Professional Documents
Culture Documents
com/info
Volume 2 Issue 2 September/October 2009
FEATURES
22 Directional Drilling Tackles Tricky Terrain
One project went through hard rock in Georgia, and the other
crossed a busy harbor in Virginia. Michels Directional Crossing and
Mears Group Inc. drill through the challenges.
28 Delivering Pipelines by Air
Vacuum technology helps improve the safety and operational costs
of lifting pipes on a jobsite. By Leanne Butkovic
32 Finding Approval
A look at how the Federal Energy Regulatory Commission (FERC)
approves infrastructure projects, sets rates and enforces the oil and
gas market. By Bradley Kramer
36 Deconstructing Worksite Hazards
Review the basics of Job Safety Analysis, a simple, inexpensive and
effective management tool that can help reduce worksite hazards.
By George Kennedy
DEPARTMENTS
8 News
12 Project Roundup
14 Market Watch
40 Product Showcase: ROW/Land Clearing
46 Events Calendar
COLUMNS
6 Editor’s Message
MARKETPLACE
45 Business Cards
46 Index of Advertisers
NORTH AMERICAN PIPELINES is published bi-monthly. Copyright 2009, Benjamin Media, Inc., P.O. Box 190, Peninsula, OH 44264. All rights reserved. No part
of this publication may be reproduced or transmitted by any means without written permission from the publisher. One-year subscription rates: complimen-
tary in the United States and Canada, and $99.00 in other foreign countries. Single copy rate: $10.00. Subscriptions and classified advertising should be
addressed to the Peninsula office. Periodical Postage Paid at Peninsula, Ohio and at additional mailing offices. POSTMASTER: send address changes to NORTH
AMERICAN PIPELINES, P.O. Box 190, Peninsula, OH 44264 USA.
Canadian Subscriptions: Canada Post Agreement Number 40040393. Send change of address information and blocks of undeliverable copies to P.O. Box 1051,
Fort Erie, ON L2A 6C7.
The global economy continues to slowly lift itself from Associate Publisher
this deep downturn, and oil and gas infrastructure projects Robert D. Krzys
have hit the brakes. Or have they?
After strong years of growth from 2006 to 2008, when Editor
natural gas pipeline construction helped fuel the recent James W. Rush
boom years, the industry has cut back on building large-
scale transmission lines, according to Jeff Wright, direc- Associate Editor
tor of energy projects for the Federal Energy Regulatory Bradley Kramer
Commission (FERC). After approving almost 6,000 miles
of pipeline projects in the last three years, the commission Contributing Staff Editors
has approved only 172 miles for 2009. But don’t bother Sharon M. Bueno
running for cover. Keith Gribbins
“The sky is not falling like everybody says,” says Ritchie Bros.’ Butch Graham, Jason Morgan
who assured me when I spoke with him for this issue’s cover story (on page 16) Pam Stask
that pipeline contractors will help pull us out of the recession.
Indeed, Wright says that while the miles of pipeline projects might be down, Creative Director
capacity is increasing as pipeline owners build support infrastructure for the pipe- W. M. Conley
lines and storage facilities.
Many of the projects that were approved in the last few years are still in the Graphic Designers
construction phases, like the two natural gas projects we cover in this issue. Sarah Hayes
Michels Directional Crossing and Mears Group completed two major expansion
Chris Slogar
projects with horizontal directional drilling (see page 22).
Elizabeth C. Stull
Regardless of what happens, the world needs energy, and energy needs infra-
structure. Pipeline projects continue to move forward — albeit at a slower pace
Marketing Manager
than in the past few years — and more projects are waiting in the wings. You can
Kelly Dadich
read about what FERC has in its approval process and other regulatory issues in
“Finding Approval” (on page 32).
Regional Sales Managers
The oil and gas industry is even finding ways to coexist with alternative and
Ryan Sneltzer
renewable energy sources, as Chevron just started building a 29-megawatt solar
Dan Sisko
steam plant at one of its oil fields in Coalinga, Calif. (New York Times, Aug. 24).
The power plant will be used to inject steam into the oil wells to enhance produc-
Circulation Manager
tion.
Alexis R. Tarbet
Forbes magazine put ExxonMobil on its cover as the “Green Company of the
Year” for investing $600 million on developing algae farms to produce automotive
Web & Interactive Manager
gasoline and continuing to boost its natural gas production.
Mark Gorman
How’s that for green?
Despite some slowdowns in the industry, the pipeline industry is resilient.
Conference Manager
We all need energy to push through our challenges and keep business moving.
Michelle Magyar
Project Roundup
Contributed by
The following oil and gas pipeline projects have been announced. U.S. Pipeline Inc. has been awarded a contract by Williams-Transco for
Projects are in order of approximate starting date. installation of 1.2 miles of 42-in. pipeline and L&R Asm. piping in Union
County, N.J. Headquarters is Linden, N.J. The superintendent is Eugene
U.S. Pipeline Inc. has been awarded a contract by Boardwalk Pipeline Weber. Approximate start date: July 15.
Partners to install two 1,600 ft horizontal directional drills of 42-in. pipeline in
Bienville Parish, La. The superintendent is Jim Jennings. Approximate start Utility Line Services Inc. has been awarded a contract by East
date: June 16. Resources/NFG to install 18.5 miles of 12-in. pipeline and a compressor
station in Bradford, Lycoming and Tioga counties, Pa. Headquarters is
Blackwell Enterprises Inc. has been awarded a contract by U.S. Pipeline Canton, Pa. The superintendent is Ron Michalkovich. Approximate start
Inc. to hydro-seed approximately 10 miles of 24-in. pipeline right-of-way in date: July 16.
Baton Rouge and Point Coupee Parishes, La. Headquarters is Port Allen, La.
The superintendent is Bob Blackwell. Approximate start date: June 22. Indianhead Pipeline Services has been awarded a contract by Michels
Corp., U.S. Pipeline Inc. and Precision Pipeline LLC for the Enbridge
Pe Ben USA Inc. has been awarded a contract by Snelson Companies Alberta Clipper and Southern Lights Project to manufacture approxi-
Inc. to string 27 miles of 24-in. pipe in Rio Blanco County, Colo. Headquar- mately 17,500 pieces of 36-in. pipeline and 171,000 ft of 20-in. pipeline in
ters is Meeker, Colo. The superintendent is Eric Gregory. Approximate start Kittson, Marshall, Pennington, Red Lake, Mahnomen, Clearwater, Beltrami,
date: June 22. Hubbard, Cass, Itasca, St. Cloud and Carlton counties, Minn. Head-
quarters is Deer River, Minn. The superintendent is Randy Rubenzer.
Welded Construction LP has been awarded a contract by Williams Gas Approximate start date: July 20.
