OPERATION RESEARCH

PLANNING AND SCHEDULING OF A


MULTI-STOREY RESIDENTIAL BUILDING




Project by:-

SHAIK KHAZAMOHIDDIN -11BCL1012



Name of Guide: -Prof. Uma maheswari




Introduction:
The feasibility studies stage considers the options for satisfying the client's needs, enabling
the client to prepare a business case for the preferred option and deciding whether to proceed with
the project. It is possible to make an outline planning application during this stage if the risk to the
project of not receiving planning permission is high, or if delays in receiving planning
permission would be problematic.
MS project is designed to assist a project manager in developing a plan, assigning resources to
tasks, tracking progress, managing the budget, and analyzing workloads, Cost Estimation can be
done in feasibility report.

Objective:-
To prepare feasibility report.
Planning, design and financial services for Multi-Storey Commercial Building
Sub Activities:
Survey and soil investigation
Preparation of Feasibility Report and financial viability of Project.
Master Plan and Conceptual Plan
Design Development & tender Documents
Invitation of Tenders and evaluation of Bids
Detailed design & Construction drawings
Top Supervision
TIME SCHEDULE
CONSULTANTS FEE STRUCTURE
REMUNERATION OF SERVICES
Complete Final Inspections





Methodology
SEQUENCE of MS Project:-
1. Set overall project information: goals, scope, assumptions, start date, manager
2. Create a Base Calendar, assign it to the project and to the Gantt chart.
3. List tasks and milestones, estimate durations
4. Outline the project (create Summary Tasks)
5. Link the tasks
6. Assign resources
7. Evaluate and refine the project
8. Save a Baseline
9. Track and update the projectActuals
10. Communicate progressReports
11. Close the project
TASK Allocation:
1. Commercial Construction 11.General Conditions
2. Long Lead Procurement 12.Mobilize on Site
3. Grading and Utilities 13. Foundations
4. Steel Erection 14.Form and Pour Concrete Floors and Roof
5. Carpentry Work 15. Masonry Work
6. Roofing 16. Window wall and
7. Store front closure 17.Building Finishes
8. Elevators 18.Plumbing
9. Electrical 19.Heating and Ventilating - AC
10. Final Clean-up and Occupancy 20.Complete Final Inspections




Task Mode Task Name Duration Start Finish Predecessors Resource Names
Auto
Scheduled
Commercial
Construction
344 days
Mon
1/3/00
Thu
4/26/01

Auto
Scheduled
General
Conditions
17 days
Mon
1/3/00
Tue
1/25/00

Auto
Scheduled
Receive notice
to proceed and
sign contract
3 days Mon 1/3/00
Wed
1/5/00

G.C. General
Management
Auto
Scheduled
Submit bond
and insurance
documents
2 days Thu 1/6/00 Fri 1/7/00 2
G.C. Project
Management,G.C.
General
Management[25%]
Auto
Scheduled
Prepare and
submit project
schedule
2 days
Mon
1/10/00
Tue
1/11/00
3
G.C. Project
Management[25%],G.C.
Scheduler
Auto
Scheduled
Prepare and
submit schedule
of values
2 days
Wed
1/12/00
Thu
1/13/00
4
G.C. General
Management[10%],G.C.
Project Management
Auto
Scheduled
Obtain building
permits
4 days Thu 1/6/00
Tue
1/11/00
2
G.C. Project
Management[50%],G.C.
Procurement[50%]
Auto
Scheduled
Submit
preliminary shop
drawings
2 wks
Wed
1/12/00
Tue
1/25/00
6
G.C. Project
Management[50%],G.C.
Procurement[50%]
Auto
Scheduled
Submit
monthly requests
for payment
1 day Thu 1/6/00 Thu 1/6/00 2
Auto
Scheduled
Long Lead
Procurement
70 days Fri 1/7/00
Thu
4/13/00

