15448.6

135.0

24536.1

3.068 Cent.&Shutt. Staircases 21st To 22nd Floor

Sqm

181.75

451.65

82,086.13

483.73

87,917.03

8.0

1454.0

24.0

4362.0

201.8

36672.8

15.4

2790.8

14.6

2652.8

85.0

15448.6

135.0

24536.1

3.069 Cent.&Shutt. Staircases 22nd To 23rd Floor

Sqm

181.75

455.65

82,813.12

483.73

87,917.03

8.0

1454.0

24.0

4362.0

201.8

36672.8

15.4

2790.8

14.6

2652.8

85.0

15448.6

135.0

24536.1

3.070 Cent.&Shutt. Staircases 23rd To 24th Floor

Sqm

181.75

459.65

83,540.12

483.73

87,917.03

8.0

1454.0

24.0

4362.0

201.8

36672.8

15.4

2790.8

14.6

2652.8

85.0

15448.6

135.0

24536.1

3.071 Cent.&Shutt. Staircases 24th To 25th Floor

Sqm

181.75

463.65

84,267.11

483.73

87,917.03

8.0

1454.0

24.0

4362.0

201.8

36672.8

15.4

2790.8

14.6

2652.8

85.0

15448.6

135.0

24536.1

3.072 Cent.&Shutt. Staircases 25th To 26th Floor

Sqm

181.75

467.65

84,994.11

483.73

87,917.03

8.0

1454.0

24.0

4362.0

201.8

36672.8

15.4

2790.8

14.6

2652.8

85.0

15448.6

135.0

24536.1

3.073 Cent.&Shutt. Staircases 26th To 27th Floor

Sqm

181.75

471.65

85,721.10

483.73

87,917.03

8.0

1454.0

24.0

4362.0

201.8

36672.8

15.4

2790.8

14.6

2652.8

85.0

15448.6

135.0

24536.1

3.074 Cent.&Shutt.Staircases 27th To 28th Floor

Sqm

181.75

475.65

86,448.10

483.73

87,917.03

8.0

1454.0

24.0

4362.0

201.8

36672.8

15.4

2790.8

14.6

2652.8

85.0

15448.6

135.0

24536.1

3.075 Cent.&Shutt. Staircases 28th To 29th Floor

Sqm

181.75

479.65

87,175.09

483.73

87,917.03

8.0

1454.0

24.0

4362.0

201.8

36672.8

15.4

2790.8

14.6

2652.8

85.0

15448.6

135.0

24536.1

3.076 Cent.&Shutt. Staircases 29th To 30th Floor

Sqm

181.75

483.65

87,902.09

483.73

87,917.03

8.0

1454.0

24.0

4362.0

201.8

36672.8

15.4

2790.8

14.6

2652.8

85.0

15448.6

135.0

24536.1

3.077 Cent.&Shutt.Staircases 30th To 31st Floor

Sqm

181.75

487.65

88,629.08

483.73

87,917.03

8.0

1454.0

24.0

4362.0

201.8

36672.8

15.4

2790.8

14.6

2652.8

85.0

15448.6

135.0

24536.1

3.078 Cent.&Shutt.Staircases 31st To 32nd Floor

Sqm

181.75

491.65

89,356.08

483.73

87,917.03

8.0

1454.0

24.0

4362.0

201.8

36672.8

15.4

2790.8

14.6

2652.8

85.0

15448.6

135.0

24536.1

3.079 Cent.&Shutt.Staircases 32nd To 33rd Floor

Sqm

181.75

495.65

90,083.07

483.73

87,917.03

8.0

1454.0

24.0

4362.0

201.8

36672.8

15.4

2790.8

14.6

2652.8

85.0

15448.6

135.0

24536.1

3.080 Cent.&Shutt.Staircases 33rd To 34th Floor

Sqm

181.75

499.65

90,810.07

483.73

87,917.03

8.0

1454.0

24.0

4362.0

201.8

36672.8

15.4

2790.8

14.6

2652.8

85.0

15448.6

135.0

24536.1

3.081 Cent.&Shutt.Staircases 34th To 35th Floor

Sqm

85.33

503.65

42,976.15

483.73

41,276.56

8.0

682.6

24.0

2047.9

201.8

17217.7

15.4

1310.2

14.6

1245.5

85.0

7253.1

135.0

11519.6

3.082 Cent.&Shutt. Beam/Lintel first basement floor Level

Sqm

12,284.06

351.65

4,319,643.83

385.95

4,741,041.34

8.0

98272.4

4.0

49136.2

124.0

1523222.9

15.4

188621.8

14.6

179295.6

85.0

1044144.8

135.0

1658347.6

3.083 Cent.&Shutt. Beam/Lintel GF Floor/ first basement roof Level

Sqm

16,382.62

347.65

5,695,356.91

385.95

6,322,883.62

8.0

131060.9

4.0

65530.5

124.0

2031444.3

15.4

251555.2

14.6

239117.4

85.0

1392522.3

135.0

2211653.1

3.084 Cent.&Shutt. Beam/Lintel 1st Floor Level

Sqm

4,490.00

351.65

1,578,892.25

463.73

2,082,141.35

8.0

35920.0

4.0

17960.0

201.8

905982.2

15.4

68944.0

14.6

65535.1

85.0

381650.0

135.0

606150.0

3.085 Cent.&Shutt. Beam/Lintel 2nd Floor Level

Sqm

4,405.32

355.65

1,566,734.99

463.73

2,042,871.35

8.0

35242.5

4.0

17621.3

201.8

888895.0

15.4

67643.7

14.6

64299.1

85.0

374451.9

135.0

594717.8

3.086 Cent.&Shutt. Beam/Lintel 3rd Floor Level

Sqm

3,849.44

359.65

1,384,438.83

463.73

1,785,097.52

8.0

30795.6

4.0

15397.8

201.8

776732.4

15.4

59108.2

14.6

56185.7

85.0

327202.8

135.0

519675.0

Testing Charges

ITEM

DESCRIPTION

TENDER
DC RATE

TENDER
DC AMOUNT

PSE
RATE

Material

PSE AMOUNT

Labour

Sub Contractor

Plant Depric.

Plant Oprn & Fuel

Wooden Shuttering

Steel Shuttering

UOM

QTY

3.087 Cent.&Shutt. Beam/Lintel 4th Floor Level

Sqm

3,837.66

363.65

1,395,549.96

463.73

1,779,631.11

8.0

30701.3

4.0

15350.6

201.8

774353.8

15.4

58927.2

14.6

56013.7

85.0

326200.8

135.0

518083.7

3.088 Cent.&Shutt. Beam/Lintel 5thFloor Level

Sqm

4,263.01

367.65

1,567,279.20

463.73

1,976,878.34

8.0

34104.1

4.0

17052.0

201.8

860180.1

15.4

65458.5

14.6

62222.0

85.0

362355.6

135.0

575506.0

3.089 Cent.&Shutt. Beam/Lintel 6th Floor Level

Sqm

3,239.28

371.65

1,203,865.84

463.73

1,502,145.68

8.0

25914.2

4.0

12957.1

201.8

653614.3

15.4

49739.1

14.6

47279.9

85.0

275338.6

135.0

437302.5

3.090 Cent.&Shutt. Beam/Lintel 7th Floor Level

Sqm

3,222.40

375.65

1,210,481.67

463.73

1,494,317.48

8.0

25779.2

4.0

12889.6

201.8

650208.1

15.4

49479.9

14.6

47033.5

85.0

273903.7

135.0

435023.6

3.091 Cent.&Shutt. Beam/Lintel 8th Floor Level

Sqm

3,261.13

379.65

1,238,076.29

463.73

1,512,279.31

8.0

26089.0

4.0

13044.5

201.8

658023.6

15.4

50074.7

14.6

47598.8

85.0

277196.1

135.0

440252.6

3.092 Cent.&Shutt. Beam/Lintel 9th Floor Level

Sqm

3,212.46

383.65

1,232,450.27

463.73

1,489,711.49

8.0

25699.7

4.0

12849.9

201.8

648203.9

15.4

49327.4

14.6

46888.5

85.0

273059.5

135.0

433682.7

3.093 Cent.&Shutt. Beam/Lintel 10th Floor Level

Sqm

3,189.00

387.65

1,236,205.94

463.73

1,478,832.42

8.0

25512.0

4.0

12756.0

201.8

643470.2

15.4

48967.2

14.6

46546.1

85.0

271065.4

135.0

430515.6

3.094 Cent.&Shutt. Beam/Lintel 11th Floor Level

Sqm

3,189.00

391.65

1,248,961.96

463.73

1,478,832.42

8.0

25512.0

4.0

12756.0

201.8

643470.2

15.4

48967.2

14.6

46546.1

85.0

271065.4

135.0

430515.6

3.095 Cent.&Shutt. Beam/Lintel 12th Floor Level

Sqm

3,189.00

395.65

1,261,717.98

463.73

1,478,832.42

8.0

25512.0

4.0

12756.0

201.8

643470.2

15.4

48967.2

14.6

46546.1

85.0

271065.4

135.0

430515.6

3.096 Cent.&Shutt. Beam/Lintel 13th Floor Level

Sqm

3,189.00

399.65

1,274,474.00

463.73

1,478,832.42

8.0

25512.0

4.0

12756.0

201.8

643470.2

15.4

48967.2

14.6

46546.1

85.0

271065.4

135.0

430515.6

3.097 Cent.&Shutt. Beam/Lintel 14th Floor Level

Sqm

3,230.08

403.65

1,303,810.97

463.73

1,497,881.43

8.0

25840.7

4.0

12920.3

201.8

651758.8

15.4

49597.9

14.6

47145.6

85.0

274557.0

135.0

436061.1

3.098 Cent.&Shutt. Beam/Lintel 15th Floor Level

Sqm

2,823.79

407.65

1,151,107.60

463.73

1,309,471.95

8.0

22590.3

4.0

11295.2

201.8

569778.0

15.4

43359.3

14.6

41215.5

85.0

240022.1

135.0

381211.6

3.099 Cent.&Shutt. Beam/Lintel 16th Floor Level

Sqm

2,545.82

411.65

1,047,976.92

463.73

1,180,568.76

8.0

20366.5

4.0

10183.3

201.8

513689.6

15.4

39091.1

14.6

37158.3

85.0

216394.6

135.0

343685.5

3.100 Cent.&Shutt. Beam/Lintel 17th Floor Level

Sqm

2,333.08

415.65

969,735.44

463.73

1,081,914.98

8.0

18664.6

4.0

9332.3

201.8

470763.3

15.4

35824.4

14.6

34053.1

85.0

198311.6

135.0

314965.5

3.101 Cent.&Shutt. Beam/Lintel 18th Floor Level

Sqm

1,931.36

419.65

810,489.51

463.73

895,628.25

8.0

15450.9

4.0

7725.5

201.8

389706.1

15.4

29656.1

14.6

28189.8

85.0

164165.9

135.0

260734.0

3.102 Cent.&Shutt. Beam/Lintel 19th Floor Level

Sqm

1,952.91

423.65

827,342.52

463.73

905,619.39

8.0

15623.3

4.0

7811.6

201.8

394053.5

15.4

29986.9

14.6

28504.3

85.0

165997.2

135.0

263642.6

3.103 Cent.&Shutt. Beam/Lintel 20th Floor Level

Sqm

1,668.34

427.65

713,458.08

463.73

773,655.34

8.0

13346.7

4.0

6673.3

201.8

336633.2

15.4

25617.3

14.6

24350.7

85.0

141808.6

135.0

225225.4

3.104 Cent.&Shutt. Beam/Lintel 21st Floor Level

Sqm

1,668.34

431.65

720,131.42

463.73

773,655.34

8.0

13346.7

4.0

6673.3

201.8

336633.2

15.4

25617.3

14.6

24350.7

85.0

141808.6

135.0

225225.4

3.105 Cent.&Shutt. Beam/Lintel 22nd Floor Level

Sqm

1,668.34

435.65

726,804.77

463.73

773,655.34

8.0

13346.7

4.0

6673.3

201.8

336633.2

15.4

25617.3

14.6

24350.7

85.0

141808.6

135.0

225225.4

3.106 Cent.&Shutt. Beam/Lintel 23rd Floor Level

Sqm

1,668.34

439.65

733,478.11

463.73

773,655.34

8.0

13346.7

4.0

6673.3

201.8

336633.2

15.4

25617.3

14.6

24350.7

85.0

141808.6

135.0

225225.4

3.107 Cent.&Shutt. Beam/Lintel 24th Floor Level

Sqm

1,668.34

443.65

740,151.46

463.73

773,655.34

8.0

13346.7

4.0

6673.3

201.8

336633.2

15.4

25617.3

14.6

24350.7

85.0

141808.6

135.0

225225.4

3.108 Cent.&Shutt. Beam/Lintel 25th Floor Level

Sqm

1,668.34

447.65

746,824.81

463.73

773,655.34

8.0

13346.7

4.0

6673.3

201.8

336633.2

15.4

25617.3

14.6

24350.7

85.0

141808.6

135.0

225225.4

3.109 Cent.&Shutt. Beam/Lintel 26th Floor Level

Sqm

1,668.34

451.65

753,498.15

463.73

773,655.34

8.0

13346.7

4.0

6673.3

201.8

336633.2

15.4

25617.3

14.6

24350.7

85.0

141808.6

135.0

225225.4

3.110 Cent.&Shutt. Beam/Lintel 27th Floor Level

Sqm

1,668.34

455.65

760,171.50

463.73

773,655.34

8.0

13346.7

4.0

6673.3

201.8

336633.2

15.4

25617.3

14.6

24350.7

85.0

141808.6

135.0

225225.4

3.111 Cent.&Shutt. Beam/Lintel 28th Floor Level

Sqm

1,668.34

459.65

766,844.85

463.73

773,655.34

8.0

13346.7

4.0

6673.3

201.8

336633.2

15.4

25617.3

14.6

24350.7

85.0

141808.6

135.0

225225.4

3.112 Cent.&Shutt. Beam/Lintel 29th Floor Level

Sqm

1,668.34

463.65

773,518.19

463.73

773,655.34

8.0

13346.7

4.0

6673.3

201.8

336633.2

15.4

25617.3

14.6

24350.7

85.0

141808.6

135.0

225225.4

3.113 Cent.&Shutt. Beam/Lintel 30th Floor Level

Sqm

1,668.34

467.65

780,191.54

463.73

773,655.34

8.0

13346.7

4.0

6673.3

201.8

336633.2

15.4

25617.3

14.6

24350.7

85.0

141808.6

135.0

225225.4

3.114 Cent.&Shutt. Beam/Lintel 31st Floor Level

Sqm

1,897.33

471.65

894,867.79

463.73

879,845.14

8.0

15178.6

4.0

7589.3

201.8

382838.6

15.4

29133.5

14.6

27693.0

85.0

161272.9

135.0

256139.3

3.115 Cent.&Shutt. Beam/Lintel 32nd Floor Level

Sqm

2,399.15

475.65

1,141,144.91

463.73

1,112,552.39

8.0

19193.2

4.0

9596.6

201.8

484094.3

15.4

36838.9

14.6

35017.5

85.0

203927.4

135.0

323884.7

3.116 Cent.&Shutt. Beam/Lintel 33rd Floor Level

Sqm

2,675.73

479.65

1,283,404.69

463.73

1,240,812.95

8.0

21405.8

4.0

10702.9

201.8

539903.1

15.4

41085.9

14.6

39054.4

85.0

227437.1

135.0

361223.7

3.117 Cent.&Shutt. Beam/Lintel 34th Floor Level

Sqm

1,385.81

483.65

670,244.22

463.73

642,641.85

8.0

11086.5

4.0

5543.3

201.8

279626.6

15.4

21279.2

14.6

20227.1

85.0

117794.2

135.0

187085.0

3.118 Cent.&Shutt. slab (steel plates) first basement Floor Level

Sqm

15,935.27

341.65

5,444,228.80

385.95

6,150,232.01

8.0

127482.2

4.0

63741.1

124.0

1975974.0

15.4

244686.2

14.6

232588.1

85.0

1354498.3

135.0

2151262.0

3.119 Cent.&Shutt. slab (steel plates)GF Floor/ first basement roof Level

Sqm

17,316.90

337.65

5,846,987.98

385.95

6,683,470.84

8.0

138535.2

4.0

69267.6

124.0

2147295.4

15.4

265901.1

14.6

252754.0

85.0

1471936.3

135.0

2337781.2

3.120 Cent.&Shutt. slab (steel plates)at 1st Floor Level

Sqm

4,784.60

341.65

1,634,640.05

463.73

2,218,754.13

8.0

38276.8

4.0

19138.4

201.8

965425.2

15.4

73467.5

14.6

69835.0

85.0

406690.7

135.0

645920.5

3.121 Cent.&Shutt. slab (steel plates)at 2nd Floor Level

Sqm

4,821.62

345.65

1,666,575.94

463.73

2,235,923.62

8.0

38573.0

4.0

19286.5

201.8

972896.0

15.4

74036.0

14.6

70375.4

85.0

409837.8

135.0

650918.9

3.122 Cent.&Shutt. slab (steel plates)at 3rd Floor Level

Sqm

4,187.55

349.65

1,464,162.78

463.73

1,941,888.07

8.0

33500.4

4.0

16750.2

201.8

844955.2

15.4

64299.9

14.6

61120.7

85.0

355942.0

135.0

565319.7

3.123 Cent.&Shutt. slab (steel plates)at 4th Floor Level

Sqm

4,188.27

353.65

1,481,167.27

463.73

1,942,221.50

8.0

33506.2

4.0

16753.1

201.8

845100.2

15.4

64310.9

14.6

61131.2

85.0

356003.1

135.0

565416.7

3.124 Cent.&Shutt. slab (steel plates)at 5th Floor Level

Sqm

4,115.30

357.65

1,471,823.90

463.73

1,908,384.52

8.0

32922.4

4.0

16461.2

201.8

830377.1

15.4

63190.5

14.6

60066.2

85.0

349800.9

135.0

555566.2

3.125 Cent.&Shutt. slab (steel plates)at 6th Floor Level

Sqm

3,609.01

361.65

1,305,186.46

463.73

1,673,602.46

8.0

28872.1

4.0

14436.1

201.8

728218.6

15.4

55416.4

14.6

52676.4

85.0

306766.1

135.0

487216.7

3.126 Cent.&Shutt. slab (steel plates)at 7th Floor Level

Sqm

3,647.15

365.65

1,333,567.16

463.73

1,691,287.67

8.0

29177.2

4.0

14588.6

201.8

735913.8

15.4

56002.0

14.6

53233.1

85.0

310007.7

135.0

492365.2

3.127 Cent.&Shutt. slab (steel plates)at 8th Floor Level

Sqm

3,617.91

369.65

1,337,349.15

463.73

1,677,730.57

8.0

28943.3

4.0

14471.7

201.8

730014.8

15.4

55553.1

14.6

52806.4

85.0

307522.8

135.0

488418.5

3.128 Cent.&Shutt. slab (steel plates)at 9th Floor Level

Sqm

3,608.10

373.65

1,348,155.34

463.73

1,673,181.39

8.0

28864.8

4.0

14432.4

201.8

728035.4

15.4

55402.5

14.6

52663.2

85.0

306688.9

135.0

487094.2

3.129 Cent.&Shutt. slab (steel plates)at 10th Floor Level

Sqm

3,585.99

377.65

1,354,238.00

463.73

1,662,928.35

8.0

28688.0

4.0

14344.0

201.8

723574.1

15.4

55063.0

14.6

52340.5

85.0

304809.6

135.0

484109.3

3.130 Cent.&Shutt. slab (steel plates)at 11th Floor Level

Sqm

3,585.99

381.65

1,368,581.98

463.73

1,662,928.35

8.0

28688.0

4.0

14344.0

201.8

723574.1

15.4

55063.0

14.6

52340.5

85.0

304809.6

135.0

484109.3

Testing Charges

ITEM

DESCRIPTION

TENDER
DC RATE

TENDER
DC AMOUNT

PSE
RATE

Material

Sub Contractor

Plant Depric.

Plant Oprn & Fuel

Wooden Shuttering

Steel Shuttering

QTY

Sqm

3,585.99

385.65

1,382,925.96

463.73

1,662,928.35

8.0

28688.0

4.0

14344.0

201.8

723574.1

15.4

55063.0

14.6

52340.5

85.0

304809.6

135.0

484109.3

3.132 Cent.&Shutt. slab (steel plates)at 13th Floor Level

Sqm

3,585.99

389.65

1,397,269.94

463.73

1,662,928.35

8.0

28688.0

4.0

14344.0

201.8

723574.1

15.4

55063.0

14.6

52340.5

85.0

304809.6

135.0

484109.3

3.133 Cent.&Shutt. slab (steel plates)at 14th Floor Level

Sqm

3,124.12

393.65

1,229,797.49

463.73

1,448,742.53

8.0

24992.9

4.0

12496.5

201.8

630377.5

15.4

47970.8

14.6

45599.0

85.0

265550.0

135.0

421755.8

3.134 Cent.&Shutt. slab (steel plates)at 15th Floor Level

Sqm

3,122.81

397.65

1,241,772.26

463.73

1,448,134.12

8.0

24982.4

4.0

12491.2

201.8

630112.7

15.4

47950.7

14.6

45579.8

85.0

265438.5

135.0

421578.7

3.135 Cent.&Shutt. slab (steel plates)at 16th Floor Level

Sqm

3,060.45

401.65

1,229,220.59

463.73

1,419,220.37

8.0

24483.6

4.0

12241.8

201.8

617531.8

15.4

46993.3

14.6

44669.8

85.0

260138.7

135.0

413161.4

3.136 Cent.&Shutt. slab (steel plates)at 17th Floor Level

Sqm

2,239.51

405.65

908,450.43

463.73

1,038,526.29

8.0

17916.1

4.0

8958.1

201.8

451884.0

15.4

34387.7

14.6

32687.5

85.0

190358.6

135.0

302334.3

3.137 Cent.&Shutt. slab (steel plates)at 18th Floor Level

Sqm

2,140.49

409.65

876,845.07

463.73

992,607.63

8.0

17123.9

4.0

8562.0

201.8

431903.9

15.4

32867.3

14.6

31242.2

85.0

181941.9

135.0

288966.5

3.138 Cent.&Shutt. slab (steel plates)at 19th Floor Level

Sqm

1,999.46

413.65

827,069.87

463.73

927,207.29

8.0

15995.7

4.0

7997.8

201.8

403446.8

15.4

30701.7

14.6

29183.7

85.0

169954.2

135.0

269927.3

3.139 Cent.&Shutt. slab (steel plates)at 20th Floor Level

Sqm

1,999.46

417.65

835,067.71

463.73

927,207.29

8.0

15995.7

4.0

7997.8

201.8

403446.8

15.4

30701.7

14.6

29183.7

85.0

169954.2

135.0

269927.3

3.140 Cent.&Shutt. slab (steel plates)at 21st Floor Level

Sqm

1,999.46

421.65

843,065.56

463.73

927,207.29

8.0

15995.7

4.0

7997.8

201.8

403446.8

15.4

30701.7

14.6

29183.7

85.0

169954.2

135.0

269927.3

3.141 Cent.&Shutt. slab (steel plates)at 22nd Floor Level

Sqm

1,999.46

425.65

851,063.40

463.73

927,207.29

8.0

15995.7

4.0

7997.8

201.8

403446.8

15.4

30701.7

14.6

29183.7

85.0

169954.2

135.0

269927.3

3.142 Cent.&Shutt. slab (steel plates)at 23rd Floor Level

Sqm

1,999.46

429.65

859,061.25

463.73

927,207.29

8.0

15995.7

4.0

7997.8

201.8

403446.8

15.4

30701.7

14.6

29183.7

85.0

169954.2

135.0

269927.3

3.143 Cent.&Shutt. slab (steel plates)at 24th Floor Level

Sqm

1,999.46

433.65

867,059.09

463.73

927,207.29

8.0

15995.7

4.0

7997.8

201.8

403446.8

15.4

30701.7

14.6

29183.7

85.0

169954.2

135.0

269927.3

3.144 Cent.&Shutt. slab (steel plates)at 25th Floor Level

Sqm

1,999.46

437.65

875,056.93

463.73

927,207.29

8.0

15995.7

4.0

7997.8

201.8

403446.8

15.4

30701.7

14.6

29183.7

85.0

169954.2

135.0

269927.3

3.145 Cent.&Shutt. slab (steel plates)at 26th Floor Level

Sqm

1,999.46

441.65

883,054.78

463.73

927,207.29

8.0

15995.7

4.0

7997.8

201.8

403446.8

15.4

30701.7

14.6

29183.7

85.0

169954.2

135.0

269927.3

3.146 Cent.&Shutt. slab (steel plates)at 27th Floor Level

Sqm

1,999.46

445.65

891,052.62

463.73

927,207.29

8.0

15995.7

4.0

7997.8

201.8

403446.8

15.4

30701.7

14.6

29183.7

85.0

169954.2

135.0

269927.3

3.147 Cent.&Shutt. slab (steel plates)at 28th Floor Level

Sqm

1,999.46

449.65

899,050.47

463.73

927,207.29

8.0

15995.7

4.0

7997.8

201.8

403446.8

15.4

30701.7

14.6

29183.7

85.0

169954.2

135.0

269927.3

3.148 Cent.&Shutt. slab (steel plates)at 29th Floor Level

Sqm

1,999.46

453.65

907,048.31

463.73

927,207.29

8.0

15995.7

4.0

7997.8

201.8

403446.8

15.4

30701.7

14.6

29183.7

85.0

169954.2

135.0

269927.3

3.149 Cent.&Shutt. slab (steel plates)at 30th Floor Level

Sqm

1,999.46

457.65

915,046.16

463.73

927,207.29

8.0

15995.7

4.0

7997.8

201.8

403446.8

15.4

30701.7

14.6

29183.7

85.0

169954.2

135.0

269927.3

3.150 Cent.&Shutt. slab (steel plates)at 31st Floor Level

Sqm

1,850.59

461.65

854,319.61

463.73

858,172.93

8.0

14804.7

4.0

7402.4

201.8

373408.6

15.4

28415.9

14.6

27010.9

85.0

157300.4

135.0

249830.1

3.151 Cent.&Shutt. slab (steel plates)at 32nd Floor Level

Sqm

1,252.95

465.65

583,433.56

463.73

581,030.65

8.0

10023.6

4.0

5011.8

201.8

252818.3

15.4

19239.1

14.6

18287.9

85.0

106501.1

135.0

169148.8

3.152 Cent.&Shutt. slab (steel plates)at 33rd Floor Level

Sqm

1,066.86

469.65

501,045.46

463.73

494,732.02

8.0

8534.9

4.0

4267.4

201.8

215268.0

15.4

16381.6

14.6

15571.6

85.0

90682.8

135.0

144025.7

3.153 Cent.&Shutt. slab (steel plates)at 34th Floor Level

Sqm

712.04

473.65

337,257.11

463.73

330,195.20

8.0

5696.4

4.0

2848.2

201.8

143674.7

15.4

10933.4

14.6

10392.9

85.0

60523.7

135.0

96126.0

3.154 Cent.&Shutt. For Lintel

Sqm

413.87

1,835,286.93

473.73

2,100,734.09

8.0

35475.7

14.0

62082.5

201.8

894777.0

15.4

68091.3

14.6

64724.6

85.0

376929.8

135.0

598653.1

3.155 Cent.&Shutt. for Bottom & Top Rails In Balcony at all Fl.

Sqm

458.87

1,839,604.23

523.73

2,099,627.90

8.0

32072.0

64.0

256576.0

201.8

808927.1

15.4

61558.2

14.6

58514.6

85.0

340765.0

135.0

541215.0

50.0

1694300.0

50.0

3573350.0

4,434.47
4,009.00
446,832.42

building elements except staircase, lintels, counters, piers, ledges, water


tanks,

lift pit, shafts etc. and whereever specifically instructed by the Engineer,

including the cost of extra labour, supervision, consummables (foam etc.) to


achieve & maintain a very high degree of accuracy for line, level etc. so as
to
achieve fair face concrete surface.
Slab

Sqm

33,886.00

50.00

1,694,300.00

50.00

3.157 Extra for additional height( floor to floor) for shuttering


beyond 3.0m for every additional one meter. (shuttering
area of horizontals and verticals above 3.0m to be measured)

Sqm

71,467.00

50.00

3,573,350.00

50.00

3.158 Extra over slab shuttering for shuttering in sunken area of plan
dimension upto 600mm*2400mm.

Sqm

4,473.00

105.00

469,665.00

105.00

177,344,442.64

Providing and laying Plain Cement Concrete 1:4:8 (1 cement: 4 coarse


sand: 8 graded
stone aggregate 20mm nominal size) in footings and bases for columns,
pile caps,
plinth beam excluding the cost of centring and shuttering & all leads and
lifts.

1,694,300.00
3,573,350.00
469,665.00

105.0

205,609,651.78
-

4.000 PCC & LEAN CONCRETE


4.001

Testing Charges

3.156 Extra for providing and fixing film face shuttering ply 12mm thick for all

PSE AMOUNT

Labour

UOM

3.131 Cent.&Shutt. slab (steel plates)at 12th Floor Level

3,574,659.40

2,278,630.30

469665.0
88,070,236

6,861,115

6,521,877

37,980,756

60,322,377

Cum

2,990.00

3,952.62

11,818,347.43

4046.63

12,099,433.88

2874.9

8596080.8

35.0

104650.0

281.8

842697.7

399.5

1194392.8

445.4

1331712.5

10.0

29900.0

Cum

2,732.00

3,952.62

10,798,570.30

4046.63

11,055,402.46

2874.9

7854345.4

35.0

95620.0

281.8

769983.4

399.5

1091331.5

445.4

1216802.2

10.0

27320.0

4865.63

29,193.80
-

3693.9

22163.7

35.0

210.0

281.8

1691.0

399.5

2396.8

445.4

2672.3

10.0

60.0

3693.9

62797.0

35.0

595.0

281.8

4791.3

399.5

6790.9

445.4

7571.6

10.0

170.0

4.002 Item same as S.No. 4.001 but under floors at all floors of Toilet & Balcony
4.003 Item same as S.No. 4.001 but under floors at entrance lobby non tower area

Cum

6.00

4,719.62

28,317.75

4.004 Providing & applying CC 1:2:4 Screed at the bottom of the drain including

providing necessary longitudinal slope in cement mortar finished with a


floating coat of neat cement as specified by the Engineer.
4.005 Screed on podium slab-Non Tower area-1:2:4

Cum
Cum

17.00

4,794.62

81,508.62
-

4,749.62

4865.63

82,715.77
-

ITEM

DESCRIPTION

0.001 Screed on water tank slab

UOM

TENDER
DC RATE

QTY

Cum

4,759.62
5,745.00

5.00

RCC IN ALL GRADES


Providing and Laying Reinforced Cement Concrete at
all levels using graded stone aggregate 20mm
nominal size and coarse sand as per the approved
mix design including curing and all leads & lifts at all
levels but excluding the cost of centring, shuttering
and reinforcement.

5.00

Providing and Laying Reinforced Cement Concrete at all levels using


graded stone aggregate 20mm nominal size and coarse sand as per
the approved mix design including curing and all leads & lifts at all
levels but excluding the cost of centring, shuttering and
reinforcement. (With batching Plant and Concrete Pumps but
excluding Transit Mixture.)

TENDER
DC AMOUNT

PSE
RATE
-

Material

PSE AMOUNT

Labour

Sub Contractor

Plant Depric.

Plant Oprn & Fuel

Wooden Shuttering

Steel Shuttering

Testing Charges

22,726,744.10

23,266,745.90
-

16,535,386.91

201,075.00

1,619,163.38

2,294,912.01

2,558,758.61

57,450.00

5.002 P&L RCC M-25 In Foundation, Raft (tower)

Cum

8,979.00

4,572.26

41,054,330.19

4666.47

41,900,264.69

3494.8

31379660.3

35.0

314265.0

281.8

2530629.8

399.5

3586773.7

445.4

3999146.0

10.0

5.003 P&L RCC M-25 - 150mm thk slab In Foundation, Raft (tower)

Cum

34.00

4,572.26

155,456.87

4666.47

158,660.10

3494.8

118822.6

35.0

1190.0

281.8

9582.5

399.5

13581.7

445.4

15143.2

10.0

89790.0
340.0

5.004 P&L RCC M-25 - UG Sump Base Slab

Cum

488.00

4,572.26

2,231,263.30

4666.47

2,277,239.02

3494.8

1705454.3

35.0

17080.0

281.8

137537.3

399.5

194937.7

445.4

217349.7

10.0

4880.0

5.005 P&L RCC M-25 In 230mm thk retainer wall at Foundation (tower)

Cum

42.00

4,572.26

192,034.96

4666.47

195,991.88

3494.8

146780.9

35.0

1470.0

281.8

11837.2

399.5

16777.4

445.4

18706.3

10.0

420.0

5.006 P&L RCC M-25 In Foundation, footing (non tower)

Cum

2,223.00

4,572.26

10,164,135.87

4666.47

10,373,570.38

3494.8

7768903.5

35.0

77805.0

281.8

626527.4

399.5

888005.1

445.4

990099.3

10.0

22230.0

5.007 P&L RCC M-25 - 150mm thkTie slab In Foundation, Raft

Cum

2,245.00

4,572.26

10,264,725.61

4666.47

10,476,232.79

3494.8

7845788.8

35.0

78575.0

281.8

632727.9

399.5

896793.3

445.4

999897.8

10.0

22450.0

5.008 P&L RCC M-25 - Retaining wall Raft In Foundation, Raft

Cum

616.00

4,572.26

2,816,512.68

4666.47

2,874,547.62

3494.8

2152786.6

35.0

21560.0

281.8

173612.6

399.5

246068.9

445.4

274359.5

10.0

6160.0

5.009 P&L RCC M-40 - in foundation ,fooring (Non Tower)

Cum

26.00

4,572.26

118,878.78

5177.59

134,617.43

4005.9

104153.5

35.0

910.0

281.8

7327.8

399.5

10386.0

445.4

11580.1

10.0

260.0

5.010 P&L RCC M-25 In Column for foundn to 1st basement floor

Cum

380.00

4,693.35

1,783,473.70

4666.47

1,773,259.89

3494.8

1328017.7

35.0

13300.0

281.8

107098.7

399.5

151795.7

445.4

169247.7

10.0

3800.0

5.011 P&L RCC M-35 In Column for foundn to 1st basement floor

Cum

318.00

5,093.35

1,619,685.88

4944.96

1,572,498.36

3773.3

1199900.9

35.0

11130.0

281.8

89624.7

399.5

127029.1

445.4

141633.6

10.0

3180.0

5.012 P&L RCC M-40 In Column for foundn to 1st basement floor

Cum

439.00

5,489.35

2,409,825.46

5177.59

2,272,963.50

4005.9

1758591.6

35.0

15365.0

281.8

123727.2

399.5

175364.0

445.4

195525.7

10.0

4390.0

5.01

P&L RCC M-40 In Column for first basement /GF floor

Cum

55.90

5,829.35

325,860.77

5177.59

289,427.47

4005.9

223930.0

35.0

1956.5

281.8

15754.8

399.5

22330.0

445.4

24897.2

10.0

559.0

5.01

P&L RCC M-40 In Column for first basement /GF floor TOWER

Cum

565.00

5,489.35

3,101,483.79

5177.59

2,925,340.27

4005.9

2263335.4

35.0

19775.0

281.8

159238.9

399.5

225696.3

445.4

251644.7

10.0

5650.0

5.02

P&L RCC M-35 In Column for first basement /GF floor TOWER

Cum

403.26

5,093.35

2,053,945.06

4944.96

1,994,105.94

3773.3

1521610.2

35.0

14114.1

281.8

113654.3

399.5

161087.2

445.4

179607.5

10.0

4032.6

5.02

P&L RCC M-25 In Column for first basement /GF floor

Cum

462.00

4,693.35

2,168,328.55

4666.47

2,155,910.71

3494.8

1614589.9

35.0

16170.0

281.8

130209.5

399.5

184551.7

445.4

205769.6

10.0

4620.0

5.02

P&L RCC M-40 In Column From GF To 1st Floor

Cum

442.38

5,489.35

2,428,379.47

5177.59

2,290,463.77

4005.9

1772131.6

35.0

15483.3

281.8

124679.8

399.5

176714.2

445.4

197031.1

10.0

4423.8

5.02

P&L RCC M- 35 In Column From GF To 1st Floor

Cum

269.97

5,093.35

1,375,052.20

4944.96

1,334,991.77

3773.3

1018670.6

35.0

9449.0

281.8

76088.0

399.5

107842.9

445.4

120241.6

10.0

2699.7

5.019 P&L RCC M- 30 In Column From GF To 1st Floor

Cum

48.39

4,923.35

238,241.00

5003.67

242,127.76

3832.0

185429.7

35.0

1693.7

281.8

13638.2

399.5

19330.0

445.4

21552.4

10.0

483.9

5.020 P&L RCC M-40 In Column From 1st To 2nd Floor

Cum

374.70

5,489.35

2,056,860.13

5177.59

1,940,044.25

4005.9

1501012.0

35.0

13114.5

281.8

105605.0

399.5

149678.6

445.4

166887.2

10.0

3747.0

5.021 P&L RCC M- 35 In Column From 1st Floor TO 2nd floor

Cum

227.13

5,093.35

1,156,853.00

4944.96

1,123,149.54

3773.3

857023.6

35.0

7949.6

281.8

64014.0

399.5

90729.9

445.4

101161.2

10.0

2271.3

5.022 P&L RCC M-25 In Column From 2nd To 3rd Floor

Cum

30.61

4,693.35

143,663.50

4666.47

142,840.75

3494.8

106975.3

35.0

1071.4

281.8

8627.1

399.5

12227.5

445.4

13633.4

10.0

306.1

5.023 P&L RCC M-35 In Column From 2nd To 3rd Floor

Cum

225.78

4,979.83

1,124,347.00

4944.96

1,116,473.84

3773.3

851929.7

35.0

7902.3

281.8

63633.5

399.5

90190.6

445.4

100559.9

10.0

2257.8

5.024 P&L RCC M-40 In Column From 2nd To 3rd Floor

Cum

330.22

5,375.83

1,775,208.02

5177.59

1,709,744.89

4005.9

1322829.4

35.0

11557.7

281.8

93068.8

399.5

131910.5

445.4

147076.3

10.0

3302.2

5.025 P&L RCC M-25 In Column From 2nd To 3rd Floor

Cum

30.61

4,579.83

140,188.73

4666.47

142,840.75

3494.8

106975.3

35.0

1071.4

281.8

8627.1

399.5

12227.5

445.4

13633.4

10.0

306.1

5.0260 P&L RCC M-35 In Column From 3rd To 4th Floor

Cum

225.78

4,985.09

1,125,532.67

4944.96

1,116,473.84

3773.3

851929.7

35.0

7902.3

281.8

63633.5

399.5

90190.6

445.4

100559.9

10.0

2257.8

5.0270 P&L RCC M-40 In Column From 3rd To 4th Floor

Cum

330.22

5,381.09

1,776,942.16

5177.59

1,709,744.89

4005.9

1322829.4

35.0

11557.7

281.8

93068.8

399.5

131910.5

445.4

147076.3

10.0

3302.2

5.0280 P&L RCC M-25 In Column From 3rd To 4th Floor

Cum

30.61

4,585.09

140,349.48

4666.47

142,840.75

3494.8

106975.3

35.0

1071.4

281.8

8627.1

399.5

12227.5

445.4

13633.4

10.0

306.1

3832.0

865185.2

35.0

7902.3

281.8

63633.5

399.5

90190.6

445.4

100559.9

10.0

2257.8

5.029 P&L RCC M-30 In Column From 4th To 5th Floor

Cum

225.78

4,820.49

5.030 P&L RCC M-35 In Column From 4th To 5th Floor

Cum

4,990.49

1,088,371.32

5003.67

5.031 P&L RCC M-40 In Column From 4th To 5th Floor

Cum

330.22

5,386.49

1,778,728.31

5177.59

1,709,744.89

4005.9

1322829.4

35.0

11557.7

281.8

93068.8

399.5

131910.5

445.4

147076.3

10.0

3302.2

5.032 P&L RCC M-25 In Column From 4th To 5th Floor

Cum

32.61

4,590.49

149,696.04

4666.47

152,173.70

3494.8

113964.9

35.0

1141.4

281.8

9190.8

399.5

13026.5

445.4

14524.1

10.0

326.1

4944.96

1,129,729.38
-

3773.3

35.0

281.8

399.5

445.4

10.0

5.033 P&L RCC M-30 In Column From 5th To 6th Floor

Cum

225.78

4,826.07

1,089,629.20

5003.67

1,129,729.38

3832.0

865185.2

35.0

7902.3

281.8

63633.5

399.5

90190.6

445.4

100559.9

10.0

2257.8

5.034 P&L RCC M-40 In Column From 5th To 6th Floor

Cum

248.21

5,392.07

1,338,364.72

5177.59

1,285,130.46

4005.9

994305.3

35.0

8687.4

281.8

69955.2

399.5

99150.6

445.4

110550.0

10.0

2482.1

5.035 P&L RCC M-35 In Column 5th to 6th floor

Cum

82.01

4,996.07

409,727.38

4944.96

405,536.45

3773.3

309446.2

35.0

2870.4

281.8

23113.6

399.5

32759.9

445.4

36526.3

10.0

820.1

5.036 P&L RCC M-30 In Column From 6th To 7th Floor

Cum

225.78

4,831.80

1,090,924.82

5003.67

1,129,729.38

3832.0

865185.2

35.0

7902.3

281.8

63633.5

399.5

90190.6

445.4

100559.9

10.0

2257.8

5.037 P&L RCC M-35 In Column From 6th To 7th Floor

Cum

330.22

5,001.80

1,651,695.88

4944.96

1,632,925.82

3773.3

1246010.3

35.0

11557.7

281.8

93068.8

399.5

131910.5

445.4

147076.3

10.0

3302.2

5.038 P&L RCC M-30 In Column From 7th To 8th Floor

Cum

225.78

4,837.72

1,092,259.30

5003.67

1,129,729.38

3832.0

865185.2

35.0

7902.3

281.8

63633.5

399.5

90190.6

445.4

100559.9

10.0

2257.8

5.039 P&L RCC M-35 In Column From 7th To 8th Floor

Cum

330.22

5,007.72

1,653,647.66

4944.96

1,632,925.82

3773.3

1246010.3

35.0

11557.7

281.8

93068.8

399.5

131910.5

445.4

147076.3

10.0

3302.2

ITEM

DESCRIPTION

UOM

QTY

TENDER
DC RATE

TENDER
DC AMOUNT

PSE
RATE

Material

PSE AMOUNT

Labour

Sub Contractor

Plant Depric.

