PUBLIC WORKS AUTHORITY Engineering Support Section , Building Affairs Projects Department Monthy Progress Report As Of ..25-02-2014..

General Information Affairs : Project Name :


Buldings Affairs Construction Of New Family Consulting Center

Department : Location :

Building Department

Section : PWA Project Manager :

General Section

AL-Shaflah

Eng.Abdullah Al Sherief

Client :

PWA

Supervision Consultant :

James Cubitt

Contractor :

BOOM

Contractor Commitment No C 2012/93 : Time: Contract Start Date:


14-Apr-13

Consultant Commitment No:

P 2013/06

Design Consultant :

United Consultants

Contract Duration:

420

Contract Completion Date: 07-Jun-14

Planned % Complete : Actual % Complete : Cost: Contract Value:

82.57% 44.69%

Approved Variation Duration :


0

Adjusted Completion Date:


07-Jun-14

71,999,992

Approved Variation/Addenda:

Adjusted Contract Value:

71,999,992

Claims Number of claims received from contractor : Number of claims replied by Consultant : Notes *Reasons of the delay : 1. Frequent Changes on the project. Reference to SI-02, SI-03 & SI-04. *Consultant Recommendation : 1. Cost & Time claims for Changes be reviewed and approved for Baseline Program revision. 2. BGC to prepare recovery program for lost time 2. BGC inability to conclude Shop drawings, Material samples submittals on time. 75 75

PREPARED BY :

REVIEWED BY :

Akinjide Akinjobi

Contractor Number Project Name Start Date Completion Date

: C 2012/93 : Construction Of New Family Consulting Center : 14 April 2013 : 07 June 2014

SUBSTRUCTURE

SUPERSTRUCTURE

WET FINISHING WORKS

Construction Progress (%)

Negative float (Cal. days)

Number

Reinforced concrete

Columns & Walls

Water Proofing

Plain concrete

Slab on Grade

EXCAVATION

Slab & Beems

Planned %

82.57

100.0%

100.0%

100.0%

100.0%

100.0%

Backfilling

Project Name

100.0%

100.0%

100.0%

100.0%

BLOCKWORK

Progress presentage (%)

100.0%

100.0%

1-

Construction Of New Family Consulting Center


Actual % 44.69 -268
100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% 100.0%

2 out of 3

External PLASTER Work

internal PLASTER Work

Contractor Number Project Name Start Date Completion Date

: C 2012/93 : Construction Of New Family Consulting Center : 14 April 2013 : 07 June 2014

WET FINISHING WORKS

FINISHING WORKS

MEP WORKS

EXTERNAL WORKS

Aluminum Works (windows / Skylight / doors)

Plumbing, Drainage & Electrical Works

WATERPROOF & INSULATIONB

Ventilation & Air conditioning

Gypsum Board Partitioning

Excavation and Earthworks

Number

Guard Room & Gate

Telephone System

Flooring

Planned %

100.0%

85.8%

75.4%

97.5%

Ceiling

Project Name

100.0%

83.2%

100.0%

1.0%

100.0%

53.6%

88.3%

100.0%

66.8%

66.6%

100.0%

15.0%

75.0%

81.0%

6.0%

0.0%

1-

Construction Of New Family Consulting Center


Actual %
12.7% 13.9% 32.1% 4.5% 4.8% 0.0% 0.0% 30.6%
0.0% 24.1% 27.9% 51.8% 40.5% 38.6% 50.0% 22.0% 0.0% 1.0% 0.0% 0.0%

Car Parking Works

Plu & Dra. Works

External Painting

Wooden Doors

Boundary Wall

Electrical Ins.

Fire Fighting

GRC Works

Progress presentage (%)

Conrete Kerbs & Interlock

Internal Painting Works

Reason of Delay

1. Frequent Changes on the project. Reference to SI-02, SI-03 & SI-04. 2. BGC inability to conclude Shop drawings, Material samples submittals on time.