Pipeline/Transco for pipeline investigation on mainline “D” of 42-in. pipeline
in Fairfax County, Va. Headquarters is Manassas, Va. The superintendent is L.A. Pipeline Construction Co. Inc. has been awarded a contract
Joe Carter. Approximate start date: June 22. by Texas Gas Transmission LLC to install new pig traps in Butler and
Warren counties, Ohio. Headquarters is Lebanon, Ohio. The superintendent
Laney Directional Drilling Co. has been awarded a contract by Henkels is Steve Drake. Approximate start date: July 20.
& McCoy Inc. for directional pipeline drilling of 1,749 ft of 42-in. pipeline in
Muskingum County, Ohio. Headquarters is on the jobsite. The superinten- Miller Pipeline Corp. has been awarded a contract by Vectren to
dent is Jimmie Johnson. Approximate start date: July 1. replace 1,900 ft of 16-in. natural gas pipeline in Montgomery County, Ohio.
The superintendent is Wes Bogard. Approximate start date: July 20.
Blackwell Enterprises Inc. has been awarded a contract by Henkels &
McCoy Inc. for right-of-way restoration and maintenance of approximately U.S. Pipeline Inc. has been awarded a contract by Enbridge Energy
60 miles of 42-in. pipeline in Lamar County, Texas. Headquarters is Paris, to install approximately 400 ft of 36-in. pipe torch cuts in Beltrami County,
Texas. The superintendent is Glen Madden. Approximate start date: July 6. Minn. Headquarters is Bemidji, Minn. The superintendent is Jim Jennings.
Approximate start date: July 20.
L.A. Pipeline Construction Co. Inc. has been awarded a contract by
Chesapeake Energy Corp. to install approximately five miles of 16-in. and Snelson Companies Inc. has been awarded a contract by Northwest
4,800 ft of 12-in. pipeline, plus launchers, receivers and valve settings Pipelines GP to install 16-in. and 24-in. piping in Rio Blanco County, Colo.
and additional 16-in. through 6-in. segments pending in Wyalusing, Pa. Headquarters is Meeker, Colo. The superintendent is Mike Swanson.
Headquarters is Wyalusing, Pa. The superintendent is Jeff Waggoner. Approximate start date: July 23.
Approximate start date: July 6.
Dun Transportation & Stringing Inc. has been awarded a contract by
Laney Inc. has been awarded a contract by Sheehan Pipe Line Con- Evraz Inc./Williams Gas to unload and stockpile approximately 80,000 ft of
struction Co. for directional drilling on 50 miles of 30-in. pipeline in Audrain, 30-in. pipe in Lincoln County, Wyo. The superintendent is Johnny Denton.
Montgomery and Lincoln counties, Mo. Headquarters is Troy, Mo. The su- Approximate start date: July 24.
perintendent is Grady Keller. Approximate start date: July 6.
Apex Pipeline Services Inc. has been awarded a contract by Columbia
Snelson Companies Inc. has been awarded a contract by Williams Gas Transmission Inc. for the following: 1) removal and replacement of
Northwest Pipeline to relocate 10,500 ft of 22-in. pipeline in Ada and Can- approximately 400 ft of 20-in. steel pipe in Floyd County, Ky.; headquarters
yon counties, Idaho. The superintendent is Louie Garcia. Approximate start is Dana, Ky.; the superintendent is Ransford Vickers; and 2) the removal
date: July 7. of approximately 1,200 ft of 12-in. pipeline and replace with approximately
1,200 ft of 8-in. steel gas line in Newport News, Va, and installation of
Henkels & McCoy Inc. has been awarded a contract by Transcontinental launcher, receiver, valve assemblies and induction bends in Isle of Wright
Gas Pipeline to install 1.93 miles of 42-in. pipeline in Luzerne County, Pa. County, Va.; headquarters is Carrollton, Va.; the superintendent is Cecil
The superintendent is George Tisdale. Approximate start date: July 13. Hill. Approximate start date: 1) July 27 and 2) Aug. 17.
Precision Pipeline LLC has been awarded a contract by Enbridge Blackwell Enterprises Inc. has been awarded a contract by Henkels &
Energy (Streator to Manhattan Project) for 46 miles of 20-in. pipeline in McCoy Inc. for right-of-way restoration of approximately 30 miles of 42-in.
LaSalle, Grundy and Will counties, Ill. Headquarters is Morris, Ill. The super- pipeline in Fairfield, Perry and Muskingum counties, Ohio. Headquarters is
intendent is Russell Fischer. Approximate start date: July 13. Zanesville, Ohio. The superintendent is Bob Blackwell. Approximate start
date: July 27.
Snelson Companies Inc. has been awarded a contract by Puget Sound
Energy for 33,000 ft of 16-in. pipeline in King County, Wash. The superinten- Henkels & McCoy Inc. has been awarded a contract by Transcontinental
dent is Jeff Elliot. Approximate start date: unknown (announced July 13). Gas Pipe Line to install 3.99 miles of 42-in. pipeline in Somerset County,
N.J. Headquarters is Neshanic, N.J. The superintendent is George Tisdale.
Snelson Companies Inc. has been awarded a contract by Avista Corp. Approximate start date: July 27.
to install 3.2 miles of 12-in. pipeline in Spokane County, Wash. The superin-
tendent is Cliff Nielson. Approximate start date: July 13. PipeSak Inc. has been awarded a contract by Enbridge to supply 130
miles of 20-in. and 36-in. fabrication weights for the Alberta Clipper Proj-
S T Pipeline Inc. has been awarded a contract by NiSource/Columbia ect in Kittson, Marshall, Polk, Red Lake and Clearwater counties, Minn.
Transmission for slip repair and pipe replacement of 100 ft of 24-in. pipeline Headquarters is Superior, Wis. The superintendent is Ryan Connors.
in Mingo, W.Va. The superintendent is George McQuain. Approximate start Approximate start date: unknown (announced July 27).
date: July 13.
BigInch Fabricators and Construction Inc. has been awarded a contract
Rockford Corp. has been awarded a contract by Wild Goose Stor- by Panhandle Eastern Pipeline to send a 26-in. launcher and receiver with
age Inc. for installation of four miles of 24-in. pipeline in Butte County, associated piping in Morgan and Sangamon counties, Ill. Headquarters in
Calif. Headquarters is Gridley, Calif. The superintendent is David Carlile. Springfield, Ill. The superintendent is Frank Ayers. Approximate start date:
Approximate start date: July 15. July 29.
H
is voice is deep and melodious in conversation, calm- Graham got into the oil and gas pipeline industry in
ing in its resonance. When he’s at work, though, it the late 1970s and early 1980s, about the time when the
sounds like a hard-driving drum solo, rattling off large Trans-Alaska Pipeline was wrapping up. He then joined
figures in quick succession, stalling for a moment to let the Ritchie Bros. in 1987 — a job he cherishes — and worked with
audience catch its place, and then the voice rattles off more company founder Dave Ritchie, for whom Graham has
numbers before it says, “Are you done?… Last call… Sold.” nothing but respect and gratitude.