Plant Oprn & Fuel

Wooden Shuttering

Steel Shuttering

Testing Charges

5.040 P&L RCC M-35 In Column From 8th To 9th Floor

Cum

330.22

5,013.80

1,655,658.00

4944.96

1,632,925.82

3773.3

1246010.3

35.0

11557.7

281.8

93068.8

399.5

131910.5

445.4

147076.3

10.0

3302.2

5.041 P&L RCC M- 30 In Column From 8th floor TO 9th floor

Cum

225.78

4,843.80

1,093,633.82

5003.67

1,129,729.38

3832.0

865185.2

35.0

7902.3

281.8

63633.5

399.5

90190.6

445.4

100559.9

10.0

2257.8

5.042 P&L RCC M-35 In Column From 9th To 10th Floor

Cum

330.22

5,020.07

1,657,728.65

4944.96

1,632,925.82

3773.3

1246010.3

35.0

11557.7

281.8

93068.8

399.5

131910.5

445.4

147076.3

10.0

3302.2

5.043 P&L RCC M-30 In Column From 9th To 10th Floor

Cum

225.78

4,850.07

1,095,049.58

5003.67

1,129,729.38

3832.0

865185.2

35.0

7902.3

281.8

63633.5

399.5

90190.6

445.4

100559.9

10.0

2257.8

5.044 P&L RCC M-25 In Column From 10th To 11th Floor

Cum

225.78

4,626.53

1,044,578.41

4666.47

1,053,596.37

3494.8

789052.2

35.0

7902.3

281.8

63633.5

399.5

90190.6

445.4

100559.9

10.0

2257.8

5.045 P&L RCC M-35 In Column 10th to 11th floor

Cum

330.22

5,026.53

1,659,861.41

4944.96

1,632,925.82

3773.3

1246010.3

35.0

11557.7

281.8

93068.8

399.5

131910.5

445.4

147076.3

10.0

3302.2

5.046 P&L RCC M-35 In Column From 11th To 12th Floor

Cum

330.22

5,033.18

1,662,058.17

4944.96

1,632,925.82

3773.3

1246010.3

35.0

11557.7

281.8

93068.8

399.5

131910.5

445.4

147076.3

10.0

3302.2

5.047 P&L RCC M-25 In Column From 11th To 12th Floor

Cum

212.48

4,633.18

984,459.03

4666.47

991,532.27

3494.8

742571.6

35.0

7436.8

281.8

59885.1

399.5

84877.8

445.4

94636.2

10.0

2124.8

5.048 P&L RCC M-35 In Column From 12th To 13th Floor

Cum

330.22

5,040.04

1,664,320.82

4944.96

1,632,925.82

3773.3

1246010.3

35.0

11557.7

281.8

93068.8

399.5

131910.5

445.4

147076.3

10.0

3302.2

5.049 P&L RCC M-25 In Column From 12th To 13th Floor

Cum

212.48

4,640.04

985,914.93

4666.47

991,532.27

3494.8

742571.6

35.0

7436.8

281.8

59885.1

399.5

84877.8

445.4

94636.2

10.0

2124.8

5.050 P&L RCC M-35 In Column From 13th To 14th Floor

Cum

248.21

5,047.09

1,252,739.18

4944.96

1,227,389.37

3773.3

936564.2

35.0

8687.4

281.8

69955.2

399.5

99150.6

445.4

110550.0

10.0

2482.1

5.051 P&L RCC M-25 In Column From 13th To 14th Floor

Cum

187.87

4,647.09

873,049.53

4666.47

876,690.36

3494.8

656565.0

35.0

6575.5

281.8

52949.0

399.5

75047.0

445.4

83675.2

10.0

1878.7

5.052 P&L RCC M-30 In Column From 13th To 14th Floor

Cum

82.01

4,877.09

399,970.47

5003.67

410,351.26

3832.0

314261.0

35.0

2870.4

281.8

23113.6

399.5

32759.9

445.4

36526.3

10.0

820.1

5.053 P&L RCC M-25 In Column From 14th To 15th Floor

Cum

158.08

4,654.36

735,761.73

4666.47

737,676.12

3494.8

552455.4

35.0

5532.8

281.8

44553.1

399.5

63147.0

445.4

70407.1

10.0

1580.8

5.054 P&L RCC M-30 In Column 14th to 15th floor

Cum

330.22

4,884.36

1,612,914.40

5003.67

1,652,313.03

3832.0

1265397.6

35.0

11557.7

281.8

93068.8

399.5

131910.5

445.4

147076.3

10.0

3302.2

5.055 P&L RCC M-30 In Column From 15th To 16th Floor

Cum

330.22

4,891.85

1,615,386.86

5003.67

1,652,313.03

3832.0

1265397.6

35.0

11557.7

281.8

93068.8

399.5

131910.5

445.4

147076.3

10.0

3302.2

5.056 P&L RCC M-25 In Column From 15th To 16th Floor

Cum

149.32

4,661.85

696,107.51

4666.47

696,797.81

3494.8

521841.1

35.0

5226.2

281.8

42084.2

399.5

59647.7

445.4

66505.5

10.0

1493.2

5.057 P&L RCC M-30 In Column From 16th To 17th Floor

Cum

330.22

4,899.56

1,617,933.50

5003.67

1,652,313.03

3832.0

1265397.6

35.0

11557.7

281.8

93068.8

399.5

131910.5

445.4

147076.3

10.0

3302.2

5.058 P&L RCC M-25 In Column From 16th To 17th Floor

Cum

145.46

4,669.56

679,234.55

4666.47

678,785.22

3494.8

508351.2

35.0

5091.1

281.8

40996.3

399.5

58105.8

445.4

64786.3

10.0

1454.6

5.059 P&L RCC M-30 In Column From 17th To 18th Floor

Cum

330.00

4,907.51

1,619,476.88

5003.67

1,651,212.22

3832.0

1264554.5

35.0

11550.0

281.8

93006.8

399.5

131822.6

445.4

146978.3

10.0

3300.0

5.060 P&L RCC M-25 In Column From 17th To 18th Floor

Cum

64.00

4,677.51

299,360.37

4666.47

298,654.30

3494.8

223666.1

35.0

2240.0

281.8

18037.7

399.5

25565.6

445.4

28504.9

10.0

640.0

3832.0

1265397.6

35.0

11557.7

281.8

93068.8

399.5

131910.5

445.4

147076.3

10.0

3302.2

3832.0

1265397.6

35.0

11557.7

281.8

93068.8

399.5

131910.5

445.4

147076.3

10.0

3302.2

3832.0

1265397.6

35.0

11557.7

281.8

93068.8

399.5

131910.5

445.4

147076.3

10.0

3302.2

3832.0

951147.3

35.0

8687.4

281.8

69956.0

399.5

99151.7

445.4

110551.2

10.0

2482.1

5.060 P&L RCC M-30 In Column From 18th To 19th Floor

Cum

330.22

4,915.69

1,623,258.26

5003.67

1,652,313.03
-

5.061 P&L RCC M-30 In Column From 19th To 20th Floor

Cum

330.22

4,924.11

1,626,041.04

5003.67

1,652,313.03
-

5.062 P&L RCC M-30 In Column From 20th To 21st Floor

Cum

330.22

4,932.79

1,628,907.30

5003.67

1,652,313.03
-

5.063 P&L RCC M-30 In Column From 21st To 22nd Floor

Cum

248.21

4,941.73

1,226,601.75

5003.67

1,241,975.79
-

5.064 P&L RCC M-25 In Column From 21st To 22nd Floor

Cum

82.01

4,711.73

386,416.50

4666.47

382,704.58

3494.8

286612.5

35.0

2870.4

281.8

23114.0

399.5

32760.5

445.4

36527.0

10.0

820.1

5.065 P&L RCC M-25 In Column From 22nd To 23rd Floor

Cum

330.22

4,720.94

1,558,970.16

4666.47

1,540,983.01

3494.8

1154062.5

35.0

11557.9

281.8

93070.0

399.5

131912.2

445.4

147078.2

10.0

3302.2

5.066 P&L RCC M-25 In Column From 23rd To 24th Floor

Cum

330.22

4,730.43

1,562,102.25

4666.47

1,540,983.01

3494.8

1154062.5

35.0

11557.9

281.8

93070.0

399.5

131912.2

445.4

147078.2

10.0

3302.2

5.067 P&L RCC M-25 In Column From 24th To 25th Floor

Cum

330.22

4,740.20

1,565,328.29

4666.47

1,540,983.01

3494.8

1154062.5

35.0

11557.9

281.8

93070.0

399.5

131912.2

445.4

147078.2

10.0

3302.2

5.068 P&L RCC M-25 In Column From 25th To 26th Floor

Cum

330.22

4,750.26

1,568,651.12

4666.47

1,540,983.01

3494.8

1154062.5

35.0

11557.9

281.8

93070.0

399.5

131912.2

445.4

147078.2

10.0

3302.2

5.069 P&L RCC M-25 In Column From 26th To 27th Floor

Cum

330.22

4,760.62

1,572,073.63

4666.47

1,540,983.01

3494.8

1154062.5

35.0

11557.9

281.8

93070.0

399.5

131912.2

445.4

147078.2

10.0

3302.2

5.070 P&L RCC M-25 In Column From 27th To 28th Floor

Cum

330.22

4,771.30

1,575,598.82

4666.47

1,540,983.01

3494.8

1154062.5

35.0

11557.9

281.8

93070.0

399.5

131912.2

445.4

147078.2

10.0

3302.2

5.071 P&L RCC M-25 In Column From 28th To 29th Floor

Cum

330.22

4,782.29

1,579,229.76

4666.47

1,540,983.01

3494.8

1154062.5

35.0

11557.9

281.8

93070.0

399.5

131912.2

445.4

147078.2

10.0

3302.2

5.072 P&L RCC M-25 In Column From 29th To 30th Floor

Cum

330.22

4,793.62

1,582,969.63

4666.47

1,540,983.01

3494.8

1154062.5

35.0

11557.9

281.8

93070.0

399.5

131912.2

445.4

147078.2

10.0

3302.2

5.073 P&L RCC M-25 In Column From 30th To 31st Floor

Cum

335.35

4,805.28

1,611,452.24

4666.47

1,564,902.04

3494.8

1171975.8

35.0

11737.3

281.8

94514.6

399.5

133959.8

445.4

149361.1

10.0

3353.5

5.074 P&L RCC M-25 In Column From 31st To 32nd floor

Cum

279.12

4,817.30

1,344,588.34

4666.47

1,302,490.37

3494.8

975452.2

35.0

9769.1

281.8

78665.9

399.5

111496.6

445.4

124315.4

10.0

2791.2

5.075 P&L RCC M-25 In Column From 32st To 33rd floor

Cum

243.96

4,829.67

1,178,256.63

4666.47

1,138,441.77

3494.8

852594.0

35.0

8538.7

281.8

68757.9

399.5

97453.6

445.4

108657.9

10.0

2439.6

5.076 P&L RCC M-25 In Column From 33rd To 34th floor

Cum

205.65

4,686.62

963,811.65

4666.47

959,667.54

3494.8

718707.7

35.0

7197.8

281.8

57960.6

399.5

82150.1

445.4

91594.9

10.0

2056.5

5.077 P&L RCC M-20 In Overhead water tank Wall 3rd to 4th floor

Cum

12.00

4,481.49

53,777.94

4454.14

53,449.72

3282.5

39389.4

35.0

420.0

281.8

3382.1

399.5

4793.5

445.4

5344.7

10.0

120.0

5.078 P&L RCC M-20 In Overhead water tank Wall 6th to 7th floor

Cum

16.54

4,498.72

74,421.12

4454.14

73,683.78

3282.5

54300.8

35.0

579.0

281.8

4662.4

399.5

6608.2

445.4

7368.0

10.0

165.4

ITEM

DESCRIPTION

UOM

TENDER
DC RATE

QTY

TENDER
DC AMOUNT

PSE
RATE

Material

PSE AMOUNT

Labour

Sub Contractor

Plant Depric.

Plant Oprn & Fuel

Wooden Shuttering

Steel Shuttering

Testing Charges

5.079 P&L RCC M-20 In Overhead water tank Wall 14th to 15th floor

Cum

24.30

4,552.85

110,625.39

4454.14

108,227.00

3282.5

79757.2

35.0

850.4

281.8

6848.1

399.5

9706.2

445.4

10822.1

10.0

243.0

5.080 P&L RCC M-20 In Overhead water tank Wall 17th to18th floor

Cum

34.91

4,576.69

159,760.74

4454.14

155,483.03

3282.5

114582.3

35.0

1221.8

281.8

9838.3

399.5

13944.2

445.4

15547.4

10.0

349.1

5.081 P&L RCC M-20 In Overhead water tank Wall 32nd to33rd floor

Cum

36.52

4,733.42

172,886.72

4454.14

162,686.18

3282.5

119890.6

35.0

1278.4

281.8

10294.1

399.5

14590.2

445.4

16267.7

10.0

365.2

5.082 P&L RCC M-20 In Overhead water tank Wall 33rd to 34th floor

Cum

32.01

4,746.55

151,935.51

4454.14

142,575.66

3282.5

105070.3

35.0

1120.3

281.8

9021.6

399.5

12786.7

445.4

14256.7

10.0

320.1

5.078 P&L RCC M-25 In Wall(UG Sump )

Cum

4,686.62

5.079 P&L RCC M-25 In Wall(Retaining) for Foundation to 1st basement floor

Cum

1,702.00

4,574.74

7,786,200.42

4666.47
4666.47

7,942,337.73

3494.8
3494.8

5948121.4

35.0
35.0

59570.0

281.8
281.8

479689.5

399.5
399.5

679885.2

445.4
445.4

758051.7

10.0
10.0

17020.0

5.080 P&L RCC M-25 In Wall(Retaining) for first basement to GF floor

Cum

1,723.00

4,574.74

7,882,269.87

4666.47

8,040,333.67

3494.8

6021511.8

35.0

60305.0

281.8

485608.1

399.5

688273.9

445.4

767404.9

10.0

17230.0

5.081 P&L RCC M-25 In Staircases for Foundation to 1st basement

Cum

49.83

4,574.74

227,946.01

4666.47

232,517.03

3494.8

174135.1

35.0

1743.9

281.8

14043.2

399.5

19904.1

445.4

22192.5

10.0

498.3

5.082 P&L RCC M-25 In Staircases for first basement to GF

Cum

55.96

4,574.74

255,985.83

4666.47

261,119.14

3494.8

195555.6

35.0

1958.5

281.8

15770.7

399.5

22352.5

445.4

24922.4

10.0

559.6

5.083 P&L RCC M-25 In Staircases from GF To 1st Floor

Cum

47.09

4,569.79

215,211.87

4666.47

219,765.33

3494.8

164585.1

35.0

1648.3

281.8

13273.1

399.5

18812.5

445.4

20975.4

10.0

470.9

5.084 P&L RCC M-25 In Staircases From 1St To 2nd Floor

Cum

50.85

4,574.74

232,611.95

4666.47

237,276.53

3494.8

177699.5

35.0

1779.6

281.8

14330.7

399.5

20311.5

445.4

22646.7

10.0

508.5

5.085 P&L RCC M-25 In Staircases From 2nd To 3rd Floor

Cum

49.42

4,579.83

226,329.47

4666.47

230,611.06

3494.8

172707.7

35.0

1729.7

281.8

13928.1

399.5

19740.9

445.4

22010.5

10.0

494.2

5.086 P&L RCC M-25 In Staircases From 3rd To 4th Floor

Cum

45.86

4,585.09

210,287.29

4666.47

214,020.00

3494.8

160282.4

35.0

1605.2

281.8

12926.1

399.5

18320.7

445.4

20427.0

10.0

458.6

5.087 P&L RCC M-25 In Staircases From 4th To 5th Floor

Cum

45.86

4,590.49

210,535.36

4666.47

214,020.00

3494.8

160282.4

35.0

1605.2

281.8

12926.1

399.5

18320.7

445.4

20427.0

10.0

458.6

5.088 P&L RCC M-25 In Staircases From 5th To 6th Floor

Cum

46.24

4,596.07

212,541.67

4666.47

215,797.61

3494.8

161613.7

35.0

1618.5

281.8

13033.4

399.5

18472.8

445.4

20596.7

10.0

462.4

5.089 P&L RCC M-25 In Staircases From 6th To 7th Floor

Cum

40.06

4,601.80

184,355.46

4666.47

186,946.20

3494.8

140006.5

35.0

1402.2

281.8

11290.9

399.5

16003.1

445.4

17843.0

10.0

400.6

5.090 P&L RCC M-25 In Staircases From 7th To 8th Floor

Cum

40.06

4,607.72

184,592.24

4666.47

186,946.20

3494.8

140006.5

35.0

1402.2

281.8

11290.9

399.5

16003.1

445.4

17843.0

10.0

400.6

5.091 P&L RCC M-25 In Staircases From 8th To 9th Floor

Cum

40.06

4,613.80

184,836.13

4666.47

186,946.20

3494.8

140006.5

35.0

1402.2

281.8

11290.9

399.5

16003.1

445.4

17843.0

10.0

400.6

5.092 P&L RCC M-25 In Staircases From 9th To 10th Floor

Cum

40.06

4,620.07

185,087.34

4666.47

186,946.20

3494.8

140006.5

35.0

1402.2

281.8

11290.9

399.5

16003.1

445.4

17843.0

10.0

400.6

5.093 P&L RCC M-25 In Staircases From 10th To 11th Floor

Cum

40.06

4,626.53

185,346.08

4666.47

186,946.20

3494.8

140006.5

35.0

1402.2

281.8

11290.9

399.5

16003.1

445.4

17843.0

10.0

400.6

5.094 P&L RCC M-25 In Staircases From 11th To 12th Floor

Cum

40.06

4,633.18

185,612.59

4666.47

186,946.20

3494.8

140006.5

35.0

1402.2

281.8

11290.9

399.5

16003.1

445.4

17843.0

10.0

400.6

5.095 P&L RCC M-25 In Staircases From 12th To 13th Floor

Cum

40.06

4,640.04

185,887.09

4666.47

186,946.20

3494.8

140006.5

35.0

1402.2

281.8

11290.9

399.5

16003.1

445.4

17843.0

10.0

400.6

5.096 P&L RCC M-25 In Staircases From 13th To 14th Floor

Cum

40.06

4,647.09

186,169.82

4666.47

186,946.20

3494.8

140006.5

35.0

1402.2

281.8

11290.9

399.5

16003.1

445.4

17843.0

10.0

400.6

5.097 P&L RCC M-25 In Staircases From 14th To 15th Floor

Cum

40.06

4,654.36

186,461.04

4666.47

186,946.20

3494.8

140006.5

35.0

1402.2

281.8

11290.9

399.5

16003.1

445.4

17843.0

10.0

400.6

5.098 P&L RCC M-25 In Staircases From 15th To 16th Floor

Cum

32.65

4,661.85

152,231.42

4666.47

152,382.38

3494.8

114121.2

35.0

1142.9

281.8

9203.4

399.5

13044.3

445.4

14544.0

10.0

326.5

5.099 P&L RCC M-25 In Staircases From 16th To 17th Floor

Cum

32.65

4,669.56

152,483.25

4666.47

152,382.38

3494.8

114121.2

35.0

1142.9

281.8

9203.4

399.5

13044.3

445.4

14544.0

10.0

326.5

5.100 P&L RCC M-25 In Staircases From 17th To 18th Floor

Cum

32.65

4,677.51

152,742.64

4666.47

152,382.38

3494.8

114121.2

35.0

1142.9

281.8

9203.4

399.5

13044.3

445.4

14544.0

10.0

326.5

5.101 P&L RCC M-25 In Staircases From 18th To 19th Floor

Cum

22.59

4,685.69

105,831.40

4666.47

105,397.44

3494.8

78933.5

35.0

790.5

281.8

6365.6

399.5

9022.3

445.4

10059.6

10.0

225.9

5.102 P&L RCC M-25 In Staircases From 19th To 20th Floor

Cum

22.59

4,694.11

106,021.74

4666.47

105,397.44

3494.8

78933.5

35.0

790.5

281.8

6365.6

399.5

9022.3

445.4

10059.6

10.0

225.9

5.103 P&L RCC M-25 In Staircases From 20th To 21st Floor

Cum

22.59

4,702.79

106,217.78

4666.47

105,397.44

3494.8

78933.5

35.0

790.5

281.8

6365.6

399.5

9022.3

445.4

10059.6

10.0

225.9

5.104 P&L RCC M-25 In Staircases From 21st To 22nd Floor

Cum

22.59

4,711.73

106,419.71

4666.47

105,397.44

3494.8

78933.5

35.0

790.5

281.8

6365.6

399.5

9022.3

445.4

10059.6

10.0

225.9

5.105 P&L RCC M-25 In Staircases From 22nd To 23rd Floor

Cum

22.59

4,720.94

106,627.69

4666.47

105,397.44

3494.8

78933.5

35.0

790.5

281.8

6365.6

399.5

9022.3

445.4

10059.6

10.0

225.9

5.106 P&L RCC M-25 In Staircases From 23rd To 24th Floor

Cum

22.59

4,730.43

106,841.91

4666.47

105,397.44

3494.8

78933.5

35.0

790.5

281.8

6365.6

399.5

9022.3

445.4

10059.6

10.0

225.9

5.107 P&L RCC M-25 In Staircases From 24th To 25th Floor

Cum

22.59

4,740.20

107,062.56

4666.47

105,397.44

3494.8

78933.5

35.0

790.5

281.8

6365.6

399.5

9022.3

445.4

10059.6

10.0

225.9

5.108 P&L RCC M-25 In Staircases From 25th To 26th Floor

Cum

22.59

4,750.26

107,289.83

4666.47

105,397.44

3494.8

78933.5

35.0

790.5

281.8

6365.6

399.5

9022.3

445.4

10059.6

10.0

225.9

5.109 P&L RCC M-25 In Staircases From 26th To 27th Floor

Cum

22.59

4,760.62

107,523.92

4666.47

105,397.44

3494.8

78933.5

35.0

790.5

281.8

6365.6

399.5

9022.3

445.4

10059.6

10.0

225.9

5.110 P&L RCC M-25 In Staircases From 27thTo 28th Floor

Cum

22.59

4,771.30

107,765.03

4666.47

105,397.44

3494.8

78933.5

35.0

790.5

281.8

6365.6

399.5

9022.3

445.4

10059.6

10.0

225.9

5.111 P&L RCC M-25 In Staircases From 28th To 29th Floor

Cum

22.59

4,782.29

108,013.37

4666.47

105,397.44

3494.8

78933.5

35.0

790.5

281.8

6365.6

399.5

9022.3

445.4

10059.6

10.0

225.9

5.112 P&L RCC M-25 In Staircases From 29th To 30th Floor

Cum

22.59

4,793.62

108,269.16

4666.47

105,397.44

3494.8

78933.5

35.0

790.5

281.8

6365.6

399.5

9022.3

445.4

10059.6

10.0

225.9

5.113 P&L RCC M-25 In Staircases From 30th To 31st Floor

Cum

22.59

4,805.28

108,532.63

4666.47

105,397.44

3494.8

78933.5

35.0

790.5

281.8

6365.6

399.5

9022.3

445.4

10059.6

10.0

225.9

5.114 P&L RCC M-25 In Staircases From 31st To 32 Floor

Cum

22.59

4,817.30

108,827.12

4666.47

105,419.84

3494.8

78950.3

35.0

790.7

281.8

6367.0

399.5

9024.2

445.4

10061.7

10.0

225.9

5.115 P&L RCC M-25 In Staircases From 32st To 33rd Floor

Cum

22.59

4,829.67

109,106.70

4666.47

105,419.84

3494.8

78950.3

35.0

790.7

281.8

6367.0

399.5

9024.2

445.4

10061.7

10.0

225.9

5.116 P&L RCC M-25 In Staircases From 33rd To 34th Floor

Cum

22.59

4,842.42

109,394.65

4666.47

105,419.84

3494.8

78950.3

35.0

790.7

281.8

6367.0

399.5

9024.2

445.4

10061.7

10.0

225.9

5.117 P&L RCC M-25 In Staircases From 34th To 35th Floor

Cum

11.00

4,855.55

53,411.05

4666.47

51,331.21

3494.8

38442.6

35.0

385.0

281.8

3100.2

399.5

4394.1

445.4

4899.3

10.0

110.0

5.118 P&L RCC M-20 In Beam At first basement Floor

Cum

245.00

4,465.74

1,094,105.28

4454.14

1,091,265.13

3282.5

804201.1

35.0

8575.0

281.8

69050.5

399.5

97868.3

445.4

109120.3

10.0

2450.0

5.119 P&L RCC M-25 In Beam At first basement Floor

Cum

1,284.00

4,574.74

5,873,960.83

4666.47

5,991,751.85

3494.8

4487301.9

35.0

44940.0

281.8

361880.9

399.5

512909.8

445.4

571879.2

10.0

12840.0

5.120 P&L RCC M-20 In Beam At first basement roof / GF floor

Cum

299.00

4,465.74

1,335,255.02

4454.14

1,331,788.88

3282.5

981453.6

35.0

10465.0

281.8

84269.8

399.5

119439.3

445.4

133171.2

10.0

2990.0

5.121 P&L RCC M-25 In Beam At first basement roof / GF floor

Cum

2,249.00

4,574.74

10,288,580.93

4666.47

10,494,898.68

3494.8

7859767.9

35.0

78715.0

281.8

633855.3

399.5

898391.1

445.4

1001679.4

10.0

22490.0

5.122 P&L RCC M-20 In Beam At 1st Floor Level

Cum

369.01

4,465.74

1,647,901.19

4454.14

1,643,623.46

3282.5

1211258.1

35.0

12915.4

281.8

104001.3

399.5

147405.7

445.4

164352.9

10.0

3690.1

5.123 P&L RCC M-20 In Beam At 2nd Floor Level

Cum

376.64

4,470.83

1,683,895.05

4454.14

1,677,608.57

3282.5

1236303.3

35.0

13182.4

281.8

106151.7

399.5

150453.6

445.4

167751.2

10.0

3766.4

5.124 P&L RCC M-20 In Beam At 3rd Floor Level

Cum

311.30

4,476.09

1,393,385.01

4454.14

1,386,554.44

3282.5

1021812.7

35.0

10895.3

281.8

87735.1

399.5

124350.8

445.4

138647.5

10.0

3113.0

5.125 P&L RCC M-20 In Beam At 4th Floor Level

Cum

309.70

4,481.49

1,387,937.09

4454.14

1,379,466.25

3282.5

1016589.1

35.0

10839.6

281.8

87286.6

399.5

123715.2

445.4

137938.7

10.0

3097.0

ITEM

DESCRIPTION

UOM

QTY

TENDER
DC RATE

TENDER
DC AMOUNT

PSE
RATE

Material

PSE AMOUNT

Labour

Sub Contractor

Plant Depric.

Plant Oprn & Fuel

Wooden Shuttering

Steel Shuttering

Testing Charges

5.126 P&L RCC M-20 In Beam At 5th Floor Level

Cum

354.05

4,487.07

1,588,648.20

4454.14

1,576,991.91

3282.5

1162154.4

35.0

12391.8

281.8

99785.1

399.5

141429.9

445.4

157690.1

10.0

3540.5

5.127 P&L RCC M-20 In Beam At 6th Floor Level

Cum

248.86

4,492.80

1,118,092.51

4454.14

1,108,471.21

3282.5

816881.0

35.0

8710.2

281.8

70139.2

399.5

99411.4

445.4

110840.8

10.0

2488.6

5.128 P&L RCC M-20 In Beam At 7th Floor Level

Cum

245.79

4,498.72

1,105,718.19

4454.14

1,094,763.13

3282.5

806778.9

35.0

8602.5

281.8

69271.8

399.5

98182.0

445.4

109470.0

10.0

2457.9

5.129 P&L RCC M-20 In Beam At 8th Floor Level

Cum

252.34

4,504.80

1,136,763.75

4454.14

1,123,980.09

3282.5

828310.2

35.0

8832.1

281.8

71120.5

399.5

100802.3

445.4

112391.6

10.0

2523.4

5.130 P&L RCC M-20 In Beam At 9th Floor Level

Cum

244.65

4,511.07

1,103,650.97

4454.14

1,089,722.83

3282.5

803064.5

35.0

8562.9

281.8

68952.9

399.5

97730.0

445.4

108966.0

10.0

2446.5

5.131 P&L RCC M-20 In Beam At 10th Floor Level

Cum

242.20

4,517.53

1,094,134.23

4454.14

1,078,781.67

3282.5

795001.5

35.0

8476.9

281.8

68260.6

399.5

96748.8

445.4

107872.0

10.0

2422.0

5.132 P&L RCC M-20 In Beam At 11th Floor Level

Cum

242.20

4,524.18

1,095,745.42

4454.14

1,078,781.67

3282.5

795001.5

35.0

8476.9

281.8

68260.6

399.5

96748.8

445.4

107872.0

10.0

2422.0

5.133 P&L RCC M-20 In Beam At 12th Floor Level

Cum

242.20

4,531.04

1,097,404.95

4454.14

1,078,781.67

3282.5

795001.5

35.0

8476.9

281.8

68260.6

399.5

96748.8

445.4

107872.0

10.0

2422.0

5.134 P&L RCC M-20 In Beam At 13th Floor Level

Cum

242.20

4,538.09

1,099,114.26

4454.14

1,078,781.67

3282.5

795001.5

35.0

8476.9

281.8

68260.6

399.5

96748.8

445.4

107872.0

10.0

2422.0

5.135 P&L RCC M-20 In Beam At 14th Floor Level

Cum

242.16

4,545.36

1,100,698.09

4454.14

1,078,608.46

3282.5

794873.8

35.0

8475.5

281.8

68249.6

399.5

96733.2

445.4

107854.7

10.0

2421.6

5.136 P&L RCC M-20 In Beam At 15th Floor Level

Cum

229.97

4,552.85

1,047,006.04

4454.14

1,024,306.66

3282.5

754856.5

35.0

8048.9

281.8

64813.6

399.5

91863.2

445.4

102424.8

10.0

2299.7

5.137 P&L RCC M-20 In Beam At 16th Floor Level

Cum

239.88

4,560.56

1,093,982.87

4454.14

1,068,455.19

3282.5

787391.4

35.0

8395.8

281.8

67607.2

399.5

95822.6

445.4

106839.4

10.0

2398.8

5.138 P&L RCC M-20 In Beam At 17th Floor Level

Cum

187.73

4,568.51

857,657.38

4454.14

836,187.84

3282.5

616223.5

35.0

6570.6

281.8

52910.3

399.5

74992.1

445.4

83614.0

10.0

1877.3

5.139 P&L RCC M-20 In Beam At 18th Floor Level

Cum

163.66

4,576.69

749,022.37

4454.14

728,966.79

3282.5

537207.6

35.0

5728.1

281.8

46125.8

399.5

65376.2

445.4

72892.5

10.0

1636.6

5.140 P&L RCC M-20 In Beam At 19th Floor Level

Cum

171.03

4,585.11

784,202.33

4454.14

761,802.07

3282.5

561405.3

35.0

5986.1

281.8

48203.5

399.5

68321.0

445.4

76175.8

10.0

1710.3

5.141 P&L RCC M-20 In Beam At 20th Floor Level

Cum

132.52

4,593.79

608,761.63

4454.14

590,255.35

3282.5

434985.0

35.0

4638.1

281.8

37348.8

399.5

52936.1

445.4

59022.1

10.0

1325.2

5.142 P&L RCC M-20 In Beam At 21st Floor Level

Cum

132.52

4,602.73

609,946.38

4454.14

590,255.35

3282.5

434985.0

35.0

4638.1

281.8

37348.8

399.5

52936.1

445.4

59022.1

10.0

1325.2

5.143 P&L RCC M-20 In Beam At 22nd Floor Level

Cum

132.52

4,611.94

611,166.67

4454.14

590,255.35

3282.5

434985.0

35.0

4638.1

281.8

37348.8

399.5

52936.1

445.4

59022.1

10.0

1325.2

5.144 P&L RCC M-20 In Beam At 23rd Floor Level

Cum

132.52

4,621.43

612,423.57

4454.14

590,255.35

3282.5

434985.0

35.0

4638.1

281.8

37348.8

399.5

52936.1

445.4

59022.1

10.0

1325.2

5.145 P&L RCC M-20 In Beam At 24th Floor Level

Cum

132.52

4,631.20

613,718.17

4454.14

590,255.35

3282.5

434985.0

35.0

4638.1

281.8

37348.8

399.5

52936.1

445.4

59022.1

10.0

1325.2

5.146 P&L RCC M-20 In Beam At 25th Floor Level

Cum

132.52

4,641.26

615,051.61

4454.14

590,255.35

3282.5

434985.0

35.0

4638.1

281.8

37348.8

399.5

52936.1

445.4

59022.1

10.0

1325.2

5.147 P&L RCC M-20 In Beam At 26th Floor Level

Cum

137.75

4,651.62

640,769.96

4454.14

613,566.71

3282.5

452164.2

35.0

4821.3

281.8

38823.8

399.5

55026.7

445.4

61353.2

10.0

1377.5

5.148 P&L RCC M-20 In Beam At 27th Floor Level

Cum

137.75

4,662.30

642,240.48

4454.14

613,566.71

3282.5

452164.2

35.0

4821.3

281.8

38823.8

399.5

55026.7

445.4

61353.2

10.0

1377.5

5.149 P&L RCC M-20 In Beam At 28th Floor Level

Cum

137.75

4,673.29

643,755.11

4454.14

613,566.71

3282.5

452164.2

35.0

4821.3

281.8

38823.8

399.5

55026.7

445.4

61353.2

10.0

1377.5

5.150 P&L RCC M-20 In Beam At 29th Floor Level

Cum

137.75

4,684.62

645,315.19

4454.14

613,566.71

3282.5

452164.2

35.0

4821.3

281.8

38823.8

399.5

55026.7

445.4

61353.2

10.0

1377.5

5.151 P&L RCC M-20 In Beam At 30th Floor Level

Cum

137.75

4,696.28

646,922.06

4454.14

613,566.71

3282.5

452164.2

35.0

4821.3

281.8

38823.8

399.5

55026.7

445.4

61353.2

10.0

1377.5

5.152 P&L RCC M-20 In Beam At 31st Floor Level

Cum

170.00

4,708.30

800,410.85

4454.14

757,204.38

3282.5

558017.1

35.0

5950.0

281.8

47912.6

399.5

67908.6

445.4

75716.1

10.0

1700.0

5.153 P&L RCC M-20 In Beam At 32nd Floor Level

Cum

256.00

4,720.67

1,208,492.67

4454.14

1,140,260.71

3282.5

840308.1

35.0

8960.0

281.8

72150.7

399.5

102262.4

445.4

114019.5

10.0

2560.0

5.154 P&L RCC M-20 In Beam At 33rd Floor Level

Cum

292.00

4,733.42

1,382,158.98

4454.14

1,300,609.87

3282.5

958476.4

35.0

10220.0

281.8

82296.9

399.5

116643.0

445.4

130053.5

10.0

2920.0

5.155 P&L RCC M-20 In Beam At 34th Floor Level

Cum

131.00

4,746.55

621,798.08

4454.14

583,492.79

3282.5

430001.4

35.0

4585.0

281.8

36920.9

399.5

52329.6

445.4

58345.9

10.0

1310.0

5.156 P&L RCC M-20 In Beam At 35th Floor Level

Cum

101.00

4,760.07

480,767.39

4454.14

449,868.48

3282.5

331527.8

35.0

3535.0

281.8

28465.7

399.5

40345.7

445.4

44984.3

10.0

1010.0

1096.7

5.157 P&L RCC M-40 In Beam At first basement

Cum

109.67

5,370.74

589,000.40

5177.59

567,818.77

4005.9

439321.3

35.0

3838.4

281.8

30908.8

399.5

43808.4

445.4

48845.1

10.0

5.158 P&L RCC M-40 In Beam At GF floor

Cum

51.15

5,365.79

274,433.53

5177.59

264,808.42

4005.9

204882.2

35.0

1790.1

281.8

14414.7

399.5

20430.5

445.4

22779.4

10.0

511.5

5.159 P&L RCC M-40 In Beam At 1st Floor Level

Cum

132.36

5,370.74

710,870.42

5177.59

685,306.09

4005.9

530221.2

35.0

4632.6

281.8

37304.2

399.5

52872.8

445.4

58951.6

10.0

1323.6

5.160 P&L RCC M-40 In Beam At 1st Floor Level - pergola Beam - Entrance Hall

Cum

9.62

4860.75

46,774.07

4005.9

38548.0

399.5

3843.9

445.4

4285.9

10.0

96.2

5.161 P&L RCC M-40 In Beam At 2nd Floor Level

Cum

134.67

5,375.83

51,730.58

5177.59

697,252.66

4005.9

539464.3

35.0

4713.4

281.8

37954.5

399.5

53794.5

445.4

59979.3

10.0

1346.7

5.162 P&L RCC M-40 In Beam At 3rd Floor Level

Cum

125.27

5,381.09

724,656.44

5177.59

648,574.48

4005.9

501802.0

35.0

4384.3

281.8

35304.7

399.5

50038.9

445.4

55791.9

10.0

1252.7

5.163 P&L RCC M-40 In Beam At 4th Floor Level

Cum

125.27

5,386.49

674,742.65

5177.59

648,574.48

4005.9

501802.0

35.0

4384.3

281.8

35304.7

399.5

50038.9

445.4

55791.9

10.0

1252.7

5.164 P&L RCC M-40 In Beam At 5th Floor Level

Cum

125.27

5,392.07

675,440.53

5177.59

648,574.48

4005.9

501802.0

35.0

4384.3

281.8

35304.7

399.5

50038.9

445.4

55791.9

10.0

1252.7

5.165 P&L RCC M-40 In Beam At 6th Floor Level

Cum

125.27

5,397.80

676,159.36

5177.59

648,574.48

4005.9

501802.0

35.0

4384.3

281.8

35304.7

399.5

50038.9

445.4

55791.9

10.0

1252.7

5.166 P&L RCC M-40 In Beam At 7th Floor Level

Cum

125.27

5,403.72

676,899.75

5177.59

648,574.48

4005.9

501802.0

35.0

4384.3

281.8

35304.7

399.5

50038.9

445.4

55791.9

10.0

1252.7

5.167 P&L RCC M-40 In Beam At 8th Floor Level

Cum

125.27

5,409.80

677,662.35

5177.59

648,574.48

4005.9

501802.0

35.0

4384.3

281.8

35304.7

399.5

50038.9

445.4

55791.9

10.0

1252.7

5.168 P&L RCC M-40 In Beam At 9th Floor Level

Cum

125.27

5,416.07

678,447.83

5177.59

648,574.48

4005.9

501802.0

35.0

4384.3

281.8

35304.7

399.5

50038.9

445.4

55791.9

10.0

1252.7

5.169 P&L RCC M-40 In Beam At 10th Floor Level

Cum

125.27

5,422.53

679,256.87

5177.59

648,574.48

4005.9

501802.0

35.0

4384.3

281.8

35304.7

399.5

50038.9

445.4

55791.9

10.0

1252.7

5.170 P&L RCC M-40 In Beam At 11th Floor Level

Cum

125.27

5,429.18

680,090.19

5177.59

648,574.48

4005.9

501802.0

35.0

4384.3

281.8

35304.7

399.5

50038.9

445.4

55791.9

10.0

1252.7

5.171 P&L RCC M-40 In Beam At 12th Floor Level

Cum

125.27

5,436.04

680,948.51

5177.59

648,574.48

4005.9

501802.0

35.0

4384.3

281.8

35304.7

399.5

50038.9

445.4

55791.9

10.0

1252.7

5.172 P&L RCC M-40 In Beam At 13th Floor Level

Cum

125.27

5,443.09

681,832.57

5177.59

648,574.48

4005.9

501802.0

35.0

4384.3

281.8

35304.7

399.5

50038.9

445.4

55791.9

10.0

1252.7

5.173 P&L RCC M-40 In Beam At 14th Floor Level

Cum

104.01

5,450.36

682,743.16

5177.59

538,516.48

4005.9

416650.1

35.0

3640.3

281.8

29313.8

399.5

41547.7

445.4

46324.5

10.0

1040.1

5.174 P&L RCC M-40 In Beam At 15th Floor Level

Cum

100.12

5,457.85

567,665.74

5177.59

518,382.83

4005.9

401072.7

35.0

3504.2

281.8

28217.8

399.5

39994.4

445.4

44592.5

10.0

1001.2

5.175 P&L RCC M-40 In Beam At 16th Floor Level

Cum

79.91

5,465.56

547,214.41

5177.59

413,726.24

4005.9

320099.9

35.0

2796.7

281.8

22520.9

399.5

31919.9

445.4

35589.7

10.0

799.1

5.176 P&L RCC M-40 In Beam At 17th Floor Level

Cum

67.42

5,473.51

437,371.72

5177.59

349,083.65

4005.9

270086.0

35.0

2359.8

281.8

19002.1

399.5

26932.6

445.4

30029.0

10.0

674.2

5.177 P&L RCC M-40 In Beam At 18th Floor Level

Cum

65.48

5,481.69

369,586.27

5177.59

339,016.83

4005.9

262297.3

35.0

2291.7

281.8

18454.1

399.5

26155.9

445.4

29163.0

10.0

654.8

5.178 P&L RCC M-40 In Beam At 19th Floor Level

Cum

65.48

5,490.11

359,479.98

5177.59

339,016.83

4005.9

262297.3

35.0

2291.7

281.8

18454.1

399.5

26155.9

445.4

29163.0

10.0

654.8

5.179 P&L RCC M-40 In Beam At 20th Floor Level

Cum

65.48

5,498.79

360,048.31

5177.59

339,016.83

4005.9

262297.3

35.0

2291.7

281.8

18454.1

399.5

26155.9

445.4

29163.0

10.0

654.8

ITEM

DESCRIPTION

UOM

QTY

TENDER
DC RATE

TENDER
DC AMOUNT

PSE
RATE

Material

PSE AMOUNT

Labour

Sub Contractor

Plant Depric.

