Pre-Bid Services for Ghandidham- Samkyali

Concept Note on Pavement Design

TABLE OF CONTENTS

1.1STIPULATIONS OF CONCESSION AGREEMENT FOR DESIGN...................................2


1.2DESIGN TRAFFIC....................................................................................2
1.3GROWTH RATES....................................................................................2
1.3.1Stipulations in the Concession Agreement..............................................................................3
1.3.2Design CBR.............................................................................................................................4
1.4OVERLAY DESIGN...................................................................................4
1.5Recommended Pavement Crust Composition.................................................5
1.6Design of Service Roads:..........................................................................7

LIST OF TABLES

1.1STIPULATIONS OF CONCESSION AGREEMENT FOR DESIGN...................................2


1.2DESIGN TRAFFIC....................................................................................2
Table 1.1 Design Traffic on the Project Road..................................................2
Table 1.2 VDF values adopted in the Design...................................................2
1.3GROWTH RATES....................................................................................2
1.3.1Stipulations in the Concession Agreement..............................................................................3
Table 1.3 Traffic Growth rates Considered.....................................................3
Table 1.4- MSA Arrived..............................................................................3
1.3.2Design CBR.............................................................................................................................4
Table 1.5 Pavement Composition for New Pavement (considering 100msa)............4
1.4OVERLAY DESIGN...................................................................................4
1.5Recommended Pavement Crust Composition.................................................5
Table 1.6 The Recommended Pavement Composition........................................6
1.6Design of Service Roads:..........................................................................7

Feedback Ventures Pvt Ltd

1-7

Pre-Bid Services for Ghandidham- Samkyali

Concept Note on Pavement Design

CONCEPT NOTE ON PAVEMENT DESIGN AND THICKNESSES ADOPTED IN THE COSTING


The Concept note on Pavement Design brings out the methodology adopted in Carrying out the
Pavement design and the thicknesses adopted in the costing for review of Concessionaire and
approval.
1.1

STIPULATIONS OF CONCESSION AGREEMENT FOR DESIGN

Design shall be carried out for 20 years

Thickness and composition of layers for widening shall be same that of existing
pavement

1.2

Flexible pavement Design shall be carried out as per IRC: 37 and IRC: 81 guidelines

Concrete pavement design shall be as per IRC:58

Service Road shall be designed for 10% of main carriageway Traffic

DESIGN TRAFFIC

The CVC and Axle Load Survey conducted by FVPL have been considered in arriving the MSA.
Table 1.1 Design Traffic on the Project Road
LCV
Bus (Pvt.)

Bus (G)

School Bus

185

381

191

2 Axle
Truck

3 Axle
Truck

4-6 Tyre

7++
Axle

1,462

4,728

2,686

Table 1.2 VDF values adopted in the Design

LCV
BUS
2 AXLE
3 AXLE
Multi axle

1.3

VDF
1.0
0.64
6.22
5.38
7.88

GROWTH RATES

Feedback Ventures Pvt Ltd

2-7

Pre-Bid Services for Ghandidham- Samkyali

1.3.1

Concept Note on Pavement Design

Stipulations in the Concession Agreement


The Concession Agreement stipulates that the growth rate shall be highest of the following
in the initial 5 years.
(a)
(b)
(c)
(d)

5% per annum for all vehicles.


Trend growth of various vehicle categories.
Projected Growth rate of revenue assumed in the concessionaires cash flow.
Growth determined from secondary socio economic data and elasticity factors.

And then reduces every 5 years by 2 (two) percentage points subject to a minimum of 3%.
The Growth rates considered in arriving the msa, since they are higher than others have been
tabulated in below Table:
Table 1.3 Traffic Growth rates Considered

Vehicle Type
Cars
Two Wheelers
Buses
LCV
2-Axle Trucks
3-Axle Trucks
MAV
All trucks GR by elasticity method
Weighted avg GR of all trucks

Final Traffic Growth Rates (%)


2009-2014
2015-2019
Beyond 2019
8.4
6.6
5.3
9.2
7.5
5.4
5.4
3.8
2.5
6.8
5.3
4.3
4.5
4.0
3.0
7.0
6.0
5.0
7.0
6.0
5.0
6.8
5.3
4.3
6.6
5.6
4.6

The project road has been divided into single homogeneous section.
The MSA arrived for 10 years and 20 years design life is tabulated in Table 1.4
Table 1.4- MSA Arrived