Butch Graham’s voice announces the sale of another Ritchie Bros. conducts more than 340 auctions each year
piece of construction equipment. at its 39 auction sites in the United States, Canada, Mexico,
As a senior auctioneer for Ritchie Bros. Auctioneers, his Europe, the Middle East and Australia, and many off-site.
voice is his trademark. However, it is Graham’s decades of The company was established in 1958 as a small, family-run
experience and expertise in the oil and gas market that led furniture store in Kelowna, British Columbia. In 1963, the
to his nickname as “the voice of the pipeline industry.” company began selling industrial equipment.
16 North American Pipelines | SEPTEMBER/OCTOBER 2009 napipelines.com
Graham is one of the most senior auctioneers at Ritchie responsibility to put my best foot forward. I always felt I
Bros., says Peter Blake, CEO of the auction company. During was representing them.”
his tenure at Ritchie Bros., Graham has worked at some of It’s Graham’s personal touch that has endeared him to the
the company’s most memorable auctions, such as the auc- oil and gas pipeline industry, says Dave Douglas, manager
tions that followed the 1989 Exxon Valdez oil spill. Close to of the Canadian Pipeline Division for Ritchie Bros. (Graham
10,000 people attended the first auction in Anchorage, and calls him “little brother,” says Douglas, who has been with
Graham remembers it all too well. Ritchie Bros. for 14 years.)
Graham gets extremely excited about converting the “Butch is so well respected by all the contractors, and
customers’ assets into cash. “It’s a tremendous rush,” he he knows them all,” Douglas says. “His outgoing personal-
says. Sometimes Ritchie Bros. hosts auctions that last two, ity and his honesty and integrity are what people respect.
three and four days. That Exxon Valdez auction lasted five When people buy a piece of equipment, they know it is
days and included all varieties of equipment, including what Butch says it is. You can take his trust to the bank.”
cranes and boats. When the auction started at 6 a.m., it Graham has worked with every major pipeline contrac-
was still dark. tor in the United States and many of the international
contractors as well. He is also heavily involved with the
industry’s trade organizations, specifically the Distribution
Contractors Association (DCA), the International Pipeline
and Offshore Contractors Association (IPLOCA) and the
Pipe Line Contractors Association (PLCA).
Graham’s market expertise is an asset to his customers,
says Tom White, president of Price Gregory Construction
and who has known Graham for 28 years. “He’s a big
force in the pipeline industry,” he says. “We’ve done
industry sales through him, but sometimes I use him as
a sounding board for what equipment is worth and the
best time to sell.”
Contractors value Graham’s knowledge of equipment
values and how best to market and sell it at an auction, says
Pat Michels, president of Michels Corp. “His talents as an
auctioneer are second to none.
Ritchie Bros. conducts more than 300 auctions all over the world,
with buyers who show up in person or bid online via a live webcast.
“Now, I’ve never been shy,” Graham says. “When the sun
peaked over the mountains and I saw that enormous crowd,
it was the only time I had a weakness in my voice.”
There was so much equipment to sell from the Exxon
Valdez spill that another three-day auction was held in
Tacoma, Wash.
Graham has been an auctioneer all his life. His father
worked in marketing livestock auctions, and his uncle,
cousin and brother worked as auctioneers. His brother still
runs the family auction business. “I’ve always had good ora-
tor skills,” he says. But auctioneering isn’t just about getting
up to the podium and talking fast.
“Anyone can get up there and talk fast,” he says.
“You have to be able to see the trends. I’m one of the
remaining auctioneers around who went through the
crash of 1982-1985 and saw the low times.”
Graham takes pride in his equipment knowledge and
building relationships. He feels that it’s his duty to know
the market and equipment so he can pass the information
along to his customers.
“One thing I’ve learned about the business as a senior
auctioneer and pipeline rep for Ritchie Bros. is you have
to make the customer your friend because your friend will
always be your customer,” Graham says. “My face and my
voice are always out there for Ritchie Bros., and it’s my For more information go to napipelines.com/info
“He is very personable and sincere. He knows what’s go- Yes, Graham has used his auctioneering skills to help those
ing on in the energy industry and is able to translate that associations, but he doesn’t expect credit. He isn’t there for his
to when he’s selling at an auction,” says Michels, who has own laurels, but as a representative of Ritchie Bros. “Without
known Graham for 20 years and considers him as a good Ritchie Bros., there would be no Butch Graham,” he says. Graham
family friend. credits Dave Ritchie for instilling these professional ethics.
Graham also passes on his vast industry knowledge “For as long as I can remember, Butch has played a very
to his colleagues at Ritchie Bros. “Our new auctioneers significant role for Ritchie Bros. in the oil and gas industry,”
look to him for advice and training,” Blake says, “and he Blake says. “And Butch is a personality everywhere he goes
has helped to make our auctioneer crew the great team — not just at your conferences. He brings his uncompromis-
it is today.” ing level of integrity and family values from his roots in
Douglas consults with Graham as he works his sales terri- Marlow, Okla., to the world.”
tory in Canada. Douglas says he tries to learn as much as he Blake thinks that people appreciate Graham’s “down
can from the auctioneer. home nature.” That appreciation shows in how the indus-
“We work hand in hand to share information about try has awarded Graham. He was elected to IPLOCA’s board
who is interested in buying or selling or what a piece of directors for a term in 2002, and he was made an Honor-
of equipment is worth,” Douglas says. “Butch knows ary Lifetime Member of DCA.
so many people that he just has a broader base to work Despite what personal successes may come his way,
from. He has relationships that are four generations old Graham is always appreciative of those around him.
in some cases. It’s more like me asking questions and him He can’t do it alone.
having the answers.” “There’s a woman in my life who is just as much of
an ambassador for Ritchie Bros. as I am,” Graham says.
Love the Industry “My wife Bonnie knows all the wives and kids. She loves
Just as Graham has been an auctioneer all his life, he also the industry and Ritchie Bros. just like I do.”
has been around the oil and gas industry since his youth. In October, Butch and Bonnie will celebrate 39 years of
He was raised and still lives in Oklahoma. As he says, marriage. He says his wife helps him build strong relation-
“I grew up around the oil patch.” Graham’s granddad was ships, forming a close knit community with the other wives
friends with Erle Halliburton. in the industry.
“You have to love what you do,” Graham says. Through- “There’s no price for that,” Graham says. “It’s all about
out his decades of auctioneering for the oil and gas pipe- relationship building. There’s no competitive way to deal
line industry, Graham has helped raise millions of dollars with that.”
through charity auctions for DCA, IPLOCA and PLCA. Through it all, Graham strives to be a good representative
He has also been involved with the American Pipeline of Ritchie Bros. and the oil and gas industry.
Contractors Association (formerly, the Rocky Mountain “I hope I’m doing it right,” he says. “You’ve got to love
Contractors Protective Association). it. And I do.”