Plant Oprn & Fuel

Wooden Shuttering

Steel Shuttering

Testing Charges

5.180 P&L RCC M-40 In Beam At 21st Floor Level

Cum

65.48

5,507.73

360,633.70

5177.59

339,016.83

4005.9

262297.3

35.0

2291.7

281.8

18454.1

399.5

26155.9

445.4

29163.0

10.0

654.8

5.181 P&L RCC M-40 In Beam At 22nd Floor Level

Cum

65.48

5,516.94

361,236.65

5177.59

339,016.83

4005.9

262297.3

35.0

2291.7

281.8

18454.1

399.5

26155.9

445.4

29163.0

10.0

654.8

5.182 P&L RCC M-40 In Beam At 23rd Floor Level

Cum

65.48

5,526.43

361,857.69

5177.59

339,016.83

4005.9

262297.3

35.0

2291.7

281.8

18454.1

399.5

26155.9

445.4

29163.0

10.0

654.8

5.183 P&L RCC M-40 In Beam At 24th Floor Level

Cum

65.48

5,536.20

362,497.36

5177.59

339,016.83

4005.9

262297.3

35.0

2291.7

281.8

18454.1

399.5

26155.9

445.4

29163.0

10.0

654.8

5.184 P&L RCC M-40 In Beam At 25th Floor Level

Cum

65.48

5,546.26

363,156.21

5177.59

339,016.83

4005.9

262297.3

35.0

2291.7

281.8

18454.1

399.5

26155.9

445.4

29163.0

10.0

654.8

5.185 P&L RCC M-40 In Beam At 26th Floor Level

Cum

10.81

5,556.62

363,834.84

5177.59

55,973.93

4005.9

43307.0

35.0

378.4

281.8

3046.9

399.5

4318.5

445.4

4815.0

10.0

108.1

5.186 P&L RCC M-40 In Beam At 27th Floor Level

Cum

10.81

5,567.30

60,186.95

5177.59

55,973.93

4005.9

43307.0

35.0

378.4

281.8

3046.9

399.5

4318.5

445.4

4815.0

10.0

108.1

5.187 P&L RCC M-40 In Beam At 28th Floor Level

Cum

10.81

5,578.29

60,305.82

5177.59

55,973.93

4005.9

43307.0

35.0

378.4

281.8

3046.9

399.5

4318.5

445.4

4815.0

10.0

108.1

5.188 P&L RCC M-40 In Beam At 29th Floor Level

Cum

10.81

5,589.62

60,428.25

5177.59

55,973.93

4005.9

43307.0

35.0

378.4

281.8

3046.9

399.5

4318.5

445.4

4815.0

10.0

108.1

5.189 P&L RCC M-40 In Beam At 30th Floor Level

Cum

10.81

5,601.28

60,554.36

5177.59

55,973.93

4005.9

43307.0

35.0

378.4

281.8

3046.9

399.5

4318.5

445.4

4815.0

10.0

108.1

5.190 P&L RCC M-40 In Beam At 31st Floor Level

Cum

24.00

5,613.30

60,684.25

5177.59

124,262.24

4005.9

96141.7

35.0

840.0

281.8

6764.1

399.5

9587.1

445.4

10689.3

10.0

240.0

5.191 P&L RCC M-40 In Beam 32nd floor level

Cum

38.00

5,625.67

213,775.63

5177.59

196,748.55

4005.9

152224.3

35.0

1330.0

281.8

10709.9

399.5

15179.6

445.4

16924.8

10.0

380.0

5.192 P&L RCC M-40 In Beam 33rd floor level

Cum

11.00

5,651.55

62,167.05

5177.59

56,953.53

4005.9

44064.9

35.0

385.0

281.8

3100.2

399.5

4394.1

445.4

4899.3

10.0

110.0

5.193 P&L RCC M-30 In Beam At GF floor

Cum

1.32

4,804.74

6,321.11

5003.67

6,582.83

3832.0

5041.4

35.0

46.0

281.8

370.8

399.5

525.5

445.4

586.0

10.0

13.2

5.194 P&L RCC M-30 In Beam At 1st floor

Cum

1.32

4,804.74

6,321.11

5003.67

6,582.83

3832.0

5041.4

35.0

46.0

281.8

370.8

399.5

525.5

445.4

586.0

10.0

13.2

5.195 P&L RCC M-30 In Beam At 2nd floor

Cum

1.32

4,809.83

6,327.82

5003.67

6,582.83

3832.0

5041.4

35.0

46.0

281.8

370.8

399.5

525.5

445.4

586.0

10.0

13.2

5.196 P&L RCC M-30 In Beam At 3rd floor

Cum

1.32

4,815.09

6,334.73

5003.67

6,582.83

3832.0

5041.4

35.0

46.0

281.8

370.8

399.5

525.5

445.4

586.0

10.0

13.2

5.197 P&L RCC M-30 In Beam At 4th floor

Cum

1.32

4,820.49

6,341.84

5003.67

6,582.83

3832.0

5041.4

35.0

46.0

281.8

370.8

399.5

525.5

445.4

586.0

10.0

13.2

5.198 P&L RCC M-30 In Beam At 5th floor

Cum

1.32

4,826.07

6,349.17

5003.67

6,582.83

3832.0

5041.4

35.0

46.0

281.8

370.8

399.5

525.5

445.4

586.0

10.0

13.2

5.199 P&L RCC M-25 In Beam At 26th floor

Cum

49.43

4,760.62

235,333.09

4666.47

230,678.95

3494.8

172758.5

35.0

1730.2

281.8

13932.2

399.5

19746.7

445.4

22017.0

10.0

494.3

5.200 P&L RCC M-25 In Beam At 27th floor

Cum

49.43

4,771.30

235,860.79

4666.47

230,678.95

3494.8

172758.5

35.0

1730.2

281.8

13932.2

399.5

19746.7

445.4

22017.0

10.0

494.3

5.201 P&L RCC M-25 In Beam At 28th floor

Cum

49.43

4,782.29

236,404.33

4666.47

230,678.95

3494.8

172758.5

35.0

1730.2

281.8

13932.2

399.5

19746.7

445.4

22017.0

10.0

494.3

5.202 P&L RCC M-25 In Beam At 29th floor

Cum

49.43

4,793.62

236,964.17

4666.47

230,678.95

3494.8

172758.5

35.0

1730.2

281.8

13932.2

399.5

19746.7

445.4

22017.0

10.0

494.3

5.203 P&L RCC M-25 In Beam At 30th floor

Cum

49.43

4,805.28

237,540.81

4666.47

230,678.95

3494.8

172758.5

35.0

1730.2

281.8

13932.2

399.5

19746.7

445.4

22017.0

10.0

494.3

5.204 P&L RCC M-25 In Beam At 31st floor

Cum

49.43

4,817.30

238,134.75

4666.47

230,678.95

3494.8

172758.5

35.0

1730.2

281.8

13932.2

399.5

19746.7

445.4

22017.0

10.0

494.3

5.193 P&L RCC M-20 In Slab At first basement roof / GF floor

Cum

231.80

4,465.74

1,035,140.80

4454.14

1,032,453.71

3282.5

760860.4

35.0

8112.9

281.8

65329.2

399.5

92593.9

445.4

103239.4

10.0

2318.0

5.194 P&L RCC M-25 In Slab At first basement

Cum

1,950.59

4,574.74

8,923,425.39

4666.47

9,102,367.57

3494.8

6816883.0

35.0

68270.6

281.8

549751.2

399.5

779186.8

445.4

868770.1

10.0

19505.9

5.195 P&L RCC M-20 In Slab At GF floor

Cum

211.00

4,460.79

941,206.58

4454.14

939,805.05

3282.5

692583.5

35.0

7384.8

281.8

59466.8

399.5

84284.9

445.4

93975.1

10.0

2110.0

5.196 P&L RCC M-25 In Slab At GF floor

Cum

2,679.46

4,569.79

12,244,549.67

4666.47

12,503,619.91

3494.8

9364125.7

35.0

93781.0

281.8

755175.0

399.5

1070343.0

445.4

1193400.6

10.0

26794.6

5.197 P&L RCC M-20 In Slab At 1st Floor Level

Cum

545.19

4,465.74

2,434,670.46

4454.14

2,428,350.39

3282.5

1789557.8

35.0

19081.6

281.8

153655.4

399.5

217782.6

445.4

242821.1

10.0

5451.9

5.198 P&L RCC M-25 In Slab At 1st Floor Level

Cum

77.21

4,574.74

353,218.37

4666.47

360,301.48

3494.8

269834.5

35.0

2702.4

281.8

21761.0

399.5

30842.8

445.4

34388.8

10.0

772.1

5.199 P&L RCC M-20 In Slab At 2nd Floor Level

Cum

528.77

4,470.83

2,364,028.87

4454.14

2,355,203.25

3282.5

1735652.5

35.0

18506.8

281.8

149027.0

399.5

211222.5

445.4

235506.8

10.0

5287.7

5.200 P&L RCC M-25 In Slab At 2nd Floor Level

Cum

77.21

4,579.83

353,612.03

4666.47

360,301.48

3494.8

269834.5

35.0

2702.4

281.8

21761.0

399.5

30842.8

445.4

34388.8

10.0

772.1

5.201 P&L RCC M-20 In Slab At 3rd Floor Level

Cum

525.93

4,476.09

2,354,116.41

4454.14

2,342,576.20

3282.5

1726347.0

35.0

18407.6

281.8

148228.0

399.5

210090.1

445.4

234244.2

10.0

5259.3

5.202 P&L RCC M-20 In Slab At 4th Floor Level

Cum

525.14

4,481.49

2,353,402.20

4454.14

2,339,038.94

3282.5

1723740.3

35.0

18379.8

281.8

148004.2

399.5

209772.8

445.4

233890.5

10.0

5251.4

5.203 P&L RCC M-20 In Slab At 5th Floor Level

Cum

512.70

4,487.07

2,300,529.54

4454.14

2,283,650.01

3282.5

1682921.7

35.0

17944.6

281.8

144499.4

399.5

204805.4

445.4

228351.9

10.0

5127.0

5.204 P&L RCC M-20 In Slab At 6th Floor Level

Cum

456.17

4,492.80

2,049,466.07

4454.14

2,031,830.19

3282.5

1497344.7

35.0

15965.8

281.8

128565.3

399.5

182221.3

445.4

203171.4

10.0

4561.7

5.205 P&L RCC M-20 In Slab At 7th Floor Level

Cum

460.36

4,498.72

2,071,019.42

4454.14

2,050,500.51

3282.5

1511103.7

35.0

16112.5

281.8

129746.7

399.5

183895.7

445.4

205038.3

10.0

4603.6

5.206 P&L RCC M-20 In Slab At 8th Floor Level

Cum

458.46

4,504.80

2,065,268.41

4454.14

2,042,043.09

3282.5

1504871.0

35.0

16046.1

281.8

129211.6

399.5

183137.3

445.4

204192.6

10.0

4584.6

5.207 P&L RCC M-20 In Slab At 9th Floor Level

Cum

455.48

4,511.07

2,054,691.84

4454.14

2,028,761.51

3282.5

1495083.2

35.0

15941.7

281.8

128371.2

399.5

181946.1

445.4

202864.5

10.0

4554.8

5.208 P&L RCC M-20 In Slab At 10th Floor Level

Cum

452.71

4,517.53

2,045,148.27

4454.14

2,016,451.37

3282.5

1486011.4

35.0

15845.0

281.8

127592.2

399.5

180842.1

445.4

201633.6

10.0

4527.1

5.209 P&L RCC M-20 In Slab At 11th Floor Level

Cum

453.19

4,524.18

2,050,334.67

4454.14

2,018,592.47

3282.5

1487589.2

35.0

15861.8

281.8

127727.7

399.5

181034.1

445.4

201847.7

10.0

4531.9

5.210 P&L RCC M-20 In Slab At 12th Floor Level

Cum

453.19

4,531.04

2,053,439.94

4454.14

2,018,592.47

3282.5

1487589.2

35.0

15861.8

281.8

127727.7

399.5

181034.1

445.4

201847.7

10.0

4531.9

5.211 P&L RCC M-20 In Slab At 13th Floor Level

Cum

453.19

4,538.09

2,056,638.37

4454.14

2,018,592.47

3282.5

1487589.2

35.0

15861.8

281.8

127727.7

399.5

181034.1

445.4

201847.7

10.0

4531.9

5.212 P&L RCC M-20 In Slab At 14th Floor Level

Cum

392.27

4,545.36

1,783,021.25

4454.14

1,747,238.25

3282.5

1287616.4

35.0

13729.5

281.8

110557.6

399.5

156698.2

445.4

174713.8

10.0

3922.7

5.213 P&L RCC M-20 In Slab At 15th Floor Level

Cum

392.51

4,552.85

1,787,048.83

4454.14

1,748,305.11

3282.5

1288402.6

35.0

13737.9

281.8

110625.1

399.5

156793.9

445.4

174820.5

10.0

3925.1

5.214 P&L RCC M-20 In Slab At 16th Floor Level

Cum

367.04

4,560.56

1,673,899.47

4454.14

1,634,839.65

3282.5

1204785.0

35.0

12846.3

281.8

103445.5

399.5

146617.9

445.4

163474.6

10.0

3670.4

5.215 P&L RCC M-20 In Slab At 17th Floor Level

Cum

281.16

4,568.51

1,284,462.07

4454.14

1,252,308.44

3282.5

922881.0

35.0

9840.5

281.8

79240.6

399.5

112311.2

445.4

125223.7

10.0

2811.6

ITEM

DESCRIPTION

UOM

TENDER
DC RATE

QTY

TENDER
DC AMOUNT

PSE
RATE

Material

PSE AMOUNT

Labour

Sub Contractor

Plant Depric.

Plant Oprn & Fuel

Wooden Shuttering

Steel Shuttering

Testing Charges

5.216 P&L RCC M-20 In Slab At 18th Floor Level

Cum

273.09

4,576.69

1,249,846.65

4454.14

1,216,381.16

3282.5

896404.6

35.0

9558.1

281.8

76967.3

399.5

109089.1

445.4

121631.1

10.0

2730.9

5.217 P&L RCC M-20 In Slab At 19th Floor Level

Cum

259.57

4,585.11

1,190,171.74

4454.14

1,156,175.22

3282.5

852036.2

35.0

9085.1

281.8

73157.7

399.5

103689.7

445.4

115610.9

10.0

2595.7

5.218 P&L RCC M-20 In Slab At 20th Floor Level

Cum

259.57

4,593.79

1,192,424.80

4454.14

1,156,175.22

3282.5

852036.2

35.0

9085.1

281.8

73157.7

399.5

103689.7

445.4

115610.9

10.0

2595.7

5.219 P&L RCC M-20 In Slab At 21st Floor Level

Cum

259.57

4,602.73

1,194,745.44

4454.14

1,156,175.22

3282.5

852036.2

35.0

9085.1

281.8

73157.7

399.5

103689.7

445.4

115610.9

10.0

2595.7

5.220 P&L RCC M-20 In Slab At 22nd Floor Level

Cum

259.57

4,611.94

1,197,135.71

4454.14

1,156,175.22

3282.5

852036.2

35.0

9085.1

281.8

73157.7

399.5

103689.7

445.4

115610.9

10.0

2595.7

5.221 P&L RCC M-20 In Slab At 23rd Floor Level

Cum

259.57

4,621.43

1,199,597.68

4454.14

1,156,175.22

3282.5

852036.2

35.0

9085.1

281.8

73157.7

399.5

103689.7

445.4

115610.9

10.0

2595.7

5.222 P&L RCC M-20 In Slab At 24th Floor Level

Cum

259.57

4,631.20

1,202,133.52

4454.14

1,156,175.22

3282.5

852036.2

35.0

9085.1

281.8

73157.7

399.5

103689.7

445.4

115610.9

10.0

2595.7

5.223 P&L RCC M-20 In Slab At 25th Floor Level

Cum

259.57

4,641.26

1,204,745.43

4454.14

1,156,175.22

3282.5

852036.2

35.0

9085.1

281.8

73157.7

399.5

103689.7

445.4

115610.9

10.0

2595.7

5.224 P&L RCC M-20 In Slab At 26th Floor Level

Cum

259.57

4,651.62

1,207,435.69

4454.14

1,156,175.22

3282.5

852036.2

35.0

9085.1

281.8

73157.7

399.5

103689.7

445.4

115610.9

10.0

2595.7

5.225 P&L RCC M-20 In Slab At 27th Floor Level

Cum

259.57

4,662.30

1,210,206.67

4454.14

1,156,175.22

3282.5

852036.2

35.0

9085.1

281.8

73157.7

399.5

103689.7

445.4

115610.9

10.0

2595.7

5.226 P&L RCC M-20 In Slab At 28th Floor Level

Cum

259.57

4,673.29

1,213,060.77

4454.14

1,156,175.22

3282.5

852036.2

35.0

9085.1

281.8

73157.7

399.5

103689.7

445.4

115610.9

10.0

2595.7

5.227 P&L RCC M-20 In Slab At 29th Floor Level

Cum

259.57

4,684.62

1,216,000.50

4454.14

1,156,175.22

3282.5

852036.2

35.0

9085.1

281.8

73157.7

399.5

103689.7

445.4

115610.9

10.0

2595.7

5.228 P&L RCC M-20 In Slab At 30th Floor Level

Cum

259.57

4,696.28

1,219,028.42

4454.14

1,156,175.22

3282.5

852036.2

35.0

9085.1

281.8

73157.7

399.5

103689.7

445.4

115610.9

10.0

2595.7

5.229 P&L RCC M-20 In Slab At 31st Floor Level

Cum

268.93

4,708.30

1,266,202.33

4454.14

1,197,852.27

3282.5

882749.8

35.0

9412.5

281.8

75794.9

399.5

107427.4

445.4

119778.4

10.0

2689.3

5.230 P&L RCC M-20 In Slab At 32nd Floor Level

Cum

148.00

4,720.67

698,659.83

4454.14

659,213.22

3282.5

485803.1

35.0

5180.0

281.8

41712.1

399.5

59120.4

445.4

65917.5

10.0

1480.0

5.231 P&L RCC M-20 In Slab At 33rd Floor Level

Cum

141.00

4,733.42

667,412.38

4454.14

628,034.22

3282.5

462825.9

35.0

4935.0

281.8

39739.3

399.5

56324.2

445.4

62799.8

10.0

1410.0

5.232 P&L RCC M-20 In Slab At 34th Floor Level

Cum

109.00

4,746.55

517,373.97

4454.14

485,501.63

3282.5

357787.4

35.0

3815.0

281.8

30720.4

399.5

43541.4

445.4

48547.4

10.0

1090.0

5.233 P&L RCC M-20 In Lintels At All Floors

Cum

247.87

4,577.62

1,134,655.80

4454.14

1,104,048.53

3282.5

813621.7

35.0

8675.5

281.8

69859.4

399.5

99014.8

445.4

110398.5

10.0

2478.7

5.234 P&L RCC M-20 In Bottom & Top Rails In Balcony At All Floors

Cum

230.51

4,577.62

1,055,188.24

4454.14

1,026,724.60

3282.5

756638.3

35.0

8067.9

281.8

64966.6

399.5

92080.1

445.4

102666.6

10.0

2305.1

5.235 P&L RCC M-20 In Nibs In Balcony Slab At All Floors

Cum

4,577.62

4454.14

3282.5

35.0

281.8

399.5

445.4

10.0

5.236 P&L RCC M-20 In Service Ledge At All Floors

Cum

4,577.62

4454.14

3282.5

35.0

281.8

399.5

445.4

10.0

Extra for Closing of leftover Cutouts in M20 grade in FHC Shafts, LV Shaft,
5.237
Electrical Shafts at all
floor levels including cost of concreting, shuttering, reinforcement steel
straightening, tying and
welding all complete as required, to be measured no of shaft per floor
5.24

Providing & laying damp proof course 40 mm thick with cement concrete
1:2:4 (1 cement : 2 coarse
sand: 4 Graded stone aggregate 12.5 mm nominal size) including the cost
of centring and shuttering &
all leads and location and providing & mixing cico No-1 in concrete (2% by
weight of cement).

Nos

619.60

870.38

539,286.90

857.05

531,023.98
-

354.5

219650.2

3.8

2342.1

406.4

251828.1

43.1

26730.6

48.1

29803.8

1.1

669.2

Sqm

307.98

5.24

Extra for providing & mixing cico No-1 in concrete (2% by weight of cement)
contact with water /
moisture(Qty. shall be paid as per concrete volume)

Cum

3,300.00

300.00

69,060.89

990,000.00

300.00

326,450,393.35

6.000 WATER PROOFING OF STRUCTURE


Note: All waterproofing works shall be carried out by specialist
waterproofing agencies approved by
the Engineer.
6.01

300.0

990000.0
243,772,268.69

2,419,136.53

19,713,148.87

Water proofing treatment in toilets & kitchens including the sunken areas
comprising of
cleaning & preparation of surface, providing injection grouting with nonshrink grouting
compound in loose pockets of concrete Providing & applying of the a
membrane

treatment (TAPECRETE) and protective plaster 15mm thick in 1:3 cement


sand mortar mixed with integral water proofing compound & finished with
neat cement
complete as directed or as recommended by water-proofing agency in
sunken slabs.

990,000.00
324,998,550.58
-

Sqm

20,726.00

400.00

8,290,400.00

380.00

7,875,880.00

380.0

7875880.0

200.0

936400.0

6.02

6.03

Providing & filling the annular space around pipes in cut-outs in toilets,
kitchen with cement concrete
1:2:4 & sealing the same thoroughly including application of epoxy putty or
injection grouting with
non shrink grout as may be required.
Providing and laying Brick Bat Coba waterproofing treatment Average
125mm thick on
roof consisting of following specifications : Cleaning & preparing the surface
for
receiving water proofing treatment including raking the construction joints,
loose
patches in concrete & providing & injecting non -shrink grout through
nozzles fix
admixed with Integral Waterproofing Compound , spreading
minimum15mm thick layer
of cement mortar 1:4 (1 cement : 4coarse sand) admixed with Integral
Waterproofing
Compound and a layer of broken bricks/ brick bats(minimum 40mm thick)
laid to
specified slope, filling the voids of brick bats with cement mortar 1:4 (1
cement : 4 coarse
sand) admixed with Integral Waterproofing Compound, applying a 20mm
thick joint
less water proofing plaster in cement mortar 1:4(1 cement :4 coarse sand)
admixed with
Integral Waterproofing Compound and finally finished with floating coat of
neat cement
slurry admixed with Integral Waterproofing Compound and marking
of300x300mm sq.
Grid including adequate curing for 14days including all leads, lifts and
making Khurras

Each

4,682.00

400.00

1,872,800.00

200.00

936,400.00
-

27,613,966.87

30,788,751.52

691,278.09

ITEM

DESCRIPTION
as specified for draining of roof water. (the minimum thickness of treatment
is to be
75mm with 10 years guarantee on approved performa. the Integral
Waterproofing
Compound to be admixed will be approved by the Owner' and the ratio of
Integral
Waterproofing Compound to cement shall be as recommended by the
respective
manufacturer.)

Extra over item no. 6.03 for additional thickness beyond average 125mm
thick

UOM

TENDER
DC RATE

QTY

TENDER
DC AMOUNT

PSE
RATE

Material

PSE AMOUNT

Labour

Sub Contractor

Plant Depric.

Plant Oprn & Fuel

Wooden Shuttering

Steel Shuttering

Testing Charges

Sqm

4,577.00

650.00

cum

5,000.00

2,975,050.00

645.00

2,952,165.00
-

645.0

2952165.0

150.0

224550.0

350.0

588000.0

435.0
450.0

497205.0
1447200.0

425.0

5339700.0

723.8

9742078.8

70.0

897820.0

6.04

6.05

Providing and laying Vatta/ gola upto 300mm high as specified all complete.
(Treatment
as specified in item no 6.04 above, is turned around on vertical walls upto a
height of
300mm)

Rm

1,497.00

200.00

299,400.00

150.00

Providing and making Khurra of size 300mm * 300mm with average


minimum
thickness of 50mm of cement concrete 1:2:4 (1-cement: 2 coarse sand : 4
graded

stone aggregate of 20mm nominal size ) applying two coat of tape Crete and

finished with 12mm cement plaster 1:3 (1-cement: 3 coarse sand) and a
coat

of neat cement rounding the edges and making and finishing the outlet

6.06

a
b

6.07

complete.

Nos

1,680.00

350.00

588,000.00

350.00

Water proofing treatment in water tanks comprising of


injection grouting with non-shrink grout on bottom &
inside walls and providing & applying a membrane
treatment (food grade epoxy) complete as directed or
as recommended by water-proofing agency.
Horizontal surface
Vertical surface

Sqm
Sqm

1,143.00
3,216.00

450.00
450.00

514,350.00
1,447,200.00

435.00
450.00

Water proofing treatment comprising of injection grouting with non-shrink


grout on inside walls in grid pattern @ 1.5m c/c & at construction joints and
providing & applying a membrane treatment (Tape Crete) & 15 mm thk.
Protective plaster in CM 1:3
complete as directed or as recommended by water-proofing agency, at all
floors

sqm

12,564.00

450.00

5,653,800.00

425.00

Removal of PVC conduit from tie rod holes and properly cleaning it:
and filling it with micro conrete mixed with water proofing compound

5,339,700.00
-

Water proofing treatment comprising of injection grouting


with non-shrink grout on inside walls in grid pattern @
1.5m c/c & at construction joints and providing & applying

CM 1:3 complete as directed or as recommended by


water-proofing agency, at all floors.

588,000.00
497,205.00
1,447,200.00
-

a membrane treatment (Tape Crete) & 15 mm thk. Protective plaster in

New

224,550.00
-

Sqm

13,460.00

Nos

12,826.00

723.78

9,742,145.86

723.78
70.00

9,742,078.80
897,820.00
-

31,383,145.86
7.00

30,500,998.80
-

BRICK WORK (Half BW)


Providing and Laying Half brick masonry with 1st class bricks in
superstructure
above plinth level at all floor levels in cement mortar 1:4 (1 cement : 4
coarse sand)
with 6 mm dia. ms bars - 2 no. at every third course embedded in cement
mortar laid
in proper line & plumb including hacking of RCC at junctions, raking of
joints,
curing and all leads & lifts complete to the satisfaction of the Engineer. (MS
Bars to
be free issued by the Owner)

30,500,998.80

7.01

Half Brickwork I-Cl. In CM 1:4 in Lower Basement to Upper Basement

Sqm

506.06

641.31

461

14.0

93

18.5

7.02

Half Brickwork I-Cl. In CM 1:4 in Upper Basement to Ground Floor

Sqm

506.06

638.61

461

14.0

90

18.5

55.2

7.03

Half Brickwork I-Cl. In CM 1:4 GF To 1st floor

Sqm

723.58

503.36

364,217.45

641.31

464,037.92

461

333500.1

14

10130.1

93

67075.7

18.5

13390.2

55.2

39941.8

7.04

Half Brickwork I-Cl. In CM 1:4 1st To 2nd floor

Sqm

2,575.78

506.06

1,303,487.96

644.09

1,659,035.35

461

1187186.3

14

36060.9

95

245937.8

18.5

47666.3

55.2

142184.1

7.05

Half Brickwork I-Cl. In CM 1:4 2nd To 3rd floor

Sqm

2,419.01

508.84

1,230,883.08

646.96

1,564,993.17

461

1114932.5

14

33866.2

98

237898.8

18.5

44765.2

55.2

133530.6

7.06

Half Brickwork I-Cl. In CM 1:4 3rd To 4th floor

Sqm

2,419.01

511.70

1,237,812.17

649.91

1,572,130.13

461

1114932.5

14

33866.2

101

245035.7

18.5

44765.2

55.2

133530.6

7.07

Half Brickwork I-Cl. In CM 1:4 4th To 5th floor

Sqm

2,419.01

514.65

1,244,949.13

652.94

1,579,481.20

461

1114932.5

14

33866.2

104

252386.8

18.5

44765.2

55.2

133530.6

7.08

Half Brickwork I-Cl. In CM 1:4 5th To 6th floor

Sqm

2,184.69

517.69

1,130,994.89

656.07

1,433,321.35

461

1006933.4

14

30585.7

107

234777.3

18.5

40429.0

55.2

120596.0

7.09

Half Brickwork I-Cl. In CM 1:4 6th To 7th floor

Sqm

2,162.01

520.82

1,126,020.84

659.30

1,425,411.77

461

996480.1

14

30268.2

111

239310.2

18.5

40009.3

55.2

119344.0

7.10

Half Brickwork I-Cl. In CM 1:4 7th To 8th floor

Sqm

2,162.01

524.04

1,132,991.04

662.62

1,432,591.07

461

996480.1

14

30268.2

114

246489.5

18.5

40009.3

55.2

119344.0

7.11

Half Brickwork I-Cl. In CM 1:4 8th To 9th floor

Sqm

2,162.01

527.37

1,140,170.35

666.04

1,439,985.75

461

996480.1

14

30268.2

117

253884.1

18.5

40009.3

55.2

119344.0

7.12

Half Brickwork I-Cl. In CM 1:4 9th To 10th floor

Sqm

2,162.01

530.79

1,147,565.03

669.56

1,447,602.28

461

996480.1

14

30268.2

121

261500.7

18.5

40009.3

55.2

119344.0

7.13

Half Brickwork I-Cl. In CM 1:4 10th To 11th floor

Sqm

2,162.01

534.31

1,155,181.55

673.19

1,455,447.30

461

996480.1

14

30268.2

125

269345.7

18.5

40009.3

55.2

119344.0

7.14

Half Brickwork I-Cl. In CM 1:4 11th To 12th floor

Sqm

2,162.01

537.94

1,163,026.57

676.93

1,463,527.67

461

996480.1

14

30268.2

128

277426.1

18.5

40009.3

55.2

119344.0

7.15

Half Brickwork I-Cl. In CM 1:4 12th To 13th floor

Sqm

2,154.01

541.67

1,166,773.55

680.78

1,466,404.23

461

992792.9

14

30156.2

132

284691.5

18.5

39861.3

55.2

118902.4

7.16

Half Brickwork I-Cl. In CM 1:4 13th To 14th floor

Sqm

1,820.04

545.52

992,877.74

684.74

1,246,262.44

461

838865.5

14

25480.6

136

247768.1

18.5

33681.0

55.2

100467.2

7.17

Half Brickwork I-Cl. In CM 1:4 14th To 15th floor

Sqm

1,818.29

549.49

999,132.85

688.83

1,252,490.24

461

838059.1

14

25456.1

140

254955.8

18.5

33648.6

55.2

100370.7

7.18

Half Brickwork I-Cl. In CM 1:4 15th To 16th floor

Sqm

1,776.00

553.57

983,144.81

693.03

1,230,826.36

461

818564.7

14

24864.0

144

256496.0

18.5

32865.9

55.2

98035.9

7.19

Half Brickwork I-Cl. In CM 1:4 16th To 17th floor

Sqm

1,168.69

557.78

651,870.44

697.37

815,003.73

461

538653.1

14

16361.6

149

173849.7

18.5

21627.3

55.2

64512.1

55.2

ITEM

DESCRIPTION

TENDER
DC RATE

TENDER
DC AMOUNT

PSE
RATE

Material

Sub Contractor

Plant Depric.

Plant Oprn & Fuel

QTY

Half Brickwork I-Cl. In CM 1:4 17th To 18th floor

Sqm

1,198.44

562.11

673,656.28

701.83

841,097.90

461

552364.5

14

16778.1

153

183623.3

18.5

22177.8

55.2

66154.3

7.21

Half Brickwork I-Cl. In CM 1:4 18th To 19th floor

Sqm

1,143.41

566.58

647,828.39

706.43

807,735.10

461

527002.9

14

16007.8

158

180448.1

18.5

21159.5

55.2

63116.8

7.22

Half Brickwork I-Cl. In CM 1:4 19th To 20th floor

Sqm

1,143.41

571.17

653,084.16

711.16

813,148.54

461

527002.9

14

16007.8

163

185861.5

18.5

21159.5

55.2

63116.8

7.23

Half Brickwork I-Cl. In CM 1:4 20th To 21st floor

Sqm

1,143.41

575.91

658,497.60

716.04

818,724.38

461

527002.9

14

16007.8

167

191437.4

18.5

21159.5

55.2

63116.8

7.24

Half Brickwork I-Cl. In CM 1:4 21st To 22nd floor

Sqm

1,143.41

580.78

664,073.45

721.06

824,467.50

461

527002.9

14

16007.8

172

197180.5

18.5

21159.5

55.2

63116.8

7.25

Half Brickwork I-Cl. In CM 1:4 22nd To 23rd floor

Sqm

1,143.41

585.81

669,816.57

726.23

830,382.92

461

527002.9

14

16007.8

178

203095.9

18.5

21159.5

55.2

63116.8

7.26

Half Brickwork I-Cl. In CM 1:4 23rd To 24nd floor

Sqm

1,143.41

590.98

675,731.98

731.56

836,475.80

461

527002.9

14

16007.8

183

209188.8

18.5

21159.5

55.2

63116.8

7.27

Half Brickwork I-Cl. In CM 1:4 24th To 25th floor

Sqm

1,143.41

596.31

681,824.86

737.05

842,751.46

461

527002.9

14

16007.8

188

215464.4

18.5

21159.5

55.2

63116.8

7.28

Half Brickwork I-Cl. In CM 1:4 25th To 26th floor

Sqm

1,143.41

601.80

688,100.52

742.70

849,215.39

461

527002.9

14

16007.8

194

221928.4

18.5

21159.5

55.2

63116.8

7.29

Half Brickwork I-Cl. In CM 1:4 26th To 27th floor

Sqm

1,143.41

607.45

694,564.45

748.53

855,873.24

461

527002.9

14

16007.8

200

228586.2

18.5

21159.5

55.2

63116.8

7.30

Half Brickwork I-Cl. In CM 1:4 27th To 28th floor

Sqm

1,143.41

613.27

701,222.30

754.52

862,730.83

461

527002.9

14

16007.8

206

235443.8

18.5

21159.5

55.2

63116.8

7.31

Half Brickwork I-Cl. In CM 1:4 28th To 29th floor

Sqm

1,143.41

619.27

708,079.89

760.70

869,794.14

461

527002.9

14

16007.8

212

242507.1

18.5

21159.5

55.2

63116.8

7.32

Half Brickwork I-Cl. In CM 1:4 29th To 30th floor

Sqm

1,143.41

625.45

715,143.20

767.06

877,069.36

461

527002.9

14

16007.8

218

249782.3

18.5

21159.5

55.2

63116.8

7.33

Half Brickwork I-Cl. In CM 1:4 30th To 31st floor

Sqm

1,143.41

631.81

722,418.42

773.62

884,562.83

461

527002.9

14

16007.8

225

257275.8

18.5

21159.5

55.2

63116.8

7.34

Half Brickwork I-Cl. In CM 1:4 31st To 32 floor

Sqm

593.50

638.36

378,869.25

780.37

463,148.88

461

273547.0

14

8309.0

232

137548.3

18.5

10983.1

55.2

32761.5

7.35

Half Brickwork I-Cl. In CM 1:4 32st To 33 floor

Sqm

158.94

652.07

103,636.52

787.32

125,133.19

461

73254.0

14

2225.1

239

37939.5

18.5

2941.2

55.2

8773.3

7.36

Half Brickwork I-Cl. In CM 1:4 33st To 34 floor

Sqm

65.64

659.23

43,268.74

794.48

52,146.20

461

30251.7

14

918.9

246

16137.9

18.5

1214.6

55.2

8.00

BRICK WORK
Providing and Laying Brickwork with 1st class bricks in foundation & in
superstructure
above plinth level, at all floor levels in Cement mortar 1:6 (1 cement : 6
coarse sand) for
walls as well as square and rectangular pillars laid in proper line & plumb
including
hacking of RCC at junctions, raking of joints, curing and all leads & lifts
complete to the
satisfaction of the Engineer. The rate is inclusive of providing arched /
curved openings at
all levels as per design/ drawings.