Auto
Scheduled
Submit shop
drawings and
order long lead
items - steel
2 wks Fri 1/7/00
Thu
1/20/00
8
Steel Erection Contractor
Management
Auto
Scheduled
Submit shop
drawings and
order long lead
items - roofing
2 wks
Wed
1/26/00
Tue 2/8/00 7
Roofing Contractor
Management
Auto
Scheduled
Submit shop
drawings and
order long lead
items - elevator
2 wks
Wed
1/26/00
Tue 2/8/00 7
Elevator Contractor
Management
Auto
Scheduled
Submit shop
drawings and
order long lead
items - plumbing
2 wks
Wed
1/26/00
Tue 2/8/00 7
Plumbing Contractor
Management
Auto
Scheduled
Submit shop
drawings and
order long lead
items - electric
2 wks
Wed
1/26/00
Tue 2/8/00 7
Electric Contractor
Management
Auto
Scheduled
Submit shop
drawings and
order long lead
items - HVAC
2 wks
Wed
1/26/00
Tue 2/8/00 7
HVAC Contractor
Management
Auto
Scheduled
Detail,
fabricate and
deliver steel
12 wks Fri 1/21/00
Thu
4/13/00
10
Steel Erection Contractor
Management[50%],Steel
Erection Contractor[50%]
Auto
Scheduled
Mobilize on Site 10 days Thu 1/6/00
Wed
1/19/00

Auto
Scheduled
Install
temporary power
2 days Thu 1/6/00 Fri 1/7/00 2 Electric Contractor
Auto
Scheduled
Install
temporary water
service
2 days Thu 1/6/00 Fri 1/7/00 2 Plumbing Contractor
Auto
Scheduled
Set up site
office
3 days
Mon
1/10/00
Wed
1/12/00
18,19
G.C. Superintendent,G.C.
Labor Crew[10%]
Auto
Scheduled
Set line and
grade benchmarks
3 days
Thu
1/13/00
Mon
1/17/00
20 G.C. Survey Crew
Auto
Scheduled
Prepare site -
lay down yard and
temporary fencing
2 days
Tue
1/18/00
Wed
1/19/00
21
Site Grading
Contractor,G.C. Labor
Crew[10%]
Auto
Scheduled
Site Grading and
Utilities
35 days
Thu
1/20/00
Wed
3/8/00

Auto
Scheduled
Clear and grub
site
3 days
Thu
1/20/00
Mon
1/24/00
20,22 Site Grading Contractor
Auto
Scheduled
Stone site
access and
temporary parking
area
2 days
Tue
1/25/00
Wed
1/26/00
24,22 Site Grading Contractor
Auto
Scheduled
Rough grade
site (cut and fill)
1 wk
Thu
1/27/00
Wed
2/2/00
25 Site Grading Contractor
Auto
Scheduled
Install storm
drainage
2 wks Thu 2/3/00
Wed
2/16/00
26 Site Grading Contractor
Auto
Scheduled
Install exterior
fire line and
building fire riser
2 wks Thu 2/3/00
Wed
2/16/00
26 Plumbing Contractor
Auto
Scheduled
Perform final
site grading
2 wks
Thu
2/17/00
Wed
3/1/00
27FF+1 day,28 Site Grading Contractor
Auto
Scheduled
Erect building
batter boards and
layout building
1 wk Thu 3/2/00
Wed
3/8/00
29 G.C. Survey Crew
Auto
Scheduled
Foundations 33 days Thu 3/9/00
Mon
4/24/00

Auto
Scheduled
Excavate
foundations
2 wks Thu 3/9/00
Wed
3/22/00
30
Site Grading
Contractor[50%]
Auto
Scheduled
Excavate
elevator pit
2 days Thu 3/9/00 Fri 3/10/00 30 Site Grading Contractor
Auto
Scheduled
Form column
piers and spread
foundations
4 days
Thu
3/23/00
Tue
3/28/00
32
G.C. Rough Carpenter
Crew
Auto
Scheduled
Rough-in
electric and
plumbing in
elevator
4 days
Mon
3/13/00
Thu
3/16/00
33
Plumbing Contractor,
Electric Contractor
Auto
Scheduled
Form elevator
pit walls
4 days Fri 3/17/00
Wed
3/22/00
35
G.C. Rough Carpenter
Crew
Auto
Scheduled
Set reinforcing
and anchor bolts
4 days
Wed
3/29/00
Mon
4/3/00
34
G.C. Rough Carpenter
Crew
Auto
Scheduled
Pour column
piers and
foundations
5 days Tue 4/4/00
Mon
4/10/00
37 G.C. Concrete Crew
Auto
Scheduled
Pour concrete
elevator walls
1 day
Thu
3/23/00
Thu
3/23/00
36 G.C. Concrete Crew
Auto
Scheduled
Cure elevator
wall concrete
7 days Fri 3/24/00
Mon
4/3/00
39 G.C. Labor Crew[10%]
Auto
Scheduled
Cure piers and
foundations
7 days
Tue
4/11/00
Wed
4/19/00
38 G.C. Labor Crew[10%]
Auto
Scheduled
Strip wall
forms
1 day Tue 4/4/00 Tue 4/4/00 40 G.C. Labor Crew[10%]
Auto
Scheduled
Strip column
piers and
foundation forms
3 days
Thu
4/20/00
Mon
4/24/00
41 G.C. Labor Crew
Auto
Scheduled
Install
pneumatic tube in
elevator pit
3 days Wed 4/5/00 Fri 4/7/00 42 Elevator Contractor
Auto
Scheduled
Prepare and
pour concrete
floor in elevator
pit
1 day
Mon
4/10/00
Mon
4/10/00
44 G.C. Concrete Crew
Auto
Scheduled
Steel Erection 45 days
Tue
4/25/00
Mon
6/26/00