18 North American Pipelines | SEPTEMBER/OCTOBER 2009 napipelines.com
Good Times and Bad $1 million are now selling at $400,000. “It’s trending down,
In a tough economy, the unreserved auction format is still but the bottom has not fallen out,” he says. Graham only
a popular option for both equipment buyers and sellers, Blake hopes that the downturn doesn’t last as long as the one in
says. During the current recession, Ritchie Bros. has seen a the 1980s.
record number of bidders participating at its auctions.
“A need for equipment still exists as global building and Auction Day
construction projects carry on,” Blake says. “Buyers are just “You have to appreciate what goes into the auction,”
more cautious of pricing right now given the current state Graham says. “The people at Ritchie Bros. research their
of the economy. This is evident given the decline in new territories for two to three months beforehand.”
equipment sales over the past year and they know they can Ritchie Bros. has more than 1,000 sales reps across the
find good equipment they need at one of our auctions at world. The field reps call on their customers to see if they
prices they are more willing to pay.” are interested in selling a piece of equipment. The reps are
The other side of that equation is that equipment own- in constant contact with their clients. Graham himself acts
ers are realizing that in this downturn, idle equipment is as a lead sales person during the lead-up to an auction.
not cost-effective, Blake says. The result is many equip- Each auction has hundreds of consignors, Graham says.
ment owners are choosing to sell their equipment instead Ritchie Bros. inspects the equipment and signs a contract
of keeping it. with the seller, and the equipment goes into one of the
In any industry, there will always be good times and company’s equipment yards. Occasionally, Ritchie Bros.
bad times, Graham says, but he is a strong believer that will do a sale off one of its sites, such as when an industry
pipeline contractors will help turn the economy around. veteran retires and needs to sell a bunch of equipment at
The world still needs to build and maintain infrastructure, once. If needed, the Ritchie Bros. refurbishes and repaints
and because of that, business will go on. the equipment.
“The sky is not falling like people think it is,” he says. Then the marketing department goes to work promot-
The natural gas market just came out of a boom year, but ing the auction. Auctions attract buyers from all over the
has taken a dive. Oil is still very profitable at more than $70 world. Bids can be placed in person or online through
per barrel. What’s hurting natural gas is the price of natural the company’s live webcast at www.rbauction.com.
gas, Graham says. “That’s why we’re not seeing much move- “When the sale date comes,” Graham says with a charge
ment on projects, because the price collapsed,” he adds. in his voice, “it’s my turn.”
Graham saw the last crash in the oil and gas industry, and
he sees many similarities with the industry now, such as Bradley Kramer is associate editor of North American Pipelines.
the trends in equipment sales. Drill rigs that used to fetch He can be contacted at bkramer@benjaminmedia.com.
• To promote, foster and develop the science and practice of constructing onshore and offshore pipelines and associ-
ated works.
• To make membership of the association a reasonable assurance of the skill, integrity, performance and good faith of
its members.
• To maintain the standards of the contracting business for onshore and offshore pipelines and associated works at the
highest professional level.
• To promote safety and to develop methods for the reduction and elimination of accidents and injury to contractors’
employees in the industry and all those engaged in or affected by operations and the work.
• To promote the protection of the environment and contribute to social, cultural and environmental development.
• To promote good and cooperative relationships amongst the membership of the association and between contractors,
owners, operators, statutory and other organizations and the public generally.
• To encourage efficiency amongst the members, associate members and their employees.
• To seek correction of injurious, discriminatory or unfair business methods practiced by or against the industry contrac-
tors as a whole.
• To maintain and develop good relations with sister associations as well as associations allied to our industry and to
play a leading role in the World Federation of Pipeline Industry Associations.
• To follow the established Codes of Conduct set out by the industry and others with respect to working within a free
and competitive market.
A
Georgia coal-burning power plant is in the The longest crossings have been drilled to lengths of
process of converting to natural gas, requiring approximately 3,000 ft while some of the shorter cross-
construction of approximately 19 miles of a ings have been closer to 1,000 ft long. Interstate 285 will
new gas pipeline in Atlanta. In order to build be crossed three times by Michels’ HDD operations and
the pipeline around the west side of the city, the utility Interstate 20 has been successfully crossed at one location.
commissioned U.S. Pipeline to lay the pipe in trenched Many other major highways and roadway crossings along
portions of the right-of-way (ROW) and prepare horizon- the route are also being completed by HDD construction, as
tal directional drilling (HDD) pipe pull sections for Michels well as several major water bodies and wetlands including
Directional Crossings. Michels had to complete the HDD a difficult crossing of the Chattahoochie River that Michels
crossings in areas where trenching is either not feasible due recently completed near the end of July.
to accessibility issues or not economically viable due to The rock encountered so far has been primarily granite-
complex pipeline construction constraints. type, varying widely in strength, hardness and consistency
In April 2009, Michels began construction of 19 planned depending on depth and degree of weathering. The rock is
HDD crossings of 30-in. pipe through these mandated also typically encountered at varying depths along the HDD
trenchless construction areas along the 19-mile pipeline design alignment and Michels has worked closely with U.S.
stretch, drilling through a varied mix of hard rock and soil Pipeline, the owner’s designer and the owner of the utility
ground conditions. to limit the lengths and depths of the crossing designs to
Michels operated up to five of its 13 large capacity minimize costs to the owner of drilling through longer
drilling rigs at any given time on this project and estimates sections of the harder rock formations at greater depths.
that over six miles of the project will be directional drilled Prior to starting the project, the owner performed an
with almost 50 percent of the HDD crossings completed extensive geotechnical study of the proposed HDD design
through rock despite extensive HDD design and construc- alignments. The crossings were initially designed as short
tion length minimization efforts. and shallow as possible based on this data, among other
22 North American Pipelines | SEPTEMBER/OCTOBER 2009 napipelines.com
ROW constraints. However, given that the elevation of the variations of bottom hole drilling assemblies are required
top of the rock can vary significantly in a short distance just to steer the pilot hole along the designed alignment
in this area, some of the crossing design paths had to be as these contrasting, “mixed-face” conditions are encoun-
re-oriented once HDD pilot hole operations were initiated tered. Fortunately, Michels’ crews are well versed in drilling
when the rock elevations were not encountered as antici- in hard rock conditions around the world with extensive
pated with the original design. experience in the Atlanta area, so the company knew what
In addition to this “adjust the design as you go” methodol- to expect and came prepared.
ogy being employed on many of the crossings, the adapta- Michels also has implemented the use of HDD intersect
tion of HDD technology in so many confined areas where technology on several of the crossings in order to success-
its use may have previously been thought unimaginable has fully complete the pilot holes within the tight constraints of
required a level of coordination and communication between the allowable design alignments. In attempting to shorten
the owner, designer and contractors that is unprecedented in these crossings as much as possible and achieve the rigor-
the HDD industry on a project of this magnitude. ous design tolerances, there are oftentimes limited options
The ultimate objective of the HDD construction is to for lengthening the crossings if the rock is encountered
provide a trenchless installation of a relatively rigid (i.e., unexpectedly or the formation prevents Michels from
wall thickness greater than a half-inch thick), 30-in. steel precisely controlling the pilot hole along the desired
pipe underground along a geometrically smooth trajectory alignment regardless of the company’s extensive inventory
from the entry to exit that allows it to bend through the of varied bottom hole assemblies.