51,331.04

28,250,916.02

PSE AMOUNT

Labour

UOM

7.20

35,403,009.61
-

23,658,688

718,635

7,242,278

949,911

Wooden Shuttering

Steel Shuttering

Testing Charges

3623.1
2,833,497

8.01

Brickwork I-Class In CM 1:6 in Lower Basement to Upper Basement

Cum

916.75

3,101.50

2,843,312.49

3886.37

3,562,847.18

2575.0

2360641.5

120.0

110010.5

530.5

486292.2

160.9

147522.3

480.0

440045.6

20.0

18335.1

8.02

Brickwork I-Class In CM 1:6 in Upper Basement to Ground Floor

Cum

1,182.45

3,101.50

3,667,371.47

3870.92

4,577,175.40

2575.0

3044811.1

120.0

141894.1

515.0

608962.2

160.9

190277.8

480.0

567581.2

20.0

23649.0

8.03

Brickwork I-Class In CM 1:6 GF To 1st Floor

Cum

1,103.62

3,088.00

3,407,972.40

3855.92

4,255,465.12

2575.0

2841816.4

120.0

132434.2

500.0

551809.0

160.9

177592.2

480.0

529741.1

20.0

22072.4

8.04

Brickwork I-Class In CM 1:6 1st To 2nd floor

Cum

853.35

3,101.50

2,646,664.42

3870.92

3,303,250.68

2575.0

2197375.8

120.0

102402.0

515.0

439475.2

160.9

137319.5

480.0

409611.3

20.0

17067.0

8.05

Brickwork I-Class In CM 1:6 2nd To 3rd floor

Cum

742.79

3,115.41

2,314,080.80

3886.37

2,886,744.80

2575.0

1912675.3

120.0

89134.4

530.5

394011.1

160.9

119527.8

480.0

356540.5

20.0

14855.7

8.06

Brickwork I-Class In CM 1:6 3rd To 4th floor

Cum

718.01

3,129.73

2,247,174.99

3902.29

2,801,879.63

2575.0

1848875.4

120.0

86161.2

546.4

392294.4

160.9

115540.8

480.0

344647.6

20.0

14360.2

8.07

Brickwork I-Class In CM 1:6 4th To 5th floor

Cum

708.49

3,144.48

2,227,846.54

3918.68

2,776,361.41

2575.0

1824373.7

120.0

85019.4

562.8

398708.5

160.9

114009.6

480.0

340080.3

20.0

14169.9

8.08

Brickwork I-Class In CM 1:6 5th To 6th floor

Cum

608.54

3,159.67

1,922,791.58

3935.56

2,394,950.14

2575.0

1566993.7

120.0

73025.0

579.6

352733.1

160.9

97925.3

480.0

292102.3

20.0

12170.8

8.09

Brickwork I-Class In CM 1:6 6th To 7th floor

Cum

604.55

3,175.32

1,919,629.64

3952.95

2,389,739.71

2575.0

1556706.4

120.0

72545.5

597.0

360929.9

160.9

97282.4

480.0

290184.6

20.0

12090.9

8.10

Brickwork I-Class In CM 1:6 7th To 8th floor

Cum

592.38

3,191.44

1,890,562.80

3970.86

2,352,277.00

2575.0

1525391.1

120.0

71086.2

614.9

364279.4

160.9

95325.5

480.0

284347.1

20.0

11847.7

8.11

Brickwork I-Class In CM 1:6 8th To 9th floor

Cum

592.38

3,208.05

1,900,398.35

3989.31

2,363,205.38

2575.0

1525391.1

120.0

71086.2

633.4

375207.7

160.9

95325.5

480.0

284347.1

20.0

11847.7

8.12

Brickwork I-Class In CM 1:6 9th To 10th floor

Cum

592.38

3,225.15

1,910,528.96

4008.31

2,374,461.61

2575.0

1525391.1

120.0

71086.2

652.4

386464.0

160.9

95325.5

480.0

284347.1

20.0

11847.7

8.13

Brickwork I-Class In CM 1:6 10th To 11th floor

Cum

592.38

3,242.76

1,920,963.48

4027.88

2,386,055.53

2575.0

1525391.1

120.0

71086.2

672.0

398057.9

160.9

95325.5

480.0

284347.1

20.0

11847.7

8.14

Brickwork I-Class In CM 1:6 11th To 12th floor

Cum

592.38

3,260.91

1,931,711.05

4048.04

2,397,997.26

2575.0

1525391.1

120.0

71086.2

692.1

409999.6

160.9

95325.5

480.0

284347.1

20.0

11847.7

8.15

Brickwork I-Class In CM 1:6 12th To 13th floor

Cum

592.38

3,279.59

1,942,781.04

4068.80

2,410,297.25

2575.0

1525391.1

120.0

71086.2

712.9

422299.6

160.9

95325.5

480.0

284347.1

20.0

11847.7

8.16

Brickwork I-Class In CM 1:6 13th To 14th floor

Cum

583.42

3,298.84

1,924,596.62

4090.19

2,386,282.32

2575.0

1502296.6

120.0

70009.9

734.3

428383.1

160.9

93882.2

480.0

280042.1

20.0

11668.3

8.17

Brickwork I-Class In CM 1:6 14th To 15th floor

Cum

522.26

3,318.67

1,733,210.45

4112.22

2,147,651.76

2575.0

1344822.8

120.0

62671.4

756.3

394983.5

160.9

84041.3

480.0

250687.5

20.0

10445.2

8.18

Brickwork I-Class In CM 1:6 15th To 16th floor

Cum

489.65

3,339.09

1,634,969.47

4134.91

2,024,639.74

2575.0

1260838.2

120.0

58757.5

779.0

381426.2

160.9

78792.9

480.0

235032.0

20.0

9792.9

8.19

Brickwork I-Class In CM 1:6 16th To 17th floor

Cum

452.18

3,360.12

1,519,388.30

4158.28

1,880,301.57

2575.0

1164371.3

120.0

54262.0

802.4

362810.5

160.9

72764.5

480.0

217049.7

20.0

9043.7

8.20

Brickwork I-Class In CM 1:6 17th To 18th floor

Cum

475.44

3,381.78

1,607,818.35

4182.35

1,988,435.01

2575.0

1224246.0

120.0

57052.2

826.4

392911.1

160.9

76506.2

480.0

228210.9

20.0

9508.7

8.21

Brickwork I-Class In CM 1:6 18th To 19th floor

Cum

342.79

3,404.09

1,166,892.97

4207.14

1,442,169.13

2575.0

882686.7

120.0

41134.9

851.2

291789.3

160.9

55161.3

480.0

164541.0

20.0

6855.8

8.22

Brickwork I-Class In CM 1:6 19th To 20th floor

Cum

342.79

3,427.08

1,174,771.28

4232.68

1,450,922.81

2575.0

882686.7

120.0

41134.9

876.8

300543.0

160.9

55161.3

480.0

164541.0

20.0

6855.8

8.23

Brickwork I-Class In CM 1:6 20th To 21st floor

Cum

342.79

3,450.75

1,182,885.94

4258.98

1,459,939.10

2575.0

882686.7

120.0

41134.9

903.1

309559.3

160.9

55161.3

480.0

164541.0

20.0

6855.8

8.24

Brickwork I-Class In CM 1:6 21st To 22nd floor

Cum

342.79

3,475.13

1,191,244.04

4286.07

1,469,225.88

2575.0

882686.7

120.0

41134.9

930.1

318846.1

160.9

55161.3

480.0

164541.0

20.0

6855.8

8.25

Brickwork I-Class In CM 1:6 22nd To 23rd floor

Cum

342.79

3,500.25

1,199,852.89

4313.97

1,478,791.27

2575.0

882686.7

120.0

41134.9

958.1

328411.5

160.9

55161.3

480.0

164541.0

20.0

6855.8

8.26

Brickwork I-Class In CM 1:6 23rd To 24th floor

Cum

342.79

3,526.11

1,208,720.00

4342.72

1,488,643.61

2575.0

882686.7

120.0

41134.9

986.8

338263.8

160.9

55161.3

480.0

164541.0

20.0

6855.8

8.27

Brickwork I-Class In CM 1:6 24th To 25th floor

Cum

342.79

3,552.76

1,217,853.12

4372.32

1,498,791.52

2575.0

882686.7

120.0

41134.9

1016.4

348411.7

160.9

55161.3

480.0

164541.0

20.0

6855.8

8.28

Brickwork I-Class In CM 1:6 25th To 26th floor

Cum

342.79

3,580.20

1,227,260.24

4402.81

1,509,243.88

2575.0

882686.7

120.0

41134.9

1046.9

358864.1

160.9

55161.3

480.0

164541.0

20.0

6855.8

8.29

Brickwork I-Class In CM 1:6 26th To 27th floor

Cum

342.79

3,608.47

1,236,949.57

4434.22

1,520,009.80

2575.0

882686.7

120.0

41134.9

1078.3

369630.0

160.9

55161.3

480.0

164541.0

20.0

6855.8

8.30

Brickwork I-Class In CM 1:6 27th To 28thfloor

Cum

342.79

3,637.58

1,246,929.58

4466.57

1,531,098.70

2575.0

882686.7

120.0

41134.9

1110.6

380718.9

160.9

55161.3

480.0

164541.0

20.0

6855.8

8.31

Brickwork I-Class In CM 1:6 28th To 29th floor

Cum

342.79

3,667.57

1,257,208.99

4499.89

1,542,520.27

2575.0

882686.7

120.0

41134.9

1144.0

392140.5

160.9

55161.3

480.0

164541.0

20.0

6855.8

ITEM

DESCRIPTION

UOM

TENDER
DC RATE

QTY

TENDER
DC AMOUNT

PSE
RATE

Material

PSE AMOUNT

Labour

Sub Contractor

Plant Depric.

Plant Oprn & Fuel

Wooden Shuttering

Steel Shuttering

8.32

Brickwork I-Class In CM 1:6 29th To 30th floor

Cum

342.79

3,698.45

1,267,796.78

4534.20

1,554,284.48

2575.0

882686.7

120.0

41134.9

1178.3

403904.7

160.9

55161.3

480.0

164541.0

20.0

6855.8

8.33

Brickwork I-Class In CM 1:6 30th To 31st floor

Cum

342.79

3,730.27

1,278,702.21

4569.55

1,566,401.62

2575.0

882686.7

120.0

41134.9

1213.6

416021.8

160.9

55161.3

480.0

164541.0

20.0

6855.8

8.34

Brickwork I-Class In CM 1:6 31st To 32 floor

Cum

298.00

3,763.04

1,121,384.77

4605.96

1,372,576.78

2575.0

767350.0

120.0

35760.0

1250.0

372512.0

160.9

47953.6

480.0

143041.2

20.0

5960.0

8.35

Brickwork I-Class In CM 1:6 32nd To 33 floor

Cum

249.00

3,796.79

945,400.02

4643.46

1,156,222.42

2575.0

641175.0

120.0

29880.0

1287.5

320597.8

160.9

40068.6

480.0

119521.0

20.0

4980.0

8.36

Brickwork I-Class In CM 1:6 33nd To 34 floor

Cum

177.00

3,831.55

678,184.50

4682.09

828,729.89

2575.0

455775.0

120.0

21240.0

1326.2

234731.7

160.9

28482.5

480.0

84960.7

20.0

3540.0

8.37

Brickwork I-Class In CM 1:6 34th To 35 floor

Cum

95.00

3,867.36

367,398.95

4721.87

448,578.11

2575.0

244625.0

120.0

11400.0

1366.0

129765.5

160.9

15287.2

480.0

45600.4

20.0

18,791.08

62,083,209.03

76,978,167.76
-

10.00 MISC. (STRUCTURE)


10.01

Providing, fabricating and fixing / erection M.S. structural work (like drain
cover,
sleeves, toilet / kitchen counter support angle, fresh air duct grill DG
exhaust grill)
fabricated from standard sections e.g. M.S. Angles, , Plates ,Rolled
Sections such as
Channels, Flats, Joists etc. including cutting to size, drilling, welding ,
providing and
applying a coat of red oxide primer, chipping of RCC& cost of nuts & bolts
but

10.02

a
b
c
d
e
10.03

a
b
c

10.04

10.05

a
b
c
10.06

0.01

Wash Basin
Kitchen Sink
Kitchen Counter
200 & 300 wide Perforated MS grating - open & closed
MS Railing in Elevation - behind GRC Jaali
5mm thk 50mm wide MS Plate - cutout closing Grills in ground floor
MS Grating as/vendor - Helipad Level
MS Grill over Plumbing Shaft

Kg
Kg
Kg
Rmt
Rmt
Sqm
Sqm
Sqm

Kg
Kg
Rmt
Rmt
Rmt

0.02

70.05
72.05
72.05
74.05
2,500.00
2,943.75
3,532.50
2,300.00

Providing & fixing PVC water bar of approved quality & make 305mm wide
and 6mm
thick (maruti brand ISI marks) with ribs interspersed with serrations on each
face in
straight length including accessories and fixing all complete as per
manufacturer's
instructions.
All charges for providing and fixing of "Supreme Industries Make"Silfil
Armour Board
of Dawn (Pinkish Type) colour, Thickness Build up using minimum 10mm
specifically
extruded high performance sheet, minimum density of
28kg/Cum,compression strength
of 0.21Kg/Sqm and Water Absorption is 0.45Maximum Kg/Sqm (Tested as
per
ASTM-D3575) complete to the satisfaction of Engg. In charge.
Between Retaining wall
Between Tower & Non Tower
Between Tower C2 & C3 and D1 & D2
Providing 200 mm dia pipe sleeve (PVC) in lift pit raft including boring
200mm dia hole
to required depth (7.5m), providing & lowering 150mm dia plain as well as
perforated
PVC pipe all complete, providing & filling pea gravel all around the pipe, as
per drawing
and to the satisfaction of Engineer.

Providing & fixing 800mm and 18 gauge GI sheet on expension joint with
12mm dia &
100mm long dashfastner @600c/c. one side fix and other side free bby
sloted hole. As
per drawing complete.

10.06 Providing & Filling Polysulphide Sealant of size 10MM deep &
25mm wide in Expansion Joints including Providing & Fixing

229.20

70.05
72.05
2,000.00
3,500.00
2,700.00

Rm
Rm
Rm

922,182.89
297,240.64
279,921.74
103,671.40
851,581.61
908,417.70
1,826,627.80

70.05
72.05
72.05
74.05
2943.75
3532.50
2300.00

922,169.72
297,236.51
279,917.85
103,670.00
851,581.61
908,417.70
1,826,627.80
-

70.1
72.1
72.1
74.1

922169.7
297236.5
279917.9
103670.0

2943.8
3532.5
2300.0

851581.6
908417.7
1826627.8

1,138.96
329.13
52.67

1,950.00
2,850.00
3,150.00

1,677,721.45
19,752,997.80
618,840.00
-

70.50
72.05

2700.00

1,688,475.00
19,752,723.65
618,840.00
-

70.5
72.1

1688475.0
19752723.7

2700.0

618840.0

2,220,972.00
938,020.50
165,910.50

1950.00
2850.00
3150.00

2,220,972.00
938,020.50
165,910.50
-

1950.0
2850.0
3150.0

2220972.0
938020.5
165910.5

350.0

2810150.0

562.0
677.5
793.0

17422.0
193765.0
831064.0

550.0

15950.0

325.5
325.5

34409.6
582468.5

834.8

158354.0

Rmt

8,029.00

350.00

2,810,150.00

350.00

2,810,150.00
-

Sqm
Sqm
Sqm

31.00
286.00
1,048.00

562.00
677.50
793.00

17,422.00
193,765.00
831,064.00

562.00
677.50
793.00

17,422.00
193,765.00
831,064.00
-

No.

Providing and fixing 300mm wide and 18G (1.25MM) thick GI sheet with
vertical raised
notches @ 300mm c/c for covering the expension joint upto GF including
fixing the
sheet by drilling holes & providing & fixing dash fastener of 10mm dia,
100mm long 'on

Retaining wall every 100m c/c - vertical


Between tower and Non Tower periphery

23,950.00
274,153.00

29.00

550.00

15,950.00

550.00

Rm
Rm

105.70
1,789.24

325.54
325.54

34,409.05
582,459.59

325.54
325.54

189.70

34,409.58
582,468.54
-

Rmt

15,950.00
-

both side @ 300mm c/c including providing adequate overlaps as required.


a
b

13,164.45
4,125.42
3,885.05
1,400.00
289.28
257.16
794.19

Providing & fabricating & fixing MS pipe (Class-A) sleeves (3.2 mm thick) in
structure
members complete as specified, including leaving the sleeve free of mortar,
slurry or
any foreign matter.
65mm dia
80mm dia
100mm dia

13,916,750

Item same as S.No. 10.01 but for hollow tubular sections only and without
any enamel
Paint for MS railing staircase, balcony and Elevation
MS Railing in Staircase & stair elevation - 3mm tk. section
MS Railing in Balcony - 3mm tk. Section
MS Railing in Staircase
MS Railing in Balcony
MS Railing in Elevation

2,254,930

excluding the cost of providing &fixing dash fastener, complete as directed.


a
b
c
d
e
f
g
h

48,387,043

834.76

158,353.97

834.76

158,353.97
-

3,023,826

9,019,796

Testing Charges

1900.0
375,822

ITEM

DESCRIPTION

UOM

TENDER
DC RATE

QTY

TENDER
DC AMOUNT

PSE
RATE

(1.25MM) thick GI sheet with vertical raised notches @ 300mm c/c for

covering the expansion joint in elevation including fixing the sheet


by drilling holes & providing & fixing dash fastener of 10mm dia,

100mm long 'on both side @ 300mm c/c including providing adequate
overlaps as required.
10.07

d
e

Providing & Filling Polysulphide Sealant in Expansion Joints including


cleaning the
surface thoroughly, providing & applying primer, tooling the polysulphide to
correct
profile as specified.
50mm wide x 25mm deep
60mm wide x 30mm deep

10.09

10.10

179.07

1,294.38

231,789.24

1294.38

10.11

a
b
c

9.13

a)
b)
c)
d)

231,790.13
-

1,098.32
-

700.00
1,000.00

768,825.46

700.00

768,825.46
-

OD + 400mm ) The pipe is projected 150mm from one side and 200mm

from other side of wall. The pipe shall be threaded for pipe of dia less

then 65mm and flanges on both side shall be welded for dia 65mm and

above complete, including leaving the puddle flanges free of mortar, slurry
or
any foreign matters & providing puncture in shuttering for pipes
25mm dia. Pipe
50mm dia. Pipe
65mm dia. Pipe
80mm dia. Pipe
100mm dia. Pipe
150mm dia. Pipe
200mm dia. Pipe
250mm dia. Pipe

Nos.
Nos.
Nos.
Nos.
Nos.
Nos.
Nos.
Nos.

14.00
12.00
3.00
3.00
29.00
7.00
4.00
6.00

1,000.00
1,200.00
1,500.00
2,000.00
2,500.00
4,000.00
5,000.00
6,500.00

Providng and fixing poly propylene caoted MS foot rests in


concrete/masonry
walls as specified & pattern.

Each

297.00
-

283.75

84,273.75
-

Wooden Shuttering

Steel Shuttering

Testing Charges

1294.4

231790.1

700.0

768825.5

1000.0
1200.0
1500.0
2000.0
2500.0
4000.0
7000.0
10000.0

14000.0
14400.0
4500.0
6000.0
72500.0
28000.0
28000.0
60000.0

283.8

84273.8

700.0
450.0

768600.0
310950.0

20.0
25.0
30.0
40.0

1695540.0
1461450.0
301710.0
505120.0
41573805.28

283.75

Nos
Nos
Nos

RM
RM
RM
RM

84,273.75
-

Rmt
Rmt

14,000.00
14,400.00
4,500.00
6,000.00
72,500.00
28,000.00
28,000.00
60,000.00
-

1,098.00
691.00
-

700.00
450.00

768,600.00
310,950.00
-

700.00
450.00

768,600.00
310,950.00
-

140.00
200.00
350.00

Providing and fixing in position the following heavy duty ISI marked PVC
conduit including all accessories (i.e clamps, nuts,bolts, bends, junction
boxes, pull boxes etc.) concealed or exposed as called for including
necessary civil work such as chase cutting & making good in all respect as
the case may be:

TOTAL

14,000.00 1000.00
14,400.00 1200.00
4,500.00 1500.00
6,000.00 2000.00
72,500.00 2500.00
28,000.00 4000.00
20,000.00 7000.00
39,000.00 10000.00
-

Providing & Fixing PVC Sleeve / Pipe in walls 63mm (O/D) for AC Piping
Provision in
all flats including fixing with cement mortar and making plaster all around
groove
complete as per insrruction of Engg. Incharge

20mm dia.
25mm dia.
32mm dia.
40mm dia

Plant Oprn & Fuel

Providing and filling Polysulphide Sealant of following sizes in expansion


joints
including cleaning the joints, providing & applying primer prior to application
of

Fire Fighting
65mm Dia
80mm Dia
100mm Dia

Plant Depric.

Rmt
Rmt

members including welding of 6mm thick Square M S Plate of size (pipe

50mm wide and 25mm deep


25mm wide and 12mm deep

Sub Contractor

polysulphide to ensure proper bond with concrete surface.(Made-Chokesy)


a
b

Labour

Rmt

10.08 Providing, fabricating & fixing C Class MS puddle flange in structure

a
b
c
d
e
f
g
h

Material

PSE AMOUNT

25MM dia backer rod & providing and fixing 300mm wide and 18G

84,777.00
58,458.00
10,057.00
12,628.00

55.00
75.00
100.00
125.00

4,662,735.00
4,384,350.00
1,005,700.00
1,578,500.00
49,201,803.09

4,577,958.00
4,325,892.00
995,643.00
1,515,360.00
49024838.28

1248703863.28

1319666276.26

54.00
74.00
99.00
120.00

34.0
49.0
69.0
80.0

2882418.0
2864442.0
693933.0
1010240.0
7451033.00
842429886.00

9875006.60

249735652.20

53887313.71

61306834.54

37980756.09

60698199.02

3752628.09

THE PRIMUS (SEC - 82 A) DLF TOWNSHIP PROJECT IN NEW GURGAON FINISHING BOQ

DLF GH Project 'The Primus' Sector-82A

TILE & PAINTING


ITEM

DESCRIPTION

UOM

QTY

Sqm
Sqm
Sqm
Sqm

14115
8650
2882
1276

TENDER
DC RATE

1.34
TENDER
DC AMOUNT

SPCL RATE

SPCL AMOUNT

PSE
RATE

1681.00
1679.00
1698.00
1679.00

23726777.08
14523853.70
4894315.20
2141564.50

1302.00
1292.00
1296.00
1302.00

Material

PSE AMOUNT

Labour

Sub Contractor

Plant Depric.

TILING / MARBLE CHIPS FLOORING


1.00 Providing & Laying of Antiskid Vitrified tiles of 1st quality confirming to IS 15622
of specified size & colour on floors inclusive of cleaning of surface, curing of surface
, wetting of tiles, cutting of edges (with high quality diamond edge cutting blades of
approved make) wherever required (i/c holes/ cutout for drains), fixing true to proper
line , levels and slope as per approved design on floors over a 30-35 mm thick bed of
1: 4 cement sand mortar . The joints to be cleaned, filled and flushed with white
cement using pigment to match the shade of tile as required as per instructions and
complete satisfaction of the Engineer.
1.01
1.02
1.03
1.04

300 x 300 Anti-skid Vitrified tiles, 8mm thick- All Balcony


600 x 600 Anti-skid Vitrified tiles, 8mm thick- Kitchen ,Toilets.
300 x 900 Anti-skid Vitrified tiles, 8mm thick- M. Toilet
300x300 Vitrified tiles, 8mm thick(S.room)

1254.00
1253.00
1267.00
1253.00

17699808.72
10838825.90
3652000.80
1598201.50

18,377,313.36
11,176,187.60
3,735,590.40
1,660,701.00
-

960.0
950.0
954.0
960.0

13,550,093
8,217,785
2,749,810
1,224,480
-

1.05 Providing and Laying POP Protection with 200 micron polythene sheet to vetrified tiles

flooring in S. Room till handing over. The item shall be operated only on instruction of

the Engineer In Charge and complete with removing the malba from site.

Sqm

1276

40

51020.00

54.00

68877.00

50.00

63,775.00
-

2.00 Providing & Laying of Ceramic tiles of 1st quality confirming to IS 15622, of
specified size & colour on Floors inclusive of cleaning of surface, curing of surface ,
wetting of tiles, cutting of edges (with high quality diamond edge cutting blades of

40.0

51,020
-

342.0
342.0
342.0
342.0

4,827,221
2,958,403
985,781
436,221
-

10.0

12,755
-

approved make) wherever required (i/c holes/ cutout for drains), fixing true to proper

line , levels and slope as per approved design on floors over 20 mm thick bed of 1:

4 cement sand mortar . The joints to be cleaned, filled and flushed with white cement

using pigment to match the shade of tile as required as per instructions and to the
complete satisfaction of the Engineer.
2.01 300 x 300 antiskid ceramic tiles, 8mm thick - S.Toilet

Sqm

374

1058

395226.48

1418.00

529708.08

1219.00

3.00 Providing & Laying of Antiskid Vitrified tiles of 1st quality confirming to IS 15622 of

455,369.64
-

877.0

327,612
-

342.0

127,758
-

specified size & colour in skirting inclusive of cleaning of surface, curing of surface ,

wetting of tiles, cutting of edges (with high quality diamond edge cutting blades of

approved make) fixing true to proper line , levels and slope as per approved design on

floors over a 12 mm thick bed of 1: 3 cement sand mortar . The joints to be cleaned,

filled and flushed with white cement using pigment as required as per instructions and

to the complete satisfaction of the Engineer.


3.01 140 mm high Anti-skid Vitrified tiles, 8mm thick - skirting in balcony
3.02 Item same as above but 75mm high skirting - S.room.

Rmt
Rmt

20148
1444

191.82
145.28

3864829.64
209841.02

257.00
195.00

5178089.97
281665.80

198.68
130.45

4,003,046.36
188,427.20
-

4.00 Providing & Fixing of Vitrified / Ceramic tiles of 1st quality confirming to IS 15622, of

134.4
72.0

2,707,919
104,000
-

64.3
58.5

1,295,127
84,428
-

specified size & colour on walls/dado inclusive of cleaning of surface, curing of


surface, wetting of tiles, cutting of edges (with high quality diamond edge cutting

blades of approved make) wherever required, (i/c holes/ cutout for electrical boxes &

sanitary fixtures), fixing in proper line, true to levels and plumb. Over 12mm thick cement

mortar in 1: 3 cement sand mortar and jointing with grey cement slurry @ 3.3 kg/sqm

including pointing (joints to be cleaned filled and flushed) with white cement using

pigment as required as per instructions and to the complete satisfaction of the Engineer.

4.01 Ceramic Wall Tiles of 300 x 600 size, 6mm thick - Kitchen & Toilets
4.02 Porcelain Vitrified Wall Tiles of 300 x 900 size, 6mm thick - M.Toilet
4.03 Ceramic Wall Tiles of 300 x 300 size, 6mm thick - S.Toilet

Sqm
Sqm
Sqm

22434
7856
1329

1165
1533
1058

26135959.50
12043217.34
1406060.84

1561.00
2055.00
1418.00

35019942.30
16144038.90
1884493.64

1221.00
1602.00
1236.00

27,392,280.30
12,585,279.96
1,642,619.28
-

Providing & laying 25 mm average thick Kota stone on treads of steps & landings in
staircase, laid on 20 mm thick cement mortar 1:4 (1 cement 4 coarse sand) and jointed
5.00 with grey cement slurry mixed with pigment to match the shade of the flooring, including
rubbing and Polishing complete as per the satisfaction to engineer in charge.
At all floor levels including all lead and lifts.
5.01 Single piece in treads of stairscase
5.02 In landings of staircase

Sqm
Sqm

1965
2283

1,221
1,105

2399473.41
2523573.84

1636.00
1481.00

3215132.64
3381685.78

1696.05
1186.69

3,333,147.97
2,709,656.57
-

SQM

1323

178

234915.93

238.00

314985.86

189.70

251,062.26
-

6.00 Providing and laying IPS in riser of staircase, 12/15mm thick in 1:3 (1 cement
3 coarse sand) & finished with neat cement slurry complete as directed by Engineer in
charge at all floor levels.

Rmt

6502

161

1049831.74

216.00

1404494.64

208.97

1,358,751.91

Page 23 of 71

19,338,367
9,764,983
1,165,515
-

359.0
359.0
359.0

677.7
677.7

1,331,817
1,547,416
-

89.7

118,715
-

Providing & laying 20 mm average thick Kota stone in skirting laid on 12 mm thick cement
mortar 1:3 (1 cement 3 coarse sand) and jointed with grey cement slurry mixed with
7.00 pigment to match the shade of the stone, including rubbing and Polishing complete in all
respect as per the satisfaction of Engineer in charge. At all floor levels including all lead
and lifts.
100 mm high skirting in steps profile of staircase

862.0
1243.0
877.0

1018.4
509.0

2,001,331
1,162,240
-

100.0

132,347
-

8,053,914
2,820,297
477,104
-

209.0

1,358,752

Plant Oprn & Fuel

Wooden Shuttering

Steel Shuttering

Testing Charges

THE PRIMUS (SEC - 82 A) DLF TOWNSHIP PROJECT IN NEW GURGAON FINISHING BOQ
TILE & PAINTING
ITEM

DESCRIPTION

UOM

QTY

TENDER
DC RATE

1.34
TENDER
DC AMOUNT

SPCL RATE

SPCL AMOUNT

PSE
RATE

Material

PSE AMOUNT
-

84102787

88933209

PAINTING WORKS

1.00

Providing & applying two or more coats of Snowcem paint in shafts at all levels, of
approved shade to give an even shade including surface cleaning / preparation, curing all
complete to the satisfaction of Engineer in charge / recommendation by manufacturer
including erection and dismantling of scaffolding ,working platform etc.

Providing & applying White wash with lime, two or more coats at all floor levels to give an
even shade including cleaning & preparation of surface , providing & mixing DDL binder or
2.00 any other adhesive/glue as approved, pigment as specified including ,erection and
dismantling of scaffolding ,working platforms as necessary complete to the satisfaction of
the Engineer. Nothing extra shall be payable for repairing & touch-ups till handing over.

SQM

20663

90

1859694.30

121.00

2500255.67

90.00

1,859,694.30
-

90.0

1,859,694
-

SQM

126372

35

4423004.60

47.00

5939463.32

35.00

4,423,004.60

35.0

4,423,005

SQM

22489

70

1574240.50

94.00

2113980.10

75.00

1,686,686.25

SQM

9474

100

947430.00

134.00

1269556.20

100.00

SQM

7281

130

946592.40

174.00

1266977.52

130.00

SQM

245862

120

29503468.80

161.00

39583820.64

120.00

947,430.00

SQM

109088

125

13636032.50

168.00

18326827.68

125.00

946,592.40

9.00

100.0

947,430

130.0

946,592

120.0

13,636,032.50

1,686,686

29,503,468.80

Providing & painting two or more coats of Exterior grade Texture Paint in trowel finish, on
External surface upto 4th floor lvl. of approved colour, make & shade, to give an even
8.00 shade including surface cleaning & preparation, and one coat of primer as base,curing as
per instructions of the Engineer/ recommendation by manufacturer including erection and
dismantling of scaffolding, working platforms etc all complete.

75.0

Providing & applying 2 or more coats of ICI - Weathershield , over one coat of Primer. on
External surface at all floor levels of approved shade to give an even shade, including
surface cleaning / preparation, curing as per instructions of the Engineer
/Recommendation by manufacturer including erection and dismantling of scaffolding
7.00
,working platform etc. Nothing extra shall be payable for repairing & touchups till handing
over.The work shall be carried out by authorised applicator of the manufacturer which is
aggreable to the owner. Warranty for 5 years shall be submitted by both Manufacturer &
the applicator thru, civil contractor.

Providing & applying Acrylic Emulsion paint of approved brand and shade, two or more
coats at all floor levels on new plastered surface to give an even shade including cleaning
& preparation of surface(excluding the cost of POP punning/Birla Putty), one coat of
6.00 primer including erection and dismantling of scaffolding, working platforms as necessary
complete to the satisfaction of Engineer / recommendation by manufacturer. Berger or
equivalent. Nothing extra shall be payable for repairing & touch-ups till handing over. Note
that the birla putty for this quantity shall be paid separately.

26733677

Providing & applying Flat Oil Paint of approved brand and shade with two or more coats on
staircase walls upto 1.10 m height at all floor levels to give an even shade including
cleaning & preparation of surface , applying putty and one coat of primer including
5.00
erection and dismantling of scaffolding , working platforms as necessary complete to the
satisfaction of the Engineer. Nothing extra shall be payable for repairing & touch-ups till
handing over.

Plant Depric.
-

62199532

Providing & applying Synthetic Enamel Paint of approved manufacturer, two or more
coats on concrete / plastered surfaces in parking area in basements (up to 1.10 m height
from FFL) to give an even shade, including cleaning & preparation of surface, applying
4.00
putty, one coat of cement primer and shifting of material from store to work place ,
complete to the satisfaction of the Engineer / recommendation by manufacturer .Nothing
extra shall be payable for repairing & touch-ups till handing over.

Sub Contractor

Providing & applying Oil Bound Distemper of approved brand and shade with two or more
coats at all floor levels (staircase, s.room, stilt floor utility areas ) to give an even shade
including cleaning & preparation of surface, applying putty, one coat of cement primer
3.00
and including erection and dismantling of scaffolding , working platforms as necessary
complete to the satisfaction of the Engineer. Nothing extra shall be payable for repairing &
touch-ups till handing over.

Labour
-

29,503,469

125.0

13,636,033

Nothing extra will be payable for repairing & touchups till handing over.

SQM

17389

250

4347145.00

335.00

5825174.30

250.00

4,347,145.00
-

250.0

4,347,145
-

Making 10mm x 15mm wide groove in proper line and level in external plaster at all floor
levels of building elevation.

Rmt

1268

15

19012.50

20.00

25350.00

15.00

19,012.50

15.0

19,013

1045.0

198,681

Making 150mm high & 175mm thick RCC Band including the cost of shuttering, scaffolding
10.00 & RCC in external elevation of buildings at 4th floor level complete to the satisfaction of
engineer in charge.

Sqm

190

1,045

198711.48

1401.00

266365.13

1045.00

198,680.63

Providing & Fixing Dholpur Stone 40 mm thick & 300 mm wide in coping at parapet wall,
laid on 20 mm thick cement mortar 1:4 (1 cement 4 coarse sand) and jointed with white
11.00
cement slurry mixed with pigment to match the shade of the stone including rubbing and
polishing complete as per the satisfaction to engineer in charge.

Rmt

1489

500

744304.76

670.00

997362.00

500.00

744,304.76

Providing & applying synthetic enamel paint, two or more coats on MS Railing of Staircase
& balcony at all floor levels to give an even shade, including cleaning & preparation of
12.00 surface, and shifting of material from store to work place ,erection and dismantling of
scaffolding ,working platforms as necessary complete to the satisfaction of the Engineer.
Nothing extra shall be payable for repairing & touch-ups till handing over.

Sqm

9293

100

929291.00

134.00

1245249.94

100.00

929,291.00

Providing & applying Duco paint two or more coats on wood work to give an even shade,
13.00 including one coat of priming coat, cleaning, & preparation of surface, applying putty as
necessary complete to the satisfaction of the Engineer .

Sqm

23659

600

14195558.40

804.00

19022048.26

600.00

14,195,558.40

Page 24 of 71

310.0

461,471

190.0

100.0

929,291

600.0

14,195,558

282,834

Plant Oprn & Fuel

Wooden Shuttering

Steel Shuttering

Testing Charges

THE PRIMUS (SEC - 82 A) DLF TOWNSHIP PROJECT IN NEW GURGAON FINISHING BOQ
TILE & PAINTING
ITEM

DESCRIPTION

Providing & Applying 6 mm thick POP (super fine quality) punning on walls, making in
14.00
proper line and levels for smooth finish in internal walls complete.

TENDER
DC RATE

1.34
TENDER
DC AMOUNT

181523

115

64366

40

UOM

QTY

Sqm

Sqm

SPCL RATE

SPCL AMOUNT

PSE
RATE

PSE AMOUNT

20875099.00

154.00

27954480.40

115.00

20,875,099.00

2574654.40

54.00

3475783.44

40.00

2,574,654.40

Material

15.00

Providing & applying one coat of Birla/Spontax putty on internal ceilings of apartments for
all floor lvl. Including the cost of scaffolding, working platform & safety arrangement.

Providing & applying two or more coats of Snowcem paint in Stilt Floor external faces of
room & Columns , of approved shade to give an even shade including surface cleaning /
16.00 preparation, curing all complete to the satisfaction of Engineer in charge /
recommendation by manufacturer including erection and dismantling of scaffolding
,working platform etc.
Sqm

634

70

44356.90

94.00

59564.98

96818597
TOTAL

180,921,383

90.00

Plant Depric.

20,875,099

40.0

2,574,654

185,876,894

90.0

461471
62,661,003

Plant Oprn & Fuel

Wooden Shuttering

Steel Shuttering

Testing Charges

57,030.30

Page 25 of 71

Sub Contractor
115.0

96943685
242,581,885

Labour
-

57,030
96482214

123,215,891

THE PRIMUS (SEC - 82 A) DLF TOWNSHIP PROJECT IN NEW GURGAON


FINISHING BOQ

DLF GH P0ject 'The Primus' Sector-82A

ITEM

DESCRIPTION

Finishes

1.34

UOM

QTY

TENDE
R DC
RATE

TENDER
DC AMOUNT

SPCL
RATE

SPCL AMOUNT

PSE
RATE

PSE AMOUNT

Material

Labour

Sub Contractor

Plant Depric.

Plant Oprn & Fuel

Wooden Shuttering

Steel Shuttering

Testing Charges

PLASTERING
1.00

Providing and applying 6 mm thick cement plaster to ceiling in cement mortar 1:3 (1
cement : 3 fine sand) at all floor levels, finished smooth in line &
level including hacking of RCC surfaces, making groove at the junction of ceiling &
wall and curing, all lead and lifts including scaffolding all complete to the satisfaction
of the Engineer.

SQM

66015

152

10034343.38

204.00

13467145.07

196.00

12,939,021.73

41.0

2.00

Providing and applying 12/15mm thick cement plaster on wall/ columns in cement
mortar 1:6 (1cement : 2 coarse sand : 4 fine sand) at all floor levels, finished smooth in
line & level including hacking of RCC surfaces and curing, all lead and lifts including
scaffolding all complete to the satisfaction of the Engineer.

SQM

253506

159

40307404.71

213.00

53996711.97

221.00

56,024,757.49

66.0

3.00

Providing and applying 18mm thick cement plaster (external elevation, open
voids/shafts) on flat/curved surface in two coats, under layer of 12mm thickness in
cement plaster 1:5 (1cement:5 coarse sand) and top layer 6mm thickness in cement
plaster 1:6 (1cement: 3 fine sand:3coarse sand ) mixing of cico no. 1 water proofing
agent in cement mortar @ 2% by weight of cement, at all floor levles, making drip
course, edges, hacking of RCC surface and curing, all lead & lifts including scaffolding
all complete to satisfaction of the Engineer.

Sqm

94358

293

27646838.33

393.00

37082619.33

382.00

36,044,683.42

90.0

4.00

Providng & applying cement plaster on balcony bottom rail, toe wall, top rail,
coloum, making of nib, patta etc complete as per Engineer in charge.

Nos.

2840

900

2556000.00

1206.00

3425040.00

900.00

2,556,000.00

5.00

Providing and applying 6 mm thick cement plaster to soffit / ceiling of balcony in


cement mortar 1:3 (1 cement : 3 fine sand) at all floor levels,
finished smooth in line & level including hacking of RCC surfaces, making groove at
the junction of ceiling & wall and curing, all lead and lifts including scaffolding all
complete to the satisfaction of the Engineer.

Sqm

16817

157

2640243.88

210.00

3531536.40

196.00

3,296,100.64

5.02

10mm x 10mm wide groove in plaster of Balcony

Rmt

18538

15

278064.00

20.00

370752.00

15.00

278,064.00

5.03

40mm x 10mm drip course in plaster of Balcony

Rmt

15576

20

311520.00

27.00

420552.00

20.00

311,520.00

5.04

40mm x 15mm drip course in plaster of Balcony

Rmt

2713

20

54268.00

27.00

73261.80

20.00

54,268.00

6.00

Providing and fixing 22 gauge 18 mm size G I chicken wire mesh of approved widths
at junction of concrete and brick work, on the base layer of double coat plaster and
other locations called for including necessary laps and "U" shape galvanized wire nail
complete as specified and as per the direction of the Engineer In charge. The rate shall
be for all heights floors, lead and lift and shall cater for all labour , material, tools &
tackles and any other cost required for the successful completion of work.

RM

133219

16.6

2211433.74

22.00

2930815.80

15.60

2,078,214.84

12.6

7.00

Providing and applying 12/15mm thick cement plaster on wall/ columns of closed
shafts in cement mortar 1:6 (1cement : 2 coarse sand : 4 fine sand) at all floor levels,
finished smooth in line & level including hacking of RCC surfaces and curing, all lead
and lifts including scaffolding all complete to the satisfaction of the Engineer in charge.

Sqm

51752

159

8228634.78

213.00

11023265.46

221.00

11,437,284.82

66.0

8.00

Making 5mm x 5mm groove in plasters in Toilets

Rmt

8330

15

124942.50

20.00

166590.00

15.00

124,942.50

9.00

Making 4mm x 4mm groove in plasters in Toilets

Rmt

7802

18

140433.48

24.00

187244.64

18.00

140,433.48

10.00

Making 5mm x 5mm "V" groove in plasters in all Lift lobby

Rmt

3204

20

64081.40

27.00

86509.89

20.00

64,081.40

11.00

Making 3mm x 3mm groove in plaster in Toilets

Rmt

127

22

2796.20

29.00

3685.90

22.00

2,796.20

12.00

Applying neat cement finish in EWS Toilets

sqm

679

140637.83

277.00

188171.64

232.65

158,043.17

207

94741642

SUBTOTAL

41.0

86.0

125510212

CEMENT CONCRETE FLOORING/ SKIRTING


1.00

Providing and laying of 40 mm thick Cement concrete flooring 1:2:4 ( 1 cement : 2


coarse sand : 4 graded stone aggregate of 12.5 mm nominal size ) in flooring including
fixing of 40 x 4 mm size glass strips of required size at 1.2m c/c both ways part thereoff
as required and finished with a floating coat of neat cement to achieve extra smooth &
levelled surface to receive laminated wooden flooring at all floor levels as directed by
Engineer-in-Charge.

Sqm

28830

290

8360811.65

389.00

11215019.77

316.30

9,119,050.78

226.3

2.00

Providing and laying 75 mm thick Cement concrete flooring 1:2:4 ( 1 cement : 2


coarse sand : 4 graded stone aggregate of 12.5 mm nominal size )in basements &
stilt floor including cleaning the surface, applying cement slurry, side shuttering with
MS channels, vibrating concrete by using screed vibrator, dewatered by vaccum
dewatering using "Tremix" process,including curing etc. The surface will be finished
with a nylon brush and the flooring shall be laid in required slope. all complete as per
direction of Engineer in charge.

Sqm

38288

455

17420898.95

610.00

23355490.90

476.00

18,224,940.44

386.0

3.00

Providing and laying IPS Flooring of 40mm thickness of Cement Concrete 1:2:4 (1
cement:2 coarse sand 4 graded stone aggregate of 12.5mm nominal size) in flooring
fixing of 40 x 4 mm size glass strips of required size at 1.2m c/c both ways part thereoff
as required and finished with a floting coat of neat cement i/c cement slurry in M/c
Room and Terrace Corridor , Electrical shaft, FHC shaft & Shop etc., all complete
including all material cost at all levels and all lead and lifts, wherever specified to the
complete satisfaction of Engineer in charge.

Sqm

6111

300.5

1836444.45

403.00

2462852.29

316.30

1,933,002.92

226.3

Page 26 of 71

2,706,632
16,731,376
8,492,203
689,490
1,678,558
3,415,660
58,422
33772340
6,524,316
14,779,048
1,382,986

10.0

10.0

13.0

10.0

10.0

660,154
2,535,057
1,226,652
168,168
517,524
5107555
-

135.0

135.0

239.0

900.0

135.0
15.0
20.0
20.0

3.0

135.0
15.0
18.0
20.0
22.0
146.6

90.0

90.0

90.0

8,912,081
34,223,268
22,551,517
2,556,000
2,270,273
278,064
311,520
54,268
399,657
6,986,577
124,943
140,433
64,081
2,796
99,622
78975100
2,594,735
3,445,892
550,017

10.0

10.0

40.0

10.0

10.0

660,154
2,535,057
3,774,312
168,168
517,524
7655216
-

THE PRIMUS (SEC - 82 A) DLF TOWNSHIP PROJECT IN NEW GURGAON


FINISHING BOQ

4.00

Providing and laying plaster skirting, 12/15mm thick in 1:3 (1 cement 3 coarse sand)
& finished with neat cement slurry complete as directed by Engineer in charge at all
floor levels in M/c room, Terrace corriodor, Electrical shaft, FHC shaft etc.

Sqm

160

177.5

28373.38

238.00

38044.30

189.70

30,323.55

89.7

5.00

Providing and laying IPS Flooring of 20mm thickness on service slab of Cement
Concrete 1:2:4 (1 cement:2 coarse sand 4 graded stone aggregate of 12.5mm nominal
size) finished with a floating coat of neat cement i/c cement slurry in all complete
including all material cost at all levels and all lead and lifts, wherever specified to the
complete satisfaction of Engineer in charge.

Sqm

794

206.1

163681.73

276.00

219195.34

219.00

173,926.73

129.0

6.00

Extra for providing & applying CICO Emalite RTU @ 4kg/m2 to 5kg/m2 on existing
CC flooring at turning points in drive way, ramps, Helipad flooring as per
Manufacturer's instruction.