Auto
Scheduled
Erect steel
columns, beams
and joist - 1st and
2nd floors
2 wks
Tue
4/25/00
Mon
5/8/00
43,16 Steel Erection Contractor
Auto
Scheduled
Erect steel
columns, beams
and joist - 3rd
floor and roof
2 wks Tue 5/9/00
Mon
5/22/00
47 Steel Erection Contractor
Auto
Scheduled
Install
miscellaneous iron
and bracing - 1st
and 2nd floors
2 wks Tue 5/9/00
Mon
5/22/00
47
Steel Erection
Contractor[75%]
Auto
Scheduled
Install
miscellaneous iron
and bracing - 3rd
floor and roof
2 wks
Tue
5/23/00
Mon
6/5/00
48
Steel Erection
Contractor[75%]
Auto
Scheduled
Install stairs
and miscellaneous
iron railing
2 wks Tue 6/6/00
Mon
6/19/00
50
Steel Erection
Contractor[50%]
Auto
Scheduled
Touch-up paint
on steel
1 wk
Tue
6/20/00
Mon
6/26/00
51
Steel Erection
Contractor[20%]
Auto
Scheduled
Form and Pour
Concrete - Floors
and Roof
85 days Tue 5/9/00
Mon
9/4/00

Auto
Scheduled
Form 2nd floor
including all floor
openings
5 days
Tue
6/27/00
Mon
7/3/00
52,13,14,15,47
G.C. Rough Carpenter
Crew,G.C. Labor
Crew[20%]
Auto
Scheduled
Install rebar
and in-floor
utilities (including
mechanical,
electrical,
plumbing)
5 days Tue 5/9/00
Mon
5/15/00
47
G.C. Labor
Crew[33%],Plumbing
Contractor[33%],Electric
Contractor[33%]
Auto
Scheduled
Pour 2nd floor
slab
4 days Tue 7/4/00 Fri 7/7/00 55,54 G.C. Concrete Crew
Auto
Scheduled
Cure 2nd floor
slab
7 days
Mon
7/10/00
Tue
7/18/00
56 G.C. Labor Crew[10%]
Auto
Scheduled
Strip forms
from 2nd floor
slab
2 days
Wed
7/19/00
Thu
7/20/00
57 G.C. Labor Crew
Auto
Scheduled
Form 3rd floor
including all floor
openings
5 days
Wed
7/19/00
Tue
7/25/00
57
G.C. Rough Carpenter
Crew[50%],G.C. Labor
Crew[20%]
Auto
Scheduled
Install rebar
and in-floor
utilities (including
mechanical,
electrical,
plumbing)
5 days
Wed
7/19/00
Tue
7/25/00
57
G.C. Labor
Crew[33%],Plumbing
Contractor[33%],Electric
Contractor[33%]
Auto
Scheduled
Pour 3rd floor
slab
4 days
Wed
7/26/00
Mon
7/31/00
60,59 G.C. Concrete Crew
Auto
Scheduled
Cure 3rd floor
slab
7 days Tue 8/1/00
Wed
8/9/00
61 G.C. Labor Crew[10%]
Auto
Scheduled
Strip forms
from 3rd floor slab
2 days
Thu
8/10/00
Fri 8/11/00 62 G.C. Labor Crew
Auto
Scheduled
Form roof slab
including all floor
openings
5 days
Thu
8/10/00
Wed
8/16/00
62
G.C. Rough Carpenter
Crew,G.C. Labor
Crew[20%]
Auto
Scheduled
Install rebar
and in-floor
utilities (including
mechanical,
electrical,
plumbing)
5 days
Thu
8/10/00
Wed
8/16/00
62
G.C. Labor
Crew[33%],Plumbing
Contractor[33%],Electric
Contractor[33%]
Auto
Scheduled
Pour roof slab 4 days
Thu
8/17/00
Tue
8/22/00