bored out rock along the HDD alignment without adversely This requires drilling the pilot hole from the opposite
affecting the integrity of the pipe during installation and end of the crossing and intersecting the section of hole
operation. In order to accomplish this, first the HDD pilot previously drilled from the entry side to ensure the exit
hole geometry must be carefully monitored and controlled hole location and desired design alignment are precisely
as it is drilled along the desired design alignment. maintained. Michels has completed more than 50 inter-
Drilling and controlling the geometric shape of the HDD sects on other projects, but intersecting pilot holes in solid
alignment is technically and physically demanding, espe- granite can add significant time to a crossing’s duration,
cially when drilling in and out of rock that is encountered so this method is only implemented after all other options
at depth in varying locations and degrees of competency have been exhausted.
along each HDD alignment and when the crossing lengths The originally planned reaming parameters also required
are designed at the bare minimum, further reducing any modification by Michels on some of the crossings to fur-
room for construction error. Oftentimes several different ther ensure the integrity of the pipe installation on several
A
10-mile pipeline that will connect the north and On the water-to-water crossings, Mears’ 500,000-lb drill
south sides of Hampton Roads Harbor, Va. — made rig sat on a 350 by 38-ft barge with a four-point mooring
possible through onshore and marine horizontal system, a 250-ton capacity anchor winch and a 230-ton
directional drilling (HDD) — will allow Virginia Natural Gas to capacity crane. Next to that was a similarly large barge hold-
expand capabilities to serve a growing customer base and will ing more than 700,000 gallons of fresh water for the drill rig, a
also open new doors for HDD projects, industry experts say. mud cleaning system, drill pipe and various other equipment.
The project’s onsite work began in May 2008 and is A smaller crane barge supported a 140,000-lb rig at the
scheduled for completion in November 2009, with the final exit holes.
land-to-water shore approach completed and tie-ins of the To stabilize the drill barge during pullback, Mears Group
24-in. steel product pipe now under way. At the heart of project superintendent Mike Vidomski says Weeks Marine
the project were seven HDD crossings completed by Mears deployed a three-anchor holdback system using a chain
Group Inc. working closely with the prime contractor, rated for 1 million lbs to anchor the barge, therefore coun-
Weeks Marine Inc. teracting the force of the Mears rig. The innovative use of
Of those seven crossings, one was a record length 7,357- a tension clamp on the drill string by Mears, together with
ft crossing beneath the Elizabeth River and three were rare the anchor system, stabilized the barge to perfection.
water-to-water drills under Hampton Roads Harbor that “When we were pulling pipe into the hole there was
required the contractors to adapt to marine conditions. no movement on the barge,” says Carolina Palmer, Weeks
Perhaps the most important water-to-water crossing was Marine project manager. “It was like we were on land.”
the 3,003-ft bore spanning the 53 ft deep Newport News Mears steering technician James Eisenhauer says,
shipping channel, one of the world’s busiest commercial “We made land where there was no land.”
and military shipping lanes. To improve steering accuracy for both the river and harbor
Virginia Natural Gas senior project manager Les Flora, crossings, the contractors also outfitted a mobile coil barge
P.E., says horizontal directional drilling under the water- that floated on the surface above the path of the 9 7/8-in.
ways was the only practical way to complete the marine drilling bit while Mears bored the pilot hole. The coil barge
crossings since governmental agencies would not grant replaced Mears’ traditional method of placing wires on the
permits for techniques such as open-cut dredging due to
environmental and shipping concerns.
“When you look at all the environmental [and] ship-
ping concerns, we probably could not have successfully
permitted this project without being able to horizontally
directional drill,” Flora says. “The only way we could get
a permit, was to HDD. I’m sure that what the contractors
have learned on this project will be of great interest to those
in the industry.”
Flora says the project’s original design called for trenching
across the majority of the harbor, but that plan was revised
after entities such as the Army Corps of Engineers indicated
that permitting would not be possible.
Instead, Virginia Natural Gas looked to HDD techniques
to cross the marine sections of the project, areas that
include environmentally sensitive areas like clam sanctuar-
ies and oyster beds and shipping traffic that includes U.S.
Navy ships that use the fueling station on Craney Island.
Flora says that by using HDD techniques, the amount
of material needed to be trenched decreased by about two-
thirds the original planned quantity. “It was a pretty signifi-
cant amount,” he says.
The marine environment created unique hurdles for the
contractors to overcome: salt water that corroded equip-
ment, strong tides and currents, storms and sonar equip-
ment from passing ships and submarines that momentarily
fooled with steering readings.
To combat against the conditions, Weeks Marine cus-
tomized its barges to support and secure the equipment
Mears needed on the water. The Weeks team designed and
installed a robust anchoring system and other equipment
such as “goal posts” — steel pile structures straddling the
pipe alignment in front of the barges that helped guide the
pipe from the drill rig to the harbor floor.
For more information go to napipelines.com/info
Vacuums in Energy
Pipe lifting is imperative in the energy sector, as Vacu-
worx thrives in the oil and gas industry. “You have to have
a way to get the energy source, whether that’s gas or crude
oil, from point A to point B,” Lowman says. “To get it there,
you have to have a pipeline. To efficiently build a pipeline,
you need vacuum lifting.”
Aside from the oil and gas market, Vacuworx has reached
out to municipal utilities, including water and sanitary
sewers, and the plate steel business. Using vacuum lifting
allows for all of the necessary pipes to be lifted with ease, from
concrete, steel, HDPE, fiberglass, ductile iron, plastic, you
name it, with any kind of coating, from tape, FBE, coal tar,
concrete and so on. And because the vacuum’s rubber-type
vacuum pad seal, which is the component that actually makes
contact with the pipe, compensates for inconsistencies and
unevenness in the pipe and must be replaced every couple
hundred hours, all of the pipes’ coatings are kept pristine.
“Chains, swings, straps, hooks, they will scratch the
coatings,” Lowman says. “Anywhere they scratch the
coating on the pipe, they have to repair. So that’s a time
Safety may be the most important factor on a jobsite. Whenever a
saver in itself because our equipment does not hurt the
heavy load is suspended, danger is literally in the air. Vacuums offer
integrity of the coating in any way.” one of the safest and least risky lifting technologies available.
It’s a valid point worth mentioning since a scratched pipe
coating can be costly now and in the future. Some compa- “Where our part becomes very integral in that is if
nies have even gone so far as to write into their contracts they’re using vacuum lifting they can bid the job cheaper
that only vacuum lifting will be used on their jobsites because they don’t have as many employees to do the job as
simply because of coating issues. Methods aside from [someone] who’s not using vacuum lifting,” Lowman says.
vacuum lifting damage pipe coatings, which leave last- The contractor may get a reduction in insurance costs
ing impressions on the pipe several years down the road. because there are fewer employees in harm’s way.