Sqm

4050

125

506250.00

168.00

680400.00

125.00

506,250.00

125.0

SUBTOTAL
TOTAL

28316460.16
123,058,102

164,924,904

14,339
102,450
506,250

29987494.42

##########

155,497,706

57,081,730

Page 27 of 71

100.0

90.0

15,985
71,477
-

6678105.13
5,107,555

85,653,205

7,655,216

THE PRIMUS (SEC - 82 A) DLF TOWNSHIP PROJECT IN NEW GURGAON


FINISHING BOQ

DLF GH P0ject 'The Primus' Sector-82A


STONE WORKS
Finishes
ITEM

1.00

DESCRIPTION

UOM

QTY

1.34

TENDER
DC RATE

TENDER
DC AMOUNT

PSE
RATE

Material

PSE AMOUNT

1.01

Imported / Omani Beige marble flooring (avg rate 230/- per sqft) in Living / Dining,
measured from plaster to plaster, at all floor levels at all leads.

Sqm

20467

3980

81458540.60

4131.00

84,549,053.07

1.02

Extra over item no. 1.01 for mirror polishing with synthetic carborandum stones.

Sqm

20467

125

2558371.25

125.00

2,558,371.25

2.00

Providing & fixing of 18 +/- 2mm marble stone skirting with 12 mm thick 1:3 cement
mortar (1 cement : 3 coarse sand) jointed with white cement mixed with pigment to
match the shade of stone. Including edge chamfering, resin filler coating & making
verticle mitred joints as specified at all floor levels as per approved design / pattern as
detailed in the drawing / instructions of the Engineer . Polishing shall be paid extra.

2.01

Imported / Omani Beige Marble (avg rate 230/- per sqft) skirting 100 mm high.

Rmt

12713

548

6966548.64

563.10

7,158,510.11

2.02

Extra over item No. 2.01 for Mirror Polishing with synthetic carborandum stones.

Rmt

12713

22.5

286035.30

22.50

286,035.30

20926702.83

4570.00

20,362,320.50

338446.00

200.00

338,446.00

3250.0

325.0

Typical Lift Lobby


1.00

Providing & Laying of 18 +/- 2 mm marble stone on 1: 4 (1cement : 4coarse sand) 20


mm thick base mortar laid to the required slope & in required pattern, jointed with white
cement slurry mixed with pigment to match the shade of stone, resin filler coating, POP
protection with 200 micron Polythene sheet till handing over and removing POP malba
from site also.The stone shall be taken to match the grains of stone work . For purpose of
matching the grains , the stone slabs shall be selected judiciously having uniform pattern
of veins / streaks The area to be laid shall be reproduced on the ground and the stone
slabs laid in position and arranged in the manner to give the desired matching of grains .
Any adjustment needed for achieving the best results shall be then carried out by
replacing or interchanging the particular slabs.

1.01

Imported / Omani Beige marble flooring (avg rate 230/- per sqft) with patterns made in
dark emperador (as per drawings), measured from plaster to plaster, at all floor levels at
all leads.

Sqm

4456

Extra labour charges for cutting and fixing strips in flooring / cladding upto clear width

Rmt.

1692

1.02

4,697
200

3330.0

Providing and Fixing 3mm thick S.S Strip in flooring fixed with Araldite in place flushing

Rmt

1692

347.60875

588233.96

347.61

588,233.96

Sqm

4456

100

445565.00

100.00

445,565.00

1867558.68

483.10

1,927,815.38

59857.65

15.00

59,857.65

292.6

with the border in flooring of Lift Lobby.


1.04

Extra over item no. 1.01 for mirror polishing with synthetic carborandum stones .

2.00

Providing & fixing of 18 +/- 2mm marble stone skirting with 12 mm thick 1:3 cement
mortar (1 cement : 3 coarse sand) jointed with white cement mixed with pigment to
match the shade of stone. Including edge chamfering, resin filler coating & making
verticle mitred joints as specified at all floor levels as per approved design / pattern as
detailed in the drawing / instructions of the Engineer . Polishing shall be paid extra.

2.01

Imported / Omani Beige Marble (avg rate 230/- per sqft) skirting 100 mm high

Rmt

3991

2.02

Extra over item No. 2.01 for Mirror Polishing with synthetic carborandum stones

Rmt

3991

15

3.00

3.01

Supply & Fixing of 18 +/- 2mm thick marble stone cladding/dado/bands/


strips/cill/soffits/jambs is specified size as per drawing laid with 20mm thick 1:3 cement
mortar(1cement : 3 coarse sand) wet cladding. The item includes providing and fixing
stainless steel cramp of adequate size fixed in cladding as per design in CM 1:2(1cement :
2coarse sand) pins,dash fasteners of approved make and fixing grit on back of stone with
araldite etc including making 4mm grooves, pointing, resin filler coating, edges
chamfering, filling of the joints with matching cement pigment, scaffolding etc. complete
as per drawing.
Imported/ Travertine Marble in Lift cladding,Jambs, Sills & Soffit(avg rate 230/- per sqft).

Sqm

2661

4421

11765960.98

4752.00

12,646,877.76

3.02

Extra over item No. 3.01 for Mirror Polishing with synthetic carborandum stones.

Sqm

2661

100

266138.00

100.00

266,138.00

4.00

Extra Labour charges for Cutting hole for Indicators & Electrical fixtures as per
detail complete.
size of 90 mm X 180 mm

Each

569

300

170700.00

300.00

170,700.00

4.01

468

66,517,653
4,131,621
14,837,315
-

of 150mm.
1.03

Labour

Sub Contractor

Plant Depric.

Plant Oprn & Fuel

Wooden Shuttering

Steel Shuttering

APARTMENTS flooring, skirting


Providing & Laying of 18 +/- 2 mm marble stone on 1: 4 (1cement : 4coarse sand) 20
mm thick base mortar laid to the required slope & in required pattern, jointed with white
cement slurry mixed with pigment to match the shade of stone, resin filler coating, POP
protection with 200 micron Polythene sheet till handing over and removing POP malba
from site also.The stone shall be taken to match the grains of stone work . For purpose of
matching the grains , the stone slabs shall be selected judiciously having uniform pattern
of veins / streaks The area to be laid shall be reproduced on the ground and the stone
slabs laid in position and arranged in the manner to give the desired matching of grains .
Any adjustment needed for achieving the best results shall be then carried out by
replacing or interchanging the particular slabs.

379.8

3798.0

Page 28 of 71

495,161
1,515,596
10,107,921
-

866.0
125.0

236.6
22.5

1225.0
200.0

55.0

100.0

103.3
15.0

954.0
100.0

300.0

17,724,396
2,558,371
3,007,820
286,035
5,458,171
-

15.0

1.5

15.0

307,005
19,069
66,835
-

338,446

93,073
445,565
412,220
59,858
2,538,957
266,138
170,700

Testing Charges

THE PRIMUS (SEC - 82 A) DLF TOWNSHIP PROJECT IN NEW GURGAON


FINISHING BOQ

STONE WORKS
Finishes
ITEM
4.02

DESCRIPTION
size of 110 mm X 320 mm

1.34
TENDER
DC AMOUNT

PSE
RATE

PSE AMOUNT

350

75950.00

350.00

75,950.00

445

3980

1772453.20

4131.00

1,839,699.54

UOM

QTY

Each

217

Sqm

TENDER
DC RATE

Material

ENTRANCE HALL & GROUND FLOOR LIFT LOBBY


1.00

Providing & Laying of 18 +/- 2 mm marble stone on 1: 4 (1cement : 4coarse sand) 20


mm thick base mortar laid to the required slope & in required pattern, jointed with white
cement slurry mixed with pigment to match the shade of stone, resin filler coating, POP
protection with 200 micron Polythene sheet till handing over and removing POP malba
from site also.The stone shall be taken to match the grains of stone work . For purpose of
matching the grains , the stone slabs shall be selected judiciously having uniform pattern
of veins / streaks The area to be laid shall be reproduced on the ground and the stone
slabs laid in position and arranged in the manner to give the desired matching of grains .
Any adjustment needed for achieving the best results shall be then carried out by
replacing or interchanging the particular slabs.

1.01

Providing & fixing Imported / Omani Beige marble flooring (avg rate 230/- per sqft)
with patterns made in dark emperador (as per drawings), measured from plaster to
plaster, at all floor levels at all leads.

1.02

Extra labour charges for cutting and fixing strips in flooring / cladding upto clear width
Rmt.

125

240

30000.00

240.00

30,000.00

1.03

Providing and Fixing 3mm thick S.S Strip fixed with Araldite in place flushing
with the border in flooring of Lift Lobby.

Rmt

125

347.60875

43451.09

347.61

43,451.09

1.04

Extra over item No. 1.01 for Mirror Polishing with synthetic carborandum stones.

Sqm

445

100

44534.00

100.00

44,534.00

2.00

2.01

Supply & Fixing of 18 +/- 2mm thick marble stone cladding/dado/bands/


strips/cill/soffits/jambs is specified size as per drawing laid with 20mm thick 1:3 cement
mortar(1cement : 3 coarse sand) wet cladding. The item includes providing and fixing
stainless steel cramp of adequate size fixed in cladding as per design in CM 1:2(1cement :
2coarse sand) pins,dash fasteners of approved make and fixing grit on back of stone with
araldite etc including making 4mm grooves, pointing, resin filler coating, edges
chamfering, filling of the joints with matching cement pigment, scaffolding etc. complete
as per drawing.
Imported/ Travertine Marble in Lift cladding,Jambs, Sills & Soffit(avg rate 230/- per sqft).

Sqm

69

4421

304297.43

4752.00

327,080.16

2.02

Extra over item No. 2.01 for Mirror Polishing with synthetic carborandum stones.

Sqm

69

100

6883.00

100.00

6,883.00

3.00

Providing & fixing of 18 +/- 2mm marble stone skirting with 12 mm thick 1:3 cement
mortar (1 cement : 3 coarse sand) jointed with white cement mixed with pigment to
match the shade of stone. Including edge chamfering, resin filler coating & making
verticle mitred joints as specified at all floor levels as per approved design / pattern as
detailed in the drawing / instructions of the Engineer . Polishing shall be paid extra.

3.01

Imported / Omani Beige Marble (avg rate 230/- per sqft) skirting 100 mm high

Rmt

549

518

284345.74

533.10

292,634.58

3.02

Extra over item No. 3.01 for Mirror Polishing with synthetic carborandum stones.

Rmt

506

10

5057.40

10.00

5,057.40

of 150mm.

3250.0

292.6

3798.0

339.0

STONE WORK
1.00

Providing, cutting & fixing pre-polished 18+/-2 mm Indian/Madnapalli Granite Stone as


worktop slab over Counter with Araldite on Modular Kitchen Top board (board is part of
Modular Kitchen) at all floor levels, including edge chamfering,making openings/holes for
sink/wash basin,mixers,soap dispenser as required and mirror polishing of edges complete
as per drawing.(avg rate 150/- per Sqft)

Sqm

797

3240

2581113.60

3213.33

2,559,869.87

1953.3

2.00

Extra over item no. 1.00 for strips, latak & band upto 150mm.

Rmt

5047

607.5

3066052.50

602.50

3,040,817.50

366.3

3.00

Providing & Fixing worktop of 18+/-2 mm thick pre-polished Imported/Emperador marble


Stone (Dark/Light) over 12mm thick waterproof ply with araldite in Toilets at all floor
levels, including resin filling, edge chamfering, making openings/holes for sink/wash
basin,mixers,soap dispenser as required and mirror polishing of edges complete as per
drawing.(avg rate 230/- per Sqft)

Sqm

1641

5,342

8769204.36

5356.67

8,792,914.77

4001.1

4.00

Providing and fixing 75 mm wide strip of 18+/-2 mm thick Imported/Omani Beige Marble
over 1:4 ( 1 cement : 4 coarse sand) 20 mm thick mortar at Shower area including edge
chamfering, edge polish, mirror polish & resin filling all complete and as per instructions
of project in charge.(avg rate 230/- per Sqft)

Rmt

1981

551

1090930.93

552.19

1,093,612.87

375.1

5.00

Providing & fixing of 18+/-2 mm thick Imported/Omani Beige marble stone on 1: 4 cement
mortar (1 cement : 4 coarse sand) 20 mm thick base mortar in threshold, cill, bands 50
mm to 250 mm including edge chamfering, edge polish, mirror polish & resin filling, joints
filled with white cement mixed with pigment matching the shade of stone all complete.
The stone shall be taken to match the grains of stone work . For purpose of matching the
grains , the stone slabs shall be selected judiciously having uniform pattern of veins /
streaks The area to be laid shall be reproduced on the ground and the stone slabs laid in
position and arranged in the manner to give the desired matching of grains . Any
adjustment needed for achieving the best results shall be then carried out by replacing or

Page 29 of 71

1,447,355
36,576
261,416
186,087
1,556,103
1,848,464
6,567,784
742,898
-

Labour

Sub Contractor
-

350.0

866.0

240.0

55.0
100.0

954.0
100.0

194.1
10.0

1260.0
236.3

1355.6

177.1

75,950
385,664
30,000
6,875
44,534
65,664
6,883
106,547
5,057
1,003,766
1,192,354
2,225,131
350,715
-

Plant Depric.

Plant Oprn & Fuel

Wooden Shuttering

Steel Shuttering

15.0

6,680
-

Testing Charges

THE PRIMUS (SEC - 82 A) DLF TOWNSHIP PROJECT IN NEW GURGAON


FINISHING BOQ

STONE WORKS
Finishes
ITEM

DESCRIPTION
interchanging the particular slabs.(avg rate 230/- per Sqft)

5.01

UOM

QTY

Sqm

3074

TENDER
DC RATE
3980

1.34
TENDER
DC AMOUNT

PSE
RATE

12233405.60

4131.00

Material

PSE AMOUNT
12,697,537.32

3250.0

Providing & Fixing Dholpur Stone 40 mm thick & 150 mm wide in coping at balcony laid on 20 mm
thick cement mortar 1:4 (1 cement 4 coarse sand) and jointed with white cement slurry mixed with
pigment to match the shade of the rubbing and polishing complete as per the satisfaction to
engineer in charge.stone includingchamfering,

Sqm

TOTAL

Labour

9,989,590
-

2780

1,979

5500752.41
163,507,090

1991.69

5,536,892.41

1669.6

167744858.48

Page 30 of 71

4,641,622
124883162

Sub Contractor
-

866.0

Plant Depric.

2,661,842
-

322.0

895,270
42416003

Plant Oprn & Fuel

Wooden Shuttering

Steel Shuttering
15.0

46,106
-

445694

Testing Charges

THE PRIMUS (SEC - 82 A) DLF TOWNSHIP PROJECT IN NEW GURGAON


FINISHING BOQ

DLF GH P0ject 'The Primus' Sector-82A


LAMINATED WOODEN FLOORING WORKS

ITEM
1

DESCRIPTION

Finishes
TENDER
DC RATE

UOM

QTY

specifications and to the satisfaction of engineer in charge all complete at all floor levels.

Sqft

288785

Providing & Fixing 75 mm high laminated wooden skirting of matching shade all complete
to the satisfaction of Engineer in charge. At all floor levels.

Rft

83455

20.26

Rft

11247

20.26

1.34
TENDER
DC AMOUNT

SPCL RATE

SPCL AMOUNT

PSE
RATE

PSE AMOUNT

Material

Labour

Sub Contractor

Plant Depric.

Plant Oprn & Fuel

Wooden Shuttering

Steel Shuttering

Testing Charges

Providing & Fixing laminated 8mm thick, AC-3, abrasion resistant wooden flooring of
(Pergo - PS4629) inclusive providing & fixing vapour barrier polythylene sheet 0.2mm
thick & underlay extruded polyethylene foam 1.5mm thick to have a floating floor
installation with perimeter expension gap, laid completely as per manufacturer's

Providing & Fixing laminated wooden T-Profile of matching shade all complete to the
satisfaction of Engineer in charge. At all floor levels.

65.75

18987615.72

88.00

25413082.64

65.75

18987615.72

1690402.44

27.00

2253272.85

20.26

1690402.44

227807.85

27.00

303663.33

20.26

20,905,826

27,970,019

65.8

227807.85
20,905,826

Page 31 of 71

20.3

20.3
-

18,987,616
1,690,402
227,808
20,905,826

THE PRIMUS (SEC - 82 A) DLF TOWNSHIP PROJECT IN NEW GURGAON


FINISHING BOQ

DLF GH P0ject 'The Primus' Sector-82A


DOOR / WINDOWS

ITEM

DESCRIPTION

Finishes

1.34

TENDER
DC RATE

TENDER
DC AMOUNT

PSE
RATE

PSE
AMOUNT

Material

UOM

QTY

RM

3787

1,039.97

3,938,678.52

1084.90

4108824.16

1024.9

RM

27310

581.30

15,874,963.99

611.90

16710647.85

551.9

necessary complete as specified. At all floor levels.

SQM

12342

2260.82

27,904,001.75

2262.03

27918938.31

1768.1

4.00

Supply and Fixing of flush door shutters of specified size & 25mm thickness including
cost of providing & fixing hard wood lipping , providing & fixing 3 nos. MS hinges
75mm long and shaft lock fixing, Cutting / re-sizing of door if necessary complete as
specified. in lift lobby for LVshaft At all floor levels.

Sqm

83

2015.06

168,036.13

2015.06

168036.13

1610.4

5.00

Supply & fixing of Pre-fabricated moulded Architrave at the junction of door frame &
wall with necessary S.S screws, Plugs made out of Teakwood for main doors and Red
meranti for other doors as specified size as per approved design.

Labour

Sub Contractor

Plant Depric.

DOOR, WINDOW & HARDWARE


1.00

Providing & Fixing 2nd Class Ghana teakwood or other specified & approved
Hard-Wood free from knots ,door frames of size 150 x 75mm in proper alignment /vertical
to the plumb including providing & fixing 6 nos. of M. S. hold fasts / Dash fasteners as
required per frame including cutting of Block masonry and casting of concrete blocks of size
300*100*150mm in C.C. 1:2:4 . The item includes mixing and placing of concrete complete as
per instructions of the Engineer . No escalation shall be payable for Hold fasts. At all floor
levels.

2.00

Providing & Fixing Red Meranti or other specified & approved Hard-Wood door
frames of size 115 x 65mm in proper alignment / vertical to the plumb including
providing & fixing 6 nos. of M. S. hold fasts / Dash fasteners per frame including
cutting of Block masonry and casting of concrete blocks of size 300*100*150mm
in C.C. 1:2:4 . The item includes mixing and placing of concrete complete as per
instructions of the Engineer . No escalation shall be payable for Hold fasts. At all
floor levels.

3.00

Supply and Fixing 38mm thick, solid core flush door shutters (commercial ply veneer
3mm thick on both faces) of specified size & thickness including cost of providing &
fixing hard wood lipping , excluding door hardwares fittings cutting / re-sizing of door if

Teak Wood
Rectangular Architrave 60mm x 12mm
Rectangular Architrave 40mm x 12mm

RM
RM

3787
3787

97.55
85.76

369,421.85
324,773.12

97.55
75.26

369421.85
285009.62

77.9
56.7

5.01
5.02

Red Mirandi
Rectangular Architrave 60mm x 12mm
Rectangular Architrave 40mm x 12mm

RM
RM

27595
27595

36
24

993,420.00
662,280.00

36.00
24.00

993420.00
662280.00

36.0
24.0

B
C
D
E

1.02
A
B
C
D
1.03
A
B
C

60.0

60.0

5.01
5.02

1.00
1.01
A

3,881,586
15,072,069
21,822,330
134,287
295,007
214,647
993,420
662,280
-

227,238
1,638,579
-

494.0

404.7

19.7
18.6

6,096,608
33,749
74,415
70,362
-

Supplying and fixing mechanically operated rolling shutters of approved make made of

80 x 1.25 mm MS laths inter locked together through their entire length and jointed
together at the end by end locks mounted on specially designed pipe shaft with
brackets, side guides and arrangements for inside and outside locking with push and
pull operation complete incl. the cost of providing and fixing necessary 27.5cm long wire
springs grade no. 2 and MS top cover 1.25mm thick for rolling shutters incl. ball bearing,
opening and closing system by gear and lever operation incl. cost of two coat of red
oxide primer and three or more coats of synthetic enamel paint of approved brand and
shade.

179,580
1,565,000
469,500
125,200
62,600
93,900
2,806,000
1,683,600
561,200
280,600
1,948,500
1,299,000
-

HARDWARE
Providing & Fixing Hardware as per SAMPLE APPROVED (DORSET)
Main Entrance Door
Providing & Fixing SS Mortice Lock, cylinder with handle sets. with bothside keyhole
on inside and outside in door including necessary S.S screws etc.all complete at all floor
levels.
Providing & Fixing SS ball bearing Hinges 125mm X 75mm X 3mm in door including
necessary S.S screws etc.all complete at all floor levels.
Providing & Fixing Door Stopper SS316 satin finish in door including necessary S.S screws
etc.all complete at all floor levels.
Providing & Fixing Door Guard SS304 satin finish in door including necessary S.S screws
etc. all complete at all floor levels.
Providing & Fixing Wide angle door viewer SS304 satin finish in door including
necessary S.S screws etc.complete at all floor levels.
Internal Bedroom / Kitchen doors
Item same as 1.01 (a) above but one side key hole & one side Knob all complete.
Providing & Fixing SS ball bearing Hinges 100mm X 75mm X 3mm in door including
necessary S.S screws etc.complete at all floor levels.
Providing & Fixing Door Stopper SS316 satin finish in door including necessary S.S screws
etc. all complete at all floor levels.
Providing & Fixing Door Guard with SS316 satin finish in door including necessary S.S
screws all complete at all floor levels
Toilet Doors
Item same as 1.01 (a) above but without cylinder and with Babylatch for toilet
doors all complete at all floor levels.
Providing & Fixing SS ball bearing Hinges 100mm X 75mm X 3mm in door including
necessary S.S screws etc.all complete at all floors.
Providing & Fixing Baby latch Brass SS finish in door including necessary S.S screws

Sqm

60

3000

179,580.00

3000.00

179580.00

Nos.

626

2500

1,565,000.00

2500.00

1565000.00

Nos.

1878

250

469,500.00

250.00

469500.00

Nos.

626

100

62,600.00

200.00

125200.00

Nos.

626

100

62,600.00

100.00

62600.00

Nos.

626

250

156,500.00

150.00

93900.00

Nos.

2806

1100

3,086,600.00

1000.00

2806000.00

Nos.

8418

200

1,683,600.00

200.00

1683600.00

Nos.

2806

75

210,450.00

200.00

561200.00

Nos.

2806

150

420,900.00

100.00

280600.00

Nos.

2165

900

1,948,500.00

900.00

1948500.00

Nos.

6495

200

1,299,000.00

200.00

1299000.00

Page 32 of 71

3000.0

2500.0
250.0
200.0
100.0
150.0

1000.0
200.0
200.0
100.0

900.0
200.0

Plant Oprn & Fuel

Wooden Shuttering

Steel Shuttering

Testing Charges

THE PRIMUS (SEC - 82 A) DLF TOWNSHIP PROJECT IN NEW GURGAON


FINISHING BOQ

DOOR / WINDOWS

ITEM

1.04
A
B

C
D
E

1.05
A
B
C

DESCRIPTION
etc.all complete. At all floors Levels.
Providing & Fixing Door Guard with SS316 satin finish in door including necessary
S.S screws etc.all complete at all floor levels.

a)
b)

PSE
RATE

150

324,750.00

150.00

324750.00

PSE
AMOUNT

Material

Labour

2165

100

216,500.00

100.00

216500.00

Nos.

178

900

160,200.00

900.00

160200.00

Providing & Fixing Aluminium Door Stopper in door including necessary screws etc.all

Nos.

178

60

10,680.00

60.00

10680.00

complete.at all floors.


Providing & Fixing Rubber Door Guard in door including necessary screws etc. all
complete at all floors.
Providing & Fixing Aluminium Tower Bolt 200mm in door including necessary screws
etc.all complete at all floors.
Providing & Fixing Aluminium Butt Hinges 100mm X 75mm X 3mm in door including
necessary screws etc.all complete at all floor levels.
S.Room Toilet (as per sample approved)
Providing & Fixing Aluminium Handle with Latch ( handle both sides ) all
complete at all floor levels.
Providing & Fixing Aluminium Butt Hinges 100mm X 75mm X 3mm in door including
necessary screws etc.all complete at all floor levels.
Providing & Fixing Rubber Door Buffer necessary screws etc.all complete at all floor
levels.

Providing, fabricating and fixing / erection M.S. structural work (like drain frame angle,
drain cover grating) fabricated from standard sections e.g. M.S.Angles, Plates , Rolled
Sections such as Channels, Flats, Joists etc. including cutting to size, drilling, welding ,
providing and applying a coat of red oxide primer only and two or more coat of Synthetic
enamel paint to the satisfaction of Engineer-in-charge, chipping of RCC & cost of nuts &
bolts but including the cost of providing & fixing dash fastener if required, complete as
directed.

a)
b)
c)
d)

2165

1.34
TENDER
DC AMOUNT

Nos.

2.00

Nos.

Finishes
TENDER
DC RATE

S.Room (as per sample approved)


Providing & Fixing Aluminium Mortice Lock with handle sets. with one side
keyhole all complete at all floor levels.

Providing & fixing MS safety lock in machine room trap door including necessary screws
etc.all complete at all floor levels..

a)
b)
c)
d)

QTY

1.06

UOM

Nos.

178

60

10,680.00

60.00

10680.00

Nos.

178

110

19,580.00

110.00

19580.00

Nos.

534

150

80,100.00

150.00

80100.00

Nos.

296

250

74,000.00

250.00

74000.00

Nos.

888

100

88,800.00

100.00

88800.00

Nos.

296

75

22,200.00

75.00

22200.00

Nos.

600

5,400.00

600.00

5400.00

Kg

70.05

FIRE DOORS
Supply and Fixing of CBRI Tested and approved 2 hour fire rated Single rebated 115mm
X 65mm thick Steel Frame made by 1.5mm thick Galvanized Steel Sheet(Zinc coating not
less than 120 gm/sqm) duly filled with vermuculite based concrete mix, all complete. The
frame will be fitted with intumuscent fire seal strip alround, frame will be fixed with dash
fastener of approved size and make, including painting with epoxy powder coated of
approved shade all complete to the satisfaction of Engineer-in-Charge at at all floor
levels.
Staircase and Lift Lobby Single Leaf - 1.10 x 2.10 meter (Typical Floor)
Electrical Room Shaft Single Leaf - 1.0 x 2.10 meter (Typical Floor)
Staircase and Lift Lobby Single Leaf - 1.10 x 2.10 meter (Basement Floor)
Electrical Room Shaft Single Leaf - 1.25 x 2.10 meter (Basement Floor)

Nos.
Nos.
Nos.
Nos.

420
215
36
30

4,246.04
4,175.36
4,455.16
4,455.16

1,783,336.80
897,702.40
160,385.76
133,654.80

4246.00
4175.00
4455.00
4455.00

1783320.00
897625.00
160380.00
133650.00

Supply and Fixing of CBRI Tested and approved 2 hour fire rated Steel shutter made of
1.0mm thick Galvanized Steel Sheet Fully flushed double skin door have interlock seam
arrangement at stile edges having 44mm (+ - 1mm) thickness with infill material having
fire rated heat-insulating material suitable for stability and integrity up to 2 hours fire
rating. Rates are including the provision for fixing necessary hardwares as required.
Shutters are suitably cleaned and epoxy Powder coated of approved colour all complete
to the satisfaction of Engineer-in-Charge at all floor levels.
Staircase and Lift Lobby Single Leaf - 1.10 x 2.10 meter (Typical Floor)
Electrical Room Shaft Single Leaf - 1.0 x 2.10 meter (Typical Floor)
Staircase and Lift Lobby Single Leaf - 1.10 x 2.10 meter (Basement Floor)
Electrical Room Shaft Single Leaf - 1.25 x 2.10 meter (Basement Floor)

Nos.
Nos.
Nos.
Nos.

402
205
36
30

11,157.62
10,017.62
11,157.62
12,811.76

4,485,363.24
2,053,612.10
401,674.32
384,352.80

11200.00
10020.00
11200.00
12820.00

4502400.00
2054100.00
403200.00
384600.00

Supply and Fixing of CBRI Tested and approved 2 hour Fire Rated Wooden Shutters
shall be constructed out of sandwitched Non combustible boards. Shutters are fully
flush double skinned having 60mm (+ - 2mm) thickness and are fully finished with 15mm
hardwood edge band on all four edges.Shutters have 12mm x 3mm shielded intumescent
strip on the three edges along with reinforcements to receive iron mongery. Rates are
including for making provision for fixing of hardwares as required. Shutters for fire doors
shall be both Side finished condition all complete to the satisfaction of
Engineer-in-Charge at all floor levels.
Staircase and Lift Lobby Single Leaf - 1.10 x 2.10 meter (Ground Floor)
Electrical Shaft Single Leaf - 1.0 x 2.10 meter (Ground Floor)

Nos.
Nos.

18
10

16,902.96
16,528.64

304,253.28
165,286.40

16905.00
16530.00

304290.00
165300.00

Nos.

456

5040

2,298,240.00

5040.00

2298240.00

SUPPLY OF HARDWARES FOR FIRE DOORS


Supplying and fixing the following 2 hour fire rated hardware with necessary screws
etc. of rating compatible with the fire rate doors as per SAMPLE APPROVED (DORSET)

4.1
a)

Staircase Doors
Providing and fixing imported Panic bar/Latch- 378 E Briton with a single body, Trim
Latch & Lock on the back side of the Panic Latch of reputed brand and manufacture to
be approved by the Engineer-in-Charge,all complete at all floor levels.

Page 33 of 71

Sub Contractor
150.0

900.0

324,750
216,500
160,200

60.0

10,680

100.0

60.0
110.0
150.0

250.0
100.0
75.0

600.0

4246.0
4175.0
4455.0
4455.0

11200.0
10020.0
11200.0
12820.0

16905.0
16530.0

5040.0

10,680
19,580
80,100
74,000
88,800
22,200
5,400
1,783,320
897,625
160,380
133,650
4,502,400
2,054,100
403,200
384,600
304,290
165,300
2,298,240

Plant Depric.

Plant Oprn & Fuel

Wooden Shuttering

Steel Shuttering

Testing Charges

THE PRIMUS (SEC - 82 A) DLF TOWNSHIP PROJECT IN NEW GURGAON


FINISHING BOQ

DOOR / WINDOWS

ITEM

DESCRIPTION

UOM

QTY

Finishes

1.34

TENDER
DC RATE

TENDER
DC AMOUNT

PSE
RATE

PSE
AMOUNT

68400.00
78,814,503

43,075,627

Providing and fixing Door closer in fire door as approved by the Architect or as shown
in the drawing including necessary screws etc. complete at all floor levels.

Nos.

456

1700

775,200.00

1700.00

775200.00

c)

Providing and fixing 2 Hr fire rated 6 mm thick clear Glass vision panel in doors complete
as per drgs.( approximate size 150mm x 750 mm ) reputed brand and manufacture to
be approved by the Engineer-in-Charge,all complete at all floor levels.

Nos.

456

2000

912,000.00

2000.00

912000.00

d)

Providing & Fixing S.S.Heavy Duty Ball Bearing butt Hinges 125mm X 75mm X 3mm
in staircase door including necessary screws etc. all complete at all floor levels. As per
the manufacturer recommendation.

Nos.

1824

100

182,400.00

200.00

364800.00

e)

Providing & Fixing Door Guard in door including necessary screws etc. all
complete at all floors.

Nos.

456

100

45,600.00

100.00

45600.00

Electrical Room Doors


Providing & Fixing of AllenKey lock with a pair of handles of approved makes in Fire
door including necessary screws etc. all complete at all floor levels. As per including
necessary screws etc. complete at all floor levels. As per the manufacturer
recommendation.

Nos.

245

250

61,250.00

250.00

61250.00

b)

Providing & Fixing S.S.Heavy Duty Ball Bearing butt Hinges 125mm X 75mm X 3mm
in staircase door including necessary screws etc. all complete at all floor levels. As per
the manufacturer recommendation.

Nos.

980

200

196,000.00

200.00

196000.00

c)

Providing & Fixing Door Guard in door including necessary screws etc. all
complete at all floors.

Nos.

456

150

68,400.00

150.00

TOTAL

77,702,007

Labour
-

b)

4.2
a)

Material

Page 34 of 71

Sub Contractor

1700.0

2000.0

200.0

100.0

250.0

200.0

150.0
-

Plant Depric.

Plant Oprn & Fuel

Wooden Shuttering

Steel Shuttering

Testing Charges

775,200
912,000
364,800
45,600
61,250
196,000
68,400
35,738,876

THE PRIMUS (SEC - 82 A) DLF TOWNSHIP PROJECT IN NEW GURGAON


FINISHING BOQ

DLF GH P0ject 'The Primus' Sector-82A


INTERIOR WORKS
Finishes
ITEM

DESCRIPTION

1.00 Providing and fixing suspended false ceiling 12.5 mm tapered edge Gypboard with
G.I. perimeter channels 0.55 mm thick having one flange of 20 mm and other
flange of 30 mm and a web of 27 mm alongwith perimeter of ceiling . G.I.
intermediate channels of size 45 mm , 0.9 mm thick with two flanges of 15 mm each
from the soffit at 1220 mm centers with ceiling angle of width 25 mm x 10 mm x
0.55 mm thick fixed to soffit with G. I. cleat and expansion fasteners . Ceiling
section of 0.55 mm thickness having knurled web of 51.5 mm and two flanges of 26
mm each with lips of 0.5 mm using standard connecting clips at 450 mm C/C , and all
hardware as specified by the manufacturer i.e. INDIA GYPSUM including filling and
finishing the tapered and square edges of the boards with jointing compound , paper
tapes and two coats of primer suitable for Gypboard . Item will be executed as per
the pattern shown in the drawing.Necessary provisions shall be made for cutouts for
air conditioners supply, return air grill, slits, light fittings, smoke detector and music
speaker etc. Actual surface area (horizental/vertical) will be measured for the
payment.Nothing extra will be payable for cove, patta and any other architectural
feature. For Entrance Hall & Lift Lobby False ceiling and Boxing of Bedrooms.
2.00 Providing and fixing tiled False Ceiling of 12.5 mm calcium Silicate of size 600x600
mm in toilets & kitchens, in true horizontal level suspended on inter locking metal grid
of hot dipped galvanised steel sections ( galvanized @ 170 gsm/sqm.) consisting of
main T runner with suitably spaced joints to get required length and of size
24x38mm made from 0.30mm thick (minimum) sheet spaced at 1200mm center to
center and cross T of size 24x25mm made of 0.30mm thick (minimum) sheet,
1200mm long spaced between main T at 600mm center to center to form a grid of
1200x600 mm and secondary cross T of length 600mm and size 24x25mm made of
0.30 mm thick (minimum) sheet to be interlocked at middle of the 1200x600mm panel
to form grids of 600x600mm and wall angle of size 21x21x0.30 mm and laying false
ceiling tiles of approved texture in the grid including, wherever, required,
cutting/making, opening for services like diffusers, grills, light fittings, fixtures, smoke
detectors etc. Main T runners to be suspended from ceiling using GI slotted cleats
fixed to ceiling with 6 mm dia and 50mm long dash fasteners, 4mm GI adjustable rods
with galvanised level clips spaced at 1200mm center to center along main T, bottom
exposed width of 24mm of all T-sections shall be pre-painted with polyester paint, all
complete at all heights as per specifications drawings and as directed by
Engineer-in-Charge.

TENDER
DC RATE

1.34
TENDER
DC AMOUNT

SPCL AMOUNT

PSE AMOUNT

Material

Labour

Sub Contractor

QTY

Sqm

21465

1100

23611555.00

1474.00

31639483.70 1100.00

23,611,555.00

1100.0

23,611,555

8858

1000

8857500.00

1340.00

11869050.00 1000.00

8,857,500.00

1000.0

8,857,500

Sqm

SPCL RATE

PSE
RATE

UOM

3.00 Providing & Applying 6 mm thick average POP (super fine quality) punning on walls,
making in proper line and levels for smooth finish in Entrance Hall & Lift Lobby
complete to the entire satisfaction of the engineer in charge.

Sqm

9882

130

1284602.80

174.00

1719391.44

130.00

1,284,602.80

130.0

1,284,603

4.00 Providing & applying two or more coats of Velvet touch paint, ICI make on POP
surfaces of walls in entrance hall & lift lobbies of approved shade to give an even
shade including one coat of primer, surface cleaning / preparation, as per instructions
of the engineer / recommendation by manufacturer including erection and dismantaling
of scaffolding, working platform etc. Nothing extra shall br payable for repairing &
touch-ups till handing over.

Sqm

745

150

111817.50

201.00

149835.45

150.00

111,817.50

150.0

111,818

5.00 Providing, making & fixing wooden panelling with 19mm commercial board base with
3mm thick Veneer finished as per the drawing / approved sample including the cost of
mouldings, framing & beading and polishing the same with melamine finish complete in
all respect to the satisfaction of Engineer in charge. The area in plan shall be
measured for the payment. (Typical Lift Lobby ceiling of Tower A & B only)at all
floor levels.

Sqm

1653

3175.00

5247925.75

4255.00

7033046.95 3175.00

5,247,925.75

3175.0

5,247,926

6.00 Providing & fixing 3mm Veneer on apartment Entrance flush door shutter, S.room
shutter and shaft door in Main lift lobby on both faces as per sample approved. The
work shall include removing the door, fixing veneer, fixing margin, melamine polish on
the door, reallignment of doors and refixing on frames. Each faces area shall be
measured separetly.

Sqm

4092

2000

8184840.00

2681.00

10971778.02 2000.00

8,184,840.00

2000.0

8,184,840

7.00 Providing and Fixing 6mm thk. Bevelled edge Float glass mirrors of ATUL, ASAHI
in toilets with backing of 300 micron HDPE film as vapour barrier and 12mm thk
marine plywood. Fixed with 4 screws and wooden pegs all complete, at all floor levels
complete to the satisfaction of Engineeer in charge.

Sqm

2334

3500

8168650.00

4691.00

10948324.90 3500.00

8,168,650.00

TOTAL

55,466,891

74,330,910

55,466,891

Page 35 of 71

3500.0
-

Plant Depric.

Plant Oprn & Fuel

Wooden Shuttering

Steel Shuttering

Testing Charges

8,168,650
55,466,891

DLF Group Housing Project - DLF Primus Sector 82 A


CONCRETE ANALYSIS

PCC

RCC

Total Concrete

74806

Total Duration

36

Months

Start

End

Time Period for concrete

25

Months

Jan-13

Jan-15

Av. Concrete per day

98

Cum

Peak concrete per day (1.5xAv.)

148

Cum

Cum

5745

69061

Machinery Cost

A)

as per PNM Sheet


Operational Cost

B)

as per PNM Sheet


Installation Cost

C)
1

Concrete Batching Plant

Nos

750,000

750,000

Tower Crane

Nos

325,000

1,950,000

Total Cost

2,700,000
Cost per cum

36

Concrete Analysis

320.00
Mix

1:2:4

Cement in Bags
Cement per Bag @ Rs.