65,64 G.C. Concrete Crew
Auto
Scheduled
Cure roof slab 7 days
Wed
8/23/00
Thu
8/31/00
66 G.C. Labor Crew[10%]
Auto
Scheduled
Strip forms
from roof slab
2 days Fri 9/1/00
Mon
9/4/00
67 G.C. Labor Crew
Auto
Scheduled
Form 1st floor 4 days Fri 7/21/00
Wed
7/26/00
58
G.C. Rough Carpenter
Crew
Auto
Scheduled
Install
electrical
underground
1 wk Fri 7/21/00
Thu
7/27/00
58 Electric Contractor
Auto
Scheduled
Install
plumbing
underground
1 wk Fri 7/21/00
Thu
7/27/00
58 Plumbing Contractor
Auto
Scheduled
Install rebar
and in-floor
utilities
4 days Fri 7/21/00
Wed
7/26/00
58
G.C. Labor
Crew[33%],Plumbing
Contractor[33%],Electric
Contractor[33%]
Auto
Scheduled
Pour 1st floor
slab
4 days Fri 7/28/00
Wed
8/2/00
69,72,70,71 G.C. Concrete Crew
Auto
Scheduled
Cure 1st floor
slab
7 days Thu 8/3/00 Fri 8/11/00 73 G.C. Labor Crew[10%]
Auto
Scheduled
Strip forms
from 1st floor slab
2 days
Mon
8/14/00
Tue
8/15/00
74 G.C. Labor Crew
Auto
Scheduled
Carpentry Work 15 days Tue 9/5/00
Mon
9/25/00

Auto
Scheduled
Install exterior
sheathing and
metal studs
3 wks Tue 9/5/00
Mon
9/25/00
63,68 Drywall Contractor
Auto
Scheduled
Masonry Work 110 days Tue 6/6/00
Mon
11/6/00

Auto
Scheduled
Rough-in
plumbing at toilets
and masonry walls
4 wks
Wed
8/16/00
Tue
9/12/00
75,13 Plumbing Contractor
Auto
Scheduled
Lay masonry at
core, mechanical,
and toilets
4 wks Tue 6/6/00
Mon
7/3/00
49,50 Masonry Contractor
Auto
Scheduled
Install exterior
masonry work
5 wks
Tue
9/26/00
Mon
10/30/00
77 Masonry Contractor
Auto
Scheduled
Install roof
drains
2 days
Tue
10/31/00
Wed
11/1/00
81 Roofing Contractor
Auto
Scheduled
Install tile in
toilet rooms
2 wks
Wed
9/13/00
Tue
9/26/00
79 Tile Contractor
Auto
Scheduled
Clean masonry 1 wk
Tue
10/31/00
Mon
11/6/00
81 Masonry Contractor[50%]
Auto
Scheduled
Clean toilet
room tile
1 wk
Wed
9/27/00
Tue
10/3/00
83 Tile Contractor[50%]
Auto
Scheduled
Roofing 31 days
Tue
10/31/00
Tue
12/12/00

Auto
Scheduled
Install flashing
at parapet walls
4 days
Tue
10/31/00
Fri 11/3/00 81 Roofing Contractor
Auto
Scheduled
Pour
lightweight
concrete roof fill
2 days
Mon
11/6/00
Tue
11/7/00
11,82,87 Roofing Contractor
Auto
Scheduled
Install
seamless roofing
material
5 days
Wed
11/15/00
Tue
11/21/00
88FS+5 days Roofing Contractor
Auto
Scheduled
Spread stone
ballast on
seamless roof
5 days
Wed
11/22/00
Tue
11/28/00
89 Roofing Contractor
Auto
Scheduled
Set rooftop
equipment
2 wks
Wed
11/29/00
Tue
12/12/00
90 HVAC Contractor
Auto
Scheduled
Window wall
and store front
closures
60 days
Tue
10/31/00
Mon
1/22/01