Not only are these scratches costly, but the damaged While the vacuum itself isn’t necessarily inexpensive, the
locations that go unrepaired or are repaired poorly are often benefits it allows you to reap save money in the long run.
fail points in the pipe long after they have been buried. The company offers, in its own words, the lowest cost of
“The U.S. Department of Transportation was doing ownership and has contractors report back to them that the
five-year dig up inspections and finding failures from where Vaculift pays for itself on its first use.
pipe was marred up from chains,” Lowman says. Those five- “I don’t know why there isn’t anyone still not using
year inspections were what sparked current talks between vacuum,” Lowman says. “It’s much faster, it’s much safer
Vacuworx and the Department of Transportation about and it impacts your bottom line heavily.”
future regulations regarding the use of vacuum lifting from
inception to burial to avoid ruined pipe coating debacles Leanne Butkovic is an editorial intern for North American
in the future. Pipelines.
30 North American Pipelines | SEPTEMBER/OCTOBER 2009 napipelines.com
For more information go to napipelines.com/info
Finding
Approval
Talking Oil and Gas Regulations
with FERC’s Jeff Wright
By Bradley Kramer
T
he Federal Energy Regulatory Commission (FERC) rest of the application. The pre-filing process truncates the
is the primary permitting agency for the oil and gas overall analysis by six to eight months.
market in the United States. The commission is in During the environmental analysis, FERC looks at anything
charge of approving the construction of natural gas pipe- alive that a project will impact: plants, animals, socio-econom-
lines and storage facilities, regulating the price of transport- ic structures and cultural boundaries. The commission has to
ing oil and gas through transmission lines and enforcing look at whether the project disrupts such things as Native
the marketplace. Jeff Wright, director of energy projects for American burial mounds, waterways or wetlands and other
FERC, spoke with North American Pipelines about how this sensitive terrain. In doing so, FERC consults with other federal
process works and how the trends of the oil and gas market agencies, such as the Bureau of Land Management (BLM) and
affect the commission’s duties. the U.S. Forest Service. An operator needs approval from FERC
Among FERC’s responsibilities is the siting and and BLM if the project touches federal land.
approval of natural gas pipelines in the interest of Working with so many other agencies can add significant
commerce, import and export facilities and connec- time to the approval of an application, but the Energy
tions between the United States and Canada or Mexico. Policy Act of 2005 named FERC as the lead agency for
Wright estimates that there are close to 215,000 miles natural gas projects, allowing the commission to set the
of pipeline and 3.8 billion cubic feet (Bcf) of natural gas schedule for other agencies to follow in order to finish
storage under FERC jurisdiction. permitting. Congress approved the legislation as a measure
Oil pipeline construction approval falls under each state’s to improve infrastructure.
laws, but FERC sets the wholesale rates for oil and gas (and
derivatives) transmission, including U.S.-Canada border Miles of New Pipeline
tariffs, and enforces the market to make sure all entities are This year has been a slow year so far for approving natural
playing nice. gas pipeline projects, Wright says. However, the downturn
Three of the commission’s stated objectives are to is not all because of the recession. Instead, the market is
promote strong infrastructure, support a competitive playing catch-up to the many miles of infrastructure built
market and enforce the market. (or still being built) in the last few years.
“These are like the three legs to a stool,” Wright says. “Sometimes after two or three big years, you see the
“We have to have a strong infrastructure — the physical industry take a step back,” Wright says. In 2008, the
thing that we regulate. We approve projects to allow that mileage of pipelines FERC approved was the third biggest
to be constructed. this decade at 2,140 miles. 2007 was the biggest at 2,700
“Competition is based on rates, which give the operator miles approved. This massive expansion was largely due to
the incentive to build infrastructure, but we make sure that the developments in shale gas production.
those rates are fair to the rate payer.
“Finally, the enforcement aspect is to ensure that every-
one plays the game correctly, according to the rules we’ve
established.”
FERC does not set the price of the end-user commodity —
say, the price you pay at the gas pump when you’re filling
up. That price is set by the marketplace.
Pipeline: Approved
FERC sites natural gas pipelines under Section 7 of the
Natural Gas Act, which gives authority to the commission
for pipeline and storage regulation. Imports and exports fall
under Section 3 of the same act. FERC approves construc-
tion for physical pipeline and storage facilities and works
with the Department of Energy on permitting for new or
expanding natural gas pipelines. FERC also approves the
costs of transmission rates from the operator.
A simplified version of the approval process goes like this:
The applicant — the pipeline owner — comes to FERC with
an idea for a natural gas pipeline from point A to point B,
and a storage facility at point Z. FERC regulates the engi-
neering, environmental impact, accounting and transmis-
sion rates, and then the commission makes a recommenda-
tion based on its review. The five commissioners mull over
that recommendation and then vote on whether to approve
the project. This process can take up to 18 months.
The most labor intensive part of FERC’s application anal-
ysis is the environmental review, which must comply with
the National Environmental Policy Act (NEPA), Wright says.
To help cut down on the application approval timeframe,
FERC offers a pre-file option whereby the applicant can
come in before filing an official application and propose a
project so that the commission can get a head start on the
environmental review while the project owner compiles the For more information go to napipelines.com/info
• HDD Good Practices Guidelines – updates and what you need to know
•E
xisting Utilities – your responsibilities as a driller; what you need to know to avoid them;
the ramifications of a utility strike
• Equipment Purchasing – changes regarding tax laws/incentives; purchase vs. lease vs. rent
• Legal/Environmental Permitting
• Trends in Trenchless Technology – telco/fiber, sewer/water, oil/gas
• Workforce Issues – training staff, staff retention, drug testing, OSHA requirements
• High-tech HDD – the cutting edge technologies that are being used
•R
ock Drilling – how rock bores are different from soil bores – what you need to know in
putting together bids and planning for the job
• Economic Outlook – economist speaking about the market and the outlook for 2010
• Roundtable – a panel of industry experts discussing the issues that are impacting them, how they
are addressing them and how they are adapting to market conditions
Wouldn’t you rather prevent an accident than investigate it after the fact? That’s what Job Safety
Analysis (JSA) is all about. Also known as Job Hazard Analysis (JHA) or Activity Hazard Analysis
(AHA), JSA is a simple, inexpensive and effective management tool that can be used to identify,
analyze and record: 1) the steps involved in performing a specific job; 2) the existing or poten-
tial safety and health hazards associated with each step; and 3) the recommended action(s)/
procedure(s) that will eliminate or reduce these hazards and the risk of a workplace injury or
illness. The benefits of Job Safety Analysis are well known: identification and elimination or con-
trol of hazards before the work begins; consistent job and safety training; improved employee
safety performance; increased management awareness of safety hazards; improved labor and
management cooperation; improved compliance with applicable regulations; and more accurate
accident investigations.