300.00

360.00

360.00

408.00

460.00

490.00

M20

M25

M30

M35

M40

M45

M50

4.00

5.00

6.00

7.20

7.20

8.16

9.20

9.80

250.00

1,600

850

1,000

1,250

1,500

1,800

1,800

2,040

2,300

2,450

0.90

0.90

0.81

0.74

0.75

0.75

0.73

0.71

0.71

0.71

1,250.96

1,126

1,126

1,011

923

934

934

916

893

888

888

0.55

0.55

0.53

0.57

0.51

0.51

0.48

0.46

0.46

0.46

729

729

614

614

1,324.55

Fly Ash
Fly Ash per cum

250.00

3.40

C.Sand Qty in cum /cum of concrete


C.Sand per cum

200.00
M7.5

6.40

S. aggr. Qty in cum /cum of concrete


S. aggr. per cum

170.00
1:4:8

696

749

669

669

630

614

80.00

70.00

80.00

80.00

80.00

82.00

1.00

80

70

80

80

80

82

Plasticiser

40.00

115.20

61.20

100.80

179.20

197.60

228.80

228.80

254.80

239.20

254.80

Wastage (Agg + Sand)

3.0%

55.65

55.65

51.21

50.16

48.09

48.09

46.38

45.21

45.06

45.06

Wastage (Cement)

2.0%

32.00

17.00

20.00

25.00

30.00

36.00

36.00

40.80

46.00

49.00

3,658

2,839

2,959

3,246

3,459

3,796

3,737

3,970

4,132

4,301

Total Material
PMV - Depr

399.46

399.46

399.46

399.46

399.46

399.46

399.46

399.46

399.46

399.46

399.46

Operational

122.70

122.70

122.70

122.70

122.70

122.70

122.70

122.70

122.70

122.70

122.70

Scaffolding

35.00

35.00

35.00

35.00

35.00

35.00

35.00

35.00

35.00

35.00

35.00

Fuel

322.69

322.69

322.69

322.69

322.69

322.69

322.69

322.69

322.69

322.69

322.69

Labour

281.84

281.84

281.84

281.84

281.84

281.84

281.84

281.84

281.84

281.84

281.84

Installation cost

36.09

36.09

36.09

36.09

36.09

36.09

36.09

36.09

36.09

36.09

36.09

Lab testing

10.00

10.00

10.00

10.00

10.00

10.00

10.00

10.00

10.00

10.00

10.00

1,207.78 1,207.78

1,207.78

4,866

4,047

Total PMV & Labour


Total Cost With Labour

1:2:4

1:4:8

1,207.78 1,207.78 1,207.78 1,207.78 1,207.78 1,207.78 1,207.78 1,207.78


4,167

M7.5

4,454

M20

4,666

M25

5,004

M30

4,945

M35

5,178

M40

5,340

M45

5,509

M50

DLF GH Project 'The Primus' Sector-82A


S.No

Description

7.00

BRICKWORK

Unit

Qty

Rate

Nos
Bag
Cum
%
Nos
Sqm
Cum

57.50
0.21
0.04
0.10
0.06
1.00
1.00

3.70
250.00
1324.55
99.00
240.00

Sqm
Nos
Rm

14.60
13.00
104.00

Providing and Laying Half brick masonry with 1st class bricks
in superstructure above plinth level at all floor levels in
cement mortar 1:4 (1 cement : 4 coarse sand) with 6 mm dia.
ms bars - 2 no. at every third course embedded in cement
mortar laid in proper line & plumb including hacking of RCC at
junctions, raking of joints, curing and all leads & lifts
complete to the satisfaction of the Engineer. (MS Bars to be
free issued by the Owner)
Bricks
Cement
Coarse Sand
Wastage on cement and sand
Labour for Shifting
Average Labour for laying i/c lifting
Hoist / Scaffolding
Cost per Sqm
Considering 04m x 3.65m area
2 No. of layers of hoop iron at every 3rd course
Total length of bars placed
Cost of 6 mm dia MS bars
Cost of Concrete
Cost of Formwork
Extra Labour
Cost for 13.25 sqm
Cost per Sqm
Total cost per Sqm without labour

8.00

50.00

2028.00

0.48
14.60
14.60

2028.00
138.90
548.61

Nos
Bag
Cum
%
`
Cum
Cum
Cum

486.00
1.25
0.27
5.00%
4.00%
0.50
1.00
1.00

3.70
250.00
1324.55
671.00
1798.00
240.00
20.00

1798
313
358
34
72
120
20
641
3356

Nos
Bag
Cum
%
Sqm
Cum

37.50
0.21
0.03
0.10
1.00
1.00

3.70
250.00
1324.55
94.00

139.00
53.00
41.00
9.00

Sqm
Nos
Rm

14.60
13.00
104.00

Item Same as S.No. 7 above but 75mm thick Brickwork IClass In CM 1:4 (1-cement :4-coarse sand)
Bricks
Cement
Coarse Sand
Wastage on cement and sand
Average Labour for laying i/c lifting
Hoist / Scaffolding
Cost per Sqm
Considering 04m x 3.65m area
2 No. of layers of hoop iron at every 3rd course
Total length of bars placed
Cost of 6 mm dia MS bars
Cost of Concrete
Cost of Formwork
Extra Labour
Cost for 13.25 sqm
Cost per Sqm
Total cost per Sqm without labour

10.00

40.56

73.71
409.71

Providing and Laying Brickwork with 1st class bricks in


foundation & in superstructure above plinth level, at all floor
levels in Cement mortar 1:6 (1 cement : 6 coarse sand) for
walls as well as square and rectangular pillars laid in proper
line & plumb including hacking of RCC at junctions, raking of
joints, curing and all leads & lifts complete to the satisfaction
of the Engineer. The rate is inclusive of providing arched /
curved openings at all levels as per design/ drawings.
Bricks
Cement
Coarse Sand
Wastage on cement and sand
Wastage on Bricks
Shifting of Material
Scaffolding
Hoist
Total cost per Cum without Labour

9.00

Kg
Cum
Sqm
Sqm
Sqm
Sqm

213.00
53.00
46.00
10.00
14.00

242.00

Kg
Cum
Sqm
Sqm
Sqm
Sqm

22.88

50.00

1144.00

0.48
14.60
14.60

1144.00
78.36
320.36

MISC. (STRUCTURE)
Providing, fabricating and fixing / erection M.S. structural
work (like drain cover, sleeves, toilet / kitchen counter
support angle, fresh air duct grill DG exhaust grill) fabricated
from standard sections e.g. M.S. Angles, Plates ,Rolled
Sections such as Channels, Flats, Joists etc. including cutting
to size, drilling, welding , providing and applying a coat of red
oxide primer, chipping of RCC& cost of nuts & bolts but
excluding the cost of providing &fixing dash fastener,
complete as directed.
Cost Per MT
Cost of Structural Steel
Transport/Shifting
Shop Drawing
Nuts & Bolts
Material Wastage
Material Cost
Tools & Plants
Lab testing
Sand Blasting
Fabrication & Erection
Power
Primer - Material
Primer - Labour
Paint - Material
Paint - Labour
Direct Cost
Cost in Kgs

MT
MT
MT
Kg.
%

1.00
1.00
1.00
2.5
2.0%

%
MT
MT
MT
MT
Lit
MT
Lit
MT
MT

2.0%
1
1
1
1
5.71
1
12.00
1
1

200.00
300.00
150.00

200.00
300.00
375.00

875.00
200.00

875.00
q
200.00

18000.00
1500.00
105.00
1000.00

18000.00
1500.00
600.00
1000.00

22175.00
22.18

TILING / MARBLE CHIPS FLOORING

1.00

Providing & Laying of Antiskid Vitrified tiles of specified size &


colour on floors inclusive of cleaning of surface, curing of
surface , wetting of tiles, cutting of edges (with high quality
diamond edge cutting blades of approved make) wherever
required (i/c holes/ cutout for drains), fixing true to proper
line , levels and slope as per approved design on floors in 1: 3
cement sand mortar . The joints to be cleaned, filled and
flushed with white cement using pigment as required as per
instructions and to the complete satisfaction of the Engineer.

1.01

300 X 300 Anti-skid Vitrified tiles, 8mm thick- All Balconies

Sqm

Cost of Tile
Wastage
Cement
Coarse Sand
Wastage of Cement & Sand
Labour for fixing
White Cement
Pigment

Sqm
%
Bag
Cum
%
Sqm
Kg
Sqm

1.00
0.10
0.32
0.05
0.10
1.00
1.20
1.00

Hoist/ scaffolding

Sqm

1.00

14,115
699.66
700.00
250.00
1324.55
141.00
341.62
17.00
15.00

Total cost per sqm


1.02

1302.00

600X 600 Anti-skid Vitrified tiles, 8mm thick- Kitchen & Toilet

Sqm

Cost of Tile
Wastage
Cement

Sqm
%
Bag

Tata Hs

700.00
70.00
80.00
61.00
14.00
342.00
20.00
15.00

8650
1.00
0.10
0.30

699.66
700.00
250.00

700.00
70.00
75.00

Balance Analysis

37/71

Coarse Sand
Wastage of Cement & Sand
Labour for fixing
White Cement
Pigment

Cum
%
Sqm
Kg
Sqm

0.04
0.10
1.00
1.20
1.00

Hoist/ scaffolding

Sqm

1.00

1324.55
132.00
341.62
17.00
15.00

57.00
13.00
342.00
20.00
15.00

Total cost per sqm


1.02

1.03

1292.00

Item same as above 1.01 but 75mm high skirting - Kitchen


Cost of Tile
Cost of cutting
Cost of chamfering
Total cost per sqm
Total cost per Rmt

Sqm
Rmt
Rmt

1.00
10.00
10.00

300x900 Anti-skid Vitrified tiles, 8mm thick- M. Toilet


Cost of Tile @ Rs 65 per Sft
Wastage
Cement
Coarse Sand
Wastage for Cement & Sand
Labour for fixing
White cement
Epoxy Grout
Pigment

Sqm
Sqm
%
Bag
Cum
%
Sqm
Kg
Mtr
Sqm

2882
1.00
0.10
0.30
0.04
0.10
1.00
1.70
4.44
1.00

Hoist/ scaffolding

Sqm

1.00

1292.00
15.00

1292.00
150.00
1442.00
144.20

699.66
700.00
250.00
1324.55
132.00
341.62

700.00
70.00
75.00
57.00
13.00
342.00

5.50
15.00

24.00
15.00

Total cost per sqm

2.01

1296.00

Providing & Laying of Porcelin / Ceramic tiles of specified size


& colour on floors inclusive of cleaning of surface, curing of
surface , wetting of tiles, cutting of edges (with high quality
diamond edge cutting blades of approved make) wherever
required (i/c holes/ cutout for drains), fixing true to proper
line , levels and slope as per approved design on floors in 1: 4
cement sand mortar . The joints to be cleaned, filled and
flushed with white cement using pigment as required as per
instructions and to the complete satisfaction of the Engineer.
Cost of Tile Rs 45/Sqft
Wastage
Cement
Coarse Sand
Wastage for Cement & Sand
Labour for fixing
Grey Cement Slurry
White Cement
Pigment
Hoist/ Scaffolding

Sqm
%
Bag
Cum
%
Sqm
Kg
Kg
Sqm
Sqm

1.00
10.00
0.30
0.04
0.10
1.00
3.30
1.20
1.00
1.00

591.80
592.00
250.00
1324.55
132.00
341.62
20.00

592
59
75
57
13
342
66

15.00

15

Total cost per sqm

4.00

4.01

1219

Providing & Fixing of Porcelin / Ceramic tiles of specified size


& colour on walls/dado inclusive of cleaning of surface,
curing of surface, wetting of tiles, cutting of edges (with high
quality diamond edge cutting blades of approved make)
wherever required, (i/c holes/ cutout for electrical boxes &
sanitary fixtures), fixing in proper line, true to levels and
plumb as per approved design on walls in 1: 3 cement sand
mortar . The joints to be cleaned filled and flushed with white
cement using pigment as required as per instructions and to
the complete satisfaction of the Engineer.
Ceramic Wall Tiles of 300x600 size, 6mm thick - Kitchen &
Toilet
Cost of Tile
Wastage
Cement
Coarse Sand
Wastage for Cement & Sand
Labour for fixing
Grey Cement Slurry
White Cement
Pigment
Hoist/ Scaffolding

Sqm
%
Bag
Cum
%
Sqm
Kg
Kg
Sqm
Sqm

1.00
10.00
0.30
0.03
0.10
1.00
3.30
1.00
1.00
1.00

591.80
592.00
250.00
1324.55
118.00
358.70
20.00

592
59
75
43
12
359
66

15.00

15

Sqm
%
Bag
Cum
%
Sqm
Kg
Kg
Sqm
Sqm

1.00
10.00
0.30
0.03
0.10
1.00
3.30
1.00
1.00
1.00

968.40
968.00
250.00
1324.55
118.00
358.70
10.00

968
97
75
43
12
359
33

15.00

15

Total cost per sqm


4.02

Porcelein Wall Tiles of 300x900 size, 6mm thick - M.Toilet


Cost of Tile
Wastage
Cement
Coarse Sand
Wastage for Cement & Sand
Labour for fixing
Grey Cement Slurry
White Cement
Pigment
Hoist/ Scaffolding

1221

Total cost per sqm

4.03

4.03

1602

Providing & Fixing of Porcelin / Ceramic tiles of specified size


& colour on walls/dado inclusive of cleaning of surface,
curing of surface, wetting of tiles, cutting of edges (with high
quality diamond edge cutting blades of approved make)
wherever required, (i/c holes/ cutout for electrical boxes &
sanitary fixtures), fixing in proper line, true to levels and
plumb as per approved design on walls in 1: 3 cement sand
mortar . The joints to be cleaned filled and flushed with white
cement using pigment as required as per instructions and to
the complete satisfaction of the Engineer.
Ceramic Wall Tiles of 300x300 size, 6mm thick - S.Toilet
Cost of Tile
Wastage
Cement
Coarse Sand
Wastage for Cement & Sand
Labour for fixing
Grey Cement Slurry
White Cement
Pigment
Hoist/ Scaffolding

Sqm
%
Bag
Cum
%
Sqm
Kg
Kg
Sqm
Sqm

1.00
10.00
0.30
0.04
0.10
1.00
3.30
1.20
1.00
1.00

591.80
592.00
250.00
1324.55
132.00
358.70
20.00

592
59
75
57
13
359
66

15.00
5.00

15

Total cost per sqm

5.00

1236

Providing and laying 50 mm average thick Crazy Omani


marble
flooring in Balcony ,rubbed and polished to
granolithic finish including applying wax, under layer average
30mm thick cement motar 1: 4 ( 1 cement :4 coarse sand) and
top layer with Omani marble Crazy (pieces of Omani Marble
are cut on all sides with grinder and arranged in a manner to
have consistent gap between the marble pieces)and marble
chips of O size from Nathdwaralaid incement marble powder
mix
3:1(3
Whitecement
:
1
marble
powder
)
byweightinproportion of 4: 7 ( 4 White cementmarble powder
mix : 7 marble chips )byvolume including cement slurry
etc.complete
as directed. (At all floor levels).Granite
Polishing (if specifically required ) shall be paid extra.

Sqm

13797

Cost of Omani Marble from wastage


Wastage
Cement
Coarse Sand
Marble Powder Mix
White cement
Mable Chips
Rubbing
Pigment

Sqm
%
Bag
Cum
Kg
Kg
Kg
Sqm
Sqm

1.00
20%
0.41
0.06
1.00
1.50
1.00
1.00
1.00

Tata Hs

300
300
-

300
60

140
10

140
10

Balance Analysis

38/71

Average Labour for laying


Hoist/ Scaffolding
Total cost per Sqm

6.00

6.01

7.00

8.00

8.01

8.02

8.03

1.00
1.00

Providing and Fixing Chicken Wire Mesh (150mm wide) at


the junction of RCC & Masonry or as specified, including fixing
with GI nails all complete. (At all floor levels)
Chicken Mesh
Wastage
Labour
Hoist/ scaffolding
Total cost per Sqm

6.00

Sqm
Sqm

Providing and laying 50 mm average thick marble chips


flooring in Service area at stilt & other places rubbed and
polished to granolithic finish including applying wax, under
layer 38mm thick cement concrete 1: 2: 4 ( 1 cement : 2
coarse sand : 4 graded stone aggregate 12.5 mm nominal
size) and top layer 12 mm thick with white marble chips of 2B
size from Nathdwara laid in cement marble powder mix 3:1
(3 Grey cement : 1 marble powder ) by weight in proportion of
4: 7 ( 4 Grey cement marble powder mix : 7 marble chips ) by
volume including cement slurry etc.complete as directed. (At
all floor levels). Granite Polishing (if specifically required)
shall be paid extra.
Item same as above but GreyTerrazo Tile of size (250mm X
250mm ) with Grey Cement and White Marble chips.(
MODERN MAKE ) in Servant Room.
Cost of Grey Terrazo Tile 250x250 @ Rs 30 / Sqft
Wastage
Concrete 1:2:4
Extra cement for neat finish
Granolithic Finish
Cement marble Powder
White cement
White Mable Chips
Rubbing
Pigment
Average Labour for laying
Hoist/ Scaffolding
Total cost per Sqm
Providing & Fixing GreyTerrazo Tile Skirting ( 75mm wide )
with Grey Cement and White Marble chips.( MODERN MAKE )
in Servant Room, rubbed and polishing to granolithic finish
including applying wax polish complete as directed ( at all
floor )
Cost of Tile
Cost of cutting
Cost of chamfering
Total cost per sqm
Total cost per Rmt
Providing & fixing Electro - Hydraulically produced and
processed under automation of specified shade and brand
Terrazo tiles in white cement top wearing layer with 6mm
down white marble chips as per approved sample, in cement
mortar 1:4 including wax polish at all leads and lifts etc.
complete
Cost of Terrazo Tiles as mentioned
Wastage
Cement
Coarse Sand
Granolithic Finish
Cement marble Powder
White cement
White Mable Chips
Rubbing
Pigment
Average Labour for laying
Hoist/ Scaffolding
Total cost per sqm
Item same as 8.00 but for terrazo tile of size 275mm x
250mm x 20mm with 3 nos. grooves of specified size in
staircase treads including wax polish all complete.
Cost of Terrazo Flooring
Groove Cutting
Wax Polish
Total cost per sqm
Item same as 8.00 but for terrazo tile of size 200mm x
200mm x 20mm with 3 nos. grooves of specified size ( if
required ) in staircase landings and service lift lobbies
including wax polish all complete.
Cost of Terrazo Flooring
Groove Cutting
Wax Polish
Total cost per sqm

626
15

626
15
1151

80
12
3

12.00
0.6
3.00
16

RM

133218.90

Sqm
%
Mtr
Mtr

0.15
5%
1.00
1.00

Sqm

1276

Sqm
%
Cum
Bag
Sqm
Kg
Kg
Kg
Sqm
Sqm
Sqm
Sqm

1.00
20%
0.64
0.60
1.00
1.00
2.40
1.00
1.00
1.00
1.00
1.00

Rmt

1403

Sqm
Rmt
Rmt

1.00
10.00
10.00

Sqm

1950.00

Sqm
%
Bag
Cum
Sqm
Kg
Kg
Kg
Sqm
Sqm
Sqm
Sqm

1.00
10%
0.49
0.07
1.00
1.00
2.40
1.00
1.00
1.00
1.00
1.00

140
10
342
5

140
10
342
5
497

Sqm
Rmt
Sqm

1.00
1.00
1.00

497
25
75

497
25
75
597

Sqm
Rmt
Sqm

1.00
1.00
1.00

497
25
75

497
25
75
597

Sqm
Rmt
Rmt

1.00
10.00
10.00

497
25
80

497
250
800
1547
155

Sqm

66015.42

Bag
Cum
Cum
%
sqm
Sqm
Sqm
Sqm

0.08
0.0043
0.0043
20%
1.00
1.00
1.00
1.00

250
1,325
846
30
5
135
10
10

20
6
4
6
5
135
10
10
196

SQM

253505.69

Bag
Cum
Cum
%
sqm
Sqm
Sqm
Sqm

0.11
0.01
0.02
20%
1.00
1.00
1.00
1.00

250
1,325
846
51
5
135
10
10

28
10
13
10
5
135
10
10
221

679
0.15
0.02
20.00
0.15
1.00

250
1,325
57
50
10

29
28
11
8
10

4,720
-

3021

140
10
470
15

140
10
470
15
3656

3,656
25
80

3656
250
800
4706
471

Item same as 8.00 but for terrazo tile skirting 75mm high of
specified size ( if required ) in staircase landings, steps and
service lift lobbies including wax polish all complete.
Cost of Tile
Cost of cutting
Cost of chamfering
Total cost per sqm
Total cost per Rmt
PLASTERING

1.00

Providing and applying 10mm thick cement plaster to ceiling


in cement mortar 1:4 (1cement : 1.33 coarse sand: 2.67 fine
sand) finished smooth in line & level including hacking of RCC
surfaces, making groove at the junction of ceiling & wall and
curing, all lead and lifts including scaffolding all complete to
the satisfaction of the Engineer.(At all floor levels)
Cement
Coarse Sand
Fine Sand
Wastage
Chicken wire mesh
Average Labour for laying
Scaffolding Material
Hoist/ scaffolding
Total cost per Sqm excluding Labour

2.00

12.00

Providing and applying 12/15mm thick cement plaster on


wall/ columns in cement mortar 1:6 (1cement : 2 coarse sand
: 4 fine sand) finished smooth in line & level including hacking
of RCC surfaces and curing, all lead and lifts including
scaffolding all complete to the satisfaction of the Engineer.(At
all floor levels)
Cement
Coarse sand
Fine sand
Wastage
Chicken wire mesh
Labour
Scaffolding Material
Hoist/ scaffolding
Total cost per Sqm
Applying neat cement finish in EWS Toilets
Cement
Coarse sand
Wastage
W/P Co
Chicken wire mesh

Tata Hs

sqm
Bag
Cum
%
Kg
sqm

Balance Analysis

39/71

Hoist/ scaffolding
Total cost per Sqm excluding Labour
Average Labour
Total cost per Cum
KOTA STONE FLOORING
STAIRCASES
Providing & laying 25 mm average thick Kota stone on treads of
steps & landings in staircase, laid on 20 mm thick cement mortar
1:4 (1 cement 4 coarse sand) and jointed with grey cement slurry
mixed with pigment to match the shade of the flooring, including
rubbing and Polishing complete as per the satisfaction to engineer in
charge.
At all floor levels including all lead and lifts.
Single piece in treads of stairscase
Cost of Stone
Wastage
Cement
Coarse Sand
Wastage of Cement & sand
Rubbing & Polishing
Nosing
Labour for Groove Cutting
Grey Cement Slurry
Pigment
Hoist/ Scaffolding
Total cost per Sqm excluding Labour
Average Labour for laying i/c lifting for Tower -B
Total cost per Cum
11.00

Wastage
Labour
Hoist/ scaffolding
Total cost per Sqm
Total cost per Sqm (Skirting)
Providing & laying 20 mm average thick Kota stone in skirting laid
on 12 mm thick cement mortar 1:3 (1 cement 3 coarse sand) and
jointed with grey cement slurry mixed with pigment to match the
shade of the stone, including rubbing and Polishing complete in all
respect as per the satisfaction of Engineer in charge. At all floor
levels including all lead and lifts.
100 mm high skirting in steps profile of staircase
Total cost per Sqm for Tower

Sqm

1.00

10

Cum

1.00

137

10
96
137
233

Sqm
Sqm
%
Bag
Cum
%
Sqm
Mtr
Mtr
Kg
Sqm
Sqm

1,965
1.00
20.00
0.27
0.04
0.10
1.00
2.35
10.00
3.00
1.00
1.00

431
431
250
1,325
119
140
49
39
5
15

Cum

1.00

384

%
Mtr
Mtr

20%
1.00
1.00

1,696
10
10

339
10
10
2055
121
2,176

Rmt

6,502
1,696

394

4,866
250
90

195
21
90
306

4,866
250
90

365
21
90
476

4,866
250
10
90

1946
150
167
900
3163
316

4,866
250
10
100

730
150
17
1000
1897
190

4,866
250
10
90

973
150
167
900
2190
219

2476
495
101
77

431
86
68
52
12
140
116
394
15
15
1,327
369
1,696

CEMENT CONCRETE FLOORING/ SKIRTING


Providing and laying of 40 mm thick Cement concrete
flooring 1:2:4 ( 1 cement : 2 coarse sand : 4 graded stone
aggregate of 12.5 mm nominal size ) finished with a floating
coat of neat cement, below kitchen counter & other locations
as directed. (At all floor levels)
3.00

4.00

Sqm

28830.39

Cum
Bag
Sqm

0.04
0.08
1.00

Sqm

38287.69

SQM
Bag
Sqm

0.08
0.08
1.00

Sqm

6111.30

Cum
Bag
Mtr
Sqm

0.40
0.60
16.67
10.00

Sqm

1323.47

Cum
Bag
Mtr
Sqm

0.15
0.60
1.67
10.00

SQM

2970.00

Cum
Bag
Mtr
Sqm

0.20
0.60
16.67
10.00

Providing, cutting & fixing Imported / Omani marble flooring


(avg rate 230/- per sqft) in Living / Dining, measured from
plaster to plaster, at all floor levels at all leads.

Sqm

20466.97

Cost of Omani Marble 230 / Sqft


Wastage
Cement
Coarse Sand
Marble Powder Mix
White cement
POP protection
Rubbing
Pigment
Average Labour for laying

Sqm
%
Bag
Cum
Kg
Kg
Sqm
Sqm
Sqm
Sqm

1.00
20%
0.41
0.06
1.00
2.40
1.00
1.00
1.00
1.00

2,476
2,476
250
1,325
17
50
140
10

Hoist/ Scaffolding
Total cost per Sqm

Sqm

1.00

15

Sqm

24848.26

Sqm

1.00

Concrete of 1:2:4
Extra cement
Extra labour
Total cost per Cum
Providing and laying of 75 mm thick Cement concrete
flooring 1:2:4 ( 1 cement : 2 coarse sand : 4 graded stone
aggregate of 12.5 mm nominal size ). The surface will be
finished with a nylon brush and the flooring shall be laid in
required slope. (At all floor levels) (In Basement and Stilt
floor)
Concrete of 1:2:4
Extra cement
Extra labour
Total cost per Cum
Providing and laying IPS Flooring of 40mm thickness in M/c
Room and Terrace Corridor , Electrical shaft, FHC shaft & Shop
etc., all complete wherever specified. (At all floor levels)

4.01

Considering 10 Sqm area


Cement concrete 1:2:4
Extra cement for neat finish
Extra for PVC strip
Extra for levelling and finishing
Total cost for 10 sqm
Total cost per sqm
Providing and laying IPS skirting 12/15mm thick ( 75 mm
high ) & finished with neat cement complete as directed in
M/C room & Bed rooms.(At all floor levels)
Considering 10 Sqm area
Cement concrete 1:2:4
Extra cement for neat finish
Extra for PVC strip
Extra for levelling and finishing
Total cost for 10 sqm
Total cost per sqm

1.00
1.01

Providing and laying IPS Flooring of 20mm avg. thickness on


service slab including making a gentle slope away from the
wall towards the free end of slab. (At all floor levels)
Considering 10 Sqm area
Cement concrete 1:2:4
Extra cement for neat finish
Extra for PVC strip
Extra for levelling and finishing
Total cost for 10 sqm
Total cost per sqm
APARTMENTS flooring, skirting
Providing, cutting , Laying , fixing and polishing stone of
18+/-2 mm thickness or other on 1: 4 cement sand base
mortar laid to the required slope & in required pattern.The
stone shall be taken to match the grains of stone work . For
purpose of matching the grains , the stone slabs shall be
selected judiciously having uniform pattern of veins / streaks
The area to be laid shall be reproduced on the ground and
the stone slabs laid in position and arranged in the manner to
give the desired matching of grains . Any adjustment needed
for achieving the best results shall be then carried out by
replacing or interchanging the particular slabs . pattern &
Strips less than 150 mm width shall be extra.

Extra over item no. 1.01 for mirror polishing with synthetic
carborandum stones
Mirror Polishing

Tata Hs

726

125.00

41
50
140
10
726
15
4131

125
125

Balance Analysis

40/71

Providing, cutting , Laying , fixing upto 100 mm high skirting


with cement mortar marble/granite of specified thickness or
other thickness as specified at all levels as per approved
design / pattern as detailed in the drawing / instructions of
the Engineer . The stone shall be fixed in position without
the use of chips or under pinning of any sort . (At all floor
levels) Polishing to be paid extra.

Rmt

548.93

Sqm
Rmt
Rmt

1.00
20.00
10.00

Sqm

4870.5

Sqm
%
Bag
Cum
Sqm
Sqm
Sqm
Kg
Sqm
Sqm

1.00
0.12
0.45
0.06
1.00
1.00
1.20
1.00
1.00

597.84
110
100
10
5

Rmt
Sqm
Rmt
Rmt

6876
1.00
20.00
13.33

723
20
50

723
400
667
1790
179

Sqm

2661

Sqm
%
Bag
Cum
Sqm
Nos
Sqm
Kg
Sqm
Sqm
Sqm

1.00
25%
0.27
0.04
1.00
4.00
1.00
2.20
1.00
1.00
1.00

2,476
2,476
250
1,325
215
75
25
15
10
939
15

2476
619
68
52
215
300
25
33
10
939
15
4752

1.00
20.00
13.33

4,131
15
30

4131
300
400
4831
483

1,614
1,453
250
1,325
150
10

1453
145

120
939
15

180
939
15
2892
3213

2,476
2,228
250
1,325
150
600
17
10
130
120
1,025
15

2228
446

Imported / Omani Beige Marble (avg rate 230/- per sqft)


skirting 100 mm high
Cost of Marble Flooring
Cost of cutting
Cost of chamfering
Total cost per sqm
Total cost per Rmt

4.00
4.01

5.00
5.01

Typical Lift Lobby


Providing, cutting , Laying , fixing and polishing stone of
18+/-2 mm ( not less then 18mm ) thickness and / or other
thickness as specified at all levels as per details in the
drawing / instructions of the Engineer on 1: 4 cement sand
base mortar laid to the required slope & in required
pattern.The stone shall be fixed with mortar in position
without the use of chips or under pinning of any sort . Care
shall be taken to match the grains of stone work . For purpose
of matching the grains, the stone slabs shall be selected
judiciously having uniform pattern of veins / streaks The area
to be laid shall be reproduced on the ground and the stone
slabs laid in position and arranged in the manner to give the
desired matching of grains . Any adjustment needed for
achieving the best results shall be then carried out by
replacing or interchanging the particular slabs . Special care
shall be taken to achieve the continuity of grains between
the two slabs , one above the other along the horizontal
joints . (Strips less than 150 mm width will only be measured
as bands/borders in RM and Strips of width 150 mm & above
shall be measured in SQM.)
Indian Marble (Avg base rate 65/- per sqft), measured from
plaster to plaster, at all floor levels at all leads.
Cost of Stone
Wastage
Cement
Coarse Sand
Extra for lift for Average 31 floors
Rubbing & Polishing
Silicon Based Water Repellent Coating
White cement
Pigment
Hoist/ Scaffolding
Total cost per sqm
Providing, cutting , Laying , fixing upto 75 mm high skirting
with cement mortar marble / granite of specified thickness or
other thickness as specified at all levels as per approved
design / pattern as detailed in the drawing / instructions of
the Engineer . The stone shall be fixed in position without
the use of chips or under pinning of any sort . (At all floor
levels) Polishing to be paid extra.
Indian Marble Avg base rate 65/- per sqft
Cost of Indian Marble as per flooring items
Cost of cutting
Cost of chamfering
Total cost per sqm
Total cost per Rmt

4,131
20
80

4131
400
800
5331
533

598
110

10
5
723

Supply, Cutting and Fixing of 18mm thick Polished Granite/


Marble of Approved Shade in cladding of Atrium / lift lobbies
and walkways etc over 35mm thick Cement Mortar 1:3 in
Proper line and level and as per pattern shown in drawing.
The rate includes providing white cement, pigment, POP for
fixing stone,P & F150 mm and Stainless Steel/ copper clamps
shall be paid extra)

2.00

Imported / Omani Marble (avg rate 230/- per sqft) Lift


Jambs, Sills & Soffit
Cost of Stone
Wastage
Cement
Coarse Sand
Rubbing & Polishing
Extra for SS cramps, Pins, etc
Grouting Material / Araldite
White cement
Pigment
Average Labour for laying
Hoist/ Scaffolding
Total cost per Sqm
Imported / Omani Beige Marble (avg rate 230/- per sqft)
Rmt
skirting 100 mm high
Cost of Imported Marble as per flooring items
Cost of cutting
Cost of chamfering
Total cost per sqm
Total cost per Rmt
STONE WORK
Providing & Fixing Pre-polished Beige Granite worktop slab
over Counter with Araldite on Modular Kitchen Top board
(board is part of Modular Kitchen) excluding Cutting Holes for
Sink & Mixer.
Cost for 1.5m x .6m
Cost of Stone
Wastage
Cement
Coarse Sand
Araldite Compound
White cement
Pigment
Silicon Based Water Repellent Coating
Extra for edge polishing & moulding
Average Labour for laying
Hoist/ Scaffolding
Total cost
Total cost per Sqm
Providing & Fixing worktop of 19mm thick Pre-polished Omani
beige marbles over 12mm thick waterproof ply with araldite
(Toilet).
Cost for 1.5m x .6m
Cost of Omani beige marbles
Wastage
Cement
Coarse Sand
Araldite Compound
Waterproof Ply
White cement
Pigment
Silicon Based Water Repellent Coating
Extra for edge polishing & moulding
Average Labour for laying
Hoist/ Scaffolding
Total cost
Total cost per Sqm
Providing and fixing e Omani Marble ledge area including
edge chamfering, edge polish, mirror polish & resin filling all
complete and as per instructions of project in charge.
Cost of Omani beige marbles
Wastage

Tata Hs

3991
Sqm
Rmt
Rmt

Sqm

797

Sqm
Sqm
%
Bag
Cum
Sqm
Kg
Sqm
Sqm
Rm
Cum
Sqm
Sqm
Sqm

0.90
0.90
10%
0.27
0.04
1.00
2.20
1.00
1.00
1.50
1.00
1.00
0.90
1.00

Sqm

1641.49

Sqm
Sqm
%
Bag
Cum
Sqm
Sqm
Kg
Sqm
Sqm
Rm
Cum
Sqm
Sqm
Sqm

0.90
0.90
20%
0.27
0.04
1.00
1.00
2.20
1.00
1.00
1.50
1.00
1.00
0.90
1.00

Rmt

4455.65

Sqm
Sqm
%

1.00
1.00
20%

2,476
2,476

150
10

150
600
37
10
130
180
1025
15
4821
5357

2476
495

Balance Analysis

41/71

1.00
1.01

Cement
Coarse Sand
Araldite Compound
Waterproof Ply
White cement
Pigment
Silicon Based Water Repellent Coating
Extra for edge polishing & moulding
Average Labour for laying
Hoist/ Scaffolding
Total cost
Total cost per Sqm
Total Cost per Rmt

Bag
Cum
Sqm
Sqm
Kg
Sqm
Sqm
Sqm
Cum
Sqm
Sqm
Sqm

0.30
0.04
1.00
1.00
2.20
1.00
1.00
1.00
1.00
1.00
1.00
1.00

250
1,325
50

75
57
50

17
10
130
200
1,025
15

37
10
130
200
1025
15
4570
4570

285.00
1482.00
1511.64
70.00
50.00
175.00
50.00
70.00
2305.87

1482
29.64
30.23
420
50
175
30
89
115.29
2,421
465.61
62,289

285.00
1482.00
1511.64
70.00
50.00
175.00
50.00
70.00
2327.87

1482
29.64
30.23
420
50
175
39
102
116.39
2,444
470.05
48,210
9,271

DOOR, WINDOW & HARDWARE


Providing & Fixing Red Mirranti or other specified & approved
Hard-Wood door frames of size 100 x 50mm in proper
alignment / vertical to the plumb including providing & fixing
6 nos. of M. S. hold fasts / Dash fasteners per frame
including cutting of Block masonry and casting of concrete
blocks of size 300*100*150mm in C.C. 1:2:4 . The item
includes mixing and placing of concrete complete as per
instructions of the Engineer . No escalation shall be payable
for Hold fasts. At all floor levels.
Item same as Sno. 1.00 above but of finished size 115mm x
65mm.
Door Frame 900 x2150 mm -115x65mm
Cost of wood
Add for taxes
Wastage
Hold fast i/c Dash Fastner
Labour for making
Labour fixing
Termite proof paint i/c Wood primer
Synthetic Enamel Paint
Add for sub contractor margin
Total cost For rmtr
Total cost For rmtr
Cost per cum
Cost per Rmt
Item same as Sno. 1.00 above but of finished size 150mm x
65mm.
Door Frame 900 x2150 mm -150x65mm
Cost of wood
Add for taxes
Wastage
Hold fast i/c Dash Fastner
Labour for making
Labour fixing
Termite proof paint i/c Wood primer
Synthetic Enamel Paint
Add for sub contractor margin
Total cost For rmtr
Total cost For rmtr
Cost per cum
Cost per Rmt

RM

22436.00

1.372
Mtr
%
%
Nos
Nos
Nos
Sqm
Sqm
%
Mtr
Mtr
Cum

5.2
5.2
2
2
6
1
1
0.60
1.27
5
5.20
1
1

RM

4024.80

1.790
Mtr
%
%
Nos
Nos
Nos
Sqm
Sqm
%
Mtr
Mtr
Cum

5.2
5.2
2
2
6
1
1
0.78
1.46
5
5.20
1
1

Supply and Fixing 35mm thick, solid core flush door shutters
(commercial ply veneer 3mm thick on both faces) of specified
size & thickness including cost of providing & fixing hard
wood lipping , excluding door hardwares cutting / re-sizing of
door if necessary complete as specified. At all floor levels.

SQM

11537.00

Door Shutter width


Door Shutter Hight
Door Shutter Area

Mtr
Mtr
Sqm

0.67
2.04
1.37

2.21
6.68

Sqm
%
Cft
Sheet
%
Sqm
No.'s
No.'s
No.'s
No.'s
%

1.37

1250.00
1713.00
1300.00

Supply and Fixing 35mm thick, solid core flush door shutters
(commercial ply veneer 3mm thick on both faces) of specified
size & thickness including cost of providing & fixing hard
wood lipping, excluding door hardwares, cutting / re-sizing of
door if necessary complete as specified. At all floor levels.

SQM

12342.41

Door Shutter width


Door Shutter Hight
Door Shutter Area

Mtr
Mtr
Sqm

0.87
2.09
1.82

2.87
6.85

Sqm
%
Cft
Sheet
%
Sqm
No.'s
No.'s
No.'s
No.'s
%

1.82
3.00
0.19
2.00
0.02
4.37
1.00
1.00
1.00
3.00
0.10
1.82

1500.00
2730.00
1800.00

Sqm

83.39

Mtr
Mtr
Sqm

0.77
2.04
1.58

2.54
6.68

Sqm
%
Cft
%
No.'s
Per Shutt
Per Shutt
Sqm
%

1.58
3%
0.10
2
3
1
1
3.79
10
1.58

1300.00
2054.00
2124.04
2318.00
60.00
100.00
250.00

2054
62
202
46.36
180
100
250

2894.36

289.44
3,184
2,015

RM

3787.00
0.025
2
10
1
1
0.084
5
1.00

1274.43
32.00
32.64
8.00
7.00
500.00
92.90

32
0.64
3.26
8
7
42
4.65
98

Cost of Door shutter 35mm thick


Rebate
Add for lipping
Add for veener
Add for Taxes
Add for Melamine Polish
Labour charge for making
Labour charge for Fixing
Labour charge for hardware Fixing
Hinges
Add for sub contractor margin 5%
Cost of Door shutter 35mm thick

Cost of Door shutter 38mm thick


wastage
Add for lipping
Add for veener
Add for Taxes
Add for Melamine Polish
Labour charge for making
Labour charge for Fixing
Labour charge for hardware Fixing
Hinges
Add for sub contractor margin 5%
Cost of Door shutter 38mm thick
Supply and Fixing of flush door shutters of specified size &
25mm thickness including cost of providing & fixing hard
wood lipping , providing & fixing 3 nos. MS hinges 75mm long
and shaft lock fixing, Cutting / re-sizing of door if necessary
complete as specified. in lift lobby for LV, FHC & AC shaft At
all floor levels.
Considering O/A door size 900 x 2100
Door Shutter
Door Shutter width
Door Shutter Hight
Door Shutter Area
Door Shutter
Wastage
Lipping
Add for Taxes
Hinges
Labour charge for making
Labour charge for Fixing
Melmine polish
Add for sub contractor margin
Cost of Door shutter 25mm thick
Supply & fixing of Pre-fabricated moulded Architrave at the
junction of door frame & wall, made out of hard wood of
specified size as per approved design.
Rectangular Archirave 60mm x 12mm
Cost of wood
Add for taxes
Wastage
Labour for making
Labour fixing
Ducco Paint
Add for sub contractor margin 5%
Total cost For rmtr

Tata Hs

Cft
%
%
Mtr
Mtr
Sqm
%
Mtr

0.10
2.00
0.02
3.29
1.00
1.00
1.00
3.00
0.05
1.37

1713
131

1844.00

37

100.00
200.00
75.00
85.00
2511

100
200
75
255
126
2,637
1,925

2730
81.9
343

3154.90

63

150.00
300.00
75.00

150
300
75

3743

374
4,117
2,262

Balance Analysis

42/71

Rectangular Architrave 40mm x 12mm


Cost of wood
Add for taxes
Wastage
Labour for making
Labour fixing
Ducco Paint
Add for sub contractor margin 5%
Total cost For rmtr

Nos.
Cft
%
%
Mtr
Mtr
Sqm
%
Mtr

3787.00
0.017
2
10
1
1
0.064
5
1.00

Sqm

94,358

Bag
Cum
Cum
%
Sqm
Sqm
Kg
Sqm
Sqm
Sqm

0.13
0.014
0.014
20.00
1.00
1.00
0.13
1.00
1.00
1.00

Making Groove in internal plaster of size including finishing


the edges all complete. The groove shall be made true to the
approved profile. Above 6 mm x 6 mm upto 8 mm x 8 mm

Rmt

18,559

Providing and fixing chicken wire mesh at the junction of RCC


& masonry or as specified, including fixing with GI nails all
complete. ( At all floor levels ) chicken wire mesh ( 4" wide )

Sqm

71,905

Sqm

788

Sqm
%
Bag
Cum
Kg
Sqm
Sqm
Sqm
Sqm
Sqm
Sqm

1.00
20.00
0.29
0.04
1.00
1.00
1.00
1.00
1.00
1.00
1.00

1274.43
22.00
22.44
8.00
7.00
500.00
71.68

22
0.44
2.24
8
7
32
3.58
75

250
1,325
846
64
5
239
60
3
10
40

33
19
12
13
5
239
8
3
10
40
382

3,766
3,766
18
726
140
15
60
12

3,766
753
18
726
140
15
60
12
5,490

2,690
2,690
18
726
100
246
140
15

2,690
538
18
726
100
579
140
15
12
4,818

A.5
Providing and applying -- PLASTER 18 MM EXTERNAL -- On
flat / curved surface in two coats, under layer of 12 mm
thickness in cement plaster 1 : 5 ( 1Cement : 5 coarse sand )
and top layer 6mm thickness in cement plaster 1 : 6 (
1cement : 3 fine sand : 3 coarse sand ) mixing of Cico No. 1
water proofing agent in cement mortar @ 2% by weight of
cement, making drip course, edges, hacking of RCC surface
and curing, all lead & lifts including scaffolding all complete to
the satisfaction of the Engineer. PLASTER 18 MM EXTERNAL
Cement
Coarse Sand
Fine Sand
Wastage
Chicken wire mesh
Average Labour for laying i/c lifting
W/P Co
Labour for Hacking
Labour for Scaffolding
Hoist/ scaffolding
Total cost per Sqm

Providing, cutting , Laying , fixing and polishing stone of 19


mm thickness
and / or other thickness as specified at all levels as per details in
the drawing
Providing, Cutting & fixing of Marble/granite slab in flooring of size >
16"x16" at
ground floor level. Any white cement bedding for white translucent
marble shall
be paid extra.The rate shall be applicable at all lead & lifts. (At all
floor levels)
Providing & laying Light Emperdor Marble flooring at ground
floor Entrance Hall.
( Basic rate - Rs.350 /Sft )
Cost for stone (Light Emperador)
Wastage
Cement
Coarse Sand
White cement
Labour for fixing
Labour for mirror polishing
Pigment
Extra for protection
Hoist/ Scaffolding
Total cost
Providing & laying Omani Beige Marble flooring in Duplex
Staircase
( Basic rate - Rs.250/Sft )
Cost for stone (Light Emperador)
Wastage
Cement
Coarse Sand
White cement
Labour for fixing
Extra for staircase
Extra for nosing
Labour for mirror polishing
Pigment
Extra for protection
Hoist/ Scaffolding
Total cost

Sqm

191

Sqm
%
Bag
Cum
Kg
Sqm
Sqm
Mtr
Sqm
Sqm
Sqm
Sqm
Sqm

1.00
20.00
0.29
0.04
1.00
1.00
1.00
2.35
1.00
1.00
1.00
1.00
1.00

Mtr

261

Sqm
Mtr
Rmt

0.10
1.00
1.00

Mtr

146

Sqm
Mtr
Rmt

0.10
1.00
1.00

12

Providing, cutting ,
Laying ,
fixing upto 100 mm high
skirting/border with cement
mortar marble/granite of specified thickness or other thickness as
specified at
all levels as per approved design / pattern as detailed in the
drawing /
instructions of the Engineer . The stone shall be fixed in position
without the
use of chips or under pinning of any sort . (At all floor levels)
Polishing to be
Providing & laying Light Emperdor Marble Skirting at ground
floor Entrance Hall.
( Basic rate - Rs.350/Sft )
Same as above
Extra for skirting
Total cost

5,490
49

549
49
598

4,818
79

482
79
561

3.00
Providing & laying Omani beige Marble Skirting in Duplex
staircase
( Basic rate - Rs.250/Sft )

Same as above
Extra for skirting
Total cost

Providing, cutting , Laying & fixing Marble/ Pre-Polished granite of


19 mm
thickness or other thickness as specified at all levels in DADO /
CLADDING as
per approved design / pattern as detailed in the drawing /
instructions of the
Engineer on 1:3 cement sand base mortar. The stone shall be fixed
with mortar
in position without the use of chips or under pinning of any sort .
Care shall be
taken to match the grains & shade of stone work . Any white cement
application
behind white/ translucent marble shall be paid extra. (At all floor
levels)

Tata Hs

Balance Analysis

43/71

Pre-Polished Granite Claddinng ( Basic rate -Rs.150


4.00

/Sft )

Cost of Stone
Wastage
Cement
Coarse Sand
Labour for fixing
SS Cramps
White Cement
Pigment
Hoist/ Scaffolding
Total cost per Sqm

Sqm

398

Sqm
%
Bag
Cum
Sqm
Nos
Sqm
Sqm
Sqm

1.00
10.00
0.29
0.03
1.00
3.00
1.00
1.00
1.00

Sqm
Sqm
Sqm
%
Bag
Cum
Sqm
Kg
Sqm
Each
Rm
Sqm
Sqm
Sqm

821
0.90
0.90
10.00
0.29
0.04
1.00
2.20
1.00
1.00
1.50
1.00
0.90
1.00

1,614
1,614
726
55
18
15
12

1,614
161
726
165
18
15
12
2,711

1,614
1,453
726
18
15

1,453
145
726
40
15
150
12
2,541
2,823

Providing , Cutting , Laying and fixing


pre-polished (Mirror
polished)
Granite/Marble of 19 mm thickness at all levels as per approved
design /
pattern as detailed in the drawing / instructions of the Engineer
with 1: 3
cement sand mortar . The granite shall be fixed with mortar in
position without
the use of chips or under pinning of any sort . (At all floor levels)

Granite slab in counters excluding cutting holes for basin, mixer but
including
edge polishing.( Basic rate - Rs.150/Sft )
Cost for 1.5m x .6m
Cost of Stone
Wastage
Cement
Coarse Sand
Labour for fixing
White cement
Pigment
Extra for making hole for wash basin and mixer
Extra for edge polishing & moulding
Hoist/ Scaffolding
Total cost
Total cost per Sqm

100
12

Light Emperdor Marble slab in counters & facias excluding cutting


holes for basin,
mixer but including edge polishing.( Basic rate -

6.000

Sqm

317

Cost for 1.5m x .6m


Cost of Stone
Wastage
Cement
Coarse Sand
Labour for fixing
White cement
Pigment
Extra for making hole for wash basin and mixer
Extra for edge polishing & moulding
Hoist/ Scaffolding
Total cost
Total cost per Sqm

/Sft )

Sqm
Sqm
%
Bag
Cum
Sqm
Kg
Sqm
Each
Rm
Sqm
Sqm
Sqm

0.90
0.90
15.00
0.29
0.04
1.00
2.20
1.00
1.00
1.50
1.00
0.90
1.00

Granite slab in facias including edge polishing.( Basic rate /Sft )

Rmt

212

Marble in facias including edge polishing.( Basic rate /Sft )

Rmt

101

Extra over item No. 4.0 for cutting holes for wash basin including
edge
polishing.