Auto
Scheduled
Install window
wall aluminum
and glass
5 wks
Tue
10/31/00
Mon
12/4/00
81 Window Contractor
Auto
Scheduled
Install interior
stud walls and
drywall
5 wks
Tue
12/5/00
Mon
1/8/01
93 Drywall Contractor
Auto
Scheduled
Install interior
doors and
hardware
2 wks Tue 1/9/01
Mon
1/22/01
94
G.C. Finish Carpenter
Crew
Auto
Scheduled
Install store
front doors and
hardware
3 wks
Tue
10/31/00
Mon
11/20/00
81 Window Contractor
Auto
Scheduled
Building Finishes 80 days
Tue
12/5/00
Mon
3/26/01

Auto
Scheduled
Install millwork
and wood trim
3 wks Tue 1/9/01
Mon
1/29/01
96,94
G.C. Finish Carpenter
Crew
Auto
Scheduled
Paint walls and
woodwork
4 wks
Tue
1/30/01
Mon
2/26/01
98,95 Painting Contractor
Auto
Scheduled
Install conduit
at ceiling plenum
space
3 wks
Tue
12/5/00
Mon
12/25/00
93 Electric Contractor
Auto
Scheduled
Install duct in
ceiling plenum
space
3 wks Tue 1/9/01
Mon
1/29/01
94,100 HVAC Contractor
Auto
Scheduled
Install ceiling
grid
2 wks
Tue
1/30/01
Mon
2/12/01
94,101 Drywall Contractor
Auto
Scheduled
Install ceiling
tile
2 wks
Tue
2/13/01
Mon
2/26/01
102 Drywall Contractor
Auto
Scheduled
Hang
wallpaper
2 wks
Tue
2/13/01
Mon
2/26/01
102 Painting Contractor
Auto
Scheduled
Install building
carpet
4 wks
Tue
2/27/01
Mon
3/26/01
99 Carpet Contractor
Auto
Scheduled
Install
hardware and
accessories
3 wks
Tue
2/27/01
Mon
3/19/01
99
G.C. Finish Carpenter
Crew
Auto
Scheduled
Complete
interior and
exterior sod and
plantings
2 wks
Tue
2/27/01
Mon
3/12/01
99 Landscape Contractor
Auto
Scheduled
Pave, curb, and
stripe parking lot
2 wks
Tue
3/13/01
Mon
3/26/01
107 Paving Contractor
Auto
Scheduled
Elevators 40 days Tue 7/4/00
Mon
8/28/00

Auto
Scheduled
Set elevator
equipment in
shafts
4 wks Tue 7/4/00
Mon
7/31/00
80,45,12 Elevator Contractor
Auto
Scheduled
Set equipment
in mechanical
room
2 wks Tue 8/1/00
Mon
8/14/00
110 Elevator Contractor
Auto
Scheduled
Test and align
doors and
equipment
2 wks
Tue
8/15/00
Mon
8/28/00
111 Elevator Contractor
Auto
Scheduled
Plumbing 90 days
Tue
11/7/00
Mon
3/12/01

Auto
Scheduled
Rough-in
plumbing in
drywall walls
4 wks
Tue
12/5/00
Mon
1/1/01
93 Plumbing Contractor
Auto
Scheduled
Tie-in fire line
riser and set
valves
2 wks
Tue
11/7/00
Mon
11/20/00
84 Plumbing Contractor
Auto
Scheduled
Set plumbing
fixtures and trim
3 wks Tue 1/2/01
Mon
1/22/01
85,114,79 Plumbing Contractor
Auto
Scheduled
Flush, test, and
clean piping and
fixtures
2 wks
Tue
2/27/01
Mon
3/12/01
99,115,116 Plumbing Contractor
Auto
Scheduled
Electrical 139 days
Wed
8/16/00
Mon
2/26/01