Which Jobs Should er involvement in company safety activities. Workers in the group are more
Be Analyzed? inclined to promote and follow the established procedures if they are involved
Workers perform many different tasks in creating them. A good time to create JSAs using this method is when work
as part of their job classifications — every- is slow and/or during inclement weather.
thing from setting up ladders and assem- As the name suggests, direct observation method involves observing a work-
bling trench shields to unloading trucks er while he or she performs a specific task. It is best to select an experienced
and entering confined spaces. Each of employee who is willing to be observed. The observer should list each step
these tasks involves different hazards performed by the worker. Cameras and video cameras can be used to record
that could be evaluated. So where to be- the steps for a more in-depth review, but don’t let taking the photographs
gin? Generally, it makes the most sense become distracting to the worker. (Try not to use the flash attachment.)
to first select jobs that have a history of The observer should then note the potential hazards connected with each
accidents, have the greatest potential for step and try to identify changes in the environment or work procedures that
serious injury, are frequently performed, will eliminate potential accidents.
are performed by the greatest number
of employees and are new to those who
will be performing them. Over a period
of time, all jobs can be evaluated. Some
jobs are routine and may require a gen-
eral evaluation. Others may require a
more in-depth evaluation. When tools,
equipment, methods, procedures or job-
sites change, some JSAs may have to be
revised or updated.
Here are just some of the hazards that
should be considered when completing
a JSA: impact with a falling or flying ob-
ject; penetration by sharp objects; caught
in or between a stationary or moving
object; falls from an elevated work plat-
form, ladders or stairs; excessive lifting,
twisting, pushing, pulling, reaching or
bending; repetitive motion; exposure to
vibrating power tools, excessive noise,
cold, heat, harmful levels of gases, va-
pors, liquids, fumes or dusts; exposure to
cave-ins; electrical hazards; light (optical)
radiation (e.g., welding operations); and
water (potential for drowning or fungal
infections caused by wetness).
JSA Methods
There are two basic JSA methods: group
discussion and direct observation. A third
method can be established by combining
the two basic methods.
The group discussion method requires
the manager/foreman to meet with
employees familiar with the job being
analyzed. Each group member draws
upon his or her experience and visual-
izes the job steps and potential hazards.
Sometimes photos or videos of a worker
performing the job are used to help stimu-
late the group members’ thought process-
es. They review the job from start to finish
by breaking it down into steps. The group
evaluates each step to determine the haz-
ards that could lead to an accident.
When the hazards are listed, the group
focuses on the changes in the environ-
ment or procedures that can control or
eliminate the hazard. The advantages
of the discussion method are the many
points of view considered, increased
worker knowledge and increased work- For more information go to napipelines.com/info
Performing the Job Safety Analysis Whatever JSA method is used the analysis should be
A JSA has three basic phases: 1) list the steps required to properly documented (see www.maricopa.gov/safety/jsa_
complete the job; 2) identify the hazards associated with library.asp for completed samples). Completed JSAs should
each step; and 3) develop solutions for controlling or be reviewed by managers, workers and the safety coor-
eliminating the hazards. dinators to ensure that nothing has been overlooked.
Executive management or safety managers should approve
Phase 1: List the job steps. Every job must be broken any results that will become part of the safety program.
down into distinct steps in the order of occurrence. Once approved, the JSA documents should be shared with
Document enough information to describe each step, all managers, foremen and supervisors to ensure they are
but do not make the breakdown too detailed. Try to limit aware of established company procedures for specific jobs.
the number of job steps to 10 or fewer well-defined steps. Effective toolbox talks can be created by selecting JSAs
Job Safety Analysis (JSA) procedures can help limit the hazards inherent in construction worksites, such as possible impact from
a falling object like pipe.
Each step will consist of a set of movements. For example, appropriate to a given jobsite. Workers tend to take great
“Pick up box and place on hand truck” or “Push hand interest in training that is directly related to what they
truck to storage area.” All steps should start with an action are doing.
word — e.g., push, pull, lift, move, carry, insert, tighten, Time and time again, Job Safety Analysis has proven to
etc. Review the steps with experienced workers to ensure be an effective means of preventing accidents by finding
they are complete and descriptive. and eliminating or controlling hazards before the job is
performed. JSAs can be used to train/retrain employees and
Phase 2: Identify the hazards. Each step should be ex- foremen and to give pre-job instructions. It can help man-
amined to discover any existing or potential hazards. When agers and supervisors develop and improve job methods
listing hazards, don’t just list the obvious hazards; list ev- and procedures, not just in the area of safety, but often in
ery conceivable hazard that could reasonably cause an ac- other areas like production and quality control. Its greatest
cident. Be sure to include health hazards, even though the value is in standardizing work methods and safe operating
potential harmful effects may not be immediate. procedures.
For further information about how to complete a JSA,
Phase 3: Determine how to control or eliminate the refer to OSHA’s Publication #3071 (www.osha.gov/Publications/
hazard. Hazards must be reviewed and recommendations osha3071.html).
made to eliminate or control them. Hazards can often be
minimized by: changing the sequence of steps; modifying or George Kennedy is vice president of safety for the National
changing the tools, machines, equipment or materials; im- Utility Contractors Association (NUCA).
38 North American Pipelines | SEPTEMBER/OCTOBER 2009 napipelines.com
For more information go to napipelines.com/equipment-showcase/index
Gyro-Trac GT-25XP
Gyro-Trac’s low-ground-pressure, high-speed mulching machines will clear unwanted trees and underbrush in a
safer, more environmentally friendly way. You can complete the job faster, and unlike bulldozers that tear up soils,
Gyro-Trac leaves soil structures
intact, eliminating erosion
and runoff pollution. Gyro-
Trac’s heavy-duty GT-25XP is
powered by a 260-hp Tier III
turbo diesel engine, power-
ful hydraulic pumps and the
latest cutter head technology.
Performance, productivity
and lack of profitability will
never be an issue with the GT-
25XP. Weighing in at 23,500
lbs, the heavy-duty mulching
machine outperforms similar-
ly sized and bigger machines.
The GT-25XP chips away at
hardwoods and softwoods
of almost any size, including
difficult ironwood, hickory,
Australian hardwoods, petri-
fied oak and more. Gyro-Trac’s
machines efficiently mulch
trees and stumps right to the
ground, leaving only a fine,
nutrient-rich mulch behind.
For more information, visit
www.gyrotrac.net.
40 North American Pipelines | SEPTEMBER/OCTOBER 2009 napipelines.com
IronWolf 700B
The IronWolf 700B in-
tegrates the mobility and
functionality of a purpose-
built crawler, and the
versatility of the IronWolf
Slasher and Crusher attach-
ments. For site excavation,
clearing and mulching
standing trees, site clear-
ing and preparation, stump
removal, asphalt recycling
and more, the IronWolf
700B stands up to the job in
all types of working condi-
tions. The 700B is powered
with a 700-hp Caterpillar
C-18 engine and rides on
36-in. wide, low ground
pressure tracks, which help
the machine maintain 6.8
psi of total ground pres-
sure. No matter what chal-
lenge you face, the power-
ful 700B creates solutions,
expands capabilities and
opens the door to new op-
portunities. For more infor-
mation, visit www.ironwolf.
com.