Year

Vehicle Type
MAV upto 6
3A
Axles

MAV more
than 6 Axles

MSA

CUMULA
TIVE
MSA

BUS

LCV

2A

2009

567

191

1462

4728

2680

7.69

2010
2011

598
630

204
218

1528
1597

5059
5413

2868
3068

1
1

8.20
8.74

2012

664

233

1668

5792

3283

7.45

7.45

2013
2014
2015
2016

700
738
766
795

248
265
279
294

1743
1822
1895
1971

6197
6631
7029
7451

3513
3759
3984
4223

1
1
2
2

7.95
8.47
8.96
9.47

15.40
23.87
32.83
42.29

Feedback Ventures Pvt Ltd

REMAR
KS

Base
Year

Start
Year

5th Year

3-7

Pre-Bid Services for Ghandidham- Samkyali

2017
2018
2019
2020
2021
2022
2023
2024
2025
2026
2027
2028
2029
2030
2031

825
856
889
915
945
975
1006
1038
1072
1106
1141
1178
1215
1254
1294

310
326
344
358
374
390
407
424
442
461
481
502
523
546
569

2049
2131
2217
2283
2352
2422
2495
2570
2647
2726
2808
2892
2979
3068
3160

Concept Note on Pavement Design

7898
8372
8874
9318
9784
10273
10787
11326
11892
12487
13111
13767
14455
15178
15937

4477
4745
5030
5282
5546
5823
6114
6420
6741
7078
7432
7803
8194
8603
9033

2
2
2
2
2
3
3
3
3
3
4
4
4
4
5

10.00
10.58
11.18
11.71
12.26
12.84
13.45
14.08
14.75
15.45
16.18
16.95
17.76
18.61
19.49

52.30
62.87
74.05
85.76
98.02
110.86
124.31
138.39
153.14
168.59
184.78
201.73
219.49
238.10
257.59

10th Year

15th Year

20th Year

The pavement design for the new Pavement has been performed for 150 MSA as it is limiting
loading as per IRC: 37:2001 and100msa for overlay as it is limiting load as per IRC:81-1991
1.3.2

Design CBR

Consultants have conducted tests on barrow area samples and the results for the same are
awaited. Meanwhile a design CBR of 10% has been considered as it can be seen from site that
Good soil is available through out the Project road.

Table 1.5 Pavement Composition for New Pavement (considering 100msa)

1.4

Section

Length
(Km)

MSA considering
Design

BC (mm)

DBM (mm)

(mm)WMM

GSB (mm)

New Pavement Composition


Total
Thickness
(mm)

SamkyaliGhandidham

58kms

150

50

150

250

200

650

OVERLAY DESIGN

The Consultants have carried out BBD survey and the characteristic values arrived from the test
varies from 0.6mm to 0.8mm; hence there is no requirement of overlay on existing pavement.
However, as a minimum case as stipulated in IRC 81-1991, an overlay of 50mm DBM and 50mm
BC has been suggested for the entire Project length.

Feedback Ventures Pvt Ltd

4-7

Pre-Bid Services for Ghandidham- Samkyali

Concept Note on Pavement Design

It is to be noted that NHAI has laid a surface course of 50mm BC in the year 2007-2008.
1.5

Recommended Pavement Crust Composition

Since as per CA requirement, the thickness and composition of layers for widening shall be same
that of existing pavement, the following crust composition has been recommended.

Feedback Ventures Pvt Ltd

5-7

Pre-Bid Services for Ghandhidam Samkyali

Pavement Design Report

Table 1.6 The Recommended Pavement Composition


The Recommended Pavement Composition

Chainage
Complete Road

Feedback Ventures Pvt Ltd

EXISTING CRUST DETAILS


BC /
DBM
WBM/WMM
Sub Base
165
325
300

Total
790

Overlay
B
DBM
C
50
50

New Pavement
Total
890

GSB
440

WMM

DBM

250

150

B
C
50

6-7

Total
890

Pre-Bid Services for Ghandhidam Samkyali

1.6

Pavement Design Report

Design of Service Roads:

10 msa has been considered in the service road pavement design.


The crust arrived for the same is
BC- 40mm
DBM- 50mm
WMM- 250mm
GSBC 200mm
Total 540mm

Feedback Ventures Pvt Ltd

7-7