Auto
Scheduled
Rough-in
electrical in
masonry walls
4 wks
Wed
8/16/00
Tue
9/12/00
75,14 Electric Contractor
Auto
Scheduled
Rough-in
electrical in
drywall walls
4 wks
Tue
12/5/00
Mon
1/1/01
93 Electric Contractor
Auto
Scheduled
Pull wire in
conduit and set
area transformers
3 wks
Tue
12/26/00
Mon
1/15/01
119,100 Electric Contractor
Auto
Scheduled
Install and
terminate
electrical devices
3 wks
Tue
1/16/01
Mon
2/5/01
121,120 Electric Contractor
Auto
Scheduled
Make electrical
terminations for
HVAC equipment
2 days
Tue
1/16/01
Wed
1/17/01
121,91 Electric Contractor
Auto
Scheduled
Install light
fixtures - test and
clean
2 wks
Tue
2/13/01
Mon
2/26/01
102,122 Electric Contractor
Auto
Scheduled
Heating and
Ventilating - AC
180 days Tue 7/4/00
Mon
3/12/01

Auto
Scheduled
Set equipment
in mechanical
room
2 wks Tue 7/4/00
Mon
7/17/00
80,15 HVAC Contractor
Auto
Scheduled
Rough-in
mechanical in
masonry walls
4 wks
Wed
8/16/00
Tue
9/12/00
75 HVAC Contractor
Auto
Scheduled
Rough-in
mechanical in
drywall walls
2 wks
Tue
12/5/00
Mon
12/18/00
93 HVAC Contractor
Auto
Scheduled
Install duct in
building chase
3 wks
Tue
12/5/00
Mon
12/25/00
126,127,93 HVAC Contractor
Auto
Scheduled
Set HVAC trim
and test and
balance system
4 wks
Tue
2/13/01
Mon
3/12/01
102,129,123 HVAC Contractor
Auto
Scheduled
Final Clean-up
and Occupancy
60 days Tue 1/9/01
Mon
4/2/01

Auto
Scheduled
Install hard tile
flooring in
common areas
1 wk Tue 1/9/01
Mon
1/15/01
94 Tile Contractor
Auto
Scheduled
Clean hard tile
floors
4 days
Tue
1/16/01
Fri 1/19/01 132 Tile Contractor[50%]
Auto
Scheduled
Remove debris
from building and
do final clean-up
4 days
Tue
3/27/01
Fri 3/30/01 ########## G.C. Labor Crew
Auto
Scheduled
Substantial
completion date
1 day Mon 4/2/01
Mon
4/2/01
134 G.C. Superintendent
Auto
Scheduled
Complete Final
Inspections
6 days
Mon
4/2/01
Mon
4/9/01

Auto
Scheduled
Complete
elevator
inspection and
certification
3 days Mon 4/2/01
Wed
4/4/01
134,112 Elevator Contractor
Auto
Scheduled
Perform
architect's
inspection
1 day Thu 4/5/01 Thu 4/5/01 134,108,137
G.C.
Superintendent[50%],G.C.
Project
Management[50%]
Auto
Scheduled
Perform local
building agency
inspection
1 day Fri 4/6/01 Fri 4/6/01 138
G.C. Project
Management[50%],G.C.
Superintendent[50%]
Auto
Scheduled
Perform Fire
Marshal's
inspection
1 day Mon 4/9/01
Mon
4/9/01
139
G.C.
Superintendent[50%],G.C.
Project
Management[50%]
Auto
Scheduled
Complete punch
list items from all
inspections
2 wks
Tue
4/10/01
Mon
4/23/01
140
G.C.
Superintendent[11%],G.C.
Labor
Crew[11%],Plumbing
Contractor[11%],Electric
Contractor[11%],HVAC
Contractor[11%],Drywall
Contractor[11%],Carpet
Contractor[11%],Paving
Contractor[11%],Painting
Contractor[11%]
Auto
Scheduled
Obtain
certificate of
occupancy
2 days
Tue
4/24/01
Wed
4/25/01
141 G.C. Project Management
Auto
Scheduled
Issue final
completion
documents
including
warranties
1 day
Tue
4/24/01
Tue
4/24/01
141 G.C. Project Management
Auto
Scheduled
Issue final
request for
payment
1 day
Thu
4/26/01
Thu
4/26/01
142,143
G.C. Project
Management[33%],G.C.
Accounting[33%],G.C.
General
Management[33%]