Nos

804

Extra over item No. 4.0 for cutting holes for CP fittings

Nos

804

Sqm
Sqm
%
Bag
Cum
Sqm
Kg
Sqm
Sqm

18,220
1.00
5.00
0.26
0.04
1.00
1.00
1.00
1.00

(Make )
(Basic rate -Rs.30/Sft )
Cost of Tile
Wastage
Cement
Coarse Sand
Labour for fixing
White Cement
Pigment
Hoist/ Scaffolding
Total cost per Sqm

Sqm
Sqm
%
Bag
Cum
Sqm
Sqm
Sqm
Sqm

2,622
1.00
5.00
0.27
0.04
1.00
1.00
1.00
1.00

Item same as item 6.0 above but upto 100mm high skirting.

Rmt

8,967

Same as above
Extra for skirting
Total cost

Sqm
Mtr
Rmt

0.10
1.00
1.00

Providing , laying & fixing of ceramic tiles 7.5mm thick of specified


size & colour
on floors inclusive of cleaning of site , curing of surface , wetting
of tiles,
cutting of edges wherever required, fixing true to proper line ,
levels, and slope as
per approved design on floors in 1: 3 cement sand mortar . The
joints to be
cleaned filled and flushed with white cement using pigment as
required as per
instructions and to the complete satisfaction of the Engineer. (At
all floor
Levels).
(Make )
( Basic rate - Rs.30/Sft )
Cost of Tile
Wastage
Cement
Coarse Sand
Labour for fixing
White Cement
Pigment
Hoist/ Scaffolding

Sqm
Sqm
%
Bag
Cum
Sqm
Kg
Sqm
Sqm

4,204
1.00
5.00
0.26
0.03
1.00
1.00
1.00
1.00

TILE FLOORING / SKIRTING


Providing & Laying of Vitrified tile flooring of 7.5mm th. And
specified size to true
levels, alignment & slope over base mortar (1:4) cement & sand
mortar laid to the
required slope . White cement & pigment also in required quantity
shall be
arranged by the Contractor at his own cost. (At all floor Levels)(Item
rate Base
upon 5% wastage)
(Make )
( Basic rate - Rs.60/Sft )
Cost of Tile
Wastage
Cement
Coarse Sand
Labour for fixing
White Cement
Pigment
Hoist/ Scaffolding
Total cost per sqm

3,766
3,389
725
18
15
100
12

3,389
508
725
40
15
150
12
4,839
5,377

645.60
646.00

646
32

307.46
18.00
15.00
12.00

307
18
15
12
1030

323
323
325
18
15
12

323
16
325
18
15
12
709

709
10

71
10
81

322.80
323.00

323
16

307.46
18.00
15.00
12.00

307
18
15
12

Providing & Laying of Vitrified tile Cladding of 7.5mm th.and


specified size to true
levels, alignment & slope over base mortar (1:4) cement & sand
mortar laid to the
required slope . White cement & pigment also in required quantity
shall be
arranged by the Contractor at his own cost. (At all floor Levels)

7.010

Tata Hs

Balance Analysis

44/71

Total cost per sqm


Item same as above-7.0 but for kitchen, 100mm high skirting .
(Item rate Base upon 10% wastage)
Same as above
Extra for skirting
Total cost

9.000

Providing , laying & fixing of 6mm thick ceramic tiles of specified


size &
colour on walls inclusive of cleaning of surface, curing of surface ,
wetting
of tiles, cutting of edges wherever required, fixing in proper line ,
levels and
plumb as per approved design on walls in 1: 3 cement sand mortar
. The
joints to be cleaned filled and flushed with white cement using
pigment as
required as per instructions and to the complete satisfaction of
the
Engineer. (At all floor Levels)
(Make )
( Basic rate -Rs.33/Sft )
Cost of Tile
Wastage
Cement
Coarse Sand
Labour for fixing
White Cement
Pigment
Hoist/ Scaffolding
Total cost per sqm

Providing , laying, fixing grinding & wax polishing of 20mm thick


Grey terrazo tiles
of specified size & colour on floos inclusive of cleaning of surface,
curing of
surface , wetting of tiles, cutting of edges wherever required, fixing
in proper line ,
levels and plumb as per approved design on floors in 1:4 cement
sand mortar .
The joints to be cleaned, filled and flushed with white cement
using pigment as
required as per instructions and to the complete satisfaction of
the Engineer.
( Basic rate - Rs.30/Sft )
(At all floor Levels) (Item rate Base upon 5% wastage)
9.010 Cost of Tile
Wastage
Cement
Coarse Sand
Labour for fixing
White Cement
10.000 Wax Polishing
Pigment
Hoist/ Scaffolding
Total cost per sqm
Item same as item 9.00 above but upto 100mm high skirting
in Staircase
Same as above
Extra for skirting
Total cost
11.00

12.00

CC FLOORING / SKIRTING
Providing and laying of 40 mm thick Cement concrete
flooring 1:2:4 ( 1
cement : 2 coarse sand : 4 graded stone aggregate of 12.5
mm nominal size )
finished with a floating coat of neat cement, below kitchen
counter & other
locations as directed.. (At all floor Levels)
Cost of 1:2:4 Concrete
Extra Labour
Extra for panels
Cement Slurry
Total Cost per Cum
Same as item no. 10.00 above but 50mm thick flooring including
making panels of
size 1500mm * 1500mm or as specified including providing &
applying "CICO
Emalite RTU" @4kg/m2 to 5kg/m2 as per Manufacturer's
instruction for Parking at
Stilt.
Cost of 1:2:4 Concrete
Extra Labour for panel
Extra Labour
Emalite RTU
Cement Slurry
Total Cost per sqm

691

Rmt
Sqm
Mtr
Rmt

7,441
0.10
1.00
1.00

Sqm
Sqm
%
Bag
Cum
Sqm
Kg
Sqm
Sqm

13,595
1.00
5.00
0.26
0.03
1.00
1.00
1.00
1.00

Sqm
Sqm
%
Bag
Cum
Sqm
Kg
Sqm
Sqm
Sqm

2,649
1.00
5.00
0.26
0.03
1.00
1.00
1.00
1.00
1.00

Rmt

2,480

Sqm
Mtr
Rmt

0.10
1.00
1.00

Sqm
Cum
Sqm
Mtr
Kg

691
7

69
7
76

355.08
355.00

355
18

229.47
18.00
10.00
12.00

229
18
10
12
642

322.80
323.00

323
16

341.62
18.00
70.00
10.00
12.00

342
18
70
10
12
791

791
7

79
7
86

13,244
0.04
1.00
0.67
4.40

3,997
80
15
6

160
80
10
26
276

Sqm
Cum
Mtr
Sqm
Kg
Kg

11,631
0.05
0.67
1.00
5.00
4.40

3,997
15
80
23
6

200
10
80
115
26
431

Sqm

13,244

Sqm
Sqm

1
1

645.60
70.00

646
70
716

3,997
6
25
75

1,599
3
417
750
2,769
277

13.00
Extra over item Nos. 10.00 for providing extra smooth & levelled
surface for
laminated wooden flooring. This item shall be payable only where
laminated
wooden flooring has to be laid. (At all floor Levels)
Material Cost
Labour
Total Cost per sqm

14.00

33.00

Providing and laying IPS Flooring of 40mm thickness in M/c Room


and
Terrace Corridor , Electrical shaft, FHC shaft & Shop etc., all
complete
wherever specified.
(At all floor Levels)
Considering 10 Sqm area
Cement concrete 1:2:4
Extra cement for neat finish
Extra for glass strip
Extra for levelling and finishing
Total cost for 10 sqm
Total cost per sqm

Sqm

446

Cum
Bag
Mtr
Sqm

0.40
0.44
16.67
10.00

Rmt

40,230

Rmt

10,296

0.918
Mtr
%
%

5.2
5.2
2
2

Providing & fixing in position glass strip of size 40x4mm in flooring


so as to
form panels of specified sizes, as per approved pattern all complete.
(At all floor Levels)
DOORS & WINDOWS
Providing & Fixing Champ-wood or other specified & approved HardWood door
frames of size 100 x 50mm in proper alignment / vertical to the
plumb including
providing & fixing 6 nos. of M. S. hold fasts / Dash fasteners per
frame
including cutting of Block masonry and casting of concrete blocks of
size
300*100*150mm in C.C. 1:2:4 . The item includes mixing and
placing of concrete
complete as per instructions of the Engineer . No escalation shall
be payable
for Hold fasts. At all floor levels.
Door Frame 900 x2150 mm -150x50mm
Cost of wood
Add for taxes
Wastage

Tata Hs

280.00
1456.00
1485.12

1,456.00
29.12
29.70

Balance Analysis

45/71

34

Hold fast i/c Dash Fastner


Labour for making
Labour fixing
Termite proof paint i/c Wood primer
Synthetic Enamel Paint
Add for sub contractor margin
Total cost For rmtr
Total cost For rmtr
Cost per cum
Rate per Mtr

Nos
Nos
Nos
Sqm
Sqm
%
Mtr
Mtr
Cum
Mtr

Supply and Fixing of 35mm solid core flush door shutters


(commercial ply veneer
3mm thick on both faces) of specified size & thickness including cost
of providing
& fixing hard wood lipping , providing & fixing 4 nos. MS hinges
100mm long,
cutting / re-sizing of door if necessary complete as specified. (4
hinges per
shutter). At all floor levels.
Door Shutter width
Door Shutter Hight
Door Shutter Area

2.21
6.68

1.370

Sqm
%
Cft
%
Sqm
No.'s
No.'s
No.'s
No.'s
%

1200.00
1644.00
1200.00
1774.95
70.00
100.00
100.00
75.00
75.00
2820

0.109
13.5
3.288
1
1
1
4
5
1.370
Sqm

1,644.00
130.95
239.62
230.16
100.00
100.00
75.00
300.00
140.99
2,960.72
2,161.11

Sqm

462

Door Shutter width


Door Shutter Hight
Door Shutter Area

0.674
2.037
1.370

Mtr
Mtr
Sqm

2.21
6.68

Cost of Door shutter 35mm thick


Rebate
Add for lipping - 6mm thk Red Marandi
Add for Taxes
Add for Enamel paint
Labour charge for making
Labour charge for Fixing
Labour charge for hardware Fixing
Hinges
Add for sub contractor margin 5%
Cost of Door shutter 38mm thick
Total cost per sqm

1.370

Sqm
%
Cft
%
Sqm
No.'s
No.'s
No.'s
No.'s
%

2000.00
2740.00
2000.00
2958.25
70.00
75.00
200.00
75.00
85.00
4278

2,740.00

333.33
333.33
378.33
397.25
3,095.22
25.00
100.00

333.33
45.00
18.92
19.86
30.95
25.00
100.00
573.06

320.00
320.00
363.20
381.36

320.00
43.20
18.16
19.07

100.00

100.00
500.43

0.109
13.5
3.288
1
1
1
4
5
1.370
Sqm

Providing and laying Precast concrete kerb stone of size 300 mm x


450 mm x 150 mm
of M15 grade including preperation of sub grade by cutting / filling
of earth wherever
required to a maximum of 150 mm depth and laying over prepared
sub grade and fixing
of kerb stone with cement mortar 1:3, all in proper line and level as
per instruction of
engineer incharge. The rate is inclusive of transportation, loading,
unloading of
precast kerb stone and all labour and materials inclusive PCC /
mortar, except
cement which will be supplied by the owner free of cost.
Size 300 mm x 450 mm x 150 mm.
Rm

Cost of kerp stone 450 X150mm


Tax
Facilties
Wastage
PCC 1:4:8 -200 x 50mm thk
Cement Mortar
Labour for fixing
Total Rate

Cost of concrete pavers 65mm thk


Tax
Facilties
Wastage
Sand
Labour for fixing
Total Rate
Providing & Fixing Dholpur Stone 40 mm thick & 150 mm wide
in coping at balcony laid on 20 mm thick cement mortar 1:4 (1
cement 4 coarse sand) and jointed with white cement slurry
mixed with pigment to match the shade of the rubbing and
polishing complete as per the satisfaction to engineer in
charge.stone includingchamfering,
Cost of Stone
Wastage
Cement
Coarse Sand
Rubbing & Polishing
Silicon Based Water Repellent Coating
Grey Cement Slurry
Pigment
Hoist/ Scaffolding
Total cost per Sqm excluding Labour
Average Labour for laying i/c lifting
Total cost per Cum
Wastage
Labour
Hoist/ scaffolding
Total cost per Sqm
Total cost per Sqm (Coping)

Tata Hs

218.25
399.36
230.16
75.00
200.00
75.00
340.00
213.89
4,491.67
3,278.59

1738.72

Rmtr
%
%
%
Cum
Mtr
Mtr
Mtr

1.00
13.50
5.00
5.00
0.01
1.00
1.00
1.00

Providing and laying 60 mm thick Grass Pavers of size


(400mmx600mm)laid over a
prepared base, cutting edge to required shape, size and pattern and
setting with
vibration complete in all respects as per manufacturers specification. Sqm

36.00

2807
Mtr
Mtr
Sqm

Supply and Fixing of solid core flush door shutters (teak ply
veneer 3mm thick
on both faces) of specified size & thickness including cost of
providing & fixing
hard wood lipping, 4 nos.MS hinges 100mm long, cutting / re-sizing
of door if
necessary complete as specified. (4 hinges per shutter). At all floor
levels.
a) 38mm thick

3.02

300.00
50.00
175.00
39.00
91.00
108.49
2,278
438.14
87,627
438
Tata housing with melamine 65 x 150mm

Sqm

50.00
50.00
175.00
50.00
70.00
2169.82

0.674
2.037
1.370

Cost of Door shutter 35mm thick


Rebate
35.000 Add for lipping - 6mm thk Red Marandi
Add for Taxes
Add for Enamel paint
Labour charge for making
Labour charge for Fixing
Labour charge for hardware Fixing
Hinges
Add for sub contractor margin 5%
Cost of Door shutter 38mm thick
Total cost per sqm

2.05

6
1
1
0.78
1.30
5
5.20
1
1

2095.80

Sqm
%
%
%
Sqm
Sqm
Sqm

1.00
13.50
5.00
5.00
1.00
1.00
1.00

Sqm

2,780

Sqm
%
Bag
Cum
Sqm
Sqm
Kg
Sqm
Sqm

1.00
20.00
0.27
0.04
1.00
1.00
1.00
1.00
1.00

861
861
250
1,325
150
49
20
15
15

Cum

1.00

15

%
Mtr
Mtr

20%
1.00
1.00

1,417
15
10

861
172
68
52
150
49
20
15
15
1,402
15
1,417
283
15
10
1725
267
1,992

Balance Analysis

46/71

The Primus - Group Housing


Depreciation

Machinery Sheet

Project

Branch
Name

DD04-DELThe Primus
DD04-DELThe Primus
DD04-DELThe Primus
DD04-DELThe Primus
DD04-DELThe Primus
DD04-DELThe Primus
DD04-DELThe Primus
DD04-DELThe Primus
DD04-DELThe Primus
DD04-DELThe Primus
DD04-DELThe Primus
DD04-DELThe Primus
DD04-DELThe Primus
Group
Housing
DD04-DELThe Primus
Group
Housing
DD04-DEL-

Delhi - RO

The Primus
Group
Housing
DD04-DELThe Primus
Group
Housing
DD04-DELThe Primus
Group
Housing
DD04-DELThe Primus
Group
Housing
DD04-DELThe Primus
Group
DD04-DELThe Primus

Delhi - RO
Delhi - RO
Delhi - RO
Delhi - RO
Delhi - RO
Delhi - RO
Delhi - RO
Delhi - RO
Delhi - RO
Delhi - RO
Delhi - RO

Remarks

PNM Class(level 2)
For Structure

Bar Bending Machine

15-Dec-12

NOS DEMOBIL_DATE
6

31-Jan-15

Internal/External
Hire
Internal Hire

Months Replacement Cost


26

350000

Depr Charge
57750

Total Dep
Earthwork
charges

15-Mar-13

30-Jun-14

Internal Hire

16

350000

38500

10-Jun-13

30-Aug-14

Internal Hire

15

350000

19250

282232

15-Dec-12

31-Jan-15

Internal Hire

26

300000

49500

1264349

30-Jun-14

Internal Hire

16

300000

33000

30-Aug-14

Internal Hire

15

300000

16500

241913

15-Apr-13

30-Jan-15

Internal Hire

22

10000000

125000

2691486

Tower H & J
EWS

Delhi - RO

Tower Crane - 2

10-May-13

15-Feb-15

Internal Hire

21

10000000

275000

1-Jun-13

10-Feb-15

Internal Hire

20

10000000

275000

5595825

10-Jun-13

15-Jul-14

Internal Hire

13

10000000

275000

3616042

Tower Crane - 5

Shirke Potain MC85A

1-Jul-13

30-May-14

Internal Hire

11

10000000

275000

3010355

Mobile Tower Crane - 1

MTC 3625

1-Oct-13

30-Oct-14

Internal Hire

13

2500000

68750

890450

Diesel Generator Set

Cummins 125 kva DG


Set with accoustic
canopy
Cummins 125 kva DG
Set with accoustic
canopy

15-Dec-12

20-Oct-15

Internal Hire

34

750000

61875

2113351

15-Apr-13

30-Jan-15

Internal Hire

22

750000

20625

444095

Diesel Generator Set

Cummins 125 kva DG


Set with accoustic
canopy

10-May-13

15-Feb-15

Internal Hire

21

750000

20625

437993

Diesel Generator Set

Cummins 125 kva DG


Set with accoustic
canopy

1-Jun-13

10-Feb-15

Internal Hire

20

750000

20625

419687

Diesel Generator Set

Cummins 125 kva DG


Set with accoustic
canopy

10-Jun-13

15-Jul-14

Internal Hire

13

750000

20625

271203

Diesel Generator Set

Cummins 125 kva DG


Set with accoustic
canopy

1-Jul-13

30-May-14

Internal Hire

11

750000

20625

225777

Diesel Generator Set

Kirloskar 4R1040TA DG
Set 82.5kVA

1-Oct-13

30-Oct-14

Internal Hire

13

550000

15125

195899

Tower Crane 5

20-Oct-12

20-Oct-15

External Hire

36

450000

49500

Dep

Reinf
Shuttering

Operation

Fuel

Total

16

997813.5437

399

123

323

845

63199854.54

1,255

179

736

2,170

21729922.32

15

11

30

13382992.29

Masonry

161

148

332

641

15827031

St. Steel

13,788,077

6,045,317

41,972,637

61,806,031

IDC

672871

134574

1751972

1459977

291995

2238330

1678748

1398956

279791

1446417

1084813

904011

180802

1204142

903107

752589

150518

356180

267135

222613

44523

61,806,031
176943645.1

IDC break up

Power

4667203

1341405

34667647

40,676,255

Vehicle/ Other Misc machinery

9120874

4703911.900

7304990

21,129,776

176943645

1902016

177638

133229

111024

22205

175197

131398

109498

21900

167875

125906

104922

20984

108481

81361

67801

13560

90311

67733

56444

11289

78360

58770

48975

9795

29882148
74806
399

890902
12566824
10013
1255

890902
6861115
446832
15

3973737
24694
161

1781805
67648660
Qty
rate/Unit

Concrete (Site Mix)

807446

2335963

211335

Structure & External Tractor


Development

Earth Work

1076594
5839908

Shirke Potain MC85A

Tower Crane 4

MTC

Shirke Potain MC85A


Shirke Potain MC85A

Tower Crane 3

Delhi - RO

241913
Shirke Potain MC85A

Tower Crane - 4

Tower Crane 2

Delhi - RO

512032

Tower Crane - 3

Diesel Generator Set

Delhi - RO

IDC

512032

Tower Crane 1
Delhi - RO

Structural
steel

282232

10-Jun-13

Tower F & G

Masonry

1264349
15-Mar-13

Tower D & E

Shuttering

597370

Bar Cutting Machine

Tower B & C

Reinf

597370

For Structure & External Bar Cutting Machine


Development
Tower Crane -1
Tower A & B

For Structure

RMC

1475074

Bar Bending Machine

For Structure

Concrete
(Site Mix)

1475074

Site Works

Delhi - RO

Mobilization Date

For Structure & External Bar Bending Machine


Development
Bar Cutting Machine
For Structure

Delhi - RO

Delhi - RO

PNM Type

576759
63951
9

13788077

The Primus - Group Housing


Operation Cost

Machinery Sheet

Project
DD04-DELThe Primus
DD04-DELThe Primus
DD04-DELThe Primus
DD04-DELThe Primus
DD04-DELThe Primus
DD04-DELThe Primus
DD04-DELThe Primus
DD04-DELThe Primus
DD04-DELThe Primus
DD04-DELThe Primus
DD04-DELThe Primus
DD04-DELThe Primus
DD04-DELThe Primus
Group
Housing
DD04-DELThe Primus
Group
Housing
DD04-DELThe Primus
Group
Housing
DD04-DELThe Primus
Group
Housing
DD04-DELThe Primus
Group
Housing
DD04-DELThe Primus
Group
Housing
DD04-DELThe Primus
Group
DD04-DELThe Primus

Branch
Name
Delhi - RO
Delhi - RO
Delhi - RO
Delhi - RO
Delhi - RO
Delhi - RO
Delhi - RO
Delhi - RO
Delhi - RO
Delhi - RO
Delhi - RO
Delhi - RO

Remarks

PNM Class(level 2)
For Structure

Bar Bending Machine

NOS DEMOBIL_DATE

15-Dec-12

Bar Bending Machine

15-Mar-13

30-Jun-14

10-Jun-13

30-Aug-14

15-Dec-12

31-Jan-15

For Structure

For Structure

Bar Cutting Machine

For Structure & External Bar Cutting Machine


Development
Tower Crane -1
Tower A & B
Tower B & C
Tower D & E
Tower F & G
Tower H & J
EWS

Tower Crane - 2

Delhi - RO

Delhi - RO

30-Aug-14

30-Jan-15

Shirke Potain MC85A

10-May-13

Concrete
(Site Mix)

RMC

Reinf

10-Feb-15

15-Jul-14

Tower Crane - 5

Shirke Potain MC85A

1-Jul-13

30-May-14

Mobile Tower Crane - 1

MTC 3625

1-Oct-13

30-Oct-14

Diesel Generator Set

Cummins 125 kva DG


Set with accoustic
canopy
Cummins 125 kva DG
Set with accoustic
canopy

15-Dec-12

20-Oct-15

15-Apr-13

30-Jan-15

Diesel Generator Set

Cummins 125 kva DG


Set with accoustic
canopy

10-May-13

15-Feb-15

Diesel Generator Set

Cummins 125 kva DG


Set with accoustic
canopy

1-Jun-13

10-Feb-15

Diesel Generator Set

Cummins 125 kva DG


Set with accoustic
canopy

10-Jun-13

15-Jul-14

Diesel Generator Set

Cummins 125 kva DG


Set with accoustic
canopy

1-Jul-13

30-May-14

Diesel Generator Set

Kirloskar 4R1040TA DG
Set 82.5kVA

1-Oct-13

30-Oct-14

Concrete (Site Mix)


Reinf
Shuttering

6500

753616

301446

226085

188404

37681

11000

6500

743261

297304

222978

185815

37163

11000

6500

712196

284878

213659

178049

35610

11000

6500

460224

184089

138067

115056

23011

11000

6500

383136

153254

114941

95784

19157

10500

6000

427416

170966

128225

106854

21371

8500

870957

8500

183021

73208

54906

45755

9151

116798

46719

35039

29200

5840

111769

44707

33531

27942

5588

539941
1794467
10013
179

539941
1512800
446832
3

5500

8500

87096

783861

0
20-Oct-12

1
50

Operation

Fuel

20-Oct-15

Total

16

399

123

323

845

1,255

179

736

2,170

15

11

30

Masonry

161

148

332

641

St. Steel

13,788,077

6,045,317

41,972,637

61,806,031

IDC

IDC

11000

Dep
Earth Work

Structural
steel

Masonry

Structure & External Tractor


Development

Shuttering

15-Feb-15

1-Jun-13

Tower Crane 5
MTC

15-Apr-13

10-Jun-13

Tower Crane 4
Delhi - RO

10-Jun-13

Shirke Potain MC85A

Tower Crane 3

Earthwork

0
Shirke Potain MC85A

Shirke Potain MC85A

Tower Crane 2

Op+Helper
cost

30-Jun-14

Tower Crane - 4

Diesel Generator Set

Delhi - RO

Tower Crane - 3

Tower Crane 1
Delhi - RO

15-Mar-13

Operator Helper

31-Jan-15

For Structure & External Bar Bending Machine


Development
Bar Cutting Machine
For Structure

Site Works

Delhi - RO

Mobilization Date

Operator

Delhi - RO

Delhi - RO

PNM Type

IDC break up

Power

4667203

1341405

34667647

40,676,255

Vehicle/ Other Misc machinery

9120874

4703911.900

7304990

21,129,776

7500
320500

29

138500

1079882
22366298

188757
63951
3

9178544
74806
123

3646413
24694
148

6045317

The Primus - Group Housing


Fuel Cost

Machinery Sheet

Project

Branch
Name

DD04-DELThe Primus
DD04-DELThe Primus
DD04-DELThe Primus
DD04-DELThe Primus
DD04-DELThe Primus
DD04-DELThe Primus
DD04-DELThe Primus
DD04-DELThe Primus
DD04-DELThe Primus
DD04-DELThe Primus
DD04-DELThe Primus
DD04-DELThe Primus
DD04-DELThe Primus
Group
Housing
DD04-DELThe Primus
Group
Housing
DD04-DEL-

Delhi - RO

The Primus
Group
Housing
DD04-DELThe Primus
Group
Housing
DD04-DELThe Primus
Group
Housing
DD04-DELThe Primus
Group
Housing
DD04-DELThe Primus
Group
DD04-DELThe Primus

Delhi - RO
Delhi - RO
Delhi - RO
Delhi - RO
Delhi - RO
Delhi - RO
Delhi - RO
Delhi - RO
Delhi - RO
Delhi - RO
Delhi - RO

Remarks

PNM Class(level 2)
For Structure

Bar Bending Machine

15-Dec-12

NOS DEMOBIL_DATE
6

15-Mar-13

30-Jun-14

10-Jun-13

30-Aug-14

15-Dec-12

31-Jan-15

For Structure

Bar Cutting Machine

For Structure & External Bar Cutting Machine


Development
Tower Crane -1
Tower A & B
Tower B & C
Tower D & E
Tower F & G
Tower H & J
EWS

Tower Crane - 2

Delhi - RO

Delhi - RO

30-Aug-14

30-Jan-15

Shirke Potain MC85A

10-May-13

Earthwork

Concrete
(Site Mix)

RMC

Reinf

10-Feb-15

15-Jul-14

Tower Crane - 5

Shirke Potain MC85A

1-Jul-13

30-May-14

Mobile Tower Crane - 1

MTC 3625

1-Oct-13

30-Oct-14

Diesel Generator Set

Cummins 125 kva DG


Set with accoustic
canopy
Cummins 125 kva DG
Set with accoustic
canopy

15-Dec-12

20-Oct-15

15-Apr-13

30-Jan-15

Diesel Generator Set

Cummins 125 kva DG


Set with accoustic
canopy

10-May-13

15-Feb-15

Diesel Generator Set

Cummins 125 kva DG


Set with accoustic
canopy

1-Jun-13

10-Feb-15

Diesel Generator Set

Cummins 125 kva DG


Set with accoustic
canopy

10-Jun-13

15-Jul-14

Diesel Generator Set

Cummins 125 kva DG


Set with accoustic
canopy

1-Jul-13

30-May-14

Diesel Generator Set

Kirloskar 4R1040TA DG
Set 82.5kVA

1-Oct-13

30-Oct-14

Structure & External Tractor


Development

20-Oct-12

Dep
Earth Work
Concrete (Site Mix)
Reinf
Shuttering

Operation

Fuel

Structural
steel

Masonry

IDC

0
0

12

11

14980782

1498078

13482703.38

15

11

3935038

1574015.385

1180512

983759.6154

196751.9231

15

11

3880969

1552387.692

1164291

970242.3077

194048.4615

15

11

3718762

1487504.615

1115628

929690.3846

185938.0769

15

11

2403077

961230.7692

720923

600769.2308

120153.8462

15

11

2000562

800224.6154

600168

500140.3846

100028.0769

12

1291108

516443.0769

387332

322776.9231

64555.38462

8
313

1
230

1403397
86928686

24139163
74805.89
322.69

701698
7368631
10013
735.91

701698
5009077
446832
11.21

8206881
24694
332.34

20-Oct-15

Total

16

399

123

323

845

1,255

179

736

2,170

15

11

30

Masonry

161

148

332

641

St. Steel

13,788,077

6,045,317

41,972,637

61,806,031

IDC

Shuttering

15-Feb-15

1-Jun-13

Tower Crane 5
MTC

15-Apr-13

10-Jun-13

Tower Crane 4
Delhi - RO

10-Jun-13

Shirke Potain MC85A

Tower Crane 3

Fuel cost

0
Shirke Potain MC85A

Shirke Potain MC85A

Tower Crane 2

Consumption

30-Jun-14

Tower Crane - 4

Diesel Generator Set

Delhi - RO

Tower Crane - 3

Tower Crane 1
Delhi - RO

15-Mar-13

Working
Hr/Km

31-Jan-15

Bar Bending Machine

For Structure

Site Works

Delhi - RO

Mobilization Date

For Structure & External Bar Bending Machine


Development
Bar Cutting Machine
For Structure

Delhi - RO

Delhi - RO

PNM Type

IDC break up

Power

4667203

1341405

34667647

40,676,255

Vehicle/ Other Misc machinery

9120874

4703911.900

7304990

21,129,776

232297
63951
3.63

41972637

DLF GH Project 'The Primus' Sector-82A


REINFORCEMENT ANALYSIS
Total Reinforcement Quantity

10013 MT

Time Period

Av. reinforcement per day

16.03 MT

Peak reinforcement per day

24.05 MT

25 months

TMT Bars

TMT Bars
Description

QTY.

UNIT

Cost of Steel (landed cost)

MT

Transportation / unloading

MT

Wastage

3.0%

Chairs & Spacers

RATE

AMOUNT

Material
46,000.00

46,000.00

MT

46,000.00

1,380.00

0.00

3.0%

MT

46,000.00

1,380.00

Binding wire

KG

58.00

522.00

PVC Cover blocks

LS

400.00

400.00

MT

1,255.05

1,255.05

MT

915.12

915.12

PNM
Depriciation
Operation and Fuel Cost
Labour

Sub str

Labour cost Fab. & Fixing (Average)

MT

Transportation fro Yard to site & Misc Labour for


scrap Collection

MT

200.00

Testing Charges for Steel

MT

300.00

Total Cost

Supr Str

0.00

3050

4750

200.00

3194

6819

300.00
52,352.17

228322814.xlsx.ms_office

DLF GH Project 'The Primus' Sector-82A


BASIC RATES OF MATERIAL
S No.

Rate
( Rs.)