Free Subscription!
Fax to 330.657.2855
Please start/renew my free* subscription
to North American Pipelines ■ Yes ■ No
Yes, I want the bi-weekly NAP E-newsletter delivering industry stories & news via email
What is your company’s Which types of equipment or services do PLEASE PRINT CLEARLY
primary activity? (check only one) you recommend for use in the oil & gas
A Pipeline Construction pipeline industry? (check all that apply) Name____________________________________________________________________
B Pipeline Maintenance A Cathodic Technology
C Consullting/Engineering B Cleaning Pigs Title______________________________________________________________________
D Government/Regulatory C Coatings/Linings
D Corrosion Monitoring
Company_________________________________________________________________
E Equipment Mfg/Supplier
F Legal E Environmental Awareness
Address__________________________________________________________________
G Financial F Flow Control Software
H Gas Transmission Pipelines G GIS/GPS systems __________________________________________________________________
I Gas Distribution H Inline Inspection
J Oil Pipeline I Leak detection/Prevention City______________________________________________________________________
K Other J Offshore Pipe Laying
K Pipe Materials State/Prov_ _______________________________________________________________
L Pipeline Communications
What is your primary job Zip/Postal Code________________________________Country_ ___________________
M Pipeline Design Engineering
title/function at your company? N Pipeline Machinery Phone____________________________________________________________________
(check only one)
O Pipeline Maintenance
A Owner/CEO/President P Pipeline Rehabilitation Fax_ _____________________________________________________________________
B Executive Mgmt/VP/COO/CFO Q Pipeline Safety
C Financial Management R Pipeline Security Email_____________________________________________________________________
D Superintendent S Project Financing & Insuring
E Engineer/Consultant Signature_________________________________ Date___________________________
T ROW Management
F Supervisor/Foreman U SCADA/Automation Software
G Attorney
Fax to: 330.657.2855
V Trenching Materials
H Other W Trenchless Technology
X Welding www.napipelines.com
Y Other *The subscription is free in the USA, Canada & Mexico NAP0909
Horizontal Directional
Drilling Good Practices
Guidelines – 2008 3rd Edition
The latest version includes a new chapter on design, and other
sections have been updated to include new developments in
technologies. Chapters include:
•Introduction and Background
•HDD Applications and Processes
•Equipment and Materials
•Design
•Bore Planning
•Jobsite Safety
•Troubleshooting and Mitigation
Publisher: HDD Consortium
279 pages/ softbound
Price: $170.00 $153.00* for a limited time only!
*Shipping and handling not included. Selling price subject to change without notice
September 19 2010
Tennessee Gas Supply Conference
13 – 17 Tennessee Gas Association January
GIS for Oil & Gas Conference Chattanooga Hotel
Geospatial Information & Technology Chattanooga, Tenn. 11 – 13
Association (GITA) Web: www.tngas.org NUCA Expo ’10
Marriott Westchase Hotel Walt Disney World Dolphin Hotel
Houston 19 – 22 Orlando, Fla.
Web: www.gita.org/oilgas Evaluation and Rehabilitation of Web: www.nuca.com
Pipelines Conference and Exhibition
14 – 18 Pittsburgh Marriott City Center 19 – 21
43rd Annual IPLOCA Convention Pittsburgh Underground Construction
International Pipeline and Offshore Web: www.clarion.org/rehab/rehab09/ Technology (UCT) 2010
Contractors Association main.php International Conference & Exhibition
Fairmont Hotel Tampa Convention Center
San Francisco Tampa, Fla.
Web: www.iploca.org November Web: www.uctonline.com
21 – 24 9
American School of Gas ASTM Symposium on Plastic Pipe February
Measurement Technology and Fittings
Marriott Westchase Hotel ASTM International 15 – 18
Houston Hyatt Regency 22nd International Pipeline Pigging
Web: www.asgmt.com Atlanta & Integrity Management Conference
Web: www.astm.org/SYMPOSIA (Plus Training Courses and Exhibition)
Marriott Westchase Hotel
October 15 – 17 Houston
AEM Annual Conference Web: www.clarion.org/ppim/ppim10/
5–7 Westin Diplomat Resort & Spa main.php
Gas Machinery Conference Hollywood, Fla.
Gas Machinery Research Council (GMRC) Web: www.aem.org 17 – 21
Hilton Hotel PLCA 62nd Annual Convention
Atlanta 19 – 20 Scottsdale, Ariz.
Web: www.gmrc.org/gmc-2006.html HDD Executive Forum Web: www.plca.org
Doubletree Hotel
6–8 Houston 23 – 28
ICUEE Web: www.trenchlessonline.com/HDD DCA 49th Annual Convention
Kentucky Exposition Center Fiesta Americana Grand Los Cabos
Louisville, Ky. December Los Cabos, Mexico
Web: www.icuee.com Web: www.dca-online.org
1–3
Deep Gulf 2009
Moody Gardens Hotel & Resort
Galveston, Texas
Web: www.deepgulfconference.com
Advertisers Index
Advertiser........................................Website......................................................Page # Advertiser........................................Website......................................................Page #
American Excelsior Company.........www.curlex.com..................................................41 Horizontal Technology Inc................www.horizontaltech.com.......................................5
Barbco..............................................www.barbco.com................................................37 John Deere.......................................www.JohnDeere.com/precision.........................48
Benjamin Media Resource Center..www.benjaminmedia.com/book-store.........43, 45 King Contracting Inc........................www.kinghdd.com..............................................17
Darby Equipment Company............www.darbyequip.com.........................................21 Leslie Equipment Company............www.lec1.com.....................................................39
Denis Camif......................................www.deniscimaf.com..........................................25 LJ Welding & Machine.....................www.Ljwelding.com............................................45
Educational Webinar Series.............www.benjaminmedia.com/webinars..................39 Mersino.............................................www.mersino.com..............................................27
Enduro Pipeline Services Inc...........www.enduropls.com...........................................33 Michels Corp....................................www.michels.us...................................................23
FAE....................................................www.faeusa.com.................................................47 Neptune Research, Inc....................www.neptuneresearch.com................................19
Fecon, Inc.........................................www.fecon.com...................................................13 Rain For Rent....................................www.results.rainforrent.com...............................11
Gabe’s Construction Co. Inc...........www.gabes.com.................................................15 REMU USA Inc.................................www.remu.fi...........................................................7
Geospatial Corporation...................www.geospatialcorporation.com.......................31 Rig Source, Inc.................................www.rigsourceinc.com.......................................45
HDD Exeuctive Forum.....................www.trenchlessonline.com/HDD.......................35 Vacuworx International.....................www.vacuworx.com..........................................2, 3