Description of Item

Unit

Remarks

Cement

Reinforcement bars

Structural steel

Coarse Aggregate

1,250.96

Cum

Coarse Sand

1,324.55

Cum

Fine Sand

846.24

Cum

Bricks

3,700.00

1000 No.'s

AAC Broken Blocks

2,216.53

Cum

Plastisizer

45.00

Kg

10

White cement

17.00

Kg

11

Binding Wire

58.00

Kg

12

Bitumen

44.00

Kg

13

Light Emperdor

3,766.00

Sqm

14

Omani Beige Marble flooring in

2,690.00

Sqm

15

Beige Granite Slab--------------

1,614.00

Sqm

Basic Rates

16

Vitrified tiles 600 x 600 ----

699.66

Sqm

Basic Rates

17

Anti skid Vitrified tiles 300 x 300 ----

18

Vitrified tiles 300 x 450 ----

19

Imported Marble, Omani------------

20

Indian Marble--------------------

21

Laminated Wooden Floor----------- Rs 55 / Sqft

22

Rs 150 / sq ft
Rs 65 /sq ft

250.00

Bag

Basic Rates

46,000.00

MT

Basic Rates

46,000.00

MT

Basic Rates

Basic Rates

699.66

Sqm

Balcony Areas

699.66

Sqm

Basic Rates

2,475.72

Sqm

Basic Rates

699.40

Sqm

Basic Rates

55.00

sqft

Basic Rates

Ceramic Wall Tiles 300x600mm--------Rs 55 / Sqft

591.80

Sqm

Basic Rates

23

Porcelein Wall Tiles 300x1200----------Rs 55 / Sqft

591.80

Sqm

Basic Rates

24

Ceramic Wall Tiles 300x300mm--------Rs 55 / Sqft

591.80

Sqm

Basic Rates

25

Kota Stone - 25 mm thk (Single Piece)

430.56

Sqm

26

Dholpur Stone - 40 mm thk

861.12

Sqm

Rs 65 /sq ft
Rs 65 /sq ft
Rs 230 / Sq ft

Rs 65 / Sqft

Page 51 of 71

DLF GH Project 'The Primus' Sector-82A


Concrete Work
Lift

3%

Average Lift per Floor

Reinforcement
3.0%

Average Lift per Floor


464.3
35
450.8
34
437.6
33
424.9
32
412.5
31
400.5
30
388.8
29
377.5
28
366.5
27
355.8
26
345.5
25
335.4
24
325.6
23
316.2
22
306.9
21
298.0
20
289.3
19
280.9
18
272.7
17
264.8
16
257.1
15
249.6
14
242.3
13
235.3
12
228.4
11
221.7
10
215.3
9
209.0
8
202.9
7
197.0
6
191.3
5
185.7
4
180.3
3
175.05
2
170.0
1
165.0
G
170.0
1B
281.8 Average

Formwork
3%
100

Average Lift per Floor

6500.0
35
6400.0
34
6300.0
33
6200.0
32
6100.0
31
6000.0
30
5900.0
29
5800.0
28
5700.0
27
5600.0
26
5500.0
25
5400.0
24
5300.0
23
5200.0
22
5100.0
21
5000.0
20
4900.0
19
4800.0
18
4700.0
17
4600.0
16
4500.0
15
4400.0
14
13
3.33% 4300.0
4200.0
12
4100.0
11
4000.0
10
3900.0
9
3800.0
8
3700.0
7
3600.0
6
3500.0
5
3400.0
4
3300.0
3
3200.0
2
3100.0
1
3000.0
G
3100.0
1B
4655.6 Average

Brick Work
5%
5.0

4.55%

Average Lift per Floor


280.0
34
275.0
33
270.0
32
265.0
31
260.0
30
255.0
29
250.0
28
245.0
27
240.0
26
235.0
25
230.0
24
225.0
23
220.0
22
215.0
21
210.0
20
205.0
19
200.0
18
195.0
17
190.0
16
185.0
15
180.0
14
175.0
13
170.0
12
165.0
11
160.0
10
155.0
9
150.0
8
145.0
7
140.0
6
135.0
5
130.0
4
125.0
3
120.0
2
115.0
1
110.0
G
115.0
1B
192.8 Average

3.0%
1366.0
34
1326.2
33
1287.5
32
1250.0
31
1213.6
30
1178.3
29
1144.0
28
1110.6
27
1078.3
26
1046.9
25
1016.4
24
986.8
23
958.1
22
930.1
21
903.1
20
876.8
19
851.2
18
826.4
17
802.4
16
779.0
15
756.3
14
734.3
13
712.9
12
692.1
11
672.0
10
652.4
9
633.4
8
614.9
7
597.0
6
579.6
5
562.8
4
546.4
3
530.5
2
515.0
1
500.0
G
515.0
1B
854.1 Average

Sub structure

167.48

3050.0

112.5

507.5

Super structure

288.57

4750.0

197.5

874.4

Half Brick Work


Average Lift per Floor

Block Work
3.0%

Average Lift per Floor


245.9
34
238.7
33
231.8
32
225.0
31
218.5
30
212.1
29
205.9
28
199.9
27
194.1
26
188.4
25
183.0
24
177.6
23
172.4
22
167.4
21
162.6
20
157.8
19
153.2
18
148.8
17
144.4
16
140.2
15
136.1
14
132.2
13
128.3
12
124.6
11
121.0
10
117.4
9
114.0
8
110.7
7
107.5
6
104.3
5
101.3
4
98.3
3
95.5
2
92.7
1
90.0
G
92.7
1B
153.7 Average

Sunken Area Filling


(Light Wt Conc)
3.0%

Average Lift per Floor


1707.4
34
1657.7
33
1609.4
32
1562.6
31
1517.0
30
1472.9
29
1430.0
28
1388.3
27
1347.9
26
1308.6
25
1270.5
24
1233.5
23
1197.6
22
1162.7
21
1128.8
20
1095.9
19
1064.0
18
1033.0
17
1002.9
16
973.7
15
945.4
14
917.8
13
891.1
12
865.1
11
839.9
10
815.5
9
791.7
8
768.7
7
746.3
6
724.5
5
703.4
4
683.0
3
663.1
2
643.8
1
625.0
G
643.8
1B
1067.6 Average

Internal Plaster 12-15mm


3.0%

Average Lift per Floor


478.1
34
464.2
33
450.6
32
437.5
31
424.8
30
412.4
29
400.4
28
388.7
27
377.4
26
366.4
25
355.7
24
345.4
23
335.3
22
325.6
21
316.1
20
306.9
19
297.9
18
289.2
17
280.8
16
272.6
15
264.7
14
257.0
13
249.5
12
242.2
11
235.2
10
228.3
9
221.7
8
215.2
7
209.0
6
202.9
5
197.0
4
191.2
3
185.7
2
180.3
1
175.0
G
180.3
1B
298.9 Average

Plaster - 20-25mm
4.0%

Average Lift per Floor


246.6
34
237.1
33
228.0
32
219.3
31
210.8
30
202.7
29
194.9
28
187.4
27
180.2
26
173.3
25
166.6
24
160.2
23
154.0
22
148.1
21
142.4
20
136.9
19
131.7
18
126.6
17
121.7
16
117.1
15
112.6
14
108.2
13
104.1
12
100.1
11
96.2
10
92.5
9
89.0
8
85.5
7
82.2
6
79.1
5
76.0
4
73.1
3
70.3
2
67.6
1
65.0
G
67.6
1B
134.9 Average

91.35

634.38

177.6

66.3

157.4

1093.1

306.1

138.9

3.0%

Ceiling
Plaster - 8Average Lift per Floor
314.2
34
305.0
33
296.1
32
287.5
31
279.1
30
271.0
29
263.1
28
255.4
27
248.0
26
240.8
25
233.8
24
227.0
23
220.4
22
213.9
21
207.7
20
201.7
19
195.8
18
190.1
17
184.5
16
179.2
15
173.9
14
168.9
13
164.0
12
159.2
11
154.6
10
150.0
9
145.7
8
141.4
7
137.3
6
133.3
5
129.4
4
125.7
3
122.0
2
118.5
1
115.0
G
118.5
1B
196.4 Average

Ext Plaster 18mm in two


4.0%

Average Lift per Floor


246.6
34
237.1
33
228.0
32
219.3
31
210.8
30
202.7
29
194.9
28
187.4
27
180.2
26
173.3
25
166.6
24
160.2
23
154.0
22
148.1
21
142.4
20
136.9
19
131.7
18
126.6
17
121.7
16
117.1
15
112.6
14
108.2
13
104.1
12
100.1
11
96.2
10
92.5
9
89.0
8
85.5
7
82.2
6
79.1
5
76.0
4
73.1
3
70.3
2
67.6
1
65.0
G
67.6
1B
134.9 Average

W/p Plaster 12mm


Item - 7.4
Average Lift per Floor

4.0%
436.3
34
419.6
33
403.4
32
387.9
31
373.0
30
358.6
29
344.9
28
331.6
27
318.8
26
306.6
25
294.8
24
283.4
23
272.5
22
262.1
21
252.0
20
242.3
19
233.0
18
224.0
17
215.4
16
207.1
15
199.1
14
191.5
13
184.1
12
177.0
11
170.2
10
163.7
9
157.4
8
151.3
7
145.5
6
139.9
5
134.5
4
129.4
3
124.4
2
119.6
1
115.0
G
119.6
1B
238.6 Average

Omni Marble
cladding
3.0%

Average Lift per Floor


218.6
34
212.2
33
206.0
32
200.0
31
194.2
30
188.5
29
183.0
28
177.7
27
172.5
26
167.5
25
162.6
24
157.9
23
153.3
22
148.8
21
144.5
20
140.3
19
136.2
18
132.2
17
128.4
16
124.6
15
121.0
14
117.5
13
114.1
12
110.7
11
107.5
10
104.4
9
101.3
8
98.4
7
95.5
6
92.7
5
90.0
4
87.4
3
84.9
2
82.4
1
80.0
G
82.4
1B
136.6 Average

Granite Cladding
3.0%

Average Lift per Floor


1502.5
34
1458.8
33
1416.3
32
1375.0
31
1335.0
30
1296.1
29
1258.4
28
1221.7
27
1186.1
26
1151.6
25
1118.0
24
1085.5
23
1053.9
22
1023.2
21
993.4
20
964.4
19
936.3
18
909.1
17
882.6
16
856.9
15
831.9
14
807.7
13
784.2
12
761.3
11
739.2
10
717.6
9
696.7
8
676.4
7
656.7
6
637.6
5
619.0
4
601.0
3
583.5
2
566.5
1
550.0
G
566.5
1B
939.5 Average

116.7

66.3

117.3

81.2

558.25

201.1

138.9

245.7

139.9

961.89

Granite Counter
3.0%

Average Lift per Floor


####
34
####
33
####
32
####
31
####
30
####
29
####
28
####
27
####
26
####
25
####
24
####
23
####
22
####
21
993.4
20
964.4
19
936.3
18
909.1
17
882.6
16
856.9
15
831.9
14
807.7
13
784.2
12
761.3
11
739.2
10
717.6
9
696.7
8
676.4
7
656.7
6
637.6
5
619.0
4
601.0
3
583.5
2
566.5
1
550.0
G
566.5
1B
939.5 Average

Marble Counter
3.0%

Average Lift per Floor


####
34
####
33
####
32
####
31
####
30
####
29
####
28
####
27
####
26
####
25
####
24
####
23
####
22
####
21
993.4
20
964.4
19
936.3
18
909.1
17
882.6
16
856.9
15
831.9
14
807.7
13
784.2
12
761.3
11
739.2
10
717.6
9
696.7
8
676.4
7
656.7
6
637.6
5
619.0
4
601.0
3
583.5
2
566.5
1
550.0
G
566.5
1B
939.5 Average

Vitrified tile Flooring


3.0%

Average Lift per Floor


1639.1
34
1591.4
33
1545.0
32
1500.0
31
1456.4
30
1413.9
29
1372.8
28
1332.8
27
1294.0
26
1256.3
25
1219.7
24
1184.2
23
1149.7
22
1116.2
21
1083.7
20
1052.1
19
1021.5
18
991.7
17
962.8
16
934.8
15
907.6
14
881.1
13
855.5
12
830.5
11
806.3
10
782.9
9
760.1
8
737.9
7
716.4
6
695.6
5
675.3
4
655.6
3
636.5
2
618.0
1
600.0
G
618.0
1B
1024.9 Average

Ceramic Tile
Flooring
3.0%

Average Lift per Floor


546.4
34
530.5
33
515.0
32
500.0
31
485.5
30
471.3
29
457.6
28
444.3
27
431.3
26
418.8
25
406.6
24
394.7
23
383.2
22
372.1
21
361.2
20
350.7
19
340.5
18
330.6
17
320.9
16
311.6
15
302.5
14
293.7
13
285.2
12
276.8
11
268.8
10
261.0
9
253.4
8
246.0
7
238.8
6
231.9
5
225.1
4
218.5
3
212.2
2
206.0
1
200.0
G
206.0
1B
341.6 Average

3.0%
546.4
34
530.5
33
515.0
32
500.0
31
485.5
30
471.3
29
457.6
28
444.3
27
431.3
26
418.8
25
406.6
24
394.7
23
383.2
22
372.1
21
361.2
20
350.7
19
340.5
18
330.6
17
320.9
16
311.6
15
302.5
14
293.7
13
285.2
12
276.8
11
268.8
10
261.0
9
253.4
8
246.0
7
238.8
6
231.9
5
225.1
4
218.5
3
212.2
2
206.0
1
200.0
G
206.0
1B
341.6 Average

558.3

558.3

609

203

203

961.9

961.9

1049.33

349.8

349.8

Ceramic TileWall
Average Lift per Floor

Vitrified tile
Cladding
3.0%

Average Lift per Floor


573.7
34
557.0
33
540.8
32
525.0
31
509.7
30
494.9
29
480.5
28
466.5
27
452.9
26
439.7
25
426.9
24
414.5
23
402.4
22
390.7
21
379.3
20
368.2
19
357.5
18
347.1
17
337.0
16
327.2
15
317.6
14
308.4
13
299.4
12
290.7
11
282.2
10
274.0
9
266.0
8
258.3
7
250.8
6
243.4
5
236.4
4
229.5
3
222.8
2
216.3
1
210.0
G
216.3
1B
358.7 Average

Terrazo Tile Flooring


3.0%

Average Lift per Floor


519.1
34
503.9
33
489.3
32
475.0
31
461.2
30
447.7
29
434.7
28
422.0
27
409.8
26
397.8
25
386.2
24
375.0
23
364.1
22
353.5
21
343.2
20
333.2
19
323.5
18
314.0
17
304.9
16
296.0
15
287.4
14
279.0
13
270.9
12
263.0
11
255.3
10
247.9
9
240.7
8
233.7
7
226.9
6
220.3
5
213.8
4
207.6
3
201.6
2
195.7
1
190.0
G
195.7
1B
324.5 Average

Kota Stone - 25mm


3.0%

Average Lift per Floor


546.4
34
530.5
33
515.0
32
500.0
31
485.5
30
471.3
29
457.6
28
444.3
27
431.3
26
418.8
25
406.6
24
394.7
23
383.2
22
372.1
21
361.2
20
350.7
19
340.5
18
330.6
17
320.9
16
311.6
15
302.5
14
293.7
13
285.2
12
276.8
11
268.8
10
261.0
9
253.4
8
246.0
7
238.8
6
231.9
5
225.1
4
218.5
3
212.2
2
206.0
1
200.0
G
206.0
1B
341.6 Average

3.0%

Average Lift per Floor


614.7
34
596.8
33
579.4
32
562.5
31
546.1
30
530.2
29
514.8
28
499.8
27
485.2
26
471.1
25
457.4
24
444.1
23
431.1
22
418.6
21
406.4
20
394.5
19
383.0
18
371.9
17
361.1
16
350.5
15
340.3
14
330.4
13
320.8
12
311.5
11
302.4
10
293.6
9
285.0
8
276.7
7
268.7
6
260.8
5
253.2
4
245.9
3
238.7
2
231.8
1
225.0
G
231.8
1B
384.3 Average

213.2

192.9

203

228.4

367.3

332.3

349.8

393.5

Indian Stone 18mm


Average Lift per Floor

Marble Chips Flooring


3.0%

Average Lift per Floor


956.2
34
928.3
33
901.3
32
875.0
31
849.5
30
824.8
29
800.8
28
777.5
27
754.8
26
732.8
25
711.5
24
690.8
23
670.6
22
651.1
21
632.1
20
613.7
19
595.9
18
578.5
17
561.6
16
545.3
15
529.4
14
514.0
13
499.0
12
484.5
11
470.4
10
456.7
9
443.4
8
430.5
7
417.9
6
405.7
5
393.9
4
382.5
3
371.3
2
360.5
1
350.0
G
360.5
1B
597.8 Average

Omani Marble Flooring


3.0%

Average Lift per Floor


751.3
34
729.4
33
708.1
32
687.5
31
667.5
30
648.1
29
629.2
28
610.9
27
593.1
26
575.8
25
559.0
24
542.7
23
526.9
22
511.6
21
496.7
20
482.2
19
468.2
18
454.5
17
441.3
16
428.4
15
416.0
14
403.8
13
392.1
12
380.7
11
369.6
10
358.8
9
348.4
8
338.2
7
328.4
6
318.8
5
309.5
4
300.5
3
291.7
2
283.3
1
275.0
G
283.3
1B
469.7 Average

3.0%
1161.1
34
1127.2
33
1094.4
32
1062.5
31
1031.6
30
1001.5
29
972.4
28
944.0
27
916.6
26
889.9
25
863.9
24
838.8
23
814.3
22
790.6
21
767.6
20
745.2
19
723.5
18
702.5
17
682.0
16
662.1
15
642.9
14
624.1
13
605.9
12
588.3
11
571.2
10
554.5
9
538.4
8
522.7
7
507.5
6
492.7
5
478.3
4
464.4
3
450.9
2
437.8
1
425.0
G
437.8
1B
725.9 Average

355.25

279.1

431.38

612.11

480.9

743.28

228322814.xlsx.ms_office

DLF GH Project 'The Primus' Sector-82A


FORM WORK ANALYSIS
Project Duration

36.00

Time Period for Formwork

24.98

Formwork Quantity

446,832

Description

Rate

Material charged to work


System Depriciation

135.00

Plastic Formwork Depriciation

Consumables

85.00

Shuttering Oil & Nails

8.00

PNM depreciation

15.36

PNM Operation & Fuel

14.60

Labour - Sub Contractor

192.78

Making Charge

9.00

PNM

Labour

Labour - Shifting

4.00

Total Cost

463.73

Total Cost Excluding Labour

270.95

Column

270.95

Staircase

300.95

Beam / Lintel

280.95

Slab

270.95

Overhead water tank

290.95

Page 58 of 71

Procedure for Staff ( requirement) Scheduling


A-2.2/01-06-01 - Format for Staff Deployment Schedule
Project Planning & Scheduling

STAFF DEPLOYMENT SCHEDULE


Project Name:

DLF PRIMUS

Project No:

2071

Location

GURGAON - DELHI RO

Date:

19-Mar-13

Sl.No

DIVISION

Name

Designation

Cadre

Nos

Salary/
Month

Staff on Site
Months
Entry

Exit

20-Oct-12

20-Oct-15

36

10

11

12

13

14

15

Oct-12

Nov-12

Dec-12

Jan-13

Feb-13

Mar-13

Apr-13

May-13

Jun-13

Jul-13

Aug-13

Sep-13

Oct-13

Nov-13

Dec-13

PERMANENT CADRE
1

MR. SHAMMI KHURANA

EXECUTION HEAD

MR. VINEET SINGH

DGM PROJECTS

200,000

1-Jul-13

20-Oct-15

28

NORTH

MR. GANGA ARYA

PROJECT MANAGER

E-003

110,000

20-Oct-12

20-Oct-15

36

SOUTH

MR. ANIMESH PRAMANIK

PROJECT MANAGER

E-003

110,000

1-May-13

20-Oct-15

30

MR. DEVARAJ DIXIT

ARCHITECT

E-003

80,000

1-Apr-13

20-Oct-15

31

12,000

1-Jul-13

20-Dec-14

200000

200000

200000

200000

200000

200000

110000

110000

110000

110000

110000

110000

110000

110000

110000

110000

110000

110000

110000

110000

110000

110000

80000

80000

80000

80000

80000

80000

80000

80000

18

12000

12000

12000

12000

12000

12000

75000

75000

75000

75000

75000

75000

90000

90000

90000

90000

90000

90000

42000

42000

42000

42000

42000

42000

110000

110000

110000

110000

110000

110000

CO-ORDINATION TEAM
5
6

DRAFTSMAN

CONTRACTS ADMIN

E-002

75,000

1-Jul-13

20-Oct-15

28

80000

PLANNING & BILLING


BILLING MANAGER

E-003

90,000

1-Apr-13

20-Oct-15

31

PRW & QS

SR. ENGINEER BILLING

S-003

42,000

1-Jul-13

20-Oct-15

28

ERP & CLIENT

SR. ENGINEER BILLING

8
9

MR. PAWAN BANSAL

90000

90000

90000

S-003

45,000

1-Jul-13

20-Apr-15

22

45000

45000

45000

45000

45000

45000

11

MR. AMIT KUMAR SHARAN

DY. MANGER PLANNING

E-001

60,000

1-Dec-12

20-Oct-15

35

60000

60000

60000

60000

60000

60000

60000

60000

60000

60000

60000

60000

60000

12

MR. ARUN.C.K

SR. ENGINEER PLANNING

S-003

50,000

1-Dec-12

20-Jun-15

31

50000

50000

50000

50000

50000

50000

50000

50000

50000

50000

50000

50000

50000

75000

75000

75000

75000

75000

75000

75000

75000

75000

45000

45000

45000

45000

45000

45000

45000

45000

45000

33000

33000

33000

33000

33000

33000

33000

10000

10000

10000

10000

10000

10000

10000

10000

10

13

BBS

MR. SANDEEP

MANAGER - BBS

E-002

75,000

1-Apr-13

20-Oct-15

31

14

BBS

MR. JASVIR SINGH

SR. ENGINEEER

S-003

45,000

1-Dec-12

20-Feb-15

27

15

BBS

ENGINEER

S-002

33,000

1-Jun-13

30-Jun-14

13

10,000

1-May-13

20-Oct-15

30

16

MR. DHARM PAL

DOCUMENT CONTROLLER

45000

45000

45000

45000

EXECUTION - STRUCTURE
17

TOWER A,B,C

MR. HARI MOHAN JHA

MANAGER

E-002

75,000

20-Oct-12

20-Oct-15

36

18

TOWER D,E,F

MR. JITENDER AHUJA

MANAGER

E-002

75,000

1-Mar-13

20-Oct-15

32

19

TOWER G,H,J

MANAGER

E-002

75,000

1-Jun-13

20-Oct-15

29

20

TOWER A

MR. ANURAG MISHRA

SR.ENGINEER

S-003

38,000

20-Oct-12

20-Jan-15

27

38000

38000

38000

38000

38000

38000

21

TOWER B

MR. VIKRAM SINGH

SR.ENGINEER

S-003

38,000

20-Oct-12

20-Jan-15

27

38000

38000

38000

38000

38000

22

TOWER C

MR. MOHIT KUMAR

SR.ENGINEER

S-003

38,000

20-Oct-12

1-Feb-15

27

38000

38000

38000

38000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

38000

38000

38000

38000

38000

38000

38000

38000

38000

38000

38000

38000

38000

38000

38000

38000

38000

38000

38000

38000

38000

38000

38000

38000

38000

38000

38000

23

TOWER D

MR. LALIT

SR.ENGINEER

S-003

40,000

20-Dec-12

20-Feb-15

26

40000

40000

40000

40000

40000

40000

40000

40000

40000

40000

40000

40000

24

TOWER E

MR. ANURAG TRIPATI

ENGINEER

S-002

38,000

20-Dec-12

20-Jun-14

18

38000

38000

38000

38000

38000

38000

38000

38000

38000

38000

38000

38000

25

TOWER F

ENGINEER

S-002

33,000

1-Jun-13

15-Jul-14

13

33000

33000

33000

33000

33000

33000

33000

26

TOWER G

ENGINEER

S-002

33,000

1-Jun-13

30-Jul-14

14

33000

33000

33000

33000

33000

33000

33000

27

TOWER H

ENGINEER

S-002

33,000

10-Jun-13

10-Jun-14

12

33000

33000

33000

33000

33000

33000

28

TOWER J

ENGINEER

S-002

33,000

1-Jul-13

15-Jun-14

11

33000

33000

33000

33000

33000

33000

NON TOWER - N MR. WASIM RAJA

SR.ENGINEER

S-003

40,000

1-May-13

1-Sep-14

16

40000

40000

40000

40000

40000

40000

40000

30

NON TOWER - S

SR.ENGINEER

S-003

40,000

1-Jun-13

11-Oct-14

16

31

TOWER A

MR. MANMOHAN JHA

FOREMAN

N-003

28,000

20-Oct-12

20-Jan-15

27

32

TOWER B

MR. HARI PRASAD

FOREMAN

N-003

28,000

1-Dec-12

20-Jan-15

26

33

TOWER C

FOREMAN

N-003

28,000

1-Mar-13

1-Feb-15

34

TOWER D

FOREMAN

N-003

25,000

1-Mar-13

35

TOWER E

FOREMAN

N-002

25,000

36

TOWER F

FOREMAN

N-002

37

TOWER G

FOREMAN

38

TOWER H

FOREMAN

39

TOWER J

FOREMAN

40

NON TOWER - N

41

NON TOWER - S

42

TOWER A

43
44

29

40000

40000

40000

40000

40000

40000

40000

40000

28000

28000

28000

28000

28000

28000

28000

28000

28000

28000

28000

28000

28000

28000

28000

28000

28000

28000

28000

28000

28000

28000

28000

28000

28000

28000

23

28000

28000

28000

28000

28000

28000

28000

28000

28000

28000

20-Feb-15

24

25000

25000

25000

25000

25000

25000

25000

25000

25000

25000

1-Apr-13

20-Jun-14

15

25000

25000

25000

25000

25000

25000

25000

25000

25000

25,000

1-Apr-13

15-Jul-14

15

25000

25000

25000

25000

25000

25000

25000

25000

25000

N-002

25,000

1-Jun-13

30-Jul-14

14

25000

25000

25000

25000

25000

25000

25000

N-002

25,000

10-Jun-13

10-Jun-14

12

25000

25000

25000

25000

25000

25000

N-002

25,000

1-Jul-13

15-Jun-14

11

25000

25000

25000

25000

25000

25000

FOREMAN

N-003

22,000

1-May-13

1-Sep-14

16

22000

22000

22000

22000

22000

22000

22000

FOREMAN

N-003

22,000

1-Jun-13

11-Oct-14

16

22000

22000

22000

22000

22000

22000

22000

SUPERVISOR

15,000

20-Oct-12

20-Oct-15

36

TOWER B

SUPERVISOR

15,000

1-Dec-12

20-Oct-15

35

TOWER C

SUPERVISOR

15,000

1-Mar-13

20-Oct-15

45

TOWER D

SUPERVISOR

15,000

1-Mar-13

46

TOWER E

SUPERVISOR

13,500

1-Apr-13

47

TOWER F

SUPERVISOR

13,500

48

TOWER G

SUPERVISOR

49

TOWER H

50
51

MR. RAM CHARAN

28000

22000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

32

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

20-Oct-15

32

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

20-Oct-15

31

13500

13500

13500

13500

13500

13500

13500

13500

13500

1-Apr-13

20-Oct-15

31

13500

13500

13500

13500

13500

13500

13500

13500

13500

13,500

1-Jun-13

20-Oct-15

29

13500

13500

13500

13500

13500

13500

13500

SUPERVISOR

13,500

10-Jun-13

20-Oct-15

28

13500

13500

13500

13500

13500

13500

TOWER J

SUPERVISOR

13,500

1-Jul-13

20-Oct-15

28

13500

13500

13500

13500

13500

13500

NON TOWER - N

SUPERVISOR

13,500

1-May-13

20-Oct-15

30

13500

13500

13500

13500

13500

13500

13500

52

NON TOWER - S

SUPERVISOR

13,500

1-Jun-13

20-Oct-15

29

53

NORTH

DY. SUP SURVEYOR

40,000

20-Oct-12

20-Oct-15

36

54

SOUTH

SURVEYOR

20,000

10-Apr-13

15-Jul-14

15

MR. HARINDER GUPTA

15000

13500

40000

40000

40000

40000

40000

40000

13500

13500

13500

13500

13500

13500

13500

40000

40000

40000

40000

40000

40000

40000

40000

20000

20000

20000

20000

20000

20000

20000

20000

EXECUTION - FINISHES
55

NORTH

MANAGER

E-002

75,000

1-Oct-13

20-Oct-15

25

56

SOUTH

MANAGER

E-002

75,000

1-Nov-13

30-Aug-15

22

57

TOWER A

ENGINEER

S-002

35,000

14-Aug-13

20-Sep-15

25

35000

58

TOWER B

ENGINEER

S-002

35,000

30-Aug-13

30-Sep-15

25

35000

59

TOWER C

ENGINEER

S-002

35,000

30-Aug-13

10-Oct-15

25

35000

60

TOWER D

ENGINEER

S-002

35,000

15-Sep-13

20-Oct-15

25

61

TOWER E,F,G

SR. ENGINEER

S-003

40,000

15-Oct-13

10-Sep-15

23

62

TOWER H & J

ENGINEER

S-002

35,000

10-Nov-13

10-Sep-15

22

63

TOWER A

FOREMAN

N-002

25,000

1-Aug-13

20-Sep-15

26

64

TOWER B

FOREMAN

N-002

25,000

15-Aug-13

30-Sep-15

65

TOWER C

FOREMAN

N-002

22,000

15-Aug-13

10-Oct-15

66

TOWER D

FOREMAN

N-002

22,000

1-Sep-13

67

TOWER E

FOREMAN

N-002

22,000

68

TOWER F

FOREMAN

N-002

69

TOWER G

FOREMAN

70

TOWER H

71

TOWER J

75000

75000

75000

75000

75000

35000

35000

35000

35000

35000

35000

35000

35000

35000

35000

35000

35000

40000

40000
35000

25000

25000

25000

25000

25000

26

25000

25000

25000

25000

26

22000

22000

22000

22000

20-Oct-15

26

22000

22000

22000

22000

1-Oct-13

10-Sep-15

23

22000

22000

22000

22,000

15-Oct-13

10-Sep-15

23

22000

22000

N-002

22,000

1-Nov-13

10-Sep-15

22

22000

22000

FOREMAN

N-002

22,000

1-Nov-13

10-Sep-15

22

22000

22000

FOREMAN

N-002

22,000

15-Nov-13

10-Sep-15

22

72

SR. MANAGER

E-003

85,000

73

MANAGER

E-002

75,000

74

DY. MANAGER

E-001

65,000

75

SR.ENGINEER

S-003

43,000

76

SR. ENGINEER

S-003

45,000

77

ENGINEER

S-002

38,000

78

FOREMAN

25,000

79

FOREMAN

25,000

80

FOREMAN

25,000

81

SUPERVISOR

16,000

82

SUPERVISOR

16,000

22000

SERVICES

ACCOUNTS & ADMIN


ADMIN MANAGER

E-003

80,000

1-May-13

20-Oct-15

30

ADMIN OFFICER

S-002

32,000

1-Jun-13

20-Oct-15

29

24,000

20-Oct-12

20-Oct-15

36

IT

20,000

1-Dec-12

31-Dec-14

25

MR. DINESH NAGPAL

ACCOUNTS MANAGER

60,000

20-Oct-12

20-Oct-15

36

MR. JITENDER

TIME KEEPER

14,000

20-Oct-12

20-Oct-15

89

MR. MIHR JHA

SR. MANAGER

E-003

90,000

20-Oct-12

90

MR. ANAND VIVEK

ENGINEER

S-002

36,000

20-Oct-12

91

MR. VINOD JOSHI

ENGINEER

S-002

32,000

1-May-13

92

FOREMAN

N-002

22,000

93

SUPERVISOR
MR. RAJEEV GUPTA

BATCHING PLANT OPER.

MR. ANIL KUMAR GANGWAL

MANAGER

E-002

75,000

SR. ENGINEER

S-003

38,000

ENGINEER

S-002

33,000

20-Oct-12

12,000

83

MR. JITENDER MANN

84
85

MR. AJAY SHARMA

ADMIN ASST

86

MR. SURESH SAHOO

87
88

80000

24000

80000

80000

80000

80000

80000

80000

80000

32000

32000

32000

32000

32000

32000

32000

24000

24000

24000

24000

24000

24000

24000

20000

20000

20000

20000

20000

20000

20000

20000

60000

60000

60000

60000

60000

60000

60000

60000

60000

14000

14000

14000

14000

14000

14000

14000

14000

14000

14000

90000

90000

90000

90000

90000

90000

90000

90000

90000

90000

90000

36000

36000

36000

36000

36000

36000

36000

36000

36000

36000

36000

32000

32000

32000

32000

32000

32000

32000

32000

22000

22000

22000

22000

22000

22000

22000

22000

22000

14000

14000

14000

14000

14000

14000

14000

14000

14000

14000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

75000

75000

75000

75000

75000

75000

75000

75000

75000

38000

38000

38000

38000

33000

33000

33000

33000

33000

33000

33000

33000

33000

33000

33000

33000

12000

12000

12000

12000

12000

12000

12000

12000

12000

12000

12000

12000

55000

55000

55000

55000

55000

55000

32000

32000

32000

32000

32000

32000

32000

32000

32000

24000

24000

24000

24000

24000

24000

20000

20000

20000

20000

20000

60000

60000

60000

60000

60000

36

14000

14000

14000

14000

20-Oct-15

36

90000

90000

90000

20-Oct-15

36

36000

36000

36000

31-Jan-15

21

20-Oct-12

20-Oct-15

36

22000

22000

22000

22000

22000

14,000

20-Oct-12

20-Oct-15

36

14000

14000

14000

14000

15,000

1-Feb-13

31-Jan-15

24

1-Apr-13

20-Oct-15

31

1-Sep-13

31-Dec-14

16

20-Oct-15

36

33000

33000

20-Oct-12

20-Oct-15

36

12000

12000

PNM

94
QA/ QC
95
96
97

MR. AKHILESH

LAB ASST

98
SAFETY
99

DY. MANAGER

E-001

55,000

1-Jul-13

30-Nov-14

17

100

SAFETY OFFICER

S-002

32,000

1-Apr-13

20-Oct-15

31

MR. BRIJESH

ASST. SAFETY

S-001

26,000

20-Oct-12

20-Oct-15

36

26000

26000

26000

26000

26000

26000

26000

26000

26000

26000

26000

26000

26000

26000

MR. YASHVIR

ASST. SAFETY

S-001

26,000

20-Oct-12

20-May-15

31

26000

26000

26000

26000

26000

26000

26000

26000

26000

26000

26000

26000

26000

26000

103

MR. KHYAL SINGH

MANAGER

E-002

65,000

20-Oct-12

20-Oct-15

36

65000

65000

65000

65000

65000

65000

65000

65000

65000

65000

65000

65000

65000

65000

104

MR. VIKAS

ASST. STORE

15,000

20-Oct-12

20-Oct-15

36

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

ASST. STORE

15,000

1-Jan-13

31-Jan-15

25

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

101
102
STORE

105
TOTAL STAFF

105

4,016,500

819,000

1,037,000

1,130,000

1,145,000

1,303,000

1,732,000

2,059,500

2,379,500

2,951,500

2,976,500

3,188,500

3,320,500

3,501,500

3,558,500

819,000

1,037,000

1,130,000

1,145,000

1,303,000

1,957,160

2,327,235

2,688,835

3,335,195

3,363,445

3,603,005

3,752,165

3,956,695

4,021,105

PROJECT BASED/OSE
TIME KEEPER
FOREMAN - MECH
SUPERVISOR - MECH
ELECTRICIAN
ELECTRICIAN
SAFETY STEWARD

CHEDULE

Project Duration
16

17

18

19

20

21

22

23

24

25

26

27

28

29

30

31

32

33

34

35

36

37

Jan-14

Feb-14

Mar-14

Apr-14

May-14

Jun-14

Jul-14

Aug-14

Sep-14

Oct-14

Nov-14

Dec-14

Jan-15

Feb-15

Mar-15

Apr-15

May-15

Jun-15

Jul-15

Aug-15

Sep-15

Oct-15

200000

200000

200000

200000

200000

200000

200000

200000

200000

200000

200000

200000

200000

200000

200000

200000

200000

200000

200000

200000

200000

200000

5,600,000

110000

110000

110000

110000

110000

110000

110000

110000

110000

110000

110000

110000

110000

110000

110000

110000

110000

110000

110000

110000

110000

110000

3,960,000

110000

110000

110000

110000

110000

110000

110000

110000

110000

110000

110000

110000

110000

110000

110000

110000

110000

110000

110000

110000

110000

110000

3,300,000

80000

80000

80000

80000

80000

80000

80000

80000

80000

80000

80000

80000

80000

80000

80000

80000

80000

80000

80000

80000

80000

80000

2,480,000

12000

12000

12000

12000

12000

12000

12000

12000

12000

12000

12000

12000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

2,100,000

90000

90000

90000

90000

90000

90000

90000

90000

90000

90000

90000

90000

90000

90000

90000

90000

90000

90000

90000

90000

90000

90000

2,790,000

42000

42000

42000

42000

42000

42000

42000

42000

42000

42000

42000

42000

42000

42000

42000

42000

42000

42000

42000

42000

42000

42000

1,176,000

45000

45000

45000

45000

45000

45000

45000

45000

45000

45000

45000

45000

45000

45000

45000

45000

60000

60000

60000

60000

60000

60000

60000

60000

60000

60000

60000

60000

60000

60000

60000

60000

60000

60000

60000

60000

60000

60000

2,100,000

50000

50000

50000

50000

50000

50000

50000

50000

50000

50000

50000

50000

50000

50000

50000

50000

50000

50000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

45000

45000

45000

45000

45000

45000

45000

45000

45000

45000

45000

45000

45000

45000

33000

33000

33000

33000

33000

33000

10000

10000

10000

10000

10000

10000

10000

10000

10000

10000

10000

10000

10000

10000

10000

10000

10000

10000

10000

10000

10000

10000

300,000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

2,700,000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

2,400,000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

2,175,000

38000

38000

38000

38000

38000

38000

38000

38000

38000

38000

38000

38000

38000

38000

38000

38000

38000

38000

38000

38000

38000

38000

38000

38000

38000

38000

38000

38000

38000

38000

38000

38000

38000

38000

38000

38000

38000

38000

38000

38000

1,064,000

40000

40000

40000

40000

40000

40000

40000

40000

40000

40000

40000

40000

40000

40000

1,040,000

38000

38000

38000

38000

38000

38000

33000

33000

33000

33000

33000

33000

33000

462,000

33000

33000

33000

33000

33000

33000

33000

462,000

33000

33000

33000

33000

33000

33000

33000

33000

33000

33000

33000

33000

40000

40000

40000

40000

40000

40000

40000

40000

40000

40000

40000

40000

40000

40000

40000

40000

40000

40000

40000

28000

28000

28000

28000

28000

28000

28000

28000

28000

28000

28000

28000

28000

28000

28000

28000

28000

28000

28000

28000

28000

28000

28000

28000

28000

28000

28000

28000

28000

28000

28000

28000

28000

28000

28000

28000

28000

28000

28000

28000

672,000

25000

25000

25000

25000

25000

25000

25000

25000

25000

25000

25000

25000

25000

25000

600,000

25000

25000

25000

25000

25000

25000

25000

25000

25000

25000

25000

25000

25000

400,000

25000

25000

25000

25000

25000

25000

25000

350,000

25000

25000

25000

25000

25000

25000

25000

25000

25000

25000

25000

25000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

540,000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

525,000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

480,000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

480,000

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

418,500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

418,500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

391,500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

378,000

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

378,000

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

13500

391,500

40000

40000

40000

40000

40000

40000

40000

40000

40000

40000

40000

40000

40000

40000

40000

40000

40000

40000

40000

40000

40000

40000

1,440,000

20000

20000

20000

20000

20000

20000

20000

Total

216,000
-

990,000
1,550,000
75000

75000

75000

75000

2,325,000
1,215,000
429,000
-

1,026,000
1,026,000

684,000

396,000
396,000
680,000
680,000
756,000
728,000

375,000

300,000
300,000
374,000
374,000

405,000

300,000

75000

75000

1,875,000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

35000

35000

35000

35000

35000

35000

35000

35000

35000

35000

35000

35000

35000

35000

35000

35000

35000

35000

35000

35000

35000

35000

35000

35000

35000

35000

35000

35000

35000

35000

35000

35000

35000

35000

35000

35000

35000

35000

35000

35000

35000

35000

35000

35000

35000

35000

35000

35000

35000

35000

35000

35000

35000

35000

35000

35000

35000

35000

35000

35000

35000

35000

35000

35000

910,000

35000

35000

35000

35000

35000

35000

35000

35000

35000

35000

35000

35000

35000

35000

35000

35000

35000

35000

35000

35000

35000

35000

875,000

40000

40000

40000

40000

40000

40000

40000

40000

40000

40000

40000

40000

40000

40000

40000

40000

40000

40000

40000

40000

40000

920,000

35000

35000

35000

35000

35000

35000

35000

35000

35000

35000

35000

35000

35000

35000

35000

35000

35000

35000

35000

35000

35000

770,000

25000

25000

25000

25000

25000

25000

25000

25000

25000

25000

25000

25000

25000

25000

25000

25000

25000

25000

25000

25000

25000

25000

25000

25000

25000

25000

25000

25000

25000

25000

25000

25000

25000

25000

25000

25000

25000

25000

25000

25000

25000

25000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

572,000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

572,000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

528,000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

506,000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

506,000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

506,000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

484,000

1,650,000
875,000
875,000

650,000
625,000

80000

80000

80000

80000

80000

80000

80000

80000

80000

80000

80000

80000

80000

80000

80000

80000

80000

80000

80000

80000

80000

80000

2,400,000

32000

32000

32000

32000

32000

32000

32000

32000

32000

32000

32000

32000

32000

32000

32000

32000

32000

32000

32000

32000

32000

32000

928,000

24000

24000

24000

24000

24000

24000

24000

24000

24000

24000

24000

24000

24000

24000

24000

24000

24000

24000

24000

24000

24000

24000

864,000

20000

20000

20000

20000

20000

20000

20000

20000

20000

20000

20000

20000

60000

60000

60000

60000

60000

60000

60000

60000

60000

60000

60000

60000

60000

60000

60000

60000

60000

60000

60000

60000

60000

60000

2,160,000

14000

14000

14000

14000

14000

14000

14000

14000

14000

14000

14000

14000

14000

14000

14000

14000

14000

14000

14000

14000

14000

14000

504,000

90000

90000

90000

90000

90000

90000

90000

90000

90000

90000

90000

90000

90000

90000

90000

90000

90000

90000

90000

90000

90000

90000

3,240,000

36000

36000

36000

36000

36000

36000

36000

36000

36000

36000

36000

36000

36000

36000

36000

36000

36000

36000

36000

36000

36000

36000

1,296,000

32000

32000

32000

32000

32000

32000

32000

32000

32000

32000

32000

32000

32000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

22000

792,000

14000

14000

14000

14000

14000

14000

14000

14000

14000

14000

14000

14000

14000

14000

14000

14000

14000

14000

14000

14000

14000

14000

504,000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

75000

2,325,000

38000

38000

38000

38000

38000

38000

38000

38000

38000

38000

38000

38000

33000

33000

33000

33000

33000

33000

33000

33000

33000

33000

33000

33000

33000

33000

33000

33000

33000

33000

33000

33000

33000

33000

1,188,000

12000

12000

12000

12000

12000

12000

12000

12000

12000

12000

12000

12000

12000

12000

12000

12000

12000

12000

12000

12000

12000

12000

432,000

55000

55000

55000

55000

55000

55000

55000

55000

55000

55000

55000

32000

32000

32000

32000

32000

32000

32000

32000

32000

32000

32000

32000

32000

32000

32000

32000

32000

32000

32000

32000

32000

32000

992,000

26000

26000

26000

26000

26000

26000

26000

26000

26000

26000

26000

26000

26000

26000

26000

26000

26000

26000

26000

26000

26000

26000

936,000

26000

26000

26000

26000

26000

26000

26000

26000

26000

26000

26000

26000

26000

26000

26000

26000

26000

65000

65000

65000

65000

65000

65000

65000

65000

65000

65000

65000

65000

65000

65000

65000

65000

65000

65000

65000

65000

65000

65000

2,340,000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

540,000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

15000

3,558,500

3,558,500

3,558,500

3,558,500

3,558,500

3,558,500

3,346,500

3,210,500

3,210,500

3,148,500

3,086,500

3,031,500

2,961,500

2,767,500

2,591,500

2,591,500

2,546,500

2,520,500

2,470,500

2,470,500

2,395,500

2,090,500

96,893,000

4,021,105

4,021,105

4,021,105

4,543,849

4,543,849

4,543,849

4,273,146

4,099,487

4,099,487

4,020,320

3,941,152

3,870,922

3,781,539

3,533,821

3,309,086

3,739,268

3,674,337

3,636,822

3,564,677

3,564,677

3,456,460

3,016,376

119,715,279

500,000

672,000

360,000
608,000

935,000

806,000
-

375,000
-

1
4
5
6

Material rates sheet rates to be updated


Brick work rate changed to Rs 500 per cum from Rs 450
Tiling rate changed from 18 to 20 per sqft
To be checked for Quantity Variation
PCC

7 Plaster lift 4%
8 Fire door rates to be checked
9 No fuel considered for pumps in Tender

Sl.NO Description
1

PNM Cost

Material
Reinforcement - Chair & Spacer

3
4

Labour Cost
Formwork
Rough Finishes Plaster

5
6

IDC
Staff Salary
Repair & Maintenance of PNM

Quantity

Tender Rate

PSE Rate

Tendor Provision (in PSE Provision (in


Cr)
Cr)
11.97

10013

446,832
388,090

205.78
135

17.69

5.72

1.58

1.38

1.38

0.38

7.61
4.31

9.19
5.23

1.59
0.93

0.44
0.26

8.48
0.1

11.97
0.68

3.49
0.58

0.96
0.16

13.68

3.77

1,380.00

170
111

Difference
(in Cr)

Project : DLF Primus


MEP Work done Sheet ( Provisional Sums)
Sl.NO
1
2
3
4

Description
DC Cost
SPCL Margin
WCT
Client Billing

Work Value
1,008,470,282
73,557,822
45,445,180
1,127,473,285

73,557,822
323,557,822
32.35578224
8.91982749

250000000
73,557,822
323,557,822
32.35578224
8.91982749

1 Office IT Setup

Department

1
2
3
4
5
6
7
8
9
10
11
12

Project Coordinator
Project Incharge
Project Manager
Planning
Billing / BBS

Services
Execution
Quality
Plant & Machinery
Stores
Accounts
Admin / Safety

Computer
with UPS

Laptop

Printer

Scanner

1
1

Fax

1
1
1
2
6
2
1
1
1
2
1
17

1
4

1
2

1
1

Hard Disk

Xerox

1
2

Mobile
Reimbursem
ent
Pen Drive

1
1
1
1
1

1
2

1
6

5,000
2,000
1,500
1,600
1,600
2,000
12,000
1,200
1,600
1,000
800
2,400
32,700

You might also like